For NGTL to file calculation of operating condition on pull back stress analysis.

Similar documents
Trenchless Pipeline Crossings

YOUR GROUND DRILLING PARTNERS.

FE Review Mechanics of Materials

In-plane testing of precast concrete wall panels with grouted sleeve

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

GREEN THREAD Piping Systems

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX B-2 FLOODWALL PILE ANALYSES EAST WALLS

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

Numerical Modeling of Slab-On-Grade Foundations

MECHANICAL PROPERTIES PROPLEM SHEET

E APPENDIX. The following problems are intended for solution using finite element. Problems for Computer Solution E.1 CHAPTER 3

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

16. Design of Pipeline Structures.

7/17/2017 Page 1 of 5

FINITE ELEMENT ANALYSIS OF COMPOSITE REPAIRS WITH FULL-SCALE VALIDATION TESTING

A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES

GLASS FIBER-REINFORCED PLASTIC POLES FOR TRANSMISSION AND DISTRIBUTION LINES: AN EXPERIMENTAL INVESTIGATION

BEHAVIOR OF INFILL MASONRY WALLS STRENGTHENED WITH FRP MATERIALS

Thermal Expansion & Helical Buckling of Pipe-in-Pipe Flowline Systems

HORIZONTAL DIRECTIONAL DRILLING WITH DUCTILE IRON PIPE

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

Structural Design of Pergola with Airfoil Louvers

Council on Tall Buildings

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

Journal of Asian Scientific Research EVALUATION OF RECTANGULAR CONCRETE-FILLED STEEL-HOLLOW SECTION BEAM-COLUMNS

Dynamic Shear Rheometer: DSR

REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES

CHAPTER 11: PRESTRESSED CONCRETE

REINFORCING LARGE DIAMETER ELBOWS USING COMPOSITE MATERIALS SUBJECTED TO EXTREME BENDING AND INTERNAL PRESSURE LOADING

R-Group Finland Oy. RTA, RWTL and RWTS Lifting anchors Design instructions

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

Bridge articulation No. 1.04

Todd F. Shupe Associate Professor School of Renewable Natural Resources Louisiana State University AgCenter Baton Rouge, LA 70803

Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION

North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition. Dallas, Texas April 27 May 2, 2008

9. VACUUM TANK 9. VACUUM TANK

Pipe Stress Analysis Where Do I Start?

UPGRADE OF SHAFT CONVEYOR USING HIGH SPEED TRIPPER DRIVE TECHNOLOGY (CASE STUDY MATLA COAL NO. 2 MINE, SHAFT CONVEYOR) Alan Exton

Gas Transmission and Distribution Piping Systems

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

DESIGN OF WALL THICKNESS AND PREVENTION OF COLLAPSE OF SERVICEABLE LARGE DIAMETER PIPELINES. Lucksyn Avuwha Omidih and Godspower O.

St.MARTIN S ENGINEERING COLLEGE

The Behavior of Tensile Fabric Membrane Structure

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL CENTRE FZE. BEng (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016

DESIGN FOR PROGRESSIVE COLLAPSE 1

PENETRATION RESISTANCE OF HYBRID FIBRE REINFORCED CONCRETE UNDER LOW VELOCITY IMPACT LOADING

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

ANCHOR BOLTS IN CLAY MASONRY WALLS

Static Response of Reinforced Soil Retaining Walls with Modular Block Facing

Schöck Isokorb type CV

A Review of Suitability for PWHT Exemption Requirements in the Aspect of Residual Stresses and Microstructures

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Drill Pipe Combined Torsion-Tension To Yield Pipe Tubes

HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES

MECHANICAL CHARACTERIZATION OF SANDWICH STRUCTURE COMPRISED OF GLASS FIBER REINFORCED CORE: PART 1

Product Manual Release 05/17

TRENCHLESS PIPELINE REMOVAL (TPR)

REVISED PAGES IMPORTANT TERMS AND CONCEPTS REFERENCES QUESTIONS AND PROBLEMS. 166 Chapter 6 / Mechanical Properties of Metals

COMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC

Trenchless Technology

LARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

Grain Silo Strengthening South Dakota. Prepared for Vector Construction Group

Manufacturing (Bending-Unbending-Stretching) Effects on AHSS Fracture Strain

SPECIFICATION FOR REINFORCED SOIL WALL

Design and Analysis of Multilayer High Pressure Vessels and Piping Tarun Mandalapu 1 Ravi Krishnamoorthy. S 2

Lecture Retaining Wall Week 12

Numerical Analysis of a Novel Piling Framed Retaining Wall System

FE MODELING OF CFRP STRENGTHENED CONCRETE BEAM EXPOSED TO CYCLIC TEMPERATURE, HUMIDITY AND SUSTAINED LOADING

Section 3 Fusible PVC Pipe Connections

Behavior and Analysis of Horizontally Curved Composite Steel Girder Bridge System

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines

DESIGN OF WALLS FOR SHEAR

Report for Handbook on large plastic pipes, published 2015, ISBN

EFFECT OF VENEER JOINT REINFORCEMENT ON BRICK TIE EMBEDMENT

SOLID WALL PVC SEWER PIPE

1E5 Advanced design of glass structures. Martina Eliášová

Non Linear Analysis of Composite Beam Slab Junction with Shear Connectors using Ansys.16

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015

SOLID WALL PVC SEWER PIPE

INHERENT DUCTILITY OF REINFORCED CONCRETE SHEAR WALLS WITH NON-SEISMIC DETAILING

APPENDIX E HORIZONTAL DIRECTIONAL DRILL EXECUTION PLAN

Pipeline Integrity. QuestIntegrity.com CHALLENGE CONVENTION

MIDAS Training Series

Stress Distribution in Masonry Walls, Loaded in Plane, Simulated with Comsol.

Aspects of wire drawing and tube drawing

Geothermal Tunnel Linings. Principles of Geothermal Tunnel Linings

Design and Analysis of a Process Plant Piping System

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.


SEISMIC RETROFIT OF A TYPICAL REINFORCED CONCRETE BUILDING THROUGH FRP JACKETING OF EXTENDED RECTANGULAR COLUMNS

Special Reinforced Concrete Structural Walls

A Guideline for Designing ASME B31 Pressure Piping Using Lokring Fittings with Elastic Strain Preload (ESP ) Technology

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

BEHAVIOR OF REINFORCED CONCRETE BEAM WITH OPENING

New Technologies for BOP Shearing

PETREX -CNT. Pipe systems for petrol stations Technical details

3. Bond, Anchorage and Shear This chapter will discuss the following topics:

Transcription:

NOVA Gas Transmission Ltd. Exhibit No. B85 National Energy Board Hearing Order GH-001-2014 Undertaking U-10 Submitted November 25, 2014 Response to Undertaking given by Mr. Trout to Chairman Vergette at Transcript Reference Vol. 15, Paragraph 19046, with respect to calculations of operating conditions on pull back stress analysis. Undertaking: For NGTL to file calculation of operating condition on pull back stress analysis. Response: NGTL provides in the stress analysis for the Peace River horizontal directional drill. November 25, 2014 Page 1 of 1

North Montney Mainline Aitken Creek Section Document No. 20141124_HMM_334888_Peace River HDD Installation Loads and Operating Stress _REP_0109 Peace River HDD Installation Loads and Operating Stress Issue and Revision Record Rev Date Originator Checker Approver Description A 11/24/14 S. Crouse G. Duyvestyn R. Delmar Issued for NEB Submission This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authorization of Hatch Mott MacDonald being obtained. Hatch Mott MacDonald accepts no responsibility or liability for the consequence of this document being used for a purpose other than the purposes for which it was commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm their agreement to indemnify Hatch Mott MacDonald for all loss or damage resulting therefrom. Hatch Mott MacDonald accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned. To the extent that this report is based on information supplied by other parties, Hatch Mott MacDonald accepts no liability for any loss or damage suffered by the client, whether through contract or tort, stemming from any conclusions based on data supplied by parties other than Hatch Mott MacDonald and used by Hatch Mott MacDonald in preparing this report.

Peace River HDD Installation Loads and Operating Stress TABLE OF CONTENTS 1 INTRODUCTION... 2 2 HDD CALCULATIONS... 3 LIST OF TABLES: TABLE 2.1 PIPELINE PROPERTIES AND INPUT PARAMETERS FOR THE HDD INSTALLATION LOAD AND STRESS EVALUATIONS TABLE 2.2 SUMMARY OF HDD OPERATING STRESS EVALUATION TABLE 2.3 SUMMARY OF ANTICIPATED HDD PULLBACK LOADS TABLE 2.4 SUMMARY OF HDD INSTALLATION STRESS EVALUATION AT THE DESIGN BENDING RADIUS OF 1,280 METRES TABLE 2.5 - SUMMARY OF HDD INSTALLATION STRESS EVALUATION AT THE DESIGN BENDING RADIUS OF 1,050 METRES TABLE 2.6 SUMMARY OF BREAK-OVER STRESS EVALUATION TABLE 2.7 SUMMARY OF SUPPORT LOAD EVALUATION TABLE 2-8 - SUMMARY OF OVER-BEND DETAILS TABLE 2-9 - SUMMARY OF OVER-BEND STRESS EVALUATION (HDD ENTRY POINT SOUTH AT STA 50+180.31) TABLE 2-10 - SUMMARY OF OVER-BEND STRESS EVALUATION (HDD ENTRY POINT NORTH AT STA 51+794.96)

Peace River HDD Installation Loads and Operating Stress 1 INTRODUCTION Hatch Mott MacDonald (HMM) has prepared this Horizontal Directional Drilling (HDD) design report at the request of NOVA Gas Transmission Ltd. (NGTL) for their proposed crossing of the Peace River, as part of the Aitken Creek Section of the larger North Montney Mainline Project. The current diameter for the proposed pipeline is NPS 42 (1067 mm). Specifically, this report summarizes HMM s evaluation of the installation loads and operating stresses for an HDD crossing of the Peace River. 20141124_HMM_334888_ REP_0109 2

2 HDD CALCULATIONS 2.1.1 PIPE PROPERTIES Peace River HDD Installation Loads and Operating Stress The pipeline properties used for the evaluation of the Peace River HDD crossing are summarized in Table 2-1 below. Table 2-1: Pipeline properties and input parameters for the HDD installation load and stress evaluations. Evaluation Parameter Value Pipe Size NPS 42 Outer Diameter 1067 mm Wall Thickness 22.2 mm Pipe Grade 483 MPa Maximum Allowable Operating Pressure 9930 kpa Minimum Operating Temperature -5 C Maximum Operating Temperature 49 C Poisson s Ratio 0.30 Elastic Modulus 207,000 MPa Coefficient of Thermal Expansion 1.2 x 10-6 1/ o C Design Factor 0.8 Location Factor 0.625 Temperature Derating Factor 1.0 Joint Factor 1.0 2.1.2 HDD DESIGN PROCEDURE INSTALLATION LOAD AND STRESS EVALUATIONS The installation load and stress analysis process for horizontal directional drill (HDD) installations consists of the following steps: 1. Evaluate minimum allowable bending radius and confirm wall thickness and grade. 2. Evaluate operating stresses based on the identified minimum bending radii. 3. Evaluate product pipe HDD installation loads. 4. Evaluate product pipe HDD installation stresses. 5. Evaluate product pipe HDD break-over stresses. 6. Evaluate product pipe HDD over-bend stresses. 2.1.3 ULTIMATE, ALLOWABLE AND DESIGN BEND RADII Vertical curvature is inherent to all HDD installations. The need for horizontal curvature however, is dependent on the restrictions specific to a single crossing. While horizontal curvature is feasible, the scope of design and construction greatly increases in complexity when horizontal curves are required. The addition of horizontal curvature also increases the stress, and therefore the risk to the product pipe. 20141124_HMM_334888_ REP_0109 3

Peace River HDD Installation Loads and Operating Stress Steering in both planes is not a standard industry practice and can lead to complex radii and a reduction in the overall bending radius that the product pipe will be subjected to, increasing risk to the product pipe and the overall installation. For this reason, a straight alignment has been selected for the Peace River crossing eliminating risks associated with drilling a horizontal curve. The minimum ultimate bend radius is a function of the maximum allowable operating pressures, pipe diameter, wall thickness, design factor, location factor, and specified minimum yield strength. The calculation is based on determining the calculated hoop and longitudinal stresses and then determining the available magnitude of stress that the product pipe can accommodate in an alignment curve. The minimum ultimate bending radius evaluation is completed in accordance with: CSA Z662-2011 Oil and Gas Pipeline Systems ASCE Manual of Practice No. 108 Pipeline Design for Installation by Horizontal Directional Drilling. 49 CFR 192 Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards. ASME B31.8 Gas Transmission Distribution and Piping Systems ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids Using the pipe properties presented in Table 2-1, the ultimate minimum bending radius is calculated for the pipe and pressure conditions. This radius represents the lowest radius that could be drilled without overstressing the product pipe for the identified pipe properties and in-service loading. Based on the pipe properties provided in Table 2-1, the ultimate minimum bending radius is approximately 905 metres, based on a design factor of 0.8 and a location factor of 0.625, yielding a combined design factor of 0.5 (0.8 multiplied by 0.625 equaling 0.5) per CSA Z662-11. The minimum allowable bending radius is the minimum radius that the HDD contractor can drill during their pilot bore to maintain the design alignment and profile. This radius is established above the calculated ultimate minimum bending radius to ensure that the product pipe is not overstressed during the HDD installation process. Based on an ultimate minimum bending radius of 905 metres, the minimum allowable bending radius has been established at 1,050 metres. The design radius is the radius selected to develop the HDD plan and profile. This radius is greater than the minimum allowable bending radius given to the HDD contractor to complete the construction of the crossing. The design bending radius for developing the Peace River HDD profile has been established at 1,280 metres, consistent with the HDD industry standard of 1,200 times the outer diameter of the project pipe. 2.1.4 OPERATING STRESS EVALUATION Evaluation of operating loads for pipelines installed by HDD methods is generally similar to the evaluation for pipelines installed by open-cut construction methods. The main difference between the two scenarios is that the condition of elastic bending (as a result of the curved HDD alignment profile) has to be considered for the HDD installation. Elastic bending stresses occur as the product pipe takes on the final shape of the HDD bore. As a rule, the bending stresses induced are not a critical stress condition on their own, but must be considered in a combined loading condition with other stress conditions such as hoop stress and longitudinal stress. 20141124_HMM_334888_ REP_0109 4

Peace River HDD Installation Loads and Operating Stress An operating stress evaluation has been completed in compliance with the American Society of Mechanical Engineers B31.4 and B31.8 and CSA Z662-11 (Revised August 2013). The input parameters for this analysis are provided Table 2-1. The results of the evaluation are provided below in Table 2-2 and are based on the minimum allowable bending radius of 1,050 metres (based on the allowable bend radius provided to the HDD contractor). This is to account for the minimum allowable bending radius established for the HDD contractor, as noted on the HDD drawings. As observed in Table 2-2, the operating stresses are below the maximum allowable limits. Hence, the pipe properties (wall thickness and grade) are sufficient to meet the operating stresses within the HDD alignment. Table 2-2: Summary of HDD operating stress evaluation. Percent of SMYS 1 (%) Maximum Allowable Percent of SMYS 1 (%) Estimated Stress Stress Condition (MPa) Longitudinal Bending Stress 105.2 21.8 -- Hoop Stress 238.6 49.4 50 (2) Longitudinal Tensile Stress from Hoop Stress 71.6 14.8 -- Longitudinal Stress from Thermal Expansion -128.6 26.6 90 (3) Net Longitudinal Stress (Compression Side of the Curve) -162.2 33.6 90 (4) Net Longitudinal Stress (Tension Side of the Curve) 48.2 10.0 90 (4) Maximum Shear Stress 200.4 41.5 45 Combined Biaxial Stress 400.7 83.0 90 (4) Notes: 1 Specified Minimum Yield Stress 2 Limited by design factor multiplied by location factor (0.8 x 0.625 = 0.5) per CSA Z662-11 3 Limited by ASME B31.4 4 Limited by ASME B31.8 2.1.5 HDD PULLBACK LOADS A total of six (6) pull load evaluations were completed for the HDD bore profile. These calculations are based on a modified version of the installation load calculation method provided in American Society of Civil Engineer MREP 108 (2005) and the Pipeline Research Committee at the American Gas Association publication entitled Installation of Pipelines by Horizontal Directional Drilling, an Engineering Guide. The modification includes inclusion of an updated fluidic drag calculation based on observed drilling fluid properties and the anticipated bore diameter. The pull load evaluation includes assumptions for final bore diameter, soil and pipe roller friction coefficients, drilling fluid yield point and plastic viscosity, drilling fluid pumping rate, and other installation parameters such as buoyancy control measures (i.e., whether or not the pipe will be filled with water during pullback operations). In addition, the evaluation accounts for the capstan effect induced by curves in the alignment, fluidic drag, buoyancy of the pipe string within the bore, and the weight of the tail string at startup and throughout the installation process. 20141124_HMM_334888_ REP_0109 5

Peace River HDD Installation Loads and Operating Stress Six (6) installation evaluations have been completed to investigate the effects of varying mud weights and buoyancy control measures during the installation of the product pipe. The six (6) scenarios evaluated include: Case 1: Drilling Fluid Weight 10 ppg (Specific Gravity of 1.20) No buoyancy control (pipe empty of water) Case 2: Drilling Fluid Weight 10 ppg (Specific Gravity of 1.20) Full buoyancy control measures (pipe full of water) Case 3: Drilling Fluid Weight 11 ppg (Specific Gravity of 1.32) No buoyancy control (pipe empty of water) Case 4: Drilling Fluid Weight 11 ppg (Specific Gravity of 1.32) Full buoyancy control measures (pipe full of water) Case 5: Drilling Fluid Weight 12.0 ppg (Specific Gravity of 1.44) No buoyancy control (pipe empty of water) Case 6: Drilling Fluid Weight 12.0 ppg (Specific Gravity of 1.44) Full buoyancy control measures (pipe full of water) A summary of the pull load evaluation for each pull load scenario is provided in Table 2-3. The anticipated installation loads as shown in Table 2-3 are well below the ultimate allowable load of the steel product pipe of approximately 28,129 kn (6,323,621 lb), based on a tensile stress equivalent to 80 percent of the yield stress for the given wall thickness and pipe grade provided in Table 2-1. It is important to note the difference in pull loads when buoyancy control measures are implemented and water is added to the product pipe during pullback, as the estimated installation loads are much lower when buoyancy control measures are used. A start-up factor of 1.5 has been applied to the estimated pullback forces to replicate the higher installation loads observed during stoppages and recommencing of pullback operations. Table 2-3: Summary of anticipated HDD pullback loads. Buoyancy Condition Estimated Pullback Force (kn) Initial Start-Up Force (kn) Drilling Fluid Specific Gravity 1.2 (Case 1) Empty 4,217 6,325 1.2 (Case 2) Full 2,418 3,626 1.3 (Case 3) Empty 4,791 7,187 1.3 (Case 4) Full 2,220 3,330 1.4 (Case 5) Empty 5,708 8,562 1.4 (Case 6) Full 2,281 3,421 2.1.6 HDD PULLBACK INDUCED STRESSES Results of the corresponding HDD installation stresses (based on the design bending radius of 1,280 metres) are summarized in Table 2-4. 20141124_HMM_334888_ REP_0109 6

Peace River HDD Installation Loads and Operating Stress Table 2-4: Summary of HDD installation stress evaluation at the design bending radius of 1,280 metres. Stress Condition Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Maximum Tensile Stress (Percent of Allowable) 57.9 MPa (12.0%) 33.2 MPa (6.9%) 65.8 MPa (13.6%) 30.5 MPa (6.3%) 78.4 MPa (16.2%) 31.3 MPa (6.5%) Maximum Bending Stress (Percent of Allowable) 86.3 MPa (17.9%) 86.3 MPa (17.9%) 86.3 MPa (17.9%) 86.3 MPa (17.9%) 86.3 MPa (17.9%) 86.3 MPa (17.9%) Maximum Hoop Stress (Percent of Allowable) 26.8 MPa (5.6%) 26.8 MPa (5.6%) 29.4 MPa (6.1%) 29.4 MPa (6.1%) 32.1 MPa (6.7%) 32.1 MPa (6.7%) Maximum Unity Check Tensile and Bending 0.43 0.36 0.45 0.36 0.48 0.36 (must be less than 1.0) Maximum Unity Check Tensile, Bending, and Hoop (must be less than 1.0) 0.46 0.41 0.54 0.47 0.63 0.54 As observed in Table 2-4, the results of the HDD installation stress evaluation are within the allowable limits for all cases. Results of the corresponding HDD installation stresses (based on the design bending radius of 1,050 metres) are summarized in Table 2-5. These stresses are based on the same HDD alignment and installation loads as observed in Table 2-4, but with the minimum bending radius of 1,050 metres inserted in place of the 1,280 metre design radius for the stress calculations. Similarly, as observed in Table 2-5, the results of the HDD installation stress evaluation are within the allowable limits for all cases. Table 2-5: Summary of HDD installation stress evaluation at the design bending radius of 1,050 metres. Stress Condition Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Maximum Tensile Stress (Percent of Allowable) 57.9 MPa (12.0%) 33.2 MPa (6.9%) 65.8 MPa (13.6%) 30.5 MPa (6.3%) 78.4 MPa (16.2%) 31.3 MPa (6.5%) Maximum Bending Stress (Percent of Allowable) 105 MPa (21.8%) 105 MPa (21.8%) 105 MPa (21.8%) 105 MPa (21.8%) 105 MPa (21.8%) 105 MPa (21.8%) Maximum Hoop Stress (Percent of Allowable) 26.8 MPa (5.6%) 26.8 MPa (5.6%) 29.4 MPa (6.1%) 29.4 MPa (6.1%) 32.1 MPa (6.7%) 32.1 MPa (6.7%) Maximum Unity Check Tensile and Bending 0.49 0.43 0.52 0.42 0.54 0.42 (must be less than 1.0) Maximum Unity Check Tensile, Bending, and Hoop (must be less than 1.0) 0.51 0.46 0.60 0.52 0.69 0.58 2.1.7 BREAK-OVER STRESS EVALUATION Stresses are induced within the product pipe as it transitions from above ground into the completed HDD bore. This stress is commonly referred to as the break-over stress and is temporary. A break-over stress evaluation was completed to evaluate pipe supports, loads and pipe stresses while the product pipe is pulled into the HDD bore. The evaluation was performed utilizing Autopipe Version 9.6 and reflects the stresses and loads induced within the product pipe as it transitions from the staging area on the ground surface, into the air, and into the HDD bore. Input parameters include the pipe properties 20141124_HMM_334888_ REP_0109 7

Peace River HDD Installation Loads and Operating Stress provided in Table 2-1, site-specific topography, staging area constraints, and the HDD bore geometry. In addition, a support spacing of 30 m, an allowable bending radius of 550 m (based on an non-pressurized pipe configuration), and the weight of a 200-mm diameter high-density polyethylene water line installed within the product pipe for buoyancy control were incorporated into the evaluation. It is assumed that the portion of the product pipe above ground will not be filled with water (for buoyancy control). Break-over stresses are determined by deforming the product pipe into the required break-over geometry. The resultant pipe stresses are provided in Table 2-6. Table 2-6: Summary of break-over stress evaluation. Notes: Lifting Point Induced Pipe Stress (MPa) Percent of SMYS 1 (%) 1 216 44.7 2 199 41.2 3 56 11.6 4 56 11.6 5 7 1.5 6 12 2.5 7 0 0.0 8 102 21.1 9 123 25.5 10 102 21.1 1 Maximum allowable percent of SMYS is 80 percent per CSA Z662-11 Support loads associated with each lifting point, relative to a horizontal plane equal to the elevation of the HDD entry location, are provided in Table 2-7. Table 2-7: Summary of support load evaluation. Lifting Point Lifting Height (mm) Support Load (kn) Support Load (Kg) 1 3100 301 30,700 2 4900 306 31,200 3 5500 160 16,300 4 6500 158 16,100 5 8000 194 19,800 6 9700 170 17,300 7 11500 158 16,100 8 13200 211 21,500 9 14400 184 18,800 10 14900 213 21,700 20141124_HMM_334888_ REP_0109 8

2.1.8 OVER-BEND STRESS EVALUATION Peace River HDD Installation Loads and Operating Stress The connection/transition/tie-in between the mainline pipeline and the HDD installation will experience stresses associated with the operation of the pipeline. Referred to as the over-bend connection, this transition piece must be designed for various operational stresses and thermal effects in accordance with CSA Z662-11. The over-bend stress evaluation was completed to evaluate the stresses induced within the transition/connection/tie-in at the start and end locations of the HDD installations. The evaluation was performed utilizing Autopipe Version 9.6. Input parameters include the pipe properties provided in Table 2-1, mainline pipe properties, mainline and HDD pipeline alignments, and soil data provided by BGC (spreadsheet entitled NMML Soil Properties at Horizontal Bend Locations dated 1/27/2014). A summary of the over-bend details used in this evaluation is summarized in Table 2-8. Table 2-8: Summary of over-bend details. Soil Type at Bend Location Bend Angle (degrees) Bend Wall Thickness (mm) Bend Material Grade (MPa) Bend Stationing Bend Radius Bend Orientation 50+288 3D Horizontal Silty Sand 45.0 23.0 483 50+297 3D Horizontal Silty Sand 45.0 23.0 483 51+910 3D Horizontal Silty Sand 45.0 23.0 483 51+918 3D Horizontal Silty Sand 45.0 23.0 483 Results of the over-bend stress evaluation are provided in Table 2-9 and Table 2-10 for the east and west HDD transition locations, respectively. Table 2-9: Summary of over-bend stress evaluation (HDD Entry Point South at STA 50+180.31). Estimated Value Percent of SMYS 1 (%) Maximum Allowable 1 Stress Condition Thermal Stresses (Expansion Case) 139.63 MPa 28.9 % 72 % of SMYS Hoop Stress (Maximum Pressure Drop) 238.59 MPa 49.4 % 50 % of SMYS Pressure and Gravity Stresses (Sustained Case) 132.41 MPa 27.4 % 80 % of SMYS Hoop and Longitudinal Stresses (Equivalent Tensile 1 Case 238.59 MPa 49.4 % 90 % of SMYS Combined Stresses (Tresca / Octahedral Case) 287.77 MPa 59.6 % 100 % of SMYS Total Stress / Allowable Stress (Stress Ratio) 0.596 -- 1.0 Vertical Deflection 15.44 mm -- 150 mm Notes: 1 Allowable values as established per CSA Z662-11 20141124_HMM_334888_ REP_0109 9

Peace River HDD Installation Loads and Operating Stress Table 2-10: Summary of over-bend stress evaluation (HDD Entry Point North at STA 51+794.96). Estimated Value Percent of SMYS 1 (%) Maximum Allowable 1 Stress Condition Thermal Stresses (Expansion Case) 169.89 MPa 35.2 % 72 % of SMYS Hoop Stress (Maximum Pressure Drop) 238.59 MPa 49.4 % 50 % of SMYS Pressure and Gravity Stresses (Sustained Case) 174.71 MPa 36.2 % 80 % of SMYS Hoop and Longitudinal Stresses (Equivalent Tensile 1 Case 238.59 MPa 49.4 % 90 % of SMYS Combined Stresses (Tresca / Octahedral Case) 354.32 MPa 73.4 % 100 % of SMYS Total Stress / Allowable Stress (Stress Ratio) 0.734 -- 1.0 Vertical Deflection 45.07 mm -- 150 mm Notes: 1 Allowable values as established per CSA Z662-11 20141124_HMM_334888_ REP_0109 10