OUTLINE SPECIFICATION ALL-WEATHER PLAYING PITCHES

Size: px
Start display at page:

Download "OUTLINE SPECIFICATION ALL-WEATHER PLAYING PITCHES"

Transcription

1 OUTLINE SPECIFICATION FOR THE CONSTRUCTION OF ALL-WEATHER PLAYING PITCHES AT PORTARLINGTON SWIMMING POOL AND LEISURE CENTRE PEOPLES PARK, LINK ROAD, PORTARLINGTON, CO. LAOIS Date: July, 2011.

2 INTRODUCTION Portarlington Swimming Pool and Leisure Centre propose to provide new outdoor facilities by the addition of two all weather pitches, at the Peoples Park, Link Road, Portarlington, Co. Laois. This specification is a brief description of the proposed works and completed installation and their impact on the existing park and adjacent facilities. PROPOSED SITE The proposed site for the new all weather pitches consists of a strip of the existing Peoples Park approximately 85m long by 25m wide immediately adjacent to the existing Swimming Pool and Leisure Centre as outlined on the drawings. The north eastern boundary of the site is approximately 35m from the Barrow-Nore Special Area of Conservation (SAC). The complete site is currently zoned Open Space/Amenity in the current Local Area Plan. The proposed site currently accommodates a public sculpture (the Reclining Bather ), two no picnic tables, a playground swing, basketball ring, board & associated frame. Approximately 50% of the area consists of grass and some young trees. There are some mature trees immediately adjacent to the site which will not be affected by the proposed development apart from the pruning of a small number of possible overhanging branches from one tree. There is an existing grass embankment up to the adjacent Swimming Pool & Leisure Centre Building and it is not intended to affect this embankment. Otherwise the site is relatively flat with a gentle gradient from the high point adjacent to the Link Road back towards the river bank walkway. There are no overhead cables crossing or immediately adjacent to the proposed site. There are no known underground services (water, gas, electricity, telecoms, sewer or surface water) in the site. There is an External ESB Transformer at the top of the embankment which will not be affected by the development. The proposed development is served by approximately 120 car parking spaces in the immediately adjacent car parks which is considered adequate for the existing uses and the proposed all weather pitches. 1

3 DRAWINGS The following drawings accompany this outline specification: 1021-SL SL SL3 Existing Site Layout Proposed New Site Layout General Arrangement Layout 1021-SL4 Details Sheet SL SL SL7 Proposed Elevations Proposed Aerial View Floodlighting Illuminance PROPOSED WORKS Works area to be fully fenced to comply with Health and Safety requirements including the provision of all appropriate signage. Site to be made secure for duration of works. Carefully remove and re-locate existing Reclining Bather sculpture, playground equipment and picnic tables. Works to be carried out in conjunction with Laois County Council & Laois Arts Officer. Remove trees and dispose of away from site. Level the site as per levels indicated, and match up circumference levels with existing grass areas and gravel paths. Surface cross falls of 1:200 from north to south and west to east. Because of the existing levels the south western side of the site will require some excavation while the north eastern end will require some fill. All unused or spare excavation or fill materials will be removed and disposed of away from site. Install under pitch drainage as shown. Connect to new main drainage pipe. Porous Macadam footpath shall be constructed around the perimeter of the pitches as per detail shown on drawings. Fencing Polyester coated galvanised posts, including all net and Rebound Fencing fixtures, bedded in 600mm x 600m x 1000mm concrete foundations 2

4 Heavy duty pvc coated anti climb security fencing 3070mm high around each pitch. Panel width 2520mm. Vertical wires 6mm diam. Horizontal wires 8mm diam. Vertical Centres 50mm except for rebound panels which will have two additional 8mm diam horizontal wires per aperture. Rebound panels to be 1200mm high on complete perimeter and 2400mm high behind goal posts. Polyester coated galvanised posts, including all net and Rebound Fencing fixtures, bedded in 600mm x 600m x 1000mm concrete foundations Roof netting shall be fixed by way of 6mm stainless steel tensioned cables around perimeter and along diagonals of each pitch. 2 no. heavy duty pedestrian, one for each pitch along with 3 no. double service gates as indicated on the drawings. Pitch Construction The proposed pitch surface is Astroturf 202 with 60mm fibres, 25mm sand filling, 35mm rubber granule filling on a deep pile carpet, on an open textured macadam base. The pitch base shall be made up as 5m spaced 100mm diagonal land-drains, Terram geo-textile membrane, 250 hardcore stone, 50mm of Clause 804 graded stone and 60mm of porous macadam Floodlighting 6 No. 12m high poles are required as indicated. The lux level on the synthetic grass pitches shall be an average of 250 lux at a 0.7 min/avg uniformity to eliminate glare and give a good colour rendering. CCTV Each light mast shall be designed such that a CCTV camera can be readily mounted on each and connected back into the centres monitors. Ducting 2 No.100mm ducts are required around the perimeter of the pitches under new two meter wide footpaths. Duct chambers shall be provided as indicated. Planting & Landscaping 3

5 Complete all new planting and landscaping including the replacement of all trees removed and the provision of new screen planting behind the existing wall on the Link Road. ENVIRONMENTAL CONSIDERATIONS The site is currently zoned Open Space/Amenity in the Local Area Development Plan and the proposed use as All Weather Pitches does not contravene this zoning. The Peoples Park lies partly in the River Barrow floodplain and the drawings outline the floodlines for Flood Zone A and Flood Zone B. The development will not appreciably affect the existing floodplain as there will likely be more excavation than fill in the levelling process. Flood Zone A is the 1% flood zone i.e. 1% or greater chance of flooding each year. Flood Zone B is the 0.1% flood zone i.e. up to 0.1% chance of flooding each year. As can be seen from the drawings Flood Zone A just about encroaches on one end of Pitch No. 2 while Flood Zone B encroaches on approximately one half of Pitch No. 2. Occasional flooding which may occur is not a problem for this type of pitch and such Amenity & Outdoor Sports Developments are deemed to be water compatible developments. The site is adjacent to the Barrow-Nore Special Area of Conservation the nearest point on the north east boundary being approximately 35m from the SAC. It is not envisaged that either the completed development or the construction of same will have any negative impact on the SAC. All materials being used are non toxic and because of the build up of the pitch bases it is not possible for either the synthetic pitch fibres or rubber granule fill to penetrate through to the surface water outfall to the river. As there is a slight rise in level to the river bank from the area of the proposed development it is highly unlikely that there will be any run off of clay or dirt into the river during construction. However, as an additional precaution, all excavation, trenching and backfill works will be carried out outside the spawning season. Additionally any stockpiling of earth, stone, gravel etc will be confined to an area as far away from the SAC as possible on the south western end of the site towards the Link Road. The Contractors Compound is to be provided in the gravel area adjacent to the Link Road and all equipment and construction materials will be stored in this area. Re-fueling of excavation or construction vehicles will not be allowed on site and any minor repairs, servicing or lubrication procedures will be confined to the Contractors Compound. The proposed floodlighting has been designed to minimize glare and spillover of light to adjoining areas. While the pitches will have an average illuminance of 250 lux, the spillover of light to the river bank in the SAC is negligible at 1 lux. The spillover of light to the Link Road is 50 lux which is very acceptable in an urban street-lit scenario. The lighting shall be separately switched for each pitch so that in periods of reduced useage the actual light spillover will be considerably less. 4

6 There are no noise emitting components or equipment in the completed installation. Electrical supply will be from the mains supply in the adjacent Leisure Centre and diesel generating plant will not be utilized for power. During construction all works will be confined to normal working hours Monday to Saturday. 5

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

Proposed Development of an All-Weather Pitch at Coláiste Eoin/Íosagain PC/PKS/01/18

Proposed Development of an All-Weather Pitch at Coláiste Eoin/Íosagain PC/PKS/01/18 Parks & Landscape Services Section, Municipal Services Department Proposed Development of an All-Weather Pitch at Coláiste Eoin/Íosagain PC/PKS/01/18 April 2018 Prepared by: Eoin O Brien, Senior Executive

More information

This guide only applies for sewer assets up to and including 225mm diameter.

This guide only applies for sewer assets up to and including 225mm diameter. INTRODUCTION This guide only applies for sewer assets up to and including 225mm diameter. These guidelines (subject to change) provide an outline of the requirements which need to be considered when planning

More information

SUPPLEMENTAL DRAWINGS

SUPPLEMENTAL DRAWINGS CITY OF GREATER SUDBURY SUPPLEMENTAL DRAWINGS TO THE ONTARIO PROVINCIAL STANDARD DRAWINGS Rev: February 2012 CITY OF GREATER SUDBURY STANDARD DRAWINGS TABLE OF CONTENTS Greater Sudbury Standard Drawings

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 - ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads,

More information

PRELIMINARY ROADWORKS COST ESTIMATE

PRELIMINARY ROADWORKS COST ESTIMATE PRELIMINARY ROADWORKS COST ESTIMATE Project Title : Glounthaune Village Improvement Scheme Client : O Mahony Developments Ltd Date : February 208 From O' Mahony Development Ltd Entrance to Glounthaune

More information

7. A saucer of soil shall be formed so that water is directed down through the roots or root ball rather than around the root ball.

7. A saucer of soil shall be formed so that water is directed down through the roots or root ball rather than around the root ball. Adopted 12/5/00; revised 3/5/02 Marietta Tree Commission Rules and Regulations I. Tree Planting A. Planting Specifications These specifications are Adapted from recommendations of the OSU Extension Service.

More information

(DC2) SITE SPECIFIC DEVELOPMENT CONTROL PROVISION

(DC2) SITE SPECIFIC DEVELOPMENT CONTROL PROVISION (DC2) SITE SPECIFIC DEVELOPMENT CONTROL PROVISION 1. General Purpose To accommodate the development of a mid rise residential building that supports a broad mix of dwelling types and provides a commitment

More information

Section 7: Specifications

Section 7: Specifications Section 7: Specifications 29 31 Building Boundary of Clear Area See Note # 1 8' Shrubs 8' Concrete Pad Equipment 8' TRAVELED WAY M Meter Pedestal 8' Curb Protective Vehicle Posts (Bollards) If Required

More information

CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE:

CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE: CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST "THE FOLLOWING CHECKLIST IS ONLY A SUMMARY THAT IS PROVIDED FOR THE APPLICANT'S BENEFIT; HOWEVER, FULFILLING THE REQUIREMENTS OF THIS SUMMARY

More information

Part 11: Lighting. Contents. Tables. Part 11: Lighting. Christchurch City Council Infrastructure Design Standard 11-1

Part 11: Lighting. Contents. Tables. Part 11: Lighting. Christchurch City Council Infrastructure Design Standard 11-1 Part 11: Lighting Contents 11.1 Referenced Documents...11-2 11.2 Introduction...11-2 11.3 Quality Assurance Requirements and Records...11-2 11.3.1 The designer... 11-3 11.3.2 Design records... 11-3 11.3.3

More information

SECTION 200 CLEARANCES

SECTION 200 CLEARANCES SECTION 200 CLEARANCES 200.01 Texas Law & OSHA Regulations To ensure safety and the protection of the public, Chapter 752 of the Texas Health and Safety Code makes it unlawful for unauthorized persons

More information

Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit. Design and Construction Guidelines

Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit. Design and Construction Guidelines Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit Design and Construction Guidelines A Guide to Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity

More information

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES INCLUDING KERB & GUTTER (CHANNEL) C224 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C224 ISSUE: NO:1 October 2007 TABLE OF CONTENTS

More information

Regulation 18 August 2009 NO Operations and Maintenance LEVEE ENCROACHMENT STANDARDS AND PROCEDURES

Regulation 18 August 2009 NO Operations and Maintenance LEVEE ENCROACHMENT STANDARDS AND PROCEDURES CENWP-EC DEPARTMENT OF THE ARMY PDR 30-2-5 Portland District, Corps of Engineers (Draft) P.O. Box 2946 Portland, Oregon 97208 Regulation 8 August 2009 NO. 30-2-5 Operations and Maintenance LEVEE ENCROACHMENT

More information

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS Version 2014-11-11 Prepared by: Building Development Division Department of Development Services 5 County Complex Ct. Suite 120 Prince William, VA 22192

More information

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING Multi family housing is an increasingly popular form of infill development in Shaker Heights because of the city s built out

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

Section 12 Hydraulics.

Section 12 Hydraulics. Design Guidelines Section 12 Hydraulics. www.canterbury.ac.nz/learningresources Standards in the Design Guidelines Suite Design Standard Guidelines Index: 01 General 02 Architecture 03 Audio Visual 04

More information

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR GROUNDING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 609 NOVEMBER 2001 CONSTRUCTION SPECIFICATION FOR GROUNDING TABLE OF CONTENTS 609.01 SCOPE 609.02 REFERENCES 609.03 DEFINITIONS - Not Used 609.04 DESIGN

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SCHEDULE OF QUANTITIES CPUT BELLVILLE JOB NO: SECTION 1 : PRELIMINARY AND GENERAL ITEM PAYMENT DESCRIPTION UNIT QTY RATE AMOUNT

SCHEDULE OF QUANTITIES CPUT BELLVILLE JOB NO: SECTION 1 : PRELIMINARY AND GENERAL ITEM PAYMENT DESCRIPTION UNIT QTY RATE AMOUNT SECTION 1 : PRELIMINARY AND GENERAL ITEM PAYMENT DESCRIPTION UNIT QTY RATE A SECTION 1 : PRELIMINARY AND GENERAL A.1 8.3 FIXED-CHARGE ITEMS A.1.1 8.3.1 Contractual Requirements A.1.2 8.3.2.1 Facilities

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables MUNICIPAL AND COMMON DIVISION 2000 ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction

More information

WASTEWATER REVIEW CHECKLIST. Project Number: Reviewed By: Telephone:

WASTEWATER REVIEW CHECKLIST. Project Number: Reviewed By: Telephone: The City of East Point DEPARTMENT OF WATER AND SEWER 1526 East Forrest Ave. Suite 400 East Point, Georgia 30344 FAX (404) 270-7215 www.eastpointcity.org WASTEWATER REVIEW CHECKLIST Project Name: Tax ID

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES CITY OF SANTA MONICA Department of Public Works Civil Engineering Division 1685 Main, Room 116 Santa Monica, CA 90401 Tel: (310) 458-2240 or (310) 458-8737 EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL

More information

#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING

#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING #4) UN-60-16 NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: September 14, 2016 Item: UN-60-16 Prepared by: Robert Eastman GENERAL INFORMATION:

More information

AS/NZS 3000: 2018 Changes to Wiring Rules Standard

AS/NZS 3000: 2018 Changes to Wiring Rules Standard BUILDING SERVICES Ref: BCA 19-01 Current at January 2019 AS/NZS 3000: 2018 Changes to Wiring Rules Standard The new edition of AS/NZS 3000 Wiring Rules Standard (Electrical Installations) was published

More information

11.1 INTRODUCTION Objectives Key References Interpretation GENERAL CONDITIONS DESIGN...

11.1 INTRODUCTION Objectives Key References Interpretation GENERAL CONDITIONS DESIGN... CONTENTS SECTION 11 TELECOMMUNICATIONS UTILITIES 11.1 INTRODUCTION... 1 11.1.1 Objectives... 1 11.1.2 Key References... 1 11.1.3 Interpretation... 2 11.2 GENERAL CONDITIONS... 2 11.3 DESIGN... 3 11.4 DESIGN

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

Section X - Miscellaneous

Section X - Miscellaneous Section X - Miscellaneous A. Introduction This section provides design criteria, specific requests/recommendations and preferences related to specifying and constructing systems and materials used in HRSD

More information

Section 32 - Miscellaneous

Section 32 - Miscellaneous Section 32 - Miscellaneous A. Introduction This section provides design criteria, specific requests/recommendations and preferences related to specifying and constructing systems and materials used in

More information

Section 1 OBC FADS /13 Access to Parking Areas

Section 1 OBC FADS /13 Access to Parking Areas Section 1 OBC 3.8.2.2 4.3.12/13 Access to Parking Areas A barrier-free path of travel is provided from: a) the entrance to the exterior parking area b) at least one parking level where a passenger elevator

More information

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

Gas meter clearances and service installation requirements

Gas meter clearances and service installation requirements FEBRUARY 2018 Gas meter clearances and service installation requirements CALL PSE S CUSTOMER CONSTRUCTION SERVICES AT 1-888-321-7779 OR VISIT PSE.COM/CUSTOMERCONSTRUCTION FOR MORE INFORMATION. Builder/owner/developer

More information

City of Logan Sanitary Sewer Design Standards

City of Logan Sanitary Sewer Design Standards City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads, and

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01

More information

FENCE PERMIT APPLICATION

FENCE PERMIT APPLICATION Department of Building, Zoning & Housing 26789 Highland Road Richmond Heights, Ohio 44143-1429 216-383-6312 Fax: 216-383-6319 richmondheightsohio.org FENCE PERMIT APPLICATION LOCATION OF JOB LOT # SUBDIVISION

More information

Plastic Permeable Paving

Plastic Permeable Paving 03 Landscaping Products solutions Plastic Permeable Paving Product Range Creating Green Infrastructure Plastic Permeable Paving Product Range Introduction Page 3 FlowBlock 4-5 SlimBlock 6-7 GS Pro 8-9

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Below are the existing regulations for solar uses included in the Charlotte County Zoning Ordinance. All proposed amendments are marked in red.

Below are the existing regulations for solar uses included in the Charlotte County Zoning Ordinance. All proposed amendments are marked in red. Below are the existing regulations for solar uses included in the Charlotte County Zoning Ordinance. All proposed amendments are marked in red. Index Sec. 10-23. Solar Energy Systems Article 9. Use Matrix

More information

CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT

CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 623 JANUARY 1990 CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT 623.01 SCOPE 623.02 REFERENCES 623.05 MATERIALS TABLE OF CONTENTS 623.05.01

More information

RESIDENTIAL BUILDING PLAN APPROVAL PROCEDURE

RESIDENTIAL BUILDING PLAN APPROVAL PROCEDURE RESIDENTIAL BUILDING PLAN APPROVAL PROCEDURE 1. Prior to the commencement on any lot, of any building work whatsoever, including outbuildings, fencing, external renovations, air-conditioners or any other

More information

OVERHEAD SERVICES - SECONDARY

OVERHEAD SERVICES - SECONDARY OVERHEAD SERVICES - SECONDARY Contents - Overhead Services... O-1 General Requirements for Overhead Service... O-2 Names of Parts for Overhead Service... O-3 Service Attachment on an Unguyed Service Mast...

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics HEKAPLAST PE-HD twin wall cable ducts and cable protection pipes for underground installation HEGLER HEKAPLAST III/ HEKAPLAST: Twin wall cable ducts or cable protection pipes to DIN 696, manufactured from

More information

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control

More information

APPENDIX A MEASUREMENT AND PAYMENT

APPENDIX A MEASUREMENT AND PAYMENT P-150 DEMOLITION 4.01 Removal of pavement shall be measured per square yard based on the area shown on the plans. Any pavement removed outside the designed limits of removal because the pavement was damaged

More information

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS TEXAS STANDARD CONSTRUCTION NOTES DRWN. BY: DSGN. BY: KJW 1 of 2 *Place geotextile fabric as a permeable seperator to prevent mixing of coarse aggregate and underlying soil. (as needed). 1. GEOTEXTILE

More information

BID SPECIFICATION: ADDENDUM A

BID SPECIFICATION: ADDENDUM A BID SPECIFICATION: ADDENDUM A SUPPLY, DELIVERY AND INSTALLATION OF CLEAR VIEW TYPE FENCE AT THE DISTRICT SIX CAMPUS. A MINIMUM CIDB RATING OF 5SQ (4SQ PE) OR HIGHER IS REQUIRED CPUT17/18 TABLE OF CONTENTS

More information

Klickitat County. On-Site Sewage System. Construction Manual

Klickitat County. On-Site Sewage System. Construction Manual Homeowner OSS Design and Construction Guide Klickitat County On-Site Sewage System Construction Manual Minimum standards and recommendations expected for the construction of on-site wastewater treatment

More information

Installation Information 2018

Installation Information 2018 Installation Information 2018 DENDRO-SCOTT Root Barrier... why use anything else? DENDRO-SCOTT Root Barrier, recognised by the Environment Agency, is known for its quality and reliability. It is flexible

More information

UniGril. for Architectural Finesse. Experience the Difference...

UniGril. for Architectural Finesse. Experience the Difference... UniGril for Architectural Finesse Experience the Difference... BONAFIDE ACCREDITATION BONAFIDE ACCREDITATION BONAFIDE ACCREDITATION BONAFIDE ACCREDITATION BONAFIDE GUARANTEE BONAFIDE GUARANTEE BONAFIDE

More information

5.0 Sports fences. Double wire panel systems Dulok Rebound 5.1 Dulok 5.2. Other systems Sports Rail 5.3 Ball Stop netting 5.4. Sports pitch systems

5.0 Sports fences. Double wire panel systems Dulok Rebound 5.1 Dulok 5.2. Other systems Sports Rail 5.3 Ball Stop netting 5.4. Sports pitch systems 449.12 CLD dividers 03_Layout 1 10/06/2010 09:27 Page 7 5.0 Double wire panel systems Dulok Rebound 5.1 Dulok 5.2 Other systems Sports Rail 5.3 Ball Stop netting 5.4 Versatile sports pitch 5.5 systems

More information

1420 Miner Street Des Plaines, IL P: desplaines.org COMMERCIAL STRUCTURES (INCLUDING ALTERATIONS AND ADDITIONS)

1420 Miner Street Des Plaines, IL P: desplaines.org COMMERCIAL STRUCTURES (INCLUDING ALTERATIONS AND ADDITIONS) 1420 Miner Street Des Plaines, IL 60016 P: 847.391.5380 desplaines.org COMMERCIAL STRUCTURES (INCLUDING ALTERATIONS AND ADDITIONS) Five sets of stamped plans and specifications (six sets if food establishment),

More information

EROSION CONTROL AND GRADING PERMIT APPLICATION

EROSION CONTROL AND GRADING PERMIT APPLICATION EROSION CONTROL AND GRADING PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 1735 MONTGOMERY STREET OROVILLE, CA 95965 530-538-2420 FAX (530) 5382426 www.cityoforoville.org APPLICATION DATE PERMIT FEE

More information

Residential Miscellaneous Permits

Residential Miscellaneous Permits Residential Miscellaneous Permits Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

Table Related Arlington County Standards, Specification and Policies

Table Related Arlington County Standards, Specification and Policies 2.1 GENERAL 2.1.1 DESCRIPTION SITE WORK V02000 2.1 GENERAL 2.1.1 Description This standard identifies minimum requirements that shall be met for all site work in the design and construction of elements

More information

REGULATIONS FOR RESIDENTIAL OPEN WOOD DECKS

REGULATIONS FOR RESIDENTIAL OPEN WOOD DECKS REGULATIONS FOR RESIDENTIAL OPEN WOOD DECKS TOTAL PERMIT FEE DUE WILL BE $375.00 ($290.00 IS REFUNDABLE AFTER POST HOLE AN FINAL INSPECTION) Furnish (2) copies of a site/plot plan drawn to scale for wood

More information

Functional Requirements for New Archery Facility

Functional Requirements for New Archery Facility Functional Requirements for New Archery Facility Introduction The archery facility, which is proposed to replace and enhance that currently located at Jubilee Park, comprises three main components: an

More information

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION 02001 Bus Traffic. Separation between bus traffic, regular vehicular flow, service traffic and pedestrian traffic. Bus traffic must have adequate

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

PLANNING DEPARTMENT 701 OCEAN STREET, 4 TH FLOOR, SANTA CRUZ, CA (831) FAX: (831)

PLANNING DEPARTMENT 701 OCEAN STREET, 4 TH FLOOR, SANTA CRUZ, CA (831) FAX: (831) COUNTY OF SANTA CRUZ PLANNING DEPARTMENT 701 OCEAN STREET, 4 TH FLOOR, SANTA CRUZ, CA 95060 (831) 454-2580 FAX: (831) 454-2131 Rooftop Rainwater Harvesting Permit Application & Inspection Checklist A building

More information

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION CHAPTER 23.105 GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION Sections 23.105.101 General... 1 23.105.102 Definitions... 1 23.105.103 Permits required... 3 23.105.104 Hazards.... 4 23.105.105 Permit

More information

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/ CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA 34695 PHONE: 727/724-1555 FAX: 727/724-1566 RIGHT-OF-WAY / EASEMENT USE PERMIT DATE SUBMITTED: EXPIRATION DATE: Submit the following to the

More information

SECTION EARTHWORK

SECTION EARTHWORK SECTION 310000 PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and perform all excavation, backfill, fill and grading required to complete the work

More information

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE 378-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION 378 - POND I. SCOPE The work shall consist of constructing an earthfill embankment and appurtenances to the lines, grades,

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

Instruction Guide APPLICATION OF CIM TO EARTHEN PONDS AND RESERVOIRS (USING CIM SCRIM)

Instruction Guide APPLICATION OF CIM TO EARTHEN PONDS AND RESERVOIRS (USING CIM SCRIM) 23 Elm St., Peterborough, NH 03458 Tel: (800) 543-3458 (603) 924-9481 Fax: (603) 924-9482 Web site: Instruction Guide APPLICATION OF CIM TO EARTHEN PONDS AND RESERVOIRS (USING CIM SCRIM) 1.0 DESCRIPTION

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

A. This Section includes subdrainage systems for foundations and underslab areas. A. Product Data: For each type of drainage panel indicated.

A. This Section includes subdrainage systems for foundations and underslab areas. A. Product Data: For each type of drainage panel indicated. ZGF Partnership Page 1 of 7 SECTION 33 46 00 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes subdrainage systems for foundations and underslab areas. 1.2 SUBMITTALS A. Product Data: For each type

More information

ZONING CLEARANCE PLAN REVIEW CHECKLIST. Based on the Revised Town of Carefree Zoning Ordinance

ZONING CLEARANCE PLAN REVIEW CHECKLIST. Based on the Revised Town of Carefree Zoning Ordinance ZONING CLEARANCE PLAN REVIEW CHECKLIST Based on the Revised Town of Carefree Zoning Ordinance Date: Applicant: Permit Number: Reviewer: Address: Lot & Subdivision: Zoning District: New SRF: Addn/Remodel:

More information

Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006

Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006 Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006 14,996 9,051 97,053 114,553 Union Street / Trematon Avenue

More information

CHAPTER 15 - "M2" HEAVY INDUSTRIAL DISTRICT

CHAPTER 15 - M2 HEAVY INDUSTRIAL DISTRICT CHAPTER 15 - "M2" HEAVY INDUSTRIAL DISTRICT Sec. 15-1. Regulations: The regulations set forth in this chapter or set forth elsewhere in this zoning ordinance when referred to in this chapter are the regulations

More information

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,

More information

Permeability across the entire site within the General Residential Zone is a minimum of 30%.

Permeability across the entire site within the General Residential Zone is a minimum of 30%. Partly Operative District Plan Rule Assessment The following assessment is to demonstrate compliance or non-compliance with the rules of the Partly Operative District Plan. The proposed duplex dwellings,

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

EDS TIMBER FENCING FOR SECONDARY SUBSTATIONS

EDS TIMBER FENCING FOR SECONDARY SUBSTATIONS Document Number: EDS 07-3103 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 07-3103 TIMBER FENCING FOR SECONDARY SUBSTATIONS EPN, LPN, SPN This standard details the requirements for timber fences

More information

The Standards referred to shall be the most recent edition.

The Standards referred to shall be the most recent edition. Page 1 of 7 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described hereunder shall consist of the excavation of trenches and tunnels; the supply and installation of pipe and/or encasement pipe; the

More information

ARTICLE 903. PD 903. PD 903 was established by Ordinance No , passed by the Dallas City Council on February 12, (Ord.

ARTICLE 903. PD 903. PD 903 was established by Ordinance No , passed by the Dallas City Council on February 12, (Ord. ARTICLE 903. PD 903. SEC. 51P-903.101. LEGISLATIVE HISTORY. PD 903 was established by Ordinance No. 29270, passed by the Dallas City Council on February 12, 2014. (Ord. 29270) SEC. 51P-903.102. PROPERTY

More information

Management Plan: Hazardous Materials Removal & Demolition

Management Plan: Hazardous Materials Removal & Demolition Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council

More information

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL 623.01 SUMMARY: GENERAL Section Includes: Landscape irrigation system as shown on the drawings for complete coverage to landscape areas. Furnish design for layout, pipe sizing, valving and head types and

More information

Cambridgeshire County Council County Planning, Minerals and Waste

Cambridgeshire County Council County Planning, Minerals and Waste Cambridgeshire County Council County Planning, Minerals and Waste Guidance on Waste Audit and Management Strategies for submission in support of a planning application or to fulfil a requirement of a planning

More information

Polysewer Gravity Sewer System SPECIFICATION

Polysewer Gravity Sewer System SPECIFICATION Polysewer Gravity Sewer System SPECIFICATION July 2014 SCOPE OF WORKS To meet the specific performance criteria detailed within this specification and accompanying drawings. The completed drainage systems

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

Installation Information 2016

Installation Information 2016 Installation Information 2016 DENDRO-SCOTT Root Barrier... why use anything else? DENDRO-SCOTT Root Barrier, recognised by the Environment Agency, is known for its quality and reliability. It is flexible

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information