LEVEL OF EFFORT & NEGOTIATIONS
|
|
- Martha McGee
- 6 years ago
- Views:
Transcription
1 LEVEL OF EFFORT & NEGOTIATIONS Phil Howlett, P.E. Richard De La Cruz, P.E. November 3, 2017
2 Table of contents Welcome Pre-Level of Effort (LOE) Level of Effort (LOE): Scopes Level of Effort (LOE): Schedule Level of Effort (LOE): Budget Good Practice Bad Practice Closing Remarks/Questions? 2
3 First Thought Productivity is never an accident. It is always the result of a commitment to excellence, intelligent planning, and focused effort. Paul J. Meyer 3
4 Look at the Big Picture We have different types of contracts Schematic and Environmental (S&E) Plans Specifications & Estimates (PS&E) Utility Engineering Traffic Engineering Survey Value Engineering Planning General Engineering Consultant (GEC) Construction Engineering Inspection (CEI) Intelligent Traffic Systems (ITS) Geotechnical Engineering Other Materials Engineering 4
5 When do we negotiate Level of Effort? Master Contracts Specific Deliverable (SD) Contracts Negotiation of LOE Indefinite Deliverable (ID) Contracts N/A Work Authorizations SD Contracts Some Negotiation may be required ID Contracts Negotiation of LOE Supplemental Agreements - maybe Supplemental Work Authorizations - maybe 5
6 Level of Effort (LOE) It is absolutely necessary that both parties have a clear understanding of the work to be accomplished and deliverables expected in order to develop a Level of Effort and evaluate the reasonableness of a cost proposal. Level of Effort (LOE) Scope (What do we want accomplished and Deliverables) Schedule (When are things to be accomplished) Budget (How much will it cost and a breakdown of who will do the work?) 6
7 Level of Effort (LOE) Negotiation Challenging Fair and Reasonable Looking for the Win-Win Time Consuming There is no easy button What would it be like to negotiate with a....dentist.. for a Tooth Extraction? 7
8 8
9 First Things First (Pre-Level of Effort) 9
10 Pre-Level of Effort Scoping Meeting Communication Project Information Scopes Invoicing Accountability 10
11 Scoping Meeting Communication Org Charts Points of Contact Best method How often Change of Personnel Escalation Process 11
12 Scoping Meeting Project Information Project Limits Control Section Job (CSJ) Numbers Schedule / Milestones Challenges Project unknowns Stakeholders Drainage, driveway, seasonal work, etc. 12
13 Vision Assumptions 13
14 Scoping Meeting - Scopes Establish the basis of payment. Review both scopes line by line. Document what needs to be added, modified, or removed. Very Important: clearly define all deliverables. 14
15 Scoping Meeting - Invoicing Obtain understanding of what will be allowed. Remember: the basis of payment used must be in the master contract. What ensures good invoicing? Well thought out and documented deliverables. If you need help, ask. (PEPS can help) 15
16 Scoping Meeting - Invoicing Remember: Any direct labor, unit cost, or other direct expense classification not included in the contract is not eligible for use under a work authorization. Any direct labor, unit cost, or other direct expense classification included in the contract, but not in a work authorization, is not eligible for payment under that work authorization. If the rates are not in the work authorization, they cannot be billed. 16
17 Scoping Meeting - Accountability Understanding of Expectations Quality Timeliness Communication Provider Evaluations 17
18 Scope Meeting Tips Have an agenda Ensure the right people attend Everybody reviews the scopes ahead of time Visit/Drive the project ahead of time Bring a list of questions Summarize Review understandings and expectations Delegate action items Document Allow time for this meeting 18
19 Level of Effort (LOE) Scopes (What and deliverables) Schedule (When) Budget (How much and who) 19
20 Level of Effort (LOE) - Scopes Finalize the scopes (clean up comments from the scoping meeting). Ensure the scopes have the level of detail needed based on the basis of payment. Lump Sum Specific Deliverable, Cost Plus Fixed Fee, Unit Cost Be sure to elaborate on specific details where needed. Spell out all acronyms the first time used. List well-defined deliverables. Consider using a phased approach when appropriate. 20
21 Level of Effort (LOE) - Scopes Remember: If the services are not in the master contract s scope, they cannot be put it in the work authorization s scope. If the services are not in the work authorization s scope, those services cannot be performed and payment cannot be expected. Use the master contract s scope to create your work authorization s scope. 21
22 Level of Effort (LOE) - Schedule Think of it as a management reporting tool as well as an implementation tool to help pace the detailed activities. Establish milestones and submittal dates. Work Breakdown Structure Tasks must follow the scopes of services and the fee schedule. Include sufficient review times (for both the State and consultant). 22
23 Level of Effort (LOE) - Schedule First activity should be Start Date = Date of Execution (Not an actual date) Do NOT use Notice to Proceed in schedule. Activity dates are later than the actual (anticipated) date of execution. Termination Date Indefinite deliverable (ID) contracts are limited to a 5-year maximum. Be sure to include Termination Date = xx/xx/20xx. Should typically be the last calendar day of a month Try not to end a work authorization in August or December. Work authorization termination date cannot go beyond the master contract s termination date 23
24 Level of Effort (LOE) - Budget Ensure tasks identified in the fee schedule align with the scope and the work schedule. Ensure the rates and labor classifications are used in accordance with the contract. ODEs must be assigned a function code. Calculations should be made from numbers rounded to the nearest penny (except mileage). Significantly helps with consistency for summary sheet Allow some flexibility. Not every item needs a quantity (classifications, unit costs, ODE, tasks) Primary control is that maximum amount payable is a not to exceed amount 24
25 Level of Effort (LOE) - Budget Ensure HUB goal or DBE goal will be met. Include a summary sheet broken out by firm, function code, and CSJ. Include a table of deliverables if using lump sum. Use the latest table of deliverable template. Align the function codes with the scope and fee schedule Ensure each deliverable description is distinguishable from one another. Rates, labor classifications and other direct expenses can only be invoiced if they are included in both the contract and the work authorization. Perform a thorough quality review of spreadsheet calculations. 25
26 Remember Clearly define deliverables. Ensure consistency between scopes, budget, and work schedule. Activities Task titles Function codes Formatting Use the available checklists to help QC contracts and work authorizations. 26
27 Work Authorization Review Checklist (Example) EXHIBITS A & B Check Headers and Footers Legacy Contract No. & WA/SWA No. (Upper Right) Contract PS No. & PS PO No. (Upper Right) Page Numbers and Exhibit A/B in Footer Ensure WA scope MUST match master contract scope Ensure Acronyms are spelled out at least once Find and Replace TxDOT to the State the State shall to the State will the Engineer will to Engineer shall the Surveyor to the Engineer s Surveyor (exception Survey Contracts) Do not use "you" or "we" this Contract to this Work Authorization Check General Formatting (Margins, excess spacing between paragraphs, justifications, etc.) Exhibit B should have CSJ, HWY, project limits, county, and district. 27
28 Work Authorization Review Checklist (Example) EXHIBIT C Check Headers and Footers Legacy Contract No. & WA/SWA No. (Upper left) Contract PS No. & PS PO No. (Upper Right) Page Number(s) and Exhibit C in Footer Dates do not begin prior to WA Execution Tasks follow Exhibit B and Exhibit D Ensure it has "Work Authorization No. XX termination date: xx/xx/20xx" Ensure it has "Prime Provider Name: xxxxxxxxxxx" (exact name) Change "Notice to Proceed" or "NTP to "Start Date = Date of Execution Termination Date must not go beyond Contract Termination Date Ensure the termination date is the last working day of the month Avoid termination dates at the end of the fiscal year and the end of the calendar year 28
29 Work Authorization Review Checklist (Example) EXHIBIT D Total amount is covered in the contract (Check PS-CAMS) and correct WA number Fee Schedule is split out by CSJ Ensure the correct Method of Payment is being used and is in master contract Check Headers and Footers Legacy Contract # & WA/SWA # (Upper left) Contract PS # & PS PO # (Upper Right) Method of Payment (Center Header) Page Numbers and Exhibit D in Footer Ensure "Prime Provider Name: xxxxxxxxxxx" or "Sub-Provider Name: xxxxxxxxx" is on each page General Formatting (Margins, excess spacing between paragraphs, justifications, etc.) Staffing Classification Names and Rates MUST match contract Formulas add up Tasks follow Exhibit B and Exhibit C Other Direct Expenses Function Code assigned Names and rates match contract Include columns: Description, Unit, Cost, Quantity Summarization by Provider (Prime and Subs), Function Code and CSJ Lump Sum WA's have a Table of Deliverables and $ amounts match 29
30 If you have any questions, PEPS is here to help. 30
31 An effective Level of Effort Productivity is never an accident. It is always the result of a commitment to excellence, intelligent planning, and focused effort. Paul J. Meyer Philip Howlett 31
32 Thank you! Questions? 32
33 Contact Information Phil Howlett, P.E. TxDOT PEPS San Antonio (210) Richard De La Cruz, P.E. TxDOT San Antonio (210)
INVOICE DEVELOPMENT AND SUBMITTAL PROCESS
INVOICE DEVELOPMENT AND SUBMITTAL PROCESS Tamika Griffin November 3, 2017 Table of Contents 1 2 3 4 5 6 7 Standard Operating Procedure Roles and Responsibilities Invoice Submittal Payment Types and Required
More informationWORK AUTHORIZATION ASSIGNMENT PROCESS
WORK AUTHORIZATION ASSIGNMENT PROCESS Lynn Daniel, P.E. Chris Henry, P.E. November 3, 2017 Table of Contents 1 2 3 4 5 6 Welcome Address & Opening Remarks PEPS Central Service Center Consultant Contract
More informationPEPS DIVISION PEPS Conference Martin Rodin, P.E.
PEPS DIVISION 2017 PEPS Conference Martin Rodin, P.E. November 3, 2017 Texas Department of Transportation, Right of Way Division May 2, 2016 Mission Mission Work with our TxDOT customers and external partners
More informationPRE-RFQ MEETING I-345 FEASIBILITY STUDY SCHEMATICS & ENVIRONMENTAL (SD)
PRE-RFQ MEETING I-345 FEASIBILITY STUDY SCHEMATICS & ENVIRONMENTAL (SD) Solicitation 18-8SDP5001 Footer Text Housekeeping Thanks for coming! Be sure to provide your information on the sign-in sheet Bathrooms
More informationPROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing
Project Description PROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing The Siphon 1 River Crossing project consists of replacing an existing aerial pipe crossing
More informationTxDOT Internal Audit Travel Division Operations Audit (1405-1) Department-wide Report
Travel Division Operations Audit (1405-1) Department-wide Report Introduction This report has been prepared for the Transportation Commission, TxDOT Administration and Management. The report presents the
More informationCOST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL
SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,
More informationOctober 19, 2017 Shailendra G. Patel, PE, DBIA Division Administrator, Alternative Project Delivery
General Engineering Consultant Services for I-64 Hampton Roads Bridge-Tunnel Expansion Project Hampton Roads District RFP No. HRD-20171013 Optional Pre-Proposal Conference October 19, 2017 Shailendra G.
More informationStep 1. Develop the Workforce Integration Project Plan. Chapter Goal
1 Step 1 Develop the Workforce Integration Project Plan The project plan is critical throughout the entire transition process and will be a working document that is continually updated. It will guide you
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS FOR COMPENSATION STUDY Proposals Due: November 3, 2016, 4:00 PM 1.0 OBJECTIVE SECTION 1 SUBMITTAL PROCEDURES & DEADLINE The City of Signal Hill is seeking proposals from qualified
More informationPURCHASING AND JOB COSTING FOR CONTRACTORS. Leslie Shiner Owner, Principal of The ShinerGroup
PURCHASING AND JOB COSTING FOR CONTRACTORS Leslie Shiner Owner, Principal of The ShinerGroup Leslie Shiner The ShinerGroup - Owner and Principal Financial & Management Consultant for Contractors MBA in
More informationPEPS Pre-RFQ Meeting. IH 10 and US 59 Freeway Expansion from 4 to 6 Lanes CEI Beaumont District. March 5, Date. Footer Text
PEPS Pre-RFQ Meeting IH 10 and US 59 Freeway Expansion from 4 to 6 Lanes CEI Beaumont District March 5, 2018 Footer Text Housekeeping Thanks for coming! Be sure to provide your information on the sign-in
More informationGROUND RULES AND PRICING INSTRUCTIONS:
GROUND RULES AND PRICING INSTRUCTIONS: F-22 REPLENISHMENT SPARES PRICING CY2013 CY2017 REQUIREMENTS CONTRACT (MRC) WITH VARIABLE QUANTITIES I. GENERAL INSTRUCTIONS: The objective of this Spares Requirements
More informationPRE-RFQ MEETING CTTS PLANNING
PRE-RFQ MEETING CTTS PLANNING Austin District Housekeeping Thanks for coming! Be sure to provide your information on the sign-in sheet Bathrooms and drinking fountain by the visitor entrance Please turn
More informationTTUHSC Staff Performance Management (PM) System User s Guide: Position Description and Performance Evaluation 12/2011
TTUHSC Staff Performance Management (PM) System User s Guide: Position Description and Performance Evaluation 12/2011 1 Table of Contents Program Overview... 4 Staff Performance Management Program Home
More informationANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore
More informationInternal Audit Report. Rail Project Management TxDOT Office of Internal Audit
Internal Audit Report Rail Project Management TxDOT Office of Internal Audit Objective To evaluate the contract management and oversight of state wide rail projects and programs, specifically, Railroad
More informationREQUEST FOR PROPOSALS TO PROVIDE PLANNING, RECOMMENDATIONS, AND CONTRACT DOCUMENTS FOR PIPELINE INSPECTION AND CONDITION ASSESSMENT FOR THE
REQUEST FOR PROPOSALS TO PROVIDE PLANNING, RECOMMENDATIONS, AND CONTRACT DOCUMENTS FOR PIPELINE INSPECTION AND FOR THE 24-INCH UNIT B AND 27-INCH UNIT K RANCHO SUMMIT DRIVE PIPELINES 12-INCH ENCINITAS
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationProject Plan. CxOne Guide
Project Plan CxOne Guide CxGuide_ProjectPlan.doc November 5, 2002 Advancing the Art and Science of Commercial Software Engineering Contents 1 INTRODUCTION... 1 1.1 DELIVERABLE PURPOSE... 1 1.2 LIFECYCLE...
More informationScope of Services Traffic Signal Retiming Contract FM NO Florida Department of Transportation District Four
Scope of Services Traffic Signal Retiming Contract FM NO. 230017-8-32-01 Florida Department of Transportation District Four A-1 Contents 1. Background... 3 2. Summary of Services... 3 3. Consultant Requirements...
More informationNIWA PY 17 One Stop Operator & WIOA Career Services RFP Questions and Answers as of
NIWA PY 17 One Stop Operator & WIOA Career Services RFP Questions and Answers as of 1.23.17 Questions prior to 1.18.17 Bidder s Meeting 1. Q: Is performance data available for the last complete program
More informationEXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: DISTRICT TWO
EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: 430959-1-22-01 DISTRICT TWO Stage I Scope A-1 August 2, 2017 SCOPE OF SERVICES DISTRICTWIDE ENVIRONMENTAL SERVICES FLORIDA DEPARTMENT OF TRANSPORTATION
More informationNC State University OESAD GUIDELINES Contract Year
July 1, 2014 NC State University OESAD GUIDELINES Contract Year 2014-2016 I. Informal Projects A. Preface Based on the North Carolina Administrative Code (NCAC), Title 01, Subchapter 30D Section.0300 Selection
More informationInternational Subawards
International Subawards Alternatives to Cost Reimbursable Subrecipient Agreements Presentation for the Federal Demonstration Partnership International Subawards Subcommittee 11 January 2008 David Brady,
More informationPete Fowler CONSTRUCTION Services, Inc. Construction Defect Estimating and Analysis. Introduction. Program Outline. Learning Objectives
Pete Fowler CONSTRUCTION Services, Inc. Construction Defect Estimating and Analysis Introduction Program Outline Construction Defect Estimating and Analysis is for anyone who needs to understand construction
More informationThe Force is Strong With This One Darth Vader, Star Wars Episode IV, Quick Start Page 1 of 14 Workamajig
The Force is Strong With This One Darth Vader, Star Wars Episode IV, 1977 Quick Start Page 1 of 14 Workamajig Quick Start Guide This section is designed for users that wish to get started with Workamajig
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR
More informationAuditing Timeline. Top-Line Version
Auditing Timeline Top-Line Version As a complement to their book Agency Audits: How to Achieve Success, Joanne Davis and Jane Twyon have created a timeline that takes marketers through the auditing journey.
More informationRequired Standards for Consultant Invoices
Required Standards for Consultant Invoices Purpose: The introduction of the Maryland Financial Management Information System (FMIS) has led us to examine our current consultant invoice payment processing.
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationA Single System to Streamline Your Project-Based Operation Corecon Technologies, Inc. All rights reserved.
A Single System to Streamline Your Project-Based Operation About Corecon Technologies, Inc. Founded in 1999 Customers in 14 Countries Construction Software Focus: Estimating, Project Management, Job Cost
More informationFinal Design Guideline
Final Design Guideline May, 2016 July, 2011 Check the Capital Project Delivery website to ensure this is the current version Table of Contents Purpose... 1 Introduction... 1 FD Support... 1 Roadway and
More informationSPECIFICATION NO. TxDOT * REVISED: AUGUST 2017 CRIMINAL BACKGROUND CHECKS
SPECIFICATION NO. TxDOT 961-30-16 * REVISED: AUGUST 2017 CRIMINAL BACKGROUND CHECKS PUBLICATION This specification is a product of the Texas Department of Transportation (TxDOT). This specification may
More informationAPPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT
APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:
More informationTABLE OF CONTENTS NEW BRAUNFELS REGIONAL AIRPORT TXDOT CSJ# 17MPNEWBR
TABLE OF CONTENTS NEW BRAUNFELS REGIONAL AIRPORT TXDOT CSJ# 17MPNEWBR 1. REQUEST FOR QUALIFICATIONS ANNOUNCEMENT 2. EVALUATION CRITERIA 3. FORM AVN-551 (PLEASE BE SURE TO DOWNLOAD THE MOST RECENT REVISED
More informationAddendum #02 New County Office Building Responses to RFP Questions
Sam Lin Manager Project Development Unit 1402 Maple Street Redwood City, CA 94063 650-369-4766 September 22, 2017 slin@smcgov.org Addendum #02 New County Office Building Responses to RFP Questions To All
More informationRelationship-Based, Performance-Based Contracting (RPC)
Relationship-Based, Performance-Based Contracting (RPC) for Professional Construction Management Services Presented at the: CMAA Owners Forum San Antonio, Texas May 17, 2011 Presented by: Robert Mannebach,
More informationScope Management Guideline January, 2016
Scope Management Guideline January, 2016 Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Scope Management Overview... 1 Charter... 4 Scope Statement...
More informationThe United States Air Force Design-Build Plus User s Guide
The United States Air Force Design-Build Plus User s Guide Design-Build Plus User s Guide Section I. Introduction II. III. IV. References Executive Summary Roles and Responsibilities V. Project Development
More informationCAPITAL PROGRAM PROJECT MANAGEMENT SOLUTION
REQUEST FOR COMPETITIVE SEALED PROPOSALS Solicitation Number: R-13-004-MR CAPITAL PROGRAM PROJECT MANAGEMENT SOLUTION ADDENDUM #2 11:00 AM Central March 28, 2013 This addendum provides answers to written
More informationJacksonville Aviation Authority (JAA)
Oracle Training isupplier for End Users Jacksonville Aviation Authority (JAA) Page i Table of Contents Introduction... 1 Objectives... 3 Topic 1: isupplier Portal and Home Page Review... 4 Topic 2: isupplier
More informationFSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT
FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT FSC36 Safe Feed/Safe Food (www.safefeedsafefood.org) is a facility certification program for the American Feed Industry Association (www.afia.org) Version 7.0
More informationTASK MANAGEMENT TOOL. A Task in Itself. How To Not Drop The Ball October 10, 2017 Footer Text. Date
TASK MANAGEMENT TOOL A Task in Itself How To Not Drop The Ball October 10, 2017 Footer Text Task Management: A task in itself Thanks to: Danny Magee, P.E. Director of Transportation Operations Laredo District
More informationHow to Hire a Consultant
There are three reasons to hire a consultant: 1. You don t have the time 2. You don t have the expertise 3. You need a neutral or external perspective How to Hire a Consultant OPG s long-term relationships
More informationREQUEST FOR PROPOSALS EXECUTIVE SEARCH SERVICES. Issuance Date November 27, 2017
REQUEST FOR PROPOSALS EXECUTIVE SEARCH SERVICES Issuance Date November 27, 2017 Submittal Deadline January 8, 2018 Page Is Blank For Photocopying MARIN LAFCO 2 TABLE OF CONTENTS Section Page Number I.
More informationSECTION CONTRACTOR QUALITY CONTROL
SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationForsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101
Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS
More informationCampus User Guide Accounts Receivable Report
Functional Area Accounting: Extramural Funds Related System Agency Billing System Collections Are a Team Effort Campus User Guide Accounts Receivable Document Authors & Contributors: Pauline M. Librenjak
More informationFederal Contracts Billing and Reporting. Facilitators: Lisa Tate, Kim Jennings
Federal Contracts Billing and Reporting Facilitators: Lisa Tate, Kim Jennings Agenda Introductions & Ground Rules Retained Learning & Pre-Class Test Group Objectives/Expectations Class Objectives Overview
More informationDesign and Construction: CIP Project Management Review. Hampton Roads Sanitation District
Design and Construction: CIP Project Management Review Hampton Roads Sanitation District May 11, 2016 Table of Contents I. Executive Summary... 2 Background... 2 Objectives... 3 Scope... 4 Methodology
More informationConstruction Software Suite
Job cost control or budget tracking is a key aspect to project management and is one of the main reasons engineering and construction firms choose Corecon. Many of these firms are satisfied with their
More informationFinance Month End. Deltek Maconomy Deltek, Inc. Deltek proprietary, all rights reserved.
Finance Month End Deltek Maconomy Copyright Information While Deltek has attempted to make the information in this document accurate and complete, some typographical or technical errors may exist. Deltek,
More informationClarity Accounts Payable Year-end Procedure Guide 2017
Clarity Accounts Payable Year-end Procedure Guide 2017 Clarity Accounts Payable Year-end Procedure Guide - 2017 Table of Contents Caselle Clarity Accounts Payable Year-end Checklist 2017... 1 Welcome back!...
More informationChapter 2 Selection Process Procedures
Chapter 2 Selection Process Procedures 2.1 Introduction The Selection Process discussed in this chapter begins with identifying the need for a consultant and continues to the Notice to Proceed for the
More informationENGINEERING AND CONSTRUCTION BULLETIN
ENGINEERING AND CONSTRUCTION BULLETIN No. 2010-26 Issuing Office: CECW-CE Issued: 24 Nov 2010 Expires: 30 Mar 2011 Subject: Emerging professionals called to apply for opportunity to work on the 2030 USACE
More informationEXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No
EXHIBIT A TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No. 429768-4-12-01 This Exhibit forms an integral part of the Agreement between the DEPARTMENT and, the CONSULTANT,
More informationRequest for Proposal For: 2018 American Bar Association Temporary Services
Table of Contents Bid Timetable [2] 1.0 General Bid Information [3] 2.0 Proposal Requirements [5] 3.0 Criteria for Selection [7] 4.0 Specifications and Work Statement [7] Appendix A: Bidder Response Sheet
More informationOracle Hospitality Reporting and Analytics Advanced
Oracle Hospitality Reporting and Analytics Advanced User Guide Release 8.5.0 E65823-01 September 2015 Oracle Hospitality Reporting and Analytics Advanced User Guide, Release 8.5.0 E65823-01 Copyright 2000,
More informationCreating a Subaward or Subcontract Requisition in BruinBuy
Creating a Subaward or Subcontract Requisition in BruinBuy Outgoing Subaward and Subcontract Initiation and Management This section teach you how to submit a subaward or subcontract requisition using the
More informationSALES 1 PREPARATION 2 CONTACT MANAGEMENT. Use the Marketing Guide to help determine if & how any kind of business will use temps.
SALES 1 PREPARATION 2 CONTACT MANAGEMENT Use the Marketing Guide to help determine if & how any kind of business will use temps. Items to include: As a sales rep, you will learn that it is wise to always
More informationREQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE
REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE General Provisions Western Municipal Water District (WMWD) requests a qualified Design Consultant
More informationINSTRUCTIONS FOR COMPLETING SCHEDULE OF PRICES, ESTIMATE FOR VOUCHER, RETENTIONS SUMMARY, AND CONTRACTOR'S INVOICE
INSTRUCTIONS FOR COMPLETING SCHEDULE OF PRICES, ESTIMATE FOR VOUCHER, RETENTIONS SUMMARY, AND CONTRACTOR'S INVOICE 1. Print out these instructions first, then follow them in completing the worksheets.
More informationGIVE THEM WHAT THEY WANT!
GIVE THEM WHAT THEY WANT! Know the evaluation process and criteria to prepare a winning research proposal Paul JAMET Ministry of Research and New Technologies French NCP co-ordinator ordinator - NEST NCP
More informationReport Basics. How do I navigate to the report? Where do I go for additional help? refreshed with data? Nightly
Report Basics What is the purpose of this report? The Payables Detail report provides voucher line and distribution line level information for vouchers throughout the processing cycle. The report displays
More informationOracle ERP Cloud Period Close Procedures
Oracle ERP Cloud Period Close Procedures Release 13 O R A C L E W H I T E P A P E R A U G U S T 2 0 1 7 Table of Contents Introduction 8 Chapter 1 Period Close Dependencies 9 Chapter 2 Subledger Accounting
More informationAdministration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
More informationINTERNSHIP STARTER HANDBOOK For Community Providers
OFFICE OF INTERNSHIPS INTERNSHIP STARTER HANDBOOK For Community Providers Thank you for your interest in partnering with California State University San Marcos to provide internship opportunities to CSUSM
More informationTips and Tools for Writing a District LCAP
Tips and Tools for Writing a District LCAP Objectives & Outcomes Provide ideas for how to take an inventory of the district s current goals, priorities, and funding Discuss strategies for aligning current
More informationARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES
ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)
More informationStrategic Thinking, Analysis and Planning
An Intensive 5 Day Training Course Strategic Thinking, Analysis and Planning Mapping-out Your Best Possible Direction 09-13 Apr 2017, Dubai 16-20 Oct 2017, London 08-12 Apr 2018, Dubai 06-JUN-17 This course
More informationEL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017
EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS 21-17 June 27, 2017 TO: RE: Invited Firms Request for Submittals to El Paso Water - Public Service Board (EPWater) Statement of Work Professional
More informationAgricultural Projects
Development and Management of Agricultural Projects Introduction Communicate Product Quality and Risk Developing a Project Ten (10) Steps To Creating a Project Plan March 11 th 2017 Facilitated by Arnold
More informationRESIDENT ENGINEER S MANUAL
Peninsula Corridor Joint Powers Board 1250 San Carlos Avenue San Carlos, California 94070-1306 RESIDENT ENGINEER S MANUAL Revision 2 Page 1 of 336 Caltrain Standard Manual RESIDENT ENGINEER S MANUAL Manual
More informationP6 Instructors Sample Presentation
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation
More informationUS Army Corps of Engineers
I I I ' A I US Army Corps of Engineers LA River Ecosystem Restoration, CA Preconstruction Engineering and Design Phase 104791 LOS ANGELES DISTRICT SOUTH PACIFIC DIVISION August 15, 2017 1 Table of Contents
More informationTask Order Authorization
Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement
More informationContract and Grant Monitoring: Steps for Success Florida Department of Financial Services
Contract and Grant : Steps for Success Florida Department of Financial Services Bureau of Auditing Department of Financial Services Bureau of Auditing 2 Department of Financial Services Bureau of Auditing
More informationBecoming an ODFI Implementation Toolkit
Becoming an ODFI Implementation Toolkit Price: $400 Member Discounted Price: $200 (Publication #566) Sharing Our Passion For Payments WesPay Publications WesPay (Western Payments Alliance) has a long tradition
More informationInstructions & Guidelines for the Contractor s Performance Evaluation
Instructions & Guidelines for the Contractor s Performance Evaluation POLICY STATEMENT: The Kentucky Transportation Cabinet requires that a Contractor s Performance Report form (TC 14 19) be completed
More informationWelcome Baby Impact Evaluation Request for Proposals FREQUENTLY ASKED QUESTIONS. Information Webinar
Last Updated: December 18, 2015 Welcome Baby Impact Evaluation Request for Proposals FREQUENTLY ASKED QUESTIONS Information Webinar Please note that some responses may have been refined to more clearly
More informationSUBRECIPIENT MONITORING GUIDE
SUBRECIPIENT MONITORING GUIDE Introduction The following Roles and Responsibilities Chart serves as a reference for University of Arizona Principal Investigators and designated department personnel (Business/Finance
More informationUNIVERSITY OF CALIFORNIA, SAN DIEGO
BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSOCIATE VICE CHANCELLOR CAPITAL PROGRAM MANAGEMENT TEL: (858) 534-2177 FAX: (858) 534-4363
More informationOPR, BOD, Systems Manual Expensive, Useless Encumbrances or Valuable, Cost Effective Tools It's Up to You
OPR, BOD, Systems Manual Expensive, Useless Encumbrances or Valuable, Cost Effective Tools It's Up to You Kent Barber, P.E., LEED AP Keithly Barber Associates Synopsis Three commissioning-related documents
More informationAttachment D: Cost Proposal, RFP Section 3.4
ATTACHMENT D: COST PROPOSAL, RFP SECTION 3.4 Instructions: Use this template to comply with Section 3.4, Cost Proposal. Because the requirements of this RFP are part of a portfolio of projects designed
More informationREQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES
REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES Pueblo Urban Renewal Authority (PURA) Pueblo Convention Center Expansion &
More informationNISQUALLY RED WIND CASINO REQUEST FOR QUALIFICATIONS / PROPOSAL FOR MASTER PLANNING SERVICES
NISQUALLY RED WIND CASINO REQUEST FOR QUALIFICATIONS / PROPOSAL FOR MASTER PLANNING SERVICES Proposal Due Date: February 7, 2018 at 1:00 PM PST RED WIND CASINO HOTEL DEVELOPMENT RFQ/P 1 January 23, 2018
More informationBest Practices in Procurement & Contract Management
Best Practices in Procurement & Contract Management Definition: Contract Administration The term is to describe the management functions that are performed after the contract has been signed to assure
More informationSIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013
SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report July 2013 TABLE OF CONTENTS Project Manager
More informationAddendum Number 1. August 31, Colcock Hall Windows. Owner Project Number: Prepared by:
Addendum Number 1 Colcock Hall Windows Owner Project Number: 50059 Prepared by: ADC Engineering, Inc. 1226 Yeamans Hall Road Hanahan, South Carolina 29410 To Bidders: This Addendum forms a part of the
More informationJetty and Revetment Repairs
BOARD OF COMMISSIONERS P.O. BOX 249 ٠ AVILA BEACH CALIFORNIA 93424 DAVE KIRK President (805) 595-5400 ٠ Fax 595-5404 MARY MATAKOVICH Vice President www.portsanluis.com DREW BRANDY Secretary BILL BARROW
More informationThe Master Task Success System. Developed by Mike Scott and Associates
The Master Task Success System Developed by Mike Scott and Associates Copyright 2012 Mike Scott and Associates. All rights reserved. Unauthorized reproduction, in any manner, is prohibited. Using Microsoft
More informationMONTH END CLOSING INSTRUCTIONS FOR ACTUALS LEDGER
MONTH END CLOSING INSTRUCTIONS FOR ACTUALS LEDGER Revised by Financial Operations 05/20/2009 Month End Closing Instructions for ACTUALS Ledger CONTENTS: OVERVIEW 3 HELP 5 DETERMINING IF A BUSINESS UNIT
More informationSTATE AID GUIDE FOR: Updated: December 16, 2005
STATE AID GUIDE FOR: Updated: December 16, 2005 1. AFTER THE FACT RIGHT OF WAY DEPARTMENT OF MINNESOTA TRANSPORTATION 2. MISCELLANEOUS AFTER THE FACT Traffic Signals, Lighting, Retaining Walls, Sidewalk,
More informationInvoicing Plan Enhancement in Purchase Order
Invoicing Plan Enhancement in Purchase Order Applies to: SAP ECC 6.0. For more information, visit the Enterprise Resource Planning homepage Summary This document helps the P2P consultants to understand
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
More informationThe Case for Outsourcing Accounts Payable
Presented by Lynn Belletti BNY Mellon Transaction Processing Director The & Procure-To-Pay Conference & Expo is produced by: The world is changing. How will you respond to the new pressures of regulatory
More informationEXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5
EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services... A-2 B. Architectural Programming... A-5 1. Project Initiation... A-5 C. Design Services... A-6 1. Schematic Design Phase...
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems January 2017 CON170, Unit 5 Lesson 1 Cost Analysis Process and Players
More informationSeller Portal Users Guide
Seller Portal Users Guide Contents Page 3 Overview 4 Seller Portal Access 5 Entering the Seller Portal 6 Main Tab: Underwriting Guidelines 7 Quote Tab: Contract Sale Process 13 Contract Tab: Existing Contracts
More information