1 ITS Project Management Framework This document provides an overview of the Project Management Framework for University of Maine System (UMS) Information Technology projects. The framework provides a standardized method to identify, classify, document and manage IT projects. It is designed to scale project management to the project s degree of compleity and risk, ensuring all projects receive just the right amount of project management. Idea/ As new ideas for technology projects are submitted to the ITS Project Management Office for consideration, they are classified using the Compleity and Risk Assessment model which scores factors to determine compleity and risk. A Classification matri is then used to determine the idea s Classification Level. This process ensures ideas are reviewed, prioritized, and then implemented in a standardized and consistent manner. Based on an idea s classification level, different combinations of reviewers, activities and outputs will be involved starting with the project review/approval process through task or project completion. The matri scores factors that measure an idea s degree of compleity and risk. The factors used to determine an idea s degree of compleity are: Clarity of scope Estimated duration Estimated resources Estimated cost The factors used to determine an idea s degree of risk are: Number of systems involved Number of customers affected Team eperience with technology Nature of data Project deadline There are three Classification Levels: Level 1, Level 2, and Level 3. Level 3: indicates high degree of compleity and risk. Requires complete review through project governance process and detailed analysis and documentation of procedures. Level 2: Indicates less compleity with medium-to-low risk Level 1: Indicates low-level compleity and risk Level 0: Indicates very low-level compleity and risk. Will not be added to Project Portfolio. ITS Idea Classification Overview Page 1 of 6 April 8, 2013
2 Project Review & Approval Process As Classification Level increases, so does the epected internal levels of project approval. Review & Approval Matri Classification Level Department Head/Supervisor Campus IT Director SSSC CIO IT SMC SSAC 0 Approve Approve Approve 1 Approve Approve Approve Consult Consult 2 Approve Approve Consult Inform 3 Approve Approve Approve Approve Project Life Cycle Activities and s Every project progresses through a lifecycle of five phases where the work of the project is defined, planned, developed or eecuted, and finally completed. Each phase is a manageable piece of work with at least one clear deliverable or output. The activities required for each phase and the number of outputs varies depending on the project s classification level. For eample, a project classified as level 1 will require fewer phase outputs than a project classified as level 3. Phase One > IDEA The idea phase is when an idea for a project is proposed, classified and approved. See the Project Approval Matri for. Information about approved projects is regularly updated and available for viewing from the ITS Project Management website at: Idea Phase Requirements 1. Submit Project Idea Form Idea Form 2. Classify Idea/ Level 3. Submit PIF for Review, Approval and Prioritization PIF 3. * Submit Business Case for Review, Approval and Business Case Prioritization *Determined by University of Maine System Business Case Process for Information Technology Projects APL. ITS Idea Classification Overview Page 2 of 6 April 8, 2013
3 Phase Two > INITIATING The Initiating phase is when the project sponsor proceeds to fully describe the project scope and prepare the project charter. The major deliverable of the phase is the project charter, which (1) identifies the stakeholders, (2) defines the project timeframe, (3) describes the rationale for the project and (4) establishes measures of success. The phase concludes when the sponsor signs off on the charter, signaling that the project manager may begin the detailed planning work required in the net phase. Initiating Phase Requirements 1. Secure Sponsor 2. Assign Project Manager 3. Develop, Approve Project Abbreviated Project Charter Charter Project Charter 4. Data Security Assessment? 5. *Develop, Release, Review, Select RFP RFP **Vendor Contract **Procure software/hardware *If required by University of Maine System Purchasing Procedures APL. **Where applicable Phase Three > PLANNING The Planning phase builds on information captured in the Initiating phase and is traditionally considered the most important. It is imperative that project teams do not minimize or overlook planning activities and, as a result, prematurely begin development activities. A well-developed and holistic project plan helps ensure that the project is successfully completed on time and on cost with limited surprises and deviations from the originating charter. The project plan must consist of the schedule and resources for the project, budget requirements, performance measures, and clear actions for managing change, risk, and communications. The phase concludes with a sponsor-approved project plan. Planning Phase Requirements ITS Idea Classification Overview Page 3 of 6 April 8, 2013
4 1. Conduct Planning Kick-off Meeting 2. Plan Schedule & Resources WBS Project Schedule Resource Plan Budget Plan 3. * Develop Supplemental Project Performance Plan Plans Risk Management Plan Change & Configuration Management Plan Procurement Plan Communications Plan Training Plan Testing Plan Security Management Plan Quality Management Plan 4. Reporting Requirements Sponsor Level 5. Compile Project Plan Summary Project Plan Project Plan 6. Approve Project Plan Sponsor Level *Required supplemental plans to be determined by project manager. ITS Idea Classification Overview Page 4 of 6 April 8, 2013
5 Phase Four > EXECUTING & CONTROLLING With an approved project plan, a project can move into the Eecuting and Controlling phase. This phase is where the project team completes the tasks outlined on the project schedule and develops the project deliverable(s). To track the work, the team delivers status reports, monitors and reports on issues and risks, creates change requests, conducts procurement activities and updates project planning documents when necessary. The Eecuting and Controlling phase concludes with a completed project deliverable that is accepted by the users and the sponsor. Eecuting & Controlling Phase Requirements 1. Conduct Kick-off Meeting 2. Eecute Project Tasks 3. Project Communications Status Report Management Meeting Agenda Meeting Minutes 4. * Manage Procurement Procurement Documents 5.Manage Data Security Security Assessment Log 6. Track/Manage Project Issues, Risks Issue and Risk Logs 7. Conduct Project Change Change Control Request Management Change Request Log 8. Reporting Requirements Sponsor Level 9. Accept Project User Acceptance Testing CISO Acceptance Sponsor Acceptance *To be determined by project team. Phase Five > CLOSING ITS Idea Classification Overview Page 5 of 6 April 8, 2013
6 The Closing phase is necessary in order to complete the project life cycle. Conducting the activities of the Closing phase is vital to continuous improvement efforts and successful transition of the project deliverable to operations. After achieving acceptance of the deliverable, the project team documents lessons learned and archives project documentation for future use. The project manager transfers the project deliverable to operations and support staff, who will maintain it as an operational activity. Finally, the project team celebrates and disbands. Closing Phase Requirements Name 1. Conduct Closeout Activities 2. Create Closeout Documentation Lessons Learned Project Closeout Report 3. Archive Project Artifacts 4. Reporting Level Sponsor Level 5. Transition to Operations Staff ITS Idea Classification Overview Page 6 of 6 April 8, 2013
ITS PROJECT MANAGEMENT FRAMEWORK
ITS PROJECT MANAGEMENT FRAMEWORK This document provides an overview of the Project Management Framework for University of Maine System (UMS) Information Technology projects. The framework provides a standardized
More informationProject Management Overview 4/17/2013 1
Project Management Overview 4/17/2013 1 Without Project Management 4/17/2013 2 Without Project Management 4/17/2013 3 What is a Project? A temporary and one-time endeavor undertaken to create a unique
More informationProject Origination: Item Description (Origination) Comments (or reasons for NOT completing)
Project Origination: (Origination) Develop Project Proposal: 24 Formulate business need/problem and 24 anticipated benefits to all parties Review project s fit with organization s mission 24 Identify project
More informationPMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions
PMP PMI Project Management Professional Processexam.com Exam Summary Syllabus Questions Table of Contents Keys to success in PMP Exam on PMI Project Management Professional... 2 PMI PMP Certification Details:...
More informationUnit 8 Project Implementation and Closure
UNIT OVERVIEW Description of the Unit In this unit, you will learn how to execute the project plan, and upon completion, close out the project. You will learn how to develop a role-responsibility matrix,
More informationTenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
More informationNYSITS. Overview of Project Management
NYSITS Overview of Management SMART objectives SPECIFIC MEASURABLE ACHIEVABLE REALISTIC TIME-SPECIFIC Initiation WBS Network Diagram Gantt Chart Kick-off Meeting Introduction Objectives Planning Risks
More informationTable of Contents. Introduction xxv. Assessment Test xxxvi. Chapter 1 What Is a Project? 1. Is It a Project? 2. Projects versus Operations 3
Table of Contents Introduction xxv Assessment Test xxxvi Chapter 1 What Is a Project? 1 Is It a Project? 2 Projects versus Operations 3 Stakeholders 5 Project Characteristics 7 What Is Project Management?
More informationPROCESS TRAINING. DIR PM Lite 2.0 Process Training v2.0 1
PROCESS TRAINING 1 PM Lite (Project Management Lite) is a project management process made up of tools, templates, and best practices that empowers its users to be more efficient and effective in project
More informationIntegrated Methodology Deliverable Descriptions
Integrated Methodology Deliverable Descriptions Copyright 2013, QAIassist C2013 This publication may not be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic,
More informationProject Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam
Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam Slide 1 Application & Exam Types of Questions PM Basics Ten Knowledge Areas Professional Responsibility Practice Exams Slide
More informationVirtualized Educational Lab Setup Project Plan and Supporting Project Documentation
Dakota State University Beadle Scholar Masters Theses & Doctoral Dissertations Spring 4-2013 Virtualized Educational Lab Setup Project Plan and Supporting Project Documentation Aaron Napierala Dakota State
More informationProject Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline April 2015 Published by: Project Management
More informationPMP PMBOK 5 th Edition Course Agenda
PMP PMBOK 5 th Edition Course Agenda 1. Introduction to PMP Course Certification What are PMI and PMP Application Requirements for the PMP Exam Guidelines to Fill Up the PMP Application About the PMP Exam
More informationTitle: Project Director Location: Tallahassee, FL Clearance: none required
Title: Project Director Location: Tallahassee, FL Clearance: none required Position Overview: The Project Director (PD) shall define, establish, and direct the planning and operations of the Project Management
More informationProject Management Professional (PMP)
Project Management Professional (PMP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published
More informationGuidance on project management
BSI Standards Publication NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW raising standards worldwide Guidance on project management BRITISH STANDARD National foreword This British
More informationProgram Management Professional (PgMP)
Program Management Professional (PgMP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published
More informationIs this a project? Do I really have to plan?
Project Weavers Successful Projects Don't Happen by Chance. 53 rd Annual WSHMMA Conference Matthew J. Weaver, PMP, CSM, ITIL President/CEO Project Weavers, LLC April 12, 2017 The content of this presentation
More informationPART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)
PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes
More informationTHE STANDARD FOR PROGRAM MANAGEMENT
THE STANDARD FOR PROGRAM MANAGEMENT COURSE STRUCTURE INTRODUCTION Module 1 PROGRAM MANAGEMENT PERFORMANCE DOMAINS Module 2 PROGRAM STRATEGY ALIGNMENT Module 3 PROGRAM BENEFITS MANAGEMENT Module 4 COURSE
More informationProject Management Academy
Project Management Academy Duration: 4 Days PDU Credits: 28 (Category A) This 4-day course provides a solid understanding and extensive hands-on experience in the tools and techniques of project management.
More informationColorado Family Support Council Project Management Tools and Techniques. Joe Mamlin, PMP. June 2, 2014
Colorado Family Support Council Project Management Tools and Techniques Joe Mamlin, PMP June 2, 2014 Presentation Agenda Defining a Project Organizing by Process Groups The Role of the Project Manager
More informationInformation Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
More informationPMI Scheduling Professional (PMI-SP)
PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management
More informationAbbreviations Foreword Author s Note. PART I Key Principles, Processes and Methodologies 1. 1 Introduction to Project Management Techniques 3
Contents Abbreviations Foreword Author s Note PART I Key Principles, Processes and Methodologies 1 1 Introduction to Project Management Techniques 3 1. What is a Project? 5 2. Types of Projects 6 3. What
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationProject Stakeholders Management. Unit 13
Project Stakeholders Management Unit 13 Project Communication Management Project Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact
More informationPMP Exam Prep Coaching Program
PMP Exam Prep Coaching Program 1 Charter Direct and Manage Work Monitor and Control Work Perform Integrated Change Control Close or Phase 2 Vinai Prakash, PMCHAMP.COM 1 Defines how the project is executed,
More informationIntroduction to Project Management
Introduction to Project Management University Business Institute Amir Dabirian Vice President for Information Technology/CIO March 21 st, 2012 2 The Man Month Men and months are interchangeable commodities
More informationMethods of IT Project Management
Methods of IT Project Management Second Edition by Jeffrey L. Brewer, PMP and Kevin C. Dittman Purdue University Press West Lafayette, Indiana CONTENTS About the Authors v Preface xix PART 1 Project Management
More informationProject Management Manual Prepared by: Project Support Office, Major Projects Department
Project Management Manual Prepared by: Project Support Office, Major Projects Department Version: 2015 Project Support Office Project Management Manual Version: November 2015 This manual is a living document
More informationProject Execution Plan For
Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended
More informationPROGRAMME MANAGER Position Description
Date: December 2018 Job Title : Programme Manager Term : 12 Months Fied Term Department : Strategic Capital Programme Location : Primarily based at North Shore Hospital campus and other Waitemata DHB facilities
More informationProject Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition
Project Management Process Groups PMP Study Group Based on the PMBOK Guide 4 th Edition Introduction PM Process Groups In order for a project to be successful, the project team must: Select appropriate
More informationA Collaborative Approach to Supporting Information System Migration Projects
A Collaborative Approach to Supporting Information System Migration Projects Marietta (Beth) Cox, CDC Mary Beth Kurilo, AIRA Marcey Propp, HLN Consulting Sara Sanford, PHII Learning Objectives Participants
More informationProject Management Body of Knowledge Chapter 3 Project Processes
Project Management Body of Knowledge Chapter 3 Project Processes PMP Exam Prep PMBOK Chapter 1 - Introduction Chapter 2 - Organizational Influences & Life Cycles Chapter 3 - Project Processes Chapter 3
More informationProject Management Professional (PMP) Exam Prep Course 1 - Application and the PMP Exam
Project Management Professional (PMP) Exam Prep Course 1 - Application and the PMP Exam Slide 1 Course Structure Application & Exam Types of Questions PM Basics Ten Knowledge Areas Professional Responsibility
More information5 DIMENSIONS OF CHANGE MANAGEMENT AND PROJECT MANAGEMENT INTEGRATION
THOUGHT LEADERSHIP ARTICLE 5 DIMENSIONS OF CHANGE MANAGEMENT AND PROJECT MANAGEMENT INTEGRATION The disciplines of change management and project management understandably cross paths throughout the execution
More informationFlorida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015
Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: April June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Financial
More informationPROGRAM MANAGEMENT PLANS AT TXDOT
PROGRAM MANAGEMENT PLANS AT TXDOT Transportation Programs Division PPM Fort Worth District Bryan District 6/6/18 Outline 1 Introduction to management plans 3-4 2 FHWA project management plans 5-7 3 4 5
More informationSoftware Project & Risk Management Courses Offered by The Westfall Team
Software Project & Risk Management is a 5-day course designed to provide a knowledge base and practical skills for anyone interested in implementing or improving Software Project and Risk Management techniques
More informationTaxonomy Governance Best Practices
November 5, 2018 Copyright 2018 Taxonomy Strategies LLC and Semantic Staffing. All rights reserved. Taxonomy Strategies semantic STAFFING Taxonomy Governance Best Practices Joseph Busch, Principal Analyst
More informationProject Integration Management
Project Integration Management Presented by Project Masters Inc. *Throughout this presentation, we reference and recognize the following trademarks, service marks, and copyrights of the Project Management
More informationProject Management Training Brochure
Project Management Training Brochure We develop project management training sessions by integrating our 40 years of combined practitioner experience with the most current project management knowledgebase
More informationAgenda. PMBOK Guide Third Edition. PMI Standards Background. PMI Life Cycle Plan for Standards. Presented by Kevin Chui, PMP. How Did We Get Here?
Agenda PMBOK Guide Third Edition Presented by Kevin Chui, PMP Vice President, PMI Hong Kong Chapter Background PMBOK Guide 2004 Update Project Structural Changes to the Standard Process Group Changes Knowledge
More informationUnit 11: Stakeholder Management (PMBOK Guide, Chapter 13)
(PMBOK Guide, Chapter 13) Stakeholder management identifies people, groups, and organizations that could impact or be impacted by the project. The topic has increased in importance with each new edition
More informationPMP PMBOK Guide Sixth Edition Training Course Agenda
PMP PMBOK Guide Sixth Edition Training Course Agenda 1. Introduction What are PMI and PMP Certification Application Requirements for the PMP Exam Guidelines to Complete the PMP Application About the PMP
More informationCase Study: Implementing an e-validation Solution within a BioPharma Company
Case Study: Implementing an e-validation Solution within a BioPharma Company Index Company Background Business Drivers Alternatives Identified Solution Justification Implementation Strategy Solution Implementation
More informationDefine and Initiate SubPhase
Project Management Methodology Project Management Methodology Training Define and Initiate SubPhase Course Purpose Familiarize team members with the Start Project Sub-Phase processes. Understand process
More informationCSU Project Management Certificate Program. Project Scope Management
CSU Project Management Certificate Program Project Scope Management Instructor: George Angel eaglebusiness@hotmail.com 303-678-9466 1 Scope gone wild! client wants what? 2 Project Scope Management Agenda
More informationDisampaikan Oleh: Muhammad Azani Hs
Disampaikan Oleh: Muhammad Azani Hs Catatan: Slide ini disadur dari Buku Teks oleh Schwalbe, Kathy. Managing Information Technology Project Seventh edition. Boston, MA: Thomson Course Technology, 2014.
More informationProject Management Session 6.2. Project Initiation Phase Integration Management
Project Management Session 6.2 Project Initiation Phase Integration Management 1 Project Phases & Knowledge Areas 1. Integration 2. Scope Management 3. Time Management 4. Cost Management 5. Quality Management
More informationWho Should be on Your Project Team: The Importance of Project Roles and Responsibilities
Who Should be on Your Project Team: The Importance of Project s and One significant factor contributing to the success of projects is having the right people engaged in the process. Who are the right stakeholders
More informationProject Management. Objectives 3/17/2015. David Borrill, MT, MBA, PMP
Project Management David Borrill, MT, MBA, PMP Objectives Nobody falls asleep or walks out. Presentation of some of the main points in the management of projects in the healthcare environment. Everybody
More information9/1/2017. Mary Vosevich Facilities Management The University of Kentucky September Eric Verzuh, The Fast Forward MBA in Project Management
Mary Vosevich Facilities Management The University of Kentucky September 2017 Project management is the planning, organizing, directing, and controlling of company resources for a relatively short-term
More informationReference B Project Management Requirements
Reference B State of Alaska TABLE OF CONTENTS 1... 2 1.1 Project Life Cycle Methodology... 2 1.2 Preliminary Project Management Narrative and Work Plan... 2 2 Master Project Management Plan and Master
More informationProject Manager s Roadmap We re all smarter together
Version 7.0a Project Manager s Roadmap We re all smarter together Think Top Down! Methodology Checklists Define Plan Execute Close Conflict Resolution Modes Contract Outsource Management Mentoring References
More informationRTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning
1 Project Management Plan Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning SOUTH WEST CORRIDOR STUDY (OXLEY ROAD) PROJECT OWNER: GRAEME READ 2 Document Change History
More information1/10/2016. Mary Vosevich Facilities Management The University of Kentucky January Eric Verzuh, The Fast Forward MBA in Project Management
Mary Vosevich Facilities Management The University of Kentucky January 2016 Project management is the planning, organizing, directing, and controlling of company resources for a relatively short-term objective
More information8. Assess strategies to manage organizational change. 8.1 Identify the role of knowledge management process in a project.
UNIT II STUDY GUIDE Project Governance and Team Course Learning Outcomes for Unit II Upon completion of this unit, students should be able to: 5. Describe the process of leadership when leading project
More informationChapter 3: The Project Management Process Groups: A Case Study. IT Project Management, Third Edition Chapter 3
Chapter 3: The Project Management Process Groups: A Case Study 1 Learning Objectives Describe the five project management process groups, the typical level of activity for each, and the interactions among
More informationGUIDE TO THE CHANGES IN PMP simpl learn i
GUIDE TO THE CHANGES IN PMP- 2015 simpl learn i Table of contents Introduction the purpose of this manual 1 New Tasks: Initiating 3 New Tasks: Planning 4 New Tasks: Executing 6 New Tasks: Monitoring and
More informationSuccessful Project Management. Overview Houston Community College Fall, 2017
Successful Project Management Overview Houston Community College Fall, 2017 Agenda Introduction Project Management Processes What Is a Process? Inputs, Tools and Techniques, Outputs Process Groups Overview
More informationProject Management Processes A process is a set of interrelated actions and activities performed to create a product, service, or result
HOLA Project Processes A process is a set of interrelated actions and activities performed to create a product, service, or result Each process is characterized by its inputs, the tools and techniques
More informationRevised IT Governance Charter Toolkit
Health Care IT Advisor Toolkit Revised IT Governance Charter Toolkit This toolkit offers guidance to business leaders and IT executives for developing an IT governance charter. Listed here are critical
More informationProject Cost Management
PMBOK Overview A Guide to the Body of Knowledge (PMBOK), created by the Institute (PMI), is the sum of knowledge within the profession of project management. The complete Body of Knowledge includes proven
More informationProject Management Lifecycle Phases. Execution and Control
Project Management Lifecycle Phases Execution and Control Execution and Control The purpose of the Project execution and control phase is to develop the product or service that the project was undertaken
More informationAPPENDIX L PENNDOT IT PROJECT MANAGEMENT HANDBOOK
APPENDIX L PENNDOT IT PROJECT MANAGEMENT HANDBOOK PennDOT PMO Handbook IT Project Management Handbook Last Updated: 10/7/15 Version: 3.4 Prepared by: PennDOT IT PMO Team iii PennDOT PMO Handbook Date Version
More informationINTEGRATION MANAGEMENT
1 INTEGRATION MANAGEMENT 4.1 Develop Project Charter: The process of developing a document that formally authorize a project or a phase and provides the project manager with the authority to apply organizational
More informationRFP #16-09 APPENDIX AA
RFP #16-09 APPENDIX AA COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF PUBLIC WELFARE INFORMATION TECHNOLOGY GUIDELINE Name Of Guideline: Work Plan Standard Guideline Domain: Business Date Issued: 04/25/2003
More informationStaffing Management Plan Template
Staffing Management Plan Template Project Name: U.S. Department of Housing and Urban Development October, 2010 Staffing Management Plan Template (V1.0) VERSION HISTORY [Provide information on how the development
More informationMeltem Özturan
Meltem Özturan www.mis.boun.edu.tr/ozturan/samd 1 1 Introduction Project Initiation Project Planning, Execution & Control - SDLC Project Closing What is Project?... a temporary endeavour undertaken to
More informationHANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES:
Handouts HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: DATE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES: FUNCTIONAL GROUPS PARTICIPATING: SAMPLE 3-1 REQUIREMENTS RECORD
More informationPrepAwayExam. High-efficient Exam Materials are the best high pass-rate Exam Dumps
PrepAwayExam http://www.prepawayexam.com/ High-efficient Exam Materials are the best high pass-rate Exam Dumps Exam : OG0-093 Title : TOGAF 9 Combined Part 1 and Part 2 Vendor : The Open Group Version
More informationJOB DESCRIPTION. Senior Project Manager.docx. Job family Project Management Grade 9
Job title Senior Project Manager Job family Project Management Grade 9 Job purpose To deliver a project, or multiple projects and expected outcomes, to stakeholder expectations, within the agreed brief,
More informationObjectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management
PMP Training Training Topics Chapter 1 Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus Chapter 2 Objectives of Project Management Framework What is Project
More information<Project Name> Charter
< NOTE: Remove the italicized, bracketed guidance before routing for approvals. > General Information 1. Project Number: 2. Project Name: 3. Executive : 4. Business : 5. IT : 6. Project Manager/Lead: Executive
More informationEstablishing a Program Management Office
Establishing a Program Management Office Agenda Why companies need Program Management 3 Objectives of Program Management 4 Program and Project Management definitions 5 Program Management infrastructure
More informationClinical trial databases are a crucial investment in clinical research. Part 4 - The "Life" of a Data Manager - Project Manager for the Database
Clinical trial databases are a crucial investment in clinical research Part 4 - The "Life" of a Data Manager - Project Manager for the Database Speakers: M.Duvenhage K. Laras S. Erari 12 Oct 2018 Overview
More informationS3. Step 3 Develop Roadmap
S3. Step 3 Develop Roadmap PART OF IT STRATEGY TOOLIKIT VERSION 0.5 MAY 2007 1 TABLE OF CONTENTS S3-1. DETERMINE PRIORITIES... 3 S3-1.1 ASSESS DEPENDENCIES... 3 S3-1.2 PRIORITISE BUILDING BLOCKS... 3 S3-1.3
More informationAGENCY FOR STATE TECHNOLOGY
AGENCY FOR STATE TECHNOLOGY PROJECT RISK & COMPLEXITY ASSESSMENT TOOL Risk & Complexity Assessment Model for State Information Technology Projects Purpose: In order to determine the level of risk associated
More informationApplied Project Management
Applied Project Management Duration: 5 Days Course Code: 2807 Overview: This project simulation course combines lectures, hands-on activities, and individual and team assignments to let you experience
More informationCOPYRIGHTED MATERIAL. Chapter. Project, Portfolio, and Program: Mind the Gap LEARNING OBJECTIVES
39981c01.fm Page 1 Wednesday, September 12, 2007 9:42 PM Chapter 1 Project, Portfolio, and Program: Mind the Gap LEARNING OBJECTIVES Basic concepts of project management The project life cycle: phases
More informationActual4Test. Actual4test - actual test exam dumps-pass for IT exams
Actual4Test http://www.actual4test.com Actual4test - actual test exam dumps-pass for IT exams Exam : OG0-093 Title : TOGAF 9 Combined Part 1 and Part 2 Vendor : The Open Group Version : DEMO Get Latest
More informationPassit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2
Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our
More informationPROJECT STANDARDS AND GUIDELINES
PROJECT STANDARDS AND GUIDELINES A Guide to DTAS Project Management Abstract This document defines our DTAS project management terminology and the outlines the standards and guidelines of our project management
More informationPracticeDump. Free Practice Dumps - Unlimited Free Access of practice exam
PracticeDump http://www.practicedump.com Free Practice Dumps - Unlimited Free Access of practice exam Exam : OG0-093 Title : TOGAF 9 Combined Part 1 and Part 2 Vendor : The Open Group Version : DEMO Get
More informationCapital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017
Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and
More informationProject Management CSC 310 Spring 2018 Howard Rosenthal
Project Management CSC 310 Spring 2018 Howard Rosenthal 1 Notice This course is based on and includes material from the text: A User s Manual To the PMBOK Guide Authors: Cynthia Stackpole Snyder Publisher:
More informationSoftware Engineering II - Exercise
Software Engineering II - Exercise April 29 th 2009 Software Project Management Plan Bernd Bruegge Helmut Naughton Applied Software Engineering Technische Universitaet Muenchen http://wwwbrugge.in.tum.de
More informationOverview: Status Reports/Dashboards provide program leadership and governance with updates on program progress, and strategic program risks/issues.
M3 Playbook Guidance Phase 4: Migration This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration
More informationTXCSES 2.0 : An Incremental Approach to System Replacement
TXCSES 2.0 : An Incremental Approach to System Replacement Texas Office of the Attorney General Child Support Division WICSEC November 1, 2011 Agenda Background of TXCSES 2.0 Initiative Need for System
More informationBuilding the Strategic Sourcing Capability
Building the Strategic Sourcing Capability Value of Strategic Sourcing As businesses manage the complexity arising from globalization, currency and commodity risk and economic uncertainty, the procurement
More informationAPPENDIX H IT PROJECT MANAGEMENT HANDBOOK
APPENDIX H IT PROJECT MANAGEMENT HANDBOOK IT Project Management Handbook Last Updated: 6/9/16 Version: 4.3 Prepared by: PennDOT IT PMO Team Date Version Description Author 2/16/10 1.0 Original PMO 4/29/10
More informationDimensions for Project Success Enabled by the Sponsor / P 3 M Relationship
Dimensions for Project Success Enabled by the Sponsor / P 3 M Relationship Agenda Literature Review Resource Method Transformational Role between Sponsor and P 3 M Standards Dimensions Implications Resource
More informationPRINCE2 and the National and International Standards
PRINCE2 and the National and International Standards Robert Buttrick, Project Workout Limited White Paper December 2012 2 PRINCE2 and the National and International Standards Contents 1 Introduction 3
More information2015 Project Execution Training December 1, 2015
2015 Project Execution Training December 1, 2015 Project Management Office Overview Vision Statement The University of Lethbridge IT PMO Will: Enable Project Teams to be successful through providing a
More informationPgMP Exam Prep Training - 4 Days
PgMP Exam Prep Training - 4 Days Course Length: 4 Days Course ID: PgMP Credits: 21 PDUs Course Duration: 3 or 4 days (Live in person or online class) Course Level: Advanced Day workshop- PgMP Boot Camp
More informationGRIP for Programmes Release 1 (DRAFT) April Network Rail GRIP for Programmes Page 1 of 104
GRIP for Programmes Release 1 (DRAFT) April 2015 Network Rail GRIP for Programmes Page 1 of 104 Network Rail GRIP for Programmes Page 2 of 104 Forward Purpose This document provides an overview and guidance