Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system.

Size: px
Start display at page:

Download "Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system."

Transcription

1 Water Projects Pump Station No. 8 Rehabilitation (CIP No. 0796) Scope of Work: Rehabilitation of aging mechanical equipment and the associated piping at the existing pump station adjacent to Reservoir No. 7 Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system. Preliminary/Final Design & Bidding April 2017 May 2018 Pump Station Construction July 2018 March 2019 Testing March 2019 May 2019 In Service - May 2019 * Design Services & Const. Support Cannon $233,073 $235,361 Pump Station Construction Cora Constructors $2,500,000 $200,905 Total: $2,733,073 $436,266 *As of 11/30/2018 La Brea Subarea - Central Basin Groundwater Development Project (CIP No. 0916) Scope of Work: Implement Water Enterprise Plan recommendation to develop groundwater resources in the La Brea Subarea of the Central Basin. Feasibility review conducted for drilling well at Sand Pit site 2300 block La Cienega Blvd. Staff reviewing feasibility of potential well site at 1700 block La Cienega Blvd with property owner. Agreement with real estate broker anticipated in January 2019 to assist with identifying other potential well sites in basin. Real Estate Acquisition May

2 Preliminary Design Report May 2017 Initial Study Mitigated Negative TBD TBD Declaration/EIR Real Estate Acquisition $9,100,000 $9,000,000 Preliminary Design Report $768,000 $767,783 Environmental Document TBD - Final Design TBD - Construction TBD - Total Project Cost: $9,868,000 $9,767,783 FY2018/19 Water Main Replacements (CIP No. 0387) Scope of Work: Replace approximately 13,400 feet of water main on Loma Vista Drive, 2,100 feet of water main on San Ysidro Drive and 7,300 feet of water main on Coldwater Canyon Drive. Existing pipelines are 6-inches to 16-inches in diameter and range with most sections between 60 and 90 years old. Project may be expanded to include Coldwater Canyon Drive design for construction in FY2019/20. Reviewing proposals for engineering design services received in. Design contract award anticipated in January Design & Bidding January 2019 June 2019 Construction August 2019 TBD 2020 Major Projects Oil and Gas Wells Plugging Project at 9865 Olympic Boulevard (CIP No. 0583) Scope of Work: Plugging of 19 Oil and Gas Wells located at 9865 Olympic Boulevard. Contractor (ARB) continues to monitor the oil well and maintain the pressure in a safe level. The gas flare is operational and being used to maintain safe pressures. 2

3 Department of Conservation Division Of Oil Gas and Geothermal Resources (DOGGR) issued permits for plugging of four oil wells: BH-15, HS-1A, HS-3 and OS-7. As of December 4, 2018, these four wells have been plugged and abandoned. The oil rig will be moved to the next well, OS-13, and begin plugging when DOGGR approval is received. Due to a number of factors, the revised project cost estimate is 2 to 3 times the original estimate of $8 million. BHUSD and City Council are informed regularly of progress and cost issues and the City Council will consider approval of a contract amendment on December 18. Anticipated Completion Engineering Design & Bidding Dec Jan Well Plugging June 2018 May 2020 * Design Services & Const. Support WZI, Inc. $460,000 $449,300 Oil Well Monitoring & Plugging Services ARB, Inc. $7,000,000 $3,540,502 Money Reimbursed to BHUSD $533,340 $533,341 Terra Firma Enterprises $3,210 DOGGR Well Plugging Bond $100,000 Total: $7,993,340 $4,626,353 *As of 11/30/2018 North Santa Monica Boulevard Reconstruction (CIP No. 0889) Scope of Work: Reconstruction of North Santa Monica Boulevard including replacement of roadway structural section, curb and gutter, curb ramps/sidewalk, street lights, traffic signal upgrades, fiber optic cable and storm drain systems. Original contract work completed in July. Bicycle lanes completed in September. Work continues on added scope for fiber optic cable and CCTV installation through January Awarded the 2018 Project of the Year for the Transportation Category from the Southern California Chapter of the American Public Works Association (APWA) and an Engineering Excellence Merit Award from the American Council of Engineering Companies (ACEC). 3

4 Design & Bidding - June 2016 Construction January 2017 Fall 2018 * Preliminary/Final Design Psomas $2,170,730 $2,106,189 Construction Griffith Company $22,841,000 $21,732,515 Construction Management Berg & Associates $2,397,000 $1,938,800 Environmental Review Services Lindmark $132,700 $100,970 SM-5 Parking Operations Parking Concepts, Inc. $518,702 $415,000 Total: $28,060,132 $26,293,474 *As of 11/29/2018 Metro Purple Line Extension Scope of Work: Construction of two subway stations (Wilshire/La Cienega & Wilshire/Rodeo) and twin tunnels along the Wilshire Boulevard corridor Section 1: Wilshire/La Cienega Station Excavation of Station Box is underway. Station Construction In Service 2023 (operational) 2024 Section 2: Wilshire/Rodeo Station All work in public right-of-way suspended through January 1 for holiday moratorium. Geotechnical seismic boring will resume in January. Demolition of 9430 Wilshire is complete. Demolition of properties on SW corner of Canon and Wilshire and relocation of City-owned utilities will begin in January. Advanced Utility Relocation September 2017 October 2018 Geotechnical Seismic Borings May 2018 November 2018 Demolition/Construction Yard July 2018 November 2018 Station Construction September In Service 2023 (operational)

5 Infrastructure Projects Infrastructure Repairs (CIP No. 0195) Scope of Work: Pavement and limited sewer repairs throughout Beverly Hills; Pavement repairs in West Hollywood related to the Beverly Hills Water utility. If there are remaining funds after all known work is completed, the contract will remain open to accommodate future asneeded repairs. Listed Beverly Hills work completed in March West Hollywood work completed in June Emergency street repairs on Loma Vista Drive were completed on August 4, Staff is in the process of closing out this project. Minor punch list items remain. Beverly Hills pavement & spot sewer repairs June 2017 March 2018 Loma Vista Drive emergency street repair July 2018 August 2018 West Hollywood pavement repairs related to June 2018 June 2018 BH Water * Construction Hardy & Harper $1,069,000 $951,437 *As of 11/26/2018 LED Street Light Replacement Program (CIP No. 0200) Scope of Work: Citywide conversion of 5,543 existing street lights to software-controlled LED. Council awarded contract on August 21, Contractor began installation on November 1. Design & Bidding January 2018 July 2018 Construction October 2018 May * Design NA NA Construction $5,105, $795,864 *As of 11/29/2018

6 Civic Center Drive Tree Planting (CIP No. 0089) Scope of Work: Plant approximately 51 large trees on the north side of the Civic Center Drive right-of-way between Beverly Boulevard and the alley west of Oakhurst Drive. Due to arsenic presence in the soil, a work plan and soils management plan must be developed and submitted to the Department of Toxic Substance Control (DTSC) and the South Coast Air Quality Management District (AQMD) for approval. Soil sampling was completed on September 7, Survey work was completed on October 26, The work plan and soil management plan were submitted to the DTSC on November 5, Preliminary review comments received December 4, Site preparation will begin in January. Tree planting will begin upon agency approvals. DTSC review and approval of the work plan November 2018 Approve a construction contract January 2019 Plant trees January 2019 February 2019 * Consulting Tree Care LA, Inc. $26,282 $11,688 Consulting Lindmark Engineering, Inc. $61,080 $21,882 *As of 11/26/2018 3rd Street Crosswalk (CIP No. 0367) Scope of Work: Construct raised crosswalk on West 3 rd Street west of North Maple Drive. Surveying and preliminary design concept completed in early October. Final design underway. Temporary crosswalk installed ahead of schedule on October 22 nd. Design & Bidding September 2018 January 2019 Temporary Crosswalk Installation October 17, 2018 October 26, 2018 Construction (Permanent Crosswalk) February 2019 April 2019 * Design $50,000 - Construction TBD - *As of 11/26/2018 6

7 Stormwater Projects Burton Way Median Green Streets/Water Efficient Landscape Project (CIP No. 0270) Scope of Work: Design and construct green streets features on Burton Way median to improve stormwater quality and infiltration in compliance with the Enhanced Watershed Management Plan (EWMP) and provide water efficient, drought tolerant landscaping. Project is proposed to be fully designed in 2018 and constructed in two phases. Amendment to prepare final designs for Phase I and Phase II approved at June 19, 2018 City Council Meeting. Final design plans and project specifications are anticipated to complete by April Feasibility Study June 2016 August 2017 Preliminary Design Alternatives September 2017 April 2018 Design of Phase I & II and Bidding/Award July 2018 April 2019 Construction Phase I May 2019 December 2019 Construction Phase II TBD TBD Study/Design CWE $638,046 $292,986 Construction TBD est. $3M - Total: $3.7M $292,986 *As of 11/29/2018 7

HILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer

HILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer April 18, 2018 MEMORANDUM PUBLIC WORKS DEPARTMENT HILLS BEVERLY CITY OF BEVERLY HILLS Public Works Commission Rob Welch, Acting City Engineer Capital Projects Update Capital Improvement Projects Update

More information

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222 Water Projects Maple Wells Project (CIP No. 0916) Scope of Work: Construction of two municipal supply wells at the Maple Yard (342 Foothill Road) and a pipeline to convey well water to the water treatment

More information

Public Works Department

Public Works Department Public Works Department Monthly Report Public Works Department Monthly February Report 2017 George Chavez Assistant City Manager/Director of Public Works Key Message The Public Works Department reached

More information

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016 Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section

More information

AGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018

AGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018 AGENDA REPORT Meeting Date: November 20, 2018 Item Number: E 15 To: From: Honorable Mayor & City Council Vincent Chee, Project Manager Subject: A CONTINUATION OF DECLARATION THAT THE PUBLIC INTEREST AND

More information

Purple Line Extension Section 2 Community Meeting September 28, 2017

Purple Line Extension Section 2 Community Meeting September 28, 2017 Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

Public Works Department Monthly Report

Public Works Department Monthly Report Key Message Public Works Department Monthly Report George Chavez Assistant City Manager/Director of Public Works We are pleased to present to you this inaugural monthly report from the Public Works Department.

More information

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation

More information

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,

More information

Presentation Overview

Presentation Overview Presentation Overview Project Background Preliminary Design Report (PDR) Objectives Status Project Elements Well Sites Conveyance System Treatment Plant Los Angeles Water Exchange Activities Over Next

More information

CITY OF BEVERLY HILLS PUBLIC WORKS DEPARTMENT MEMORANDUM PUBLIC WORKS COMMISSION. Vince Damasse, Water Resources Manager

CITY OF BEVERLY HILLS PUBLIC WORKS DEPARTMENT MEMORANDUM PUBLIC WORKS COMMISSION. Vince Damasse, Water Resources Manager CITY OF BEVERLY HILLS PUBLIC WORKS DEPARTMENT MEMORANDUM TO: FROM: PUBLIC WORKS COMMISSION Vince Damasse, Water Resources Manager Trish Rhay, Assistant Director of Public Works DATE: SUBJECT: ATTACHMENT:

More information

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

Department of Street Services

Department of Street Services Department of Street Services FY 07-08 Proposed Budget Briefing to the City Council September 5, 2007 Purpose An overview of the Department of Street Services Scope of operation and maintenance activities

More information

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session Long-Term Capital Improvement Funding Plan March 18, 2014 City Council Study Session Overview Long-term 10 year view to know what s planned Project Overview Focus on FY 2014-15 and FY 2015-16 Funding Plan

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

ATTACHMENT 4 Section Project Status Quarterly Report - Dec 31, 2015 Measure V - Clean Beaches and Ocean Parcel Tax

ATTACHMENT 4 Section Project Status Quarterly Report - Dec 31, 2015 Measure V - Clean Beaches and Ocean Parcel Tax ATTACHMENT 4 Section 3.0 - Project Status Quarterly Report - Dec 31, 2015 Completed Projects Description Bicknell Avenue Green Street Pier Storm Drain Improvement Pier Water Quality Improvement Permeable

More information

Proposed Water Rate Adjustment

Proposed Water Rate Adjustment Proposed Water Rate Adjustment Frequently Asked Questions Q: Why do utility rates need to be adjusted now? A: The City reviewed water rates as part of a 10-year financial plan and determined that rates

More information

Engineering & Construction -- Transit Status Report. Significant Issues

Engineering & Construction -- Transit Status Report. Significant Issues ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT

More information

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

Westside Purple Line Extension Section 1 Project Overview

Westside Purple Line Extension Section 1 Project Overview Westside Purple Line Extension Section 1 Project Overview Westside Purple Line Extension (WPLE) Section 1 Project Purple Line Project Alignment The WPLE corridor traverses portions of three jurisdictions,

More information

Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010

Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Presented in Beverly Hills: June 7, 2010 Where We are in the

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

WATER ENTERPRISE PLAN (WEP) REASSESSMENT

WATER ENTERPRISE PLAN (WEP) REASSESSMENT WATER ENTERPRISE PLAN (WEP) REASSESSMENT City of Beverly Hills Public Works Commission October 12, 2017 1 BACKGROUND City adopted 2015 WEP to enhance water supply portfolio Since then, the following has

More information

Purple Line Extension. Construction Community Meeting March 16, 2017

Purple Line Extension. Construction Community Meeting March 16, 2017 Purple Line Extension Construction Community Meeting March 16, 2017 1 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking:

More information

ckly STAFF REPORT Trish Rhay, Assistant Director of Public Works Caitlin Sims, Senior Management Analyst

ckly STAFF REPORT Trish Rhay, Assistant Director of Public Works Caitlin Sims, Senior Management Analyst Subject: Distribution of Water Rates Public Notice Phase 1: Five-Year Rate Review and Adjustment to Address Revenue Phase 2: WEP Unit Capital Charge and Cost of Service Study. With that direction, staff

More information

Purple Line Extension. Westside/Central Service Council August 13, 2014

Purple Line Extension. Westside/Central Service Council August 13, 2014 Purple Line Extension Westside/Central Service Council August 13, 2014 1 Project Overview & Schedule 2 Approved Project 3 Approved Project - Schedule Planned Schedule Forecasted Schedule Section 1 Section

More information

AGENDA REPORT. To: Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location

AGENDA REPORT. To: Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location 9 Meeting Date: May 8, 2018 Item Number: D 6 To: From: Subject: AGENDA REPORT Honorable Mayor & City Council Robert Welch, Acting City Engineer Raj Patel, City Building Official ASBESTOS ABATEMENT PERMIT

More information

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program STAFF REPORT DATE: November 14, 2017 TO: Bryan Montgomery, City Manager Approved and Forwarded to the City Council FROM: SUBJECT: Kevin Rohani, P.E. Public Works Director/City Engineer FY 2017/18 First

More information

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058

More information

sewers ANd storm drains Storm Drain Under Construction, 1916

sewers ANd storm drains Storm Drain Under Construction, 1916 sewers ANd storm drains Storm Drain Under Construction, 1916 A d o p t e d C A p I t A L I M p R o V e M e N t p R o G R A M F I s C A L Y e A R 2 1 9 FY 219-223 Capital Improvement Program FY 218 FY 219

More information

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT SECTION 7 Public Infrastructure, Facilities and Services 8Chapter 8 INFRASTRUCTURE ELEMENT INF-2 CHAPTER 8 Infrastructure Element INTRODUCTION Cupertino s public infrastructure works in tandem with the

More information

Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-16. Santa Monica/San Vicente 1/4-Mile Station Area August 16, 2010 Page 5-35 Figure 5-17. Beverly Center 1/4-Mile Station Area August 16, 2010 Page 5-36 5.8 Alternative 5 Santa Monica Extension

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN

INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN FINAL REPORT INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN Prepared for: City of Modesto Prepared by: Willdan Financial Services Approved by Modesto City Council on July 9, 2013 Resolution

More information

CITY OF BEVERLY HILLS BEVERLY HILLS PUBLIC WORKS DEPARTMENT MEMORANDUM TO: FROM: SUBJECT: Public Works Commission

CITY OF BEVERLY HILLS BEVERLY HILLS PUBLIC WORKS DEPARTMENT MEMORANDUM TO: FROM: SUBJECT: Public Works Commission BEVERLY HILLS CITY OF BEVERLY HILLS PUBLIC WORKS DEPARTMENT MEMORANDUM TO: FROM: DATE: SUBJECT: Public Works Commission Shana Epstein, Director of Public Works June 14, 2018 Director s Report The following

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Seismic Boring Study Advance Utility Relocation

More information

MINUTES ENGINEERING AND OPERATIONS COMMITTEE Special Meeting May 3, 2018

MINUTES ENGINEERING AND OPERATIONS COMMITTEE Special Meeting May 3, 2018 MINUTES ENGINEERING AND OPERATIONS COMMITTEE Special Meeting May 3, 2018 EVMWD BOARD ACTION APPROVED APPROVED AS AMENDED DENIED CONTINUED The Engineering and Operations Committee Meeting was held at 31315

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS

INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS 1 of 5 8/1/2013 2:10 PM INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS Project Location and Description Glen Mayberry, Project Manager Roy F. Weston, Houston, TX The project is in

More information

5 YEAR CAPITAL IMPROVEMENT PROGRAM

5 YEAR CAPITAL IMPROVEMENT PROGRAM 5 YEAR CAPITAL IMPROVEMENT PROGRAM 329 City of Hermosa Beach Department of Public Works Capital Improvement Program For Fiscal Years 2015-16 Thru 2019-20 PROJECT NAME FY15-16 1 FY16-17 FY 17-18 FY 18-19

More information

S EXECUTIVE SUMMARY. S.1 Introduction

S EXECUTIVE SUMMARY. S.1 Introduction S EXECUTIVE SUMMARY S.1 Introduction This Final Supplemental Environmental Impact Statement (Final SEIS) and Section 4(f) Evaluation is a limited scope document that was prepared in response to the Final

More information

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS 2018-19 THROUGH 2022-23 Project Number Stg No. Project

More information

Task Order Authorization

Task Order Authorization Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update

More information

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT:

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT: AGENDA HEADING: Unfinished Business AGENDA REQUEST COMMISSION MEETING DATE: June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell AGENDA ITEM NO: VI.2. Originating Department SUBJECT: Department

More information

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas.

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas. Affected Environment, Environmental 2.1.4 Utilities and Service Systems This section addresses the potential impacts to public utilities and service systems within the project area as a result of project

More information

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2 Addendum Number 1 Request for Proposals No. 17-001 Various On-call Professional Design and Engineering Services To all prospective firms under specifications for Request for Proposals (RFP) No. 17-001,

More information

DOCUMENT ADDENDA AND MODIFICATIONS

DOCUMENT ADDENDA AND MODIFICATIONS DOCUMENT ADDENDA AND MODIFICATIONS PART 1 1.1 PROCEDURE GENERAL A. For filing purposes, add Addenda and Modifications to the Contract Documents following this page. Modified June 20, 2017 Addenda and Modifications

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

study for 2018 include:

study for 2018 include: MEMORANDUM TO: Mayor and City Council gk FROM: Shawn Sanders irector of Public Works DATE: March 15, 2018 RE: Feasibility Study for the 2018 Street Improvement Project Project No. 2018-02 INTRODUCTION

More information

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7.1 E-Permit and U-Permit Permit Description and Purpose The Excavation Permit (E-Permit) and the Utility Permit (U-Permit) are issued to allow construction,

More information

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report BRIDGE DISTRICT Phase 1 Infrastructure Improvement Project (for work completed thru November 2011) Cover Photo: Joint Utility Trench installation along Fifth Street just north of Bridge Street. Page 1

More information

STORM DRAIN PROJECTS

STORM DRAIN PROJECTS STORM DRAIN PROJECTS PROJECT DESCRIPTIONS The CIP includes a general list of projects scheduled during each of the five years of the program, followed by detailed project sheets arranged by project category,

More information

PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT

PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT 34 One Gateway Plaza Los Angeles, CA 90012-2952 CONSTRUCTION COMMITTEE SEPTEMBER 20, 2012 PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT ACTION: APPROVE USE OF DESIGN-BUILD CONTRACTING DELIVERY

More information

SFPUC Flooding Workshop Tuesday, February 9, 2016

SFPUC Flooding Workshop Tuesday, February 9, 2016 Presenters: SFPUC Flooding Workshop Tuesday, February 9, 2016 Tommy Moala, Assistant General Manager, Wastewater Enterprise Stefani Harrison, Project Manager Photo: Dec 3, 2014 End of Cayuga Street 25-year

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

PUBLIC WORKS SERVICES DEPARTMENT MEMORANDUM WATER SUPPLY EXACTION FEE

PUBLIC WORKS SERVICES DEPARTMENT MEMORANDUM WATER SUPPLY EXACTION FEE CITY OF BEVERLY HILLS PUBLIC WORKS SERVICES DEPARTMENT MEMORANDUM TO: FROM: PUBLIC WORKS COMMISSION Vince Damasse, Water Resources Manager Trish Rhay, Assistant Director of Public Works Services DATE:

More information

PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL

PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL o PUBLIC WORKS DEPARTMENT PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL CIVIL ENGINEERING AND ARCHITECTURE 1. Offsite Improvements - Civil Engineering drawings may be required to show the following: Replacement

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

6.13 Utilities and Service Systems

6.13 Utilities and Service Systems 6.13 6.13.1 Introduction This section describes impacts for utilities and service systems that would result from construction and operation of the CEQA Alternatives. 6.13.2 Regulatory Setting There are

More information

B \ v36.doc

B \ v36.doc MEMORANDUM OF AGREEMENT FOR CONTRACT C1120 OF THE PURPLE LINE EXTENSION PROJECT SECTION 2 BETWEEN THE CITY OF BEVERLY HILLS AND THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY TABLE OF CONTENTS

More information

2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements. December 11, 2017 Public Improvement Hearing

2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements. December 11, 2017 Public Improvement Hearing 2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements December 11, 2017 Public Improvement Hearing Project Objectives Reconstruct Deteriorated Streets Upgrade City Underground

More information

Stormwater Bio-Infiltration Pilot Project Concept Proposal Submitted by

Stormwater Bio-Infiltration Pilot Project Concept Proposal Submitted by Concept Proposal Submitted by Public Works Department 1947 Center Street, Fourth Floor Berkeley, CA 94704 December 17, 2009 Executive Summary The s Public Works Department submits this concept proposal

More information

~E~RLY AGENDA REPORT. Meeting Date: April 11,2013 Item Number:

~E~RLY AGENDA REPORT. Meeting Date: April 11,2013 Item Number: ~E~RLY Meeting Date: April 11,2013 Item Number: To: From: Subject: F li AGENDA REPORT Honorable Mayor & City Council Anne Garvey-Zaworski, Principal Civil Engineer Kevin Watson, Water Operations Manager

More information

Public Works designs, manages and builds more than $4 billion in construction projects across San Francisco. DOING BID ON OUR PROJECTS. JOIN THE CITY TEAM. BUSINESSwith BUILDINGS PLAYGROUNDS STREET RESURFACING

More information

Planning Committee February 10, 2015

Planning Committee February 10, 2015 Leland Reservoir Replacement Planning Committee February 10, 2015 Open-Cut Reservoir Projects Permanently out of service Completed Next five years (FY2016-20) Construction beyond FY2020 LELAND RESERVOIR

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINISTRATOR MARCH 27, 2018

QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINISTRATOR MARCH 27, 2018 QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINISTRATOR MARCH 27, 2018 Aragona Drainage Improvements D A S H B O A R D Ashville Park Drainage Improvements

More information

4.11 Water Resources Regulatory Setting. Federal

4.11 Water Resources Regulatory Setting. Federal 4.11 Water Resources This section has been updated from the Draft EIS/EIR to focus on the analysis of the effects of the LPA on water resources. The analysis results have not changed from the Draft EIS/EIR.

More information

A PENNEY (ROAD) SAVED IS A LESSON (L)EARNED

A PENNEY (ROAD) SAVED IS A LESSON (L)EARNED Session #29 Collection System 3: Rehabilitation Issues A PENNEY (ROAD) SAVED IS A LESSON (L)EARNED New England Water Environment Association 2019 Annual Conference Marriot Copley Place, Boston, MA January

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

B \ v44.doc

B \ v44.doc MEMORANDUM OF AGREEMENT FOR CONTRACT C1120 OF THE PURPLE LINE EXTENSION PROJECT SECTION 2 BETWEEN THE CITY OF BEVERLY HILLS AND THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY TABLE OF CONTENTS

More information

CAPITAL IMPROVEMENT PROGRAM WATER

CAPITAL IMPROVEMENT PROGRAM WATER CAPITAL IMPROVEMENT PROGRAM 246 247 FUNDS (711-715) Access Road Improvements c709840 Minor road repair and pipeline clearance work to gain access to water facilities and equipment. Project Cost Estimate

More information

3.10 Hydrology and Water Quality. Environmental Setting

3.10 Hydrology and Water Quality. Environmental Setting 3.10 Hydrology and Water Quality This section describes the potential hydrology and water quality impacts associated with the proposed changes to the approved project. Environmental Setting This section

More information

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-6. Century City 1/4-Mile Station Area August 16, 2010 Page 5-14 Figure 5-7. Wilshire/Westwood 1/4-Mile Station Area August 16, 2010 Page 5-15 Alternative 1 would be constructed underneath existing

More information

Modified FY ,100, ,329,791

Modified FY ,100, ,329,791 Retail/North Andrews Gardens Neighborhood Improvement Program Expenses Through FY 4 Modified FY 5 Budget FY 26-21 North Andrews Gardens Neighborhood Improvement Project 21,524,34 22,75,757 --- 6,1, 6 ---

More information

CPC GPA-ZC-HD-CU-CUB-ZAI-SPR T-1 CONDITIONS FOR EFFECTUATING TENTATIVE (T) CLASSIFICATION REMOVAL

CPC GPA-ZC-HD-CU-CUB-ZAI-SPR T-1 CONDITIONS FOR EFFECTUATING TENTATIVE (T) CLASSIFICATION REMOVAL CPC-2014-3808-GPA-ZC-HD-CU-CUB-ZAI-SPR T-1 CONDITIONS FOR EFFECTUATING TENTATIVE (T) CLASSIFICATION REMOVAL Pursuant to Los Angeles Municipal Code Section 12.32 G, the T Tentative Classification shall

More information

GOLD LEVEL AWARD WINNER. City of Pomona Sustainability Best Practices Activities

GOLD LEVEL AWARD WINNER. City of Pomona Sustainability Best Practices Activities GOLD LEVEL AWARD WINNER City of Pomona Sustainability Best Practices Activities About This Document This document tracks and shares local agency best practice activities completed and counted as part of

More information

Zone 1 Report to the Zone Commissioners By Jason Uhley, General Manager-Chief Engineer November 2018

Zone 1 Report to the Zone Commissioners By Jason Uhley, General Manager-Chief Engineer November 2018 Zone 1 Report to the Zone Commissioners By Jason Uhley, General Manager-Chief Engineer November 2018 Current/Recent Construction Projects Monroe MDP - Monroe Channel Stage 4 (1-8-00071-04) Construction

More information

Project Need and Evaluation

Project Need and Evaluation City of Brooklyn Center 2011 Palmer Lake East Street and Utility Reconstruction Project Public Hearings February 14, 2011 Public Improvement Hearing: Special Assessments Local public improvements to the

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

FY2018 CIRP Detailed Summary

FY2018 CIRP Detailed Summary FY2018 CIRP Detailed Summary 1 FY 2018 CIRP New Allocations Type of Project Number % Budget Asset Management Renewal 15 6 19,562,000 Cityshed 6 6 19,238,000 CSO 12 16 50,470,000 SSO 87 61 195,696,000 Treatment

More information

LADWP WATER INFRASTRUCTURE PLAN

LADWP WATER INFRASTRUCTURE PLAN LADWP 2017-18 WATER INFRASTRUCTURE PLAN Introduction All major components of the Water System infrastructure are evaluated as part of the ongoing Asset Management (AM) Program. The goal of AM is to systematically

More information

OTHER CEQA CONSIDERATIONS

OTHER CEQA CONSIDERATIONS Chapter 5 OTHER CEQA CONSIDERATIONS CEQA Guidelines Section 15128 requires that an EIR disclose the reasons why various possible environmental effects of a proposed project are found not to be significant

More information

CITY OF ALBANY Public Works Department ADDENDUM #1 ST , MAIN STREET REHABILITATION

CITY OF ALBANY Public Works Department ADDENDUM #1 ST , MAIN STREET REHABILITATION CITY OF ALBANY Public Works Department ADDENDUM #1 ST-13-04-2014, MAIN STREET REHABILITATION In order to clarify the intent of the Specifications and Drawings, the following provisions are provided and

More information

SECTION MAINTENANCE OF EXISTING CONDITIONS

SECTION MAINTENANCE OF EXISTING CONDITIONS SECTION 02 01 00 MAINTENANCE OF EXISTING CONDITIONS PART 1 GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged

More information

QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINISTRATOR JUNE 26, 2018

QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINISTRATOR JUNE 26, 2018 QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINISTRATOR JUNE 26, 2018 Aragona Drainage Improvements D A S H B O A R D Central Resort District Drainage

More information

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION City of Santa Monica Community Maintenance Department Public Landscape Division 2600 Ocean Park Blvd. Santa Moni ca, CA 90405 (310) 458-8974

More information

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6 UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN CONSTRUCTION, INC. PG. 6 TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT TRAUTWEIN CONSTRUCTION, INC. TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

BEVERLY HILLS AGENDA REPORT. Meeting Date: March 5, 2019 Item Number: C 2 To: From:

BEVERLY HILLS AGENDA REPORT. Meeting Date: March 5, 2019 Item Number: C 2 To: From: BEVERLY HILLS AGENDA REPORT Meeting Date: March 5, 2019 Item Number: C 2 To: From: Honorable Mayor & City Council Shana Epstein, Director of Public Works Josette Descalzo, Environmental Compliance and

More information