Please contact the undersigned if you have any questions.

Size: px
Start display at page:

Download "Please contact the undersigned if you have any questions."

Transcription

1 Richard B. Miller Assistant General Counsel April 24, 2017 Via Hon. Kathleen H. Burgess, Secretary NYS Public Service Commission Three Empire State Plaza Albany, New York Re: Case 16-E-0060, Con Edison s Electric Rate Plan Dear Secretary Burgess: The Commission s Order Approving Electric and Gas Rate Plans, issued and effective January 25, 2017, in Cases 16-E-0060, 16-G-0061, and 16-E-0196, established the Consolidated Edison Company of New York, Inc. ( Con Edison or Company ) Electric Rate Plan. The Rate Plan provides for a Con Edison Distributed Generation Interconnection Procedures Collaborative and that the Company will file an informational report with the Secretary by six (6) months from the initial collaborative meeting, identifying the topics discussed, recommendations developed and the actions taken or to be taken to implement those recommendations. The Rate Plan further provides that for any recommendation that is not implemented, the Company will explain the reason(s) why the recommendation has not been or will not be implemented. Con Edison provided a draft of this report to the Collaborative on April 10, 2017 and reviewed the report at an in-person Collaborative meeting on April 12 th. Con Edison then provided a revised draft to the Collaborative on April 13 th and held a Collaborative conference call to discuss the revised draft on April 21 st. Please contact the undersigned if you have any questions. Yours very truly, Richard B. Miller cc: Active Parties, Case 16-E-0060 Consolidated Edison Company of New York, Inc. 4 Irving Place New York NY fax millerrich@coned.com

2 Con Edison Interconnection Procedures Collaborative: Informational Report April 24, 2017

3 TABLE OF CONTENTS Page I. Introduction and Rate Plan Overview... 1 II. Distributed Generation in Con Edison Service Territory... 2 III. Collaborative Meetings... 4 IV. Topics Discussed During Collaborative... 5 V. Recommendation Developed Through Collaborative and Actions Taken or To Be Taken to Implement Recommendations and Reason(s) for Not Implementing Recommendations Not Implemented... 5 Appendices A. Con Edison DG Documentation Checklist B. DG up to 5MW System Diagram Checklist C. Three Line Diagram Example D. Verification Testing and Inspection Checklist E. List of Collaborative Meeting Topics F. List of Collaborative Meeting Participants

4 I. Introduction and Rate Plan Overview The Consolidated Edison Company of New York, Inc. ( Con Edison or Company ) Interconnection Procedures Collaborative ( the Collaborative ), chaired by the New York State Distributed Generation Ombudsman, was agreed to by the Con Edison rate case parties and adopted by the Public Service Commission ( Commission ) as part of the Company s Rate Plan. 1 As provided in the Rate Plan, the Collaborative discussed the implementation of the following items related to Con Edison s interconnection of distributed generation ( DG ): 1. Development of checklists of requirements for customers and/or developers and the Company to provide transparency and an understanding of each party s obligations 2. Improvement to Con Edison s written materials for developers, including explanation of how Con Edison applies the applicable standards 3. Scheduling of business meetings to consider project specific issues; and 4. Development of a streamlined internal review process for failed DG inspections where the customer requests a review. As provided in the Rate Plan, additional issues 2 that the Collaborative members could discuss included: 1. Procedures and processes for streamlining and improving the interconnection process, including the potential for a single point of contact within Con Edison for each DG project (note if a single point of contact is established, the parties will discuss that point of contact s responsibilities); 2. Procedures for soliciting and submitting information, such as drawings or project plans to and from Con Edison, developers, customers and contractors 3. Timelines for review of project information 4. Customer requests for estimates of interconnection costs 1 Cases 16-E-0060 et al. Proceeding on Motion of the Commission as to the Rates, Charges, Rules and Regulations of Consolidated Edison Company of New York, Inc. for Electric Service, Order Approving Electric and Gas Rate Plans (issued January 25, 2017), Order at Con Edison is required to follow the New York State Standardized Interconnection Requirements ( SIR ) in interconnecting distributed generation., The Rate Plan accordingly provided that the [a]s applicable, modifications to Con Edison s processes resulting from this collaborative shall be in accordance with the New York State Public Service Commission Standard Interconnection Requirements. As appropriate, and to the extent actions of the Commission and the Department of Public Service to improve DG interconnection related activities are known, the modifications to Con Edison s processes will be harmonized with such actions. Id. at pp

5 Con Edison agreed to implement changes in its procedures based on the Collaborative discussions and input from interested parties. As provided in the Rate Plan, Con Edison also explains in this report why it did not agree to some of the recommendations proposed by Collaborative members. Con Edison appreciates the constructive participation of developers, customers, and other stakeholders in this Collaborative. The changes it has agreed to implement will lead to positive improvements for DG developers and Con Edison customers and support the State s Reforming the Energy Vision ( REV ) goals. This Report discusses the Collaborative s outcomes, accomplishments, and areas requiring further discussion according to some Collaborative members. II. Distributed Generation in Con Edison Service Territory Table 1 below describes DG interconnections in Con Edison service territory as of February 28, Solar generation represents 98% of completed projects and 95% of projects in the queue, based on number of installations, and combined heat and power ( CHP ) generation represents 51% of completed projects and 53% of projects in the queue on a capacity basis. In 2016, solar represented 88% of all new installed DG capacity in Con Edison s service territory and Con Edison expects that in 2017 solar will overtake CHP for installed MW. Tables 2 and 3 provide a further breakdown of size ranges installed and in the queue for the two main DG technologies, solar and CHP. Over 95% of PV projects in the queue are under 50kW, and 84% of CHP projects in the queue are under 300kW.

6 Table 1: Installed and In-Queue DG in Con Edison service territory Installed In Queue Con Edison Installed and Queued DG (As of March 31st, 2017) Total Percentage (%) Technology Installs kw Installs kw Battery Storage 12 1, % 0.41% Fuel Cells 25 10, % 3.22% CHP , % 50.0% Solar 14, , % 46.3% Wind % 0.04% Total 14, ,817 Battery Storage 11 1, % 0.86% Fuel Cells 10 5, % 3.9% CHP , % 52.3% Solar 2,251 58, % 43.0% Wind % 0.0% Total 2, ,671 Table 2: Size distribution of solar projects in Con Edison service territory Current PV Installed and in Queue Size Range (kw AC) % of Installed Projects % of Installed Capacity % of Projects in Queue % of Queue Capacity 0-50kW 97.96% 66.95% 94.51% 24.71% kW 1.76% 18.32% 3.53% 17.33% kW 0.27% 12.81% 1.62% 35.79% kw 0.01% 1.93% 0.33% 22.16% Table 3: Size distribution of CHP in Con Edison service territory Current CHP Installed and In Queue Size Range (kw AC) % of Installed Projects % of Installed Capacity % of Projects in Queue % of Queue Capacity 0-50kW 6.87% 0.10% 12.96% 0.34% kW 74.25% 12.37% 71.30% 13.34% kW 8.58% 7.41% 7.41% 5.31% kw 5.58% 18.88% 2.78% 6.13% Above 5000 kw 4.72% 61.23% 5.56% 74.88% In order to support further growth of DG, the Collaborative built on several existing Con Edison resources for DG customers and developers. All of these resources are available via Con Edison s website. Con Edison welcomes input on its website so that it can improve and enhance the site. These include:

7 Solar Website Solar Video Interconnection Application Webpage Con Edison Guide for CHP Con Edison Large DG Guide (Systems Over 5MW) Presentations from Solar Interconnection Workshops (annual) Solar FAQs DG Specifications and Tariffs III. Collaborative Meetings The Collaborative officially began in October 2016 when the New York State Ombudsman, Elizabeth Grisaru (New York State Department of Public Service Staff) and Houtan Moaveni (New York State Energy Research and Development Authority), serving as co- chairs, commenced discussions for interested parties to develop improvements to Con Edison s internal

8 process for managing interconnections. 3 After the kick off meeting in October 2016, the Collaborative held monthly in-person meetings with developers, customers, and other stakeholders in November and December 2016 and in January, February, March, and April There was an additional online-only webinar held in March Con Edison posted the Collaborative schedule and presentation materials on its DG website. IV. Topics Discussed During Collaborative Con Edison prepared presentations for each meeting covering the topics listed in the Rate Plan. The presentations outlined the topics of the day and future work plan and schedules. The Collaborative engaged in discussion, provided feedback, asked further questions, and made suggestions for other topics or clarifications. The Collaborative discussed the topics included in the Rate Plan and additional items (e.g., detail on SIR workflow). A full list of the presentations and discussion topics is included in Appendix E. Con Edison will post on its Company web site the documents developed during this Collaborative, and it has included the checklists developed as appendices to this report. V. Recommendation Developed Through Collaborative and Actions Taken or To Be Taken to Implement Recommendations and Reason(s) for Not Implementing Recommendations Not Implemented The resolution of specific issues by the Collaborative for each Rate Plan topic is set forth below. Con Edison reviewed all of these topics with the Collaborative and incorporated the Collaborative s input as it deemed appropriate. The Collaborative agrees that the solutions Con Edison has agreed to implement will enhance the Company s DG interconnection process. As discussed in more detail below, however, Con Edison has not agreed to implement the recommendations advanced by Collaborative members who believe that it is necessary to develop resources such as checklists or guidelines to clarify the interconnection process for other projects such as large DG projects. It is important to note that Con Edison will continue to enhance the resources it created pursuant to this Collaborative, and its DG interconnection process, as it continues to receive more developer/stakeholder input and as technology and procedures evolve. 3 A notice for the first meeting was sent to the active parties list for Con Edison s rate case and the active developers in the Con Edison service territory. The Collaborative membership list was established after this first meeting and after this rate case parties and developers who comprised the members were provided with notice. The list of Collaborative members is attached hereto as Appendix F.

9 Rate Plan Initial Topics 1. Development of checklists of requirements for customers and/or developers and the Company to provide transparency and an understanding of each party s obligations: Con Edison has created the following: an application checklist based on SIR requirements; a checklist for requirements of system drawings and examples for DG up to 5 MW; a verification test checklist for solar projects; and FAQs for verification tests for solar projects. Con Edison received input from the Collaborative on these checklists that Con Edison incorporated to enhance transparency and consistency for customers/developers. The DG Documentation Checklist (Appendix A) is derived from the SIR and describes how those requirements translate into specific Con Edison procedures, and shows where to find all of the Con Edison procedural documents. The System Diagram Checklist (Appendix B) and Verification Testing and Inspection Checklist (Appendix D) include requirements for drawings and what developers should expect Con Edison to review during verification testing. In addition, the Verification Testing and Inspection Checklist covers what developers should have completed in order to request a verification test. The system design diagram checklist covers the majority of Con Edison DG installations while the verification test checklist covers all solar projects connected to Con Edison s secondary system. For projects not included in the SIR (i.e., above 5MW), Con Edison has a Large DG Guide 4 that describes requirements for those projects. Con Edison welcomes feedback from developers and stakeholders on how this guide could be improved or clarified. Additional Checklists Some Collaborative members suggested that Con Edison develop additional checklists for CHP and storage. Con Edison reviewed the CHP technology types in its queue and decided to create a system diagram and verification test checklists for inverter-based CHP up to 300 kw. The Company expects to complete this work by September 1, Approximately 91 CHP installation projects (84%) in the queue are below 300kW, and 97% of those projects are inverter-based. The Company believes that a checklist would not be able to cover all site-specific issues for certain technologies and systems that are more complex (e.g., synchronous CHPs, 4

10 combinations of DG technologies). For example, many large DG/CHP projects go through multiple changes and redesigns through the design and construction stages. In these cases, Con Edison has found that the best strategy is frequent, in-person meetings to review projectspecific requirements and iterations. In addition, the Con Edison CHP guide and Large DG Guide identify the issues that can arise in interconnecting CHP systems on the Con Edison System. Many CHP customers have used this guide because it is helpful in identifying the different factors involved in developing these projects. 2. Improvement to Con Edison s written materials for developers, including explanation of how Con Edison applies the applicable standards Technology Guides In 2011, Con Edison published two new DG guides, one for large DG not covered under the then current SIR, and another for CHP systems in general. The Company revised these guides in 2016 to reflect the new SIR DG size limits to cover projects below 5MW. These guides cover general requirements, procedures, Con Edison specifications, and contacts for further questions. The Company created these guides for CHP projects because they are often larger than solar projects and are more complex. Con Edison used these guides as a basis for the creation of a solar guide 5 and a fuel cell guide. 6 These guides also reflect content that Con Edison presents at its annual solar installer workshop at the Learning Center. During the Collaborative, Con Edison presented the outlines and then shared full drafts of the guides for comment. Con Edison has incorporated feedback received from the Collaborative and has posted the guides on the Company s website. 7 Con Edison also welcomes feedback from developers and stakeholders on the CHP and Large DG Guides. All these Guides will change and evolve as technology and markets change The Company is also integrating the March 9 Value of DER order, and will publish an updated version on the Con Edison DG website later in 2017.

11 Additional Guides Some Collaborative members recommended that the Company develop an energy storage guide, as well as guidance for DG systems over 5MW. In particular, New York City has recently set targets for energy storage and considers storage to be an important part of its energy policy. As discussed above, Con Edison already has an existing DG guide for projects above 5 MW and an existing CHP guide, and will continue to refine these guides based upon its interactions with developers and stakeholders. Con Edison agrees that an energy storage guide would be helpful, but has not seen many such projects interconnected or in the queue. Energy storage represents less than 1% of both installed and in queue DG. It is expected that storage will grow in coming years owing to Con Edison utility-sited and customer-sited storage projects and New York City s target to facilitate the deployment of 100 MWh of energy storage by The City believes that the presence of these projects and policy drivers will encourage FDNY and DOB to develop more standardized permitting guidance for various energy storage technologies, namely lithium ion batteries, which is expected to increase market penetration. Con Edison plans to develop an energy storage guide if there is expanded penetration in the storage market, similar to that of the solar market over the past few years. The City and other Collaborative members believe that Con Edison should develop a guide now in anticipation of market penetration but Con Edison disagrees because it is not clear at this time which storage technologies and configurations will advance even if there is increased market penetration. Con Edison notes that all of its DG technology guides will continually evolve in response to market and technology changes and application interactions. The Company is committed to helping all of its customers who are interested in installing DG resources. Members of the Collaborative also raised whether Con Edison could give technical interconnection classes for developers. Con Edison is evaluating the potential for these classes. Communications Templates Multiple Con Edison departments manage DG applications and conduct the SIR technical analyses. Con Edison is committed to providing a consistent experience for developers and

12 DG applicants going forward. To provide this consistency, Con Edison created standard communications templates that will be used by Con Edison Energy Services and Distribution Engineering to communicate the results of various steps in the SIR process to applicants. These templates will result in consistency across projects, engineers, and customer project managers ( CPMs ) and create a standard set of expectations for developers going through the interconnection process. Con Edison has also created a high-level workflow document that explains the new SIR process and the options an applicant has for moving through an interconnection project. The workflow document is available on the Con Edison website. 8 Members of the Collaborative also expressed interest in workflows for projects above 5MW. There is a workflow document on page 14 of the Large DG Guide. The City and other Collaborative members requested that Con Edison incorporate timelines into the workflows in the Large DG Guide. Con Edison will review addition of timeframes to the Large DG Guide. 3. Scheduling of business meetings to consider project specific issues The Collaborative discussed the value of project-specific meetings in cases of large groups of projects, or projects that present complex technical issues. Collaborative members also discussed whether Con Edison could increase its responsiveness to meeting requests. Con Edison explained to the Collaborative that it understands that business meetings can add value and clarification for DG developers. Generally, the CPM is the first point of contact to request a project meeting(s) and Con Edison seeks to respond to meeting requests in a timely manner. In addition, the DG Ombudsman s office, or the Energy Services manager, is always available for meetings on request, or other concerns that the developer believes have not been resolved by the CPM, and the contact information for each is available on the Con Edison website. In addition, the Company will hold regular meetings when appropriate. For example, any DG project above 5MW normally has regularly scheduled meetings with Energy Services 8 p. 49.

13 because these projects are complex and typically undergo several project scope and design iterations. 9 Collaborative members noted that the SIR pre-application discussions can be quite valuable in explaining the process, managing expectations, and identifying any unique constraints or scheduling needs in advance. Con Edison will continue to encourage developers to schedule these meetings if they have any concerns. The SIR (as of March 2016) provides for several meetings within the application process itself, including the Preliminary Screening Results Meeting and the Supplemental Screening Results Review Meeting. Additionally, meetings are helpful for more specialized billing situations, such as Remote Net Metering, Community DG Distributed Generation, or Offset Tariff. In these cases, Con Edison encourages developers to schedule meetings, through their project manager, with relevant billing departments in advance of final interconnection. Con Edison understands the importance of responding in a transparent, consistent, and timely manner to meeting requests, and seeks to meet developers expectations, as was further discussed during the Collaborative. Some stakeholders raised concerns about experiencing trouble in receiving feedback on DG inquiries. Con Edison emphasized that in cases where inquiries are not processed in a timely manner the applicant should reach out to the CPM s manager or to the DG Ombudsman s office as soon as possible. Some Collaborative members expressed concern that escalation to higher levels will not sufficiently address responsiveness concerns, and the City proposed for example, that Con Edison should use its project center to more closely monitor work. Con Edison believes, however, that informing customers and developers that they have access to both the CPM s manager and the DG ombudsman s office to resolve issues adequately addresses this concern. 10 Con Edison will continue to review whether its project center can be modified to help address this concern Incentives for timeliness and customer satisfaction for DG projects is being considered in the Con Edison Interconnection Earning Adjustment Mechanism Collaborative.

14 4. Development of a streamlined internal review process for failed DG inspections where the customer requests a review. Con Edison proposed a draft process to review failed inspections. The Collaborative provided input and Con Edison revised the process accordingly. The process provides for an applicant to appeal the results of a failed inspection and provide notification of the appeal to the following Con Edison employees: the project manager, the engineer, the respective managers, and the Con Edison DG Ombudsman. Con Edison will acknowledge the appeal within 2 business days and respond to the applicant with a resolution, and rationale for the resolution, within 10 business days. Con Edison s Energy Services will be responsible for managing the appeals process and will reach out to the applicant to either resolve the matter or request more information prior to providing a its response to the appeal within 10 days. Following resolution of the appeal, the process will revert to following SIR timelines where applicable. Con Edison has included the specifics of how to submit an appeal, and related timelines on both the Company s verification checklist and the technology guides (and on the Con Edison DG website). Additional Topics The Rate Plan stated that the Collaborative s members may discuss the following additional topics. 1. Procedures and processes for streamlining and improving the interconnection process, including the potential for a single point of contact within Con Edison for each DG project (note if a single point of contact is established, the parties will discuss that point of contact s responsibilities) The Collaborative members offered input on how past experiences with multiple project managers could be improved in the future. Customers stated that they do not want to be responsible for coordinating internal Con Edison workflows. To provide information to the Collaborative on how it manages workflows, Con Edison provided detail on how the Company manages different types of work. The CPMs are the central point of contact for all DG projects. Con Edison has created specialized groups to handle different types of service requests. A request for gas service to power a CHP system

15 is a different scope of work than a DG interconnection request, which is in turn different from the a new building service, and each of these will be handled by a CPM who has specialized knowledge in that type of work. Con Edison has recently centralized all DG applications above 50kW within one specialized group to further streamline the process. Accordingly, some customer projects require more than one CPM for each type of work required. As discussed above, this additional work could include gas service, upgrades to electrical service or new electrical service. For these kinds of customer projects, while there will be a single CPM for the DG project, that CPM will coordinate in a timely manner with the CPM(s) who are responsible for such additional work. For example, in existing buildings, the DG CPM will be the single point of contact for DG projects, but if the DG project includes a new service or work that is outside of the DG scope, the applicant will have more than one CPM. Con Edison committed in the Collaborative to having the DG CPM act as the primary contact for the applicant and coordinating the multiple case work so that the work can be completed in an efficient manner. Con Edison presented workflows on the coordination of work within a new building and within an existing building. 2. Procedures for soliciting and submitting information, such as drawings or project plans to and from Con Edison, developers, customers and contractors The Collaborative identified several items that would provide a better experience for users of Con Edison s existing online system for processing interconnection applications. Con Edison will include the following items in a July 2017 upgrade of the system: Specific identification of Community DG projects, and tailored requests for these types of projects (e.g., Community DG forms rather than Form G) Ability to communicate all project requests and communications through the portal to provide better tracking (e.g., replace s for inspection appeals with automated request form); and Improved tracking of drawing revisions and communications about approvals

16 In addition, in accordance with the Collaborative recommendation, Con Edison will add Rider H and Rider J forms for CHP projects in future updates. Several members of the Collaborative asked about communicating with Con Edison on project-related issues. To provide transparency and accurate record keeping, the Company suggests that all communications be uploaded to Project Center in addition to ing the CPM. Con Edison has updated the technology guides accordingly. In response to a request from some Collaborative members, Con Edison agreed to consider the adoption of a system that will automatically upload communications to the Project Center. 3. Timelines for review of project information Con Edison presented a basic SIR workflow document and reviewed timelines associated with each step with the Collaborative. Con Edison tracks each project as it moves through the interconnection process to monitor compliance with the SIR and takes action where appropriate. The Collaborative asked for information on systems above 5MW. These projects are complex and typically have longer timelines. The general workflows for these types of projects are located in the Large DG Guide. Con Edison is open to further feedback on the detail presented in the Large DG Guide. Some Collaborative members proposed that the Collaborative should continue for this Guide and other matters. The Company disagrees that the Collaborative is necessary in order for it to receive and respond to input on these guides. 4. Customer requests for estimates of interconnection costs The Collaborative discussed interconnection costs and how they are derived. Con Edison provided information on the two main components of interconnection cost: cost of study and cost of upgrades. The Collaborative asked for more insight into how interconnection study costs are developed, what information is given to developers who are going through an engineering study, and what drives upgrade costs. The engineering study that is referred to as the Coordinated Electric System Interconnection Review ( CESIR ) is the SIR step that will give most applicants information on how their projects will impact the Con Edison system and what needs to be done to mitigate those

17 impacts (e.g., service upgrade, network protector relay upgrades, communications equipment). The SIR provides that the utility will provide the applicant with the cost of conducting the CESIR within 5 business days of a request. For non-sir projects above 5 MW, the City requested that Con Edison will follow the same process and provide the applicant the cost of conducting the engineering study within 5 business days of a request. Con Edison does not believe it is possible to adopt a standard time frame for projects larger than 5 MW. Con Edison explained that the CESIR cost estimate is site specific and based on the following factors: Type of technology (e.g., inverter, synchronous) Size (kw) Operation (export, non-exporting) Interconnection type (network versus non-network) As a result of the Collaborative discussions, Con Edison will include information about the project when it provides the CESIR cost to the applicant as follows: The cost of your CESIR is based on your request to interconnect a <<1.2MW solar photovoltaic>> system with <<an inverter>>, <<exporting>> to <<an underground network electric distribution service>>. This will allow developers to confirm that the CESIR costs are in line with the project they submitted. Con Edison also agreed as a result of Collaborative discussions to include CESIR cost ranges in its guides. Con Edison explained that upgrade costs are site-specific and cannot estimate such costs before it completes the engineering study. However, Con Edison DG Ombudsman s office frequently gives out information on the service type and potential upgrade requirements (type, not cost) to developers. For instance, the office would tell a developer if its project is on a spot network and might require Con Edison s Communication Aided Tripping ( CAT ) solution. This type of information will be available in July 2017 on the CUNY New York Solar Map website, as part of the Grid Ready project with Con Edison.

18 Appendix A: DG Documentation Checklist The following table is intended to assist installers of Distributed Generation Projects understand the equivalent Con Edison documents or process items required to comply with the Appendix F Application Package Checklist as found in the New York State Standardized Interconnection Requirements and Application Process For New Distributed Generators 5 MW or Less Connected in Parallel with Utility Distribution Systems. Appendix F Equivalent Document or Location Application Package Checklist Process Requirement Completed standard application form (Appendix Completed Project Center B or C) Application New York State Standardized Acknowledgement Appendix H of SIR NYS SIR of Property Owner Consent Form For Systems above 50kW up to 5MW Only Refer to Appendix H for form Signed copy of the standard contract Appendix A (Standard Contract) NYS SIR or Project Center Letter of authorization, signed by the Customer, Customer Letter Of Con Edison website to provide for the contractor to act as the customer s agent, if necessary Authorization If requesting a new service, a site plan with the proposed interconnection point identified by a Google Earth, Bing Maps or similar satellite image. For those projects on existing services, Attach drawing/plan. Provided by developer. account and meter numbers shall be provided Description / Narrative of the project and site proposed. If multiple DG systems are being proposed at the same site/location, this information needs to be identified and explained in detail Include in Scope of Work in Project Center application. Project Center DG technology type Included in Project Center fields. Project Center DG fuel source / configuration Included in Project Center fields. Project Center Proposed project size in AC kw Included in Project Center fields. Project Center Project is net metered, remote, or community net metered Metering configuration Copy of the certificate of compliance referencing UL 1741 Copy of the manufacturer s data sheet for the interface equipment Copy of the manufacturer s verification test procedures, if required System Diagram - A three line diagram for designs proposed on three phase systems, including detailed information on the wiring configuration at the PCC and an exact representation of existing utility service. One line diagrams shall be acceptable for single phase installations Application Form G, or for CDG the Community DG Forms, also Include in Scope of Work in Project Center. Included as part of the line diagram and/or Form G Attach document. Attach document. Attach document. Attach drawing. Con Edison website. Provided by developer. Provided by developer. Provided by developer. Provided by developer. See Con Edison System Diagram Checklist. Provided by developer.

19 Appendix B: DG up to 5MW System Diagram Checklist This checklist will be used to conduct system diagram review prior to Con Edison giving approval to build. These checklist items are intended to cover the baseline requirements for the majority of cases; however, unique configurations or operating uses may have additional requirements. Component Details Check box Three Line Drawing Does drawing show three (3) lines for each phase, OR One (1) line with clear indications that all three phases are identical? P.E. Stamp If connecting to system voltage > 1,000 V, OR If qualifying as efficient CHP as per Form G, are drawings stamped by P.E.?* Equipment Locations Title Block Are locations (e.g., basement, roof, electrical room) clearly noted for disconnect switch ( 89L ), meter, and all inverters? Does the title block include: Customer name and address? Account and Meter Number? Revision number and date of last revision? DG System Drawing Is the DG Type (e.g., PV, Battery, Fuel Cell, etc.) clearly Details labelled on drawing? Is the A.C. nameplate kw clearly labelled? Is the 89L clearly labelled? Is the make and model of the inverter clearly labelled and does it match submitted technical specifications? Service Characteristics Is the Con Edison existing service type and configuration Drawing Details clearly labelled? (e.g. 120/208V, 120/240V, 265/460V) Is the grounding connection clearly labeled? If there is existing DG on site, is the connection to existing system shown on diagram? *Note that projects that connect to the Con Edison system < 1,000V do not require a P.E. Stamp. (page 12 of SIR)

20 D R A F T Appendix C: Three Line Diagram Example Example Three Line Drawing Components Equipment Locations Title Block DG System Drawing Details Service Characteristic Drawing Details

21 D R A F T Appendix C: Three Line Diagram Example (Continued)

22 D R A F T Appendix C: Three Line Diagram Example (Continued)

23 Appendix D: Verification Testing and Inspection Checklist for solar projects at existing company secondary facilities This checklist will be used to conduct on site verification testing prior to Con Edison giving final acceptance for interconnection. These checklist items are intended to cover the baseline field verification requirements; however, unique configurations, other distributed generation technologies, or operating uses may have additional requirements. Any additional requirements will be discussed prior to site verification testing. NOTE: If you disagree with a failed inspection, send an to your CPM and [distribution list address], which includes Energy Services and Distribution Engineering senior managers. The subject line should include the case number and Appeal of Verification Test. The should describe in detail, as related to the verification test checklist, why you disagree with the results of the inspection. Include any documentation or photographs that are necessary. In addition, upload the to the case in Project Center. You will receive an acknowledgement of your appeal in 2 business days via , and Con Edison will respond with a resolution and rationale within 10 business days. Component Drawing Version Pre-testing Prior to Requesting Site Verification Test: Applicant Checklist Details Has latest drawing version been submitted to Project Center and approved by Con Edison? Has applicant verified that all inverters are operational? (Note: applicant should verify whether testing restrictions are in place prior to pre-test) Local municipality sign-off Attendance Has the project passed the local building department inspection? The following personnel should be present: applicant, facilities representative with access, and any required technicians. Site Verification Test To Be Completed by Con Edison Engineering Component Details Check box (failed steps in grey boxes require reinspection) Disconnect Switch ( 89L ) Grounding Consistency with Submitted Drawing Are directions to 89L clearly marked at meter location? Is the 89L: clearly labelled? visibly broken when operated? load breaking? gang operated? lockable? Is the switchgear properly grounded? Is the inverter properly grounded (if necessary)? Are the panels properly grounded (if necessary)? Does the nameplate kw match approved drawing? Does the inverter make and model match the approved drawing? Is the DG system interconnected to Con Edison s system as shown in

24 Operation Check Reverse Power Relay (if applicable) the approved drawing? Does the customer DG system pass the 5 minute test? (carried out by the customer, witnessed by Con Edison) Is the inverter output (voltage and power) balanced? Is the reverse power relay connected correctly? Is the reverse power relay programmed correctly? Does the reverse power relay operate correctly? Is the approved (and latest) drawing laminated and posted near the meter?

25 Appendix D: Verification Testing and Inspection Checklist (continued) Verification Testing and Inspections: Frequently Asked Questions 5. What is verification testing and why is it necessary? As per Step 9 of the New York State Standardized Interconnection Requirements (March 2016), all DG systems above 50kW are to be tested prior to final acceptance and interconnection. This ensures that the system is installed as designed and is operating safely. 6. How should I prepare for verification testing? Applicants should have completed construction as per latest drawing approved by Con Edison and ensured that all inverters are working properly. The most recent drawings must be uploaded to Project Center and been reviewed by Con Edison. 7. How do I request a verification test? You should submit a request in writing via to your Customer Project Manager (CPM). 8. What happens if I fail a test? Any items above with a grey checkbox (e.g., inverter does not work) that do not pass will require reinspection. Once the deficiency has been corrected you will need to request another test. Other items, such as labeling, can be passed without re-inspection if a new drawing and/or photographs are submitted. Your CPM will provide details of those items. Any new submittals will be reviewed within 10 business days. 9. I disagree with the results of my inspection. How can I appeal? If you disagree with a failed inspection, send an to your CPM and [distribution list address], which includes Energy Services and Distribution Engineering senior managers. The subject line should include the case number and Appeal of Verification Test. The should describe in detail, as related to the verification test checklist, why you disagree with the results of the inspection. Include any documentation or photographs that are necessary. In addition, upload the to the case in Project Center. You will receive an acknowledgement of your appeal in 2 business days via , and Con Edison will respond with a resolution and rationale within 10 business days.

26 Appendix E: List of Collaborative Meeting Topics This appendix lists, at a high level, the topics and material that Con Edison presented at each meeting and key points of discussion and feedback from stakeholders and developers. November 2016: Con Edison Presentation Topics Overview of topics to be discussed by the Collaborative Review of existing materials and resources for developers (e.g., New York State Standardized Interconnection Requirements ( SIR ), Con Edison CHP guide, Con Edison DG website) Outline of next steps for Con Edison (e.g., create checklists, inspection FAQs, guides, written materials) Collaborative Discussion Topics Request that checklists should cover application requirements, including a Con Edison version of the SIR Appendix F, in addition to system diagram checklists and inspection checklists Request for procedures for DG that is sized above current SIR limits (5 MW) Con Edison versus Department of Buildings compliance, including inspectional jurisdiction and order Clarification on when Con Edison accepts a single-line versus a three-line diagram for drawings Consistency of communications from engineering reviews, avoiding iterative and multiple engineering reviews, and consistency between engineers Improved understanding of Con Edison technical standards for review Value found in past technical interconnection classes held by Con Edison Questions about closeout and meter set processes Process for regular business meetings December 2016 Con Edison Presentation Topics Outlines of solar and fuel cell guides Frequently Asked Questions topics for inspections Clarification on when single line versus three line system drawings are accepted Collaborative Discussion Topics Straw proposal requested from Con Edison on regular business meetings Questions on SIR workflow and difference between supplemental screens and Coordinated Electric System Interconnection Review ( CESIRs ) Updates to Con Edison Project Center to reflect process improvements (e.g., rate application forms specific to type of project) Questions on labeling for 89L disconnect switches Ensuring consistency of reviewed drawings with subsequent revisions and inspections 23

27 New York City Department of Buildings ( DOB ) participation Timelines for post-failed inspection procedures Clarifying when engineering reviews a project that passes Preliminary or Supplemental SIR screens January 2017 Con Edison Presentation Topics Application checklist: Con Edison version of SIR Appendix F Three-line diagram checklist and samples Verification test checklist Verification test FAQs Collaborative Discussion Topics Process for DG larger than 5MW Request for checklists covering additional technologies, e.g., CHP DOB and Con Edison coordination Preliminary discussions with developers for additional requirements Project Center updates and ability to track revised drawings Process for opening meter pan or CT cabinets February 2017 Con Edison Presentation Topics Process for regular business meetings SIR workflow Standardized templates for Con Edison completion of SIR steps: Preliminary Screening, Supplemental Screening, and CESIR Collaborative Discussion Topics Additional guidance and checklists for CHP Coordination between customer project managers ( CPMs ) on different systems (gas, electric, new service) Responsiveness of CPMs, standard procedures for replying to developers Workflows for under 50kW and above 5MW projects Guidance on how to go through SIR CESIR costs Appeals process for failed inspections March 13, 2017 (online Webinar only) 24

28 Con Edison Presentation Topics Solar Guide Fuel Cell Guide Collaborative Discussion Topics Questions on under 50kW process Guidance for DG above 5MW Guides should emphasize that all communications should go through Project Center Guides should discuss roles of all parties (CPM, engineer, Ombudsman, DPS, etc.) Request for guide on energy storage March 27, 2017 Con Edison Presentation Topics Coordinating DG cases with new or upgraded service cases Appeals process for failed inspections CESIR cost estimates Existing Con Edison guides for CHP and DG above 5MW Collaborative Discussion Topics Con Edison expedited process for solar under 25kW Definition of timelines for acknowledgement and resolution response for appeals for failed inspections Availability of general magnitude of cost for CESIRs Storage guide Checklist for CHP Guidance for systems over 5MW April 12, 2017 Con Edison Presentation Topics Review draft informational report on Collaborative Review additional Items Collaborative Discussion Topics Collaborative report comments 25

29 Appendix F: List of Collaborative Meeting Participants This is a list of participant organizations in the meetings, either in-person or by phone, as best represented from meeting minutes and sign-in sheets. This may not be all-inclusive but is compiled based on existing records. Con Edison New York State Department of Public Service New York State Energy Research and Development Authority RSP Systems City of New York Best Energy Power EnterSolar E Cubed Company LLC Consumer Power Advocates Association for Energy Affordability City University of New York County of Westchester New York Energy Consumers Council (NYECC) Local Unions Related New York State Department of State, Utility Intervention Unit 26

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

REVISION NO.: 8 EFFECTIVE: 03/26/18

REVISION NO.: 8 EFFECTIVE: 03/26/18 Distributed Generation Interconnection Process for Residential and Small General Service OVERVIEW REVISION NO.: 8 EFFECTIVE: 03/26/18 Required Steps for ED3 s Distributed Generation Interconnection Process

More information

CON EDISON TURNKEY SOLAR: CLARIFICATION ANSWERS AND QUESTIONS

CON EDISON TURNKEY SOLAR: CLARIFICATION ANSWERS AND QUESTIONS CON EDISON TURNKEY SOLAR: CLARIFICATION ANSWERS AND QUESTIONS This document answers questions that were submitted by February 19, 2018 or that were asked at the Shared Solar Site Visits. Enabled Respondents

More information

Dated: April 16, 2002

Dated: April 16, 2002 Central Hudson Gas & Electric Corporation (CHG&E) Application Process for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System Dated: April 16,

More information

Union Power Cooperative

Union Power Cooperative Union Power Cooperative INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities of the local

More information

Smart Grid Small Generator Interconnection Procedure (SGIP) Updates. December 06, 2016

Smart Grid Small Generator Interconnection Procedure (SGIP) Updates. December 06, 2016 Smart Grid Small Generator Interconnection Procedure (SGIP) Updates December 06, 2016 1 Agenda Background on Interconnection Procedure Modification on SGIP process Interconnection Online Application Portal

More information

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I

More information

New York. NYSolar Smart Final Report. U.S. Department of Energy SunShot Initiative. Rooftop Solar Challenge II. Sustainable CUNY

New York. NYSolar Smart Final Report. U.S. Department of Energy SunShot Initiative. Rooftop Solar Challenge II. Sustainable CUNY New York NYSolar Smart Final Report U.S. Department of Energy SunShot Initiative Rooftop Solar Challenge II Sustainable CUNY City University of New York December 2016 Executive Summary Rooftop Solar Challenge

More information

RECOMMENDATIONS FOR EXPEDITED PERMITTING FOR SMALL PV SYSTEMS

RECOMMENDATIONS FOR EXPEDITED PERMITTING FOR SMALL PV SYSTEMS 3 RECOMMENDATIONS FOR EXPEDITED PERMITTING FOR SMALL PV SYSTEMS A streamlined, expedited permit process for small solar PV systems that simplifies and consolidates the structural, electrical and fire review

More information

Possible Noncompliance Review Processing

Possible Noncompliance Review Processing Possible Noncompliance Review Processing October 31, 2018 RAM-200 3000 Bayport Drive, Suite 600 Tampa, Florida 33607-8410 (813) 289-5644 - Phone (813) 289-5646 Fax www.frcc.com Table of Contents Page

More information

Navigating Local Utility Requirements for Microgrids: Lessons from New York

Navigating Local Utility Requirements for Microgrids: Lessons from New York A W H I T E P A P E R B Y V E O L I A Navigating Local Utility Requirements for Microgrids: Lessons from New York TABLE OF CONTENTS Introduction 2 I. Resiliency, Microgrids and Utility Reforms 2 II. What

More information

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS Program Guide TABLE OF CONTENTS Introduction... 2 Purpose... 2 About CHP... 2 Program Description... 2 Call for CHP Projects... 3 Participant Webinar...

More information

RENEWABLE ENERGY ELECTRIC GENERATING SYSTEM APPLICATION INSTRUCTIONS

RENEWABLE ENERGY ELECTRIC GENERATING SYSTEM APPLICATION INSTRUCTIONS RENEWABLE ENERGY ELECTRIC GENERATING SYSTEM APPLICATION INSTRUCTIONS All renewable energy systems require an electrical permit. In some cases, a building permit is also required. The following process

More information

TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. Policy Bulletin No Appendix A SAFETY & INTERCONNECTION REQUIREMENTS FOR ALTERNATE ENERGY PRODUCTION

TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. Policy Bulletin No Appendix A SAFETY & INTERCONNECTION REQUIREMENTS FOR ALTERNATE ENERGY PRODUCTION TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. Policy Bulletin No. 3-17 Appendix A SAFETY & INTERCONNECTION REQUIREMENTS FOR ALTERNATE ENERGY PRODUCTION The Cooperative recognizes the various electric industry

More information

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION FortisAlberta s Distributed Energy Resource (DER) Process explains what is required

More information

Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant

Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant RFP FY2017-BFD-01 Release Date: May 8 th, 2017 Applications Due: June 23 rd, 2017 1. PROGRAM SUMMARY

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT NETWORK SYSTEMS SECTION SPECIFICATION EO-4133 REVISION 2 OCTOBER, 2006 GENERAL REQUIREMENTS

More information

Experimental Advanced Renewable Program (EARP) Anaerobic Digester. David Ronk

Experimental Advanced Renewable Program (EARP) Anaerobic Digester. David Ronk 1 Experimental Advanced Renewable Program () Anaerobic Digester David Ronk -AD Agenda 2 Overview David Ronk How to Participate Keith Troyer -AD Process Keith Troyer & Matt Good Overview 3 What is? Why

More information

Technical Requirements for Distributed Generation Connection

Technical Requirements for Distributed Generation Connection Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting

More information

APPLICATION FOR SOLAR PERMIT

APPLICATION FOR SOLAR PERMIT APPLICATION FOR SOLAR PERMIT Permit Application Application Checklist o New York State Unified Solar Permit Application for Roof Mounted Systems 12kW or less. (Includes Electrical Permit Application) o

More information

LONG ISLAND LONG ISLAND

LONG ISLAND LONG ISLAND Utility 2.0 Long Range Plan 1 The proposed Utility 2.0 investments are designed to benefit all Long Island customers. Our Utility 2.0 proposal is a component of a broader set of solutions to improve reliability

More information

What You Need to Know Before Requesting Interconnection

What You Need to Know Before Requesting Interconnection Connecting to the Utility Grid What You Need to Know Before Requesting Interconnection Peter Giannotti Southern California Edison August 16, 2017 Tampa Convention Center Tampa, Florida Why is Grid Interconnection

More information

Energy Storage Buildings-to- Grid Applications

Energy Storage Buildings-to- Grid Applications Energy Storage Buildings-to- Grid Applications Ben Falber NYSERDA Energy Storage Program March 14 th Capture the Energy 2019 2 Advanced Energy Storage Deployed Approximately 20 MW of chemical, 20 MW of

More information

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015 Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating

More information

Interconnection Application

Interconnection Application Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

LEVEL 2 Application For Interconnection And Net Metering

LEVEL 2 Application For Interconnection And Net Metering LEVEL 2 Application For Interconnection And Net Metering Use this Application form when generating facility is not inverter-based or is not certified by a nationally recognized testing laboratory to meet

More information

CUSTOMER GUIDE FOR DISTRIBUTION SYSTEM INTERCONNECTION INVERTER-BASED DISTRIBUTED RESOURCES. < 50 kw

CUSTOMER GUIDE FOR DISTRIBUTION SYSTEM INTERCONNECTION INVERTER-BASED DISTRIBUTED RESOURCES. < 50 kw CUSTOMER GUIDE FOR DISTRIBUTION SYSTEM INTERCONNECTION OF INVERTER-BASED DISTRIBUTED RESOURCES < 50 kw October 10, 2011 1 Index Introduction 1 Process Overview 1 Minimum Requirements for Interconnection

More information

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW

More information

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS TITLE: GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS DOCUMENT STATUS: FINAL REVISION: DATE: 1 21 September 2015 2015 Electricity Networks Corporation trading

More information

TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS. for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP

TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS. for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP RFP No. TPL SOLAR IPP 1 NOTICE TO OFFEROR REQUEST FOR PROPOSALS

More information

effective date 1/8/01

effective date 1/8/01 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical

More information

Requirement for Application Submittal For use in all New York State counties with the exception of Nassau County and Suffolk County.

Requirement for Application Submittal For use in all New York State counties with the exception of Nassau County and Suffolk County. 600 Town Hall Drive, Hudson, New York 12534 Phone and Fax: 518-822-8420 Email: bi@townofgreenport.com Website: greenport.yourtownhub.com New York State Unified Solar Permit Expedited Solar Permit Process

More information

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw)

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw) An applicant (Generator Owner) makes application to to install and operate a generating facility greater than 100 kw interconnected with the utility system. Section 1, Applicant Information Directly Interconnected

More information

Stakeholder Engagement Session on Long-Term Load and DER Forecasting July 14, 2017

Stakeholder Engagement Session on Long-Term Load and DER Forecasting July 14, 2017 Stakeholder Engagement Session on Long-Term Load and DER Forecasting July 14, 2017 Draft for Discussion Purposes Only 1 AGENDA Introduction Addressing Stakeholder Feedback from prior Engagements Consolidated

More information

DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY

DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY Dominica Electricity Services 2016 Version 2.00 DOCUMENT TITLE AND APPROVAL PAGE DOCUMENT NUMBER: 2016/002/D DOCUMENT TITLE: DISTRIBUTED RENEWABLE ENERGY

More information

Non Registered Embedded Generation Information Pack

Non Registered Embedded Generation Information Pack Non Registered Embedded Generation Information Pack > 30 KW to 5 MW Ergon Energy Network Embedded Generator Information Pack With a focus on energising our diverse QLD communities, we are committed to

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59933-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 59625-E Rule 21 Sheet 7 A. TABLE OF CONTENTS Hh. Smart Inverter Generating

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF FARMINGDALE NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

Get Connected: Distributed Generation

Get Connected: Distributed Generation Get Connected: Distributed Generation Our goal is to make sure your distributed generation project is connected safely and efficiently. Getting connected to our system is a six-phase process. Use this

More information

SCHEDULE SS STANDBY SERVICE

SCHEDULE SS STANDBY SERVICE SCHEDULE SS STANDBY SERVICE SHEET NO. 69 A. APPLICABILITY: Applicable to customers with alternate regular source(s) of energy other than electricity from the Company when such sources are connected to

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7

More information

Table of Contents Welcome... 2 Project Communication Hierarchy... 5 Electric, Gas, and Steam Interconnection Process Details... 6 Design Review...

Table of Contents Welcome... 2 Project Communication Hierarchy... 5 Electric, Gas, and Steam Interconnection Process Details... 6 Design Review... LEGAL DISCLAIMER: This guide is for informational purposes only and does not constitute legal advice. This does not substitute for any applicable laws, rules or regulations, tariffs, and/or specifications.

More information

LEVEL 1 Application for Interconnection and Net Metering

LEVEL 1 Application for Interconnection and Net Metering LEVEL 1 Application for Interconnection and Net Metering Use this application form only for a generating facility that is inverter based and certified by a nationally recognized testing laboratory to meet

More information

INTERCONNECTION APPLICATION AND AGREEMENT

INTERCONNECTION APPLICATION AND AGREEMENT INTERCONNECTION APPLICATION AND AGREEMENT With Terms and Conditions for Interconnection For a Level 1 Review (Certified Inverter-based Units under 10kW) Mailing Address PSE&G Net Metering 750 Walnut Avenue

More information

Feed-in-Tariff (FIT) Connection Application Guidelines

Feed-in-Tariff (FIT) Connection Application Guidelines Generation Planning & Transmission Capacity Feed-in-Tariff (FIT) Connection Application Guidelines These guidelines help to ensure efficient processing and implementation of the FIT project. It is important

More information

Peninsula Advanced Energy Community (PAEC) Task 2.10: Final Report on Policy Recommendations and Guidelines for Permitting Energy Storage

Peninsula Advanced Energy Community (PAEC) Task 2.10: Final Report on Policy Recommendations and Guidelines for Permitting Energy Storage Peninsula Advanced Energy Community (PAEC) Task 2.10: Final Report on Policy Recommendations and Guidelines for Permitting Energy Storage Prepared for California Energy Commission 1516 Ninth St., MS-51

More information

VIA ELECTRONIC FILING. August 29, 2014

VIA ELECTRONIC FILING. August 29, 2014 VIA ELECTRONIC FILING August 29, 2014 Hon. Kathleen H. Burgess Secretary to the Commission New York State Public Service Commission 3 Empire State Plaza Albany, New York 12223 1350 Ms. Julia Bovey Director

More information

Market Requirements Document

Market Requirements Document Market Requirements Document Committee name: Prepared by: Deployment Working Group Joseph H. Cain, P.E. Modified Date: 1.05.17 Revision Number: 1 This work was created under the DOE Project Number EE-0007315

More information

BGE Smart Energy Savers Program Combined Heat and Power Program Manual

BGE Smart Energy Savers Program Combined Heat and Power Program Manual BGE Smart Energy Savers Program Combined Heat and Power 2015-2017 Program Manual Page 1 of 20 Table of Contents Introduction... 3 Purpose... 3 Goal... 3 ICF s Role... 3 Overview of BGE... 3 BGE Service

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

DISTRIBUTED GENERATION INTERCONNECTION PROCEDURES. June 21, 2011

DISTRIBUTED GENERATION INTERCONNECTION PROCEDURES. June 21, 2011 DISTRIBUTED GENERATION INTERCONNECTION PROCEDURES June 21, 2011 Adopted June 28, 2011 Page i TABLE OF CONTENTS I. GENERAL CONSIDERATIONS 1 II. III. IV. SMALL DISTRIBUTED GENERATOR RESOURCES A. Application

More information

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems

More information

May 1, To: Parties currently registered on Proceeding Distributed Generation Review Proceeding Application A001

May 1, To: Parties currently registered on Proceeding Distributed Generation Review Proceeding Application A001 May 1, 2017 To: Parties currently registered on Proceeding 22534 Distributed Generation Review Proceeding 22534 Application 22534-A001 Process for Proceeding 22534 1. On March 31, 2017, the Alberta Utilities

More information

NYISO Pilot Program Guide

NYISO Pilot Program Guide NYISO Pilot Program Guide October 2017 Table of Contents ABOUT THE NYISO... 4 NYISO PILOT PROGRAM... 5 Overview of the Pilot Program... 5 Value of the Pilot Program to NYISO Stakeholders and Pilot Participants...

More information

INTRA-CITY MEMORANDUM OF UNDERSTANDING BETWEEN CERTIFIED NEIGHBORHOOD COUNCILS AND LOS ANGELES DEPARTMENT OF WATER AND POWER

INTRA-CITY MEMORANDUM OF UNDERSTANDING BETWEEN CERTIFIED NEIGHBORHOOD COUNCILS AND LOS ANGELES DEPARTMENT OF WATER AND POWER INTRA-CITY MEMORANDUM OF UNDERSTANDING BETWEEN CERTIFIED NEIGHBORHOOD COUNCILS AND LOS ANGELES DEPARTMENT OF WATER AND POWER This five-year Memorandum of Understanding (hereinafter MOU ) is mutually agreed

More information

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management:

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management: Evolution of Con Edison efforts in Energy Efficiency and Demand Management: Innovative programs and technologies, and their impacts on customers, contractors and the markets Con Edison Con Edison - Overview

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

Initial Distributed System Implementation Plan

Initial Distributed System Implementation Plan Initial Distributed System Implementation Plan Orange and Rockland Utilities, Inc. Case No. 14-M-0101 June 30, 2016 Table of Contents Introduction... 2 Executive Summary... 9 Chapter 1 Distribution System

More information

Power Saver TM Program

Power Saver TM Program Power Saver TM Program COMMERCIAL SOLAR PHOTOVOLTAIC PERFORMANCE-BASED INCENTIVE PROGRAM GUIDELINES These guidelines govern the procedures and qualifications for incentives under the Austin Energy Commercial

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit PROJECT ELIGIBILITY FOR UNIFIED PERMITTING PROCESS By submitting this application, the applicant attests that the proposed project meets the established

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF UPPER BROOKVILLE PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that

More information

ENERGEX Inverter Energy Systems

ENERGEX Inverter Energy Systems ENERGEX Inverter Energy Systems Connecting Your Inverter Energy System to the ENERGEX Network 8181 13.08.2010 ENERGEX Limited trading as ENERGEX ABN: 40 078 849 055 http://www.energex.com.au Requests and

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION- City of Elmira NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the

More information

Address of Installation Building Permit #

Address of Installation Building Permit # TOWN OF NISKAYUNA NY State Unified Solar Permit Application One Niskayuna Circle, Niskayuna NY 12309 Phone: 518-386-4522 Fax: 518-386-4592 Email: buiding@niskayuna.org The Town of Niskayuna has adopted

More information

Energy Efficiency and Economic Development Incentives in New York

Energy Efficiency and Economic Development Incentives in New York Energy Efficiency and Economic Development Incentives in New York Presented to EMPOWERACTIVE 2015 June 17, 2015 by Catherine Luthin, President Luthin Associates Program Goals Discuss the Reforming the

More information

Business Programs: Commercial and Industrial Renewable Energy Loan Program. Technical Application and Instructions

Business Programs: Commercial and Industrial Renewable Energy Loan Program. Technical Application and Instructions Business Programs: Commercial and Industrial Renewable Energy Loan Program Technical Application and Instructions DEFINITIONS Annual Cost Savings is the amount of energy cost savings that results from

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES

CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES SOP #.004 Title: MONITORING OF CONTRACT PERFOMANCE AND DELIVERABLES Version: 1 Approval Date: May 10, 2018 1. Purpose. The purpose of a contract monitoring

More information

REQUEST FOR PROPOSAL (RFP) FOR CONTRACT MANAGEMENT SYSTEM ISSUED BY THE RFP INFORMATION

REQUEST FOR PROPOSAL (RFP) FOR CONTRACT MANAGEMENT SYSTEM ISSUED BY THE RFP INFORMATION REQUEST FOR PROPOSAL (RFP) FOR CONTRACT MANAGEMENT SYSTEM ISSUED BY THE NEW YORK ehealth COLLABORATIVE CONTACT NAME EMAIL ADDRESS SUBMISSION DEADLINE RFP INFORMATION NYeC RFP rfpcontact@nyehealth.org September

More information

SOLAR PANEL INSTALLATIONS NYC Department of Buildings March 18, 2019

SOLAR PANEL INSTALLATIONS NYC Department of Buildings March 18, 2019 SOLAR PANEL INSTALLATIONS NYC Department of Buildings March 18, 2019 Agenda Solar Permits Processing at the DOB Overview General Requirements Solar Approval / Permit / Sign off Property Tax Abatement Program

More information

SOLAR PANEL INSTALLATION NYC Department of Buildings

SOLAR PANEL INSTALLATION NYC Department of Buildings SOLAR PANEL INSTALLATION NYC Department of Buildings Agenda Solar Permits Processing at the DOB: Overview General Requirements Solar Approval / Permit / Sign off Property Tax Abatement Program Zoning Requirements

More information

INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS

INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS March 2008 Table of Contents 1.0 Introduction 3 1.1 Scope 3 1.2 Copyright and Reprint 3 1.3 Disclaimer 3 1.4 Project Responsibilities

More information

Your guide to interconnecting to the We Energies distribution system

Your guide to interconnecting to the We Energies distribution system Your guide to interconnecting to the We Energies distribution system We appreciate the opportunity to serve you. This booklet provides some basic information about connecting customer generation systems,

More information

Objectives and Task Analysis for a Small Wind Energy System Installer

Objectives and Task Analysis for a Small Wind Energy System Installer North American Board of Certified Energy Practitioners Small Wind Technical Committee Document Approved December 7, 2006 Objectives and Task Analysis for a Small Wind Energy System Installer Introduction

More information

Technical Guideline for. Section 8. Inspection and Approval of Construction

Technical Guideline for. Section 8. Inspection and Approval of Construction Technical Guideline for Section 8. Inspection and Approval of Construction Ontario Regulation 22/04 Electrical Distribution Safety January 12, 2005 Technical Guideline Section 8 General Legal Disclaimer

More information

ISO New England - ISO New England Inc. Transmission, Markets and Services Tariff

ISO New England - ISO New England Inc. Transmission, Markets and Services Tariff ATTACHMENT K REGIONAL SYSTEM PLANNING PROCESS TABLE OF CONTENTS 1. Overview 2. Planning Advisory Committee 2.1 Establishment 2.2 Role of Planning Advisory Committee 2.3 Membership 2.4 Procedures (a) Notice

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section 19825 V 11-10-12 6p2s H:\2012 Permit Masters\v 11-10-12 e-inspection Residential PV Installation

More information

ORLANDO UTILITIES COMMISSION Open Access Transmission Tariff Original Sheet 91 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service The Transmission Customer shall compensate

More information

Rule 21 Working Group 3

Rule 21 Working Group 3 Rule 21 Working Group 3 CONFERENCE CALL JANUARY 16, 2019 HTTPS://WWW.UBERCONFERENCE.COM/GRIDWORKS https://gridworks.org/initiatives/rule-21-working-group-3/ Agenda 2:00-2:10 Regulatory updates 2:10-2:15

More information

City of Santa Monica Building and Safety Division Submittal Requirements Expedited Solar Photovoltaic (10 kw or Less)

City of Santa Monica Building and Safety Division Submittal Requirements Expedited Solar Photovoltaic (10 kw or Less) City of Santa Monica Building and Safety Division Submittal Requirements Expedited Solar Photovoltaic (10 kw or Less) Permits for One- and Two-Family Dwellings This following information is to guide applicants

More information

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION PLATEAU ELECTRIC COOPERATIVE INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION Policy B32 1 P a g e TABLE OF CONTENTS PAGE 1. GENERAL PROCEDURES & STANDARDS 3 1.1 Scope 1.2 Application for Interconnection

More information

Enabling Integration of Distributed Renewables - Program 174

Enabling Integration of Distributed Renewables - Program 174 Enabling Integration of Distributed Renewables - Program 174 Program Description Program Overview The integration of distributed renewable generation sources into the electricity grid poses a number of

More information

October 17, Advice No Electric Tariff Filing Filed Electronically

October 17, Advice No Electric Tariff Filing Filed Electronically October 17, 2018 Filed Via Web Portal Mr. Mark L. Johnson, Executive Director and Secretary Washington Utilities and Transportation Commission P.O. Box 47250 Olympia, WA 98504-7250 RE: Advice No. 2018-42

More information

SOLAR PANEL INSTALLATION NYC Department of Buildings April 26, 2018

SOLAR PANEL INSTALLATION NYC Department of Buildings April 26, 2018 SOLAR PANEL INSTALLATION NYC Department of Buildings April 26, 2018 Agenda Solar Permits Processing at the DOB Overview General Requirements Solar Approval / Permit / Sign off Property Tax Abatement Program

More information

Objectives and Task Analysis for a Professional Small Wind Energy System Installer

Objectives and Task Analysis for a Professional Small Wind Energy System Installer North American Board of Certified Energy Practitioners Objectives and Task Analysis for a Professional Small Wind Energy System Installer Introduction This document presents an in-depth task analysis for

More information

Exhibit A - Scope of Services AMI Implementation Project Management Services

Exhibit A - Scope of Services AMI Implementation Project Management Services Exhibit A - Scope of Services AMI Implementation Project Management Services Deliver to: City of Santa Rosa 90 Santa Rosa Avenue Santa Rosa, CA 95401 Attn: Kimberly Zunino City of Santa Rosa June 2, 2016

More information

Metering Procedures for PA Renewable Energy Credits (MPREC)

Metering Procedures for PA Renewable Energy Credits (MPREC) Metering Procedures for PA 11-80 Renewable Energy Credits (MPREC) Published: 01/01/2015 Revised: 08/08/2017 MPREC REV. 4 1.0 Introduction: A Facility must follow the metering specifications in Tables 1-1

More information

The State of Community Solar in New York Dennis Phayre EnterSolar, LLC

The State of Community Solar in New York Dennis Phayre EnterSolar, LLC The State of Community Solar in New York Dennis Phayre EnterSolar, LLC January 11 th, 2017 Halfmoon Community Solar Farm NY ISO Zones Halfmoon Solar Park EnterSolar Case Study EnterSolar developed and

More information

IEEE SCC21* Standards

IEEE SCC21* Standards IEEE SCC21* Standards M. Coddington, NREL; P. McNutt, NREL; T. Basso, NREL** and IEEE SCC21 Secretary; and R. DeBlasio, NREL and IEEE SCC 21 Chair Solar America Board for Codes and Standards National and

More information

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14 FERC Electric Tariff Page 1 of 2 ATTACHMENT N Small Generator Interconnection Procedures and Agreement (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

Business Requirements Specification

Business Requirements Specification Business s Specification Date Created: 3/19/2013 Doc ID: GNFDMDEHU6BB-46-53 Page 1 of 18 Disclaimer Business s Specification Date Created: 3/19/2013 All information contained in this draft Business s Specification

More information

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles Addressing Affected System Impacts of Generator Interconnection: Processes and Principles August 5, 2013 Table of Contents 1 Executive Summary... 2 2 Introduction... 2 3 Stakeholder Process and Schedule...

More information

Small Scale Solar Permit Application

Small Scale Solar Permit Application Town of Berne Small Scale Solar Permit Application Town of Berne PO Box 57 Berne, NY 12023 (518) 872-1448 2/14/18 PROJECT ELIGIBILITY FOR PERMITTING PROCESS By submitting this application, the applicant

More information

Distributed Renewable Energy Generation Interconnection Policy

Distributed Renewable Energy Generation Interconnection Policy Distributed Renewable Energy Generation Interconnection Policy Dominica Electricity Services 2010 Version Table of Contents Executive Summary... 2 1. Interconnection Policy... 6 1.1 Introduction... 6 1.2

More information

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets March 8, 2010 Revised Draft Final Proposal for Participation of Non- Generator Resources

More information