CTA Capital Construction Update August 8, 2007

Similar documents
Construction Project Briefing

Construction Project Briefing

Construction Project Briefing. April 14, 2010

Construction Project Briefing. December 9, 2009

Construction Project Briefing. May 9, 2018

Chicago Transit Authority. Construction Reorganization

Construction Project Briefing. March 9, 2016

Construction Project Briefing. June 14, 2017

Construction Project Briefing. October 10, 2018

Construction Project Briefing. December 14, 2016

Construction Project Briefing. July 11, 2018

Construction Project Briefing. November 14, 2018

Construction Project Briefing. April 20, 2015

Construction Project Briefing. September 9, 2015

Construction Project Briefing. November 16, 2016

Construction Project Briefing. November 9, 2011

Second Avenue Subway

Construction Project Briefing. April 13, 2012

APPENDIX 1 PROJECT REQUIREMENTS

Construction Project Briefing. November 14, 2012

SYSTEM-WIDE RAIL CAPACITY STUDY

Construction Project Briefing. August 8, 2012

Construction Project Briefing. November 19, 2014

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study

Construction Project Briefing. September 11, 2013

Construction Project Briefing. January 16, 2015

Construction Project Briefing. January 9, 2019

Construction Project Briefing. April 10, 2019

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

John A. Roebling Bridge Rehabilitation History

Second Avenue Subway

CTA Blue Line Forest Park Branch Feasibility/Vision Study Village of Forest Park Board of Directors. Tuesday, October 13, 2015

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017

I-91 Viaduct Public Information Briefing

MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, MTA Capital Construction 0

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

I-91 Viaduct Public Information Briefing

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager

APPENDIX 1 PROJECT REQUIREMENTS

LEAD PAINT ABATEMENT

John A. Roebling Bridge Rehabilitation History

Eglinton Crosstown LRT Construction Liaison Committee

RPM Phase One: Lawrence to Bryn Mawr Modernization

COMMUNITY BOARD EIGHT

REHABILITATION PACKAGE 4-a

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Zinc Rich Paint in a Pigeon Rich Environment

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

COMMISSION ON CHICAGO LANDMARKS NOTICE OF A REGULAR MEETING

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Dulles Corridor Metrorail Project

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

TABLE OF CONTENTS Public Safety Building

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 06/04/2017 to 06/10/2017

MINUTES OF THE MEETING COMMISSION ON CHICAGO LANDMARKS March 5, 2015

Dulles Corridor Metrorail Project

VPL-3300B Commercial Vertical Platform Lift Technical Specifications

Administration Building Needs Assessment

DESIGN & CONSTRUCTION GUIDELINES

L Project Update. New Design Recommendations Overall Project Update. January 15, 2019

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Description of Phase 2 Modified Design

Red and Purple Modernization

CITY OF CHICAGO PEDWAY

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 04/09/2017 to 04/15/2017

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows:

ADDENDUM 2 - JULY 14, 2015

3.6 Construction Methods

SECTION 11 Architectural and Nonstructural Elements Field Investigation

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

Jeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C

Revision 1 RAM ELEVATORS. Elevator Electrical Planning Guide. RAM Manufacturing Ltd

Division 16 Sections for electrical service for elevators to and including disconnect and fused switches at machine room.

PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant

ELVORON LU/LA ELEVATOR

Piping system (steam, hot water, chilled water system) including pipe and duct insulation needs replacement.

Engineering & Construction -- Transit Status Report. Significant Issues

Millennium Line Broadway Extension Project. Cost Report

EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN. Category #1: Work that must be done to cure dangerous and hazardous conditions

NEW MIDDLE SCHOOL PROJECT

SECTION The specification section is organized by placing information in three standard parts:

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 03/05/2017 to 03/11/2017

Building Excellence IV Capital Levy Projects Under Construction

Conceptual Design Report

Vesey Street Stair Remnant

B. Sections and all references contained therein form a part of this Section of the Specifications.

Specification for MRL Passenger Elevators

VPL-3300B Commercial Vertical Platform Lift Technical Specifications rev: (5) ILS-01100

Building Architecture

Alterations, disproportionality, and the 20% rule

Stairpans Stair Treads Landing Pans Carrier Angles Nosings Infill Panels U-Edging Hems

DESIGN OF ROAD OVERBRIDGES

Resources: Industrial Corridors. 20 Chicago Sustainable Industries

Transcription:

Block 37 Signals Project Brown Line Howard CTA Capital Construction Update August 8, 2007 1

Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block 37 Tunnel Connections Project Dearborn/Congress/Kennedy/Block 37 - Train Control System and Traction Power System Upgrades and Improvements Loop Signals Project 2

Howard Station Reconstruction Project Summary BUDGET Total CTA budget: $87 million SCHEDULE Contractor: McHugh Construction NTP: February 27, 2006 Project Completion: Spring 2009 PROJECT GOALS Key station to be made accessible in compliance with the Americans with Disabilities Act Accessibility Guidelines by July 26, 2010 Reconstruct Howard station, Rail Operations and Facilities Maintenance facilities Infrastructure upgrades will include newly-installed precast concrete platforms, viaduct repairs, track work, new elevators, and escalators 3

Project Activities Howard Station Reconstruction Continued platform and canopy construction Continued repairing underside of deck and piers for Howard Street viaduct Continued installing stairs J and K in the north tenant space Continued erecting building steel columns Three Month Look Ahead Continue repairing underside of deck and piers and begin installation of conduit at Howard Street viaduct Continue and complete welding and installation of canopy support steel and decking Resume and complete removal and replacement of remaining southbound and northbound platform Begin construction of the electrical switchgear room Begin renovation of columns M and N inside adjacent retail storefront Begin installation of escalators Continue work in the north tenant space, including installation of stairs J and K Complete steel installation 4

Brown Line Capacity Expansion Project Project Summary BUDGET Total project budget: $529.9 million SCHEDULE Project Completion: December 31, 2009 PROJECT GOALS Extend platforms to allow 8-car operations Make stations ADA compliant Add elevators to 13 stations Rehabilitate 18 stations Restore 8 historic stations Upgrade signal, communications and power delivery system 5

Brown Line Capacity Expansion Project Project Activities Continued concrete pours at Belmont for the new northbound track. Continued concrete pour caps, struts and columns for tracks 2 and 3 at Fullerton station Completed platform canopy abatement at Diversey. Continue replacement of elevated structure foundations at Southport and Diversey Installed new stairs for Superior Street entrance and exit at Chicago Station. Continued excavation for elevator, stairs and platform foundations at Chicago Continued installation of metal panels storefront at Superior auxiliary entrance at Chicago Station Opened new temporary station house at Armitage on July 23, 2007 Completed installation of the new platform decking and structural steel at the sound end of Armitage Station Continued installation of the elevator towers and elevator at Sedgwick. New stairwell was also installed at Sedgwick Continued masonry installation at Montrose and Addison station houses Completed platform steel structure at Montrose and Addison 6

Brown Line Capacity Expansion Project Three Month Look Ahead Complete and place in service the new track 4 and northbound platform at Belmont. Begin demolition of track 3 Complete columns for tracks 2 and 3 and begins structural steel installation at Fullerton Shift main entrance at Chicago Avenue to the temporary station house located on Superior Street Install second elevator tower at Armitage. Renovate existing historic station house Complete installation of new station house masonry walls at Montrose and Addison and begin platform decking and railing installation Install elevator equipment at Montrose and Addison Continue bent foundation work at Southport and begin platform steel erection and pouring station house foundations at Southport Continue foundation work and platform demolition work at Diversey Complete elevator installation at Sedgwick 7

Block 37 Tunnel Connections Project Project Summary BUDGET Total project budget: $213.3 million SCHEDULE Project completion: September 2008 PROJECT GOALS Kiewit-Reyes to construct connecting tunnels, linking the existing CTA Dearborn and State Street subway tunnels to a new transit station to be constructed within the substructure of the Block 37 Development by Joseph Freed & Associates Install new track in the connecting tunnels and transit station. Station will be designed to eventually function as a downtown terminal for express trains to O Hare and Midway Replace 4,196 existing wood half-ties in the Dearborn Subway and 12,500 existing wood half-ties in the State Street subway with new cast-in-place concrete half ties and rail fasteners 8

Block 37 Tunnel Connections Project Project Activities Project Activities Kiewit-Reyes is relocating utilities in conflict with tunnel connections locations. Began slurry wall installation at the intersection of State and Washington Streets Three Month Look Ahead Protect existing utilities that must remain within the limits of the tunnel connections excavations Construct slurry wall at the intersection of State/Washington and Dearborn/Randolph Streets Install steel beams and deck plate to support vehicular traffic at the intersections of State/Washington and Dearborn/Randolph prior to starting excavation Continue to replace existing wood half-ties and rail fasteners in the Blue Line and Red Line subway tunnels at identified locations Obtain city approval to close one additional traffic lane on Washington, Dearborn and Randolph Streets 9

Dearborn/Congress/Kennedy/Block 37 - Train Control System and Traction Power System Upgrades and Improvements Project Summary BUDGET $251 million SCHEDULE Contractor: Aldridge-Mass Joint Venture (AMJV) Construction NTP: December 1, 2005 Project completion: Summer 2009 PROJECT GOALS Replace approximately 20 miles of the existing train control systems on the Blue Line that are between 35 and 54 years old Install new interlockings and train controls for Block 37 Installation of new fiber communication backbone with copper backup on the Congress Line and in the Dearborn Subway Traction Power upgrades in the State and Dearborn Subways 10

Dearborn/Congress/Kennedy/Block 37 - Train Control System and Traction Power System Upgrades and Improvements Project Activities Continued the installation of local hand holes, conduit and signal foundations on the Congress and O Hare Lines Continued the installation of communication cable, signal cable and traction power cable in the Dearborn Subway New cab signals were put in service on the Congress Line between the Pulaski interlocking and the east end of Forest Park Station Continued subway lighting fixture replacement in the Dearborn Subway Continued wiring Kedzie interlocking for the cutover and continued underground work at Western interlocking Continued pocket demolition at LaSalle interlocking for the relay house structural steel installation Installed the Forest Park relay house 11

Dearborn/Congress/Kennedy/Block 37 - Train Control System and Traction Power System Upgrades and Improvements Three Month Look Ahead Continue installation of local hand holes, conduit and signal foundations on the Congress Branch and O Hare Branch Continue installation of traction power cable in the State Street and Dearborn Subways Continue replacing the DC circuit breakers with disconnect switches in the State Street and Dearborn Subways Continue installation of signal cable in the Dearborn Subway Install the new relay house at Jefferson Park Continue lighting installation in the Dearborn Subway Complete the Kedzie relay house cutover and continue underground work for the relay house at Forest Park Yard and at Western interlocking Continue pocket demolition for the LaSalle relay house installation Install polymer flooring and paint the subway signal rooms 12

Loop Signals Project PROJECT BUDGET $78.8 million SCHEDULE Contractor: Divane Brothers Electric Company Construction NTP: February 21, 2007 Project completion: Summer 2009 PROJECT GOALS Provide new train control system for the Loop elevated structure, replacing a system that is more than 30 years old. The new signal system will help to improve reliability of CTA rail service by regulating train movement, speed and intervals at these junctions. Construct new control tower at Lake and Wells to replace the current Tower 18, and new interlockings at Towers 18 and 12. 13

Loop Signals Project Project Activities Divane Brothers has submitted their construction schedule, safety and quality plans Continued work on the signal block design Removed timber decking and structural steel at the old Randolph west platform Set up staging area on Van Buren for Tower 12 south platform demolition work Three Month Look Ahead Approve contractor s construction schedule Approve contractor s safety and quality plans Install containment, lead abate, prime and paint the structural steel in the areas around Towers 12 and 18 Hang brackets and pipes at the passenger stations in the Loop Begin raceway work in the Dearborn Subway 14

Signals Block 37 Signals Project Brown Line Howard CTA Capital Construction Update August 8, 2007 15