Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014

Size: px
Start display at page:

Download "Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014"

Transcription

1 Study on Economic Partnership Projects in Developing Countries in FY2013 Study on the Highway Bridge in the New Urban Area of Hai Phong, the Socialist Republic of Vietnam Final Report SUMMARY February 2014 Prepared for: The Ministry of Economy, Trade and Industry Ernst & Young Shin Nihon LLC Japan External Trade Organization Prepared by: Chodai Co., Ltd. IHI Infrastructure Systems Co., Ltd. Mitsubishi Corporation Nippon Steel & Sumitomo Metal Corporation

2 (1) Background and Necessity of the Project 1) Background of the Project The socialist Republic of Viet Nam (hereinafter referred to as Vietnam ) enacted the Doi Moi (Renovation Policy in 1986 and began obtaining its effects around After that, economic grouth in Vietnam continued as high as 9% for the years of 1995 and In 1997, however, tendencies such as slow-down of the growth rate surfaced and foreign direct investment abruptly decreased under the impact of the Asian economic crisis, thereby decreasing the growth of rate to 4.8% in In 2010, the growth rate recovered to 6.8%, the level before the crisis, because the governmental policies of economic stimulus and monetary easing (interest rate of 4%) worked well, which came into effect in However, due to monetary restraint by the Vietnamese government for inflation control, the growth rate slowed down to 5.9%. The economic growth rate of Vietnam in 2012 was 5.0%, which was below both the government s original goal of 6.0% and the downward-revised goal of 5.2%. On the other hand, the raise of consumer price index remained 9.2% in yearly average, lower than the government goal of 10.0%. Exchange rate against US dollars maintains 20,800 (VND (Vietnam Dong) / USD (US Dollar)). These infer that the macroeconomy of Vietnam remains stable. Trade balance turned to surplus after 19 years. Hai Phong city is the third largest city of Vietnam, located in the northern part of the country, approximately 100km away in the east side from Ha Noi. Hai Phong city is proceeding the urban development based on the Amendment of Haiphong Construction Master Plan to 2025 and Vision to 2050 (approved by the prime minister in September 2009). This master plan aims to develop Hai Phong city to be a modern industrial city based on science technologies, targeting to urbanize 90 ~ 95% of the city. Figure S1 Hai Phong City Master Plan North urban development area Nomura-Haiphong Ind. zone Development area Industrial area Government/ Public facility 3 rd ring road Cam river Existing city area Dinh Vu industrial parks 2 nd ring road Cat Bi airport Lach Huyen port Ha Noi Hai Phong Expressway k Source: Hai Phong City Master Plan 2) Necessity of the Project The master plan includes the followings:

3 Port development-demolition of existing Hai Phong port and its function relocation to Dimh Vu port and Lach Huyen port. Urban development development of urban area in the north of Cam river and relocation of administrative areas. Development of large industrial parks in Dinh Vu area and the north area of Cam river in addition to the existing Nomura-Haiphong Industrial Zone. Diversification of means of transport such as: Formulation of highway network such as Ha Noi Hai Phong Expressway, 2nd and 3rd ring roads Internationalization of Cat Bi airport and new construction of Tien Lang airport The Project intends to secure the linkage for the newly developed city area at the north of Hai Phong city among the existing city area and new city area including administrative district embracing approximately 200,000 of daytime population, securing access function ring roads and urban arterial highways with two of long span bridges such as Vu Yen bridge and Nguyen Trai bridge and additionally intends to aim for promotion of urban development and enticement/functional extension of industrial campus, for which Japanese firms would participate, based on access improvement for Lach Huyen port being constructed by Japan's ODA. Herein, further economic growth will be advanced, improving road traffic network of Hai Phong city in conjunction with precedent infrastructure development of ocean, sky and river. In case that the Project is not be implemented, because the existing urban arterial highways crossing Cam river between new and old city areas are only connected by Binh bridge constructed by Japan's ODA in 2005, cable-stayed bridge with 4 lanes, and Kien bridge constructed by Japan's yen loan in 2003, cable-stayed bridge with 2 lanes, the pre-feasibility study implemented by AECOM in 2013 reported that serious stagnation of urban function would be caused due to excess of allowable traffic volume of the existing bridges as of 2025 against increased vehicle volume resulted by development of new city area, north side industrial campus and new administrative district. The traffic jam caused by shortage of crossing-river bridges will affects the lives of Japanese and local workers in Japanese firms constituting majority of the new industrial campus, which may bring economic losses such as reduction of logistics and productivity. Therefore, adequate securement of commuting traffic network as well as urban arterial highway aiming for efficient logistics to Lach Huyen port is requisite development. Figure S2 Project location Source: Hai Phong City Master Plan

4 Photo-S1 shows the north development area model in VSIP office. The project location of Nguyen Trai bridge and Vu yen bridge is shown in Photo-S2, S3. The Construction condition of Ha Noi-Hai Phohg Expressway which the south approach of Vu Yen Bridge will be connected is shown in Photo-S4. Photo S1 North Development Area Model Photo S2 Project Location of Nguyen Trai Bridge Bridge Location Photo S3 Project Location of Vu Yen Bridge Photo S4 The Construction condition of Ha Noi-Hai Phohg Expressway Bridge Location (2) Basic Policy for determining the contents of the project 1) Scope of the Project The target two bridges are defined as important installations of the ring road plan of Hai Phong city and are located on the major route on the basis of the city development master plan "Amendment of Hai Phong Construction Master Plan to 2025 and Vision to 2050" approved by the government of Vietnam in For Vu Yen Bridge, DOT of Hai Phong City prepared a study report in 2012 and for Nguyen Trai Bridge AECOM, which is a Singaporean consultant, prepared a study report in In this report, The report by DOT of Hai Phong City is described as "Vu Yen Bridge Study Report" and the report by AECOM is described as "Nguyen Trai Bridge Study Report". The location of the bridges are located as follows: Vu Yen Bridge: Crossing Cam river in the overlap section of the second and third ring roads at Hai Phong city.

5 Cable-Stayed Bridge, Bridge length L=640m, Center Span 300m, Approach bridges L=785m+800m, total length 1,585m. Nguyen Trai Bridge: Directly connected among new and existing city area, administrative districts, north side industrial campus and Cat Bi airport. Cable-Stayed Bridge, Bridge length L=630m, Center Span 290m, Approach bridges L=240m x 2, total length 480m. The Project consists of the following elements: - Approach Road - Main Bridges (Cable-Stayed bridges) - Approach Bridge Because it was considered that the bridge site planned on Hai Phong development master plan was validid, the bridge site for Vu Yen Bridge and Nguyen Trai Bridge was the same as the master plan. The scope of the Project included in the city development master plan of Hai Phong City as a major route is proper scope from the point of view of constructability and existing condition with neighboring work sections. Figure S3 and S4 shows the project location respectively. Figure S3 Scope of the Project (Vu Yen Bridge) L=785m Total L=2,225m L=640m L=800m Figure S4 Scope of the Project (Nguyen Trai Bridge) Total L=1,110m L=240m L=630m L=240m

6 2) Outline of the Project a) Road Standard, Design Speed Road Standard: TCVN 4054: 2005 (Highway-Specifications for Design) Design Speed: V=100km/h b) Road Width Following cross sections connecting to bridges and approach roads are shown below: Figure S5 Location of Approach Roads and Standard Cross Sections (b) (d) (c) (a) Source: Hai Phong City Master Plan b)-1. Vu Yen Bridge Figure S6 South Side (a) Source: DOC Hai Phong Figure S7 North Side (b) Source: DOC Hai Phong

7 Figure S8 Bridge b)-2. Nguyen Trai Bridge Figure S9 South Side (c) Figure S10 North Side (d) Source: DOC Hai Phong Figure S11 Bridge 3) Basic Policy for determining the contents of the project a) Traffic Demand Forecasting The significant population growth is expected in Hai Phong city through an economic growth with Lach Huyen port construction and urban development in the Northern area of Cam River. Especially, forecast population in Thuy Nguyen district which is located in Northern area of Cam River is 251,000 in 2025 (about 240,000 increase from 16,000 in 2009). From the above, the chronic traffic congestion is predicted to occur in both existing bridges, Kien bridge and Binh bridge, and it interfere daily activities of local residents and distribution activities of companies.

8 In this study, traffic demand forecast was made to evaluate the necessity of Nguyen Trai bridge and Vu Yen bridge construction and the effect (included calculation for economic analysis). Urban development master plan approved by Hai Phong city in 2009 predicted traffic demand based on a traffic survey which is studied in 2004 and prepared future OD tables for 2020 and 2030 and future network. b) Natural Condition b)-1. Geographical and Geological Conditions Natural low-lying area by mangrove coast is distributed around geographical condition around the bridge location. For geological condition along Cam river, sensitive clay is accumulated until the depth of GL-30m. The ground base of such the low-lying area tends to effect geologically particularities such as Change of pure water pressure attended by transition of ground water, erosion effected by flowing water and ocean waves, softening by interfusion and immersion, Salinity eluviations/ accumulation and Shrinkage/ hardening by aridity. Therefore, the following items may be recommendable to be studied for technical examination for foundations on the neighboring ground base. - Settlement/ deformation due softening of ground stiffness - Reduction of bearing capacity due to decrease of effective stresses in fracture face b)-2. Earthquake For seismic design for structures, Vietnam Standards, SPECIFICATION BRIDGE DESIGN 22 TCN , is applied. As the horizontal seismic coefficient, Seismic Zone 3 is determined. Load factor design method is utilized in consideration of the coefficients corresponding to elastic wave velocity of the ground and damping characteristic designated by each structure. b)-3. Navigation Clearance Based on discussions with the Ports and Harbors Bureau, the following navigational clearances are required. With regard to the navigational clearance of Nguyen Trai bridge, official letter No. 1522/CVHHHP-PC dated November 29th 2013 (See Appendix-3), the major point of which is "Hoan Dieu Harbor located upstream of the bridge will be relocated downstream of the Cam River after 2025; however, careful attention should be paid in planning to the fact that existing harbors will be used by pleasure ships or foreign military vessels" was issued. Therefore, in the Project a navigational clearance of 25m will be applied to Nguyen Trai bridge. In addition, the result of study about the case that 45m of navigation clearance will be applied to Nguyen Trai Bridge is also shown.

9 Table S1 Navigational Clearances in the Project Bridge Vu Yen Br. Nguyen Trai Br. Target Vessel *1 20,000DWT 20,000DWT(5,000DWT) Clearance (H) * 2 Hmax5%(+1.75m)+ 45.0m Hmax5%(+1.14m)+45.0m( 25.0m) Width (B) 80m 80m *1: When the Preparatory Survey will be carried out, it is necessary to investigate the marine traffic conditions for use of port and delay of harbor transfer. HPPC suggests the possibility that the navigation clearance, H=30m-35m, will be adopted for the ship which is from 10,000DWT to 15,000 DWT. *2: The water levels at Vu Yen Bridge and Nguyen Trai Bridge apply to the water levels at Binh Bridge and Bach Dang Bridge *3, respectively. *3: Ha Long - Hai Phong road (Official name: The road to be connected between Ha Long and the Hanoi-Hai Phong highway), which is planned in Quang Ninh Province, is in approximately 25km length. Bach Danh bridge will be constructed on the highway. b)-4. Air space The air space of Vu Yen bridge basically has 45m due to the location where the horizontal surface of the Cat Bi airport is, however, the air space, 95m, will be adopted because Bach Danh bridge has been approved on the same limitations. And then, Nguyen Trai bridge does not significantly affect the bridge plan since the distance from the airport becomes 7,000 m or more. b)-5. Other Natural Conditions Data and information for other natural conditions, such as for climate/weather, river characteristics, wind velocity/direction, were collected during the site survey. This study considered the data and information. 4) Examination of Technical Approach a) Bridge Type and Span Arrangement a)-1. Selection of Main Bridge Type For the main bridge crossing Cam river, applicable bridge types are pointed as candidates, and then, the most appropriate type is selected among them.. The length of center span should be determined as more than 300m for Vu Yen bridge and 290m for Nguyen Trai bridge, considering navigation width of W=80m, scale of foundations and lateral clearance. The applicable bridge types can be pointed as following three types Case 1: Cable-Stayed Bridge Case 2: Arch Bridge Case 3: Self-Anchored Cable Suspension Bridge

10 The comparison study is shown in Table S2 and S3. As a result of the study, the cable-stayed bridge was selected as the most suitable type of bridge from the perspective of economic efficiency and maintainability. Vu Yen Bridge Study Report and Nguyen Trai Bridge Study Report are reviewed and selectable studies are carried out, the results that a concept design was carried out are shown in Table S6 and S7. Table S2 Comparison Study of Main Bridge(Vu Yen Bridge) Bridge Type Evaluation Type-1 Type-2 Type-3 Cost Efficiency 1.00 Superstructure 288,033JPY/m 2, Substructure 187,367JPY/ m 2 Structural Efficiency Steel-PC Composite Cable Stay bridge with Double-I-Shape Girder. Pylon and Slab (PC). The standard span length is from 130m to 450m, so that there is no problem structurally. Workability The cantilever method is adopted as a erection method. It is possible to minimize the inhibition of river traffic during the construction. Maintenance Long-term anticorrosive coating(flluorine series) are applied. In case of application of such the coating, painting life will be 20 to 30 years under partial repainting. The repainting can carried out using a inspection vehicle. (Recommendable Bridge Type) Cost Efficiency 1.20 Superstructure 573,840JPY/m 2, Substructure 335,446JPY/ m 2 Structural Efficiency Arch bridge has structural properties which is high rigidity and excellent cross-section efficiency. A tied arch type is selected in the long arch bridge as the horizontal force increases. Workability The large erection method is adopted as a erection method. The adjustment with river administrator is required. Maintenance Same to Case-1, long-term anticorrosive coating is applied. The repainting needs a scaffolding to be installed to parts of arch, so that the traffic restriction is needed during the work. Cost Efficiency 1.35 Superstructure 548,306JPY/m 2, Substructure 217,027JPY/ m 2 Structural Efficiency It is the type to fix the cable at both ends of the girder without anchorage. Therefore, large compressive force is working to the girder. The standard span length is from 150m to 2000m, so that there is no problem structurally. Workability The girder needs a support during the construction, so that the effect on river traffic is high. Maintenance Same to Case-1, long-term anticorrosive coating is applied. The repainting is required to apply inner surface because of the box girder.

11 Table S3 Comparison Study of Main Bridge(Nguyen Trai Bridge) Bridge Type Evaluation Type-1 Type-2 Type-3 Cost Efficiency 1.00 Superstructure 288,033JPY/m 2, Substructure 187,367JPY/ m 2 Structural Efficiency Steel-PC Composite Cable Stay bridge with Double-I-Shape Girder. Pylon and Slab (PC). The standard span length is from 130m to 450m, so that there is no problem structurally. Workability The cantilever method is adopted as a erection method. It is possible to minimize the inhibition of river traffic during the construction. Maintenance Long-term anticorrosive coating(flluorine series) are applied. In case of application of such the coating, painting life will be 20 to 30 years under partial repainting. The repainting can carried out using a inspection vehicle. (Recommendable Bridge Type) Cost Efficiency 1.20 Superstructure 573,840JPY/m 2, Substructure 335,446JPY/ m 2 Structural Efficiency Arch bridge has structural properties which is high rigidity and excellent cross-section efficiency. A tied arch type is selected in the long arch bridge as the horizontal force increases. Workability The large erection method is adopted as a erection method. The adjustment with river administrator is required. Maintenance Same to Case-1, long-term anticorrosive coating is applied. The repainting needs a scaffolding to be installed to parts of arch, so that the traffic restriction is needed during the work. Cost Efficiency 1.35 Superstructure 548,306JPY/m 2, Substructure 217,027JPY/ m 2 Structural Efficiency It is the type to fix the cable at both ends of the girder without anchorage. Therefore, large compressive force is working to the girder. The standard span length is from 150m to 2000m, so that there is no problem structurally. Workability The girder needs a support during the construction, so that the effect on river traffic is high. Maintenance Same to Case-1, long-term anticorrosive coating is applied. The repainting is required to apply inner surface because of the box girder.

12 Figure S12 Vu Yen Bridge

13 Figure S13 Nguyen Trai Bridge

14 (3) Outline of the Project 1) Construction Cost A preliminary total project cost is shown in Table S4 and Table S5. The preliminary total project cost for Vu Yen Bridge is estimated approximately 23.6 billion yen (4 trillion billion Vietnam Dong), for Nguyen Trai Bridge is estimated approximately 19.2 billion yen (3 trillion billion Vietnam Dong), in case that 45m of navigation clearance for Nguyen Trai Bridge is estimated approximately 25.1 billion. Table S4 Preliminary Total Project Cost for Vu Yen Bridge Item JPY (Mill.) VND (Mill.) Equivalent JPY(Mill.) Equivalent VND(Mill.) Construction Cost 12, ,856 16,265 3,299,096 Consultant Fee 10% 1,248 76,786 1, ,910 Contingency 10% 1,248 76,786 1, ,910 Sub Total 14, ,427 19,518 3,958,915 Land Acquisition Administration Cost 5% - 164, ,955 Value Added Tax(VAT) 10% - 329,910 1, ,910 Import Tax 10% - 329,910 1, ,910 Sub Total - 824,774 4, ,774 Total 14,975 1,746,201 23,584 4,783,689 Table S5 Preliminary Total Project Cost for Nguyen Trai Bridge Item JPY (Mill.) VND (Mill.) Equivalent JPY(Mill.) Equivalent VND(Mill.) Construction Cost 9, ,203 11,872 2,407,947 Consultant Fee 10% ,220 1, ,795 Contingency 10% ,220 1, ,795 Sub Total for 25m 11, ,644 14,246 2,889,536 Sub Total for 45m (13,663) (1,117,852) (19,175) (3,889,295) Land Acquisition - 400,000 1, ,000 Administration Cost 5% - 120, ,397 Value Added Tax(VAT) 10% - 240,795 1, ,795 Import Tax 10% - 240,795 1, ,795 Sub Total - 1,001,987 4,940 1,001,987 Total for 25m 11,215 1,616,630 19,186 3,891,523 Total for 45m (13,663) (2,328,121) (25,141) (5,099,565)

15 2) Calculation of Ratio of Material, Equipment and Others of Japan Origin Table S6 shows the calculation of a ratio of material, equipment and others of Japan origin based on the guidelines prepared by relevant ministries of Japan. As shown in the table, the 30% condition for STEP scheme is satisfied. Table S6 Ratio of material, equipment and others of Japan origin Vu Yen Bridge Item Cost JPY (Mill) Remark Cost for Japanese Technology Material 1,171 Sub total estimated in Table 8-2 Steel Girder 4,061 Fabrication, Erection, Stay Cable (Materials and Installation Cost ) Wind tunnel test Steel Pipe 20 Contain test Model 2,848 SPSP and Screwed Pipe (Material and Installation Cost) Total (i) Total Project Cost (ii) Ratio 8,100 About 81 hundred-millions 16,265 About 163 hundred-millions 49.8% >30% 1/2 Nguyen Trai Bridge Item Cost JPY (Mill) Remark Cost for Japanese Technology Material 743 Sub total estimated in Table 8-2 Steel Girder 4,001 Fabrication, Erection, Stay Cable (Materials and Installation Cost ) Wind tunnel test Steel Pipe 20 Contain test Model 1,415 SPSP and Screwed Pipe (Material and Installation Cost) Total (i) Total Project Cost (ii) Ratio (H=25m) Ratio (H=45m) 6,179 About 62 hundred-millions 11,872 About 118 hundred-millions 52.0% >30% 1/2 47.5% >30% 3) Overview of Preliminary Economic/Finance Analysis a) Economic Analysis In order to evaluate the effectiveness of this project from the viewpoint of the national economy, a comparative analysis of economic cost and benefit both in the case of executing the project (With the project) and not executing the project (Without the project) is carried out. In the project, the object of analysis has two bridges which are Vu Yen Bridge and Nguyen Trai Bridge, so the comparative analysis is carried out on three scenarios as follows to evaluate the effectiveness of both projects. Both Nguyen Trai Bridge and Vu Yen Bridge will be constructed Only Nguyen Trai Bridge will be constructed and Vu Yen will be not Only Vu Yen Bridge will be constructed and Nguyen Trai will be not As the evaluation indices, Economic Internal Rate of Return (EIRR), Benefit Cost Ratio (B/C) and Net Present Value (NPV) are applied.

16 The result being analyzed based on the benefit and the cost is shown in Table S7, S8, S9. When compared with social discount rate of Vietnam, this project is considered to be economically feasible. Table S7 Results of cost benefit analysis Case B/C Ratio N.P.V EIRR Both Nguyen Trai Bridge and Vu Yen Bridge will be constructed million USD 17.9% Only Nguyen Trai Bridge will be constructed and Vu Yen will be not million USD 19.8% Only Vu Yen Bridge will be constructed and Nguyen Trai will be not million USD 25.4% In the elements assumed for the economic analysis, variable factors are included in each element and some elements are based on simple assumptions. As a sensitivity analysis, some margin will be given in accordance with such variable factors and by finding out how the result of the analysis will vary; the stability of the feasibility of this project will be confirmed. From the results of analysis shown in the table below, the value of EIRR exceeds 9.3% even in the case of 20% construction cost increase or 20% benefit decrease in either scenario, so the possibility of realization of this project is high. Case Both Nguyen Trai Bridge and Vu Yen Bridge will be constructed Only Nguyen Trai Bridge will be constructed and Vu Yen will be not Only Vu Yen Bridge will be constructed and Nguyen Trai will be not b) Financial Analysis Table S8 Result of Sensitivity Analysis Construction Cost Benefit -20% 0% 20% 20% 24.3% 20.6% 17.9% -20% 17.9% 15.1% 13.1% 20% 26.7% 22.7% 19.8% -20% 19.8% 16.8% 14.6% 20% 34.1% 29.0% 25.4% -20% 25.4% 21.5% 18.8% The value of FIRR of this project is a positive value in either scenario, however, there is no financial feasibility of this project because it has less than 9.3%, which is long-term interest rate of Vietnam. On the other hand, the value of NPV is also becomes negative. It does not reach the level to promote private investment. Table S9 Result of sensitivity analysis Case B/C Ratio N.P.V FIRR Both Nguyen Trai Bridge and Vu Yen Bridge will be constructed USD 3.0% Only Nguyen Trai Bridge will be constructed and Vu Yen will be not USD 6.6% Only Vu Yen Bridge will be constructed and Nguyen Trai will be not USD 3.8% Note:Benefit of the B/C ratio uses the assumed revenue

17 In the elements assumed for this analysis (Investment cost and revenue), unknown factors are included. Some margin will be added to each element corresponding to each unknown factor, the variation of the result of the analysis is observed and the financial stability of this project will be verified. From the table below, in all cases, it is found that the value of FIRR does not satisfy the long-term interest rate of Vietnam, 9.3%. If the project will be carried out based on the appropriate construction plan and management plan, it is hard to be feasibility in a financial standpoint. Case Both Nguyen Trai Bridge and Vu Yen Bridge will be constructed Only Nguyen Trai Bridge will be constructed and Vu Yen will be not Only Vu Yen Bridge will be constructed and Nguyen Trai will be not Table S10 Result of sensitivity analysis Revenue Construction cost -20% 0% 20% 20% 5.0% 3.9% 3.0% -20% 3.0% 2.0% 1.3% 20% 9.2% 7.7% 6.6% -20% 6.6% 5.4% 4.4% 20% 5.9% 4.7% 3.8% -20% 3.8% 2.8% 2.0% * In parentheses, in the case of 45m of navigation clearance for Nguyen Trai Bridge 4) Considerations on Natural and Social Environments This study is conducted in the earliest phase of the decision making process. The major objective of Environmental and social considerations in project formation studied is to provide data to determine whether the project should be taken to the next phase, and to clearly identify a broad range of items to be investigated in the next phase, if the project goes forward, from an environmental and social standpoint. Following shows the summary that the environmental reviews to identify major impacts on natural and social environments using the JICA check list in the screening form. In this project, it is expected that there is no impact on the natural environment such as air pollution, noise, water pollution, protected areas, etc. On the earth work at construction stage, it is expected that there is no effect on water pollution, noise and vibration by implementing the measures as necessary. However, impact is expected in some places for land acquisition before construction. The impact only occurs in the site of south side approach road of the Nyguen Trai Bridge. For the construction of the south side approach road of the Nyguen Trai Bridge (the road width: 50.5m), existing Nguyen Trai street will be planned to widen. Currently, there are many residents, stores, and offices along the street. Therefore, it need to follow proper regulations and rules when this project is conducted. On the Nguyen Trai street, The widening direction is not decided, and there are following 3 plans; a) Plan of expansion to the both sides of the Nguyen Trai street

18 b) Plan of expansion to the East side of the Nguyen Trai street c) Plan of expansion to the West side of the Nguyen Trai street The Ngo Quyen People s Committee push widening plan at west side of the Nguyen Trai street, which amount of compensation is the lowest. However, the consultation is required in the government in the future. Table S11 Total Acquired Area, Number of Affected Households, and Estimated Cost for compensation Plans Total acquired area(m 2 ) Organizations Area of Affected Households(m 2 ) Households Cose to the road Far from the road 3-floor collective housing Estimated Cost (VND) Both Side 13,500 4 (3,800) 110 (8,260) 15 (900) 36 (540) 400 billion East Side 14,600 2 (5,300) 85 (5,200) 75 (3,100) billion West Side 13,600 4 (6,300) 67 (3,900) 52 (2,900) 36 (500) billion According to the Decree No.29/2011/ND-CP, this project falls under Project No. 26: Projects to build road and rail bridges, and also requires that EIA be conducted during the F/S phase. In this project, the provincial-level People s Committee is in charge of EIA reports. The project operator submits EIA reports to DONRE for certification. (4) Implementation Schedule A tentative schedule from the present time to completion of the construction is shown in Table S12 As a result of the traffic demand forecasts, it will not keep up with the traffic demand if two bridges are not constructed until For this purpose, it is necessary to follow the implementation schedule such as the preparatory survey has in 2014, the government Exchange of Notes and the loan agreement has in 2015 and the construction will be started in Based on these, a detailed implementation schedule was made At the beginning, implementation method is discussed among relevant authorities in Vietnam. When the implementation by Japanese ODA is selected, GOV (Government of Vietnam) request to JICA Hanoi for the ODA application followed by bilateral discussion and investigation on the Project. In Table S8, it is assumed that preparatory survey is carried out because of the immature level of BRITEC Report. When both countries agreed, the L/A (Loan Agreement) is signed by the two countries based on the agreed TOR (Terms of Reference) of the ODA. A required period for the said process varies depending on the contents of a project. Based on the information of the past similar projects, the time of the L/A is assumed to be October After the L/A, works including selection of the consultant, the design phase and bidding for contractors are carried out. The period of the design phase is assumed to be 11 months including F/S review, B/D (Basic design) and D/D (Detailed Design). The commencement time of the construction is assumed to be August 2017.

19 The construction would require 44 months for Vu Yen bridge and 39 months for Nguyen Trai bridge based on the study resulted in the completion time of the end of March 2021 and October 2020 respectively. (5) Feasibility on ODA Request and Implementation The Project is currently planned by HPPC although it has been included in the master plan of Hai Phong. The first step for HPPC is to request the MOT for probability of ODA implementation. Funding by GOV is not likely because of the large project scale. Private sectors may be reluctant to invest on the Project because of the large scale and the low FIRR. In addition to these financial problems, the Project requires the state-of-the-art technology on the design and construction of a cable stayed bridge. The technology has not fully established in Vietnam. Because of these reasons, HPPC hope that Vu Yen Bridge and Nguyen Trai Bridge are constructed by Japanese ODA having high reputation on the quality and schedule management. Therefore, no serious obstacle are found for the ODA implementation. Many foreign countries, such as Finland, Germany and Korea, are investing on the port facilities and factories in nearby industrial parks. Under the situation, Japan is expected to provide advice and assistance for the implementation of the Project. This would be a good opportunity for Japan to impress people with its existence.

20 Table S12 Total Project Schedule (Plan) Financial Year in Japan Work Items Final Report Submission to 1 Counterpart (HPPC,DOT) Calender Year Month Project Study in 2 Vietnam GOV requests to 3 (HANOI) ODA Project Study 4 between Japan and Vietnam 5 E/N,L/A 6 Slection of Consultant 7 F/S Review, B/D, D/D 8 Approval for Design 9 Tender Procedure 10 Tender 11 Contract Construction Work Nguyen Trai Bridge Preparation & Temporary Work 12 Main Bridge Work Approach Bridge Work Road & Miscellaneous Work Construction Work Vu Yen Bridge Preparation & Temporary Work 13 Main Bridge Work Approach Bridge Work Road & Miscellaneous Work

21 (6) Technical advantages of Japanese Firms As stated foregoing, design and construction of a cable stayed bridge of which center span is 360m requires not only sophisticated knowledge but also high-developed equipment and materials. Japan has vast of overseas experiences and lead the state-of-the-art technology in this area. Moreover, the Japanese technologies and experiences for wind tunnel tests and wind-resistant stability design are also leading the edge of the world. Additionally, some other Japanese technologies, which are applicable to the Project, such as Vacuum Consolidation Method (VCM) for soft ground improvement, Screwed Steel Pile foundation and Structural Health Monitoring System (SHMS) are also quite unique and competitive technologies. Based on the above, it is quite apparent that Japanese firms have enough competitive power and a possibility of participation to the Project. As stated above, Japanese firms have sufficient competitiveness in terms of economic efficiency, quality control and resolution of technical difficulties, etc. Consequently, application of the technologies, which make the participation of Japanese firms who are familiar to the leading-edge technologies developed by Japan dominantly, is essential to this project. It is recommended to propose and exhibit above competitiveness of Japan working on the cutting edge of bridge engineering. This approach would also provide Japanese firms and technologies with good opportunities of orders. (7) Specific Schedule until L/A and Potential Risks for Implementation Table S13 shows a tentative schedule from the present time to L/A. No considerable risks are found in the schedule because the counterpart wish to complete the Project under STEP scheme of Japanese ODA. Many large scale road/bridge projects are simultaneously ongoing in Vietnam, in some of which the schedule is behind the original one. The main reason is the resettlement and land procurement. In this Project, however, almost no people are living in the area. Therefore, social problem could be solved relatively easily once compensation for fishery and shrimp farming is smoothly agreed. One little concern may be a possible delay of the process due to negotiation and administrative procedures among the two countries, which could be managed by close communication and cooperation. In Table S12, the time of L/A is assumed to be October A potential risk to decelerate the implementation schedule may be an internal factor of the two countries.

22 1 Final Report Submission Work Items Table S13 Total Project Schedule (Plan) Financial Year in Japan Calender Year Month Cumulative No Consultant 2 Final Report Submission to Counterpart (HPPC, DOT) 3 HPPC requests to GOV GOV 4 Consensus Formation in GOV GOV 5 GOV requests to (Hanoi) 6 Evaluation by (Hanoi) 7 (Hanoi) requests to (Headquater) 8 Evaluation by (Headquater) 9 Preparation for Preparatory Survey GOV 10 Selection of Consultant for Preparatory Survey 11 Implementation of Preparatory Survey 12 Evaluation of Preparatory Survey GOV 13 Jugement of ODA Implementation 14 Preparation of TOR Exchange of Notes (E/N) 15 Loan Agreement (L/A) GOV GOV 16 Selection of PMU GOV Preparation for Tender Documents 17 for Consultant Selection GOV 18 Selection of Consultant GOV Design Phase 19 (F/S Review, B/D, D/D) GOV Consultant

23 (8) Project Location Map Figure S14 shows the project location. Figure S14 the project location Hải Phòng Đà Nẵng 0 TP HCM Nguyen Trai Bridge Vu Yen Bridge Source: Hai Phong City Master Plan

Study on Economic Partnership Projects. in Developing Countries in FY2010. Study on Phuoc An Bridge Construction Project

Study on Economic Partnership Projects. in Developing Countries in FY2010. Study on Phuoc An Bridge Construction Project Study on Economic Partnership Projects in Developing Countries in FY2010 Study on Phuoc An Bridge Construction Project on Cai Mep Thi Vai Inter-Port Road in the Socialist Republic of Vietnam SUMMARY March

More information

Japanese ODA. Ex-ante Evaluation

Japanese ODA. Ex-ante Evaluation Japanese ODA Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: North-South Expressway Construction Project (Da Nang Quang Ngai Section) (I) (II) (III) L/A signed

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Viet Nam Project: Lach Huyen Port Infrastructure Construction Project (I) L/A signed on: November 2, 2011

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Viet Nam Project: North-South Expressway Construction Project (Ben Luc Long Thanh Section)(II) L/A signed

More information

Japanese ODA. Ex-ante Evaluation

Japanese ODA. Ex-ante Evaluation Japanese ODA Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: Second Ho Chi Minh City Water Environment Improvement Project (I) (II) (III) L/A signed on: March

More information

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge)

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge) Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge) Chodai Co., Ltd., Nippon Engineering Consultants Co., Ltd., IHI Infrastructure Systems Co,. Ltd., and Sumitomo Mitsui Construction

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1.Name of the Project Country: The Socialist Republic of Vietnam Project: North-South Expressway Construction Project (Da Nang Quang Ngai Section)(I) L/A signed on:

More information

Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014

Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014 Study on Economic Partnership Projects in Developing Countries in FY2013 Study on the small hydro power project in the province of Lam Dong in Socialist Republic of Vietnam Final Report SUMMARY February

More information

Ex-ante Project Evaluation

Ex-ante Project Evaluation Ex-ante Project Evaluation 1. Name of project Country: Socialist Republic of Vietnam Name of project: Hai Phong City Environmental Improvement Project (II) L/A signing date: March 31, 2009 Loan amount:

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name. VIETNAM: Haiphong Urban Transport Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name. VIETNAM: Haiphong Urban Transport Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name VIETNAM:

More information

Study on Economic Partnership Projects. in Developing Countries in FY2009. Da Nang City in Socialist Republic of Viet Nam SUMMARY.

Study on Economic Partnership Projects. in Developing Countries in FY2009. Da Nang City in Socialist Republic of Viet Nam SUMMARY. Study on Economic Partnership Projects in Developing Countries in FY2009 Study on the Water Environment Improvement Project for Da Nang City in Socialist Republic of Viet Nam SUMMARY March 2010 NIHON SUIDO

More information

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2008. Study on the Improvement Project of Rail Freight

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2008. Study on the Improvement Project of Rail Freight Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2008 Study on the Improvement Project of Rail Freight Transport for Hanoi - Hai Phong in the Socialist Republic of Viet

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: Socialist Republic of Vietnam Project: Cai Mep - Thi Vai International Port Construction Project (II) Loan Agreement:

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1.Name of the Project Country: The Republic of the Union of Myanmar Project: Bago River Bridge Construction Project Loan Agreement: March 1,

More information

Ex-ante Evaluation - 1 -

Ex-ante Evaluation - 1 - Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: The North-South Expressway Construction Project (Ho Chi Minh City Dau Giay) (I) (Loan Agreement: March 31,

More information

STUDY ON FINAL REPORT SUMMARY. February 2013

STUDY ON FINAL REPORT SUMMARY. February 2013 STUDY ON ECONOMIC PARTNERSHIP PROJECTS IN DEVELOPING COUNTRIES IN FY2012 STUDY ON THE SECOND JAKARTA-CIKAMPEK TOLL-ROAD PROJECT IN THE REPUBLIC OF INDONESIA FINAL REPORT SUMMARY February 2013 Prepared

More information

Summary of Preliminary Study Result for Technical Cooperation Project. Date: 2008/10/8

Summary of Preliminary Study Result for Technical Cooperation Project. Date: 2008/10/8 Summary of Preliminary Study Result for Technical Cooperation Project Date: 2008/10/8 1. Full title of the Project The Project on Integrated UMRT and Urban Development for Hanoi 2. Type of the study Feasibility

More information

STUDY ON THE DEVELOPMENT OF BACH DANG BRIDGE

STUDY ON THE DEVELOPMENT OF BACH DANG BRIDGE STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS IN DEVELOPMENT COUNTRIES IN FY2012 STUDY ON THE DEVELOPMENT OF BACH DANG BRIDGE ON HALONG-HAIPHONG HIGHWAY IN THE SOCIALIST REPUBLIC OF VIETNAM FINAL

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People's Republic of Bangladesh Project: Kanchpur, Meghna and Gumti 2 nd Bridges Construction and Existing

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People s Republic of Bangladesh Project: Dhaka Mass Rapid Transit Development Project (Line 1) (E/S) Loan Agreement: June

More information

Your reliable investment location

Your reliable investment location DEEP C INDUSTRIAL CLUSTER Your reliable investment location Hanoi Haiphong Expressway Tan Vu Lach Huyen Road & Bridge Lach Huyen Deep Sea Port New Cat Bi International Airport Dinh Vu Industrial Zone Overview

More information

in Developing Countries in FY2010 Study on Ring Road No.4 Project (Trung Gia - Phung Section) in the Socialist Republic of Vietnam SUMMARY March 2011

in Developing Countries in FY2010 Study on Ring Road No.4 Project (Trung Gia - Phung Section) in the Socialist Republic of Vietnam SUMMARY March 2011 Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2010 Study on Ring Road No.4 Project (Trung Gia - Phung Section) in the Socialist Republic of Vietnam SUMMARY March 2011

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People s Republic of Bangladesh Project: The Kanchpur, Meghna and Gumti 2nd Bridges Construction and Existing Bridges Rehabilitation

More information

Ex-ante Evaluation 1. Name of the Project 2. Background and Necessity of the Project

Ex-ante Evaluation 1. Name of the Project 2. Background and Necessity of the Project Ex-ante Evaluation 1. Name of the Project Country: India Project Title: Hyderabad Outer Ring Road Project (Phase 2) Loan Agreement: November 21, 2008 Loan Amount: 42,027 million Yen Borrower: The President

More information

STUDY ON THE PROJECT FOR DEVELOPMENT OF NATIONAL STRATEGIC OIL STOCKPILING MEGA-FLOATING SYSTEM IN VIET NAM SUMMARY. February 2012.

STUDY ON THE PROJECT FOR DEVELOPMENT OF NATIONAL STRATEGIC OIL STOCKPILING MEGA-FLOATING SYSTEM IN VIET NAM SUMMARY. February 2012. STUDY ON ECONOMIC PARTNERSHIP PROJECTS IN DEVELOPING COUNTRIES IN FY2011 STUDY ON THE PROJECT FOR DEVELOPMENT OF NATIONAL STRATEGIC OIL STOCKPILING MEGA-FLOATING SYSTEM IN VIET NAM SUMMARY February 2012

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People's Republic of Bangladesh Project: Dhaka Urban Transport Development Project (I) Loan Agreement: February

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Democratic Socialist Republic of Sri Lanka Project: Greater Colombo Urban Transport Development Project Phase 2 (II) Loan

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People s Republic of Bangladesh Project: Dhaka Mass Rapid Transit Development Project (Line 5) (E/S) Loan

More information

Summary of Environmental and Social Consideration in Development Study (Preparatory Study)

Summary of Environmental and Social Consideration in Development Study (Preparatory Study) Summary of Environmental and Social Consideration in Development Study (Preparatory Study) 1. Full title of the Project The Study on Integrated Development Strategy for Danang City and Its Neighboring

More information

Case-history Steel Tubular Pile Cofferdam Foundations in Bangladesh

Case-history Steel Tubular Pile Cofferdam Foundations in Bangladesh Case-history Steel Tubular Pile Cofferdam Foundations in Bangladesh Mr. Tsunenobu Nozaki 1. Introduction General Manager International Construction Design and Planning Department Giken Ltd. The Japanese

More information

Preliminary Project Evaluation Sheet JICA, Southeast Asia and Pacific Department, Southeast Asia Division 4

Preliminary Project Evaluation Sheet JICA, Southeast Asia and Pacific Department, Southeast Asia Division 4 Preliminary Project Evaluation Sheet JICA, Southeast Asia and Pacific Department, Southeast Asia Division 4 1. Project name Country: Republic of the Union of Myanmar (Myanmar) Project name: Yangon-Mandalay

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country:Mongolia Project:New Ulaanbaatar International Airport Construction Project (II) Loan Agreement:April 16, 2015

More information

STUDY ON THE VESSEL NAVIGATION AND SECURITY MANAGEMENT NETWORK REINFORCEMENT PROJECT IN THE SOCIALIST REPUBLIC OF VIETNAM SUMMARY.

STUDY ON THE VESSEL NAVIGATION AND SECURITY MANAGEMENT NETWORK REINFORCEMENT PROJECT IN THE SOCIALIST REPUBLIC OF VIETNAM SUMMARY. STUDY ON ECONOMIC PARTNERSHIP PROJECTS IN DEVELOPING COUNTRIES IN FY2011 STUDY ON THE VESSEL NAVIGATION AND SECURITY MANAGEMENT NETWORK REINFORCEMENT PROJECT IN THE SOCIALIST REPUBLIC OF VIETNAM SUMMARY

More information

Ex-ante Evaluation - 1 -

Ex-ante Evaluation - 1 - Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: Hue City Water Environment Improvement Project (Loan Agreement: March 31, 2008; Loan Amount: 20,883 million

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japan ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: Republic of Tunisia Project: Mejerda River Flood Control Project Loan Agreement: July 17, 2014 Loan Amount: 10,398

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

1. Name of the Project

1. Name of the Project Japan ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Mumbai Metro Line III Project Loan Agreement: September 17, 2013 Loan Amount: 71,000 million yen

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of Mozambique Project: Mandimba Lichinga Road Upgrading Project Loan Agreement: November 29, 2013

More information

INTRODUCTION VINH PHUC INVESTMENT PROMOTION AGENCY. Nguyen Tien Hanh Director, IPA Vinh Phuc

INTRODUCTION VINH PHUC INVESTMENT PROMOTION AGENCY. Nguyen Tien Hanh Director, IPA Vinh Phuc VINH PHUC INVESTMENT PROMOTION AGENCY INTRODUCTION INVESTMENT CLIMATE & POLICIES FOR INVESTMENT ATTRACTION IN VINH PHUC PROVINCE VIET NAM Nguyen Tien Hanh Director, IPA Vinh Phuc CONTENT 1 ADVANTAGES OF

More information

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2008. System in the Socialist Repubic of Viet Nam SUMMARY

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2008. System in the Socialist Repubic of Viet Nam SUMMARY Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2008 Study on the PPP Project Formation for Hanoi Water Supply System in the Socialist Repubic of Viet Nam SUMMARY March

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 7 th Independent Monitoring Report September 2011 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of Indonesia Project: Construction of Jakarta Mass Rapid Transit Project (II) Loan Agreement: December

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1.Name of the Project Country: Socialist Republic of Viet Nam Project: O Mon Thermal Power Plant Unit No.2 Construction Project (II) Loan Agreement:

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of Indonesia Project: Patimban Port Development Project (I) Loan Agreement: November 15, 2017 Loan

More information

TRANSPORT INFRASTRUCTURE DEVELOPMENT & LEGAL FRAMEWORK ON PPP INVESTMENT OF VIET NAM

TRANSPORT INFRASTRUCTURE DEVELOPMENT & LEGAL FRAMEWORK ON PPP INVESTMENT OF VIET NAM TRANSPORT INFRASTRUCTURE DEVELOPMENT & LEGAL FRAMEWORK ON PPP INVESTMENT OF VIET NAM Total investment capital required: US$44bn + From State Budget: US$28.9bn (65.7%) for: Contribute to capital of BOT

More information

"Project Formulation Survey" under the Governmental Commission on the Projects for ODA Overseas Economic Cooperation in FY2012 Summary Report

Project Formulation Survey under the Governmental Commission on the Projects for ODA Overseas Economic Cooperation in FY2012 Summary Report "Project Formulation Survey" under the Governmental Commission on the Projects for ODA Overseas Economic Cooperation in FY2012 Summary Report Socialist Republic of Viet Nam Project Formulation Survey on

More information

Objectives and Methodology of the Study

Objectives and Methodology of the Study Chapter 1 Objectives and Methodology of the Study 1-1 Background to the Study In response to growing awareness of the importance of donor-partner cooperation in tackling development challenges and global

More information

Vietnam Ex-post Evaluation of Japanese ODA Loan Project National Highway No. 10 Improvement Project (I) (II)

Vietnam Ex-post Evaluation of Japanese ODA Loan Project National Highway No. 10 Improvement Project (I) (II) Vietnam Ex-post Evaluation of Japanese ODA Loan Project National Highway No. 10 Improvement Project (I) (II) Masumi Shimamura Mitsubishi UFJ Research and Consulting Co., Ltd. 1.Project Description Myanmar

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5812 Project Name. Vietnam Industrial Pollution Control Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5812 Project Name. Vietnam Industrial Pollution Control Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5812 Project Name Vietnam

More information

The Red River Delta Transport Development Program

The Red River Delta Transport Development Program Vietnam-Japan Joint Program Evaluation Study Chapter 2 The Red River Delta Transport Development Program 2-1 Overview of Vietnam s Transport Sector Vietnam s transport sector provides a full range of transport

More information

Ex-Ante Evaluation Africa Division 4, Africa Department, JICA 1. Basic Project Information 2. Background and Necessity of the Project

Ex-Ante Evaluation Africa Division 4, Africa Department, JICA 1. Basic Project Information 2. Background and Necessity of the Project Ex-Ante Evaluation Africa Division 4, Africa Department, JICA 1. Basic Project Information Country: Republic of Côte d Ivoire Project: Abidjan Port Cereal Berth Construction Project Loan Agreement: March

More information

Japanese ODA Loan. Ex-ante Evaluation

Japanese ODA Loan. Ex-ante Evaluation Japanese ODA Loan Ex-ante Evaluation 1.Name of the Project Country:Republic of El Salvador Project:San Miguel Bypass Construction Project Loan Agreement:20 August 2014 Loan Amount:12,595 million yen Borrower:Government

More information

Vietnam Sea-Ports Sector Overview

Vietnam Sea-Ports Sector Overview TAN VIET SECURITIES INCORPORATION (TVSI) 5 th Floor, HANESC Bld.152 Thuy Khue Str., Tay Ho, Hanoi, Vietnam Phone: 04 728 0921 Website: www.tvsi.com.vn Fax: 04 728 0920 Email: info@tvsi.com.vn Vietnam Sea-Ports

More information

1. Name of the Project 2. Necessity and Relevance of JBIC Assistance 1. Situation and issues of the road sector in Sri Lanka

1. Name of the Project 2. Necessity and Relevance of JBIC Assistance 1. Situation and issues of the road sector in Sri Lanka Ex-ante Evaluation 1. Name of the Project Country: The Democratic Socialist Republic of Sri Lanka Project: Southern Highway Construction Project II Loan Agreement: July 29, 2008 Loan Amount: 17,499 million

More information

The Northern Delta Transport Development Project (NDTDP) Environmental Management Process Framework For Phase 2 Investments

The Northern Delta Transport Development Project (NDTDP) Environmental Management Process Framework For Phase 2 Investments Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Northern Delta Transport Development Project (NDTDP) Environmental Management Process

More information

Ex-Post Evaluation of Japanese ODA Loan Project Bai Chay Bridge Construction Project

Ex-Post Evaluation of Japanese ODA Loan Project Bai Chay Bridge Construction Project Viet Nam Ex-Post Evaluation of Japanese ODA Loan Project Bai Chay Bridge Construction Project External Evaluator: Ryujiro Sasao, IC Net Limited 0. Summary The objective of this project is to promote smooth

More information

STUDY ON THE PROBE TRAFFIC INFORMATION SYSTEM IN DKI JAKARTA, THE REPUBLIC OF INDONESIA

STUDY ON THE PROBE TRAFFIC INFORMATION SYSTEM IN DKI JAKARTA, THE REPUBLIC OF INDONESIA STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES IN FY2011 STUDY ON THE PROBE TRAFFIC INFORMATION SYSTEM IN DKI JAKARTA, THE REPUBLIC OF INDONESIA SUMMARY February 2012 Prepared

More information

The basic design drawings for the 43 objective bridges listed in Table are shown starting from the next page.

The basic design drawings for the 43 objective bridges listed in Table are shown starting from the next page. 2-2-3 Basic Design Drawings The basic design drawings for the 43 objective bridges listed in Table 2.2.3.1 are shown starting from the next page. Table 2.2.3.1 List of 43 Objective Bridges 2 Ban Sai 30

More information

Socialist Republic of Viet Nam FY2016 Ex-Post Evaluation of Japanese ODA Loan Project Energy Efficiency and Renewable Energy Promoting Project

Socialist Republic of Viet Nam FY2016 Ex-Post Evaluation of Japanese ODA Loan Project Energy Efficiency and Renewable Energy Promoting Project Socialist Republic of Viet Nam FY2016 Ex-Post Evaluation of Japanese ODA Loan Project Energy Efficiency and Renewable Energy Promoting Project External Evaluator: Tomoo MOCHIDA, OPMAC Corporation 0. Summary

More information

Study on Economic Partnership Projects. in Developing Countries in FY2009. India SUMMARY. March 2010

Study on Economic Partnership Projects. in Developing Countries in FY2009. India SUMMARY. March 2010 Study on Economic Partnership Projects in Developing Countries in FY2009 Study on Geothermal Power Project at Uttrakhand State in India SUMMARY March 2010 West Japan Engineering Consultants, INC. Mitsubishi

More information

Ex-Post Evaluation of Japanese ODA Loan Project Cai Lan Port Expansion Project

Ex-Post Evaluation of Japanese ODA Loan Project Cai Lan Port Expansion Project Viet Nam Ex-Post Evaluation of Japanese ODA Loan Project Cai Lan Port Expansion Project External Evaluator: Ryujiro Sasao, IC Net Limited 0. Summary This project, the objective of which is to improve the

More information

Japanese ODA Loan. Ex-Ante Evaluation

Japanese ODA Loan. Ex-Ante Evaluation Japanese ODA Loan Ex-Ante Evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Haor Flood Management and Livelihood Improvement Project Loan Agreement: June 16, 2014 Loan

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Ex-Ante Evaluation (for Japanese ODA Loan) Southeast Asia Division 1, Southeast Asia and Pacific Department, JICA 1. Basic Information Country: The Republic of Indonesia Project: Construction of Jakarta

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: Federative Republic of Brazil Project: Belem Metropolitan Trunk Bus System Project Loan Agreement: September

More information

Ex-ante Evaluation. (1) Current Status and Issues of the Transportation Sector in the Republic of Kazakhstan

Ex-ante Evaluation. (1) Current Status and Issues of the Transportation Sector in the Republic of Kazakhstan Ex-ante Evaluation 1. Name of the Project Country: Kazakhstan Project: CAREC Transport Corridor (Zhambyl Oblast) Improvement Project Loan Agreement: August 23, 2010 Loan Amount: 6,361 million yen Borrower:

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of Indonesia Project: Engineering Services (E/S) for Construction of Jakarta Mass Rapid Transit East-West

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of the Union of Myanmar Project: Yangon-Mandalay Railway Improvement Project Phase I (II) Loan

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Republic of the Philippines Project: Flood Risk Management Project for Cagayan de Oro River Loan Agreement:

More information

1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance 3. Project Objectives

1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance 3. Project Objectives Ex-ante Evaluation 1. Name of the Project Country: The Democratic Socialist Republic of Sri Lanka Project: The Galle Port Development Project (I) Loan Agreement: March 28, 2006 Loan Amount: 14,495 million

More information

Study on Economic Partnership Projects. in Developing Countries in FY2007. Study on the Danube Crossing Bridge in BELGRADE CITY.

Study on Economic Partnership Projects. in Developing Countries in FY2007. Study on the Danube Crossing Bridge in BELGRADE CITY. Study on Economic Partnership Projects in Developing Countries in FY2007 Study on the Danube Crossing Bridge in BELGRADE CITY of SERBIA SUMMARY March 2008 CHODAI CO., LTD. Mitsui Consultants Co., LTD.

More information

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2007. Vietnam SUMMARY. March 2008

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2007. Vietnam SUMMARY. March 2008 Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2007 Study on Coal-fired Thermal Power Projects in Southern Vietnam SUMMARY March 2008 Electric Power Development Co.,Ltd.

More information

Bangkok Chonburi Highway Construction Project (1)

Bangkok Chonburi Highway Construction Project (1) Thailand Bangkok Chonburi Highway Construction Project (1) 1. Project Profile and Japan s ODA Loan Report Date: March 2001 Field Survey: September 2000 Myanmar Loas Thailand Bangkok Chonburi Cambodia Project

More information

Haiphong International Container Terminal Co., Ltd. The First & Best Deep-water Terminal In The North Of Vietnam

Haiphong International Container Terminal Co., Ltd. The First & Best Deep-water Terminal In The North Of Vietnam Haiphong International Container Terminal Co., Ltd. The First & Best Deep-water Terminal In The North Of Vietnam HICT - A HEARTFELT, INNOVATIVE & CARING TERMINAL 1 Container Throughput in Vietnam 2012-2017

More information

JOBS AROUND THE WORLD

JOBS AROUND THE WORLD PILE DRIVERS AND THE U.S. SUPREME COURT: A STORIED FOUNDATION OF CONSTRUCTION LAW EST. 1984 THE INTERNATIONAL PILE DRIVERS, DEEP FOUNDATIONS & MARINE CONTRACTOR S MAGAZINE PILE BUCK PRESENTS 2013 VOLUME

More information

Ex-Post Evaluation of Japanese Technical Cooperation Project The Project on the Improvement of Port Management System

Ex-Post Evaluation of Japanese Technical Cooperation Project The Project on the Improvement of Port Management System Vietnam Ex-Post Evaluation of Japanese Technical Cooperation Project The Project on the Improvement of Port Management System External Evaluator: Nobuyuki Kobayashi, OPMAC Corporation 0. Summary This project

More information

PREPARATORY SURVEY ON LACH HUYEN PORT INFRASTRUCTURE CONSTRUCTION PROJECT (ROAD AND BRIDGE PORTION) IN THE SOCIALIST REPUBLIC OF VIETNAM FINAL REPORT

PREPARATORY SURVEY ON LACH HUYEN PORT INFRASTRUCTURE CONSTRUCTION PROJECT (ROAD AND BRIDGE PORTION) IN THE SOCIALIST REPUBLIC OF VIETNAM FINAL REPORT No. SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT NO.2 (PMU2) PREPARATORY SURVEY ON LACH HUYEN PORT INFRASTRUCTURE CONSTRUCTION PROJECT (ROAD AND BRIDGE PORTION) IN THE SOCIALIST

More information

Sustainable Water Supply and Sewerage Services for Small Towns in Vietnam

Sustainable Water Supply and Sewerage Services for Small Towns in Vietnam Sustainable Water Supply and Sewerage Services for Small Towns in Vietnam O. M. Keski-Saari Water and Sanitation Programme for Small Towns in Vietnam, 37 Le Dai Hanh, Hanoi, Vietnam (E-mail: olli.keski-saari@lappavesi.fi)

More information

(1) Current State and Issues of the Electricity Sector in Indonesia

(1) Current State and Issues of the Electricity Sector in Indonesia Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Lumut Balai Geothermal Power Plant Project Loan Agreement: March 30, 2011 Loan Amount: 26,966 million

More information

Study on Economic Partnership Projects. in Developing Countries in FY2009. Study on Ho Chi Minh Elevated Railway Project in Socialist

Study on Economic Partnership Projects. in Developing Countries in FY2009. Study on Ho Chi Minh Elevated Railway Project in Socialist Study on Economic Partnership Projects in Developing Countries in FY2009 Study on Ho Chi Minh Elevated Railway Project in Socialist Republic of Viet Nam SUMMARY March 2010 Japan Transportation Consultants,

More information

Socialist Republic of Viet Nam Ex-Post Evaluation of Technical Cooperation Project The Project for Building Disaster Resilient Societies in Central

Socialist Republic of Viet Nam Ex-Post Evaluation of Technical Cooperation Project The Project for Building Disaster Resilient Societies in Central Socialist Republic of Viet Nam Ex-Post Evaluation of Technical Cooperation Project The Project for Building Disaster Resilient Societies in Central Region in Vietnam External Evaluator: Kenichi Inazawa,

More information

Japanese ODA Loan. Ex-Ante evaluation

Japanese ODA Loan. Ex-Ante evaluation Japanese ODA Loan Ex-Ante evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Matarbari Ultra Super Critical Coal-Fired Power Project (I) Loan Agreement: June 16, 2014 Loan

More information

Feasibility Study on HCMC UMRT Line-2 (Ben Thanh An Suong Section) E&M System : Rolling Stock MARCH 2008 JAPAN RAILWAY TECHNICAL SERVICE (JARTS)

Feasibility Study on HCMC UMRT Line-2 (Ben Thanh An Suong Section) E&M System : Rolling Stock MARCH 2008 JAPAN RAILWAY TECHNICAL SERVICE (JARTS) Line2 (Ben Thanh An Suong Section) Feasibility Study on HCMC UMRT Line2 (Ben Thanh An Suong Section) E&M System : Rolling Stock Tsukuba Express (Japan) Odakyu Line (Tokyo, Japan) MARCH 2008 JAPAN RAILWAY

More information

PLAN FOR IMPLEMENTATION OF THE PARIS AGREEMENT OF HAIPHONG CITY

PLAN FOR IMPLEMENTATION OF THE PARIS AGREEMENT OF HAIPHONG CITY PLAN FOR IMPLEMENTATION OF THE PARIS AGREEMENT OF HAIPHONG CITY Vu Thi Thu Huong - Haiphong Department of Nature and Resource Environment (DONRE), Vietnam Bangkok 1-3, November 2017 1 HAI PHONG CITY The

More information

Summary of Terminal Evaluation

Summary of Terminal Evaluation Summary of Terminal Evaluation 1.Outline of the Project Country: Socialist Republic of Vietnam Project title:the Project for Strengthening the Traffic Police Training in People s Police Academy and Various

More information

Study on Economic Partnership Projects. in Developing Countries in FY2007. Socialist Republic of Vietnam. ( Project Operation Approach )

Study on Economic Partnership Projects. in Developing Countries in FY2007. Socialist Republic of Vietnam. ( Project Operation Approach ) Study on Economic Partnership Projects in Developing Countries in FY2007 Study on Da Nang-Quang Ngai Expressway Project in the Socialist Republic of Vietnam ( Project Operation Approach ) SUMMARY March

More information

Project for Enhancing Functions of Agricultural Cooperatives

Project for Enhancing Functions of Agricultural Cooperatives Socialist Republic of Viet Nam Ex-Post Evaluation of Japanese Technical Cooperation Project Project for Enhancing Functions of Agricultural Cooperatives External Evaluator: Tomoo Mochida, OPMAC Corporation

More information

ABRAHAM LINCOLN BRIDGE

ABRAHAM LINCOLN BRIDGE ABRAHAM LINCOLN BRIDGE PROJECT LOCATION: CONNECTING LOUISVILLE, KY WITH JEFFERSON, IN ACROSS THE OHIO RIVER. CATEGORY B: TRANSPORTATION PROJECT OWNER: KENTUCKY TRANSPORTATION CABINET COWI North America

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Madhya Pradesh Transmission System Modernisation Project Loan Agreement: June 16, 2011 Loan Amount:

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Democratic Socialist Republic of Sri Lanka Project: Landslide Disaster Protection Project of the National

More information

This project will support the development of a sewerage service targeting districts not

This project will support the development of a sewerage service targeting districts not Ex-Ante Evaluation 1. Name of Project Country: The Republic of Indonesia Project: Denpasar Sewerage Development Project (II) Loan Agreement: March 28, 2008 Loan Amount: 6,004 million yen Borrower: The

More information

Thailand Dao Kanong - Klong Toey Port Expressway Project (Stage I) (Construction of bridge section of the Chao Phya River Crossing)

Thailand Dao Kanong - Klong Toey Port Expressway Project (Stage I) (Construction of bridge section of the Chao Phya River Crossing) Thailand Dao Kanong - Klong Toey Port Expressway Project (Stage I) (Construction of bridge section of the Chao Phya River Crossing) 1. Project Profile and Japan s ODA loan Report Date: October 2002 Field

More information

Ex-ante Evaluation. Indonesia have one of the important strategic programs of increasing stable water supply and

Ex-ante Evaluation. Indonesia have one of the important strategic programs of increasing stable water supply and Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Integrated Water Resources and Flood Management Project for Semarang (Loan Agreement: March 29, 2006; Loan Amount:

More information

MOIT FiT Circular No. 02 Decision No. 39

MOIT FiT Circular No. 02 Decision No. 39 Renewable Energy Vietnam Client Alert January 2019 For further information, please contact: Fred Burke +84 28 3520 2628 frederick.burke@bakermckenzie.com Dang Chi Lieu +84 24 3936 9341 chilieu.dang@bakermckenzie.com

More information

Japanese ODA Loan. Ex-Ante Evaluation

Japanese ODA Loan. Ex-Ante Evaluation Japanese ODA Loan Ex-Ante Evaluation 1. Name of the Project Country: People s Republic of Bangladesh Project: Dhaka-Chittagong Main Power Grid Strengthening Project Loan Agreement: December 13, 2015 Loan

More information

A connection icon: Cao Lanh bridge. Mr. Phan Duy Lai Deputy General Manager Cuu Long CIPM

A connection icon: Cao Lanh bridge. Mr. Phan Duy Lai Deputy General Manager Cuu Long CIPM 1 2 A connection icon: Cao Lanh bridge Mr. Phan Duy Lai Deputy General Manager Cuu Long CIPM THE ICONIC CONNECTION PROJECT: CAO LANH BRIDGE 4 CONTENT 1. INTRODUCTION 2. PREPARATION OF THE PROJECT THE FIRST

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) 1. Basic Information Ex-Ante Evaluation (for Japanese ODA Loan) South Asia Division 1, South Asia Department, JICA Country: India Project Name: Project for the Construction of Turga Pumped Storage (I)

More information

1.4 Borrower/Executing Agency The Government of the Republic of the Philippines / The Department of Public Works and Highways (DPWH).

1.4 Borrower/Executing Agency The Government of the Republic of the Philippines / The Department of Public Works and Highways (DPWH). Philippines Second Mandaue Mactan Bridge Construction Project Report Date September, 2002 Field Survey June, 2001 1. Project Profile and Japan s ODA Loan Project Location Map Second Mandaue-Mactan Bridge

More information

PORT AND LOGISTICS INFRASTRUCTURE IN VIETNAM, OPPORTUNITES FOR COOPERATIVE DEVELOPMENT. MSc. NGUYEN XUAN TINH Busan, Oct 2018

PORT AND LOGISTICS INFRASTRUCTURE IN VIETNAM, OPPORTUNITES FOR COOPERATIVE DEVELOPMENT. MSc. NGUYEN XUAN TINH Busan, Oct 2018 PORT AND LOGISTICS INFRASTRUCTURE IN VIETNAM, OPPORTUNITES FOR COOPERATIVE DEVELOPMENT MSc. NGUYEN XUAN TINH Busan, Oct 2018 Vietnam IMO s member state Area: 331.699 km² EEZ: 1million km² Population: 96,566,780

More information

Cao trình đập bê tông trọng lực vị trí I

Cao trình đập bê tông trọng lực vị trí I F-31 Hình S4.3 Cao trình đập bê tông trọng lực vị trí I F-32 Hình S4.4 Mặt cắt điển hình đập bê tông trọng lực vị trí I F-33 Hình S4.5 Bố trí khoan phụt đập bê tông trọng lực vị trí I Description Quantity

More information

Japanese ODA Loan. Ex-ante Evaluation

Japanese ODA Loan. Ex-ante Evaluation Japanese ODA Loan Ex-ante Evaluation 1.Name of the Project Country:Republic of the Philippines Project:New Bohol Airport Construction and Sustainable Environment Protection Project Loan Agreement:27 March

More information