LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012

Size: px
Start display at page:

Download "LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012"

Transcription

1 LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012

2 01 STONY MOUNTAIN PIPELINE Laricina will develop and follow an environmental protection plan that meets or exceeds regulatory requirements and industry standards. About Laricina Energy Stony Mountain Pipeline Environmental Stewardship, Health and Safety Laricina Energy Ltd. (Laricina) is a privately held, Calgary-based company that is creating value by developing Canada s oil sands using innovative in situ technologies. Laricina has a portfolio of targeted oil sands assets containing a variety of reservoir environments and geological character. These assets range from the familiar oil sands of the McMurray Formation to the developing Grand Rapids and Grosmont Formations, all of which offer significant resource potential. Laricina s diverse portfolio of oil sands assets are at varied stages of development. Development is underway at Saleski and Germain, Laricina s two core properties in the West Athabasca Oil Sands region. At Saleski an 1,800 barrels per day (bpd) pilot project is in operation and at Germain a 5,000 bpd commercial demonstration project is under construction. Laricina is a responsible energy company that will respond to the growing demand for crude oil through in situ oil sands development. Laricina proposes to construct a new 24-inch, 184 km blended crude bitumen pipeline to transport production from its Saleski Steam-Assisted Gravity Drainage (SAGD) development, located in the West Athabasca Oil Sands region of Alberta, to the Enbridge Pipelines Inc. (Enbridge) Cheecham Terminal, located approximately 70 km south of Fort McMurray. A second 12-inch diluent pipeline is planned for the same right of way. Diluent is a light petroleum liquid used to dilute bitumen and heavy oil so it can be shipped through a pipeline to domestic and export markets. Laricina is currently planning to install the two pipelines along with required tankage and associated facilities over two winter seasons in order to manage project timing and meet business commitments. The initial capacity of the blended crude bitumen pipeline, scheduled for completion in mid-2015, will be 200,000 bpd. The initial capacity of the diluent pipeline, scheduled for completion in 2016, will be 70,000 bpd. To mitigate the impact on environmentally sensitive areas, the proposed pipelines are routed south of both the Grand Rapids and Stony Mountain Wildland Provincial Parks commencing from Laricina s Saleski lease located at Townships 84 and 85 and in Ranges 19 and 20 W4M (approximately 70 km northeast of Wabasca, Alberta) to Enbridge s Cheecham Terminal located at W4M. (See map on page 3). Laricina has named this development the Stony Mountain Pipeline. Laricina is committed to carefully assessing and mitigating potential impacts on the environment, to considering socio-economic issues related to the pipeline and to protecting the health and safety of Aboriginal communities, the public, contractors and our employees. The commitment to stakeholders is to ensure facilities are designed, constructed and operated with these results in mind. We will seek input from those who may be affected by construction activities and will work together to address their concerns early in the process as we work through the regulatory process for the Stony Mountain Pipeline. Through studies and ongoing dialogue with Aboriginal communities, regulatory agencies and other stakeholders, we will identify the potential effects the pipeline may have on the various land, air, fish, bird, wildlife and freshwater environments along the route and will utilize existing and proven mitigation measures during construction and operations. Laricina will develop and follow an environmental protection plan that meets or exceeds regulatory requirements and industry standards. Construction work will be conducted in accordance with Laricina s environmental, health and safety standards. Prior to going into service, the pipeline will undergo a rigorous inspection process to ensure that it is safe for use. The pipeline will be operated in an environmentally safe and responsible manner.

3 Horizontal Directional Drilling (HDD) HDD is an established and extensively-used pipeline boring technique which is particularly effective for water crossings. 02 A bore hole is drilled under the water body and the pipeline is then pulled back through the bore hole to the other side. HDD rig section of pipeline direction of pipeline pull Pipeline Need Preliminary Route Selection As new in situ projects are being developed, additional pipeline capacity is required out of the West Athabasca Oil Sands region. Laricina is currently operating a pilot at Saleski which has an approved 1,800 bpd capacity. Regulatory approval for the Phase 1 10,700 bpd expansion at Saleski is being sought which will increase the proposed production capacity to 12,500 bpd. Phase 1 will be the first of six expansion phases expected to increase Saleski s production to more than 270,000 bpd over a 30-year period. While pilot production is currently being trucked to market, the increased production from the planned expansion at Saleski will require a connection to existing pipeline infrastructure. The Stony Mountain Pipeline will initially serve Saleski, however, it is expected that other neighbouring projects may also use the pipeline. To meet the full development potential of Saleski and other potential neighbouring projects, the initial pipeline capacity of 200,000 bpd will need to be expanded in the future. Expansion options will be considered in the context of balancing overall operational requirements with protecting sensitive environments and mitigating new land disturbance. Laricina s preliminary route planning and selection for the pipeline has undergone careful consideration consisting of desktop reviews of topographical maps, land use and tenure information and land disturbances in the vicinity of the region, as well as route and site inspection by helicopter. Our primary pipeline route selection is founded on our commitment to manage potential impacts to wildlife and to the local environment, through mitigation, both during and following construction activities. Route selection criteria included the environment, construction cost and timing, existing linear disturbances, river crossing feasibility and right of way reclamation. As the Athabasca River crossing is a critical control point for the overall pipeline routing, Laricina conducted a preliminary assessment of the proposed crossing location in spring A geotechnical borehole investigation was executed during June and July 2011 and through this investigation Laricina determined that a horizontal directional drill (HDD) under the Athabasca River was a viable crossing option. Using HDD for pipeline crossings of roads, rivers and other obstacles is an established and commonly used technique. Additional geotechnical investigations will be conducted at the Athabasca River, and other watercourse crossings along the proposed route, as warranted, to gather the information required to ensure the pipeline is installed in a manner that minimizes potential impacts to the environment. Development of the proposed pipeline is contingent upon receiving regulatory approvals. Laricina will consult with regulators, Aboriginal communities, stakeholders, and land users on routing.

4 03 STONY MOUNTAIN PIPELINE 89 Development of the proposed pipeline is contingent upon receiving regulatory approvals. Laricina will consult with local 88 regulators, Aboriginal communities, stakeholders and land users on routing. Grand Rapids Wildland Park 87 Athabasca River 86 MUNICIPAL DISTRICT OF OPPORTUNITY NO. 17 REGIONAL MUNICIPALITY OF WOOD BUFFALO KP 0 Saleski 18 KP KP 20 LEGEND KP 30 Kilometre Post Proposed Stony Mountain Pipeline Highway KP 40 Railway Watercourse Waterbody Bovin Creek Municipal Boundary City / Town Park or Protected Area Proposed Conservation or Recreation Area First Nations Land Athabasca River KP 50 KP 60 KP KP 80 KP 79 LAC LA BICHE COUNTY

5 Fort McMurray 04 N 89 Grand Rapids Wildland Park Clearwater River Clearwater Gipsy Lake Wildland Park 87 Gregoire/Willow Lake Expansion Gipsy - Gordon Wildland Park 86 Hangingstone Provincial Recreation Area Gregoire Lake 176 Gregoire Lake Provincial Park Maqua Lake Provincial Recreation Area Stony Mountain Wildland Park KP 184 KP 180 Cheecham 83 Engstrom Lake Provincial Recreation Area KP KP KP 100 KP KP 120 KP 130 KP 140 KP 150 Janvier 194 SCALE: 1: 500,000 km

6 NITY NO STONY MOUNTAIN PIPELINE 19 KP 0 eski 18 KP 10 KP 20 Right of Way Width K Community Involvement Given that the terrain poses challenges with respect to wetlands and access, we recognize how important it is to optimize working space and safety on the right of way. Laricina has determined that safe installation of the pipeline project will require an approximately 35 metre wide right of way (30 metre permanent and 5 metre temporary). Additional temporary workspace may be taken in areas of challenging slopes, wet terrain, road and water course crossings and other infrastructure such as existing pipelines. Laricina is committed to transparent consultation with all stakeholders and nearby communities in the areas in which we operate. Our public consultation program is designed to reflect Energy Resources Conservation Board (ERCB) Directive 56 to ensure that we: engage with Aboriginal communities in the area to learn and understand how our proposed pipeline project may impact their rights and traditional uses; build and maintain transparent, mutually beneficial and respectful relationships with Aboriginal communities and our stakeholders; listen effectively and seek to understand the Aboriginal communities and stakeholders perspectives, requests, and recommendations and give them every consideration in light of our business requirements; review our progress and learnings with potentially impacted Aboriginal communities; seek input into the design of the consultation process and practices to ensure we respect and meet the communications and consultation needs of participants in the area; provide timely, accurate information in a manner that is conducive to promoting understanding of the information we are sharing; provide Aboriginal communities and stakeholders with the opportunity to understand our plans and operations and provide feedback on how their input will be incorporated in our plans and operations; and establish and maintain open communication and a high level of inclusiveness by identifying and including those who may have an interest or potentially be impacted by our activities and proposed activities.

7 TE CU XE ACK B T R O CO STA M E RE P Laricina s Commitments Communications Model will be adopted to promote open dialogue and integrate stakeholder feedback into our consultation program. EN T IS R OU T TE ITMEN M Laricina will seek input into the design of the consultation process and will inform Aboriginal communities and stakeholders of proposed Stony Mountain Pipeline developments. We will provide all communities with the opportunity to understand our plans and operations, as well as provide feedback. L 06 Schedule Laricina intends to file regulatory applications in mid Pending regulatory approval, construction would start in late 2013 with right of way clearing. Based on Laricina s current plan, the blended crude bitumen pipeline will be completed by mid-2015, with the diluent pipeline completed a year later Aboriginal and public consultation process Application preparation Application filing Regulatory review Engineering Blended crude bitumen pipeline Construction Start-up Diluent pipeline Construction Start-up Final clean up

8 WE HOPE TO HEAR FROM YOU PLEASE CONTACT US We will listen to you and to what matters most to your community. Your voice will be heard through direct dialogue with our team. By understanding your priorities, we can work together to minimize the impact of the Stony Mountain Pipeline. FOR MORE INFORMATION Laricina welcomes input from local communities, Aboriginal communities, land users, and stakeholders and can be contacted for questions or comments. Yvonne Walsh Manager, Community Engagement Laricina Energy Ltd. T: East Tower, 5 th Ave Place F: Suite 800, st St. SW pipeline@laricinaenergy.com Calgary, AB T2P 3L8

Cold Lake expansion project

Cold Lake expansion project Cold expansion project Initial project description Plain language summary March 2016 Our commitment Imperial Oil Limited s success depends on our ability to maintain an open dialogue with, and ongoing

More information

Project Summary Table BlackPearl Resources Inc Blackrod Commercial SAGD Project Proponent Name: BlackPearl Resources Inc. Date: November, 2011

Project Summary Table BlackPearl Resources Inc Blackrod Commercial SAGD Project Proponent Name: BlackPearl Resources Inc. Date: November, 2011 Project Summary Table BlackPearl Resources Inc Blackrod Commercial SAGD Project Proponent Name: BlackPearl Resources Inc. Date: vember, 2011 Project Name: Blackrod Commercial SAGD Project Company Contact

More information

Telephone Lake project

Telephone Lake project Telephone Lake project Cenovus Energy Inc. is a Canadian oil company. We re committed to applying fresh, progressive thinking to safely and responsibly unlock energy resources the world needs. Our operations

More information

Jackfish 2 Project. Public Disclosure Document. August 2005

Jackfish 2 Project. Public Disclosure Document. August 2005 Jackfish 2 Project Public Disclosure Document August 2005 Table of Contents Introduction...1 Company Profile...2 Preliminary Project Description...2 The Plan...2 The Process...3 Facilities...3 Physical

More information

Canada s oil sands the in situ producers perspective

Canada s oil sands the in situ producers perspective Canada s oil sands the in situ producers perspective February 11, 2010 By: Chris Bloomer (Presented by: Gerald W. Bruce, IOSA member) IOSA Member Petrobank Who is IOSA? In situ Oil Sands Alliance Independent

More information

Nexen Inc. and CNOOC Canada Inc.

Nexen Inc. and CNOOC Canada Inc. Decision 2012-330 Long Lake Project December 6, 2012 The Alberta Utilities Commission Decision 2012-330: Long Lake Project Application No. 1608729 Proceeding ID No. 2074 December 6, 2012 Published by The

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

Imperial s Sarnia Products Pipeline Mississauga, Ontario. Credit River Valley Project

Imperial s Sarnia Products Pipeline Mississauga, Ontario. Credit River Valley Project Imperial s Sarnia Products Pipeline Mississauga, Ontario Credit River Valley Project Preventative pipeline maintenance in Mississauga s Credit River Valley Imperial s Sarnia Products Pipeline (SPPL) carries

More information

In us, you ll find a trusted resource. Oil Sands

In us, you ll find a trusted resource. Oil Sands In us, you ll find a trusted resource Oil Sands 20% increase of plant throughput at Cenovus Foster Creek in situ facility. In Canada s oil sands, you are tapping into one of the world s largest oil reserves.

More information

Progressing C-SAGD recovery of bitumen from the Grosmont D reservoir

Progressing C-SAGD recovery of bitumen from the Grosmont D reservoir Progressing C-SAGD recovery of bitumen from the Grosmont D reservoir LARICINA ENERGY Steve Brand P. Eng. WHOC15-280 Organized by: Outline Project overview 1D experience and knowledge gained Early cycle

More information

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT Notice NOTICE OF APPLICATIONS SHELL CANADA LIMITED QUEST CARBON CAPTURE AND STORAGE RADWAY FIELD ENERGY RESOURCES CONSERVATION BOARD APPLICATIONS NO. 1689376, 1670112, AND 1671615 ALBERTA ENVIRONMENT ENVIRONMENTAL

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

Society of Petroleum Engineers - Paper "Study and Demonstration of a Process to Extract Bitumen from Utah Tar Sands"

Society of Petroleum Engineers - Paper Study and Demonstration of a Process to Extract Bitumen from Utah Tar Sands Servicing the Utah and Athabasca Oil Sands Industries MENU HOME ASPHALT RIDGE - STATUS ASPHALT RIDGE - HISTORY SERVICES KEY PERSONNEL CONTACT US LINKS INTRODUCTION ASPHALT RIDGE - OUR HISTORY & a TECHNOLOGY

More information

Recovery Process - Cold Heavy Oil

Recovery Process - Cold Heavy Oil Recovery Process - Cold Heavy Oil CHOPS (Cold Heavy Oil Production with Sand) CHOPS is a heavy oil recovery technique where the reservoir sand is deliberately produced to improve reservoir performance.

More information

Nexen Inc. OPTI Canada Inc.

Nexen Inc. OPTI Canada Inc. Decision 2010-006 Nexen Inc. OPTI Canada Inc. Long Lake South Phase 1 Cogeneration Power Plant January 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-006: Nexen Inc. and OPTI Canada Inc. Long Lake

More information

Prince Rupert Gas Transmission Project Overview Prince Rupert

Prince Rupert Gas Transmission Project Overview Prince Rupert Prince Rupert Gas Transmission Project Overview Prince Rupert Gas Transmission Project ALBERTA ALBERTA Prince Rupert Gas Transmission Project 37 Pink Mountain Wonowon Fort St. John ALASKA Stewart 37 Prince

More information

6 DRILLING AND COMPLETIONS

6 DRILLING AND COMPLETIONS Cenovus FCCL Ltd. 6-1 Drilling and Completions 6 DRILLING AND COMPLETIONS 6.1 OVERVIEW This section contains information about the drilling and completion of wells within the CLTP. Well counts, locations

More information

OPPORTUNITY PROFILE. Fort McKay Sustainability Department (FMSD) Senior Manager, Industry & Government Relations

OPPORTUNITY PROFILE. Fort McKay Sustainability Department (FMSD) Senior Manager, Industry & Government Relations OPPORTUNITY PROFILE Fort McKay Sustainability Department (FMSD) ABOUT FORT MCKAY FIRST NATION Fort McKay First Nation (FMFN) is composed of over 800 band members, including those of Cree and Dane heritage,

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

Keystone Projects Overview

Keystone Projects Overview Keystone Projects Overview TransCanada Assets Wholly Owned Natural Gas Pipeline Partially Owned Natural Gas Pipeline Natural Gas Pipeline Under Construction Natural Gas Pipeline In Development Natural

More information

EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference. D. Glen Snarr, President & CFO September 21, 2006

EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference. D. Glen Snarr, President & CFO September 21, 2006 EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference D. Glen Snarr, President & CFO glen.snarr@earthenergyresources.com September 21, 2006 ISSUES FACING OIL SAND PRODUCTION Issues Facing Athabasca

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

Pipeline Performance: Building Trust & Raising the Bar

Pipeline Performance: Building Trust & Raising the Bar Pipeline Performance: Building Trust & Raising the Bar Jim Donihee, OMM CD June 19 th, 2014 Outline Relevance & Background CEPA Who are we & What do we stand for? Defining Moments Catalyst for Change How

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

Grizzly Oil Sands ULC

Grizzly Oil Sands ULC Decision 2013-124 Algar Lake Project Distribution System Exemption March 28, 2013 The Alberta Utilities Commission Decision 2013-124: Algar Lake Project Distribution System Exemption Application No. 1609370

More information

Integrated Watershed Management Plan

Integrated Watershed Management Plan mighty peace watershed alliance Integrated Plan SUMMARY What is the Plan? The Mighty Peace Alliance (MPWA) supports the three goals of Alberta s Water for Life Strategy: safe secure drinking water, healthy

More information

SHELL ONSHORE OPERATING PRINCIPLES

SHELL ONSHORE OPERATING PRINCIPLES SHELL ONSHORE OPERATING PRINCIPLES FOR TIGHT SAND OR SHALE OIL AND GAS In 2011, Shell publicly shared five aspirational operating principles that govern the activities where we operate and where hydraulic

More information

Part 1: Project Description

Part 1: Project Description Application for Approval of the AOSP Bitumen Blending Facility Project Part 1: Project Description Submitted to: Alberta Energy and Utilities Board and Alberta Environment Submitted by: Shell Canada Limited

More information

The Peace Watershed. Current and Future Water Use and Issues, 2011

The Peace Watershed. Current and Future Water Use and Issues, 2011 This is an Executive Summary. For full report go to: www.mightypeacewatershedalliance.org The Peace Watershed Current and Future Water Use and Issues, 2011 March 2012 EXECUTIVE SUMMARY This study was undertaken

More information

FORT McMURRAY MINEABLE OIL SANDS INTEGRATED RESOURCE MANAGEMENT PLAN DRAFT. As of October 2005

FORT McMURRAY MINEABLE OIL SANDS INTEGRATED RESOURCE MANAGEMENT PLAN DRAFT. As of October 2005 FORT McMURRAY MINEABLE OIL SANDS INTEGRATED RESOURCE MANAGEMENT PLAN 2005 DRAFT As of October 2005 This ideas presented in this discussion paper are intended to stimulate discussion. We would like to hear

More information

Pengrowth Energy Corporation

Pengrowth Energy Corporation Decision 2013-308 Lindberg SAGD Industrial System Designation August 20, 2013 The Alberta Utilities Commission Decision 2013-308: Lindberg SAGD Industrial System Designation Application No. 1609200 Proceeding

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED HORIZON NORTH PIT EXTENSION PROJECT

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED HORIZON NORTH PIT EXTENSION PROJECT PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED HORIZON NORTH PIT EXTENSION PROJECT Approximately 70 km North of Fort McMurray, Alberta ISSUED

More information

Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency -

Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency - Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency - Nov-29, 2017 JAPEX (Japan Petroleum Exploration Co., Ltd) Canada Oil Sands Project Dept. Tanetomo (Tom) Izumi Japan

More information

Canada s Oil Sands - A World-Scale Hydrocarbon Resource

Canada s Oil Sands - A World-Scale Hydrocarbon Resource Canada s Oil Sands - A World-Scale Hydrocarbon Resource Prepared by: R.B. (Bob) Dunbar, P. Eng. bob.dunbar@strategywest.com February 2009 www.strategywest.com PO Box 76037; Calgary, Alberta T2Y 2Z9; Phone

More information

ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta

ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta PETRO-CANADA OIL AND GAS STEAM-ASSISTED GRAVITY DRAINAGE PROJECT MACKAY RIVER PROJECT Decision 2000-50 ATHABASCA OIL SANDS AREA Applications No. 1032550

More information

Proposed Heartland Cavern Lateral Pipeline and Meter Station. Public Information Document

Proposed Heartland Cavern Lateral Pipeline and Meter Station. Public Information Document Proposed Heartland Cavern Lateral Pipeline and Meter Station Public Information Document April 16, 2015 Proposed Heartland Cavern Lateral Pipeline and Meter Station Project 2 Contents Project Necessity...

More information

Considerations. Report of the Joint Review Panel for the Enbridge Northern Gateway Project Volume 2

Considerations. Report of the Joint Review Panel for the Enbridge Northern Gateway Project Volume 2 Considerations Report of the Joint Review Panel for the Enbridge Northern Gateway Project Volume 2 Considerations Report of the Joint Review Panel for the Enbridge Northern Gateway Project Volume 2 Permission

More information

Montney Development. in the South Peace

Montney Development. in the South Peace Montney Development in the South Peace Fort St. John Table of contents British Columbia Mapped area Dawson Creek British Columbia Pouce Coupe Alberta Beaverlodge Grande Prairie Your feedback matters! Please

More information

Shell Canada Limited. Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No

Shell Canada Limited. Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No Shell Canada Limited Shell s Comments for Phase 4: Oral Proceeding Related to Alberta Energy Regulator Proceeding No. 1769924 January 22, 2014 Good (morning/afternoon) Panel Members, AER staff, members

More information

Parsons Creek Aggregates Project. Part D: Environmental Impact Assessment (EIA) Methodology

Parsons Creek Aggregates Project. Part D: Environmental Impact Assessment (EIA) Methodology Part D: Environmental Impact Assessment (EIA) Methodology Table of Contents D. ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY... 1 D.1 EIA TERMS OF REFERENCE... 1 D.2 SCOPE OF THE ASSESSMENT... 2 D.2.1 Scope

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

Large-Scale CCS Demonstration Projects in Canada

Large-Scale CCS Demonstration Projects in Canada Carbon capture and sequestration technology holds enormous potential to reduce our greenhouse gas emissions as we use our own energy resources to power our economy. Prime Minister Stephen Harper, February

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline

JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline Thermal In-Situ Scheme Progress Report JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline 1. Introduction Project Background, Activity Summary

More information

transportation BUSINESS PLAN

transportation BUSINESS PLAN Transportation BUSINESS PLAN 2014-17 Accountability Statement This business plan was prepared under my direction, taking into consideration the government s policy decisions as of February 12, 2014. original

More information

Site C Clean Energy Project Agricultural Mitigation and Compensation Plan

Site C Clean Energy Project Agricultural Mitigation and Compensation Plan Site C Clean Energy Project Agricultural Mitigation and Compensation Plan Revision 1: September 25, 2017 Table of Contents 1.0 Background... 4 1.1 The Site C Clean Energy Project... 4 1.2 Project Benefits...

More information

Murphy Oil Operations in the PEACE RIVER AREA

Murphy Oil Operations in the PEACE RIVER AREA Murphy Oil Operations in the PEACE RIVER AREA April 27 th, 2015 Craig Sinclair Manager, Special Projects MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR 1 Our purpose today includes: Our Purpose

More information

Transmission Pipelines: Changing context

Transmission Pipelines: Changing context Transmission Pipelines: Changing context CATHY HAY, DIRECTOR, RESEARCH & SPECIAL PROJECTS JANUARY 2015 Who is CEPA? The Canadian Energy Pipeline Association (CEPA) represents Canada s transmission pipeline

More information

Welcome. to the Community Meeting for the Niagara Region Wind Project. Thank you for coming!

Welcome. to the Community Meeting for the Niagara Region Wind Project. Thank you for coming! Welcome to the Community Meeting for the Niagara Region Wind Project Thank you for coming! In early September we will host the first Public Open House under We are happy to share information about this

More information

SAGD Water Disposal Options, Associated Impacts, and Strategies to Improve Environmental Footprint. Basil Perdicakis, January 27, 2011

SAGD Water Disposal Options, Associated Impacts, and Strategies to Improve Environmental Footprint. Basil Perdicakis, January 27, 2011 SAGD Water Disposal Options, Associated Impacts, and Strategies to Improve Environmental Footprint Basil Perdicakis, January 27, 2011 Statoil Canada Kai Kos Dehseh (KKD) Lease Leismer site currently producing

More information

The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture. Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April

The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture. Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April 13 2013 Motivation Province of Alberta targets a 2050 GHG emissions

More information

Welcome. Public Information Event. Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study

Welcome. Public Information Event. Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study Welcome Public Information Event Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study Please sign in to be added to the study mailing list and receive

More information

PROPOSED PIPELINES TO SERVE THE COMMUNITY OF FENELON FALLS: ENVIRONMENTAL REPORT

PROPOSED PIPELINES TO SERVE THE COMMUNITY OF FENELON FALLS: ENVIRONMENTAL REPORT 1.0 INTRODUCTION 1.1 PROJECT DESCRIPTION Enbridge Gas Distribution Inc. ("Enbridge") is proposing to construct up to a total of approximately 37 kilometres (km) of natural gas pipelines at different nominal

More information

SHALE FACTS. Production cycle. Ensuring safe and responsible operations

SHALE FACTS. Production cycle. Ensuring safe and responsible operations SHALE FACTS Production cycle Ensuring safe and responsible operations Statoil is committed to developing our shale projects in a safe, responsible and open manner. Statoil takes a long term perspective

More information

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet WELCOME Please sign in Representatives are available to answer questions Please complete a comment sheet Place it in the box or send it to the Consultant undertaking the study or to the Town of Wasaga

More information

Urban Pipeline. Replacement Program A NATURAL GAS PIPELINE INITIATIVE. Southwest Calgary Connector & South Glenmore Lateral. Safety First. Always.

Urban Pipeline. Replacement Program A NATURAL GAS PIPELINE INITIATIVE. Southwest Calgary Connector & South Glenmore Lateral. Safety First. Always. Urban Pipeline Replacement Program A NATURAL GAS PIPELINE INITIATIVE Southwest Calgary Connector & South Glenmore Lateral Safety First. Always. ATCO s Urban Pipeline Replacement Program In January 2014,

More information

Oil Sands Performance. Muskeg River Mine & Scotford Upgrader

Oil Sands Performance. Muskeg River Mine & Scotford Upgrader Oil Sands Performance Report Muskeg River Mine & Scotford Upgrader ABOUT THIS REPORT 01 This document is a report to our stakeholders and is an important part of Shell s continuing dialogue with governments,

More information

orporate responsibility 2009 performance measures

orporate responsibility 2009 performance measures orporate responsibility performance measures about cenovus 2 3 4 economic 5 environment 2 4 workforce 6 community 6 governance our approach to CR reporting health and safety energy efficiency and R&D measurement

More information

TABLE OF CONTENTS PART 1 PROJECT UPDATE... 1 PROPOSED PLANT SITE EXPANSION...1

TABLE OF CONTENTS PART 1 PROJECT UPDATE... 1 PROPOSED PLANT SITE EXPANSION...1 Canadian Natural Resources Limited - i - Table of Contents TABLE OF CONTENTS SECTION PAGE PART 1 PROJECT UPDATE... 1 PROPOSED PLANT SITE EXPANSION...1 PART 2 SUPPLEMENTAL INFORMATION REQUEST RESPONSES...

More information

Sustainable Water Management in the Athabasca River Basin Initiative (ARB Initiative) DRAFT Working Group Terms of Reference

Sustainable Water Management in the Athabasca River Basin Initiative (ARB Initiative) DRAFT Working Group Terms of Reference Sustainable Water Management in the River Basin Initiative (ARB Initiative) DRAFT Working Group Terms of Reference December 2016 Contents 1.0 Background...3 2.0 Vision...4 3.0 Project Principles...4 4.0

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22447-D01-2017 Vauxhall Solar Power Plant July 4, 2017 Alberta Utilities Commission Decision 22447-D01-2017 Vauxhall Solar Power Plant Proceeding 22447 Application 22447-A001 July 4, 2017 Published

More information

Biomass supply and diesel requirements for cofeeding a bitumen upgrader in Alberta

Biomass supply and diesel requirements for cofeeding a bitumen upgrader in Alberta Engineering Conferences International ECI Digital Archives BioEnergy IV: Innovations in Biomass Conversion for Heat, Power, Fuels and Chemicals Proceedings Spring 6-12-2013 Biomass supply and diesel requirements

More information

Water Conservation, Efficiency and Productivity Plan Progress Report Upstream Oil and Gas Sector

Water Conservation, Efficiency and Productivity Plan Progress Report Upstream Oil and Gas Sector Guide Water Conservation, Efficiency and Productivity Plan Progress Report Upstream Oil and Gas Sector January 2016 2016-0037 The Canadian Association of Petroleum Producers (CAPP) represents companies,

More information

THE NORTHERN GATEWAY PIPELINE: A POSSIBLE CORRIDOR TO SEED RENEWABLE ENERGY IN BRITISH COLUMBIA, CANADA. McGill University, Montreal, Quebec, H3A 2A7

THE NORTHERN GATEWAY PIPELINE: A POSSIBLE CORRIDOR TO SEED RENEWABLE ENERGY IN BRITISH COLUMBIA, CANADA. McGill University, Montreal, Quebec, H3A 2A7 World Mining Congress 2013 THE NORTHERN GATEWAY PIPELINE: A POSSIBLE CORRIDOR TO SEED RENEWABLE ENERGY IN BRITISH COLUMBIA, CANADA Mory Ghomshei 1,2,*, Ferri Hassani 1, John Meech 2, and Nima Mousavi 3

More information

EXCELLENCE * INTEGRITY * STEWARDSHIP * COMMITMENT * EFFICIENCY * VISION

EXCELLENCE * INTEGRITY * STEWARDSHIP * COMMITMENT * EFFICIENCY * VISION 1 TOPICS September 8 & 22, 2011 The Challenge The Solution (Part of it) The Grand Park The Results 2 The North Georgia Water Challenge High dependency on Lake Lanier and Chattahoochee River (>70%). 11

More information

OPPORTUNITY PROFILE Director, Communications & Stakeholder Relations

OPPORTUNITY PROFILE Director, Communications & Stakeholder Relations OPPORTUNITY PROFILE Director, Communications & Stakeholder Relations 1 THE ORGANIZATION REGIONAL MUNICIPALITY OF WOOD BUFFALO Stretching from north central Alberta to the borders of Saskatchewan and the

More information

PXP Point Arguello / Gaviota

PXP Point Arguello / Gaviota PXP Point Arguello / Gaviota An ongoing project consisting of three offshore platforms (Hermosa, Harvest and Hidalgo) that produce and process oil and gas from the Point Arguello Offshore field and an

More information

Proposed Northern Gateway Pipeline

Proposed Northern Gateway Pipeline Fall 2014 Proposed Northern Gateway Pipeline RISK MITIGATION STRATEGY REPORT JEFFREY KENT YORK UNIVERSITY Disaster Risk Management Course Table of Contents Introduction... 1 Description of Mitigation Strategies...

More information

PUBLIC NOTICE Section 404 of the Clean Water Act - Permit Review ENVIRONMENTAL IMPACT STATEMENT U.S. ARMY CORPS OF ENGINEERS REGULATORY BRANCH

PUBLIC NOTICE Section 404 of the Clean Water Act - Permit Review ENVIRONMENTAL IMPACT STATEMENT U.S. ARMY CORPS OF ENGINEERS REGULATORY BRANCH US Army Corps of Engineers Omaha District PUBLIC NOTICE Corps ID No: NWO-2007-1337-DEN Project: Regional Watershed Supply Project Applicant: Million Conservation Resource Group Issue Date: May 8, 2009

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

More information

Evaluation of Western Kentucky s Heavy Oil and Bitumen Resources

Evaluation of Western Kentucky s Heavy Oil and Bitumen Resources 2014 Eastern Unconventional Oil and Gas Symposium - November 5-7, 2014 in Lexington, Kentucky, USA http://www.euogs.org Evaluation of Western Kentucky s Heavy Oil and Bitumen Resources 2014 Eastern Unconventional

More information

PART 1: ROUTING UPDATE

PART 1: ROUTING UPDATE PART 1: ROUTING UPDATE TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PIPELINE CORRIDOR... 2 Page 2.1 Overview of Pipeline Corridor Selection and Optimization Process... 2 2.2 Environmental, Socio-Economic

More information

Yeo Substation Project

Yeo Substation Project Yeo Substation Project Application to the Alberta Utilities Commission October 2014 10035 105 Street, Edmonton AB, Canada T5J 2V6 Tel: 1-866-600-0022 Fax: 780-420-5030 www.atcoelectric.com Application

More information

Tar Sands: Why Should I Care?

Tar Sands: Why Should I Care? Tar Sands: Why Should I Care? Tar sands (bitumen) is extracted in Canada and is transported by pipeline through Minnesota and Wisconsin and points further south. Tar sands and tar sands pipelines can have

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by

More information

Dead Horse Creek Project. Community Open House Minnewasta Golf & Country Club Morden, Manitoba June 15, 2017

Dead Horse Creek Project. Community Open House Minnewasta Golf & Country Club Morden, Manitoba June 15, 2017 Dead Horse Creek Project Community Open House Minnewasta Golf & Country Club Morden, Manitoba June 15, 2017 Dead Horse Creek Project Overview Enbridge operates seven pipelines that cross Dead Horse Creek

More information

Cases for QAES's and QWAES's and QWSP s and QAP s

Cases for QAES's and QWAES's and QWSP s and QAP s Cases for QAES's and QWAES's and QWSP s and QAP s ARHCA Environment Session, Red Deer, AB November 6, 2014 Jay S. White, M.Sc., P. Biol, QWAES, QAES Aquality Environmental Consulting Ltd. Water Act (1999)

More information

ENFORCEMENT OF THE ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT WATER ACT

ENFORCEMENT OF THE ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT WATER ACT ENFORCEMENT OF THE ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT And TER ACT 1 Apr 2010-30 Jun 2010 July 2010 Environmental Management Division Alberta Environment Administrative Penalties Ritchie & Sons

More information

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

Environmental Impact Statement for the Slave Falls Tramway Conversion Project Environmental Impact Statement for the Slave Falls Tramway Conversion Project Prepared for Submitted by 41844.101 March 2008 ENVIRONMENTAL IMPACT STATEMENT FOR THE SLAVE FALLS TRAMWAY CONVERSION PROJECT

More information

GENERAL GUIDELINES FOR CONDUCTING THREATENED AND ENDANGERED SPECIES SURVEYS IN THE PINELANDS AREA. March 25, 2006 INTRODUCTION

GENERAL GUIDELINES FOR CONDUCTING THREATENED AND ENDANGERED SPECIES SURVEYS IN THE PINELANDS AREA. March 25, 2006 INTRODUCTION GENERAL GUIDELINES FOR CONDUCTING THREATENED AND ENDANGERED SPECIES SURVEYS IN THE PINELANDS AREA March 25, 2006 INTRODUCTION This document is intended to provide general guidance for use in conducting

More information

Department of the Army Permit Application

Department of the Army Permit Application Department of the Army Permit Application DA File Number U.S. Army Corps of Engineers Honolulu District Date Received by CEPOH-RO Send Completed Application to: Honolulu District, U.S. Army Corps of Engineers

More information

6.0 ENVIRONMENTAL AND SOCIO-ECONOMIC EFFECTS ASSESSMENT

6.0 ENVIRONMENTAL AND SOCIO-ECONOMIC EFFECTS ASSESSMENT 6.0 ENVIRONMENTAL AND SOCIO-ECONOMIC EFFECTS ASSESSMENT The description of the environmental and socio-economic setting, and current state of the environment within the Project area (Section 5.0), are

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Operations Mine Site, Tote Road and Railway

Operations Mine Site, Tote Road and Railway Operations Mine Site, Tote Road and Railway 2 Panel Members Michael Anderson Richard Cook John Binns Fernand Beaulac Steve Walker Mike Lepage Michael Sheahan 3 The Panel will address: FEIS Volumes 3, 5,

More information

Geophysical Guidelines for the Muskwa-Kechika Management Area

Geophysical Guidelines for the Muskwa-Kechika Management Area Geophysical Guidelines for the Muskwa-Kechika Management Area May 18, 2004 TABLE OF CONTENTS TABLE OF CONTENTS...i OIL AND GAS COMMISSION...1 1.0 PURPOSE OF THE GUIDELINE...3 2.0 ADAPTIVE MANAGEMENT /

More information

Accompanying this letter are three documents with further information about the project and BowArk s public involvement:

Accompanying this letter are three documents with further information about the project and BowArk s public involvement: BowArk Energy Ltd. Suite 0 Devon Tower 00 Ave SW Calgary, Alberta, TP H (0 - www.bowark.com March 0, 0 RE: Lanfine Wind Power Project Dear neighbour, My name is Keith Knudsen, and I am the lead developer

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

Energy. on this world and elsewhere. Instructor: Gordon D. Cates Office: Physics 106a, Phone: (434)

Energy. on this world and elsewhere. Instructor: Gordon D. Cates Office: Physics 106a, Phone: (434) Energy on this world and elsewhere Instructor: Gordon D. Cates Office: Physics 106a, Phone: (434) 924-4792 email: cates@virginia.edu Course web site available at www.phys.virginia.edu, click on classes

More information

INDUSTRIAL FORT SASKATCHEWAN S. fortsask.ca/business LOCATION CONNECTIONS GROWTH

INDUSTRIAL FORT SASKATCHEWAN S. fortsask.ca/business LOCATION CONNECTIONS GROWTH INDUSTRIAL FORT SASKATCHEWAN S L E A D I N Gedge LOCATION CONNECTIONS GROWTH fortsask.ca/business Fort Saskatchewan is a major industrial and commercial centre in northern Alberta. We are the largest urban

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Wetlands in Alberta: Challenges and Opportunities. David Locky, PhD, PWS, PBiol Grant MacEwan University

Wetlands in Alberta: Challenges and Opportunities. David Locky, PhD, PWS, PBiol Grant MacEwan University Wetlands in Alberta: Challenges and Opportunities David Locky, PhD, PWS, PBiol Grant MacEwan University Overview What & Where Function & Value Alberta s Keystone Ecosystem Losses & Impacts Restoration

More information

PROVINCE OF BRITISH COLUMBIA REGULATION OF THE MINISTER OF ENVIRONMENT AND CLIMATE CHANGE STRATEGY. Environmental Management Act M328

PROVINCE OF BRITISH COLUMBIA REGULATION OF THE MINISTER OF ENVIRONMENT AND CLIMATE CHANGE STRATEGY. Environmental Management Act M328 PROVINCE OF BRITISH COLUMBIA REGULATION OF THE MINISTER OF ENVIRONMENT AND CLIMATE CHANGE STRATEGY Environmental Management Act Ministerial Order No. M328 I, George Heyman, Minister of Environment and

More information

PIPELINE SAFETY MUNICIPAL CONCERNS AND EXPECTATIONS

PIPELINE SAFETY MUNICIPAL CONCERNS AND EXPECTATIONS PIPELINE SAFETY MUNICIPAL CONCERNS AND EXPECTATIONS Scott Pearce, Reeve, MRC of Argenteuil and Mayor, Township of Gore Frédérick Jones, GIS Geographer, MRC of Argenteuil 2 June 2015 Introduction Consultations

More information

Effective June 17, 2013, the Energy Resources Conservation Board (ERCB) has been succeeded by the Alberta Energy Regulator (AER).

Effective June 17, 2013, the Energy Resources Conservation Board (ERCB) has been succeeded by the Alberta Energy Regulator (AER). Directive 055 Addendum Directive 055 Addendum: Interim Requirements for Aboveground Synthetically- Lined Wall Storage Systems, Updates to Liner Requirements, and Optional Diking Requirements for Single-Walled

More information

CAPROCK INTEGRITY FOCUS Analyzing How To Utilize Technical Testing Methodologies To Ensure Caprock Integrity. Tuesday, May 24 th, 2011

CAPROCK INTEGRITY FOCUS Analyzing How To Utilize Technical Testing Methodologies To Ensure Caprock Integrity. Tuesday, May 24 th, 2011 CAPROCK INTEGRITY FOCUS Analyzing How To Utilize Technical Testing Methodologies To Ensure Caprock Integrity Tuesday, May 24 th, 2011 Forward-Looking Information and Advisories This presentation contains

More information

E.L. SMITH SOLAR FARM PROJECT UPDATE

E.L. SMITH SOLAR FARM PROJECT UPDATE E.L. SMITH SOLAR FARM PROJECT UPDATE Artist rendering: Looking northeast from Anthony Henday Drive (located southwest of project site) In June 2017, we sent you information about the E.L. Smith Solar Farm

More information

ALBERTA S ENERGY STORY

ALBERTA S ENERGY STORY ALBERTA S ENERGY STORY TABLE OF CONTENTS INTRODUCING ENERGY IQ 2 OVERVIEW OF ALBERTA 3 OIL SANDS 4 NATURAL GAS 8 COAL 12 RENEWABLE ENERGY 16 QUESTION & ANSWER Joe Dion on First Nations in the energy sector

More information

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014 Decision 2014-212 Syncrude Canada Ltd. Mildred Lake Power Plant July 17, 2014 Decision 2014-212: Syncrude Canada Ltd. Mildred Lake Power Plant Application No. 1610311 Proceeding No. 3068 July 17, 2014

More information