Public consultation on the tariffs and conditions for using underground natural gas storage facilities in France. Technical consultation notice

Similar documents
Locational Spread: a market mechanism

TRANSMISSION CONTRACT ON THE NATURAL GAS TRANSMISSION SYSTEM

Deliberation. I - The Context. 1. The European regulatory framework: Directive 2003/55/CE

Evolution of the ATM5 offer Proposals from Elengy and Fosmax LNG

Map of Storage Groups and Storage Products for

Deliberation. 1. Context The regulatory framework applicable to third party access exemptions

APPENDIX C Storage Operational Conditions

Decision. on 1 st April Decision of 30 October 2014 forming a ruling on the changes to the ATRT5 tariff concerning the interim measures

Study on the value of flexibility in the management and design basis of distribution networks in France

Natural Gas Storage Contract APPENDIX D Rules for the allocation of storage capacities

8.1. GENERAL RULES OF CAPACITY BOOKING

TRF : Maintenance Schedule GRTgaz and Teréga common superpoints

Feasability study of the merger of GRTgaz North and GRTgaz South zones

CRE consultation on the creation of a single gas market area

GRTGAZ NETWORK TRANSMISSION CONTRACT

CALL FOR MARKET INTEREST NOTICE

EASEE-gas. European Association for the Streamlining of Energy Exchange gas

Gas Natural Fenosa comments to ERGEG Public Consultation on Existing transparency requirements for natural gas

Locational Spread. For network congestion management Winter 17/18

Winter Outlook Released 24 October 2017

Winter Outlook

LNG TERMINALLING PROGRAMME.

LNG TERMINALLING PROGRAMME.

Main developments in the gas and electricity markets in France in Commission de Régulation de l Energie (CRE) 31 st July 2013

ERGEG Guidelines for Good Practice on Open Season Procedures (GGPOS) Ref: C06-GWG-29-05c 21 May 2007

FLUXYS STORAGE SERVICES : ISP - SC

Press Dossier Lussagnet's 50th birthday September

CAMG Gestion Opérationnelle des Contrats Tariff Operational rules

CODE OPERATIONNEL DE RESEAU TRANSMISSION

5 solutions to solve your BREXIT related customs issues

Draft Modification Report Revision of the Gas Balancing Alert (GBA) Trigger/Safety Monitor Modification Reference Number 0257 Version 1.

UNOFFICIAL TRANSLATION

Introducing Carrier Selection & Carrier Pre- Selection in Malta

LNG TERMINALLING PROGRAMME

Natural gas transport contract. Appendix B1: Rules for subscription and allocation on the Main Grid

5 solutions to solve your BREXIT related customs issues

IMPLEMENTATION OF ARTICLE 33 and ARTICLE 41 OF DIRECTIVE 2009/73/EC regarding Gas Storage

TRF : Maintenance Schedule 2019

TRF & PEG news. Prices and liquidity of the. Price and liquidity focus p.2-3. Network flows and limits. 2 days of red alert*, i.e.

UNOFFICIAL TRANSLATION

CRE consultation on the implementation of regulated access to underground gas storage in France

GRTGAZ NETWORK TRANSMISSION CONTRACT

INVITATION TO APPLY FOR INVERSE STORAGE CAPACITY

Present: Philippe DE LADOUCETTE, Chairman, Olivier CHALLAN BELVAL, Catherine EDWIGE and Michel THIOLLIERE commissioners.

Energy market development in Latvia and the Baltic States

Winter Outlook

EUROPEAN ENERGY SECURITY GAS INFRASTRUCTURE CONTRIBUTION FRENCH ILLUSTRATION

FERC GAS TARIFF FIRST REVISED VOLUME NO. 1. (Superseding Original Volume No. 1) SOUTHERN STAR CENTRAL GAS PIPELINE, INC.

where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37.

Underground Natural Gas Storage Course No. PT0131 PDH: 2

Code Opérationnel de Réseau Transmission

INVITATION TO APPLY FOR INVERSE STORAGE CAPACITY

Marketing infrastructures and networks

APPENDIX E.1: PROCEDURE FOR THE MARKETING OF CAPACITIES AT THE PIRINEOS VIRTUAL INTERCONNECTION POINT

The present ACER Guidance to ENTSOG provides a framework for the development of a

Seminar on African Electrical Interconnection. Module 7 - Market Operational Structures

INVITATION TO APPLY FOR INVERSE STORAGE CAPACITY

1 The Modification Proposal

Present: Jean-François CARENCO, President, Catherine EDWIGE, Hélène GASSIN, Jean-Laurent LASTELLE et Jean-Pierre SOTURA, commissioners.

Study on Underground Gas Storage in Europe and Central Asia. Working Party on Gas Geneva, January 22, 2013 G.-H. Joffre (Storengy) et al.

PROPOSAL FOR THE UPGRADE OF THE BALANCING SYSTEM OF GRTGAZ S TRANSMISSION NETWORK

Fluxys natural gas transport services in Belgium Indicative Conditions & Tariffs

PETRONAS GAS BERHAD NETWORK CODE FOR PENINSULAR GAS UTILISATION TRANSMISSION SYSTEM

3 rd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

CORE TRANSMISSION. The English Translation for information. Version of Disclaimer

CORE TRANSMISSION. The English Translation for information. Version of Disclaimer

EU Gas Market Reform what does it mean in practice?

Interconnector (UK) Limited IUK Access Code

Energie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model (Gas Market Model Ordinance 2012) Title 1 Principles

Winter Review 2017/2018

UK Flaring Policy. UKCS Associated Gas Production, Flaring, and Utilization Rate. Billion Cubic Meters Uitlization Rate. 80 Production 98% Flaring

Dominion Energy Transmission, Inc. FERC Gas Tariff Tariff Record No. 20. Fifth Revised Volume No. 1 Version TARIFF RATE SCHEDULES

Press release 11 May Interim statement. 1. Customer invoicing. Regulated information: interim statement

STUDY SUMMARY (F) CDC-1319

CRE consultation concerning the terms for marketing natural gas storage as of October 2018

PJM Fixed Transmission Rights (FTRs)

AB AMBER GRID RULES FOR ACCESS TO THE NATURAL GAS TRANSMISSION SYSTEM

Gas Storage Regulation and Security of Supply

STORAGE AND TRANSPORTATION RATES FOR CONTRACT CARRIAGE CUSTOMERS

Role of the Public Electricity Supplier and the Supplier of Last Resort in the De-regulated Electricity Market

NATURAL GAS TRANSPORTATION SERVICES PROVIDED BY IUK BETWEEN GB AND BELGIUM

Introducing Carrier Selection & Carrier Pre- Selection in Malta

Jersey Competition Regulatory Authority. Consultation Document Telephone Number Portability in Jersey

COMMISSION STAFF WORKING DOCUMENT EXECUTIVE SUMMARY OF THE IMPACT ASSESSMENT. Accompanying the document. Commission decision

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013

Pricelist for Services Provided by POZAGAS a.s. and Terms and Conditions of Prices Application

Towards TRF and PEG on 1st November Training session 4th of June, 2018

ACER call for comments on the Network Code Emergency and Restoration

Objective, transparent and regulated grid access tariffs

INSPECTION PROCESS INPUTS TECHNICAL STANDARD INSPECTION PROCESS. Inputs suitable for use in Organic Agriculture

Connection tariffs

Reference Access and Interconnection Offer

COMMISSION STAFF WORKING PAPER INTERPRETATIVE NOTE ON DIRECTIVE 2009/73/EC CONCERNING COMMON RULES FOR THE INTERNAL MARKET IN NATURAL GAS

Review of the General Conditions of Entitlement. Transposition table for general conditions

Economic analysis of the sunset clause

Virtual Workshop on PJM ARR and FTR Market 2017/2018

ATTACHMENT B Services Fees

NSTAR ELECTRIC COMPANY M.D.P.U. No. 6 WESTERN MASSACHUSETTS TERMS AND CONDITIONS GREEN OPTIONS SUPPLIERS

APPLICABILITY The following Provisions shall apply to School/Government Suppliers under Rate 185.

Transcription:

Public consultation on the tariffs and conditions for using underground natural gas storage facilities in France Technical consultation notice Preamble Law n 2004-803 of August 9 th 2004 introduces negotiated third party access to underground natural gas storage facilities in France, in accordance with European directive 2003/55/EC of June 26 th 2003. It notably stipulates that former suppliers are required to free up the storage capacities required by new suppliers, and that the tariffs and conditions for using the storage facilities are negotiated between the operators of these facilities and their users: "the methods of accessing storage capacities [ ] and particularly the price of access are negotiated under transparent and non-discriminatory conditions". In April and October 2004 respectively, Gaz de France and TOTAL Stockage Gaz France (TGSF), a subsidiary of TOTAL, published the conditions and prices for using their storage facilities, which can be found on the following websites: http://stockage.gazdefrance.com and http://www.total-tsgf.com. In France, storage facilities are essential elements for the security and flexibility of supply to end consumers, and each operator has a monopoly in most of the geographical zones he serves. In this context, CRE wishes to consult all the players concerned regarding the offers made by the two storage facility operators. If any improvements are required, CRE would like to see them made public by February 15 th 2005, so that they can be implemented from April 1 st 2005. I. Presentation of conditions for using storage facilities I. 1. Products marketed Gaz de France and TSGF sell storage units. A storage unit comprises an injection capacity, a withdrawal capacity and a storage volume, in proportions reflecting the physical characteristics of the storage facilities. I. 2. Overall structure of supply I. 2. 1. Gaz de France Gaz de France markets its storage services in groups of facilities. These groups of storage facilities have been formed according to the geographical location of the facilities, their performance (extraction speed) and the nature of the gas (H or L quality). In each balancing zone of Gaz de France's transmission network, there is at least one group of facilities, which can be accessed via a PITS (Interface Point between Transport & Storage). 1

Description of Gaz de France's storage facility groups Group Transmission balancing zone Working gas volume Centre (H gas) Ouest and CFM zones 46 TWh Île de France Nord (H gas) North 13 TWh Île de France Sud (H gas) Nord 13 TWh Lorraine (H gas) Est 7 TWh Salins Sud (H gas) Sud 9 TWh Picardie (L gas) Nord 10 TWh Source: Gaz de France website I. 2. 2. TSGF In the south-west of France, the storage facilities at Lussagnet and Izaute are mutualised and TSGF proposes two offers: one called "Equilibre", which features a low deliverability per unit of volume stored; and another called "Dynamique", which allows a high deliverability per unit of volume stored. TSGF does not yet publish any indicators of its marketable working gas volumes, but intends to do so by January 1 st 2005. The two offers can be accessed from the GSO transmission network, via a single PITS. I. 3. Contract start date and prior notice In the two storage facility operators' current offers, it is made clear that contracts for using the facilities can only begin on April 1 st, with three months' prior notice for Gaz de France and six weeks for TSGF. I. 4. Physical constraints The technical constraints on the operation of storage facilities ("physical constraints") are passed on to each individual user depending on his specific situation, independently of other users. There are two types of physical constraints, affecting the level of gas stored and the injection and withdrawal capacities. I. 4. 1. Constraints on the level of gas stored Storage facility operators impose seasonal obligations for the management of each user's gas stock. For each group or offer, these obligations are represented by two annual curves, which define the lower and upper limits for gas stored, day by day. It should be noted that, for each group or offer, the store of gas at the end of the withdrawal period must not exceed 40% of the volume subscribed (except for Gaz de France's "Salins Sud" offer: 100%, i.e. there is no withdrawal obligation). At the end of the injection period, the store of gas must be no less than 85%, 90% or 92% of the subscribed volume, depending on the groups or offers concerned. 2

I. 4. 2. Modification of firm withdrawal and injection capacities depending on the user's current stock level The physical injection and withdrawal capacities of an underground storage facility depend on the volume of gas stored. The facility operators impose limits on the amount of injection and withdrawal capacity for each user. These limits take the form of a "reduction factor" dependent on the user's current stock level, which is applied to the nominal capacity subscribed. The deliverability available from facilities operated by Gaz de France and TSGF therefore varies depending on the user's current stock level. On the other hand, TSGF's available injection capacity remains equal to the nominal capacity subscribed throughout the year. I. 5. Non-availability due to works or maintenance For each group of storage facilities, Gaz de France stipulates a certain number of planned interruptions in injection or withdrawal (maximum of 20 days during the withdrawal period and 30 days during the injection period), for which users receive no compensation. It also stipulates a limited number of unplanned interruptions (20 days max.) for which compensation is paid. TSGF stipulates a maximum of 15 days of planned interruptions during the injection period, none during the withdrawal period and a maximum of 15 days of unplanned interruptions. These interruptions do not give rise to any compensation. Beyond 30 days, financial compensation is provided. II. Presentation of tariffs for using storage facilities The two operators' tariff structures are very similar. They only differ in terms of a few options. However, the levels of the tariff terms are different. It is nevertheless worth noting that, since each storage facility or group of facilities has specific costs and performance levels, a direct comparison is not necessarily relevant. II. 1. Tariff terms Gaz de France and TSGF propose basic offers corresponding to the subscription of storage units, and a number of options. II. 1. 1. Basic offers a) Fixed management term Both operators invoice each shipper a fixed management term which amounts to 24,000 per year and per group of storage facilities for Gaz de France, and 10,000 per year and per offer for TSGF. b) Terms proportional to the storage volume subscribed This term accounts for the major part of the invoice received by each storage facility user. For 1 MWh of storage volume subscribed, the term is between 4.60 and 13.30 depending on the group of facilities for Gaz de France, and is equal to 2.50 and 4.50 respectively for TGSF's "Equilibre" and "Dynamique" offers. The volume of storage subscribed by users entitles them, for each group or offer, to specific withdrawal and injection capacities. 3

c) Terms proportional to the quantities injected and withdrawn Each MWh injected under the basic offer is invoiced at 0.30 by Gaz de France, and at 0.10 by TSGF. Each MWh withdrawn under the basic offer is invoiced at 0.10 by Gaz de France, and at 0.20 by TSGF. d) Direction change term Both operators charge a supplement for all changes in direction (where a daily withdrawal nomination follows a daily injection nomination or vice versa) over and above a certain fixed number. This number is 4 per season for Gaz de France, and 18 per year for TSGF. The price supplement is equal to 6,000 per change in direction for Gaz de France, and 0.002 per storage unit subscribed (with a minimum of 1,000) per change in direction for TSGF. II. 1. 2. Peak options a) Gaz de France Gaz de France proposes peak withdrawal and injection options. The extra peak withdrawal capacity offered is equal to 15%, 20% or 25% of the basic capacity reserved according to groups of storage facility, and may be used on extremely cold days, plus a further 10 days per year. The tariff charged for this option includes an annual fixed term of 6,000, a term proportional to the extra capacity subscribed of 16.7 per MWh/day, and a term proportional to the extra quantities extracted of 1.2 per MWh. The extra peak injection capacity offered is 15% (except Salins Sud: 40%) of the basic capacity reserved and may be used on 50 days per year. The tariff charged for this option includes an annual fixed term of 6,000, a term proportional to the extra capacity subscribed of 17.5 per MWh/day, and a term proportional to the extra quantities injected of 0.35 per MWh. b) TSGF TSGF proposes a peak withdrawal option, which is only available under the "dynamique" offer. The extra peak withdrawal capacity offered is equal to 26% of the basic capacity reserved. It may be used on 6 days per year at no extra cost. Beyond these 6 days, the tariff is 1.0/MWh for the extra quantities withdrawn. II. 1. 3. Other optional services The transfer of storage units and stored gas is invoiced by the storage operators, at 6,000 per operation by Gaz de France and 1,000 per operation by TSGF. Currently, only transfers of storage units are allowed. There is no option to transfer volume, withdrawal and injection capacities separately. The sale of stored gas is only authorised by Gaz de France at the start and end of the contract period. Both operators offer a daily balancing service according to similar conditions. Under the service, the storage user's daily balance on the transmission network can be optimised, up to a limit of 10% of the total nominal injection capacity and nominal withdrawal capacity subscribed. With Gaz de France, the price of the service includes, for each group, an annual fixed term of 6,000 and a term proportional to the capacity subscribed of 15/MWh/d per year. With TSGF, the price of this service includes an annual fixed term of 1,000 and a proportional term equal to 0.1 per storage unit subscribed and per year. 4

II. 2. Penalties Each storage facility user must ensure that his current stored gas level remains within the set limits at all time. If a user breaches the upper limit, he is obliged to sell the excess gas to the storage facility operator, at a price equal to 50% of the reference price for the balancing zone. If the user breaches the lower limit, he is obliged to purchase the shortfall in gas from the storage facility operator, at a price equal to 150% of the reference price of the balancing zone. 5

CRE invites players who so wish to send it their comments and observations on the offers for access to storage facilities described in this document, as well as any other issues they wish to raise during this consultation, no later than January 14 th 2005. As an indication, some possible questions are listed below: General questions Q1 : Q2 : What is your opinion of the overall structure of storage facility access offers? Are you favourable to the introduction of flexible options not offered to date, notably: - the introduction of a secondary market allowing the separate sale of storage, withdrawal and injection capacities between users? - the sale by the facility operator of unused capacities on a daily basis? Q3 : Q4 : What do you think of the level of offers for access to storage facilities in France, notably in comparison with those found elsewhere in Europe and the flexibility market prices in Zeebrugge and the United Kingdom (NBP)? Do you think you receive sufficient information about facility operators' offers and available capacities? If not, what extra information would you like the facility operators to publish on their websites? Questions of a technical nature Q5 : Q6 : Q7 : Q8 : Q9 : What is your opinion of the fixed management term and the other fixed terms in Gaz de France and TSGF's offers? Would you like to see them replaced by terms proportional to volumes or capacities? What is your opinion of the terms charged for changes in direction? Do you have any comments or suggestions on the optional services offered by storage facility operators? What is your opinion of the way physical storage constraints are incorporated into the operators' offers? What do you think of the non-availability periods for maintenance stipulated by the operators, and the compensation paid to users? Q10 : Do you have any other comments or suggestions regarding the tariffs and conditions for using storage facilities? Q11 : Do you have any other comments or suggestions on standard contracts for using storage facilities? 6