Mooney s Bay Section

Size: px
Start display at page:

Download "Mooney s Bay Section"

Transcription

1 Mooney s Bay Section General Scope of Work Page 1 of General 1.1 The following is a general scope of work intended to assist the Contractor in assessing the work involved for the Mooney s Bay 2.0 Mobilization 2.1 Provide 8-foot modular construction fencing and signage as necessary to separate the Work area from the remainder of the surrounding public area. Lay-down area for materials storage to be approved by the City of Ottawa. 2.2 Provide environmental protections and abatement during the work as specified in Sections: - Section : Lead-Based Paint Test Area Precautions; - Section : Lead-Based Paint Abatement Intermediate Precautions - Section : Lead-Based Paint Abatement Maximum Precautions 3.0 Demolition 3.1 Notify the Consultant for review of the existing structure in conjunction with the Contractor prior to commencing Work. 3.2 Remove and dispose of the existing plank decking, guard rails, and any other deleterious materials to expose existing glulam beam structure and cross bracing. 4.0 Glulam Beam Coating Removal 4.1 Sample Removal Area: Clean all loose, deleterious materials including creosote and paint residue from a minimum of three 500x500mm sample areas at the inside vertical surface of the existing glulam beams. Do not remove more than 5mm thickness of the wood substrate during cleaning. Provide 72 hours notice to Consultant for review of sample cleaned area. Cleaning methods may include: - Provide One Area: Preparation using hand tools and solvent based paint removers (In conjunction with Section Intermediate Precautions); - Provide Two Areas: Preparation using sandblasting with soda, crushed glass, or crushed walnut shell (In conjunction with Section Maximum Precautions) 4.2 Upon approval of the Sample Removal Area by the City and Consultant, proceed to clean all deleterious materials using the chosen cleaning method from the exterior surfaces of the entire glulam bridge structure. Do not remove more than 5mm thickness of the wood substrate during cleaning.

2 Mooney s Bay Section General Scope of Work Page 2 of Cross Bracing Replacement 5.1 Remove and replace existing cross bracing between glulam beam members. Remove only one set of braces at a time and install new set of braces prior to removing and replacing subsequent sets. Using new pressure-treated members as per the project specifications and drawings, match the existing size, layout and fastening profile of the existing cross bracing. 6.0 New Decking and Guards 6.1 Upon completion of the glulam beam coating removal, install new dampproofing membrane to the top surface of the glulam beams. Ensure membrane terminates on the horizontal cross section of the beam and is not visible from grade after the new bridge deck is installed. 6.2 Install new pressure treated wood decking and guardrails using galvanized steel fasteners as per the project specifications and drawings. 1. Note: Build-out new stairs at the ends of the bridge generally as per the project drawings and specifications. New stairs are to be constructed of the same cross section of wood as the bridge deck. Risers and horizontal supports shall also be constructed of the same cross section of wood as the bridge deck, double-ply, set on the short edge and trimmed to match the curve of the bridge. Ensure all stair risers are the same height plus/minus 6mm. 2. Note: Provide a base price for straight sections of top and bottom rail, with joints at each post in order to match the mid-point tangent slope of the existing bridge between each post. Provide an optional price to install a curved top and bottom rail to match the curve radius of the existing bridge. 7.0 Coatings and Finishes 7.1 Optional Glulam Waterproofing Sealer: At the glulam beams, apply a 500x500mm sample area of environmentally safe, water based, breathable, high binding, colour tint-able, clear acrylic, penetrating waterproofing sealer at an interior surface of the beam for review and testing by the Consultant and the City. Provide optional colourant to be selected by the City from standard colour options. Upon approval of the test area, apply the waterproofing sealer to the entire exposed exterior surfaces of the glulam beams as per the project specifications and manufacturer s instructions. 7.2 Pressure Treated Lumber Waterproofing Sealer: After installation of new wood components, allow minimum 8 months time to pass (3 seasons) prior to installing any coatings or finishes to the pressure treated lumber. Apply a new environmentally safe, water based, breathable, high binding, colour tint-able, clear

3 Mooney s Bay Section General Scope of Work Page 3 of 3 acrylic, penetrating waterproofing sealer to all pressure-treated wood components of the South Bridge as per the project specifications, drawings, and manufacturer s instructions. This includes all posts, pickets, rails, and decking. Provide optional colourant to be selected by the City from standard colour options. 7.3 Bridge Deck Anti-Slip Coating: After installation of waterproofing sealer at the bridge deck, apply a new environmentally safe, non-flammable, non-hazardous, waterborne, acrylic based, quartz, non-cementitious, anti-slip coating that is compatible with the waterproofing sealer. Provide optional colourant to be selected by the City from standard colour options. Apply the anti-slip coating across all pedestrian surfaces as per the project specifications, drawings and manufacturer s instructions. END OF SECTION

4 Mooney s Bay Section Carpentry and Wood Treatments Page 1 of 5 PART 1 - GENERAL 1.1 SECTION INCLUDES.1 Installation of wood members in accordance with specified materials, condition requirements and procedures. 1.2 REFERENCES.1 Canadian Standards Association (CSA International).1 CSA B111-[74(R1998)], Wire Nails, Spikes and Staples..2 CAN/CSA-O80 Series-[08], Wood Preservation..2 National Evaluation Reports (US):.1 National Evaluation Report (NER): Report No. NER-628 Preservative Treated Wood.3 American Wood-Preservers Association (AWPA).1 AWPA.M2-[07], Wood Treatment..4 ASTM International (ASTM).1 ASTM F-1677, ASTM F-1679, Coefficient of Friction Test (Anti-Skid Test). 1.3 QUALITY ASSURANCE.1 Contractors undertaking work in this section are required to be skilled craftsmen and to have a minimum of 5 years of experience in this field..2 Lumber by grade stamp of an agency certified by Canadian Lumber Standards Accreditation Board. 1.4 STORAGE AND PROTECTION 1.5 WASTE MANAGEMENT AND DISPOSAL.1 Deliver, handle, store and protect materials in a clean, dry environment. Protect materials from increased moisture levels..1 Separate and recycle waste materials to the maximum extent economically possible..2 Do not burn scrap at the project site..3 Place materials defined as hazardous or toxic waste in designated containers..4 Seal and store emptied containers safely away

5 Mooney s Bay Section Carpentry and Wood Treatments Page 2 of 5 PART 2 - PRODUCTS from children for disposal..5 Dispose of surplus chemical and finishing materials in accordance with federal, provincial and municipal regulations. 2.1 MATERIALS.1 All New Lumber: Softwood, S4S, moisture content S-Dry graded, micronized copper pressure treated and stamped in accordance with the following standards:.1 CSA NLGA Standard Grading Rules for Canadian Lumber..3 Micronized copper pressure treatment to NER Sized as required to match project drawings..2 Miscellaneous fasteners:.1 Spikes and Deck Screws: to CSA B111 flat head, round shank, diamond point mm hot dipped galvanized..2 Deck Screws: to CSA B111 flat head, hot dipped galvanized, sized as shown on project drawings..3 Bolts: 12.5mm diameter, hot dipped galvanized, complete with nuts and washers..3 Sealers/Coatings:.1 Waterproofing Sealers: Acrylic emulsion waterproofing sealer, 10% solids by weight. Provide optional water-based colourants for approval and selection by City. Approved Products:.1 #5990 Excel Waterproofing Sealer by GH International;.2 Or approved equivalent..2 Anti-Slip Coating: Acrylic based, quartz, non-cementitious, anti-slip coating to ASTM F-1677 and ASTM F Provide optional acrylic enamel paint additive for coulourants

6 Mooney s Bay Section Carpentry and Wood Treatments Page 3 of 5 PART 3 - EXECUTION as per manufacturer s recommendation for approval of City. Approved Products:.1 #5551 Excel Anti-Slip Coating by GH International;.2 Or approved equivalent. 3.1 ACCEPTABLE INSTALLERS.1 Work to be executed by skilled craftsmen trained in this field, according to best practice. 3.2 EXAMINATION.1 Stop work and report immediately to Departmental Representative evidence of structural deficiencies, unacceptable conditions, fungal activity or insect infestation not described on drawings which may affect the scope of the work and durability of the finished product. 3.3 PREPARATION.1 Remove all existing wood decking, wood guards, and other deleterious materials to fully expose glulam beams and cross bracing..2 Sample Glulam Beam Coating Removal: Clean all loose, deleterious materials including creosote and paint residue from a minimum of three 500x500mm sample areas at the inside vertical surface of the existing glulam beams. Employ different cleaning methods at each sample area. Cleaning methods may include: Provide One Sample Area: Use hand tools to scrape away all deleterious materials; Provide Two Sample Areas: Sandblasting using either soda, crushed glass, or crushed walnut shell; Or approved equivalent. Provide 72 hours notice to Consultant for review of sample cleaned area. Upon approval by the City and Consultant, proceed to clean all deleterious materials using the chosen cleaning method from the exterior surfaces of the entire glulam bridge structure. Do not remove more than 5mm thickness of the wood substrate during cleaning.

7 Mooney s Bay Section Carpentry and Wood Treatments Page 4 of CONSTRUCTION.1 Remove and replace existing cross bracing between glulam beam members. Remove only one set of braces at a time and install new set of braces prior to removing and replacing subsequent sets. Match the existing size, layout and fastening profile of the existing cross bracing. Using new pressure-treated members as per the project specifications and drawings.2 Install new self-adhering, damp-proofing membrane on the top surface of the glulam beams as per the Drawings. Submit material specifications for damp-proofing to Consultant for review and approval prior to installation..3 Install the new wood bridge deck, vertical posts, rails and pickets as per the project drawings. All wood products to be micronized pressure treated (pressure treatment finish colour natural brown) as specified..4 Note: Build-out new stairs at the ends of the bridge generally as per the project drawings and as follows: New stairs are to be constructed of the same cross section of wood as the bridge deck. Risers and horizontal supports shall also be constructed of the same cross section of wood as the bridge deck, double-ply, set on small edge and trimmed to match the curve of the existing glulam beams. Ensure all stair risers are the same height plus/minus 6mm. Ensure the run of the stairs remains within plus/minus 50mm between the bottom step and the top step..4 General:.1 Fit corner joints and intersecting members accurately..2 Contractor to confirm all dimensions on site. Job dimensions, where applicable are to govern size of fabricated units.

8 Mooney s Bay Section Carpentry and Wood Treatments Page 5 of Wood Treatment.1 Waterproofing Sealer at Glulam Beams: Apply the waterproofing sealer to a 500x500mm sample area of the glulam beam for review and testing by the Consultant and the City. Upon approval of the test area, apply the waterproofing sealer the entire exposed exterior surfaces of the glulam beams..2 Schedule: All additional wood treatments specified below shall be carried out after a specified seasoning time period: - Minimum: 8 months - Maximum: 12 months -.3 Waterproofing Sealer: Apply a waterproofing sealer to all pressure treated wood members as per the manufacturer s instructions..4 Bridge Deck Anti-Slip Coating: Apply a non-slip coating across all pedestrian surfaces, as per the manufacturer s instructions. END OF SECTION

9 Mooney s Bay Section LEAD - BASED PAINT TEST AREA PRECAUTIONS Page 1 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following Work:.1 Performing Sample Removal Area: Cleaning all loose, deleterious materials including creosote and paint residue from a minimum of three 500x500mm sample areas at the inside vertical surface of the existing glulam beams. Cleaning methods may include: Sandblasting using either soda, crushed glass, or crushed walnut shell; or brush-cleaning/scraping using hand tools. 1.2 SECTION INCLUDES.1 Requirements and procedures for abatement of lead based paints modified procedures for test sample areas. 1.3 RELATED SECTIONS.1 Ontario Ministry of Labour Guideline Lead on Construction Projects.2 Lead-based paint abatement Intermediate Precautions ( ).3 Lead-based paint abatement Maximum Precautions ( ) 1.4 DEFINITIONS 1.5 REFERENCES.1 Ontario Ministry of Labour Guideline Lead on Construction Projects.2 Health Canada.1 Workplace Hazardous Materials Information System (WHMIS), Material Safety Data Sheets (MSDS)..3 Human Resources and Social Development Canada (HRSDC).1 Canada Labour Code Part II, - SOR Occupational Health and Safety Regulations..4 Transport Canada (TC).1 Transportation of Dangerous Goods Act, 1992 (TDGA). 1.6 DEFINITIONS.1 HEPA vacuum: High Efficiency Particulate Air filtered vacuum equipment with filter system capable of collecting and retaining fibres greater than 0.3 microns in any direction at 99.97% efficiency..2 Authorized Visitors: Owner, Departmental Representative, Engineer, Consultant or designated representatives and representatives of regulatory agencies.

10 Mooney s Bay Section LEAD - BASED PAINT TEST AREA PRECAUTIONS Page 2.3 Occupied Area: work site that is outside Work Area..4 Sprayer: garden reservoir type sprayer or airless spray equipment capable of producing mist or fine spray. Must be appropriate capacity for scope of work..5 Airlock: ingress or egress system, without permitting air movement between contaminated area and uncontaminated area. Consisting of two curtained doorways at least 2 m apart..6 Curtained doorway: arrangement of closures to allow ingress and egress from one room to another. Typically constructed as follows:.1 Place two overlapping polyethylene sheets over existing or temporarily framed doorway, securing each along top of doorway, securing vertical edge of one sheet along one vertical side of doorway, and secure other sheet along opposite vertical side of doorway..2 Reinforce free edges of polyethylene with duct tape and add weight to bottom edge to ensure proper closing..3 Overlap each polyethylene sheet at openings 1.5 m on each side..7 Action level: employee exposure, without regard to usage of respirators, to an airborne concentration of lead of 50 micrograms per cubic meter of air calculated as 8 hour timeweighted average (TWA). Intermediate precautions for lead abatement are based on airborne lead concentrations greater than 0.05 milligrams per cubic meter of air within Work Area..8 Competent person: individuals capable of identifying existing lead hazards in workplace and taking corrective measures to eliminate them..9 Lead in Dust: wipe sampling on vertical and/or horizontal surfaces, dust and debris is considered to be lead contaminated if it contains more than 40 micrograms of lead in dust per square foot. 1.7 SUBMITTALS.1 Provide proof satisfactory to Consultant that suitable arrangements have been made to dispose of lead based paint waste in accordance with requirements of authority having jurisdiction..2 Quality Control:.1 Provide proof satisfactory to Consultant that employees have had instruction on hazards of lead exposure, respirator use, dress, entry and exit from Work Area, and aspects of work procedures and protective measures..2 Provide proof that supervisory personnel have attended lead abatement course, of not less than two days duration, approved by Consultant. Minimum of one supervisor for every ten workers. 1.8 QUALITY ASSURANCE.1 Regulatory Requirements: comply with Provincial and local requirements pertaining to lead paint, in case of conflict among those requirements or with these specifications more stringent requirement applies. Comply with regulations in effect at time work is performed..2 Health and Safety:

11 Mooney s Bay Section LEAD - BASED PAINT TEST AREA PRECAUTIONS Page 3.1 Do construction occupational health and safety in accordance with the Ontario Occupational Health and Safety Act..2 Safety Requirements: worker and visitor protection..1 Protective equipment and clothing to be worn by workers and visitors in Work Area includes:.1 NIOSH approved half-face respirator and equipped with P-100 filter cartridges. Provide sufficient filters so workers can install new filters following disposal of used filters and before re-entering contaminated areas..2 Disposable type protective clothing that does not readily retain or permit skin contamination, consisting of full body covering including head covering with snug fitting cuffs at wrists, ankles, and neck..2 Requirements for workers:.1 Remove street clothes outside Work Area and put on respirator with new filters or reusable filters, clean coveralls and head covers before entering Work Area. Store street clothes, uncontaminated footwear, towels, and similar uncontaminated articles outside Work Area..2 Remove gross contamination from clothing before leaving Work Area. Place contaminated work suits in receptacles for disposal with other lead - contaminated materials. Upon completion of lead abatement, dispose of footwear as contaminated waste or clean thoroughly inside and out using soap and water before removing from Work Area..3 Eating, drinking, chewing, and smoking are not permitted in Work Area..4 Ensure workers wash hands and face when leaving Work Area..5 Provide and post the procedures described in this Section, in both official languages..6 Ensure no person required to enter Work Area has facial hair that affects seal between respirator and face..7 Visitor Protection: 1.9 WASTE MANAGEMENT AND DISPOSAL.1 Provide protective clothing and approved respirators to Authorized Visitors to Work Areas..2 Instruct Authorized Visitors in use of protective clothing, respirators and procedures..3 Instruct Authorized Visitors in proper procedures to be followed in entering into and exiting from Work Area..1 Disposal of lead waste generated by removal activities must comply with Provincial regulations. Dispose of lead waste in sealed double thickness 6 ml bags or leak proof drums. Label containers with appropriate warning labels EXISTING CONDITIONS.1 Reports and information pertaining to lead based paint to be handled, removed, or otherwise disturbed and disposed of during this Project are available upon request.

12 Mooney s Bay Section LEAD - BASED PAINT TEST AREA PRECAUTIONS Page 4 Part 2 Products 2.1 MATERIALS.1 Polyethylene: 0.15mm unless otherwise specified; in sheet size to minimize joints..2 FR polyethylene: 0.15mm woven fibre reinforced fabric bonded both sides with polyethylene..3 Tape: fibreglass - reinforced duct tape suitable for sealing polyethylene under dry conditions and wet conditions using amended water..4 Slow - drying sealer: non-staining, clear, water - dispersible type that remains tacky on surface for at least 8 hours and designed for trapping residual lead paint residue. Part 3 Execution 3.1 SUPERVISION.1 Approved Supervisor must remain in the vicinity of Work Area during disturbance, removal, or other handling of lead based paints. 3.2 PREPARATION.1 Work Area Modified Proceedure:.1 Cover ground surfaces in work area with two layers of polyethylene drop sheets..2 Affix one layer of polyethylene drop sheet to existing bridge on the three exposed sides. Tape and seal to floor or ground surface to extent practicable..2 Separation of Occupied Areas.1 Barriers between Occupied Area and general public area to be constructed as follows:.1 Caution tape 5 m in circumference from work area..3 Maintenance of Enclosures:.1 Maintain area in clean condition..2 Ensure barriers and polyethylene linings are effectively sealed and taped. Repair damaged barriers and remedy defects immediately. 3.3 LEAD - BASED PAINT ABATEMENT.1 Remove lead based paint in small sections and pack as it is being removed in sealable 0.15mm plastic bags and place in labelled containers for transport..2 After completion of stripping work, clean work areas using HEPA vacuum. If not practicable, use wet cleaning method. Do not use methods that raise dust, such as dry sweeping, or vacuuming using other than HEPA vacuum. 3.4 FINAL CLEANUP.1 Following specified cleaning procedures, proceed with final cleanup.

13 Mooney s Bay Section LEAD - BASED PAINT TEST AREA PRECAUTIONS Page 5.2 Remove polyethylene sheet by rolling it away from walls to centre of work area. Vacuum visible lead containing particles observed during cleanup, immediately, using HEPA vacuum equipment..3 Place polyethylene seals, tape, cleaning material, clothing, and other contaminated waste in plastic bags and sealed labelled waste containers for transport..4 Clean-up Work Areas, and other contaminated enclosures..5 Clean-up sealed waste containers and equipment used in Work and remove from work areas..6 Conduct final check to ensure no dust or debris remains on surfaces as result of dismantling operations. 3.5 RE-ESTABLISHMENT OF OBJECTS AND SYSTEMS.1 Repair or replace objects damaged in course of work to their original state or better, as directed by Consultant. END OF SECTION

14 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page 1 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following Work:.1 Removal of lead based paint from bridge by scraping or sanding using non-powered hand tools..2 Manual demolition of lead-painted bridge components by striking wall with sledgehammer or similar tool. 1.2 SECTION INCLUDES.1 Requirements and procedures for abatement of lead based paints. 1.3 RELATED SECTIONS.1 Ontario Ministry of Labour Guideline Lead on Construction Projects.2 Lead-based paint abatement Maximum Precautions ( ) 1.4 DEFINITIONS 1.5 REFERENCES.1 Ontario Ministry of Labour Guideline Lead on Construction Projects.2 Health Canada.1 Workplace Hazardous Materials Information System (WHMIS), Material Safety Data Sheets (MSDS)..3 Human Resources and Social Development Canada (HRSDC).1 Canada Labour Code Part II, - SOR Occupational Health and Safety Regulations..4 Transport Canada (TC).1 Transportation of Dangerous Goods Act, 1992 (TDGA). 1.6 DEFINITIONS.1 HEPA vacuum: High Efficiency Particulate Air filtered vacuum equipment with filter system capable of collecting and retaining fibres greater than 0.3 microns in any direction at 99.97% efficiency..2 Authorized Visitors: Owner, Departmental Representative, Engineer, Consultant or designated representatives and representatives of regulatory agencies..3 Occupied Area: work site that is outside Work Area..4 Sprayer: garden reservoir type sprayer or airless spray equipment capable of producing mist or fine spray. Must be appropriate capacity for scope of work.

15 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page 2.5 Airlock: ingress or egress system, without permitting air movement between contaminated area and uncontaminated area. Consisting of two curtained doorways at least 2 m apart..6 Curtained doorway: arrangement of closures to allow ingress and egress from one room to another. Typically constructed as follows:.1 Place two overlapping polyethylene sheets over existing or temporarily framed doorway, securing each along top of doorway, securing vertical edge of one sheet along one vertical side of doorway, and secure other sheet along opposite vertical side of doorway..2 Reinforce free edges of polyethylene with duct tape and add weight to bottom edge to ensure proper closing..3 Overlap each polyethylene sheet at openings 1.5 m on each side..7 Action level: employee exposure, without regard to usage of respirators, to an airborne concentration of lead of 50 micrograms per cubic meter of air calculated as 8 hour timeweighted average (TWA). Intermediate precautions for lead abatement are based on airborne lead concentrations greater than 0.05 milligrams per cubic meter of air within Work Area..8 Competent person: individuals capable of identifying existing lead hazards in workplace and taking corrective measures to eliminate them..9 Lead in Dust: wipe sampling on vertical and/or horizontal surfaces, dust and debris is considered to be lead contaminated if it contains more than 40 micrograms of lead in dust per square foot. 1.7 SUBMITTALS.1 Provide proof satisfactory to Consultant that suitable arrangements have been made to dispose of lead based paint waste in accordance with requirements of authority having jurisdiction..2 Quality Control:.1 Provide proof satisfactory to Consultant that employees have had instruction on hazards of lead exposure, respirator use, dress, entry and exit from Work Area, and aspects of work procedures and protective measures..2 Provide proof that supervisory personnel have attended lead abatement course, of not less than two days duration, approved by Consultant. Minimum of one supervisor for every ten workers. 1.8 QUALITY ASSURANCE.1 Regulatory Requirements: comply with Provincial and local requirements pertaining to lead paint, in case of conflict among those requirements or with these specifications more stringent requirement applies. Comply with regulations in effect at time work is performed..2 Health and Safety:.1 Do construction occupational health and safety in accordance with the Ontario Occupational Health and Safety Act..2 Safety Requirements: worker and visitor protection..1 Protective equipment and clothing to be worn by workers and visitors in Work Area includes:

16 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page 3.1 NIOSH approved half-face respirator and equipped with P-100 filter cartridges. Provide sufficient filters so workers can install new filters following disposal of used filters and before re-entering contaminated areas..2 Disposable type protective clothing that does not readily retain or permit skin contamination, consisting of full body covering including head covering with snug fitting cuffs at wrists, ankles, and neck..2 Requirements for workers:.1 Remove street clothes in clean change room and put on respirator with new filters or reusable filters, clean coveralls and head covers before entering Work Area. Store street clothes, uncontaminated footwear, towels, and similar uncontaminated articles in clean change room..2 Remove gross contamination from clothing before leaving work area. Place contaminated work suits in receptacles for disposal with other lead - contaminated materials. Leave reusable items except respirator in Equipment and Access Room. When not in use in Work Area, store work footwear in Equipment and Access Room. Upon completion of lead abatement, dispose of footwear as contaminated waste or clean thoroughly inside and out using soap and water before removing from Work Area or from Equipment and Access Room..3 Enter unloading room from outside dressed in clean coveralls to remove waste containers and equipment from Holding Room of Container and Equipment Decontamination Enclosure system. Workers not to use this system as means to leave or enter work area..3 Eating, drinking, chewing, and smoking are not permitted in Work Area..4 Ensure workers are fully protected with respirators and protective clothing during preparation of system of enclosures prior to commencing actual lead abatement..5 Ensure workers wash hands and face when leaving Work Area..6 Provide and post in Clean Change Room and in Equipment and Access Room the procedures described in this Section, in both official languages..7 Ensure no person required to enter Work Area has facial hair that affects seal between respirator and face..8 Visitor Protection: 1.9 WASTE MANAGEMENT AND DISPOSAL.1 Provide protective clothing and approved respirators to Authorized Visitors to Work Areas..2 Instruct Authorized Visitors in use of protective clothing, respirators and procedures..3 Instruct Authorized Visitors in proper procedures to be followed in entering into and exiting from Work Area..1 Disposal of lead waste generated by removal activities must comply with Provincial regulations. Dispose of lead waste in sealed double thickness 6 ml bags or leak proof drums. Label containers with appropriate warning labels.

17 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page EXISTING CONDITIONS.1 Reports and information pertaining to lead based paint to be handled, removed, or otherwise disturbed and disposed of during this Project are available upon request SCHEDULING.1 Provide Consultant copy of notifications prior to start of Work..2 Hours of Work: perform work involving lead removal during normal working hours. Part 2 Products 2.1 MATERIALS.1 Polyethylene: 0.15mm unless otherwise specified; in sheet size to minimize joints..2 FR polyethylene: 0.15mm woven fibre reinforced fabric bonded both sides with polyethylene..3 Tape: fibreglass - reinforced duct tape suitable for sealing polyethylene under dry conditions and wet conditions using amended water..4 Slow - drying sealer: non-staining, clear, water - dispersible type that remains tacky on surface for at least 8 hours and designed for trapping residual lead paint residue. Part 3 Execution 3.1 SUPERVISION.1 Approved Supervisor must remain within Work Area during disturbance, removal, or other handling of lead based paints. 3.2 PREPARATION.1 Work Area:.1 Clean work areas using HEPA vacuum. If not practicable, use wet cleaning method. Do not use methods that raise dust, such as dry sweeping, or vacuuming using other than HEPA vacuum..2 Cover ground surfaces in work area with two layers of polyethylene drop sheets..3 Build airlocks at entrances and exits from work areas to ensure work areas are always closed off by one curtained doorway when workers enter or exit..4 At point of access to work areas install warning signs in both official languages in upper case "Helvetica Medium" letters reading as follows where number in parentheses indicates font size to be used:.1 CAUTION LEAD HAZARD AREA (25 mm)..2 NO UNAUTHORIZED ENTRY (19 mm)..3 WEAR ASSIGNED PROTECTIVE EQUIPMENT AND RESPIRATOR (19 mm).

18 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page 5.4 BREATHING LEAD CONTAMINATED DUST CAUSES SERIOUS BODILY HARM (7 mm)..5 Where water application is required for wetting lead containing materials, provide temporary water supply by use of appropriately sized hoses for application of water as required..2 Worker Decontamination Enclosure System:.1 Worker Decontamination Enclosure System includes Equipment and Access Room and Clean Room, as follows:.1 Equipment and Access Room: construct between exit and work areas, with two curtained doorways, one to the rest of suite, and one to work area. Install waste receptor and storage facilities for workers' shoes and protective clothing to be re-worn in work areas. Build large enough to accommodate specified facilities, equipment needed, and at least one worker allowing sufficient space to change comfortably..2 Clean Room: construct with curtained doorway to outside of enclosures. Provide lockers or hangers and hooks for workers' street clothes and personal belongings. Provide storage for clean protective clothing and respiratory equipment. Install mirror to permit workers to fit respiratory equipment properly..3 Separation of Work Areas from Occupied Areas.1 Barriers between Work Area and occupied area to be constructed as follows:.1 Construct barrier fence around the lead removal work area. Provide sufficient room for equipment and workers based on the terrain. Cover with polyethylene sheeting and seal with duct tape..4 Maintenance of Enclosures:.1 Maintain enclosures in clean condition..2 Ensure barriers and polyethylene linings are effectively sealed and taped. Repair damaged barriers and remedy defects immediately..3 Visually inspect enclosures at beginning of each work day. 3.3 LEAD - BASED PAINT ABATEMENT.1 Removal of lead based paint to be performed by scraping or sanding using non-powered hand tools, or manual demolition bridge components by striking a wall with sledgehammer or similar tool..2 Remove lead based paint in small sections and pack as it is being removed in sealable 0.15mm plastic bags and place in labelled containers for transport..3 Seal filled containers. Clean external surfaces thoroughly by wet sponging. Remove from immediate working area to Staging Area. Clean external surfaces thoroughly again by wet sponging before moving containers to decontamination Washroom. Wash containers thoroughly in decontamination Washroom, and store in Holding Room pending removal to Unloading Room and outside. Ensure containers are removed from Holding Room by workers who have entered from uncontaminated areas dressed in clean coveralls.

19 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page 6.4 After completion of stripping work, wire brush and wet sponge surface from which lead based paint has been removed to remove visible material. During this work keep surfaces wet..5 After wire brushing and wet sponging to remove visible lead based paint, and after encapsulating lead containing material impossible to remove, wet clean work area including equipment and access room, and equipment used in process..6 Wet clean work area and equipment and access room. 3.4 INSPECTION.1 Perform inspection to confirm compliance with specification and governing authority requirements. Deviations from these requirements not approved in writing by Consultant will result in work stoppage, at no cost to Owner..2 Consultant will inspect work for:.1 Adherence to specific procedures and materials..2 Final cleanliness and completion..3 No additional costs will be allowed by Contractor for additional labour or materials required to provide specified performance level..3 When lead dust leakage from Work Area occurs Consultant may order Work shutdown..1 No additional costs will be allowed by Contractor for additional labour or materials required to provide specified performance level. 3.5 FINAL CLEANUP.1 Following specified cleaning procedures, proceed with final cleanup..2 Remove polyethylene sheet by rolling it away from walls to centre of work area. Vacuum visible lead containing particles observed during cleanup, immediately, using HEPA vacuum equipment..3 Place polyethylene seals, tape, cleaning material, clothing, and other contaminated waste in plastic bags and sealed labelled waste containers for transport..4 Clean-up Work Areas, Equipment and Access Room, and other contaminated enclosures..5 Clean-up sealed waste containers and equipment used in Work and remove from work areas, via Container and Equipment Decontamination Enclosure System, at appropriate time in cleaning sequence..6 Conduct final check to ensure no dust or debris remains on surfaces as result of dismantling operations. 3.6 RE-ESTABLISHMENT OF OBJECTS AND SYSTEMS.1 Repair or replace objects damaged in course of work to their original state or better, as directed by Consultant.

20 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - INTERMEDIATE PRECAUTIONS Page 7 END OF SECTION

21 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page 1 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following Work:.1 Abrasive blasting of lead based paint on bridge. 1.2 RELATED SECTIONS.1 Ontario Ministry of Labour Guideline Lead on Construction Projects.2 Lead-based paint abatement Intermediate Precautions ( ) 1.3 REFERENCES.1 Ontario Ministry of Labour Guideline Lead on Construction Projects.2 Health Canada.1 Workplace Hazardous Materials Information System (WHMIS), Material Safety Data Sheets (MSDS)..3 Human Resources and Social Development Canada (HRSDC).1 Canada Labour Code Part II, - SOR Occupational Health and Safety Regulations..4 Transport Canada (TC).1 Transportation of Dangerous Goods Act, 1992 (TDGA). 1.4 DEFINITIONS.1 HEPA vacuum: High Efficiency Particulate Air filtered vacuum equipment with a filter system capable of collecting and retaining fibres greater than 0.3 microns in any direction at 99.97% efficiency..2 Authorized Visitors: Owner, Departmental Representative, Engineer, Consultant, or designated representatives of regulatory agencies..3 Occupied Area: area of building or work site outside Work Area..4 Dioctyl Phthalate (DOP) Test: testing method used to evaluate particle penetration and air flow resistance properties of filtration materials - HEPA filter leak test..5 Sprayer: garden reservoir type sprayer or airless spray equipment capable of producing mist or fine spray. Appropriate capacity for scope of work..6 Airlock: ingress or egress system without permitting air movement between contaminated area and uncontaminated area. Consisting of two curtained doorways at least 2 m apart.

22 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page 2.7 Curtained doorway: arrangement of closures to allow ingress and egress from one room to another while permitting minimal air movement between rooms, typically constructed as follows:.1 Place two overlapping sheets of polyethylene over existing or temporarily framed doorway, secure each along top of doorway, secure vertical edge of one sheet along one vertical side of doorway, and secure vertical edge of other sheet along opposite vertical side of doorway..2 Reinforce free edges of polyethylene with duct tape and add weight to bottom edge to ensure proper closing..3 Overlap each polyethylene sheet at openings 1.5 m on each side..8 Action level: employee exposure, without regard to usage of respirators, to an airborne concentration of lead of 50 micrograms per cubic metre of air calculated as an 8-hour timeweighted average (TWA). Maximum precautions for lead abatement are based on airborne lead concentrations greater than 1.25 milligrams per cubic meter of air within Work Area..9 Competent person: Individuals capable of identifying existing lead hazards in workplace and taking corrective measures to eliminate them..10 Lead in Dust: wipe sampling on the vertical and/or horizontal surfaces, dust and debris is considered to be lead contaminated if it contains more than 40 micrograms of lead in dust per square foot..11 Negative Air Pressure Machine: extracts air directly from work area and filters extracted air through a HEPA filter, discharge air to exterior of building. 1.5 SUBMITTALS.1 Maintain pressure differential of 5 to 7 Pa relative to adjacent areas outside of work areas. Machine to be equipped with instrument to continuously monitor pressure differentials..1 Provide proof satisfactory to Consultant that suitable arrangements have been made to dispose of lead based paint waste in accordance with requirements of authority having jurisdiction..2 Quality Control:.1 Provide proof satisfactory to Consultant that employees have had instruction on hazards of lead exposure, respirator use, dress, entry and exit from Work Area, and aspects of work procedures and protective measures..2 Provide proof that supervisory personnel have attended lead abatement course, of not less than two days duration, approved by Consultant. Minimum of one supervisor for every ten workers. 1.6 QUALITY ASSURANCE.1 Regulatory Requirements: comply with Federal, Provincial/Territorial and local requirements pertaining to lead, in case of conflict among those requirements or with these specifications the more stringent requirement applies. Comply with regulations in effect at time work is performed..2 Health and Safety:

23 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page 3.1 Do construction occupational health and safety in accordance with the Ontario Occupational Health and Safety Act..2 Safety Requirements: worker and visitor protection..1 Protective equipment and clothing to be worn by workers while in Lead Work Area includes:.1 Abrasive blasting of lead paint: NIOSH approved and equipped with filter cartridges with assigned protection factor of Suitable for type of lead and level of lead dust exposure in Lead Work Area. Respirator to be equivalent Type CE abrasive blast supplied air respirator operated in a pressure demand or positive pressure mode with a tight-fitting full-face-piece. Compressed air used to supply supplied air respirators to meet breathing air purity requirements of CAN/CSA-Z Where an oil-lubricated compressor is used to supply breathing air, a continuous carbon monoxide monitor/alarm to be provided..2 Disposable protective clothing that does not readily retain or permit skin contamination, consisting of full body covering including head covering with snug fitting cuffs at wrists, ankles, and neck..2 Requirements for workers:.1 Remove street clothes in clean change room and put on respirator with new filters or reusable filters, clean coveralls and head covers before entering Equipment and Access Rooms or Work Area. Store street clothes, uncontaminated footwear, towels, and similar uncontaminated articles in clean change room..2 Remove gross contamination from clothing before leaving work area. Place contaminated work suits in receptacles for disposal with other lead contaminated materials. Leave reusable items except respirator in Equipment and Access Room. When not in use in work area, store work footwear in Equipment and Access Room. Upon completion of lead abatement, dispose of footwear as contaminated waste or clean thoroughly inside and out using soap and water before removing from work area or from Equipment and Access Room..3 Enter unloading room from outside dressed in clean coveralls to remove waste containers and equipment from Holding Room of Container and Equipment Decontamination Enclosure system. Workers not use this system as means to leave or enter Work Area..3 Eating, drinking, chewing, and smoking are not permitted in Work Area..4 Ensure workers are fully protected with respirators and protective clothing during preparation of system of enclosures prior to commencing actual lead abatement..5 Ensure workers wash hands and face when leaving Lead Work Area..6 Provide and post in Clean Change Room and in Equipment and Access Room the procedures described in this Section, in both official languages..7 Ensure no person required to enter Work Area has facial hair that affects seal between respirator and face..8 Visitor Protection:

24 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page WASTE MANAGEMENT AND DISPOSAL.1 Provide protective clothing and approved respirators to Authorized Visitors to work areas..2 Instruct Authorized Visitors in use of protective clothing, respirators and procedures..3 Instruct Authorized Visitors in proper procedures to be followed in entering into and exiting from Work Area..1 Disposal of lead waste generated by removal activities must comply with Provincial regulations. Dispose of lead waste in sealed double thickness 6 ml bags or leak proof drums. Label containers with appropriate warning labels. 1.8 EXISTING CONDITIONS.1 Reports and information pertaining to lead based paint to be handled, removed, or otherwise disturbed and disposed of during this Project are available upon request. Part 2 Products 2.1 MATERIALS.1 Polyethylene: 0.15mm unless otherwise specified; in sheet size to minimize joints..2 FR polyethylene: 0.15mm woven fibre reinforced fabric bonded both sides with polyethylene..3 Tape: fibreglass - reinforced duct tape suitable for sealing polyethylene under dry conditions and wet conditions using amended water..4 Slow - drying sealer: non-staining, clear, water - dispersible type that remains tacky on surface for at least 8 hours and designed for trapping residual lead paint residue. Part 3 Execution 3.1 SUPERVISION.1 Approved Supervisor must remain within Work Area during disturbance, removal, or handling of lead based paints. 3.2 PREPARATION.1 Work Area:.1 Clean work areas using HEPA vacuum. If not practicable, use wet cleaning method. Do not use methods that raise dust, such as dry sweeping, or vacuuming using other than HEPA vacuum..2 Install negative pressure machine system and operate continuously from installation of polyethylene sheeting until completion of final cleanup. Provide automatic continuous monitoring and recording instrument of pressure difference..3 Cover ground surfaces in work area with two layers of polyethylene drop sheets.

25 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page 5.4 Build airlocks at entrances and exits from work areas to ensure work areas are always closed off by one curtained doorway when workers enter or exit..5 At point of access to work areas install warning signs in both official languages in upper case "Helvetica Medium" letters reading as follows where number in parentheses indicates font size to be used:.1 CAUTION LEAD HAZARD AREA (25 mm)..2 NO UNAUTHORIZED ENTRY (19 mm).3 WEAR ASSIGNED PROTECTIVE EQUIPMENT AND RESPIRATOR (19 mm)..4 BREATHING LEAD CONTAMINATED DUST CAUSES SERIOUS BODILY HARM (7 mm)..6 Where water application is required for wetting lead containing materials, provide temporary water supply by use of appropriately sized hoses for application of water as required..2 Worker Decontamination Enclosure System:.1 Worker Decontamination Enclosure System includes Equipment and Access Room and Clean Room, as follows:.1 Equipment and Access Room: construct between exit and work areas, with two curtained doorways, one to the rest of the suite, and one to work area. Install waste receptor and storage facilities for workers' shoes and protective clothing to be re-worn in work areas. Build large enough to accommodate specified facilities, equipment needed, and at least one worker allowing sufficient space to change comfortably..2 Clean Room: construct with curtained doorway to outside of enclosures. Provide lockers or hangers and hooks for workers' street clothes and personal belongings. Provide storage for clean protective clothing and respiratory equipment. Install mirror to permit workers to fit respiratory equipment properly..3 Construction of Decontamination Enclosures:.1 Construct framing for enclosures. Line enclosure with polyethylene sheeting and seal with tape, apply two layers of polyethylene on ground..2 Construct curtain doorways between enclosures so when people move through or waste containers and equipment are moved through doorway, one of two closure comprising doorway always remains closed..3 Shower room in decontamination facility to be provided with the following:.1 Hot and cold water or water of constant temperature not less than 40 degrees Celsius or more than 50 degrees Celsius..2 Individual controls inside to regulate water flow and temperature..4 Prior to each shift in which a decontamination facility is being used, a competent person should inspect the facility to ensure that there are no defects that would allow lead-containing dust to escape. Defects should be repaired before the facility is used. The decontamination facility should be maintained in a clean and sanitary condition..4 Separation of Work Areas from Occupied Areas:.1 Barriers between Work Area and occupied area to be constructed as follows:

26 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page 6.1 Construct floor to ceiling lumber stud framing, cover all walls, floor and ceiling with polyethylene sheeting and seal with duct tape..5 Maintenance of Enclosures:.1 Maintain enclosures in tidy condition..2 Ensure barriers and polyethylene linings are effectively sealed and taped. Repair damaged barriers and remedy defects immediately..3 Visually inspect enclosures at beginning of each working day. 3.3 LEAD - BASED PAINT ABATEMENT.1 Removal of lead based paint to be performed using abrasive blasting techniques..2 Remove lead based paint in small sections and pack as it is being removed in sealable 0.15 mm plastic bags and place in labelled containers for transport..3 Wet method to be used to reduce dust generation. Examples of wet methods include wetting surfaces, wet scraping, and wet shovelling. Wet method not be used if it creates a hazard or cause damage to equipment or to project..4 Seal filled containers. Clean external surfaces thoroughly by wet sponging. Remove immediate from working area to staging area. Clean external surfaces thoroughly again by wet sponging before moving containers to decontamination Washroom. Wash containers thoroughly in decontamination Washroom, and store in Holding Room pending removal to Unloading Room and outside. Ensure containers are removed from Holding Room by workers who have entered from uncontaminated areas dressed in clean coveralls..5 After completion of stripping work, wire brush and wet sponge surface to remove visible material. During this work keep surfaces wet. After wire brushing and wet sponging, wet clean and HEPA vacuum entire work area including Equipment and Access Room. Compressed air or dry sweeping not be used to clean up lead-containing dust or waste..6 Wet clean work area and equipment and access room. 3.4 INSPECTION.1 Perform inspection to confirm compliance with specification and governing authority requirements. Deviations from requirements not been approved in writing by Consultant will result in Work shutdown, at no cost to Owner..2 Consultant will inspect work for:.1 Adherence to specific procedures and materials..2 Final cleanliness and completion..3 No additional costs will be allowed for additional labour or materials required to provide specified performance level..3 When lead dust leakage from Work Area occurs Consultant will order Work shutdown..1 No additional costs will be allowed by Contractor for additional labour or materials required to provide specified performance level.

27 Mooney s Bay Section LEAD - BASED PAINT ABATEMENT - MAXIMUM PRECAUTIONS Page FINAL CLEANUP.1 Following specified cleaning procedures proceed with final cleanup..2 Remove polyethylene sheet by rolling it away from walls to centre of work area. Vacuum visible lead containing particles observed during cleanup, immediately, using HEPA vacuum..3 Place polyethylene sheets, tape, cleaning material, clothing, and contaminated waste in plastic bags and sealed labelled waste containers for transport..4 Clean up Work areas, Equipment and Access Room, and other contaminated enclosures..5 Remove sealed waste containers and equipment used in Work and remove from work areas at appropriate time in cleaning sequence..6 Conduct final check to ensure no dust or debris remain on surfaces as result of dismantling operations. 3.6 RE-ESTABLISHMENT OF OBJECTS AND SYSTEMS.1 Repair or replace objects damaged in course of work to their original state or better, as directed by Consultant. END OF SECTION

28

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work: Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:.1 Removing roofing materials that are suspected of containing asbestos using wet material

More information

INTERIOR RENOVATIONS FINANCE DIVISION LEAD ABATEMENT TYPE 1 OPERATION MINIMUM PRECAUTIONS PAGE 1 OF 7

INTERIOR RENOVATIONS FINANCE DIVISION LEAD ABATEMENT TYPE 1 OPERATION MINIMUM PRECAUTIONS PAGE 1 OF 7 TYPE 1 OPERATION MINIMUM PRECAUTIONS PAGE 1 OF 7 PART 1 GENERAL 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work activities which are defined as a Type 1 lead operation

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work: 125 Syndicate Avenue Page 1 of 12 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work:.1 Removal of asbestos-containing pipe and duct insulation, as

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work: 125 Syndicate Avenue, Thunder Bay, Ontario Page 1 of 5 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:.1 Removing asbestos-containing transite

More information

City of Winnipeg Section SEWPCC Ventilation and Misc. Upgrade ASBESTOS ABATEMENT TYPE 2 Bid Opportunity Page 1 of 6

City of Winnipeg Section SEWPCC Ventilation and Misc. Upgrade ASBESTOS ABATEMENT TYPE 2 Bid Opportunity Page 1 of 6 City of Winnipeg Section 02 82 11 SEWPCC Ventilation and Misc. Upgrade ASBESTOS ABATEMENT TYPE 2 Bid Opportunity 545-2012 Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section

More information

These procedures are to be followed by all persons required to perform the following work:

These procedures are to be followed by all persons required to perform the following work: These procedures are to be followed by all persons required to perform the following work: Entry into any ceiling space above which an asbestos-containing fireproofing or thermal insulation is present.

More information

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace

More information

PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I:

PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY FACILITIES AND SERVICES PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: SMALL ISOLATED AREA (less than 10sq. ft.) -- e.g. CEILING TILES AND

More information

Office of Environmental Health and Safety 1.0 INTRODUCTION

Office of Environmental Health and Safety 1.0 INTRODUCTION Office of Environmental Health and Safety 1.0 INTRODUCTION Silica (SiO 2) is the second most common mineral in the earth s crust and is a major component of sand, rock and mineral ores. Silica exists in

More information

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES TY PE 2 WOR K PR OCE DUR ES These procedures are to be followed by all maintenance personnel and contractors performing the following work at KPDSB buildings.

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations. 2. Scope The OSHA requirements and this

More information

Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS

Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS The following procedures are presented as a guide. Comprehensive site-specific technical specifications for the removal of mould-contaminated

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations.

More information

Standard Operating Procedures for the Control of Lead During Building Maintenance and Construction Activities. Type 1 Lead Operations

Standard Operating Procedures for the Control of Lead During Building Maintenance and Construction Activities. Type 1 Lead Operations Standard Operating Procedures for the Control of Lead During Building Maintenance and Construction Activities Type 1 Lead Operations Lead is a heavy metal that has and continues to be widely used in industry

More information

Section Asbestos Containment Procedures

Section Asbestos Containment Procedures Section Cover Page Section 02 82 05 2017-10-01 Use this Section where full containment will be required, or if a Contractor option, may be required, depending on the removal method(s) selected by the Contractor.

More information

Asbestos Management Program

Asbestos Management Program Oct. 10/06 Oct 10/06 1/13 Table of Contents 1 INTRODUCTION...2 2 PURPOSE...2 3 SCOPE...2 4 ROLES & RESPONSIBILITIES...2 5 INVENTORY...6 6 ACCESS CONTROL...6 7 INSPECTION...6 8 CLASSIFICATIONS OF ASBESTOS

More information

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the City of Vancouver Invitation to Tender including all available documents,

More information

Pre renovation Information Regarding Designated Substances

Pre renovation Information Regarding Designated Substances Pre renovation Information and Specification Sections for Designated Substances City of Thunder Bay Current River Park Picnic Shelter and Washrooms 570 Cumberland Street North, Thunder Bay, Ontario Pre

More information

CLASS I AND II ABATEMENT PROJECT SUBMITTALS

CLASS I AND II ABATEMENT PROJECT SUBMITTALS 5.1 Pre-Work Submittals CLASS I AND II ABATEMENT PROJECT SUBMITTALS Abatement contractors shall submit the following in a bound notebook to AU or our designated representative at the mandatory pre-construction

More information

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the Invitation to Tender including all available documents, meeting minutes,

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

CADMIUM AWARENESS Revision Date: 04/2017

CADMIUM AWARENESS Revision Date: 04/2017 CADMIUM AWARENESS 7.1 PURPOSE 7.1.1 The purpose of this policy is to provide guidelines for safely working with cadmium. It includes provisions for training, PPE guidelines, monitoring, medical surveillance,

More information

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc.

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc. The following work procedures are specified on all full containment asbestos abatement projects that we design. A. Preliminary Air Sampling: Many buildings contain background fiber levels prior to, or

More information

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES Project Description: Date Work Conducted: Completed by: (Name and Dept) NOTIFICATION/AWARENESS: 1.

More information

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL At 130 Liberty Street New York, New York Lower Manhattan Development Corporation

More information

PIGEON DROPPINGS CLEAN UP WORK TABLE OF CONTENTS

PIGEON DROPPINGS CLEAN UP WORK TABLE OF CONTENTS PIGEON DROPPINGS CLEAN UP WORK TABLE OF CONTENTS PAGE PIGEON DROPPINGS CLEAN UP WORK... 1 1 GENERAL... 1 1.1 GENERAL CONDITIONS AND RELATED WORK... 1 1.2 DESCRIPTION OF WORK... 1 1.3 DOCUMENTS TO BE SUBMITTED...

More information

Section Asbestos Removal

Section Asbestos Removal Section Cover Page Section 02 82 33 2017-10-01 Use this Section to specify removal of materials containing asbestos, as listed below. Always use in conjunction with Section 02 82 01 - Asbestos Control

More information

Certification Number: NAT Lead Renovation, Repair and Painting Program

Certification Number: NAT Lead Renovation, Repair and Painting Program Certification Number: NAT-117534-2 Lead Renovation, Repair and Painting Program August 2018 Lead Renovation, Repair and Painting Program TABLE of CONTENTS I. Purpose II. Risk Identification III. Responsibilities

More information

ASBESTOS ABATEMENT C.O.S. - WASTEWATER TREATMENT PLANT PAGE 1 of 10

ASBESTOS ABATEMENT C.O.S. - WASTEWATER TREATMENT PLANT PAGE 1 of 10 ASBESTOS ABATEMENT C.O.S. - WASTEWATER TREATMENT PLANT PAGE 1 of 10 1.0 GENERAL.1 SCOPE The City of Saskatoon intends and this specification covers the removal of Asbestos Containing Material from within

More information

Adv. 3.2: Asbestos Abatement Rev

Adv. 3.2: Asbestos Abatement Rev ADVISORY NO. 3.2: ASBESTOS ABATEMENT TERMINOLOGY AND DEFINITIONS Abatement: Procedures to control fiber release from asbestos-containing materials, i.e., removal, encapsulation, or enclosure. Air Lock:

More information

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 REFERENCE: ISSUE DATE: January, 1983 CHANGES: TOPIC: Asbestos INITIATED BY: Business Services DATE OF

More information

LEAD HAZARD CONTROL PROGRAM

LEAD HAZARD CONTROL PROGRAM LEAD HAZARD CONTROL PROGRAM Supervisor s Manual Prepared by Environmental Health and Safety Services Occupational Safety Programs GLOSSARY Abatement or Deleading CFR Control Measure Encapsulation EPA HEPA

More information

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS PART 1.0 GENERAL REQUIREMENTS.............................................. 1 1.1 Introduction.............................................................

More information

Work Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos

Work Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos University of Washington Facilities Services Maintenance & Alterations 9.5.02 Work Practice for Penetrating or Removing Wallboard Systems with

More information

INTRODUCTION TO THE PROGRAM

INTRODUCTION TO THE PROGRAM INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information

More information

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 932 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE 932.01 SCOPE 932.02 REFERENCES 932.03 DEFINITIONS TABLE OF CONTENTS 932.04 SUBMISSION

More information

"ASBESTOS AWARENESS IN THE WORKPLACE"

ASBESTOS AWARENESS IN THE WORKPLACE MAJOR PROGRAM POINTS "ASBESTOS AWARENESS IN THE WORKPLACE" Training For THE OSHA ASBESTOS STANDARD Quality Safety and Health Products, for Today...and Tomorrow Outline of Major Points Covered in the "Asbestos

More information

Municipality of the County of Pictou Project PC Linacy School Demolition. Linacy, Pictou County

Municipality of the County of Pictou Project PC Linacy School Demolition. Linacy, Pictou County Municipality of the County of Pictou Project PC201802 Linacy School Demolition Linacy, Pictou County Issued for Tender November 2018 THESE PROJECT DOCUMENTS HAVE BEEN PREPARED FOR USE WITH AND REQUIRE

More information

Lead in Construction Guidance

Lead in Construction Guidance Lead in Construction Guidance Scope All construction work where an employee may be occupationally exposed to lead, is covered by the OSHA 29 CFR 1926.62 Lead standard. Definitions The Action Level (AL)

More information

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f:

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f: VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA 02189 www.vertexeng.com p: 781.952.6000 f: 781.335.3543 EZRA BAKER ELEMENTARY SCHOOL/GYMNASIUM ASBESTOS ABATEMENT WORK PLAN ASBESTOS CONTAINING

More information

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION SECTION 13280 ASBESTOS CONTAINING MATERIALS REMEDIATION PART 1 GENERAL 1.1 SECTION INCLUDES A. Furnishing all labor, materials, equipment, and transportation necessary for properly and safely removing,

More information

Tasks estimated to generate a TWA of 50 micrograms per cubic meter of air include:

Tasks estimated to generate a TWA of 50 micrograms per cubic meter of air include: Lead Exposure Compliance Program for Construction The purpose of this program is to inform interested persons, including employees, that Prairie Construction is complying with the OSHA Lead Standard, Title

More information

T Attachment #5 Lead Abatement Specifications The Annex Exterior Roof and Soffits, 510 George Street North, Peterborough Page 1

T Attachment #5 Lead Abatement Specifications The Annex Exterior Roof and Soffits, 510 George Street North, Peterborough Page 1 T-09-15 Attachment #5 Lead Abatement Specifications The Annex Exterior Roof and Soffits, 510 George Street North, Peterborough Page 1 Section 02082 Site Work Lead Abatement PART 1 GENERAL 1.1 General Conditions

More information

In general, the management plan development process consisted of:

In general, the management plan development process consisted of: NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department

More information

PART 1 GENERAL 1.1 General 1.2 Abatement Contractors 1.3 Site Conditions

PART 1 GENERAL 1.1 General 1.2 Abatement Contractors 1.3 Site Conditions Crestwood Secondary School Section 02 82 00 1885 Sherbrooke Street West, Peterborough, Ontario Site Conditions and Outline of Work Pinchin File Number 218575 Page 1 of 6 PART 1 GENERAL 1.1 General.1 Read

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

National Master Specification (NMS) Section Publisher: Spex.ca Page 1. Approved: RELATED REQUIREMENTS.1 Section [ ].

National Master Specification (NMS) Section Publisher: Spex.ca Page 1. Approved: RELATED REQUIREMENTS.1 Section [ ]. National Master Specification (NMS) Section 07 21 16 BLANKET INSULATION Publisher: Spex.ca Page 1 Approved: 2014-12-31 Part 1 General 1.1 RELATED REQUIREMENTS.1 Section [ ]. 1.2 REFERENCES.1 CSA Group.1

More information

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 REVISION 7 ITEM 516 INSTALLATION OF FLEX BEAM GUARDRAIL

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 REVISION 7 ITEM 516 INSTALLATION OF FLEX BEAM GUARDRAIL AFTER NOVEMBER 1, 2008 ITEM 516 INSTALLATION OF FLEX BEAM GUARDRAIL 516.1 Description. This item shall govern for furnishing and placing 10 or 12 gauge galvanized flex beam guardrail, complete with timber

More information

Work Plan dated February 17, Prepared by Axiom Partners, Inc. Stephen E. Minassian Massachusetts Asbestos Designer License #AD051928

Work Plan dated February 17, Prepared by Axiom Partners, Inc. Stephen E. Minassian Massachusetts Asbestos Designer License #AD051928 ABATEMENT WORK PLAN FOR EMERGENCY ASBESTOS ABATEMENT PROJECT CONSENTINO MIDDLE SCHOOL 685 WASHINGTON STREET HAVERHILL, MASSACHUSETTS Work Plan dated February 17, 2016 Prepared by Axiom Partners, Inc. Stephen

More information

ASBESTOS MANAGEMENT PROGRAM. Carleton University

ASBESTOS MANAGEMENT PROGRAM. Carleton University ASBESTOS MANAGEMENT PROGRAM Carleton University November Oct 10/06 2/25 Table of Contents 1 INTRODUCTION... 3 2 PURPOSE... 3 3 SCOPE... 3 4 ROLES & RESPONSIBILITIES... 3-7 5 INVENTORY... 7 6 ACCESS CONTROL...

More information

BP OIL -- TOLEDO REFINERY. Refinery Wide. Lead Exposure Management Plan. Authorized By: Robert Myak (signature on file)

BP OIL -- TOLEDO REFINERY. Refinery Wide. Lead Exposure Management Plan. Authorized By: Robert Myak (signature on file) BP OIL -- TOLEDO REFINERY Document Type: Practice Effective Date: September 18, 2014 Owner: Matthew Grimes Refinery Wide Lead Exposure Management Plan Authorized By: Robert Myak (signature on file) Practice

More information

EPA s Lead Program Rule At-A-Glance

EPA s Lead Program Rule At-A-Glance EPA s Lead Program Rule At-A-Glance FLOW CHART 1: Do the Requirements Apply to the Renovation? If you will be getting paid to do work that disturbs painted surfaces in a pre-1978 home, apartment building,

More information

Form 9: Infection Control Preventive Measures Level 4

Form 9: Infection Control Preventive Measures Level 4 Form 9: Infection Control This form is filled out by the construction planning team or designated person(s) to identify the required preventive measures for the activity described in Form 1 Infection Control

More information

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts 1) Introduction Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts Triumvirate Environmental Inc. (TEI) shall perform

More information

INSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT

INSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT INSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT MAY 2009 prepared by N. A. JACOBSEN, P.Eng. CIVIL ENGINEERING CONSULTANT Whitehorse, Yukon ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT MAY

More information

(Specification writer shall choose the most appropriate section that applies to a given scope of work) SECTION Painting and Coating

(Specification writer shall choose the most appropriate section that applies to a given scope of work) SECTION Painting and Coating Guide Specification Miracote Mirastain Architectural Staining System (Specification writer shall choose the most appropriate section that applies to a given scope of work) PART 1 - GENERAL 1.1 SUMMARY

More information

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS 1. DESCRIPTION OF WORK: ATTACHMENT A RFP # 024-0-2016BH ASBESTOS ABATEMENT REQUIREMENTS The work includes pre-cleaning, repair and/or removal and disposal of friable and non-friable asbestos containing

More information

A. Environmental Limitations: Comply with ASTM C 840 requirements or gypsum board manufacturer's written instructions, whichever are more stringent.

A. Environmental Limitations: Comply with ASTM C 840 requirements or gypsum board manufacturer's written instructions, whichever are more stringent. SECTION 092900 - GYPSUM BOARD PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Thames Valley District School Board. The Board has assigned the following responsibilities to ensure compliance with the above Policy and Legislation.

Thames Valley District School Board. The Board has assigned the following responsibilities to ensure compliance with the above Policy and Legislation. Thames Valley District School Board PROCEDURE Title ASBESTOS PROCEDURES Procedure No. 2005a Department ORGANIZATIONAL SUPPORT SERVICES (HUMAN RESOURCES) Reference(s) Policy: Health and Safety - Occupational

More information

Developed and Presented by: Wisconsin Healthcare Engineering Association

Developed and Presented by: Wisconsin Healthcare Engineering Association Infection Control Risk Assessment (ICRA) Developed and Presented by: Wisconsin Healthcare Engineering Association What is an ICRA? An Infection Control Risk Assessment is a tool devised to protect patients

More information

BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS

BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS OF 5 BUILDINGS 1400 E. MISSION BOULEVARD POMONA, CA PROJECT NO. 3009860 JUNE 23, 2017 Prepared

More information

Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature:

Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature: Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature: Skill Skill Set Description #1 Using EPA Recognized Test Kits and Paint Chip Sample

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.10/22/08, 10/15/09 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information

Safety Policy Manual Policy No. 144

Safety Policy Manual Policy No. 144 Policy: Lead Management Program Page 1 of 11 APPLICATION NYU Langone PURPOSE To protect employees, patients, students, tenants, and members of the community from exposure to lead. To comply with regulations

More information

.2 Section Waste Management and Disposal.

.2 Section Waste Management and Disposal. Issued 2006/08/01 Section 05121 Structural Steel for Buildings Page 1 of 5 PART 1 GENERAL 1.1 RELATED SECTIONS.1 Section 01330 Submittal Procedures..2 Section 01355 Waste Management and Disposal..3 Section

More information

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995.

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995. April 2012, rev. 00 02 8213 Asbestos Abatement 1. General 1.01 Summary of Work A. Contractor 1.02 Definitions 1. The Contractor shall provide removal and proper disposal of asbestos containing materials.

More information

The City of Winnipeg NEWPCC Lab Renovation

The City of Winnipeg NEWPCC Lab Renovation Bid Opportunity 253-2011 Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Work under this contract includes, but is not necessarily limited to:.1 Surface preparation of substrates as required for acceptance of

More information

AIR POLLUTION CONTROL REGULATION NO. 24 REMOVAL OF LEAD BASED PAINT FROM EXTERIOR SURFACES

AIR POLLUTION CONTROL REGULATION NO. 24 REMOVAL OF LEAD BASED PAINT FROM EXTERIOR SURFACES 24.1 Definitions AIR POLLUTION CONTROL REGULATION NO. 24 REMOVAL OF LEAD BASED PAINT FROM EXTERIOR SURFACES As used in these regulations, the following terms shall, where the context permits, be construed

More information

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification SECTION 028200 - ABESTOS ABATEMENT PART 1 - GENERAL 1.1 SCOPE OF WORK A. The following asbestos-containing materials is known to be present on the First and Second Floor classrooms of the North Wing of

More information

Asbestos Management Program

Asbestos Management Program SUPERIOR-GREENSTONE DISTRICT SCHOOL BOARD Asbestos Management Program Introduction Asbestos, a designated substance, is a natural fibre commonly used in the manufacture of building materials. The use of

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 553 FEBRUARY 1991 CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS 553.01 SCOPE 553.02 REFERENCES 553.03 DEFINITIONS TABLE OF CONTENTS 553.04 SUBMISSION

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

.4 Submit proof of qualifications and authorization in writing to the Contract Administrator, four (4) weeks prior to commencement of Work.

.4 Submit proof of qualifications and authorization in writing to the Contract Administrator, four (4) weeks prior to commencement of Work. Construction of Roads and Landscaping Page 1 of 8 1. GENERAL 1.1 Work Included.1 Supply and Installation of specialty coatings for the concrete pavement areas adjacent to the south side of the Bulk Chemical

More information

3. Asbestos Handling Program

3. Asbestos Handling Program 1.0 Introduction 3. Asbestos Handling Program This program will establish guidelines and procedures in the operations and maintenance of asbestos containing materials at PLU to protect all employees, contractors,

More information

BRANZ Appraisal Certificate # 461 (2010) Internal wet areas.

BRANZ Appraisal Certificate # 461 (2010) Internal wet areas. SPECIFICATION FOR PROTECTO WRAP AFM-WM FOR INTERNAL WET AREAS BRANZ Appraisal Certificate # 461 (2010) Internal wet areas AFM/WM INTERNAL 0104 Page 1 AFM-WM INTERNAL SPECIFICATION PRODUCT DESCRIPTION Anti

More information

Sunshine Coast Regional District Section Port Facility Reparation Page 1

Sunshine Coast Regional District Section Port Facility Reparation Page 1 Sunshine Coast Regional District Section 06 15 00 TIMBER Port Facility Reparation Page 1 PART 1 GENERAL 1.1 SCOPE.1 This section relates to the following:.1 Pickup of Owner supplied timber materials from

More information

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 932 NOVEMBER 2009 CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE TABLE OF CONTENTS 932.01 SCOPE 932.02 REFERENCES 932.03 DEFINITIONS 932.04

More information

Asbestos Management Program

Asbestos Management Program Asbestos Management Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 5/8/2018 Table of Contents 1.

More information

UC Irvine Environmental Health & Safety SECTION: TITLE: Lead Compliance Program

UC Irvine Environmental Health & Safety SECTION: TITLE: Lead Compliance Program UC Irvine Environmental Health & Safety SECTION: TITLE: Lead Compliance Program INITIATOR: Susan Robb REVISION DATE REVIEW DATE December 2012 July 2016 1. Program Description 2. Scope 3. Definitions 4.

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 061600 - SHEATHING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions.

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions. 028333 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions. B. Contract Drawings. 1.2 SUMMARY A. The lead removal work is in support

More information

CONSTRUCTION SPECIFICATION FOR EXPANDED METAL ANTI-GLARE SCREEN

CONSTRUCTION SPECIFICATION FOR EXPANDED METAL ANTI-GLARE SCREEN ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 791 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR EXPANDED METAL ANTI-GLARE SCREEN TABLE OF CONTENTS 791.01 SCOPE 791.02 REFERENCES 791.03 DEFINITIONS

More information

BASF Corporation Title: ASBESTOS HANDLING, REMOVAL AND DEMOLITION

BASF Corporation Title: ASBESTOS HANDLING, REMOVAL AND DEMOLITION Procedure No.: IH-6 Page: 1 of 16 Preparer: Owner: Approver: RECORD OF REVISIONS Date Details of Change 11/02/01 Added a Record of Revisions table. 08/14/08 Review of entire procedure. Deleted 4.3.3 and

More information

OHE Project No.: Art Gallery of Peterborough Hazardous Material 250 Crescent Street Abatement Specifications

OHE Project No.: Art Gallery of Peterborough Hazardous Material 250 Crescent Street Abatement Specifications Peterborough, Ontario Page 1 of 66 Section 02080 Site Work Asbestos Abatement PART 1 GENERAL 1.1 General Conditions and Related Work 1.1.1 This section forms a part of the Contract Document and should

More information

SECTION ASBESTOS ABATEMENT

SECTION ASBESTOS ABATEMENT SECTION 020710 ASBESTOS ABATEMENT PART1 GENERAL 1.1 SCOPE This section covers the removal of asbestos-containing materials as identified in Section 011000 - Summary of Work. Compliance with all applicable

More information

Standard Specification for Abatement of Vinyl Asbestos Floor Tile and Mastic Tile Adhesive 2010

Standard Specification for Abatement of Vinyl Asbestos Floor Tile and Mastic Tile Adhesive 2010 Standard Specification for Abatement of Vinyl Asbestos Floor Tile and Mastic Tile Adhesive 2010 Prepared for and by The University of Vermont Department of Physical Plant Training and Compliance Office

More information

SRP-AirOutshield ROOF Issued:

SRP-AirOutshield ROOF Issued: SECTION 07276: Breathable Underlayment Guide Specification This specification is a guide only and may need editing for the specific intended application. It is the responsibility of the design professional

More information

TITLE 250 DEPARTMENT OF ENVIRONMENTAL MANAGEMENT

TITLE 250 DEPARTMENT OF ENVIRONMENTAL MANAGEMENT 250-RICR-120-05-24 TITLE 250 DEPARTMENT OF ENVIRONMENTAL MANAGEMENT CHAPTER 120 AIR RESOURCES SUBCHAPTER 05 AIR POLLUTION CONTROL PART 24 - Removal of Lead Based Paint from Exterior Surfaces 24.1 Purpose

More information

Lead Based Paint Policy

Lead Based Paint Policy Lead Based Paint Policy 1. Guidance for the removal or maintenance of lead-based paint has undergone changes that affect the painting industry. The U.S. Department of Housing and Urban Development (HUD)

More information

1.3 Work shall include all reinforcement and accessories necessary to complete installation.

1.3 Work shall include all reinforcement and accessories necessary to complete installation. CERAMIC TILING GENERAL INFORMATION 1.1 Ceramic mosaic tile floors and bases, glazed wall tile wainscots and walls, and marble thresholds. 1.2 Installation will typically be with latex-portland cement mortar

More information

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 2 Definitions 2 Responsibilities 3 Hazard

More information

SECTION GYPSUM BOARD

SECTION GYPSUM BOARD SECTION 092900 GYPSUM BOARD PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION RESILIENT SHEET FLOORING

SECTION RESILIENT SHEET FLOORING SECTION 09 65 16 RESILIENT SHEET FLOORING SPEC WRITER NOTE: Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1.

More information

EPA s New Renovation, Repair and Painting Rule

EPA s New Renovation, Repair and Painting Rule When is Compliance with the EPA Renovation, Repair, and Painting Rule Required? Scope of Rule: Renovation, repair and painting activities on target housing or child-occupied facility built before 1978

More information

SECTION INJECTED or CAVITY-FILL POLYURETHANE FOAM (IPF)

SECTION INJECTED or CAVITY-FILL POLYURETHANE FOAM (IPF) SECTION 07200 INJECTED or CAVITY-FILL POLYURETHANE FOAM (IPF) Specifier Note: This specification is provided as guidelines for your use. Please review before publishing. PART 1.00 - GENERAL 1.01 DESCRIPTION:

More information

MATERIAL SPECIFICATION FOR WOOD, PRESERVATIVE TREATMENT, AND SHOP FABRICATION

MATERIAL SPECIFICATION FOR WOOD, PRESERVATIVE TREATMENT, AND SHOP FABRICATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 1601 NOVEMBER 2014 MATERIAL SPECIFICATION FOR WOOD, PRESERVATIVE TREATMENT, AND SHOP FABRICATION TABLE OF CONTENTS 1601.01 SCOPE 1601.02 REFERENCES

More information

HOTEL SPECIFICATION SECTION 08100

HOTEL SPECIFICATION SECTION 08100 Part 1 General HOTEL SPECIFICATION SECTION 08100 1.01 Work Included A. The work under this section shall include the furnishing of all items shown on the drawings and as specified including, but not limited

More information

Glossary. Accredited Testing Laboratory

Glossary. Accredited Testing Laboratory Glossary Accredited Testing Laboratory ACM Air Monitoring An asbestos testing laboratory accredited by the National Association of Testing Authorities, Australia (NATA) or a similar accreditation authority,

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 907 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS TABLE OF CONTENTS 907.01 SCOPE 907.02 REFERENCES 907.03 DEFINITIONS 907.04

More information