CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 03/05/2017 to 03/11/2017

Similar documents
CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 02/26/2017 to 03/04/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 06/04/2017 to 06/10/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 04/09/2017 to 04/15/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 12/11/2016 to 12/17/2016

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 08/12/2018 to 08/18/2018

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/23/2016 to 10/29/2016

Cumberland Viaduct Rehabilitation Project Contract No. AL R Presenter Bob Bofinger MDSHA Office of Structures

PUBLIC INFORMATION MEETING June 24, 2015

TENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1

TENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

MINNESOTA AVENUE NE REVITALIZATION PHASE II CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Ironton Russell Bridge Project

Bridge Asset Management City of Battle Creek Planning and Projects

CTA Capital Construction Update August 8, 2007

Lesner Bridge Replacement

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS

Ironton Russell Bridge Project

Canadian Consulting Engineering Awards 2016 CANADIAN NIAGARA POWER FOREBAY BRIDGE RECONSTRUCTION

Accelerated Bridge Construction in USA

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

REHABILITATION PACKAGE 4-a

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

Northeast Bridge Preservation Partnership Meeting

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

UPCOMING CONSTRUCTION PROJECTS 3 rd Quarter 2017 (Project & Construction Management)

City of Des Moines. Activity ID: Bridge Rehabilitation: Court Avenue over the Des Moines River

The Main Street Bridge - Supporting Transportation Systems

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

Lesner Bridge Replacement

Ironton Russell Bridge Project

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer

Review of Plans and Specs from a Constructability Perspective

High Bridge Re-Deck Project

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

LRFD Bridge Design Manual Changes

extent feasible. Per the and low constructability,

3.6 Construction Methods

Project Overview. Wilson Boulevard over Route 50 Bridge Rehabilitation. Get Involved. Public Information Meeting. Contact Information

SCCRTC- MP San Lorenzo River Bridge Walkway Widening Feasibility Report

Federal Project No.: STP-BR04 (304)

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6

Ironton Russell Bridge Project

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

Ironton Russell Bridge Project

Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement

Maine Turnpike Authority

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

National Roads Authority

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN

Pattullo Bridge Replacement Project. Cost Report

State of New Jersey NEW JERSEY DEPARTMENT OF TRANSPORTATION 1035 PARKWAY AVENUE P.O. Box 600 TRENTON, NEW JERSEY

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

GREENE COUNTY - SR 221(J10) # PROPOSAL:$11.76 PLANS:$ X18:$ X36:$47.10

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

ADDENDUM NO. 1. for the VETERANS PARK RENOVATIONS CITY OF TALLADEGA, ALABAMA. Posting Date: June 20, 2013

INVITATION TO TENDER ITT / NO. PS BURRARD BRIDGE REHABILITATION QUESTIONS AND ANSWERS NO. 3

Federal Project No.: BH-BR04(273)

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms

Virginia Concrete Conference March, Open Spandrel Concrete Arches New and Old

LIST OF BID ITEMS STRUCTURAL WIDENING OR REPAIR SUPERSTRUCTURE REFER TO ITEM VDOT QTY. PAY ITEM FOOTNOTE SPECS ROUND- UNIT CODE REF.

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

Exposition Light Rail Transit Project

CONTRACT PROPOSAL/CONTRACT ACCEPTANCE HIGDON LOOP ROAD BRIDGE

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Highway Bridge Structure Components

Construction Project Briefing. June 14, 2017

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management)

Federal Project No.: BH-BR04(273)

Maryland Transportation Authority (MDTA)

REHABILITATION OF THE HIGH BRIDGE SCHEMATIC DESIGN PRESENTATION TO: COMMUNITY BOARDS 4 (BX) & 12 (MN) OCTOBER 4 & 5, 2010

I-70 over SR 121 Bridge Slide Construction and Engineering

UPCOMING DESIGN & CONSTRUCTION PROJECTS 2 nd Quarter 2018 (Project & Construction Management)

Constructability Guidelines

Pipeline Rehabilitation amidst Environmentally Sensitive Location

SOUTHEAST TEXAS CONTINUING EDUCATION BRIDGE INSPECTION, MAINTENANCE AND REPAIR

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL

Norfolk Southern s Online Rebuild of the Coosa River Bridge

OHIO S CONCRETE BRIDGES

LMC Overlays For Bridge Deck Preservation 2011 Southeast Bridge Preservation Partnership Meeting, Raleigh NC April 13-15, 2011

DESIGN OF ROAD OVERBRIDGES

Drawing Modification Summary Effective:

Future Programmatic Beyond 01/06/2020 Sorted By District (Subject to Departmental Changes)

I-94/I-69 Interchange Bridge Construction

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Alaskan Way Viaduct Independent Technical Review

Transcription:

AECOM Field Office Water Street, NW Under Key Bridge along Water Street, NW REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.: DCKA-2014-C-0074 FAP No.: BH-1104 (013) CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 03/05/2017 to 03/11/2017 Project Website: www.keybridgeproject.com Page 1 of 10

PAGE 2 of 10 1. EXECUTIVE SUMMARY Project Description: Page 2 of 10 The AECOM Construction Management and Inspection team is providing construction and inspection services for the Rehabilitation of the Francis Scott Key Bridge over the Potomac River (Bridge No. 0007). This Francis Scott Key Bridge, built in 1929 is a historic 1,781-foot long reinforced concrete, open-spandrel arch bridge consisting of eight spans over the George Washington Parkway, Potomac River, Whitehurst Freeway and C&O Canal. The bridge not only served as a major commuter route into Washington, DC, but it also was listed on the National Register of Historic Place, which required coordination with the National Park Service since it spanned the C&O Canal and George Washington Parkway. This rehabilitation project is to restore the deteriorated portions of the structure, improving its structural integrity for another 30 years while maintaining those architectural features which contribute to its historical significance. The repair plans include conventional concrete patching repairs as well as strengthening with carbon fiber reinforced polymer reinforcing bars and sheeting materials. The construction cost is estimated to be approximately $14.5 million. The scope of the construction work includes the following: 1. Installing pedestrian/bicycle detection loops and warning flashers on the Bridge at the ramp to eastbound Whitehurst Freeway. 2. Cleaning and painting the existing steel pedestrian railing on the bridge. 3. Removing the concrete bollards from the east sidewalk at the east ramp exit. 4. Removing and installing new street light poles on the bridge. 5. Removing and resetting portion of the precast concrete traffic barrier on the Bridge. 6. Repairing the precast concrete traffic barrier and grout pads and he northwest concrete traffic barrier end post. 7. Strengthening the deck overhangs with carbon fiber reinforced polymer bars. 8. Repairing the concrete wearing surface on the bridge. 9. Repairing grout pockets at the post-tensioned deck hold down bolts. 10. Replacing the non-armored expansion joint seal (B-0007 and East Ramp). 11. Replacing the armored expansion joint seals (B-0007 and East Ramp) 12. Overlaying the right lanes (inbound and outbound directions) on the bridge with a high molecular weight methacrylate resin (HMWM) overlay; Milling and overlaying the Rosslyn approach structure with a very high early strength latex-modified concrete (LMC-VE). 13. Cleaning debris from all bridge deck drainage scuppers and pier chambers and Removing and replacing the Bridge deck drainage downspout. 14. Rehabilitating the support for a 30-inch Washington Aqueduct water main on the bridge. 15. Repairing portions of the concrete encased and the reinforced concrete floor beams; Cleaning and painting the exposed end of the steel floor beams. 16. Replacing failed concrete deck pedestals and Replacing portions of the utility gallery floor slabs full depth. 17. Repairing portions of the concrete superstructure, including but not limited to: deck soffit, deck pedestals, spandrel arches, spandrel columns, main arches, diaphragm walls, deck slab, and arch struts. 18. Repairing portions of the concrete substructure, including the piers, abutments, abutment chambers, and wing walls and Encapsulating the pier footings with fiber reinforced polymer jackets at the waterline. 19. Removing and replacing the fixed steel access ladder at North abutment and installing a new fixed steel access ladder at the South abutment. 20. Removing and replacing portion of chain link fencing (bridge access deterrent) on the main arches. 21. Cleaning the Bridge fascia with pressurized water and Applying an anti-graffiti treatment to portions of the piers. 22. Removing and applying new pavement markings (B-0007 and East Ramp). 23. Maintenance of pedestrian and vehicular traffic during construction of the project, including temporary lane and sidewalk closures necessary to perform the work.

PAGE 3 of 10 2. STATUS OF CONSTRUCTION / PROGRESS SUMMARY Progress Summary: 1. Contractor continued installation of suspended scaffold system from pier 4 to North abutment and at pier 3. 2. Completed PCO-01 package. Package has been reviewed by DDOT, signed by Technopref and uploaded to DDOT package tracker, awaits approval. 3. Continued to update the project website. 4. Contractor continued the demolition work for the concrete repairs at pier 4 and North abutment. 5. Continue to follow up on the concrete color matching efforts with the contractor. 6. Contractor prepared/casted test panels for dry mix shotcrete samples. 7. Contractor cored test panels for specimen samples for concrete compressive testing. 8. Contractor performed mockup samples for dry mix shotcrete to be inspected and evaluated by DDOT. 9. Contractor repaired location at pier 4 regarding NCR 001 10. Coordinating and planning meeting with DC Water and Washington Aqueduct regarding the work associated with the 30 inch Water Main and the 16 inch water pipe at the east gallery. 11. CM Community Outreach Activities The team communicated with the key stakeholders during the week to give them project status updates and identify any concerns that they might have about the project. Stakeholder Contact: Sean followed up with Greg King, Thompson s Boat Center on 3/7 to discuss follow up items from the 3/1 meeting Sean distributed minutes of 3/1 meeting regarding spring rowing season on the Potomac. To meeting attendees Greg King, Thompson s Boat Center; Tim Staples, Marine Solutions; Kevin Burns, DDOT; Sean Moore, CSMI; Joseph Chukwueke, AECOM; Bemen Amin, CKI; Ali Soltani, Technopref; Mathieu Delanoe, Technopref Notes: Project collateral submitted to DDOT on 2/24 is awaiting review by DDOT. Items including e-blast text and FAQs document, provided content and project rack card Reminded Technopref that any inquiries from the public need to be directed through Sean Key Takeaways: Communications team will continue to develop relationships with key businesses near the bridge that can help us distribute project information to their customers 3. ISSUES / ACTION ITEMS - Ongoing Issues / Items: - Pepco Cable on the East Ramp Concrete Bent Columns still unresolved although Pepco confirmed the ownership of overhead wires overhanging East Ramp piers as being theirs for some weeks now. DDOT continues to work with Pepco to determine the appropriate solutions to safely accommodate proposed work at the bent columns. On-site meeting on Monday February 06, 2017 and Pepco indicated that cables cannot be relocated until the new underground cables are in place. Page 3 of 10

PAGE 4 of 10 - Technopref of its obligations under the Contract and asked to summarize and submit its additional costs, in an amount not to exceed $35,000 as stipulated in the January 24, 2017 letter. - Action Items: NPS issued Limited Special Use permit, and verbally provided access to the river. Contractor has since had access and been working on barges on the river unimpeded. Hardcopy permit still awaited although does not impact progress of contractor s operations on site. - New Issues / Items: None, except as noted elsewhere in this report. 4. MEETINGS / PROJECT COORDINATION - Conference call continued to be utilized to communicate with the contractor when a physical meeting is not possible. - Weekly coordination meeting continues with DDOT team, project progress meeting with DDOT and the contractor. Monday 03/06/17 5. DAILY WORK PERFORMED 1. Technopref was on-site and continued cleaning at the staging area. Continued working on air and water lines (for construction purposes). Performed trial for the power washing operation on the West face of North Abutment at level 1 of scaffolding system 2. Handon services continued erecting scaffolding system from pier 4 to North abutment. Continued loading scaffold materials on barge. 3. Fibrwrap was on-site and continued the demolition process for the concrete repairs at pier 4. Resumed the demolition process at North abutment. 4. Handon Services sub for Fibrwrap was on site and performed mock up samples for dry mix shotcrete to be inspected by DDOT. Tuesday 03/07/17 1. Technopref was on-site and continued cleaning at the staging area. Continued working on air and water lines (for construction purposes). Performed trial for the power washing operation on the West face of North Abutment at level 1 of scaffolding system. 2. Handon services started erecting scaffolding system at pier 3. 3. Fibrwrap was on-site and continued the demolition process for the concrete repairs at pier 4. Continued the demolition process at North abutment. Wednesday 03/08/17 1. Technopref was on-site and continued cleaning at the staging area. Continued working on air, electrical and water lines (for construction purposes). 2. Handon services continued erecting scaffolding system at pier 3.. 3. Fibrwrap was on-site and continued the demolition process for the concrete repairs at North abutment Page 4 of 10

PAGE 5 of 10 4. Handon Services sub for Fibrwrap was on site and repaired location at pier 4 regarding NCR 001 (The restriction on concrete removal limits as specified on our drawing sheet 132 to prevent structural issue) Thursday 03/09/17 1. Technopref was on-site and continued cleaning at the staging area. Continued and concluded sounding at span C. Started sounding at span E Continued working on air, electrical and water lines (for construction purposes). Installed protection nets at pier 4. 2. Handon services continued erecting scaffolding system at pier 3.. 3. Fibrwrap was on-site and continued the demolition process for the concrete repairs at North abutment and pier 4. 4. Handon Services sub for Fibrwrap was on site and repaired location at pier 4 (Pier 4-Pilaster 1) regarding NCR 001 (The restriction on concrete removal limits as specified on our drawing sheet 132 to prevent structural issue) Friday 03/10/17 1. Technopref was on-site and continued cleaning at the staging area. Continued working on air, electrical and water lines (for construction purposes). 2. Handon services continued erecting scaffolding system at pier 3.. 6. INSPECTION & MATERIAL TESTS PERFORMED - Pay items worked this week are: 000 003 Employee Training. We were on site to observe Employee Training. 7. RFI s / SUBMITTALS - Requests For Information: o RFI No. 034 Area of Concern - East Ramp Bent 16A - Top of Wall deterioration o RFI No. 039 Exterior chamber wall o RFI No. 040 Deterioration Between Faces o RFI No. 041 Pier 2 Encapsulation o RFI No. 042 Alternative Means and Methods for demolition - Submittals: o Submittal No. 070A MOT - George Washington Parkway Forwarded to NPS o Submittal No. 088 Temporary fence for existing railing Page 5 of 10

PAGE 6 of 10 o o o o Submittal No. 089 Alternative design for scaffolding at mid-span Submittal No. 090 Water main support - Threaded rods Forwarded to Washington Aqueduct and DC Water Submittal No. 091 Pea Gravel Forwarded to DDOT/QAQC Submittal No. 092 Anti-graffiti PSX700 Forwarded to DDOT/QAQC 8. CHANGE ORDERS/TASK ORDERS - Negotiations were completed as of November 02, 2016 with contractor for CO #1 items. Completed PCO- 01 package. Package has been reviewed by DDOT and sent to Technopref for signature. Technopref objects to the standard language and requested language adjustment. DDOT responded and rejected the request for language change/revision from the standard. Contractor however, proceeded and submitted a signed document and included a hand-written non-standard language contrary to DDOT s directive which DDOT again rejected and asked the contractor to remove and submit. DDOT informed the contractor that it was willing to proceed with a unilateral change should they refuse to comply. Contractor signed PCO and it been uploaded to DDOT package tracker. 9. DBE or CBE PARTICIPATION SUMMARIES - AECOM DBE Activity: o CSMI Project Public out Reach. o CKI Aid to Construction Management and Inspection Services - Technopref o Intelect Corporation o Handon Diving Services Inc. 10. ACCIDENTS / INCIDENTS There were no reported personnel or safety accidents within the limits of the project during this reporting period. Page 6 of 10

PAGE 7 of 10 11. PHOTOS OF WORK PERFORMED THIS PERIOD Mock ups location for dry mix shotcrete Dry mix shotcrete application Mock up panels preparation Concrete demolishing and saw-cutting at pier 4 Page 7 of 10

PAGE 8 of 10 Concrete demolishing and saw-cutting at North abutment Concrete demolishing and saw-cutting at pier 3 Installation dust netting at Pier 4 Installation of scaffolding system at pier 3 Page 8 of 10

PAGE 9 of 10 Loading scaffold material Cleaning and switching concrete skips Loading scaffold material to barges Installing scaffold at pier 3 Page 9 of 10

PAGE 10 of 10 NCR 001 repair preparation NCR 001 repair preparation (installing rebar, bonding agent and wire mesh) NCR 001 repair preparation (form work) NCR 001 repair (pouring concrete) Page 10 of 10