Initiation Report Inland Revenue Transformation Plan project
|
|
- Claude Lambert
- 6 years ago
- Views:
Transcription
1 Inland Revenue Plan project Project Sponsors: Peter Mersi and Tim Occleshaw Withheld under section 9(2)(a) of the Official Information Act 1982 Prepared by: Date: June 2011 Draft In Confidence
2 About this document The is the required output of IR's Project Management Framework's Develop Initiation Report activity (Initiate phase). The report summarises the successful completion of the Initiate phase activities required by IR's Project Management Framework and seeks approval and funding from the Portfolio Governance and Investment Committee for the project to commence Design phase activities. Withheld under section 9(2)(a) of the Official Information Act 1982 Document Signoff The IR Plan project recommendations are approved: Formal Review Area Name Signature Date Sponsor Business Sponsor ID&S Peter Mersi Tim Occleshaw 2 Inform Future Decisions Draft In Confidence
3 Contents Introduction 4 Project Objectives 4 Critical Success Factors 5 Scope 5 Approach 6 Deliverables 8 Project schedules 9 Risk and Issue Management 10 Stakeholder Assessment 11 Resources - core team 11 Resources - subject matter experts 12 Management Structure 13 Management Roles and Responsibilities 13 Budget 14 Recommendations 14 3 Inform Future Decisions Draft In Confidence
4 Introduction The Inland Revenue (IR) Plan project brings together several existing streams of work related to business blueprints, technology renewal and extension of FIRST's life that have to date been managed as separate workstreams within Business and ID&S. The rationale of combining these related pieces of work is to develop an enterprise wide view (people, process, policy and technology) of the transformation options and roadmap work for Ministers by September. Inland Revenue has made a commitment to the Ministers (IRD2011/037 refers) that it will deliver the following information to them by September: options to maintain elements of the FIRST operating environment for longer than originally anticipated and for the de-coupling and packaging of functions into services options for deploying systems change. These options include maintaining our current product-byproduct approach, building by functionality, or building a new system in isolation using currently licensed enterprise COTS packages a clearer view of our end-to-end processes and the demands placed on them. The purpose of this document is to gain sponsor approval on the overall approach, scope and plans. Project Objectives The primary objective of this project is to develop a set of Executive Board (EB) and/or Business Programme Board (BTPB) endorsed plans for business transformation along with the technologies required to support it. The aim of these plans is to provide Ministers with the confidence that Inland Revenue knows how it will transform its business. The plans will inform future decision making for all business change and technology renewal activities going forward. A current state business blueprint that details the products, services and processes that Inland Revenue currently supports A future state business blueprint that details the products, services and processes that Inland Revenue will need to support in the future based on the organisation's intended direction as outlined in IR for the Future and the 2014 work. A technology future state vision based on the future state business blueprint work A feasibility report on how Inland Revenue could maintain FIRST including consideration of the stabilisation activities required to support the desired future business state. This work will also feed into the 'do nothing' option in the options work A set of preferred and prioritised transformation options that have been chosen using a set of BTPB endorsed evaluation criteria An assessment of the fit of Inland Revenue's current and planned project activities against the future business and technology states A roadmap of the transformation projects and activities based on BTPB endorsed option(s) An indication of the cost benefit models and level of funding required to support the transformation options and roadmap A delivery approach to support the options and roadmap when implementing the transformation roadmap. This will include a prioritisation method and benefits model to support the selection of the most effective project investments and implementation options. This may include making recommendations as to which projects should be stopped due to overlaps and/or organisational capacity/capability constraints and/or non-alignment with agreed priorities. Engage and work with an optimal number of Inland Revenue's business units to ensure that the prioritised transformational options and roadmap have buy-in, credibility and best meet the IR transformation and strategic objectives. 4 Inform Future Decisions Draft In Confidence
5 Critical Success Factors Project Objectives Critical Success Factors Key Indicators Metrics To develop a set of Executive Board (EB) and/or Business Programme Board (BTPB) endorsed plans for business transformation along with the technologies required to support it. To develop a delivery approach to support the options and roadmap when implementing the transformation roadmap. To develop a set of cost benefit models and level of funding required to support the transformation options and roadmap To develop a future state business blueprint that details the products, services and processes that Inland Revenue will need to support in the future To develop a set of cost benefit models to support the transformation options and roadmap Inland Revenue has an EB/BTPB endorsed business and technology future state along with the options, roadmaps and funding strategies required to achieve the future state complete by September Ministers understand Inland Revenue's transformation direction and how they intend to achieve the transformation. Inland Revenue has supporting processes, management and governance in place to implement the roadmap. Inland Revenue is ready to start developing business cases to seek funding for activities on the roadmap.. Inland Revenue has been able to make decisions on what should be included in the transformation plan based upon quantifiable and evidence based rationale Ministers papers are completed on time Ministers papers have BTPB/EB endorsement Ministers have sufficient information to choose transformation option from options provided in Ministers papers BTPB know how to govern and manage the plan going forward. Inland Revenue is starting stage 1 business cases. BTPB feel confident that the initiatives outlined on the plans are the right initiatives. Ministers papers ready by September 2011 EB/BTPB meeting minutes record endorsement of transformation plans and Ministers papers prior to release to Ministers Ministers choose a transformation option by October 2011 Within funding constraints BTPB can start initiatives on Roadmap planned for January 2012 on time. Inland Revenue is starting stage 1 business cases as required by January BTPB is able to direct organisation to proceed on initiatives as planned. Scope In Scope Confirmation of business drivers A current and future state business model A future state technology vision (based on business drivers and technology imperatives) A set of preferred transformation options that include consideration of people, process, policy and technology based on business and technology future states. The preferred option list will be selected using agreed selection criteria from an option long list. Development of cost benefit models for the preferred transformation options only. This is to provide the necessary financial information for the development of a funding strategy Out of Scope Recreating business vision - existing material to be used from 2014 and IR for the Future Detailed current state assessment of current technology (but sufficient current state analysis to inform vision, option and roadmap work) Detailed analysis of the transformation option long list - a high level analysis will only be performed on the preferred transformation options The cost benefit work for the preferred options will only be to provide a comparison of the relative merit of the options, an indication of order of magnitude and will require more work to be included in future business cases. No cost benefit analysis will be performed for the long list options. 5 Inform Future Decisions Draft In Confidence
6 A funding strategy (an indication of the one-off and ongoing costs and benefits for implementing the roadmaps) A set of roadmaps to show the sequence and timing of the major initiatives required to transform the business (up to a ten year period) to achieve the business and technology future states. There will be more detail on the initiatives in the 1-3 years with less detail on the initiatives 4+ years on. An assessment of the more significant current projects underway to determine their fit against the future state and recommendations on their inclusion or not within the roadmap. A proposed decision making process for Inland Revenue's governance groups to use in implementing and managing the roadmap delivery approach Development of the paper (and supporting documentation) for Ministers summarising the artefacts in scope above. Sufficient stakeholder consultation to provide Executive Board with confidence that the process was robust and the output of sufficient quality to be presented to Ministers. Independent assurance for the latter parts of the project during August and September to assure senior management on quality of process and output. Project will tailor PMF deliverables to be 'fit for purpose' in agreement with project sponsors Development of stage 1 and/or 2 business cases to seek funding. Business and Technology Strategies (but the options and roadmap work will be essential inputs into these strategies) Detailed plans sufficient to initiate projects from. Stakeholder consultation and communication across the whole organisation. Completion of all PMF deliverables Approach The IR Plan project consists of two workstreanns that will be responsible for the delivery of a number of individual and joint deliverables as follows: Business Blueprint: This workstreann is responsible for the development of current and future states for the business cased upon business drivers and strategic outcomes. They will then work in tandem with the Technology workstream to deliver roadmaps, options, the funding strategy, a delivery approach and papers for Ministers. Technology : This workstreann is responsible for the development of a future technology state along with a position on how FIRST's life could be maintained. They will then work in tandem with the Blueprint team to deliver the remaining deliverables as above. 6 1 Inform Future Decisions Draft In Confidence
7 The diagram below shows the key deliverables along with the month in which they are to be delivered. May/June July August September SME Group: Business units Business Blueprint workstream Technology workstream Business Blueprint - current & future state Technology Vision Maintain FIRST feasibility report including Stabilisation activities Transfor - mation options 0 Transfor mation roadmap Transfor Transfor mation 40. mation funding delivery strategy approach Transfor - mation paper for Ministers SME Group: Technology Hub Stakeholder communication and consultation/btpb endorsement Due to the aggressive timeframes to be met to deliver the required output for Ministers by September 2011, the following approach is required: Joint Design: Once technology and business future state work is complete, the options and roadmap work will be completed by a team of business and technology subject matter experts supported by a small core full time team. Structured workshops: Workshops will be facilitated in a structured way to enable attendees to provide maximum input based on the Business Blueprint and Technology Vision work completed through June. This will include: O Set up of all workshops in advance O Agendas and objectives O Pre-reading O 'Strawman' deliverables as starters for 10 to aid discussion as quickly as possible at workshops O Quick turn around of workshop output Timeboxed activities: The project plan attached to this project will be baselined with a final deliverable date to fit within required Ministerial timeframes. This means that the contributing activities will be timeboxed which for some deliverables may mean a less than optimal level of consultation and/or detail. Where possible throughout the process there will be some scope for iterative development of the deliverables up until final sign out for Ministers by Executive Board. Optimal consultation: The team will aim for as much consultation with internal and external stakeholders as is practical within the timeframe. As a minimum the Executive Board (or BTPB) must endorse the deliverables as outlined below. Ongoing QA: Throughout process workshop attendees will be encouraged to take back workshop inputs and outputs to test with their BAU colleagues and external independent assurance expertise will also be sought to QA outputs. 7 Inform Future Decisions Draft In Confidence
8 Deliverables The deliverables below have been grouped into the 3 next steps that Inland Revenue has committed to with Ministers for the September paper. The deliverables with asterisks (*) relate to more than one of the next steps. "Options to maintain elements of the FIRST operating environment for longer than originally anticipated and for the de-coupling and packaging of functions into services." Deliverable Deliverable description De livery date Maintain FIRST assessment* A paper outlining how long FIRST will able to be maintained and an indication of activities that may be required to keep FIRST running and to support future business needs Draft 1 complete by 17 June 2011 Draft 2 ready for EB (if required) by 29 June 2011) "Options for deploying systems change. These options include maintaining our current product-byproduct approach, building by functionality, or building a new system in isolation using currently licensed enterprise COTS packages." Deliverable Deliverable description Delivery date Technology Vision option selection criteria* options* A visual representation of how the technology of IR of the future looks in 10 years and may include visuals to show: architectural frameworks key types of applications capabilities an overlay on business vision and business requirements A set of high level descriptions that support the diagrams/visuals including: key features drivers for change alignment to enterprise and cross-govt strategies and initiatives alignment to business requirements risks/opportunities extent of change/impact to organisation capabilities required comparison to good practice and other tax administrations principles/assumptions Draft 1 ready for use in Technology Options workshops 18 July 2011 Draft 2 ready for BTPB endorsement 7 July 2011 Draft 3 ready for final endorsement by BTPB for release to Ministers 23 August 2011 A set of criteria by which options will be assessed. Draft 1 ready for BTPB endorsement 7 July 2011 Draft 2 ready for use in Technology Options workshops 19 July 2011 A set of transformation options (including the do nothing option (the counter factual)) to deliver the intent of the business and technology future states. Each option will include: major activities and timeframes degree of alignment to future business state and business requirements strengths/weaknesses risk profile doability - org capacity/capability assessment on ability to meet Service and other potential IR and cross govt initiatives comparison to good practice and other tax administrations value for money considerations impact on current technology infrastructure/contracts/people/processes impact on business - people/processes/policy/technology overall assessment of alignment to principles Draft 1 ready for recommended option workshops 22 July Inform Future Decisions Draft In Confidence
9 Recommended option(s)* Recommended roadmap option(s) detailed* roadmap(s)* roadmap delivery approach* September report back to Ministers on Business and Systems * overall assessment of merit of option A subset of the technology transformation roadmap option(s) of greatest merit (as assessed by the metrics defined in deliverable 3 above and scored during deliverable 4). Each of the recommend transformation roadmap option(s) above will be further defined and include: more detail on activities and timeframes a comparison to the do nothing option idea of financial cost one off to implement and ongoing to run (including impact on BAU costs) off ramps (along with indication of costs/benefits to stop at off ramps) more detail on impacts/doability A visual that shows how the recommended option(s) would be sequenced, durations and years of implementation A set of principles/guidelines for use by IR management during the implementation of the recommended technology transformation roadmap option(s) A summary of the deliverables above to be issued to the Minister of Revenue and the Minster of Finance as committed to in April 2011 (IRD 2011/037). This will include: business vision/blueprints technology vision recommended transformation roadmap option(s) alignment of options to successful deployments in similar organisations globally transformation roadmap(s) transformation delivery approach organisation capabilities and capacities potential funding strategies supported with cost benefit models Draft 1 ready for Roadmap and Cost benefit model work 29 July 2011 Draft 2 ready for BTPB 4 August 2011 Draft 1 ready for funding strategy work 12 August 2011 Draft 1 ready for funding strategy work 12 August 2011 Draft 2 ready for BTPB endorsement 17 August 2011 Draft 1 ready for BTPB endorsement 17 August 2011 Draft 1: ready for internal review 26 August 2011 Draft 3: ready for SSC, Treasury and Ministers offices 30 August 2011 Final: ready for Ministers 1 September 2011 "A clearer view of our end-to-end processes and the demands placed on them" Deliverable Deliverable description Delivery date Blueprint An outline of the model to be used for current Draft 1 ready for use in current and outline and future state that will contain an indication of the business processes, business drivers, futures state blueprint work 17 June 2011 metrics by service and function, current projects Draft 2 ready for BTPB endorsement on 13 July 2011 Business A set of business drivers and targets Draft 1 ready for use in current and Drivers A set of target metrics for change future state blueprint work options workshops 17 June 2011 Draft 2 ready for BTPB endorsement on 13 July 2011 Current State A current state process map Draft 1 ready for use in future state Blueprint Agreed metrics for drivers blueprint work 8 July 2011 Draft 2 ready for BTPB endorsement on 13 July 2011 Future State A future state process map Draft 1 ready for use in options Blueprint Current projects mapped against future state workshops 18 July 2011 blueprint Draft 2 ready for BTPB endorsement on 4 August 2011 Project schedules A project plan has been developed in MS Project and will be baselined with the approval of this initiation report. The critical path has been identified and the project's progress will be monitored against the activities on the critical path. 9 Inform Future Decisions Draft In Confidence
10 Risk and Issue Management A separate Risk and Issue Management Plan is maintained containing a fuller set of risks and issues (no issues currently). This will be a standard agenda item at the BTPB at each monthly meeting from July onwards. Risk Risk # description Aggressive timelines may mean insufficient 1 consultation and communication within IR Resource unavailability Inability to gain consensus at workshops and/or Executive Board meetings in timely manner resulting in delays to delivery dates Inability to quantify the costs and benefits for one off and ongoing current and future business and technology may weaken the options and funding feasibility work required for the Ministers papers. Current third tier realignment work may impact management focus on this project Like- Conse- Risk lihood quence Rating Mitigation Almost Major Extreme Sponsors will need to keep EB/BTPB and certain 3rd tier management informed during project enabling core team to get on with delivering project Sponsors to work with team on agreeing stakeholder plans and agree relative priority of each stakeholder group Almost Major Extreme Sponsors and/or BTPB will need to certain communicate relative priority of this work to teams Timeframe expectations communicated to resources (and their managers in advance) Workshops to be set up in advance Structured approach to workshops so that time at workshops is optimally used and there is minimal out of workshop time commitments required of workshop attendees Possible Severe Extreme Sponsors and/or BTPB may have to provide direction when workshop teams cannot agree Relative importance or risk assessments will need to be overlaid on the work that cannot be agreed as it may be sufficient to park some elements of the work until after September Likely Major Extreme Work with F&P and budget baseline holders to make assumptions about how current costs. Use reference sites and external expertise to assist in identifying future costs and benefits Possible Major High Keep 3rd tier management informed throughout process Escalate any issues re gaining 3rd tier support to BTPB as required 10 Inform Future Decisions Draft In Confidence
11 Stakeholder Assessment Below is a high level table of the stakeholders. This work will be further detailed in a Stakeholder Management Plan as a separate deliverable. External Stakeholder Minister of Revenue Minister of Finance ICT Ministers SSC, Treasury, Ministers and Ministers offices Internal Stakeholder Commissioner of Inland Revenue EB BTBP Carolyn Tremain Peter Merci Tim Occleshaw Service Delivery Management Team ID&S Management Team 3rd Tier Management Team Identified managers within Service Delivery, ID&S, Business, PAD and Corporate Services. Inland Revenue Consultation approach Updates at weekly meetings Updates at fortnightly meetings Meet monthly Meet monthly Consultation approach Via BTPB meetings and other meetings as required As directed by BTPB when the implications of decisions being required are outside of BTPB's remit Monthly meetings for progress updates and deliverable endorsement Fortnightly meetings Weekly meetings Other meetings as required Weekly meeting via ID&S Leadership team Other meetings as required Weekly meetings with key representatives Review of key deliverables prior to presentation at BTPB for endorsement Weekly updates Review of key deliverables prior to presentation at BTPB for endorsement Updates as required Weekly meetings with key representatives Updates via intranet Resources - core team Withheld under section 9(2)(a) of the Official Information Act Inform Future Decisions Draft In Confidence
12 Withheld under section 9(2)(a) of the Official Information Act 1982 Resources - subject matter experts Supporting the core team will be a series of subject matter experts who will be available to provide specialist Inland Revenue knowledge. They will be involved through workshops, 1:1 meetings and to review outputs. These groups have an advisory role and will be required to provide assurance regarding the quality of the outputs to EB/BTPB. For the Business Blueprint work the following groups are involved on a part time basis. Specific names are currently being identified and will be added when known. Expertise and Inland Revenue Business Unit Data/Information Specialists from: NARU Policy Forecast Modellers Strategic Compliance Risk Customer & Product Innovation F&P Business Experts and Advisors Call/Contact Centre Frontline/Field Processing Compliance Management Debt Management Audit Management Prosecutions/Litigations Service Delivery Management Team (Tier 3 managers from Service Delivery) Purpose To provide IR customer, product, channel and transaction volume data information To provide specialist IR knowledge about the IR current state operation, strategic opportunities and potential future state operation. Future champions of the Business Programme To provide Service Delivery review and feedback on Business Blueprint, options and business road map. To provide nominated business experts and advisors to the project For the Technology work the following groups are involved: Withheld under section 9(2)(a) of the Official Information Act Inform Future Decisions Draft In Confidence
13 ID&S Management Team (Tier 3 managers from ID&S) To provide feedback on all Technology output prior to distribution to BTPB for endorsement To provide nominated business experts and advisors to the project Management Structure The diagram below outlines the proposed management structure for the project. Below the diagram are a list of the responsibilities for each of the roles. Deputy Commissioner Programme Manager Programme Office Business Blueprint Technology transformation Management Roles and Responsibilities Name Role Specific Responsibility Peter Mersi Deputy Responsible for delivery of Ministers paper by September Commissioner Responsible for the integration of the Technology and Blueprint workstreams to produce the overall transformational plan. Responsible for managing key internal and external stakeholders relationships (specifically SSC, Treasury, Ministers Offices and Ministers). Responsible for managing trade-off decisions arising from the project. Responsible for managing escalations to BTPB, EB or the Cornmissioner. Responsible for delivery of Business Blueprint workstream. Tim Occleshaw Deputy Responsible for delivery of the Technology Commissioner workstream. Responsible for assisting the delivery of Ministers paper by September Responsible for assisting the integration of the Technology workstream with the Business Blueprint workstream. 13 Inform Future Decisions Draft In Confidence
14 Withheld under section 9(2)(a) of the Official Information Act 1982 Programme Manager Technology Project Manager Project Manager Programme Office Responsible for all components of the IR Plan project on behalf of the Deputy Commissioner, Business. Specific tasks include all standard project management activities including management of: Management of the two workstreams and the intersecting activities between the two streams Project schedules Risk management Set up of independent assurance panel of suppliers and initial appointment of assurer for the September deliverable Reporting to BTPB and Executive Board Stakeholder management (specifically with SSC, Treasury, Ministers Offices, BTPB, Executive Board and 3rd tier management teams) Responsible for delivery of the Technology workstream. Responsible for assisting in the delivery of all project deliverables. Responsible for delivery of Business Blueprint workstream. Responsible for assisting in the delivery of all project deliverables. Responsible for supporting the Programme Manager in the delivery of the information, communications and support required to manage this project. Budget All internal resources working on this project will be provided to the project free of charge. The contractors used on this project will be paid for by Business. The costs for use of external contractors have been included in the 2010/11 and 2011/12 budgets. Recommendations The IR Plans project recommends that the sponsors: o Note the contents of this report; o Note that a more detailed Stakeholder Plan will be developed as a separate deliverable for sponsor approval; and Agree the IR Plan project can proceed as detailed in this. 14 Inform Future Decisions Draft In Confidence
Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference:
Inland Revenue Transformation Programme Sourcing Workstream PROCUREMENT PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 28/06/2013 v1.0 FINAL Reference: 2013050 Document Control File
More informationWithheld under section 9(2)(f)(iv) of the Official Information Act
the due diligence process. Resources from the State Services Commission, the Treasury and the affected departments will be applied to a Transition Taskforce that will undertake the due diligence. 5 The
More informationManitoba Health, Seniors and Active Living Transformation Program Charter. February 16, 2018 Version 1.0
Manitoba Health, Seniors and Active Living Transformation Program Charter February 16, 2018 Version 1.0 Table of Contents 1 Purpose... 3 2 Background... 3 3 Scope of the Transformation Program... 5 3.1
More informationManaging Successful Programmes 2011 Glossary of Terms and Definitions
Version 2, November 2011 This glossary: is subject to terms and conditions agreed to by downloading the glossary, uses international English which has been adopted to reflect and facilitate the international
More informationNational Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide
National Commissioning Board Leading Integrated and Collaborative Commissioning A Practice Guide March 2017 Introduction The short practical guide is intended to stimulate commissioners and other senior
More informationIPMA Professional Development Event
IPMA Professional Development Event Department of Revenue Tax and Licensing Systems Replacement (TLSR) Project January 27, 2016 Transforming Revenue s Future through collaborative efforts, improved processes,
More informationNHSBT BOARD 30 MARCH 2017 ODT HUB PROGRAMME 2017/18 BUSINESS CASE
1. STATUS: Public NHSBT BOARD 30 MARCH 2017 ODT HUB PROGRAMME 2017/18 BUSINESS CASE 2. EXECUTIVE SUMMARY 2.1 The ODT Hub Programme was initiated in 2015 to allow the organisation to meet the challenges
More informationPassit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2
Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our
More informationCHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS
CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS Objectives Introduction The objectives are: Describe the purpose of the phase planning activity, preconditions, and deliverables in the implementation methodology.
More information2. Creating and monitoring the overall program milestone plan and cross-functional dependencies and issues.
Deloitte 2200 Ross Ave Suite 1600 Dallas, TX 75201 www.deloitte.com Chris Garcia Director of Operations PharmaKat 123 Main St. Dallas, TX Dear Chris, Deloitte is pleased to confirm that it will provide
More informationModernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management
Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction How to Read an Activity Description Objective: Provides the overall objective of the activity :
More informationInformation Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
More informationBranch Development and Support, Information and Knowledge Services Branch
Business Advisor Branch Development and Support, Information and Knowledge Services Branch The Business Advisor is responsible for preparing, coordinating and delivering the provision of high quality advice
More informationAudit and Advisory Services Integrity, Innovation and Quality
Audit and Advisory Services Integrity, Innovation and Quality Follow-up Progress Assessment of the Audit of IM/IT Project Life Cycle Controls 1577-13/14-101 Table of Contents EXECUTIVE SUMMARY 1 1. Introduction
More informationCHILDREN'S SOCIAL CARE SERVICES ALTERNATIVE DELIVERY MODEL BUSINESS CASE APPROVAL
AGENDA ITEM 4 CABINET 29 MARCH CHILDREN'S SOCIAL CARE SERVICES ALTERNATIVE DELIVERY MODEL BUSINESS CASE APPROVAL Relevant Cabinet Member Mr A C Roberts Relevant Officer Director of Children, Families and
More informationInformation is available in large print, audio and Braille formats. Text Relay service number 18001
Jon Thompson Chief Executive and Permanent Secretary Meg Hillier MP Chair of the Public Accounts Committee House of Commons London SW1A 0AA 100 Parliament Street London SW1A 2BQ 28 March, 2018 Dear Ms
More informationCare.data Programme Board Terms of Reference
Document filename: care.data Programme Board Terms of Reference Directorate / Programme Document Reference Care.data Programme Project Programme Director Eve Roodhouse Status Final Owner Eve Roodhouse
More informationEY Center for Board Matters. Leading practices for audit committees
EY Center for Board Matters for audit committees As an audit committee member, your role is increasingly complex and demanding. Regulators, standard-setters and investors are pressing for more transparency
More informationDCC Business Case for DCC activities during the Transitional Phase of the Switching Programme
DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme Version: V3.0 Date: 29 March 2017 Author: Classification: Aimi Hayman and Bryn Coles DCC Public Document Control
More informationIdentification and Prioritisation of NHS England Policy Research Needs
Identification and Prioritisation of NHS England Policy Research Needs Identification and Prioritisation of NHS England Policy Research Needs First published: June 2013 Updated: July 2014 Prepared by:
More informationMeeting the Challenge Benefits Realisation Plan
Appendix A Meeting the Challenge Benefits Realisation Plan Version 1.1 14 June 2006 BENEFITS REALISATION PLAN Contents: Introduction 4 Background 4 Purpose of Document 4 Scope of Document 5 Drivers for
More informationOur Corporate Strategy Information & Intelligence
Our Corporate Strategy Information & Intelligence May 2016 UNCLASSIFIED Information & Intelligence: Executive Summary What is our strategic approach for information & intelligence? Our decisions and actions
More informationTools To use with the Learning Plan Methodology. Business Implications of Emerging Technologies
Tools To use with the Learning Plan Methodology Business Implications of Emerging Technologies 2.4 Use a Learning Plan The Learning Plan Template Learning Approach: T M R O As of (Date) Status: What is
More informationJob description and person specification
Job description and person specification Position Job title Head of Genomics Unit Directorate Finance, Commercial and Specialised Commissioning Pay band AFC Band 9 Responsible to Director of Strategy and
More informationThe healthy business strategy tool. The Healthy Business Coalition
The healthy business strategy tool The Healthy Business Coalition DEFINITION 2 Healthy Business [hel-thee biz-nis] (noun) A management approach that seeks to create value and optimize performance by improving
More informationB.29[18b] Inland Revenue Department: Procurement for the Business Transformation programme
B.29[18b] Inland Revenue Department: Procurement for the Business Transformation programme Photo acknowledgement: mychillybin.co.nz Niels Schipper B.29[18b] Inland Revenue Department: Procurement for the
More informationThe Benefits of Portfolio Defra a case study
The Benefits of Portfolio Management @ Defra a case study Achilleas Mavrellis Performance, Panel and Portfolio Management Lead, Defra with acknowledgements to Tom Taylor Director of Finance and Performance,
More informationPortfolio Marketing. Research and Advisory Service
Portfolio Marketing Research and Advisory Service SiriusDecisions Team Jeff Lash VP and Group Director, Go-to-Market Christina McKeon Service Director, Portfolio Marketing Tyler Anderson Team Leader, Account
More informationFive Guiding Principles of a Successful Center of Excellence
Five Guiding Principles of a Successful Center of Excellence What is a Center of Excellence? At some point in their life cycle, most companies find it beneficial to develop a Center of Excellence (CoE).
More informationMARKET SOUNDING EXECUTION PLAN
Inland Revenue Transformation Mobilisation Programme MARKET SOUNDING EXECUTION PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 25/06/13 v 3.0.0 CLASSIFIED IN CONFIDENCE - INLAND REVENUE
More informationSupreme Audit Institutions Performance Measurement Framework
Supreme Audit Institutions Performance Measurement Framework Implementation Strategy 2017-19 October 2016 Table of Contents 1. Introduction 2 1.1. What is the SAI PMF? 2 1.2. Why is SAI PMF of such strategic
More informationBusiness Case Guidelines for Investment in Information Technology
Business Case Guidelines for Investment in Information Technology Citation: Ministry of Health. 2004. Business Case Guidelines for Investment in Information Technology. Wellington: Ministry of Health.
More informationThe Integrated Support and Assurance Process (ISAP): detailed guidance on assuring novel and complex contracts
The Integrated Support and Assurance Process (ISAP): detailed guidance on assuring novel and complex contracts Part C: Guidance for NHS trusts and NHS foundation trusts Published by NHS England and NHS
More informationProgram and Project Responsibilities
Program and Project Responsibilities The attached roles help establish a project governance system and can be adjusted for your particular organisation. Depending on the selected function(s) of your Project
More informationBusiness Architecture Fundamentals
Course Description 3 day - expert led hands-on In this turbulent and increasingly competitive global economy, and the rapid pace of change in business models involving changing technology and customer
More informationNSW DIGITAL GOVERNMENT STRATEGY. digital nsw DRIVING WHOLE OF GOVERNMENT DIGITAL TRANSFORMATION DESIGNING IN OUR NSW DIGITAL FUTURE
NSW DIGITAL GOVERNMENT STRATEGY digital nsw DRIVING WHOLE OF GOVERNMENT DIGITAL TRANSFORMATION DESIGNING IN OUR NSW DIGITAL FUTURE CONTENTS 1 MINISTER S FOREWORD 2 TRANSFORMATION IMPERATIVE 3 ROAD MAP
More informationState of Oklahoma CIO Assessment Study
in collaboration with State of Oklahoma CIO Assessment Study October 21, 2010 Government Modernization Committee Alex Z. Pettit Chief Information Officer State of Oklahoma Table of Contents Confirmation
More informationPER13 PPP. Terms of Reference for consultancy on Public Private Partnerships in the Transport sector
PER13 PPP Terms of Reference for consultancy on Public Private Partnerships in the Transport sector I. Background Public Private Partnership (PPP) is an important instrument for the Government to attract
More informationFinance Effectiveness How to free up your time to do more interesting things
Finance Effectiveness How to free up your time to do more interesting things Adrian Gilder and Aly Jamal Grant Thornton UK LLP 18 October 2017 Agenda What is Finance Effectiveness? Why undergo a transformation
More informationCATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015
POLICY NUMBER P15/2 VERSION 1.0 CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 AUTHORISED BY Trust ISSUED DATE 10/08/2015 DISTRIBUTION External REVIEW DATE
More informationSAI Performance Measurement Framework Implementation strategy
SAI Performance Measurement Framework Implementation strategy 2017-19 24 September 2016 Draft SAI PMF strategy, 2017-19 Page 1 SAI PMF Strategy 2017-2019 1. Introduction 1.1 What is the SAI PMF? The SAI
More informationAn Overview of Modern Business Analysis
An Overview of Modern Analysis Sergey Korban, Aotea Studios, 2012 Background The feedback we receive from our readers and customers indicates that the business analysis framework described in the BABOK
More informationAn Example Portfolio Management Process
BEST PRACTICES WHITE PAPER An Example Portfolio Management Process Jenny Stuart, Vice President of Consulting, Construx Software Version 1, June 2009 Contributors Jerry Deville, Professional Software Engineer
More informationPortfolio Management In An Agile World
Portfolio Management In An Agile World Rick Austin VP, Enterprise Engagements Principal Consultant 2017 @rickaustin, @leadingagile @GoAgileCamp #AgileCamp2017 2 RICK AUSTIN Information Technology Director
More informationObjective (c.f., p.58)
TOGAF 9.1 CIS 8090 Session #4 Chapter 6 Preliminary Phase Chapter 7 Phase 4 Architecture Vision Part III Chapter 18 Introduction to ADM Guidelines and Techniques Sources: 1. Primary Slide Deck By: Samuel
More informationProject Management Manual Prepared by: Project Support Office, Major Projects Department
Project Management Manual Prepared by: Project Support Office, Major Projects Department Version: 2015 Project Support Office Project Management Manual Version: November 2015 This manual is a living document
More informationworking with partnerships
A practical guide to: working with partnerships Practical step-by-step building blocks for establishing an effective partnership in the not-for-profit sector N 2 (squared) Consulting with Nottingham Council
More informationICT Strategic Leadership Group: Terms of Reference
ICT Strategic Leadership Group: Terms of Reference April 2015 Purpose To support ICT Functional Leadership as a lever for system transformation, with particular focus on the direction of the GCIO s All
More informationProject Management Initiation Document
Project Management Initiation Document This document provides an ideal project management plan template which can be used by anyone at any level who is undertaking a project and is looking for a plan structure
More informationOverview. Genesys confidential and proprietary information. Unauthorized disclosure is prohibited. 2
Overview Change Happens When Change Doesn t Happen Making Change Happen Organizational Change Management Organizational Readiness Assessment Case Study Summary Questions Genesys confidential and proprietary
More informationA Guide to Critical Success Factors in Agile Delivery
IBM Global Business Services, U.S. Federal May 6, 2016 A Guide to Critical Success Factors in Agile Delivery Paul Gorans, Agile Competency Lead, IBM GBS Federal A bit about me 6 Years USAF: NSA Operations,
More informationTemplate for ToR for Transaction Advisory Services
Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services
More informationREQUIREMENT DRIVEN TESTING. Test Strategy for. Project name. Prepared by <author name> [Pick the date]
REQUIREMENT DRIVEN TESTING Test Strategy for Project name Prepared by [Pick the date] [Type the abstract of the document here. The abstract is typically a short summary of the contents of
More informationHR Excellence. Confederation of Indian Industry
HR Excellence HR Excellence Assessment Model 2010 Leadership Broad Parameters Human Resource Strategy HR Management & Processes People Knowledge & Competencies People well being & engagement Results Perception
More informationBusiness Case Guidance. Draft March 2018
Business Case Guidance Draft March 2018 This version of the Draft Business Case Guidance (The Guidance) was released in March 2018. The feedback received from stakeholders will be considered during the
More informationEMEA TMC client conference Developing a tax technology architecture. The Crystal, London 9-10 June 2015
EMEA TMC client conference Developing a tax technology architecture The Crystal, London 9-10 June 2015 1 Agenda Background - Why look at your tax technology architecture? Reasons for initiating Market-specific
More informationJOB DESCRIPTION. You will need to be able to travel to London and other parts of the UK, with occasional nights away from home.
JOB DESCRIPTION Job title: Location: Reports to: Job level: Head of Primary Care Contracting Leeds Assistant Director - Primary Care Contracting Grade B Date prepared: May 2017 PURPOSE The Primary Care
More informationReleased under NSW GIPA Act GIPA Application TRA Page 1
GIPA Application TRA-000616 - Page 1 GIPA Application TRA-000616 - Page 2 Executive Summary Introduction and Context > A new IT Service Delivery (ITSD) function was established within TfNSW in 2012 as
More informationLeading Practice: Approaches to Organizational Change Management
Leading Practice: Approaches to Organizational Change Management Abstract This document provides recommended approaches to organizational change management (OCM) when implementing CA Project and Portfolio
More informationAzure Infrastructure for SAP
Azure Infrastructure for SAP Sizing and Assessment Offers 40% - 75% cost operational cost savings (Lower TCO) Fast and inexpensive deployment of SAP landscapes (minutes vs. weeks) Automation provisioning
More informationWhat. (what activities or tasks are planned to achieve the outcome)
CCPS: WORKFORCE DEVELOPMENT Work Plan 2014-15 Overall Aims To work in collaboration with SSSC and other key partners, through sharing knowledge and practice, in order to build workforce capacity and leadership
More informationJOB DESCRIPTION. Manager Service Management Technical Systems & Proposed band. Job family
Job title Job family Manager Service Management Technical Systems & Proposed Delivery band E Job purpose The Manager, Service Management is responsible for leading a functional team in one of the specialist
More informationSpeed to Value in Portfolio Management
Speed to Value in Portfolio Management Presentation Objectives Attendees will learn about: Creating an environment where IT becomes viewed as a strategy enabler and value driver for the organization Ensuring
More information<Project Name> Business Case
Business Case Author(s) Contributors Department Campus DOCUMENT HISTORY Version Date Person Notes 1.0 ITS Portfolio Management Office Business Case Page 1 TABLE OF CONTENTS
More informationEDINBURGH AND SOUTH EAST SCOTLAND CITY REGION DEAL
EDINBURGH AND SOUTH EAST SCOTLAND CITY REGION DEAL Report by Executive Director SCOTTISH BORDERS COUNCIL 2 November 2017 1 PURPOSE AND SUMMARY 1.1 This report provides an update on the overall composition
More informationInformation and Communication Technologies Strategic Plan 2016/ /20
Information and Communication Technologies Strategic Plan 2016/17 2019/20 Foreword Mike Russell Chief Information Officer We must continue providing the infrastructure and vital support systems to keep
More informationICT Integration in Mergers & Acquisitions
ICT Integration in Mergers & Acquisitions ICT M&A White Paper Copyright Midagon 2017 Ltd. All rights reserved Copyright Midagon 2017 Ltd. All rights reserved 2 Contents Introduction 4 Mobilization 4 Current
More informationDoD Hazmat Business Process Reengineering: Environment, Safety and Occupational Health (ESOH) Transformation
DoD Hazmat Business Process Reengineering: Environment, Safety Occupational Health (ESOH) Transformation Office of the Deputy Under Secretary of Defense for Installations Environment ODUSD(I&E) Business
More informationCorality Academy Financial Modelling for Renewable Energy Projects. 3 day duration
Corality Academy Financial Modelling for Renewable Energy Projects 3 day duration Company overview About Mazars Global Infrastructure Finance For project developers, investors and financiers in the infrastructure
More informationStakeholder Engagement Plan
CALTRANS SYSTEM PLANNING TO PROGRAMING STUDY (SP2P) Stakeholder Engagement Plan Final 9/1/15 Prepared By Emergent Transportation Concepts, Kittleson & Associates, Inc. and System Metrics Group SP2P Stakeholder
More informationArchitecture Planning Adding value to projects with Enterprise Architecture. Whitepaper. September By John Mayall
Adding value to projects with Enterprise Architecture Whitepaper September 2007 By John Mayall W O R L D C L A S S A R C H I T E C T U R E Architecture Planning Introduction We are often asked what an
More informationChapter 4 - Recommendations for an Enhanced Enterprise Information Technology Governance Structure
Enterprise IT governance in a state government context is best seen as an evolving process, responding to new technological capabilities, organizational practices, and dynamic political environments. Designing
More information4/26. Analytics Strategy
1/26 Qlik Advisory As a part of Qlik Consulting, Qlik Advisory works with Customers to assist in shaping strategic elements related to analytics to ensure adoption and success throughout their analytics
More informationINCREASING PRODUCTIVITY BY MORE THAN 20% THROUGH RE-ORGANIZATION
INCREASING PRODUCTIVITY BY MORE THAN 20% THROUGH RE-ORGANIZATION A CASE STUDY AUTHORS GREG RUNG AASHISH WADHWA THE CHALLENGE A mid-sized regional bank with strong revenue growth wanted to get better control
More informationPOSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8
1200, Scotia Place, Tower 1 10060 Jasper Avenue Edmonton, Alberta T5J 3R8 edmonton.ca/auditor POSSE System Review January 30, 2017 The conducted this project in accordance with the International Standards
More informationSuccessful Delivery of Change How Managing Benefits is helping Dubai Customs optimize its return on investment
Successful Delivery of Change How Managing Benefits is helping Dubai Customs optimize its return on investment By Stephen Jenner, Author & Chief Examiner of Managing Benefits with Mohammad Rashed Bin Hashim
More informationBUSINESS CASE FRAMEWORK AND PROCEDURES
BUSINESS CASE FRAMEWORK AND PROCEDURES Section Finance Contact National Capital Manager Last Review May 2014 Next Review May 2017 Approval N/A Document Purpose: This document establishes Massey University
More informationMake the complex manageable
Make the complex manageable Deal Advisory / Global We help create clear Solvency Strategies. Realizing value through insolvency. / 1 Your vision. Our proven capabilities. Insolvencies can test the limits
More informationAFRRCS Agency Handbook
AFRRCS Agency Handbook Governance Documents AFRRCS Agency Handbook Section: Governance Documents Version 1.0 AFRRCS Agency Handbook Governance Documents Contents 1. Vision, Mission, Values, Goals 2. Governance
More informationHow to Drive Business Value with Capacity Management
How to Drive Business Value with Capacity Management 18 July 2017 Your Presenter Jim Smith The Building Blocks Executive Buy-in Benefits realization Assessment Roles and responsibilities Strategy Toolset
More informationFinance and Investment Committee Tuesday 26 May hours
Meeting Finance and Investment Committee Date and Time Tuesday 26 May 2015 1000-1330 hours Location Pacific Quay Title of Paper Facilities Management Item Number 12.1 Presented By Susan Mitchell Recommendation
More informationMeasures for Assuring Projects
Measures for Assuring Projects APM toolkit June 2016 1 @Association for Project Management 2016 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted,
More informationBank of Ireland. Service Integration as a means to govern a multivendor. 11 th October 2013
Bank of Ireland Integration as a means to govern a multivendor IT estate 11 th October 2013 Gerry Flanagan (Accenture) Sharon Donnelly (Bank of Ireland) Agenda Introductions What is Introduction and why
More informationPosition Description. Senior Business Analyst. NZSIS mission and values. Our mission. Our values STAFF-IN-CONFIDENCE STAFF-IN-CONFIDENCE PAGE 1
Position Description Senior Business Analyst Directorate: Position purpose: Directorate overview: Staff management: Financial authorities: Remuneration indicator: Capability Directorate This role provides
More informationTRUST BOARD DELIVERING EXCELLENCE: UPDATE ON THE TRUST S INTEGRATED MEDIUM TERM PLAN
TRUST BOARD DELIVERING EXCELLENCE: UPDATE ON THE TRUST S INTEGRATED MEDIUM TERM PLAN Meeting Date: 13 th July 2017 Author: Sponsoring Executive Director: Report Presented by: Committee/Group who have received
More informationTECHNICAL GOVERNANCE REVIEW RESPONSE TO FINAL REPORT
Australia s independent, not-for-profit, developer of Australian Standards TECHNICAL GOVERNANCE REVIEW RESPONSE TO FINAL REPORT April 2018 Page 2 Background Each year, Standards Australia hosts open forums
More informationProgramme Business Case Addendum
t io Inland Revenue Te Tan i Taake Programme Business Case Addendum Delivering New Zealand's future revenue system October 2014 COMMERCIAL IN CONFIDENCE This document has been released by Inland Revenue
More informationAuditing e-government
8 into IT Auditing e-government Life-cycle risks and setting up a database Biography Erna Lea is a Deputy Director General at the Office of the Auditor General of Norway (OAG). She has a degree in economics
More informationAudit of Shared Services Canada s Information Technology Asset Management
Audit of Shared Services Canada s Information Technology Asset Management Audit Report June 2017 Period of Examination from September 1, 2014, to September 30, 2015 TABLE OF CONTENTS Executive Summary...
More informationInsurance Analytics: Organizing Analytics capabilities to get value from Data Analytics solutions A Deloitte point of view on Data Analytics within
Insurance Analytics: Organizing Analytics capabilities to get value from Data Analytics solutions A Deloitte point of view on Data Analytics within the Dutch Insurance industry Insurance Analytics A Deloitte
More informationA practical guide to governance of enterprise-scale Agile projects. 4 October 2011
A practical guide to governance of enterprise-scale Agile projects 4 October 2011 What are we talking about! Governance of enterprise-scale Agile projects What is Governance? What is enterprise-scale Agile?
More informationProactively released by the Minister of Internal Affairs
IN-CONFIDENCE Office of the Minister of Internal Affairs Cabinet Committee on State Sector Reform and Expenditure Control REVIEW OF THE GOVERNMENT ICT STRATEGY Proposal 1. The purpose of this paper is
More informationTransforming the office of the CFO
www.pwc.in Transforming the office of the CFO Maximising Finance Effectiveness We help the office of the CFO to optimise and excel in business insights, efficiency and control We address the fundamental
More informationLevel 2, 77 Hereford St Christchurch. Bill Dwyer (Chair) Bruce Irvine Bob Lineham. Fiona Mules Dr Jane Gregg Darren Wright Peter Houghton
STATEMENT OF INTENT FY 2017 Directory Address: C/o Christchurch City Holdings Ltd PO Box 73049 Christchurch 8154 Registered office: Level 2, 77 Hereford St Christchurch Establishment Board: Bill Dwyer
More informationRISK MANAGEMENT STRATEGY
Agenda Item No: 15 RISK MANAGEMENT STRATEGY PURPOSE: The Risk Management Strategy has been updated to reflect the revised approach to the Corporate Risk Register and Board Assurance Framework and to reflect
More informationIBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM)
IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM) DK_INTC-8838-00 11-2011 Page 1 of 17 Table of Contents 1.Scope of Services...3 2.Definitions...3
More informationSystem Under Development Review of the Departmental Financial Management System Renewal Project
System Under Development Review of the Departmental Financial Management System Renewal Project Audit and Evaluation Branch In collaboration with Deloitte LLP December 2015 List of Acronyms AAFC ADM AEB
More informationInternal Audit Charter
Internal Audit Charter 1. Introduction 1.1 This document sets out the Internal Audit service vision and clarifies the role and responsibilities of the London Borough of Barnet Internal Audit Service and
More informationBETTER BUSINESS CASE - EFFICIENT DECISION MAKING Chris Purchas, Tonkin + Taylor Limited
BETTER BUSINESS CASE - EFFICIENT DECISION MAKING Chris Purchas, Tonkin + Taylor Limited Introduction If you are involved in any type of public infrastructure development in New Zealand you have probably
More informationRisk Advisory Services Developing your organisation s governance for competitive advantage
Advisory Services Developing your organisation s governance for competitive advantage The Deloitte Advisory Platform of Services can help you to govern your strategic plan to guide your operations measure
More information