1 9 Meeting Date: May 8, 2018 Item Number: D 6 To: From: Subject: AGENDA REPORT Honorable Mayor & City Council Robert Welch, Acting City Engineer Raj Patel, City Building Official ASBESTOS ABATEMENT PERMIT APPLICATION FOR THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY AND ITS CONTRACTORS TO PERFORM ASBESTOS ABATEMENT AT AND WILSHIRE BOULEVARD IN PREPARATION FOR FUTURE DEMOLITION, CONSTRUCTION AND A LAYDOWN LOCATION FOR THE RODEO STATION IN SECTION 2 OF THE PURPLE LINE EXTENSION PROJECT Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location RECOMMENDATION Staff recommends that City Council authorize issuance of an asbestos abatement permit to the Los Angeles County Metropolitan Transportation Authority (Metro) and its Contractor for the properties located at and Wilshire Boulevard. INTRODUCTION Metro is requesting City Council approval for an asbestos abatement permit at and Wilshire Boulevard (Attachment 1). This site will be used as a staging area for future construction for the Wilshire/Rodeo Station. This abatement work is required to be completed by Metro prior to demolition of the building and the design-build station construction activities. Because of the very limited scope of the work, all the permit conditions are included with the permit instead of developing a Memorandum of Agreement (MOA). Future work, including demolition and use of the site are expected to be part of the MOA. Page 1 of 3 5/3/2018

2 Meeting Date: May 8, 2018 DISCUSSION Metro is requesting City Council approval for asbestos abatement at and Wilshire Boulevard (Attachment 1) in preparation for the future Wilshire/Rodeo Station construction. Per Beverly Hills Municipal Code , the contractor must obtain an asbestos abatement permit to remove asbestos from a property prior to demolition of the building under the City s asbestos abatement checklist. To obtain this permit, the contractor is required to submit evidence of State certification for asbestos removal. The contractor has satisfied this requirement. Metro s contractor is required to follow survey requirements, notification requirements and work regulations set forth by the California Division of Occupational Safety and Health (Cal OSHA) and the Air Quality Management District (AQMD) Rule At completion of the work, the Contractor must submit to the City a written Certificate of Completion that the asbestos has been removed in accordance with State requirements. Construction In formation and A esthetics: The abatement work at and Wilshire Boulevard is contained within the building and on the rooftop. The work will be performed during the City s standard construction hours of 8 am and 6 pm, Monday through Friday for five weeks. Any additional time beyond five weeks will require an amendment to the permit. There will be no work on weekends or holidays. Recommended permit conditions are in Attachment 2. The contractor estimates an average of less than one truck per day will be necessary to remove the material. These trucks are required to follow the City-approved haul routes. All trucks are required to be clean and not track dirt or debris into or out of the site. Construction fencing will be placed in the alley along the property line and will be visible from the alley located between North Crescent Drive and North Canon Drive (Attachment 3). This fence will be set back from the road as far as possible and will be covered with a solid color screen consistent with the public information graphics program previously approved by City of Beverly Hills. AQMD requires fencing to be installed to deter access by the general public and enclose the area during movement of the materials. The fence will not be installed until required by the AQMD construction regulations and is intended to stay in place during the demolition of the structures. All construction vehicles will be parked on site. Construction/Permit oversight will be administered by City of Beverly Hills staff. Prior to abatement of asbestos containing materials, the contractor will establish physical barriers to isolate the work by erecting a containment area. The containment will be sealed at the perimeter of the work zone to prevent dust migration outside of the abatement area. The contractor will install air filtration units, fitted with multiple filters efficient at filtering out asbestos fibers and other particulates to continuously filter the air inside the containment. Asbestos-containing material will be wetted and removed carefully. All asbestos-containing waste materials will be promptly bagged and stored in appropriately labeled leak tight waste bags prior to transportation off site for disposal. In addition, an independent consultant will perform air sampling for asbestos at the perimeter of the abatement work areas. Air samples will be analyzed daily to ensure compliance with Environmental Protection Agency (EPA) requirements. Final air clearance sampling will be conducted by the independent consultant to verify completeness of abatement activities and prior to removing containments. Page2of3 5/2/2018

3 Meeting Date: May 8, 2018 The building itself is not anticipated to be demolished until July Staff will return to City Council before issuing a permit, unless an MOA is previously approved by City Council, for the demolition work and will develop a series of conditions to mitigate impacts associated with the demolition work. Finally, a piece of public art is currently displayed on the property, which was initially installed in satisfaction of the City s public art ordinance. The public art is expected to be stored during construction and returned upon redevelopment of the site. A covenant in favor of the City was recorded against the property to ensure the continued maintenance of the art on site. City Council will be presented with an amendment to the current covenant to ensure that the art is properly stored during construction. Community Engagement On April 4, and May 2, 2018, Metro provided an update at the monthly Beverly Hills community meeting where the abatement work was discussed. On Monday, April 16, 2018, Metro ed and hand delivered notices to the adjacent businesses/buildings and posted it on the Purple Line Extension construction notice webpage. FISCAL IMPACT All permit-related fees are to be collected in accordance with the City s approved and adopted Schedule of Taxes, Fees and Charges. Metro will reimburse the City for all other costs for additional staff and Consultants performing work on this project, including the scope described above and detailed in the permit conditions, within the total amount authorized by the approved annual Form 60 work plan, which outlines the City costs associated with each work task for the year. / han%> (,>/i.? )rpidroved By Page 3 of 3 5/2/2018

4 Attachment 1

5 0 -J a) 0 Cu 0 D0 > a) a) C,) -c3 Cu C ) 0 C ) C ) U) U) a) -c -c 4: 4- a) U)

6 Attachment 2

7 Rights-of-Way north of Charleville Boulevard only) q) Thanksgiving Day through New Year s Day (work outside staging areas and City p) Next Night Block Party (work on Beverly Drive only) e) The Academy Awards c) Martin Luther King Jr. Day a) New Year s Day zone, at any time on a Saturday. For the purpose of this section, public holiday shall mean: at any time on a Saturday, Sunday or public holiday. In addition, no person shall engage between the hours of six o clock (6:00) P.M. and eight o clock (8:00) A.M. of any day, or shall engage in construction, maintenance or repair work which requires a city permit 10, Chapter 3, Article 42 and Title 9, Chapter 1, Article 1. 1) Asbestos permits shall be obtained in accordance with Beverly Hills Municipal Code, Title 2) Construction activity: In accordance with Beverly Hills Municipal Code no person in such work within a residential zone, or within five hundred feet (500 ) of a residential b) The Golden Globe Awards U) President s Day f) Mother s Day g) Memorial Day h) Father s Day i) Easter Sunday j) The First Two Days of Passover k) Independence Day I) Labor Day m) Rosh Hashanah n) Yom Kippur o) Veteran s Day Recommended Permit Conditions Asbestos Abatement Permit

8 record in accordance with California Code of Regulations Title 24 and local amendments and codes. AQMD Notification is required to be submitted to the City for final approval. 4) Building Inspections are requited to be requested by the contractor listed on the permit of o clock (8:00) A.M. interest of the public. 11) Other permit specific conditions of approval as necessary to issue City permits in the best 10) Permit related fees. Plan review fees will be collected at the time of application and plan City s approved and adopted Schedule of Taxes, Fees, and Charges. the scope of work. All fees collected are in accordance with State laws, local laws, and the review submittal. Permit related fees will be collected at the time of permit issuance for Chapter 3, Article 42 and (102.10) of related construction permits in accordance with Beverly Hills Municipal Code Title 10, 9) Bonds related to demolition requirements shall be posted and paid for prior to the issuance disturbances. 8) Metro is to Maintain 24/7 phone line for concerns from the public related to construction 7) Contractor is required to follow the City Approved Haul Routes. parking must be on private property at all times during the work. contractors for vehicles or equipment unless approved by the City Council. Construction 6) Commercial or residential on-street parking may not be used by the Metro or its pavement and concrete breaking/cutting equipment shall be enclosed to the extent greater in accordance with approved Memorandum of Understanding Agreement All equipment and vehicle engines, 17 for Advanced Utility Relocation Segment sound barrier enclosures with a Sound Transmission Class (ST rating of STC 25 or possible. a) To the extent possible, noise producing activities and equipment shall be enclosed in 5) Noise mitigation measures shall include: requires a City permit shall enter a site on which such work will be done prior to eight 3) No person employed for the purposes of construction, maintenance, or repair work which

9 Attachment 3

10 U- C C.) -J 0 Ci Cu 0 4 IIIb :1. A! LJi if

11 E 0I-. I C-) U-

ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM

ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM CITY OF PASADENA 175 NORTH GARFIELD AVENUE PASADENA, CA 91109 PROPOSED MITIGATED NEGATIVE DECLARATION PROJECT

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 18, 2015

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 18, 2015 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 18, 2015 DATE: July 9, 2015 SUBJECT: U-3372-13-1, USE PERMIT AMENDMENT for an amendment to Condition #12.A.5) to permit construction

More information

The Port Authority will demolish, remediate, and clear the site for future development by a company or end user.

The Port Authority will demolish, remediate, and clear the site for future development by a company or end user. Who is the Port of Greater Cincinnati Development Authority? The Port of Greater Cincinnati Development Authority (Port Authority) is a quasi-governmental, economic development agency that initiates projects

More information

CONTRACT AGREEMENT. This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the

CONTRACT AGREEMENT. This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the CONTRACT AGREEMENT This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the "City") and Contractor as of the date the last party to this Contract Agreement signed below. W I T N E

More information

STAFF REPORT. Attachments: 1. Location Map 2. Project Schedule 3. Sound Wall Graphics Design Concept

STAFF REPORT. Attachments: 1. Location Map 2. Project Schedule 3. Sound Wall Graphics Design Concept STAFF REPORT Meeting Date: June 5, 218 To: Honorable Mayor & ity ouncil From: Darren Grilley, ity Engineer Robert Welch, Project Manager Subject: Metro Purple Line Extension Section 1, La ienega Station

More information

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation

More information

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES 1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE LATEST EDITION OF THE STANDARD PLANS OF THE CITY OF LA QUINTA, THE LATEST EDITION OF THE STANDARD SPECIFICATIONS

More information

INTRODUCTION. A. Overview. A. Scope of Work. B. Additional Requirements

INTRODUCTION. A. Overview. A. Scope of Work. B. Additional Requirements RFP 2019-01 Reeta s Building Demolition City of Morgantown REQUEST FOR PROPOSALS Demolition Contractors INTRODUCTION A. Overview This Request for Proposals ( RFP ) is being issued by the City of Morgantown

More information

THE SUSSEX COUNTY MUNICIPAL UTILITIES AUTHORITY ASBESTOS DISPOSAL APPLICATION AND FORMS

THE SUSSEX COUNTY MUNICIPAL UTILITIES AUTHORITY ASBESTOS DISPOSAL APPLICATION AND FORMS THE SUSSEX COUNTY MUNICIPAL UTILITIES AUTHORITY ASBESTOS DISPOSAL APPLICATION AND FORMS Revised 2/13/19 Dear Applicant: The Sussex County Municipal Utilities Authority provides for the proper disposal

More information

El Dorado Avenue

El Dorado Avenue A t t a c h m e n t 1 F i n d i n g s a n d C o n d i t i o n s 1995-1999 El Dorado Avenue Use Permit #08-10000055 JULY 10, 2008 CEQA FINDINGS 1. The project is categorically exempt from the provisions

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

AGENDA REPORT. Meeting Date: Item Number: To: From: June 5, 2018

AGENDA REPORT. Meeting Date: Item Number: To: From: June 5, 2018 çy AGENDA REPORT Meeting Date: Item Number: To: From: Subject: Attachments: June 5, 218 F i Honorable Mayor & ity ouncil Robert Welch, Project Manager Raj Patel, ity Building Official DEMOLITION AND PUBLI

More information

Idaho Solid Waste Association

Idaho Solid Waste Association Idaho Solid Waste Association Idaho Snow: Debris from Collapsed Buildings EPA Asbestos Requirements for Demolishing a Building John Pavitt U.S. Environmental Protection Agency Region 10, Alaska Operations

More information

Application for a Residential Building Permit

Application for a Residential Building Permit Town of Chevy Chase 301-654-7144 (phone) 4301 Willow Lane 301-718-9631 (fax) Chevy Chase, MD 20815 townoffice@townofchevychase.org Town Permit No.: Application for a Residential Building Permit Please

More information

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS PART 1 GENERAL 1.1 DESCRIPTION A. Temporary Utilities: Electricity, lighting, heating, cooling, ventilation, water, and sanitary facilities. B. Temporary Controls: Barriers, fencing, erosion control, exterior

More information

Delaware Street

Delaware Street A t t a c h m e n t 1 F i n d i n g s a n d C o n d i t i o n s 2004-06 Delaware Street Use Permit #09-10000052 APRIL 22, 2010 CEQA FINDINGS 1. The project is categorically exempt from the provisions of

More information

AGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018

AGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018 AGENDA REPORT Meeting Date: November 20, 2018 Item Number: E 15 To: From: Honorable Mayor & City Council Vincent Chee, Project Manager Subject: A CONTINUATION OF DECLARATION THAT THE PUBLIC INTEREST AND

More information

ORDINANCE NO. An ordinance amending Section of the Los Angeles Municipal Code by amending the zoning map.

ORDINANCE NO. An ordinance amending Section of the Los Angeles Municipal Code by amending the zoning map. ORDINANCE NO. An ordinance amending Section 12.04 of the Los Angeles Municipal Code by amending the zoning map. THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS: Section. Section 12.04 of the

More information

Mitigation Monitoring and Reporting Program

Mitigation Monitoring and Reporting Program Mitigation Monitoring and Reporting Program Mitigation Monitoring and Reporting Program The Infill Environmental Checklist identifies the applicable mitigation measures from the Downtown Area Plan Environmental

More information

DEMOLITION BY USE OF EXPLOSIVES

DEMOLITION BY USE OF EXPLOSIVES INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC 91.3303.9 Effective: 7-14-95 DOCUMENT NO. P/BC 2002-020 Revised: 11-17-00 Previously Issued As: MGD #105 DEMOLITION BY USE OF EXPLOSIVES

More information

STATEMENT OF OFFICIAL ACTION

STATEMENT OF OFFICIAL ACTION STATEMENT OF OFFICIAL ACTION 72 LA CUESTA (APN: 262-032-015) EDP-2016-034 JANUARY 22, 2018 STATEMENT OF OFFICIAL ACTION ACTION: Zoning Administrator Approval SUBJECT: Major Modification to Elevated Deck

More information

B \ v36.doc

B \ v36.doc MEMORANDUM OF AGREEMENT FOR CONTRACT C1120 OF THE PURPLE LINE EXTENSION PROJECT SECTION 2 BETWEEN THE CITY OF BEVERLY HILLS AND THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY TABLE OF CONTENTS

More information

Generator for Maintenance/Police Complex

Generator for Maintenance/Police Complex NOTICE TO ALL BIDDERS ADDENDUM NO. 1 TO TUCSON AIRPORT AUTHORITY 11/29/2018 In accordance with the Project Specifications and Contract Documents, and as noted in the Instructions to Bidders, Bidders on

More information

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2065

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2065 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2065 APPROVED: SIGNED DATE: March 8, 2007 Jon Adams Director of Compliance TITLE: SUBJECT: RULE 4002 NATIONAL EMISSION

More information

The Grande Excelsior Lanai Screen Enclosures Requirements for Decorators, Contractors and Subcontractors

The Grande Excelsior Lanai Screen Enclosures Requirements for Decorators, Contractors and Subcontractors The Grande Excelsior Lanai Screen Enclosures Requirements for Decorators, Contractors and Subcontractors 1. Owners must register with The Grande Preserve Management Office providing the name, address,

More information

CCSD#1 Stormwater Standards

CCSD#1 Stormwater Standards SECTION 6 EROSION CONTROL STANDARDS 6.1 INTRODUCTION The policies of this section shall apply during construction and until permanent measures are in place following construction as described herein, unless

More information

INFORMATION SHEET. To demolish the entire building to the foundation will require a demolition permit (Form 6).

INFORMATION SHEET. To demolish the entire building to the foundation will require a demolition permit (Form 6). City and County of San Francisco Department of Building Inspection Edwin M. Lee, Mayor Tom C. Hui, S.E., C.B.O., Director INFORMATION SHEET NO. 5-04 DATE CATEGORY SUBJECT : June 22, 2015 Structural Demolition

More information

Project # 570-CSI-001. Expand Mental Health Center, Building 27 SCOPE OF WORK

Project # 570-CSI-001. Expand Mental Health Center, Building 27 SCOPE OF WORK DEPARTMENT OF VETERANS AFFAIRS VA Central California Healthcare System Project # 570-CSI-001 Expand Mental Health Center, Building 27 SCOPE OF WORK 1. GENERAL DESCRIPTION The awarded contractor shall provide

More information

1. Title. This regulation shall be known as the Construction Activities and Compliance Deposit Regulation.

1. Title. This regulation shall be known as the Construction Activities and Compliance Deposit Regulation. CONSTRUCTION ACTIVITIES AND COMPLIANCE DEPOSIT REGULATION Adopted 3/16/90 Revised 4/10/92 Revised 4/7/94 Revised 4/8/98 Revised 10/21/98 Revised 11/27/2010 Revised 05/25/2017 1. Title. This regulation

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: OWNER: Shell and Core Improvements-1235 Mission Scope 1: Stairs DATE: December 29, 2017 1235 Mission Street San Francisco, California SFUSD Project

More information

B \ v44.doc

B \ v44.doc MEMORANDUM OF AGREEMENT FOR CONTRACT C1120 OF THE PURPLE LINE EXTENSION PROJECT SECTION 2 BETWEEN THE CITY OF BEVERLY HILLS AND THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY TABLE OF CONTENTS

More information

Delaware Street

Delaware Street A t t a c h m e n t 1 F i n d i n g s a n d C o n d i t i o n s 2004-06 Delaware Street Use Permit #09-10000052 JULY 22, 2010 CEQA FINDINGS 1. The project is categorically exempt from the provisions of

More information

STREET ADDRESS OF EVENT: Description of Event:

STREET ADDRESS OF EVENT: Description of Event: TEMPORARY USE PERMIT STREET ADDRESS OF EVENT: Description of Event: To Run from: (Date) (Hour) AM PM To: (Date) (Hour) AM PM Applicant: (Print) Applicant address: (Print) City, State Zip: Phone: Fax: Email:

More information

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION SECTION 13280 ASBESTOS CONTAINING MATERIALS REMEDIATION PART 1 GENERAL 1.1 SECTION INCLUDES A. Furnishing all labor, materials, equipment, and transportation necessary for properly and safely removing,

More information

In general, the management plan development process consisted of:

In general, the management plan development process consisted of: NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Seismic Boring Study Advance Utility Relocation

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor

More information

ADDENDUM No. 1 July 11, 2013 ASBESTOS ABATEMENT SPECIFICATIONS. Crawlspace Abatement and New Beginnings Academy

ADDENDUM No. 1 July 11, 2013 ASBESTOS ABATEMENT SPECIFICATIONS. Crawlspace Abatement and New Beginnings Academy BID No. 13.01 ADDENDUM No. 1 July 11, 2013 ASBESTOS ABATEMENT SPECIFICATIONS Crawlspace Abatement and Reinsulation @ New Beginnings Academy Owner NEW BEGINNINGS ACADEMY 211 East Michigan Avenue Ypsilanti,

More information

# 5 ) UN THREE CUPS YARD NORTH AMERICA CULTIVATION FACILITY SPECIAL USE PERMIT PUBLIC HEARING

# 5 ) UN THREE CUPS YARD NORTH AMERICA CULTIVATION FACILITY SPECIAL USE PERMIT PUBLIC HEARING # 5 ) UN-74-16 THREE CUPS YARD NORTH AMERICA CULTIVATION FACILITY SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: November 9, 2016 Item: UN-74-16 Prepared by: Marc

More information

# 11 ) UN MEDICAL MARIJUANA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING

# 11 ) UN MEDICAL MARIJUANA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING # 11 ) UN-31-16 MEDICAL MARIJUANA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: June 8, 2016 Item: UN-31-16 Prepared by: Marc Jordan GENERAL INFORMATION:

More information

Purple Line Extension Section 2 Community Meeting September 28, 2017

Purple Line Extension Section 2 Community Meeting September 28, 2017 Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance

More information

MITIGATION MONITORING AND REPORTING PROGRAM CHABOT COLLEGE 2012 FACILITIES MASTER PLAN

MITIGATION MONITORING AND REPORTING PROGRAM CHABOT COLLEGE 2012 FACILITIES MASTER PLAN EXHIBIT 2 Prepared for Chabot Las Positas Community College October 29, 2017 Land Use and Environmental Planning 1.0 INTRODUCTION 1.1 Background When adopting a Mitigated Negative Declaration, Public Resources

More information

CLASS I AND II ABATEMENT PROJECT SUBMITTALS

CLASS I AND II ABATEMENT PROJECT SUBMITTALS 5.1 Pre-Work Submittals CLASS I AND II ABATEMENT PROJECT SUBMITTALS Abatement contractors shall submit the following in a bound notebook to AU or our designated representative at the mandatory pre-construction

More information

NEW CONSTRUCTION APPLICATION

NEW CONSTRUCTION APPLICATION NEW CONSTRUCTION APPLICATION CONSTRUCTION COMMITMENT AND CONTRACTOR GUIDELINES The General Contractor is solely responsible for the compliance of these guidelines by all subcontractors, suppliers, and

More information

Noise Variance Review

Noise Variance Review Noise Variance #: NVAR17-0012 Noise Variance Review The noise variance (NVAR17-00012) request dated May 5, 2017 was evaluated based on the information provided in the variance submitted and any additional

More information

Management of Kern County Erskine Wildfire Debris

Management of Kern County Erskine Wildfire Debris Management of Kern County Erskine Wildfire Debris To ensure safety to workers, the public, and the environment, certain protocols should be followed during a wildfire disaster when removing structural

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

STAFF REPORT CITY OF SOLANA BEACH

STAFF REPORT CITY OF SOLANA BEACH 7-13-16 Mtg Item D.1. Updated Report #1 STAFF REPORT CITY OF SOLANA BEACH TO: Honorable Mayor and City Councilmembers FROM: Gregory Wade, City Manager MEETING DATE: ORIGINATING DEPT: Community Development

More information

DIVISION 2- EXISTING CONDITIONS

DIVISION 2- EXISTING CONDITIONS DIVISION 2- EXISTING CONDITIONS 024100- SELECTIVE DEMOLITION PART 1 - GENERAL: 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

5/13/2015 1

5/13/2015 1 1 2 3 4 5 6 7 In pipeline system design, the standard: NACE SP0169 clearly states that coatings are the primary corrosion protective system. Coating PIPE 8 9 What are my options? 10 11 UV/Photo-degradation

More information

Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC)

Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC) Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC) Plan Check Submittal Date: Plan Check / PCIS App #: Job Address: Applicant: P.C. Engineer: (Print first / last name) Phone:

More information

Your Store Logo Here. Brands You Trust People Who Know. Calendar

Your Store Logo Here. Brands You Trust People Who Know. Calendar Your Store Logo Here Brands You Trust People Who Know 2017 Calendar Vendor Logo January Store Name Vendor Logo Sunday Monday Tuesday Wednesday Thursday Friday Saturday 1 New Year s Day 2 New Year s Day

More information

REQUEST FOR BIDS METROPOLITAN PARK DISTRICT OF TACOMA Northwest Trek Core Area Fence Upgrade SWR BID NO. T Request for Bids

REQUEST FOR BIDS METROPOLITAN PARK DISTRICT OF TACOMA Northwest Trek Core Area Fence Upgrade SWR BID NO. T Request for Bids REQUEST FOR BIDS METROPOLITAN PARK DISTRICT OF TACOMA Northwest Trek Core Area Fence Upgrade SWR BID NO. T-2016-0210-05410910 Request for Bids The Metropolitan Park District of Tacoma will receive sealed

More information

City of West Hollywood Construction Period Mitigation Plan

City of West Hollywood Construction Period Mitigation Plan City of West Hollywood Construction Period Mitigation Plan Construction in an urban environment like the City of West Hollywood, presents challenges that require a well thought-out construction period

More information

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995.

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995. April 2012, rev. 00 02 8213 Asbestos Abatement 1. General 1.01 Summary of Work A. Contractor 1.02 Definitions 1. The Contractor shall provide removal and proper disposal of asbestos containing materials.

More information

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/ CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA 34695 PHONE: 727/724-1555 FAX: 727/724-1566 RIGHT-OF-WAY / EASEMENT USE PERMIT DATE SUBMITTED: EXPIRATION DATE: Submit the following to the

More information

COMMERCIAL PROJECT INFORMATION

COMMERCIAL PROJECT INFORMATION Community Development Building and Inspection Services 2100 Ridge Avenue Evanston, Illinois 60201-2798 T 847.448.4311 FAX 847.448.8020 www.cityofevanston.org COMMERCIAL PROJECT INFORMATION The Community

More information

TECHNICAL SPECIFICATIONS FOR INTERCEPTOR AND SIPHON INSPECTION/CLEANING

TECHNICAL SPECIFICATIONS FOR INTERCEPTOR AND SIPHON INSPECTION/CLEANING A. GENERAL TECHNICAL SPECIFICATIONS FOR INTERCEPTOR AND SIPHON INSPECTION/CLEANING Contractor shall furnish all labor, materials, equipment, traffic control, transportation, and supervision necessary for

More information

MITIGATION MONITORING PROGRAM

MITIGATION MONITORING PROGRAM MITIGATION MONITORING PROGRAM FOR ASPHALT PLANT NO. 1 REPLACEMENT AND MODERNIZATION W.O. E1907820 Initial Study/ Mitigated Negative Declaration SCH # 2015121036 Prepared By CITY OF LOS ANGELES BUREAU OF

More information

RESIDENTIAL PROJECT INFORMATION

RESIDENTIAL PROJECT INFORMATION Community Development Building and Inspection Services 2100 Ridge Avenue Evanston, Illinois 60201-2798 T 847.448.4311 FAX 847.448.8020 www.cityofevanston.org RESIDENTIAL PROJECT INFORMATION The Community

More information

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California for Bay Shore Library Bret Harte Library Dana Library Background Information Site/Building Owner: City of Long Beach Site Contact: The City of Long Beach Public Works Department, 333 West Ocean Blvd. Long

More information

or

or April 25, 2017 George Cooper Westminster II 1655 W. Fairview Avenue Boise, ID 83702 gcwestminster@yahoo.com Re: DRH17-00118 / 924 N. 21 st Street Dear Applicant: This letter is to inform you of the action

More information

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES The District of West Vancouver requires a Traffic Management Plan (TMP) to be submitted for acceptance by the Land Development

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

COUNTY OF ROCKLAND Department of General Services Purchasing Division

COUNTY OF ROCKLAND Department of General Services Purchasing Division COUNTY OF ROCKLAND Department of General Services Purchasing Division Title: Contract Period: Asbestos Abatement Services October 1, 2015 through September 30, 2016 w/2-1 year options, Extend through September

More information

RESOLUTION NO. Resolution No. Page 1 of 6

RESOLUTION NO. Resolution No. Page 1 of 6 RESOLUTION NO. RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF SANTA ROSA APPROVING A ZONING VARIANCE TO ALLOW SURFACE PARKING TO BE LOCATED IN THE FRONT OF THE COMMERCIAL BUILDING, AND ALLOW 24%

More information

Mitigation Monitoring Program Campus Master Plan 2015

Mitigation Monitoring Program Campus Master Plan 2015 Mitigation Program Campus Master Plan 2015 California State University, Sacramento May 2015 Environmental Mitigation Program Sacramento Campus Master Plan 2015 Project Section 1: Authority This Environmental

More information

SECTION AIR POLLUTION AND HAZARDOUS WASTE CONTROLS

SECTION AIR POLLUTION AND HAZARDOUS WASTE CONTROLS 1.0 GENERAL 1.01 DESCRIPTION SECTION 01 57 22 AIR POLLUTION AND HAZARDOUS WASTE CONTROLS The Work specified in this Section consists of eliminating or minimizing air and soil pollution generated by construction

More information

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system.

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system. Water Projects Pump Station No. 8 Rehabilitation (CIP No. 0796) Scope of Work: Rehabilitation of aging mechanical equipment and the associated piping at the existing pump station adjacent to Reservoir

More information

8.0 MITIGATION MONITORING AND REPORTING PROGRAM

8.0 MITIGATION MONITORING AND REPORTING PROGRAM 8.0 MITIGATION MONITORING AND REPORTING PROGRAM Public Resources Code, Section 21081.6 requires that mitigation measures identified in environmental review documents prepared in accordance with CEQA are

More information

Attachment 1 Findings and Conditions

Attachment 1 Findings and Conditions 2451 Ridge Road Use Permit #04-10000066 Attachment 1 Findings and Conditions APRIL 10, 2008 CEQA FINDINGS 1. The project is categorically exempt from the provisions of the California Environmental Quality

More information

SECTION TRAFFIC REGULATIONS

SECTION TRAFFIC REGULATIONS PART 1 GENERAL 1.1 DESCRIPTION A. Traffic Control permits, notifications, mobilization, temporary signs, barriers, lights, flagging personnel, striping, markings, and demobilization and removal. 1.2 RELATED

More information

#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING

#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING #4) UN-60-16 NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: September 14, 2016 Item: UN-60-16 Prepared by: Robert Eastman GENERAL INFORMATION:

More information

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project

More information

PROCEDURES FOR FIBER OPTIC CABLE PERMITS REVISED: OCTOBER 18, 2018

PROCEDURES FOR FIBER OPTIC CABLE PERMITS REVISED: OCTOBER 18, 2018 JIM STRICKLAND MAYOR ENGINEERING DIVISION PROCEDURES FOR FIBER OPTIC CABLE PERMITS REVISED: OCTOBER 18, 2018 CITY OF MEMPHIS 125 N. Main St., Memphis TN 38103 Table of Contents I Introduction & General

More information

A D M I N I S T R A T I V E U S E P E R M I T

A D M I N I S T R A T I V E U S E P E R M I T Planning and Development Department Land Use Planning Division A D M I N I S T R A T I V E U S E P E R M I T 901 Arlington Avenue Project Description: To construct a 726 square foot, one-story addition

More information

AGENDA REPORT ALTERNATIVE PARKING FACILITIES TO PROVIDE REQUIRED PARKING IN COMMERCIAL

AGENDA REPORT ALTERNATIVE PARKING FACILITIES TO PROVIDE REQUIRED PARKING IN COMMERCIAL Meeting Date: November 1, 2016 Item Number: E-2 AGENDA REPORT To: From: Subject: Honorable Mayor & City Council Ryan Gohlich, AICP Assistant Director of Community Development I City Planner AN ORDINANCE

More information

Asbestos Dust Mitigation Plan (ADMP) Application

Asbestos Dust Mitigation Plan (ADMP) Application El Dorado County Air Quality Management District (AQMD) 330 Fair Lane, Placerville, CA 95667 Phone: 530-621-7501 / Fax: 530-295-2774 www.edcgov.us/airqualitymanagement Asbestos Dust Mitigation Plan (ADMP)

More information

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

Commercial Submittal Packet

Commercial Submittal Packet Commercial Submittal Packet City of Pepper Pike Building Department 28000 Shaker Boulevard Pepper Pike, Ohio 44124 Phone: (216) 896-6134 Fax: (216) 831-6525 www.pepperpike.org Submitting for the Architectural

More information

AS AMENDED BY THE PLANNING COMMISSION APRIL 6, 2006 NOTE: Approval of this application is valid only if the following conditions are met. This permit shall expire unless activated within 18 months of the

More information

Mississippi Department of Environmental Quality. Policy for Handling Demolitions of Structures to Address Potential Asbestos January 3, 2006

Mississippi Department of Environmental Quality. Policy for Handling Demolitions of Structures to Address Potential Asbestos January 3, 2006 Disclaimer: Mississippi Department of Environmental Quality Policy for Handling Demolitions of Structures to Address Potential Asbestos January 3, 2006 This guidance supersedes MDEQ December 16, 2005,

More information

EXCAVATION / RIGHT OF WAY PERMIT

EXCAVATION / RIGHT OF WAY PERMIT $25 Application Fee PERMIT# EXCAVATION / RIGHT OF WAY PERMIT NOTE: No permit shall be issued without current Montana Contractors License, Insurance and Bonding on file with the Public Works Department.

More information

DRH / 1909 N.

DRH / 1909 N. February 28, 2017 David Benoit Syringa Construction 5839 Yaquina Head Garden City, ID 83714 dhbenoit@yahoo.com RE: DRH16-00473 / 1909 N. 15 th Street Dear Applicant: This letter is to inform you of the

More information

PERFORMANCE WORK STATEMENT FOR AJJY , REMOVAL AND DISPOSAL OF COMPUTERS (HARDWARES) IN B21000, ANDERSEN AIR FORCE BASE, GUAM

PERFORMANCE WORK STATEMENT FOR AJJY , REMOVAL AND DISPOSAL OF COMPUTERS (HARDWARES) IN B21000, ANDERSEN AIR FORCE BASE, GUAM PERFORMANCE WORK STATEMENT FOR AJJY 14-1081, REMOVAL AND DISPOSAL OF COMPUTERS (HARDWARES) IN B21000, ANDERSEN AIR FORCE BASE, GUAM 29 August 2014 1 of 6 AJJY 14-1081, REMOVAL AND DISPOSAL OF COMPUTERS

More information

Demolition Information Packet

Demolition Information Packet Table of Contents I. Demolition Process Checklist II. III. IV. Approval for Demolition Demolition Permit Utility Disconnections V. Other Important Issues Asbestos and Lead VI. VII. Demolition Standards,

More information

ZAB Hearing May 14, 2015

ZAB Hearing May 14, 2015 ZAB Hearing May 14, 2015 Comments from April 23rd TOPICS Streamlined Environmental Review Protections for Berkeley High School Air Quality, Noise, and Traffic Project Alternatives Water Supply/Wastewater

More information

EXHIBIT A. Scope of Work

EXHIBIT A. Scope of Work EXHIBIT A Scope of Work 1.0 INTRODUCTION With the opening of Denver International Airport (DIA) in February 1995, the era of aviation at SIA, which began as Denver Municipal Airport in 1929 ended. With

More information

1900A. 1900A.B.3. ARTICLE 19A PEACE AND GOOD ORDER [Article 19A created by Ord. No. 224, previously Art. 19]

1900A. 1900A.B.3. ARTICLE 19A PEACE AND GOOD ORDER [Article 19A created by Ord. No. 224, previously Art. 19] 1900A. 1900A.B.3. ARTICLE 19A PEACE AND GOOD ORDER [Article 19A created 7-9-14 by Ord. No. 224, previously Art. 19] SECTION 1900A ENVIRONMENTAL CONTROLS A. Purpose. It is the intent of these regulations

More information

Holiday Compensation Updated: December 2017

Holiday Compensation Updated: December 2017 Holiday Compensation Updated: December 2017 Recognized Legal Holidays The City recognizes the following eleven legal holidays: January 1 (New Year s Day) the third Monday in January (Martin Luther King,

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: OWNER: Shell and Core Improvements-1235 Mission Scope 2: Roof 2 DATE: December 29, 2017 1235 Mission Street San Francisco, California SFUSD Project

More information

DEMOLITION OF BUILDINGS

DEMOLITION OF BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC Chapter 33 Effective: 01-01-2017 DOCUMENT NO.: P/BC 2017-039 Revised: 01-22-2019 Previously Issued As: P/BC 2014-039 DEMOLITION OF BUILDINGS

More information

Asbestos and Lead-Based Paint Abatement Requirements at Brownfields/Voluntary Cleanup Program Sites

Asbestos and Lead-Based Paint Abatement Requirements at Brownfields/Voluntary Cleanup Program Sites Asbestos and Lead-Based Paint Abatement Requirements at Brownfields/Voluntary Cleanup Program Sites Hazardous Waste Program Fact Sheet Asbestos-containing materials and lead-based paint have the potential

More information

PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL

PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL o PUBLIC WORKS DEPARTMENT PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL CIVIL ENGINEERING AND ARCHITECTURE 1. Offsite Improvements - Civil Engineering drawings may be required to show the following: Replacement

More information

DEMOLITION OF BUILDINGS

DEMOLITION OF BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC Chapter 33 Effective: 01-01-2014 DOCUMENT NO.: P/BC 2014-039 Revised: 05-11-2016 Previously Issued As: P/BC 2008-039 DEMOLITION OF BUILDINGS

More information

FENCES YOU MUST HAVE YOUR PROPERTY STAKES LOCATED AND EXPOSED BEFORE A PERMIT WILL BE ISSUED

FENCES YOU MUST HAVE YOUR PROPERTY STAKES LOCATED AND EXPOSED BEFORE A PERMIT WILL BE ISSUED FENCES The purpose of City Code Chapter 129-203 is to promote a pleasant physical environment and to protect the public and private property within the City by regulating the location, height, type of

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work: 125 Syndicate Avenue, Thunder Bay, Ontario Page 1 of 5 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:.1 Removing asbestos-containing transite

More information