Underground Cable Installation Manual

Size: px
Start display at page:

Download "Underground Cable Installation Manual"

Transcription

1 Underground Cable Installation Manual

2

3 DOCUMENT CONTROL Document Owner (May also be the Process Owner) Approved By * Authorisation ** Process Owner is hereby vested with authority and responsibility to manage the process end to end. Name: Mark Van Vuuren Position: Field Practices Coordinator Date: March 2013 Name: Mark Van Vuuren Position: Field Practices Coordinator Date: March 2013 Name: Lance Roberts Position: Manager Safety and Health Date: March 2013 Date Created/Last Updated April 2015 Review Frequency *** Every 3 years Next Review Date *** October 2018 * Must be the Process Owner and is the person assigned authority and responsibility for managing the whole process, endto-end, which may extend across more than one division and/or functions, in order to deliver agreed business results. ** This person will have the power to grant the process owner the authority and responsibility to manage the process from end to end. *** Frequency period is dependent upon circumstances maximum is 5 years from last issue, review, or revision whichever is the latest. If left blank, the default will be 1 year unless otherwise specified. STAKEHOLDERS The following positions must be consulted if an update or review is required: Work Delivery Coordinators Network Asset Management Coordinators NOTIFICATION LIST The following positions must be notified of any authorised change: Regional Managers Manager Asset & Works Engineering & Projects

4 Important Notice to Users This Underground Cable Installation manual has been developed for use by Horizon Power employees and Contractors, engaged to perform construction and maintenance work on Horizon Powers underground electrical distribution networks. This manual has been developed to provide guidelines for a minimum acceptable standard of underground construction that is required by Horizon Power. To this end, this manual provides the framework by which auditing of the underground electricity distribution network may be undertaken. It is issued by as a controlled document by Horizon Power to Horizon Power employees and Contractors on the condition that it will only be used whilst undertaking Underground Cable Installation work on Horizon Power underground electrical distribution networks. Underground Cable Installation work will only be performed by individuals who are appropriately trained and qualified in accordance with accepted standards within Horizon Power. This Manual is not intended, and should not in any way be relied upon, as a substitute for such training. Copyright 2012 Copyright is owned by Horizon Power. Horizon Power (ACN ). All rights reserved. No part of this work may be reproduced or copied in any form or by any means (graphic, electronic, taping or information retrieval system) without the written permission of the copyright owner.

5 Table of Contents Page i Table of Contents Section Page Number 1 PURPOSE APPLICATION DEFINITIONS AND REFERENCES Definitions References GENERAL REQUIREMENTS Training and Authorisation Job Planning and Risk Assessments (Work Planning) Personal Protective Equipment (PPE) Contractor Responsibilities Traffic Management Instructions, Procedures and Standards SURVEYING AND AS CONSTRUCTED RECORDS Survey Benchmarks and Datum Points As Constructed Records CROSSINGS Railway Crossings Planning Requirements Installation of Cables and Conduits Installation of Cable Location Markers Installation of Power Cables under tracks and elsewhere on railway property Existing Pipes or Cables Gas Mains Communications Existing Underground Electrical Cables Road and Vehicle Crossings Horizontal Cable Clearance to other Services at Road Crossings CABLE TUNNELS AND SUPPORT SYSTEMS General Access Pits Cable Support CABLE ON AND OFF NORMAL ALIGNMENT Standard Cable Alignment Alternative Cable Alignment Easements Retrospective Undergrounding

6 Table of Contents Page ii 9 TRENCHING AND EXCAVATION General Blasting Excavated Materials DIRECTIONAL DRILLING Installation Principles Drilling Drilling Fluids Management Plan PLOUGHING CABLE LAYING Drum Mounting and Inspection Inspection prior to installation: Preparation for installation Protection of Cables during Installation Cable Installation methods Stocking Pulling Installation using Pulling Eyes Bond Pulling Armour Pulling Mechanical Assisted Installation Cable Pulling Tensions Pulling Speed Cable Bending Radii Maximum Number of Cable Joints Installation of Cables on Poles Bedding and Backfill Depth of Cover for Cables Cable Protection Covers and Marker Tapes Sealing of Cables CONDUITS Application Requirements for cables installed outside normal alignments Encased Conduits Sealing of Conduits Installation requirements for Conduits Pulling Cables through Conduits CABLE JOINTING AND TERMINATIONS General Cable Joint Excavations Jointing Termite Proofing Terminations Working Ends TESTING AND COMMISSIONING

7 Table of Contents Page iii 16 REINSTATEMENT General Compaction Levelling Restoration of Surface DAMAGE TO PROPERTY General PILLARS AND PITS General APPENDIX A - SERVICE ALIGNMENT, DEPTH AND COLOURS FOR GREENFIELD SITES... 1 APPENDIX B CABLE INSTALLATION DATA... 3 APPENDIX C - DIAL BEFORE YOU DIG SERVICE... 4

8 Table of Contents Page iv This Page Not Used.

9 SECTION 1 Page PURPOSE This manual specifies the technical requirements for the safe and efficient installation of underground cables on Horizon Power s electrical distribution networks. This document refers to other Horizon Power documents to provide reference standards for underground cable installation work.

10 SECTION 1 Page 1-2 This Page Not Used.

11 SECTION 2 Page APPLICATION This manual has been developed for use by Horizon Power employees and Service Providers engaged in the installation of high and low voltage distribution cables on the Horizon Power electrical networks. Horizon Power employees and Service Providers shall comply with these requirements, except as otherwise approved. For subdivisional work managed by a developer where the subdivision does not require equipment to be installed on public land, some items in this document may not be applicable as they are specified in the Underground Distribution Scheme (UDS) Manual. Note: Public land is land that at the time of subdivision is freely available for public use, e.g., existing road reserves, Public Access Way (PAW), Public Open Space (POS) etc.

12 SECTION 2 Page 2-2 This Page Not Used.

13 SECTION 3 Page DEFINITIONS AND REFERENCES 3.1 Definitions Accredited Service Provider (ASP) Approved Authorised Person Cable Conductor Construction Project Manager (CPM) Earthed Energised High voltage Insulated Live Low voltage A person or an entity who has been accredited through the accreditation scheme of Horizon Power to undertake any construction work on Horizon Power underground network. Appropriate organisation endorsement in writing for a specific function. A person with technical knowledge or sufficient experience who has been approved or delegated authority to act on behalf of Horizon Power to perform the duty concerned. A single cable core, or two or more cable cores laid up together, either with or without fillings, reinforcements or protective coverings. A wire or other form of conducting material suitable for carrying current, but not including wire or other metallic parts directly employed in converting electrical energy into another form. The officer appointed by Horizon Power as Horizon Power s representative to whom all site contractual and technical matters are referred. Directly electrically connected to the general mass of earth so as to ensure and maintain the effective dissipation of electrical energy. Connected to a source of electrical supply. A nominal voltage exceeding 1,000 V ac or exceeding 1,500 V dc. Separated from adjacent conducting material by a nonconducting substance or airspace permanently providing resistance to the passage of current, or to disruptive discharges through or over the surface of the substance or space, to obviate danger of shock or injurious leakage of current. Energised or subject to hazardous induced or capacitive voltages. Nominal voltage exceeding 50 V ac or 120 V dc but not exceeding 1000 V ac or 1500 V dc.

14 SECTION 3 Page 3-2 Safe Safety Observer Shall Should Voltage HDPE HV LV MRWA PTA PAW POS UDS Manual WAGR WAPC XLPE Not posing an unacceptable risk to life, health or property. A person competent for the task and specifically assigned the duty of observing and warning against unsafe approach to electrical apparatus, or other unsafe conditions. A requirement is "mandatory. A requirement Is "advisory or discretionary. A potential difference between conductors or between conductors and earth. High Density Polyethylene High Voltage Low Voltage Main Roads Western Australia Public Transport Authority Public Access Way Public Open Space Underground Distribution Schemes Manual Western Australian Government Railway Western Australian Planning Commission Cross-linked Polyethylene

15 SECTION 3 Page References Requirements and Information relating to this Standard may be found within the source documents detailed below: Utility Providers Code of Practice, Main Roads WA; Restoration and Reinstatement Specification for Local Governments in Western Australia published by the Institute of Public Works Engineering Australia (available from Main Roads WA s web site); Horizon Power Field Practice Manual (FIM) Section 4, Underground Work Horizon Power Underground Distribution Schemes (UDS) Manual; Horizon Power Network Standard: Testing & Commissioning Technical Requirements; Dial Before You Dig Service for lodging an enquiry and requesting a plan; Traffic Management for Works on Roads - Code of Practice, Main Roads WA; Occupational Safety and Health Act 1984 and Occupational Safety and Health Regulations WorkSafe Code of Practice: Excavation Explosives and Dangerous Goods Act 1961 and Explosives and Dangerous Goods (Explosives) Regulations 1963; AS 1742 Manual of uniform traffic control devices, Australian Standards; AS/NZS 3000 Australian/New Zealand Wiring Rules; and AS Installation of underground utility services and pipelines within railway boundaries.

16 SECTION 3 Page 3-4 This Page Not Used.

17 SECTION 4 Page GENERAL REQUIREMENTS All Horizon Power underground cables shall be a termite protected type. Termite protection is critical to achieve 40+ year cable life, as Horizon Power cables are often installed in termite affected areas Cables are termite protected using the following means: a) inclusion of a termite protection in the outer sheath (Horizon Power method); b) double brass tapes; c) nylon sheaths The cable sheath MUST NOT be scratched during installation. Scratch damage to the outer sheath may allow termites mandibles (pincers) to bite into the cable outer sheath. 4.1 Training and Authorisation Underground Cable Installation work shall only be performed by individuals who are appropriately trained, qualified and authorised in accordance with accepted standards within Horizon Power. Service Providers are responsible for ensuring all its employees and Sub-Contractor employees have been authorised by Horizon Power. They must submit to Horizon Powers site representative confirmation of authorisation for each employee, prior to the commencement of the works. Note: This Manual is not intended, and should not in any way be relied upon, as a substitute for training. 4.2 Job Planning and Risk Assessments (Work Planning) Prior to the commencement of the work, an on-site job risk assessment must be undertaken by all Horizon Power and Service Provider team members in accordance with Horizon Powers Job Risk Assessment Process and Field Instruction FI 2.23 Job Hazard & Risk Assessment, to ensure all aspects of our work is carried out in a safe manner. The on-site job risk assessment shall include but not limited to: Identify and discuss the job hazards; Assess the risks that may result because of the hazard; Agree on the tasks assigned to control or remove the hazards & risks; and Implement the control measures

18 SECTION 4 Page Personal Protective Equipment (PPE) Horizon Power employees and Contractors engaged in the installation of high and low voltage distribution cables on the Horizon Power electrical networks shall wear the Personal Protective Equipment (PPE) as required in accordance with Horizon Power s Field Instruction Manual : FI 2.1 Glove Protection FI 2.2 Head Protection FI 2.5 Other Personal Protective Equipment FI 2.6 Worksite Clothing/Personal Protective Equipment 4.4 Contractor Responsibilities The Contractor is to provide competent, qualified and licensed Personnel to undertake Underground Cable Installation. All Contractor Personnel utilised to carry out work activities on or near Horizon Powers electrical networks must have Horizon Power authorisation prior to the commencement of the Services, refer to Field Instruction Manual: FI 1.2 Contractor Authorisation Process FI 1.3 Construction site access minimum requirements 4.5 Traffic Management Horizon Power employees and contractors shall ensure that where Services are sited adjacent to existing roads, adequate precautions are taken at all times to protect personnel, associated plant, and the general public. Horizon Power employees and contractors shall comply with the Main Roads Department Traffic Management for Road Works Code of Practice and Horizon Powers Field Instruction Manual: FI 2.15 Temporary Safety Barriers and/or Warning Signs FI 2.20 Traffic Management The Local Government Authority shall be notified of any occasion it may be necessary to obstruct a road or footpath to carry out the Services. The Contractor shall obtain the written consent of the Main Roads Department and the relevant local authority before creating such obstruction. All vehicles shall be fitted with suitable warning lights.

19 SECTION 4 Page Instructions, Procedures and Standards Horizon Power employees and contractors shall comply with Horizon Power instructions, procedures, standards and construction drawings when engaged in the installation of high and low voltage distribution cables on the Horizon Power electrical networks. This includes but not limited to the following Horizon Power documents: Horizon Power Field Instruction Manual (FIM) Horizon Power Safe Work Method Statements (SWMS) Field Operations Electrical Safety Standards (ESS) Fit for Work Policy Hazard Incident Reporting Notification and Investigation Procedure Excavation Work Near Horizon Powers Underground And Overhead Electrical Networks Underground Distribution Schemes (UDS) Manual. Underground Cable Installation Manual Testing & Commissioning Standard Substation Installation Manual Distribution Equipment Labelling Standard Construction Drawings

20 SECTION 4 Page 4-4 This Page Not Used.

21 SECTION 5 Page SURVEYING AND AS CONSTRUCTED RECORDS 5.1 Survey Benchmarks and Datum Points There may be official survey benchmarks installed in the project work area. Precautions shall be taken to avoid disturbing these markers. Should any markers be disturbed, all costs associated with restoring the benchmarks to their correct position shall be borne by those responsible for such disturbance. 5.2 As Constructed Records Upon completion of all work, the following As Constructed records shall be provided to the Horizon Powers Construction Project Manager (CPM): 1. Cable installation record. Where cables are installed using directional drilling, the length and depth of cables shall be recorded. 2. Electrical test schedules. 3. HV cable joint schedule. 4. Materials & equipment schedule. The As Constructed records shall meet the requirements of Section of the Underground Distribution Schemes Manual. Standard forms for Electrical Test Schedules, HV Cable Joint Schedules and Materials & Equipment Schedule are available for download from Horizon Power s web site.

22 SECTION 5 Page 5-2 This Page Not Used.

23 SECTION 6 Page CROSSINGS 6.1 Railway Crossings Planning Requirements Before commencing any works associated with railway property, it is essential that all necessary applications are made and approvals obtained. Details of the applications and approval process requirements are contained in the Utility Providers Code of Practice for Western Australia (Appendix D- Utilities Located in Rail Reserves). The approval process can take several months, so appropriate planning for the works is recommended. In most cases, arrangements will be required to use a railway flagman at the site for the duration of the works Installation of Cables and Conduits Where site conditions permit, the installation shall be by boring or directional drilling for the portion under the tracks and at least 3 m beyond the outer rails or 3 m beyond the toe of embankment, whichever is the further. In the case of boring, the diameter of the bored hole shall not exceed the outside diameter of the pipe/conduit by more than 50 mm. If the diameter of the bored hole exceeds the outside diameter of the pipe/conduit by 50 mm or the bored hole needs to be abandoned, the hole shall be backfilled and remedial measures shall be taken to provide support for the railway Installation of Cable Location Markers Cable marker details are available in Horizon Power s Distribution Design Catalogue (DDC) Section 7. Cable markers shall be installed to indicate the location of all underground power cables. 1. The markers shall be located above or adjacent to the buried cable: a) At points of entering and leaving the Public Transport Authority (PTA) property; b) At changes of direction; c) At a distance between consecutive markers of the lesser of 200 m or line of sight; and d) Where specified, at the ends of the under track crossing (the end of the under track crossing is taken as the point 3 m beyond the outer rail or toe of the embankment).

24 SECTION 6 Page The wording on the markers shall include the following: a) The owner s name; b) A warning of the presence of a buried service; c) The nature of the buried service; and d) Contact details and advice in the event of an emergency. 3. The markers shall comply with the following requirements: a) Stand at least 800 mm out of the ground, to the bottom of the marker plate; b) Be of non-combustible material for the marker plates and of at least fireresistant material for the pole; and c) Wording on the markers shall be legible, permanent, and formed in a noncombustible medium, or as otherwise approved by the PTA. 4. The descriptive wording and instructions shown on the markers shall face the railway Installation of Power Cables under tracks and elsewhere on railway property Power cables passing under the tracks shall be enclosed in an appropriate Category A system. The top of the encasing pipe or conduit shall be at a depth of not less than 2000 mm below the top of rail and shall be maintained at this depth for not less 3000 mm beyond the outer rails, when measured at right angles to the track, unless otherwise stated in the approved design. A Category A system is an underground system where: a) Cables are enclosed in heavy duty insulating conduit without further mechanical protection. b) Cables are enclosed in insulating wiring enclosures encased in concrete. c) Sheathed cables are enclosed in galvanised steel pipe without further mechanical protection or d) Armoured sheathed cables or neutral screened cables are buried direct in the ground without mechanical protection.

25 SECTION 6 Page 6-3 Dimension Description Minimum depth (mm) X Y Depth between top of rail and conduit, pipe or cable Depth between top of rail and encasing pipe 1200/1500 (directly buried optic) 2000 (power) 1200/2000 (power) Figure 1 Section of conduit or pipe-carrying cable under tracks Power cables passing elsewhere on the property of the PTA shall be laid at a depth of not less than 1000 mm below ground level, or at the same depth below the level of drain inverts they may cross unless, otherwise stated in the approved design.

26 SECTION 6 Page 6-4 Where specified by the PTA, the cables shall also be enclosed in conduits or covered by protective slabs. Figure 2 Section of cable within and parallel to railway reserve 6.2 Existing Pipes or Cables Whenever a crossing is made of an existing pipe or cable, such pipe or cable shall be securely supported during the progress of the work. The minimum spaces required between services are contained in the Utility providers Code of Practice, summarised as follows. 1. Electricity is to pass under gas and water at reticulation crossings.

27 SECTION 6 Page The existing cable shall be protected by a split length of heavy duty conduit or concrete slabs. If 150 mm clearances cannot be maintained then the cable shall be sleeved with a conduit. The length of conduit shall be at least of 500 mm on either side of the crossing. 3. A minimum clearance of 300mm is required between gas and electricity services. If 300mm clearance cannot be achieved, approval of the Gas Service Provider shall be obtained. 4. A minimum clearance of 150mm is required between the electricity services and the sewer and water mains. 5. All reticulation shall be laid within ± 100 mm of the indicated centre line and secured against movement with initial backfill. 6.3 Gas Mains Where work is required close to the gas transmission system such work shall be performed in accordance with Horizon Power s Field Instruction FI 4.1 Work Adjacent to Gas Mains. 6.4 Communications The communications alignment is between mm from the property boundary within the verge, and 450 mm deep. Whenever a cable crosses is a communications cable, the cable shall be securely supported during the process of the work and the power cable shall go under the communications cable, maintaining a 300 mm clearance as per Utility Providers Code of Practice. The space between the power cable and the communications cables shall be maintained when the trench is backfilled. Appendix A provides the diagram for the road reserve allocation for utility providers. 6.5 Existing Underground Electrical Cables Prior to the commencement of excavation work, all efforts must be made to determine if underground cables are present in the vicinity of the proposed excavation. This includes but is not limited to using the One Call service. Work on or near existing underground cables shall be in accordance with Horizon Power s manual, Excavation Work Near Horizon Power s Overhead and Underground Network and Field Instruction: FI 4.4 Excavation Work and FI 4.16 Directional Drilling. If any unrecorded underground cables, conduits or bare earth wires are exposed, work in the vicinity must cease and Horizon Powers CPM must be notified immediately.

28 SECTION 6 Page Road and Vehicle Crossings All cables crossing roads and vehicle crossovers shall be installed in conduits. Road crossings shall be installed: a) Perpendicular to the property street boundaries; and b) Between readily recovered target points, e.g., common property boundaries or intersections. For service cables and streetlight cables, the conduits shall be installed from the edge of the cable alignment to as close as practical to the termination point (e.g. street light column, etc.) For cables with a large bending radius, road-crossing conduits shall extend a minimum of 1000 mm beyond the kerb into the verge and as practically close to the termination point. Cable covers shall be installed over cables in the gaps between the end of conduits and the edge of cable alignment, to ensure that the cable is protected until it enters the cable alignment. Where roads and vehicle crossings are already constructed, thrust boring shall be used to install the required conduits. Conduit crossing locations shall be permanently identified on the road kerb-face. Typical identification methods could include a: a) 75 mm high letter E embedded or cut in, b) Proprietary brass plate/letter E adhered to the face. Where conduits are installed across roadways where no kerbs currently exist or will not be installed when the conduits are installed, conduit location as-built drawings shall show the conduit centreline end-point relative to surveyed property boundaries. 6.7 Horizontal Cable Clearance to other Services at Road Crossings All cables and conduits crossing roads shall be installed with a minimum horizontal clearance of 150 mm from other services.

29 SECTION 7 Page CABLE TUNNELS AND SUPPORT SYSTEMS 7.1 General Where cable tunnels are to be used, the construction and installation requirements shall be included on the design drawings. Cables running through cable tunnels shall be supported on cleats with a maximum spacing of 1500 mm or on cable ladders. Horizontal spacing of cable and circuits shall be at least 100 mm between adjacent circuits. 7.2 Access Pits In circumstances where there is a significant change in direction of the cables being installed, the design may require the installation of an access pit to be large enough to: a) Allow two people to work comfortably on the cable. b) install rollers; and c) Accommodate the bending radii of the largest cable. 7.3 Cable Support A cleat support system shall be installed in at a distance to ensure the cable is maintained in a straight line and only minimal sagging occurs. When using cleats, it is necessary to ensure the cable is rigidly held at the cleat position. Cleats for long vertical runs shall be designed to support the weight of the cable. Cleats used on single core cable shall be of non-magnetic material, such as wood or aluminium. Single core cables shall never be surrounded with a steel ring, as this will cause local heating problems. Care shall be taken to ensure the correct size cleat is used otherwise damage to the cable may result. A tight cleat may pinch the cable whereas a loose cleat may allow excessive cable movement. Wooden cleats shall be used for paper/lead insulated cables.

30 SECTION 7 Page 7-2 This Page Not Used.

31 SECTION 8 Page CABLE ON AND OFF NORMAL ALIGNMENT 8.1 Standard Cable Alignment Wherever practicable, cables shall be installed in Horizon Power s standard alignment of mm from the property boundary in accordance with the Utility Providers Code of Practice for Western Australia and Drawing in Appendix E; Other services shall not be installed in the power cable alignment without written approval from Horizon Power. All front boundary pegs shall be identified prior to the commencement of excavation. 8.2 Alternative Cable Alignment Cables may be installed in the 2.7m alignment where there are installation and maintenance issues adjacent to retaining walls and other structures in the standard mm alignment. This is provided it is acceptable to the other Utility Service Providers and it does not interfere with street trees. In special circumstances if the 2.4 m to 3 m alignment is not available, a written request to the other Utilities will be required to obtain approval to use their alignments. 8.3 Easements Where HV and LV cables are installed outside the standard alignment or in locations other than road reserves, including private property, public open space or public access way, they shall be protected by surveyed and registered easements. Two types of underground distribution easements exist. a) Development areas controlled by the WAPC process: Easements are arranged under Section 167 of the Planning and Development Act b) Other developments areas: Easements are arranged under the Energy Operators (Power) Act The appropriate easement shall be selected and documented in the design file for each particular location. Note: For subdivision developments, developers shall comply with the requirements of the UDS Manual.

32 SECTION 8 Page Retrospective Undergrounding Where the standard cable alignment is not practically available for retrospective underground areas, the cable centre line shall be relocated to a centreline of 2.7 m from the property line (i.e the standard pole and trees alignment). The correct property line shall be identified by survey and where there is any doubt as to its correct location, the required directions shall be obtained from the relevant authority. Where existing overhead electrical apparatus (poles) impedes the installation of underground electrical apparatus (cables) in the 2.7 m alignment, approval may be requested to install the cables on the opposite side of the road in the standard cable alignment. Where the poles and trees alignment is not available, special arrangements will need to be determined and directed by Horizon Power s Asset Management support group.

33 SECTION 9 Page TRENCHING AND EXCAVATION 9.1 General All excavation work shall be carried out in accordance with the requirements of: WorkSafe WA Code of Practice Excavation Excavation Work near Horizon Powers Underground and Overhead Electrical Networks manual FI 4.4 Excavation Work FI 4.16 Directional Drilling Trenches shall be excavated to a width sufficient for satisfactory and safe working conditions. Excavations shall provide the specified minimum cover so as to avoid damage or loss of support to, obstacles such as pipes, drains, cables and other utilities and services; and The excavated area shall be reinstated in accordance with section 16 of this manual. Note: The use of a dedicated safety observer will be required when excavating with a machine in the vicinity of live or de-energised underground cables or ground mounted electrical apparatus. 9.2 Blasting On occasions blasting operations may be undertaken for excavation in rock, limestone and clay. Blasting is not permitted within 30 metres of other utilities and where the blasting will affect their equipment. Handling and use of explosives for blasting operations shall be carried out by, or under the direct supervision of, a licensed shot-firer. Adequate warning signs shall be displayed and all precautions against flying material taken by the use of pegged or weighted blasting mats or similar aids Blasting shall be limited in built up areas and shall only take place when all nearby building occupants have been notified in writing and all buildings have been thoroughly inspected, photographed (where required) and their condition recorded. Note: Contractors shall pay for any damage or injury caused by blasting.

34 SECTION 9 Page Excavated Materials In built up areas where permitted by the relevant authorities and where practicable, reusable top layers of excavated material such as lawns, pavers, topsoil, etc. shall be neatly stacked on one side of the trench and the bottom layer of soil shall be stacked separately on the opposite side of the trench. Some Local Government Authorities require all excavated materials, including paving materials to be removed permanently from site to enable continued pedestrian access without having to walk on the road and reduce the potential for vandalism. Unsuitable soil shall be disposed of and graded backfill brought in. No excavated material shall be placed, or encroach, on private property without the written approval of the owner. In built up areas, excavated soil shall be covered with tarpaulins or similar protection if weather conditions will cause soil to be washed or blown away.

35 SECTION 10 Page DIRECTIONAL DRILLING 10.1 Installation Principles Directional drilling is becoming the preferred method of installation for underground works due to improvements in technology and minimum installation disruption. Conduits and cables shall be installed in accordance with the approved construction drawings. In general, the following principles shall apply: a) Each cable shall be installed in a single way conduit. b) Cable and conduit installations shall be installed between 900 mm minimum depth and 1500 mm maximum depth unless other requirements of this document (e.g. rail crossings) or local site conditions apply. c) Cable spacing s shall meet the requirements of Drawing No. UDS-6-2 in the Underground Distribution Scheme (UDS) Manual or as designed for alternative installations. d) Conduits installed by directional drilling shall not require additional cable protection covers or cable marker tapes. A maximum of two LV cables of 185mm², including streetlight cables can be installed in a common directional drilling bore if there will be no tee or service joints along the cables. One 35mm² HV transformer cable and one LV cable of 185mm² or less can be installed in a common directional drilling bore if there will be no tee or service joints along the LV cable. Multiple high voltage feeder cables (185mm², 240mm² or 400mm²) shall not be combined into a single directional drilling bore. Separate directional drilling bores shall be used between 900mm minimum depth and 1500mm maximum depth. Cable spacing shall meet the requirements of Drawing No. UDS-6-2 in Appendix 22 of the UDS Manual

36 SECTION 10 Page Drilling During construction, continuous monitoring and plotting of the pilot drill and back reamer progress shall be recorded to ensure compliance with the required alignment and installation depth. Refer to Field Instruction Manual FI 4.16 Directional Drilling and FI 4.4 Excavation Work. The monitoring may be accomplished either by manual plotting based on the location and depth readings provided by the tracking system or by computer-generated track logs fed by this information. The tracking system shall provide information on: a) Clock and pitch. b) Alignment and Depth. c) Position (x-y). d) Azimuth - is defined as the direction of cable where a walkover is not possible. The bore logs shall show a depth and bore position from a known boundary every 3m along the bore line. These records shall be made available to Horizon Power electronically as a permanent record. To prevent collapse of the borehole, drilling mud or similar material rather than just water shall be used for both drilling and back reaming operations. Drilling, back-reaming speeds and fluid flow shall be set to ensure spoil is removed without putting unacceptable pressure on the surrounding soil (e.g. surface humping). During conduit and/or cable installation, pull-back tension shall be set so as to not exceed conduit/cable manufacturers maximum pulling tensions. Note: See Appendix B or Manufacturers recommendations for maximum pulling tension for various cable types and sizes Drilling Fluids Management Plan A drilling fluids management plan shall be completed prior to the commencement of directional drilling work. The plan shall contain the following: a) Method of slurry containment. b) Method of recycling drilling fluids and spoil if applicable. c) Method of transporting drilling fluids and spoil off site. d) Drilling fluid pressures. e) Measures to contain and clean the affected area for inadvertent return of drilling or hydraulic fluids. f) Measures to adequately clean-up of surface seepage of drilling fluids and spoils.

37 SECTION 11 Page PLOUGHING Ploughing Ploughing technology allows cables to be ploughed into the ground with an envelope of clean backfill sand. Ploughing equipment has the capability of installing cables in the following arrangements: o Three single core cables (not twisted) in flat or trefoil (triangular) formation. As a minimum, cores must be transposed at every drum change. o Triplex (twisted). The cable configuration must be surrounded with clean sand that is free of rocks and other hard formations: o 150 mm underneath the cable o 50 mm on either side of the cable o 300 mm above the cable Lay orange marker tape over the clean sand, as described in the Marking the ploughed cable route section, below. Fill the trench and compact to ground level with remaining material (ensure that stones and rocks have been removed). Marking the ploughed cable route Permanent above-ground cable markers must be installed along a cable route as described in Table 1 below.

38 SECTION 11 Page 11-2 Table 1 Cable Marking Requirements Alignment category Description Marker tape required? (300 mm above cables) Above ground cable markers required? A Cable within the standard mm alignment Install cable at a depth of 850 mm. Use orange marker tape above cable. Yes No B Cable within the m alignment Install cable at a depth of 850 mm. Use orange marker tape above cable. Yes No C Cable outside road reserve (in remote area where there are no other services or infrastructure in the vicinity) Install cable at a depth of 1200 mm. Use orange marker tape above cables and above ground cable markers. Yes Yes When markers are required (per Table 1, above), they must be placed: on either side of the road at the crossing point wherever a cable crosses a boundary (e.g. road reserve property boundary, etc) and as close as possible to the cable installation For cables in paddocks and open spaces: place markers so that the impact or damage to agriculture (including livestock) is kept to a minimum place markers at the boundaries if a cable has to cross a paddock Markers should also be placed: to signify a change in direction of the cable route so that adjacent markers are visible from each other at a maximum distance of 150 m apart

39 SECTION 11 Page 11-3 This Page Not Used.

40

41 SECTION 12 Page CABLE LAYING 12.1 Drum Mounting and Inspection Prior to installation of cables, the following shall be carried out: Inspection prior to installation: Following removal of the drum battens or transport protective covering and prior to commencing cable installation, check: a) each drum for transport damage; b) integrity of manufacturer s seals on inner and outer cable ends; c) condition of armouring, serving and sheath, particularly damage from drum batten nails; d) Mechanical damage, corrosion and/or leakage of impregnating oil (where applicable). If the cable is found to be defective, it shall not be installed and arrangements made for it to be returned to the supplier for replacement Preparation for installation Each drum should be mounted on jacks, cable trailer or cable stands so the cable is preferably pulled from the top and always in the direction opposite to that indicated by the arrow on the drum; Lighter cables may be laid by mounting the cable drum on its side on a truck-mounted turntable and laying the cable directly into the trench; Prior to removing the cable drum battens, ensure the drum-spindle is level and that the drum turns freely; If it is necessary to roll a drum into position prior to mounting, ensure the drum is rolled in the direction indicated by the arrow on the drum; Cable drums should be positioned in line with the direction of cable pull; As an alternate to a fixed mounting for the cable drum, cables may be rolled directly into a trench from the drum mounted on mobile plant (e.g. excavator) moving along the trench. WARNING Sealed cables may contain methane (a flammable gas) The cable manufacturing process produces methane inside the cable. Where a cable has fitted with a heat shrink end cap & pressure relief valve before the cable is cut, any pressure build up shall be bled by inserting a pin into the valve until no further gas is heard to be escaping. Cable end cap with pressure relief valve

42 SECTION 12 Page Protection of Cables during Installation Cable should be fed from the top of the drum to prevent cable slack. When pulling from large drums, the cable should be supported between the drum and the trench with a suitable ramp or rollers to prevent stressing the cable; Cables shall be kept clear of abrasive surfaces by suitable means, e.g. rollers, etc. to prevent any damage to the cable sheath. The cable shall be placed in the trench without sustaining abrasion damage and without allowing rocks or debris to fall into the trench that could also damage the sheath integrity (allowing termite attack); Precautions should be taken to prevent the drum from over-rotating and allowing cable slack. A suitable braking mechanism should be installed, either in the form of a drum flange drive or an effective friction brake, eg plank brake shoe. Where brake shoes are utilised, care shall be taken to ensure no damage occurs to the cable Z (inner) end that protrudes through the drum flange; On long cable runs or where a cable has significant direction changes (both horizontal and/or vertical), rollers shall be used to ensure minimum pulling or bending of radii are maintained to ensure a smooth pull and avoid damage to the cable; Cables which are pulled into position by a winch, shall use suitable cable stockings and swivels to prevent damage; and When installing cable by directional drilling, it is essential the cable sheath is not damaged, since damage to the outer jacket may cause sheath faults or compromise the integrity of the cable termite protection Cable Installation methods There are numerous methods by which the cable can be pulled into the final installed position. Generally, the most economical methods employ power winches. If considering only those pulling methods using mechanical winches, then there are four distinct methods: Stocking Pulling Cable pulling using a steel mesh cable stocking is probably the most common form of installation for cables up to and including 33 kv. The cable stocking is slipped on to the end of the cable and the winch rope attached. Application of pulling tension locks the stocking onto the cable sheath. Care shall be taken to ensure the manufacturer s recommended pulling tensions are nor exceeded as cable damage will result.

43 SECTION 12 Page Installation using Pulling Eyes The strength of the cable sheath limits the length and size of the cable that can be pulled by stocking pulling. For long and large cross section cables, pulling-eyes can be fixed directly to cable conductors for pulling the cable Bond Pulling When likely pulling tensions may exceed the tension limit of the cable, straight end pulls may have to be replaced by bond pulls. In this method, the cable is lashed to the pulling rope at close intervals (e.g. every half metre for a distance of 20 metres or more) to distribute the strain of the pulling. Mechanical padding is required to protect the cable sheath from damage at the lashing points Armour Pulling This system uses the armour wires of a cable as the pulling medium. The armour wires, left extended past the end of the cable, are formed into a pulling eye and the winch rope attached to it. Caution: This method shall not be used for XLPE cables Mechanical Assisted Installation For long or difficult cable installation or large cable sizes, mechanical assistance can be used to insist installation. Typical methods include: a) One or more cable caterpillars installed mid or multi-point along the cable route to provide intermediate cable thrust; b) Power assisted driven cable drums Cable Pulling Tensions Cable pulling tensions shall not exceed the manufacturer s recommendations. The maximum recommended pulling tensions when using stocking grips to install unarmoured XLPE cables are shown in Appendix B. The trench or conduit line should be set out so that any necessary deviations from a straight line occur over the largest possible radius. When pulling cable into conduits incorporating bends or pulling rope rollers, lower maximum pulling tensions may be necessary to avoid the wire pulling rope cutting into the side of the conduit. Any winch used to pull cables shall have either a facility to automatically limit the pulling tension applied to a cable (a tension fuse) or a continuous reading dynamometer incorporated in the pulling arrangement to enable the actual pulling tension to be monitored. In special circumstances, cable pulling pits may be required at significant changes in cable route direction. Required pits shall be indicated on the design drawing.

44 SECTION 12 Page 12-4 On long or complicated cable installations, intermediate cable feeder equipment (or caterpillars ) may be required to limit pulling tensions Pulling Speed To avoid damage due to overruns, the cable should be pulled just fast enough to keep the drum rotating smoothly. Higher speeds are possible when pulling small cables into straight trenches or conduits with good conditions at the feeding and pulling ends; Drums with long lengths of cable should not be rotated rapidly as overrun can cause cable damage if pulling is slowed or stopped suddenly Cable Bending Radii The permissible bending radii of all cables are given in Appendix B. No twists, knots or kinks are permitted. Where a 3x1 core HV cable is to be laid to transformers or switchgear, the three twisted cores can be separated at termination location (e.g. Triplex style) into three individual cores to reduce the minimum bending radius required Maximum Number of Cable Joints Underground cable joints between terminal points shall be kept to a minimum. For information on the maximum numbers of through joints that may be installed in any section of cable, refer to the Underground Distribution Scheme (UDS) Manual, Section Installation of Cables on Poles Where cables are installed onto termination poles, the cable shall be installed as directly as possible from the cable trench to the pole. No spare loop of cable is required to be installed at the base of the pole, as it is better to joint in a new section of cable if a termination failure occurs. The section of cable off the standard alignment shall be protected by cable slabs and marker tape. Property Boundary 12.9 Bedding and Backfill To protect the cable sheath, all cables shall be firmly and uniformly bedded on sand free from rocks or other hard formation. The cable shall be surrounded with a thickness of sand prior to backfilling, bottom by 150 mm and two sides by 100 mm, top by 300 mm as shown in drawings R 55, R 56, R 57, R 58, and R 59 of the Distribution Construction Standards Manual. The upper 300 mm of the backfill to final ground level shall also meet the local government authority s requirements.

45 SECTION 12 Page Depth of Cover for Cables The depth of cover over cables shall not be less than 850 mm. The depth of cover shall be increased as required to ensure that cable joints will have the required depth of cover Cable Protection Covers and Marker Tapes The cable covers shall comply with the requirements of clauses of AS/NZS 3000:2000 and if required, cable covers and PVC marker tape shall be laid at the required levels, as shown in drawing R 51 Distribution Construction Standards (Placement of Duct beneath Road Crossings) Where more than one cable is installed, the PVC maker tape or cable cover must be wide enough to fully cover the cables, otherwise additional maker tapes and covers shall be installed. Additional cable protection shall: 1. be placed maximum 75 mm above the wiring system 2. be not less than 150 mm wide 3. overlap the wiring system by at least 40 mm on each side 4. consist of one or a combination of the following: Note: a) precast concrete slabs with a minimum thickness of 40 mm and a classification of not less than grade 20 degrees in accordance with AS 3600 b) a continuous concrete pour having a thickness of not less than 75 mm c) fibrous cement slabs having a thickness of not less than 12 mm d) bricks (slabs) manufactured specifically for the protection of electric cables e) polymeric cable cover strip (complying with AS 4702) f) Other materials that offer the same degree of protection as the materials in items (a) to (e) above. Conduits installed by directional drilling shall not require cable protection covers and marker tapes Sealing of Cables To ensure water cannot penetrate into the cable conductors or insulation, ends of cables shall be kept sealed. On completion of the cable pulling, any damaged or nonwaterproof pulling eyes or sealing end caps should be removed and the cable resealed, unless it is to be terminated immediately. Where cables have been cut following installation, both the installed and drum ends shall be sealed immediately, except where the cable is to be jointed immediately.

46 SECTION 12 Page 12-6 This Page Not Used.

47 SECTION 13 Page CONDUITS 13.1 Application Conduits complying with Australian Standard AS 2053 shall be used to protect cables where they are installed in the following situations: a) in easements; b) exit cables from a distribution substation that is set back from road or property boundary; c) near retaining walls where there is a danger of cable installation damage due to foundation subsidence; d) crossing roads; e) crossing water courses and drains; f) crossing high pressure gas pipelines; g) crossing under railway lines or restricted access areas such as airports; and h) Within bridge crossings Requirements for cables installed outside normal alignments Where cables are installed outside the mm standard alignment or the mm alignment as approved by Horizon Power for street installation, conduits are NOT required. The cables shall be direct buried, laid in accordance with and protected with cable slabs as shown in Drawing in R 51 Placement of Duct beneath Road Crossings in the Distribution Construction Standards Manual Encased Conduits In some locations PVC conduits may be encased in concrete pipes, steel pipes or concrete encased steel pipes. Unless approved by Horizon Power, cables shall not be installed directly in concrete conduits due to potential damage to sheaths during installation Sealing of Conduits All conduits, including spare conduits, shall be effectively sealed at the ends and at couplings; Sealing of conduits is required to prevent the ingress of water and any foreign material that may cause blockage or flooding of cable pits, basement-type substations and switch rooms; Wherever possible, suitable conduit plugs or covers should be used for sealing of conduits in lieu of taping or other makeshift arrangements.

48 SECTION 13 Page 13-2 Conduit joints and couplings shall be installed and sealed in accordance with the manufacturer s instructions Installation requirements for Conduits Where conduits are installed in excavations, they shall be installed: a) with a minimum cover of 850 mm to the top of the conduit; b) not more than 1100 mm cover as approved by Horizon Power; c) where all cables in the trench are all installed in conduits, excavated soil may be used for bedding and backfill, provided it is free of organic matter and rocks of 50 mm diameter or larger; d) normally in flat, horizontal formation for up to four cables, thereafter in tier formation; e) for road crossings, in accordance with Section 6.6 Road and Vehicle Crossings; f) sealed with suitable end caps; g) with approved draw wires provided in every conduit; h) When installed prior to the main cable trenching, installed with marker tape 300 mm above the conduit. The marker tape shall be brought out to ground level at each end, with the conduit end position also being marked with a peg. The most economical method shall be used to install conduits across roads. Subject to cost, boring is preferred for single or double conduit crossings, where conduits of 100 mm size or larger are required. For locations where more than two conduits are to be installed together, open excavation methods may be used for crossing roads Pulling Cables through Conduits Care shall be taken to avoid damaging the outer sheath of the cable where it enters and leaves the duct. Single core bundled XLPE high voltage cables are particularly susceptible due to their uneven shape and thin outer sheath. To prevent future cable failure a suitable lubricant should be used to reduce the friction between the cable and the duct. A tapered or belled entry shall be used at the entry end of ducts during pulling to prevent damage to cable.

49 SECTION 14 Page CABLE JOINTING AND TERMINATIONS 14.1 General Underground cable jointing is based on the following Principles of Good Cable Jointing : 1. Safety shall never be compromised; 2. Jointing pits should be large enough to allow jointers to work freely; 3. Before joining any cable it must be positively identified by approved testing methods and marked at both ends of the cable; 4. Water barrier within the cables to checked prior to joining the cables: 5. The correct kit for joint and cable size shall be selected; 6. Manufacturers jointing instructions shall be followed unless practicalities suggest a variation. Where fixture torque are recommended, apply those with torque wrench; 7. Accurate measuring, cutting, stripping and torque settings and workmanship shall be in accordance with the manufacturer s instructions; 8. Ground covers shall be used to keep tools & equipment and jointing components clean throughout the job. (Ensure joints don t get contaminated with surrounding soil, sand, or moisture); 9. Ensuring enough spare cable so that the cable stripping distances are suitable for lay of cable (after cable is manipulated to correct position) to complete the joint(s) in accordance with the manufacturers requirements; 10. All cable ends are to be sealed after cutting. Where they are not sealed they are to be considered suspicious and checked for water ingress prior to use. 11. Housekeeping keep the work environment clean by placing used packaging in box as work progresses Cable Joint Excavations There is no standard size for a jointing pit, however joint sizes vary and therefore the size of the pit in which to carry out the jointing will vary. To facilitate the joining of Cables and to reduce the impacts on the health and safety of the employee/contractor completing the joints, as a minimum, a pit in the trench should be excavated to the following dimensions: a) 2 meters wide; b) 2 meters in either direction (4 meters long) of the joint; and

50 SECTION 14 Page 14-2 c) At the same depth as the trench. Depending upon the depth of the trench / lay of cable; an additional step should be to excavate in the pit to either side of the cable joint to allow for ease of access and facilitate the joiner working on the joint. Fig 1 illustrates the concept. Figure 3 Cable joint pit dimensions The sides of the pits should be covered with tarpaulins or similar to prevent soil from being dislodged while working in the pit Jointing Before joining any cable it must be positively identified by approved testing methods and marked at both ends of the cable. Water barrier within the cables must be checked prior to joining the cables to ensure no moisture has penetrated into the cable. (Moisture barrier turns green when water is present) If moisture is detected, the cable must be strip the cable back to the point where no moisture is present. All jointing equipment shall be installed in accordance with the manufacturer s instructions supplied with the equipment kit to which they relate. The use by date of the jointing equipment shall be checked prior to use. Where the used by date has expired, the jointing equipment shall be removed from service and returned to the depots store for disposal. Ensure no conductive material is left on the XLPE cable. If necessary remove any remaining semi-con material with abrasive paper (sandpaper) then clean with a solvent wipe. Note: Never use a knife to cut the semi-con. This can create a void and could result in the delaminating of the XLPE screen below the ring cut. When stripping the semi-con screen and you score the XLPE insulation, sandpaper the damaged area to smooth out the void/irregularities

51 SECTION 14 Page 14-3 The installer identification tags are required on all joints. They shall be marked and fitted adjacent to the joint or termination equipment as per drawing R39 in the Reference section of the Distribution Construction Standards Manual. All 11KV rated cable requiring transition joints shall use FJ0310 and FJ0405 joint assemblies. All 22KV rated cables requiring transition joints shall use FJ0403 joint assembly. Shear bolts ends shall be filed back to prevent the sharp edges creating a stress point within the cable joint Termite Proofing Termite proofing shall be installed over all XLPE to XLPE HV straight joints. The preferred method of termite proofing shall be of the stocking type, which is fitted over the cable prior to joining. Where the stocking type is not available, termite sheeting may be used in conjunction with heat shrink outer seal of the entire termite protection area. Full heat shrink sleeve as provided in kit or zip shrink if jointing area is restricted On completion of the joint, the termite stocking can be moved over the joint with a minimum cable overlap of 200mm. The ends of the termite stocking shall be sealed with brass roll springs as provided within termite protection kit TPKIT Where termite sheeting is used, it shall be wrapped around the cable twice and have a minimum cable overlap of 200mm. The ends of the termite sheeting shall be sealed with brass roll springs as provided within termite protection kit TPKIT These may be sourced individually from the supplier. The remaining overlap of termite sheeting over the joint body should be secured evenly in intervals every 150mm to 200mm with the use of 5mm stainless steel cable ties 14.5 Terminations All Low Voltage terminations shall be completed in accordance with Part 5 - Low Voltage Underground of the Distribution Construction Standards Manual. Where no termination drawing exists, all equipment shall be installed in accordance with the manufacturer s instructions supplied with the equipment kit to which they relate.

52 SECTION 14 Page Working Ends If a cable for a future scheme/connection is laid from a universal pillar, kiosk or a low voltage frame unit in an existing scheme, then the remote end of this cable must not be left on a cable drum. The cable must be made off, insulated to approved methods and placed in a mini pillar with its top painted white. In areas where it is not possible to install a pillar, then the remote end of this cable must be made off in a joint/shell located in Horizon Power s cable alignment. When this method is utilised, the location of the joint/shell (e.g. distance from closest property boundary) must be recorded accurately in GIS.

53 SECTION 15 Page TESTING AND COMMISSIONING Testing and commissioning shall only be carried out by qualified and Horizon Power authorised personnel and in accordance with: Horizon Power s Network Testing & Commissioning Standards (CS10# ) VLF Testing of HV Cables manual (CS10# ) Available on Power Link and the Horizon Power external web site, under Network Contractors. The Tester-in-Charge shall be responsible for carrying out tests in accordance with these standards and recording all test results and additional comments where relevant.

54 SECTION 15 Page 15-2 This Page Not Used.

55 SECTION 16 Page REINSTATEMENT 16.1 General The excavated or disturbed land shall be restored to its original condition. Backfilling and reinstatement of road verges and vehicle crossings as necessary shall be completed within three working days from the time the cables are laid and jointed. Road reserves and all work sites shall be levelled and left clean and tidy. Debris, trees, stumps and excess soil dug from the excavation shall be removed from site when trench backfilling has been finished. All materials, stakes, plant and equipment used during installation shall be removed and all work sites left in a safe condition. All material off cuts, waste materials and general rubbish shall be removed from site and disposed of in accordance with the Local Government Authority s requirements. The initial backfill over the bedded cables shall be carried out in accordance with Section 12.9 Bedding and Backfill of this manual. Trenches shall be backfilled, reinstated and compacted to their original level and/or in accordance with the requirements for footpaths by the Local Government Authority Compaction Spoil or other approved filling shall be carefully placed in layers into the trench. Stones, rocks and paving material shall be removed from site and not used as backfill. All backfilling shall be compacted to a minimum 90% of the density as the surrounding soil in accordance with Horizon Powers Field Instruction Manual: FI 3.23 Soil Compaction Testing Requirements to prevent future subsidence. All results shall be compiled on the Compaction Test Certificate in (CS10# ) 16.3 Levelling Backfilled excavations shall be levelled so as not to constitute a hazard and shall be to the same as the original unexcavated land.

56 SECTION 16 Page Restoration of Surface On completion of any operations affecting pavements or constructed surfaces, except Greenfield subdivision the pavements or constructed surfaces shall be restored in accordance with the Restoration and Reinstatement Specification for Local Governments in Australia Published by the Institute of Public Works Engineering Australia, which is available at Traffic/Road-works/Working on main roads from Main Roads WA s web site or through the Institute of Public Works Engineering Australia (WA Division) on the IPWEA website. Restoration of surface includes restoration of all type of footpath materials, e.g. bitumen, brick paving, liquid limestone, etc. Where cement footpath slabs have been removed to allow cable trench excavation, they shall be replaced and reinstated in accordance with the Local Government Authority s requirements unless otherwise directed by the Horizon Power.

57 SECTION 17 Page DAMAGE TO PROPERTY 17.1 General In all areas where cable installation work has been carried out, except as approved by Horizon Power, property or services damaged shall be repaired or replaced as soon as possible after making safe. Fences around areas holding livestock shall be secured at all times and if damaged during construction shall be repaired or made safe immediately to prevent the stock from straying. Damage to reticulation systems and underground services that are disturbed or damaged shall be restored to working order. Trees planted in the road verge shall be protected as far as possible. Tree limbs interfering with the construction shall be removed appropriately by pruning and sealing and the trees left in a reasonable condition. Inspection shall be done of any structures located along the cable trench route prior to the commencement of works and arrangements shall be made to protect these structures if there is a possibility of damage or hazards occurring. Horizon Power s CPM shall be notified in all cases of such damage or hazards occurring.

58 SECTION 17 Page 17-2 This Page Not Used.

59 SECTION 18 Page PILLARS AND PITS 18.1 General Where approved by Horizon Power, service pillars shall be located within the lot boundaries at the corner, adjacent to common boundaries where possible, refer to the Utilities Code of Practice for Western Australia for Road Reserve allocations. Pits shall only be used where it is impractical to install a pillar, such as on a traffic island or beside a narrow driveway where there is a high probability of impact damage. Where there is a change in level between the service tee and the pillar, the cable shall be protected in conduit where it traverses the slope. Figure 4 - Service pit installation

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV Network(s): Summary: ENGINEERING INSTRUCTION EI 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV EPN, LPN, SPN This engineering instruction details the minimum requirements acceptable for the installation

More information

11.1 INTRODUCTION Objectives Key References Interpretation GENERAL CONDITIONS DESIGN...

11.1 INTRODUCTION Objectives Key References Interpretation GENERAL CONDITIONS DESIGN... CONTENTS SECTION 11 TELECOMMUNICATIONS UTILITIES 11.1 INTRODUCTION... 1 11.1.1 Objectives... 1 11.1.2 Key References... 1 11.1.3 Interpretation... 2 11.2 GENERAL CONDITIONS... 2 11.3 DESIGN... 3 11.4 DESIGN

More information

Field Instruction. All Horizon Power workers who work in and around excavations.

Field Instruction. All Horizon Power workers who work in and around excavations. 6.4 Excavation work and directional drilling Purpose This instruction provides the minimum requirements for: All Horizon Power workers who work in and around excavations. All Horizon Power workers who

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

Landscaping and Fencing

Landscaping and Fencing Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing

More information

NSP/002 Policy for the Installation of Distribution Power Cables

NSP/002 Policy for the Installation of Distribution Power Cables Version:- 3.1 Date of Issue:- November 2016 Page 1 of 27 NSP/002 Policy for the Installation of Distribution Power Cables 1. Purpose The purpose of this document is to detail Northern Powergrid s (the

More information

TS 804 CABLES TABLE OF CONTENTS TRAFFIC SIGNAL EQUIPMENT POLE WIRING DIAGRAM LOCATIONS WITH CENTRE MEDIANS

TS 804 CABLES TABLE OF CONTENTS TRAFFIC SIGNAL EQUIPMENT POLE WIRING DIAGRAM LOCATIONS WITH CENTRE MEDIANS TORONTO TRANSPORTATION January 2012 TS 804 CABLES TABLE OF CONTENTS 1. DRAWINGS TTD 804.001 TTD 804.002 TTD 804.003 TTD 804.005 TTD 804.006 TTD 804.007 TTD 804.010 TTD 804.015 TTD 804.020 TTD 804.025 TTD

More information

NPS/002/020 Technical Specification for 11 & 20kV Power Cables

NPS/002/020 Technical Specification for 11 & 20kV Power Cables Version:- 3.1 of Issue:- Nov - 09 Page 1 of 11 NPS/002/020 Technical Specification for 11 & 20kV Power Cables 1. Purpose The purpose of this document is to detail Northern Powergrid (the Company) requirements

More information

UNDERGROUND DROP CABLE CONDUIT INSTALLATION AND SPECIFICATION GUIDELINES FOR SINGLE DWELLING RESIDENTIAL APPLICATIONS

UNDERGROUND DROP CABLE CONDUIT INSTALLATION AND SPECIFICATION GUIDELINES FOR SINGLE DWELLING RESIDENTIAL APPLICATIONS UNDERGROUND DROP CABLE CONDUIT INSTALLATION AND SPECIFICATION GUIDELINES FOR SINGLE DWELLING RESIDENTIAL APPLICATIONS 1. SPECIFICATIONS This document details the specifications for the installation of

More information

Specifications for Residential Underground Electric Service Installation

Specifications for Residential Underground Electric Service Installation Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (URD) Index General Discussion... 1-2 Description... 3-7 Drawings (Available

More information

DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS. Wireline Occupancies

DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS. Wireline Occupancies DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS Wireline Occupancies OFFICE OF: VICE PRESIDENT ENGINEERING JACKSONVILLE, FLORIDA ISSUED: September 15, 2003 REVISED: December 16, 2016 THIS PAGE BLANK DESIGN

More information

ROAD PAVEMENTS GENERAL

ROAD PAVEMENTS GENERAL ROAD PAVEMENTS GENERAL Contents Clause Title Page 701 Pavement Construction... 2 702 Horizontal Alignments, Surface Levels and Surface Regularity of Pavement Courses... 2 703 Not Used... 4 704 Not Used...

More information

TESTING PTE EARTHING

TESTING PTE EARTHING 1 SCOPE This section of the Power Systems Live Working Manual details the procedures to be followed to achieve Safety from the System when carrying out examination, testing and remedial work on PTE (Pole

More information

STANDARD PRACTICE INSTRUCTION

STANDARD PRACTICE INSTRUCTION STANDARD PRACTICE INSTRUCTION DATE: March 1, 2001 SUBJECT: Scaffolding Safety Program. REGULATORY STANDARDS: 29 CFR 1910.28 Safety Requirements For Scaffolding. 29 CFR 1910.29 Manually Propelled Mobile

More information

Contractor s Guide to Applying for Permit to Dig/Excavate

Contractor s Guide to Applying for Permit to Dig/Excavate Contractor s Guide to Applying for Permit to Dig/Excavate Page 1 of 15 Contractor s Guide to Applying for Permit to Dig/Excavate Contents Purpose... 3 Inclusion Group... 3 1. Pre commencement worksite

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2018.03 EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 The following changes are made to the Proposal, Specifications, and Plans. PROPOSAL Proposal Sheets

More information

WIRING METHODS CHAPTER 38

WIRING METHODS CHAPTER 38 CHAPTER 38 WIRING METHODS SECTION E3801 GENERAL REQUIREMENTS E3801.1 Scope. This chapter covers the wiring methods for services, feeders and branch circuits for electrical power and distribution. E3801.2

More information

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics HEKAPLAST PE-HD twin wall cable ducts and cable protection pipes for underground installation HEGLER HEKAPLAST III/ HEKAPLAST: Twin wall cable ducts or cable protection pipes to DIN 696, manufactured from

More information

High Voltage Cable Routes

High Voltage Cable Routes Engineering Specification Electrical L1-CHE-SPE-070 High Voltage Cable Routes Version: 2 Issued: October 2017 Owner: Chief Engineer Approved By: Andrew Russack Head of Electrical Engineering PRINTOUT MAY

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information

Specifications for Electrical Underground Residential Distribution Systems

Specifications for Electrical Underground Residential Distribution Systems Specifications for Electrical Underground Residential Distribution Systems Specification DDS-2 Revision 13, February 2010 ONCOR ELECTRIC DELIVERY COMPANY SPECIFICATIONS FOR ELECTRICAL UNDERGROUND RESIDENTIAL

More information

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August Double Slide Rail August 2015 1 DOUBLE SLIDE RAIL INSTALLATION METHOD Introduction Slide rail shoring systems can be used for trenches up to 12m wide and 6m deep. Module length is determined by panels

More information

INFORMATION FOR PROPERTY DEVELOPERS, CONSULTANTS, BUILDERS AND CUSTOMERS Telstra s lead-in trenching requirements

INFORMATION FOR PROPERTY DEVELOPERS, CONSULTANTS, BUILDERS AND CUSTOMERS Telstra s lead-in trenching requirements INFORMATION FOR PROPERTY DEVELOPERS, CONSULTANTS, BUILDERS AND CUSTOMERS Telstra s lead-in trenching requirements This publication has been prepared and written by Telstra Corporation Limited (ABN 33 051

More information

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

This guide only applies for sewer assets up to and including 225mm diameter.

This guide only applies for sewer assets up to and including 225mm diameter. INTRODUCTION This guide only applies for sewer assets up to and including 225mm diameter. These guidelines (subject to change) provide an outline of the requirements which need to be considered when planning

More information

NPS/002/023 Technical Specification for 132kV Power Cables.

NPS/002/023 Technical Specification for 132kV Power Cables. Version:- 2.2 of Issue:- June 09 Page 1 of 11 NPS/002/023 Technical Specification for 132kV Power Cables. 1. Purpose The purpose of this document is to detail the technical requirements of Northern Powergrid

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

General Symbols, Ducts and Cables

General Symbols, Ducts and Cables DIVISION 2000 - ABBREVIATIONS 2009 11 2000.001 0 Abbreviations, General 2009 11 2011.101 0 General Symbols, Ducts and Cables 2009 11 2011.201 0 General Symbols, Maintenance Holes, Junction Boxes, Pads,

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

More information

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings G U I D E L I N E S F O R L A N D O W N E R S, D E V E L O P E R S A N D C O N T R A C T O R S T A B L E O F C O N T E N T S 1 Introduction 2 Office Locations/Map 3 General Requirements 4 Structures and

More information

Procedure and Specification for the Construction of Vehicle Access Crossings over Footways and Verges April 2016

Procedure and Specification for the Construction of Vehicle Access Crossings over Footways and Verges April 2016 Procedure and Specification for the Construction of Vehicle Access Crossings over Footways and Verges April 2016 (1) Authorisation to work in the Highway Persons wishing to construct a vehicular crossing

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

Worksite Safety Update Promoting safety in road construction

Worksite Safety Update Promoting safety in road construction Worksite Safety Update Promoting safety in road construction No 122 August 2012 In this Edition: Work Near Overhead and Underground Utility Services Page 1 The Regional Rail Link Experience Page 9 This

More information

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17 Technical Specification for Overhead and Underground Service Connection works for the Year 2016-17

More information

THE KANSAS CITY SOUTHERN RAILWAY COMPANY 427 West 12 th Street Kansas City, Missouri

THE KANSAS CITY SOUTHERN RAILWAY COMPANY 427 West 12 th Street Kansas City, Missouri Utility Permit Process Instructions How to apply: In an effort to effectively facilitate the permit process, The Kansas City Southern Railway Company ( KCS ) has partnered with JLL who is committed to

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

Reliant Holdings Ltd Safety Management System

Reliant Holdings Ltd Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to falls from elevated work areas and ensure employees

More information

Cables for Railway Signalling Applications General Requirements

Cables for Railway Signalling Applications General Requirements Discipline: Engineering (Signalling) Category: Procedure Cables for Railway Signalling Applications General Requirements ESA-11-01 Applicability ARTC Network Wide Primary Source ESA-02-01 Document Status

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS December 2012 CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions Specifications...

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Wokingham Borough Council Street Lighting Design, Adoption Process and Specification Guide

Wokingham Borough Council Street Lighting Design, Adoption Process and Specification Guide Wokingham Borough Council Street Lighting Design, Adoption Process and Specification Guide 1. Design Process 1.1 All street lighting layouts and equipment specifications on new housing developments will

More information

HAS/042/001 Code of Practice for Work on Street Lighting and Street Furniture including Installation, Repairs and Maintenance

HAS/042/001 Code of Practice for Work on Street Lighting and Street Furniture including Installation, Repairs and Maintenance Version:- 2.0 Date of Issue:- March 2017 Page 1 of 13 HAS/042/001 Code of Practice for Work on Street Lighting and Street Furniture including Installation, Repairs and Maintenance 1. Purpose The purpose

More information

Underground Piping for Private Hydrants & Sprinkler Supply Line

Underground Piping for Private Hydrants & Sprinkler Supply Line City of Brea Brea Fire Department Fire Prevention 1 Civic Center Circle Phone: (714) 990-7655 Underground Piping for Private Hydrants & Sprinkler Supply Line PURPOSE The provision of adequate water supplies

More information

WHS Management Plans

WHS Management Plans WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the

More information

Part 11: Lighting. Contents. Tables. Part 11: Lighting. Christchurch City Council Infrastructure Design Standard 11-1

Part 11: Lighting. Contents. Tables. Part 11: Lighting. Christchurch City Council Infrastructure Design Standard 11-1 Part 11: Lighting Contents 11.1 Referenced Documents...11-2 11.2 Introduction...11-2 11.3 Quality Assurance Requirements and Records...11-2 11.3.1 The designer... 11-3 11.3.2 Design records... 11-3 11.3.3

More information

Minimum grade (%) Velocity at full flow (m s 1 )

Minimum grade (%) Velocity at full flow (m s 1 ) 1.6 Pipes Effluent can be conveyed by channels or pipes under gravity or in dedicated pipelines under pressure. If pipes are used, pressure rating, water-hammer and excessive friction losses must be considered

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Electric Service Handbook

Electric Service Handbook Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated

More information

Collection of standards in electronic format (PDF) 1. Copyright

Collection of standards in electronic format (PDF) 1. Copyright Collection of standards in electronic format (PDF) 1. Copyright This standard is available to staff members of companies that have subscribed to the complete collection of SANS standards in accordance

More information

SPECIFICATIONS SCOPE OF WORK

SPECIFICATIONS SCOPE OF WORK SPECIFICATIONS SCOPE OF WORK The intent of this contract is for the supply of all necessary labour, materials, and equipment to install underground traffic signal plant, vehicles detection loops, installation

More information

Member Service Electric Wiring Guidelines

Member Service Electric Wiring Guidelines Member Service Electric Wiring Guidelines Table of Contents A. Definitions... 2 B. Member Service Wiring Guidelines... 2 C: Meter located on the house from an underground source - pad transformer or j-box....

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703) Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA 20155 Phone (703) 754-6750 Work Request # UNDERGROUND DISTRIBUTION FACILITIES AGREEMENT (FOR COMMERCIAL CUSTOMER) Developer/Builder/Owner

More information

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL 8.01 GENERAL This material is not intended to cover service from OPPD s network in the downtown Omaha area. See Chapter 12 for details

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

nbn Lead-in Trenching Requirements

nbn Lead-in Trenching Requirements nbn Lead-in Trenching Requirements Engineering Document number F0002-31-11578 Document category Guide Author Engineering Status Approved Issue date 15 JULY 2016 Revision number 2.1 Classification Public

More information

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

METERING GUIDE PART 1 METERING GENERAL

METERING GUIDE PART 1 METERING GENERAL 1 METERING GUIDE PART 1 METERING GENERAL 2 METERING GUIDE 1 INTRODUCTION 3 PURPOSE OF THIS GUIDE 3 METERING GENERAL 4 ELECTRICITY SUPPLY - INDUSTRY PLAYERS 4 1.1.2 Generators 4 1.1.3 Networks 4 1.1.4 Retailers

More information

Specifications for Residential Overhead Electric Service Installation

Specifications for Residential Overhead Electric Service Installation Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

Meter and Sub- Metering Technical Specifications

Meter and Sub- Metering Technical Specifications Meter and Sub- Metering Technical Specifications 24 July 2015 Table of Contents 1. Introduction... 3 2. Metering Technical Specifications... 3 2.1 Water Meter Types... 3 2.2 Water Service and Meter Sizing...

More information

TRENCHING AND EXCAVATION

TRENCHING AND EXCAVATION TRENCHING AND EXCAVATION The following guide is an aid intended for students who have completed the ClickSafety training course or module associated with Trenching and Excavation. This guide is a resource

More information

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NOVEMBER 2016 GRANDWALL. retaining walls installation guide NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

INDUSTRIAL PIPE FITTINGS, LLC

INDUSTRIAL PIPE FITTINGS, LLC Page 1 of 9 SPIROLITE MUNICIPAL AND INDUSTRIAL ODOR CONTROL PIPING Municipal wastewater treatment plants, industrial processes and composting facilities can be assured of trouble free transport of foul

More information

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National Grid, on or near to its electricity apparatus. National

More information

Polysewer Gravity Sewer System SPECIFICATION

Polysewer Gravity Sewer System SPECIFICATION Polysewer Gravity Sewer System SPECIFICATION July 2014 SCOPE OF WORKS To meet the specific performance criteria detailed within this specification and accompanying drawings. The completed drainage systems

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS L L S! " # #! " # # $ % & ' (! & ) * + ', - )!!!. &! - * + ', - )!!!. &! - * " # # $ % & ' (! & ) " &! % - / 0 1 2 3 4 3 2 5 6 3 7 8 4 7 9 : 7 5 ; < 7 9 = > / 1 9 3 1 >? @ A A B C 9 1 8 2 D E 1 > > F 8

More information

Retaining Wall System

Retaining Wall System Your local distributor Retaining Wall System Prestige & Quality Near Vertical Walls Do It Yourself No Concrete Footings Flexible - 90 o Corners, Steps, Straight or Curved Walls Commercial or Civil Walls

More information

ENCROACHMENT GUIDELINES

ENCROACHMENT GUIDELINES 2727 North Loop West, Houston, TX 77008-1044 P.O. Box 4324 Houston, TX 77210-4324 ENCROACHMENT GUIDELINES March 01, 2010 Revision 0 TABLE OF CONTENTS SECTION PAGE 1.0 Purpose and Scope...3 2.0 General

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 280.21-300.50 CHANGES FROM 2011 TO 2014 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1000 volts II. Instillation III. Connecting Surge

More information

Industry guidance for the safe operation of tilt-tray vehicles

Industry guidance for the safe operation of tilt-tray vehicles Industry guidance for the safe operation of tilt-tray vehicles This document provides practical advice on meeting the Duty of Care requirements of the Occupational Safety and Health Act 1984 (the Act)

More information

Information Bulletin:

Information Bulletin: Equipment Advisory Adv. No. 2015-020 1 Supersedes: 0 Issue Date: Aug 19, 2015 File: 1613.9.1 Information Bulletin: Duct Spacers and Warning Boards for PVC Duct evision Note evised text in this advisory

More information

Site Quality Assurance Inspection Regime for Connections Extension Assets

Site Quality Assurance Inspection Regime for Connections Extension Assets Site Quality Assurance Inspection Regime for Connections Extension Assets Background Northern Powergrid undertakes sample quality assurance inspections of assets installed by Independent Connection Providers

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

DIVISION 33 UTILITIES SPECIFICATION : HORIZONTAL DIRECTIONAL DRILLING

DIVISION 33 UTILITIES SPECIFICATION : HORIZONTAL DIRECTIONAL DRILLING 1.1 DESCRIPTION DIVISION 33 UTILITIES SPECIFICATION 330523: HORIZONTAL DIRECTIONAL DRILLING PART 1.0 GENERAL 1.1.1 The directional drilling method is a multi-stage process that involves site preparation

More information