Capital Projects Update

Similar documents
Capital Projects Update

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

BOND CONSTRUCTION UPDATE

Division 09 FINISHES TABLE OF CONTENTS

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Cheldelin Middle School

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

Application for Commercial Plan Review and Building Permit. Address:

LOVEJOY Independent School District

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Yardmen Arena Expansion & Renovation Project Update

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

Program Update. Chino Health Science Parking Lot

Facility Improvements

Building Expansion Project Description. Rutgers The State University of New Jersey

2016 FEBRUARY. all of which was built by 60 individuals, from 18 churches, from 8 states.

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER

CODE COMPLIANCE PLAN REVIEW PROCEDURES

LEWIS ELEMENTARY SCHOOL

Completed projects. Projects in progress. Program developments

Section 4 - Design and Construction Overview

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

STRUCTURAL ASSESSMENT OBSERVATION REPORT

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

Structural Inspection

Madison School District. Strategic Five-Year Facility Maintenance Plan

The Inspection Process. Waxhaw N.C.

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

SECTION ALTERNATES

WILKINSON ELEMENTARY SCHOOL

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

M-DCPS DESIGN CRITERIA Table of Contents

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved.

CHARTRES COURT Washington Avenue Houston, Texas ChartresCourtHouston.com CHARTRES COURT LLC

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene

School Without Walls

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

PLUMMER ELEMENTARY SCHOOL

CENTENNIAL SCHOOL DISTRICT

CAREERS. in the Construction TRADES

Property Condition Assessment

Facility Assessment Report, Montgomery Independent School District

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

CARL E. SCHLUTER ELEMENTARY SCHOOL

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

St. Germain Facility Study

Perimeter Site Improvements

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

BUREAU Joe Iuviene, AIA January 20, 2017

MADISON HIGH SCHOOL // Executive Summary

Crockett Elementary School Renovations

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

DSA Inspectors. Arcadia USD. Arcadia HS Campus Enrichment. Inspection Report Apr 2014

Excellence in. Modular Building Design

COOLIDGE SENIOR HIGH SCHOOL

Schedule of Values Cruise Terminal 2 Expansion

A/E Design Deliverable Checklist

1 AND 2 FAMILY DWELLING REQUIREMENTS

STRUCTURAL CONDITION ASSESSMENT

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Home Building Planner

Stevens & Associates, Inc. Building Construction Projects. Fact Sheets

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT

LECKIE ELEMENTARY SCHOOL

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

Davis Frame Co., Inc. Construction Budget Considerations

The Homeowner s Building Application Checklist for Constructing a Residential Addition

BOWIE LEARNING CENTER

Building Inspection Report

SUBSTANTIAL IMPROVEMENT

Construction Update. May 2016

CATAMARAN TOWER - 1 Seef Area Plot 19, 20

Commercial Remodel Permit

ORANGE VISTA HIGH SCHOOL PHASE I

BUILDING CODES & DESIGN CRITERIA

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013

CONTRACT DOCUMENTS REVIEW PACKAGE CHECKLIST

Portsmouth Middle School Additional Funding Request

ORANGE VISTA HIGH SCHOOL PHASE I

Section 5 - Project Logistics

CONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.

A/E Design Deliverable Checklist

Mount Vernon Elementary School Grades PK 5

THE CONSTRUCTION SUPERVISOR

BUILDING FOR OUR FUTURE

Transcription:

Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront installation at the Commons and circulation bridges is underway and is a major step towards full enclosure of all building areas. Classroom cabinets have been set in the north and center wings. Installation has begun in the south wing. Science lab cabinet installation began the first week of March. Ceiling grid, light fixtures and ceiling fan installation is moving forward. Installation of sheetrock and finish work is nearing completion in the main and upper auxiliary gyms. Commons area slab pours are complete. Installation of plumbing rough-in, HVAC piping and ductwork, and electrical rough-in continues in the areas east of the classroom wings. The north classroom wing is nearly ready for the installation of light fixtures, final trim and floor finishes. Second floor Commons view to the southeast. Capital Projects Department Main gym and upper auxiliary gym. Steve Crawford Director Mike Archer Debbie Massaro Tom Mullins Royce Nourigat Ladd Stejskal Phone: 425-837-7040 Fax: 425-837-7041

Page 2 Issaquah High School Reconstruction South courtyard. North courtyard. South wing science lab. Center wing science lab. South wing classroom. Commons and view towards the football field.

March 2010 Page 3 Issaquah High School Reconstruction Library. Weight training room. May Valley Service Center Pod 5 Replacement The new buildings are nearly complete. Fire sprinkler risers remain to be completed. Site and paving work has been delayed by wet weather but is expected to be complete by the end of March New Buildings F & E. Interior Building E. North side, upper level Building F. Enlarged and lined detention pond.

Page 4 Skyline High School Expansion and Alteration Some new classrooms, the expanded Commons, administration and counseling areas were occupied when school started following winter break. The new gym is nearing completion and should be ready for school use in mid-march. Move-in of the new weight room and training rooms will begin 3/4/10. Concrete walkways at the entry plaza have been poured. Curbs have been poured at the new parking lot west of the gym with fine grading for paving set to follow completion of the sidewalks. Locker rooms have been primed and locker installation is underway. Sheetrock of the new art room is approximately 50% complete. Framing and rough-in at the Black Box Theater is complete with sheetrock installation underway. New gym. Weight training room. Corridor between new gym and weight training room. Plaza at entrance to new gym. New parking lot west of the gym.

March 2010 Page 5 Creekside Elementary School - Home of the Otters! The remaining structural steel beams and bow trusses have been set. This will allow completion of the roof deck and roofing. Installation of beams and bow trusses at the covered play areas will occur at a later date. Exterior masonry is complete. Siding installation continues. Window manufacturing delays required the contractor to cover openings with poly sheeting so temporary heat could be started to continue progress on sheetrock installation and finishing. Windows started to arrive on-site the beginning of March. Rough plumbing is complete. HVAC ductwork and equipment installation is moving forward as roofing is completed. Sheetrock installation is complete in classroom areas with finish work well underway. Painting and vinyl wall-covering in classroom areas will begin the first week of March. Classroom cabinetry mock-up is completed and full installation will start in two weeks. Above right: View of exposed truss and roof structure at second floor, above Library. View of gym and Commons with roof truss. View of main entry from parking area; admin area is to the left. Above: View of 2-story classroom wing facing the paved playground. At right: View of 2nd floor classroom wing clerestory corridor.

Page 6 Maywood Middle School The permit pre-application package was submitted to King County DDES for review and comment. Comments were distributed and discussed 3/4/10. King County is taking a unique interpretation of the code section related to gymnasium construction and use that could increase construction costs or reduce the size of the proposed gym. Additional work is required to review options which could include submitting a code interpretation request to the International Building Code Interpretation Committee. While the existing site drainage and infiltration has worked perfectly since the school opened in 1969, it does not meet current code calculation requirements. Additional work is required to refine options and achieve a reasonable solution. Permit submittal documents will be completed as soon as possible following the comments and review. Resolving questions and uncertainties tends to help speed-up the permitting process. Liberty High School Schematic design work continues to develop a site/building master plan. The team continues to review design options to address the current scope of work and long term campus needs. The master plan will address longterm future needs so the current project will not inhibit or limit future options.