1 TW5 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 015/016 URBAN DRAINAGE SYSTEMS MODULE NO: BLT40 Date: Tuesday 17 May 016 Time: INSTRUCTIONS TO CANDIDATES: There are FIVE questions. Answer FOUR questions. All questions carry equal marks. Marks for parts of questions are shown in brackets. This examination paper carries a total of 100 marks. All working must be shown. A numerical solution to a question obtained by programming an electronic calculator will not be accepted. A formula sheet and HRS tables are attached.

2 Page of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Question 1 a) Describe the natural purification processes taking place in a river reach and their contribution in reducing pollution in rivers. (5 marks) b) Explain your understanding of River Environmental Standards and Compliance Assessment of a river reach and who issue and oversee them (5 marks) c) The figure below shows two reaches of a river which serves as receiving water for a nearby town drainage system. The river receives final effluent from the town treatment work (FE), a combined sewer overflow (CSO), a Surface Water Outfall (SWO) and a runoff flow from rural catchment (CFB) at different locations as illustrated in Figure Q1. For a particular moment of time the values of flow and concentrations of the BOD, NH4 & DO for these inputs, as well as for the upstream end of the river reach (RBF), are given in Table 1. The percentage increase or decrease for the concentrations of BOD, NH4 & DO, due to the natural biochemical processes within the two reaches, is given in Table. i) Using the principle of mass balance and natural biochemical processes, find the concentrations of BOD, NH4 and DO in the river at locations P1, P, P3 and P4. (10 marks) ii) Carry out compliance assessment for the two reaches against the UK UPM standards for fishery (shown in Table 3) at same locations mentioned in (i). (5 marks) CFB SWO FE CSO RBF P3 P P1 P4 Reach1 3 Figure Q1 Question 1 continued over the page 1

3 Page 3 of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Question 1 continued Table 1: Input Data Input Name Flow C BOD C NH4 C DO m 3 /sec mg/l mg/l mg/l River Base Flow (RBF) Final Effluent (FE) Combined Sewer Overflow (CSO) Surface Water Outfall (SWO) Catchment Flow Boundary (CFB) Table : Effects of Biochemical Processes Process Reach1 Reach DO Percentage Increase by Aeration 0 15 DO Percentage Decrease by Biodegradation & Nitrification BOD Percentage Decrease by Biodegradation NH4 Percentage Decrease by Nitrification Table 3: Pollution Standards UPM Standards for Fishery Pass Fail DO >=5 <5 NH4 <=4 >4 Total 5 marks Please turn the page

4 Page 4 of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Question a) Explain the principles of sediment transportation. (8 marks) b) An 18m wide channel has a bed slope of The particles in the channel have a density of 50kg/m 3 and the particle size d 50 = 1.30mm. During a storm event the flow in the channel is raised to 5.8m 3 /s. Assuming uniform flow conditions, and µ: 1.14*10-3 ms/kg, determine whether sediment transportation occurs and if so whether particles are in bed-load or suspended load. (17 marks) Question 3 Total 5 marks Critically comment upon the shortcomings of conventional approaches to urban drainage design and outline the alternative sustainable techniques. Comment on the design and other issues that currently prevent their wider use. Discuss what systemic changes may be required to ensure their wider acceptance. Question 4 Total 5 marks a) Discuss the parameters that affect catchment response to rainfall in a rural area. Explain how urbanisation can impact some of these parameters and the consequence of this impact on the runoff hydrograph. (10 marks) b) Discuss the structural and non-structural mitigation measures of urbanisation impacts on a runoff hydrograph and give two examples for each of these measures. (10 marks) c) Explain your understanding for the concept of catchment modelling and differentiate between Blackbox, Conceptual and Physically-based mathematical models. (5 marks) Total 5 marks Please turn the page

5 150m Page 5 of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Question 5 a) For Site A in Figure 5A, provide a preliminary sketch for a storm drainage design. Assume a 75% runoff rate from grounds. Comment on all assumptions made. (9 marks) 100m 99.8m 99.6m 99.54m Building footprint and roof ridges 99.4m Site A boundary 170m Figure 5A - Site A Question 5 continued over the page

6 Page 6 of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Question 5 continued. b) During setting out and construction of the manholes on Site B the original drainage design was misinterpreted. The storm drains are now required to be connected into the Combined Sewer manhole MH C, see Figure 5B. i) Complete the Site B drainage scheme in Tables 5B-1 and 5B- by selecting suitable pipe diameters and gradients to accommodate a 1 in 0year storm event. (HRS tables and rainfall charts are provided). (1 marks) ii) Using Building Regulation Part H, state the bedding and surround requirements for all pipes in the storm drainage network. (3 marks) Total 5 marks Please turn the page

7 Page 7 of 10 MHC1 MHC MH MH3 1.0 MH4 Grassed area to drain through infiltration due to very permeable soil conditions MH1 MH5 Building footprint 36m 5m Site B boundary

8 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Page 8 of 16 Manhole No. Cover level (m) Site B - Manhole Schedule Invert level (m) Ground catchment area (Ha) Roof catchment area (Ha) MH MH MH MH MH MTC n/a n/a MHC n/a n/a Table 5B-1 Table Q5B-1. To be handed in with answer book Candidate ID No... Please turn the page

9 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Page 9 of 16 Pipe No Pipe Length (m) Pipe gradient (1 in ) Pipe fall (m) Vel (m/s) Time of flow (min) Time of Conc. (min) Rate of rainfall i (mm/hr) Imp. Area (ha) Cumulative Imp. Area (ha) Flow Q (l/s) Pipe dia. (mm) Pipe capacity (l/s) Table Q5B-. To be handed in with answer book Candidate ID No... END OF QUESTIONS Please turn the page

10 Page 10 of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Formula A = DWF P + E l/d DWF = PG + I + E D MIN = 0.7 Q MAX 0.4 F r = 4.06 Q 0.5 gd 5 Q O = C D x A O x ( x g x H O ) 0.5 Formula sheet H O = 1.D + 0.5D O C D = db Do u db - D o d B =.5 x D MIN, L = 7 x D MIN s = 0.8D + D O Q w = C Qw H w = C C 1 = 3 1 C d d 3 Q C 3 3/ g LH w w g L Q C 3 w 3,C gl s K 1,C 3 gl t K, C d = 0.7, K 1, K =.0 h f = S o x L n=(sinθ)d 1/6, τ o = ρgrs V = τ o ρ τ = τ O ρ(s 1)gd s Please turn the page

11 School of Engineering Semester Two Examination 015/016 Module No. BLT40 Page 11 of 16

12

13 Page 13 of 16 School of Engineering Semester Two Examination 015/016 Module No. BLT40

14

15

16

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 [ESS29] UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 Date: Monday 21 st May 2018 Time: 10:00 13:00 INSTRUCTIONS

More information

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL COLLEGE FZE BENG (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL COLLEGE FZE BENG (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016 OCD63 UNIVERSITY OF BOLTON WESTERN INTERNATIONAL COLLEGE FZE BENG (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 015/016 WATER ENGINEERING AND THE ENVIRONMENT MODULE NO: CIE601 Date: 15 January 016

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

Learning objectives. Upon successful completion of this lecture, the participants will be able to: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to: Describe and perform the required step for designing sewer system networks Outline Design

More information

Sanitary Sewer Design. Sanitary Sewers, Page 1

Sanitary Sewer Design. Sanitary Sewers, Page 1 Sanitary Sewer Design Sanitary Sewers, Page 1 Sanitary Sewers, Page 2 Sanitary Sewer Design sanitary sewers collect and transport domestic and industrial wastes via gravity flow the ultimate destination

More information

CIE4491 Lecture. Quantifying stormwater flow Rational method

CIE4491 Lecture. Quantifying stormwater flow Rational method CIE4491 Lecture. Quantifying stormwater flow Rational method 27-5-2014 Marie-claire ten Veldhuis, Watermanagement Department Delft University of Technology Challenge the future Robust method stationary

More information

SECTION-I. b) Write a short note on pumping of savage. 4

SECTION-I. b) Write a short note on pumping of savage. 4 UNIVERSITY OF PUNE [4364]-401 B. E. (Civil Engineering Semester I) Examination - 2013 ENVIRONMENTAL ENGINEERING-II (2008 Pattern) [Total No. of Questions :12] [Total No. of Printed Pages :4] [Time : 3

More information

Course: Wastewater Management

Course: Wastewater Management Course: Wastewater Management Prof. M. M. Ghangrekar Questions 1 1. Describe advantages and disadvantages offered by the water carriage system. 2. What are the possible adverse effects when untreated or

More information

Storm Sewer Design - Introduction

Storm Sewer Design - Introduction Class 4 [1] Storm Sewer Design - Introduction As urban drainage can not be expected to accommodate all rainfall events, the first step in the design procedure is to select an appropriate design storm.

More information

Storm Sewers, Page 2

Storm Sewers, Page 2 Storm Sewers storm sewer systems are dendritic systems used to collect and direct stormwater runoff storm sewer systems are integral components of any urban infrastructure curbs, gutters and storm inlets

More information

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management Husam Al-Najar Storm water management : Collection System Design principles The Objectives

More information

6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON

6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON 6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON STORM WATER MANAGEMENT DESIGN BRIEF NEW DEVELOPMENT DRAINAGE SYSTEM REV 0 August 29, 2017 PREPARED BY: HALLEX PROJECT #170532 HALLEX NIAGARA HALLEX HAMILTON

More information

STORM WATER REPORT. Proposed Row House Complex Clare and Hilson 566 Hilson Ave. & 148 Clare St. Ottawa, Ontario PREPARED FOR:

STORM WATER REPORT. Proposed Row House Complex Clare and Hilson 566 Hilson Ave. & 148 Clare St. Ottawa, Ontario PREPARED FOR: Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT Proposed Row House Complex Clare and

More information

Foul Water Drainage Strategy Monkton Road Minster CT12 4EE

Foul Water Drainage Strategy Monkton Road Minster CT12 4EE 66-68 Monkton Road Minster CT12 4EE RMB Consultants (Civil Engineering) Ltd May 2016 RMB Consultants (Civil Engineering) Ltd 39 Cossington Road Canterbury Kent CT1 3HU Tel 01227 472128 www.rmbconsultants.co.uk

More information

Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario

Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario Site Servicing and Stormwater Management Report for Site Plan Control Application C&C Transportation 8015 Russell Road Ottawa, Ontario Prepared for The C and C Group of Companies Attention: Mr. Bob Cousins

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7: Hydraulic Design of Sewers and Storm Water Drains 7.0 HYDRAULIC DESIGN OF SEWERS AND STORM WATER DRAINS 7.1 General Consideration

More information

St. Boniface Industrial Park Phase 2 Municipal Servicing Report

St. Boniface Industrial Park Phase 2 Municipal Servicing Report St. Boniface Industrial Park Phase 2 Municipal Servicing Report Prepared for: City of Winnipeg Prepared by: Stantec Consulting Ltd. File: 116809351 November 5, 2015 ST. BONIFACE INDUSTRIAL PARK PHASE 2

More information

Site Servicing & Stormwater Management Report for Site Plan Control Application. Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario

Site Servicing & Stormwater Management Report for Site Plan Control Application. Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario Site Servicing & Stormwater Management Report for Site Plan Control Application Proposed New Multi-Unit Development 284 Presland Road Ottawa, Ontario Prepared for: Martin Clement Attention: Mr. Martin

More information

Flood Risk Assessment. for. Proposed Residential Development at Bentletts Scrap Yard Claygate Road Collier Street Kent

Flood Risk Assessment. for. Proposed Residential Development at Bentletts Scrap Yard Claygate Road Collier Street Kent Flood Risk Assessment for Proposed Residential Development at Bentletts Scrap Yard Claygate Road Collier Street Kent 1129-1008 February 2016 RCD Consultants Ltd Proposed Residential Development Bentletts

More information

HOTEL KANATA 140 HEARST WAY KANATA, ONTARIO STORMWATER MANAGEMENT REPORT. Prepared for: David Johnston Architect. Prepared By:

HOTEL KANATA 140 HEARST WAY KANATA, ONTARIO STORMWATER MANAGEMENT REPORT. Prepared for: David Johnston Architect. Prepared By: HOTEL KANATA 140 HEARST WAY KANATA, ONTARIO STORMWATER MANAGEMENT REPORT Prepared for: David Johnston Architect Prepared By: BaseTech Consulting Inc. 309 Roywood Crescent Newmarket, Ontario L3Y 1A6 BCI

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to describe:

Learning objectives. Upon successful completion of this lecture, the participants will be able to describe: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to describe: The different approaches for estimating peak runoff for urban drainage network

More information

EPA Waste Water Discharge Licence Application

EPA Waste Water Discharge Licence Application Duleek Waste Water Treatment Works EPA Waste Water Discharge Licence Application ARTICLE 16 COMPLIANCE REQUIREMENTS Meath County Council EPA Document Ref: D0133-01 Section A: Non-Technical Summary Update

More information

DESIGN BULLETIN #16/2003 (Revised July 2007) Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas.

DESIGN BULLETIN #16/2003 (Revised July 2007) Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas. Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas. July 2007 Update to Design Bulletin #16/2003: Added under Design Criteria Culverts of 600mm diameter are commonly used to

More information

CEE 371 May 14, 2009 Final Exam

CEE 371 May 14, 2009 Final Exam CEE 371 May 14, 2009 Final Exam Closed Book, two sheets of notes allowed Please answer questions 3, 6 and 7. In addition, answer either question 1 or 2, and answer either question 4 or 5. The total potential

More information

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

WASTEWATER & STORM WATER COLLECTION AND REMOVAL CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

Summary of Detention Pond Calculation Canyon Estates American Canyon, California

Summary of Detention Pond Calculation Canyon Estates American Canyon, California July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i

More information

New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario

New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario Site Servicing and Stormwater Management Report By Mohamad Salame, P.Eng. Kamco Technique Ltee. 60 Grand Avenue North Cambridge, Ontario N1S

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING Question Bank CE2354 - ENVIRONMENTAL ENGINEERING - II Prepared By: Year: 3rd year Semester: 6th Semester R.THENMOZHI / A.P.Civil J.SHANMUGAPRIYA

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. STORMWATER MANAGEMENT REPORT 22 Perkins Street Ottawa, Ontario Report No. 13030-SWM February 6, 2015 D. B. G R A Y E N G I N E E R I N G I N. Stormwater Management - Grading & Drainage - Storm & Sanitary

More information

Stormwater Management Report Bachman Terrace Residential Development

Stormwater Management Report Bachman Terrace Residential Development Stormwater Management Report Bachman Terrace Residential Development Project # 160401069 Prepared for: Tega Developments Prepared by: Stantec Consulting Ltd. April 14, 2014 Sign-off Sheet This document

More information

STORMWATER DRAINAGE ASSESSMENT. 479 Line 1 Road, Niagara-on-the-Lake, Ontario

STORMWATER DRAINAGE ASSESSMENT. 479 Line 1 Road, Niagara-on-the-Lake, Ontario STORMWATER DRAINAGE ASSESSMENT 479 Line 1 Road, Niagara-on-the-Lake, Ontario November, 2015 1. Site Description Size: Location: Existing Land Use: Proposed Land Use: Soils: Stormwater Outlet: 1.38 hectares

More information

Odense & VCS Denmark 3rd largest city in Denmark 200,000 Inhabitants Birthplace of H.C. Andersen VCS Denmark est Reputation for innovation

Odense & VCS Denmark 3rd largest city in Denmark 200,000 Inhabitants Birthplace of H.C. Andersen VCS Denmark est Reputation for innovation Integreret modellering i Odense. En ny tilgang til udvikling af langsigtede og integrerede spildevands- og regnvandsløsninger Dansk Vand Konference November 2016 Odense & VCS Denmark 3rd largest city in

More information

Level 6 Graduate Diploma in Engineering Hydraulics and hydrology

Level 6 Graduate Diploma in Engineering Hydraulics and hydrology 910-103 Level 6 Graduate Diploma in Engineering Hydraulics and hydrology Sample Paper You should have the following for this examination one answer book ordinary graph paper pen, pencil, ruler Work sheet

More information

Integrated Catchment Modelling

Integrated Catchment Modelling Integrated Catchment Modelling Modelling the whole water cycle in one package Ann Pugh Integrated Water Planning Historically water, wastewater and stormwater modelling occurred in silos with little integration

More information

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012 Bridge Planning Updates Bridge Planning Practitioners Workshop April 2012 Bridge Website Bridge Website Bridge Website Bridge Website BPG 11 Stormwater Management at Rural Bridges Released July 2010 Documents

More information

Hamidreza Kazemi, PhD Candidate Thomas Rockaway, Ph.D., P.E. Josh Rivard, MUP Center for Infrastructure Research Civil and Environmental Engineering

Hamidreza Kazemi, PhD Candidate Thomas Rockaway, Ph.D., P.E. Josh Rivard, MUP Center for Infrastructure Research Civil and Environmental Engineering Hamidreza Kazemi, PhD Candidate Thomas Rockaway, Ph.D., P.E. Josh Rivard, MUP Center for Infrastructure Research Civil and Environmental Engineering Department University of Louisville 1 MSD s Consent

More information

Quantity of sewage. Dry weather flow: Domestic and industrial wastewater (Base flow) including inflow, infiltration and exfiltration

Quantity of sewage. Dry weather flow: Domestic and industrial wastewater (Base flow) including inflow, infiltration and exfiltration Quantity of sewage Quantity of sewage depends on Dry weather flow and storm water Dry weather flow: Domestic and industrial wastewater (Base flow) including inflow, infiltration and exfiltration Infiltration

More information

SCHAEFFERS FUNCTIONAL SERVICING REPORT PROPOSED RESIDENTIAL DEVELOPMENT LAKESHORE ROAD WEST TOWN OF OAKVILLE

SCHAEFFERS FUNCTIONAL SERVICING REPORT PROPOSED RESIDENTIAL DEVELOPMENT LAKESHORE ROAD WEST TOWN OF OAKVILLE FUNCTIONAL SERVICING REPORT PROPOSED RESIDENTIAL DEVELOPMENT 346 362 LAKESHORE ROAD WEST TOWN OF OAKVILLE PROJECT 2016-4442 JULY 2017 REVISED: APRIL 2017 C O N S U L T I N G E N G I N E E R S 64 Jardin

More information

Module 8 (L31 L34): Storm Water & Flood Management : Storm water management, design of drainage system, flood

Module 8 (L31 L34): Storm Water & Flood Management : Storm water management, design of drainage system, flood Module 8 (L31 L34): Storm Water & Flood Management : Storm water management, design of drainage system, flood routing through channels and reservoir, flood control and reservoir operation, case studies.

More information

Kildare County Council. Proposed Development of 74 no. Residential Units at Craddockstown Road, Cradockstown Demesne, Naas, Co. Kildare.

Kildare County Council. Proposed Development of 74 no. Residential Units at Craddockstown Road, Cradockstown Demesne, Naas, Co. Kildare. Job No. : 16027 SHB1-CRA-CS-MOR Date: April 2017 Kildare County Council Proposed Development of 74 no. Residential Units at Craddockstown Road, Cradockstown Demesne, Naas, Co. Kildare. 2B Richview Office

More information

Introduction to Urban Drainage. Scott Arthur. Civil Engineering at the School of the Built Environment. [Class 1 - Into+ 1]

Introduction to Urban Drainage. Scott Arthur. Civil Engineering at the School of the Built Environment. [Class 1 - Into+ 1] Introduction to Urban Drainage Scott Arthur s.arthur@hw.ac.uk Civil Engineering at the School of the Built Environment [Class 1 - Into+ 1] Do we even need a drainage system? [Class 1 - Into+ 2] Greenfield

More information

Waste Water treatment by Multi Soil Layering Method

Waste Water treatment by Multi Soil Layering Method Waste Water treatment by Multi Soil Layering Method 1 Background The use of soil for water treatment has a long history in the world. Conventional method Land treatment Sand filter Septic systems (EPA)

More information

Whole of Water Cycle Modelling Pilot Study

Whole of Water Cycle Modelling Pilot Study Whole of Water Cycle Modelling Pilot Study Presentation Outline Background Model development Water and Sewer Stormwater Advantages of Integrated Modelling Challenges and Limitations Project Aims To investigate

More information

Water supply components

Water supply components Water supply components Water sources structures (Dams, wells, reservoirs) Surface water Groundewater Pipelines from source Water treatment plant components Pumping stations Storage (elevated tanks) Distribution

More information

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY FOR CITY OF OTTAWA PROJECT NO.: 11-532 FOR TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Existing Conditions... 2 1.2 Required Permits / Approvals...

More information

Type of Area Density (persons/ha) Large lots 5-7 Small lots, single family 75 Small lots, two family 125 Multistory apartments min.

Type of Area Density (persons/ha) Large lots 5-7 Small lots, single family 75 Small lots, two family 125 Multistory apartments min. Design of Sanitary Sewer System Key components Service connections, Manholes and pump stations Design Flows 1. Infiltration and interflow (71 to 14 m 3 /d/km). Flow from the service connections Type of

More information

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Environmental Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Sustainable, Reliable, Affordable Stormwater Attenuation Systems Sustainable Drainage

More information

Appendix H. Storm Water Management

Appendix H. Storm Water Management Appendix H Storm Water Management R.J. Burnside & Associates Limited 292 Speedvale Avenue West Unit 20 Guelph ON N1H 1C4 CANADA telephone (519) 823-4995 fax (519) 836-5477 web www.rjburnside.com Technical

More information

International Journal of Advance Research in Engineering, Science & Technology

International Journal of Advance Research in Engineering, Science & Technology Impact Factor (SJIF): 3.632 International Journal of Advance Research in Engineering, Science & Technology e-issn: 2393-9877, p-issn: 2394-2444 Volume 3, Issue 5, May-2016 ANALYSIS OF RAINFALL DATA AND

More information

Storm water Catchment Analysis

Storm water Catchment Analysis Storm water Catchment Analysis Analysis index 1. Storm water attenuation tank sizing method 2. Consent notices for storm water attenuation tanks 3. Summary of sub catchments 4. Hydrological Analysis for

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

Newtown Creek Superfund Site Point Sources Sampling CAG Meeting March 22, 2016

Newtown Creek Superfund Site Point Sources Sampling CAG Meeting March 22, 2016 Newtown Creek Superfund Site Point Sources Sampling CAG Meeting March 22, 2016 CSTAG Meeting May 19-20, 2014 May 19, 2015 1 Objectives Define point source discharge for the study area Discuss the purpose

More information

The Drainage Basin System

The Drainage Basin System The Drainage Basin System These icons indicate that teacher s notes or useful web addresses are available in the Notes Page. This icon indicates that the slide contains activities created in Flash. These

More information

What is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream

What is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream What is runoff? Runoff Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream 1 COMPONENTS OF Runoff or STREAM FLOW 2 Cont. The types of runoff

More information

Using SWMM 5 in the continuous modelling of stormwater hydraulics and quality

Using SWMM 5 in the continuous modelling of stormwater hydraulics and quality Using SWMM 5 in the continuous modelling of stormwater hydraulics and quality M.J. Cambez 1, J. Pinho 1, L.M. David 2 * 1 Trainee at Laboratório Nacional de Engenharia Civil (LNEC) 2 Research Officer at

More information

OHM Groups. FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph August 5, Prepared By:

OHM Groups. FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph August 5, Prepared By: Prepared By: OHM Groups FUNCTIONAL SERVICING REPORT 33 Arkell Road City of Guelph 114169 August 5, 2015 Guelph Owen Sound Listowel Kitchener Exeter Hamilton GTA 650 Woodlawn Rd. W., Block C, Unit 2, Guelph

More information

APPENDIX E Drainage and Stormwater Management Report

APPENDIX E Drainage and Stormwater Management Report APPENDIX E Drainage and Stormwater Management Report Drainage and Stormwater Management Report Courtneypark Drive East Class EA & Preliminary Design Prepared for: City of Mississauga Prepared by: Stantec

More information

EXECUTIVE SUMMARY 1 INTRODUCTION 2 METHODOLOGY 4

EXECUTIVE SUMMARY 1 INTRODUCTION 2 METHODOLOGY 4 EXECUTIVE SUMMARY 1 INTRODUCTION 2 Objective 2 Background 2 METHODOLOGY 4 Site Selection 4 Testing Procedure 4 Methods 4 Rainfall 4 Discharge Recording. 5 Water sampling 5 Stormwater Analysis 5 Maintenance

More information

FROM ROOFTOP TO DRAIN NON-TRADITIONAL APPLICATIONS OF HEC-RAS 2D FROM ROOFTOP. Calibration: A Hands-On Approach to Making a Model Reflect Reality

FROM ROOFTOP TO DRAIN NON-TRADITIONAL APPLICATIONS OF HEC-RAS 2D FROM ROOFTOP. Calibration: A Hands-On Approach to Making a Model Reflect Reality FROM ROOFTOP TO DRAIN NON-TRADITIONAL APPLICATIONS OF HEC-RAS 2D Andrew C. Yung, PE, CFM Andres A. Salazar, PhD, PE April 26, 2017 1 FROM ROOFTOP 2 Amphitheater: 97,000 SF flexible engineered fabric roof

More information

Water Resources Management Plan

Water Resources Management Plan P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

Sewer Capacity Assessment

Sewer Capacity Assessment Sewer Capacity Assessment Wainlode Lane, Norton, Gloucestershire DE-1607-722 Version 2 Date: 10 th February 2017 Black & Veatch Ltd. 60 High Street Redhill Surrey RH1 1SH Sewer Capacity Assessment Summary

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method

More information

Integrating Triple Bottom Line

Integrating Triple Bottom Line WATER WASTE ENERGY Shifting Decision Making Integrating Triple Bottom Line Social Environmental Financial Background Project Basis: The likely future direction of the management of urban drainage Design

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS ESTIMATING RUNOFF FROM SMALL WATERSHEDS June 2011 THIS PAGE LEFT BLANK INTENTIONALLY. June 2011 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method Values June 2011

More information

Landfill design General principles

Landfill design General principles Landfill design General principles Average height of a landfill should be at least 15 m Each section (cell) should accommodate waste to be landfilled during 5 years period Sections/cells should be hydraulically

More information

MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation

MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation Watershed MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1 A watershed is an area of land thaaptures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed

More information

Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS

Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Lagan Cement Ltd. IPPC Licence Application Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Air Contents F.2.0 Air Emissions.3 Water

More information

Kildare County Council. Proposed Development of 77 no. Residential Units at College Wood Manor, Ballingappa Road, Clane, Co. Kildare.

Kildare County Council. Proposed Development of 77 no. Residential Units at College Wood Manor, Ballingappa Road, Clane, Co. Kildare. Job No. : 16027 SHB2-CLA-CS-MOR Date: Feb 2018 Kildare County Council Proposed Development of 77 no. Residential Units at College Wood Manor, Ballingappa Road, Clane, Co. Kildare. Engineering Report 2B

More information

WinSLAMM v Program Modifications Final, 3/16/19

WinSLAMM v Program Modifications Final, 3/16/19 WinSLAMM v 10.4.1 Program Modifications Final, 3/16/19 1. Printing Set up a printing option for.pdf files for input data and output summary data. 2. Added the Pipe input data to the printing input data

More information

The Membrane Wastewater Treatment Plant in Ihn Layman s report

The Membrane Wastewater Treatment Plant in Ihn Layman s report The Membrane Wastewater Treatment Plant in Ihn Layman s report 1 Entsorgungsverband Saar, Tel. +49 6 81/ 60 00-0, P.O.Box 10 01 22, D-66001 Saarbrücken, www.entsorgungsverband.de The Wastewater Treatment

More information

Respond! Housing Association. Residential Development at Flinters Field, Athy, Co. Kildare. Engineering Report. Job No. : Date: April 2017

Respond! Housing Association. Residential Development at Flinters Field, Athy, Co. Kildare. Engineering Report. Job No. : Date: April 2017 Job No. : 16036 Date: April 2017 Respond! Housing Association Residential Development at Flinters Field, Athy, Co. Kildare Engineering Report 2B Richview Office Park Clonskeagh Dublin 14 Contents Amendment

More information

GLOBAL SENSITIVITY ANALYSIS FOR URBAN WATER QUALITY MODELLING: COMPARISON OF DIFFERENT METHODS

GLOBAL SENSITIVITY ANALYSIS FOR URBAN WATER QUALITY MODELLING: COMPARISON OF DIFFERENT METHODS Uncertainty assessment of sewer sediment erosion modelling 9th International Conference on Urban Drainage Modelling Belgrade 2012 GLOBAL SENSITIVITY ANALYSIS FOR URBAN WATER QUALITY MODELLING: COMPARISON

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

UMLALAZI-NKANDLA SMART GROWTH DEVELOPMENT CENTRE PROVISION OF CIVIL ENGINEERING SERVICES

UMLALAZI-NKANDLA SMART GROWTH DEVELOPMENT CENTRE PROVISION OF CIVIL ENGINEERING SERVICES UMLALAZI-NKANDLA SMART GROWTH DEVELOPMENT CENTRE PROVISION OF CIVIL ENGINEERING SERVICES PROPOSED STORMWATER RETICULATION DESIGN AND MANAGEMENT DATE: OCTOBER 2011 PREPARED FOR: PREPARED BY: DEPARTMENT

More information

Design criteria, Flooding of sewer systems in flat areas.

Design criteria, Flooding of sewer systems in flat areas. Design criteria, Flooding of sewer systems in flat areas. Ir Harry. Van Luijtelaar Tauw bv, P.O. box 830, 7400 AV Deventer, The Netherlands, Telephone +31570699304, Fax +31570699666, E-mail hlj@tauw.nl.

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Dunpar Developments Inc.

Dunpar Developments Inc. Dunpar Developments Inc. Proposed Townhouse Development 2158, 2168, 2180 and 2192 Trafalgar Road Oakville, Ontario Functional Servicing and Stormwater Management Report (in Support of a Re-Zoning and Site

More information

SITE SERVICING PRELIMINARY DESIGN BRIEF

SITE SERVICING PRELIMINARY DESIGN BRIEF 855 Carling Avenue Proposed Redevelopment SITE SERVICING PRELIMINARY DESIGN BRIEF March 2010 March 23, 2010 RVA 081785 Arnon Corporation 1801 Woodward Dr. Ottawa, ON K2C 0R3 Attention: Mike Casey Re: 855

More information

ENV 4001: ENVIRONMENTAL SYSTEMS ENGINEERING. University of South Florida Civil & Environmental Eng.

ENV 4001: ENVIRONMENTAL SYSTEMS ENGINEERING. University of South Florida Civil & Environmental Eng. ENV 4001: ENVIRONMENTAL SYSTEMS ENGINEERING Fall 2016 Quiz #2 Wednesday, October 26 University of South Florida Civil & Environmental Eng. Prof. J.A. Cunningham Instructions: 1. You may read these instructions,

More information

Drainage Servicing Report - Terms of Reference

Drainage Servicing Report - Terms of Reference Urban Form and Corporate Strategic Development City Planning 7th Floor, Edmonton Tower 10111 104 Avenue NW Edmonton, AB T5J 0J4 edmonton.ca July 2018 1 Introduction: Drainage Servicing Reports Drainage

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

Introduction. Keywords: Oil Palm, hydrology, HEC-HMS, HEC-RAS. a * b*

Introduction. Keywords: Oil Palm, hydrology, HEC-HMS, HEC-RAS. a * b* The Effect of Land Changes Towards in Sg. Pandan Perwira Bin Khusairi Rahman 1,a* and Kamarul Azlan bin Mohd Nasir 1,b 1 Faculty of Civil Engineering, Universiti Teknologi Malaysia, Malaysia a * wirakhusairirahman@gmail.com,

More information

PROPOSED FOOD STORE 150 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For:

PROPOSED FOOD STORE 150 TORONTO STREET SOUTH MARKDALE, ONTARIO. Job No ENGINEERING REPORT. Prepared For: PROPOSED FOOD STORE 150 TORONTO STREET SOUTH Job No. 16227 ENGINEERING REPORT Prepared For: MAVERICK DEVELOPMENT CORPORATION 150 Woodbine Avenue Suite 3005 Toronto, Ontario Prepared By: The Odan/Detech

More information

Landbase Systems Draft 5/2/2014 Page: 1

Landbase Systems Draft 5/2/2014 Page: 1 Study of the potential Green Stormwater Infrastructure (GSI) strategies and options to reduce localized flooding and combined sewer overflows in conjunction with combined network adjustments along and

More information

WASTEWATER PLANNING USERS GROUP GUIDE TO THE QUALITY MODELLING OF SEWER SYSTEMS

WASTEWATER PLANNING USERS GROUP GUIDE TO THE QUALITY MODELLING OF SEWER SYSTEMS WASTEWATER PLANNING USERS GROUP WASTEWATER PLANNING USERS GROUP GUIDE TO THE QUALITY MODELLING OF SEWER SYSTEMS Version 1.0 November 2006 WASTEWATER PLANNING USERS GROUP GUIDE TO THE QUALITY MODELLING

More information

Managed Aquifer Recharge (MAR) Practical Techniques for the Caribbean

Managed Aquifer Recharge (MAR) Practical Techniques for the Caribbean Managed Aquifer Recharge (MAR) Practical Techniques for the Caribbean Scope of Presentation What is MAR? Antigua and Barbuda water resources issues Why promote MAR? MAR: Techniques MAR: Design criteria

More information

Carlow County Council

Carlow County Council Carlow County Council WASTEWATER DISCHARGE LICENCE APPLICATION FOR THE AGGLOMERATIO OF CARLOW TOWN AND ENVIRONS AND SECTIONS OF GRAIGUECULLEN IN COUNTY LAOIS WASTEWATER DISCHARGE LICENCE APPLICATION NON-TECHNICIAL

More information

Sixth Semester B. E. (R)/ First Semester B. E. (PTDP) Civil Engineering Examination

Sixth Semester B. E. (R)/ First Semester B. E. (PTDP) Civil Engineering Examination CAB/2KTF/EET 1221/1413 Sixth Semester B. E. (R)/ First Semester B. E. (PTDP) Civil Engineering Examination Course Code : CV 312 / CV 507 Course Name : Engineering Hydrology Time : 3 Hours ] [ Max. Marks

More information

Sewer system- Design Criteria

Sewer system- Design Criteria The Islamic University of Gaza Faculty of Engineering Civil Engineering Department Sanitary Engineering (ECIV 4325) Instructor: Dr. Abdelmajid Nassar Lect. 05-07 Sewer system- Design Criteria according

More information

2. DEFINITIONS. American Association of State Highway and Transportation Officials.

2. DEFINITIONS. American Association of State Highway and Transportation Officials. 2. DEFINITIONS 2.010 Definitions [See Amendment 2] In addition to words and terms that may be defined elsewhere in this manual, the following words and terms shall have the meanings defined below: AASHTO:

More information

The Source Loading and Management Model (SLAMM)

The Source Loading and Management Model (SLAMM) The Source Loading and Management Model (SLAMM) A Water Quality Management Planning Model for Urban Stormwater Runoff Robert Pitt, P.E., Ph.D., DEE Department of Civil and Environmental Engineering, The

More information

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Sanitation District No. 1 of Northern Kentucky Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Ohio WEA Collection Systems Workshop May 5, 2011 Sanitation District No. 1

More information

Modelling and Analysis of EES Systems Using SWMM

Modelling and Analysis of EES Systems Using SWMM Planning and Design of a Right-of-Way LID (Etobicoke Exfiltration System) July 24 th 2015 Toronto, Ontario, Canada ling and Analysis of EES Systems Using SWMM Darko Joksimovic Department of Civil Engineering,

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

TECHNICAL BULLETIN. Synthetic Turf Athletic Field Drainage Design Assistance

TECHNICAL BULLETIN. Synthetic Turf Athletic Field Drainage Design Assistance TECHNICAL BULLETIN Synthetic Turf Athletic Field Drainage Design Assistance The SportsEdge HQ geocomposite strip drain products are engineered specifically for use in synthetic turf athletic field base

More information

STORM DRAINS AND IRRIGATION

STORM DRAINS AND IRRIGATION TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 STORM DRAINS AND IRRIGATION 105.1. STORM DRAINS... 105.1 105.2. METHODS OF ANALYSIS... 105.1 105.2.1. Rational Method... 105.1 105.2.2.

More information

WinSLAMM v Program Modifications Final, 12/12/17

WinSLAMM v Program Modifications Final, 12/12/17 WinSLAMM v 10.3.4 Program Modifications Final, 12/12/17 1. Corrected an error in the Biofilter caused by an improperly defined variable that caused an overflow during very long model runs. 2. Corrected

More information