Project Scheduler for Smart Project Management XLGantt User Manual
|
|
- Sophie Wilkins
- 6 years ago
- Views:
Transcription
1 Project Scheduler for Smart Project Management XLGantt User Manual Version Jun 6, 2017
2 Contents XLGantt Update History Quick Start Guide What is XLGantt? XLGantt Interface Features of XLGantt 1) Task Management and Progress Calculation ) Gantt Chart ) Analysis Report ) Schedule Change Management ) Deliverables ) Adding Tasks to Microsoft Outlook Calendar ) Multilingual Support ) Importing Schedules from Another File ) Setting Nonworking Days ) Integration with Excel Features Glossary When an Error Occurred..., Terms of Use / Contact / 26
3 XLGantt Update History XLGantt version : 05/03/2017 Release - Added the feature to automatically set the earliest start date and the latest finish date of the tasks to project start-finish date. - Modified to display as a group item even if no date is entered for the task. - Fixed an error that occurs when you save XLGantt file to a different name. XLGantt version : 12/01/2016 Release - Multilingual Support (Korean and English are added). - Added analysis features(analysis of workload per person, calculation of planned progress). - Fields(columns) and rows can be added, user-defined functions available. - Text color and background color of tasks can be changed. 2 / 26
4 Quick Start Guide If you want to get started quickly, proceed as follows. For details, please refer to the detail page for each item. 1 Enable macros If you want to use the macro when opening XLGantt file, select "Enable". If not selected, XLGantt program will not run. 3 Enter the project information Click the Options button on the ribbon. Enter the project name, start and finish date, and so on. 2 Set nonworking days in the project calendar Before entering the project schedule, enter nonworking days in the Calendar sheet, such as Saturday, Sunday, or public holidays. When you enter nonworking days, XLGantt excludes them from calculations of working time. 4 Enter task information In the Schedule sheet, enter the task names, start and finish dates, and the %Work Complete values. The orange columns are automatically calculated, so you do not need to enter them. 5 Update Schedule After you enter the project information and WBS data, you always have to click "Update Schedule" on the ribbon to automatically calculate the durations and the planned %Work Complete values, and so on. 3 / 26
5 What is XLGantt? XLGantt is a program designed to enable project scheduling in Microsoft Excel. It is composed of the following features. You don't need to install this program because it is a Excel macro file. You just download this file, save it to a folder, and open it in Excel. The latest version is available at XLGantt homepage, 1) Task Management and Progress Calculation When you enter task names, start and finish dates, and %work complete values, XLGantt automatically calculates the task durations, planned %work complete values. 2) Gantt Chart Displays the Gantt chart of the schedule. In the options, you can choose whether to display task name and dates and so on. 3) Analysis Report Shows you the progresses and workloads of the project by weeks, months, and resources. 4) Scheduling Change Management Manages the planned schedule and actual schedule of the project. 5) Deliverables Specifies the save path of the deliverables and open the deliverables. 6) Adding Tasks to Microsoft Outlook Calendar Adds tasks to the Outlook calendar. 7) Multilingual Support Currently we support only English and Korean as user interface(ui) language at XLGantt. Since the program code and the resource file for multiple languages are separated, it is possible to add multiple languages without modifying the program. 8) Importing Schedules from Another File Imports schedules into XLGantt. You can import the schedules by mapping the fields. 9) Setting Nonworking Days When you enter nonworking days, XLGantt excludes them from calculations of working time. Standard calendar is the default calendar. If you want to specify a different calendar for a specific task, please use "User Defined Calendar 1" or "User Defined Calendar 2". 10) Integration with Excel Features You can include the formulas and functions of the Excel in XLGantt. 4 / 26
6 XLGantt Interface XLGantt Ribbon WBS Gantt Chart Project Calendar Settings Project Progress Project WBS, Gantt chart Analysis Report 5 / 26
7 Features of XLGantt 1) Task Management and Progress Calculation (1/4) When you enter task names, start and finish dates, and %work complete values, XLGantt automatically calculates the tasks durations, planned %work complete values. Enter the following fields : - Items marked with an asterisk (*) are required, and those without an asterisk (*) are optional fields. - WBS, duration, etc., shown in orange, are automatically calculated fields, so you do not have to enter values. - When you enter values in the required fields and click the Update Schedule (or Save button) on the ribbon, the orange fields (duration, progress, etc.) are automatically calculated. - If you want to indent or outdent the tasks, select the tasks you want(multiple tasks can be selected) and click the Indent or Outdent button. Enter the task names by Level. If they are Level 2, enter them in the second column. You can enter tasks up to Level 7. Summary tasks are automatically displayed in bold, so you can easily see them as summary tasks. WBS No.(Automatically calculated) Enter the project start and finish dates(if you rightclick in the date field, the calendar window appears. Double-click the date you want in the calendar to enter the date) Workload that should have been performed by today (Automatically calculated) = Workload * Weight (Except for nonworking days, Automatically calculated) Duration on calendar except nonworking days(automatically calculated) Planned progress that should have performed by today Weight is the value of the workload. For example, if a task requires 1 person, weight is 1, but if two people are needed, weight is 2. By entering weights, you can accurately calculate the actual workload of the project. The default value of weight is 1. If you do not enter a weight, 1 will be entered automatically Actual progress (enter manually) 6 / 26
8 Features of XLGantt 1) Task Management and Progress Calculation (2/4) Summary tasks automatic calculation : 1. Enter the task names, start and finish dates, and progress values(%work Complete) and click Update Schedule (or Save button). 2. When you complete the above, the orange fields (WBS, workload, duration, Planned %Work Complete) are automatically calculated. 3. At the same time, the start and finish date of the summary task are automatically calculated as the earliest start date and the latest finish date of the subtasks, and the summary task of the planning progress(planned %Work Complete) and the actual progress (%Work complete) are automatically calculated by accumulating the values of the subtasks. = Workload * Weight (Except for nonworking days, Automatically calculated) Duration on calendar except nonworking days(automatically calculated) 7 / 26
9 Features of XLGantt 1) Task Management and Progress Calculation (3/4) The meaning of planned progress(planned %Work Complete) and actual progress(%wok Complete) : As shown in the picture below, assume that there is a task to complete from January 1 to January 10, which is a 10-day work. If today is January 7, 70% of the plan should be completed. That is, the completion rate that should have been processed by today is called the planned progress. If today is January 7, but only 6-day work has been done, the actual progress(%work Complete) will be 60%. So, this task will be in a 10% delayed state. Start 1/1 Today 1/7 Finish 1/10 Planned %Work Complete is 70% If only 6-day work has been done, %Work Complete is 60% How do I change the current date to view the Planned %Work Complete in the future or past? In the options, set the Calculation Base Date of Planned %Work Complete" to the date you want. 8 / 26
10 Features of XLGantt 1) Task Management and Progress Calculation (4/4) Viewing planned progress(planned %Work Complete) and actual progress(%wok Complete) of the entire project : - At the top of the Schedule sheet, you can see the progress of the entire project. Planned progress (Planned %Work Complete) Actual progress (%Wok Complete) - On the Progress sheet, you can see the workload of the entire project, the planned workload, the actual workload, and the progress, etc. 9 / 26
11 Features of XLGantt 2) Gantt Chart Customizing Gantt Chart view : - Click the "Options" button on the ribbon to customize a Gantt Chart view. 1 You can choose whether to display task name, date, progress on the Gantt Chart. 2 You can choose where to display task name in the Gantt chart. 3 You can set the width of the Gantt Chart. What if the Gantt Chart does not display properly? - If the WBS area, Gantt Chart, etc. are not displayed properly, click Reformatting" button on the ribbon to restore normal state. 10 / 26
12 Features of XLGantt 3) Analysis Report - Progresses by Resources This feature shows you workloads, progresses(%work complete), etc by resources. 1 On the ribbon : Click on the menu you want from the menus below. 2 Viewing Progresses by Resources Click "Progress by Resources" on the menu to automatically calculate workloads, progresses(%work complete), etc by resources entered in the Resources" fields in the Schedule Sheet(For example, When the total workload of a task is 6 Man/Day, if you enter Elsa, Anna in the field, 3 Man/Day is calculated for each resource). Click on the number of the subtotal level in the upper left corner to show subtotals. 11 / 26
13 Features of XLGantt 3) Analysis Report Workload by Weeks/Months This feature shows you workload allocations by weeks or months. 1 On the ribbon : Click Workloads by Weeks or Workloads by Months on the ribbon to display the workloads in figures and charts. 2 Workloads by Weeks The average number of working days per month is usually 21 days, but it can be changed to 20 days or 22 days and so on. 3 Workloads by Months 12 / 26
14 Features of XLGantt 3) Analysis Report Workloads by Resources This feature shows you workload allocations by resources. 1 On the ribbon : Click Workloads by Resources on the ribbon to display the workloads in figures and charts. 2 Workloads by Resources The average number of working days per month is usually 21 days, but it can be changed to 20 days and 22 days and so on. 13 / 26
15 Features of XLGantt 3) Analysis Report Planned Project Progresses by Weeks This feature shows you planned project progresses by weeks. 1 On the ribbon : Click Planned Progress on the ribbon to display the project progresses in figures and charts. 14 / 26
16 Features of XLGantt 4) Schedule Change Management (1/2) You can use actual start and finish dates. So You can identify the schedule is delayed or aheaded by entering actual start and finish dates. Click the "Options" button on the ribbon to choose schedule options. If you choose Managing Schedule Changes, the following fields are displayed: Actual Start Date, Actual Finish Date, and Actual Total Work. 15 / 26
17 Features of XLGantt 4) Schedule Change Management (2/2) How to enter actual start date, actual finish date, %work complete? 1 If you enter the actual start date and the actual finish date directly If you enter the actual start date and the actual finish date directly, the %Work Complete is automatically entered as 100%. If the planned schedule differs from the actual schedule, the background color of the date is displayed in yellow and the Gantt chart displays the actual schedule in blue lines. If the planned schedule differs from the actual schedule, the background color of the date is displayed in yellow Original plan Changed schedule Changed schedule is indicated by a blue line. If the planned schedule is different from the actual schedule, it will be out of the Gantt chart area as shown above. 2 If a task is finished as planned If a task is finished on the same schedule as the planned schedule, you can enter 100% of the %Work Complete only. If you do not enter the actual start date and actual finish date, they will be filled with the same date as the planned start date and finish date. 3 If a task is not finished yet If a task is not finished, enter only the actual start date and the %Work complete. If you enter the actual finish date, the task is considered finished, so you only need to enter the actual start date. 16 / 26
18 Features of XLGantt 5) Deliverables You can specify the save path of the deliverables and open the deliverables. 1 Options > Deliverables tab Set the saving path of deliverables and the execution path to open deliverables. If you choose "Set path by the task name automatically", you will find the deliverables in the same directory as the task name structure entered in the Schedule sheet. So, in order to manage the deliverables in this way, you should create the folder structures as shown below and save the deliverables in the folders. 2 Open Deliverables If you select the deliverables name and click the right mouse button, the menu appears. Choose "Open Deliverables" to open the deliverables saved in the path shown above. If you check "Include in the selection list when deliverables not specified" in the above picture, the deliverables will be opened if the folder name and the deliverables name are the same even if you do not enter the deliverables name in the deliverables field of the schedule sheet. The deliverables should be saved in the form of folder name + extension because the program is looking for the deliverables as an extension of the program. 17 / 26
19 Features of XLGantt 6) Adding Tasks to Microsoft Outlook Calendar You can add tasks to the Outlook calendar. 1 Select tasks and add to Outlook Calendar If you select a task name and click the right mouse button, the menu appears. Choose Add to MS Outlook Calendar" to add the task to it. If you select several tasks and add them, several will be added at once. (MS Outlook must be installed on your PC) 2 See if tasks have been added to MS Outlook You can see that tasks are added as below. 18 / 26
20 Features of XLGantt 7) Multilingual Support Currently we support only English and Korean as user interface(ui) language at XLGantt. Since the program code and the resource file for multiple languages are separated, it is possible to add multiple languages without modifying the program. 1 Choose a language Depending on the language setting of the computer O/S, the language is automatically chose or you can choose the language from the options menu. 2 Add languages Since the program code and the resource file(translatedlanguages sheet) for multiple languages are separated, it is possible to add multiple languages without modifying the program If you want to use another language as your UI language, add it using the "Add Languages" menu. Add a translation for each language in the "TranslatedLanguages" sheet (The TranslatedLanguages sheet is hidden. You can unhide it on the sheet menu). If you do not add the translation, English is used as the UI language. 19 / 26
21 Features of XLGantt 8) Importing Schedules from Another File (1/2) Import schedules into XLGantt. You can import the schedules by mapping the fields. 1 From the Ribbon Click "Import" and choose the file you want to import. 2 Choose a file type to import 3 Select files to import Note) If you want to import a schedule from MS Project, export it as an Excel file from the Export menu in MS Project and import it into XLGantt. 20 / 26
22 Features of XLGantt 8) Importing Schedules from Another File (2/2) Import schedules into XLGantt. You can import the schedules by mapping the fields. 4 Mapping the fields to be imported (But XLGantt file is automatically imported without mapping) To import a file from source to the target file, map the respective fields. Select a field in source file first and then find a corresponding field in the target file. 5 Import After you finish field mapping, click the Import button. 21 / 26
23 Features of XLGantt 9) Setting Nonworking Days (1/2) Setting nonworking days in the project calendar 1 Enter nonworking days only on the Calendar sheet. All days other than nonworking days will be set as working days. When you enter nonworking days, XLGantt excludes them from calculations of working time. 2 Standard calendar is the default calendar. If you want to specify a different calendar for a specific task, please use "User Defined Calendar 1" or "User Defined Calendar 2". 3 If you enter nonworking days, the Gantt Chart displays nonworking days as orange bars. 22 / 26
24 Features of XLGantt 9) Setting Nonworking Days (2/2) How to specify a user defined calendar 1 You can edit a task information by selecting "Edit a Task" in the context menu (right-click) and specify a user defined calendar. 2 To see the calendars applied to each task at once, refer to the "Calendar" column. The "Calendar" column is the hidden, which you can see by Unhide command. 23 / 26
25 Features of XLGantt 10) Integration with Excel Features You can include the formulas and functions of the Excel in XLGantt. Display project information using functions provided by XLGantt Add columns and enter Excel formulas Excel formula You can add rows above the title and use the functions provided by XLGantt to display the project start date, etc. at the range you want. List of functions provided by XLGantt xlgantt.projectname(): Get project name xlgantt.projectstartdate(): Get project start date xlgantt.projectfinishdate(): Get project finish date xlgantt.projectplanprogress(): Get planned progress of project(planned %Work Complete) xlgantt.proejctactualprogress(): Get actual progress of project(%work Complete) xlgantt.projectprogressstring(): Get project progress summary information xlgantt.commentonheadarea(): Get comment to display at the top of the Schedule sheet You can add columns and enter formulas. *SPI(Schedule Performance Index) : The Schedule Performance Index indicates how efficiently you are actually progressing compared to the planned project schedule. 24 / 26
26 Glossary Terms used in XLGantt... 1 Weight The weight is the number of people who are put in full time for a task. For example, if you need 1 person to complete a task, enter 1 as weight, but you want 2 people, enter 2 as weight(in the figure below, if the weight is 2 and the total duration is 4 days, the amount of total work is calculated as 8 (duration * weight)). By entering weights, you can accurately calculate the actual workload of the project. The weight defaults to 1. If not entered, 1 is automatically entered. 3 %Work Complete The portion of the plan s total scheduled work that has been completed so far. It must be entered manually. Because the %Work complete of summary task are automatically calculated by accumulating the values of the subtasks, you only need to enter %Work complete values of subtasks. 2 Workload Workload = Duration * Weight(the amount of workload is expressed as Man-day) 4 Planned %Work Complete The planned %Work Complete values that should have completed so far. They are calculated automatically by XLGantt, so you do not need to enter them. 25 / 26
27 When an error occurred... If an error occurred, try the followings. 1 If the format of the Schedule sheet is damaged If you can not see the group area of Task, Gantt Chart, etc., click Reformatting" button on the ribbon. Terms of Use / Contact XLGantt Terms of Use This Program" is free software developed and distributed by xlworks.net. This program is free to use anywhere, anytime including personal / business / government / school. This Software is protected by copyright laws and other intellectual property laws and international treaties and may not be modified, reverse engineered, decompiled, disassembled, or made part of other software. 2 If you can not recover the Schedule sheet after reformatting, If you delete the original XLGantt column, the Schedule sheet may not be recovered. If you try to reformat the Schedule sheet and still can not recover it, try downloading XLGantt file from XLGantt homepage again. Contact with us Homepage: admin@xlworks.net 26 / 26
Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard
Your easy, colorful, SEE-HOW guide! Plain&Simple Microsoft Project 03 Ben Howard Published with the authorization of Microsoft Corporation by O Reilly Media, Inc. 005 Gravenstein Highway North Sebastopol,
More informationEmbarking new Project
Embarking new Project Go to file, select new. This will open a screen for blank project click ok. You can now enter your project information viz. start date, finish date and also how would you like to
More informationWhat's New - Task Planning
What's New - Task Planning by Dale Howard and Gary Chefetz With this chapter, teach yourself how to use Microsoft Project 2010 s new manual scheduling feature. This self-paced study guide includes hands-on
More informationTivoli Workload Scheduler
Tivoli Workload Scheduler Dynamic Workload Console Version 9 Release 2 Quick Reference for Typical Scenarios Table of Contents Introduction... 4 Intended audience... 4 Scope of this publication... 4 User
More informationTask Control for bpm'online. User Manual
Task Control for bpm'online User Manual Index of Contents Task Control for bpm'online OVERVIEW 3 Installation 4 Activities form 6 Quick filters at the Activities section 8 Activities control 9 child tasks
More informationThe Basics 7. Introduction 8 Project Management 9 What s New? 10 Version Comparison 12 The Gantt Chart 14 Getting Help 15 Summary 16
Contents Contents 1 2 3 4 The Basics 7 Introduction 8 Project Management 9 What s New? 10 Version Comparison 12 The Gantt Chart 14 Getting Help 15 Summary 16 User Interface 17 User Interface 18 File 20
More informationMAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS
1 MAKE YOUR SCHEDULE REALISTIC BY USING CALENDARS Prakash K P, Director of Project Management, Grade Results, Inc. 2 Learning Objectives At the end of this session, you will be able to do the following
More informationExam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.
Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside
More informationS15-Hours & Tasks Instructions
S15-Hours & Tasks Instructions S15-Hours-50 Spreadsheet to Assign Daily Hours and Tasks to 50 People for 4 Weeks Section Name TABLE OF CONTENTS Line Number Click to go there I. Introduction 29 II. Shift
More informationTS-10-ATP Instructions
TS-10-ATP Instructions TABLE OF CONTENTS Click Section Name A. Definitions to go there A B. Templates Sheet B C. Scheduling Sheet Instructions C D. Payroll Sheet D E. Vacations, etc. Sheet Instructions
More informationDAMELIN CORRESPONDENCE COLLEGE
DAMELIN CORRESPONDENCE COLLEGE DATE: 11 JUNE 2012 TIME: 14H00 16H00 TOTAL: 100 MARKS DURATION: 2 HOURS PASS MARK: 40% THIS EXAMINATION PAPER CONSISTS OF 5 SECTIONS: SECTION A: CONSISTS OF 20 MULTIPLE-CHOICE
More informationRiskyProject Lite 7. User s Guide. Intaver Institute Inc. Project Risk Management Software.
RiskyProject Lite 7 Project Risk Management Software User s Guide Intaver Institute Inc. www.intaver.com email: info@intaver.com 2 COPYRIGHT Copyright 2017 Intaver Institute. All rights reserved. The information
More informationRiskyProject Lite 7. Getting Started Guide. Intaver Institute Inc. Project Risk Management Software.
RiskyProject Lite 7 Project Risk Management Software Getting Started Guide Intaver Institute Inc. www.intaver.com email: info@intaver.com Chapter 1: Introduction to RiskyProject 3 What is RiskyProject?
More informationMicrosoft Office Project 2010 Basic Course 01: Getting Started
Microsoft Office Project 2010 Basic Course 01: Getting Started Slide 1 Topic A Project Management Concepts Slide 2 Project Constraints Slide 3 Phases of Project Management The initial Phase Initiating
More informationQ&As. Managing Projects with Microsoft Project Pass Microsoft Exam with 100% Guarantee
74-343 Q&As Managing Projects with Microsoft Project 2013 Pass Microsoft 74-343 Exam with 100% Guarantee Free Download Real Questions & Answers PDF and VCE file from: 100% Passing Guarantee 100% Money
More informationS3 Template Scheduler Instructions
S3 Template Scheduler Instructions TABLE OF CONTENTS Click to go there Section Name A Definitions A B Scheduling Assistant.xls B C Scheduling Sheet C D ReSchedule Sheet D E OT Signups Sheet E F Scheduling
More informationWelcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course
Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Administration Evacuation Timings, meals and facilities Mobile phones and emails Introductions
More informationSynergist Spotlight on...
Synergist Spotlight on... Gantt Charts A useful tool in Synergist that allow you to produce Gantts for a single job and for multiple jobs with flexible printing options Jobs can be sub-divided into phases
More informationMicrosoft Project Tips & Tricks. Project Solutions Group, Inc.
Microsoft Project Tips & Tricks Project Solutions Group, Inc. Objectives Formatting & Printing Gantt Charts Leveling Resources Calculating Costs & Pricing Information Collecting & Entering Project Actuals
More informationManaging Projects with MS Project 2010
Aptech Ltd. Version 1.0 Page 1 of 13 Table of Contents A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Aptech Ltd. Version 1.0 Page 2 of 13 Accrual Actuals Allocation Assignment Assignmenttimephased
More informationKeyedIn Projects Project Manager User Guide
KeyedIn Projects Project Manager User Guide Version 2.0 July 27, 2012 Project Manager User Guide 1 2012 KeyedIn Solutions, Inc. Welcome to the Project Manager User Guide. This user guide will provide you
More informationTime and Attendance configuration and T&A report generation
Time and Attendance configuration and T&A report generation Time and Attendance feature is used to calculate work time for created users, able to display when the user enters and leaves and calculate the
More informationCustomizing the Gantt chart View
In this lab, you will learn how to: Customize a Gantt chart view. LAB # 9 Formatting and Sharing Your Plan Customizing the Gantt chart View The Gantt chart became a standard way of visualizing project
More informationP6 Instructors Sample Presentation
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation
More informationGantt chart for bpm'online. User manual
Gantt chart for bpm'online User manual Contents Core functions 3 Installation 4 Setting up display of the Gantt chart 9 Set up the linear representation 9 Set up the hierarchical representation 10 Gantt
More informationMicrosoft Project study guide
Microsoft Project study guide Chap 1 An estimated duration appears with a(n) after the duration. a. pound sign c. question mark b. exclamation point d. red bullet Which of the following tasks in a LAN
More informationProject Scheduling with GanttProject. EGR 386w
Project Scheduling with GanttProject EGR 386w 1 GanttProject http://www.ganttproject.biz/ Download version 2.6.x Has numbered tasks option The video (access from ganttproject.biz) http://www.youtube.com/watch?v=5rhcsa5ad34&feature=youtu.be
More informationService Plan Creator. Quick Reference Guide RapidFire Tools, Inc. All rights reserved. V Ver 1I
Service Plan Creator Quick Reference Guide 2017 RapidFire Tools, Inc. All rights reserved. V20170423 Ver 1I Contents Purpose of this Guide... 2 Service Plan Creator Use Cases... 2 Creating Service Plans
More informationRiskyProject Professional 7
RiskyProject Professional 7 Project Risk Management Software Getting Started Guide Intaver Institute 2 Chapter 1: Introduction to RiskyProject Intaver Institute What is RiskyProject? RiskyProject is advanced
More informationUnit4 PSA Suite Business Performance Edition
for Microsoft Dynamics CRM Unit4 PSA Suite Business Performance Edition Release Notes Unit4 PSA Suite Business Performance Edition July 2017 v.31.07.2017 - MvB (C) Copyright 2017 Unit4 Table of Contents...
More informationSample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda
THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 to 15.1 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration
More informationCAREER PATHWAY PERFORMANCE MANAGEMENT SYSTEM EMPLOYEE USER GUIDE
CAREER PATHWAY PERFORMANCE MANAGEMENT SYSTEM EMPLOYEE USER GUIDE TABLE OF CONTENTS Process and System Information... 2 Performance Management Process... 2 Accessing Career Pathway... 2 Goals, Competencies,
More informationMICROSOFT PROJECT 2007 Level 1
Microsoft Project 2007 Level 1 Contents MICROSOFT PROJECT 2007 Level 1 WWP Learning and Development Page 1 Microsoft Project 2007 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project
More informationFast Start. prorm Fast Start. User Guide. promx AG Nordring Nuremberg
Fast Start prorm Fast Start User Guide promx AG Nordring 100 90409 Nuremberg E-Mail: sales@promx.net 2 Table of Contents 1. Introduction 5 1.1 About prorm Fast Start 5 1.2 prorm Fast Start Navigation 5
More informationProject Management LAB
Project Management LAB Marek Ł. Michalski, PhD, MBA Faculty of Management AGH University of Science and Technology www.agh.edu.pl/mlmichal rev. 2013.03.07 Project Management System With a good project
More informationCAT Enterprise. Supervisor Manual
CAT Enterprise Supervisor Manual Version 1.6 Revised February 20, 2013 NOTICE AND DISCLAIMER The information contained herein (WORK) was prepared by or contributed to by various parties in support of professional
More informationFast Start. prorm Fast Start. User Guide. promx GmbH Nordring Nuremberg
Fast Start prorm Fast Start User Guide promx GmbH Nordring 100 90409 Nuremberg E-Mail: sales@promx.net 2 Table of Contents 1. Introduction 5 1.1 About prorm Fast Start 5 1.2 prorm Fast Start Navigation
More informationNorthClark Computing, Inc. Capacity Planning User Guide
ERP Consulting Web Development Custom Programming Solutions Desktop & Web Applications for Manfact NorthClark Computing, Inc. Capacity Planning User Guide Web and Desktop Applications for Manfact by Epicor
More informationScheduler Book Mode User Guide Version 4.81
Scheduler Book Mode User Guide Version 4.81 Contents Introduction...2 Scheduler Active Tab...2 Appointment Colors and Markings...2 Setting Book Mode...3 Active Tab Options...3 Active Tab Use...3 Active
More informationS19-Bus Scheduler Instructions
S19-Bus Scheduler Instructions Bus-50 for 50 Employees, 50 Buses and 100 Shifts or Routes TABLE OF CONTENTS Line Number Click to go Section Name there I. INTRODUCTION 32 II. SETUP SHEET 40 III. SHIFTS
More informationSoftware Application: Information System Elements
Software Application: Information System Elements Project Scheduling Basics Working With Resources Fine Tuning the Project Managing the Project Project Presentations Project Management in Information Technology
More informationWelcome to the Project Manager guide
Contents Getting around... 3 Creating a new project... 4 Selecting an existing project... 6 Dashboards... 6 Project planning... 9 Project roles... 9 Gantt view... 11 Adding a task in Gantt view... 12 Parent
More information(Frequently Asked Questions)
(Frequently Asked Questions) Aptech Ltd. Version 1.0 Page 1 of 6 Table of Contents S# Question 1. Why are the Auto Schedule and Manually Schedule Icons Greyed Out in MS 2. How can you create a Timeline
More informationMICROSOFT PROJECT. Global Information Systems
Global Information Systems MICROSOFT PROJECT This manual is not a complete discussion of project management, but you need to be familiar with some of the basic terms and concepts that are used in most
More informationSupervisors of Non-Exempt Employees (RDP): Responsibilities & Getting Started Responsibilities and Getting Started (RDP)
Responsibilities and Getting Started (RDP)! caltime@berkeley.edu caltime.berkeley.edu Table of Contents Accessing CalTime... 3 Training... 3 The Biweekly Pay Period... 3 Supervisor s Responsibilities...
More informationWorkforce Management Web for Supervisors Help. About WFM Web
Workforce Management Web for Supervisors Help About WFM Web 12/18/2017 Contents 1 About WFM Web 1.1 WFM Agent Mobile Client Support 1.2 Screen Reader Support 1.3 Changing GUI colors 1.4 Changing WFM Web
More informationMICROSOFT PROJECT 2007 Level 1
Microsoft Project 2007 Level 1 Contents MICROSOFT PROJECT 2007 Level 1 WWP Training Limited Page 1 Microsoft Project 2007 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management
More informationINTRO TO WORK PLANNING IN MIRADI 4.4
INTRO TO WORK PLANNING IN MIRADI 4.4 Overview of Work Plan High Level Work Planning Adding Financial Information Analyzing & Using Work Plan Data Key Work Plan Controls Detailed Work Planning Work Planning
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR
More informationMicrosoft Excel or Microsoft Project? Why Microsoft Office Project 2007 is Easier and More Effective for Managing Projects
Microsoft Excel or Microsoft Project? Why Microsoft Office Project 2007 is Easier and More Effective for Managing Projects Summary: Using the right tool gives project managers a distinct advantage when
More informationProject Management Courses
"A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the
More informationMicrosoft Office: Excel 2013
Microsoft Office: Excel 2013 Intro to Charts University Information Technology Services Training, Outreach and Learning Technologies Copyright 2014 KSU Department of University Information Technology Services
More informationOracle Talent Management Cloud Using Career Development 19A
19A 19A Part Number F11450-01 Copyright 2011-2018, Oracle and/or its affiliates. All rights reserved. Authors: Sweta Bhagat, Jeevani Tummala This software and related documentation are provided under a
More informationMS Project 2007 Overview Table of Contents
Table of Contents Microsoft Project Overview... 1 Terminology... 1 Starting Microsoft Project... 2 Projects on the Web... 2 Toolbars... 2 View Bar... 2 Views... 3 Setting Up the Project... 3 Identifying
More informationQueueMetrics Wallboard
Asterisk Call Center Management using QueueMetrics Wallboard In this tutorial we will detail in a step to step fashion, how to create a new QueueMetrics Wallboard. Since QueueMetrics 17.06 the new Wallboard
More informationBusiness/Accounting Applications
TCTC ACT ACT! Level 1... 40 ACT! Level 2... 40 QuickBooks QuickBooks Pro Level 1... 41 QuickBooks Pro Level 2... 41 Microsoft Microsoft Project 2003 - Level 1... 42 Microsoft Project 2003 - Level 2...
More informationThe Museum Project. 1. Creating the Project
1. Creating the Project The Museum Project You have just come out of a meeting in which you have been given the task to plan and manage a project for the local museum. In the meeting you were told that
More informationForecast Scheduling Microsoft Project Online 2018
Forecast Scheduling Microsoft Project Online 2018 Best Practices for Real-World Projects Eric Uyttewaal, PMP President ProjectPro Corporation Published by ProjectPro Corporation Preface Publishing Notice
More informationMICROSOFT PROJECT PLAN PROCEDURE
COMPANY NAME MICROSOFT PROJECT PLAN PROCEDURE Table of Contents Revision History... iii 1. Introduction... 1 1.1. Purpose... 1 1.2. Objectives... 1 2. Procedure Description... 1 2.1. Overview... 1 2.2.
More informationMicrosoft Project 2013 Training
Microsoft Project 2013 Training Project Tasks Tables Charts Forms Resources Tables Charts Forms Task Ribbon > Properties Grouping > Display Task Details * This allows you to view the Task Form pane so
More informationIf you want to flag a question for later review, select the "Mark for review" button.
Exam Number: 584002RR Lesson Name: Microsoft Excel 2016 Exam Guidelines: This exam is now available only in the online assessment system. If your study guide still contains an exam, that exam is no longer
More informationServiceLedger. Getting Started Guides. Getting Started with the Scheduling Manager
ServiceLedger Getting Started Guides Getting Started with the Scheduling Manager This guide will document how to use the ServiceLedger Scheduling Manager to schedule jobs, dispatch resources, drag and
More informationOracle Project Portfolio Management Cloud Using Project Execution Management
Oracle Project Portfolio Management Cloud Using Project Execution Management Release 9 This guide also applies to on-premise implementations Oracle Project Portfolio Management Cloud Part Number E53160-01
More informationProject management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include
Abeer Bin Humaid Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements Triple constraints of project management Every
More informationSchedule Editor for Supervisors of Non-Exempt Employees
Schedule Editor for Supervisors of Non-Exempt Employees Using Schedule Editor Table of Contents Accessing Schedule Editor... 5 CalTime Home Screen for Supervisors... 5 Schedule Editor s Tabs... 5 Schedule
More informationAgilent Quality Tool Online Help. Printable Version. Intelligent Test Software Solutions. ITFSS p January 2005
Agilent Quality Tool Online Help Printable Version Intelligent Test Software Solutions ITFSS 03.10 p 1204 January 2005 Agilent Quality Tool Online Help: Printable Version 1 Copyrights and Notices Agilent
More informationMICROSOFT PROJECT 2010 Level 1
MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning
More informationUser Quickstart Guide
User Quickstart Guide November 2015 Page 2 The Two Minute Overview Campus User Quick Start Guide for VeriTime provides a full picture time and attendance by placing absences captured in Aesop alongside
More informationSupervisors of Non-Exempt Employees (Web): Responsibilities and Getting Started. Accessing CalTime. Training. The Biweekly Pay Period
Accessing CalTime Web access to CalTime can be found at http://caltime.berkeley.edu/access. If you have any problems accessing CalTime, please contact the CalTime Help Desk:! caltime@berkeley.edu, which
More informationSBW For Windows TM. Version Advanced Quoter Guide Module 7.2: Pricing
SBW For Windows TM Version 12.0 Advanced Quoter Guide Module 7.2: Pricing Updated June 2005 SBW for Windows 12.0 Page 2 of 7 June 2005 Copyright 2004 Hewlett-Packard Development Company, L.P. The information
More informationOracle Project Portfolio Management Cloud Using Project Execution Management. Release 13 (update 18C)
Oracle Project Portfolio Management Cloud Release 13 (update 18C) Release 13 (update 18C) Part Number E98219-03 Copyright 2011-2018, Oracle and/or its affiliates. All rights reserved. Authors: Mahesh Ramadugu,
More informationExcel 2011 Charts - Introduction Excel 2011 Series The University of Akron. Table of Contents COURSE OVERVIEW... 2
Table of Contents COURSE OVERVIEW... 2 DISCUSSION... 2 OBJECTIVES... 2 COURSE TOPICS... 2 LESSON 1: CREATE A CHART QUICK AND EASY... 3 DISCUSSION... 3 CREATE THE CHART... 4 Task A Create the Chart... 4
More informationProject Management Step by Step Guide
Project Management Step by Step Guide BNH Expert Software ADVISOR Enterprise User's Guide Copyright 995 to 208 BNH Expert Software Inc. Latest Update: February 2, 208 All rights reserved. No part of this
More informationThe biweekly pay period for non-exempt employees begins at 12:00 AM on Sunday and closes the following second Saturday at 11:59:59 PM.
Accessing CalTime Supervisors of Non-Exempt Employees (Web): Web access to CalTime can be found at http://caltime.berkeley.edu/access. If you have any problems accessing CalTime, please contact the CalTime
More informationSCH202: Manage Schedules
SCH202: Manage Schedules CERTIFIED COURSE CURRICULUM SAGE UNIVERSITY IMPORTANT NOTICE This document and the Sage 100 Contractor software may be used only in accordance with the Sage 100 Contractor End
More informationDRM DISPATCHER USER MANUAL
DRM DISPATCHER USER MANUAL Overview: DRM Dispatcher provides support for creating and managing service appointments. This document describes the DRM Dispatcher Dashboard and how to use it to manage your
More informationtechnical tips and tricks
technical tips and tricks Detailed assignment editing Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationFinance Manager: Payroll
: Payroll Timesheet Entry The Timesheet Entry function allows you to record timesheet entries for different payroll dates at the same time. You can group and enter payroll period data by employee number,
More informationCroner Simplify. Croner Simplify. ~ Manager Training Workbook ~ Version 5.0. P a g e 1. January 17
~ Manager Training Workbook ~ Version 5.0 P a g e 1 Manager View Managers can see information about themselves and their teams. Their role within Croner Simplify is to complete certain tasks for their
More informationCroner Simplify. Croner Simplify. ~ Manager Training Workbook ~ Version 6.0. P a g e 1
~ Manager Training Workbook ~ Version 6.0 P a g e 1 Manager View Managers can see information about themselves and their teams. Their role within Croner Simplify is to complete certain tasks for their
More informationProject 2003 Intermediate
Microsoft Application Series Project 2003 Intermediate Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery
More informationAdvantage Mobile Users Guide 06/11/2015
Advantage Mobile Users Guide 06/11/2015 Updated 06/11/2015 Page 1 of 11 Advantage Mobile Advantage Mobile allows you to access commonly used Webvantage modules from your mobile device. Modules in the first
More informationACCOUNTING TAB OVERVIEW PAYMENT/DEPOSIT LIST. Accounting Tab>Add New Payment/Deposit
O f f i c e A l l y 1 ACCOUNTING TAB OVERVIEW This module has been designed to provide full accounting capabilities enabling the user to report and apply payments, create billing statements, and generate
More informationStrategic Management Guide
Strategic Management Guide for Planview Enterprise 11.4 SUPPORT.PLANVIEW.COM North America: support@planview.com EU: support@planview.eu Copyright 2006-2015, Planview, Inc. All rights reserved. Planview,
More informationChapter 7 at a Glance
Change how tasks are related to each other, page 123 Apply constraints to control when tasks can start or stop, page 131 Enter percent work complete per task, page xx, View the project s critical path
More information1. Select Goals on the dropdown navigation menu; your goal plan will appear.
Performance Goals In MyHR, a Goal Plan (online worksheet) is used by you and your manager to create performance goals and track progress throughout the year. Opening Your Goal Plan 1. Select Goals on the
More informationManaging Projects with Microsoft Project Server 2010
Managing Projects with Microsoft Project Server 2010 Duration: 4 Days Course Code: GK2597 Delivery Method: Company Event Overview: Learn to take project management to the next level using Microsoft Project
More informationRemote Entry. Installation and User Guide
Remote Entry Installation and User Guide S OFTWARE M ANUAL VERSION 1.0 Copyright? 2003 by Sundial Time Systems Code copyright? 2003 by Sundial Time Systems Sundial Time Systems makes no representation
More informationTechnical Search and Rescue (SAR) Capability Calculator ~ Technical Guide
Technical Search and Rescue (SAR) Capability Calculator ~ Technical Guide About the SAR capability calculator... 2 Getting started your information... 4 By total population... 4 By user-defined scenario...
More informationCroner Simplify. Croner Simplify. ~ Employee Training Workbook ~ Version 3.0. P a g e 1
~ Employee Training Workbook ~ Version 3.0 P a g e 1 Employee View An Employee logging on to is known as a Self-Service Employee. An employee can see and manage information about themselves. An employee
More informationitaskx 3 Project Management User Manual
itaskx 3 Project Management User Manual GET STARTED Basics Recommended workflow Views in itaskx Adjust project options Set working time for the project-calendar 2 Unit 1 Project management basics Learn
More informationOracle. SCM Cloud Implementing Supply Chain Planning. Release 13 (update 18A)
Oracle SCM Cloud Release 13 (update 18A) Release 13 (update 18A) Part Number E92337-02 Copyright 2011-2018, Oracle and/or its affiliates. All rights reserved. Authors: Barbara Mise, Dhruba Jyoti Pokhrel,
More informationACTAtek Timesheet User Manual
ACTAtek Timesheet User Manual Version 1.1 30 October 2008 ACTAtek UK Limited Revision History Revision Date Description Author 1.0 7 July 2008 Initial Release Nicola 1.1 16 October 2008 Sage Integration
More informationProject and Portfolio Management Center
Project and Portfolio Management Center Software Version: 9.42 Resource Management User Guide Go to HELP CENTER ONLINE http://admhelp.microfocus.com/ppm/ Document Release Date: September 2017 Software
More information