1 September 2008 Research Report: Comparison of Pre-Cast and Cast-in-Place Concrete Pavements Under Heavy Vehicle Simulator Loads Author: Erwin Kohler Work Conducted as part of Partnered Pavement Research Center Strategic Plan Element No. 4.17: HVS testing of pre-cast PCC panels in District 8 PREPARED FOR: California Department of Transportation (Caltrans) Division of Research and Innovation PREPARED BY: University of California Pavement Research Center UC Davis and Berkeley

2 DOCUMENT RETRIEVAL PAGE Research Report No.: Title: Comparison of Pre-cast and Cast-in-place Concrete Pavements Under Heavy Vehicle Simulator Loads Authors: Erwin Kohler Prepared for: Caltrans Division of Research and Innovation and Caltrans District 8 FHWA No.: Work Submitted: April 28, 2009 Date: February 2008 Strategic Plan Element No.:4.17 Status: Draft Version No: Stage 2 Abstract: The California Department of Transportation (Caltrans) evaluated use of the Super-Slab System of pre-cast concrete pavement as a strategy for the long-life rehabilitation of concrete pavements by conducting accelerated pavement testing using the Heavy Vehicle Simulator (HVS) on a specially constructed experimental pavement in San Bernardino County. HVS testing of the pre-cast pavement occurred in Caltrans had conducted similar HVS tests on Jointed Plain Concrete Pavements (JPCP) on between 1998 and 2001 at SR-14 in Palmdale. This report compares the results of the accelerated tests on these two pavement types. A difference in the location of the loading made it necessary to apply conversion factors to the Palmdale JPCP data for the comparison. Tests on that pavement used edge loading, while testing on the San Bernardino pre-cast slabs used wheelpath loading. The comparison results suggest that similar service life ranges can be obtained from this pre-cast system and jointed plain concrete pavements. A rough estimate of about 200 million ESALs seem to represent this service life. There is insufficient data to judge the variability in the expected life of pre-cast pavements; however, significant variability was observed in the cast-in-place JPCP slabs tested. Keywords:pre-cast concrete slabs, Super-Slab, Heavy Vehicle Simulator, HVS, experimental pavement section, dry and wet pavement tests, accelerated pavement testing, instrumented slabs Proposals for implementation: None Related documents: Kohler et al. (2008). HVS Testing of Pre-Cast PCC Panels First-Level Report Test 597FD. (UCPRC-RR ). Kohler et al. (2008). HVS Testing of Pre-Cast PCC Panels First-Level Report Test 5987FD. (UCPRC-RR ). Du Plessis et al. (2002). HVS Test Results on Fast-Setting Hydraulic Cement Concrete, Palmdale, California Test Sections, South Tangent. ( UCPRC-RR ) Du Plessis et al (2005). HVS Testing of the Palmdale Test Site, North Tangent Sections: Evaluation of Long Life Pavement Rehabilitation Strategies-Rigid. (UCPRC-RR ) Signatures: Erwin Kohler First Author John Harvey Technical Review David Spinner Editor John Harvey Principal Investigator T. Joseph Holland Caltrans Contract Manager ii

3 DISCLAIMER The contents of this report reflect the views of the authors who are responsible for the facts and accuracy of the data presented herein. The contents do not necessarily reflect the official views or policies of the State of California or the Federal Highway Administration. This report does not constitute a standard, specification, or regulation. PROJECT OBJECTIVES This project is responsive to the objectives identified by Caltrans District 8 in its request to the Caltrans Pavement Standards Team (PST) for evaluation of the Super-Slab System: The short-term objectives are to answer a constructability question regarding opening to traffic in the ungrouted condition and to determine what the failure mechanisms of the Super-Slab panels are.. The long-term objective is to provide information to Caltrans to help determine how the performance of precast panels compares to that of current Long-Life Pavement Rehabilitation Strategies (LLPRS) designs for jointed plain concrete pavements. The project involves the evaluation of transverse joint behavior; measurement of load transfer efficiency; observations of possible joint deterioration; measurement of faulting, cracking, and settlement that may result from slab and cement-treated base (CTB) deterioration; estimation of expected service life of Super-Slab pavement based on HVS test results; and comparison of Super-Slab performance (expected service life) to Heavy Vehicle Simulator (HVS) tests conducted on cast-in-place jointed plain concrete slabs (SR-14 at Palmdale). iii

4 iv

5 EXECUTIVE SUMMARY In an effort to evaluate whether the pre-cast concrete pavement system known as the Super- Slab System can be used as a long-life pavement rehabilitation strategy, the California Department of Transportation (Caltrans) had the University of California Pavement Research Center (UCPRC) perform accelerated pavement tests (APT) using a Heavy Vehicle Simulator (HVS). This testing, which took place on a specially constructed experimental pavement in San Bernardino County, was similar to that on an earlier project that used cast-in-place jointed plain concrete pavements (JPCP) on State Road 14 (SR-14) in Palmdale. When the tests on the Super-Slab sections were completed, the results were compared with those of the Palmdale tests. This report presents the results of the comparison. In the San Bernardino pre-cast pavement two identical sections were evaluated. The sections were on two sides of a five-by two slab arrangement of 225-mm thick slabs constructed on a specially built 150-mm thick cement-treated base. For the cast-in-place, Palmdale JPCP slabs, a series of 14 HVS tests were conducted, all with one concrete mix, but with four different pavement structures. (Two additional cast-in-place sections are mentioned, but these were excluded from the analysis because the slab thicknesses were not comparable to the pre-cast slabs.) The four JPCP sections that were compared with the pre-cast ones consisted of sections with the following design characteristics: No dowel bars and no asphalt shoulder, paved on an aggregate base No dowels but an asphalt shoulder, paved on top of a cement treated base. Dowel bars and also a tied concrete shoulder, paved on a cement treated base Dowel bars and in a widened lane configuration, on a cement treated base One notable difference between the tests on the pre-cast slabs and those on the cast-in-place slabs was the placement of the HVS load: on the pre-cast slabs, the load was applied in the wheelpath, almost 2 ft (0.6 m) from the slab edge, and HVS loads on the cast-in-place slabs were applied at the slab edge (except for the widened lane, where the load was placed 2 ft [0.6 m] from the edge). Since the stresses that result from edge loading are much higher than those resulting from interior loading, the cast-in-place JPCP slabs failed under fewer load repetitions than the pre-cast slabs. A process was followed, based on earlier research, to compare edge loads to interior loads so that a meaningful comparison could be drawn. v

6 Another notable difference was that the JPCP slabs at Palmdale that are compared with the pre-cast in this project were allowed to cure for at least a year prior to HVS loading. Although the concrete mix used for the JPCP slabs consisted of a blend of fast-setting hydraulic cement and portland cement, measured values for strength from cores taken from the slabs showed that they had similar strength to JPCP slabs built by Caltrans at the time the Palmdale sections were subjected to HVS loading. Therefore the comparison presented in this report does not include comparison between pre-cast slabs and slabs placed in nighttime closures and opened to traffic the next morning. The results of the comparison between the two pavement types suggest that similar ranges of service life can be obtained from this pre-cast system and from jointed concrete pavements. Large variability was found in the expected life from cast-in-place JPCP pavements, both between pavements with different designs (i.e., base type, dowel/no dowels, tied concrete shoulder, widened lane) and within a given design. Given that only two sections of pre-cast pavements were tested, insufficient data are available to judge their variability. Assuming a fixed heavy traffic level of 6.6 million equivalent single axle loads (ESALs) per year, a service life for each was calculated. One pre-cast pavement section failed after the equivalent of 37 years, while the other was perfectly functional after 22 years of equivalent traffic levels and was not loaded to failure. The lives of cast-in-place JPCP pavements ranged between zero (slabs with lengths greater of 18 ft [5.5 m] cracked before any traffic loading in the hot, dry environment) and 80 years; and if only the designs on cement-treated bases and doweled joints are considered, this type of pavement would be expected to last on average the equivalent of approximately 23 years. vi

7 TABLE OF CONTENTS Project Objectives... iii Executive Summary... v List of Figures... viii List of Tables... viii Abbreviations Used in the Text... ix Abbreviations Used in the Text... ix 1 Introduction Background Types of Concrete Pavements Pre-cast Versus Rapid-Setting Concrete Process Used to Compare Performance of Cast-in-Place and Pre-cast Concrete Under HVS Loading HVS Experiments on Pre-cast and Cast-In-Place Concrete Experiments Pre-cast Concrete Pavement in San Bernardino Cast-in-Place JPCP Concrete Pavement in Palmdale Comparison of Structures and Traffic Loading to Failure Summary and Comparison References vii

8 LIST OF FIGURES Figure 1: Pre-cast pavement testing. (a) Placement of a slab, and (b) HVS applying traffic loads Figure 2: Dowel grouting. (a) Dowel bars are free immediately after slab placement, (b) dowel grouting completed in one of the two joints, and (c) dowel slot filled with grout... 8 Figure 3: Pavement condition at the end of the HVS test for Section 2 (not failed) and Section 1 (failed), plus map of cracking including location of MDD, excavation, and cores Figure 4: Typical cracks observed in slabs from Palmdale (14) Figure 5 Test sections characteristics for the cast-in-place study, thickness, materials, presence of dowel bars, and edge support conditions Figure 6: Comparison of equivalent single axle loads for the PCPS and the different JPCP pavements of the study LIST OF TABLES Table 1: Sequence of Test and Loading Conditions in Section Table 2: Sequence of Test and Loading Conditions in Section Table 3. Comparison of Structure, ESALs, and Expected Life for Precast and Cast-In-Place Pavements Loaded with HVS in California Table 4. Edge Load Factor, ELF (after Ref.[18]) viii

9 ABBREVIATIONS USED IN THE TEXT AASHTO Caltrans CTB DRI ESAL GPR HVS JDMD LTE LLPRS LVDT METS MDD PPRC PCC American Association of State Highway and Transportation Officials California Department of Transportation cement-treated base Division of Research and Innovation equivalent single-axle load ground-penetrating radar Heavy Vehicle Simulator joint deflection measurement device load-transfer efficiency Long-Life Pavement Rehabilitation Strategies linear variable differential transformer Materials Engineering and Testing Services multidepth deflectometer Partnered Pavement Research Center portland cement concrete ix

10 SI* (Modern Metric) Conversion Factors APPROXIMATE CONVERSIONS TO SI UNITS Symbol Convert From Multiply By Convert To Symbol LENGTH In. Inches 25.4 millimeters mm Ft Feet meters M AREA In.2 square inches square millimeters mm2 ft2 square feet square meters M2 VOLUME ft3 cubic feet cubic meters M3 MASS Lb Pounds kilograms kg TEMPERATURE (exact degrees) F Fahrenheit 5 (F-32)/9 Celsius C or (F-32)/1.8 FORCE and PRESSURE or STRESS Lbf Poundforce 4.45 newtons N Lbf/in.2 poundforce/square inch 6.89 kilopascals kpa APPROXIMATE CONVERSIONS FROM SI UNITS Symbol Convert From Multiply By Convert To Symbol LENGTH Mm Millimeters inches In. M Meters 3.28 feet Ft AREA mm2 square millimeters square inches In.2 M2 square meters square feet Ft2 VOLUME M3 cubic meters cubic feet Ft3 MASS Kg Kilograms pounds Lb TEMPERATURE (exact degrees) C Celsius 1.8C+32 Fahrenheit F FORCE and PRESSURE or STRESS N Newtons poundforce lbf kpa Kilopascals poundforce/square inch lbf/in.2 *SI is the symbol for the International System of Units. Appropriate rounding should be made to comply with Section 4 of ASTM E380. (Revised March 2003.) x

11 1 INTRODUCTION Use of precast slabs is being considered as a rehabilitation strategy for extending the service life of distressed concrete pavement. Benefits of the strategy include the long life expectancy of concrete slabs cast in factory-controlled conditions and the fact that fully cured pre-cast slabs can be put into use almost immediately after installation, which makes them attractive for use on heavily traveled highways where work windows for full-depth repairs are short. A Heavy Vehicle Simulator (HVS) research project to evaluate the expected performance of the Super-Slab system of pre-cast concrete pavement was conducted for the California Department of Transportation (Caltrans) by the University of California Pavement Research Center (UCRPC). This work was performed as Partnered Pavement Research Center Strategic Plan Element 4.17 (PPRC SPE 4.17), titled HVS testing precast PCC panels in District 8, and was approved by the Caltrans Pavement Standards Team in February The short-term objective of the project was to determine failure mechanisms of the Super- Slab panels and to answer a constructability question regarding opening to traffic in the ungrouted condition. This constructability question has to do with the effect on the pavement when the pre-cast slabs are opened to traffic shortly after they are placed and before grout is injected into the transverse joints and under the slab to activate their dowels. The project s long-term objective was to provide information to Caltrans to help determine how the performance of pre-cast panels compares to that of current Long-Life Pavement Rehabilitation Strategies (LLPRS) designs for jointed plain concrete pavements (JPCPs) constructed as part of lane replacement using extended traffic closures. The results in this report do not consider comparison of pre-cast panels with JPCP constructed in nighttime closures and opened to traffic the next morning with only several hours for strength gain prior to loading. This report is one of a series of documents generated by this study that cover specific aspects of this project. Among the other items published are a test plan (1), a report on construction of the test sections (2), a technical memorandum containing an interim assessment of structural life (3), and reports detailing the HVS tests and their results on each of the two sections (4, 5). This report provides comparative information regarding the structural capacity of the pre-cast concrete pavement evaluated in this project and the structural capacity of cast-in-place jointed plain concrete pavements (JPCP) previously evaluated by the UCPRC with an HVS. 1

12 2

13 2 BACKGROUND 2.1. Types of Concrete Pavements The service life that can be obtained from alternative pavement systems is one of the most important factors that agencies take into account when deciding the pavement type for a specific project and it is a critical factor in performing a Life Cycle Cost Analysis to select the most cost-efficient design alternative for a project. Concrete pavements are in general considered to have longer lives than asphalt pavements, but even the performance of concrete pavements will vary depending upon design and type. Pavements across the nation contain an historical mix of different concrete pavement types. Jointed reinforced concrete pavements (JRCPs) are seldom used today, although they were used extensively in the 1960s. There are two problems with JRCP: One is the wide transverse joint openings caused by volumetric changes that are the result of long slabs, and the other is the appearance of transverse cracks caused by friction forces opposing the volumetric changes. Continuously reinforced concrete pavements (CRCPs) are generally considered the most durable type of pavement (6, 7, 8), and there are cases of CRCP serving heavy highway traffic for more than 60 years (9). Use of CRCP is increasing in the United States and in many European countries (10). However, by far the most common type of concrete pavement is jointed plain concrete pavement (JPCP). A great deal of field performance data exist for JPCP, and it shows a wide range of service lives. In cases where JPCPs have not performed as well as expected, problems have generally been attributed to design (specifically, to longer slab lengths and the absence of dowels in transverse joints) and construction issues (particularly built-in thermal curling which precludes good uniform support under the slabs). Pre-cast concrete pavement systems (PCPSs), a newer type of concrete pavement, has gained popularity for use in roadways in the U.S. during the last six to seven years. However, because its development and use are relatively recent, little performance data is available at this time. Although a market exists for PCPS pavements because of the short construction windows available during the rehabilitation of congested roadways, it is important for agencies charged with selecting the most cost-effective pavement solution to be able to compare the expected lives of PCPS against more traditional cast-in-place concrete pavements, particularly JPCP. 3

14 2.2. Pre-cast Versus Rapid-Setting Concrete To be effective, a conventionally produced replacement slab (of poured concrete) must gain flexural strength sufficient for opening to traffic within a short construction window. A study by Kumara et al. (11), which investigated the early strength requirements of concrete slab replacements by loading them with an HVS 6 hours after placement, confirmed that replacement slabs must possess greater flexural strength than the anticipated maximum induced stress at the time they are opened to traffic if they are to avoid premature failure. Although there are concrete slab-replacement products already in use that gain strength rapidly, it remains to be seen whether projects rehabilitated with rapid-setting concrete can last as long as projects rehabilitated with regular concrete. The issue here is consumption of fatigue life at early age, when some of the slabs have yet to gain enough strength to resist traffic. Evidence exists that shows that regular concrete made with Type I/II cement and rapid-setting concretes are comparable as long as the flexural strength is the same, if the beams are subjected to the same stress levels (12). Having same stress levels for pavement slabs means that they are subjected to similar traffic and to similar thermal curling and drying shrinkage conditions. Given the uncertainties regarding early strength gain and the associated risk of early cracking with opening to traffic that are entailed in using cast-in-place concrete without providing sufficient time for greater strength gain through use of weekend or extended traffic closures the concept of pre-cast pavements is an intelligent solution. However, impediments remain to the widespread use of pre-cast pavements. One of these impediments is contractors current preference for paving with rapid-setting concrete (which gains strength more quickly than conventional concrete precisely to allow earlier opening to traffic). Many contractors prefer this method because their crews are familiar with the required equipment and possess the skills to use it; using the installation technology for precast slabs would mean retraining and added risks for construction crews (or competition from a general contractor who normally would not bid for a paving job). A second impediment is posed by the logistics and increased attention to project coordination needed for use of pre-cast panels. Because panels of different sizes are used in a project, delivery of the right panel at the right time is essential, and without proper timing of delivery construction operations can come to a halt. Making this timing work places additional demands on the manufacturers when the panels are made, stacked, and loaded onto trucks, and on the contractor to saw cut and remove damaged pavement within a short work window. However, assuming that the pavement life yielded by each system is comparable, the decision to use pre-cast panels or rapid setting concrete is best taken in a case-by-case 4

15 basis. The remainder of this report focuses in finding out whether the assumption of comparable life is valid Process Used to Compare Performance of Cast-in-Place and Pre-cast Concrete Under HVS Loading Data from two sets of HVS tests were used to compare the estimated performance of precast and cast-in-place concrete pavements: Data from HVS testing of cast-in-place JPCP on the shoulder of State Route 14 (SR- 14) performed as part of PPRC SPE 4.2, titled Evaluation of Rigid Pavement Long- Life Pavement Rehabilitation Strategies (LLPRS-Rigid), from 1998 through 2001; and, Data from HVS testing of precast slabs as part of this project. The load repetitions for each set of sections were equated with each other using a Load Equivalence Factor (LEF) to convert repetitions of different loads into repetitions of Equivalent Single Axle Loads (ESALs). The paths of the wheel loads for the two sets of data relative to the edge of the slab, which were different, were then translated into equivalent repetitions based on previous analyses performed by others. With the assumptions inherent in these conversions, the performance in terms of load repetitions to failure of the two types of concrete pavement could be compared on an approximate basis, as if the loads and load locations had been the same. 5

16 6

17 3 HVS EXPERIMENTS ON PRE-CAST AND CAST-IN-PLACE CONCRETE EXPERIMENTS 3.1. Pre-cast Concrete Pavement in San Bernardino A pre-cast test pavement was constructed near San Bernardino, an hour east of Los Angeles. It consisted of ten slabs in a two by-five arrangement. The details of the test slab installation were developed to mirror the pavement details of a potential specific project in nearby highway I-15. The main components of the installation included (2): Construction of a 150-mm (6 in.) cement-treated base; Placement of an 8-mm layer of fine bedding material (stone sand); Placement of precast Super-Slab sections, 225 mm thick (8-7/8 in.) on precisely graded sub-base; Application of grout through the slab surface at joints where slots for dowels and tie bars were present, followed by application of a second type of grout that reached under the slab (bedding grout); Diamond grinding of the surface of the slab to meet smoothness requirements of the project. Two test sections were evaluated between June 2005 and August 2006, one on each side of the two-by-five panel arrangement (Figure 1). The main test objectives were (1) to evaluate whether traffic could be safely allowed on the newly placed slabs before grouting (2) to identify how much traffic loading the system could carry (which relates to years of expected service), and (3)to determine failure mechanisms for this type of PCPS. a) b) Figure 1: Pre-cast pavement testing. (a) Placement of a slab, and (b) HVS applying traffic loads. 7

18 Traffic loading was applied to both sections to simulate the exposure to traffic from the time of placement of the slabs to the time of grouting, which would normally occur during the next nighttime closure. The grouting process completes installation of the pre-cast system. There are two types of grouting, one for dowel bars and tie bars, and the other for filling of voids under the slabs. The dowel grout activates the dowels bars, which would otherwise float in the open slots (Figure 2). a) b) c) Figure 2: Dowel grouting. (a) Dowel bars are free immediately after slab placement, (b) dowel grouting completed in one of the two joints, and (c) dowel slot filled with grout. After preliminary loading of the ungrouted pavement, the sections were grouted, and the grouted sections were then loaded for extended periods under different conditions in the sequence shown in Table 1 (note that testing on Section 1 resumed after completion of testing on Section 2). All the loading on these sections was performed in the wheelpath, 0.6 m (2 ft) from the slab edge. Section 1 was heavily overloaded to cause failure and allow identification of failure modes and Section 2 was utilized to determine performance under lower, more realistic load levels that were still heavy enough to potentially fail the pavement within a reasonable amount of time, such as a couple of months.. Wet pavement conditions were simulated by applying water directly onto the slabs at the joints. 8

19 Table 1: Sequence of Test and Loading Conditions in Section 1 Moisture Condition Slab Condition Traffic Mode Portion of Section Tested Traffic Load (kn) Date and Repetitions at the End of the Phase Date Each Repetitions Cumulative Dry Wet Uncracked Corner crack at cabin-end transverse joint Second corner crack Twoway Oneway Twoway Full Half Jun , , Jun , , Aug , , Aug , , Sep ,218 1,239, May-06 62,716 1,301, Jun-06 97,206 1,399, Jul-06 15,958 1,415, Aug-06 31,241 1,446, Aug ,689 1,605, Aug-06 77,332 1,682, Aug-06 2,018 1,684,422 Moisture Condition Table 2: Sequence of Test and Loading Conditions in Section 2 Slab Condition Traffic Mode Traffic Load (kn) Target Actual Date Date and Repetitions at the End of the Phase Repetitions Each Cumulative Oct , ,801 Dry Feb- 2,334,349 2,578, Twoway Uncracked Mar-06 2,456,357 5,034,507 Wet Mar-06 2,552,935 7,587, Mar-06 2,664,929 10,252, May-06 3,459,387 13,711,758 Only Section 1 reached the end of its serviceable life, and for that reason the results of Section 2 are presented first. No sign of any distress was observable at the end of the dry test. The dry test consisted of two loading conditions, 60 kn and later a 100 kn load level. Once the responses measured by the sensors indicated a stable condition at a 100 kn load, water application at the joints was initiated and loading continued. During the wet part of the test, loading was applied at levels between 60 kn and 100 kn (13.5 and 22.5 Kips). No distresses were observable at this stage either, despite the fact that considerable pumping of material from under the slab occurred during the wet trafficking. The pumping of fine sand, however, did not result in any significant rise in corner deflections. An investigation was carried out to evaluate the extent of the suspected voids under the slab caused by pumping and it revealed that the pumped material was comprised of the finer particles from the sand bedding layer and disintegrated bedding grout. There was no clearly observable void in the wheelpath under the joint, but there were widespread channels of washed fines. 9

20 Loading in Section 1 was applied with an aircraft tire able to apply load levels above 100 kn. Corner cracks appeared on both sides of one of the two loaded joints. HVS trafficking under dry conditions was stopped when the pavement responses were once again stable despite the cracks. After the wet traffic was initiated, the slabs were able to withstand nearly a half million more heavy load repetitions before traffic was stopped, which was a clear indication of a still sound structural condition of the cracked slabs. The cracks neither widened nor developed faulting or spalling. Failure of Section 1 was reached in the form of a localized collapse at one of the joints and a more extended corner crack on the other joint. Forensic investigation revealed that the localized failure happened between dowel bars, exactly under the wheelpath. The combined observations point toward concrete fatigue under channelized traffic and the loss of support caused by pumping. The other joint in Section 1 presented a failure that can be considered typical of cast-in-place, with large concrete cracks. Both failed joints in Section 1 are shown in Figure 3. Drill cores obtained from various locations in both test sections indicated very good performance of the dowel grout. There was no sign of looseness of the dowel, which means that the grout was strong enough to sustain the compressive forces of the dowel as load was transmitted across the joint. Likewise, there were no signs of debonding issues between the grout and the surrounding concrete of the slot. HVS wheel-path MDDs Slab excavation Cores Slab 2 Slab 3 Section 2 Section 1 Slab 4 Figure 3: Pavement condition at the end of the HVS test for Section 2 (not failed) and Section 1 (failed), plus map of cracking including location of MDD, excavation, and cores. 10

21 3.2. Cast-in-Place JPCP Concrete Pavement in Palmdale Approximately five years before this pre-cast experiment, an investigation was undertaken to evaluate the use of rapid-strength concrete for accelerating construction of new concrete pavements and for rapid rehabilitation of existing facilities (i.e., slab replacements). A series of HVS tests were conducted to evaluate the fatigue behavior of fast-setting hydraulic cement concrete pavements (13) and various design features, namely base type (granular and CTB), tied concrete shoulder, dowels, and widened truck lane. Six full-scale pavement test sections were constructed on State Route 14 (SR-14) near Palmdale, California, about an hour north of Los Angeles. Each section was 70 m long and consisted of approximately 15 slabs. The concrete used for the slabs was an 80/20 blend of Ultimax and Type I/II portland cement. The concrete mix met specifications for Fast-Setting Hydraulic Cement Concrete (FSHCC) at the time of construction. Joints were sawed at 90 degrees, and the joint spacing followed an alternating pattern of 3.7, 4.0, 5.5, 5.8 m (12, 13, 18, 19 ft). An important difference existed between the fastsetting concrete used in Palmdale and the concrete that is most regularly used in overnight slab replacements: The Palmdale sections used in this comparison were not trafficked until more than a year after construction, so their flexural strength at time of opening to traffic was not an issue (13). The point here is that in contrast to the typical case of overnight construction with traffic opening the same morning, the concrete at Palmdale had a chance to gain most of its final strength before it took any traffic loading. The early consumption of fatigue life in concrete that is opened to truck traffic within 2 to 3 hours of placement is likely one of the major causes of short life for slab replacements in the field.. Extensive laboratory testing (12) showed similar fatigue life for same stress ratio (ratio of tensile stress to flexural strength) for both types of material compared in this report, the blend used at Palmdale and the conventional Type I/II cement used at San Bernardino. For this reason, it is assumed that cement type is not a variable in the performance comparison. The pavements in Palmdale Sections 1, 3, and 5 consisted of plain jointed concrete slabs of various thicknesses, and were tested between July 1998 and May These three sections were placed on a compacted granular base. Sections 7, 9, and 11 were designed and constructed on 100 mm of cement-treated base on top of 150 mm of an aggregate base. The differences among these sections are as follows: Section 7 had no dowels and an asphalt concrete shoulder; Section 9 was constructed with dowels, normal lane width, and a concrete shoulder with tie bars (the tied shoulder was the adjacent lane); and Section 11 was constructed using a widened truck lane (4.26 m instead of 3.66 m wide) and doweled 11

22 joints. The testing on Sections 7, 9, and 11 took place between June 1999 and December The main mode of failure observed on all JPCP sections consisted of the development of a longitudinal crack parallel to the direction of traffic but outside the trafficking area. The majority of the cracks started as transverse cracks, but turned into longitudinal or, in some cases, corner cracks. Figure 4 shows typical examples of the cracking observed in the 23 tested locations within the six sections. Figure 4: Typical cracks observed in slabs from Palmdale (14). The reason for the longitudinal cracking was found to be associated with built-in curling of the slabs, and to a lesser extent, to the half axle loading. In addition to the use of fast-setting high early-strength concrete, these pavements were built in desert conditions and under daytime construction. These conditions resulted in top-down shrinkage and thermal cracks (15) and high estimated built-in temperature differential values (16). Regardless of the inclusion of dowels and tie bars on Sections 7, 9, and 11, the study showed that slab curling played a major role on the deflections observed under HVS loading, and therefore on the stresses that led to cracking of the concrete. The loss in support from the substructure, especially in the proximity of the longitudinal free edge, resulted in the development of high tensile stresses at the top of the concrete, which in turn caused the slabs to crack in the observed fashion. 12

23 All the test sections at Palmdale with 5.5 and 5.8 m (18 and 19 ft) slab lengths cracked before HVS loading was performed, and no other heavy loads were applied. These cracks were due to temperature curling and shrinkage only. All HVS tests were therefore performed on the 3.7 and 4.0 m (12 and 13 ft) long slabs. In general, deflection sensors placed just below the concrete in the base layer close to the edge registered very small deflections, even with the application of test loads greater than 90 kn (20.3 Kips). Deflections recorded in the base layer were typically less than 0.2 mm, while the surface-mounted sensors recorded deflections between 1.0 and 1.2 mm for the same test. This means that the slab was not in complete contact with the base, as less than 20 percent of the surface deflections were passed on to the base layer (17). Temperature also played a significant role in the structural behavior of the concrete slab. Daily variations in slab temperatures caused the slabs to go through cycles of expansion and contraction, which had a noticeable effect on the measured load transfer efficiency (LTE) (17). During the hot part of the day the slabs expanded, the joints locked up, and LTE values close to 100 percent were commonly calculated. At night, when slab contraction took place, LTE values dropped below 80 percent. Also, the concrete slabs went through curling cycles owing to temperature differentials (temperature at the surface of the slab with respect to the temperature at the bottom of the slab),. High deflection measurements were associated with lower surface temperatures. The advantages of dowels, tie bars, and a widened lane were clearly illustrated in the study. Even after the application of aggressive 150-kN loading (33.8 Kips), no obvious LTE deterioration could be detected on the sections constructed with dowels, tie bars, and widened lanes. Although significant cracks developed during the testing period, no significant drop in LTE values could be detected after the formation of the cracks, an indication of the effectiveness of the dowels to transfer load across joints even after extensive joint deterioration. The dowels had a significant influence in controlling slab edge movements. In contrast to this, the sections without dowels or tie bars experienced significant reductions in LTE due to trafficking and after the appearance of corner cracks. The damaging effect of repetitive loading caused a significant reduction in the life of the pavement in comparison with the doweled jointed sections. 13

24 14

25 4 COMPARISON OF STRUCTURES AND TRAFFIC LOADING TO FAILURE Only one pre-cast pavement type was tested in San Bernardino, while various structures of jointed plain concrete pavement (JPCP) were studied in Palmdale. The test sections main structural characteristics, including slab thicknesses and edge support condition, are presented in Table 3. Note the slab thickness in JPCP Sections 1 and 3. They were constructed with reduced slab thickness of 100 mm and 150 mm, are not comparable to the pre-cast sections that were 225 mm thick, and therefore are not included in comparison with the pre-cast concrete pavement system (PCPS). The slab thickness of the other JPCPs was similar to the PCPS slab thickness (see Rows A and B. in Table 3), and even though the underlying materials do not exactly match (see Row C in Table 3), it was considered close enough to compare the performance of the two types of pavements. PCPS and JPCP sections of comparable structure are shown in Figure 5. The particular features of the JPCP pavements are listed in Row D, such as the use of dowels in the transverse joints and edge support conditions. The HVS used in these experiments was able to test up to 8 m (26.5 ft) of pavement, and therefore in most cases three slabs/two joints were evaluated per HVS test. As indicated previously, two HVS tests were conducted in the pre-cast pavement, one on each side of the two-by-five arrangement. On the JPCP there was room for up to five replicate tests in each section, as shown in Row E in Table 3. One important aspect of the comparison is the subgrade. Dynamic cone penetrometer (DCP) testing at the San Bernardino site indicated CBR values under the pre-cast sections between 45 and 80 percent, while CBR at Palmdale had been found to be close to 100 percent. This information is confirmed by the fact that backcalculated subgrade modulus at San Bernardino ranged mostly between 50 and 100 MPa, while at Palmdale the modulus was approximately 200 MPa. 15

26 Table 3. Comparison of Structure, ESALs, and Expected Life for Precast and Cast-In-Place Pavements Loaded with HVS in California Summary PCPS Section 1 PCPS Section 2 JPCP Section 1 JPCP Section 3 JPCP Section 5 JPCP Section 7 JPCP Section 9 JPCP Section 11 A. Design slab thickness, mm B. Mean measured thickness, mm C. Underlying structure, mm 150 CTB 150 CTB 150 AggB 150 AggB 150 AggB 100 CTB 150 AggB 100 CTB 150 AggB 100 CTB 150 AggB D. Design features Load transfer Shoulder Slab size Length, m Width, m Dowels, Asphalt Dowels, Asphalt No dowels None No dowels None No dowels None No dowels Asphalt Dowels, Tied PCC Dowels, Widened L E. Number of HVS tests F. Edge Load Factor G. Average ESALs, millions H. ESALs each test, millions - - 4, 4, 22 0, 4, 5, 11, 18 2, 8, 31, , 48, 115, , 162, , 205, 298 I. Years to failure* J. Range of years to failure* 37 > * Years to failure assumes 6.6 million ESALs per year. PCPS JPCP - 5 JPCP - 7 JPCP - 9 JPCP PCPS 8 Bed Sand 150 CTB (dowels & grout) 200 JPCP 100 CTB 150 AggB (no dowels) 200 JPCP 100 CTB 150 AggB (no dowels) 200 JPCP 100 CTB 150 AggB (dowels) 200 JPCP 100 CTB 150 AggB (dowels) AC Shoulder AC Shoulder AC Shoulder PCC Tied Shoulder Wide lane Figure 5 Test sections characteristics for the cast-in-place study, thickness, materials, presence of dowel bars, and edge support conditions. 16

27 The total number of Equivalent Single Axle Loads (ESALs) applied to a pavement takes into consideration the various load levels used during the course of an HVS test. It is a gross approximation at best, but provides a means to compare different loading sequences. The HVS passes are normalized to the passage of an 80 kn axle load through the ESALs calculation. The computation of ESALs in this study was done according to Equation 1, which used the Caltrans load equivalence exponent of 4.2, where L is the half-axle load level in kn and ELF is the Edge Load Factor. 4.2 L 1 ESALs = ELF (1) 40 An ELF accounts for the difference in pavement damage caused by a wheel load applied at the edge of the pavement with respect to the damage caused when the load is in the wheelpath. The ELFs for the HVS loads applied to the JPCP sections were determined from an Illinois DOT study (18). The ELFs are reported in Table 3 in Row F. For HVS tests on PCPS the ELF was taken as 1.0, as the wheel load was at the wheelpath, i.e., approximately at 460 mm from the edge, as can be seen in Figure 3. For the JPCP sections, the wheel loads were at the edge of the slab as seen in Figure 4 (except in the case of the widened truck lane, where the load was 0.6 m from the edge of wide slab, at the edge of the expected truck traffic wander pattern). The ELFs for edge loads were determined from Table 4, which is adopted (by interpolation) from work done at the University of Illinois (18). The edge load factors of 0.050, 0.161, and (shown in Table 3), taken as inverse numbers, imply that the numbers of repetitions for the same damage is respectively 20, 6.20, and 6.15, depending on the edge support condition of each section. Edge Support Asphalt Shoulder 3-m Concrete Shoulder (Medium load transfer efficiency) 3-m Concrete Shoulder (High load Table 4. Edge Load Factor, ELF (after Ref.[18]) Slab Wheelpath@0.46m* Wheelpath@0.3m thickness, mm k=100** k=200 k=100 k= transfer efficiency) Widened lane (0.6m) *Two cases of wheelpath distance from the edge, which depends on lane width and other factors. ** k-value is the modulus of subgrade reaction in pounds per cubic inch. 17

28 The total number of ESALs that each section was able to sustain before the end of the HVS loading is shown in Row G. of Table 3. Given that multiple replicate HVS tests were conducted in each JPCP section, the details of ESALs in each one of those replicate tests are shown in Row H. The average of ESALs in all the tests for a given section is the value reported in Row G. The individual test data exhibit a wide range of scatter, which is attributed to the variable field conditions. To make the results more easily understood, the total ESALs were converted to an equivalent number of years in service. This arbitrary conversion of the results used the current traffic on highway I-15 near the site of the pre-cast pavement experiment. The assumed total of ESALs per year at that location is 6.6 million. The results are presented in Rows I and J in Table 3, for average and range respectively, and reveal that these pavements should be able to remain in service between 1 and 37 years (JPCP sections 1 and 3 are excluded). These service lives are very conservative because the yearly traffic is high, despite of assuming constant ESALs for the computations (zero rate of increase over the years for traffic volume and axle loads). The 6.6 million ESALs per year used for estimation of life is the result of taking the AADT values for highway 15 in San Bernardino County (Caltrans District 8) near the junction with highway 10. For this segment the Caltrans reported traffic volumes in 2006 for trucks with 2, 3, 4, and 5 axels were respectively 6,401; 1,209; 526; and 13,000. The conversions for ESALs per truck were taken as 0.26, 0.42, 0.42, and This resulted in 18,027 ESALs a day, which translates to 6.58 million ESALs a year. Proper pavement design mandates that AADT has to be split equally into the two traffic directions and only a fraction of this traffic be assigned to a design lane through the use of a lane factor. Taking 60% as the lane factor and applying it to the one-direction traffic leads to an estimated 1.97 million ESALs per year, which in turn means pavement lives that are 3.33 times longer. This portends that the best estimate for service life is not up to 37 years, but up to 123 years. This is too long of a time span to be reported with confidence, so the very conservative approach that results from concentrating the two-way traffic count on a single design lane was adopted. Furthermore, the main reason to convert ESALs to years is to offer a simpler comparison between pavements, and should be seen more in relative rather than in absolute terms. A graphical representation of the ESALs to failure for the PCPS and JPCP sections is shown in Figure 6. These results are interpreted as a rough indication that the expected life of precast concrete pavement systems does not differ greatly from that expected from cast-in place jointed plain concrete pavements. However, these results should be used with caution due to the many assumptions used to permit comparison of the two sets of data. It should be 18

29 noted that HVS loading at PCPS Section 2 was halted at 142 million ESALs without pavement damage, and it is not known whether failure would have been achieved at a higher or lower number of ESALs than PCPS Section 1. From data shown in Table 3 and Figure 6 a rough estimate of about 200 million ESALs seem to represent the life expectancy for the type of PCPS that was evaluated, and also for the JPCP pavement types that were evaluated in this study ESALs (millions) Not loaded to failure 0 PCPS section 1 PCPS section 2 JPCP section 5 JPCP section 7 JPCP section 9 JPCP section 11 Figure 6: Comparison of equivalent single axle loads for the PCPS and the different JPCP pavements of the study. 19

30 20

31 5 SUMMARY AND COMPARISON Use of pre-cast concrete pavement systems (PCPSs), which are relatively new and have not been widely deployed, is being considered as a strategic alternative to the use of conventional cast-in-place slab replacements for the rehabilitation of projects that carry large traffic loads. However, before pre-cast systems gain more widespread implementation, more information is required about how they compare to JPCP, especially data about their capacity to carry large amounts of traffic loads, which is a point of major controversy. Since long-term field performance data for pre-cast systems under real traffic conditions does not exist, and because this type of information is needed to provide a preliminary evaluation of their cost-efficiency, this study was undertaken. The study compared the number of ESALs that pre-cast and cast-in-place jointed pavement resisted under Heavy Vehicle Simulator (HVS) loads. The study provides the first, full-scale experimental comparison of load capacity between PCPS and JPCP and is intended to inform the discussion about which type of pavement lasts longer. It should be remembered that the JPCP slabs at Palmdale that are compared with the precast in this project were allowed to cure for at least a year prior to HVS loading. Although the concrete mix used for the JPCP slabs consisted of a blend of fast-setting hydraulic cement and portland cement, measured values for strength from cores taken from the slabs showed that they had similar strength to JPCP slabs built by Caltrans at the time the Palmdale sections were subjected to HVS loading. Therefore the comparison presented in this report does not include comparison between pre-cast slabs and slabs placed in nighttime closures and opened to traffic the next morning. The results of this study indicated that 200 millions ESALs is a valid rough approximation of the capacity of PCPS and JPCP of approximately 200- to 225-mm slab thickness. Unfortunately only two PCPS sections were tested and only one was trafficked until pavement failure was achieved. The two sections were loaded differently, which meant that there were no replicate tests, which therefore precluded an assessment of the results variability. One can speculate that slabs manufactured in a pre-cast plant would be more uniform than field-cast JPCP slabs in terms of thickness and strength, and that this would lead to them to have less field variability. The JPCP testing results agreed with field observations that there is considerable variability in JPCP performance, with some test sections failing (cracking) very early under live traffic, while others lasted considerably longer. 21

32 The variable nature of the performance of complex infrastructure systems makes it difficult to come up with test results that allow for prediction of the exact moment when either a precast pavement or a cast-in-place concrete pavement will fail, and in the pre-cast experiment it was unfortunately not possible to obtain replicate tests. The results showed that one section remained intact (no cracks or faulting or any other distress) after 142 millions ESALs, while another section failed after 242 million ESALs. Similarly, transverse or corner cracking was observed in one of the JPCP tests at as early as 160 thousand ESALs, while another withstood 536 million ESALs before cracking. Assuming a fixed heavy traffic level of 6.6 million ESALs per year, a service life for each type of pavement was calculated. One of the pre-cast pavement sections failed after what would be 37 years, assuming very conservative traffic levels, while the other was still perfectly functional after 22 years of equivalent traffic levels. The lives of cast-in-place JPCP pavements ranged between zero (long slab lengths) and 80 years, but if only the designs that include cement-treated bases and doweled joints are considered, this type of pavement would last on average around 23 years for the very heavy annual ESALs considered for this calculation (6.6 million ESALs per year). In sum, a preliminary assessment, based on the limited results in this project, is that doweled JPCP and PCPS pavements of similar thicknesses can be expected to have similar performance and failure mechanisms. 22

Evaluation of Precast Concrete Slabs Using a Heavy Vehicle Simulator ABSTRACT

Evaluation of Precast Concrete Slabs Using a Heavy Vehicle Simulator ABSTRACT Evaluation of Precast Concrete Slabs Using a Heavy Vehicle Simulator Erwin Kohler 1, John Harvey 2, Louw DuPlessis 3, and Hecther Theyse 4 ABSTRACT Precast slabs are considered an attractive pavement option

More information

Palmdale South Tangent Slab Built-In Curling and Cracking: Preliminary Analysis Report

Palmdale South Tangent Slab Built-In Curling and Cracking: Preliminary Analysis Report Palmdale South Tangent Slab Built-In Curling and Cracking: Preliminary Analysis Report Draft Report Prepared for the California Department of Transportation by: Shreenath Rao and Jeff Roesler University

More information

Mechanistic-Empirical Pavement Design Guide

Mechanistic-Empirical Pavement Design Guide Mechanistic-Empirical Pavement Design Guide Tommy Nantung INDOT Research and Development Division February 13, 2014 Pavements are designed to fail (in a predictable way) Performance vs. Design Life From

More information

General Information for Joints

General Information for Joints Design Manual Chapter 5 - Roadway Design 5G - PCC Pavement Joints 5G-1 General Information for Joints A. General Information The need for a jointing system in concrete pavements results from the desire

More information

October 2005 Research Report: UCPRC-RR Authors: M. Bejarano, D. Jones, B. Morton, and C. Scheffy PREPARED FOR: PREPARED BY:

October 2005 Research Report: UCPRC-RR Authors: M. Bejarano, D. Jones, B. Morton, and C. Scheffy PREPARED FOR: PREPARED BY: October 25 Research Report: UCPRC-RR-25-3 Reflective Cracking Study: Initial Construction, Phase 1 HVS Testing, and Overlay Construction Authors: M. Bejarano, D. Jones, B. Morton, and C. Scheffy Partnered

More information

7.1 Flexible Pavement Design. 7.2 Rigid Pavement Design TRANSPORTATION SYSTEM ENGINEERING 1, 61360

7.1 Flexible Pavement Design. 7.2 Rigid Pavement Design TRANSPORTATION SYSTEM ENGINEERING 1, 61360 7.1 Flexible Pavement Design 7.2 Rigid Pavement Design 1 Highway pavements are divided into two main categories: Flexible -Bituminous concrete Rigid -Portland cement concrete- Flexible pavements usually

More information

Performance of Dowel Bar Retrofitted Concrete Pavement Under HVS Loading

Performance of Dowel Bar Retrofitted Concrete Pavement Under HVS Loading Performance of Dowel Bar Retrofitted Concrete Pavement Under HVS Loading John T. Harvey, Associate Professor University of California, Davis Department of Civil and Environmental Engineering 3139 Engineering

More information

Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS

Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS I. INTRODUCTION...1 II. III. Purpose...1 What Is LCCA?...1 History of

More information

April 2015 Technical Memorandum: UCPRC-TM Authors: A. Mateos, J. Harvey, J. C. Paniagua and F. Paniagua

April 2015 Technical Memorandum: UCPRC-TM Authors: A. Mateos, J. Harvey, J. C. Paniagua and F. Paniagua April 2015 Technical Memorandum: UCPRC-TM-2015-01 Authors: A. Mateos, J. Harvey, J. C. Paniagua and F. Paniagua Partnered Pavement Research Center (PPRC) Strategic Plan Element (SPE) 4.58B: Evaluate Early

More information

Performance of Drained and Undrained Flexible Pavement. Structures under Wet Conditions. Accelerated Test Data. Test Section 544 Undrained

Performance of Drained and Undrained Flexible Pavement. Structures under Wet Conditions. Accelerated Test Data. Test Section 544 Undrained Performance of Drained and Undrained Flexible Pavement Structures under Wet Conditions Accelerated Test Data Test Section 544 Undrained Prepared for: California Department of Transportation by: Manuel

More information

Pavement Design Overview. Rebecca S. McDaniel March 10, 2011

Pavement Design Overview. Rebecca S. McDaniel March 10, 2011 Pavement Design Overview Rebecca S. McDaniel March 10, 2011 Plan Review types of pavements Features Advantages and Disadvantages Typical Distresses Common design techniques/considerations AASHTO Mechanistic-Empirical

More information

Performance of Thin Roller Compacted Concrete Pavement under Accelerated Loading

Performance of Thin Roller Compacted Concrete Pavement under Accelerated Loading Moving Advancements into Practice MAP Brief May 2016 Best practices and promising technologies that can be used now to enhance concrete paving May 2016 www.cproadmap.org ROAD MAP TRACK 8 PROJECT TITLE

More information

Evaluation of Longer-Life Concrete Pavements for California using Accelerated Pavement Testing

Evaluation of Longer-Life Concrete Pavements for California using Accelerated Pavement Testing Evaluation of Longer-Life Concrete Pavements for California using Accelerated Pavement Testing Paper Number CS2-3 Accelerated Pavement Testing 1999 International Conference October 18-20, 1999 Reno, Nevada

More information

PRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW

PRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW Indiana DOT Precast Concrete Pavement Forum Indianapolis, Indiana August 11, 2016 PRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW Shiraz Tayabji, stayabji@gmail.com Applied Research Associates, Inc. (ARA)

More information

SUDAS Revision Submittal Form

SUDAS Revision Submittal Form SUDAS Revision Submittal Form Status Date: As of 5/18/2018 Topic: Pavement thickness design Manual: Design Manual Location: Section 5F-1 Requested Revision: Reason for Revision: Comments: See attached.

More information

Draft Report. Goal 4 Long Life Pavement Rehabilitation Strategies Rigid: Flexural Fatigue Life of Hydraulic Cement Concrete Beams

Draft Report. Goal 4 Long Life Pavement Rehabilitation Strategies Rigid: Flexural Fatigue Life of Hydraulic Cement Concrete Beams Draft Report Goal 4 Long Life Pavement Rehabilitation Strategies Rigid: Flexural Fatigue Life of Hydraulic Cement Concrete Beams Part of PPRP Strategic Plan Item 4.2 Prepared by: Erwin Kohler Abdikarim

More information

CRCP Long-Term Performance

CRCP Long-Term Performance R E S E A R C H S E R I E S N O. 9 S UMMARY OF CRCP Long-Term Performance PERFORMANCE OF CONTINUOUSLY REINFORCED CONCRETE PAVEMENT IN THE LTPP PROGRAM Identifying design and construction factors that lead

More information

Evaluation of Concrete Pavement Repair Using Precast Technology in Virginia

Evaluation of Concrete Pavement Repair Using Precast Technology in Virginia April 24, 2009,St. Louis, MO Evaluation of Concrete Pavement Repair Using Precast Technology in Virginia Shabbir Hossain Research Scientist Celik Ozyildirim Principal Research Scientist A partnership of

More information

Technical Memorandum-TM UCB PRC Overlay Design for Cracked and Seated Portland Cement Concrete. (PCC) Pavement Interstate Route 710

Technical Memorandum-TM UCB PRC Overlay Design for Cracked and Seated Portland Cement Concrete. (PCC) Pavement Interstate Route 710 Technical Memorandum-TM UCB PRC 99-3 Overlay Design for Cracked and Seated Portland Cement Concrete (PCC) Pavement Interstate Route 710 Prepared for: Long Life Pavement Task Force Prepared by: C. L. Monismith

More information

EXHIBIT A SCOPE OF SERVICES COMPOSITE PAVEMENTS

EXHIBIT A SCOPE OF SERVICES COMPOSITE PAVEMENTS EXHIBIT A SCOPE OF SERVICES COMPOSITE PAVEMENTS BACKGROUND Composite pavements are pavement systems constructed with both portland cement concrete (PCC) and hot mix asphalt (HMA) pavement layers. Two types

More information

Analysis of Paved Shoulder Width Requirements

Analysis of Paved Shoulder Width Requirements Analysis of Paved Shoulder Width Requirements Research Report RR-14-02 Prepared for Texas Department of Transportation Maintenance Division Prepared by Texas A&M Transportation Institute Emmanuel Fernando

More information

Session 3: Concrete Pavement Evaluation

Session 3: Concrete Pavement Evaluation Session 3: Concrete Pavement Evaluation 3.2 Learning Outcomes 1. Describe the need for a thorough pavement evaluation 2. Name the common pavement evaluation components 3. Describe what information is obtained

More information

SUDAS Revision Submittal Form

SUDAS Revision Submittal Form SUDAS Revision Submittal Form Status Date: As of 3/20/2017 Topic: Pavement thickness Manual: Design Manual Location: Section 5F-1 Requested Revision: Reason for Revision: Comments: See attached. Updating

More information

SUDAS Revision Submittal Form

SUDAS Revision Submittal Form SUDAS Revision Submittal Form Status Date: As of 3/15/2018 Topic: Pavement thickness Manual: Design Manual Location: Section 5F-1 Requested Revision: Reason for Revision: Comments: See attached. Updating

More information

Life Cycle Cost Analysis July 2011 Materials Division Page 1 TABLE OF CONTENTS V. ASPHALT PAVEMENT CONSTRUCTION/RECONSTRUCTION...

Life Cycle Cost Analysis July 2011 Materials Division Page 1 TABLE OF CONTENTS V. ASPHALT PAVEMENT CONSTRUCTION/RECONSTRUCTION... Materials Division Page 1 TABLE OF CONTENTS EXECUTIVE SUMMARY...2 I. INTRODUCTION...4 II. Purpose...4 What is LCCA?...4 History of LCCA in VDOT...4 ECONOMIC ANALYSIS COMPONENTS...6 Analysis Period...6

More information

SHRP2 R21 Composite Pavement Systems Project Overview

SHRP2 R21 Composite Pavement Systems Project Overview SHRP2 R21 Composite Pavement Systems Project Overview Michael I. Darter & Shreenath Rao Applied Research Associates, Inc. 2100 Louisiana Transportation Conference Baton Rouge, LA 10 January 2011 SHRP2

More information

LONG TERM PAVEMENT PERFORMANCE PROGRAM DIRECTIVE. Program Area: General Operations Directive Number: GO-09. Date: September 14, 1998 Supersedes: S-2

LONG TERM PAVEMENT PERFORMANCE PROGRAM DIRECTIVE. Program Area: General Operations Directive Number: GO-09. Date: September 14, 1998 Supersedes: S-2 LONG TERM PAVEMENT PERFORMANCE PROGRAM DIRECTIVE For the Technical Direction of the LTPP Program Program Area: General Operations Directive Number: GO-09 Date: September 14, 1998 Supersedes: S-2 Subject:

More information

Vision for Caltrans/UC-Berkeley Partnered Pavement Research Center. Mission for Partnered Pavement Research Program

Vision for Caltrans/UC-Berkeley Partnered Pavement Research Center. Mission for Partnered Pavement Research Program J. Harvey, UC-Berkeley Pavement Research Center December, 2000 v1.1.1 Vision for Caltrans/UC-Berkeley Partnered Pavement Research Center The vision for the Caltrans/UCB Partnered Pavement Research Center

More information

VDOT MECHANSTIC EMPIRICAL PAVEMENT DESIGN (MEPDG) IMPLEMENTATION

VDOT MECHANSTIC EMPIRICAL PAVEMENT DESIGN (MEPDG) IMPLEMENTATION VDOT MECHANSTIC EMPIRICAL PAVEMENT DESIGN (MEPDG) IMPLEMENTATION 2018 Virginia Concrete Conference Richmond, Virginia Girum Merine, PE Senior Pavement Engineer, VDOT Material Division March 2, 2018 Presentation

More information

Concrete Pavement Performance in the Southeastern United States

Concrete Pavement Performance in the Southeastern United States Concrete Pavement Performance in the Southeastern United States by Norbert J. Delatte, Mudhar Safarjalani, and Natalie B. Zinger Department of Civil and Environmental Engineering The University of Alabama

More information

Evaluation Plan for Investigation of In- Place Recycling of Asphalt Concrete as Unbound Base Material

Evaluation Plan for Investigation of In- Place Recycling of Asphalt Concrete as Unbound Base Material November 2004 Evaluation Plan for Investigation of In- Place Recycling of Asphalt Concrete as Unbound Base Material PPRC 2003-2004 Strategic Plan Item 2.4.2 Prepared by Partnered Pavement Research Center

More information

Long-Life. Life Concrete Pavements. Virginia Concrete Conference March 10, 2006 Richmond, VA. Kurt D. Smith, P.E. Applied Pavement Technology, Inc.

Long-Life. Life Concrete Pavements. Virginia Concrete Conference March 10, 2006 Richmond, VA. Kurt D. Smith, P.E. Applied Pavement Technology, Inc. Long-Life Life Concrete Pavements Virginia Concrete Conference March 10, 2006 Richmond, VA Kurt D. Smith, P.E. Applied Pavement Technology, Inc. Presentation Outline! Background! Goals and Features! Components

More information

Construction and Materials Tips

Construction and Materials Tips Construction and Materials Tips Utilizing Slot Stitching for Longitudinal Joint Separation Repair Background Published by the Construction and Bridge Divisions November 2013 Many miles of Continuously

More information

Design of Rigid Pavements

Design of Rigid Pavements Traffic and Highway Engineering (ІІ) CVL 4324 Chapter 20 Design of Rigid Pavements Dr. Sari Abusharar Assistant Professor Civil Engineering Department Faculty of Applied Engineering and Urban Planning

More information

21 PAVEMENTS General Administrative Requirements Standards Personnel Certification

21 PAVEMENTS General Administrative Requirements Standards Personnel Certification 21 PAVEMENTS 21.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with all Project pavements. The permanent pavement structure for all Project roadways is

More information

Report Number: CP2C

Report Number: CP2C Evaluation of RAC-O-HB Project FRE I-5-PM 0-38 HB project on I-5 north of Bakersfield Report Number: CP2C- 2007-103 July 7, 2007 California Pavement Preservation Center 203 Langdon Hall California State

More information

Concrete Pavement Preservation. Integrating Engineering, Economics and the Environment

Concrete Pavement Preservation. Integrating Engineering, Economics and the Environment Concrete Pavement Preservation Integrating Engineering, Economics and the Environment Some Things Last Forever Some Things Last Forever And others need a little TLC And others need a little TLC PCCP Withstands

More information

A Simplified Pavement Design Tool

A Simplified Pavement Design Tool A Simplified Pavement Design Tool Marshall Klinefelter Maryland Asphalt Association September 25, 2015 www.pavexpressdesign.com Brief Overview Why PaveXpress? What Is PaveXpress? An Introduction Overview

More information

PAVEMENT SECTION CONSTRUCTION AND MATERIALS

PAVEMENT SECTION CONSTRUCTION AND MATERIALS PAVEMENT SECTION CONSTRUCTION AND MATERIALS ME DESIGN MANUAL March 2005 1 ME DESIGN MANUAL CONTENTS SECTION 1.0 INTRODUCTION SECTION 2.0 GENERAL RECOMMENDATION 2.1 Uncalibrated ME Design Guide Justification

More information

Mechanistic Analysis of Rigid Pavement for Wheel Load Stresses by Finite Element Method Considering Different Sub-Grade

Mechanistic Analysis of Rigid Pavement for Wheel Load Stresses by Finite Element Method Considering Different Sub-Grade International Journal of Engineering Trends and Technology (IJETT) Volume Number -January 08 Mechanistic Analysis of Rigid Pavement for Wheel Load Stresses by Finite Element Method Considering Different

More information

Dr. P. NANJUNDASWAMY Department of Civil Engineering S J College of Engineering Mysore

Dr. P. NANJUNDASWAMY Department of Civil Engineering S J College of Engineering Mysore Dr. P. NANJUNDASWAMY Department of Civil Engineering S J College of Engineering Mysore 570 006 pnswamy@yahoo.com In this presentation Rigid pavement design considerstions Wheel load and temperature stresses

More information

Evaluation and Selection Guide of Method of Repair for Routine

Evaluation and Selection Guide of Method of Repair for Routine Evaluation and Selection Guide of Method of Repair for Routine Maintenance For TxDOT Maintenance Engineers Product 0-5821-P3 Project 0-5821 Project Title: Develop Guidelines for Routine Maintenance of

More information

USER RESPONSIBILITY.1 CHAPTER 1: INTRODUCTION.3 CHAPTER 2: PAVEMENT DESIGN PROCEDURES.5 CHAPTER 3: PROJECT SCOPE.7 CHAPTER 4: DATA COLLECTION.

USER RESPONSIBILITY.1 CHAPTER 1: INTRODUCTION.3 CHAPTER 2: PAVEMENT DESIGN PROCEDURES.5 CHAPTER 3: PROJECT SCOPE.7 CHAPTER 4: DATA COLLECTION. Oregon Department of Transportation Pavement Services Unit April 2006 TABLE OF CONTENTS Page USER RESPONSIBILITY...1 CHAPTER 1: INTRODUCTION...3 CHAPTER 2: PAVEMENT DESIGN PROCEDURES...5 CHAPTER 3: PROJECT

More information

Review of Caltrans Concrete Pavement Sealed and Unsealed Pavement Performance

Review of Caltrans Concrete Pavement Sealed and Unsealed Pavement Performance 2010 Review of Caltrans Concrete Pavement Sealed and Unsealed Pavement Performance Field Review Observations On August 24-25, 2010 a joint Caltrans and Industry group met to discuss the state- 0f- the

More information

Deterioration of Concrete Roads

Deterioration of Concrete Roads Deterioration of Concrete Roads Concrete Roads Joint Spalling Punch outs Cracking Faulting Slab failures Riding Quality Models From USA Chile 2 Types of Deterministic Models Absolute (Concrete HDM-4) Predicts

More information

Construction, Instrumentation, and Testing of Fast-Setting. Hydraulic Cement Concrete in Palmdale, California

Construction, Instrumentation, and Testing of Fast-Setting. Hydraulic Cement Concrete in Palmdale, California Construction, Instrumentation, and Testing of Fast-Setting Hydraulic Cement Concrete in Palmdale, California Report Prepared for CALIFORNIA DEPARTMENT OF TRANSPORTATION By Jeffery R. Roesler, Clark W.

More information

Rigid pavement in the United States dates back to the

Rigid pavement in the United States dates back to the Finite element analysis and load tests of full-scale, variable-thickness precast, prestressed concrete pavement on granular base Nasser M. Alwehaidah and Bruce W. Russell Rigid pavement in the United States

More information

INTERSTATE 40 FREEWAY

INTERSTATE 40 FREEWAY 11 YEAR U P D A T E 2 0 1 1 40 INTERSTATE 40 FREEWAY SOIL STABILIZATION EXTENDS SERVICE LIFE EMC SQUARED System Outperforms Lime Treatment The EMC SQUARED Treatment extends project Theoretical Design Life

More information

National Trends in Pavement Design

National Trends in Pavement Design National Trends in Pavement Design Southeastern States Pavement Management Association Pavement Management and Design May 11, 2009 New Orleans, Louisiana Gary Crawford Federal Highway Administration gary.crawford@dot.gov

More information

Chapter 1: INTRODUCTION

Chapter 1: INTRODUCTION Chapter 1: INTRODUCTION Figure 1.1. Photo of deteriorated concrete pavement. Pavement Repair: A Worldwide Necessity The need for rapid repair and replacement of concrete pavement is evident in every large

More information

CHAPTER B TABLE OF CONTENTS

CHAPTER B TABLE OF CONTENTS July 2006 Page B-1 CHAPTER B TABLE OF CONTENTS B.00 Introduction B.01 Definitions B.02 Maintenance Levels B.03 Definition of Traveled Way B.04 Policy for Performing Roadbed Maintenance Work B.05 Surface

More information

Introduction to Pavement Overlays

Introduction to Pavement Overlays Introduction to Pavement Overlays Course No: C02-046 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980

More information

Technology Transfer Program

Technology Transfer Program Institute of Transportation Studies TECHNICAL TOPICS Technology Transfer Program The Technology Transfer Program is the continuing education arm of UC Berkeley s Institute of Transportation Studies. Our

More information

Implementation of the AASHTO Pavement Design Procedures into MULTI-PAVE

Implementation of the AASHTO Pavement Design Procedures into MULTI-PAVE Implementation of the AASHTO Pavement Design Procedures into MULTI-PAVE Master Degree Project Abiy Bekele Division of Highway and Railway Engineering Department of Civil and Architectural Engineering Royal

More information

PRESENTATION OVERVIEW

PRESENTATION OVERVIEW Professor Jeffery Roesler, P.E. Dept. of Civil & Environmental Engineering University of Illinois at Urbana Champaign TRB Webinar Continuously Reinforced Concrete Pavement Part 2: Mechanistic Empirical

More information

Constructability and Productivity Analysis for Long. Life Concrete Pavement Rehabilitation Strategies

Constructability and Productivity Analysis for Long. Life Concrete Pavement Rehabilitation Strategies Constructability and Productivity Analysis for Long Life Concrete Pavement Rehabilitation Strategies Report Prepared for CALIFORNIA DEPARTMENT OF TRANSPORTATION By E. B. Lee, C.W. Ibbs, J.T. Harvey, J.

More information

Florida s Concrete Test Road. National Concrete Consortium Meeting September 23-25, 2013

Florida s Concrete Test Road. National Concrete Consortium Meeting September 23-25, 2013 Florida s Concrete Test Road National Concrete Consortium Meeting September 23-25, 2013 1 Why a Florida Test Road? Answers need for detailed data for rigid (PCC) pavement under Florida conditions. Currently

More information

Concrete Paving in NOVA Conventional and Pervious Concrete & Streets and Local Roads. Rod Meyers, PE, BASF Construction Chemicals

Concrete Paving in NOVA Conventional and Pervious Concrete & Streets and Local Roads. Rod Meyers, PE, BASF Construction Chemicals Concrete Paving in NOVA Conventional and Pervious Concrete & Streets and Local Roads Rod Meyers, PE, BASF Construction Chemicals How Thick Should The Pervious Concrete Pavement Be? ACI 552-10, Report on

More information

Chapter Forty-four PAVEMENT DESIGN BUREAU OF LOCAL ROADS AND STREETS MANUAL

Chapter Forty-four PAVEMENT DESIGN BUREAU OF LOCAL ROADS AND STREETS MANUAL Chapter Forty-four PAVEMENT DESIGN BUREAU OF LOCAL ROADS AND STREETS MANUAL Jan 2012 PAVEMENT DESIGN 44(i) Chapter Forty-four PAVEMENT DESIGN Table of Contents Section Page 44-1 GENERAL... 44-1(1) 44-1.01

More information

Design of Illinois Tollway Composite Pavements

Design of Illinois Tollway Composite Pavements Design of Illinois Tollway Composite Pavements William R. Vavrik, Ph.D., P.E. FHWA Tollway National Open House, August 20, 2013 1 Presentation Overview Starting in Composite Pavements Move to 2-Lift Concrete

More information

ACKNOWLEDGMENT OF SPONSORSHIP

ACKNOWLEDGMENT OF SPONSORSHIP ACKNOWLEDGMENT OF SPONSORSHIP This work was sponsored by the American Association of State Highway and Transportation Officials, in cooperation with the Federal Highway Administration, and was conducted

More information

Investigation of Design and Construction Issues for Long Life. Concrete Pavement Strategies

Investigation of Design and Construction Issues for Long Life. Concrete Pavement Strategies Investigation of Design and Construction Issues for Long Life Concrete Pavement Strategies Report Prepared for CALIFORNIA DEPARTMENT OF TRANSPORTATION By Jeffery R. Roesler, John T. Harvey, Jennifer Farver,

More information

Achieve Longer Life Pavement Structure. Tommy E. Nantung INDOT Research and Development Division

Achieve Longer Life Pavement Structure. Tommy E. Nantung INDOT Research and Development Division Pavement Underdrain to Achieve Longer Life Pavement Structure Tommy E. Nantung INDOT Research and Development Division Sources of Moisture Through permeable surface From edge Capillary action Seepage from

More information

Evaluation of New Patching Material for Open-Graded Asphalt Concrete (OGAC) Wearing Courses

Evaluation of New Patching Material for Open-Graded Asphalt Concrete (OGAC) Wearing Courses June 2005 Technical Memorandum: UCPRC-TM-2005-9 Evaluation of New Patching Material for Open-Graded Asphalt Concrete (OGAC) Wearing Courses Author: Karl Frick, California Department of Transportation,

More information

Concrete Pavement Preservation 2018 TRC Transportation Engineering Conference May 16, 2018 Hot Springs, Arkansas

Concrete Pavement Preservation 2018 TRC Transportation Engineering Conference May 16, 2018 Hot Springs, Arkansas Concrete Pavement Preservation 2018 TRC Transportation Engineering Conference May 16, 2018 Hot Springs, Arkansas Peter Taylor, PhD., P.E. ptaylor@iastate.edu 1 Outline Service Life Trigger Values Typical

More information

RESPONSE OF IOWA PAVEMENTS TO A TRACKED AGRICULTURAL VEHICLE

RESPONSE OF IOWA PAVEMENTS TO A TRACKED AGRICULTURAL VEHICLE RESPONSE OF IOWA PAVEMENTS TO A TRACKED AGRICULTURAL VEHICLE FINAL REPORT Sponsored by the Highway Division of the Iowa Department of Transportation Iowa DOT Project HR-1075 CTRE Management Project 99-51

More information

July 2009 Research Report: UCPRC-RR

July 2009 Research Report: UCPRC-RR July 29 Research Report: UCPRC-RR-29-2 Warm-Mix Asphalt Study: First-Level Analysis of Phase 2 HVS and Laboratory Testing and Phase 1 and Phase 2 Forensic Assessments Authors: D. Jones, R. Wu, B. Tsai,

More information

Széchenyi István University Faculty of Architecture, Civil Engineering and Transport Sciences Department of Transport Infrastructure.

Széchenyi István University Faculty of Architecture, Civil Engineering and Transport Sciences Department of Transport Infrastructure. Széchenyi István University Faculty of Architecture, Civil Engineering and Transport Sciences Department of Transport Infrastructure Pavement failures Themes of lecture Failure types of pavements Different

More information

Thickness Requirement of a Rigid Pavement with varying Conditions of Subgrade, Sub-Base and Shoulders

Thickness Requirement of a Rigid Pavement with varying Conditions of Subgrade, Sub-Base and Shoulders IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: -, p-issn: -X. PP - Thickness Requirement of a Rigid Pavement with varying Conditions of Subgrade, Sub-Base and Shoulders Surender Singh,

More information

Performance Experience and Lessons Learned from the SPS 2 Test Sections of the Long Term Pavement Performance Program (LTPP)

Performance Experience and Lessons Learned from the SPS 2 Test Sections of the Long Term Pavement Performance Program (LTPP) December 2018 www.cproadmap.org ROAD MAP TRACK 6 PROJECT TITLE Performance Experience and Lessons Learned from the SPS 2 test sections of the Long Term Pavement Performance Program (LTPP) AUTHOR Kevin

More information

SHRP2 Renewal Project R23 PAVEMENT RENEWAL SOLUTIONS

SHRP2 Renewal Project R23 PAVEMENT RENEWAL SOLUTIONS SHRP2 Renewal Project R23 PAVEMENT RENEWAL SOLUTIONS Pavement Design Section Roadway Engineering Group Arizona Department of Transportation December, 2016 ABSTRACT One of the goals for the creation of

More information

Investigation of Tire/Pavement Noise for Concrete Pavement Surfaces: Summary of Four Years of Measurements

Investigation of Tire/Pavement Noise for Concrete Pavement Surfaces: Summary of Four Years of Measurements June 2013 Research Report: UCPRC-RR-2013-12 Investigation of Tire/Pavement Noise for Concrete Pavement Surfaces: Summary of Four Years of Measurements Authors: A. Rezaei and J. Harvey Work Conducted as

More information

Competitive pricing Good fitwith new environmental designs. Why Parking lots? Design is out of whack! Construction Practices Today

Competitive pricing Good fitwith new environmental designs. Why Parking lots? Design is out of whack! Construction Practices Today Parking lot construction Why Concrete? Competitive pricing Good fitwith new environmental designs Why Parking lots? Design is out of whack! Construction Practices Today Why Concrete? Pricing of concrete

More information

JOINTED PCC PAVEMENTS

JOINTED PCC PAVEMENTS JOINTED PCC PAVEMENTS REINVENTING THE OLD APPROACH Hua Chen, P.E Rigid Pavements and Concrete Materials Branch Construction Division, TxDOT 2014 Short Course Jointed PCC Pavements - Jointed Portland Cement

More information

Scoping & Design Project Level. By Robert J. Blight Principal Engineer Pavement Management & Technology

Scoping & Design Project Level. By Robert J. Blight Principal Engineer Pavement Management & Technology Scoping & Design Project Level Data Collection & Analysis By Robert J. Blight Principal Engineer Pavement Management & Technology Goals Share process Provide knowledge Identify key data Feedback Reliable

More information

Integrated Pavement Solutions

Integrated Pavement Solutions Integrated Pavement Solutions 1 Product Solutions for Every Paving Need Application Solution Mainline highways Commercial airports General aviation airports PCC pavement Heavy-duty industrial Concrete

More information

How Loads Are Distributed

How Loads Are Distributed LOAD DISTRIBUTION 1 LOAD DISTRIBUTION This section illustrate how load will transmit from the deck to the stringers. Determining the fraction of load carried by a loaded member and the remainder distributed

More information

June 2006 Research Report: UCPRC-RR

June 2006 Research Report: UCPRC-RR June 26 Research Report: UCPRC-RR-24-7 Full-Depth Pavement Reclamation with Foamed Asphalt: First-Level Analysis Report on HVS Testing on State Route 89 Authors: H Theyse, F Long, D Jones, and J Harvey

More information

PERFORMANCE OF CONCRETE PAVEMENTS WITH OPTIMIZED SLAB GEOMETRY

PERFORMANCE OF CONCRETE PAVEMENTS WITH OPTIMIZED SLAB GEOMETRY CIVIL ENGINEERING STUDIES Illinois Center for Transportation Series No. 09-053 UILU-ENG-2009-2034 ISSN: 0197-9191 PERFORMANCE OF CONCRETE PAVEMENTS WITH OPTIMIZED SLAB GEOMETRY Prepared By Victor Cervantes

More information

Interpretation of Backcalculated Layer. Falling Weight Deflectometer Data. Moduli of Crack-and-Seat Pavement from

Interpretation of Backcalculated Layer. Falling Weight Deflectometer Data. Moduli of Crack-and-Seat Pavement from TRANSPORTATION RESEARCH RECORD 1377 167 Interpretation of Backcalculated Layer Moduli of Crack-and-Seat Pavement from Falling Weight Deflectometer Data MUSTAQUE HOSSAIN AND LARRY A. SCOFIELD In 1986 the

More information

RESILIENT INFRASTRUCTURE June 1 4, 2016

RESILIENT INFRASTRUCTURE June 1 4, 2016 RESILIENT INFRASTRUCTURE June 1 4, 2016 REPAIRING HIGH VOLUME HMA HIGHWAYS WITH PRECAST CONCRETE INLAY PANELS Daniel Pickel, M.A.Sc., B.Ed. University of Waterloo, Canada Susan Tighe, Ph.D., P.Eng, M.C.S.C.E.

More information

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two. Design Manual Chapter 6 - Geotechnical 6C - Pavement Systems 6C-1 Pavement Systems A. General Information This section addresses the importance of pavement foundations and the potential for pavement problems

More information

SPECIAL PROVISION Concrete Pavement

SPECIAL PROVISION Concrete Pavement 1995 Metric CSJ s 0902-48-305, etc. SPECIAL PROVISION 360---036 Concrete Pavement For this project, Item 360, Concrete Pavement, of the Standard Specifications, is hereby amended with respect to the clauses

More information

LIFE CYCLE COST ANALYSIS OF PRECAST CONCRETE PAVEMENT Shiven Jiten Sompura 1 and Hakob Avetisyan, Ph.D. 2

LIFE CYCLE COST ANALYSIS OF PRECAST CONCRETE PAVEMENT Shiven Jiten Sompura 1 and Hakob Avetisyan, Ph.D. 2 LIFE CYCLE COST ANALYSIS OF PRECAST CONCRETE PAVEMENT Shiven Jiten Sompura 1 and Hakob Avetisyan, Ph.D. 2 1 Graduate Research Assistant at the Department of Civil and Environmental Engineering, 800 N.

More information

SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA

SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA 0 0 0 0 SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA Mohamed Elfino, Ph.D., P.E. * Assistant State Materials

More information

Introduction to Asphalt Pavement Design and Specifications

Introduction to Asphalt Pavement Design and Specifications Introduction to Asphalt Pavement Design and Specifications Ensuring Good Performance in Flexible Pavement Design and Construction: accomplished through: 1. Proper structural (thickness) design for the

More information

Concrete Pavement: Concrete Pavement Basics. Basic Components of a Concrete Pavement. Concrete Pavement Types. Jointed Plain

Concrete Pavement: Concrete Pavement Basics. Basic Components of a Concrete Pavement. Concrete Pavement Types. Jointed Plain Concrete Pavement: PCCP Repair & Rehabilitation Applications, Options & Performance Concrete Pavement Basics Purdue Road School March 25, 2003 Basic Components of a Concrete Pavement Surface smoothness

More information

Laboratory Evaluation of Fiber-Reinforced Polymer Dowel Bars for Jointed Concrete Pavements

Laboratory Evaluation of Fiber-Reinforced Polymer Dowel Bars for Jointed Concrete Pavements Laboratory Evaluation of Fiber-Reinforced Polymer Dowel Bars for Jointed Concrete Pavements Yi Bian Erwin Kohler John Harvey TRB Annual Meeting, Washington D.C. January 24 th, 2007 Introduction LTE controls

More information

April 2015 Technical Memorandum: UCPRC-TM

April 2015 Technical Memorandum: UCPRC-TM April 2015 Technical Memorandum: UCPRC-TM-2015-02 Authors: S. Louw and D. Jones Partnered Pavement Research Center (PPRC) Project Number 4.52a (DRISI Task 2708): Microcracking of Cement-Stabilized Pavement

More information

INDOT Thin Concrete Overlay Initiatives. Tommy E. Nantung INDOT Division of Research and Development

INDOT Thin Concrete Overlay Initiatives. Tommy E. Nantung INDOT Division of Research and Development INDOT Thin Concrete Overlay Initiatives Tommy E. Nantung INDOT Division of Research and Development System of Concrete Overlays Thinner Concrete Overlays Thicker Bonded Overlay System Unbonded Overlay

More information

Work Plan UCPRC-WP-2005/05 (Version 2) November 22, 2005

Work Plan UCPRC-WP-2005/05 (Version 2) November 22, 2005 Work Plan UCPRC-WP-2005/05 (Version 2) November 22, 2005 Work Plan for: Development of Improved Mix and Structural Design and Construction Guidelines for Deep In-Situ Recycling (DISR) of Cracked Asphalt

More information

MnROAD Phase 3 Concrete Pavement Construction Update

MnROAD Phase 3 Concrete Pavement Construction Update MnROAD Phase 3 Concrete Pavement Construction Update Tom Burnham, P.E. Senior Road Research Engineer, Minnesota Department of Transportation NCC Fall Meeting, Minneapolis, MN 9/20/2017 MnROAD Facility

More information

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five Project Overview Location SR 600 / US 92, Volusia County FPN:

More information

Pavement Design. TTP Orientation Seminar 2011

Pavement Design. TTP Orientation Seminar 2011 Pavement Design TTP Orientation Seminar 2011 What are Pavements? Engineered structures in contact with the earth's surface built to facilitate movement of people and goods Pedestrians Personal vehicles

More information

GlasGrid Asphalt Pavement Reinforcement. October 21, 2016

GlasGrid Asphalt Pavement Reinforcement. October 21, 2016 GlasGrid Asphalt Pavement Reinforcement October 21, 2016 Introduction to Cracks Crack sources are numerous and varied Cracks are consistent pavements aren t Solutions for cracks have had mixed results

More information

550 Surface Treatments

550 Surface Treatments Table of Contents 550 Surface Treatments... 550-1 550.1 Introduction... 550-1 551 Crack Sealing... 550-1 551.1 Project Selection... 550-1 551.2 Design Considerations... 550-1 552 Chip Sealing... 550-2

More information

NETWORK LEVEL PAVEMENT STRUCTURAL EVALUATION THROUGH THE USE OF THE ROLLING WHEEL DEFLECTOMETER

NETWORK LEVEL PAVEMENT STRUCTURAL EVALUATION THROUGH THE USE OF THE ROLLING WHEEL DEFLECTOMETER NETWORK LEVEL PAVEMENT STRUCTURAL EVALUATION THROUGH THE USE OF THE ROLLING WHEEL DEFLECTOMETER Paul Wilke, P.E. Applied Research Associates Inc. 3605 Hartzdale Drive Camp Hill, PA 17011 December 4, 2014

More information

Design of Continuously Reinforced Concrete Pavement with Heat Transfer System for a Bus Terminal in Hamilton

Design of Continuously Reinforced Concrete Pavement with Heat Transfer System for a Bus Terminal in Hamilton Design of Continuously Reinforced Concrete Pavement with Heat Transfer System for a Bus Terminal in Hamilton Ludomir Uzarowski, Ph.D., P.Eng., Golder Associates Ltd., Whitby, Ontario Imran Bashir, M.Sc.,

More information

Long-Life and Sustainable Concrete Pavements

Long-Life and Sustainable Concrete Pavements Long-Life and Sustainable Concrete Pavements by Mang Tia Professor of Civil Engineering Engineering School of Sustainable Infrastructure and Environment University of Florida Presentation at 3 rd International

More information

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt

More information