ENGINEER S REPORT MAIN TILE IMPROVEMENTS DRAINAGE DISTRICT NO. 131 WRIGHT COUNTY

Size: px
Start display at page:

Download "ENGINEER S REPORT MAIN TILE IMPROVEMENTS DRAINAGE DISTRICT NO. 131 WRIGHT COUNTY"

Transcription

1 ENGINEER S REPORT MAIN TILE IMPROVEMENTS DRAINAGE DISTRICT NO. 131 WRIGHT COUNTY 2013

2

3 TABLE OF CONTENTS Page I. Introduction 1 II. Background 1 III. Existing Conditions 1-4 IV. Improvement Options 4-6 V. Recommendation 6-7 VI. Reclassification 8 VII. Wetlands 8 VIII. Administration 8 APPENDIX Cost Estimate Plat N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM

4 I. Introduction The following report on the investigation for improvements for Drainage District No. 131 is herein submitted. A petition was filed to investigate the main tile of DD No. 131 due to a lack of drainage that results in prolonged flooding at the north end of the district. There was also some concern related to the surface drainage of land within the district. It was requested that the natural surface drainage be looked at along the north line of Section 27 and adjacent to county road C54. It was also requested that a private tile line at the upper end of the main tile be investigated to determine if it is draining land outside of the district boundary. II. Background DD No. 131 was established April 18, 1916 and construction was completed October 30, 1917 for $26, The district consists of a main tile with four laterals and drains 2,120 acres. The main tile is located five miles east of Eagle Grove and runs through Sections 27, 34 and 35 of Dayton Township and Sections 2, 11 and 12 of Woolstock Township. The main tile outlets into the White Fox Creek. There is no record of significant repairs being made in the district. III. Existing Conditions Main Tile Drainage The main tile of DD No. 131 consists of 22,000 feet of clay tile and ranges in size from 10 to 32 inches. A capacity analysis was done on the main tile using the grades and pipe sizes shown on the original profile and as measured in the field. The tables below show the tile size, grade, capacity, drainage area, and drainage coefficient of the existing tile. The drainage coefficient is the amount of water a tile can drain per acre within a 24 hour period. A typical modern design would be for a ½ drainage coefficient. The majority of the main tile has a drainage coefficient of 1/8 with the exception of a 6,450 foot stretch of tile that has a 3/32 drainage coefficient. Land owners noted that water tends to drain slowly from the upper reaches of the tile. This is likely due to lack of capacity in relation to the amount of private tile draining into the system. Looking at aerial photos, it appears that almost half of the land within the district is drained by private tile lines. A letter written by the Board in 1970 noted that the district tile system was overloaded at that time. The four lateral tiles are Lateral 1, A, B and 2. Lateral 1 and 2 tie directly into the main tile and have drainage coefficients greater than the main tile. Lateral 1 has a drainage coefficient of ¼ and Lateral 2 has a drainage coefficient of 3/8. Lateral A and B tie into Lateral 1. Lateral A has a drainage coefficient of 1/8 and Lateral B has a coefficient of 1. N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 1

5 Main Tile Capacity Analysis Table DD 131 Station Existing Tile (in.) Existing Grade Existing Capacity (cfs) D.A. (Acres) Existing D.C % /8" % /8" % /8" % /8" % /8" % /8" % /32" % /32" % /32" % /32" % /32" % /8" % /8" % /32" Lateral Tile Capacity Analysis Table Station Existing Tile (in.) Existing Grade Existing Capacity (cfs) D.A. (Acres) Existing D.C. Lat % /4" % /8" % /8" Lat A % /8" Lat B % " Lat % /8" N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 2

6 Surface Drainage Two areas were requested to be looked at with concerns on how the surface water drains through the district. Surface Drainage Area 1: The first area is at the north fence line of Section 27 as shown on the attached map. Approximately 24 acres drain from the north into Section 27. The surface water from the north drains through a 24 inch road culvert and ponds in the road ditch until it drains into a tile intake or reaches a depth that allows it to surface drain into the field to the south. The intakes in the ditch and the main tile are not sufficient to drain a moderate rainfall since the tile system is not designed to act as a storm sewer. Once the water gets deep enough it flows into the field to the south and floods the field. The concern the west property owner (NE NW) has is that the south ditch bank has been artificially built up on the east side (NW NE) of the fence causing water to flow across his field when it should naturally drain to the east. Survey shots taken in the field and on the top of slope of the road ditch show that the water should naturally drain into the east field. The top of slope elevation on the east side is 0.77ft lower than the west side at their respective low points. The reason water may flow into the west field first is because the water must pass under a field entrance to get to the east field. The culvert under the gravel road is a 24 inch but the culvert under the field entrance is only a 15 inch. This likely caused water to pass under the road at a higher rate than it can pass under the field entrance causing the water to back up on the west side. All things being equal, a 24 inch pipe has 2.7 times the capacity of a 15 inch pipe. If the field entrance culvert is plugged or the openings are obstructed then this would compound the problem. Increasing the field entrance culvert size could help equalize the flow of water on both sides of the field entrance. This is not a drainage district issue. The land owners should work with the Secondary Roads Department if they wish to increase the field entrance culvert size. Increasing the tile size will help drain the fields that flood quicker. Surface Drainage Area 2: The second area with surface drainage issues is north and south of county road C54 in Sections 27 and 34 as shown on the attached map. The land in Section 27 drains south into Section 34 through a 60 x70 corrugated metal arch pipe. There is a natural waterway through the north field that drains approximately 518 acres. The north field has a history of flooding and the land owner has attempted reshaping the waterway to bring the ground elevation up. Their concern is that the land to the south is at a higher elevation than their low ground causing the area to flood with the only outlet being the tile intake in the road ditch. Survey ground shots show that the north field is 0.5ft lower than the highest field elevation to the south. At a minimum this causes the north field to flood 0.5ft with the only outlet being the ditch intake to the district tile. Two options are available to relieve the flooding in the field. One is to grade the south field to allow water to flow freely and the other option is to improve the drain tile to drain the north field quicker when it floods. A properly designed grassed waterway would be designed to convey the peak runoff from the 10 year, 24 hour duration storm. The field to the south however does not provide adequate grade or depth to install a waterway that would transmit this flow. At best there could be a very shallow channel cut that would allow the north field to drain over a period of time. A typical grassed waterway would ideally have a minimum N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 3

7 grade of 1% but the maximum grade possible through the south field is 0.08% which would tend to silt in. Drainage districts typically do not control how surface water flows through a field and to do so would be to create a district controlled ditch or waterway. This would also be an expense paid for by the entire district that would benefit only one or two land owners. To help alleviate the flooding in this area it is recommended to improve the tile capacity or the land owners could work together to grade the field. Drain tile do not function as a storm sewer and the field will still flood after heavy rain storms. However, an improved drain tile would drain the field faster reducing the amount of crop loss. Private Tile across District Boundary Line It was requested that we investigate the possibility that there is a private tile line draining land from outside the district boundary. The tile in question is at the north end of the district in Section 22 as shown on the attached map. In 1970 the Board was informed that a private tile was installed in the north road ditch running east and west along 260 th Street that drained land from outside of the district watershed boundary to the west. The land owner was directed to disconnect the tile line 420 feet west of the southeast corner of the SW ¼ of Section 22. If the tile was not disconnected then it would be done by the county. There is no record if this tile line was disconnected. We probed across the road ditch in a couple of locations and were not able to find the private tile line. It is possible that the tile no longer exists or we missed it with our probe. To determine if the tile line is still in existence and to see if it drains beyond the district boundary the district could have a contractor trench across the road ditch near the district boundary location. If the tile is found to be intact the district could either disconnect the line to the west or allow the land owner to annex into the district. If a project is selected then it would be recommended to include the exploration as part of the project. IV. Improvement Options Improvement options for the ¼ and ½ drainage coefficient are shown below. In order to improve the drainage at the north and south ends of Section 27 and to improve the drainage capacity in general for the entire district, it will be necessary to increase the main tile size. The options include completely replacing the existing main or installing a parallel relief tile line. Costs are provided to compare the presented options. Another option would be to televise the existing main to determine if the existing tile has obstructions or broken segments that are impeding the tile flow. This would confirm if the existing tile is suitable as a relief tile or if the tile is not operating at its peak capacity. There may be improvement by simply repairing any damaged sections. Aerial photos appear to show that nearly half of the district is drained by private tile. These tile systems can only operate effectively if they have an adequate outlet. As mentioned above, the existing tile system has a 1/8 drainage coefficient. Increasing the capacity to the ¼ or ½ drainage coefficient would double or quadruple the capacity respectively. Option 1 Televise Existing Main Tile This option would be to televise the existing main for two reasons. First it would identify any existing damaged or obstructed sections of tile that may be obstructing the flow. Examples would include collapsed pipe sections, sedimentation, or private tile inlets that extend too far into the pipe. If an improvement option is not selected then this would at least confirm that the N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 4

8 existing tile is operating at its peak efficiency. The second reason to televise would be to gauge the suitability of the tile to remain in service if a relief tile is installed. A relief tile will rely on the existing main for a large portion of the drainage capacity and it would be beneficial to know if the combined tile system will operate as expected. As part of this option the private tile line would be investigated at the north end of the district to determine if land outside of the district is being drained. The estimated cost for this option is $51,503 as shown on the cost estimate in the Appendix. The cost would include exposing the existing main periodically, repairing the exposed sections, televising the main, surveying the tile location and depth, and reviewing the televising report. It is possible to scale the extent of the televising down if there are specific areas that landowners feel would need to be investigated. Costs to make repairs would be determined after the tile is televised. An estimated range to repair an isolated section would be $500 - $1,500 per repair. Option 2A/2B Increase Tile Capacity to ¼ D.C. This option would increase the tile capacity from a 1/8 drainage coefficient to a ¼ drainage coefficient, doubling the capacity of the main. There are two ways to accomplish this. One is to install a relief tile line and the second is to replace the existing main with a larger tile line. Option 2A would install a relief tile line parallel to the existing main. The relief tile would follow the grade of the existing tile and range in size from 30 inches at the outlet to 12 inches at the upper end. Periodic cross connections would be made between the new and old tile to help equalize the flow. This option relies on a nearly 100 year old tile that will require maintenance as it ages. The estimated cost for this option is $962,320 as shown on the cost estimate in the Appendix. Option 2B would remove and replace the existing main with a larger pipe that would follow the existing main grade and alignment. The new main would range in size from 42 inches at the outlet to 12 inches at the upper end. The lower 2,400 feet of the existing tile, near the outlet at the White Fox Creek, has limited cover and increasing the tile size would reduce this further. It may be necessary to shift the alignment of the new tile into deeper cover in order to maintain a minimum level of cover. Ideally a minimum of 2ft of cover would be maintained over the tile however it is possible there would be limited stretches with only a foot of cover. The land along the White Fox is not currently cultivated which eases the need for more cover. The estimated cost for this option is $1,221,449 as shown on the cost estimate in the Appendix. Option 3A/3B Increase Tile Capacity to ½ D.C. This option would increase the tile capacity from a 1/8 drainage coefficient to a ½ drainage coefficient, nearly quadrupling the capacity of the main for most of its length. As with Option 2, there are two ways to accomplish this. One is to install a relief tile line and the second is to replace the existing main with a larger tile line. Option 3A would install a relief tile line parallel to the existing main. The relief tile would follow the grade of the existing tile and range in size from 48 inches at the outlet to 12 inches at the upper end. Periodic cross connections would be made between the new and old tile to help equalize the flow. As with Option 2B, the increased tile size reduces the amount of cover along N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 5

9 the lower 2,400 feet. It would most likely be necessary to shift the alignment of the tile to provide more cover. Alternatively to shifting the alignment, arched pipe could be utilized to attain the maximum amount of cover. This option relies on a nearly 100 year old tile that will require maintenance as it ages. The estimated cost for this option is $1,339,950 as shown on the cost estimate in the Appendix. Option 3B would remove and replace the existing main with a larger pipe that would follow the existing main grade and alignment. The new main would need to range in size from 54 inches at the outlet to 12 inches at the upper end. However, due to the lack of cover at the outlet, the 54 inch pipe would not have sufficient cover and would likely have no cover in depressed areas. The original drainage plan called for a drainage ditch for the first 1,000 feet at the outlet but this was changed to tile before construction. In lieu of a 54 inch tile, an open ditch could be installed for the last 1,000+ feet of the outlet. This will require the purchase of right of way for the ditch and the construction of a headwall at the tile outlet. It will also be necessary to work with the Army Corps of Engineers to obtain any required permits to construct an open ditch within the flood plain of the White Fox Creek. The alignment of the tile may need to be shifted into higher ground to provide a minimum level of cover. Ideally a minimum of 2ft of cover would be maintained over the tile however it is possible there would be limited stretches with only a foot of cover. The estimated cost for this option is $1,587,005 as shown on the cost estimate in the Appendix. The advantage of the replacement options is that the entire length of main tile will be new and not rely on the old existing tile line. Each of the improvement options is expensive with a high average cost per acre. The high average cost is due to the shape of the district. It is long but also narrow which results in high construction costs but relatively fewer acres paying towards the construction. A summary of costs is below. Cost Summary of Options Option Description Estimate Avg. $/AC Avg. $/AC over 10yrs. 1 Televise Main Tile $51,503 $24 $3 2A Main Relief Tile 1/4" Drainage Coefficient $962,320 $454 $62 2B Main Replacement tile 1/4" Drainage Coefficient $1,221,449 $576 $78 3A Main Relief Tile 1/2" Drainage Coefficient $1,339,950 $632 $86 3B Main Replacement Tile 1/2" Drainage Coefficient $1,587,005 $749 $102 V. Recommendation There is a desire from some land owners to improve the drainage through the main tile system and to alleviate some surface drainage problems. With intense row-cropping the need for good drainage is vitally important, and to compound the issue, the added pattern tiling over the years has more than ever created a greater need for more subsurface drainage capacity. Subsurface drainage systems are only as efficient as their outlet. An article provided by the Iowa State University Extension is quoted below regarding the benefits of improved drainage. 6 N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM

10 Investment Analysis The major reason for installing subsurface drainage is to improve the productivity of the farmland. Higher yields translate into more returns. This is especially true in recent years due to higher grain prices. So the investment decision is based on whether the higher crop returns will justify the investment in subsurface drainage. A secondary benefit is that fields will dry out quicker, allowing planting and harvesting to be completed earlier in the spring and fall. It also provides a larger window of time for a farmer to plant and harvest the crop allowing it to be done in a more efficient manner in terms of time and money. This is especially advantageous for farmers who have large acreages to cover. Specific advantages of tile drainage are: 1. More consistent yields Allows for more efficient use of resources Reduces financial risk 2. Earlier and more timely planting 3. Improved harvesting conditions 4. Less wear and tear on equipment 5. Less power required for field operations 6. Better plant stand 7. Less plant stress 8. Fewer plant diseases 9. Less soil compaction Another major advantage of tile drainage is the increase in sale value of the land. If the land will be sold in the future, the advantages listed above will be capitalized into the value of the land. Subsurface drainage is a long-term investment. The investment is made up-front but the benefits are spread over many future years. So the investment decision should be made with the time-lag in mind. The most difficult part of computing a tile investment analysis is estimating the yield response from the improved drainage. The size of the expected yield improvement dramatically impacts the economic feasibility of installing tile drainage as shown in the example below. The improvement options would increase the capacity of the main providing a better outlet for the laterals and private tile lines. Each of the laterals would see a benefit to the increased capacity of the main by either more closely matching the laterals drainage coefficients or by freeing up bottlenecks in the system. The option to televise and make repairs would serve to ensure the existing system is operating at its peak capacity. The options are presented for the landowners in the Drainage District to discuss and determine if any of the improvement options appear to be worthy of pursuing. Although an improvement project would increase the capacity of the main tile, there would still be periods with standing water in the field. Drain tile are designed to drain the subsurface moisture. They are not designed to act as storm sewers to drain surface water quickly. Increasing the tile size would decrease the amount of time it takes to drain the excess moisture. A field s drainage will also depend on the amount of private tile installed. N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 7

11 VI. Reclassification The original classification is in use to apportion costs and does not have a separate schedule for each lateral. If an improvement option is chosen then a reclassification would be required for DD 131 (Section ). A reclassification is estimated to cost $20,000. VII. Wetlands Improvement projects have the potential to affect wetlands and farmed-wetlands. It is up to the individual landowner to notify the Board of Supervisors if the project will disturb any wetlands that could result in the need for mitigation to avoid jeopardizing any producers FSA program eligibility. Landowners need to present this information at or before the public hearing. If wetlands or farmed-wetlands exist, it will be necessary to mitigate them if an improvement project is selected. The mitigation needs to be done before construction starts so prompt action from the landowners is important. The drainage district may elect to pay for the mitigation costs. VIII. Administration The Code of Iowa requires a public hearing date be set regarding this report and notice given to all district landowners (Section , para. 1.c.). If a project is approved, a public bid letting will also be required (Section ). N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM 8

12 N:\Projects\WRC \Cler\Design\DD 131 Report.doc 12/24/2013/10:28 AM APPENDIX

13 Opinion of Probable Costs Main Tile Improvements DD No. 131 Wright County Dec-13 Option 1 - Televise Main Tile (22,000 ft) item description quantity unit unit cost extension 1. Mobilization 1 ls $1,500 $1, Televise 6" to 10" 1,500 lf $0.70 $1, Televise 12" to 18" 6,000 lf $0.85 $5, Televise 24" to 30" 12,100 lf $1.20 $14, Televise over 30" 2,400 lf $1.40 $3, Expose Existing Tile 14 ea $500 $7, Repair Exposed Tile 14 ea $200 $2, Tile Exploration 16 hr $150 $2,400 Total $37,730 10% Contingency $3,773 Bidding Phase & Contracts $2,500 Engineer Review Televising Report $5,000 Survey Tile Location $2,500 Estimated Total Project $51,503 Average Assessment DD 131: $51,503 /2,120 ac= $24.29 Average Cost Per Acre Over 10 6%: $3.30 per acre per year N:\Projects\WRC \Cler\Design\ Costs

14 Opinion of Probable Costs Main Tile Improvements DD No. 131 Wright County Dec-13 Option 2A - DD 131 Relief Tile 1/4" Drainage Coeficient (22,000 ft) item description quantity unit unit cost extension 1. 12" RCP 1,500 lf $20 $30, " RCP 1,500 lf $22 $33, " RCP 1,500 lf $24 $36, " RCP 1,500 lf $26 $39, " RCP 3,500 lf $28 $98, " RCP 10,000 lf $32 $320, " RCP 2,500 lf $36 $90, " CMP Tile Outlet 20 lf $30 $ Tile Intake 2 ea $500 $1, Flow Equalization Lines 10 ea $500 $5, Field Tile Connections 110 ea $200 $22, Locate Existing Tile 24 hr $150 $3, Trench Stabilization Rock 1,100 tn $25 $27, Lateral Connection 2 ea $600 $1, Seeding, Fertilizing, Mulch 6 ac $1,500 $9,300 Total Construction $716,200 10% Contingency $71,620 Survey, Records Review, Report & Hearings $10,000 Survey, Plans, Specifications, Bidding Phase & Contract Documents $9,000 Construction Staking, Construction Review & Administration $35,000 Legal Notices, Miscellaneous $1,500 ROW Damages $2,250/ac) $99,000 Reclassification $20,000 Estimated Total Project $962,320 N:\Projects\WRC \Cler\Design\ Costs

15 Average Assessment DD 131: $962,320 /2,120 ac= $ Average Cost Per Acre Over 10 6%: $61.67 per acre per year Secondary Roads Expense 260th Street Crossing $5,400 C-54 Crossing (Bored) $27,000 Keokuk Avenue Crossing $5, th Street Crossing $6,100 Lee Avenue Crossing $6,500 C-60 Crossing $6,500 Total $57,400 N:\Projects\WRC \Cler\Design\ Costs

16 Opinion of Probable Costs Main Tile Improvements DD No. 131 Wright County Dec-13 Option 2B - DD 131 Replacement Tile 1/4" Drainage Coeficient (22,000 ft) item description quantity unit unit cost extension 1. 12" RCP 500 lf $20 $10, " RCP 1,000 lf $22 $22, " RCP 1,000 lf $24 $24, " RCP 1,700 lf $26 $44, " RCP 1,800 lf $28 $50, " RCP 1,200 lf $32 $38, " RCP 2,600 lf $36 $93, " RCP 3,700 lf $40 $148, " RCP 5,000 lf $45 $225, " RCP 3,476 lf $52 $180, " RCP Tile Outlet 24 lf $55 $1, Tile Intake 2 ea $500 $1, Crush and Bury Existing Tile 22,000 lf $2.25 $49, Field Tile Connections 110 ea $200 $22, Locate Existing Tile 24 hr $150 $3, Trench Stabilization Rock 1,100 tn $25 $27, Lateral Connection 2 ea $600 $1, Seeding, Fertilizing, Mulch 6 ac $1,500 $9,300 Total Construction $951,772 10% Contingency $95,177 Survey, Records Review, Report & Hearings $10,000 Survey, Plans, Specifications, Bidding Phase & Contract Documents $9,000 Construction Staking, Construction Review & Administration $35,000 Legal Notices, Miscellaneous $1,500 N:\Projects\WRC \Cler\Design\ Costs

17 ROW Damages $2,250/ac) $99,000 Reclassification $20,000 Estimated Total Project $1,221,449 Average Assessment DD 131: $1,221,449 /2,120 ac= $ Average Cost Per Acre Over 10 6%: $78.28 per acre per year Secondary Roads Expense 260th Street Crossing $5,700 C-54 Crossing (Bored) $38,000 Keokuk Avenue Crossing $6, th Street Crossing $7,000 Lee Avenue Crossing $7,450 C-60 Crossing $7,450 Total $72,400 N:\Projects\WRC \Cler\Design\ Costs

18 Opinion of Probable Costs Main Tile Improvements DD No. 131 Wright County Dec-13 Option 3A - DD 131 Relief Tile 1/2" Drainage Coeficient (22,000 ft) item description quantity unit unit cost extension 1. 12" RCP 500 lf $20 $10, " RCP 500 lf $22 $11, " RCP 500 lf $24 $12, " RCP 1,000 lf $26 $26, " RCP 1,700 lf $28 $47, " RCP 600 lf $32 $19, " RCP 1,400 lf $36 $50, " RCP 1,100 lf $40 $44, " RCP 2,700 lf $45 $121, " RCP 9,300 lf $52 $483, " RCP 2,700 lf $60 $162, " RCP Tile Outlet 20 lf $30 $ Tile Intake 2 ea $500 $1, Flow Equalization Lines 10 ea $700 $7, Field Tile Connections 110 ea $200 $22, Locate Existing Tile 24 hr $150 $3, Trench Stabilization Rock 1,100 tn $25 $27, Lateral Connection 2 ea $600 $1, Seeding, Fertilizing, Mulch 6 ac $1,500 $9,300 Total Construction $1,059,500 10% Contingency $105,950 Survey, Records Review, Report & Hearings $10,000 Survey, Plans, Specifications, Bidding Phase & Contract Documents $9,000 N:\Projects\WRC \Cler\Design\ Costs

19 Construction Staking, Construction Review & Administration $35,000 Legal Notices, Miscellaneous $1,500 ROW Damages $2,250/ac) $99,000 Reclassification $20,000 Estimated Total Project $1,339,950 Average Assessment DD 131: $1,339,950 /2,120 ac= $ Average Cost Per Acre Over 10 6%: $85.88 per acre per year Secondary Roads Expense 260th Street Crossing $5,900 C-54 Crossing (Bored) $38,000 Keokuk Avenue Crossing $7, th Street Crossing $7,450 Lee Avenue Crossing $8,000 C-60 Crossing $8,000 Total $74,350 N:\Projects\WRC \Cler\Design\ Costs

20 Opinion of Probable Costs Main Tile Improvements DD No. 131 Wright County Dec-13 Option 3B - DD 131 Replacement Tile 1/2" Drainage Coeficient (22,000 ft) item description quantity unit unit cost extension 1. 12" RCP 500 lf $20 $10, " RCP 500 lf $22 $11, " RCP 1,000 lf $24 $24, " RCP 500 lf $26 $13, " RCP 1,000 lf $28 $28, " RCP 1,000 lf $32 $32, " RCP 1,500 lf $36 $54, " RCP 1,000 lf $40 $40, " RCP 1,000 lf $45 $45, " RCP 5,000 lf $52 $260, " RCP 6,800 lf $60 $408, " RCP 2,000 lf $100 $200, Open Ditch Excavation (700 LF) 2,000 cy $4 $8, Headwall 1 ea $22,000 $22, Tile Intake 2 ea $500 $1, Crush and Bury Existing Tile 22,000 lf $2.25 $49, Field Tile Connections 110 ea $200 $22, Locate Existing Tile 24 hr $150 $3, Trench Stabilization Rock 1,100 tn $25 $27, Lateral Connection 2 ea $600 $1, Seeding, Fertilizing, Mulch 6.5 ac $1,500 $9,750 N:\Projects\WRC \Cler\Design\ Costs

21 Total Construction $1,269,550 10% Contingency $126,955 Survey, Records Review, Report & Hearings $10,000 Survey, Plans, Specifications, Bidding Phase & Contract Documents $11,000 Construction Staking, Construction Review & Administration $35,000 Legal Notices, Miscellaneous $1,500 ROW Damages $2,250/ac) $99,000 Open Ditch ROW $7,000/ac) $14,000 Reclassification $20,000 Estimated Total Project $1,587,005 Average Assessment DD 131: $1,587,005 /2,120 ac= $ Average Cost Per Acre Over 10 6%: $ per acre per year Secondary Roads Expense 260th Street Crossing $5,400 C-54 Crossing (Bored) $45,000 Keokuk Avenue Crossing $7, th Street Crossing $8,000 Lee Avenue Crossing $10,600 C-60 Crossing $10,600 Total $87,050 N:\Projects\WRC \Cler\Design\ Costs

22 POSSIBLE PRIVATE TILE OUTSIDE DISTRICT BOUNDARY STA: END TILE IMPROVEMENTS AREA 1 SURFACE DRAINAGE CONCERN DISTRICT BOUNDARY MAIN TILE T LA 2 AREA 2 SURFACE DRAINAGE CONCERN EAGLE GROVE 5 Mi. STA: STA: LAT A STA: LAT B MAIN T ILE LAT 1 STA: 0+00 BEGIN TILE IMPROVEMENTS WHITE FOX CREEK STA: 20+00

Engineer s Report Drainage District #93 Main Tile Improvements Wright County, Iowa MEC Figure 1: Wright County Drainage District #93

Engineer s Report Drainage District #93 Main Tile Improvements Wright County, Iowa MEC Figure 1: Wright County Drainage District #93 April 30, 2015 Board of Supervisors Wright County Courthouse 115 North Main Street Clarion, IA 50525 RE: Engineer s Report Drainage District #93 Main Tile Improvements Wright County, Iowa MEC 1414013 Dear

More information

AGRICULTURAL DRAINAGE

AGRICULTURAL DRAINAGE AGRICULTURAL DRAINAGE ARCHITECTURE + ENGINEERING + True Expertise + Sustainable Solutions ENVIRONMENTAL + PLANNING Facing the Challenges Together With over 40 years of experience, ISG is focused on improving

More information

AGRICULTURAL DRAINAGE

AGRICULTURAL DRAINAGE AGRICULTURAL DRAINAGE ARCHITECTURE + ENGINEERING + ENVIRONMENTAL + PLANNING True Expertise + Sustainable Solutions Facing the Challenges Together With over 40 years of experience, ISG is focused on improving

More information

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

GRASS-LINED CHANNEL (acre) CODE 840

GRASS-LINED CHANNEL (acre) CODE 840 NATURAL RESOURCES CONSERVATION SERVICE ILLINOIS URBAN MANUAL PRACTICE STANDARD GRASS-LINED CHANNEL (acre) CODE 840 (Source: NC Erosion and Sediment Control Field Manual) DEFINITION A natural or constructed

More information

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac) Permit Application No.: 17-181 Rules: Erosion Control, Wetland Protection, and Waterbody Crossings & Structures Applicant: Hennepin County Received: 4/27/17 Project: CSAH 112 Phase II Complete: 9/5/17

More information

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site.

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site. INLET PROTECTION From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.state.ma.us/dep/brp/stormwtr/files/esfull.pdf Definition: A sediment filter or an excavated

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

5/25/2017. Lumpkin Detention Basin Houston, Texas By Brian Whitney, P.E., CFM Victor Rendon. Lumpkin Basin. Lumpkin Road Overall Description

5/25/2017. Lumpkin Detention Basin Houston, Texas By Brian Whitney, P.E., CFM Victor Rendon. Lumpkin Basin. Lumpkin Road Overall Description Lumpkin Detention Basin Houston, Texas By Brian Whitney, P.E., CFM Victor Rendon TEXAS FLOODPLAIN MANAGEMENT ASSOCIATION April 27, 2017 PROJECT LOCATION PROJECT VICINITY MAP Lumpkin Road Overall Description

More information

Anoka County Ditch 53-62, Branch 1 Lateral 1 Repair Memorandum Date: November 2, 2016 Project: R

Anoka County Ditch 53-62, Branch 1 Lateral 1 Repair Memorandum Date: November 2, 2016 Project: R Technical Memorandum To: Cc: From: Phil Belfiori, District Administrator, RCWD Tom Schmidt Mark Deutschman Nancy Stowe, P.E. Through: Chris Otterness, P.E. Subject: Anoka County Ditch 53-62, Branch 1 Lateral

More information

Saturated Buffer. Subsurface Drainage PURPOSE N REDUCTION LOCATION COST BARRIERS

Saturated Buffer. Subsurface Drainage PURPOSE N REDUCTION LOCATION COST BARRIERS Saturated Buffer To intercept tile drainage prior to discharging to surface waters and redistribute the water laterally in the soil profile of the streamside buffer. Subsurface drainage, also known as

More information

Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017

Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017 SPONSOR: Gary Pestorious Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017 REFER TO: 2012-01634-DAS SECTION:404 - Clean Water Act 1. WETLAND COMPENSATORY MITIGATION BANK PROPOSAL: Pickerel Lake

More information

Sheet 2 of 27

Sheet 2 of 27 Sheet 1 of 27 Sheet 2 of 27 Sheet 3 of 27 Sheet 4 of 27 Sheet 5 of 27 INDEX OF PLANS SHEETS Sheet 1 to 5 (Incl.) Sheet 6 Sheet 7 to 9 (Incl.) Sheet 10 Sheet 11 to 13 (Incl.) Sheet 14 Sheet 15 Sheet 16

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Project # Brown County PCN i40h Replace Section Line Road Culvert

Project # Brown County PCN i40h Replace Section Line Road Culvert Project # 010-151 PCN i40h Replace Section Line Road Culvert R 64 W FREDERICK POP. 199 R 63 W R 62 W R 61 W 6 5 4 3 6 5 4 3 1 Dry 402 AVE 102 ST 387 AVE 12 388 AVE 390 AVE 7 8 9 10 11 12 391 AVE 393 AVE

More information

SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004

SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004 SOUTHSIDE TOWNSHIP ROADWAY STANDARDS POLICY Adopted September 7, 2004 General: Sections of the Minnesota Department of Transportation (Mn/DOT), Standard Specification for Construction, 2000 or Current

More information

Old Mill School Stream Restoration

Old Mill School Stream Restoration Project Overview This conceptual plan restores and stabilizes two consecutive reaches of a highly incised and unstable stream and reconnects them with the floodplain. The restoration reaches are part of

More information

If you have any questions, feel free to contact the office of the Planning Commission at

If you have any questions, feel free to contact the office of the Planning Commission at Attention: Enclosed, is an application for a zoning permit for the Townships of Amboy, Franklin, Fulton & York. You may return your application and check made payable to: ZONING FEES Fulton County Regional

More information

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL New Chevrolet and Cadillac Dealership Jasper, AL Andrew Kennedy Homework #6 July 24, 2007 0 Table of Contents Table of

More information

Jacobi, Toombs, and Lanz, Inc.

Jacobi, Toombs, and Lanz, Inc. Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations

More information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage

More information

Master Plan of Storm Drainage for East Garden Grove Wintersburg Channel Tributary Area

Master Plan of Storm Drainage for East Garden Grove Wintersburg Channel Tributary Area CITY OF ANAHEIM Master Plan of Storm Drainage for East Garden Grove Wintersburg Channel Tributary Area JANUARY 2006 VOLUME 1 Table of Contents VOLUME 1 1. Executive Summary... 1 1.1 General... 1 1.2

More information

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads No. 6 December, 1995 Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads Steve Holaday, Wisconsin Dept. of Natural Resources, and Jeff Martin, Dept. of Forestry, UW-Madison BMPs

More information

Guidance Document for Storm Water Pollution Prevention Plan (SWPPP) Submittal. A2 Plat showing building lot numbers/boundaries and road layout/names:

Guidance Document for Storm Water Pollution Prevention Plan (SWPPP) Submittal. A2 Plat showing building lot numbers/boundaries and road layout/names: Exhibit SW12-3 Page 1 of 10 Guidance Document for Storm Water Pollution Prevention Plan SECTION A CONSTRUCTION PLAN ELEMENTS A1 Plan Index showing locations of required items: The plan index should include

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS 12.1 The subdivider shall construct and install the improvements in accordance with the County's Standards for Construction Plans and Specifications

More information

1.2 REGULATORY REQUIREMENTS

1.2 REGULATORY REQUIREMENTS Table 1.1. Soil textural classes and general terminology used in soil descriptions (Source: US Environmental Protection Agency 1977). Name Texture Basic soil textural common class names Sandy soils Coarse

More information

DRAINAGE REPAIR POLICY FOR COUNTY DRAINAGE SYSTEMS. Drainage System No.

DRAINAGE REPAIR POLICY FOR COUNTY DRAINAGE SYSTEMS. Drainage System No. DRAINAGE REPAIR POLICY FOR COUNTY DRAINAGE SYSTEMS Drainage System No. The following policy is intended to supplement Minnesota Statutes Chapter 103E in the Maintenance and Operation of Drainage Systems

More information

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

DRAINAGE & DESIGN OF DRAINAGE SYSTEM Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means

More information

METROPOLITAN UTILITIES DISTRICT No Page: 1 of 10

METROPOLITAN UTILITIES DISTRICT No Page: 1 of 10 Page: 1 of 10 A. GENERAL Erosion control measures such as silt fence, inlet filters and soil stabilization blankets and matting, incorporated into underground pipeline construction projects, help prevent

More information

DRAINAGE BASICS Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements

DRAINAGE BASICS Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements DRAINAGE BASICS 1 Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements 2 Common Terminology & Useful Tools CFS= Cubic Feet per Second-

More information

MINNEHAHA COUNTY HIGHWAY DEPARTMENT CULVERT REPLACEMENT REQUEST FORM

MINNEHAHA COUNTY HIGHWAY DEPARTMENT CULVERT REPLACEMENT REQUEST FORM MINNEHAHA COUNTY HIGHWAY DEPARTMENT CULVERT REPLACEMENT REQUEST FORM Instructions & Background Information (This page to be completed by Township personnel) The purpose of this form is to provide a means

More information

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until

More information

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018)

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018) ADOPTED BY CHOCTAW LAKE BOARD OF TRUSTEES ORIGINAL APPROVAL SEPTEMBER 20, 1990 REVISED AND APPROVED AUGUST 10, 2004, JANUARY 9, 2018 THIS DOCUMENT IS A PART OF THE CLPOA BUILDING CODE CHANGES TO THIS DOCUMENT

More information

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

LAKE COUNTY HYDROLOGY DESIGN STANDARDS LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide

More information

Permit Application: Soil Erosion and Sediment Control Program

Permit Application: Soil Erosion and Sediment Control Program Missaukee Conservation District Soil Erosion and Sediment Control Program 6180 W. Sanborn Road, Suite 3 Lake City, MI 49651 Ph 231.839.7193 Fax 231.839.5411 http://missaukeecd.org/soil-erosion/ kate.nietling@macd.org

More information

DRAINAGE STUDY PHASE 2 REPORT HORRY COUNTY STORMWATER DEPARTMENT HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: APRIL 07, 2016 J

DRAINAGE STUDY PHASE 2 REPORT HORRY COUNTY STORMWATER DEPARTMENT HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: APRIL 07, 2016 J DRAINAGE STUDY PHASE 2 REPORT FOR: HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: HORRY COUNTY STORMWATER DEPARTMENT APRIL 07, 2016 Prepared by: Savannah, GA Charleston, SC Myrtle Beach, SC Brunswick, GA

More information

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES MINNESOTA WETLAND RESTORATION GUIDE BLOCKING AND FILLING SURFACE DRAINAGE DITCHES TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-1 Publication Date: 10/14/2015 Table of Contents Introduction Application

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

Guidance on each of the 23 basic elements follows: Plan Index showing locations of required items: The plan index should include a list of the

Guidance on each of the 23 basic elements follows: Plan Index showing locations of required items: The plan index should include a list of the Guidance on each of the 23 basic elements follows: A1 Plan Index showing locations of required items: The plan index should include a list of the required items in the rule and where they occur in the

More information

BRANDT IMPOUNDMENT OUTLET DITCH ESTABLISHEMENT PRELIMINARY SURVEY REPORT

BRANDT IMPOUNDMENT OUTLET DITCH ESTABLISHEMENT PRELIMINARY SURVEY REPORT BRANDT IMPOUNDMENT OUTLET DITCH ESTABLISHEMENT PRELIMINARY SURVEY REPORT PROPOSED AS: RED LAKE WATERSHED DISTRICT DITCH #15 RLWD Project No. 175 HDR Project No. 186028 Engineering Inc. 324 2nd Street East

More information

Suggested Stormwater Management Practices For Individual House Lots

Suggested Stormwater Management Practices For Individual House Lots Suggested Stormwater Management Practices For Individual House Lots These practices are necessary to satisfy the water quantity and water quality criteria of the Rappahannock Stormwater Ordinance. These

More information

PERMANENT FARMING REQUEST FOR EXEMPTION CONFIRMATION LETTER

PERMANENT FARMING REQUEST FOR EXEMPTION CONFIRMATION LETTER PERMANENT FARMING REQUEST FOR EXEMPTION CONFIRMATION LETTER Subject: File Number: (Assigned by the District) Project Name: County: Section: Township: Range: Total Land Area Owned (acres): Project Area

More information

Town of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /

Town of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) / Town of Friday Harbor PO Box 219 / Friday Harbor / WA / 98250 (360) 378-2810 / fax (360) 378-5339 / www.fridayharbor.org LAND CLEARING, GRADING, OR FILLING PERMIT APPLICATION APPLICATION DATE GRD No. APPLICANT/FRANCHISE

More information

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT August 28, 2017 Please find the following addendum to the below mentioned BID. Addendum No.: 1 Bid#: 416-15-17-53-2 Project Name: Lower W-15 Area

More information

Report for 2001SD1941B: Alternative Conservation Practices to Improve Soil and Water Quality

Report for 2001SD1941B: Alternative Conservation Practices to Improve Soil and Water Quality Report for 2001SD1941B: Alternative Conservation Practices to Improve Soil and Water Quality Other Publications: Kathol, John. 2002. Using a Precipitation-Runoff Model to Predict Runoff for Frequency Based

More information

STATE OF SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION PLANS FOR PROPOSED

STATE OF SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION PLANS FOR PROPOSED STATE OF SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION PLANS FOR PROPOSED PROJECT 000P-151 US HWY 12 DAY COUNTY Construction of New Field Approach PCN i4g8 Sheet 1 of 11 ENVIRONMENTAL COMMITMENTS An Environmental

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT BOWEN PRIVATE INDUSTRY SOLID WASTE DISPOSAL FACILITY (ASH LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals

More information

ITEM 706 PIPE SLOPE DRAIN

ITEM 706 PIPE SLOPE DRAIN AFTER NOVEMBER 1, 2008 ITEM 706 PIPE SLOPE DRAIN 706.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control pipe slope drains, utilized during construction

More information

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1 To: From: The City of Virginia Beach Lewis White and Rachael Johnson on behalf of WSP Date: June 6, 2017 Subject: s Drainage Alternatives Analysis This memorandum represents the summary of findings from

More information

ORDINARY FARMING REQUEST FOR EXEMPTION CONFIRMATION LETTER

ORDINARY FARMING REQUEST FOR EXEMPTION CONFIRMATION LETTER ORDINARY FARMING REQUEST FOR EXEMPTION CONFIRMATION LETTER Subject: File Number: (Assigned by the District) Project Name: County: Section: Township: Range: Total Land Area Owned (acres): Project Area (acres):

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY FOR BIG ROCK CLUSTER SOLAR FARMS PREPARED FOR: Daniel Kolta 90FI 8me LLC & 92JT 8me LLC 211 Sutter Street, Fl. 6 San Francisco, CA. 94108 Prepared 5 15 17 Revised 5 26 17 Revised

More information

Herrington Property Surface Water Issue. Presented to BLLC on Thursday August 6 th, 2009

Herrington Property Surface Water Issue. Presented to BLLC on Thursday August 6 th, 2009 Herrington Property Surface Water Issue Presented to BLLC on Thursday August 6 th, 2009 BRIGHTON LANDFILL SW10 SW1 BRIGHTON LANDFILL SW2 SW4 SW7 SW11 SW6 SW5 SW3 BRIGHTON LANDFILL History of Surface

More information

Stormwater line will be ABOVE ground corrugated pipe (No need to bury) running down to basin on NW 99 th St. It is simple and approved.

Stormwater line will be ABOVE ground corrugated pipe (No need to bury) running down to basin on NW 99 th St. It is simple and approved. Stormwater Drainage: Stormwater line will be ABOVE ground corrugated pipe (No need to bury) running down to basin on NW 99 th St. It is simple and approved. Please see pages 11 and 12 of the document below

More information

Figure Inlet protection (Source: Minnesota DOT)

Figure Inlet protection (Source: Minnesota DOT) 3.9 INLET PROTECTION Figure 3.14. Inlet protection (Source: Minnesota DOT) Overview Description: A manufactured protective device or barrier used to trap sediment at a storm drain surface or curb inlet.

More information

Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI PH. (517) FAX (517)

Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI PH. (517) FAX (517) Date Issued Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI 48854 PH. (517) 676-8395 FAX (517) 676-8364 APPLICATION FOR SOIL EROSION AND SEDIMENTATION POLLUTION

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

STORMWATER AND EROSION CONTROL PERMIT

STORMWATER AND EROSION CONTROL PERMIT STORMWATER MANAGEMENT AND EROSION CONTROL PERMIT INSTRUCTIONS AND INFORMATION Any project that involves the disturbance of ANY quantity of land requires the applicant to receive approval for the project

More information

STORMWATER AND EROSION CONTROL PERMIT

STORMWATER AND EROSION CONTROL PERMIT STORMWATER MANAGEMENT AND EROSION CONTROL PERMIT INSTRUCTIONS AND INFORMATION Any project that involves the disturbance of ANY quantity of land requires the applicant to receive approval for the project

More information

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Model Poultry Burial E&S Plan (7-2-15) 1. GENERAL INFORMATION Name of project Name of person responsible Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Address Phone number Municipality

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

Single Family Residential Construction Erosion/Sediment Control Standards

Single Family Residential Construction Erosion/Sediment Control Standards Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended

More information

Information for File # MVP MHK

Information for File # MVP MHK Information for File # MVP-017-04353-K Applicant: Corps Contact: Town of Brookfield Marie Kopka Address: 50 N. Sunnyslope Road, Suite 96, Brookfield, WI 53005 E-Mail: Phone: (651) 90-5733 Primary County:

More information

Engineering Report Preliminary Floodplain Study. Executive Summary

Engineering Report Preliminary Floodplain Study. Executive Summary Executive Summary Engineering Report Preliminary Floodplain Study The Federal Emergency Management Agency (FEMA) has updated the Flood Insurance Rate Maps (FIRM) for Finney County, including the City of

More information

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm

More information

CUYAHOGA COUNTY ENGINEER

CUYAHOGA COUNTY ENGINEER CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 May 28, 2010 Revisions to the July 29, 2009 edition are noted

More information

PRELIMINARY ENGINEERING REPORT FOR THE GOODRICH DRAIN #0896 PREPARED FOR:

PRELIMINARY ENGINEERING REPORT FOR THE GOODRICH DRAIN #0896 PREPARED FOR: PRELIMINARY ENGINEERING REPORT FOR THE GOODRICH DRAIN #0896 PREPARED FOR: MR. JEFFREY WRIGHT GENESEE COUNTY DRAIN COMMISSIONER GENESEE COUNTY, MICHIGAN PREPARED BY: Fleis & VandenBrink Engineering, Inc.

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions) Adams Co. Conservation District 670 Old Harrisburg Road, Suite 201 Gettysburg, PA 17325 Telephone: 334-0636 Fax: 337-0730 www.adamscounty.us Erosion and Sediment Pollution Control Guidelines for Residential

More information

Memorandum. Creekside Woods I & II Plymouth, MN BCWMC Summary: General Background & Comments. Floodplain

Memorandum. Creekside Woods I & II Plymouth, MN BCWMC Summary: General Background & Comments. Floodplain Memorandum To: Bassett Creek Watershed Management Commission BCWMC June 15, 2017 Meeting Agenda Project: 23270051 2017 2128 4F Creekside Woods I & II Plymouth, MN BCWMC 2017-21 Summary: Proposed Work:

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

Appendix K: Soil Erosion and Sedimentation Control Plan Check List

Appendix K: Soil Erosion and Sedimentation Control Plan Check List Appendix K: Soil Erosion and Sedimentation Control Plan Check List Drain Commissioner 46 February 2005 SOIL EROSION AND SEDIMENTATION CONTROL PLAN CHECK LIST Items listed below must be clearly depicted

More information

2014 WORKSHOP Field Trip 3

2014 WORKSHOP Field Trip 3 2014 WORKSHOP Field Trip 3 This trip visits a RoaDrain geosynthetic drainage material demo, GRS-IBS bridge project, and a completed project from 2011. Site 1 - Laurel Run Road: Recently completed project

More information

Upper Lightning Lake Water Level Management Environmental Assessment Worksheet. Attachment D Design Report for Upper Lightning Lake

Upper Lightning Lake Water Level Management Environmental Assessment Worksheet. Attachment D Design Report for Upper Lightning Lake Upper Lightning Lake Water Level Management Environmental Assessment Worksheet Attachment D Design Report for Upper Lightning Lake DESIGN REPORT for Upper Lightning Lake Wetland Enhancement MN-332-2 I

More information

DRAINAGE PLAN AND REPORT OLD DENVER ROAD

DRAINAGE PLAN AND REPORT OLD DENVER ROAD DRAINAGE PLAN AND REPORT 16140 OLD DENVER ROAD PART OF THE NW1/4 SEC. 28, T.11S., R.67W., 6 th P.M. EL PASO COUNTY February 3, 2017 Revised January 5, 2018 Prepared for All About Outdoor Storage Oliver

More information

ENGINEERING REPORT. Blair Lane to Blairmont Drive Drainage Improvements. PREPARED FOR: City of Lebanon Engineering Department

ENGINEERING REPORT. Blair Lane to Blairmont Drive Drainage Improvements. PREPARED FOR: City of Lebanon Engineering Department engineers planners surveyors environmental scientists landscape architects ENGINEERING REPORT Blair Lane to Blairmont Drive Drainage Improvements PREPARED FOR: City of Lebanon Engineering Department PREPARED

More information

MORENO MASTER DRAINAGE PLAN

MORENO MASTER DRAINAGE PLAN RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT Riverside, California MORENO MASTER DRAINAGE PLAN ZONE FOUR Original Plan September 1980 Revision No. 2 April 2015 WARREN D. WILLIAMS General

More information

STORM DRAINAGE DESIGN CRITERIA

STORM DRAINAGE DESIGN CRITERIA BWM Orig. 01/01/05 Revised 01/01/10 LUCAS COUNTY ENGINEERS OFFICE STORM DRAINAGE DESIGN CRITERIA Drainage The design of storm sewer systems will be based upon the Rational Method using the equation Q=CiA

More information

STORM DRAINAGE DESIGN MANUAL

STORM DRAINAGE DESIGN MANUAL Appendix I STORM DRAINAGE DESIGN MANUAL by: SUNGATE DESIGN GROUP, P.A. GEN ERAL DESIGN STAN DARDS AN D POLICIES 1. STREET AND LOCAL DRAINAGE Discharge estimates for specified design storms shall be calculated

More information

Hey and Associates, Inc.

Hey and Associates, Inc. Hey and Associates, Inc. Table 1: 100-Year Study Existing Conditions Discharges and Elevations vs. FIS Results Location Existing FIS Q (cfs) Existing FIS Elevation Existing XP- SWMM Q (cfs) Existing XP-SWMM

More information

MCLEOD COUNTY JOINT DRAINAGE SYSTEM POLICY AND GUEIDELINES FOR REPAIR

MCLEOD COUNTY JOINT DRAINAGE SYSTEM POLICY AND GUEIDELINES FOR REPAIR MCLEOD COUNTY JOINT DRAINAGE SYSTEM POLICY AND GUEIDELINES FOR REPAIR MEEKER, DISTRICTS 3, 4 and 5 OF MCLEOD, RENVILLE AND SIBLEY COUNTIES The following policy is intended to supplement Minnesota Statutes

More information

Rock Sock (RS) Rock Sock height.

Rock Sock (RS) Rock Sock height. Rock Sock (RS) SC-5 Description A rock sock is constructed of gravel that has been wrapped by wire mesh or a geotextile to form an elongated cylindrical filter. Rock socks are typically used either as

More information

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control

More information

Accessor Parcel Number: Scale: 1 = 10. Figure 1. Plan Overview with Schedules for Windows and Doors

Accessor Parcel Number: Scale: 1 = 10. Figure 1. Plan Overview with Schedules for Windows and Doors Accessor Parcel Number: 057900-0175 Scale: 1 = 10 Figure 1. Plan Overview with Schedules for Windows and Doors City of Seattle Department of Construction and Inspections Issued for Permit Issued By:

More information

CLOCA Rural & Agricultural Guide to Permits

CLOCA Rural & Agricultural Guide to Permits CLOCA Rural & Agricultural Guide to Permits Regulation of Development, Interference with Wetlands and Alterations to Shoreline and Watercourses, Ontario Regulation 42/06 April 2014 Table of contents Introduction...

More information

DRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For:

DRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For: DRAFT Technical Memorandum Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update Prepared For: Pinellas County Department of Environment and Infrastructure Division of Engineering and

More information

IN T R A / M IN T R A M

IN T R A / M IN T R A M SPRING MESA SUBDIVISION CONSTRUCTION PLANS A PART OF SECTION 35, TOWNSHIP 2 SOUTH, RANGELINE 70 WEST, 6th. PRINCIPAL MERIDIAN. CITY OF ARVADA, COUNTY OF JEFFERSON, STATE OF COLORADO COVER SHEET MARTIN

More information

Storm Water Pollution Prevention Plan (SWP3) Checklist

Storm Water Pollution Prevention Plan (SWP3) Checklist . Summit Soil and Water Conservation District Storm Water Pollution Prevention Plan (SWP3) Checklist Modified from the Ohio EPA SWP3 Checklist (Revised January 2017) SITE NAME: REVIEWER: DATE RECEIVED:

More information

COYOTE CREEK 4 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD ID #

COYOTE CREEK 4 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD ID # LOS ANGELES COUNTY, CALIFORNIA NLD ID # 3805010027 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY SEPTEMBER 2012 FINAL RATING: MINIMALLY ACCEPTABLE FINAL RATING DATE: 19 SEPTEMBER 2012 PERIODIC

More information

Jason R. Vogel, Ph.D., P.E. Biosystems and Agricultural Engineering Oklahoma State University

Jason R. Vogel, Ph.D., P.E. Biosystems and Agricultural Engineering Oklahoma State University Stormwater 101 OKLAHOMA STATE UNIVERSITY Biosystems and Agricultural Engineering Department Jason R. Vogel, Ph.D., P.E. Biosystems and Agricultural Engineering Oklahoma State University Stormwater is excess

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Plant Hammond Site Location: Site Address:

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

Calculating System Development Charges for Stormwater Facilities

Calculating System Development Charges for Stormwater Facilities Calculating System Development Charges for Stormwater Facilities Arthur C. Nelson Reprinted with permission from Nelson, Arthur C. 1995. System Development Charges for Water, Wastewater, and Stormwater

More information

Managing Erosion in Vineyard Blocks and Avenues

Managing Erosion in Vineyard Blocks and Avenues Managing Erosion in Vineyard Blocks and Avenues Preventing Erosion and Flow Concentration Managing Concentrated Storm Runoff and Sediment Delivery from Vineyards Evaluating drainage and erosion to comply

More information

Table E-1 SUMMARY OF DESIGN CHANGES AND MITIGATIONS Meadow View Surface Mine Waterloo, New York

Table E-1 SUMMARY OF DESIGN CHANGES AND MITIGATIONS Meadow View Surface Mine Waterloo, New York TABLES Table E-1 SUMMARY OF DESIGN CHANGES AND MITIGATIONS Description of Design Change or Mitigation Design (D) change or Mitigation (M) Section 6-foot-tall vegetated screening berm along Burgess Road,

More information

Warner Robins Stormwater Local Design Manual

Warner Robins Stormwater Local Design Manual Warner Robins Stormwater Local Design Manual Prepared for Houston County City of Warner Robins City of Perry City of Centerville May 17, 2005 Version 4 (As presented with adopted Stormwater Ordinance)

More information

Culverts and Flood Gates

Culverts and Flood Gates 1 of 5 2/15/2011 8:45 AM University of Missouri Extension G1606, Reviewed October 1993 Culverts and Flood Gates C. F. Cromwell, Jr. and Mark Peterson Department of Agricultural Engineering The tables in

More information