Civil Engineering Construction Technology

Size: px
Start display at page:

Download "Civil Engineering Construction Technology"

Transcription

1 Civil Engineering Construction Technology Detailed Paper on Crossrail Tunnels Nouman The paper includes the detailed study of major considerations of design and the tunneling operation of the mega project of the Crossrail Tunnels

2 Contents 1. Introduction Geological Considerations Tunnel Stabilization and Lining 6 4. Dewatering Grouting Tunnel Boring Machine (TBM) Removing the excavated material.9 8. Quality of Project Problems and Proposed Solutions Health and Safety Conclusions and Recommendations

3 Civil Engineering Construction Crossrail Tunnels Introduction: Crossrail is a project to build a railway network under London. Based around an eastwest tunnel there is a central section from Paddington to Liverpool Street station. The other route is the Chelsea Hackney line. The project was approved in October The agreement regarding the full finance for the project was signed in late carriage trains are proposed to run at the frequency of up to 24 trains per hour in each direction through the central tunnel section. Figure 1 Crossrail Stations and Route by Transport for London (which reports to the Mayor of London) and the Department for Transport (which reports to the secretary of states for transport) are responsible for the sponsorship of the project. Full cost of the project will be financed by these two departments and Network Rail, BAA and City of London will also contribute. Transport for London is drawing funding from the European Investment Bank. In 2009 the enabling work phase of the project started, demolition work took place demolishing buildings including Astoria Theatre, Royal Oak Portal Taxi Facility Demolition, Demolition works for Crossrail Bond Street Station, Demolition works for Crossrail Tottenham Court Road 3

4 Station and Pudding Mill Lane Portal. The enabling work contracts were awarded to different civil engineering companies. Figure 2 Year-wise Proposed Development by (2009) Design: Tunneling provides solutions to the increased urbanization, congestion and pollution in the present age but tunneling is not such an easy task with huge challenges encountered because the work is carried out under major urban cities. The major factors responsible for problems are: i. Varying Geology ii. An array of sewers iii. Tunnels and pipes iv. Foundations of buildings These factors make tunneling beneath large cities the most complex structure in civil engineering. Geological Considerations: Geological considerations are very important in design of any civil engineering project in general and in tunneling operation in particular. Figure 3 Central Tunnels Geology by 4

5 The important challenges for which geological considerations are to be taken into account are i. Vast uncertainty in underground behaviors of soils ii. Every feature of geological aspect should be known exactly for tunneling operation iii. Geology dominates the cost and feasibility of any tunneling project iv. Ground water reservoirs and levels should be known because it is the most important consideration v. Geology dictates the selection of system of construction (tunneling system) The important phases in geological considerations are Proposal and Scoping Process Existing Data Collection and Evaluation Geological Reconnaissance Feasibility Investigation and Design Preliminary Investigation and Design Final Investigation and Design Exploration Evaluation of Results and Geotechnical Design Identification of Cost Issues Additional Exploration to Support Cost Estimates Final Design Interaction with Designers and Cost Estimators Construction Services Preconstruction briefings and periodic meetings Reviews of submittals Construction inspection Confirmation of actual geotechnical conditions and behavior Compare actual to predicted conditions and behavior (Ground and Groundwater) Exploration during construction to solve specific geological needs Instrumentation to confirm design and for early warning of problems Problem Solving Table 1 Geological Considerations The engineering properties to be considered are i. Soil Mass Strength ii. Soil Mass Modulus iii. Soil Mass Permeability The major design considerations are i. Water: the resistance to hydrostatic pressures ii. Constructability: compatibility of construction process with the expected ground conditions iii. Shield Systems: diameter of the shield, larger than the diameter of the tunnel section iv. Lining Dimensions: the length and width of the precast concrete segments 5

6 The most important consideration before the start of the tunneling operation is to know the nature of the soil. In case of soft ground tunneling, clay is somewhat easy to be tunneled into as compared to coarse grained soils (sand and gravels). The London clay, in this regard, through which much of the Crossrail s tunnels will pass very much supports tunneling operation. This nature of the London clay allowed the engineers to construct the rail tunnels in London as early as the 1880 s. But the clay in the area itself has variable properties and the major task is to determine these fluctuations in properties by analyzing the load Figure 4 Tottenham Court Rd. Station by crossrail.co.uk/library response of samples recovered from boreholes. The microstructure of soil reveals presence of diatoms which have very significant effect on the behavior of clay in terms of strength and compressibility. The variation of the geology is most significant between King Cross and Stratford. Clays, mainly London clay, are present in the form of mixtures with sands (thanet sand) and gravels. The geology of the project site can be summed up as Made ground, terrace gravels and alluvium (gravel, sand, silt and clay), London Clay and various deposits of the Lambeth Group (sand, silt, clay) and groundwater table above tunnel roof elevations by Gall Zeidler Consultants (2010). The proposed system for tunneling operation in case of Crossrail is the tube tunnel rail system in which TBM s (Tunnel Boring Machine) are used to bore 6m tunnels followed by circular precast concrete lining jointed by bolts as in cast iron lining. Tunnel Stabilization and Lining The type lining to be used in Crossrail tunnels is known as segmental lining. Soft ground tunneling usually employs this technique. Segmental lining provide a one-pass system using a shield protection during construction, providing both stabilization of the tunnel opening during construction and a permanent service lining. Segmental lining can also be used in two-pass system, as the case with Crossrail tunnels. Segmental linings have smaller diameter than that of the tunnel excavation because they are fixed inside a protective shield which is the part of the tunneling assembly. As the excavation or TBM moves forward, grout is pumped into the space between the excavated tunnel and lining. The segmental lining is bolted and in wet grounds, joints are sealed to avoid water leakage. Dry 6

7 grounds can have unbolted segmental linings. Sometimes an initial stabilization system is maintained in grounds with damp conditions. A water proofing membrane is provided between the stabilization system and the inner lining some sections of the Crossrail tunnels will be constructed according to this conditions where the soil is damp. Dewatering In some of the sections in the Crossrail tunnels dewatering is required to decrease the water level and dampness of soil to protect the tubes from leakage. Dewatering is carried by means of pumps which are installed in shafts or specially bored holes for this purpose. Grouting Grouting in tunnels can be done by cement or chemicals. In Crossrail tunnels, grouting would be done by cement along with chemical admixtures which make the cement water repellent. The Crossrail tunnels can be successfully grouted because average 8% of the soil (crossrail.co.uk) passes through the sieve #200. TBM (Tunnel Boring Machine) The other name for tunnel boring machine (TBM) is mole. It is a machine used to excavate circular cross-section tunnels. This excavating operation can be carried out in different types of soil and rock conditions. Sometimes the tunnel boring machine are used to excavate tunnels of diameter as less as Figure 5 TBM by 1m for cable trenches, this type of TBM s are called micro TBM s. On the other hand the maximum diameter of excavation so far achieved using TBM s is a little more than16m. Tunnel boring machines have replaced the conventional hand mining in practice in the soft grounds and so is the case with the Crossrail tunnels where all of the excavation operation will be carried out by eight TBM s. TBM s significantly reduce the cost of lining because they produce very smooth walls of the excavation. The cost of tunnel boring machines is very high but in Figure 6 Running Tunnels by 7

8 case of large lengths the cost of hand mining as compared with the cost of construction of a TBM becomes much more so ultimately TBM keeps the engineers on the safer side from finances viewpoint. The other main advantage of TBM is the reduction in the time period of the project. The structure of the Crossrail tunnel boring machines consists of a cutting wheel called a cutter head. The cutter head has behind it i. main bearing ii. thrust system iii. trailing support mechanism The Crossrail TBM s to be used are Earth Pressure Balance Machines (a type of TBM). Thrust cylinders are used to advance forward and concrete segments are pushed back. A combination of tungsten carbide cutting bits and carbide disc cutter makes the cutterhead. The Earth Pressure Balance Machines of the Crossrail are meant to create a balance between the earth and pressure. The design is considered to make the advancement time and time of cutting equal to each other. Bentonite and other polymers are also being used to stabilize the soil. Eight tunnel boring machines are to be used to build 6m-diameter tunnels through which the trains will run. According to estimate these TBM s will excavate eight million cubic meters of soil working 24/7. The tunnel boring machines will advance and the precast concrete tunnel sections would be fixed behind. In some areas TBM s will not be used. These areas are decided after deeply studying the geology Figure 7 Tunneling Strategy by of the sites. In these areas other excavation techniques are used and concrete is lined by spraying. The areas which will be constructed by this method are the larger platforms tunnels and the smaller tunnels which are to be excavated for passenger circulation from ground level to underground. The reason for this is that that TBM s are very expensive to construct and the 8

9 amount of work in stations tunnels and circulation/transition tunnels is very less that construction of separate TBM s for these tunnels is not economically feasible. Moreover not all the station tunnels and circulation tunnels have same diameters. Another example of this sprayed concrete lining is the construction of Waterloo station during the construction of Jubilee Line extension. TBM s are ideal for use in heavily urbanized areas like London. The TBM s to be used in Crossrail tunnels will have their crossheads rotating at a speed of 1 to 3 rpm. The tunnel waste i.e. the excavated material will be removed at a controlled rate from the tunnel face with the help of a screw conveyor which in turn deposits the collected material on a series of belt conveyors which will take the excavated material out of the tunnel. There will be an additional assembly provided to inject foam into the face of the TBM for assistance in handling the excavated material. A mechanism involving a series of hydraulic rams at the back of the shield pushes forward the last segment of the precast concrete erected and makes the TBM move ahead. The process continues as the next precast concrete ring is erected in the shield after it has been moved forward. The mechanical and electrical support equipments are fixed on a series of trailers which are towed behind the shield. The scheme of tunneling support and lining consists of precast segments made up into rings of approximately 6 segments. All the longitudinal and circumferential joints are bolted. Removing the excavated material As the spoil will fall from the excavated face scoops will pick it up and transfer to conveyor belt. This is then transferred to the trucks at the back of the TBM to be taken outside the tunnel. 50 lorries a day are currently taking the earth away from the ongoing works on the tunnels. The lorries will transport earth from central sites including Bond Street Station, Hanover Square, Newman Street, Oxford Street, Charing Cross Road, Goslett Yard, Westbourne Park, Royal Oak and Paddington. Figure 8 Removing Earth from the site by The Crossrail excavated material will go up to 200k cubic meter per month at peak which will be transported by rail (14%), by barge (39%) and by road (46%). 9

10 Clay Piling and Diaphragm Walling Arisings Sprayed Concrete Line Sand & Gravels Chalk Lambeth Group Demolition Arisings Subtotal Recovery Aggregate and hardcore Total for beneficial use Table 2 Excavated Material 2.3M cubic meter 0.68M cubic meter 1.4M cubic meter 1.15M cubic meter 0.6M cubic meter 0.9M cubic meter 0.27M cubic meter 7.3M cubic meter -2.0M cubic meter 5.3M cubic meter Quality of the Project and High Quality Materials: The following aspects make Crossrail tunnels a high quality project. 1. Environment friendly because it will decrease the hydro-carbon fueled road traffic of London 2. High quality materials ensure high efficiency decreasing the chances of delays and thus Crossrail in this respect surpasses other projects of its kind 3. Robust cost control mechanism shall be in place throughout the lifetime of the Project. 4. Environmental assurance, safety and security regimes were established to be implemented during the phases of construction, commissioning and shall be established during service operation. 5. The design of the Crossrail project complies with the applicable laws and applicable standards particularly pertaining to safety, security, interoperability, the environment and provision for the disability 6. The materials used in the Crossrail tunnels are of very high quality, some of them coming out from far off place. These include a. Sand: The sand used for the lining and the grouting mortar is with high degree of sorting coupled with high degree of rounding. Well graded sand with rounded particles and free from impurities with bulk specific gravity ranging from 1.7 to 2. The sand locally available is not of such a good quality. 10

11 b. Precast linings: The precast concrete linings used are also of very good quality being water proof and frost resistant due to addition of admixtures, with high quality rubber washers used at the back and the front of the tunnel lining to seal the bolts. c. Use of PE-foam and XPS (expanded polyester) for the sealing of joints along with water tight membrane of PVC placed along each of the segment. d. High quality aggregates (crush) tested to according to BS 812 crushed using methods which mirrors natural processes of crushing, using primary water-born techniques of crushing. Problems: The Crossrail is the Europe s largest civil engineering project, keeping in view the complex nature of the project the following are the major management and design problems to be encountered. 1. Number of industry bodies are not pleased with the project, with concerns regarding design 2. Short deadlines to be met, with operation expected to start by High cost of the project i.e. 16bn. 4. High demand of man-power, Crossrail requires having around people at the peak of the construction project. 5. Requirement of relatively long working shifts. 6. Requirement of multi-disciplinary workforce (ground engineers, specialists of contaminated land, railway engineers, structure engineers and transport planners) 7. Shortage of suitable recruits. 8. Complex IT infrastructure. 9. The settlement of the buildings which are directly above the Crossrail tunnels. 10. Vibrations caused by the TBM and later caused by the passing trains during operation. 11. Contaminated excavated material. Solutions: 1. Creating awareness about the design by issuing free brochures explaining the design and management aspects to the common people and the concerned industry people. 2. Creating divisions and simultaneously working on different sites. 3. Drawing funds by providing incentives and using BOT type of contracts. 4. Providing incentives to the labor liking boarding and lodging facilities and easy visa considerations in collaboration with the government to attract labor from 3 rd world nations. 11

12 5. High wages should be provided. 6. Acquiring the services of companies supplying construction professional services (CPS) 7. Establishment of a number of project offices and site offices. 8. Evaluation of the settlement and controlling the settlement of the building above the tunnels using different techniques like filling the grounds near the foundations with liquid cement compensation grouting using steel tubes etc. 9. The vibrations due to TBM are monitored using computer monitoring and to check the effect of vibrations during the operation full scale models should be tested. 10. The tunnel material to be excavated should be tested and contaminated material should be dumped accordingly. 11. Foundations of high rise buildings and important heritage buildings above the tunnels should be underpinned using new piling. 12. Underground concrete walls should also be built to restrict movements. Health and Safety: The Crossrail will provide high levels of health and safety services to its users 1. Provision of emergency medical facilities at all the stations and interchange terminals. 2. Provision of automatic fire fighting system at the terminals, stations and in the tunnels. 3. Use of environment friendly fire extinguisher powder rather than CO 2 4. Provision of fire-escape system 5. Air-conditioned carriages customized by air-filtering mechanism to ensure better breathing environment for the commuters. 6. Dedicated space for wheel chair users. 7. Audio and visual information about the trains journey. 8. Overhead line disconnection system with remote transmission indicating the switching status inside and outside the tunnel portals will help maintain safe flow of the traffic. 9. Provision of orientation lighting 10. Marked emergency escape routes 11. Fire water supplied throughout the tunnels 12. Emergency telephones with position identification in the train operation centre 13. Radio facilities for emergency response organizations 14. Rescue areas and access ways (Roller Pallets) 12

13 Conclusion and Recommendations: Original design methods along with special construction techniques are being implemented in the Crossrail tunnels. Due to safety, environmental aspects and space restrictions precast RCC lining is used in the tunnels. Precast piling should be used to support the foundations of the buildings which are directly above the tunneling sites. The retaining system should consist of concrete pile walls, micropiles and pre stressed anchors. The management issues should be addressed properly and the affected people should be provided proper alternatives ensuring their satisfaction, for this purpose separate department should be founded. The cultural heritage should be preserved as far as possible because the 18 th century buildings above the tunnels are of importance for preserving the cultural heritage. An extensive program of geotechnical measurements need to be undertaken after the construction of each of the section to assess the behavior of the open cuts and the functioning of the retaining system, for this special instruments should be installed in specific locations. In order to improve the escape route situation, unconventional measures such as cross-passages between road tunnels and railway tunnels may also offer professional, financially feasible and efficient solutions. The responsibilities for the installation inside the cross-passages are thoroughly to be considered in the initial design and ultimately should be defined based on the possible strategies designed to overcome conceivable accident scenarios. Overall the project is an combination of conventional and modern techniques of tunneling. The management and finances issues are as complex as the design itself and need to be given importance also. The project if completed on time and within the estimated cost of the project will turn out to be an ultimate success not only for the workforce involved in this project but also will serve as a pioneer for civil engineering projects of the future. 13

14 References John O. Bickel, Thomas R. Kuesel, Elwyn H. King (2002) Tunnel Engineering Handbook, CBS Publishers and Distributers C. A. Pequignot (1963) Tunnels and Tunneling, Hutchison Scientific and Technical F. G. Bell (2004) Engineering Geology and Construction, Spon Press Crossrail (2010) [April 2010] Frederick E. Gould (2005) Managing the Construction Process, Pearson Education Ltd. R. C. Smith, C. K. Andres (1989) Materials of Construction, McGraw-Hill Co. 14

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY CROSSRAIL INFORMATION PAPER TUNNEL CONSTRUCTON METHODOLOGY This paper sets out the proposed Crossrail tunnel construction strategy and methodology. It will be of particular relevance to those in the vicinity

More information

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

D7: TUNNEL CONSTRUCTION AND METHODOLOGY HIGH SPEED TWO INFORMATION PAPER D7: TUNNEL CONSTRUCTION AND METHODOLOGY This paper outlines the proposed tunnelling methodology. It will be of particular interest to those potentially affected by the

More information

CROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY

CROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY CROSSRAIL INFORMATION PAPER TUNNELLING DURATION AND CONSTRUCTION STRATEGY This paper sets out the proposed Crossrail tunnel construction strategy and duration. It will be of particular relevance to those

More information

Learning Legacy Document Duration of data recorded (approx.) 1

Learning Legacy Document Duration of data recorded (approx.) 1 Table 1: Crossrail Water Consumption Data Contract C300/C410 - Crossrail Running Tunnels - West; Bond Street & Tottenham Court Road s - Early Access Shafts & SCL Works (JV: BAM Nuttall Ltd / Ferrovial

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

TBM Selection and Specification

TBM Selection and Specification By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements

More information

Delivering Projects in Urban Environments Noise Control. Andrew Bird Colin Cobbing

Delivering Projects in Urban Environments Noise Control. Andrew Bird Colin Cobbing Delivering Projects in Urban Environments Noise Control Andrew Bird Colin Cobbing Structure Project description and update TBM noise and vibration Environmental requirements Construction railway (C300

More information

Pipe Jacking. Japan Sewage Works Association

Pipe Jacking. Japan Sewage Works Association Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

Presented by: Frank Guyamier

Presented by: Frank Guyamier FTBA Orlando Tuesday, March 20, 2012 Presented by: Frank Guyamier Project Engineer P3 PROJECT PARTNERS Public Sponsors 90% Equity Partner Design/Build Contractor 10% Equity Partner VMS Operator Federal

More information

Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS

Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS (Emergency Concepts, Security Exits, Cross-section Design, Guideway Types in the tunnel, Sonic-Boom-Effects, Shocks) (*) Author: Dipl.-Ing. Andreas WERTH,

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater Introduction to Soft Ground Tunnelling in Urban Environment Dr. Noppadol Phienwej Geotechnical and Geo-environmental environmental Engineering School of Engineering and Technology Asian Institute of Technology

More information

From Colonia Jardín to Cuatro Vientos

From Colonia Jardín to Cuatro Vientos 60 METROSUR Line 10, Section 1A Contractor: From Colonia Jardín to Cuatro Vientos The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of

More information

How we would build the proposed storm relief sewer

How we would build the proposed storm relief sewer Counters Creek storm relief sewer How we would build the proposed storm relief sewer We would build the proposed Counters Creek storm relief sewer using the most advanced construction methods and we would

More information

2 Technology of closed-face tunnelling machines

2 Technology of closed-face tunnelling machines 2 Technology of closed-face tunnelling machines 2.1 Machine types There are two basic types of pressurised closed-face tunnelling systems slurry tunnelling machines (STMs) and earth pressure balance machines

More information

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati Steve Lamb The Robbins Company, Solon, Ohio, USA Steve Abernathy Midwest Mole, Inc., Indianapolis, Indiana, USA ABSTRACT: A Robbins

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

MEDIA BRIEFING NOTE CROSSRAIL S FIRST TBM UNVEILED

MEDIA BRIEFING NOTE CROSSRAIL S FIRST TBM UNVEILED MEDIA BRIEFING NOTE CROSSRAIL S FIRST TBM UNVEILED About Crossrail: Crossrail is Europe s largest construction project with a total funding envelope of 14.8bn - it will deliver a 118 kilometre rail line

More information

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA Miranda Roman D. *, LaFaso Edward Iseki, Inc. 7518 Carroll Road, San Diego, Calif. 92121-2402 USA This paper will discuss the

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View J. Mayrhuber and P. Stering VERBUND Austrian Hydro Power AG, Am Hof 6a, A-1010 Wien, Austria

More information

Boletín Geotécnico Artículo

Boletín Geotécnico Artículo Boletín Geotécnico Artículo Crossrail: Inside the tunnels of Europe's biggest construction project The UK's new Crossrail rail route features 42 km (26 miles) of new tunnels dug below London (Photo: Stu

More information

Promoters. Presentation. Tunnel. Tim Smart Head of Engineering & Operations. 20 th October

Promoters. Presentation. Tunnel. Tim Smart Head of Engineering & Operations. 20 th October Promoters Tunnel Presentation Tim Smart Head of Engineering & Operations 20 th October 2014 1 Tunnel Briefing Agenda 1. Why tunnel? 2. Operational aspects of tunnels 2.1 Safety requirements 2.2 Noise and

More information

IMPACTS OF TUNNELS IN THE UK. Non-technical summary

IMPACTS OF TUNNELS IN THE UK. Non-technical summary IMPACTS OF TUNNELS IN THE UK Non-technical summary September 2013 IMPACTS OF TUNNELS IN THE UK Non-technical summary September 2013 High Speed Two (HS2) Limited has been tasked by the Department for Transport

More information

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System An Introduction to Metal Foundation System By Michael L. Schumaker, P.E. Introduction Various types of deep foundations are routinely used to support structures. Selection of the appropriate type of deep

More information

Promoters Tunnel Presentation

Promoters Tunnel Presentation Promoters Tunnel Presentation Tim Smart Head of Engineering & Operations 20 th October 2014 1 P653 (1) HOC/10009/0002 Tunnel Briefing Agenda 1. Why tunnel? 2. Operational aspects of tunnels 2.1 Safety

More information

Crossrail Brief to INCOSE Chris Sexton Technical Director

Crossrail Brief to INCOSE Chris Sexton Technical Director Crossrail Brief to INCOSE Chris Sexton Technical Director 24January 2012 Delivering a world-class affordable railway, safely, and through effective partnerships What is Crossrail? Largest civil engineering

More information

Risk Management of the Restoration of Shanghai Metro Line 4

Risk Management of the Restoration of Shanghai Metro Line 4 ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management of the Restoration of Shanghai Metro Line 4 X. P. Yu, W. J. Zhu

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS fib Symposium Keep Concrete Attractive, Budapest 2005 COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS Kolic D. 1, Hörlein N. 2, Schneider K. 3, Steiner H. 3 NEURON Consult ZT 1, PORR Tunnelbau GmbH 2, ÖBB-Infrastruktur

More information

TBM rescue projects using shafts and ground freezing

TBM rescue projects using shafts and ground freezing TBM rescue projects using shafts and ground freezing Dipl.-Ing. Michael Löffler, Dipl.-Ing. Helmut Haß (CDM Consult GmbH, Germany) Dipl.-Ing. Thomas Ahlbrecht (Deilmann-Haniel Shaft Sinking GmbH, Germany)

More information

An introduction to. pipe jacking

An introduction to. pipe jacking An introduction to pipe jacking The pipe jacking technique The major applications for pipe jacking and microtunneling include new sewerage and drainage construction, sewer replacement and lining, gas and

More information

Tunnel. Immersed Tunnels

Tunnel. Immersed Tunnels Tunnel Tunnels are underground spaces, usually, in a tubular shape with substantial lengths. They can either be man-made or natural and can be used as passageways, storages, carriageways and utility ducts.

More information

rapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions.

rapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions. herrenknecht AG utility tunnelling Traffic tunnelling SEPARATION PLANTS HERRENKNECHT SEPARATION PLANTS KEEP IT FLOWING. RAPID TUNNELLING THANKS TO EFFICIENT SEPARATION. Low-impact mechanized tunnelling:

More information

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS PRODUCTIVITY IN A PIPE Creating stability Drilled casings, or casing advancement systems, are today's preferred method for drilling in difficult ground

More information

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more. TECHNOLOGY Diaphragm walls Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS 1 PART ONE - GENERAL 1.1 COORDINATION SECTION 02466 DRILLED CONCRETE PIERS AND SHAFTS A. The General, Supplementary, and Special Conditions of these specifications shall all be considered as a part of

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

2 Support of the cavity and settlement Support of the face Natural support Mechanical support... Table of Contents The authors... VII Foreword to the 2nd Edition... IX 1 Introduction... 1 1.1 Basic principles and terms... 3 1.2 Types of tunnel boring machine according to DAUB... 5 1.2.1 Categories

More information

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment rotary drill hydro-mill backhoe Clamshell + Kelly bar VERTICAL BARRIERS SLURRY

More information

DIFFICULT GROUND SOLUTIONS:

DIFFICULT GROUND SOLUTIONS: Tunnelling April/May 2016 www.tunnellingjournal.com journal The international journal for the tunnelling industry SEE PAGE 6 SEE PAGE 12 SEE PAGE 27 WORLD NEWS MONITOR PROGRESS CUTTER CARE HIGHLIGHTS FROM

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

03/12/2012. JSPS/CSIC international symposium on Smart Infrastructure and Construction. Business opportunities for Smart Infrastructure

03/12/2012. JSPS/CSIC international symposium on Smart Infrastructure and Construction. Business opportunities for Smart Infrastructure JSPS/CSIC international symposium on Smart Infrastructure and Construction Business opportunities for Smart Infrastructure 13 November 2012-10:30 11:00 Crossrail, CSIC and using instrumentation to make

More information

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors An Introduction to Keller in the UK Piling and Ground Improvement Grouting, Soil Nails and Anchors Retaining Walls Equipment Manufacture Monitoring and Instrumentation PHI GROUP GETEC COLCRETE EURODRILL

More information

Specialising in Ground Engineering & Slope Stabilisation

Specialising in Ground Engineering & Slope Stabilisation Specialising in Ground Engineering & Slope Stabilisation Ground Engineering & Slope Stabilisation for the Road, Rail, Construction & Mining Industries Company Profile Warner Company is proudly an Australian

More information

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. Author: Frank B. Stevens Pr. Eng, BSc (Civil), HonFIMESA, FSAICE Technical Representative for Herrenknecht AG (Utility Tunnelling). stevens.frank@herrenknecht.de

More information

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Compaction and Jet Grouting

Compaction and Jet Grouting Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials

More information

Figure (12.1) Foundation Grouting

Figure (12.1) Foundation Grouting Chapter 12 - Foundation Grouting 12. Foundation Grouting 12.1. Introduction: The construction of structures on weak ground often requires the soil to be improved in order to ensure the safety and the stability

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

Crossrail - the Application of Advanced Engineering and Science to Grow London's Transport Network

Crossrail - the Application of Advanced Engineering and Science to Grow London's Transport Network 1 Crossrail - the Application of Advanced Engineering and Science to Grow London's Transport Network 1. Introduction Crossrail is a rail network which goes under London and aims both to improve journey

More information

Quality management system. Environmental management system. Occupational health and safety management system.

Quality management system. Environmental management system. Occupational health and safety management system. Company Profile Gulf Rock Engineering Group was started in 1975 as a specialist blasting sub-contractor and has since developed into one of the Gulf regions leading earthworks and underground construction

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

SECTION PRECAST CONCRETE SEGMENTAL TUNNEL LINING

SECTION PRECAST CONCRETE SEGMENTAL TUNNEL LINING SECTION 31 74 16 PRECAST CONCRETE SEGMENTAL TUNNEL LINING PART 1 - GENERAL 1.1 DESCRIPTION A. The Work specified in this Section consists of the requirements for manufacturing, installing, erecting and

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Diaphragm wall Construction

Diaphragm wall Construction Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support

More information

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. Roger Woodhead, PhD, P.Eng., SNC-Lavain Inc. Paper prepared for

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 415 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING TABLE OF CONTENTS 415.01 SCOPE 415.02 REFERENCES 415.03 DEFINITIONS

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) Topic 5 Tunnelling 1. Introduction Tunnels can be defined as underground passages constructed for the purpose of transportation connection between two points. 2. Type of Tunnels There are many types of

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used

More information

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS AFTER FEBRUARY 1, 2011 ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS 481.1 Description. This specification shall govern for the construction of monolithic, reinforced concrete box sewers of the size,

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.4 PERMEATION GROUTING 7.4.1 Definitions 7.4.1.1 Geotechnical Data Report (GDR)

More information

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP A. TECHNICAL INFORMATION OF OUR FOUNDATION WORKS The major types of our foundation works (with illustrative diagram, where applicable) are set out below: 1. Bored piles 0.80m 3.5m pile shaft By Grabbing

More information

SECTION 303 CULVERTS

SECTION 303 CULVERTS 303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the

More information

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro S. Smading The Robbins Company, Singapore ABSTRACT: Today s mega metro projects are using multiple TBMs in difficult ground, short

More information

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design Wet Speed-Mixing WSM - Soil Mixing Procedure in Design Method description WSM - a fast alternative for shoring applications What is WSM? WSM stands for Wet Speed-Mixing, a fast soil mixing procedure. The

More information

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e. No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for

More information

FOR HIGHWAY TUNNEL GALLERIA SPARVO.

FOR HIGHWAY TUNNEL GALLERIA SPARVO. HERRENKNECHT EPB SHIELD S-574 FOR HIGHWAY TUNNEL GALLERIA SPARVO. PRODUCT PORTFOLIO OF HERRENKNECHT GROUP. MECHANIZED TUNNELLING TECHNOLOGY. STEEP TUNNELLING. St. Petersburg 30 downhill EPB Shield Access

More information

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY P H FERREIRA Pr. Eng (Mining), Managing Director, Minova

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

FEBRUARY 2015 MONITORING

FEBRUARY 2015 MONITORING FEBRUARY 2015 MONITORING Licensing Exam 100 Years Too Late Pole of Inaccessibility Experience or not? Then and now Cartographic features MOVING LONDON SAFELY FORWARD An artist s impression of the new Paddington

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

MEDIA BRIEFING NOTE: CROSSRAIL TUNNEL CONTRACTS & TUNNELLING

MEDIA BRIEFING NOTE: CROSSRAIL TUNNEL CONTRACTS & TUNNELLING 10 December 2010 MEDIA BRIEFING NOTE: CROSSRAIL TUNNEL CONTRACTS & TUNNELLING Introduction: A total of 21 km of twin-bore tunnel is required to be constructed for Crossrail. The five tunnels to be constructed

More information

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS 4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS This section discusses the geology, soils, seismicity, hazardous materials, and subsurface obstructions along Flower Street, and evaluates their potential

More information

of GENERAL. A. Description

of GENERAL. A. Description 02920-1 of 11 SECTION 02920: EARTH TUNNELING 02920.01 GENERAL A. Description Earth tunneling shall include, but not necessarily be limited to, constructing earth tunnels and furnishing and installing tunnel

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

Crossrail and our international tunnelling expertise

Crossrail and our international tunnelling expertise Crossrail and our international tunnelling expertise Analyst briefing Thursday 1 October 2015 Neil Thomas Managing director Water, Ground and Environment Crossrail Crossrail Crossrail has one purpose to

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways

More information