APPENDIX "B" November 5, 2002 Page 1 of 6 BOILERSMITH LTD. STACKS AND BREECHING
|
|
- Gyles Daniel
- 6 years ago
- Views:
Transcription
1 APPENDIX "B" November 5, 2002 Page 1 of 6 BOILERSMITH LTD. STACKS AND BREECHING NOTE The Stack and Breeching shall be installed in conformance with national, regional and local codes and standards and/or appropriate legislation. The purpose of the stack and breeching is to conduct the products of combustion safely to the atmosphere. In addition a well designed stack will provide sufficient draft to overcome friction losses in the breeching and stack. Considerations On individual units, a direct vertical connection off the flue gas outlet of the boiler (it is preferable to support the stack/breeching independent from the boiler) or a horizontal offset connection may be utilized. See Figure 1. In the case of multiple boilers, it is always better to utilize a separate stack for each boiler. If this is not practical, See Figure 2 for a Typical Multiple Boiler Installation with Common Breeching. BREECHING Installation AND Construction of the Breeching shall be in conformance with national, regional and local codes and standards and/or appropriate legislation. Changes in breeching direction, shape and flow area must be accomplished separately and as gradually as possible to eliminate turbulence which may adversely affect burner performance. See Figure 3. The Breeching should be as short and straight as possible without excessive bends to minimize flow resistance. A round breeching is preferred over a square or rectangular breeching and stack. Insulating the breeching will help to minimize flue gas condensation which may result in excessive corrosion. In addition the higher resultant stack temperature will aid in increasing the available draft. STACKS Construction AND Installation of the Stack shall be in conformance with national, regional and local codes and standards and/or appropriate legislation. The following types of chimneys are suitable for use with boilers as supplied by Boilersmith Ltd. - Rectangular Brick Masonry Chimneys - Radial Brick Masonry Chimneys - Reinforced Concrete Chimneys - Metal Chimneys - Factory-Built, Type A Chimneys - Factory-Built Pressure Fired Chimneys Factory-Built, Type B, L or Class 1 BH for NATURAL GAS FIRED APPLIANCES ONLY may be used if the flue gas temperature is less than 500 o F and a negative pressure exists at the flue gas outlet vent of the boiler.
2 APPENDIX "B" November 5, 2002 Page 2 of 6 BOILERSMITH LTD. STACKS AND BREECHING The walls of any chimney, gas vent or flue pipe shall be constructed to be gas-, smoke- and flametight. A round stack is preferred over square stack. Every chimney shall be capable of providing sufficient draft to vent properly the appliances that it serves. The cross-sectional area of the flue pipe shall not be less than the area of the flue outlet of the appliance, except that a tapered reduction in the section of the flue adjacent to the chimney is permitted provided adequate draft is maintained. Insulating the stack will help to minimize flue gas condensation which may result in excessive corrosion. In addition the higher resultant stack temperature will aid in increasing the available draft. A rain cap or hood should be used at the top of the stack to minimize the entrance of rain or snow. See Figure 4. The top of every chimney shall be at least 3 ft above the highest point at which it comes in contact with the roof, and 2 ft above a roof surface or structure with a horizontal distance of 10 ft from the chimney. See Figure 5. Installation of the Stack shall be in conformance with national, regional and local codes and standards and/or appropriate legislation. The stack should be higher than nearby structures or geographical prominence since they could create down drafts or eddy current. SIZING BREECHING AND STACK A Breeching and stack should be sized on the basis of maintaining a flue gas flow of 30 ft/sec or less with the boiler operating at maximum capacity. In the case of a multiple boiler installation utilizing a common stack and breeching, the breeching should be sized to maintain a constant velocity of flow. The Equivalent Diameters of Breeching for Multiple Boiler Installations to maintain a constant velocity of flow are shown in Chart 1. For single boiler installations the Suggested Minimum Breeching Size and Boiler Outlet Diameters for Boilersmith Ltd. boilers is shown in Chart 2. It is generally recommended that the stack size selected be larger than the breeching diameter and should not be selected smaller than the flue gas outlet supplied with the boiler.
3
4
5
6 EQUIVALENT DIAMETERS OF BREECHING FOR MULTIPLE BOILER INSTALLATIONS Required Diameter (inches) Equivalent Diameter of Breeching to maintain approximately the same flue gas velocity for one to five boilers (in inches) one two three four five Boiler Boilers Boilers Boilers Boilers CHART 1 MINIMUM BREECHING DIAMETER (inches O.D.) BHP Minimum Breeching Boiler Outlet Diameter Diameter < CHART 2
Dunbrik A1 Concrete Flue Liners
Dunbrik A1 Concrete Flue Liners System Guide Firebelly stove FB2 woodburner in pewter domestic flue & chimney systems Certificate No.FM24104 Benefits of a Chimney A chimney adds appeal to a house A real
More informationFlue Pipe Considerations
Flue Pipe Considerations Objective The application summary outlined here will communicate the necessary flue piping arrangement for EnergyLogic (EL) furnaces and boilers and give a fundamental understanding
More informationDuraFlex. Flexible stainless steel relining for masonry chimney. UL 1777 and ULC S635.
DuraFlex Flexible stainless steel relining for masonry chimney. UL 1777 and ULC S635. Specifications DuraFlex SW Applications DuraFlex SW smooth wall flexible relining for masonry chimney. Use with gas,
More informationRECONSTRUCTION AND REPLACEMENT OF EARTHQUAKE DAMAGED MASONRY CHIMNEYS
INFORMATION BULLETIN / PUBLIC BUILDING CODE REFERENCE NO.: LABC 2113 and LARC R1001 DOCUMENT NO.: P/BC 2014-070 Previously Issued As: P/BC 2008-070 Effective: 01-01-2014 Revised: 01-16-2014 RECONSTRUCTION
More informationTaking value to the highest level.
Venting Solutions Taking value to the highest level. Example: 2D Drawings Schebler Chimney Systems is a premier source of custom, modular prefabricated stainless steel chimneys, heavy wall engineered stacks,
More informationSTANDARD PLAN BULLETIN SP-2 (Structural)
STANDARD PLAN BULLETIN SP-2 (Structural) Date: January 20, 2000 This Los Angeles Department of Building and Safety (LADBS) standard plan provides prescriptive details to facilitate the reconstruction of
More informationInstallation instructions
Installation instructions Holetherm Single-walled flue gas discharge system (EW) 2016 All information in this release is subject to misprints. No liability is accepted for the consequences of misprints.
More informationCity of Republic Community Development Department. Residential Roofs REVISION DATE: JANUARY 2017
City of Republic Community Development Department Residential Roofs REVISION DATE: JANUARY 2017 A residential roof permit is required for new roofs and for replacement roofs when the replacement area is
More informationAppendix VIII: Determination of chimney heights
Appendix VIII: Determination of chimney heights 181 Regional Air Quality Plan for Taranaki 182 Regional Air Quality Plan for Taranaki Appendix VIII: Determination of stack heights and boiler operation
More informationTC54. for architects & designers. Dimensions Clearances Venting
for architects & designers TC54 Series D Dimensions Clearances enting IMPORTANT This booklet is intended as a basic specification guide for architects, designers and builders. Please refer to the Instruction
More informationInnovative New Chimney Design for Wet Flue Gas. Paul Nederlof, Msc. Hadek Protective Systems, Inc. 651 Holiday Drive Pittsburgh, PA 15241
Innovative New Chimney Design for Wet Flue Gas Paul Nederlof, Msc. Hadek Protective Systems, Inc. 651 Holiday Drive Pittsburgh, PA 15241 ABSTRACT For removal of a large number of flue gas components, wet
More informationIntro. ADA Operations Contact Info
Intro ADA Operations Contact Info Todd Grugel ph: 651-366-3531 email: todd.grugel@state.mn.us Joe Zilka ph: 651-366-3311 email: joseph.zilka@state.mn.us Harvey Unruh ph: 651-216-2912 email: harvey.unruh@state.mn.us
More informationBALCONY FLUE OUTLET KIT
BLCONY FLUE OUTLET KIT LOGIC Combi LOGIC + Combi LOGIC Heat LOGIC + Heat LOGIC System LOGIC + System LOGIC Code Combi i-mini When replacing any part on this appliance, use only spare parts that you can
More informationRinnai Infinity XR26/HD200 Internal Flueing
Flueing Options and Rinnai Flue Kits Available Rinnai have developed two flueing kits to make installation of Rinnai Infinity XR26i/XR26ia and HD200i Internal units as easy as possible. Use the kit options
More informationSI T T FST
SI 440-600-700-700T-780-780T-900-1100 Freestanding TAPER TOP Open Fire - Wood Burner Installation Instructions Note: FLUE SYSTEMS Casing. Flue System may require to be Doubled Lined to Comply. Ref ASNZS:2918:2001
More informationStandards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition
STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm
More informationGREEN THREAD Piping Systems
Bulletin No. A1300 February 15, 2006 SMITH FIBERCAST GREEN THREAD Piping Systems PRODUCT GREEN THREAD pipe is filament wound using an amine cured epoxy resin and fiberglass and has a resin-rich liner reinforced
More informationRediflow Concrete Gas Flue System
Rediflow Concrete Gas Flue System Rediflow Concrete Gas Flue System Rediflow the complete gas flue block system Red Bank s range of Rediflow pre-cast concrete gas flue block system manufactured to BS EN
More informationBuderus SB745WS/1550 Stainless Steel Condensing Boiler
Stainless Steel Condensing Boiler Engineering Submittal Sheet Boiler Components R Engineering Specifications The boiler(s) shall have a full three pass fire tube design to allow complete combustion of
More informationSUBMITTAL RECORD. Material Selection FLUE (INNER WALL) CASING (OUTER WALL) GALVALUME
SUBMITTAL RECORD UL 1978 - Grease Duct Professional Series Kitchen Ventilation DCL Single Wall DAS1 1-inch Air Insulated DIS1 1-inch Insulated (AES WOOL) DIS2 2-inch Insulated (AES WOOL) DIS4 4-inch Insulated
More informationHIGH EFFICIENCY POSITIVE PRESSURE VENTING SYSTEMS FOR CONDENSING APPLIANCES, CATEGORIES II, III AND IV Single & Double Wall Construction
HIGH EFFICIENCY POSITIVE PRESSURE VENTING SYSTEMS FOR CONDENSING APPLIANCES, CATEGORIES II, III AND IV Single & Double Wall Construction Models HEP HEPL HEPL2 28 KJ This symbol shows that CHEMINÉE LINING.E
More informationHigh Performance Pumice Based Concrete Flue Linings
High Performance Pumice Based Concrete Flue Linings 7mm Pumice Based Flue Liners High performance pumice based concrete flue liners Red Bank s range of 7mm High Performance Pumice Based Concrete Liners
More informationDIVISION: SPECIALTIES SECTION: MANUFACTURED FIREPLACES REPORT HOLDER: EARTHCORE INDUSTRIES, LLC
0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2316 Reissued 10/2017 This report is subject to renewal 10/2018. DIVISION: 10 00
More information10.0 Storm Sewer Systems
October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and
More informationInstallation instructions
Installation instructions Holetherm Double-walled flue gas discharge system (DW) 2016 All information in this release is subject to misprints. No liability is accepted for the consequences of misprints.
More informationChapter 2: Foundation
Chapter 2: Foundation Crawlspace [V502.1.2] [V502.1.2] [V502.1.3] Vents. Vents in the crawlspace help keep floor insulation and floor framing dry. Crawlspace vents also reduce the potential for radon buildup
More informationFireplace. Opening. Old. Opening up an old fireplace is like striking gold in your very own home.
Opening up an Opening up an old fireplace is like striking gold in your very own home. In addition to a glowing, warmer, more welcoming living room, you are creating a much healthier and more invigorating
More informationDuraFlex AL. Installation Instructions
Installation Instructions Flexible aluminum relining system for relining masonry chimneys for natural gas or liquid propane category I, draft hood equipped appliances, and appliances tested and listed
More informationMODEL N, VSI, IVSI & ZC SINGLE WALL, DOUBLE WALL AIR & CERAMIC FIBER INSULATED POSITIVE PRESSURE PIPING SYSTEMS
INSTALLATION INSTRUCTIONS & MAINTENANCE GUIDE MODEL N, VSI, IVSI & ZC SINGLE WALL, DOUBLE WALL AIR & CERAMIC FIBER INSULATED POSITIVE PRESSURE PIPING SYSTEMS BOILER STACK ENGINE EXHAUST GREASE DUCT VENTILATION
More informationSECTION SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS REVISED PART 1 GENERAL 1.1 DESCRIPTION:
SECTION 13 05 41 SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS REVISED 1-25-13 PART 1 GENERAL 1.1 DESCRIPTION: A. Provide seismic restraint in accordance with the requirements of this section
More informationZ-Vent Model SVE Series III
Special Stainless Steel Venting System for Gas Burning Appliances Category I, II, III, & IV Tested and Listed By Underwriters Laboratories Inc. UL 1738 & BH636 Note the following before installation of
More informationGas Fireplaces. P36D-10 Gas Fireplace. Unit Dimensions With Vignette Faceplate. *** Important: Framing height requires consideration of the hearth
28-15/16 (735mm) Model P36D-NG10 P36D-LP10 Fuel Type Natural Gas Propane Gas Fireplaces Minimum Supply Pressure Manifold Pressure - High Manifold Pressure - Low 5 W.C. (1.25 kpa) 3.8 W.C. (0.95 kpa) 1.1
More informationGas Fireplaces. P33 Zero Clearance Direct Vent Gas Fireplace. *** Important: Framing height requires consideration of the hearth
P33 Zero Clearance Direct Vent Gas Fireplace P33 WITH THE FLUSH OR BAY FRONT Model P33-NG4 P33-LP4 Fuel Type Natural Gas Propane Minimum Supply Pressure 5 W.C. (1.25 kpa) 12 W.C. (3.00 kpa) Manifold Pressure
More informationAdministrative Changes
Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings
More informationSanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:
Oklahoma Department of Environmental Quality Water Quality Division Phone: 405-702-8100 Construction Permitting Section 707 N. Robinson, OKC, OK 73102-6010 P.O. Box 1677, OKC, OK 73101-1677 Sanitary Sewer
More informationENBRIDGE GAS DISTRIBUTION METER BOX. Builders Installation Guidelines September 2011
ENBRIDGE GAS DISTRIBUTION METER BOX Builders Installation Guidelines September 2011 Meter Box Builder s Guildline for Installations Introduction These guidelines are provided to communicate to Builders,
More informationNatural Gas Service Installation and Meter Clearance Requirements
Natural Gas Service Installation and Meter Clearance Requirements Call SJG s new construction line at 1-844-611-5605 for more information. Builder/Owner/Developer Requirements The clearances in this handout
More informationDuraPlus. All-fuel, triple-wall chimney system. UL 103 HT.
DuraPlus ll-fuel, triple-wall chimney system. UL 103 HT. Specifications pplications DuraPlus himney is a triple-wall, all-fuel chimney for use with wood stoves, fireplaces, furnaces, boilers, stoves, ranges,
More informationDINAK Camiño do Laranxo, , VIGO (SPAIN) DIFLUX POLYPOPRYLENE. TÜV Industrie Service GmbH TÜV SÜD Gruppe 0036 CPD
Rev.2 DECLARATION OF CONFORMITY AND PRODUCT DESCRIPTION 14471 Chimneys - System chimneys with plastic flue liners - Requirements and test methods Manufacturer: Product commercial name: Product description:
More informationINSTALLATION INSTRUCTIONS
CHIMNEY CONNECTOR WALL THIMBLE MODEL IWT INSTALLATION INSTRUCTIONS Warnock Hersey C US LISTED ULC-S641/UL103 IT IS OF THE UTMOST IMPORTANCE THAT THIS WALL THIMBLE BE INSTALLED ONLY Y IN ACCORD CCORDANCE
More informationFIREPLACE INSERT ENCLOSURE INSTALLATION INSTRUCTIONS
FIREPLACE INSERT ENCLOSURE INSTALLATION INSTRUCTIONS ENCLOSURE MODEL 90566400 FOR INSERT MODEL 5660NA And ENCLOSURE MODEL 90566000 FOR INSERT MODEL 5660 STANDARD KEEP THESE INSTRUCTIONS FOR FUTURE USE
More informationDe Montfort Mark 7 Incinerator (Flatpack)
De Montfort Mark 7 Incinerator (Flatpack) Introduction This design is specially for those occasions when a large number of incinerators are to be built at one location and transported to the places where
More informationGRAND MERIDIAN WOOD BURNING / VENT-FREE GAS FIREPLACES INDOOR / OUTDOOR TRULY TIMELESS. Traditional. Fireplace Design Collection
GRAND MERIDIAN WOOD BURNING / VENT-FREE GAS FIREPLACES INDOOR / OUTDOOR Traditional Fireplace Design Collection TRULY TIMELESS 4 SHOW YOURSELF Create a room that begs you to stick around, sit down and
More informationTek Spec 4.0. Reference Guide
Tek Spec 4.0 Reference Guide RECOMMENDED PRACTICES FOR FIREPLACE, CHIMNEY AND BAKE OVEN CONSTRUCTION A well-constructed masonry fireplace or bake oven adds several elements of interest to the home, providing
More informationConcrete Block Machines Typical Fixed Block Machine
SEAOG 2016 Masonry Workshop Concrete Masonry Units and Terminology Concrete Masonry in Georgia Georgia World Congress Center Reference: Inspector s Handbook Masonry Institute of America Roy Keck, FACI
More informationPLANS REVIEW CRITERIA - COMMERCIAL BUILDINGS
PLANS REVIEW CRITERIA - COMMERCIAL BUILDINGS NOTE: Building Code compliance is the obligation of design professionals and/or contractors. Plan review and inspection guidelines are to be used to ensure
More informationDETERMINATION OF CONCENTRATION AND MASS FLOW OF PARTICULATE MATTER IN FLUE GAS FOR STATIONARY SOURCE EMISSIONS
MS 1596: 2003 DETERMINATION OF CONCENTRATION AND MASS FLOW OF PARTICULATE MATTER IN FLUE GAS FOR STATIONARY SOURCE EMISSIONS Presented BY: UiTM A&A Laboratory Malaysia s 1 st University Affiliated Environmental
More informationECONOMIZER ECM. Turnkey Price Installed: $115,295
ECONOMIZER ECM Turnkey Price Installed: $115,295 PRICE INSTALLED PER INVESTMENT GRADE AUDIT. CALCULATED ANNUAL SAVINGS OF $29,027.51 WITH A SIMPLE PAYBACK OF 3.97 YEARS. (SEE ATTACHED SAVINGS CALCULATIONS)
More informationREAD ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter X X X Adopt Entire Chapter as amended (amended sections listed below) X X X X X X
CALIFORNIA PLUMBING CODE MATRIX ADOPTION TABLE CHAPTER 9 - VENTS (Matrix Adoption Tables are non-regulatory, intended only as an aid to the user. See Chapter 1 for state agency authority and building application.)
More informationSimpson Dura-Vent Engineered Excellence
DuraLiner Simpson Dura-Vent Engineered Excellence pplications Materials and onstruction DuraLiner DuraLiner ensures safe and efficient venting of heating appliances, while protecting the masonry chimney
More informationElectric Furnace Off-Gas Cleaning Systems Installation at PT Inco ABSTRACT
Electric Furnace Off-Gas Cleaning Systems Installation at PT Inco Paykan Safe and Matt Russell WorleyParsons Gas Cleaning, Irving, Texas USA ABSTRACT PT Inco is a ferronickel smelter in Soroako, Sulawesi,
More informationBuderus SB625WS/640 Stainless Steel Condensing Boiler
Stainless Steel ondensing Boiler Engineering Submittal Sheet Boiler omponents R Engineering Specifications The boiler(s) shall have a full three pass fire tube design to allow complete combustion of the
More informationThese installation instructions cover the installation and operation of Jetmaster Inset and Freestanding Barbecues
These installation instructions cover the installation and operation of Jetmaster Inset and Freestanding Barbecues ADDRESS Jetmaster Fires Ltd Unit 2, Peacock Trading Estate Goodwood Road Eastleigh Hampshire`
More informationPVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe
Design and Installation Guide PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar
More informationModern Rumford. MR 48 fireplaces
Modern Rumford MR 48 fireplaces Construction Guidelines For MR-48-1 Kit System Cellar Building, Suite 300 1124 NW Couch Street Portland, OR 97209 Ph. 503-227-0547 Fax 503-227-0548 info@mobergfireplaces.com
More informationE APPENDIX. The following problems are intended for solution using finite element. Problems for Computer Solution E.1 CHAPTER 3
E APPENDIX Problems for Computer Solution The following problems are intended for solution using finite element analysis software. In general, the problems associated with Chapters 3, 4, and 9 can be solved
More informationGCI60 Hampton Cast Iron Pellet Insert
CI60 Hampton Cast Iron Pellet Insert 26 7 8 24 ¾ 16 3 8 43 3 16 33 9 16 41 7 8 11 ¾ 22 15 16 12 ¾ FI60 Wood Pellet Insert INSTALLED AS A FIREPLACE INSERT STOVE MODEL (FPI) / A INSTALLE COMME UN MODELE
More informationThe Inspection Process. Waxhaw N.C.
The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"
More informationInstallation Instructions. High-Temperature, Factory Insulated Double-Wall Masonry Relining system 5" Round 6", 8" Round and Oval.
Installation Instructions High-Temperature, Factory Insulated Double-Wall Masonry Relining system 5" Round 6", 8" Round and Oval DuraLiner A MAJOR CAUSE OF VENT RELATED FIRES IS FAILURE TO MAINTAIN REQUIRED
More informationDownsizing a Claus Sulfur Recovery Unit
INFRASTRUCTURE MINING & METALS NUCLEAR, SECURITY & ENVIRONMENTAL Downsizing a Claus Sulfur Recovery Unit OIL, GAS & CHEMICALS By Charles L. Kimtantas and Martin A. Taylor ckimtant@bechtel.com & mataylo1@bechtel.com
More informationMODEL IPIC SERIES 4G GREASE DUCT
INSTALLATION AND MAINTENANCE INSTRUCTIONS WALMART APPLICATION 637N MODEL IPIC SERIES 4G GREASE DUCT 7N71 IT IS OF THE UTMOST IMPORTANCE THAT THIS DUCT BE INSTALLED ONLY IN ACCORDANCE WITH THESE INSTRUCTIONS.
More informationPIPE
The highest quality stainless steel liners at the best prices in the industry. The Lifetime Mission At Lifetime Chimney Supply, we make the highest quality stainless steel chimney liners, sell them at
More informationCITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures
CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person
More informationContact the Jurisdictional Engineer for materials allowed by each jurisdiction.
Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the
More informationABSTRACT I. INTRODUCTION II. METHODS AND MATERIAL
2017 IJSRSET Volume 3 Issue 2 Print ISSN: 2395-1990 Online ISSN : 2394-4099 Themed Section: Engineering and Technology Chiller and AHU Design for A commercial Usage S M Azfar Hashmi, Mirza Muneer Baig,
More informationSECTION CLAY BARREL TILE ROOFING. A. American Society for Testing and Materials (ASTM):
SECTION 07320 CLAY BARREL TILE ROOFING PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02072 - Removals. 2. 07600 - Flashing and Sheet Metal. 1.02 REFERENCES A. American Society for Testing and Materials
More informationLOGIC FLUE & ACCESSORIES GUIDE.
& ACCESSORIES GUIDE. COMBI C COMBI ESP1 + COMBI C SYSTEM S + SYSTEM S HEAT H + HEAT H CODE COMBI ESP1 WWW.IDEALBOILERS.COM This manual is for guidance only and must be read in conjunction with the Installation
More informationCHAPTER 26 PLASTIC SECTION BC 2601 SECTION BC 2603 GENERAL FOAM PLASTIC INSULATION
CHAPTER 26 PLASTIC SECTION BC 2601 GENERAL 2601.1 Scope. These provisions shall govern the materials, design, application, construction and installation of foam plastic, foam plastic insulation, plastic
More informationNOTE: Some guidance on a performance approach to natural ventilation systems design is provided in the Supplement to this Standard.
19 SECTION 3 NATURAL VENTILATION 3.1 SCOPE OF SECTION This Section specifies the means of achieving the quantity of outdoor air required in a naturally ventilated enclosure. The provisions described include
More informationDetails for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses
Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses Released May 20, 2009 Updated March 9, 2011 Introduction: Wood frame structures with attached brick masonry veneer
More informationSECTION SLOPED TRANSLUCENT METAL SKYLIGHT SYSTEM
PART 1- GENERAL 1.1 SUMMARY A. Section Includes: SECTION 084523 - SLOPED TRANSLUCENT METAL SKYLIGHT SYSTEM 1. Flat factory prefabricated structural insulated translucent sandwich panels; with glazed endwalls.
More informationRead Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED
Chapter 17 Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.1.1 Applicability The regulations in this chapter apply to any private potable water supply system where plumbing fixtures are
More informationTested to BS EN and BS EN 1443
Tested to BS EN 1856-2 and BS EN 1443 Introduction Page 2 Midtherm Flue Systems Limited is an independent British manufacturing company producing a wide range of flue and chimney products, along with associated
More informationAir flue duct for use with ecotec boilers
For the installer Flue installation instructions Air flue duct for use with ecotec boilers Concentric System Ø 80/5 (Galvanized steel air duct/plastic flue duct) GB Contents Notes on the documentation
More informationLOGIC FLUE & ACCESSORIES GUIDE.
& ACCESSORIES GUIDE. COMBI C COMBI ESP1 + COMBI C SYSTEM S + SYSTEM S HEAT H + HEAT H CODE COMBI ESP1 WWW.IDEALBOILERS.COM This manual is for guidance only and must be read in conjunction with the Installation
More informationTECHNICAL INFORMATION
TECHNICAL INFORMATION SECTION 07320 TWO-PIECE TAPERED MISSION CLAY ROOFING TILE PART 1 GENERAL 1.01 SECTION INCLUDES A. Formed clay roofing tiles, complete with components and other required accessories
More informationNFPA STANDARDS DEVELOPMENT SITE
of 34 http://submittals.nfpa.org/terraviewweb/contentfetcher?contentid=/te... 1/20/2017 12:55 PM NFPA STANDARDS DEVELOPMENT SITE Released Version Closing Date: January 16, 2017 NOTE: All Public Comment
More informationXtratherm Thin-R Partial Fill Cavity Wall Board (XT/CW Grade)
CERTIFICATE NO. 03/0183 DETAIL SHEET 1 Xtratherm Thin-R Partial Fill Cavity Wall Board (XT/CW Grade) PRODUCT DESCRIPTION This Detail Sheet relates to Xtratherm Thin-R Partial Fill Cavity Wall Board, as
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 22 1319 - SANITARY WASTE PIPING SPECIALTIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationCombustible Exterior Wall Cladding Systems: An ICC Perspective
Combustible Exterior Wall Cladding Systems: An ICC Perspective The tragic Grenfell Tower fire in London brought extensive public focus on combustible exterior wall systems, often called cladding, prompting
More informationRockwool Blown Cavity Wall Insulation System
CI/SfB (21) K IRISH AGRÉMENT BOARD CERTIFICATE NO. 05/0222 Rockwool Ltd., Unit 11, Northwood Court, Santry, Dublin 9. Tel: 01 4038456 Fax: 01 4038457 Email: info@rockwool.ie Rockwool Blown Cavity Wall
More informationConcentric Vent/Air System Supplement
Concentric Vent/Air System Supplement This document is intended to be used by a qualified heating contractor or service technician. Read all instructions within this document and within the CHAL- LENGER
More informationCORROSION ENGINEERING SPECIFICATION FOR INSTALLATION SPECIFICATION FOR CONCRETE VESSELS DESIGNED TO RECEIVE BRICK OR MEMBRANE AND BRICK LINING
AN ERGONARMOR COMPANY TECHNICAL INFORMATION CES-301 03/00 SUPERSEDES 02/99 PAGE 1 OF 5 CORROSION ENGINEERING SPECIFICATION FOR INSTALLATION SPECIFICATION FOR CONCRETE VESSELS DESIGNED TO RECEIVE BRICK
More informationTHE BUILDING BLOCKS FOR LUXURY OUTDOOR SPACES.
THE BUILDING BLOCKS FOR LUXURY OUTDOOR SPACES. THERE S NOTHING QUITE LIKE enjoying the pleasures of an evening dining alfresco. Extending your living space to the outdoors is no longer just a trend, but
More informationDDK DUCT (IN-SLAB DUCT SYSTEM)
DDK DUCT (IN-SLAB DUCT SYSTEM) General information Components Fan sizing table Testing data MAX 3-H F & FT RATING Tested in accordance with ULC S115-M95 and ASTM E814-02 Distributed by: Dennis D.Kiselbach
More informationROXUL Blanket (and Batt) Insulation Section Master Guide Specification (AFB) Page 1 April 2015
Master Guide Specification (AFB) Page 1 Click on the pilcrow in the MS Word Toolbar to toggle ROXUL GUIDE NOTES on and off. Delete this text before incorporating the section into a Project Manual. 1 GENERAL
More informationNJ AIHA CIH Review Industrial Ventilation
NJ AIHA CIH Review Industrial Ventilation Thomas Block, CIH MPH tblock@aps.rutgers.edu 848-445-2550 2016 American Industrial Hygiene Association, New Jersey Section, Inc. Course Objectives At the end of
More informationA. Source Limitations: Obtain each type of building insulation through one source.
SECTION 07210 - BUILDING INSULATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationCopper and Copper Alloy Tube, Pipe and Fittings COPPER and COPPER ALLOY TUBE and PIPE Seamless Copper Pipe: Copper pipe is almost pure copper manufactured to the requirements of ASTM B 42 - Standard Specification
More informationCopyright 2017, ProVent Systems Inc., All Rights Reserved
Copyright 2017, ProVent Systems Inc., All Rights Reserved Introduction to ProVent Systems A PVC Plastic Single Stack Waste and Vent System The ProVent System is a plumbing engineered single stack system
More informationOvalizing Flexible Liners
Installation Instructions FasNSeal Flex DuraFlex SW Ventinox Ovalizing Flexible Liners A MAJOR CAUSE OF VENT RELATED FIRES IS FAILURE TO MAINTAIN REQUIRED CLEARANCES (AIR SPACES) TO COMBUSTIBLE MATERIALS.
More informationSECTION UNIT PRICES. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 012200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationSECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS
SECTION 270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Communications equipment coordination and installation. 2. Sleeves for pathways and cables. 3. Raceway
More informationInstallation instruction
Installation instruction Ci51 www.contura.eu 114 CERTIFICATE Declaration of performance according to Regulation (EU) 305/2011 No. Ci51-CPR-150821-SE-2 PRODUCT Product type Type designation Manufacturing
More informationAPPENDIX 6 (not yet reviewed by UCCS) STRUCTURAL ANALYSIS/VIBRATION CRITERIA
APPENDIX 6 (not yet reviewed by UCCS) STRUCTURAL ANALYSIS/VIBRATION CRITERIA GENERAL The purpose of this standard is to identify structural submittal requirements, as well as identify vibration design
More informationBuilding Codes and Ordinances ARC 227
Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction 03.02.10 Instructor: Rick Staub, AIA Email: staub@pointonearchitects.com Phone: 860-434-7707 Fire Resistive Construction Passive
More informationAPPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS)
101050.22.RP.0001 A Environmental Impact Statement 15 th April 2005 APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS) S:\Projects\190900\101050
More informationDIVISION 04 MASONRY CAST STONE. A. Design Considerations. 1. Cast stone shall comply with ASTM C1364, Standard Specification for Cast Stone.
DIVISION 04 MASONRY 04720 CAST STONE A. Design Considerations 1. Cast stone shall comply with ASTM C1364, Standard Specification for Cast Stone. 2. Care must be taken in the design of individual units
More informationEPA Method 1 Field Procedures Example:
EPA Method 1 Field Procedures Step Instruction 100 Is the stack or duct circular or square/rectangle? If square/rectangular go to step 170. 105 Determine the diameter of the stack from one of the following