OHE Project No.: Art Gallery of Peterborough Hazardous Material 250 Crescent Street Abatement Specifications

Size: px
Start display at page:

Download "OHE Project No.: Art Gallery of Peterborough Hazardous Material 250 Crescent Street Abatement Specifications"

Transcription

1 Peterborough, Ontario Page 1 of 66 Section Site Work Asbestos Abatement PART 1 GENERAL 1.1 General Conditions and Related Work This section forms a part of the Contract Document and should be read in conjunction with all other Sections and Divisions in order to comply with the requirements of the General Conditions of the Contract It is the intent that work performed as outlined in this section will result in the removal and disposal of all asbestos-containing materials and lead-containing materials, existing asbestos and lead contaminated materials and materials that become contaminated by asbestos and/or lead as a result of the work specified by this Section. The referenced materials include, but are not limited to texture coat and vinyl floor tile Dispose of all waste as specified in applicable sections of the specifications document The Environmental Consultant may perform area and personal air sampling to verify effectiveness of dust suppression methods and adequacy of the respirators used by the Contractor. Contractor s personnel shall co-operate with the Environmental Consultant in collecting air samples This project and all work associated with it is regulated by Ontario Regulation 278/05, The Occupational Health and Safety Act and other applicable regulations Provide all equipment, material, services, supervision and labour required or specified to complete the scope of work of this project as described in the Contract and Specifications Documents. 1.2 Description of Work Before submitting a bid, confirm the scope of work of the project by visiting the site and reading the entire Contract documents. The information and any drawings presented should not be used as the only basis for submitting a bid Work Area 1: Ramp (Lower Level, Ground Floor, Second Floor), Lower Level Hallway, Ground Floor Reception and Vestibule, Second Floor Red Room : Work in this area shall be carried out following Type 3 Removal Operation procedures as detailed in O. Reg. 278/05 (Subsections 3.4) and Type 2a Operation procedures as detailed in the Guideline: Lead on Construction Projects (Sub-section 3.9) as follows: Pre-clean the entire Work Area including floors, walls, electrical panels housing, conduits, wires and cables, and all other equipment and items present in the work area using vacuum units equipped with HEPA filters and wet wiping Pre-clean and remove all movable objects and items present in the Work Area Shut off, lock out all ventilation, and seal all vents, ductwork, doors, or other openings into the work area, with the application of rip-proof polyethylene sheeting and properly seal Protect all floors, walls and objects which are scheduled to remain in the Work Areas before commencing any work using rip-proof polyethylene sheeting and duct tape. Maintain air tight and water tight. Floors, walls and objects to be protected using 2 layers of rip-proof poly sheeting Erect upper and critical seals where required. Pre-clean and seal (air and water tight) all openings that lead from the Work Area. Ensure that all floor openings are independently sealed and are water tight. Use silicone or caulking where necessary to achieve water tightness, if required Erect Type 3 enclosures using rip-proof polyethylene sheeting from floor to ceiling supported using zip-poles or studs (wood used must be fire-rated (cannot be treated with fireproof paint), including 2x4 s) Ensure that the Work Area is separated from the rest of the building as required. Separate the asbestos removal work area from other areas on the floor required to remain in use by erecting hoarding walls constructed of rip-proof polyethylene sheeting and wood studs as specified in the applicable sections of the specifications document.

2 Peterborough, Ontario Page 2 of The Contractor shall be responsible for providing their own temporary hot and cold water. The Contractor shall be responsible for providing their own temporary lighting using ground fault panels. It is the Contractor s responsibility to provide electricity as needed for the duration of the abatement activities. The level of lighting shall be acceptable to the Consultant. The Contractor shall remove and dispose of the lights, light fixtures, track lighting and tracks, and ballasts from the Work Area. Proof of disposal shall be required Extract all required light ballasts, clean and place in a temporary staging area pending an examination by the Consultant to determine PCB content. All PCB-containing ballasts (as identified by the Consultant) shall be placed in steel drums properly labeled and shall be disposed of according to applicable environmental regulations. The Contractor shall be responsible for arranging and paying for the cost of disposal. A copy of the certificate of destruction shall be submitted to the Consultant once the PCB-containing materials are disposed of Maintain the fire alarm and other life/safety systems in operation. Immediately advise the Consultant in case the systems are damaged during the execution of work The asbestos abatement Contractor shall allow for the removal and disposal of the asbestos-containing texture coat following Type 3 Operations (approximately four thousand (4,000) square feet in total) The material present in the project areas contains Chrysotile Asbestos. Full-face negative pressure respirators equipped with P-100 filter cartridges shall be worn as a minimum if the material is wetted. The Environmental Consultant may perform area and personal air monitoring to verify effectiveness of dust suppression methods and adequacy of the respirators used by the Contractor. Contractor s personnel shall co-operate with the Inspector in collecting air samples All waste generated in the work area shall be double bagged using asbestos labelled yellow bags and disposed of as asbestos waste Following the final cleaning phase, OHE Consultants will complete a post-abatement verification inspection of the work area and clearance air sampling to verify the effectiveness of the abatement procedures The contractor will be responsible for re-cleaning the work area in case of failure of the postabatement verification inspection and/or clearance air sampling Dispose of all waste as specified in applicable sections of the specifications document Restart all the systems present in the Work Areas which were shut down to accommodate the asbestos removal project. Ensure that the systems are operating in a manner that is similar to their operations prior to the asbestos abatement project, if applicable Return each of the areas to an as found condition, if applicable Work Area 2: Lower Level Preparation Room, Art Storage Room, Elevator Machine Room and Janitors Closet: Work in this area shall be carried out following Type 1 procedures as detailed in O. Reg. 278/05 (Sub-section 3.3) as follows: Pre-clean the work area including floors, walls, ceilings, conduits, wires, cables, duct openings, and all other equipment and items present in the work area using vacuum units equipped with HEPA filters and wetting techniques Pre-clean and remove all movable objects and items present in the Work Area Remove and dispose of any wood storage units for artwork prior to removing the vinyl floor tile The Contractor shall be responsible for providing their own temporary lighting using ground fault panels. It is the Contractor s responsibility to provide electricity as needed for the duration of the abatement activities. The level of lighting shall be acceptable to the Consultant The asbestos abatement Contractor shall allow for the removal and disposal of the asbestos-containing vinyl floor tile, 12" x 12", off-white with gray streaks, following Type 1 Operations (approximately one thousand two hundred and fifty (1,250) square feet in total).

3 Peterborough, Ontario Page 3 of Clean and protect all equipment, gauges, sprinkler systems and wiring present and passing through the work area but not scheduled for removal Clean and protect all electrical panels, sensors and all other equipment and items not scheduled for removal. Reinstate such items to an as found condition if they were removed to facilitate asbestos cleanup and removal operations Maintain the fire alarm and other life/safety systems in operation. Immediately advise the Environmental Consultant in case the systems are damaged during the execution of the work The material present in the project areas contains Chrysotile Asbestos. Half-face negative pressure respirators equipped with P-100 filter cartridges shall be worn as a minimum if the material is wetted. The Environmental Consultant may perform area and personal air monitoring to verify effectiveness of dust suppression methods and adequacy of the respirators used by the Contractor. Contractor s personnel shall co-operate with the Inspector in collecting air samples Dispose of all waste as specified in applicable sections of the specifications document. 1.3 Definitions Abatement: Procedures to control fibre release from asbestos containing building materials. Includes encapsulation, enclosure, and removal Amended Water: Water containing a wetting agent or surfactant that is added for the purpose of reducing water surface tension to allow proper wetting of asbestos material Asbestos: The term includes chrysotile, amosite, crocidolite, tremolite, anthophyllite, and actinolite, and any of these that have been chemically treated and/or altered Airlock: A system for ingress or egress without permitting air movement between a contaminated area and an uncontaminated area, consisting of two curtained doorways at least 6 feet apart Area Monitoring: Sampling of asbestos fibre concentrations within the asbestos control area and outside the asbestos control area which is representative of the airborne concentrations of asbestos fibers which may reach the breathing zone Asbestos Work/Control Area: An area where asbestos removal operations are performed which is isolated by physical boundaries to prevent the spread of asbestos dust, fibers, or debris Air Monitoring: The process of measuring the asbestos fibre content of a specific volume of air in a stated period of time Asbestos Containing Material (ACM): Any material analyzed and found to contain 0.5 percent more asbestos either alone or mixed with other fibrous or nonfibrous materials Asbestos Fibers: For this specification, asbestos fibers are those fibers 5 microns or longer having an aspect ratio of at least 3: Authorized Visitor: The building Owner or his representative, persons of any regulatory or other agency having jurisdiction over the project and the asbestos abatement Environmental Consultant or his representative Barrier: Any surface that closes up the work area to prevent the movement of fibres Curtained Doorway: A device to allow ingress or egress from one room to another while permitting minimal air movement between the rooms, constructed by placing two overlapping sheets of ripproof plastic over an existing or temporarily framed doorway, securing each along the top of the doorway, securing the vertical edge of one along one vertical side of the doorway, and securing the vertical edge of the other sheet along the opposite vertical side of the doorway. The free bottom edge of the plastic sheets shall be weighted to ensure proper closure. The plastic sheets shall over lap by no less than 1.5 meters.

4 Peterborough, Ontario Page 4 of Critical Barrier: One or more layers of plastic sealed over all openings into a regulated area or any other similarly placed physical barrier sufficient to prevent airborne asbestos in a regulated area form migrating to an adjacent area Contractor/Supervisor: An individual who supervises asbestos abatement work and has the proper qualifications and training as specified in this document Disposal: Procedures necessary to transport and deposit the asbestos contaminated material stripped and removed from the building, piping, and equipment in an approved waste disposal site in compliance with the applicable environmental regulations Demolition: The razing, removing or wrecking of any building component, assembly or system together with any associated handling operations Decontamination Area: An enclosed area adjacent and connected to the regulated area and consisting of an equipment room, shower area, and clean room, which is used for the decontamination of workers, materials, and equipment that are contaminated with asbestos Dispersion Oil Particulate (DOP) Test: A test method that uses dispersion oil particulate to challenge a HEPA filter-equipped negative pressure unit to determine its integrity and effectiveness to filter out asbestos fibres Emery 3004 a compound (a poly-alpha olefin) that may be substituted for DOP in HEPA filter testing Encapsulant: A liquid material which can be applied to asbestos containing material and which controls the possible release of asbestos fibers from the material either by creating a membrane over the surface (bridging encapsulant) or by penetrating into the material and binding its components together (penetrating encapsulant). A third type of encapsulant (removal encapsulant) is a penetrating encapsulant and is designed to be applied during the removal of asbestoscontaining materials to minimize the release of fibres Disposal Bag: A 0.15 mm 6 mil thick, leak-tight plastic bag, pre-labeled as containing asbestos waste and used for transporting asbestos waste from containment to disposal site Disturbance: Activities that disrupt the matrix of ACM, crumble or pulverize ACM, or generate visible debris from ACM Encapsulation: Procedures necessary to coat all asbestos-containing materials with an encapsulate to control the possible release of asbestos fibers into the ambient air Enclosure: All herein specified procedures necessary to complete enclosure of all asbestos containing material behind airtight, impermeable, permanent barriers Equipment Room: A contaminated area or room which is part of the worker decontamination enclosure system, with storage for contaminated clothing and equipment Friable Asbestos Material: Material that when dry can be crumbled, pulverized or powdered by hand pressure and includes material that is crumbled, pulverized or powdered Filtration System for Water: A multistage system for filtering water from the decontamination shower and wastewater. The system is usually manufactured with two filters: a primary filter and a secondary filter. The primary filter collects and retains particles that are 20 microns or larger and the secondary filter removes particles that are 5 microns or larger Glove Bag System: A portable asbestos abatement system designed for the isolation of an object from which materials containing asbestos are to be removed HEPA Filter Equipment: High efficiency particulate air filtered vacuuming equipment with a filter system capable of collecting and retaining asbestos fibers. Filters shall be capable of trapping and retaining at least percent of 0.3 micrometer diameter particles Negative Pressure Fan System: An air purifying fan system located within or outside the isolated work area, which draws air out of the work area through a HEPA filter and discharges this air directly to the exterior of the building, thus keeping the static air pressure in the work area lower

5 Peterborough, Ontario Page 5 of 66 than in adjacent areas and preventing infiltration of contaminated air from work area to adjacent areas. This system shall be equipped with an alarm to warn of system breakdown, shall maintain a minimum pressure differential of 0.02 water gauge relative to adjacent areas outside of work areas and shall be equipped with an instrument to continuously monitor and automatically record pressure differences Non-friable Asbestos Material: Material that contains asbestos in which the fibers have been locked in by a bonding agent, coating, binder, or other material so that the asbestos is well bound and will not release fibers during any appropriate use, handling, demolition, storage, transportation, processing, or disposal Negative Pressure Respirator: A respirator in which the air inside the respiratory inlet covering is negative during inhalation in relation to the air pressure of the outside atmosphere and positive during exhalation in relation to the air pressure of the outside atmosphere Powered Air Purifying Respirator (PAPR): A full-face mask into which filtered air is pumped at approximately litres per minute (4 6 cubic feet per minute). The PAPR consists of a full-face mask, a battery pack, an air pump, high efficiency filter and hoses Personal Monitoring: Sampling of asbestos fibre concentrations within the breathing zone (within 12 inches of the mouth) of an employee Personnel: Supervisors, Contractor employees, subcontractor employees Positive Pressure Respirator: A respirator that maintains a positive pressure inside the facepiece during inhalation and exhalation in relation to the atmospheric pressure Shower Room: A room between the clean room and the equipment room in the worker decontamination enclosure system, with hot and cold or warm running water and arranged for complete showering during decontamination. The shower room comprises an airlock between contaminated and clean areas Supplied-air respirator an accepted respirator and air-supply hose with a hood/helmet, a tight fitting facepiece that is supplied with compressed breathing air from a compressed breathing air system Surfactant: A chemical wetting agent added to water to improve penetration, thus reducing the quantity of water required for a given operation or area Tape-Sealed Polyethylene Sheets: Rip-proof polyethylene sheets or polyethylene sheets of type and thickness as specified, sealed with tape along the edges, around objects, over cuts and in other locations as required to provide a continuous polyethylene membrane to protect underlying surfaces from water damage and damage by sealant and to prevent the escape of asbestos fibres through the sheeting into a clean area Wet Cleaning: The process of eliminating asbestos from building surfaces and objects by using cloths, mops, or other cleaning tools dampened with water Work Decontamination Enclosure System: A decontamination system for workers, consisting of a clean room, a shower room, and an equipment room. One entrance to the clean room shall be outside of the contaminated area. One entrance to the equipment room shall be connected directly to the contaminated area Work: Includes all labour, supervision, materials and equipment required for the complete execution of the project as specified in the contract. 1.4 Work Schedule It is the responsibility of the Contractor to provide the necessary manpower and work shifts to meet the schedule as specified below: The start date for the project will be April 13, 2015 and the end date for the project will be April 24, There will be no exceptions to the schedule. If a bidding Contractor cannot meet this schedule then this Contractor shall not provide a bid.

6 Peterborough, Ontario Page 6 of The Contractor shall, at no extra cost to the owner, be responsible for the completion of work required or scheduled to be performed on weekends, holidays and after regular hours and shall be carried out as required to meet the schedule specified In all situations where the Contractor fails to meet the specified schedule, the Contractor shall pay all costs of inspection and air monitoring by the Environmental Consultant. 1.5 Submittals All submittals must be received by the Environmental Consultant or his representative before the work is allowed to commence The Contractor shall submit the following: Proof that the Contractor has made arrangement for the transport and disposal of asbestos waste. The proof shall be satisfactory to the Environmental Consultant Name of the landfill A copy of the weight scale or waste manifest/bill of lading (once received) Proof satisfactory to the Environmental Consultant that each Supervisor scheduled to work on the project has successfully completed an approved asbestos abatement course and can provide an up to date training certificate issued by a competent entity References that each and every supervisor had supervised a minimum of 7 other asbestos removal projects of similar size and scope. One supervisor shall remain on site while asbestos removal or cleanup is being carried out Copies of Insurance certificates and Workplace Safety and Insurance Board status D.O.P test results and performance data for negative air unit systems Proposed work schedule Work force expected to be present on site daily Proposed number of shifts Layouts of proposed platforms and hoardings for the Environmental Consultant s review and approval Layout of proposed waste and worker decontamination facilities and asbestos work area enclosures Proof that all workers have received Workplace Hazardous Material Information System (WHMIS) training A WHMIS information package containing documentation addressing test results, flammability and fire data and Material Safety Data Sheets (MSDSs) for products, chemicals and materials used on site during the course of the asbestos abatement project Notice of Project form issued by the Ministry of Labour Proof satisfactory to the Environmental Consultant that each worker scheduled to work on the project has successfully completed an approved asbestos abatement course and can provide an up to date training certificate issued by a competent entity Proof satisfactory to the Environmental Consultant that each worker scheduled to work on the project has been fit tested for the appropriate respirator to be used Code of practice for respiratory protection Pressure differential monitoring data to be submitted on a daily basis.

7 Peterborough, Ontario Page 7 of Quality Assurance Ensure that work progresses according to schedule Ensure that work complies with all the requirements of the applicable regulations, guidelines and manuals Ensure that no water runoff or airborne asbestos material contaminates areas outside the asbestos removal work area enclosures. The Environmental Consultant has been given authorization by the Owner to stop any work where contamination of areas outside enclosures are suspected. The Contractor shall be responsible for all costs to rectify the problem Use only skilled and qualified workers for all trades required to work on this project Only the asbestos abatement Contractor, and never the Environmental Consultant, is responsible for the following: Safety programs and precautions required by applicable regulations for the work being performed Control over the acts and omissions of the Contractor s workers, agents, subcontractors and other employees of the Contractor required to perform work on the project Control over construction techniques, methods, means or procedures. 1.7 Regulations The Contractor shall comply with all local, provincial and federal requirements relating to asbestos and other work being carried out In case of conflict among the above mentioned requirements or with these specifications, the more stringent requirements shall apply Perform work following the requirements of the various regulations in effect at the time the work is being carried out The regulations shall include, but are not limited to: Ontario Occupational Health and Safety Act Ontario Regulation 278/05, Regulation Respecting Asbestos on Construction Projects and in Building and Repair Operations Ontario Ministry of Environment Regulation 347 (as amended) for the disposal of asbestos waste made under the Environmental Protection Act Regulations respecting the Handling, Offering for Transport and Transportation of Dangerous Goods Regulations for Construction Projects Ontario Regulation 213/91 made under the Occupational Health and Safety Act WHMIS Regulations. 1.8 Supervision The Contractor shall provide a trained and qualified shift supervisor for each and every shift during which asbestos removal and clean up is being carried out. The Owner reserves the right to stop all work if this requirement is not complied with, at no additional charge to the Owner The qualification of the supervisor shall meet the requirements specified under Section 1.5 Submittals above The shift supervisor shall have the authority to make decisions and take actions with respect to production, manpower and equipment Obtain approval from the Owner of his representative before replacing supervisory personnel.

8 Peterborough, Ontario Page 8 of At the request of the Owner or his representative, the Contractor shall, without asking for explanation, replace supervisory personnel with 2 days from receiving the Owner s written request. 1.9 Notifications The Contractor shall be responsible for immediately notifying the following, orally and in writing, prior to any work on this project commencing: Ontario Ministry of Labour, Construction Health and Safety branch closest to the location of the project The land fill site which agreed to accept the waste as per the requirements of regulation 347 (as amended) The Fire Marshall, in cases were the execution of the work will result in blocking building exists or when turning off, removing or temporarily altering fire alarms Proscriptions The use of motorized lift equipment in the work area is not allowed The use of compressed air for removal or clean up of asbestos dust and debris from any surface is not allowed Smoking, eating, drinking or chewing is not allowed in the work area Unauthorized persons or persons not using proper personal protective equipment shall not be allowed to enter the work area No entry into the work area shall be permitted to any person who has facial hair growth that prevents the establishment of a proper seal between the respirator and the skin The use of torches, propane-fired heaters and other open flames shall not be permitted in the asbestos removal work area Equipment and Material Protection and Replacement Before starting the removal operations, the Contractor shall perform a survey to document existing damage in all areas where asbestos removal will be carried out or in areas where transportation of waste will take place The Contractor shall be responsible for protecting all equipment and materials within, and in the vicinity of, the work area The Contractor shall be responsible for replacing all equipment and materials that become damaged as a result of the work being carried out by the Contractor at no additional cost to the owner Worker and Visitor Protection Instruct all personnel (workers and visitors) in all aspects of work procedures and protective equipment before allowing entry into the asbestos abatement work areas A competent person (as defined by the Occupational Health and Safety Act) shall provide all the training and instructions Instructions and training shall include, but shall not be limited to, the following: Entry and exit from asbestos abatement work areas Work practices and personal hygiene The use, cleaning and care of respirators and protective clothing.

9 Peterborough, Ontario Page 9 of Protective measures and work procedures Asbestos work area entry and exit procedures shall be posted in the clean room of the decontamination unit Respiratory Protection: All personnel required to wear respirators shall be fit tested either by a qualitative or quantitative fit testing method Each worker or visitor required to enter an asbestos abatement work area shall be provided with a personally issued respirator that is: Appropriate for the work that is being carried out Acceptable to the Ministry of Labour, Occupational Health and Safety Division The worker shall be responsible for wearing a respirator that is issued by the Contractor The following criteria, as outlined in Table 1, shall be followed when selecting an appropriate respirator:

10 Peterborough, Ontario Page 10 of 66 Table 1: Respirators Column 1 Column 2 Work Category Required respirator Type 1 Operations Worker requests that the employer provide a respirator to be used by the worker, as described in paragraph 12 of section 14 Type 2 Operations Air purifying half-mask respirator with N-100, R-100 or P-100 particulate filter Work described in paragraph 1 of subsection 12 (3) One of the following: - Air purifying full-facepiece respirator with N-100, R-100 or P- 100 particulate filter - Powered air purifying respirator equipped with a tight-fitting facepiece (half or full-facepiece) and a high efficiency filter or N-100, P-100 or R-100 particulate filter - Negative pressure (demand) supplied air respirator equipped with a full-facepiece - Continuous flow supplied air respirator equipped with a tight fitting facepiece (half or full-facepiece) Work described in paragraphs 2 to 7 and 9 to 11 of subsection 12 (3) Air purifying half-mask respirator with N-100, R-100 or P-100 particulate filter Type 3 Operations Breaking, cutting, drilling, abrading, grinding, Material is not wetted One of the following: sanding or vibrating non-friable material containing - Air purifying full-facepiece respirator with N-100, R-100 or P- asbestos by means of power tools, if the tool is 100 particulate filter attached to a dust collecting device equipped with a HEPA filter as described in paragraph 8 of subsection 12 (3) Breaking, cutting, drilling, abrading, grinding, sanding or vibrating non-friable material containing Material is wetted to control spread of fibre Material is not wetted - Powered air purifying respirator equipped with a tight-fitting facepiece (half or full-facepiece) and a high efficiency filter or N-100, P-100 or R-100 particulate filter - Negative pressure (demand) supplied air respirator equipped with a full-facepiece - Continuous flow supplied air respirator equipped with a tight fitting facepiece (half or full-facepiece) Air purifying half-mask respirator with N-100, R-100 or P-100 particulate filter Pressure demand supplied air respirator equipped with a half mask

11 Peterborough, Ontario Page 11 of 66 Table 1: Respirators (continued) Column 1 Column 2 Work Category Required respirator Type 3 Operations asbestos by means of power tools, if the tool is not attached to a dust collecting device equipped with a HEPA filter as described in paragraph 5 of Material is wetted to control spread of fibre One of the following: subsection 12 (4) - Air purifying full-facepiece respirator with N-100, R-100 or P- 100 particulate filter - Powered air purifying respirator equipped with a tight-fitting facepiece (half or full-facepiece) and a high efficiency filter or N-100, P-100 or R-100 particulate filter Work with friable material containing asbestos, as described in paragraphs 1 to 4 and 6 of subsection 12 (4) Work with friable material, as described in paragraphs 1 to 4 and 6 of subsection 12 (4), that contains a type of asbestos other than chrysotile Material is not wetted Material was applied or installed by spraying, and is - Negative pressure (demand) supplied air respirator equipped with a full-facepiece - Continuous flow supplied air respirator equipped with a tight fitting facepiece (half or full-facepiece) Pressure demand supplied air respirator equipped with a full facepiece Pressure demand supplied air respirator equipped with a half mask Work with friable material, as described in wetted to control One of the following: paragraphs 1 to 4 and 6 of subsection 12 (4), that contains only chrysotile asbestos spread of fibre - Air purifying full-facepiece respirator with N-100, R-100 or P- 100 particulate filter - Powered air purifying respirator equipped with a tight-fitting facepiece (half or full-facepiece) and a high efficiency filter or N-100, P-100 or R-100 particulate filter - Negative pressure (demand) supplied air respirator equipped with a full-facepiece - Continuous flow supplied air respirator equipped with a tight fitting facepiece (half or full-facepiece) Work with friable material containing asbestos, as Material was not One of the following: described in paragraphs 1 to 4 and 6 of subsection 12 (4) applied or installed by spraying, and is wetted to control spread of fibre - Air purifying full-facepiece respirator with N-100, R-100 or P- 100 particulate filter - Powered air purifying respirator equipped with a tight-fitting facepiece (half or full-facepiece) and a high efficiency filter or N-100, P-100 or R-100 particulate filter - Negative pressure (demand) supplied air respirator equipped with a full-facepiece - Continuous flow supplied air respirator equipped with a tight fitting facepiece (half or full-facepiece)

12 Peterborough, Ontario Page 12 of Respiratory protection systems shall be certified by the National Institute for Occupational Safety and Health (NIOSH), the British Standards Institution or any other testing agency that is acceptable to the Ministry of Labour Respirator shall be stored in a clean location such as the clean room of the decontamination unit. This room can also be used for charging PAPR batteries The procedures specified by the equipment manufacturer shall be followed while using and maintaining the respirators Respirators shall be cleaned and inspected at the end of each shift. All damaged and deteriorated parts found during the inspection shall be replaced before the respirator is used again Appropriate combination cartridges shall be used if substances other than asbestos are to be handled inside the asbestos removal work area Used filters shall be tested and replaced as specified by the manufacturer or as specified below. The more stringent testing and replacement protocol shall be followed Cartridges for negative pressure respirators should be replaced every 16 hours of actual usage Cartridges for PAPRs should be replaced every 8 hours Cartridges shall be treated as asbestos waste and shall be disposed of accordingly after usage inside an asbestos removal work area Protective Clothing: The Contractor shall provide every worker and authorized visitor with full body disposable coveralls All personnel shall wear the protective coveralls before they are allowed to enter into the asbestos removal work area Coveralls shall be equipped with head covering (hood), foot covering and tight fitting cuffs at the neck, ankles and wrists The disposable coveralls shall be made up of materials that does not readily permit the penetration of asbestos fibers Disposable coveralls shall be immediately repaired (using duct tape) or replaced once torn Coveralls shall be disposed of as asbestos waste once they are worn inside an asbestos abatement area Workers are allowed to wear reusable protective clothing provided that the clothing is left in the equipment room until the end of the asbestos abatement project. The clothing shall then be disposed of as asbestos waste Safety shoes, hard hats and additional body protection equipment shall be used as necessary to meet the requirements of applicable safety regulations Inspections The asbestos abatement Environmental Consultant will be present on site to carry out quality control inspections for the entire duration of the project. The inspections will be performed inside and outside the work areas The purpose of the inspections is to ensure that the work is being carried out following the requirements and procedures outlined in the specifications documents and applicable regulations The Environmental Consultant will issue written instructions to the asbestos abatement Contractor throughout the duration of the project. The instructions will authorize the Contractor to proceed to next phase of work. The general phases of work will consist of the following: Pre-cleaning, set-up

13 Peterborough, Ontario Page 13 of 66 and preparation of the work area, removal of specified materials, clean-up of work area and tear down of containment The Contractor shall not proceed to the next phase of work without obtaining authorization form the Environmental Consultant The Environmental Consultant has been given authorization by the Owner to order a shutdown of work in case contamination of areas adjacent to controlled work areas has occurred In all non-controlled areas where it is determined by the Environmental Consultant (through visual inspection or air monitoring) that contamination has leaked, the Contractor shall be responsible to the complete isolation and cleaning of such areas under the direction of the Environmental Consultant and at no extra charge to the Owner The Environmental Consultant has been given authorization by the Owner to ensure that the Contractor adheres to specified procedures and materials and to inspect for completion and final cleanliness. Any additional work (including labour and material charges) specified by the Environmental Consultant to achieve completion of work to the level specified shall be carried out by the Contractor at no additional charge to the Owner The Contractor shall ensure that all equipment and materials to be used on the project are acceptable to the Environmental Consultant. Unacceptable materials and equipment shall be replaced by the Contractor at no additional charge to the Owner The Contractor shall be responsible for all additional inspection charges which are carried out as a result of a failure by the Contractor to meet set criteria relating to schedule, health and safety and quality Air Monitoring Air samples will be collected by the Environmental Consultant (on behalf of the owner) from the start of work until the completion of the tear down operations, both inside and/or outside the controlled work areas The objective of air monitoring is to detect defects in the containment of controlled areas and to ensure that any contamination of building spaces beyond the controlled areas is discovered and rectified immediately Any contamination of areas outside the limits of the controlled work areas (as determined by air monitoring) shall be contained and shall be thoroughly cleaned to the Environmental Consultant s satisfaction. The Contractor shall be responsible for all additional charges associated with such work Air monitoring will be carried out following procedures specified in the latest edition of the National Institute for Occupational Safety and Health (NIOSH) method 7400A. The samples will be analyzed by the Phase Contrast Microscopy (PCM) technique as specified in NIOSH method 7400A. A Fibrous Aerosol Monitor (FAM) may also be used The Contractor shall cooperate with the Environmental Consultant during air monitoring and shall: Provide workers to wear the sampling equipment for up to the duration of an entire shift Ensure that the workers exercise care and avoid damaging the Environmental Consultant s equipment Ensure that the samples and equipment are not tampered with The Contractor shall be responsible for charges associated with re-sampling due to tampering with the air samples The Contractor shall be responsible for repair or replacement charges of testing equipment that become damaged due to the actions of the Contractor forces The maximum allowable concentration of airborne fibres outside an asbestos work area is 0.05 fibres per cubic centimetre (fibre/cc).

14 Peterborough, Ontario Page 14 of PCM or FAM results equal to or greater than the specified level will indicate asbestos contamination of these perimeter areas The contaminated areas shall be isolated, contained and cleaned to the satisfaction of the Environmental Consultant The maximum allowable concentration of airborne fibres inside an asbestos work area is 2.5 fibres/cc Clearance air samples will be collected inside the work area after it is visually inspected by the Environmental Consultant, authorization is given to spray a lock-down agent and the lock-down agent is allowed to completely dry-up Air samples will be analyzed by the PCM method. The area will be considered clean and clear for public occupancy only if the fibre levels are less than 0.01 fibres/cc In case the fibre levels are equal to or greater than 0.01 fibres/cc, the Contractor shall be responsible for re-cleaning the asbestos work area and re-applying the lock-down agent. This process will have to be repeated until the fibre levels are below the specified limit The Contractor shall be responsible for all charges associated with additional air monitoring which can only be carried out by the Environmental Consultant Clearance air sampling will be carried out using aggressive sampling procedures as specified in O. Reg. 278/05, S.18(6) The exhaust from forced air equipment (such as a 1 horsepower leaf blower) is directed towards ledges, ceilings, floors, walls and other surfaces in the room before the sampling pumps are started The forced air equipment will be operated for a period of 5 minutes for every 1,000 square feet of floor space The 20 fan(s) is then located in the middle of the room, placed on slower speed and directed towards the ceiling One 20 fan will be employed for every 10,000 cubic feet of room space Waste Transport and Disposal All asbestos-containing and asbestos-contaminated materials shall be disposed of as prescribed by Ontario Regulation 347 (as amended), Waste Management Regulation, made under the Environmental Protection Act and the provincial and federal regulations for the Transportation of Dangerous Goods All wash water generated from decontamination activities shall be treated as asbestos waste and shall be disposed of accordingly All non-asbestos containing waste generated during demolition activities inside an asbestos work area shall be treated as asbestos waste Non-porous materials that can be washed and properly cleaned can be disposed of as clean waste All sharp asbestos-contaminated materials (such as hangers, T-bars, wood, etc) that could rip or damage a 6mil polyethylene waste disposal bag shall be disposed of in a sealed solid asbestos waste container The waste must be stored and transported in an enclosed, lockable waste bin Every vehicle used for the transportation of asbestos waste shall display a Class 9 Label.

15 Peterborough, Ontario Page 15 of Both sides of the vehicle used for the transportation of asbestos waste and every waste bag and container shall display the word CAUTION in letters not less than 10 cm in height and the words: CONTAINS ASBESTOS FIBRES Avoid Creating Dust Asbestos May Be Harmful to Your Health Wear Approved Protective Equipment The transport vehicle must be properly equipped to deal with asbestos waste spills. Equipment shall include, but not limited to, respiratory protective equipment, disposable protective clothing, 6 mil polyethylene bags, shovel and broom and wetting agent For asbestos waste of unknown material or an asbestos type other than Chrysotile, the words Asbestos, Blue, Product Identification Number 2212 must be displayed on every waste container For Chrysotile asbestos, the words Asbestos, White, Product Identification Number 2590 must be displayed on every waste container The Contractor shall submit to the Environmental Consultant a copy of the shipping document and weight receipt for every shipment of asbestos waste.

16 Peterborough, Ontario Page 16 of 66 PART 2 - FACILITIES AND PRODUCTS 2.1 Equipment Provide equipment that is suitable for intended use as specified by the proper standards. All equipment used on the project shall be clean and in good state of repair Airless Sprayer: Equipment used for the application of amended water to saturate asbestoscontaining materials before removal Electrical Components and Equipment: supplied by the Contractor for performance of work on this project shall meet the requirements of the Canadian Standards Association (CSA) for use as installed Electrical Power Cords: Use single length power cords. If single length will not reach work area, use waterproof connectors to connect separate lengths. Use heavy duty cords in high traffic areas or in areas where abrasion of cords is expected. Only grounded electrical cords will be allowed Ground Fault Panel: use an electrical panel that is installed by a licensed electrician and is equipped with the following: Ground fault circuit interrupts (breaker type) of sufficient capacity to supply all lights and equipment to be used in the work area Breakers shall have 5mA ground fault protection Main switch disconnect, test buttons and reset switches and circuit breaker lights Proper enclosure to prevent the penetration of moisture, dust and debris Temporary Lighting: Provide illumination as required in all work areas to perform the work safely and adequately. Illumination can be achieved by the use incandescent or fluorescent lamps. All lamps shall be protected by grounded guard cages or tempered glass enclosures Fine Atomizing Spray Nozzle: an airless sprayer nozzle that is designed to deliver no less than 1 gallon per minute of fine spray of water or lock-down agent Flexible Ducting: Tubing used for the exhaust of negative air units. The tubing is made up of plastic with metal reinforcement and is of a diameter that is equal to the exhaust port of a negative air unit Garden Sprayer: a metal or plastic pressure-can hand pump equipped with a hose and a metal wand. The pump is used to spray a fine mist of liquid on surfaces in a work area Glove Bag: The glove bag shall meet the following requirements if it will be used more than once: Shall be a Safety-T-Strip trade product with a configuration suitable to fit the work at hand Shall have an internal ziplock feature for sealing the waste at the bottom of the bag Shall be secured around the material being removed using the securing device supplied with the bag. The securing device consists of a 1 inch reusable nylon straps with a metal tightening buckle for sealing the ends of the bag Shall be made of polyvinyl chloride (10 mil) minimum thickness with integral gloves and valve ports Shall be equipped with reversible double pull zipper with protective flaps to facilitate installation and progressive movement on pipes If it will not be used more than once, the glove bag shall meet the following requirements: Shall be made of polyvinyl chloride or equivalent plastic bag with a minimum thickness of 6 mil Shall be equipped with two gloves projecting inward and valves for attaching a vacuum hose or a metal wand.

17 Peterborough, Ontario Page 17 of Shall have a pouch for storing tools and enough space to accommodate the storage of removed materials and to allow for proper sealing of the bag. The bag shall also be labelled with warning signs to identify the content of the bag HEPA Filtered Negative Air Unit: A portable air handling system which is used to create negative air pressure differential by the extracting the air directly from the work area and discharging it to the exterior of the area. The unit shall be equipped as follows: Fan, HEPA filter, pre-filters, pressure differential gauge, cabinet, high/low switch, on/off switch The fan shall have a capacity of 1500 cubic feet per minute. The fan shall be considered to have 80% of the rated of air flow unless tested and certified by a company specializing in such measurements and subject to the approval of the Environmental Consultant Each unit shall have a HEPA filter installed as a final filter in the unit. A tight seal shall be established between the filter and the filter housing through the use of a rubber gasket. Each filter shall be clearly marked with the serial number, direction of air flow, efficiency, air flow rating, name of manufacturer and resistance and shall bear UL586 label Each unit shall have an on/off switched located on the exterior of the cabinet. The unit shall also be equipped with overload protection and components such as cabinet, fan, motor, etc shall be grounded Each unit shall have a pressure differential gauge to monitor the filter loading and to indicate when the filters needs to be changed. The unit shall also have a time meter to indicate the total accumulated hours of operation Each unit shall have the following warning and safety devices: a means for preventing the unit from operating without a HEPA filter; auto shutoff system to stop the fan in case of HEPA filter failure such as rupture of the filter of blockage of air flow through the filter Provide units with pre and intermediate filters installed at the intake of the unit and secured in place with clamps or special filter housings. Two pre-filters are required: the first pre-filter shall be of the low efficiency type and shall be 98% efficient for particles 100 microns and larger; the second prefilter shall be of the medium efficiency type and shall be 95% efficient for particles down to 5 microns The cabinet of the unit shall be constructed of durable material able to withstand rough handling during removal work. The cabinet shall have wheels and shall be designed to allow access to the inside of the unit from the intake side for maintenance and replacement of filters. The unit shall be factory sealed to prevent the escape of dust and debris during transport and use HEPA Vacuum: A vacuum unit equipped with HEPA filter and designed so that all discharged air passes through the filter. Shall be equipped with all attachments, tools and fittings to facilitate the performance of the work Pressure Differential Monitoring Unit: An instrument designed to measure the difference in pressure between the interior and exterior of a work area. As a minimum, the instrument shall consist of the following: a continuous recoding wheel chart or tape; a gauge with a range from 0 to 0.1 inches water; sensor tubing and wall clamps; wall mounting devices, low limit and high limit audible alarm; and auto reset Power Washer: A piece of equipment capable of delivering an airless stream of liquid (water) at a pressure between 1200 and 2500 psi. Typically used for cleaning of work area surfaces and equipment and for saturating materials scheduled for removal before work start to reduce the creation of dust Scaffolding: Select, erect and use scaffolding in a manner that is in compliance with all applicable occupational health and safety regulations Types of scaffolding allowed consist of suspension or standing types such as cantilever, metal tube and coupler, pole or outrigger or tubular welded frame Provide non-skid surfaces and/or foot boards on all scaffolds where foot traffic is anticipated.

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work: 125 Syndicate Avenue, Thunder Bay, Ontario Page 1 of 5 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:.1 Removing asbestos-containing transite

More information

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work: Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:.1 Removing roofing materials that are suspected of containing asbestos using wet material

More information

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc.

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc. The following work procedures are specified on all full containment asbestos abatement projects that we design. A. Preliminary Air Sampling: Many buildings contain background fiber levels prior to, or

More information

Asbestos Management Program

Asbestos Management Program Oct. 10/06 Oct 10/06 1/13 Table of Contents 1 INTRODUCTION...2 2 PURPOSE...2 3 SCOPE...2 4 ROLES & RESPONSIBILITIES...2 5 INVENTORY...6 6 ACCESS CONTROL...6 7 INSPECTION...6 8 CLASSIFICATIONS OF ASBESTOS

More information

These procedures are to be followed by all persons required to perform the following work:

These procedures are to be followed by all persons required to perform the following work: These procedures are to be followed by all persons required to perform the following work: Entry into any ceiling space above which an asbestos-containing fireproofing or thermal insulation is present.

More information

T Attachment #5 Lead Abatement Specifications The Annex Exterior Roof and Soffits, 510 George Street North, Peterborough Page 1

T Attachment #5 Lead Abatement Specifications The Annex Exterior Roof and Soffits, 510 George Street North, Peterborough Page 1 T-09-15 Attachment #5 Lead Abatement Specifications The Annex Exterior Roof and Soffits, 510 George Street North, Peterborough Page 1 Section 02082 Site Work Lead Abatement PART 1 GENERAL 1.1 General Conditions

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work: 125 Syndicate Avenue Page 1 of 12 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work:.1 Removal of asbestos-containing pipe and duct insulation, as

More information

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES Project Description: Date Work Conducted: Completed by: (Name and Dept) NOTIFICATION/AWARENESS: 1.

More information

CLASS I AND II ABATEMENT PROJECT SUBMITTALS

CLASS I AND II ABATEMENT PROJECT SUBMITTALS 5.1 Pre-Work Submittals CLASS I AND II ABATEMENT PROJECT SUBMITTALS Abatement contractors shall submit the following in a bound notebook to AU or our designated representative at the mandatory pre-construction

More information

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES TY PE 2 WOR K PR OCE DUR ES These procedures are to be followed by all maintenance personnel and contractors performing the following work at KPDSB buildings.

More information

City of Winnipeg Section SEWPCC Ventilation and Misc. Upgrade ASBESTOS ABATEMENT TYPE 2 Bid Opportunity Page 1 of 6

City of Winnipeg Section SEWPCC Ventilation and Misc. Upgrade ASBESTOS ABATEMENT TYPE 2 Bid Opportunity Page 1 of 6 City of Winnipeg Section 02 82 11 SEWPCC Ventilation and Misc. Upgrade ASBESTOS ABATEMENT TYPE 2 Bid Opportunity 545-2012 Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section

More information

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 Department Title: Safety Department Page: 2 Department Title: Safety Department Page:

More information

INTERIOR RENOVATIONS FINANCE DIVISION LEAD ABATEMENT TYPE 1 OPERATION MINIMUM PRECAUTIONS PAGE 1 OF 7

INTERIOR RENOVATIONS FINANCE DIVISION LEAD ABATEMENT TYPE 1 OPERATION MINIMUM PRECAUTIONS PAGE 1 OF 7 TYPE 1 OPERATION MINIMUM PRECAUTIONS PAGE 1 OF 7 PART 1 GENERAL 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work activities which are defined as a Type 1 lead operation

More information

TYPE 3 ASBESTOS ABATEMENT UNIVERSITY OF WINDSOR BIOLOGY BUILDING LABS 204 & 206 WINDSOR, ONTARIO. Issued: March 15 th, 2010

TYPE 3 ASBESTOS ABATEMENT UNIVERSITY OF WINDSOR BIOLOGY BUILDING LABS 204 & 206 WINDSOR, ONTARIO. Issued: March 15 th, 2010 Environmental Consultants 931 Commissioners Rd East, Suite 100 London, Ontario N5Z 3H9 Tel: (519) 685-9048 Fax: (519) 685-1042 TYPE 3 ASBESTOS ABATEMENT UNIVERSITY OF WINDSOR BIOLOGY BUILDING LABS 204

More information

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f:

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f: VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA 02189 www.vertexeng.com p: 781.952.6000 f: 781.335.3543 EZRA BAKER ELEMENTARY SCHOOL/GYMNASIUM ASBESTOS ABATEMENT WORK PLAN ASBESTOS CONTAINING

More information

Section Asbestos Removal

Section Asbestos Removal Section Cover Page Section 02 82 33 2017-10-01 Use this Section to specify removal of materials containing asbestos, as listed below. Always use in conjunction with Section 02 82 01 - Asbestos Control

More information

Asbestos Management Program

Asbestos Management Program SUPERIOR-GREENSTONE DISTRICT SCHOOL BOARD Asbestos Management Program Introduction Asbestos, a designated substance, is a natural fibre commonly used in the manufacture of building materials. The use of

More information

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the City of Vancouver Invitation to Tender including all available documents,

More information

ASBESTOS ABATEMENT C.O.S. - WASTEWATER TREATMENT PLANT PAGE 1 of 10

ASBESTOS ABATEMENT C.O.S. - WASTEWATER TREATMENT PLANT PAGE 1 of 10 ASBESTOS ABATEMENT C.O.S. - WASTEWATER TREATMENT PLANT PAGE 1 of 10 1.0 GENERAL.1 SCOPE The City of Saskatoon intends and this specification covers the removal of Asbestos Containing Material from within

More information

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the Invitation to Tender including all available documents, meeting minutes,

More information

Standard Operating Procedures for the Control of Lead During Building Maintenance and Construction Activities. Type 1 Lead Operations

Standard Operating Procedures for the Control of Lead During Building Maintenance and Construction Activities. Type 1 Lead Operations Standard Operating Procedures for the Control of Lead During Building Maintenance and Construction Activities Type 1 Lead Operations Lead is a heavy metal that has and continues to be widely used in industry

More information

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION SECTION 13280 ASBESTOS CONTAINING MATERIALS REMEDIATION PART 1 GENERAL 1.1 SECTION INCLUDES A. Furnishing all labor, materials, equipment, and transportation necessary for properly and safely removing,

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations. 2. Scope The OSHA requirements and this

More information

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos?

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos? CHAPTER 34 ASBESTOS 34 ASBESTOS This chapter provides some brief information about asbestos in construction. If you encounter asbestos on the job, you will need more information. Here are the two main

More information

Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS

Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS The following procedures are presented as a guide. Comprehensive site-specific technical specifications for the removal of mould-contaminated

More information

PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I:

PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY FACILITIES AND SERVICES PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: SMALL ISOLATED AREA (less than 10sq. ft.) -- e.g. CEILING TILES AND

More information

Asbestos Management Program

Asbestos Management Program Asbestos Management Program March 20, 2006 MNarchMarch TABLE OF CONTENTS OVERVIEW.. 4 ASBESTOS CONTROL PROGRAM.. 4 OWNER RESPONSIBILITIES 4 PROGRAM SUPERVISOR S RESPONSIBLITIES... 5 WORKER S RESPONSIBILITIES....

More information

Calvin College Asbestos Operations and Maintenance Plan

Calvin College Asbestos Operations and Maintenance Plan Calvin College Asbestos Operations and Maintenance Plan INTRODUCTION Calvin College s Asbestos Operations and Maintenance Plan has three primary objectives: 1) remove existing contamination and remove/repair

More information

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 REFERENCE: ISSUE DATE: January, 1983 CHANGES: TOPIC: Asbestos INITIATED BY: Business Services DATE OF

More information

PART 1 GENERAL 1.1 General 1.2 Abatement Contractors 1.3 Site Conditions

PART 1 GENERAL 1.1 General 1.2 Abatement Contractors 1.3 Site Conditions Crestwood Secondary School Section 02 82 00 1885 Sherbrooke Street West, Peterborough, Ontario Site Conditions and Outline of Work Pinchin File Number 218575 Page 1 of 6 PART 1 GENERAL 1.1 General.1 Read

More information

"ASBESTOS AWARENESS IN THE WORKPLACE"

ASBESTOS AWARENESS IN THE WORKPLACE MAJOR PROGRAM POINTS "ASBESTOS AWARENESS IN THE WORKPLACE" Training For THE OSHA ASBESTOS STANDARD Quality Safety and Health Products, for Today...and Tomorrow Outline of Major Points Covered in the "Asbestos

More information

BASF Corporation Title: ASBESTOS HANDLING, REMOVAL AND DEMOLITION

BASF Corporation Title: ASBESTOS HANDLING, REMOVAL AND DEMOLITION Procedure No.: IH-6 Page: 1 of 16 Preparer: Owner: Approver: RECORD OF REVISIONS Date Details of Change 11/02/01 Added a Record of Revisions table. 08/14/08 Review of entire procedure. Deleted 4.3.3 and

More information

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 2 Definitions 2 Responsibilities 3 Hazard

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations.

More information

Section Asbestos Containment Procedures

Section Asbestos Containment Procedures Section Cover Page Section 02 82 05 2017-10-01 Use this Section where full containment will be required, or if a Contractor option, may be required, depending on the removal method(s) selected by the Contractor.

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

Form 9: Infection Control Preventive Measures Level 4

Form 9: Infection Control Preventive Measures Level 4 Form 9: Infection Control This form is filled out by the construction planning team or designated person(s) to identify the required preventive measures for the activity described in Form 1 Infection Control

More information

CADMIUM AWARENESS Revision Date: 04/2017

CADMIUM AWARENESS Revision Date: 04/2017 CADMIUM AWARENESS 7.1 PURPOSE 7.1.1 The purpose of this policy is to provide guidelines for safely working with cadmium. It includes provisions for training, PPE guidelines, monitoring, medical surveillance,

More information

LEAD HAZARD CONTROL PROGRAM

LEAD HAZARD CONTROL PROGRAM LEAD HAZARD CONTROL PROGRAM Supervisor s Manual Prepared by Environmental Health and Safety Services Occupational Safety Programs GLOSSARY Abatement or Deleading CFR Control Measure Encapsulation EPA HEPA

More information

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995.

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995. April 2012, rev. 00 02 8213 Asbestos Abatement 1. General 1.01 Summary of Work A. Contractor 1.02 Definitions 1. The Contractor shall provide removal and proper disposal of asbestos containing materials.

More information

ASBESTOS MANAGEMENT PROGRAM. Carleton University

ASBESTOS MANAGEMENT PROGRAM. Carleton University ASBESTOS MANAGEMENT PROGRAM Carleton University November Oct 10/06 2/25 Table of Contents 1 INTRODUCTION... 3 2 PURPOSE... 3 3 SCOPE... 3 4 ROLES & RESPONSIBILITIES... 3-7 5 INVENTORY... 7 6 ACCESS CONTROL...

More information

Adv. 3.2: Asbestos Abatement Rev

Adv. 3.2: Asbestos Abatement Rev ADVISORY NO. 3.2: ASBESTOS ABATEMENT TERMINOLOGY AND DEFINITIONS Abatement: Procedures to control fiber release from asbestos-containing materials, i.e., removal, encapsulation, or enclosure. Air Lock:

More information

In general, the management plan development process consisted of:

In general, the management plan development process consisted of: NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department

More information

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 Issued 6/1/95 Revised 11/08/2004; 3/6/06 Please direct any questions or comments about the applicability of this document to Luigi

More information

Work Plan dated February 17, Prepared by Axiom Partners, Inc. Stephen E. Minassian Massachusetts Asbestos Designer License #AD051928

Work Plan dated February 17, Prepared by Axiom Partners, Inc. Stephen E. Minassian Massachusetts Asbestos Designer License #AD051928 ABATEMENT WORK PLAN FOR EMERGENCY ASBESTOS ABATEMENT PROJECT CONSENTINO MIDDLE SCHOOL 685 WASHINGTON STREET HAVERHILL, MASSACHUSETTS Work Plan dated February 17, 2016 Prepared by Axiom Partners, Inc. Stephen

More information

Page No.: 1. Subject:

Page No.: 1. Subject: 1 1. Introduction The Environmental Health & Safety Standard Operating Procedure (SOP) for asbestos was developed by the Department of Environmental Health & Safety in accordance with the University s

More information

HIGGINSVILLE HABILITATION CENTER MISC. BUILDING RENOVATIONS STATE OF MISSOURI HIGGINSVILLE, MISSOURI SECTION ASBESTOS ABATEMENT PART 1 -GENERAL

HIGGINSVILLE HABILITATION CENTER MISC. BUILDING RENOVATIONS STATE OF MISSOURI HIGGINSVILLE, MISSOURI SECTION ASBESTOS ABATEMENT PART 1 -GENERAL HIGGINSVILLE HABILITATION CENTER MISC. BUILDING RENOVATIONS STATE OF MISSOURI HIGGINSVILLE, MISSOURI SECTION 028213 ASBESTOS ABATEMENT PART 1 -GENERAL 1.01 Description 1.02 Related Requirements 1.03 Applicable

More information

Asbestos Awareness Program

Asbestos Awareness Program Safety Manual 1 of 9 Safety Manual Sect: 1.0 Purpose 2.0 Scope Rel. Date: Last Review: This program covers Ardent policy related to asbestos, either discovered or suspected in the workplace. Ardent recognizes

More information

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS 1. DESCRIPTION OF WORK: ATTACHMENT A RFP # 024-0-2016BH ASBESTOS ABATEMENT REQUIREMENTS The work includes pre-cleaning, repair and/or removal and disposal of friable and non-friable asbestos containing

More information

ARTICLE 4: ASBESTOS CONTROL STANDARDS

ARTICLE 4: ASBESTOS CONTROL STANDARDS ARTICLE 4: ASBESTOS CONTROL STANDARDS SECTION 4.01 ASBESTOS DEFINITIONS Adopted 06/08/95 (818) Revised 02/12/98 (863), 07/13/00 (918), 09/26/02 (978), 02/27/03 (987), 03/26/09 (1148) (a) AHERA BUILDING

More information

(2) Separate provisions shall be issued on licences required for asbestos work, competence of asbestos workers and worker health examinations.

(2) Separate provisions shall be issued on licences required for asbestos work, competence of asbestos workers and worker health examinations. Translation from Finnish Legally binding only in Finnish and Swedish Ministry of Social Affairs and Health, Finland Government Decree on the Safety of Asbestos Work (798/2015) Section 1 Scope of application

More information

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL At 130 Liberty Street New York, New York Lower Manhattan Development Corporation

More information

Cooling Tower Replacement Project Section Page 1 of 23

Cooling Tower Replacement Project Section Page 1 of 23 220955 Page 1 of 23 PART 1 GENERAL 1.1 General and Related Work.1 Read this section in conjunction with all other sections so as to comply with the requirements of Division 1 and the General Conditions

More information

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts 1) Introduction Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts Triumvirate Environmental Inc. (TEI) shall perform

More information

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification SECTION 028200 - ABESTOS ABATEMENT PART 1 - GENERAL 1.1 SCOPE OF WORK A. The following asbestos-containing materials is known to be present on the First and Second Floor classrooms of the North Wing of

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager Asbestos Management Plan Program originated: 02/2000 Last updated: 6/2015 Wendel Reece University Safety Manager TABLE OF CONTENTS I. Introduction II. Purpose III. Operations and Maintenance Asbestos Related

More information

Site Specific Hazardous Material Abatement Work Plan

Site Specific Hazardous Material Abatement Work Plan Site Specific Hazardous Material Abatement Work Plan Jobsite Location: Pier 31 Building and Roof Repair Project Port of San Francisco San Francisco, California Prepared By: North Tower Environmental, Inc.

More information

INTRODUCTION TO THE PROGRAM

INTRODUCTION TO THE PROGRAM INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information

More information

Developed and Presented by: Wisconsin Healthcare Engineering Association

Developed and Presented by: Wisconsin Healthcare Engineering Association Infection Control Risk Assessment (ICRA) Developed and Presented by: Wisconsin Healthcare Engineering Association What is an ICRA? An Infection Control Risk Assessment is a tool devised to protect patients

More information

Mooney s Bay Section

Mooney s Bay Section Mooney s Bay Section 00 40 00 General Scope of Work Page 1 of 3 1.0 General 1.1 The following is a general scope of work intended to assist the Contractor in assessing the work involved for the Mooney

More information

Addendum No. 1. June 12, 2017 Renovation of Consuella Carter Music Hall Coahoma Community College

Addendum No. 1. June 12, 2017 Renovation of Consuella Carter Music Hall Coahoma Community College June 12, 2017 Renovation of Consuella Carter Music Hall Coahoma Community College Addendum No. 1 This Addendum forms part of the Contract Documents for the above referenced project. All other requirements

More information

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION The following appendix includes information and standard drawings that are diagrammatic and are used only to convey intent. Guidelines for Use of Sample

More information

McMaster University Asbestos Awareness Environmental & Occupational Health Support Services Gilmour Hall Room 304

McMaster University Asbestos Awareness Environmental & Occupational Health Support Services Gilmour Hall Room 304 The Campaign for McMaster University The Campaign for McMaster University McMaster University Asbestos Awareness Environmental & Occupational Health Support Services Gilmour Hall Room 304 The Campaign

More information

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS PART 1.0 GENERAL REQUIREMENTS.............................................. 1 1.1 Introduction.............................................................

More information

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY ASBESTOS CONTROL PROGRAM September 22, 2006 Table of Contents 1.0 Introduction... 4 2.0 Purpose and Applicability... 4 3.0 Roles and Responsibilities... 5 3.1

More information

Rowan University Asbestos Management Program

Rowan University Asbestos Management Program Rowan University Asbestos Management Program Table of Contents I. Introduction II. Regulatory Compliance III. Department Responsibilities for Asbestos A. EHS (Safety Specialist Staff) B. EHS (Asbestos

More information

Office of Environmental Health and Safety 1.0 INTRODUCTION

Office of Environmental Health and Safety 1.0 INTRODUCTION Office of Environmental Health and Safety 1.0 INTRODUCTION Silica (SiO 2) is the second most common mineral in the earth s crust and is a major component of sand, rock and mineral ores. Silica exists in

More information

NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES

NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES September 12, 2008 INTRODUCTION North Dakota Department of Transportation (NDDOT) is seeking an asbestos

More information

HEALTH AND SAFETY MANUAL

HEALTH AND SAFETY MANUAL HEALTH AND SAFETY MANUAL Title: Spray Finishing Approved by: Greg Savoy Rev. 1/108 1 Purpose/Scope: The Company is firmly committed to providing each of its employees a safe and healthy work environment.

More information

Safety Policy and Procedure

Safety Policy and Procedure Safety Policy and Procedure Policy Number 045 Authorized By: The Cianbro Companies Alan Burton Title: Asbestos Operations Effective Date: 03/25/09 Page 1 of 10 1 Status 1.1 Update of existing policy, effective

More information

SECTION POLYCHLORINATED BIPHENYLS (PCB) REMOVAL

SECTION POLYCHLORINATED BIPHENYLS (PCB) REMOVAL SECTION 18200 POLYCHLORINATED BIPHENYLS (PCB) REMOVAL PART 1 GENERAL 1.01 RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division

More information

Asbestos cement products in your home

Asbestos cement products in your home Asbestos cement products in your home What is asbestos? Asbestos is a naturally occurring fibrous crystalline mineral, found in rock formations. Three main types of asbestos have been mined in Australia,

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 30 APR 2018 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

3. Asbestos Handling Program

3. Asbestos Handling Program 1.0 Introduction 3. Asbestos Handling Program This program will establish guidelines and procedures in the operations and maintenance of asbestos containing materials at PLU to protect all employees, contractors,

More information

Rutgers Environmental Health and Safety (REHS)

Rutgers Environmental Health and Safety (REHS) Rutgers Environmental Health and Safety (REHS) Program Name: Asbestos Management Program Responsible Executive: Executive Director of REHS Adopted: Reviewed/Revised: August 2, 2018 1. Program Statement

More information

Asbestos During Brake and Clutch Service Work Self Inspection Checklist

Asbestos During Brake and Clutch Service Work Self Inspection Checklist Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Asbestos During Brake and Clutch Service Work Self Inspection Checklist Guidelines: This

More information

PIGEON DROPPINGS CLEAN UP WORK TABLE OF CONTENTS

PIGEON DROPPINGS CLEAN UP WORK TABLE OF CONTENTS PIGEON DROPPINGS CLEAN UP WORK TABLE OF CONTENTS PAGE PIGEON DROPPINGS CLEAN UP WORK... 1 1 GENERAL... 1 1.1 GENERAL CONDITIONS AND RELATED WORK... 1 1.2 DESCRIPTION OF WORK... 1 1.3 DOCUMENTS TO BE SUBMITTED...

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.10/22/08, 10/15/09 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information

Certification Number: NAT Lead Renovation, Repair and Painting Program

Certification Number: NAT Lead Renovation, Repair and Painting Program Certification Number: NAT-117534-2 Lead Renovation, Repair and Painting Program August 2018 Lead Renovation, Repair and Painting Program TABLE of CONTENTS I. Purpose II. Risk Identification III. Responsibilities

More information

March 27, 2018 Académie de la Tamise, London, ON

March 27, 2018 Académie de la Tamise, London, ON 202-138 King St. W., Chatham, ON N7M 1E3 ADDENDUM NO. 1 T 519-326-6161 www.bairdae.ca Conseil scolaire Viamonde File: Baird AE File No.: Date: Project: 18-34 17-191 March 27, 2018, London, ON The following

More information

Asbestos Management Program

Asbestos Management Program Asbestos Management Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 5/8/2018 Table of Contents 1.

More information

Glossary. Accredited Testing Laboratory

Glossary. Accredited Testing Laboratory Glossary Accredited Testing Laboratory ACM Air Monitoring An asbestos testing laboratory accredited by the National Association of Testing Authorities, Australia (NATA) or a similar accreditation authority,

More information

Asbestos Management Program. Site Function: Ecology, Health and Safety (EHS) Procedure No.: WYN Page: 1 of 13

Asbestos Management Program. Site Function: Ecology, Health and Safety (EHS) Procedure No.: WYN Page: 1 of 13 (EHS) Procedure No.: WYN032.051 Page: 1 of 13 Preparer: Owner: Approver: EHS Specialist EHS Specialist EHS Hub Manager Revision Date Revision Number 12/2003 1 New standard. 3/2012 2 5/2017 3 Revision History

More information

SECTION ASBESTOS ABATEMENT

SECTION ASBESTOS ABATEMENT SECTION 020710 ASBESTOS ABATEMENT PART1 GENERAL 1.1 SCOPE This section covers the removal of asbestos-containing materials as identified in Section 011000 - Summary of Work. Compliance with all applicable

More information

Anticipated ICR 56 Revisions. Relating to Fire/Life Safety & Other Significant Issues

Anticipated ICR 56 Revisions. Relating to Fire/Life Safety & Other Significant Issues Anticipated ICR 56 Revisions Relating to Fire/Life Safety & Other Significant Issues Introduction Anticipated Timeframe for ICR 56 Revisions ICR 56 Fire & Life Safety Issues Cleanup of uncontrolled asbestos

More information

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions.

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions. 028333 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions. B. Contract Drawings. 1.2 SUMMARY A. The lead removal work is in support

More information

FRIABLE AND NON-FRIABLE ASBESTOS REMOVAL. Provisions of the General Conditions and Special Conditions are part of this Division.

FRIABLE AND NON-FRIABLE ASBESTOS REMOVAL. Provisions of the General Conditions and Special Conditions are part of this Division. SECTION 02080 FRIABLE AND NON-FRIABLE ASBESTOS REMOVAL PART 1 - GENERAL Provisions of the General Conditions and Special Conditions are part of this Division. 1.1 SCOPE OF WORK 1. General: The work specified

More information

McMaster University Asbestos Awareness

McMaster University Asbestos Awareness McMaster University Asbestos Awareness Presented by Christopher Hurley Environmental & Occupational Health Support Services Topics Covered Properties of asbestos Uses of asbestos Health hazards of asbestos

More information

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 07 Thermal and Moisture Protection 8400 Firestopping

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 07 Thermal and Moisture Protection 8400 Firestopping 1 General 1.1 The bidding requirements, contracting requirements, and applicable parts of Division 1 - General Requirements, as listed in the Table of Contents, shall be included in and made a part of

More information

GENERIC ASBESTOS OPERATION AND MAINTENANCE (O&M) PLAN

GENERIC ASBESTOS OPERATION AND MAINTENANCE (O&M) PLAN Environmental Sciences Corporation 25 Years of Environmental Excellence National Environmental Assessment, Compliance, Industrial Hygiene, UST/AST, Construction Management and Engineering Services GENERIC

More information

BID SHEET EAST AND WEST TECHNOLOGY ASBESTOS ABATEMENT

BID SHEET EAST AND WEST TECHNOLOGY ASBESTOS ABATEMENT Renovations Asbestos Abatement BID SHEET EAST AND WEST TECHNOLOGY ASBESTOS ABATEMENT Asbestos Material Quantity Unit Price Bid Price Mud Compound Insulation 795 each Floor Tile 10,560 sf Lab Counter Tops

More information

Project Monitoring & Air Sampling

Project Monitoring & Air Sampling Project Monitoring & Air Sampling 1. Qualifications of Air Sampling Personnel. The project air sampling shall be conducted by an asbestos project air sampling technician who has been trained in the selected

More information

Read Health Canada s Tools for schools Action Kit s Introduction, Backgrounder and pages 14-3 to

Read Health Canada s Tools for schools Action Kit s Introduction, Backgrounder and pages 14-3 to DRAFT Renovation and Repair Checklist Excerpted from Tools for Schools Action Kit, Health Canada. Date: To be completed by: Facilities maintenance staff School Custodial staff Contract service providers

More information

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843)

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843) ASBESTOS ABATEMENT PLAN 1814 PRINCE STREET 2-STORY Georgetown, South Carolina Asbestos Inspections, LLC Project # 2017-48 Performed in general accordance with SCDHEC Asbestos Regulation 61.86.1 Assessment

More information

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843)

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843) ASBESTOS ABATEMENT PLAN 1814 PRINCE STREET Georgetown, South Carolina Asbestos Inspections, LLC Project # 2017-48 Performed in general accordance with SCDHEC Asbestos Regulation 61.86.1 Assessment Completed

More information

SECTION 2080 ASBESTOS ABATEMENT

SECTION 2080 ASBESTOS ABATEMENT SECTION 2080 ASBESTOS ABATEMENT PART 1 - GENERAL 1.01 SECTION INCLUDES A. Specification for the abatement of identified asbestos-containing materials (ACMs) and asbestos-containing construction materials

More information

EACO Mould Abatement Guidelines Edition 1

EACO Mould Abatement Guidelines Edition 1 Foreword This guideline has been prepared to assist building owners, constructors, contractors, subcontractors and workers who have duties under the Occupational Health and Safety Act and its Regulations

More information