Owner Project Requirements
|
|
- Elinor Smith
- 5 years ago
- Views:
Transcription
1 Owner Project Requirements How to get what you need From an Owner s Perspective Learning Objectives What is an OPR Case Study (CHC) Looking to the Future Closing Arguments Crafton Hills College 1
2 What is an OPR? Origin, definition and purpose Definition The Owner s Project Requirements (OPR) is a written document that details the functional requirements of a project and the expectations of how it will be used and operated. Guideline Standard
3 Purpose The OPR provides the basis from which all design, construction, acceptance, and operational decisions are made. An effective Cx Process depends upon a clear, concise, and comprehensive OPR document, which includes information to help the project team properly plan, design, construct, operate, and maintain systems and assemblies. Commissioning The OPR are considered the heart and soul of the Commissioning Process Design Programming OPR Construction Turnover 3
4 Without an OPR When the OPR is not developed, the owner, designer, contractors, and operation and maintenance (O&M) personnel each interpret the project requirements, including their individual responsibilities, from the standpoint of their own specific needs Without an OPR 4
5 Issues Discussed in the OPR Purpose of the Project (Functional Uses) Comfort. Occupancy. Sustainability & Energy Goals. Security. Durability. Operation and Maintenance. Criteria for Success. Case Study Crafton Hills College 5
6 Crafton Hills College Bond Program 6 Major New Construction & Modernization Projects Crafton Center Central Complex Public Safety/Allied Health PE Complex Clock Tower Building Canyon Hall Different Architects Same MEP Engineer Same Controls Contractor Same Commissioning Authority Challenges Same MEP Design Firm = Same Design? Same Control Contractor = Same Installation? Think again 6
7 What was common The Owner Project Requirements & Campus Standards College Facilities Personnel The Commissioning Authority What we achieved Standardized the Building Automation System Standardized the Air Handlers Quality and Configuration Standardized Connections to the central plant Standardized VAV terminal box installation details 7
8 Building Automation System Operates the HVAC systems Responsible for Occupants Comfort Manages Energy use How we did it We specified Same Controllers Same Valves Same Sensors Same Actuators Selected only quality devices Used fastest and most capable DC controllers Used same sequences to operate similar systems 8
9 Same Look and Feel Custom Screens 9
10 Benefits Quality Control Less vendors to deal with Familiarity of the M&O personnel with the systems Less Training Required Ease of use Looking to the Future What will the next version of the OPR include 10
11 HVAC Require a maximum of 12 for flexible pipe connections or none. Use specific HVAC equipment identification scheme Specify piping flushing and cleaning procedures specially when connecting to a campus loop. Use Chilled Water and Hot Water supply water temperature at point if use as basis of design. Specify chemical treatment type and quantities to be provided for new building Standalone controls of HVAC equipment is prohibited. Everything connected to BAS. TAB contractor to be contracted to the District and overseen by the CxA Electrical Electrical meters installed at the Factory by switchgear manufacturer Connect all the meters to the BAS. Use of single use quick wire connections are prohibited Water proof for underground connectors Connect vending machine power to BAS for switching OFF Use LED lighting throughout Design and submittals must include manufacturer seismic bracing details and requirements Standardize electrical systems identification. 11
12 Plumbing Do not provide hot water for lavatories. Do not specify refrigeration units for drinking water faucets or fill stations. Provided bottle fill stations at all drinking fountains. Require that all paper and soap dispensers to be compatible with campus vendor products. Specify point of use water heaters as required. Exterior plumbing access doors to be non-keyed. Connect water heaters and recirculating hot water pumps to the BAS for control and monitoring Lighting Controls Specify the System you want (Standards) Make sure the system is accessible through internet. Specify schedules and zone identification scheme to be used by system programmer. Include in construction contract additional programing and training at 60 days and 11 month mark after initial training. Include 3-5 years service contract with construction funding. 12
13 Envelope Use PVC dual ply roofing system on all new roofs. Require 25 year warranty minimum on roof system. Do not use asphalt roofing materials when possible. Use only Low VOC cold application asphalt materials and systems. Incorporate fall protection anchor points into building design. Incorporate windows cleaning equipment access in civil design. Landscaping Use same arborist for all filed reports Require the use of native plants only Specify irrigation system and specific system requirements. Connect irrigation system for remote access and monitoring. Define restoration of areas impacted by construction. Establish and require the use of campus identification scheme 13
14 Elevators Avoid if possible Do not let the Architect design a glass elevator. Standardize manufacturer Specify traction elevators only. Require remote scheduling capabilities for exterior elevators Exclude proprietary controls or parts. Include one year of monthly services in contract. Include re-permitting/testing at the one year mark in contract. Closing Arguments Lessons Learned, Project Management & Recommendations 14
15 Lessons Learned 1. Engage a Commissioning Authority at the inception of the project(s) 2. Include the OPR in the solicitation for Bids from Design Teams. 3. Use your Cx Authority to verify compliance. 4. Stay engaged. Support the Cx process 5. Customize OPR for each project. 6. Require the CM be involved in the Cx process and tie their success to successful functional completion. 7. Secure Board approval for Campus Standards Board Approval 1. Secure Board approval for all Campus Standard Systems as required by public contract code. Building Automation System Fire Alarm System Irrigation System Card readers Door locks 15
16 Closing Thoughts The OPR is the opportunity for the Owner to set a quality assurance process, standards and expectation for the project. The OPR is used to convey these expectations to the Design and Construction teams. The OPR serves as the basis for evaluating whether the Design and Construction has been completed to the Owner s satisfaction. You get what you spec Owner Project Requirements Questions? 16
17 Owner Project Requirements Rick Lasser, QCxP, CEM, CMVP, LEED AP Commissioning Authority, ARUP W. Jefferson. Building D, Los Angeles, CA Rick.Lasser@arup.com Larry Cook Director, Facilities Maintenance & Operation, Sand Canyon Rd, Yucaipa, CA lcook@craftonhills.edu Hussain Agah, MSCE, PMP, CCM, LEED AP BD+C, Director, Facilities Planning & Construction 114 S. Del Rosa Drive, San Bernardino, CA / Cell hagah@sbccd.cc.ca.us 17
DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING
DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York
More informationHigher Value Commissioning
Higher Value Commissioning Presented by: Erik Jeannette, PE May 2011 Commissioning What is it? Commissioning (Cx) is a comprehensive and systematic process to verify and document the systems of a facility
More informationDESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS
SECTION 01 91 13 GENERAL COMMISSIONING REQUIREMENTS GENERAL The University of South Alabama is officially and formally committed to the concept of Commissioning all new buildings and major renovations.
More informationCommissioning Electrical Systems: An Expansion of LEED
Commissioning Electrical Systems: An Expansion of LEED IEEE-SF-IAS April 26, 2011 by Rick Miller, PE, LEED AP RNM Engineering, Inc. San Luis Obispo, CA Outline LEED commissioning. What clients are actually
More informationNEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014
NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings March 5, 2014 0 Moderator Jim Huber, NEBB President-Elect and President of Complete Commissioning Jim Huber
More informationCommissioning: What Architects Need to Know
Commissioning: What Architects Need to Know Rino Zan P.Eng., Morrison Hershfield Ltd. rzan@morrisonhershfield.com Ontario Association of Architects May 12 & 13, 2016 Commissioning: What Architects need
More informationREQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa #
REQUEST FOR PROPOSAL Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # Addendum #1 Issued Wednesday, February 10, 2016 Changes: Item #01: Item #02: Section
More informationCommissioning & Retro-Commissioning Meet Energy Code
Commissioning & Retro-Commissioning Meet Energy Code Agenda Introductions What is Commissioning Value of Commissioning Code Required Cx Process Customize your Cx Process What documentation should be expected
More informationExecutive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX:
Executive Summary Sample Company BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA 17070 PHONE: 717-697-6300 FAX: 717-697-1699 Executive Summary Sample Company has constructed a 80,000 sf. addition
More informationUniversity of Delaware
SECTION 22 05 00_COMMON WORK FOR PLUMBING SYSTEM University Contact: Energy & Engineering Group (302) 831-1744 Part 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality
More informationCommissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014
1 Commissioning at NYP Joseph Lorino, PE, LEED Corporate Director April 1, 2014 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program NYP Commissioning Process
More informationB. OPR and BoD documentation may be included by reference for information only.
SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationMinnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation
Minnesota State Colleges and Universities South Central College Request for Proposals for Commissioning Agent STEM and Healthcare Renovation Date: 12/18/2017 ADDENDUM #1 1. The Sign-In sheet for the voluntary
More informationBuilding Commissioning
Building Commissioning Roles, Responsibilities, and Benefits 2010 ASHRAE Annual Meeting CxA WORKSHOP Saturday, June 26, 2010 Jim Magee, CxA, LEED-AP Facility Commissioning Group Overview Cx Advocacy, Economics,
More informationCommissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015
1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program
More informationJanice Reedus, Director of Business & Auxiliary Services Campus Center Building A, Room Houbolt Road Joliet, IL 60431
DATE: January 9, 2015 Addendum No. 1 Page 1 of 7 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Respondents SUBJECT: Addendum No. 1 PROJECT NAME: Commissioning Agent Services
More informationCommissioning: The Most Important Component of LEED. Rick Miller, PE, LEED AP. RNM Engineering, Inc. San Luis Obispo, CA
Commissioning: The Most Important Component of LEED by Rick Miller, PE, LEED AP RNM Engineering, Inc. San Luis Obispo, CA LEED and Commissioning EA Prerequisite Fundamental Commissioning of Building Energy
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction November 26, 2014 Re: Request for Qualifications - Commissioning Services Bowen Science Building Modernize Building Systems University of Iowa The
More informationMay 17 th New Youth Services Center Architect s Contract Amendment Building Commissioning Services. Dear Mr. Carrizal:
May 17 th 2011 Ernie Carrizal, P.E. County of El Paso, Texas Road & Bridges Public Works Administration 500 E. San Antonio, 4 th Floor El Paso, Texas 79901 Re: New Youth Services Center Architect s Contract
More informationSECTION COMMISSIONING
SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery
More informationSECTION COMMISSIONING
SECTION 018100 ART 1 GENERAL 1.01 SUMMARY A. Section includes: 1. Building commissioning of the following systems: a. Building Envelope. b. HVAC system: interaction of cooling, heating, and comfort delivery
More informationLessons Learned from Continuous Commissioning of a LEED Gold Building in Texas
ESL-TR-08-08-04 Lessons Learned from Continuous Commissioning of a LEED Gold Building in Texas Submitted to Lawrence Berkeley National Laboratory By David Claridge, Ph.D. P.E. John Bynum August 2008 Energy
More informationMaking LEED Work for You
Making LEED Work for You Rick Lasser, QCxP, CMVP, LEED AP Arup Synopsis While many Architects and Engineers design buildings with sustainable features, post-occupancy data that provides measurable results
More informationCOLGATE UNIVERSITY'S
2015 COLGATE UNIVERSITY'S GREEN BUILDING STANDARDS Colgate University 13 Oak Drive Hamilton, NY 13346 Colgate University 2015 Table of Contents SECTION 1: Introduction... 4 1. Goals and Objectives... 5
More informationHow We Retro-Cx 4M sf in Four Months. St. Louis Green Business Challenge
How We Retro-Cx 4M sf in Four Months St. Louis Green Business Challenge Presenters David Meyers, AIA, CxA, PMP, LEED AP Manager of Commissioning Mr. Meyers is a Certified Commissioning Authority and Program
More informationMission Critical Commissioning for Healthcare Facilities
Mission Critical Commissioning for Healthcare Facilities Steven R. Rusty Ross SSRCx, LLC Synopsis Healthcare Facilities serve a critical and unique mission. Few facilities delivered by the construction
More informationSECTION : OPERATION & MAINTENANCE MANUALS
SECTION 01 17 73: OPERATION & MAINTENANCE MANUALS 1. GENERAL: A. This section includes requirements for Contract Record - Operations and Maintenance manuals required prior to project closeout including,
More informationFull-Scope Commissioning for High-Quality Buildings
Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building
More informationSERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS
SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,
More informationdate: 10 july 2012 the pennsylvania state university: burrowes building
the pennsylvania state university: burrowes building. faculty/staff committee project overview introductions goals of the renovation critical considerations exterior envelope mechanical systems interior
More informationA. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.
SECTION 23 0800 COMMISSIONING HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED 1.2 RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary
More informationGuideline HVAC&R Technical Requirements for The Commissioning Process
Guideline 1-2007 HVAC&R Technical Requirements for The Commissioning Process Charles E Dorgan, PE, PhD University of Wisconsin - Madison Synopsis The commissioning process for delivering quality new construction
More informationRefer to Part 4 Section D20 for performance requirements of the building elements included in the plumbing system.
6. ENGINEERING SYSTEMS REQUIREMENTS D20 PLUMBING SYSTEMS REQUIREMENTS PLUMBING TEMPLATE 02/18 Instructions for using this template: There are template files for each UNIFORMAT Level 2 Group Element. This
More informationNorthwestern Facilities
Northwestern Facilities NU Master Specification - Issuances Record & Summary of Changes Only the most current version of an NU Master Specification is included as a PDF for download on this website. The
More informationB. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.
SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationBuilding Careers in Sustainable Facilities Design and Management
Building Careers in Sustainable Facilities Design and Management November 29, 2017 11:15 am 12:15 pm Presented By Robert T. Mejia, Executive Director, Economic, Resource, and Community Development, San
More informationEnergy Strategies That Work
Energy Strategies That Work Emmy Presenter s Riley, Building name Professional Energy Specialist Title (eg. architect/energy Illini Center specialist..) 10-10-12 Smart Energy Design Assistance Center (SEDAC),
More informationUniversity of Delaware
SECTION 23 05 00_COMMON WORK FOR HVAC SYSTEMS University Contact: Energy & Engineering Group (302) 831-1744 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality Control
More informationSECTION SANITARY WASTE INTERCEPTORS
SECTION 22 13 23 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable in the section
More informationROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION
INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document
More informationARMSTRONG DESIGN ENVELOPE FAQ
ARMSTRONG DESIGN ENVELOPE FAQ File No: 100.202 Date: december 28, 2015 Supersedes: 100.202 Date: september 22, 2015 q1 a1 Armstrong is the greenest, most cost effective and most flexible building mechanical
More informationFranklin Hall Renovation TABLE OF Document Indiana University Bloomington
VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...
More informationS CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS
S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS This Attachment lists the items to be provided by the Architect in accordance with Owner/Architect Agreement. This list is not all-inclusive, nor is it
More informationMSBA OWNERS PROJECT MANAGER ROUNDTABLE
MSBA OWNERS PROJECT MANAGER ROUNDTABLE September 12, 2018 Winchester High School Winchester, MA AGENDA 9:00 A.M. Welcome and Introduction 9:05 A.M. Presentation Commissioning Experiences on MSBA Projects
More informationLEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering
LEED Commissioning and Actual Energy Use John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering AIA Quality Assurance Learning Objectives 1. Why Best Practice and Fundamental Commissioning are
More informationMessiah College Natural Gas and Combined Cooling, Heat and Power Plant
Messiah College Natural Gas and Combined Cooling, Heat and Power Plant For the past decade, Messiah College wanted to bring natural gas to its campus, eliminating the use of propane and associated maintenance
More informationREQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I
Dover School District (Owner) requests written proposals to secure commissioning authority (CxA) services for the renovations project at the Garrison Elementary School in Dover, New Hampshire. The Owner
More informationIntroduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1
Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:
More informationAbsolute Energy Raters Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither
More informationFACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017
FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding
More informationWhat Contractors Need to Know about LEED Commissioning & IAQ Management
What Contractors Need to Know about LEED Commissioning & IAQ Management Presented by Energy Ace, Inc. Wayne Robertson, PE, CxA What is Commissioning? Commissioning is a systematic process of assuring that
More informationCONSTRUCTION REQUIREMENTS
CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary
More informationFinding Value in Building Enclosure Commissioning
Finding Value in Building Enclosure Commissioning Brian S. Rose, P.E. Technical Staff Jeffrey D. Kerr, P.E. Senior Project Manager 12 March 2015 www.sgh.com Course Description This presentation will outline
More informationImproving the efficiency, occupant comfort, and financial well-being of campus buildings
GHAUSI HALL ENERGY PROJECT REPORT Improving the efficiency, occupant comfort, and financial well-being of campus buildings ACE TEAM, ENERGY CONSERVATION OFFICE UC DAVIS FACILITIES MANAGEMENT Executive
More informationUnit Substation Transformer Construction Checklist (under 500 kva)
Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationE mail:
April 12, 2017 Mr. Michael Otavka William S. Hart Union High School District 21380 Centre Pointe Parkway Santa Clarita, CA 91350 Re: Castaic High School HVAC Systems and Controls Commissioning (Cx) Dear
More informationUSD 497. Request for Qualifications Commissioning Engineers Building Commissioning Services. August 11, 2017
USD 497 Request for Qualifications Commissioning Engineers Building Commissioning Services August 11, 2017 1 INTRODUCTION Lawrence Public Schools, in accordance with the policies of the Board of Education,
More informationCampusMaker ModPod. Mobile Modular s. The Flexible Solution for Sustainable Learning Spaces
Mobile Modular s CampusMaker ModPod The Flexible Solution for Sustainable Learning Spaces CampusMaker ModPod the state-of-the-art eco-friendly modular classroom. Adaptable Classrooms for Today s Changing
More informationBuilding Enclosure Commissioning of a Student Athletic Facility
Building Enclosure Commissioning of a Student Athletic Facility Presented by: Paul Totten, PE, Senior Project Manager BEST3 Conference Atlanta, Georgia 3 April 2012 www.sgh.com Presentation Outline Section
More informationCITY OF ANDERSON BUILDING AND CODES 601 South Main Street
CITY OF ANDERSON BUILDING AND CODES 601 South Main Street Plan Review Notes (STREET ADDRESS) ANDERSON, SC Plan Review Number: Building Plans prepared by: Plans Signed by: Project Name: Plans Received:
More informationtest and verify performance through commissioning DESIGN STRATEGIES
test and verify performance through commissioning DESIGN STRATEGIES DESIGN STRATEGIES VERIFYING GREEN BUILDINGS THAT WORK GLUMAC COMMISSIONING Testing, validation and documentation as a quality assurance
More informationCommissioning the Project Schedule
Commissioning the Project Schedule Matthew S. Malinosky, PE, LEED AP BD+C, CCP Mechanical Engineer Molly B. Meyer, PE, LEED AP BD+C, CEM Mechanical Engineer AIA Quality Assurance The Building Commissioning
More information2. Representatives of the facility user and operation and maintenance personnel.
PART I 1 GENERAL COMMISSIONING REQUIREMENTS 1.1 Description of Work a) The purpose of the commissioning process is to provide the owner/operator with assurance that the systems have been installed according
More informationand LEED Energy and Atmosphere Credits Jean Ascoli, LEED AP BD+C Architect, Energy Specialist
ASHRAE University of Illinois Student Chapter April 20, 2011 Building Energy Efficiency and LEED Energy and Atmosphere Credits Jean Ascoli, LEED AP BD+C Architect, Energy Specialist Building Research Council,
More informationBest Practices in Commissioning Existing Buildings Building Commissioning Association
Best Practices in Commissioning Existing Buildings Building Commissioning Association Presented at the 16 th National Conference on Building Commissioning by: Mark Miller, PE, CCP, CEM, LEED AP Principal,
More informationRefer to Part 4 Section D20 for performance requirements of the building elements included in the plumbing system.
6. ENGINEERING SYSTEMS REQUIREMENTS D20 PLUMBING SYSTEMS REQUIREMENTS PLUMBING TEMPLATE 02/18 Instructions for using this template: There are template files for each UNIFORMAT Level 2 Group Element. This
More informationSequences, Integration: Who's in Control? Wick Fisher White Consulting Engineers Hanson Professional Services Inc.
Sequences, Integration: Who's in Control? Tony DiLeonardo, LEED AP, CxA Robert J. Knoedler, P.E., CxA, EMP Wick Fisher White Consulting Engineers Hanson Professional Services Inc. AIA Quality Assurance
More informationLEEDv4: What s New? February 18, 2016
LEEDv4: What s New? February 18, 2016 CLAYTON BARTCZAK, LEED-AP BD+C Sustainable Design Team Leader TRACEY WHALEY, PE, FPE, CxAP Commissioning Team Leader 2016 Ambient Energy all rights reserved. 2015
More informationCxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP
CxA Gap Session April 25, 2017 2:00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP AIA Provider Number 50111116 Course Description This session and short quiz,
More informationPreparing a Cx Plan. Technical vs. Process Commissioning TECHNICAL FEATURE
ASHRAE www.ashrae.org. Used with permission from ASHRAE Journal, December 2013 at www.atkinsglobal.com. This article may not be copied nor distributed in either paper or digital form without ASHRAE s permission.
More informationOwner/Operator Involvement in Cx Cx to Facilitate Owner Training & Turnover. Kent Barber, PE Managing Principal KBA
Owner/Operator Involvement in Cx Cx to Facilitate Owner Training & Turnover Kent Barber, PE Managing Principal KBA AIA Quality Assurance Learning Objectives 1. Understand how turnover is critical to long
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction February 17, 2015 Re: Request for Proposals- Commissioning Services Madison Street Residence Hall Construct Facility University of Iowa The University
More informationFundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619
AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,
More informationA Guide for Architects and Owners:
A Guide for Architects and Owners: Practical Green Mechanical Engineering from Kohler & Lewis May 27, 2008 With certain exceptions for very small projects, every Kohler & Lewis project is a Practical Green
More informationMetropolitan Regional Housing Authority Tender No. MET Mechanical Upgrades ADDENDUM NO July 2018
Metropolitan Regional Housing Authority Tender No. MET18-108 Mechanical Upgrades ADDENDUM NO. 04 23 July 2018 The Tender Documents shall be amended and will become part of the Contract Documents. This
More informationCONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST
CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST Check off each item that is included within the submitted Contract Documents Review Package. Provide a written explanation for any omissions. The following items,
More informationRETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE
RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT Adam Renzi, PE AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute
More informationLOS ANGELES UNIFIED SCHOOL DISTRICT Policy Bulletin
TITLE: NUMBER: ENERGY AND RESOURCE CONSERVATION POLICY ROUTING All Employees All Locations ISSUER: DATE: June 8, 2015 Mark Hovatter, Chief Facilities Executive Facilities Services Division POLICY: The
More information445: Building Commissioning
445: Building Commissioning Class Objectives Introduce the concepts and language of Commissioning to those with limited exposure. Bring new ideas and resources to those with commissioning experience. Focus
More informationPermit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE
STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE Applicant must complete numbered items
More informationASHRAE/USGBC/IES Standard What Does It Mean for Commissioning Providers?
ASHRAE/USGBC/IES Standard 189.1-2009 What Does It Mean for Commissioning Providers? Kent W. Peterson, PE, FASHRAE, LEED AP P2S Engineering, Inc. kent.peterson@p2seng.com What is Standard 189.1? ANSI standard
More informationTexas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017
Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Plumbing - 220000 Without limiting the application of all of the Contract Documents to the Subcontract,
More informationBanyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL
SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:
More informationSECTION SANITARY WASTE INTERCEPTORS
SECTION 22 13 23 SANITARY WASTE INTERCEPTORS PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable
More informationOUT OF THE DARKNESS, INTO THE LIGHTING
OUT OF THE DARKNESS, INTO THE LIGHTING Commissioning Lighting Systems in the Predesign & Design Phase James Donson P.E. LC Senior Engineer, kw Engineering 21 st National Conference on Building Commissioning
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa
More informationEVERY ITEM WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON-APPLICABILITY (NA).
DESIGN LIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED EVERY WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON-APPLICABILITY (NA). SECTION 11 - PLUMBING A GENERAL - Check 1.
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 25 0800 - COMMISSIONING OF INTEGRATED AUTOMATION GENERAL 1.1 SUMMARY This section defines responsibilities of the Integrated Automation Contractor to facilitate the Commissioning process for the
More informationThe Benefits of Building Commissioning. Jay Cederberg, P.E. Energy Solutions Specialist
The Benefits of Building Commissioning Jay Cederberg, P.E. Energy Solutions Specialist All of these jobs would work nicely and probably give satisfaction if the man who knew the most or paid the most attention
More informationDESIGN DEVELOPMENT REVIEW PACKAGE CHECKLIST
DESIGN DEVELOPMENT REVIEW PACKAGE CHECKLIST Check off each item that is included within the submitted Design Development Review Package. Provide a written explanation for any omissions. The following items,
More informationOwner s Project Requirements for Federal Guiding Principles for High Performance and Sustainable Buildings
Owner s Project Requirements for Federal Guiding Principles for High Performance and Sustainable Buildings Project: Weaver Mountain Fire Station, L140D00737 Location: 33501 South Highway 89, Wickenburg,
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction March 7, 2013 Re: Request for Proposals- Commissioning Services Mayflower Hall Permanent Flood Recovery & Mitigation (UI# 0200201) University of Iowa
More informationRFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.
SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall
More informationJuly 21, Jeff Nichols, PE, LEED AP, CEM, CPMP. Donn Young, CPMP, QCxP, LEED AP BD+C 7/28/2017. Vice President EEI Operations
Jeff Nichols, PE, LEED AP, CEM, CPMP Donn Young, CPMP, QCxP, LEED AP BD+C July 21, 2017 Engineering Economics, Inc. Jeff Nichols, PE, LEED AP, CEM, CPMP Vice President EEI Operations Donn Young, CPMP,
More informationBrown University Updated March 11, 2013 Facilities Design & Construction Standards
SECTION 01 17 90 UTILITY & CRITICAL SYSTEM CONNECTIONS AND INTERRUPTIONS PART 1 - GENERAL 1.1 SUMMARY: A. Brown University operates and maintains extensive campus and building utilities and distribution
More informationUniversity of Central Florida Main Campus. Chilled Water. Service and Meter Installations Requirements. Issued January 26 th, 2017.
University of Central Florida Main Campus Chilled Water Service and Meter Installations Requirements Issued January 26 th, 2017 1 P a g e Table of Contents 1. GENERAL INFORMATION... 3 2. DEFINITIONS...
More informationPermit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2)
STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2) Applicant must complete
More informationClosing the Loop. Approaches to Net Zero Water. May 15, 2018 Presented to the Sixth Emerging Water Technology Symposium by Carmen Cejudo, PE, PAE
Closing the Loop Approaches to Net Zero Water May 15, 2018 Presented to the Sixth Emerging Water Technology Symposium by Carmen Cejudo, PE, PAE To be sustainable our culture must function as a mature ecosystem.
More information