1 TPDES Program & Effluent Limit Guidelines April 11, 2011 Philip Handley Storm Water Construction Supervisor
2 Page 1 Topics TPDES Permit Requirements & Enforcement Construction on the Edwards Aquifer EPA Effluent Guidelines for Construction
3 Page 2 TPDES Permit Filing Fee with TCEQ $325 for paper NOIs - 7 days from the postmark $225 for electronic NOIs - Immediate coverage after confirmation of receipt No Annual billing No SAWS Permit or Fee Bexar Co. now Phase II MS4 program and they have permit and fee
4 Page 3 epermits State of Texas Environmental Electronic Reporting System (STEERS) Must sign up with STEERS Only open to those with TX DL
5 Page 4 SWPPP The Storm Water Pollution Prevention Plan (SWPPP) is a working, dynamic document. The SWPPP describes to you: What to do How to do it When to do it Currently to Maximum Extent Practical (MEP) design standard
6 SWPPP Page 5 SWPPP must contain information that meets the requirements of the TPDES Construction General Permit TXR150000: Site Description Erosion and Sedimentation Controls Stabilization Practices Structural Control Practices Permanent Storm Water Controls Other Controls
7 Page 6 SWPPP SWPPP must contain information that meets the requirements of the TPDES Construction General Permit TXR150000: Approved State and Local Plans (example WPAP) Maintenance Inspection of Controls Non-Storm Water Discharges
8 Page 7 SWPPP Reporting Inspections must be conducted: At least once every fourteen (14) calendar days AND within twenty four (24) hours of the end of a storm event of 0.5 inches or greater. OR At least once every seven (7) calendar days, on a specifically defined day, regardless of whether or not there has been a rainfall event since the previous inspection.
9 Page 8 SWPPP Signatory Requirements Notice of Intent or Construction Site Notice requires signature Meet signatory requirements in the manner required by 30 TAC Engineer Seal or other Certification Seal not currently required for SWPPP in San Antonio Bexar Co. S.W. Program requires Engineer Seal on SWPPP.
10 Page 9 SWPPP Inspection Report
11 Page 10 Inspector Qualifications Permit, Page 3, 7 (a) Inspection of Controls Personnel conducting these inspections must be knowledgeable of the general permit, familiar with the construction site and knowledgeable of the SWP3 for site. Changing requirements in future TPDES Permit may require more qualifications (Certification)
12 Page 11 Inspection Delegation of Authority If the inspector does not meet signatory requirements, the inspector can be delegated this authority through a letter of delegation. The letter of delegation, signed by a company official that meets signatory authority, authorizes the inspector to sign the inspection reports.
13 Page 12 SWPPP Reporting Include the Letter of Delegation with the SWPPP
14 Page 13 SAN ANTONIO ORDINANCE STORM WATER COMPLIANCE FOR CONSTRUCTION ACTIVITY
15 Page 14 Ordinance Purpose: To reduce pollutants introduced into the MS4 as required by the State Permit (TPDES Construction General Permit TXR150000)
16 Page 15 Ordinance SAWS designated as enforcement staff Directs use of BMPs on construction sites (all-no acreage/size limit) Requires SWPPPs to be available for on-site for inspection SAWS has authority to enforce within City Limits and 5,000 feet beyond Provides penalties
17 Page 16 Ordinance Field Correction Notice
18 Ordinance Field Correction Notice Page 17
19 Page 18 Ordinance Enforcement A violation may result in a Field Corrective Notice 1st 24 hour period to remove and remediate offending material or comply with compliance action 2nd 24 hour period to install or repair corrective BMPs or ensure action If no action is taken
20 Ordinance Enforcement Page 19 Stop Work Order Results when FCN corrections are not made in a timely manner ALL WORK STOPS
21 Page 20 Edwards Aquifer Primary source of drinking water for San Antonio and the surrounding region Serving approximately 1.7 million people Extends from Williamson County, north of Austin through Kinney County, west of San Antonio
22 Page 21 Edwards Aquifer LEGEND Green=Contributing Zone Light Pink=Recharge Zone Dark Pink=Transition Zone
23 Page 22 Edwards Aquifer Protection Program Regulates activities over the Recharge, Transition and Contributing Zone of the Edwards Aquifer Water Pollution Abatement Plans Required Each operator covered by an Edwards Plan must maintain a copy of the approved plan and the approval letter for that plan on-site
24 Page 23 Edwards Plans All plans are required to be developed in accordance with the Edwards Aquifer Protection Program rules and Guidance Documents Portions of the plans need to be signed and sealed by Professional Engineers and Geologists licensed by the State of Texas
25 Page 24 Inspection Frequency Every 7 days and after each ½ inch rain fall Daily inspections may be warranted when sensitive features are located on or adjacent to the site
26 ELG & Changes coming for MS4 s With EPA rule on Effluent Limit Guidelines (ELG) changes will occur with SW Permits & how MS4 s will need to manage SWPPP & NPDES Page 25 SWPPP design moves from Maximum Extent Practical to Performance Based Design
27 Page 26 USEPA ELG for Construction Sites Effluent Limit Guidelines (ELG) for construction and development sites All Industries have identified discharge limits on various constituents based on characterization of their operation function Construction Industry-had none EPA decided to remove ELG from requirement, got sued for action, then required by Fed. Court to develop ELG
28 ELG For Construction Chronology of events: Dec EPA issues numeric limit for turbidity-final Effluent Guideline Rule for Construction and Development Established National Monitoring Requirement Enforceable Numeric Limitations on Storm Water Discharge (Turbidity-280 NTU) NTU: Nephelometric Turbidity Units Page 27
29 ELG for Construction-Chronology Page (later in the year after rule promulgated). EPA withdrew the limit to correct calculation errors identified by petitions filed by Small Business Administration and the National Assoc. of Home Builders
30 ELG for Construction-Chronology Dec Page 29 EPA submitted a proposed Rule to revised turbidity limit to the Office of Management and Budget (OMB) 2011 EPA recently withdrew this proposal from OMB EPA decided to seek additional treatment performance data before proposing a revised turbidity limit
31 ELG for Construction-Chronology Jan.3, 2012-EPA published Fed. Register notice requesting additional data from development sites before proposing a revised Turbidity Limit Page 30 Jan. 4, 2012-EPA Stayed the numeric limit of 280 NTU published in Dec. 1, 2009, Const. & Develop. ELG FUTURE: EPA will propose a revised limit in a future rule making
32 ELG-What is going on? Page 31 Turbidity
33 ELG-What is going on? Page 32 What is the complication? Turbidimeters: EPA Standard Methodologies are for Table Turbidimeters and field sampling will be conducted with portable Turbidimeters.
34 ELG-What is going on? Storm Water Technology (BMP s) ASTM standards for S.W. BMP s-no turbidity data Testing laboratories (Universities) test S.W. BMP s by measuring total percentage of sediment retained in controlled lab testing Re-tooling the Testing Industry Create S.W. BMP Tool Box of data Page 33
35 Page 34 Texas A&M Texas Transportation Institute
36 ELG and SWPPP Design With the EPA ELG Rule, design of SWPPP will move from designs of Maximum Extent Practical To.. Performance Based Design What does this mean? Persons designing SWPPP will now need to utilize storm water and soil engineering expertise (soil/civil engineers, CPESC, etc.) Page 35
37 ELG and SWPPP Design It s about the SOIL! Hydraulics.Manning s Formula/Coefficient Still need it? YES However, you will need to also know: Soil characterization and identification Mechanics of erosion, sediment transport and sedimentation Calculating sediment yields Page 36
38 ELG and SWPPP Design RUSLE Calculations Revised Universal Soil Loss Equation A=(R) (K) (LS) (C) (P) A=Area R=Erosive power of Rain K=Soil Erodibility LS=Land slope and length C=Degree of Soil Cover P=Conservation Practices Page 37
39 ELG and SWPPP Design MUSLE Calculations Modified Universal Soil Loss Equation Developed to relate storm-period sediment yields to upland soil loss rates indexed by USLE erodibility factors and transport efficiency of surface runoff indexed by a function of the product of total storm runoff volume and peak runoff rate. Page 38
40 ELG and SWPPP Design Treatment Train Design to meet discharge Water quality (a future revised NTU) Rain Parameter: most significant factor causing sheet erosion is raindrop impact (typical rain drop is around 1/16 th Inch and travels at terminal velocity of about 18 feet per second) Page 39 Soil Parameter: Shearing force of flowing water is most important in rill and gully erosion
41 ELG and SWPPP Design Page 40 When and how does Erosion begin?
42 ELG and SWPPP Design Raindrop typical size: 1/16 to 1/4 dia. Fall velocity: 18 ft/sec. or about 20 mph Page 41
43 ELG and SWPPP Design Raindrop Impact on Soil (example diagram) Splash Pattern: Page 42
44 ELG and SWPPP Design Erosion Control begins at The source (raindrops impact Bare soil). Page 43 Sediment Control begins down Slope of the erosion source and Terminates in a discharge point/water resource
45 ELG and SWPPP Design Page 44 Light Soils- Smaller granular size Less material but greater turbidity Reading than larger clay soils Dark Soils- Larger granular size More material but clays suspend
46 ELG and SWPPP Design Page 45
47 Guidelines TPDES Program & Effluent Limit Philip Handley Philip Handley Storm Water Construction Supervisor Storm Water Construction Supervisor
Starting Construction: Your Storm Water Permit
Starting Construction: Your Storm Water Permit Asma Vahora Compliance Assistance Specialist Small Business and Local Government Assistance San Antonio- Region 13 210-403-4039 Asma.Vahora@tceq.texas.gov
More informationStarting Construction: Your Storm Water Permit
Starting Construction: Your Storm Water Permit Asma Vahora Compliance Assistance Specialist Small Business and Local Government Assistance San Antonio- Region 13 210-403-4039 Asma.Vahora@tceq.texas.gov
More informationTexas Department of Transportation Book 2 - Technical Provisions. IH 35E Managed Lanes Project. Attachment 4-3
Texas Department of Transportation Book 2 - Technical Provisions IH 35E Managed Lanes Project Attachment 4-3 Form 2448 IH 35E Managed Lanes Project Book 2 - Technical Provisions Attachment 4-3 Show Form
More informationHarris County Pollution Control Services Department
Harris County Pollution Control Services Department Industrial Storm Water Inspections July 24, 2013 Nuguent Cotton, Field Manager Pollution Control Services In compliance with Harris County s TPDES MS4
More information901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT
SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants
More information.. / '\1 r.;... ~ -.. ~ /\ c~v TEXAS COMMISSION ON ENVIRONMENTAL QUALITY. Protecting Texas by Reducing and Preventing Pollution.
B1yan W. Shaw, Ph.D., P.E., Chairman Toby Baker, Commissioner Zak Covar, Commissioner Richard A. Hyde, P.E., Executive Director.. / ~ '\1 r.;... ~ -.. ~ /\ c~v TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
More informationTexas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions
Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance
More informationAppendix B Stormwater Pollution Prevention Plan Outline
Outline Annotated Outline of SWPPP Components to meet General Permit Requirements This appendix presents a recommended structure for a traditional construction site Stormwater Pollution Prevention Plan
More informationStormwater Construction General Permit CGP-2013
Stormwater Construction General Permit CGP-2013 Stormwater Construction General Permit (CGP) Stormwater Outreach for Regional Municipalities MS4 Statewide Summit June 18, 2013 Prepared by Chris Henninger
More informationReign Consulting Presents
Reign Consulting Presents COVERED TOPICS 1. Introduction and Legal 2. Small MS4 Permit 3. Risk 4. Discharges 5. What to expect 6. How to prepare 7. Conclusion INTRODUCTION AND LEGAL INTRODUCTION GOAL =
More informationQSD/QSP Training Module 9 SWPPP Preparation
QSD/QSP Training Module 9 SWPPP Preparation Anna Lantin, P.E., CPESC, CPSWQ Overview and Learning Objectives Given a project Risk Level or LUP Type, you will learn to: Prepare a compliant SWPPP Determine
More informationPreparing for a Stormwater Comprehensive Compliance Investigation (CCI) Part I. Presented by: Jack Higginbotham
Preparing for a Stormwater Comprehensive Compliance Investigation (CCI) Part I Presented by: Jack Higginbotham Jack Higginbotham Senior Environmental Investigator TCEQ Region 13 San Antonio Office 14250
More informationNorth Carolina Sedimentation Control Law
1 North Carolina Sedimentation Control Law North Carolina Sediment Control Law 1 North Carolina Sedimentation Control Law The purpose of this section is to highlight the portions of the North Carolina
More informationThe NPDES Storm Water Permit - Chasing Dirt. March 18, 2014 WaterCon 14 - Springfield
The NPDES Storm Water Permit - Chasing Dirt March 18, 2014 WaterCon 14 - Springfield Today s Topics FOS Perspective A. SW NPDES History and Purpose B. NOI Notice of Intent to Construct C. SW Pollution
More informationInnovative Storm Water Program Implementation
Innovative Storm Water Program Implementation US Environmental Protection Agency, Region III Water Protection Division 1650 Arch Street Philadelphia, PA 19103 EPA Storm Water Contacts: Region III SW Coordinator
More informationPhase II MS4 Annual Report Transmittal for Fort Bend County Municipal Utility District No TPDES Permit Number: TXR040319
Rebecca Villalba, Team Leader Texas Commission on Environmental Quality Storm Water and Pretreatment Team (MC-148) P.O. Box 13087 Austin, Texas 78711-3087 Re: Phase II MS4 Annual Report Transmittal for
More informationTPDES INDUSTRIAL STORMWATER MULTI-SECTOR GENERAL PERMIT (TXR050000) Lindsay Garza. Stormwater and Pretreatment Team Water Quality Division
TPDES INDUSTRIAL STORMWATER MULTI-SECTOR GENERAL PERMIT (TXR050000) Lindsay Garza Stormwater and Pretreatment Team Water Quality Division INDUSTRIAL STORMWATER PERMIT APPLICABILITY If a facility discharges
More informationKey Requirements of the Construction General Permit Scott Taylor, P.E. Tanya Bilezikjian, P.E.
Key Requirements of the Construction General Permit Scott Taylor, P.E. Tanya Bilezikjian, P.E. Learning Objectives Course participants shall be able to: Recognize basic permit elements Recognize the need
More informationLOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum
LOUISIANA URBAN STORMWATER COALITION EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum SWPPP NOTIFICATION SIGN Post sign at entrance of site or areas where the public can easily access.
More informationAngelo State University. Stormwater Management Program. TPDES No. TXR040000
Angelo State University Stormwater Management Program TPDES No. TXR040000 October 2014 As Amended June 2017 TABLE OF CONTENTS Table of Contents... ii Table of Changes...iv Commonly Used Acronyms...vi 1.
More information11 Ways to Avoid Storm Water Fines. No Exceptions!
11 Ways to Avoid Storm Water Fines Do not start until you have gone over this with a SWPPP Rep. No Exceptions! 1. Contact Mark Atwood at 801-319-1331 or Jake Pettersson at 801-709-4463. 2. Submit a Notice
More informationClean Water Act Industrial Stormwater Applicability Flowchart. July 2009
Clean Water Act Industrial Stormwater Applicability Flowchart July 2009 Office of Compliance Office of Enforcement and Compliance Assurance U.S. Environmental Protection Agency 1200 Pennsylvania Avenue,
More informationSACHSE EROSION CONTROL GUIDELINES
SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the
More informationEL PASO COUNTY TEXAS POLLUTANT DISCHARGE ELIMINATION SYSTEM (TPDES) MANAGEMENT PROGRAM. Section I Overview 1. Storm Water Rule Overview.
EL PASO COUNTY TEXAS POLLUTANT DISCHARGE ELIMINATION SYSTEM (TPDES) MANAGEMENT PROGRAM TABLE OF CONTENTS Section I Overview 1. Storm Water Rule Overview. 2 Section II Permit Applicability and Coverage
More informationThe Solution to Pollution is Dilution
The Solution to Pollution is Dilution The cornerstone of surface water quality protection in the United States gave EPA the authority to implement pollution control programs and... established the basic
More informationUnderstanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More informationTPDES General Permit #TXR EL PASO COUNTY Storm Water Management Program
TPDES General Permit #TXR040000 EL PASO COUNTY Storm Water Management Program Permit Year 2007-2012 Storm Water Management Program El Paso County, Texas EL PASO COUNTY TEXAS POLLUTANT DISCHARGE ELIMINATION
More informationModule 7: When Things Deviate from the Plan!
Continuing Education Associated with Maintaining CPESC and CESSWI Certification Module 7: When Things Deviate from the Plan! Sponsors: ODOT Local Technical Assistance Program (LTAP) November 2012 March
More informationSAWS Annual Irrigation Checkup -- FAQs
SAWS Annual Irrigation Checkup -- FAQs 1. What is the SAWS Annual Irrigation Checkup requirement? In an effort to maximize year-round water conservation efforts, the San Antonio City Council passed a water
More informationResponsible Person to Implement or Coordinate this Minimum Control Measure: County Planning and Development Director.
4.0 CONSTRUCTION SITE RUNOFF CONTROL Responsible Person to Implement or Coordinate this Minimum Control Measure: County Planning and Development Director. The purpose of construction site runoff controls
More informationCity: Stormwaterville Zip Code: County: Addison. City: Stormwaterville Zip Code: County: Addison
NOTICE OF INTENT TO USE GENERIC PERMIT FOR DISCHARGE OF STORMWATER FROM PHASE II MUNICIPAL SEPARATE STORM SEWER SYSTEMS (RULE 62-621.300(7)(b), F.A.C.) For FDEP Internal Use Only Permit : FLR INSTRUCTIONS:
More informationNPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions. ( ) - ext. ( ) - ext. Owner Name Telephone Fax
NPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions MPCA use only White-MPCA Canary-Site copy Delta record Project Name / Location MN R100001-C000 Stormwater
More informationIngham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI PH. (517) FAX (517)
Date Issued Ingham County Drain Commissioner Patrick E. Lindemann 707 BUHL AVENUE P. O. BOX 220 MASON MI 48854 PH. (517) 676-8395 FAX (517) 676-8364 APPLICATION FOR SOIL EROSION AND SEDIMENTATION POLLUTION
More informationCPS Energy Environmental Documentation Requirements
CPS Energy Environmental Documentation Requirements This document contains the requirements CPS Energy will be incorporating into its design process for developer/customer requests for service. These requirements
More informationLarge-Scale Sediment Retention Device Testing (ASTM D 7351) FLEXSTORM Inlet Filter
Large-Scale Sediment Retention Device Testing (ASTM D 7351) of FLEXSTORM Inlet Filter February 2009 Submitted to: Inlet & Pipe Protection, Inc. 24137 W. 111 th St., Unit A Naperville, IL 60564 Attn: Mr.
More informationJames Ferrell 10/3/07 Page 2
October 15, 2007 James Ferrell 103 Sandal Court Hot Springs, Arkansas 71913 RE: Construction Site at 5552 Central Avenue NPDES Permit No.: ARR150000 Dear Mr. Ferrell: On October 8, 2007,, I performed a
More informationAPPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT
APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:
More informationWELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR
WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR All the documents shown today are in the MN Stormwater Manual on the page titled 2018 Construction Stormwater Permit Public Notice and Public Informational
More informationVirginia Stormwater Management Permitting
Virginia Stormwater Management Permitting Construction Activities J. Douglas Fritz Overview of VSMP Construction Stormwater Permitting Discharges from regulated Construction Activities are industrial discharges
More informationNPDES Permit No: AR , Routine Compliance Inspection
May 26, 2009 Dallas Ray Goad, Superintendent City Of Bradford 308 B, W. Walnut St Bradford, AR 72020 AFIN: 73-00072 NPDES Permit No: AR0050911, Routine Compliance Inspection Dear Mr. Goad: On May 20, 2009,
More informationRichland County Department of Public Works Engineering (Land Development) Division
Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or
More informationVIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION. FORM B - ANIMAL FEEDING OPERATIONS (AFOs)
VIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION FORM B - ANIMAL FEEDING OPERATIONS (AFOs) Department of Environmental Quality Rev. 02-2013 VIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION FORM
More informationSTORM WATER QUALITY MANAGEMENT
REGULATIONS OF HARRIS COUNTY, TEXAS FOR STORM WATER QUALITY MANAGEMENT AS ADOPTED AUGUST 21, 2001 AMENDED SEPTEMBER 25, 2001 EFFECTIVE OCTOBER 1, 2001 AMENDED APRIL 13, 2004 AMENDEND MAY 1, 2011 HARRIS
More informationRichland County Industrial and High Risk Runoff Program. Alan Trim BP Barber
Richland County Industrial and High Risk Runoff Program Alan Trim Industrial and High Risk Runoff Program Program Components: Richland County Storm Water Ordinance. Industrial and High Risk Facility Database.
More informationErosion & Sedimentation Control Policy
Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of
More informationUMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist
UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from
More informationStorm Water Pollution Prevention Plan (SWPPP) for Small Construction Sites
for Small Construction Sites *(Please note this document is intended for guidance only and does not ensure permit compliance.) PROJECT NAME: Single Family Residence PROJECT SITE: XXXX Subdivision LOT #
More informationForney Stadium Improvements in Forney, Texas
STORM WATER POLLUTION PREVENTION PLAN for CONSTRUCTION ACTIVITIES associated with Forney Stadium Improvements in Forney, Texas Prepared: April 27, 2004 By: Don Wims President of SWPPP INSPECTIONS, INC.
More informationConcrete Waste Management
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationStormwater Management Program Plan (SWMPP) NPDES Permit ALR Revised May 31, Prepared By:
City of Fultondale 1210 Walker Chapel Road P.O. Box 699 Fultondale, Al 35068 Stormwater Management Program Plan () Revised May 31, 2017 Prepared By: 7110 University Court, Montgomery, Alabama 36117 (THIS
More informationSeptember 26, RE: Waste Water Treatment System. Dear Mr. Starks:
September 26, 2008 Leon Starks, Director of Maintenance Arkansas Department of Correction East Arkansas Regional Unit 7800 Correction Circle Pine Bluff, Arkansas 71603 RE: Waste Water Treatment System
More informationSouth Carolina
www.scdhec.gov/water South Carolina NPDES GENERAL PERMIT FOR STORMWATER DISCHARGES FROM SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION CONSTRUCTION ACTIVITIES In compliance with the provisions of the SC Pollution
More informationSAWS Role In Development of the Edwards Aquifer Recharge Zone
SAWS Role In Development of the Edwards Aquifer Recharge Zone Presented by Annalisa Peace and Ron Green on behalf of the Greater Edwards Aquifer Alliance to the SAWS Board Development Task Force October
More informationALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT (ADEM) NOTICE OF INTENT NPDES GENERAL PERMIT NUMBER ALG850000
ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT (ADEM) NOTICE OF INTENT NPDES GENERAL PERMIT NUMBER ALG850000 Instructions: This form should be used to submit a Notice of Intent for coverage under NPDES
More informationShelbyville, KY Stormwater Best Management Practices January Appendix F EPSC Qualified Contractor Forms
Shelbyville, KY Stormwater Best Management Practices January 2013 EPSC Qualified Contractor Forms City of Shelbyville EPSC Contractor Qualifications: Description The Storm Water Ordinance adopted by the
More informationSmall Site Stormwater Quality Permit Application
Small Site Stormwater Quality Permit Application PUBLIC WORKS ADMINISTRATION BUILDING (PWA) STORMWATER DIVISION 2525 WEST FIRST STREET LOVELAND, CO 80537 GENERAL INFORMATION (970) 962-2772 www.cityofloveland.org/stormwater
More informationElements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)
Elements of the Storm Water Management Plan Storm Water Pollution Prevention Plan (SWPPP) Small Construction Site Storm Water Management Rodney Hendrick Water Quality Specialist LSU Ag Center Plan Requirements
More informationSTATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION GENERIC PERMIT FOR DISCHARGE OF STORMWATER FROM PHASE II
STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION GENERIC PERMIT FOR DISCHARGE OF STORMWATER FROM PHASE II MUNICIPAL SEPARATE STORM SEWER SYSTEMS May 1, 2003 1 Generic Permit for Discharge of Stormwater
More informationUNDERSTANDING THE LAW. In Pennsylvania, both state and federal law govern water pollution caused by stormwater. We briefly examine both.
UNDERSTANDING THE LAW In Pennsylvania, both state and federal law govern water pollution caused by stormwater. We briefly examine both. FEDERAL REQUIREMENTS In the United States, the Environmental Protection
More informationJEFFERSON COUNTY STORM WATER MANAGEMENT
JEFFERSON COUNTY STORM WATER MANAGEMENT B-210 Courthouse, Birmingham, Alabama 35203 Telephone: (205) 325-8741 Erosion and Sedimentation Control Measures for Commercial Projects (Plans Requirements) -All
More informationRE: Complaint Investigation at Highway 282 near Mountainburg in Crawford County
October 8, 2010 Mr. Jimmy Johnson, Engineer City of Fort Smith Utilities Department 3900 Kelley Highway Fort Smith, AR 72904 RE: Complaint Investigation at Highway 282 near Mountainburg in Crawford County
More informationSECTION EROSION AND SEDIMENTATION CONTROLS
SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL
More informationNEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL
NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by
More informationSoil Erosion Control Soil Erosion Control
Ordinance 1 FILLMORE COUNTY SOIL EROSION CONTROL ORDINANCE ADOPTED 1982 AMENDED 1990 AMENDED 1994 AMENDED 1996 2 FILLMORE COUNTY SOIL EROSION CONTROL ORDINANCE AN ORDINANCE REQUIRING THAT FARMING PRACTICES
More informationSTORMWATER POLLUTION PREVENTION PLAN (SWP3)
City of Moore, Oklahoma Community Development Department 301 North Broadway Moore, Oklahoma 73160 STORMWATER POLLUTION PREVENTION PLAN (SWP3) The SWP3 is a written narrative describing the site, potential
More informationSECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL
SECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL Subdivision 1: Purpose Subdivision 2: Scope Subdivision 3: Definitions Subdivision 4: Permit Application and Plan Subdivision 5: Stormwater Pollution
More informationiswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1
City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June 2010... Chapter 1 i CITY OF AZLE iswm CRITERIA MANUAL FOR SITE DEVELOPMENT AND CONSTRUCTION Incorporating the Regional NCTCOG Integrated
More informationLANCASTER COUNTY Act 167 Frequently Asked Questions (FAQs)
LANCASTER COUNTY Act 167 Frequently Asked Questions (FAQs) DISCLAIMER: The questions and answers outlined in this document are intended to help municipalities comply with Act 167 and other state and federal
More informationFLORENCE COUNTY STORMWATER DESIGN MANUAL
FLORENCE COUNTY STORMWATER DESIGN MANUAL JULY 18, 2013 Resolution No. 02-2013/14 Florence County Council TABLE OF CONTENTS TITLE PAGE NO. SECTION 1. GENERAL 1.1 INTRODUCTION--------------------------------------------------------------------------
More informationKANSAS STORMWATER 2016 ANNUAL REPORT FORM FOR MUNICIPAL SEPARATE STORM SEWER SYSTEMS (MS4s)
KANSAS STORMWATER 2016 ANNUAL REPORT FORM FOR MUNICIPAL SEPARATE STORM SEWER SYSTEMS (MS4s) Permittee Information Check box if this is a new name, address, phone, etc. Permittee (Agency Name) Mailing Address
More informationGUIDELINES FOR PREPARATION OF CAPACITY ANALYSIS REPORTS
GUIDELINES FOR PREPARATION OF CAPACITY ANALYSIS REPORTS Florida Department of Environmental Regulation July 1992 TABLE OF CONTENTS PURPOSE AND APPLICABILITY................... 1 Purpose............................
More informationSTORMWATER MANAGEMENT PROGRAM. Pottawatomie County, Kansas Stormwater Management Program
STORMWATER MANAGEMENT PROGRAM Pottawatomie County, Kansas Stormwater Management Program AGENDA PROJECT BACKGROUND STORMWATER MANAGEMENT PLAN (SMP) ELBO CREEK WATERSHED SAND CREEK WATERSHED HOW IT ALL TIES
More informationConstruction Site Erosion Control and Phase II of the Stormwater Permit Program
Construction Site Erosion Control and Phase II of the Stormwater Permit Program Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa, AL In Georgia,
More informationEvaluation of Compliance ISO 14001:
1. PURPOSE: This document describes the procedure for planning, performing, and documenting periodic internal environmental compliance assessments completed as part of the Office of Quality (OEQ) Compliance
More informationCHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS
CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for
More informationManaging Construction Stormwater: SWRO Contaminated Site Experiences
Managing Construction Stormwater: SWRO Contaminated Site Experiences Carol Serdar, LG Contaminated Construction SW and Hydroelectric WQ Compliance Manager (Water Quality Program SWRO) Managing Stormwater
More informationSTATE OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL
STATE OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL Official Release and Effective: June 2007 Latest Update: July 2013 Prepared for: FLORIDA DEPARTMENT OF TRANSPORTATION & FLORIDA
More informationAppendix C. BMPS, Measurable Goals, and Implementation Schedule
Appendix C BMPS, Measurable Goals, and Implementation MCM 1 Public Education, Outreach and Involvement Public Education and Outreach Residents BMP 1.1 Utility Bill Insert Continue implementation of existing
More informationEROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: (Rev ) SP1 G180
EROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: 1-16-07 (Rev 1-15-08) SP1 G180 General Schedule and conduct construction activities in a manner that will minimize soil erosion and the resulting sedimentation
More informationConstruction Stormwater Compliance: Are You Covered Under the EPA s New 2017 Construction General Permit?
Construction Stormwater Compliance: Are You Covered Under the EPA s New 2017 Construction General Permit? Presented by: Jennifer Hildebrand Environmental Compliance Group Manager WSB and Associates, Inc.
More informationCDPHE/COGCC Stormwater Management Programs
OPERATOR GUIDANCE AND STORMWATER PROGRAMS Document Control: Created Date: May 6, 2015 Last Updated Date: May 6, 2015 Last Updated By: Dave Kulmann Review Cycle: Yearly Review Systems Used: None Document
More informationLOCATION AND DESIGN DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Virginia Stormwater Management Program SPECIFIC SUBJECT: Application of the
More informationCIBOLO CANYON GOLF COURSE ENVIRONMENTAL MANAGEMENT PLAN
CIBOLO CANYON GOLF COURSE ENVIRONMENTAL MANAGEMENT PLAN TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY... 1 2.0 INTRODUCTION... 2 2.1 Purpose... 2 2.2 Goals and Objectives... 2 2.3 Applicability... 3 2.4 Relationship
More informationModule 3. Module 3a. As of July : A lot of local ESC ordinances are out of date! Virginia Erosion & Sediment Control Program
Module 3. Virginia Erosion & Sediment Control Program Module 3a. Statutory and Regulatory Requirements: Virginia Erosion and Sediment Control Law and Regulations As of July 1 2013: A lot of local ESC ordinances
More informationSTORM WATER MANAGEMENT PLAN
STORM WATER MANAGEMENT PLAN Table of Contents Executive Summary ES.1 Overview of pg. ES-1 ES.2 Program Management pg. ES-1 ES.3 Program Development and Implementation pg. ES-1 ES.4 Proposed Strom Water
More informationCustomer Bulletin #117 Water Quality Regulations for property in the Edwards Aquifer Recharge Zone
TO: SUBJECT: Planning and Inspection Services departments Customers Customer Bulletin #117 Water Quality Regulations for property in the Edwards Aquifer Recharge Zone DATE: March 11, 2015, revised May
More informationAppendix G. Stormwater Management Program Subsequent Revisions
Appendix G Stormwater Management Program Subsequent Revisions Annita McCormick From: Annita McCormick Sent: Friday, June 27, 2014 4:32 PM To: 'Jerad Laxson' Subject: RE: McKinney SWMP RFI. Attachments:
More informationSTATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT
STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION
More informationFebruary 17, Jon Myhre Enerco Operating Corporation 6237 Tulip Lane Dallas, TX Fouke # D-3 SWD System Inspection (Miller Co)
February 17, 2015 Jon Myhre Enerco Operating Corporation 6237 Tulip Lane Dallas, TX 75230 RE: Fouke # D-3 SWD System Inspection (Miller Co) AFIN: 46-00279 State Permit No.: 0572-WG-SW-2 Dear Mr. Myhre:
More informationState of Georgia Department of Natural Resources Environmental Protection Division
General Permit No. GAR100000 State of Georgia Department of Natural Resources Environmental Protection Division Authorization To Discharge Under The National Pollutant Discharge Elimination System Storm
More informationSTORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW
SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission
More informationCHAPTER 2 EROSION CONTROL
CHAPTER 2 EROSION CONTROL 2.1 EROSION AND EROSION CONTROL Understanding Erosion Erosion occurs when soil particles are detached from the land surface and carried downslope by moving water. Figure 2.1-1
More informationLandfills And The New Virginia Stormwater Management Program Regulations
Landfills And The New Virginia Stormwater Management Program Regulations Agenda Overview of regulatory programs Specific guidance from DEQ Quiz Questions and Answers Why Is this such a hot topic? NEW REGULATIONS
More informationPierce County Public Works & Utilities Road Operations Division. Pierce County ROAD MAINTENANCE NPDES COMPLIANCE AND ASSET MANAGEMENT
Pierce County Public Works & Utilities Road Operations Division Pierce County ROAD MAINTENANCE NPDES COMPLIANCE AND ASSET MANAGEMENT Phase 1 NPDES Road Maintenance Compliance Requirements S5.C.8.b.iv.
More informationAPPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports
APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan
More informationPERMIT APPLICATION FOR RECLAIMED WATER REUSE (RWR)
PERMIT APPLICATION FOR RECLAIMED WATER REUSE (RWR) ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION-MUNICIPAL SECTION PO BOX 301463 MONTGOMERY, ALABAMA 36130-1463 INSTRUCTIONS: APPLICATIONS
More informationPhotographic Processing Facility Sector Control Policy
Photographic Processing Facility Sector Control Policy Persigo Wastewater Treatment Plant Industrial Pretreatment Division 2145 River Road Grand Junction, CO 81505 970-256-4180 I. INTRODUCTION The United
More informationReview of State and Federal Stormwater Regulations November 2007
Review of State and Federal Stormwater Regulations November 2007 By: James T. Spaulding, PE, CPESC Joseph M. Ducharme, Jr., PE TTG ENVIRONMENTAL CONSULTANTS, LLC 27 LOCKE ROAD, CONCORD, NH 03301-5301 TELEPHONE:
More informationFOR PHASE I PROPERTIES
FOR PHASE I PROPERTIES Updated March 2012 Port of Seattle Stormwater Management Program for Phase I Properties Table of Contents Introduction... 1 Port Overview... 1 Permit Overview... 2 Key Implementation
More informationReissuance of OPDES Multi-Sector General Permit OKR05 for Stormwater Discharges Associated with Industrial Activity within the State of Oklahoma
Oklahoma Department of Environmental Quality Water Quality Division Reissuance of OPDES Multi-Sector General Permit OKR05 for Stormwater Discharges Associated with Industrial Activity within the State
More information