1 Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79, This Task Order pertains to the On-Call Agreement by and between the ( City ) and ( Service Provider ), dated March 8, Task Order 6 is generally described as follows: This work shall consist of installing storm sewer Capital Improvement Projects 1, 2, 4, and 8 in addition to storm sewer improvements identified by City staff noted as Sites 5 & 6. See Exhibit A for project scope. The Service Provider shall perform the services on the project described below as provided herein and in the Agreement. This Task Order shall not be binding until it has been fully executed by both parties. Upon execution, this Task Order shall supplement the Agreement as it pertains to the project described above. See attached Exhibit A for project scope. This Task Order is executed this day of,. CITY OF CLYDE HILL By: Dated: Its: SERVICE PROVIDER By: Dated: Page 1
2 EXHIBIT A 2017 Small Drainage Program Scope, Hour and Fee Estimate March, 2017 Engineering Services, Preparation of Bid Documents & On-Call Construction Services PROJECT DESCRIPTION The Consultant shall prepare final Plans, Specifications and Estimates for the 2017 Small Drainage Program. The project will include the following sites: CIP # 1 (Site 1): th Ave NE Remove and replace approximately 80LF of existing 12 concrete pipe in drainage easement with new HDPE storm water pipe. Install in-line catch basin prior to storm water draining to 84 th Ave NE and connect to 84th Ave NE system. As necessary, replace existing asphalt pavement, concrete sidewalk and curb & gutter and restore private property to original conditions. CIP # 2 (Site 2): th Pl. NE Remove and replace approximately 150LF of existing 8 corrugated metal pipe in drainage easement. Easement must be cleared of large trees, and landscaping prior if installation of standard trenching construction methods is used. Install in-line catch basin prior to system draining to 84 th Ave NE system in order to improve maintenance and inspection of upstream pipe located within drainage easement. CIP # 4 (Site 3): 8805 Points Dr. NE Install new bar screen and inlet headwalls (if needed) on 30 CMP inlet located in a drainage easement, removal of sediment and loose debris, stabilization of existing slopes and rockery wall repair (if needed). HPA permit required. CIP # 8 (Site 4): 8420 NE 19 th Pl. Replace existing damaged (root intrusion) 6 pipe along property frontage within ROW with new 8-12 pipe and catch basins at connections/junction points. Private roof drains shall be reconnected to system. Restoration includes installing HMA pavement and driveway apron and landscaping. Coordinate with property developer at 8420 NE 19 th Pl as needed. CCTV (by city) downstream connection across 8408 NE 19 th Pl to verify free flow downstream of issue. Site 5: th Ave NE Remove one existing inlet structure and install new beehive grate intake structure and surrounding quarry spall pad within drainage easement. Site 6: 94 th Ave NE 2017 Small Drainage Program Page 1 of 6 March 22, 2017
3 Install new storm drainage system on 94 th Ave NE, extending south (upstream) from NE 24 th St. for approximately 650 feet. The storm drainage system will be designed to collect storm drainage discharges (both pumped and gravity) from adjacent private properties. The Consultant shall provide necessary surveying, project design, quantity and cost estimates, and utility coordination required to complete final bid documents. It is anticipated that sites will be bid as a single bid package for the 2017 Small Drainage Program as budget or other considerations allow. The Consultant shall provide surveyed base maps with horizontal utility locations, ortho-photography, and GIS data as necessary for each site. Surveyed base maps will include right-of-way line work based on ROW research. Project horizontal and vertical datum will be assumed on all sites. The Consultant shall provide assistance to the City with preparation of an HPA application required for Site 3. No additional permits are anticipated. It is the Consultants understanding that none of the 2017 Small Drainage Program sites require biological assessments, additional permits beyond those listed, wetland delineations, geotechnical review, detention facilities, or water quality treatment facilities. The budget assumes a straightforward approval process with no special studies or extensive coordination. All work will be completed within City rights of way or easements and no easement acquisition is anticipated. For the 2017 Small Drainage Program, the Consultant shall submit a 30% Review Submittal (plans and estimate only), and a 90% review Submittal that includes plans, specifications and estimate to the City for review prior to bidding. SCOPE OF WORK TASK Small Drainage Program Design 1.1 MANAGEMENT/COORDINATION/ADMINISTRATION The Consultant shall provide continuous project management and administration for the duration of the Project. (Estimate 8 months). The consultant shall meet the City at all project sites for one (1) project kickoff meeting. Hold project coordination meetings with the City to update progress and review submittals. Assume (2) meetings for the 30% and 90% reviews. The Consultant shall provide monthly status reports and billings. The Consultant shall provide independent QA/QC reviews by senior in-house staff of all deliverables prior to submittal to the City. o The City shall perform necessary property owner coordination and the Consultant shall assist on an as-requested basis Small Drainage Program Page 2 of 6 March 22, 2017
4 1.2 TOPOGRAPHIC SURVEY/UTILITY LOCATES/ROW PREPARATION The Consultant shall prepare base maps for each 2017 Small Drainage Program site. Topographic survey will be performed for all sites including horizontal utility locations within the right of way and easements. The consultant will utilize a private utility locating service to determine the location of utilities in the project corridor, including watermains, gas, and other underground utilities, and if possible, existing storm drain force main locations. The consultant shall conduct right of way calculations and establish right of way from assessor/gis/plat maps The consultant shall identify existing easements from existing city filed data and include in base maps. o Title reports will not be ordered. o Existing topography survey performed for the City of Bellevue s 2011 AC Water Main Replacement, Phase 1 project will be utilized to the extent possible in creating the basemap. Deliverables o CAD file and PDF of basemap 1.3 ALTERNATIVE ANALYSIS The consultant shall review all available site data including CCTV, drainage easements, site conditions and perform an alternative analysis for: o CIP # 1 (Site 1): th Ave NE Alternative 1: Trenchless pipe method Alternative 2: Complete pipe replacement via standard trenching methods. o CIP # 2 (Site 2): th Pl NE Alternative 1: Trenchless pipe method Alternative 2: In-Line catch basin installation only. o The City shall order any CCTV inspections needed for site review. 1.4 PREPARE 30% PLANS & ESTIMATE The Consultant shall prepare final Plans for the proposed improvements including the following: o Plans shall be prepared with such provisions in such detail as to permit field layout and construction within a degree of accuracy acceptable to the City and per industry standards Small Drainage Program Page 3 of 6 March 22, 2017
5 o o o o o It is assumed there will be eighteen (18) plan sheets at 1 =20 scale full size (22 X 34 ), 1 =40 at reduced scale (11 X 17 ). Details will be prepared for items not available as standard details from the City, State, or WSDOT standard drawings. The plans shall illustrate complete details of construction of the proposed improvements including limits of construction and removals, proposed invert elevations, rim elevations and required construction materials. Plans shall also illustrate site restoration as necessary including roadway and private property restoration to generally meet the conditions that existed prior to construction. Drainage designs will be determined through alternative analysis (where identified) consultation with City staff and from previous experience rather than detailed basin modeling. Calculate quantities and prepare Engineers Estimate of Probable Construction Cost. o For 94 th Ave NE The proposed storm drain is not intended to collect street runoff; therefore the pipe alignment and catch basin locations will be designed to connect private drainage systems while minimizing impacts to other utilities. The proposed storm drain will be 12 diameter and will not require conveyance capacity calculations to be performed. o The plan set will include the following sheets: Cover sheet (1) Index/Abbreviation plan sheet (1) Site preparation/tesc plan sheet (4) Storm drainage plan/profile sheets/site restoration (8) Detail sheet(s) (4) 1.5 UTILITY COORDINATION The consultant shall prepare a potholing plan and the city shall order potholes if needed. The Consultant shall distribute the 60% plans to franchise utility owners to identify potential conflicts within the Project limits. o It will be determined if potholing is necessary after the 30% design submittal is complete. o No utility upgrades are planned for in the project design SMALL DRAINAGE PROGRAM FINAL DESIGN The Consultant shall conduct QA/QC and constructability reviews in the field for each site and consult with City staff during the field reviews. The Consultant shall calculate quantities and prepare Engineers Estimate of Probable Construction Cost for the 90% submittal and Bid Documents Small Drainage Program Page 4 of 6 March 22, 2017
6 The Consultant shall prepare the Contract Specification per 2016 WSDOT Standard Specifications for the 90% submittal and Bid Documents. The Consultant shall assist the City with Project Advertisement and Award. o No federal funding is anticipated for the Project engineering or construction. o Drainage & Water Quality Reports will not be required. o Geotechnical Engineering services will not be required. o Environmental Documentation will not be required with exception of SEPA Checklist. SEPA Checklist shall be prepared by the city to support the HPA permit. Deliverables o 30% review submittal with Plans and Estimate o 90% review submittal with Plans, Specifications, and Estimate. o Bid Documents and Engineer s Estimate o 3 sets of Plans (11 X 17 ) and specifications provided for each review submittal. o 5 sets of Plans (11 X 17 ) and specifications for the Bid Documents. o 1 sets of Plans (22 X 34 ) for the Bid Documents. o Coordinate upload of Plans and Specifications to Builders Exchange and posting of advertisement to a local newspaper. TASK Small Drainage Program Permitting 2.1 The Consultant shall meet in the field with a representative from Washington Department of Fish & Wildlife and prepare a JARPA for HPA approval on Site 3. o No wetland or stream delineations will be required. o No special studies (biological assessments, etc.) will be required. o The $150 processing fee for the JARPA application will be paid by the Consultant and reimbursed by the City through the invoice process. Deliverables o JARPA Application TASK 3 Construction Services 3.1 Construction management, inspection and materials testing will be provided by the City. An allowance is included in the budget for on-call construction support provided by the Consultant as requested by the City. These services may include preconstruction conference, construction inspection and engineering, submittal reviews, and/or record drawings within the budget allowances included in Exhibit B Small Drainage Program Page 5 of 6 March 22, 2017
7 Additional Services The may require other services of the consultant. These services could include additional design, right of way, utility potholing, environmental documentation, property owner coordination. Additional construction services or other work tasks not included in the scope of work. At the time these services are required, the Consultant will provide the City with a detailed scope of work and an hour and fee estimate. The Consultant will not proceed with the work until the City has authorized the work and issued a Notice to Proceed Small Drainage Program Page 6 of 6 March 22, 2017
8 HOUR AND FEE ESTIMATE EXHIBIT B Project: On Call Task Order Small Drainage Program March 22, 2017 Labor Hour Estimate Total Fee Principal Project Project Design CAD Const Survey Senior Office Task Description Engineer Manager Engineer Engineer Technician Inspector Crew Admin Admin $ $ $ $ $ $ $ $ $ Fee Task Small Drainage Program Design 1.1 Management, administration & QA/QC Reviews $ 4, Topographic Survey/Basemapping/ROW Establishment Topographic Survey - CIP # 1,2,4,8, Site 5 & Site $ 8, Base Map Creation - CIP # 1,2,4,8, Site 5 & Site 6 56 $ 5, ROW Establishing $ 3, Alternative Analysis CIP #1 (Site 1) th Ave NE $ 1, CIP #2 (Site 2) th Pl. NE $ 1, Prepare Plans CIP #1 (Site 1) th Ave NE $ 3, CIP #2 (Site 2) th Pl. NE $ 3, CIP #4 (Site 3) 8805 Points Dr. NE $ 4, CIP #8 (Site 4) 8420 NE 19th Pl $ 3, (Site 5) th Ave NE $ 1, (Site 6) 94th Ave NE $ 4, Utility Coordination $ - CIP # 1,2,4,8, Site 5 & Site $ 1, Final Design Field Reviews - CIP # 1,2,4,8, Site 5 & Site $ 1, Quantity and Cost Estimating - CIP # 1,2,4,8, Site 5 & Site $ 7, Prepare Specifications - CIP # 1,2,4,8, Site 5 & Site $ 7, Finalize Bid Documents - CIP # 1,2,4,8, Site 5 & Site $ 3, Reimbursable expenses - see breakdown for details $ 4, Task Totals $ 71, Task Small Drainage Permitting 2.1 HPA Permitting - Site $ 1, Reimbursable expenses - see breakdown for details $ Task Totals $ 1, Task 3 - Construction Services 3.1 Construction Services CIP # 1,2,4,8, Site 5 & Site $ 6, Reimbursable expenses - see breakdown for details $ Task Totals $ 6, Total hours by Classification Project Total: $ 79, /5/2017
9 HOUR AND FEE ESTIMATE EXHIBIT B Project: On Call Task Order Small Drainage Program March 22, 2017 Reimbursable Breakdown Cost Task Small Drainage Program Design Mileage - CIP #1,2,4,8, Site 5 & Site 6 $ Utility Locates - CIP #1,2,4,8, Site 5 & Site 6 $ 4, Reproduction $ Task 1 - Total $ 4, Task Small Drainage Permitting Mileage $ JARPA Application $ Reproduction $ Task 2 - Total $ Task 3 - Construction Services Mileage $ Reproduction $ Task 3 - Total $ Total Reimbursable Costs: $ 5, /5/2017
GRADING, EROSION AND SEDIMENTATION CONTROL
SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,
More informationCONSTRUCTION PLAN CHECKLIST
CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted
More informationCITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT
CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards
More informationDate: June 2, CONTRACT for Engineering Services Kortsen Relief Sewer Design Concept Report. Dear Mr. McKeon,
Date: June 2, 2016 To: Subject: Terrence S. McKeon, P.E. City of Casa Grande 3181 N. Lear Avenue Casa Grande, AZ 85122 Phone: 520-421-8625 x3341 Email: tmckeon@ci.casa-grande.az.us CONTRACT for Engineering
More informationCHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN
CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth
More informationPLANNING AND ZONING COMMISSION APPLICATION FOR IMPROVEMENT PLAT APPROVAL
PLANNING AND ZONING COMMISSION APPLICATION FOR IMPROVEMENT PLAT APPROVAL Date Submitted: Project Number: CITY OF ALEXANDRIA 8236 WEST MAIN STREET ALEXANDRIA, KY 41001 (859) 635-4125 FAX (859) 635-4127
More informationStorm. Section. B. General Design and Drawing Standards Design
Section Storm 5 General Plans for the existing stormwater system are maintained in digital and printed form by the City. Copies may be obtained from the Utility Division of the Public Works Department.
More informationStormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)
Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater
More informationPRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS
PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS 39 AUGUST 2005 TABLE OF CONTENTS PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS PAGE SECTION 1 DESIGN CRITERIA 41 SECTION 2 SUBMITTAL 44 SECTION 3 STRUCTURES
More informationItems in this checklist identify the base requirements that are to be provided by the design professional.
The Project Manager or other Owner designee will serve as the Plan Reviewer. This checklist is to be completed by the Plan Reviewer on behalf of the Owner. The Plan Reviewer s role is to review the submitted
More information6 STORMWATER IMPROVEMENTS
6 STORMWATER IMPROVEMENTS 6.01 General Requirements a. In addition to the standards contained in this, the design of stormwater systems is also governed by several ordinances and regulations. (1) Projects
More information6 STORMWATER IMPROVEMENTS
6 STORMWATER IMPROVEMENTS 6.01 General Requirements a. In addition to the standards contained in this, the design of stormwater systems is also governed by several ordinances and regulations. (1) Projects
More informationStep 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required.
Overview of Section 9 9.0 The GESC Permit Section provides a description of the Small Utility GESC Permit Program. Step 1. Determine if a GESC Permit is Applicable and if a Project Specific GESC Plan is
More informationAPPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
More informationDOCUMENT ADDENDA AND MODIFICATIONS
DOCUMENT ADDENDA AND MODIFICATIONS PART 1 1.1 PROCEDURE GENERAL A. For filing purposes, add Addenda and Modifications to the Contract Documents following this page. Modified June 20, 2017 Addenda and Modifications
More informationTOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements
TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves
More informationChapter 3: Permit Procedures and Requirements
Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8
More informationCITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413
Page: 1 of 5 CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413 COMMERCIAL/RESIDENTIAL UTILITY PLAN COMPLETENESS CHECK LIST Updated
More informationCITY OF LAKE FOREST PARK BUILDING CHECKLIST FOR NEW CONSTRUCTION, ADDITION, AND REMODEL BUILDING PERMIT
CITY OF LAKE FOREST PARK BUILDING CHECKLIST FOR NEW CONSTRUCTION, ADDITION, AND REMODEL BUILDING PERMIT The following checklist identifies the minimum requirements for acceptance of an application for
More informationMODEL Stormwater Local Design Manual. City of Centerville
MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge
More informationProject Need and Evaluation
City of Brooklyn Center 2011 Palmer Lake East Street and Utility Reconstruction Project Public Hearings February 14, 2011 Public Improvement Hearing: Special Assessments Local public improvements to the
More informationSUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required.
SUBDIVISION CHECKLIST Subdivision Name Account Number Review Engineer Prior To Review Preliminary plan approved by Planning Commission / Council as required. Review fee paid. Statement of Responsibility
More informationGCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887
GCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887 Phone: (978) 657-9714 Fax: (978) 657-7915 November 17, 2017 Ms. Sheila Page, Town Planner 101 Main
More informationMiddle Tennessee State University (MTSU) Stormwater Plan Review Checklist
For Middle Tennessee State University (MTSU) projects, the Project Manager or other MTSU designee will serve as the Plan Reviewer. This checklist is to be completed by the Plan Reviewer on behalf of MTSU.
More informationSECTION 2 DESIGN CRITERIA
SECTION 2 DESIGN CRITERIA 2.1 GENERAL The following criteria will be utilized by the District Engineer, and/or a consultant, in the review of development plans for recommending approval of the proposed
More informationCHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
More informationAPPLICATION FOR RIGHT OF WAY PERMIT
City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER
More informationCity of Elgin SUBDIVISION FINAL ENGINEERING Engineering Submittal Checklist
If this is a re-submittal, please provide a point-by-point response to previous review comments, identifying how each comment has been addressed, location in the plan set of the changes made to address
More informationAgenda Item B.9 CONSENT CALENDAR Meeting Date: May 19, 2015
CPMS Agenda Item B.9 CONSENT CALENDAR Meeting Date: May 19, 2015 TO: FROM: Mayor and Councilmembers Rosemarie Gaglione, Public Works Director CONTACT: James Winslow, Sr. Project Manager SUBJECT: Amendment
More informationStormwater Local Design Manual For Houston County, Georgia
Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.
More informationWarner Robins Stormwater Local Design Manual
Warner Robins Stormwater Local Design Manual Prepared for Houston County City of Warner Robins City of Perry City of Centerville May 17, 2005 Version 4 (As presented with adopted Stormwater Ordinance)
More informationGeneral Rules and Regulations
General Rules and Regulations City of Hamilton, Ohio Sanitary Sewer Collection and Treatment Revised December 23, 2016 Page 1 of 13 To Our Customers, Sanitary Sewer Collection and Treatment Department
More informationSECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS
SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS 12.1 The subdivider shall construct and install the improvements in accordance with the County's Standards for Construction Plans and Specifications
More informationTOWN of LAKESHORE SUBDIVISION DEVELOPMENT PLAN CHECKLIST
Project Name: Project Location: Date Submitted: TOWN of LAKESHORE SUBDIVISION DEVELOPMENT PLAN CHECKLIST Last Revised January 31, 2014 Name Phone Number E-mail Address Owner: Contractor/ Engineer: ( )
More informationSubmittal Requirements. Post Construction Verification Document Plan Requirements
Submittal Requirements Post Construction Verification Document survey plan in accordance with the items of this Checklist Supporting calculations in accordance with the items of this Checklist A copy of
More informationFDOT REF. ITEM DESCRIPTION
EXHIBIT B NAPLES BASIN V Stormwater Improvements BID TABULATION SUMMARY OF PAY ITEMS FDOT REF. ITEM DESCRIPTION Est. Quant. Cost 0 Mobilization LS 02 2 Maintenance of Traffic LS 3 Preconstruction Audio/Video
More informationAppendix J: Storm Conveyance Design Parameters
Appendix J: Storm Conveyance Design Parameters Drain Commissioner 39 February 2005 STORM DRAINAGE DESIGN CRITERIA A. STORM SEWERS 1. The required discharge capacity shall be determined by the Rational
More information7.00 INTRODUCTION... 1
SITE PLANS, REZONING, LAND DIVISION AND CONDOMINIUM SECTION 7 GENERAL REQUIREMENTS INDEX Page 7.00 INTRODUCTION... 1 7.01 SITE GRADING AND MECHANICAL PLANS... 2 7.01.01 Submission Procedures... 2 7.01.02
More informationENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)
EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY
More informationDawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228
Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:
More informationThe City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater.
Background The City of rth Las Vegas strives to provide the development community with adequate information to ensure the successful completion of any project in the City. To aid in the submittal of a
More informationTABLE OF CONTENTS SECTION 700 STORM DRAINAGE STANDARDS...
TABLE OF CONTENTS SECTION 700 STORM DRAINAGE STANDARDS... 700-1 701 GENERAL... 700-1 702 GENERAL REQUIREMENTS... 700-1 703 GENERAL DESIGN STANDARDS... 700-2 704 POND DESIGN STANDARDS... 700-2 705 EROSION
More informationPART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS
PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm
More informationCITY OF MERIDIAN LAND DEVELOPMENT SERVICES SUBDIVISION PLAN REVIEW CHECK LIST
Project Name: Hearing Date: Reviewer: Date of Review: # OK NEED N/A General Plan Design All documents, design standards, specifications, and forms should be taken from the website each time they are used
More informationENGINEERING REVIEW CHECKLIST City of Mount Clemens
(To be completed by the Developer s & Submitted with ing Plans) DATE: PROJECT NAME: Site Plan Approved: Date DESIGN ENGINEERING COMPANY: ing Company Contact Information: Name: Phone: Email: Owner Contact
More informationReplace BID SCHEDULE with attached revised BID SCHEDULE.
CONTRACT ADDENDUM Project: 9 st Ave SE & 4 th Street SE Sidewalk Improvements Project No: 00 Addendum No: Date: 0 September 0 Addendum: Replace BID SCHEDULE with attached revised BID SCHEDULE. Section
More informationPROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM
PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM Project ID Number: 2- Problem: Storm runoff from the park flows overland through a gap in a berm and then into the neighboring subdivision
More informationSECTION GENERAL EXCAVATION
02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,
More informationSECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationPUBLIC WORKS SKAGIT COUNTY SAMISH ISLAND ROAD SAMISH ISLAND ROAD SLIDE REPAIR
EASEMENT NOTES:. EASEMENT LIMIT SHOWN AS PROVIDED BY. TESC NOTES:. CONTRACTOR SHALL DEVELOP TEMPORARY EROSION AND SEDIMENT CONTROL PLAN AND PROVIDE ONSITE CERTIFIED EROSION AND SEDIMENT CONTROL LEAD (CESCL)
More informationEXHIBIT A FEE SCHEDULE
EXHIBIT A FEE SCHEDULE PERMIT FEE WORKSHEET INSTRUCTIONS: Each application for a new permit or change in status shall be accompanied by the appropriate fee as indicated below. NO PERMIT APPLICATION WILL
More informationCITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE:
CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST "THE FOLLOWING CHECKLIST IS ONLY A SUMMARY THAT IS PROVIDED FOR THE APPLICANT'S BENEFIT; HOWEVER, FULFILLING THE REQUIREMENTS OF THIS SUMMARY
More informationCity of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development
City of Redwood City Stormwater Pollution Prevention Program Drainage Guidelines for Residential Development General Requirements A. Plot & Finished Grading Plan must be submitted with Building Permit
More informationAPPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT
APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:
More informationSTORM DRAINAGE DESIGN MANUAL
Appendix I STORM DRAINAGE DESIGN MANUAL by: SUNGATE DESIGN GROUP, P.A. GEN ERAL DESIGN STAN DARDS AN D POLICIES 1. STREET AND LOCAL DRAINAGE Discharge estimates for specified design storms shall be calculated
More informationPUBLIC NOTICE PROFESSIONAL ENGINEERING SERIVCES: DESIGN OF TURF FIELD
PUBLIC NOTICE The Township of Union has adopted the Fair and Open Process of the Pay-to-Play Law (N.J.S.A. 19:44A-20a, et seq.) in its request for proposals and awarding goods and services contracts with
More informationCUSTOM HOMES, ADDITIONS TAYLOR BUILDING & COMMERCIAL DESIGNS 63 KENSINGTON ROAD, SAN ANSELMO, CALIFORNIA SPIRIT LIVING GROUP APN
SPIRIT LIVING GROUP 63 KENSINGTON ROAD, SAN ANSELMO, CALIFORNIA 100 HELENS LANE MILL VALLEY, CA 94941 415 388 9585 F 415 388 0412 CPD ENGINEERS / SURVEYORS / PLANNERS 1646 N CALIFORNIA BLVD SUITE 400 WALNUT
More information401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:
SECTION 400 SANITARY SEWER SYSTEM The design of sanitary sewers shall be in conformance with the applicable sections of the State of Washington, Department of Ecology manual, Criteria for Sewage Works
More informationGood Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions
September 18, 2018 Good Housekeeping Phones Weather related emergencies Breaks and facilities Introductions Goals and Objectives 1. Plan Review Process 2. Land Disturbance Permitting 3. Erosion and Sediment
More informationZONING ORDINANCE FOR THE ZONED UNINCORPORATED AREAS ARTICLE 1500 OF PUTNAM COUNTY, WEST VIRGINIA Page 149 ARTICLE 1500 DRAINAGE AND STORM SEWERS
OF PUTNAM COUNTY, WEST VIRGINIA Page 149 ARTICLE 1500 DRAINAGE AND STORM SEWERS 1500.01 GENERAL REQUIREMENTS 1500.02 NATURE OF STORM WATER FACILITIES 1500.03 DRAINAGE EASEMENTS 1500.04 STORM WATER MANAGEMENT
More informationSECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements
SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature
More information12 DRAINAGE General Administrative Requirements Standards
12 DRAINAGE 12.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with drainage, including culverts, bridge hydraulics, roadway ditches, and closed storm
More informationENGINEERING DESIGN STANDARDS
CITY OF SOUTHFIELD DEPARTMENT OF PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS APPROVED BY: Gary M. Mekjian, P.E. City of Southfield Director of Public Works Dated: Oct. 1, 2007 Revised:
More informationRequest for Proposal Design Engineering Services City of Glendale 2019 Road Projects August 2018
Request for Proposal Design Engineering Services City of Glendale 2019 Road Projects August 2018 The City of Glendale, Wisconsin is requesting engineering proposals from qualified consultants for the design
More informationAppendix B Construction SWPPP Short Form
Appendix B Construction SWPPP Short Form Projects falling within the thresholds listed below may use this short form instead of preparing a formal Construction Stormwater Pollution Prevention Plan (SWPPP).
More informationBuilding Project Guide
Building Project Guide Permit Submittal Procedure and Requirements This guide is intended to help homeowners and their agents understand what needs to be included in a permit submittal package. For more
More informationAMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE
AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE This Amendment D to the Contract for Independent Contractor between the City of Fernley and NCE is entered
More informationT a b l e o f C o n t e n t s
C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General
More informationPART V - STORM DRAIN DESIGN CRITERIA
PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement
More informationPART V - STORM DRAIN DESIGN CRITERIA
PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement
More informationB-PERMIT PLAN CHECK MANUAL
B-PERMIT PLAN CHECK MANUAL 8. EROSION CONTROL PLANS All B-Permit and Department of Building and Safety (B&S) Grading Permit plans must have an approved Wet Weather Erosion Control Plan (WWECP) i by September
More informationTOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK
TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,
More informationHighway / Utility Guide
Oregon Department of Transportation Highway Division Right of Way Section Highway / Utility Guide Railroad & Utilities Unit Right of Way Section STATEMENT OF PURPOSE It is important to understand that
More informationSECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1
CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1
More informationA.1 WATER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS
PC Plan Submittal and Review A.1 WATER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for water main extensions, improvements and modifications shall be submitted to the District manager.
More informationRichland County Department of Public Works Engineering (Land Development) Division
Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or
More informationPRELIMINARY ENGINEERING
Source: LAND DEVELOPMENT HANDBOOK PART IV.B REFINEMENT OF PREVIOUS ASSUMPTIONS C HAPTER 16 David A. Jordan, P.E. INTRODUCTION Preliminary engineering is an integral component of the third step in the land
More informationTxDOT Houston District Permit Requirements (Information contained herein is subject to change)
Houston District Permit Requirements (Information contained herein is subject to change) Access Driveway for Commercial / Industrial Developments; or Street Tie-In / Drainage-Only 1) Complete the three
More informationIndex. Composition and Order of Plan Set. Utility Plan... 5
City of Des Plaines Public Works and Engineering Department Revised-October 5, 2012 Index Composition and Order of Plan Set Title Page Number Cover Sheet... 1 Requirements for Site Development... 2 Grading
More information4.8. Subsurface Infiltration
4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration
More informationYES, we received Addendum No. 1
TRANSMITTAL SHEET Date sent: Friday, April 6, 2018 Sent to: All Planholders Deliver to: Project Estimator Transmission sent from: Reichhardt & Ebe Engineering Number of pages including this page: 36 CONFIRMATION
More informationLOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007:
LOT GRADING DEFINITION Lot grading is the reshaping or sloping of the land in such a way that surface drainage from rain runoff is directed away from the buildings and is controlled in a manner that eliminates
More informationStormwater Infrastructure Funding Study Public Education Session May 27, :00 9:00 pm City Hall, Multi-Purpose Room Level 100
Stormwater Infrastructure Funding Study Public Education Session May 27, 2015 7:00 9:00 pm City Hall, Multi-Purpose Room Level 100 What is the Stormwater Infrastructure funding study? Purpose of the Stormwater
More informationStormwater line will be ABOVE ground corrugated pipe (No need to bury) running down to basin on NW 99 th St. It is simple and approved.
Stormwater Drainage: Stormwater line will be ABOVE ground corrugated pipe (No need to bury) running down to basin on NW 99 th St. It is simple and approved. Please see pages 11 and 12 of the document below
More informationCITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390
CITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390 ENGINEERING DESIGN STANDARDS Prepared by: Boss Engineering Howell, Michigan October 5, 2016 TABLE OF CONTENTS PART I. INTRODUCTION SECTION 1.0
More informationDEVELOPMENT SERVICES BUILDING COMMUNITY RISK REDUCTION ENGINEERING PLANNING PERMIT SERVICES TRANSPORTATION
DEVELOPMENT SERVICES BUILDING COMMUNITY RISK REDUCTION ENGINEERING PLANNING PERMIT SERVICES TRANSPORTATION Submit this completed form at City Hall, or use www.mybuildingpermit.com to submit your application
More informationOrdinance No Lot Surface Drainage
Ordinance No. 35-2008 - Lot Surface Drainage The Township has adopted a new Lot Surface Drainage Ordinance which amends Chapter 170, Article IX, Subdivision and Site Plan Review by adding a new Section
More information4.4.6 Underground Detention
4.4.6 Underground Detention Limited Application Water Quality BMP Description: Detention storage located in underground pipe systems or vaults designed to provide water quantity control through detention
More informationDIVISION 5 STORM DRAINAGE CRITERIA
DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the
More informationCUYAHOGA COUNTY ENGINEER
CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 May 28, 2010 Revisions to the July 29, 2009 edition are noted
More informationSTATE UNIVERSITY CONSTRUCTION FUND
DIRECTIVE 2-1 Issue date: September 2012 1. General SITEWORK OVERVIEW This Directive outlines the Fund s requirements for the Consultant relative to the development, design and presentation of documents
More informationVILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS
VILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS For general information concerning submittal requirements, please refer to Village Code 7-9-4 (c.).
More informationMetropolitan St. Louis Sewer District Statement of Policy for Maintenance of Stormwater Sewer Systems
Metropolitan St. Louis Sewer District Statement of Policy for Maintenance of Stormwater Sewer Systems 1.0 Introduction Adequate drainage in the Metropolitan St. Louis area is necessary to preserve and
More informationADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows:
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION 00 91 11.02 ADDENDUM NUMBER TWO June 22, 2016 TO: PLANHOLDERS SUBJECT: PCT TRUCK STAGING PROJECT PROJECT NO. 091606 CONTRACT NO. 070287 This
More informationCITY OF FARMINGTON HILLS DEPARTMENT OF PUBLIC SERVICES ENGINEERING DIVISION. ENGINEERING DESIGN STANDARDS For Site Development and Redevelopment
CITY OF FARMINGTON HILLS DEPARTMENT OF PUBLIC SERVICES ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS For Site Development and Redevelopment ADOPTED BY: City of Farmington Hills City Council July 11,
More informationREQUEST FOR PROPOSALS For Engineering Design Services Street Reconstruction at Various Locations CITY OF SAN MATEO, CALIFORNIA
REQUEST FOR PROPOSALS For Engineering Design Services Street Reconstruction at Various Locations CITY OF SAN MATEO, CALIFORNIA The City of San Mateo hereby requests proposals for engineering design services
More informationBuilding Permit Submittal Requirements
CITY OF MONTE SERENO 18041 Saratoga-Los Gatos Road Monte Sereno, CA 95030 Phone (408) 354-7635 Fax (408) 395-7653 www.cityofmontesereno.org Building Permit Submittal Requirements NOTE: Submit three (3)
More informationCITY OF MONROE LA. DRAINAGE AND UTILITY IMPACT STATEMENT NAMES AND ADDRESS OF PERSON, FIRM, OR CORPORATION SUBMITTING STATEMENT
CITY OF MONROE LA. DRAINAGE AND UTILITY IMPACT STATEMENT TITLE OF DEVELOPMENT: LOCATION: OWNER: DESCRIPTION OF DEVELOPMENT: NAMES AND ADDRESS OF PERSON, FIRM, OR CORPORATION SUBMITTING STATEMENT DATE PRINT
More informationCITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application
CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application Good for 90 days from the Date Issued This permit is only required if the work location is owned or controlled by the City of Homestead and
More informationPROPOSAL KITSAP COUNTY DEPARTMENT OF PUBLIC WORKS COUNTY ROAD PROJECT NO NW Golf Club Hill Road Culvert Replacement To the Honorable Board of Co
PROPOSAL KITSAP COUNTY DEPARTMENT OF PUBLIC WORKS COUNTY ROAD PROJECT NO. 3690 NW Golf Club Hill Road Culvert Replacement To the Honorable Board of Commissioners Kitsap County 614 Division Street Port
More information