1 Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Presented by: Robyn Minter Smyers Alan S. Ritchie Heather A. Bartzi Erin Luke

2 Presentation Team Robyn Minter Smyers Partner, Thompson Hine Alan Ritchie Partner, Thompson Hine Heather Bartzi Partner, Thompson Hine Erin Luke Senior Associate, Thompson Hine

3 Beginning of Design and Construction Project Ideal Process Plenty of Time Ample Budget Project Goals Clearly Identified Competitive Selection of Designer and Constructor Abundant Information 3

4 But, IRL Starting Tomorrow Way Over Budget Unresponsive Proposals Scope of Project is a Moving Target Result: Do what you did for the last project with the same design and construction team. 4

5 What Happens? Late Completion Over-Budget Bad Fit, No Cooperation Among Team Disappointment Unhappy Stakeholders Basically 5

6

7 The Fix Effectively Plan the Project Early Align Goals and Address Project Risks and Challenges Select Appropriate Project Delivery Method Use Good RFP/RFQ for Selection of Designers and Constructors 7

8 Best Practices of Construction Projects: Front End Planning and Process We will discuss in this seminar: Review and prioritize critical project parameters Identify constraints that limit possible delivery options Review project delivery methodologies Compare options based upon stakeholder priorities Identify special tools to enhance project delivery success 8

9 Address Key Questions What are the critical project parameters? Absolute constraints that limit options? What is owner s need for control vs. shifting risk to designer and/or constructor? Type of project? (e.g., manufacturing, office building, infrastructure) Other concerns? (e.g., real estate, environmental, health & safety) 9

10 Roles & Responsibilities Of Stakeholders Management Profile: In-House Expertise & Resources Approach to Design Management Tolerance for Risk Relationship Network 10

11 Project Management The Problem Project delivery system often selected without objective analysis The way we always do it What the Architect/Engineer wanted The form the lawyer used LET S DO WHAT S NEW AND EXCITING!!! and not tailored to solve project specific issues. Can lead to project failure time, scope and cost 11

12 What is Project Delivery? Business and legal structure that identifies and aligns: Project Goals Project Requirements Project Processes Legal Structures Risk Mitigation 12

13 Legal Structure Quality Budget Changes Safety Process and Risk Management Schedule Aesthetics

14 Acceleration of Detail/Decisions into Design 14

15 Project Delivery Methodologies Multiple Prime Contracting Design-Bid-Build (General Contractor) Construction Management As Advisor Not utilized often At-Risk (As Constructor) Design-Build Bridging Design-Build Integrated Project Delivery 15

16 Design/Bid/Build (General Contractor) Approach A/E Owner Consultant Consultant Consultant P R I C E General Contractor Design Construction SUB SUB SUB 16

17 Construction Manager at Risk Approach A/E Owner Construction Manager Consultant Consultant Consultant P R I C E Design + Precon Construction SUB SUB SUB 17

18 Bridging Design/Build Approach Criteria A/E Owner Consultant Consultant Consultant Design/ Builder A/E SUB SUB SUB Consultant Consultant Consultant 18

19 Project Compensation Models Lump Sum, Stipulated Price Cost of the Work No GMP Cost of the Work with GMP Target Price 19

20 Basis of Design and Pricing Owner s Basis of Design Performance Requirements Design- Build Schematic or Design Development Documents Bridging Design- Build 35% to 95% Construction Documents Risk Complete Construction Documents General Contractor (D-B-B) 20

21 Lump Sum vs. GMP Approach Lump Sum Contract GMP Contract GMP Contingency Final Savings Lump Sum Cost of the Work Cost of the Work GCs Fee GCs Fee 21

22 Lump Sum vs. GMP Approach Lump Sum Contract GMP GMP Contract Contingency Final Loss Cost Cost of the Lump Sum of the Work Work GCs GCs Fee Fee 22

23 Target Pricing 23

24 Selection of Design and Construction Team Identify Goals Uses & Needs Budget & Contingency Schedule & Milestones What s Important What s Unique Set Team Facilities Finance Management Legal EHS Owner s Rep 24

25 Good Paperwork RFQ / RFP Uniform Requests = Uniform Submissions 25

26 Required Submissions Firm Profile Project Experience Insurance and Bonding Current Workload Litigation History Key Personnel / Staffing Financial Strength Agreement Comments References Pricing Proposal Approach / Method Value Add Ideas 26

27 Due Diligence Review Preliminary Research Firm Interviews Contact References Assemble Information Discuss and Evaluate Teamwork v. Price 27

28 Project Partnering Communication Protocols ID Key Stakeholders Address Concerns Collaboration Team Work Project Success! 28

29 Tools to Enhance Project Success Project Sponsorship/ Resources Project Delivery Facilitated GMP Process Contingency Management Insurance Review Dispute Resolution Issues 29

30

31 Yippee- Kai-Yay!

32 Questions? Robyn Minter Smyers Partner, Thompson Hine Alan Ritchie Partner, Thompson Hine Heather Bartzi Partner, Thompson Hine Erin Luke Senior Associate, Thompson Hine

33 This presentation may be reproduced, in whole or in part, with the prior permission of Thompson Hine LLP and acknowledgement of its source and copyright. This publication is intended to inform clients about legal matters of current interest. It is not intended as legal advice. Readers should not act upon the information contained in it without professional counsel. This document may be considered attorney advertising in some jurisdictions THOMPSON HINE LLP. ALL RIGHTS RESERVED. 33

AIA Contract Documents

AIA Contract Documents AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

2017 National Council of Architectural Registration Boards (NCARB) This document, effective August 2017, supersedes all previous editions of the ARE

2017 National Council of Architectural Registration Boards (NCARB) This document, effective August 2017, supersedes all previous editions of the ARE ARE 5.0 Handbook 2017 National Council of Architectural Registration Boards (NCARB) This document, effective August 2017, supersedes all previous editions of the Handbook. Please check NCARB s website,

More information

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K CONTRACTS CATALOG Updated Docs Inside ou Ah ead o f the Cur v e gy epin e K ... BUILDING A BETTER WAY! Whether working at the office, from the road or even at home, the platform provides instant access

More information

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits

More information

UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNIVERSITY OF CALIFORNIA, SAN DIEGO BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSOCIATE VICE CHANCELLOR CAPITAL PROGRAM MANAGEMENT TEL: (858) 534-2177 FAX: (858) 534-4363

More information

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services B-Series B- S E R I E S The documents in the B Series relate to various forms of agreement between an owner and an architect for professional services. B141 Standard Form of Agreement Between Owner and

More information

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective CMAA National Conference October 13, 2008 Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective Date Presenters Howard W. Ashcraft,

More information

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES Pueblo Urban Renewal Authority (PURA) Pueblo Convention Center Expansion &

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Working Effectively with Outside Counsel Checklist

Working Effectively with Outside Counsel Checklist View the online version at http://us.practicallaw.com/7-617-8668 Working Effectively with Outside Counsel Checklist PRACTICAL LAW This Checklist provides in-house counsel with general guidance on working

More information

Strategic Management and Project Selection

Strategic Management and Project Selection Strategic Management and Project Selection Strategic Management and Project Selection Maturity of Project Management Overview Criteria for PS Models Nature of PS Models Types of PS Models Uncertainty Analysis

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

PLI s 8th Annual Patent Law Institute

PLI s 8th Annual Patent Law Institute PLI s 8th Annual Patent Law Institute Managing Patent Litigation Michelle Waites Senior Patent Counsel Xerox Corporation Focus on Efficiency Focus on Controlling Costs At the Start of the Case Thorough

More information

Employment & Labour Law Practice

Employment & Labour Law Practice Employment & Labour Law Practice Experts in Employment Law ABSOLUTE SPECIALIZATION DEFINITIVE ADVICE POWERFUL LITIGATION Our Employment & Labour Law Practice has in-depth, genuine and proven expertise

More information

2016 Architecture & Engineering

2016 Architecture & Engineering 2016 Architecture & Engineering Market Outlook Survey The results are in... 1 Grassi & Co. and Zetlin & De Chiara LLP are pleased to announce the release of our 2016 Architecture & Engineering (A&E) Industry

More information

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together The New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together This document printed Friday, 04/15/2016 Contracting Opportunity Title:

More information

FMD Project File Management Procedures

FMD Project File Management Procedures Issued: November 10, 2014 Revised: April 9, 2015 GUIDELINE: Applies to: All Planning, Project Management and Business Office Employees of the Facilities Management Department (FMD) PURPOSE: To establish

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

Helpful Hints for Creating Requests for Proposals:

Helpful Hints for Creating Requests for Proposals: Helpful Hints for Creating Requests for Proposals: Troy W. Miller, AIA, REFP Education Focus Leader Troy.Miller@LHBcorp.com Direct: 612.766.2819 Cell: 952.448.3357 Agenda 1. The Typical Request for Proposal

More information

Tips For Managing The In-House And Outside Counsel Relationship. By David F. Johnson

Tips For Managing The In-House And Outside Counsel Relationship. By David F. Johnson Tips For Managing The In-House And Outside Counsel Relationship By David F. Johnson Introduction Corporate counsel owe duties to their clients to retain effective and cost-appropriate outside counsel.

More information

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE Risks Associated with Alternative Delivery Methods Managing Expectations Presented by Dan Becker, CCM, PMP, CCE 1 3 Primary Methods for Delivering Projects in WA and OR Design/Bid/Build Design/Build CM

More information

Trinity Well Field and Production Facilities Project Management Using CMAR

Trinity Well Field and Production Facilities Project Management Using CMAR Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,

More information

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013 FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS June 1, 2013 For general guidance the following information is provided as an aid to those preparing submittals in response to Design-Build solicitations.

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

1/4/2014. Alternative Project Delivery Methods 1. Agenda

1/4/2014. Alternative Project Delivery Methods 1. Agenda Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia

More information

Energy Trading Risk Management (ETRM) System Selection and Implementation Top Challenges

Energy Trading Risk Management (ETRM) System Selection and Implementation Top Challenges Energy Trading Risk Management (ETRM) System Selection and Implementation Top Challenges May 27, 2014 Energy Trading Risk Management Challenges Agenda Agenda Speaker Introduction Overview of Energy Trading

More information

Two Parts of our Discussion

Two Parts of our Discussion Two Parts of our Discussion Part One: The basics (what, why, how, when, etc) An overview of process By no means comprehensive (not enough time) Part Two: From the trenches stuff Not contained in statute

More information

Mentoring Plan Template In-House Lawyers

Mentoring Plan Template In-House Lawyers Mentoring Plan Template In-House Lawyers NOTE: If you wish to delete activities or to add activities not listed, simply confirm with CAMP or with your Sponsoring Program facilitator, especially if you

More information

FEMA PA Match Training

FEMA PA Match Training FEMA PA Match Training PROCUREMENT REQUIREMENTS USING CDBG-DR FUNDS Regulatory/Statutory Citations Selection Procedures - (2 CFR 200.319) Conflict of Interest - (2 CFR 200.318) Contract Administration

More information

Owner s Representative SCOPE OF SERVICES

Owner s Representative SCOPE OF SERVICES Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,

More information

PRIVACY 101 SETTING UP THE FUNCTION

PRIVACY 101 SETTING UP THE FUNCTION PRIVACY 101 SETTING UP THE FUNCTION Evie Kyriakides, Mars, Incorporated Heather Egan Sussman, McDermott Will & Emery LLP Mac Macmillan, Hogan Lovells International LLP March 5, 2014 INTRODUCTION Making

More information

construction solutions asia pacific

construction solutions asia pacific construction solutions asia pacific The outlook of the construction industry within the Asia Pacific region remains strong, however pressures to successfully deliver projects against a backdrop of finite

More information

Progressive Design-Build

Progressive Design-Build Progressive Design-Build Progressive Design-Build Design-Build Procured with a Progressive Design & Price A Design-Build Done RightTM Primer 1 Design-Build Progressive Design-build Design-Build Procured

More information

Metropolitan Washington Airports Authority. Request for Qualifications Information (RFQI) RFQI No C084. for

Metropolitan Washington Airports Authority. Request for Qualifications Information (RFQI) RFQI No C084. for Request for Qualifications Information (RFQI) RFQI No. for Project Controls Task Contract for Project Support & Management at Washington Dulles International Airport and Ronald Reagan Washington National

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.

More information

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Job Description: Solicitor

Job Description: Solicitor Job Description: Solicitor Reporting to: Location: Responsible for: Head of Team Cambridge No direct reports Special Requirements: This post is office based but will involve out of office activity and

More information

FACILITIES CONFERENCE

FACILITIES CONFERENCE FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity

More information

1913 Lausanne, Switzerland

1913 Lausanne, Switzerland FIDIC What is FIDIC? An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the

More information

Legal Project Management (LPM)

Legal Project Management (LPM) Legal Project Management (LPM) NGB Extra session 9 February 2017 Agenda Introduction LPM 15.45 16.30 Examples / common pitfalls 16.30 16.45 Break 16.45 17.00 Planning exercise and group discussion 17.00

More information

Council Agenda Report

Council Agenda Report Agenda Item #7 Council Agenda Report SUBJECT: REVIEW, DISCUSS AND PROVIDE STAFF WITH DATES TO SCORE PROPOSALS AND INTERVIEW ATTORNEY FIRMS MEETING DATE: December 16, 2010 RECOMMENDATION Staff recommends

More information

POSITION NUMBER: LOCATION: Vancouver. DATE: January 2013

POSITION NUMBER: LOCATION: Vancouver. DATE: January 2013 POSITION TITLE: Human Resources Consultant REGION: CLBC Headquarters CURRENT CLASSIFICATION LEVEL: Management SUPERVISOR POSITION NUMBER: POSITION NUMBER: LOCATION: Vancouver DATE: January 2013 SUPERVISOR

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

Middle East Delivering Expertise Since 1978

Middle East Delivering Expertise Since 1978 Middle East Delivering Expertise Since 1978 Global Construction Consultancy ABOUT US We have excelled at providing construction and engineering focused services since 1978. Our Project Management, Programming,

More information

PORTFOLIO OF SERVICES

PORTFOLIO OF SERVICES Supporting gender equality in business leadership by providing startups that have women founders or women senior executives with greater access to the legal services and the networks needed to launch,

More information

MT. PLEASANT, MICHIGAN

MT. PLEASANT, MICHIGAN THE CITY OF MT. PLEASANT, MICHIGAN CITY HALL 320 W. Broadway St. 48858-2312 (989) 779-5300 (989) 773-4691 fax PUBLIC SAFETY 804 E. High 48858-3595 (989) 779-5100 (989) 773-4020 fax PUBLIC WORKS 1303 N.

More information

Request for Proposal For: 2018 American Bar Association Temporary Services

Request for Proposal For: 2018 American Bar Association Temporary Services Table of Contents Bid Timetable [2] 1.0 General Bid Information [3] 2.0 Proposal Requirements [5] 3.0 Criteria for Selection [7] 4.0 Specifications and Work Statement [7] Appendix A: Bidder Response Sheet

More information

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK THE KEY ELEMENTS OF QUANTITY SURVEYING WORK A Presentation to the Institution of Surveyors of Uganda by Tom Joseph Mukasa BSc, MSc, MRICS, ICIOB, AISU 2016 1. The following are key elements (divided into

More information

REQUEST FOR PROPOSAL (RFP) LEGAL SERVICES. Submission Date: November 28, :00 p.m.

REQUEST FOR PROPOSAL (RFP) LEGAL SERVICES. Submission Date: November 28, :00 p.m. COLTS NECK TOWNSHIP BOARD OF EDUCATION 70 CONOVER ROAD, COLTS NECK, NJ 07722 REQUEST FOR PROPOSAL (RFP) LEGAL SERVICES Submission Date: November 28, 2017 4:00 p.m. The Colts Neck Township School District

More information

Veterinarians Rely on Pacific Continental Bank

Veterinarians Rely on Pacific Continental Bank Veterinarians Rely on Pacific Continental Bank Just as veterinarians are committed to their patients welfare, Pacific Continental is committed to the financial health of veterinary clinics. We understand

More information

A DESIGN-BUILDER'S LOOK AT THE NEW AIA DESIGN-BUILD FAMILY OF DOCUMENTS

A DESIGN-BUILDER'S LOOK AT THE NEW AIA DESIGN-BUILD FAMILY OF DOCUMENTS American Bar Association Forum on the Construction Industry A DESIGN-BUILDER'S LOOK AT THE NEW AIA DESIGN-BUILD FAMILY OF DOCUMENTS Matthew A. Gillies Stites & Harbison, PLLC 400 West Market Street, Suite

More information

jackson lewis Preventive Strategies and Positive Solutions for the Workplace Corporate Diversity Counseling ALL WE DO IS WORK

jackson lewis Preventive Strategies and Positive Solutions for the Workplace Corporate Diversity Counseling ALL WE DO IS WORK Corporate Diversity Counseling jackson lewis Preventive Strategies and Positive Solutions for the Workplace ALL WE DO IS WORK Attorneys in our Corporate Diversity Counseling practice bring to bear over

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies CM CORE 1 Cost Engineering Commercial Management Core Competency Cost Engineering Specialism COMPETENCIES AND ASSESSMENT Financial and commercial processes in civil engineering January 2015 Technical Member

More information

Expression of Interest Guidelines. February Financial Services Page 1 of 8

Expression of Interest Guidelines. February Financial Services Page 1 of 8 February 2012 Financial Services Page 1 of 8 Financial Services EXPRESSION OF INTEREST GUIDELINES Responsible Position: Manager, Financial Operations Approved by: Chief Financial Officer Table of Contents

More information

Integrated Project Delivery

Integrated Project Delivery 2014 HDR Architecture, 2014 HDR, Inc., all all rights reserved. Integrated Project Delivery It s A New World, And How It Can Benefit Municipal Owners Rich Atoulikian, PMP, PE Rich.Atoulikian@hdrinc.com

More information

PROJECT PROCUREMENT MANAGEMENT. 1 Powered by POeT Solvers Limited

PROJECT PROCUREMENT MANAGEMENT. 1  Powered by POeT Solvers Limited PROJECT PROCUREMENT MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited CONDUCT PROCUREMENT PROCESSES BY PROCESS GROUP Planning Executing Monitoring and controlling Closing 12.1 12.2 12.3 12.4

More information

Welcome. Bill Gibson, President COLPM

Welcome. Bill Gibson, President COLPM Welcome Bill Gibson, President COLPM Welcome Ron Staudt, Chicago-Kent College of Law Scholarship Center for Access to Justice & Technology Center for Information, Society and Policy Center for Open Government

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS DEPARTMENT SUITE 209S - LOGAN OFFICE CENTER ONE HARBORSIDE DRIVE EAST BOSTON, MASSACHUSETTS 02128-2909 REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL DATE: February 24, 2015 Shimizu North America LLC 909 3rd Avenue, 28th Floor New York, NY 10022 RFP Queries (646) 205-4722 Fax (212) 223-1930 PROJECT: The Japan Foundation New York

More information

ARCHITECTURAL / ENGINEERING SERVICES RFQ. North Sound Behavioral Health Organization

ARCHITECTURAL / ENGINEERING SERVICES RFQ. North Sound Behavioral Health Organization ARCHITECTURAL / ENGINEERING SERVICES RFQ North Sound Behavioral Health Organization ARCHITECTURAL/ENGINEERING RFQ TABLE OF CONTENTS SECTION 1.0 PROJECT DESCRIPTION... 3 Background Owner & Team Members

More information

Continuing Education Credits

Continuing Education Credits Recent Developments in (IPD) for NECA Members October 14, 2013 9:00-9:50 AM Following this session, you will be able to: Explain the concept and structure of an IPD project. Identify the issues and risks

More information

Careers List Professional Careers in Construction

Careers List Professional Careers in Construction Careers List Professional Careers in Construction Architect Designs buildings, including the preparation of detailed construction drawings and specifications, and advises on their construction. May specialize

More information

Client Focused Results Driven

Client Focused Results Driven Client Focused Results Driven Accountants & consultants YOU CAN TRUST. ACM offers you a World Class Experience through our highly skilled team of passionate professionals, unique delivery model and global

More information

Coordination of Consultants

Coordination of Consultants Coordination of Consultants Ontario Association of Architects Practice Tip PT.27 Version 1.0 May 21, 2012 2012 OAA, all rights reserved. Persons who are not members of the OAA must obtain written permission

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320 REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE 2015 2016 ROOF AND HVAC REPLACEMENT PROJECT PW1320 Issued by: City of Stockton Public Works Department 22 E. Weber Avenue, Room 301 Stockton, CA 95202

More information

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

More information

DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) AGREEMENT (STATE FORM SC-9.0)

DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) AGREEMENT (STATE FORM SC-9.0) STATE OF COLORADO OFFICE OF THE STATE ARCHITECT STATE BUILDINGS PROGRAMS DESIGN/BUILD GUARANTEED MAIMUM PRICE (GMP) AGREEMENT (STATE FORM ) CONTRACT ID NUMBER: AGENCY IDENTIFICATION NUMBER: 2007-133P14-02

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response

More information

Commonwealth of Virginia

Commonwealth of Virginia Commonwealth of Virginia Alternative Project Delivery Division April 2017 Virginia Department of Transportation TABLE OF CONTENTS INTRODUCTION... 2 1.0 DEFINITIONS... 3 2.0 PRELIMINARY PROJECT SELECTION...

More information

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005 CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS August 2005 Projects Requiring Licensed Architect / Engineer: *Project Cost Threshold New Construction or Additions $135,000 + Major Repairs

More information

Fairfax County Government Construction Management At Risk (CMAR)

Fairfax County Government Construction Management At Risk (CMAR) Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of

More information

Connecting Clients With Solutions. Navigant Consulting 2005 Annual Report

Connecting Clients With Solutions. Navigant Consulting 2005 Annual Report Connecting Clients With Solutions Navigant Consulting 2005 Annual Report Navigant Consulting Financial Highlights Navigant Consulting is an international Results of Operations 2003 2004 2005 consulting

More information

Request for Qualifications (RFQ) #HM-R6-RFQ1 2018/2019 Highway Maintenance Agreements Prequalification RESPONSES TO RESPONDENT QUESTIONS SUMMARY #1

Request for Qualifications (RFQ) #HM-R6-RFQ1 2018/2019 Highway Maintenance Agreements Prequalification RESPONSES TO RESPONDENT QUESTIONS SUMMARY #1 RESPONSES TO RESPONDENT QUESTIONS SUMMARY #1 NOMINATED WORK EXAMPLES Question 1.01: When providing Nominated Work Examples, is it permitted for the Respondent Team to use Nominated Work Examples specific

More information

(pronounced krice'-son) (origin Ancient Greek κρείσσων, ον) (noun) stronger, i.e. greater advantage: better

(pronounced krice'-son) (origin Ancient Greek κρείσσων, ον) (noun) stronger, i.e. greater advantage: better (pronounced krice'-son) (origin Ancient Greek κρείσσων, ον) (noun) stronger, i.e. greater advantage: better ABOUT US Kreisson is a construction, engineering and property law firm based in Sydney. We act

More information

Invitation to Tender. External Audit Services. July 2015

Invitation to Tender. External Audit Services. July 2015 External Audit Services July Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 4 1.5. Copyright...

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

Metrics that Matter: A Law Firm Management Workshop

Metrics that Matter: A Law Firm Management Workshop Metrics that Matter: A Law Firm Management Workshop Dr. Evan Parker, LawyerMetrix Steven R. Petrie, Faegre Baker Daniels Jill S. Weber, Stinson Leonard Street Agenda Case Study Overview (15 minutes) Small

More information

Extended Enterprise Risk Management

Extended Enterprise Risk Management Extended Enterprise Risk Management Driving performance through the extended enterprise October 2015 A network within a network The Extended Enterprise is the concept that an organization does not operate

More information

Vendor Selection: Identifying Effective Procedures & Strategies

Vendor Selection: Identifying Effective Procedures & Strategies Outsourcing Clinical Trials Canada 15 th November 2012 Vendor Selection: Identifying Effective Procedures & Strategies John S Andrews PhD President and CSO, NeurAxon Inc President, Ketogen Inc CSO, Talon

More information

SchulteRieSenkampff.

SchulteRieSenkampff. SchulteRiesenkampff. Company Profile Legal expertise, sector specific know-how and business savvy to meet your business objectives. Interlinked thinking, cooperation with different teams and personal advice,

More information

GETTING THE CLIENT RELATIONSHIP REVIEW MEETING RIGHT

GETTING THE CLIENT RELATIONSHIP REVIEW MEETING RIGHT GETTING THE CLIENT RELATIONSHIP REVIEW MEETING RIGHT We are often asked by clients how they can conduct effective client relationship review meetings. Getting this right is very important the feedback

More information

Presentation for the New York State Bar Association. Keith Emmer Startegix LLC

Presentation for the New York State Bar Association. Keith Emmer Startegix LLC Presentation for the New York State Bar Association Keith Emmer Startegix LLC 212.920.9205 keith@startegix.com Lawyers and Public Relations Lawyers are a Great Fit for PR! U.S. Media Consumption How much

More information

Developing a Proper Franchise Program

Developing a Proper Franchise Program AUTHOR: Michael H. Seid, Managing Director Developing a Proper Franchise Program Franchising represents an attractive means for many manufacturers, retailers, and service providers to expand their businesses.

More information

Project Delivery Method Selection Workshop

Project Delivery Method Selection Workshop 3 rd Avenue Bridge Rehabilitation, Minneapolis Project Delivery Method Selection Workshop Project Name: SP Project Workshop Date: 5/2/2017 Workshop Location: Water s Edge Room C Facilitator: Kevin Hagness

More information

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM Contracting for Architectural and Engineering (A/E) Services Webinar August 30, 2011 10 AM to 11:30 AM 1 Where We're Going Today Webinar Operation - Fred Ward 5 minutes (+/-) Topic Introduction - John

More information

Tips for Hiring a Consultant. Why hire a consultant

Tips for Hiring a Consultant. Why hire a consultant Tips for Hiring a Consultant Why hire a consultant When your organization is faced with problems that won't go away, a consultant may be your answer. In the long run, you can save time and money by funding

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL COLORADO HOUSING AND FINANCE AUTHORITY REQUEST FOR PROPOSAL (RFP) COLORADO HOUSING AND FINANCE AUTHORITY 1981 BLAKE STREET DENVER, CO 80202 REQUEST FOR PROPOSAL Technology Assessment POSTED: 11/17/2017

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information