Feed-in-Tariff (FIT) Connection Application Guidelines

Size: px
Start display at page:

Download "Feed-in-Tariff (FIT) Connection Application Guidelines"

Transcription

1 Generation Planning & Transmission Capacity Feed-in-Tariff (FIT) Connection Application Guidelines These guidelines help to ensure efficient processing and implementation of the FIT project. It is important that you read and understand the application guidelines before completing any forms. If you have any questions or concerns, please or call For technical requirements associated with the connection of the Embedded Generation project, please refer to the following documents, also located at The Toronto Hydro Conditions of Service Complete Document (i.e. including the reference documents) contains among other things information for the connection of distributed generation facilities. Distributed Generation Requirements, one of the reference documents attached to the Conditions of Service outlines the classifications and general terms and conditions for the connection of distributed generation facility to the distribution system. Toronto Hydro Parallel Generation Requirements, an attachment to the Distributed Generation Requirements document provides technical requirements for interconnecting parallel generation greater than 0 kw. Toronto Hydro Requirements for the Design & Construction of Customer-Owned High Voltage Substations, section 6, Reference #4 in the Conditions of Service provides guidance for the design and construction of.8 kv and 7.6 kv customer owned substations, including substation switchgear and primary cable. Contents Submission of Application... Solar PV CIA Cost & Payment... CIA Completion and OPA Notice to Proceed... Documents Required for Processing CCA/OTC... ESA Certification & Commissioning Reports... FIT Processing Checklists... 4 FIT Application Checklist... 4 Connection Cost Agreement/Offer to Connect Checklist... 5 Final Inspection Checklist... 6 FIT Connection Application Guidelines - March 4, 04

2 Generation Planning & Transmission Capacity. Submission of Application Payment is required for the processing of the application. Please attach a copy of your payment information with your application. Please submit the completed Embedded Generation Connection Application Form with the required documents including copy of payment information to the attention of: Gary Thompson, Generation Planning Section 500 Commissioners Street, rd Floor Electronic copies of all documents shall be submitted to fit@torontohydro.com.. Solar Photovoltaic (PV) Connection Impact Assessment (CIA) Cost & Payment The estimated cost for preparing the CIA for solar PV FIT Capacity Allocation Exempt project is $500 plus HST. Applicant will be advised of further costs associated with the processing and implementation of the FIT project. Completed CIA s are valid for months. Any revisions due to expired CIA s will be subjected to an estimated cost of $800 plus HST. Any material revisions to the design, planned equipment or plans for the embedded generation facility shall be filed with Toronto Hydro and a new CIA will be prepared as per Distribution System Code (DSC) section The estimated cost for preparing the revised CIA is $800 plus HST. Please submit CIA payment fee payable to. Official invoice(s) stamped paid will be sent for your records. CIA payment fee AND first page of the Embedded Generation Connection Application Form will be submitted directly to: 500 Commissioners Street, Toronto ON M4M N7 Attn: Ellipse Miscellaneous Accounts Receivable **PLEASE NOTE THIS IMPORTANT CHANGE IN PROCEDURE**: There is no longer an option to drop-off applications and payments. All applications and payments must be sent to Toronto Hydro via Canada Post, or courier, at the above address.. Connection Impact Assessment completion and OPA Notice to Proceed The applicant will submit the completed CIA to the Ontario Power Authority (OPA) in order to obtain Notice to Proceed (NTP). A FIT project must receive NTP approval from the OPA in order to connect to the Toronto Hydro distribution system. FIT Connection Application Guidelines - March 4, 04

3 Generation Planning & Transmission Capacity 4. Documents Required for Processing Connection Cost Agreement - Offer To Connect. (CCA/OTC) Upon receiving NTP approval, Toronto Hydro will provide the applicant with the connection costs associated with connection to the Toronto Hydro grid in the CCA/OTC. The following is required for the processing of the CCA/OTC;. Copy of Ontario Power Authority contract (signed by Proponent and OPA).. In the case where the supplier name and the Toronto Hydro customer name for the existing service are different, a signed agreement that authorizes the supplier to have access to the roof top for the PV installation is required. Typically this is referred to as an Agreement.. Copy of the Notice to Proceed. 4. Construction schedule indicating relevant project dates. Note: Revenue meters and instrument transformers can only be provided after there is an executed Connection Cost Agreement Offer to Connect (CCA/OTC) between the parties. 5. Electrical Safety Authority (ESA) Certification & Commissioning Reports Once there is an executed CCA/OTC, the following documentation is required in order to connect the DG facility to Toronto Hydro s distribution system:. A scanned copy of the ESA notice of inspection shall be ed to Generation Planning section (fit@torontohydro.com) as soon as the final ESA inspection is completed. Please specify in the subject line: ESA Notice of inspection, project address and FIT ID number.. Single line electrical drawing which identifies the as constructed Connection Point (must be signed, dated and sealed by a Professional Engineer who is registered in the province of Ontario).. A Commissioning Report certified by an Independent Professional Engineer as per Toronto Hydro Distribution Generation Requirements (section Commissioning and Testing). Any material revisions to the design, planned equipment or plans for the embedded generation facility shall be filed with Toronto Hydro and a new CIA will be prepared as per Distribution System Code (DSC) section The new CIA will be performed at the Generator s expense. The estimated cost for a revised CIA is $800 plus HST FIT Connection Application Guidelines - March 4, 04

4 Generation Planning Transmission Capacity Toronto Hydro Electric System Limited FIT APPLICATION CHECKLIST To be completed by Applicant Project Address: FIT Project Ref. Number: FIT - F Project Size (kw): FIT Application Yes No Send to Completed Embedded Generation Connection Application Form signed by applicant Completed Connection Impact Assessment Generator Form signed by applicant Single Line Diagram (SLD) stamped and signed by a Professional Engineer Notes 4 Site plan including details of meter location and room layout 5 Inverter Manufacturer information i. Protection Philosophy ii. Settings iii. Single Line Diagram of inverter iv. Internal transformer specifications 6 Monitoring and Control information 7 Copy of Ontario Power Authority (OPA) contract (signed by Proponent and OPA) 8 CIA Application Fee & first page of Embedded Generation Connection Application Form (Item ) AR 9 Copy of CIA Application Fee (Item 8) - Generation Planning, Gary Thompson AR- Ellipse Miscellaneous Accounts Receivable 500 Commissioners St, rd Floor 500 Commissioners St * Note: A single-phase inverter can ONLY connect on a single-phase system and a three-phase inverter MUST be used on a three-phase system. Single-phase inverters WILL NOT be allowed to connect on three-phase systems. Print Applicant Signature Date FIT Application Checklist March 4, 04

5 Generation Planning Transmission Capacity Toronto Hydro Electric System Limited CONNECTION COST AGREEMENT/OFFER TO CONNECT (CCA/OTC) CHECKLIST To be completed and submitted by Applicant Project Address: FIT Project Ref. Number: FIT - F Project Size (kw): 4 5 Documentation confirming OPA approval of (if applicable): i. Supplier Information Update ii. Change in contract capacity Copy of Ontario Power Authority (OPA) Contract (signed by Proponent and OPA) Signed agreement that authorizes the Supplier to have access to the rooftop for the PV installation (if applicable) Copy of the OPA Notice to Proceed Construction schedule Connection Cost Agreement /Offer to Connect Information Yes No Notes DG Owner Contact Details. DG Owner:. DG Owner Address:. Contact Person: Tel: Cell: OTC CCA Checklist March 5, 0

6 Generation Planning Transmission Capacity Toronto Hydro Electric System Limited FINAL INSPECTION CHECKLIST To be completed by Applicant Project Address: FIT Project Ref. Number: FIT - F Final Inspection Information Project Size (kw): Yes No Notes 4 5 Project is installed as per "Toronto Hydro - Parallel Connection Outline" DG System metering voltage, phase and wire is identical to load meter Meter base is as per Section 6 - Reference #6 "Toronto Hydro - Electric Systems Metering Requirements 750 Volts or Less" in the Condition of Service ESA Notice of Inspection All labels are 75mm x 9mm lamacoid plate c/w minimum 6mm high white letters on black background and fastened to respective item 6 Labels Installed: LOAD METER AND GENERATOR METER DG SYSTEM DISCONNECT WARNING - TWO PARALLEL SOURCE SYSTEM GENERATOR & UTILITY PARALLEL GENERATOR on overhead connection standpipe PARALLEL GENERATOR in vault or equipment room PARALLEL GENERATOR on pad-mounted equipment Exterior isolating device is visible, accessible and lockable 4/7 Exterior isolating device is locked with "U" bolt DG Distribution panel or Disconnect is in same location as meter DG Distribution panel or Disconnect is labelled "Parallel Generator Source" Meter room isolating devices are within m of the "Generator" meter Additional disconnect switch is installed (connected to a splitter for meter base isolation) Generator Meter location in the same room as the Load Meter Dedicated Bell line is installed from "Generator" meter to the "Load" meter On-site contact for Bell phone line activation Applicant Signature Final Inspection Checklist March 5, 0 Date

How to Connect Your Generation Facility ( 10 kw) To Kitchener-Wilmot Hydro s Distribution System

How to Connect Your Generation Facility ( 10 kw) To Kitchener-Wilmot Hydro s Distribution System Title: Customer Guideline File No. 7542-2009-2 Prepared by: S. Wang Document No. Approved by: M. B. McKague Effective Date: Oct. 22, 2009 Revision Date: June 5, 2014 KWHDG-1 Rev: 3 How to Connect Your

More information

INTERCONNECTION APPLICATION AND AGREEMENT

INTERCONNECTION APPLICATION AND AGREEMENT INTERCONNECTION APPLICATION AND AGREEMENT With Terms and Conditions for Interconnection For a Level 1 Review (Certified Inverter-based Units under 10kW) Mailing Address PSE&G Net Metering 750 Walnut Avenue

More information

APPLICATION FOR SOLAR PERMIT

APPLICATION FOR SOLAR PERMIT APPLICATION FOR SOLAR PERMIT Permit Application Application Checklist o New York State Unified Solar Permit Application for Roof Mounted Systems 12kW or less. (Includes Electrical Permit Application) o

More information

Photovoltaic System Installation Request for Proposals. St. Mary s School, Boise, ID

Photovoltaic System Installation Request for Proposals. St. Mary s School, Boise, ID Photovoltaic System Installation Request for Proposals St. Mary s School, Boise, ID This Request for Proposals ( RFP ) is to solicit competitive quotes from photovoltaic (PV) system installers to design

More information

Solar microfit Program

Solar microfit Program Solar microfit Program Green Energy Act 2009 The act aims to expand Ontario s renewable energy production and create clean-energy jobs by: Creating a feed-in-tariff program that guarantees rates for energy

More information

RENEWABLE ENERGY ELECTRIC GENERATING SYSTEM APPLICATION INSTRUCTIONS

RENEWABLE ENERGY ELECTRIC GENERATING SYSTEM APPLICATION INSTRUCTIONS RENEWABLE ENERGY ELECTRIC GENERATING SYSTEM APPLICATION INSTRUCTIONS All renewable energy systems require an electrical permit. In some cases, a building permit is also required. The following process

More information

Address of Installation Building Permit #

Address of Installation Building Permit # TOWN OF NISKAYUNA NY State Unified Solar Permit Application One Niskayuna Circle, Niskayuna NY 12309 Phone: 518-386-4522 Fax: 518-386-4592 Email: buiding@niskayuna.org The Town of Niskayuna has adopted

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF FARMINGDALE NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION FortisAlberta s Distributed Energy Resource (DER) Process explains what is required

More information

City of Santa Monica Building and Safety Division Submittal Requirements Expedited Solar Photovoltaic (10 kw or Less)

City of Santa Monica Building and Safety Division Submittal Requirements Expedited Solar Photovoltaic (10 kw or Less) City of Santa Monica Building and Safety Division Submittal Requirements Expedited Solar Photovoltaic (10 kw or Less) Permits for One- and Two-Family Dwellings This following information is to guide applicants

More information

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw)

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw) An applicant (Generator Owner) makes application to to install and operate a generating facility greater than 100 kw interconnected with the utility system. Section 1, Applicant Information Directly Interconnected

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section 19825 V 11-10-12 6p2s H:\2012 Permit Masters\v 11-10-12 e-inspection Residential PV Installation

More information

Small Scale Solar Permit Application

Small Scale Solar Permit Application Town of Berne Small Scale Solar Permit Application Town of Berne PO Box 57 Berne, NY 12023 (518) 872-1448 2/14/18 PROJECT ELIGIBILITY FOR PERMITTING PROCESS By submitting this application, the applicant

More information

Commercial Solar Photovoltaic System Permit

Commercial Solar Photovoltaic System Permit Commercial Solar Photovoltaic System Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning

More information

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) This application, terms, and conditions, and Interconnection Agreement is for Xcel Energy customers requesting the installation of a small generation

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF UPPER BROOKVILLE PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION Town of Warwick Building Department (845) 986-1127 NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit PROJECT ELIGIBILITY FOR UNIFIED PERMITTING PROCESS By submitting this application, the applicant attests that the proposed project meets the established

More information

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1 INDEX Page SECTION 1.0: SCOPE 1 1.1 Toronto Hydro Requirements 1 1.2 Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1 SECTION 3.0: DEFINITIONS AND THE INTERNATIONAL SYSTEM OF UNITS 1 3.1 Definitions

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION- City of Elmira NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the

More information

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW

More information

Feed-In Tariff (FIT) MUNICIPAL COUNCIL SUPPORT RESOLUTION GUIDE & APPLICATION

Feed-In Tariff (FIT) MUNICIPAL COUNCIL SUPPORT RESOLUTION GUIDE & APPLICATION This document contains both information and form fields. To read information, use the Down Arrow from a form field. Feed-In Tariff (FIT) MUNICIPAL COUNCIL SUPPORT RESOLUTION GUIDE & APPLICATION MATERIALS

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

Requirement for Application Submittal For use in all New York State counties with the exception of Nassau County and Suffolk County.

Requirement for Application Submittal For use in all New York State counties with the exception of Nassau County and Suffolk County. 600 Town Hall Drive, Hudson, New York 12534 Phone and Fax: 518-822-8420 Email: bi@townofgreenport.com Website: greenport.yourtownhub.com New York State Unified Solar Permit Expedited Solar Permit Process

More information

REVISION NO.: 8 EFFECTIVE: 03/26/18

REVISION NO.: 8 EFFECTIVE: 03/26/18 Distributed Generation Interconnection Process for Residential and Small General Service OVERVIEW REVISION NO.: 8 EFFECTIVE: 03/26/18 Required Steps for ED3 s Distributed Generation Interconnection Process

More information

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating

More information

Request for Proposals for Photovoltaic System Installation

Request for Proposals for Photovoltaic System Installation Request for Proposals for Photovoltaic System Installation Presented by: Mason County Public Utility District No. 1 Prepared by: Locations: Contact: Bonneville Environmental Foundation, Renewable Energy

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 614 NOVEMBER 2012 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT TABLE OF CONTENTS 614.01 SCOPE 614.02 REFERENCES 614.03 DEFINITIONS

More information

CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY

CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY Page 1 of 5 REFERENCE Denver Building and Fire Code (DBC) Section 131, International Residential Code (IRC) Section M2301, the National Electrical Code (NEC) Articles 690 & 705 PROCEDURE The procedure

More information

Solar PV User Guide for Residential Consumers

Solar PV User Guide for Residential Consumers Table of Contents 1. Introduction... 2 2. Electricity Generation Licence... 3 3. Electrical Installation... 3 4. Connection Requirements... 5 5. Market Settlement... 7 6. Monitoring Requirements... 8 7.

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

SUBMITTAL REQUIREMENTS FOR EXPEDITED ROOF TOP SOLAR PERMITTING

SUBMITTAL REQUIREMENTS FOR EXPEDITED ROOF TOP SOLAR PERMITTING KERN COUNTY PUBLIC WORKS DEPARTMENT CRAIG M. POPE, P.E., DIRECTOR 2700 M STREET BAKERSFIELD, CA 93301-2370 ADMINISTRATION & ACCOUNTING OPERATIONS & MAINTENANCE BUILDING & DEVELOPMENT ENGINEERING Phone:

More information

GRENLEC s Renewable Standard Offer

GRENLEC s Renewable Standard Offer GRENLEC s Renewable Standard Offer Version: 1.1 Last Updated: September 10 th, 2011 This document provides as a general overview of the Customer-owned Renewable Generation Standard Offer, for the purchase

More information

Code Change Alert: Permitting of Solar Photovoltaic Systems in Washington State

Code Change Alert: Permitting of Solar Photovoltaic Systems in Washington State Code Change Alert: Permitting of Solar Photovoltaic Systems in Washington State Emergency Rule Regarding Rooftop Solar Photovoltaic Installations On June 13, 2014 the Washington State Building Code Council

More information

GPI Conditions of Service - Revision History The following is a summary of key changes made to the document.

GPI Conditions of Service - Revision History The following is a summary of key changes made to the document. Identification of Grimsby Power 1.1 Added licence number. and Service Area 1.1.1 Distribution Overview Added Niagara West Municipal Transformer Station. Added section with general information about servicing,

More information

Addition to Section 4 - Special Use Regulations

Addition to Section 4 - Special Use Regulations Large-Scale Ground-Mounted Solar Photovoltaic Installations Addition to Section 4 - Special Use Regulations 4.4 Large Scale Ground-Mounted Solar Photovoltaic Installations 4.4.1 Purpose The purpose of

More information

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017 Net Energy Metering 2.0 Solar PV Interconnection Handbook Effective December 1, 2017 Important Information The NEM 1.0 solar PV rate is closed. The NEM 2.0 is the current PV rate option available for solar

More information

Power Saver TM Program

Power Saver TM Program Power Saver TM Program COMMERCIAL SOLAR PHOTOVOLTAIC PERFORMANCE-BASED INCENTIVE PROGRAM GUIDELINES These guidelines govern the procedures and qualifications for incentives under the Austin Energy Commercial

More information

Building and Safety Division Public Information

Building and Safety Division Public Information B&S STD E-18 Solar Photovoltaic (PV) Systems Revised: January, 2017 The following document outlines the requirements for the issuance of building and electrical permits for solar photovoltaic systems.

More information

atlantic cit~ elect,ic

atlantic cit~ elect,ic atlantic cit~ elect,ic A PHI Company NEW JERSEY LEVEL 1 INTERCONNECTION APPLICATION/AGREEMENT With Terms and Conditions for Interconnection For a Level 1 Review (Certified Inverter-Based Generators 10kW

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

ELECTRICAL INSPECTION BULLETIN (Effective )

ELECTRICAL INSPECTION BULLETIN (Effective ) ELECTRICAL INSPECTION BULLETIN (Effective 2009-02-01) Rule 36-000 Customer Owned High Voltage Installations With the increase in customer own high voltage equipment there appears to be confusion over which

More information

Bulletin Grounding and bonding of solar photovoltaic systems Rules , , , and

Bulletin Grounding and bonding of solar photovoltaic systems Rules , , , and Bulletin 64-2-0 Grounding and bonding of solar photovoltaic systems Rules 64-064, 64-066, 64-068, 64-070 and 64-222 Scope (1) Introduction (2) Grounding of solar photovoltaic system output, ac grounding

More information

Union Power Cooperative

Union Power Cooperative Union Power Cooperative INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities of the local

More information

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT Mike Lara Building Official PHOTOVOLTAIC PERMITTING GUIDELINES PLANS AND PERMITS In order to minimize installation problems, plans must be provided that

More information

New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric

New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric New York State Unified Solar Permit Expedited Solar Permit Process for Small-Scale Roof-Mounted Residential and Commercial Solar Electric Requirements for Application Submittal Part A For use in all New

More information

Interconnection Application

Interconnection Application Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

Dated: April 16, 2002

Dated: April 16, 2002 Central Hudson Gas & Electric Corporation (CHG&E) Application Process for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System Dated: April 16,

More information

Get Connected: Distributed Generation

Get Connected: Distributed Generation Get Connected: Distributed Generation Our goal is to make sure your distributed generation project is connected safely and efficiently. Getting connected to our system is a six-phase process. Use this

More information

Solar Photovoltaic (PV) Incentive Program. Shannon Ripley, Environmental Services

Solar Photovoltaic (PV) Incentive Program. Shannon Ripley, Environmental Services Solar Photovoltaic (PV) Incentive Program Shannon Ripley, Environmental Services shannon.ripley@banff.ca Information Session April 6, 2017 Overview Town of Banff municipal solar installations Why did the

More information

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017 Net Energy Metering 2.0 Solar PV Interconnection Handbook Effective January 1, 2017 Overview This Handbook illustrates the steps, processes, and requirements to apply for a Solar Photovoltaic (PV) interconnection

More information

Large Distributed Generation Process Guide

Large Distributed Generation Process Guide Scotland Large Distributed Generation Process Guide A guide to applying for embedded generation which export 10MW or more 2 Large Distributed Generation Guide Evelis rem quiditiunt et utendipit. Contents

More information

Connecting to the network information pack Version 1

Connecting to the network information pack Version 1 Connecting to the network information pack Version 1 Contents 1.0 What is a new connection or connection alteration?... 3 2.0 Connection enquiry... 3 3.0 Connection application... 3 3.1 Processing your

More information

Solar PV User Guide for Generators

Solar PV User Guide for Generators Table of Contents 1. Introduction... 2 2. Electricity Generation Licence... 4 3. Electrical Installation... 4 4. Connection Requirements... 6 5. Market Settlement... 9 6. New Pricing Mechanism... 10 7.

More information

PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS

PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS Building Division 555 Santa Clara Street Vallejo CA 94590 707.648.4374 1. PERMIT INFORMATION: The installation of a photovoltaic solar electric system requires

More information

Cluster Study Process

Cluster Study Process Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO

More information

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION PLATEAU ELECTRIC COOPERATIVE INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION Policy B32 1 P a g e TABLE OF CONTENTS PAGE 1. GENERAL PROCEDURES & STANDARDS 3 1.1 Scope 1.2 Application for Interconnection

More information

REQUEST FOR PROPOSAL RFP 31 ( ) INDO-MALAYA PAVILION GENERATOR REPLACEMENT ADDENDUM #1

REQUEST FOR PROPOSAL RFP 31 ( ) INDO-MALAYA PAVILION GENERATOR REPLACEMENT ADDENDUM #1 2018-09-07 REQUEST FOR PROPOSAL RFP 31 (2018-08) INDO-MALAYA PAVILION GENERATOR REPLACEMENT This addendum shall be incorporated into, and form part of RFP 31 (2018-08) and take precedence over all requirements

More information

This application process is for the New Modernized Drive Clean Program that uses the new OBD II and/or TSI, and Heavy Duty test equipment.

This application process is for the New Modernized Drive Clean Program that uses the new OBD II and/or TSI, and Heavy Duty test equipment. DRIVE CLEAN ACCREDITATION CHECKLIST How to Become a Light Duty Test Only, Test & Repair, Repair Only, Heavy Duty Non-Diesel, or Heavy Duty Diesel (Mobile or Non-Mobile) Drive Clean Facility Important Complete

More information

Solar Rooftop PV Municipal regulation, application, approval etc. processes. GIZ - All rights reserved

Solar Rooftop PV Municipal regulation, application, approval etc. processes. GIZ - All rights reserved Solar Rooftop PV Municipal regulation, application, approval etc. processes Hardcopies participants will need: Full AMEU resource pack Process flow diagram Application process checklist Filled in application

More information

FY2017 SREC Registration Program (SRP) Final As-Built Technical Worksheet Instructions Page 1

FY2017 SREC Registration Program (SRP) Final As-Built Technical Worksheet Instructions Page 1 If the SRP Registration was submitted in paper form, the Final As Built Packet must be submitted in paper. If the SRP Registration was submitted via the online portal, the Final As Built documents must

More information

ROOFTOP PV GUIDELINES FOR SAFE AND LEGAL INSTALLATIONS IN CAPE TOWN

ROOFTOP PV GUIDELINES FOR SAFE AND LEGAL INSTALLATIONS IN CAPE TOWN Photo credit: Bruce Sutherland, City of Cape Town. Grid-tied PV system at the City of Cape Town s Royal Ascot building. ROOFTOP PV GUIDELINES FOR SAFE AND LEGAL INSTALLATIONS IN CAPE TOWN If you are considering

More information

CONTACT INFORMATION. PV System will require a separate Electrical Permit.

CONTACT INFORMATION. PV System will require a separate Electrical Permit. SOLAR APPLICATION P. O. Box 72 Mountlake Terrace, WA 98043 Phone 425.744.6267 Fax 425.778.6421 PermitSpecialist@ci.mlt.wa.us www.cityofmlt.com Application # Job Site Address Single-Family Residential Multi-Family

More information

INVITATION TO BID ITB _UNDP PSU Clarifications 2 to Bidders 02/08/2016

INVITATION TO BID ITB _UNDP PSU Clarifications 2 to Bidders 02/08/2016 Question 1: LOT 2: Plug and play PV system with cabinet for ZIMBABWE: item 1.4: Minimum IP 55 class storage cabinet. and LOT 3: Plug and play PV system with cabinet for ZIMBABWE: item 1.5: Minimum IP 55

More information

DRAFT Commercial Solar Bylaw November 8, 2011

DRAFT Commercial Solar Bylaw November 8, 2011 145-28. Commercial Solar Photovoltaic Installations A. Purpose This bylaw is to encourage the use of solar energy systems and protect solar access consistent with MGL 40A 9B and with the Green Communities

More information

TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR ENERGY CONVERSION SYSTEM S

TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR ENERGY CONVERSION SYSTEM S TOWN OF DEWITT PLANNING AND ZONING PERMIT REQUIREMENTS FOR ENERGY CONVERSION SYSTEM S 1) This will apply to the installation of solar photovoltaic systems. 2) All units to be installed according to the

More information

Request for New Point of Receipt

Request for New Point of Receipt Request for New Point of Receipt Overview of Process Upon completion and Submission of the New Point of Receipt form: Millennium will provide an Interconnect Agreement including but not limited to outlining

More information

Board Staff Discussion Paper

Board Staff Discussion Paper Ontario Energy Board Board Staff Discussion Paper on Issues Related to the Connection of Micro-Embedded Generation Facilities EB-2012-0246 December 20, 2012 - 2 - INTRODUCTION Prior to the introduction

More information

Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects

Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects Date, Venue, etc..( Arial, Font size 18 ) 3 rd April 2012 1 Renewable Energy Portfolio of Tata Power Mithapur 25 MW Samana 50 MW Mulshi

More information

Clarifications in Methodology of Grid Connected Roof top solar projects in the state of Maharashtra.

Clarifications in Methodology of Grid Connected Roof top solar projects in the state of Maharashtra. Clarifications in Methodology of Grid Connected Roof top solar projects in the state of Maharashtra. Sr.No. Queries MNRE requirement Clarification As per the methodology manufacturers has to NA As the

More information

INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS

INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS March 2008 Table of Contents 1.0 Introduction 3 1.1 Scope 3 1.2 Copyright and Reprint 3 1.3 Disclaimer 3 1.4 Project Responsibilities

More information

Technical Guideline for. Section 8. Inspection and Approval of Construction

Technical Guideline for. Section 8. Inspection and Approval of Construction Technical Guideline for Section 8. Inspection and Approval of Construction Ontario Regulation 22/04 Electrical Distribution Safety January 12, 2005 Technical Guideline Section 8 General Legal Disclaimer

More information

PETERBOROUGH UTILITIES INC.

PETERBOROUGH UTILITIES INC. 2245 Keene Road, PO Box 4125, Station Main Peterborough ON K9J 6Z5 August 13, 2014 PROJECT SCOPE SUMMARY Peterborough Utilities Inc. (PUI) will be constructing one (1) rooftop and twelve (12) ground mount

More information

Professional Corporation Application for Registration (Form 4-6C)

Professional Corporation Application for Registration (Form 4-6C) Chartered Professional Accountants of Ontario 69 Bloor Street East Toronto ON M4W 1B3 T. 416 962.1841 Toll free 1 800 387.0735 cpaontario.ca Professional Corporation Application for Registration (Form

More information

Non Registered Embedded Generation Information Pack

Non Registered Embedded Generation Information Pack Non Registered Embedded Generation Information Pack > 30 KW to 5 MW Ergon Energy Network Embedded Generator Information Pack With a focus on energising our diverse QLD communities, we are committed to

More information

ROCHESTER PUBLIC UTILITIES

ROCHESTER PUBLIC UTILITIES ROCHESTER PUBLIC UTILITIES INTERCONNECTION REQUIREMENTS Distribution Connected Distributed Generation Systems (40kW 10MW) (Version 1.1) 1 Revision History Date Revision Description Version # Revised by

More information

SOLAR PANEL INSTALLATION NYC Department of Buildings

SOLAR PANEL INSTALLATION NYC Department of Buildings SOLAR PANEL INSTALLATION NYC Department of Buildings Agenda Solar Permits Processing at the DOB: Overview General Requirements Solar Approval / Permit / Sign off Property Tax Abatement Program Zoning Requirements

More information

SOLAR PANEL INSTALLATIONS NYC Department of Buildings March 18, 2019

SOLAR PANEL INSTALLATIONS NYC Department of Buildings March 18, 2019 SOLAR PANEL INSTALLATIONS NYC Department of Buildings March 18, 2019 Agenda Solar Permits Processing at the DOB Overview General Requirements Solar Approval / Permit / Sign off Property Tax Abatement Program

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT NETWORK SYSTEMS SECTION SPECIFICATION EO-4133 REVISION 2 OCTOBER, 2006 GENERAL REQUIREMENTS

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

Welcome to Douglas County PUD

Welcome to Douglas County PUD Welcome to Douglas County PUD We are committed to providing the best possible utility services at the lowest possible cost consistent with sound business principles. To better serve you, please fill out

More information

Generator Interconnection Process. Wholesale Distribution Overview

Generator Interconnection Process. Wholesale Distribution Overview 1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation

More information

Anguilla Electricity Company Limited. Request for Proposal. Battery System. Anguilla Electricity Company Limited P.O. Box 400 The Valley Anguilla

Anguilla Electricity Company Limited. Request for Proposal. Battery System. Anguilla Electricity Company Limited P.O. Box 400 The Valley Anguilla Anguilla Electricity Company Limited Request for Proposal Battery System Anguilla Electricity Company Limited P.O. Box 400 The Valley Anguilla Request for Proposal Schedule Release Date: June 20, 2017

More information

RECOMMENDATIONS FOR EXPEDITED PERMITTING FOR SMALL PV SYSTEMS

RECOMMENDATIONS FOR EXPEDITED PERMITTING FOR SMALL PV SYSTEMS 3 RECOMMENDATIONS FOR EXPEDITED PERMITTING FOR SMALL PV SYSTEMS A streamlined, expedited permit process for small solar PV systems that simplifies and consolidates the structural, electrical and fire review

More information

PV ENDORSEMENT REGISTRY APPLICATION FORM FOR SOLAR PV SUPPLIERS/INSTALLERS. This application is valid for a year from to

PV ENDORSEMENT REGISTRY APPLICATION FORM FOR SOLAR PV SUPPLIERS/INSTALLERS. This application is valid for a year from to Seychelles Energy Commission Room No. 307 & 308, Block B, Unity House, Victoria, Mahe, Seychelles. Tel: 4 610 819 Email: info@sec.sc Website: www.sec.sc 1 PV ENDORSEMENT REGISTRY APPLICATION FORM FOR SOLAR

More information

effective date 1/8/01

effective date 1/8/01 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical

More information

Solar Photovoltaic System Permit

Solar Photovoltaic System Permit Solar Photovoltaic System Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts,

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org C5-1036 AORC Technical meeting 2014 Solar PV Rooftop System Connection to MEA s Distribution Network: Technic and Economic Aspects Tosak Thasananutariya Metropolitan Electricity

More information

Bid form for installation of Solar PV Rooftop System at PNR Society Bhavnagar

Bid form for installation of Solar PV Rooftop System at PNR Society Bhavnagar Bid form for installation of Solar PV Rooftop System at PNR Society Bhavnagar PNR Society Bhavnagar invites technical and financial bids for installation of 85 (50 kw and 35 kw) Solar PV Rooftop System

More information

Solar PV User Guide for Generators

Solar PV User Guide for Generators Table of Contents 1. Introduction... 2 2. Electricity Generation Licence... 4 3. Electrical Installation... 4 4. Connection Requirements... 6 5. Market Settlement... 11 6. New Pricing Mechanism... 12 7.

More information

EXTERNAL REVENUE. Updated: EB Exhibit E1 Tab 1 Schedule 2 Page 1 of STRATEGY

EXTERNAL REVENUE. Updated: EB Exhibit E1 Tab 1 Schedule 2 Page 1 of STRATEGY Page of.0 STRATEGY EXTERNAL REVENUE Hydro One Distribution s strategy is to focus on core work and continue to be responsive to external work requests and accommodate customer needs where Hydro One Distribution

More information

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

Building Codes in Effect: 2010 California Building, Residential, Fire, Energy and Electrical Codes, including Article 690.

Building Codes in Effect: 2010 California Building, Residential, Fire, Energy and Electrical Codes, including Article 690. AGUA CALIENTE BAND OF CAHUILLA INDIANS A SOVEREIGN TRIBAL GOVERNMENT Planning & Development Department Building and Safety Division 5401 Dinah Shore Drive Palm Springs, CA 92264 (760) 669-6800 RESIDENTIAL

More information

BUILDING/FIRE/ZONING PERMIT GUIDE

BUILDING/FIRE/ZONING PERMIT GUIDE BUILDING/FIRE/ZONING PERMIT GUIDE Summary Guidelines The following is an instructional guide that will serve to assist you in securing the various permits issued by the Bureau of Code Administration. In

More information

BULLETIN SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS, AND ELECTRIC SERVICE REQUIREMENT CHANGES OR ADDITIONS

BULLETIN SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS, AND ELECTRIC SERVICE REQUIREMENT CHANGES OR ADDITIONS SaskPower Electrical Inspections BULLETIN 01-2017 February 15, 2017 TO: LICENSED ELECTRICAL CONTRACTORS ELECTRICAL CONSULTANTS AND ENGINEERS SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS,

More information