PHASE III REMEDIAL ACTION PLAN (PHASE III RAP) 350 IRVING STREET FRAMINGHAM, MASSACHUSETTS. PREPARED FOR: NSTAR Gas Company Boston, Massachusetts

Size: px
Start display at page:

Download "PHASE III REMEDIAL ACTION PLAN (PHASE III RAP) 350 IRVING STREET FRAMINGHAM, MASSACHUSETTS. PREPARED FOR: NSTAR Gas Company Boston, Massachusetts"

Transcription

1 PHASE III REMEDIAL ACTION PLAN (PHASE III RAP) 350 IRVING STREET FRAMINGHAM, MASSACHUSETTS PREPARED FOR: NSTAR Gas Company Boston, Massachusetts PREPARED BY: GZA GeoEnvironmental, Inc. Norwood, Massachusetts January 2009 File No Copyright 2009 GZA GeoEnvironmental, Inc.

2

3 TABLE OF CONTENTS Page 1.00 INTRODUCTION OBJECTIVES AND SCOPE OF THE PHASE III RAP ORGANIZATION OF DOCUMENT BACKGROUND SITE DESCRIPTION SITE HISTORY MCP COMPLIANCE HISTORY Immediate Response Action, October Phase II Comprehensive Site Assessment, October REMEDIAL OBJECTIVES RESPONSE ACTION OUTCOMES Permanent Solution Temporary Solution DEVELOPMENT OF REMEDIAL ALTERNATIVES NO FURTHER ACTION INSTITUTIONAL CONTROLS INITIAL SCREENING OF SOIL AND NAPL REMEDIAL TECHNOLOGIES Natural Attenuation Containment Technologies In-Situ Technologies In-Situ Physical/Chemical Technologies In-Situ Biological Treatment In-Situ Thermal Treatment Excavation and Off-Site Disposal 19

4 TABLE OF CONTENTS (continued) Page Ex-Situ Treatment Technologies and Off-Site Disposal Options INITIAL SCREENING OF GROUNDWATER REMEDIAL TECHNOLOGIES Natural Attenuation In-Situ Biological Treatment In-Situ Physical/Chemical Treatment Ex-Situ Physical and Chemical Treatment Containment INITIAL SCREENING OF WETLAND REMEDIAL TECHNOLOGIES Natural Attenuation Excavation and Off-Site Disposal Containment In-Situ Treatment Ex-Situ Treatment EVALUATION OF PERMANENT AND TEMPORARY SOLUTIONS DETAILED EVALUATION OF REMEDIAL ALTERNATIVES FOR SOIL/NAPL Permanent Solution Excavation of Off-Site Disposal Solidification/Stabilization Temporary Solution Excavation and Off-Site Disposal of Soil Containment of Soil DETAILED EVALUATION OF REMEDIAL ALTERNATIVES FOR GROUNDWATER Passive Reactive Barriers Groundwater Extraction and Treatment DETAILED EVALUATION OF REMEDIAL ALTERNATIVES FOR WETLANDS 36

5 TABLE OF CONTENTS (continued) Page Permanent Solution Excavation and Off-Site Disposal Containment of Sediment Temporary Solution Excavation and Off-Site Disposal Containment of Sediment SELECTION OF REMEDIAL ALTERNATIVE SELECTION OF THE PREFERRED REMEDIAL ACTION FOR A A PERMANENT SOLUTION SELECTION OF THE PREFERRED REMEDIAL ACTION ALTERNATIVE FOR A TEMPORARY SOLUTION ENTERTAINING STEPS TO OBTAIN A PERMANENT SOLUTION SCHEDULE FOR IMPLEMENTATION PUBLIC INVOLVEMENT SUMMARY AND CONCLUSIONS PHASE III COMPLETION STATEMENT 45 TABLES TABLE 1 TABLE 2 INITIAL SCREENING OF REMEDIAL TECHNOLOGIES TECHNOLOGY SCREENING MATRIX PERMANENT SOLUTION TABLE 3 TECHNOLOGY SCREENING MATRIX TEMPORARY SOLUTION APPENDICES APPENDIX A APPENDIX B TRANSMITTAL FORM BWSC108 LIMITATIONS J:\17,000-18,999\18640\ DDM\Phase III\TABLE OF CONTENTS.doc

6 1.00 INTRODUCTION GZA GeoEnvironmental, Inc. (GZA) has prepared this Phase III Remedial Action Plan (Phase III RAP) on behalf of NSTAR Gas Company (NSTAR Gas) for the property located at 350 Irving Street, in Framingham, Massachusetts (the Site ). The Site was formerly occupied by a manufactured gas plant (MGP) from approximately 1889 to Tar processing and storage also occurred on two portions of the property. The Site is identified by the Massachusetts Department of Environmental Protection (MassDEP) using Release Tracking Number (RTN) This document has been prepared in accordance with Section of the Massachusetts Contingency Plan (MCP), and supports the endorsed Comprehensive Response Action Transmittal Form (BWSC108) contained in Appendix A. This document and the work described herein are subject to the limitations contained in Appendix B. Our analysis employed the procedures and criteria contained in the current version of the MCP (310 CMR In addition, to foster green remediation strategies and environmental stewardship, we considered the relative fossil fuel consumption and greenhouse gas (GHG) emissions from each viable remedial alternative OBJECTIVES AND SCOPE OF THE PHASE III - RAP As defined in the MCP, the objectives of Phase III are: 1. to identify and evaluate Remedial Action Alternatives (RAA) which, when implemented, are reasonably likely to achieve a level of No Significant Risk to surrounding human and environmental receptors; and, 2. to recommend a RAA that is a Permanent Solution or Temporary Solution, where a Permanent Solution includes measures that reduce, to the extent feasible, the concentrations of oil and/or hazardous material (OHM) in the environment to levels that achieve or approach background. The scope of the Phase III consists of the following tasks: 1. identification of the extent of OHM in Site media which require remediation; 2. screening of appropriate remedial technologies; 3. development of applicable RAA based on the screening results; 4. performance of a comparative evaluation of the RAA; and, 5. selection of a preferred RAA. 1

7 The evaluations and recommendations contained in the Phase III are based on fieldwork, environmental explorations, and sampling and analyses performed by GZA on behalf of NSTAR Gas during implementation of an Immediate Response Action (IRA) and Phase II Comprehensive Site Assessment (CSA). The IRA Completion Report was submitted to MassDEP in October 2006, and the Phase II CSA was submitted in October A summary of these assessments are provided below in Section ORGANIZATION OF DOCUMENT This document is organized into eight sections as outlined below: 1. Section 1.00 contains the introduction to and the purpose of the Phase III; 2. Section 2.00 provides relevant project background, including a description of the Site and the immediate vicinity, the historical uses of the Site, MCP compliance history, and the results of previous environmental assessments; 3. Section 3.00 gives a summary of the remedial objectives for the Site; 4. Section 4.00 contains a discussion of general classes of remedial technologies that are typically applicable at similar sites, and presents the results of the initial screening of technologies in these classes; this section includes the first step in the feasibility assessment, where technologies that would be ineffective or not implementable at the Site are eliminated from further consideration; 5. Section 5.00 presents a detailed evaluation of three selected RAA, including a discussion of the screening criteria used for selection; 6. Section 6.00 provides a description of the preferred RAA and the justification for the selection; 7. Section 7.00 provides a summary of the Phase III evaluation; and, 8. Section 8.00 contains the Phase III Completion Statement BACKGROUND The following sections present a brief description of the Site and the immediate vicinity, and summaries of historical Site use, MCP compliance history, and previous environmental assessments. Detailed summaries are provided in Section 2.00 of the Phase II CSA. 2

8 2.10 SITE DESCRIPTION A Site Locus Map showing the location of the Site with respect to topographic and cultural features in the town of Framingham and the physical layout of the Disposal Site is shown on Figures 1 and 2 respectively in the Phase II CSA. These figures also include the delineation of the eight Areas of Concern (AOC) identified during the Phase II. The Site consists of 22 acres of land bounded to the south and southwest by Irving Street, to the west by commercial property, to the north by wetlands and Beaver Dam Brook (which flows from the west, then to the north as it exits the Site), and to the east by wetlands and an unnamed tributary stream that flows north and discharges to Beaver Dam Brook. NSTAR Gas owns the majority of the Site, with the exception of a parcel of land to the southeast owned by the operators of Wellesley Trucking Services, Inc. In addition, a portion of the Beaver Dam Brook area is included with the Site Disposal Boundary, however the Beaver Dam Brook area has not been fully delineated and the Site Disposal Boundary may change in the area of Beaver Dam Brook upon further investigation. The Sudbury Aqueduct, an inactive water supply tunnel owned by the Commonwealth of Massachusetts and operated by the Massachusetts Water Resources Authority (MWRA), bisects the Site from roughly west to east, and divides the Site into north and south parcels. The aqueduct was built in 1878, and is a brick-lined, gravity flow conveyance, with an average diameter of 8.5 feet and a design flow of approximately 90 million gallons per day. The aqueduct connects the Framingham Reservoir system to the Chestnut Hill Reservoir. The MWRA currently considers the aqueduct a water resource for emergencies only, and rehabilitation would be required prior to restoration to active service. MWRA has no immediate plan to rehabilitate the aqueduct. The open areas of the property to the north of the aqueduct are currently used by a landscape materials supplier for staging large piles of loam and mulch, and pallets of dimension and decorative stone and brick. This portion of the property is surrounded by a soil berm containing variable quantities of debris (asphalt, shingles, and concrete) that was imported and placed by the former property owner, Mr. John Glynn. The unused northern and eastern portions of this property are bounded by wetlands associated with Beaver Dam Brook (to the north) and an unnamed tributary (to the east). Areas of mowed vegetation and wetland are on either side of the Sudbury Aqueduct. The western portion of the property to the south of the aqueduct is used by the landscape materials supplier for storing smaller piles of sand and gravel, and pallets of dimension stone and brick. The central portion is used by a variety of tenants for parking cars and storing landscape vehicles and equipment, and for cutting and storing piles of firewood. The southeastern portion of the Site is owned by Wellesley Trucking Services, Inc., and used for parking garbage trucks, storing roll-off containers and trash dumpsters, and for performing maintenance on trucks and equipment. The unused eastern portions of the property south of the aqueduct, and the area along the immediate-southern boundary of the aqueduct, consist of upland forest and wetlands. 3

9 2.20 SITE HISTORY In order to locate potential source-areas of contamination associated with MGP and tar handling operations, GZA reviewed available scaled plans of the Site ranging in date from 1886 to The plans were obtained from various Framingham municipal offices and from NSTAR Gas archives. Based on historical topographic maps, in 1886, the majority of the Site, with the exception of portions along Irving Street, existed as wetlands prior to construction of the Sudbury Aqueduct. Portions of the property were subsequently filled and first developed by the Framingham Gas, Fuel, and Power Company in The Site was used for MGP operations up to Processing and storage of by-product tar was also conducted on portions of the property north and south of the aqueduct from 1926 to at least Areas of the property were sequentially filled as MGP and tar processing operations changed. By 1968, all MGP and tar processing operations ceased and the majority of the infrastructure removed MCP COMPLIANCE HISTORY According to historical records filed with Town of Framingham municipal offices, ComGas, a corporate predecessor of NSTAR, took possession of the property in In 1982, ComGas sold the property to John Glynn of Environmental Restoration, Inc., with the strict requirement that the buyer properly remediate the property. In 1983, ownership of the property was transferred to 350 Irving Street Trust with Mr. John Glynn as trustee. The southeast portion of the Site was subsequently sold to 3D Realty Trust, the operators of Wellesley Trucking Services, Inc. Mr. Glynn failed to remediate the property and achieve regulatory closure under Chapter 21E and the MCP, and in September, 2008 NSTAR Gas acquired the property for the purposes of addressing the historical environmental conditions. With the exception of the Sudbury Aqueduct, NSTAR Gas owns the remainder of the Site. The Site has been the subject of numerous environmental assessments. In 1983, a hydrogeologic assessment was conducted by IEP Geoscience (IEP) on behalf of then owner Mr. John Glynn (350 Irving Street Trust). This study identified levels of organic volatile and semi-volatile contaminants concentrated within the shallow and intermediate portions of the groundwater system. In 1990, under the provisions of the 1988 MCP, the Site was listed by MassDEP as a Priority Disposal Site and RTN was assigned. In 1995, under the revised 1993 version of the MCP, the Site was designated a Tier 1B Disposal Site, and a Public Involvement Site. In 1998, as part of a Release Abatement Measure (RAM) undertaken by the 350 Irving Street Trust, 6 acres of the property were paved with asphalt. In 1998, the Trust submitted MCP Phase II and Phase III reports to MassDEP in response to a Notice of Non- Compliance (NON) issued in In 1999, the Trust submitted a Phase IV report to MassDEP that included plans for paving additional areas of the Site with asphalt, construction of a groundwater treatment system, and drainage improvements. However, those tasks specified in the Phase IV report were not implemented. 4

10 In 1999, Comprehensive Environmental, Inc. (CE) performed an inspection of the interior of the inactive Sudbury Aqueduct on behalf of the MWRA. At that time, oil/tar residue was observed seeping into the aqueduct near Aqueduct Manhole Sta Orange mineral precipitate indicative of oxidized iron was also observed in the seepage. To address this condition, the Trust submitted an IRA Plan to MassDEP in September The IRA Plan included subsurface explorations in the vicinity of the aqueduct and soil and groundwater sampling and analyses. In April 2004 an Addendum to the 1999 IRA Plan was prepared for the Trust by Corporate Environmental Advisors, Inc. (CEA). The Addendum included a proposal to (1) mitigate the seepage of NAPL into the aqueduct using a 700-foot interceptor trench, and (2) removal of coal-tar impacted sediments in the on-site wetlands, followed, and augmented by, bioremediation. In 2004, MassDEP issued RTN following the discovery of NAPL in a monitoring well installed during an assessment performed in support of a real estate transaction. In response, an IRA Plan was prepared by CEA, on behalf of the Trust, and submitted to MassDEP on October 21, In February 2005, MassDEP issued a NON to the Trust for failing to perform certain additional assessment activities and remedial actions. In response to the NON, the Trust submitted a notice of Financial Inability indicating that it was no longer financially able to implement the required MCP Response Actions. In April 2005, MassDEP issued an NOR to NSTAR Gas, the successor to ComGas, as a new Responsible Party (RP) under MGL Chapter 21E. In response to the NOR, NSTAR completed an assessment-only IRA in October 2006 and a Phase II Comprehensive Site Assessment in October Summaries of each investigation are provided in the sections that follow Immediate Response Action, October 2006 The IRA included field explorations and sampling to evaluate: the intrusion of light non-aqueous phase liquid (LNAPL) into the Sudbury Aqueduct; the presence of LNAPL in the wetlands and surface water bodies that border the Site to the north and east; and, the presence of dense non-aqueous phase liquid (DNAPL) in monitoring wells located near the southwest margin of the Site. Stains and incrustations of what appeared to be historic seeps of coal tar were identified during the interior inspection of the Sudbury Aqueduct. The seeps originated from the mortar joints between the bricks of the aqueduct s walls at approximately the elevation of the groundwater table. NAPL was not detected in any of the six new piezometers installed along the alignment of the aqueduct. This data, along with the historical data from the previously installed wells, most of which were subsequently destroyed, did not indicate that a mobile NAPL pool existed outside that section of the 5

11 aqueduct where historic coal tar intrusion was observed. Thus, it was concluded that the available groundwater data, combined with the results of the interior aqueduct inspection, did not indicate that an ongoing condition of Substantial Release Migration, as defined in the MCP, existed at the Site in the vicinity of the aqueduct. Visual observations of the extent of sheens on surface water and within the wetlands indicated that a condition of Readily Apparent Harm (RAH), as defined in the MCP, existed in the wetlands and certain upland areas both north and south of the Sudbury Aqueduct. It was estimated that the limits of visible contamination, as evidenced by the occurrence of sheens, stains, and NAPL, totaled approximately 7 acres. The area of impacted sediments was estimated to be greater than 1,000 square feet. The delineation of the area of RAH, as defined during IRA and Phase II exploration and sampling, is shown on Figures 3 and 4 in the Phase II CSA and further discussed in this report in Sections 4.00 and It was concluded in the IRA that the presence of OHM in the wetland areas did not present an Imminent Hazard to the environment. GZA did not observe readily apparent signs of stress to vegetation in the wetlands, nor gross adverse impacts to the on-site benthic community. The Site wetlands or tributary stream that discharges to Beaver Dam Brook does not function as fish habitat.. An area of cyanide waste and soil, most likely derived from the disposal of spent oxides from the MGP purifier-boxes, was identified in shallow samples (0 to 3 feet below grade) of upland soil collected in the vicinity of the wetlands that fringe the southeastern margin of the Site. The levels of physiologically available cyanide (PAC) in samples were below the level that would represent an Imminent Hazard to human health. The evaluation also indicated that Imminent Hazards to safety and public welfare did not exist at the Site. Further assessment of CN in soil in this area was conducted during the Phase II and is discussed below in Section Borings drilled in the vicinity of MW-6 and MW-17 encountered up to 10 feet of granular fill overlying glacio-lacustrine deposits, overlying glacial till. Refusal, interpreted to be the top of bedrock was encountered at approximately 70 feet below grade. Thin stringers of NAPL characteristic of coal tar were identified within the granular fill deposit and at the contact between the fill and lacustrine deposits; within fine sand seams present in the lacustrine deposits; at the contact between the lacustrine and glacial till units; and within fine sand laminations and fractures within the till. Following the installation of monitoring wells, DNAPL was identified in wells GZ-1M, GZ-2M and GZ-2D, and GZ-6D. The source area (s) for the observed DNAPL was not identified during the IRA. However, based on a review of historic plans of the MGP, it was hypothesized that DNAPL in GZ-1 and GZ-2 originated from the open tar well/tar storage tank formerly located near the southwest corner of the Site, and DNAPL in GZ-6D was attributed to the use of the surrounding vicinity for tar processing and storage. Delineation of historic source areas, as evaluated during the Phase II, is further discussed in Section

12 Phase II Comprehensive Site Assessment, October 2008 In October 2008, NSTAR submitted a Phase II CSA Report to MassDEP. A summary of findings is given below. Historical use of the Site as a MGP and tar processing facility has resulted in the presence of the following OHM in Site soil, groundwater, surface water and sediment: coal tar, light oils, and tar-water emulsions, found as LNAPL and DNAPL in monitoring wells, on the surface of the peat in a number of test pits, and in samples of wetland sediment; hardened tar, found as thin layers above the water table and as components of the granular fill primarily in test pits excavated to the north of the Sudbury Aqueduct; poly-nuclear aromatic hydrocarbons (PAH) and volatile aromatic hydrocarbons detected in soil and sediment samples and dissolved in groundwater and surface water; metals (primarily arsenic, chromium, copper, lead, nickel, and zinc) found sporadically across the Site in soil and sediment samples; and, inorganic compounds such as cyanide found in surface soil in the southwestern portion of the property, dissolved in groundwater throughout the Site, and detected in samples of wetland sediment and surface water. The geology beneath the Site consists of granular fill material which overlies a discontinuous layer of organic silt and peat (and at other locations, fine sand). The organic unit represents the historical wetlands that once covered most of the Site. Beneath the organic layer lies a deposit of glacio-lacustrine silt, and fine sand and silt. Layers of fine and medium sand were identified in several borings advanced through the lacustrine deposit. The lacustrine sediments overlie a unit of grey glacial till. Numerous laminations of fine sand were present in the till layer, and at certain borings, layers of sand up to 1 foot in thickness occurred in the till. Bedrock beneath the Site ranges from approximately 66 to 77 feet below grade. To facilitate the evaluation of historic source areas and contaminant distributions across the Site, the property was divided into eight (8) AOC which were defined based on the locations of historic MGP facilities and tar processing infrastructure, and the potential for each area to function as a contaminant source. The eight AOC were initially defined following a review of historical plans of the Site made available to GZA. Each area was further delineated during Phase II field explorations. 7

13 The eight AOC are defined below: 1. Northern Area of Concern (AOC-1): encompassing the majority of the northern portion of the Site, including filled land and two suspected Infiltration Lagoons north of the Sudbury Aqueduct; 2. OCTC-North (AOC-2): former Old Colony Tar Company (OCTC) tar processing and storage area north of the aqueduct; 3. Open Tar Well (AOC-3): former tar well located near the southwest boundary of the Site; 4. Former MGP Area (AOC-4): including the majority of the former MGP infrastructure south of the aqueduct (gas holders, purifiers, gas generator house, and processing equipment); 5. OCTC-South (AOC-5): former OCTC tar processing and storage area south of the aqueduct, including three large aboveground tar and/or gas-oil storage tanks, and one large aboveground oil storage tank; 6. Spent Oxide Waste (AOC-6): area of suspected spent oxide waste adjacent to the wetlands that occur at the southeast margin of the Site (this AOC overlaps with AOC-5 OCTC-South); 7. Coal Gas Generation Plant (AOC-7): relict structures associated with the former coal gasification plant located adjacent to and north of the Sudbury Aqueduct; and, 8. Wetlands and Beaver Dam Brook (AOC-8): wetlands and surface water that occur along the eastern and northern margins of the Site, and within Beaver Dam Brook north of the Site, where sheens and/or NAPL saturated sediment have been observed. During the Phase II fieldwork and following evaluation of results, GZA identified three primary NAPL source areas based on historical use within the MGP facilities and tar processing infrastructure, field observations, and analytical data: 1. OCTC-North (AOC-2): an area to the north of the Sudbury Aqueduct that consisted of several aboveground tanks used by the OCTC from before 1962 for the processing and storage of tar by-products generated during the gas manufacturing process; 2. A former Open Tar Well/Tar Storage Tank (AOC-3) located at the southwest corner of the Site; and, 8

14 3. OCTC-South (AOC-5): an area to the south of the aqueduct used by OCTC from before 1946 to no later than 1962 and consisting of numerous aboveground tanks for the processing and storage of by-product tar. Once released from these sources, the denser fractions of NAPL migrated horizontally and vertically through discontinuities in the till, through contacts between the fill and lacustrine deposits and lacustrine and till deposits, and within sand layers in the lacustrine and till deposit. DNAPL has migrated vertically and reached the bedrock at multiple well locations. LNAPL from the source areas has historically migrated on the surface of the groundwater table; however, since no widespread areas of measurable LNAPL have been observed, LNAPL appears to have reached a level of residual saturation held by capillary forces between soil particles. Sheens and sporadic, thin discontinuous layers of NAPL continue to be present on the surface of the groundwater. Based on borings drilled to the top of bedrock beyond the limits of the property, NAPL has not migrated off of the property. The viscosity of the denser NAPL fractions precludes significant migration from source areas. While NAPL in the subsurface continues to function as a source of dissolved MGPconstituents in groundwater, levels above applicable MCP Reportable Concentrations (RCs) have not been detected beyond the limits of the property boundaries. Groundwater flowing to the northeast through areas of NAPL continues to produce dissolved MGPrelated compounds from the NAPL at rates based on compound-specific solubilities. Hydrocarbon fractions dissolved in groundwater will continue to attenuate through dilution, mechanical dispersion through and adsorption to the soil matrix (especially soil high in organic content, such as the peat), and biodegradation. Lighter aromatic fractions will also attenuate through volatilization to the vadose zone and the atmosphere. Shallow groundwater in the granular fill (and most likely the lacustrine deposits) flows primarily to the northeast and discharges to the wetlands that bound the property to the east, southeast, and south; deep groundwater in the till also flows to the northeast. Dissolved constituents in groundwater discharge to the wetlands. However, contaminants of concern (COC) discharging to surface water will continue to attenuate through surface water dilution. In addition, the organic deposits in the wetlands function as a substrate for adsorption of COC. Visual observations of the extent of sheens on surface water and within the wetlands indicated that a condition of Readily Apparent Harm (RAH) existed in the wetlands and certain upland areas both north and south of the Sudbury Aqueduct. As defined in the MCP at (3), the following condition constitutes RAH: Visible presence of oil, tar, or other non-aqueous phase hazardous material in soil within three feet of the ground surface over an area equal to or greater than two acres, or over an area equal to or greater than 1,000 square feet in sediment within one foot of the sediment surface. If a condition of RAH harm exists in any environmental medium, then a condition of no significant risk of harm does not exist. It was estimated that the limits of visible 9

15 contamination, as indicated by observations of sheens, stains, and NAPL, totaled approximately 7 acres. The area of impacted sediments was estimated to be greater than 1,000 square feet. NAPL observed in sediments in the wetlands most likely resulted from direct surface discharges that occurred decades ago at multiple locations (as opposed to subsurface migration) during operation of the MGP and tar processing facility. Layers of viscous NAPL (coal tar) observed in test pits excavated near the wetlands occur within and upon the peat layer, indicating direct discharge to historical wetlands. Viscous NAPL in the subsurface has limited potential for migration at this Site. However, NAPL appears to have migrated to impact sediments in the intermittent stream and Beaver Dam Brook downstream from the property boundary. No ongoing discharge of NAPL or sheens to surface water have been observed, except if sediments are physically disturbed or extended precipitation events occur. One source of cyanide was identified in soil adjacent to the wetlands at the eastern margin of the Site; this area functions as a source of dissolved cyanide in groundwater, which most likely discharges to the wetlands; total cyanide was detected in samples of surface water from the wetland to the northeast and east. Cyanide in groundwater throughout the remainder of the Site most likely originates from limited areas of purifier waste included in the materials used to historically fill the wetlands. Localized areas of purifier waste were not observed in test pits excavated outside of AOC-6. With the exception of intermittent sheens and concentrations of MGP-related OHM in surface water and sediments associated with the wetlands and Beaver Dam Brook, and CN-containing surface soil in AOC-7 (adjacent to wetlands), exposure to OHM by human and environmental receptors is limited. Groundwater at the Site and the surrounding area is not used as a source of drinking water, and, with the exception of AOC-6, the majority of the property is surfaced with asphalt or densely compacted gravel. Groundwater containing elevated levels of volatile constituents is not located within 30 feet of occupied structures. Trespassers and facility workers may come into direct contact with surface water and sediment within the wetlands, and surface soil in AOC-6. However, calculated risks for facility workers, emergency utility workers, and trespassers do not exceed MCP risk limits. Cumulative risk estimates for future construction workers exceed MCP risk limits. In addition, the average surface water concentration exceeded applicable public health Ambient Water Quality Criteria (AWQC) protective of fish consumption, for benzene; however there is no evidence of fish or fishing at the Site. Accordingly, a condition of No Significant Risk of harm to human health exists for current uses of the Site; however, a condition of No Significant Risk of harm to human health does not exist for future uses of the Site. 10

16 3.00 REMEDIAL OBJECTIVES 3.10 RESPONSE ACTION OUTCOMES This section identifies potential site remediation outcomes relative to Response Action Outcomes (RAOs) as defined in the MCP (310 CMR ). The remedial alternatives presented in Section 4.00 of this report were evaluated based on their likelihood of achieving a Permanent Solution (Class A or B RAO) or Temporary Solution (Class C RAO). The MCP requires that a Phase III evaluation result in the selection of a RAA that is likely to result in a Permanent Solution, except where it is demonstrated to be infeasible and the implementation of a Temporary Solution is more cost effective and timely. Furthermore, the feasibility of achieving or approaching background levels of OHM shall be evaluated. The definitions of Permanent and Temporary Solutions are presented in the following sections Permanent Solution As described previously, the MCP requires that remedial actions be evaluated based on their ability to reach a Permanent Solution, if feasible. The achievement of a Permanent Solution will result in a Class A or B RAO. As defined in 310 CMR , a Class A RAO applies to sites where remedial activities have: 1. achieved a level of No Significant Risk (in accordance with 310 CMR ); 2. eliminated or controlled sources of oil and/or hazardous material (as defined in 310 CMR (5)); and 3. reduced, to the extent possible, the level of OHM in the environment to background concentrations. A Class A RAO can be further categorized as A-1, A-2, A-3, or A-4. These distinctions are defined below: A-1 A Permanent Solution has been achieved through remediation and the level of OHM has been reduced to background. All threats of release have been eliminated and no AULs are necessary to maintain a level of No Significant Risk. A-2 A Permanent Solution has been achieved through remediation, but OHM concentrations exceed background levels. No AULs are necessary to maintain a level of No Significant Risk. A-3 A Permanent Solution has been achieved, and OHM concentrations exceed background levels but do not exceed applicable MCP Upper Concentration Limits (UCLs) 11

17 in soil or groundwater. AULs are a necessary component of the remedial alternative to maintain a level of No Significant Risk. A-4 A Permanent Solution has been achieved, and AULs are a necessary component of the remedial alternative to maintain a level of No Significant Risk. OHM concentrations in soil deeper than 15 feet beneath the ground surface or beneath an engineered barrier exceed background levels and one or more applicable UCLs. In addition, a Phase III evaluation determines that it is not feasible to reduce OHM concentrations in the soil to less than or equal to applicable UCLs. Except as noted above under a Class A-4 RAO, Class A RAOs do not apply to disposal sites where average groundwater and/or soil concentrations exceed UCLs as specified in 310 CMR Additionally, a Class A RAO cannot be achieved if groundwater concentrations exceed an applicable standard where groundwater is categorized as GW-1. A Class B RAO applies to sites at which a condition of No Significant Risk exists without remedial actions being conducted; as such, a Class B RAO would not apply to this Site since interim remedial actions would be required to achieve a condition of No Significant Risk Temporary Solution A Temporary Solution (Class C RAO) may be applicable if achieving a condition of No Significant Risk at a Site is not feasible and/or timely. In accordance with 310 CMR , a Temporary Solution must mitigate the conditions which cause Substantial Hazard (i.e., a hazard which would present a significant risk if it continued to be present for several years), and, to the extent feasible eliminate, control or mitigate any source of OHM, as that term is defined in the MCP. The condition of RAH which exists based on the extent of tar and sheens in the wetlands and upland areas adjacent to the wetlands constitutes a Substantial Hazard to ecological receptors, specifically, the wetlands, and, in order to achieve a condition of No Substantial Hazard to the environment, steps must be taken to eliminate or mitigate the visible presence of oil, tar or other non-aqueous phase hazardous material in soil within 3 feet of the ground surface over an area equal to or greater than two acres, or over an area equal to or greater than 1,000 square feet in sediment within 1 foot of the sediment surface. Contaminant concentrations may exceed UCLs under a Temporary Solution. The MCP requires periodic evaluation and definitive and enterprising steps towards achieving a Permanent Solution if a Temporary Solution is implemented. Temporary Solutions are further divided into Class C-1 and C-2 RAOs: C-1 A condition of No Substantial Hazard exists and it is concluded that response actions to achieve a Permanent Solution are not feasible. 12

18 C-2 A condition of No Substantial Hazard exists and it is concluded that response actions to achieve a Permanent Solution are feasible and are to be conducted DEVELOPMENT OF REMEDIAL ALTERNATIVES To develop a set of remedial alternatives for detailed analysis, GZA performed an initial screening of available remedial technologies capable of addressing the OHM at the Site. These remedial alternatives are based on technologies included in the Federal Remediation Technologies Roundtable s Remediation Technologies Screening Matrix and Reference Guide, Version 4.0 (Screening Matrix) ( The technology categories screened for soil and NAPL remediation included: No Further Action; Institutional Controls; Natural attenuation; Containment; In-situ treatment; Ex-situ treatment; and Excavation and off-site treatment or disposal Technology categories screened for groundwater remediation included: No Further Action; Institutional Controls; Natural attenuation; Containment; In-situ treatment; and Ex-situ treatment Technology categories screened for wetland sediment remediation included: No Further Action; Institutional Controls; Natural attenuation; Containment; In-situ treatment; and Ex-situ treatment Certain technologies listed in the Screening Matrix within each technology category listed above are not applicable based on Site conditions including the types and concentrations of COCs present and media affected. These technologies are identified by a Worse rating in the Screening Matrix, and were not evaluated in this Phase III investigation. Additionally, a remedial approach involving the implementation of a combination of technologies may be necessary to attain remedial goals. 13

19 Within each category, both standard and innovative technologies were evaluated to determine their potential applicability at the Site. A remedial technology was judged to be acceptable for further evaluation if it was likely to achieve a Permanent or Temporary Solution, and if the individuals with the expertise needed to effectively implement the technology would be available. Remedial alternatives were evaluated with respect to the remedial goals outlined in Section The evaluation of remedial alternatives was based on the following criteria: Technical Feasibility: This evaluation criterion considered the applicability and reliability of the remedial alternative to address the COCs, the success of the technology at similar sites, and history of operational and maintenance performance of the alternative. Environmental and Public Health Impact: This evaluation criterion considered the potential effects of the remedial alternative on public health and the environment during and after implementation of the technology. The following sections present an overview of the classes of technology evaluated and a general description of the nature of each technology, followed by a discussion of its specific applicability to the areas of the Site. As discussed above, this Site has impacts in the vadose zone soil, saturated soil and groundwater, and the wetlands area including sediment and surface water. Due to the different impacted media, this report evaluates remedial technologies relating specifically to soil/napl, groundwater and wetlands and is segregated as such. The initial screening matrix of remedial technologies is presented in Table 1. The remedial alternatives of No Further Action and Institutional Controls are screened independent of the type of media impacted at the Site as these alternatives apply to all media. It should be noted that free phase NAPL is present onsite, and there are conditions of Readily Apparent Harm in the soil at AOC-6 and in the wetlands sediment which may not have a Permanent Solution and therefore are also evaluated for a Temporary Solution. Groundwater containing dissolved COCs above GW-3 standards does not appear to have migrated off site at this time and, although groundwater will be evaluated for a Permanent Solution, it will not be evaluated for a Temporary Solution NO FURTHER ACTION The no further action alternative assumes no additional efforts are made to remediate the Site. This alternative does not reduce Site risks associated with contaminants currently present, and provides no additional protection to safety, public welfare or the environment. However, it does provide a basis for assessing the effects of taking remedial actions and a baseline against which other remedial technologies can be compared. The no further action alternative would be ineffective at reducing the current or potential risks in any of the areas of the Site. As such, the alternative will not result in a Permanent or Temporary Solution in a timely manner and will not be retained for further evaluation. 14

20 4.20 INSTITUTIONAL CONTROLS Institutional controls are mechanisms to limit access to contaminated media and include alternatives such as site fencing and Activity and Use Limitations (AULs) in the form of deed restrictions. AULs are a legal tool to limit future site activities and uses in those areas that pose an unacceptable human health risk of exposure. While institutional controls do not eliminate contamination, they can provide an effective, low cost means for reducing human health exposure potential, and thus risk, in certain cases, if properly maintained and enforced. Some degree of institutional controls, such as the use of AULs to restrict future use in upland areas, may be applicable at this Site. Such controls would serve to limit risk to potential human receptors, including construction workers and potentially future on-site workers. However, the use of institutional controls alone would not address all the identified risks to the environment associated with the Site. Specifically, AULs could not be used to address conditions in the wetland areas. Institutional controls are a viable alternative for this Site to reduce potential risks to human health and will be retained for further evaluation, but only in companion with a more active remedial technology INITIAL SCREENING OF SOIL AND NAPL REMEDIAL TECHNOLOGIES Natural Attenuation Natural attenuation relies on naturally occurring processes such as volatilization, adsorption, dilution, oxidation, reduction, and biodegradation to reduce the mass, concentration, and/or toxicity of contaminants. Biodegradation is the transformation of organic compounds via metabolism by microorganisms. The rate of attenuation is determined by several factors related to the availability of required elements (i.e. carbon and oxygen), nutrients (i.e. nitrogen and phosphorous), and organic growth factors necessary for the growth of the microbial population. Natural attenuation is considered a passive remedial technology in that no active remediation is performed. Often, the rate and progress of natural attenuation is assessed via routine soil and/or groundwater monitoring (i.e., monitored natural attenuation [MNA]); such monitoring may include the assessment of surrogate indicators of attenuation processes. Under this approach, periodic monitoring would be conducted to assess the natural reduction in contaminant concentrations and to monitor potential migration. 15

21 Under favorable Site conditions, natural attenuation may be an appropriate selection depending on chemical concentrations and characteristics, hydrogeologic characteristics of the Site and presence of NAPL. However, the Site conditions are not favorable to natural attenuation due to the presence of NAPL, the proximity to a wetland, and other chemical characteristics and, therefore, natural attenuation is not retained for further evaluation Containment Technologies The primary purpose of containment technologies is to isolate contaminated media, and thus control potential exposure risks. Passive containment involves placement of physical barriers to limit the potential for exposure to contaminated soil. Engineered barriers are the most commonly used passive containment technologies. Passive remediation systems use little or no external energy and typically have a low carbon footprint. Horizontal engineered barrier designs include impermeable caps, which typically consist of a layer of asphalt pavement, concrete, or natural low permeability material such as clay. Impermeable caps limit surface water infiltration into the contaminated media, thereby limiting the potential for contaminant migration. An engineered barrier, as defined in 310 CMR is a cap that meets the following specifications: prevents direct contact with contaminated media; controls any vapors or dust emanating from contaminated media; prevents erosion and any infiltration of precipitation or run-off that could jeopardize the integrity of the barrier or result in the potential mobilization and migration of contaminants; is comprised of materials that are resistant to degradation; is consistent with the technical standards of RCRA Subpart N, 40 CFR , 310 CMR or equivalent standards; and includes a defining layer that visually identifies the beginning of the barrier. This technology would also require implementation of an AUL and monitoring. However, containment does not remediate the soil and must be indefinitely maintained in place. The Phase II Report identified surface soil in the Suspected Spent Oxides Area (AOC-6) which contained physiologically available cyanide at concentrations which exceed the significant risk level. An engineered barrier as well as implementation of an AUL in this area may be feasible as a Temporary Solution. At other portions of this site, the risks associated with direct contact and vapor intrusion can be adequately maintained via the implementation of an AUL in the upland areas, but an engineered barrier could not be adequately designed to address other areas of the Site with active businesses and buildings. Therefore, a horizontal barrier is not considered applicable at this site for either a Permanent Solution or a Temporary Solution, except as noted above. 16

22 Passive containment technologies can also include the removal of NAPL from the subsurface as it collects in trenches and/or wells. In this respect, passive removal systems are differentiated from active containment technologies by the fact that no artificial gradient is induced to draw the NAPL and/or contaminated liquid toward the removal location. Passive removal technologies include the use of adsorbent materials within recovery wells, simple systems that use the natural density difference between oil and water to passively collect SPH in storage containers, manual bailing of wells for NAPL and vertical low permeability barriers which prevent NAPL from migrating but must be designed to prevent groundwater from mounding. Passive containment does not actively address the NAPL exceeding UCL standards and is not effective for use in attaining a Permanent Solution, but can be effective in limiting migration of NAPL off site and may be utilized as part of a Temporary Solution. Due to the size of the site and the fact that a large portion of the NAPL is not LNAPL, only passive removal technologies will be evaluated for a Temporary Solution. Active containment systems are designed to control the migration of NAPL by imposing a gradient toward one or more product and/or groundwater collection locations. This process results in the capture of NAPL through NAPL and/or groundwater depression within a certain distance from the removal location, and limits natural migration. An advantage of active removal technologies, as opposed to strict containment technologies, is that the mass of contaminants in the subsurface is also reduced via the removal, collection, and/or treatment of contaminated groundwater and NAPL. However, although fuel oil LNAPL product recovery technologies have been used extensively and their successes are well documented, they are generally considered infeasible at MGP sites as part of a Permanent Solution. This is because, as demonstrated consistently at other sites, MGP contaminants are not amenable to pumping due to their thick, tar-like consistency as well as their DNAPL components. Active containment does not actively address the NAPL exceeding UCL standards and is not effective for use in attaining a Permanent Solution. Active Containment can be effective in limiting migration of NAPL off site only in conjunction with groundwater extraction and due to the heterogeneous presence of NAPL and limited recovery while extracting groundwater, Active Containment will only be selected for a Temporary Solution as a part of groundwater extraction, if selected, and is not selected as stand alone for a Temporary Solution In-Situ Technologies In-situ treatment destroys, neutralizes, or reduces the toxicity of contaminants while leaving soil in place. In-situ technologies result in limited site disturbance with limited need for excavation, treatment and/or handling of contaminated media. This limits risks to remedial construction workers, on-site employees, and Site abutters that can occur during more intrusive removal activities. In-situ treatment technologies include the following: In-Situ Physical/Chemical Technologies 17

23 Soil flushing is a method of in-situ chemical treatment. According to the Federal Remediation Technologies Roundtable web site, soil flushing may be potentially used for desorbing VOCs, SVOCs and metals from soils; however, the heterogeneity of the vadose zone, varied chemical properties of the COCs, limited technological information regarding the application, and presence of NAPL, treatment and reinjection area make this an unsuitable technology for this particular application. Based on this information, soil flushing was not considered appropriate for use at the Site for a Temporary or Permanent Solution. Soil vapor extraction (SVE) is an in-situ physical treatment technology that is fully developed and widely utilized. An SVE system would apply a vacuum to the vadose soil to induce a controlled flow of air to remove VOCs and some SVOCS from soil. The extracted soil gas may be treated using activated carbon or catalytic oxidation to remove organic contaminants from the system exhaust. The SVOCs, NAPL and metals present in the vadose zone will not volatilize sufficiently to consider this an effective technology and this technology is not considered appropriate for use at the Site for a Temporary or Permanent Solution. Chemical Oxidation is an in-situ chemical treatment technology that has limited full scale development for the COCs, is not effective for metals, and is difficult to implement in vadose soil conditions. Based on this information, chemical oxidation was not considered appropriate for use at the Site for a Temporary or Permanent Solution. Solidification/Stabilization is an in-situ technology which utilizes Portland cement, jet grouting, or other binding agent to encapsulate inorganic compounds to prevent leaching of the inorganic chemical. This technology has been used successfully in fullscale applications for cyanide complexes in soil, but has not been shown to be effective for the organic COCs or NAPL. This technology is retained for detailed evaluation as a Permanent Solution for the treatment of cyanide and metals COCs only at the Site In-Situ Biological Treatment Bioremediation is a managed or spontaneous process in which microbiological activity transforms contaminants to less toxic or non-toxic forms thereby mitigating or eliminating environmental contamination. Microorganisms require carbon sources and nutrients to provide energy for growth and survival. Degradation of natural substances in soil and sediment and carbon from the contaminants of concern provides food for the development of microbial populations in these media. Technical information regarding biodegradation of the COCs indicate that the SVOCs will biodegrade most quickly under aerobic conditions, while the cyanide and NAPL in the soil are resistive to biological treatment. Since cyanide and NAPL are much more widespread and of significant importance in the soil at the Site, in-situ bioremediation by any application method was not considered appropriate for use at the Site for a Temporary or Permanent Solution. 18

6.12 Former UGI Columbia Manufactured Gas Plant, Columbia, Pennsylvania

6.12 Former UGI Columbia Manufactured Gas Plant, Columbia, Pennsylvania 6.12 Former UGI Columbia Manufactured Gas Plant, Columbia, Pennsylvania The UGI Columbia Gas Plant site is located on less than 1 acre in an industrial area of the Borough of Columbia, Lancaster County,

More information

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location Maryland Department of the Environment Site Location FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) This 2.4581-acres site (Site) consists of four parcels of

More information

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013 DECISION DOCUMENT Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013 Prepared by Division of Environmental Remediation New York State Department of Environmental

More information

D2 Project Environmental Remediation Briefing August 21, 2018

D2 Project Environmental Remediation Briefing August 21, 2018 D2 Project Environmental Remediation Briefing August 21, 2018 The Union Square Revitalization Project (USQ) is a 2.4 million square foot transit-oriented, mixed use project that is transforming Union Square,

More information

Tyree 26 Town Forest Road, Webster, MA Fax: Phone:

Tyree 26 Town Forest Road, Webster, MA Fax: Phone: Tyree 26 Town Forest Road, Webster, MA 01570 Fax: 508-640-0370 Phone: 508-640-0300 April 9, 2012 Massachusetts Department of Environmental Protection Northeast Regional Office 205B Lowell Street Wilmington,

More information

IMMEDIATE RESPONSE ACTIONS MASSDEP RTN

IMMEDIATE RESPONSE ACTIONS MASSDEP RTN Former Revere Copper Products, Inc. New Bedford, Massachusetts Request for Determination of Applicability May 2017 IMMEDIATE RESPONSE ACTIONS MASSDEP RTN 4-26614 Request for Determination of Applicability

More information

PROPOSED DECISION DOCUMENT. CE - E. 19th St. Station Voluntary Cleanup Program New York, New York County Site No. V00542 October 2017

PROPOSED DECISION DOCUMENT. CE - E. 19th St. Station Voluntary Cleanup Program New York, New York County Site No. V00542 October 2017 PROPOSED DECISION DOCUMENT CE - E. 19th St. Station Voluntary Cleanup Program New York, New York County Site No. V00542 October 2017 Prepared by Division of Environmental Remediation New York State Department

More information

PROPOSED DECISION DOCUMENT. CE - E. 17th St. Station Voluntary Cleanup Program New York, New York County Site No. V00541 October 2017

PROPOSED DECISION DOCUMENT. CE - E. 17th St. Station Voluntary Cleanup Program New York, New York County Site No. V00541 October 2017 PROPOSED DECISION DOCUMENT CE - E. 17th St. Station Voluntary Cleanup Program New York, New York County Site No. V00541 October 2017 Prepared by Division of Environmental Remediation New York State Department

More information

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS

More information

ROUX ASSOCIATES, INC. Environmental Consulting & Management

ROUX ASSOCIATES, INC. Environmental Consulting & Management February 28, 2012 PARTIAL RESPONSE ACTION OUTCOME STATEMENT (RAO) 17 Central Street Property Peabody Essex Museum RTN 3-23396 Prepared for PEABODY ESSEX MUSEUM East India Square Salem, Massachusetts 01907

More information

Executive Summary. ES.1 Objectives and Scope

Executive Summary. ES.1 Objectives and Scope Executive Summary This Remedial Investigation and Focused Feasibility Study (RI/FFS) report was prepared on behalf of Northern States Power Co. (NSP) to document the findings of the multi-media environmental

More information

MNA CLOSURE STRATEGY AT A REDEVELOPED MGP SITE IN FLORIDA Jacksonville Recycling Facility Former MGP Site in Florida September 2018

MNA CLOSURE STRATEGY AT A REDEVELOPED MGP SITE IN FLORIDA Jacksonville Recycling Facility Former MGP Site in Florida September 2018 MNA CLOSURE STRATEGY AT A REDEVELOPED MGP SITE IN FLORIDA Jacksonville Recycling Facility Former MGP Site in Florida September 2018 Steven R Sagstad and Jeff Manuszak Jacksonville Recycling Site History

More information

PERMANENT SOLUTION STATEMENT. Hydraulic Oil Release 68 Hopkinton Road Westborough, Massachusetts

PERMANENT SOLUTION STATEMENT. Hydraulic Oil Release 68 Hopkinton Road Westborough, Massachusetts PERMANENT SOLUTION STATEMENT Hydraulic Oil Release 68 Hopkinton Road Westborough, Massachusetts Release Tracking Number: 2-19324 CHES Job No.: 1402479917 TABLE OF CONTENTS INTRODUCTION... 1 SITE SETTING...

More information

MASSACHUSETTS CONTINGENCY PLAN REMEDY OPERATION STATUS OPINION

MASSACHUSETTS CONTINGENCY PLAN REMEDY OPERATION STATUS OPINION 273 West Main Street, Norton, MA 02766 Tel: (508) 226-1800 Fax: (508) 226-1811 MASSACHUSETTS CONTINGENCY PLAN REMEDY OPERATION STATUS OPINION CITGO BULK STORAGE TERMINAL 385 QUINCY AVENUE BRAINTREE, MASSACHUSETTS

More information

Spill Prevention Control and Countermeasures Plan Former Raytheon Facility 430 Boston Post Road Wayland, Massachusetts

Spill Prevention Control and Countermeasures Plan Former Raytheon Facility 430 Boston Post Road Wayland, Massachusetts SPCC PLAN Raytheon Company Spill Prevention Control and Countermeasures Plan Former Raytheon Facility 430 Boston Post Road Wayland, Massachusetts 6 November 2002 143.65 Environmental Resources Management

More information

Proposed Plan Closed Sanitary Landfill

Proposed Plan Closed Sanitary Landfill Fort George G. Meade Proposed Plan Closed Sanitary Landfill Public Meeting May 18, 2016 1 18MAY2017 Public Meeting Purpose U.S. Army is inviting the public to comment on the proposed environmental actions

More information

Modern Electroplating Site Update. Dudley Vision Advisory Task Force September 2008 Meeting

Modern Electroplating Site Update. Dudley Vision Advisory Task Force September 2008 Meeting Modern Electroplating Site Update Dudley Vision Advisory Task Force September 2008 Meeting 1 Modern Electroplating Uncontrolled Waste Site Key elements that define a site relative to MA DEP and US EPA

More information

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA) DRAFT Analysis of Brownfields Cleanup Alternatives (ABCA) Preliminary Evaluation Ball Square Station Site Boston Avenue and Broadway Somerville and Medford, Massachusetts Massachusetts DEP Release Tracking

More information

PROJECT OVERVIEW. Site Assessment for Proposed Coke Point Dredged Material Containment Facility at Sparrows Point

PROJECT OVERVIEW. Site Assessment for Proposed Coke Point Dredged Material Containment Facility at Sparrows Point PROJECT OVERVIEW Site Assessment for Proposed Coke Point Dredged Material Containment Facility at Sparrows Point Capacity of existing placement sites for dredged material from the Baltimore Harbor remains

More information

Creamer Environmental. Containment, Caps & Liners. 12 Old Bridge Road C ed ar Grov e, N e w Jer s e y

Creamer Environmental. Containment, Caps & Liners. 12 Old Bridge Road C ed ar Grov e, N e w Jer s e y Containment, Caps & Liners While excavation and treatment are common solutions for many soil and groundwater remediation projects, containment can sometimes be a more appropriate and more economical alternative.,

More information

Case Studies in Risk Management Methods as a Component of the Remedial Process

Case Studies in Risk Management Methods as a Component of the Remedial Process Case Studies in Risk Management Methods as a Component of the Remedial Process Cecile Willert, P.Eng., QP RA January/February 2013 Agenda Issues Summary Case Study # 1 RA of DNAPL site (combined with remediation)

More information

New York State Department of Environmental Conservation

New York State Department of Environmental Conservation New York State Department of Environmental Conservation FACT SHEET Voluntary Cleanup Program Rochester Gas and Electric Corporation (RG&E) February 2014 RG&E-Brockport MGP Site, Perry and Erie Street(s)

More information

Silver Line Phase III Hazardous Materials Technical Appendix

Silver Line Phase III Hazardous Materials Technical Appendix Silver Line Phase III Hazardous Materials Technical Appendix Introduction This Technical Appendix contains a description of hazardous materials release locations occurring within the limits of construction

More information

FINAL PLAN OF REMEDIAL ACTION

FINAL PLAN OF REMEDIAL ACTION FINAL PLAN OF REMEDIAL ACTION Clayville Dump Christiana, DE DNREC Project No. DE-0095 November 2002 Delaware Department of Natural Resources and Environmental Control Division of Air and Waste Management

More information

Soil Vapor Extraction O&M Report Camp Stanley Storage Activity, Texas

Soil Vapor Extraction O&M Report Camp Stanley Storage Activity, Texas Appendix C Soil Vapor Extraction O&M Report Camp Stanley Storage Activity, Texas APPENDIX C TECHNOLOGY EVALUATION MEMORANDUM, VEG/OIL BARK MULCH ENHANCEMENT (ORIGINALLY PRESENTED DURING THE SWMU B-3 REMOVAL

More information

SOIL MANAGEMENT PLAN

SOIL MANAGEMENT PLAN SOIL MANAGEMENT PLAN BELFAST BOATYARD 39 & 41 FRONT STREET BELFAST, MAINE Prepared by: Ransom Consulting, Inc. 400 Commercial Street, Suite 404 Portland, Maine 04101 (207) 772-2891 March 22, 2013 1.0 INTRODUCTION

More information

ENVIRONMENTAL GEOLOGY - GEOL 406/506

ENVIRONMENTAL GEOLOGY - GEOL 406/506 ENVIRONMENTAL GEOLOGY - GEOL 406/506 Glossary of useful Terms: 1. Abiotic: not living. 2. A b s o r p t i o n: the penetration of atoms, ions, or molecules into the bulk mass of substrate. 3. Acclimation:

More information

PROPOSED DECISION DOCUMENT. CE - E. 14th St. (StuyTown) Works Voluntary Cleanup Program New York, New York County Site No. V00535 October 2017

PROPOSED DECISION DOCUMENT. CE - E. 14th St. (StuyTown) Works Voluntary Cleanup Program New York, New York County Site No. V00535 October 2017 PROPOSED DECISION DOCUMENT CE - E. 14th St. (StuyTown) Works Voluntary Cleanup Program New York, New York County Site No. V00535 October 2017 Prepared by Division of Environmental Remediation New York

More information

Risk-Based Cleanup Actions for Closure of a Brownfield Site

Risk-Based Cleanup Actions for Closure of a Brownfield Site Risk-Based Cleanup Actions for Closure of a Brownfield Site H.W. Rice, J.F. Feild, L.C. Farr Jr. AMEC Earth and Environmental, Inc. 7376 SW Durham Road, Portland, Oregon 97224 USA ABSTRACT Operating as

More information

Informational Meeting: Onsite and Offsite Response Action Plans

Informational Meeting: Onsite and Offsite Response Action Plans Informational Meeting: Onsite and Offsite Response Action Plans Kop-Flex Voluntary Cleanup Program Site #31 June 24, 2015 BACKGROUND ONSITE AREA SUMMARY OF SITE HISTORY Koppers Company purchased the property,

More information

Site Background December 2005

Site Background December 2005 Site Background December 2005 The South of Runway 18-36 Area consists of the lowland area surrounding the southern portion of runway 18-36. It extends from the East Canal of the airport ditch system on

More information

PROPOSED PLAN OF REMEDIAL ACTION FOR THE REICHHOLD CHEMICAL SITE CHESWOLD, DELAWARE

PROPOSED PLAN OF REMEDIAL ACTION FOR THE REICHHOLD CHEMICAL SITE CHESWOLD, DELAWARE PROPOSED PLAN OF REMEDIAL ACTION FOR THE REICHHOLD CHEMICAL SITE CHESWOLD, DELAWARE July 1999 DNREC Project DE-245 Prepared by: Delaware Department of Natural Resources and Environmental Control Division

More information

MEMORANDUM. Pleasant Run Crossing Prospect Place West. The boundaries and approximate acreages for each of the parcels are depicted on Figure 1.

MEMORANDUM. Pleasant Run Crossing Prospect Place West. The boundaries and approximate acreages for each of the parcels are depicted on Figure 1. MEMORANDUM Date: May 19, 2017 To: From: Ms. Shannon Stahley Citizens Energy Group August Mack Environmental Subject: Environmental Conditions at Citizens Property Associated with the Former Coke and Manufactured

More information

Valentine-Clark State Superfund Site Bridal Veil Pond Open Space Operable Unit City of Minneapolis, Hennepin County, Minnesota

Valentine-Clark State Superfund Site Bridal Veil Pond Open Space Operable Unit City of Minneapolis, Hennepin County, Minnesota October 12, 2007 SITE DESCRIPTION FINAL MINNESOTA DECISION DOCUMENT Valentine-Clark State Superfund Site Bridal Veil Pond Open Space Operable Unit City of Minneapolis, Hennepin County, Minnesota The Bridal

More information

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies TASK Tersus Advanced Surface Kinetics NAPL Surfactants Tersus is the worldwide distributor of the

More information

LNAPL REMEDIATION USING ELECTRICAL RESISTANCE HEATING

LNAPL REMEDIATION USING ELECTRICAL RESISTANCE HEATING LNAPL REMEDIATION USING ELECTRICAL RESISTANCE HEATING TRS Group, Inc. ABSTRACT An Electrical Resistance Heating (ERH) pilot test was conducted in the fall of 1998 to determine the effectiveness of using

More information

FINAL PLAN OF REMEDIAL ACTION FOR THE NVF-NEWARK COMPANY SITE NEWARK, DELAWARE

FINAL PLAN OF REMEDIAL ACTION FOR THE NVF-NEWARK COMPANY SITE NEWARK, DELAWARE FINAL PLAN OF REMEDIAL ACTION FOR THE NVF-NEWARK COMPANY SITE NEWARK, DELAWARE May, 1999 DNREC Project DE-199 Prepared by: Delaware Department of Natural Resources and Environmental Control Division of

More information

Reference Guideline #1. Hydrogeological Impact Assessment

Reference Guideline #1. Hydrogeological Impact Assessment Reference Guideline #1 Hydrogeological Impact Assessment Reference Guideline #1 Hydrogeological Impact Assessment Hydrogeological assessments are required for some subdivision applications when triggered

More information

DRAFT PHASE III EVALUATION OF REMEDIAL ALTERNATIVES AND REMEDIAL ACTION PLAN OUTLINE RUSSELL FIELD CAMBRIDGE, MASSACHUSETTS

DRAFT PHASE III EVALUATION OF REMEDIAL ALTERNATIVES AND REMEDIAL ACTION PLAN OUTLINE RUSSELL FIELD CAMBRIDGE, MASSACHUSETTS PHASE III EVALUATION OF REMEDIAL ALTERNATIVES AND REMEDIAL ACTION PLAN OUTLINE RUSSELL FIELD CAMBRIDGE, MASSACHUSETTS Prepared For: Ms. Susanne Rasmussen City of Cambridge 57 Inman Street Cambridge, MA

More information

Vapor Intrusion in Massachusetts Gerard Martin

Vapor Intrusion in Massachusetts Gerard Martin Vapor Intrusion in Massachusetts Gerard Martin Chief Compliance, Enforcement and Brownfields Redevelopment Section Bureau of Waste Site Cleanup, MassDEP Proposed MCP Amendments Relative to Vapor Intrusion

More information

APPENDIX I A SITE-SPECIFIC RECAP EVALUATION FOR TYPICAL UST SITES

APPENDIX I A SITE-SPECIFIC RECAP EVALUATION FOR TYPICAL UST SITES APPENDIX I A SITE-SPECIFIC RECAP EVALUATION FOR TYPICAL UST SITES LDEQ RECAP 2003 TABLE OF CONTENTS List of Figures List of Tables List of Worksheets Page... i... i... ii I1.0 APPENDIX I UNDERGROUND STORAGE

More information

Enhanced Anaerobic Bioremediation Using CAP18 as a Polishing Application for CVOC Impacted Groundwater

Enhanced Anaerobic Bioremediation Using CAP18 as a Polishing Application for CVOC Impacted Groundwater www.burnsmcd.com Author: Presented Date: Walter McClendon, Martha Hildebrandt and John Hesemann, Burns & McDonnell John Shimp, Directorate of Public Works, Fort Riley, Kan. Bradden Bigelow, Environmental

More information

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation. Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation February 2014 FACT SHEET Petroleum Remediation Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: For

More information

In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure

In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure M. Brewster 1, S. Penny 1, B. Odell 1 and T. Jorgensen-Nelson 2 Abstract A very shallow (1 2 m deep) hydrocarbon

More information

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation. Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation November 2013 FACT SHEET Brownfield Cleanup Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: West 28th

More information

WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS. GENERAL WATER POLLUTION CONTROL PERMIT Permit Number: GP-WV-1-07

WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS. GENERAL WATER POLLUTION CONTROL PERMIT Permit Number: GP-WV-1-07 WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS GENERAL WATER POLLUTION CONTROL PERMIT Permit Number: GP-WV-1-07 FACT SHEET, RATIONALE AND INFORMATION FOR GENERAL PERMIT FOR

More information

Remediation of BTEX in Shallow, Silty Clay Soil Successes and Insights

Remediation of BTEX in Shallow, Silty Clay Soil Successes and Insights Remediation of BTEX in Shallow, Silty Clay Soil Successes and Insights Brian D. Symons, P.E. FOTH Infrastruture & Environment, LLC Overland Park, Kansas What We Want to Learn? Complexities of Nature Treatment

More information

Summary of Investigations & Remedial Activities

Summary of Investigations & Remedial Activities Summary of Investigations & Remedial Activities Former Farmland Industries Nitrogen Manufacturing Plant Lawrence, Kansas November 9, 2009 Topics of Discussion Previous Investigations/Remedial Actions (Pre-2000s)

More information

Application of Mulch Biowall for Anaerobic Treatment of Perchlorate in Shallow Groundwater

Application of Mulch Biowall for Anaerobic Treatment of Perchlorate in Shallow Groundwater Paper G-04, in: G.B. Wickramanayake and H.V. Rectanus (Chairs), In Situ and On-Site Bioremediation 2009. Tenth International In Situ and On-Site Bioremediation Symposium (Baltimore, MD; May 5 8, 2009).

More information

PROPOSED PLAN OF REMEDIAL ACTION

PROPOSED PLAN OF REMEDIAL ACTION PROPOSED PLAN OF REMEDIAL ACTION Former Lewes, Delaware DE-1167 June 2001 Department of Natural Resources and Environmental Control Division of Air and Waste Management Site Investigation and Restoration

More information

SECTION RISK-BASED ASSESSMENT AND CORRECTIVE ACTION FOR NON-UST PETROLEUM RELEASES

SECTION RISK-BASED ASSESSMENT AND CORRECTIVE ACTION FOR NON-UST PETROLEUM RELEASES SECTION.0500 - RISK-BASED ASSESSMENT AND CORRECTIVE ACTION FOR NON-UST PETROLEUM RELEASES 15A NCAC 02L.0501 PURPOSE AND SCOPE (a) The purpose of this Section is to establish procedures for risk-based assessment

More information

RECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 (VERSION 1.0)

RECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 (VERSION 1.0) RECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 (VERSION 1.0) RECYCLED ASPHALT PAVEMENT AND ASPHALT MILLINGS (RAP) REUSE GUIDANCE MARCH 2013 A. GENERAL INFORMATION It is

More information

Wickes Manufacturing TCE Plume Site Mancelona, Michigan

Wickes Manufacturing TCE Plume Site Mancelona, Michigan Wickes Manufacturing TCE Plume Site Mancelona, Michigan December 2017 What is TCE? Trichloroethylene (TCE) Common Industrial Solvent Known Human Carcinogen Federal and State Safe Drinking Water of 5 µg/l

More information

FINAL PLAN OF REMEDIAL ACTION. Burns and McBride. South Market and A Streets August 19, 2008

FINAL PLAN OF REMEDIAL ACTION. Burns and McBride. South Market and A Streets August 19, 2008 FINAL PLAN OF REMEDIAL ACTION Burns and McBride South Market and A Streets August 19, 2008 Wilmington, Delaware DNREC Project No. DE-0325 This Revised Final Plan of Remedial Action (Final Plan) presents

More information

Pump & Treat Remediation

Pump & Treat Remediation Pump & Treat Remediation Selection and Planning Pump & Treat Extraction of contaminated water Extraction of free product in the form of a NAPL Removal or destruction of the contaminant from the extracted

More information

EBC Site Remediation & Redevelopment Program: Evaluation and Closure of NAPL Sites

EBC Site Remediation & Redevelopment Program: Evaluation and Closure of NAPL Sites EBC Site Remediation & Redevelopment Program: Evaluation and Closure of NAPL Sites Welcome from the Committee Chair Jon Kitchen Chair, EBC Site Remediation & Redevelopment Committee Senior Project Manager

More information

FINAL PLAN OF REMEDIAL ACTION

FINAL PLAN OF REMEDIAL ACTION FINAL PLAN OF REMEDIAL ACTION DRAVO SHIPYARD Operable Unit II RDC/Harbor Associates Properties Wilmington, Delaware DNREC Projects No. DE-1092 & DE-1096 February 2001 Department of Natural Resources and

More information

Former NCBC Davisville Site 16 Former Creosote Dip Tank and Fire Training Area

Former NCBC Davisville Site 16 Former Creosote Dip Tank and Fire Training Area Former NCBC Davisville Site 16 Former Creosote Dip Tank and Fire Training Area Review of Site 16 Information Phase III Quality Assurance Project Plan Scope of Work Implementation and Schedule Site 16 Map

More information

September 20, 2015 PN:

September 20, 2015 PN: AECOM 1155 Elm Street, Suite 401 Manchester, NH 03101-1508 www.aecom.com 603 606 4800 tel 603 606 4801 fax September 20, 2015 PN: 60422003 Dr. Brenda K. Weis, Director Board of Health City of New Bedford

More information

LNAPL Recovery Using Vacuum Enhanced Technology. Theresa Ferguson, R.G. June 2014

LNAPL Recovery Using Vacuum Enhanced Technology. Theresa Ferguson, R.G. June 2014 LNAPL Recovery Using Vacuum Enhanced Technology Theresa Ferguson, R.G. June 2014 Presentation Overview v LNAPL in the Subsurface v What is Vacuum Enhanced Technology? v Technology Description and Application

More information

5.14 CONTAMINATED MATERIALS

5.14 CONTAMINATED MATERIALS 5.14 CONTAMINATED MATERIALS 5.14.1 Introduction Contaminated materials are toxic or potentially harmful substances that may be present in soil, groundwater, and building materials. Contaminated materials

More information

PROPOSED PLAN OF REMEDIAL ACTION. 560 Terminal Avenue New Castle, DE

PROPOSED PLAN OF REMEDIAL ACTION. 560 Terminal Avenue New Castle, DE PROPOSED PLAN OF REMEDIAL ACTION 560 Terminal Avenue New Castle, DE DNREC Project No. DE 1123 October 2002 Delaware Department of Natural Resources and Environmental Control Division of Air and Waste Management

More information

Manufactured Gas Plant Site Management - Program 50

Manufactured Gas Plant Site Management - Program 50 Manufactured Gas Plant Site Management - Program 50 Program Description Program Overview Most former manufactured gas plants (MGPs) ceased operation by the 1960s, but by-products and wastes, often disposed

More information

New York State Department of Environmental Conservation August Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation August Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation August 2013 FACT SHEET Environmental Restoration Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: 1201

More information

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies TASK Tersus Advanced Surface Kinetics NAPL Surfactants Tersus is the worldwide distributor of the

More information

Gray s Fine Printing Site Proposed Plan of Remedial Action DE1094

Gray s Fine Printing Site Proposed Plan of Remedial Action DE1094 Gray s Fine Printing Site DE1094 June 1998 Department of Natural Resources and Environmental Control Division of Air and Waste Management Site Investigation and Restoration Branch Table of Contents I.

More information

Multi-Component Remediation of Petroleum and Metals at a Former Power Plant in San Francisco, California

Multi-Component Remediation of Petroleum and Metals at a Former Power Plant in San Francisco, California Multi-Component Remediation of Petroleum and Metals at a Former Power Plant in San Francisco, California October 2 nd, 2014 Insert then choose Picture select your picture. Right click your picture and

More information

Alternative Cleanup Methods for Chlorinated VOCs

Alternative Cleanup Methods for Chlorinated VOCs Slide 1 Alternative Cleanup Methods for Chlorinated VOCs Getting beyond pump and treat Slide 2 Soil Vapor Extraction Vacuum is applied through extraction wells Creates a pressure gradient that induces

More information

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies

Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies Advancing the Science of In Situ Groundwater Remediation Petroleum Hydrocarbon Remediation Technologies RemBind Vadose Zone Treatment Tersus is the exclusive North American distributor for RemBind (US

More information

IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B

IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B IN-SITU CHEMICAL OXIDATION REMEDIATION PROGRAM INTERIM REPORT PHASE 2B SITE: CHAMPAIGN FORMER MGP SITE CHAMPAIGN, ILLINOIS JULY 24, 2013 PREPARED FOR: PSC INDUSTRIAL OUTSOURCING, LP 210 WEST SAND BANK

More information

7.0 EVALUATION OF REMEDIAL ALTERNATIVES

7.0 EVALUATION OF REMEDIAL ALTERNATIVES 7.0 EVALUATION OF REMEDIAL ALTERNATIVES This section provides a description of the developed remedial alternatives based on viable remedial technologies and process options, as identified in Section 4.0,

More information

OVERVIEW SCOPE OF WORK (SOW)

OVERVIEW SCOPE OF WORK (SOW) Site Description The subject property is occupied by the former Parker Service Station, which contained a former Service Garage (now called Former Garage) and Filling Station Store (now called Storage

More information

MINNESOTA DECISION DOCUMENT

MINNESOTA DECISION DOCUMENT MINNESOTA DECISION DOCUMENT 3M Cottage Grove Disposal Site City of Cottage Grove, Washington County, Minnesota SITE DESCRIPTION Background The 3M Cottage Grove Site (Site) encompasses a large industrial

More information

Final Plan of Remedial Action

Final Plan of Remedial Action Final Plan of Remedial Action Peninsula Park LLC Operating Unit -1 (OU-1) East Seventh Street Peninsula Wilmington, Delaware DNREC Project No. DE-1147 February 2000 Department of Natural Resources and

More information

In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project

In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project ABSTRACT In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project R. Juhlin, M. Butherus S.M. Stoller Corporation 2597 B ¾ Road, Grand Junction, C0 81506 USA The

More information

Provide overview of multi-stage constructed wetland groundwater treatment system design and operation

Provide overview of multi-stage constructed wetland groundwater treatment system design and operation Treatment of Hydrocarbon Impacted Groundwater from a Former Refinery using Multi-Stage Constructed Wetlands CHMIDT: : AECOM CORPORATION MARTIN SCHMIDT ORPORATION SCOTT WALLACE: : NATURALLY N WALLACE ERIC

More information

UNITED STATES FORGECRAFT

UNITED STATES FORGECRAFT UNITED STATES FORGECRAFT STATE PRIORITY LIST SITE FORT SMITH, ARKANSAS ADEQ 5301 Northshore Drive North Little Rock, Arkansas 72118 EPA RCRA ID No: ARD006341747 EPA CERCLA ID No: ARD006341747 AFIN: 66-00145

More information

In Situ Treatment of Contaminated Soil and Groundwater: Lessons Learned from the Field

In Situ Treatment of Contaminated Soil and Groundwater: Lessons Learned from the Field In Situ Treatment of Contaminated Soil and Groundwater: Lessons Learned from the Field Presented by Alan Weston, Ph.D. Conestoga-Rovers & Associates Niagara Falls, NY, USA Agenda 1. Introduction to In

More information

PA Vapor Intrusion Guidance

PA Vapor Intrusion Guidance PA Vapor Intrusion Guidance Society of Women Environmental Professionals Capital Chapter November 10, 2016 Presented by: Carolyn Fair - Land Recycling Program PA Department of Environmental Protection

More information

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 GEOTECHNICAL INVESTIGATION UPDATE. CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 October 5, 2013 Project No. SCR-0720 SANTA CRUZ SEASIDE COMPANY Craig French 911 Center Street, Suite B Santa

More information

Manufactured Gas Plant Site Remediation - Program 50

Manufactured Gas Plant Site Remediation - Program 50 Manufactured Gas Plant Site Remediation - Program 50 Program Description Program Overview More than 1,500 former manufactured gas plant (MGP) sites in the United States require either investigation or

More information

IXPER 70C Calcium Peroxide CASE STUDY

IXPER 70C Calcium Peroxide CASE STUDY IXPER 70C INTRODUCTION TO ENHANCED AEROBIC BIOREMEDIATION Enhanced aerobic bioremediation is a well-established and viable remediation technology for in situ degradation of a variety of petroleum hydrocarbon

More information

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program www.pca.state.mn.us Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program This document describes the requirements for excavating petroleum-contaminated soil

More information

SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B

SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B SCHEDULE 3-1 DETAILED CONSTRUCTION PLAN Part B Narrative: Work Area B We will carry out the excavation for Work Area B as per Company s

More information

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation. Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation February 2014 FACT SHEET State Superfund Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: Powers Chemco

More information

Environmental Hazard Evaluations

Environmental Hazard Evaluations Environmental Hazard Evaluations Item Type text; Proceedings Authors Ricci, Edward D. Publisher Arizona-Nevada Academy of Science Journal Hydrology and Water Resources in Arizona and the Southwest Rights

More information

Collect deeper soil samples and groundwater from beneath site?

Collect deeper soil samples and groundwater from beneath site? Uncertainties for which sampling is (i.e., to be incorporated into Work Plan). No. Uncertainty Recommended Resolution/ 1 SS005 No evidence of Acquire samples from three closest MOGas in soil. Tank as surface

More information

Receive Site Fact Sheets by . See "For More Information" to Learn How.

Receive Site Fact Sheets by  . See For More Information to Learn How. April 2015 FACT SHEET State Superfund Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: K - Fulton Works DEC Site #: 224051 Address: Nevins, DeGraw & Sackett

More information

Site Investigation of Ground Water

Site Investigation of Ground Water Site Investigation of Ground Water Christina Page New Jersey Department of Environmental Protection Bureau of Inspection and Review 1 Ground Water Site Investigation Overview Applicable Ground Water Remediation

More information

TABLE OF CONTENTS 1.0 INTRODUCTION COMMUNITY ROLE IN THE SELECTION PROCESS SITE BACKGROUND... 2

TABLE OF CONTENTS 1.0 INTRODUCTION COMMUNITY ROLE IN THE SELECTION PROCESS SITE BACKGROUND... 2 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 COMMUNITY ROLE IN THE SELECTION PROCESS... 2 3.0 SITE BACKGROUND... 2 4.0 REMEDIAL INVESTIGATION SUMMARY... 3 4.1 Type and Distribution of Soil Contamination...

More information

Chapter 11: Hazardous Materials A. INTRODUCTION

Chapter 11: Hazardous Materials A. INTRODUCTION Chapter 11: Hazardous Materials A. INTRODUCTION This chapter relies on the analysis from the Fresh Kills Park Final Generic Environmental Impact Statement (FGEIS) and summarizes the conclusions drawn from

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada

TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada INTRODUCTION The Historic Turner Valley Gas Plant is located

More information

McCormick and Baxter Superfund Site Long-Term Performance Monitoring

McCormick and Baxter Superfund Site Long-Term Performance Monitoring Northwest Region Cleanup Program McCormick and Baxter Superfund Site Long-Term Performance Monitoring Scott Manzano Oregon Department of Environmental Quality Background Background Wood treatment facility;

More information

Section 5 Relative Effects of Manure Spreading and Confined Feeding Operations on Groundwater Quality

Section 5 Relative Effects of Manure Spreading and Confined Feeding Operations on Groundwater Quality Section 5 Relative Effects of Manure Spreading and Confined Feeding Operations on Groundwater Quality 5.1 Introduction The third objective of the Livestock Manure Impacts on Groundwater Quality in Alberta

More information

A-2. Soils. Soil Media. Chapter Contents. Soil Media In-situ Soil Testing Separation from Seasonal High Water Table (SHWT)

A-2. Soils. Soil Media. Chapter Contents. Soil Media In-situ Soil Testing Separation from Seasonal High Water Table (SHWT) A-2. Soils Chapter Contents Soil Media In-situ Soil Testing Separation from Seasonal High Water Table (SHWT) Importance of Soil Composition in SCMs The soil composition of many stormwater SCMs also is

More information

MISSOURI DEPARTMENT OF NATURAL RESOURCES. Monitored Natural Attenuation of Groundwater Contamination at Voluntary Cleanup Program Sites

MISSOURI DEPARTMENT OF NATURAL RESOURCES. Monitored Natural Attenuation of Groundwater Contamination at Voluntary Cleanup Program Sites MISSOURI DEPARTMENT OF NATURAL RESOURCES Monitored Natural Attenuation of Groundwater Contamination at Voluntary Cleanup Program Sites Technical Bulletin 1/2002 Hazardous Waste Program The chemical, physical

More information

ENVIRONMENTAL ASSESSMENT FINDINGS AND CONCLUSIONS WEBER SIGN SERVICE, INC. th 730 EAST 8 STREET MICHIGAN CITY, INDIANA 46360

ENVIRONMENTAL ASSESSMENT FINDINGS AND CONCLUSIONS WEBER SIGN SERVICE, INC. th 730 EAST 8 STREET MICHIGAN CITY, INDIANA 46360 ENVIRONMENTAL ASSESSMENT FINDINGS AND CONCLUSIONS WEBER SIGN SERVICE, INC. th 730 EAST 8 STREET MICHIGAN CITY, INDIANA 46360 Prepared for: THE MICHIGAN CITY REDEVELOPMENT COMMISSION 100 EAST MICHIGAN BOULEVARD

More information

Fill Material and Soil Management

Fill Material and Soil Management Fill Material and Soil Management What You Need to Know The purpose of this fact sheet is to describe how fill material and excess soil can be reused properly during the cleanup and redevelopment of properties

More information

TABLE OF CONTENTS PART III. REVISION 0 6-ii

TABLE OF CONTENTS PART III. REVISION 0 6-ii TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 6-1 2.0 GENERAL LANDFILL GAS AND SITE CHARACTERISTICS [330.371(b)(1)(A)-(E)... 6-2 2.1 INTRODUCTION... 6-2 2.2 SOIL CONDITIONS... 6-2 2.3 FACILITY STRUCTURES...

More information