1 FOR: Bridge Construction (Structures) ROAD NO.: 345 & 445 BRIDGE SITE NO.: , SUMMARY OF PRICES CONTRACTOR SECTION 1 SECTION 2 BID TOTAL Armcon Ltd 893, ,135, ,029, M.D. Steele Cosntruction Ltd. 1,032, ,287, ,320, Macaw MacDonald Ltd. 1,117, ,233, ,350, Graham Construction & Engineering LP 1,161, ,256, ,417, Coco Paving (Canada) Inc. 1,662, ,957, ,620, Minty's Moving Ltd. 1,428, ,961, ,390, Ver: Page 1

2 SECTION I: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15126 PROJECT NO.: 6743 Armcon Ltd M.D. Steele Cosntruction Ltd. Macaw MacDonald Ltd. Graham Construction & Engineering LP Mobilization of Equipment 1 lump sum 113, , , , , , , , Traffic Control Level II (Mod) 1 lump sum 10, , , , , , , , Supply of Field Office Class "B" (Mod) 1 lump sum 8, , , , , , , , Environmental Management Procedures 1 lump sum 1, , , , , , , , Access Roads and Site Work Roads 1 lump sum 7, , , , , , , , Work Bridges, Work Platforms & Rock Berms 1 lump sum 10, , , , , , , , Water Control 1 lump sum 5, , , , , , Dewatering 1 lump sum 5, , , , , , Cofferdam Construction 1 lump sum 10, , , , , , Dismantle and Salvage of Existing Structure 1 lump sum 7, , , , , , , , Structural Excavation (Mod) 1 lump sum 10, , , , , , , , Supplying Steel H Piles 660 m , , , , Driving Steel H Piles 598 m , , , , Splicing Steel H-pile 20 each , , , , Supply of Pile Tips 20 each , , , , Installation of Pile Tips 20 each , , , , Supply and Fabricate Miscellaneous Metal kg , , , , Placing Miscellaneous Metal kg , , , , Supplying & Placing Granular Backfill 600 t , , , , Supply Bearings 32 each , , , , Placing Bearings 32 each , , Delivery of PP Concrete Girders 16 each , , , , , , Erection of PP Concrete Girders 16 each , , , , , , , Miscellaneous Grouting 1 lump sum 2, , , , , , , , Install Precast Panels 87 m , , , , Lump Sum Backfill 1 lump sum 7, , , , , , , , Supp & Installation of Geotextile Fabric 2730 m , , , , Supplying and Placing Subsurface Drainage 1 lump sum 9, , , , , , , , Removing Asphalt Pavement (Mod) 1560 m , , , , Stone Rip-Rap, Class 350 mm 515 m3 Ver: , , , , Page 2

3 SECTION I: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15126 PROJECT NO.: 6743 Armcon Ltd M.D. Steele Cosntruction Ltd. Macaw MacDonald Ltd. Graham Construction & Engineering LP Granular Base Course Class "A" 2000 t , , , , Stripping Slopes 2 sta , , , , Granular Fill 575 t , , , , Bench Cuts 2 sta , , , , Seeding Using Imported Topsoil (Mod) 4750 m , , , , S/P ECB Cl1, Type Urban Biodegradable (Mod) 4750 m , , , , Supply and Apply Prime Coat (Mod) 1650 L , , , , Bit Pvmt, Cl "B" (Oils Supp. by Cont.) (Mod) 450 t , , , , Connect Guardrail to Bridge 4 each , , Installation of Thrie Beam Guardrail 16 m , , , , Install W Thrie Beam Transition Guardrail 8 m , , , , Installation of W-Beam Guardrail 16 m , , , , Installation of Guardrail End Treatment 4 each 1, , , , , , , , End Drains 0 lump sum Motor Grader 15 h , , , , Hydraulic Excavator 15 h , , , , Wheel Loader 15 h , , , , Removal of Concrete Barriers 160 m , , , , Contingency (formerly Extra Work) 1 $ 100, , , , , , , , , ,032, ,117, ,161, BID TOTAL 3,029, ,320, ,350, ,417, Ver: Page 3

4 SECTION I: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15126 PROJECT NO.: 6743 Coco Paving (Canada) Inc. Minty's Moving Ltd. Mobilization of Equipment 1 lump sum , , Traffic Control Level II (Mod) 1 lump sum , , Supply of Field Office Class "B" (Mod) 1 lump sum , , Environmental Management Procedures 1 lump sum , , Access Roads and Site Work Roads 1 lump sum , , Work Bridges, Work Platforms & Rock Berms 1 lump sum , , Water Control 1 lump sum , , Dewatering 1 lump sum , , Cofferdam Construction 1 lump sum , , Dismantle and Salvage of Existing Structure 1 lump sum , , Structural Excavation (Mod) 1 lump sum , , Supplying Steel H Piles 660 m , , Driving Steel H Piles 598 m , , Splicing Steel H-pile 20 each , , Supply of Pile Tips 20 each , , Installation of Pile Tips 20 each , , Supply and Fabricate Miscellaneous Metal kg , , Placing Miscellaneous Metal kg , , Supplying & Placing Granular Backfill 600 t , , Supply Bearings 32 each , , Placing Bearings 32 each , , Delivery of PP Concrete Girders 16 each , , Erection of PP Concrete Girders 16 each , , Miscellaneous Grouting 1 lump sum , , Install Precast Panels 87 m , , Lump Sum Backfill 1 lump sum , , Supp & Installation of Geotextile Fabric 2730 m , , Supplying and Placing Subsurface Drainage 1 lump sum , , Removing Asphalt Pavement (Mod) 1560 m , , Stone Rip-Rap, Class 350 mm 515 m3 Ver: , , Page 4

5 SECTION I: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15126 PROJECT NO.: 6743 Coco Paving (Canada) Inc. Minty's Moving Ltd. Granular Base Course Class "A" 2000 t , , Stripping Slopes 2 sta , , Granular Fill 575 t , , Bench Cuts 2 sta , , Seeding Using Imported Topsoil (Mod) 4750 m , , S/P ECB Cl1, Type Urban Biodegradable (Mod) 4750 m , , Supply and Apply Prime Coat (Mod) 1650 L , , Bit Pvmt, Cl "B" (Oils Supp. by Cont.) (Mod) 450 t , , Connect Guardrail to Bridge 4 each , Installation of Thrie Beam Guardrail 16 m , , Install W Thrie Beam Transition Guardrail 8 m , , Installation of W-Beam Guardrail 16 m , , Installation of Guardrail End Treatment 4 each , , End Drains 0 lump sum Motor Grader 15 h , , Hydraulic Excavator 15 h , , Wheel Loader 15 h , , Removal of Concrete Barriers 160 m , , Contingency (formerly Extra Work) 1 $ , , ,662, ,428, BID TOTAL 4,620, ,390, Ver: Page 5

6 SECTION II: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15095 PROJECT NO.: 6536 Armcon Ltd M.D. Steele Cosntruction Ltd. Macaw MacDonald Ltd. Graham Construction & Engineering LP Mobilization of Equipment 1 lump sum 154, , , , , , , , Traffic Control Level II (Mod) 1 lump sum 10, , , , , , , , Supply of Field Office Cl "B" (Mod) 1 lump sum 14, , , , , , , , Environmental Management Procedures 1 lump sum 1, , , , , , , , Access Roads and Site Work Roads 1 lump sum 7, , , , , , , , Work Bridges, Work Platforms & Rock Berms 1 lump sum 10, , , , , , , , Water Control 1 lump sum 5, , , , , , , , Dewatering 1 lump sum 5, , , , , , , , Cofferdam Construction 1 lump sum 10, , , , , , , , Structural Excavation (Mod) 1 lump sum 10, , , , , , , , Supplying Steel H Piles 1010 m , , , , Driving Steel H Piles 944 m , , , , Splicing Steel H-pile 28 each , , , , Supply of Pile Tips 28 each , , , , Installation of Pile Tips 28 each , , , , Supply and Fabricate Miscellaneous Metal kg , , , , Placing Miscellaneous Metal kg , , , , Supplying & Placing Granular Backfill 575 t , , , , Supply Bearings 48 each , , , , Placing Bearings 48 each , , , Delivery of PP Concrete Girders 24 each , , , , , , Erection of PP Concrete Girders 24 each 1, , , , , , , , Miscellaneous Grouting 1 lump sum 2, , , , , , , , Install Precast Panels 88 m , , , , Lump Sum Backfill 1 lump sum 7, , , , , , , , Supp & Installation of Geotextile Fabric 4700 m , , , , Supplying and Placing Subsurface Drainage 1 lump sum 9, , , , , , , , Ver: Page 6

7 SECTION II: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15095 PROJECT NO.: 6536 Armcon Ltd M.D. Steele Cosntruction Ltd. Macaw MacDonald Ltd. Graham Construction & Engineering LP Removing Asphalt Pavement (Mod) 3850 m , , , , Stone Rip-Rap, Cl 350 mm 2000 m , , , , Granular Base Course Cl "A" 4750 t , , , , Stripping Slopes 3.6 sta , , , , Granular Fill t , , , , Bench Cuts 3.6 sta , , , , Seeding Using Imported Topsoil (Mod) m , , , , S/P ECB Cl1, Type Urban Biodegradable (Mod) m , , , , Supply and Apply Prime Coat (Mod) 3565 L , , , , Bit Pvmt, Cl "B" (Oils Supp. by Cont.) (Mod) 1075 t , , , , Connect Guardrail to Bridge 4 each , , Installation of Thrie Beam Guardrail 16 m , , , , Install W Thrie Beam Transition Guardrail 8 m , , , Installation of W-Beam Guardrail 16 m , , , , Installation of Guardrail End Treatment 4 each 3, , , , , , , , End Drains 0 lump sum Motor Grader 15 h , , , , Hydraulic Excavator 15 h , , , , Wheel Loader 15 h , , , , Contingency (formerly Extra Work) 1 $ 100, , , , , , , , ,135, ,287, ,233, ,256, BID TOTAL 3,029, ,320, ,350, ,417, Ver: Page 7

8 SECTION II: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15095 PROJECT NO.: 6536 Coco Paving (Canada) Inc. Minty's Moving Ltd. Mobilization of Equipment 1 lump sum , , Traffic Control Level II (Mod) 1 lump sum , , Supply of Field Office Cl "B" (Mod) 1 lump sum , , Environmental Management Procedures 1 lump sum , , Access Roads and Site Work Roads 1 lump sum , , Work Bridges, Work Platforms & Rock Berms 1 lump sum , , Water Control 1 lump sum , , Dewatering 1 lump sum , , Cofferdam Construction 1 lump sum , , Structural Excavation (Mod) 1 lump sum , , Supplying Steel H Piles 1010 m , , Driving Steel H Piles 944 m , , Splicing Steel H-pile 28 each , , Supply of Pile Tips 28 each , , Installation of Pile Tips 28 each , , Supply and Fabricate Miscellaneous Metal kg , , Placing Miscellaneous Metal kg , , Supplying & Placing Granular Backfill 575 t , , Supply Bearings 48 each , , Placing Bearings 48 each , , Delivery of PP Concrete Girders 24 each , , Erection of PP Concrete Girders 24 each , , Miscellaneous Grouting 1 lump sum , , Install Precast Panels 88 m , , Lump Sum Backfill 1 lump sum , , Supp & Installation of Geotextile Fabric 4700 m , , Supplying and Placing Subsurface Drainage 1 lump sum , , Removing Asphalt Pavement (Mod) 3850 m , , Stone Rip-Rap, Cl 350 mm 2000 m , , Granular Base Course Cl "A" 4750 t Ver: , , Page 8

9 SECTION II: Bridge Construction (Structures) ROAD NO.: 345 & 445 REGION 3 LOCATION: Bridge Site No WORK ORDER NO.: F15095 PROJECT NO.: 6536 Coco Paving (Canada) Inc. Minty's Moving Ltd. Stripping Slopes 3.6 sta , , Granular Fill t , ,782, Bench Cuts 3.6 sta , , Seeding Using Imported Topsoil (Mod) m , , S/P ECB Cl1, Type Urban Biodegradable (Mod) m , , Supply and Apply Prime Coat (Mod) 3565 L , , Bit Pvmt, Cl "B" (Oils Supp. by Cont.) (Mod) 1075 t , , Connect Guardrail to Bridge 4 each , Installation of Thrie Beam Guardrail 16 m , , Install W Thrie Beam Transition Guardrail 8 m , , Installation of W-Beam Guardrail 16 m , , Installation of Guardrail End Treatment 4 each , , End Drains 0 lump sum Motor Grader 15 h , , Hydraulic Excavator 15 h , , Wheel Loader 15 h , , Contingency (formerly Extra Work) 1 $ , , ,957, ,961, BID TOTAL 4,620, ,390, Ver: Page 9

APPENDIX I APPENDIX I SAMPLE COST ESTIMATES AND SUMMARY

APPENDIX I APPENDIX I SAMPLE COST ESTIMATES AND SUMMARY APPENDIX I SAMPLE COST ESTIMATES AND SUMMARY May 7, 2002 This page left blank intentionally. May 7, 2002 Preliminary Cost Estimate Summary ESTIMATE TYPE A ABC Consulting Hwy 99:06 ABC Project No. 1234-01-56789

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount CPM Constructors - Freeport, ME $13,984,117.36 Reed & Reed, Inc. - Woolwich, ME $14,883,139.00 Page 1 of 11 CPM Constructors Freeport, ME 201.11 Clearing AC 2.00 10000.00

More information

Lump Sum L.S. (15") EA

Lump Sum L.S. (15) EA Page of 6 ROADWAY ITEMS 000 000000000-N 800 MOBILIZATION Lump Sum L.S. 000 000000000-N 80 CONSTRUCTION SURVEYING 0003 009000000-N SP REINFORCED BRIDGE APPROACH FILL, STATION ************ (5+6.0) 000 0050000000-E

More information

MERCED COUNTY CAMPUS PARKWAY SEGMENT 2

MERCED COUNTY CAMPUS PARKWAY SEGMENT 2 MERCED COUNTY BID LIST CAMPUS PARKWAY SEGMENT 2 CONTRACT 2017191 The bidder must provide unit prices for each bid item listed below, based on the specified unit of measure. The unit price for each item

More information

Federal Project No.: STP-033-2(049)

Federal Project No.: STP-033-2(049) Schedule of Items Page: 2 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING CONSTRUCTION 0030 301 00110 CLRING AND GRUBBING 0040 303 00120 REGULAR EXCAVATION 32,27 0050 302 504 00525 CONCRETE

More information

Taxiways P and P7 Drainage Improvements Re-bid CONTRACT NO ADDENDUM NUMBER ONE

Taxiways P and P7 Drainage Improvements Re-bid CONTRACT NO ADDENDUM NUMBER ONE Department of Aviation Airport Office Building 8500 Peňa Boulevard Denver, Colorado (303) 342-2200 www.flydenver.com March 3, 2015 Taxiways P and P7 Drainage Improvements Re-bid ADDENDUM NUMBER ONE This

More information

Appendix I. Cost Estimate Tables

Appendix I. Cost Estimate Tables Appendix I Cost Estiate Tables CITY OF GUELPH NISKA ROAD IMPROVEMENT CLASS EA ROAD RECONSTRUCTION COST ESTIMATE Ite No. Description Unit Estiated Contract Total Unit Price Quantity Aount PART A -SITE PREPARATION

More information

Bids JANUARY 10, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $29,000,000.00) Miller Bros. Const., Inc. $27,699,031.59

Bids JANUARY 10, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $29,000,000.00) Miller Bros. Const., Inc. $27,699,031.59 General Info Number: PROJECT NO. 43-19-07 Description: BRIDGE REHABILITATION AND 3RD LANE WIDENING OHIO TURNPIKE OVER AI CREEK M.P. 47.4, OHIO TURNPIKE OVER S.R. 64 (N. MAIN ST.) M.P. 47.5 MILEPOST 46.50

More information

Division 1. Form of Tender

Division 1. Form of Tender Division 1 Form of Tender Essex-Windsor Solid Waste Authority Page 1 ESSEX-WINDSOR SOLID WASTE AUTHORITY TENDER FOR CONTRACT NO. 8 TENDER CLOSING DATE April 20, 2018 at 12:00 noon (Local Time) TENDER FOR

More information

1. FROM (Bidder): (Name)

1. FROM (Bidder): (Name) Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3

More information

FEBRUARY 13, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $9,000,000.00) Bids. Kokosing Construction Company, Inc. $8,623,609.96

FEBRUARY 13, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $9,000,000.00) Bids. Kokosing Construction Company, Inc. $8,623,609.96 General Info Number: PROJECT NO. 43-19-02 Description: BRIDGE DECK REPAIR AND REHABILITATION OHIO TURNPIKE OVER ABANDONED RAILROAD M.P. 34.2, OHIO TURNPIKE OVER STATE ROUTE 108 M.P. 34.5, COUNTY ROUTE

More information

MAINE DEPARTMENT OF TRANSPORTATION BID DATE OF OPENING : CALL ORDER : CONTRACT ID : PROJECTS STP-1277(700)S

MAINE DEPARTMENT OF TRANSPORTATION BID DATE OF OPENING : CALL ORDER : CONTRACT ID : PROJECTS STP-1277(700)S MAINE DEPARTMENT OF TRANSPORTATION BID DATE OF OPENING : CALL ORDER : CONTRACT ID : 012777.00 PROJECTS ------------------------------ STP-1277(700)S COUNTY : ANDROSCOGGIN CONTRACT ID : 012777.00 MAINE

More information

3Bureau of Construction and Maintenance

3Bureau of Construction and Maintenance Promptly sign and date on the line below, then EMAIL IT BACK TO KDOT, EVEN IF NOT BIDDING. Or you may still FAX IT TO the Estimating Section at (785) 296-0999. Any instructions not followed will result

More information

Proposer shall make note of and/or incorporate all changes listed below into the requested

Proposer shall make note of and/or incorporate all changes listed below into the requested Request for Proposal (RFP) Bid No: 18-10-1940LE Addendum No. 4 Date: November 27, 2018 To: All Proposers Subject: Addendum No. 4 Consisting of nine (9) Pages RFP No.: Project Name: Owner: 18-10-1940LE

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018

ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018 CBBEL PROJECT NO. 02-0065.H0226 ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018 Modification No. 1 In regards to the COBBLESTONE PAVERS specification,

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount Wyman & Simpson Inc. - Richmond, ME $3,379,844.00 Scott Construction Corporation - Portland, ME $3,572,184.50 CPM Constructors - Freeport, ME $3,732,667.25 Page 1 of 16 Wyman

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 07/10/17 Comp. Dt:

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 07/10/17 Comp. Dt: Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 1213-12 Contract ID: Contract Description: Contract Location: Recommendation: 170022 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

General Info Number: PROJECT NO Description: REPAIRS AND RESURFACING INTERCHANGE 209 MILEPOST TRUMBULL COUNTY, OHIO

General Info Number: PROJECT NO Description: REPAIRS AND RESURFACING INTERCHANGE 209 MILEPOST TRUMBULL COUNTY, OHIO General Info Number: PROJECT NO. 59-18-03 Description: REPAIRS AND RESURFACING INTERCHANGE 209 MILEPOST 209.20 TRUMBULL COUNTY, OHIO Deadline: April 25, 2018 at 2:00 P.M. (Eastern) (Estimated Cost: $3,100,000.00)

More information

MAY 11, 2017 T-MC-107A & T-MC-107B1

MAY 11, 2017 T-MC-107A & T-MC-107B1 Schedule of Bid Items - Part A ROADWAY 107A 201(A) - CLEARING AND GRUBBING - LSUM 1.00 30,000.00 30,000.00 $100,000.00 $100,000.00 $65,000.00 $65,000.00 $120,000.00 $120,000.00 $50,000.00 $50,000.00 $18,262.05

More information

ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS

ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2016138 TRACS No. Project No. County District Gross

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

Whatcom County Bid ADDENDUM NO. 2 West Badger Road / Bertrand Creek Bridge #50 Replacement CRP Federal Aid BRS-2037(107)

Whatcom County Bid ADDENDUM NO. 2 West Badger Road / Bertrand Creek Bridge #50 Replacement CRP Federal Aid BRS-2037(107) WHATCOM COUNTY ADMINISTRATIVE SERVICES DEPARTMENT FINANCE/ACCOUNTING Whatcom County Courthouse 311 Grand Avenue, Suite #503 Bellingham WA 98225-4082 Brad Bennett, Finance Manager March 19, 2019 Whatcom

More information

TENDER WELLCOX ACCESS ROAD ADDENDUM 1

TENDER WELLCOX ACCESS ROAD ADDENDUM 1 TENDER 2336-2019 WELLCOX ACCESS ROAD ADDENDUM 1 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2336-2019. Revisions supersede the information

More information

ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007

ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007 ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007 Sheet 1 of 7 GENERAL The Kansas Department of Transportation STANDARD SPECIFICATIONS FOR STATE ROAD AND

More information

Federal Project No.: NONE

Federal Project No.: NONE Schedule of Items Page: 2 0001 BASE BID- STA. 10+00-23+00 0010 513 00100 0020 517 00101 MOBILIZATION LUMP SUM LUMP SUM CONSTRUCTION SURVEYING (CONSTRUCTION) 0030 301 00110 LUMP SUM LUMP SUM CLRING AND

More information

Federal Project No.: NHPP-BR01(335)

Federal Project No.: NHPP-BR01(335) Order : N46 Schedule of Items Page: 2 Oversight/State Project : 0081-086-793, C501, B660, B661 Federal Project : NHPP-BR01(335) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION)

More information

DECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids

DECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids General Info Number: PROJECT NO. 43-17-04 : BRIDGE DECK REPAIR AND BRIDGE REMOVAL OHIO TURNPIKE OVER QUARRY ROAD, M.P. 138.0 OHIO TURNPIKE OVER INACTIVE RAILROAD, M.P. 138.2 LORAIN COUNTY, OHIO Deadline:

More information

Virginia Department of Transportation. Tabulation of Bids. Counties: REPLACE SUPERSTRUCTURE OVER NORFOLK SOUTHERN RR

Virginia Department of Transportation. Tabulation of Bids. Counties: REPLACE SUPERSTRUCTURE OVER NORFOLK SOUTHERN RR Page 1 of 14 0010 00100 MOBILIZATION 0020 00101 CONSTRUCTION SURVEYING (CONSTRUCTION) 0030 00110 CLEARING AND GRUBBING 0040 00120 REGULAR EXCAVATION 0050 00126 EARTHWORK 0060 00140 BORROW EXCAVATION ACRE

More information

OKLAHOMA TURNPIKE AUTHORITY JUNE 7, 2018 SCHEDULE OF BID ITEMS EOC JP 26422(10) INTERCHANGE AT I-40

OKLAHOMA TURNPIKE AUTHORITY JUNE 7, 2018 SCHEDULE OF BID ITEMS EOC JP 26422(10) INTERCHANGE AT I-40 PART A - ROADWAY - EOC 2461 201(A) CLEARING AND GRUBBING LSUM 1.00 $500,000.00 $500,000.00 202(A) UNCLASSIFIED EXCAVATION CY 651,706.00 $4.00 $2,606,824.00 202(D) UNCLASSIFIED BORROW CY 7,500.00 $8.00

More information

ITEM QUANTITY UNITS UNIT PRICE AMOUNT. Contractor Construction Staking 1.0 Lump Sum

ITEM QUANTITY UNITS UNIT PRICE AMOUNT. Contractor Construction Staking 1.0 Lump Sum KTA Contract No. 5677 KANSAS TURNPIKE AUTHORITY ALT 1 Schedule of Prices Contract No. 5677 County Leavenworth Type of Work: Remove and reconstruct Bridge 221.542 (120'-170'-170'-120' Weathering Steel Spans).

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

Maine Turnpike Authority

Maine Turnpike Authority PAVEMENT REHABILITATION & CLEAR ZONE IMPROVEMENTS MM 80.7 TO MM 88.6 202.121 Removing Existing Concrete (6CY) 1.00 LS 202.127 Removing of Existing Bituminous Pavement (470 SY) 1.00 LS 202.202 Removing

More information

Federal Project No.: STP-5162 (108)

Federal Project No.: STP-5162 (108) Order : N80 Schedule of Items Page: 2 Oversight/State Project : (NFO) 0029-162-270, C501, B601 Federal Project : STP-5162 (108) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING CONSTRUCTION

More information

Contractor Construction Staking 1.0 Lump Sum. Granular Backfill (Wingwalls) (Set Price) 1.0 Cu.Yds $50.00 $ Mobilization 1.

Contractor Construction Staking 1.0 Lump Sum. Granular Backfill (Wingwalls) (Set Price) 1.0 Cu.Yds $50.00 $ Mobilization 1. KTA Contract No. 5677 KANSAS TURNPIKE AUTHORITY ALT 1 Schedule of Prices Contract No. 5677 County Leavenworth Type of Work: Remove and reconstruct Bridge 221.542 (120'-170'-170'-120' Weathering Steel Spans).

More information

The Regional Municipality of Peel Basis of Payment

The Regional Municipality of Peel Basis of Payment Page PS-1 THE REGIONAL MUNICIPALITY OF PEEL BASIS OF PAYMENT FOR SANITARY SEWER CONSTRUCTION Page PS-2 INDEX Page No. PS.1. EXCAVATION...4 1.1. Trench Excavation...4 1.2. Asphalt/Concrete Removal...5 PS.2.

More information

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION Edition

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION Edition CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION PURPOSE, INTENT AND INTERPRETATION OF SPECIFICATIONS The purpose of these Specifications is to establish, where applicable, minimum acceptable standards

More information

Kansas Department of Transportation DISTRICT 1. Project(s): 089 U / HSIP-U231(701) Min: Max:

Kansas Department of Transportation DISTRICT 1. Project(s): 089 U / HSIP-U231(701) Min: Max: Page 1 of 18 SECTION: 01 COMMON ITEMS 1 025323 MOBILIZATION 2 070626 MOBILIZATION (DBE) 3 025600 FIELD OFFICE AND LABORATORY (TYPE A) 4 012340 FOUNDATION STABILIZATION (SET PRICE) 5 020100 CONTRACTOR CONSTRUCTION

More information

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations. Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet

More information

Significant Changes. 101 Definitions and Terms. 102 Bidding Requirements and Conditions 105 Control of Work

Significant Changes. 101 Definitions and Terms. 102 Bidding Requirements and Conditions 105 Control of Work 1 SIGNIFICANT CHANGES IN CDOT's 2017 STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION The following are significant changes from the 2011 Standard Specifications Book to the new 2017 Standard Specifications

More information

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) 0002.0001 Structural Standard Drawings - Layering Structure n/a Aug 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details n/a Jun 2002 Jul

More information

ADDENDUM #2 - MARCH 16, 2012 CONTRACT ENG FAIRBANK LAKE ROAD (M.R.4) IMPROVEMENTS Hwy 17W to C Johnson Rd

ADDENDUM #2 - MARCH 16, 2012 CONTRACT ENG FAIRBANK LAKE ROAD (M.R.4) IMPROVEMENTS Hwy 17W to C Johnson Rd ADDENDUM #2 - MARCH 16, 2012 CONTRACT ENG 12-19 FAIRBANK LAKE ROAD (M.R.4) IMPROVEMENTS Hwy 17W to C Johnson Rd This Addendum shall form an integral part of the plans and specifications for the above mentioned

More information

ADVERTISEMENT SET DECEMBER 2013

ADVERTISEMENT SET DECEMBER 2013 Sheet List Table GREELEY CANAL #2 WCR 21 PROJECT AREA N SH-392 ADVERTISEMENT SET DECEMBER 2013 LINE DESCRIPTION PROPOSED LINE POWER / COMMUNICATIONS EXISTING LINE LINE DESCRIPTION PROPOSED LINE BOUNDARY

More information

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B401: DELETED B402: DELETED B403: DELETED B404: STRUCTURE/CULVERT IDENTIFICATION SIGNS B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B406: ITEM 514 - FIELD PAINTING, MISC.; REPAIR PAINTING

More information

CONTRACT ID : COMPLETION DATE : 09/15/08 =========

CONTRACT ID : COMPLETION DATE : 09/15/08 ========= PAGE : 1 COMPLETION DATE : 09/15/08 PROJECT(S): ER-1453(310)X LOCATION(S): YORK, CULVERT REPLACEMENT MAINE STATE DEPARTMENT OF TRANSPORTATION A TRUE COPY : TITLE : ATTEST : CONTRACT DESCRIPTION : YORK,

More information

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount CPM Constructors - Freeport, ME $1,417,760.75 Scott Construction - Falmouth, ME $1,418,884.50 T Buck Construction - Auburn, ME $1,520,203.00 Page 1 of 16 CPM Constructors

More information

Kansas Department of Transportation Bureau of Construction and Maintenance Estimating Section

Kansas Department of Transportation Bureau of Construction and Maintenance Estimating Section Promptly sign and date on the line below, then EMAIL IT BACK TO KDOT, EVEN IF NOT BIDDING. Or you may still FAX IT TO the Estimating Section at (785) 296-0999. Any instructions not followed will result

More information

Automated Machine Guidance

Automated Machine Guidance House Select Committee on Strategic Planning and Long Term Funding Solutions October 24, 2016 Automated Machine Guidance Lamar Sylvester, PE State Construction Engineer Automated Machine Guidance (AMG)

More information

Milestones: September 4 NTP

Milestones: September 4 NTP September September 30, 2018 : Mobilization to site Install Erosion Control Early shop drawing review Material Procurement o Obermeyer Gates o Rip Rap & Boulders o Pedestrian Bridges o Rapid Blocks o Debris

More information

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS ... m NOISE BARRIER - Item No.... m NOISE BARRIER INCLUDING PRECAST NOISE/TRAFFIC BARRIER - Item No.... m NOISE BARRIER ON STRUCTURES - Item No.... m SALVAGEABLE NOISE BARRIER - Item No.... m SALVAGEABLE

More information

ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007

ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007 ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007 07-ER-1-R18 Sheet 1 of 10 GENERAL The Kansas Department of Transportation STANDARD SPECIFICATIONS FOR STATE

More information

ANSWERS TO QUESTIONS RECEIVED THROUGH 12:00 PM ON MAY 15, 2018:

ANSWERS TO QUESTIONS RECEIVED THROUGH 12:00 PM ON MAY 15, 2018: ADDENDUM NO. PROJECT NO. 3-8-0 PAGE ANSWERS TO QUESTIONS RECEIVED THROUGH :00 PM ON MAY 5, 08: Q# PBQs regarding Project 3-8-0: Reference 3 Concrete Walk is,870 SQ YD in the Bid Express file. The quantity

More information

Ohio Department of Transportation - Prebid Questions

Ohio Department of Transportation - Prebid Questions Project No. 110467 Sale Date - 8/25/2011 HAM-83469 - CR-CR 239-9.49 (WINTON/ S. GILMORE ROAD) 8/22/2011 9:56:54 AM Pole E on plan page 323 shows that 2" anchor bolts should be used for this pole. However,

More information

KEY MAP - SCALE 1:1,500,000 NOTE 1. SLIDE FEATURES RECORDED USING A HAND HELD GPS. SLIDE MOVEMENT DIRECTION 2014 PH26 INSPECTION PLAN

KEY MAP - SCALE 1:1,500,000 NOTE 1. SLIDE FEATURES RECORDED USING A HAND HELD GPS. SLIDE MOVEMENT DIRECTION 2014 PH26 INSPECTION PLAN Z:\\-1-305\\-1-305_PH2-1.dwg - 2-1 - Dec., KEY MAP - 1:1,500,000 NOTE 1. SLIDE FEATURES RECORDED USING A HAND HELD GPS. SLIDE MOVEMENT DIRECTION TEST HOLE LOCATIONS 0 40 0 0 m 1:00 PH2 INSPECTION PLAN

More information

SHOULDER DETAIL CONCRETE CURB SHOULDER DETAIL ASPHALT CURB SHOULDER DETAIL PAVEMENT JOINT DETAIL PAVEMENT JOINT DETAIL NORMAL SECTION COMMON AND ASPHALT ALTERNATE NOTES ITEM LEGEND EX. ITEM LEGEND CONCRETE

More information

ADDENDUM #3. STATE ROUTE 60 AT POTRERO BOULEVARD INTERCHANGE PHASE I AND IA City Project No ; Federal Project No.

ADDENDUM #3. STATE ROUTE 60 AT POTRERO BOULEVARD INTERCHANGE PHASE I AND IA City Project No ; Federal Project No. ADDENDUM #3 STATE ROUTE 60 AT POTRERO BOULEVARD INTERCHANGE PHASE I AND IA City Project No. 2016-003; Federal Project No. DEM10L-5209(008) November 9, 2017 Addendum for: AND IA STATE ROUTE 60 AT POTRERO

More information

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT August 23, 2018 Please find the following addendum to the below mentioned BID. Addendum No.: 1 Bid#: 312-00-18-30-2 Project Name: 2018 District 12

More information

3.0 TEMPORARY DETOUR BRIDGES

3.0 TEMPORARY DETOUR BRIDGES 3.0 TEMPORARY DETOUR BRIDGES Table of Contents 3.1 General...1 3.2 STORAGE SITES:...2 3.3 BID ITEMS:...2 3.4 INDEX OF PLAN SHEETS with H-Pile:...3 3.5 INVENTORY SHEET FOR DETOUR BRIDGES WITH H-PILE:...4

More information

I2-0 LIST OF ACTIVE SSDs

I2-0 LIST OF ACTIVE SSDs I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006

More information

PROPOSAL KITSAP COUNTY DEPARTMENT OF PUBLIC WORKS COUNTY ROAD PROJECT NO NW Golf Club Hill Road Culvert Replacement To the Honorable Board of Co

PROPOSAL KITSAP COUNTY DEPARTMENT OF PUBLIC WORKS COUNTY ROAD PROJECT NO NW Golf Club Hill Road Culvert Replacement To the Honorable Board of Co PROPOSAL KITSAP COUNTY DEPARTMENT OF PUBLIC WORKS COUNTY ROAD PROJECT NO. 3690 NW Golf Club Hill Road Culvert Replacement To the Honorable Board of Commissioners Kitsap County 614 Division Street Port

More information

Kansas Department of Transportation DISTRICT 5. Project(s): Min: Max:

Kansas Department of Transportation DISTRICT 5. Project(s): Min: Max: Page 1 of 11 518105 SECTION: 01 COMMON ITEMS 1 020100 CONTRACTOR CONSTRUCTION STAKING 2 025603 FIELD OFFICE 3 025323 MOBILIZATION 4 070626 MOBILIZATION (DBE) 5 025200 REMOVAL OF EXISTING STRUCTURES 6 012340

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2017.02 Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5 The following changes are made to the Proposal, Specifications and Plans: SPECIFICATIONS:

More information

B512 - GABIONS - OPSS 512

B512 - GABIONS - OPSS 512 B512 - - OPSS 512 512.1 GENERAL Gabions are contained rectangular units made of steel wire mesh and filled with stone. The double twisted wire mesh is galvanized and PVC (polyvinyl chloride) coated. Gabions

More information

Alberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.

Alberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges. STANDARD BRIDGE & CULVERT COMPONENTS Alberta Bridge Inventory In Alberta there are about 13,300 bridges. Types of bridges in Alberta: Standard bridges 3521 (26%) Bridge size culverts 8348 (63%) Major bridges

More information

3Bureau of Construction and Maintenance

3Bureau of Construction and Maintenance Promptly sign and date on the line below, then EMAIL IT BACK TO KDOT, EVEN IF NOT BIDDING. Or you may still FAX IT TO the Estimating Section at (785) 296-0999. Any instructions not followed will result

More information

Thank you for your response to our Request for Bid submissions. The following is a summary of the submitted bids for this project.

Thank you for your response to our Request for Bid submissions. The following is a summary of the submitted bids for this project. Thank you for your response to our Request for Bid submissions. The following is a summary of the submitted bids for this project. 1. PARKING LOT PHASE (PLP) PL - 1 Obtain Building Permit (including permit

More information

10:00 AM, Wednesday, May 6, Peters Creek Sanitary Sewer Rehabilitation Project

10:00 AM, Wednesday, May 6, Peters Creek Sanitary Sewer Rehabilitation Project NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, May 6, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference

More information

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS ... m NOISE BARRIER - Item No.... m NOISE BARRIER INCLUDING PRECAST NOISE/TRAFFIC BARRIER - Item No.... m NOISE BARRIER ON STRUCTURES - Item No.... m SALVAGEABLE NOISE BARRIER - Item No.... m SALVAGEABLE

More information

Table of Contents. Chapter 1 : Introduction 1. Chapter 2 : Structure and design 15

Table of Contents. Chapter 1 : Introduction 1. Chapter 2 : Structure and design 15 Table of Contents Chapter 1 : Introduction 1 1-1 Overview of Japan 1 1-1-1 Topography 1 1-1-2 Climate 1 1-1-3 Population 3 1-1-4 Economy 3 1-2 History and current status of roads in Japan 5 1-2-1 Road

More information

Invitation to Tender No. T170523EN. lump sum $ days $1,500 $ ha 0.4 $ $ m 3 18,000 $ $ m 3 31,000 $ $ m 3 1,175 $ $ m 130 $ $ t 210 $ $

Invitation to Tender No. T170523EN. lump sum $ days $1,500 $ ha 0.4 $ $ m 3 18,000 $ $ m 3 31,000 $ $ m 3 1,175 $ $ m 130 $ $ t 210 $ $ Addendum No. 1 TOWNSHIP ROAD 510 RECONSTRUCTION Invitation to Tender No. T170523EN Amendment 1. Bidders shall note the following: a) Revised Section 3.3.2 Unit Price Table : REVISED Schedule A : Invitation

More information

Minimum Sample and Test Requirements (MSTR)

Minimum Sample and Test Requirements (MSTR) South Dakota Department of Transportation Minimum Sample and Test Requirements (MSTR) Table of Contents Page 1. Asphalt Construction:... 1 1.1 Asphalt Concrete, Hot Mix... 3 A. Aggregate, Composite...

More information

BASE BID FORM FY 2015

BASE BID FORM FY 2015 BASE BID FORM FY 2015 STORMWATER TREATMENT AREA - BASE BID (FY2015) THE LUMP SUM (LS) PRICES FOR ITEMS 1-6 SHALL BE DONE IN ACCORDANCE WITH THE CONTRACT DOCUMENTS AND SPECIFICATIONS AND ALL APPLICABLE

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 04/03/17 Comp. Dt: 10/06/17

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 04/03/17 Comp. Dt: 10/06/17 Letting: 17030200 Letting Dt: March 02, 2017 9:30 A.M. State Proj.: 6216-127 Contract ID: Contract Description: Contract Location: Recommendation: 170023 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

All Bidders of Record Stephen Diglio, P.E., KAS Inc. Nanette Rogers, Brent Meacham, Town of Westford

All Bidders of Record Stephen Diglio, P.E., KAS Inc. Nanette Rogers, Brent Meacham, Town of Westford Seymour Road Replacement Bridge Addendum #1 April 27, 2015 To: From: Cc: All Bidders of Record Stephen Diglio, P.E., KAS Inc. Nanette Rogers, Brent Meacham, Town of Westford RE: Construction Bid Information

More information

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # 2016-04 PROJECT SPECIFICATIONS TABLE OF CONTENTS SECTION 100 GENERAL... 1 SECTION 200 MATERIALS... 1 CONSTRUCTION METHODS... 1 SECTION

More information

SECTION 500 STRUCTURES

SECTION 500 STRUCTURES SECTION 500 STRUCTURES 500.1 GENERAL This section defines the various construction items that are associated with the completion of a concrete, steel, timber, or masonry unit structures, or a combination

More information

Index to Technical Specifications

Index to Technical Specifications Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 01 29 00 PAYMENT PROCEDURES PART 1 GENERAL 1.01 SECTION INCLUDES A. For each BID item, the WORK will be measured and paid for on either a unit price basis or on a lump sum basis. The quantities

More information

Item No. Description Unit Quantity Rate (EUR) Amount (EUR) No 2

Item No. Description Unit Quantity Rate (EUR) Amount (EUR) No 2 BILL NO.1 : PRELIMINARY AND SUPERVISORY SERVICES 1.01 Allow a prime cost sum for material testing to be spent in whole or part as directed by the Resident Engineer. PC Sum 1 1,351.35 1,351.35 1.02 Contractor's

More information

Kansas Department of Transportation DISTRICT TE / TA-T045 (501) Project(s): Min: Max:

Kansas Department of Transportation DISTRICT TE / TA-T045 (501) Project(s): Min: Max: Page 1 of 11 SECTION: 01 COMMON ITEMS 1 020100 CONTRACTOR CONSTRUCTION STAKING 2 025600 FIELD OFFICE AND LABORATORY (TYPE A) 3 025323 MOBILIZATION 4 070626 MOBILIZATION (DBE) 5 025200 REMOVAL OF EXISTING

More information

Ministry of Forests, Lands and Natural Resource Operations

Ministry of Forests, Lands and Natural Resource Operations Ministry of Forests, Lands and Natural Resource Operations Southern Engineering Group N2-38 FINDLAY CREEK FINDLAY-LAVINGTON FSR 12.6km SITE INFORMATION N SITE No. N2-38 STRUCTURE No. N2-38A FSR NAME &

More information

February Page 1

February Page 1 February 2017 - Page 1 CHAPTER 1 LOCATED ON. This section is revised as shown in the highlight below The description of the project location should reflect the beginning and ending location of the project.

More information

Introduction to the Guidance on Measuring and Pricing

Introduction to the Guidance on Measuring and Pricing Introduction to the Guidance on Measuring and Pricing October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing and improving

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.03 EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 The bid opening date is Thursday February 15, 2018 at 11:00 a.m. The following changes are made

More information

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17 S&L Gravel, Section B: Proposal Page 10701.0 - TRAFFIC CONTROL - LUMP SUM 1.00 $6,425.00 $6,425.00 $6,425.00 $10,000.00 10720.0 - TRAFFIC CONTROL SIGN - PORTABLE ARROW BOARD - DAYS 25.00 $25.00 $625.00

More information

Final Estimates Level 2

Final Estimates Level 2 Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure

More information

PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR

PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR 99.0 PUBLIC AND PRIVATE IMPROVEMENTS CODE 99.0 PUBLIC AND PRIVATE IMPROVEMENTS CODE OF THE TOWNSHIP OF UPPER ST. CLAIR TABLE OF CONTENTS 99.1. ADMINISTRATION AND GENERAL REGULATIONS...2 99.1.1. Title...2

More information

Civil Engineering Operations (Construction) v6

Civil Engineering Operations (Construction) v6 Qualification : NVQ Diploma in Construction and Civil Engineering Operations (Construction) v6 Pathway 1: NVQ Diploma in Construction Operations (Modular Pavement Construction) Pathway : NVQ Diploma in

More information

ANSWERS TO QUESTIONS RECEIVED THROUGH 11:00 A.M. ON JANUARY 4, 2019:

ANSWERS TO QUESTIONS RECEIVED THROUGH 11:00 A.M. ON JANUARY 4, 2019: ADDENDUM NO. PROJECT NO. 3-9-07 PAGE 2 ANSWERS TO QUESTIONS RECEIVED THROUGH :00 A.M. ON JANUARY, 209: Q# Plan sheet 2 has a note MAINTENANCE OF TRAFFIC (LOCAL ROADS) which relates to bid item 22 and calls

More information

CITY OF GUELPH CONTRACT NO SUPPLEMENTAL SPECIAL PROVISIONS

CITY OF GUELPH CONTRACT NO SUPPLEMENTAL SPECIAL PROVISIONS CITY OF GUELPH CONTRACT NO. 2-1306 SUPPLEMENTAL SPECIAL PROVISIONS INDEX Contents 1. EXTERNAL CONTRACT DOCUMENTS AND DRAWINGS... 1 2. GENERAL INFORMATION... 4 3. UTILITY COORDINATION, TRAFFIC AND PEDESTRIAN

More information

PRELIMINARY ROADWORKS COST ESTIMATE

PRELIMINARY ROADWORKS COST ESTIMATE PRELIMINARY ROADWORKS COST ESTIMATE Project Title : Glounthaune Village Improvement Scheme Client : O Mahony Developments Ltd Date : February 208 From O' Mahony Development Ltd Entrance to Glounthaune

More information

Unit Price Averages Reports

Unit Price Averages Reports Unit Price Averages Reports Disclaimer The information provided in this File is only for the use of Alberta Infrastructure & Transportation staff and its Consultants for the development of construction

More information

For Addendum No. 6 Revised Bid Form Page 1 of 7. Revised Bid Form

For Addendum No. 6 Revised Bid Form Page 1 of 7. Revised Bid Form For Addendum No. 6 Revised Bid Form Page 1 of 7 Revised Bid Form Deliver bid to: CITY OF FREDERICK PURCHASING DEPARTMENT 111 AIRPORT DRIVE EAST FREDERICK MARYLAND 21701 CITY OF FREDERICK WWTP ENR UPGRADE

More information

CITY AND COUNTY OF DENVER

CITY AND COUNTY OF DENVER 2-1.1b REMOVE COMBINATION CONCRETE CURB, GUTTER AND SIDEWALK (3'-11") 2-1.2a REMOVE 6" CONCRETE CURB AND/OR GUTTER S Holly: See near STA: 25+56 S Poplar 300 LF 25 LF 2-1.4 REMOVE HANDICAP CONCRETE CURB

More information