EDS Upgrades and CBRA Improvements. Addendum No. 2 DATE OF ADDENDUM: 08/17/2016

Similar documents
EDS Upgrades and CBRA Improvements. Addendum No. 1 DATE OF ADDENDUM: 08/05/2016

BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION

Question 2: Regarding Section VII, part 10, which jurisdiction issues permits for work performed at Ronald Reagan Washington National Airport?

REQUEST FOR SEALED PROPOSAL. ADVERTISEMENT for CONSTRUCTION SERVICES RFP - GICC GATEWAY CENTER ARENA ADDENDUM No 1 OWNER S BID PROPOSAL FORM

Revised Drawings A, E, and M dated 11/13/18 (that include additional specifications)

ADDENDUM NO. 5. Except as hereinafter specified, the work shall be in accordance with the drawings and specifications.

SAN ANTONIO WATER SYSTEM University Pump Station Improvements Project SAWS Job No Solicitation No. B DD

All subcontractor bidders are responsible for assuring that their subcontractors and vendors are properly apprised of the contents of this Addendum.

PRE-PROPOSAL CONFERENCE

DALLAS FORT WORTH INTERNATIONAL AIRPORT ADDENDUM NO. 01. Terminal D Expansion Joints Rehabilitation CONTRACT NO

QUESTIONS & ANSWERS FOR B SOUTHWEST SERVICE CENTER BOOKING REMODEL 02/20/2019

Angio to Cath. Lab Renovation ADDENDUM #2 12/29/2017

ADDENDUM NO. 1. This Addendum is issued to clarify and revise the construction documents dated July 6, 2016 as follows:

RFP No C108. Response: This contract does not have an incumbent. Can the Authority provide a list of equipment for review?

Transbay Transit Center San Francisco, CA CM/GC Contract No CMGC-000 Project No PROPOSAL PACKAGE TG17.1 ADDENDUM # 2

December 2, Enclosed is Addendum No. 1 to SEPTA's Sealed Bid No AMJP Frazer Shop & Yard Expansion Contract 2 (Re-Bid GC).

PURCHASING DEPARTMENT. Project # Addendum # # of pages Original Issue Date April 24, 2015

MEMORANDUM. Taylor Schoel with Walter Schoel Engineering. DATE: August 29, Addendum 1 - Green Drive Culvert Replacement.

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

ADDENDUM NO. 4 TENDER CALL NO CONTRACT NO. MCP Highland Creek Treatment Plant ECAP 06 MCCs Replacement and RPU/SCADA Upgrades

APPENDIX D CONSTRUCTION PHASE CRITERIA

All Plan Holders 3/3/

TOWN OF EAST HADDAM INVITATION TO BID EAST HADDAM COMPANY #1 FIREHOUSE INTERIOR RENOVATIONS ADDENDUM NO. 1 TO CONTRACT DOCUMENTS

CHARLES COUNTY GOVERNMENT ITB NO MATTAWOMAN WATER RECLAMATION FACILITY (MWRF) PRIMARY CLARIFIER NO. 1 IMPROVEMENTS

Checked Baggage Technology Update. Rick Phillips Division Director (Acting), Checked Baggage Technologies Division

NOTE: Responses marked with * indicate revisions to the Contract Documents reflected in the future Addendum.

ADDENDUM #4. Lanier Filter Plant Ozone System Safety Improvements BL079-14

AMENDMENT OF SOLICITATION

CHARLES COUNTY GOVERNMENT ITB NO PINEFIELD DRAINAGE IMPROVEMENTS

Solicitation Number: FA B-A001 Project Numbers: RKMF Demo Base Gymnasium & RKMF Demo Pool Facilities.

Tiger Drylac Canada Inc. Batching Room and Storage Addition 110 Southgate Drive, Guelph, ON December 4, 2017

ADDENDUM #1 TO REQUEST FOR PROPOSALS FOR SCADA SYSTEM DESIGN/INSTALL

Schendt Engineering Corporation 2912 Beacon Street (719)

ORANGE COUNTY WATER DISTRICT Ward Street Fountain Valley, California ADDENDUM NO. 2 TO REQUEST FOR PROPOSALS FOR

LSCC MISC. PROJECTS (PACKAGE D) MILLSAP BUILDING ROOF REPLACEMENT Addendum 3

ADDENDUM #2 REQUEST FOR COMPETITIVE SEALED PROPOSALS FOR A GENERAL CONTRACTOR. The University of Texas Health Science Center at San Antonio

Generator for Maintenance/Police Complex

ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project PW

ACZC Summary Of Questions / Answers Addendum No. 4. 1) What is the anticipated date of a SEPTA site visit from SEPTA?

BID INSTRUCTIONS. Montour County Courthouse Retaining Wall Repair Project

MIRACOSTA COLLEGE. [X] MiraCosta College Bid Opportunities Website /FAX

RFP /ME - ADDENDUM 2

RESPONSES TO QUESTIONS. March 1, 2018

City of Frederick PURCHASING DEPT.

Via Internet Posting 14 pages

Enclosed is Addendum No. 2 to SEPTA's Sealed Bid No ATMM 5 & Market Station Enhancement Project.

ADDENDUM NUMBER ONE BRISTOL WATER FILTRATION PLANT MCC UPGRADE CITY OF BRISTOL, TENNESSEE

TELEPHONE: (215) Addendum No. 03

Airport Baggage Handling Control Systems. Corporate Member


The purpose of this addendum is to respond to RFI s submitted to the County and issue a revised SECTION BID FORM.

PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA. Terrazzo Floors at Concourse B, C and E ADDENDUM NO. 4

ADDENDUM NO. TWO (2) ILM TERMINAL IMPROVEMENTS CONTRACT 2

FLORIDA DEPARTMENT OF TRANSPORTATION

ADDENDUM 2 KODIAK ISLAND BOROUGH CHINIAK TSUNAMI CENTER AND LIBRARY Kodiak, AK

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT

ADDENDUM NO. 1. FY 2012 Full Depth Reclamation Project CITY OF GAINESVILLE, GEORGIA

Montclair, NJ ADDENDUM NO. 2. Request for Proposal # 987 Access and Revenue Control System

C o u n t y o f F a i r f a x, V i r g i n i a

Main Building Auditorium

PROJECT MANUAL BID DOCUMENT 95% REVIEW CHECKLIST PROJECT BID NO EPWU PEM. CONSULTANT SUBMITTED ON / / as a 95% (A) original

Addendum No Variable Frequency Drives Section A, revise per following:

ASHCROFT PUMP STATIONS 2 & 3 CAPACITY IMPROVEMENTS PROJECT ACSA Project No Addendum 1 June 20, 2018

Request for Bids. At The Greenville-Spartanburg International Airport

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

Herrington Architects PC 101 Richard Arrington Jr. Blvd. S. Birmingham, AL phone fax

1. Meeting minutes from the pre-bid conference are attached for inclusion in the Bid Documents.

Transmittal. Oshawa, ON L1H 7K7. Mr. Kevin Jones DC - Design Services Durham College Whitby Campus Weston Grant for Farming Expansion

DALLAS-FORT WORTH INTERNATIONAL AIRPORT

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

ADDENDUM NO. 1 FOR RENOVATIONS TO LINCOLN ANIMAL SHELTER RFP # February 1, 2018

Business Services Procurement University of North Texas University of North Texas Health Science Center University of North Texas at Dallas

ATTACHMENT D SCOPE OF SERVICES

METROPOLITAN PIER AND EXPOSITION AUTHORITY INVITATION FOR BIDS (IFB) # M OFFICE BUILD OUT, 5 TH FLOOR OF ABC BUILDING ADDENDUM NO.

ADDENDUM NO. 2. Except as hereinafter specified, the work shall be in accordance with the drawings and specifications.

RFP CULVER CITYBUS STOP IMPROVEMENT PROGRAM: BUS SHELTER, BENCH, TRASH RECEPTACLE PROCUREMENT, REMOVAL AND INSTALLATION

ADDENDUM #1. The following constitutes Addendum #1 to the above referenced solicitation.

Questions and Answers (Q and A) ITB UNHCR/PMCS/2016/GOODS/MI ITB/001

INVITATION FOR BID (IFB):

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect.

Solicitation No Passenger Wait Time System, please be advised of the following clarifications to the above referenced Solicitation.

We will need to keep a minimum of 6-0 wide pathway.

has been changed to Thursday, December 14, 2017 at 10:30 A.M., prevailing Eastern Time.

Request for Bids. At The Greenville-Spartanburg International Airport

DEAN + TYLER + BURNS ARCHITECTURE

CITY OF FERNDALE, WA PAGE 1

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

ADDENDUM NO. B. TO THE BID DOCUMENTS, dated 1/5/16 FOR THE

ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

Attachment A Repair Knee Brace on High Arch Salt Building Fayette County, Mill Run Stockpile #24 Project # Building #PA

MEMPHIS-SHELBY COUNTY AIRPORT AUTHORITY MEMPHIS, TENNESSEE

SAN JOAQUIN COUNTY PURCHASING AND SUPPORT SERVICES PURCHASING DIVISION

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK

AUTOMATIC METER READING SYSTEM DETAILED SPECIFICATION

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.

CHARLES COUNTY GOVERNMENT ITB NO GOVERNMENT BUILDING ATRIUM RENOVATION

ADDENDUM NO. 2 Page 1 of 13

RFB Waco City Hall Chiller Replacement. Date: 3/20/2018 RFP No: Commodity: Waco City Hall Chiller Replacement

Addendum #1. January 22, 2018

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN & CONSTRUCTION LOBBY AND CAFETERIA FLOORING INSTALLATION EVERETT MIDDLE SCHOOL ADDENDUM NO.

Transcription:

EDS Upgrades and CBRA Improvements Addendum No. 2 DATE OF ADDENDUM: 08/17/2016 The following changes, additions, and/or deletions are considered as Addendum No. 1, and are hereby made a part of the contract documents. All bidders are required to base their bid upon the information furnished in this addendum; and as required in the contract documents. The Contractor is required to acknowledge Addendum No. 1 in their company proposal. Failure to acknowledge addendum on the bid form will result in bid being declared non-responsive. Bid records will be available for public inspection after issuance of the notice of intent to award or the award of the contract. Bidder should contact the Airport to arrange an appointment to review the bid record. The sealed bids received by date scheduled for August 23, 2016 at 2:00 p.m. in the Spokane has not changed. Attached are the following documents to be acknowledged with each contractors bid package as part of Addendum No. 2 Attachments to this addendum are as follows: 1. RFI Bid s 2. Sample Portering Calculations CHANGES, ADDITIONS, DELETIONS AND/OR CLARIFICATIONS TO THE CONTRACT DOCUMENTS: GENERAL NOTES/CLARIFICATIONS There are no additional notes or clarifications issued with this addendum. End of Addendum No. 2 1

RE-BID QUESTIONS TRACKING LOG Project Name: EDS Upgrades and CBRA Improvements Project Location: GEG Date Issued: 08/17/2016 Item No. 1 2 3 4 5 6 & Drawing BM- 503 & Drawing BM-503: The drawings show Baggage Inspection Table details that reflect PGDS v5.0, which requires Baggage Status Displays at each BIT. If it is the intent of the Owner or the Engineer to want BSDs at each BIT, please provide specifications on the desired display hardware. : Please provide specifications (make, model, size, etc.) for the new ribbon displays to be installed at each Baggage Removal Point. : Page -55 references a new Motor Control Panel, A2-CC3, which will hold the VFDs for SB2-08/13. Please provide specifications on this new MCP and/or details on existing MCPs. : Page -49 states that there will be eighty (80) hours of airport maintenance training, which is a much greater number of hours as compared with the airport operations training and TSA operations training. Please confirm that eighty (80) is correct. : In regards to the existing upper level system will the selected contractor be able to obtain source files in order to modify the system as necessary? Please also provide more information on the type of software used in the system. made during site visit for the GC's to utilize the vendor currently employed by SIA for the interim baggage handling operation while the conveyors are being changed. Please provide contact information for follow up. This project is not PGDS 5.0 compliant. It is specified page -22 (P. 1-line message display assemblies) It will be 1-door panel with 60A (page -55) and enclosures are specified in page -20. Change eighty (80) hours of airport maintenance training to eight (8). Source files will be made available to the successful bidder. The airport currently uses Kodiak Security Services for additional security services, including escorting through SIDA and portering; contact info is 509.244.3929. 7 8 The requirements for portering are too open ended so it is impossible to compare bids. In order for the bids to be fair and accurate, I suggest you determine a set dollar amount and have all the General Contractors include that as an allowance in their bid for portering. (Refer to Section 001010 Summary of Work and Item 3 in Addendum #1). There is currently no way to determine how many porters are required, or for how long. Without defining this better, SIA opens itself up for potential contract disputes later on. You could either direct the GC s to include a certain dollar amount as an allowance, or include a certain number of porters for a given duration and a set number of hours per day. We have the contact phone number for Kodiak Security Services, but that will only give us their rates. Company planning to bid on SIA project; is there a specific wage determination assigned for this project in regards to those prevailing wages? See the attached sample Porter Calculation as a guideline. Porters can come from a variety of labor categories, so long as they can perform the task, and be screened and badged by the airport. The Contractor is responsible for providing porters for the phased duration of the work. If the Contractor's estimated schedule is greater than that indicated in the Contract Documents, then portering cost shall be adjusted appropriately. The prevailing wage rates for the project can be found at: http://www.lni.wa.gov/tradeslicensing/prevwage/wa gerates/ Both the state prevailing wage law and the federal Davis-Bacon and related Acts apply, contractors must pay the higher of the state or the federal wage rates, on a classification by classification basis. 9 10-1 1.01 B. 3.A -18 2.01.U.3 Due to the potential of building constraints, we are requesting that this required minimum clearance be lowered to 7'6." We are requesting a "pan" style catwalk be allowed as an equal substitution. Existing tug clearance must be maintained. 8'-0" preferred, 7'-6" absolute minimum. Relocate A1 existing crossover catwalk. No new catwalk is required. 11 26 05 29-4 3.5.A.2 Do we need to x-ray all anchoring locations where pre- or post-tensioned concrete is located prior to anchoring. The existing drawings do not indicate pre or posttensioned concrete slabs, columns or beams. However, if contractor suspects a structural element is pre- or post-tensioned then the reinforcement must be located prior to placing anchors. 12-11 2.01.A.2.E.3 Our standard color for drip pans is yellow. Is it okay to use our standard color for drip pans? No. The existing drip pans match the conveyor color.

Item No. 13 A-02-51 Please confirm what testing is required at the end of the project to ensure the system is in an acceptable state for customer acceptance. VTC will witness OEM testing described in section 5.01 BHSC Testing to include but not limited to: static, dynamic and functional testing of each of the systems modified or replaced to ensure conveying performance and controls/tracking performance, e- stop zoning and BHS integration and communications with the upgraded ISD machine software. TSA IV&V testing is not anticipated. 14 15 16 17-18 2.01.U.4-16 2.01.N.8 Request confirmation that the P.E. stamping requirements for structural elements are limited to the conveyor system structural elements, connections and associated loads, point loads imposed to the building structure only. We will not providing validation of the buildings structural capacity. Request copies of the CTX integration guide for the CTX9400 which has been selected for the Scope of work does not include integration or CEG project. modifications to the BHS to CTX interface. The National Electric code as it relates to working space in front of electrical components will The current scope of work does not include any not be possible using the spec requirement for catwalk. catwalk. The Siemens HSD II Control Panel meets all the above, however does not provide the E-Stop. Control station typical drawing includes a Type-7 Control Station (next to diverter). Please advise, if we can proceed with not using any Type-7 control stations, given that the Siemens Control Panel functions to meet the above specifications, and we will provide a control station near all Siemens HSD II devices if required for the E-Stop functionality. This is acceptable as long as all functional and operational requirements for HSD sub-system are met. 18 19 20 001010-3 1.2.A.4.K.4-18 2.1.T.2-1 1.01.B.2.A Please confirm if the BHS contractor is responsible for providing the porters. Request to use 4" round pipe with ¼" wall thickness as a replacement for the posts; as it is its standard product. This is in direct conflict with the contract drawings. In the contract drawings, 36" is noted twice as the clearance requirement. These locations are in the General Notes Section #5 on Drawing No. BM-100 and on drawing No. BM 502. Please confirm the required clearance is above the conveying surface. Portering cost is to be included in the bid. Bid to project specifications. All requests for substitution will be discussed after bid award. Specification supersedes drawings. Please use Specification Section 34 77 16 1.01.B to define Bag Clearance requirements. 21 Request substitution to supply Morcon CBRA table in lieu of Lucasey. Bid to project specifications. All requests for substitution will be discussed after bid award. 22-21 2.02 N Do all motors require quick disconnects. 23 000309-3 This project is only PGDS compliant in relation to the What version of PGDS is compliant with this project? 2 PLC change process. 24 What is the PGDS version of the current running system? This system was certified pre PGDS. 25 Current project scope of work does not include any Please confirm the existing interface between CTX9000 and BHS PLC can remain same and modifications to the existing screening machine does not require any modification for the upgraded CTX9000 and BHS PLC. interface. 26 Please confirm there is no SAC. There is no SAC. 27-51 A-02 Please confirm "Glideview" handles both Graphic Status Display and Reports. 28 29 30 Please confirm the Glideview project (development) is available and can be delivered to project team. The current PLC system is an warm-back up configuration. Does the back-up PLC retain tracking information? Please confirm all the Motor control panel that needs to be modified as per the specification, airport can provide the as-built drawing in the AutoCAD '.DWG' file format. The contractor will have full access to the upper level system in the airport. No. This configuration and warm-back logics remain the same as it is now. Assume that all as-built documentation will be provided in.pdf format. A majority of drawings are available in '.DWG' format; however we cannot confirm that all drawings are in '.DWG' format.

Item No. 31 32 33 34 Exhibit A 35 Add Alternate #2 Please confirm existing current PLC code and RSNetworx configuration files is available for the project team. ED3-14 shows HSD- is HSD to be supplied as a new unit? It does not show in the equipment list as new HSD. The VTC spec. lists $500 then lists $1,000/day in the schedule portion of the general conditions. With this project at least partially funded by the TSA, please confirm PGDS requirements and related testing & certification will not be required. a. To what level of PGDS will the modified CBRA be tested against? b. Will the addressing and correction of deficiencies be considered additional scope? c. If this alternate is accepted, will additional time be granted to perform these tests? 36 Has the TSA reviewed and accepted the proposed controls design as described within the RFP? 37 ED2/ ED4 & XO1 Will the removal of ED2 & ED4 and the installation of XO1 require system throughout testing? SB1 is the HSD diverter that is on the ED3-14. This diverter is to be supplied as new. The liquidated damages reference in Section 000420 Bid Form apply. a. CBRA is tested for static, functional, tracking and status display using ribbon strip. b. Correction of deficiencies if identified by TSA will be considered additional scope. c. Yes, if the testing alternate is accepted the schedule will be adjusted. TSA has completed a 100% design review with no outstanding open items Removal of ED2 and ED4 does not trigger re-testing of ED1 and ED3. The XO1 installation does not change or impact conveyor speeds feeding the existing ISD machines, therefore no ISD though put testing is required. a. There appears to be a temporary belt conveyor parallel with column 8 in the public area. Is this conveyor powered? If yes, please clarify how it is to be powered and controlled. 38 Temporary Belt Conveyor b. What, if any, reports are required for the temporary screening machines and related temporary conveyor? a. The airport has a temporary conveyor to be used for the temporary lobby screening solution. Power for the conveyor is shown on the electrical drawings. A disconnect is used to power on the conveyor. b. No anticipated BHS reporting is necessary. TSA and Reveal will provide all reporting. 39 Will the upgrade of the CTX9000 to CTX9400 affect the existing communication and handshake between the existing BHS control system such that programming changes may be required? Morpho has indicated that the handshake and communications between BHS and the ISD remains the same. 40 001340, page 8, item H Does this requirement apply to baggage conveyor equipment? If yes, please confirm accurate as-thibuilt drawings will be provided of the existing systems in an editable format upon award. builts will be provided in.pdf section applies to all new work. Existing as- format. 41 Technical Support Based on the numerous controls changes that will be made to the existing baggage handling system, it is recommended that a comprehensive Technical Support package should be included No. Technical support post contract can be discussed within the scope of this project. Please confirm that technical support for a fixed period should at a later date. be included in bid pricing, and also the general requirements for scope. A service agreement for specified period of time a minimum of 2-3 years. 42 Relating to the Concourse C CBRA upgrade, please confirm there is sufficient space within the The current scope of work does not include any existing motor control panel(s) to accommodate the additional drives. additional panels in concourse C. 43 Should the bidder assume all data drops will be of sufficient length to be reused? No. Cable extenders can be used. 44 Please confirm the existing source code relating to the BHS upper level controls (graphical, reports, etc.) will be provided to the successful bidder upon award. All source code will be provided.

Sample Portering Calculation Source: Specification Section 001010 This is one example of how to quantify the number of Porters required to meet the project requirements. Other costs may include badging, administrative cost for scheduleing of porters. Porters can come from a variety of labor sources, but all must pass security screening and be badged. The Contractor is responsible for pricing the portering requirements. General Portering Porters are generally required for 18 hours per day for 7 days a week and can be adjusted to meet actual flight schedules. Concourse C Provide as a minimum one porter at the temporary lobby screening site to assist TSA in transitioning bags from the temporary screening node to the ticket counter for the duration of the current flight hours from 0600 to 2355 hours. Provide additional porters as required for break periods and shift changes. Anitcipated construction duration is 42 working days or 58 calendar days....duration of the current flight hours from 0600 to 2355 hours. 2355 hrs - 0600 hrs = 17 hrs 55 min therefore use 18 hrs/day 7 days/week. hrs/day days/wk hrs/wk 40 hrs/porter Say 3 days Total Portering hrs Portering rate Portering Cost 18 7 126 3.15 3 58 8.3 994.3 $30.00 $29,828.57 A1 to A2 Crossover Portering not required Rate determined by Contractor Contingency Cost, badging cost or other costs determined by Contractor A3 CBRA A minimum of one porter is needed for the duration of Delta s current flight schedule from 0515 through 2000 hours. Provide additional porters as required for break periods and shift changes Anticipated construction schedule duration is 15 working days or 21 calendar days 2000 hrs - 0515 hrs = 14 hrs 45 min Say 15 hrs/day Use flight schedule rather than general portering hrs/day days/wk hrs/wk 40 hrs/porter Say 3 days Total Portering hrs Portering rate Portering Cost 15 7 105 2.625 3 21 3.0 360.0 $30.00 $10,800.00 A2 CBRA A minimum of one porter is needed for the duration of United Airlines current flight schedule from 0500 through 1335 hours Anticipated construction schedule duration is 25 working days or 35 calendar days 1355 hrs - 0500 hrs = 8 hrs 55 min say 9 hrs/day hrs/day days/wk hrs/wk 40 hrs/porter Say 2 days Total Portering hrs Portering rate Portering Cost 9 7 63 1.575 2 35 5.0 400.0 $30.00 $12,000.00 A1 CBRA Portering not required