1 1 Commissioning at NYP Joseph Lorino, PE, LEED Corporate Director April 1, 2014
2 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program NYP Commissioning Process Roles & Responsibilities
3 Definitions 3 The Commissioning Process. A quality focused process for enhancing the delivery of a project. The process focuses upon verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, tested, operated and maintained to meet the Owner s Project Requirements (OPR). -ASHRAE Guideline
4 The Commissioning Process 4 ASHRAE Guideline : The Commissioning Process (To be used as the foundation of ASHRAE Guideline 1 and the NIBS Total Building Commissioning Process technical guidelines) ASHRAE Guideline 1-200X HVAC&R Technical Requirements for The Commissioning Process NIBS Guidelines 2-200X through X Technical commissioning guidelines dealing with lighting, fire, interiors, envelopes, plumbing, etc. Guideline 1 ASHRAE, HVAC&R System Guideline 2 ASCE, Structural Systems Guideline 3 BETEC, Exterior Envelope Systems Guideline 4 NRCA, Roofing Systems Guideline 5 AWCI, Interior Systems Guideline 6 NEII, Elevator Systems Guideline 7 ASPE, Plumbing Systems Guideline 8 IES, Lighting Systems Guideline 9 IEEE, Electrical Systems Guideline 10 NFPA, Fire Protection Systems Guideline 11 TIA, Telecommunications Systems
5 Why Commission? 5 Evolving complexity of building control systems Modern ventilation, lighting and comfort systems are energy intensive Construction deficiencies at outset in most buildings Need for independent & objective peer review Operations & Maintenance (O&M) staff unprepared to operate complicated buildings efficiently Frequent user complaints Long term operating costs utility costs & maintenance higher than expected
6 Benefits of Commissioning 6 Improved system & equipment function Increased occupant & owner satisfaction Lower utility bills through energy savings Significant extension of equipment/systems lifecycle Improved building occupant productivity Benefits 2000 NYSERDA & 2001 PECI Surveys: 70% fewer post acceptance deficiencies 65% fewer occupancy complaints 50% decrease of litigation 65% improvement of comfort control 60% owners get what they paid for Source: NEMI National Energy Management Institute
7 7 The NYP Program Why? Design review sessions Utility capacities Unplanned shutdowns Construction deficiencies High cost of repair Inaccessibility Adjacencies to patients DOH Pre-Occupancy Inspections Mandates after construction Impact to patient care
8 New York Presbyterian Hospital Program Overview 8 Columbia University Medical Center Weill Cornell Medical Center Morgan Stanley Children s Hospital Allen Hospital Westchester Division Lower Manhattan Hospital
9 9 Bridging the Gap
10 10 The NYP Program The Process RFQ Interviews Selection
11 Selected Commissioning Agents 11 Columbia Presbyterian Site Strategic Building Solutions (SBS) East of Fort Washington Ave. Horizon Engineering Associates West of Fort Washington Ave. Weill Cornell, Westchester, Lower Manhattan Sites Dometech Assigned by Project Manager Eneractive Solutions Assigned by Project Manager Allen Hospital Horizon Engineering Associates
12 Project Table of Organization 12 NYP PM Cx Agent Facilities Operations Design Group A/E
13 National Building Commissioning 13 Association Best Practices Article in Commission Publication
14 Typical Commissioned Systems 14 HVAC Fire smoke dampers Electrical Lighting Plumbing Pneumatic tube Medical gas Nurse call Fire alarm Security Fire protection Vertical transportation Fire Stopping
15 15 Non-traditional Commissioning Beyond ASHRAE Guideline 0 Assist in DOH Pre-occupancy inspections Barcode assets Develop equipment PM program Assist A/E pre-existing conditions survey Inspect rated wall penetrations & firestopping Phasing coordination Decanting of space
16 16 The NYP Program The Projects Ongoing Project Reviews Renovations Infrastructure Major Projects New Building
17 The Commissioning Process FEASIBILITY DESIGN CONSTRUCTION POST-CONSTRUCTION 17 Identify Cx Team Define OPR Develop Preliminary Cx Plan Establish Initial Budget for Cx Incorporate Cx into A/E Scope of Services Retain CxA Review OPR and BoD Concept, DD, and CD Design Reviews Update Cx Plan Develop Cx Specifications Define Training Review Submittals Construction Checklists Perform Field Inspections Oversee and Document FPT Lead Cx Team Meetings Conduct Owner Training Turnover Cx Record Perform Deferred & Seasonal Testing End of Warranty Review Complete Final Cx Report Final Satisfaction Review with Customer Agency ReCx Every 3-5 Years Cx Integrated into Planning Documents? Contract Documents Aligned with OPR? System Performance Documented & Accepted? System Performance Sustained?
18 Cx Agent Roles & Responsibilities 18 Enlisted in the project at earliest possible stage, Feasibility or Schematic Design Establish the Owners Project Requirements (OPR) Apply Best Practice standards during design review process Ensure the MEP installation and operation complies with the design intent and manufacturer s specifications Ensure that the MEP installation will be maintainable by Facilities Operations Ensure O&M Materials and Warranty are available, scanned, indexed and appropriate for the installation Coordinate in Facilities Operations Staff Training Coordinate work with the Campus Engineer and Facilities Operations Develop Preventive Maintenance Program for installed equipment, in TMS format
19 19 Feasibility Phase Develop Owner s Project Requirements (OPR) Project Overview Functional Uses Occupant Requirements Performance Criteria Integrate stakeholders in this phase (clinical staff, O&M staff) Identify scope for Cx process Develop draft Cx Plan The Basis of Design is the Design Team s technical interpretation of the OPR
20 Design Phase 20 Verify the Basis of Design (A/E) meets the Owner s Project Requirements Identify scope for Cx process Basis of design Update the Cx Plan Begin developing the Cx Log Develop Cx process for inclusion in the CDs Multiple Focused Design Reviews Develop project specific Cx Specifications Value Engineering assistance Define O&M Training requirements
21 Construction Phase 21 Update OPR & Cx Plan Verify submittals & shop drawings meet OPR Develop test procedures Equipment / system Installation is per contract documents Pre-functional Equipment start-ups System testing (duct leakage, flushing/cleaning, pressure, electrical) Functional testing BMS-Controls / graphics to be completed prior to functional testing Individual components Systems and interfaces Document all issues (Issues or Deficiency Log) Re-inspection and re-testing as required Verify training activities
22 Acceptance & Occupancy Phase 22 Complete seasonal testing Deficiency Closeout Performance Testing Design Criteria TAB Verification Integrated System Performance Testing Facilitation of End User Training Approved Syllabus prior to any sessions Engage factory trained representatives As-Built drawings to be submitted prior to training O&M manuals to be available Final Report
23 Occupancy Phase 23 Development and Delivery of a Functional Integrated Systems Manual Seasonal Testing Occupant Interviews Warranty Review Update All Cx Documentation
24 Cx Documents (Example) 24 Cx Issues Log Building Floor Room Component Trade Contractor Reference Urgency Impact Description Date Found Date Corrected Cx Inspector
25 25 Deficiency No.1: Accessibility
26 26 Construction Team Roles & Responsibilities Include Commissioning Process requirements in contracts Provide adequate accessibility to properly operate & maintain equipment as per OEM requirements Remedy deficiencies identified by the CxA Obtain cooperation of all subcontractors Attend Commissioning meetings Include Commissioning milestones in project schedule Implement training program as detailed in contract documents Provide submittals to Owner, Design Team, CxA
27 27 Construction Team Roles & Responsibilities Notify the CxA when systems & assemblies are ready for testing Demonstrate the operation & performance of the equipment and systems to the CxA Continuously maintain the as-built drawings
28 2013 Results Over 100 projects successfully commissioned 28 Steam traps and condensate piping improperly installed. Heating coils could freeze and burst, resulting in AHU partial or total shutdown Return fans trip on overcurrent during partial restart. The AHU unnecessarily shuts off, resulting in loss of space pressurization and compromising patient safety. Thermostats wired/mapped to the wrong rooms. Patients would not be able to control the temperature in their rooms compromising patient comfort. Fire-smoke dampers not wired to the building automation system. Remote status of dampers in ceilings above patient rooms would not be available requiring manual inspection and temporary shutdown of patient rooms.
29 2013 Results 29 Isolation Room was found to have insufficient pressurization Installation of door sweep improved pressurization of the Isolation Room; pressurization improved from in w.c. to in w.c. Review of the HVAC Balancing Report key for DOH inspection identified multiple errors. Unbalanced VAV boxes cannot maintain room temperature setpoints and lead to patient discomfort. Selected Balancing Contractor was found to be uncertified for Testing and Balancing (TAB) per NYPH Engineering Standards. Thermostat for a VAV serving Patient Rooms was found to be incorrectly installed in the Suite corridor Relocation of the patient room VAV s thermostat now accurately reflects zone conditions and improves patient comfort, as well as Facilities Operations troubleshooting capabilities.
30 2013 Results 30 Cooling condensate coils were not piped. Water would drain onto the original roof in the interstitial space under the new MER. The original design proposed a single-fan air handling unit. The system would have to be shut down entirely to change the main filters, resulting in significant ILSMs for planned maintenance. Sections of ductwork repeatedly failed pressure tests. There would have been significant duct leakage resulting in energy losses. Systems reported as complete were not fully operational. Spaces would have to be taken off-line after patient occupancy for repairs. VAV box control points on the Siemens BMS identified incorrectly tagged/addressed VAV boxes. Improperly addressed boxes diminish Facility Operation s ability to respond to patient and staff temperature requirements, and maintain incorrect space temperature setpoints for patient rooms.
31 31 Thank You Joseph Lorino, PE, LEED AP
Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015
1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program
More informationDESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS
SECTION 01 91 13 GENERAL COMMISSIONING REQUIREMENTS GENERAL The University of South Alabama is officially and formally committed to the concept of Commissioning all new buildings and major renovations.
More informationNEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014
NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings March 5, 2014 0 Moderator Jim Huber, NEBB President-Elect and President of Complete Commissioning Jim Huber
More informationBuilding Commissioning
Building Commissioning Roles, Responsibilities, and Benefits 2010 ASHRAE Annual Meeting CxA WORKSHOP Saturday, June 26, 2010 Jim Magee, CxA, LEED-AP Facility Commissioning Group Overview Cx Advocacy, Economics,
More informationDIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING
DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York
More informationCommissioning: What Architects Need to Know
Commissioning: What Architects Need to Know Rino Zan P.Eng., Morrison Hershfield Ltd. rzan@morrisonhershfield.com Ontario Association of Architects May 12 & 13, 2016 Commissioning: What Architects need
More informationB. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.
SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction November 26, 2014 Re: Request for Qualifications - Commissioning Services Bowen Science Building Modernize Building Systems University of Iowa The
More informationCommissioning Guide. Transportation and Works Building Design and Construction Division
Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...
More informationPreparing a Cx Plan. Technical vs. Process Commissioning TECHNICAL FEATURE
ASHRAE www.ashrae.org. Used with permission from ASHRAE Journal, December 2013 at www.atkinsglobal.com. This article may not be copied nor distributed in either paper or digital form without ASHRAE s permission.
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa
More informationBanyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL
SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationA. The purpose of this section is to specify Division 23 responsibilities in the commissioning process.
SECTION 23 99 50 - (ADD#4) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationHigher Value Commissioning
Higher Value Commissioning Presented by: Erik Jeannette, PE May 2011 Commissioning What is it? Commissioning (Cx) is a comprehensive and systematic process to verify and document the systems of a facility
More informationCommissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan
Commissioning National Training for Commissioning, 2006 Presented By Paul Sra and Mike Cavan 1 Scope of Presentation Commissioning overview Commissioning requirements for LEED Standard Roles and responsibilities
More informationCxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP
CxA Gap Session April 25, 2017 2:00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP AIA Provider Number 50111116 Course Description This session and short quiz,
More informationCommissioning: The Most Important Component of LEED. Rick Miller, PE, LEED AP. RNM Engineering, Inc. San Luis Obispo, CA
Commissioning: The Most Important Component of LEED by Rick Miller, PE, LEED AP RNM Engineering, Inc. San Luis Obispo, CA LEED and Commissioning EA Prerequisite Fundamental Commissioning of Building Energy
More informationCommissioning & Retro-Commissioning Meet Energy Code
Commissioning & Retro-Commissioning Meet Energy Code Agenda Introductions What is Commissioning Value of Commissioning Code Required Cx Process Customize your Cx Process What documentation should be expected
More informationGuideline HVAC&R Technical Requirements for The Commissioning Process
Guideline 1-2007 HVAC&R Technical Requirements for The Commissioning Process Charles E Dorgan, PE, PhD University of Wisconsin - Madison Synopsis The commissioning process for delivering quality new construction
More informationAbsolute Energy Raters Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither
More informationROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION
INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document
More informationMODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS
MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA 02210 (T) 617-423-7423 (F) 617-423-7401 mwalsh@vanderweil.com Module
More informationMSBA OWNERS PROJECT MANAGER ROUNDTABLE
MSBA OWNERS PROJECT MANAGER ROUNDTABLE September 12, 2018 Winchester High School Winchester, MA AGENDA 9:00 A.M. Welcome and Introduction 9:05 A.M. Presentation Commissioning Experiences on MSBA Projects
More informationFact Sheet. Commissioning WHAT IS THE PURPOSE OF THIS REQUIREMENT? WHAT VALUE DOES IT PROVIDE TO THE OWNER? HOW DOES IT SAVE ENERGY?
Commissioning Fact Sheet Funding for this publication is provided by the Northwest Energy Efficiency Alliance. OCTOBER 2017 VOLUME 1, ISSUE 2 WHAT IS THE PURPOSE OF THIS REQUIREMENT? There is a saying
More informationPROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems
More informationB. OPR and BoD documentation may be included by reference for information only.
SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction February 26, 2015 Re: Request for Proposals- Commissioning Services College of Public Health Building - Fit Out Fifth Floor University of Iowa The
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/05/2018
SECTION 01 9113 - GENERAL COMMISSIONING REQUIREMENTS GENERAL 1.1 SUMMARY The Owner has retained an independent Commissioning Authority (CxA) to coordinate commissioning activities for this project. The
More informationCommissioning Guidelines for the Arkansas Energy Performance Contracting Program
Commissioning Guidelines for the Arkansas Energy Performance Contracting Program Version 1.1 March 2014 Arkansas Economic Development Commission Energy Office 900 West Capitol Avenue Little Rock, Arkansas
More informationCODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017
CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017 OVERVIEW The recent adoption by the Centers for Medicaid and Medicare Services
More informationTHE COTTAGE at THORNAPPLE Hastings, Michigan
THE COTTAGE at THORNAPPLE ADDENDUM NO. 2 March 07, 2012 The Cottage at Thornapple 2580 Nashville Road Hastings, MI 49058 Owner: Barry County / Thornapple Manor 2700 Nashville Road Hastings, MI 49058 Architect:
More informationDESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE
DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes
More informationIntroduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D.
New and xisting Facilities D. ric Gregory, CCP Commissioning Manager Sustainable Performance Program Manager mory University eric.gregory@emory.edu (404) 727-1388 Introduction Cx Manager at mory University
More informationCapital Projects Group Mechanical Work Commissioning Specification
Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:
More informationDUKE UNIVERSITY CONSTRUCTION STANDARDS
1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply
More informationMEP Design Standards & Equip Cuts NYP BEST PRACTICES. Presentation for GC/CM Retreat 2014
1 MEP Design Standards & Equip Cuts NYP BEST PRACTICES Presentation for GC/CM Retreat 2014 We Put Patients First Agenda 2 Disclaimer Consultant Engineer & Commissioning Agent May 2012 Edition NYP Revised
More information2. Representatives of the facility user and operation and maintenance personnel.
PART I 1 GENERAL COMMISSIONING REQUIREMENTS 1.1 Description of Work a) The purpose of the commissioning process is to provide the owner/operator with assurance that the systems have been installed according
More informationMission Critical Commissioning for Healthcare Facilities
Mission Critical Commissioning for Healthcare Facilities Steven R. Rusty Ross SSRCx, LLC Synopsis Healthcare Facilities serve a critical and unique mission. Few facilities delivered by the construction
More informationPay for Performance - NC Technical Topic
Commissioning Resources and Clarifications Executive Summary Pay for Performance - NC Technical Topic This Technical Topic provides resources and clarifications for commissioning requirements of the Pay
More informationCOMMISSIONING for LEED New and Existing Buildings
Better Buildings By Design Conference Burlington, Vermont February 11-12. COMMISSIONING for LEED New and Existing Buildings Ron Wilkinson, P.E., LEED AP rwilkinson@akf-eng.com AKF Group, LLC What is Commissioning?
More informationA. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.
SECTION 23 0800 COMMISSIONING HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED 1.2 RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary
More informationCommissioning & Retro-Commissioning Helping You Get the Most of Your Facilities
Commissioning & Retro-Commissioning Helping You Get the Most of Your Facilities John Rimer, CFM Introduction John Rimer, CFM 16+ Years Facility Management Numerous Industries & Various Roles Owner, FM360
More informationOpening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction
Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Matthew Tunnard, PE, CCP, LEED AP, Senior Engineer Horizon Engineering Associates, LLP AIA Quality Assurance
More informationH59-N944-PD ATTACHMENT C: SECTION GENERAL COMMISSIONING REQUIREMENTS
ATTACHMENT C: SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SCOPE A. This section provides for commissioning of the project equipment and systems as specified herein. The commissioning
More informationMinnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation
Minnesota State Colleges and Universities South Central College Request for Proposals for Commissioning Agent STEM and Healthcare Renovation Date: 12/18/2017 ADDENDUM #1 1. The Sign-In sheet for the voluntary
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction February 17, 2015 Re: Request for Proposals- Commissioning Services Madison Street Residence Hall Construct Facility University of Iowa The University
More informationREQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa #
REQUEST FOR PROPOSAL Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # Addendum #1 Issued Wednesday, February 10, 2016 Changes: Item #01: Item #02: Section
More informationIntroduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1
Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:
More informationProcedure Yes; No; greater than
Procedure 1. Project manager (PM) notifies facilities information coordinator of forecasted substantial completion date one month prior to reaching substantial completion. 2. PM completes the project information
More informationLori A. Brown, LEED AP BD+C, LEED AP ND, LEED AP O+M -- LEED Green Associate Exam -- Power Jam Study! -- lorisweb.com 1
Lori A. Brown, LEED AP BD+C, LEED AP ND, LEED AP O+M -- LEED Green Associate Exam -- Power Jam Study! -- lorisweb.com 1 Lori A. Brown, LEED AP BD+C, LEED AP ND, LEED AP O+M -- LEED Green Associate Exam
More informationOwner/Operator Involvement in Cx Cx to Facilitate Owner Training & Turnover. Kent Barber, PE Managing Principal KBA
Owner/Operator Involvement in Cx Cx to Facilitate Owner Training & Turnover Kent Barber, PE Managing Principal KBA AIA Quality Assurance Learning Objectives 1. Understand how turnover is critical to long
More informationFundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619
AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,
More informationE mail:
April 12, 2017 Mr. Michael Otavka William S. Hart Union High School District 21380 Centre Pointe Parkway Santa Clarita, CA 91350 Re: Castaic High School HVAC Systems and Controls Commissioning (Cx) Dear
More informationExecutive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX:
Executive Summary Sample Company BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA 17070 PHONE: 717-697-6300 FAX: 717-697-1699 Executive Summary Sample Company has constructed a 80,000 sf. addition
More informationRequest for Proposal. for. Building Commissioning Services
Page 1 of 11 Request for Proposal for Building Commissioning Services State College Area School District High School Project December 15, 2014 Page 2 of 11 Request for Proposal for Building Commissioning
More informationASHRAE/USGBC/IES Standard What Does It Mean for Commissioning Providers?
ASHRAE/USGBC/IES Standard 189.1-2009 What Does It Mean for Commissioning Providers? Kent W. Peterson, PE, FASHRAE, LEED AP P2S Engineering, Inc. kent.peterson@p2seng.com What is Standard 189.1? ANSI standard
More informationAcceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance
Acceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance PAUL M. RASCHILLA, PARTNER M B A, E P M, C H C, C B C P, L E E D A P, C M V P, C S D P AKF GROUP LLC AKF Group LLC is....
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 25 0800 - COMMISSIONING OF INTEGRATED AUTOMATION GENERAL 1.1 SUMMARY This section defines responsibilities of the Integrated Automation Contractor to facilitate the Commissioning process for the
More informationOwner Project Requirements
Owner Project Requirements How to get what you need From an Owner s Perspective Learning Objectives What is an OPR Case Study (CHC) Looking to the Future Closing Arguments Crafton Hills College 1 What
More informationGuideline for Building Envelope Commissioning: New Buildings
Guideline for Building Envelope Commissioning: New Buildings Introduction Building envelope failures may arise from inadequacies in the design, construction and operation of buildings and appear to be
More informationA Building Commissioning Overview. Presented by: Goetting & Associates Commissioning
A Building Commissioning Overview Presented by: Goetting & Associates Commissioning www.goettingcx.com What is the Definition of Commissioning? Building Commissioning is a Quality Assurance Process of
More informationREQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I
Dover School District (Owner) requests written proposals to secure commissioning authority (CxA) services for the renovations project at the Garrison Elementary School in Dover, New Hampshire. The Owner
More informationCOMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202
COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning
More informationFinding Value in Building Enclosure Commissioning
Finding Value in Building Enclosure Commissioning Brian S. Rose, P.E. Technical Staff Jeffrey D. Kerr, P.E. Senior Project Manager 12 March 2015 www.sgh.com Course Description This presentation will outline
More informationDesign-Phase Commissioning. Glenn Hansen, P.E., Senior Engineer PECI
Design-Phase Commissioning Glenn Hansen, P.E., Senior Engineer PECI November 13, 2013 Overview Background Applicability Required qualifications Process Checklists 2 Background CCC initiated and helped
More informationSECTION COMMISSIONING
SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery
More informationSECTION COMMISSIONING
SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery
More informationSummary of Modifications/Changes in this Update
Summary of Modifications/Changes in this Update This Summary of Changes is for information only. It is not a part of the referenced document, and should not be used for project documentation. U.S. Department
More informationCommissioning Toolkit for In-House Commissioning of Small Buildings
1 Commissioning Toolkit for In-House Commissioning of Small Buildings Dan Burgoyne Sustainability Manager California Department of General Services California Commissioning Collaborative April 12, 2007
More informationCONSTRUCTION REQUIREMENTS
CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary
More informationMulti-Institutional Academic Health Science & Research Center Evansville, IN
SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationCommissioning Green Buildings
Commissioning Green Buildings Hazem Elzarka, PhD, PE, LEED AP University of Denver Denver, CO, USA Owners are increasingly recognizing building commissioning as an effective means of ensuring quality and
More informationLEED BD+C: NC, CS, S, R, DC, WDC, HOS, HC
LEED Building Design and Construction Activity #6 Energy and Atmosphere (EA) Before completing this Activity Read: Reference Guide for Building Design and Construction v4 Pages 318-465 Note the following
More informationBuilding Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506
AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group
More informationA. General Design and Construction Requirements
A. General Design and Construction Requirements 1. Introduction This portion of the Facility Standards includes general design and construction requirements for use by the Consultant in the course of a
More informationICC 1000 APPLICATION OF THE COMMISSIONING PROCESS. March 27, Proposed Revision: GJKettler May 11, 2014
ICC 1000 APPLICATION OF THE COMMISSIONING PROCESS March 27, 2014 Updated April 2, 2014 By Formatting and Style Committee Committee Update April 17, 2014 Proposed Revision: GJKettler May 11, 2014 - = indicates
More informationNon Residential Commissioning:
Non Residential Commissioning: Title 24 Part 6 (Energy) vs. Part 11 (Cal Green) Contact Role Email Phone Gina Rodda Presenter gina@gabelenergy.com (510) 428-0803 ext 204 CEC Hotline title24@energy.ca.gov
More informationBuild it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning
Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning NFMT 2016 T. Stephen Kisielnicki, RWC, LEED AP, BECxP March 24, 2016 About Gale Building Envelope Technology Roof, walls,
More informationRetro-Commissioning for Existing Facilities
Retro-Commissioning for Existing Facilities Tom Meyer Director, Technical Programs National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, Maryland 20877 (301) 977-3698 www.nebb.org
More information~fied1tr: SLONE . I. Submittal #39. Title - Commissioning of HV AC Systems Plan Specification Section ,00 10 SD# 02,03,07.
I SLONE ASSOCIATES, INC. Repair FRC Building 1553 Naval Station, Mayport, Florida Submittal #39 Title - Commissioning of HV AC Systems Plan Specification Section - 23 0800,00 10 Index SD# 02,03,07 Item
More informationand LEED Energy and Atmosphere Credits Jean Ascoli, LEED AP BD+C Architect, Energy Specialist
ASHRAE University of Illinois Student Chapter April 20, 2011 Building Energy Efficiency and LEED Energy and Atmosphere Credits Jean Ascoli, LEED AP BD+C Architect, Energy Specialist Building Research Council,
More informationWhat Contractors Need to Know about LEED Commissioning & IAQ Management
What Contractors Need to Know about LEED Commissioning & IAQ Management Presented by Energy Ace, Inc. Wayne Robertson, PE, CxA What is Commissioning? Commissioning is a systematic process of assuring that
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:
More informationSECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC. B. Testing, adjustment, and balancing of refrigerating systems.
SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 GENERAL 1.1 SECTION INCLUDES A. Testing, adjustment, and balancing of air systems. B. Testing, adjustment, and balancing of refrigerating
More informationMODULE #5 MECHANICAL, ELECTRICAL, PLUMBING II
MODULE #5 MECHANICAL, ELECTRICAL, PLUMBING II MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA 02210 (T) 617-423-7423 (F) 617-423-7401 mwalsh@vanderweil.com Module
More informationFull-Scope Commissioning for High-Quality Buildings
Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building
More informationSustainability and Energy Use
AIA Provider #: 40108008 Sustainability and Energy Use AIA Course #: SUS101 Presented by: Jason Borowski, PE LEED AP BD+C, Vice President jborowski@centuryeng.com 1 Sustainability and Energy Use Credit(s)
More informationGuideline Exterior Enclosure Technical Requirements for The Commissioning Process
Guideline 3-2006 Exterior Enclosure Technical Requirements for The Commissioning Process Joseph Deringer The Deringer Group Inc David Altenhofen Hiller Architecture Wagdy Anis Shepley Bulfinch Richardson
More informationNIBS Guideline
National Institute of BUILDING SCIENCES NIBS Guideline 3-2012 Building Enclosure Commissioning Process BECx This Guideline is for Use with ASHRAE Guideline 0-2005: The Commissioning Process An Authoritative
More informationBECx Design Phase Specification Review Workshop. Design Phase. Construction Risk Management. Building Enclosure Coordination Process
BECx Design Phase Specification Review Workshop Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by William R. Nash Design Phase Pre Design
More informationCommissioning for the 2015 IECC Code. Lunch & Learn Presentation O Connell Robertson - TEMA March 10, 2016
Commissioning for the 2015 IECC Code Lunch & Learn Presentation O Connell Robertson - TEMA March 10, 2016 Learning Objectives Impact of Statewide Change from IECC 2009 to IECC 2015 At the end of this program,
More informationTABLE OF CONTENTS. Appendix A DoDEA UFC High Performance Sustainable Building Compliance Checklist...9. Version 2.0 August2017 Page 2
TABLE OF CONTENTS Acronyms...3 1.0 Purpose...4 2.0 Applicability...4 3.0 References...4 4.0 Responsibilities...4 4.1 Department of Defense Education Activity, Headquarters (HQ DoDEA)...4 4.2 DoDEA Regional
More informationDayton Chapter February 9, Bob Thomson, P.E., LEED-AP, CDT
Dayton Chapter February 9, 2009 Bob Thomson, P.E., LEED-AP, CDT World Population is estimated to be 6,000,000,000 people U.S. Population is estimated to be 3,000,000 people U.S. makes up 5% of the world
More informationHow LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.
How LEED & The Retro-Commissioning Credits Produce Energy Savings James Vallort Vice President Environmental Systems Design, Inc. Retro-Commissioning Today s session will focus on the following items:
More informationP-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07
PART 1 GENERAL 1.1 REFERENCES SECTION 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 The publications listed below form a part of this specification to the extent referenced. The publications
More informationSECTION : OPERATION & MAINTENANCE MANUALS
SECTION 01 17 73: OPERATION & MAINTENANCE MANUALS 1. GENERAL: A. This section includes requirements for Contract Record - Operations and Maintenance manuals required prior to project closeout including,
More informationASSESSMENT, CLEANING & RESTORATION OF HVAC SYSTEMS (ACR-2002)
ASSESSMENT, CLEANING & RESTORATION OF HVAC SYSTEMS (ACR-2002) C Cochrane * and T Yacobellis National Air Duct Cleaners Association ACR 2002 Committee, Washington, DC, USA ABSTRACT In the fall of 2001 NADCA
More informationTraining Certification Categories
Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and
More informationPermit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE
STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE Applicant must complete numbered items
More informationBUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME
BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap
More information