THE PRICING OF CONTRACT PRELIMINARIES: QUANTITY SURVEYORS AND CONTRACTORS COMPARED The pricing of preliminaries

Size: px
Start display at page:

Download "THE PRICING OF CONTRACT PRELIMINARIES: QUANTITY SURVEYORS AND CONTRACTORS COMPARED The pricing of preliminaries"

Transcription

1 THE PRICING OF CONTRACT PRELIMINARIES: QUANTITY SURVEYORS AND CONTRACTORS COMPARED The pricing of preliminaries P.A. BOWEN?? Department of Building and Surveying, Glasgow Caledonian University, Glasgow, Scotland K.A. HALL Department of Construction Economics and Management, University of Cape Town, Cape Town, South Africa P.J. EDWARDS Department of Building and Construction Economics, Royal Melbourne Institute of Technology, Melbourne, Australia Abstract This paper documents the results of an empirical study into the methods adopted by quantity surveyors and contractors for estimating the preliminaries component of project tenders. The pricing procedures of twenty-seven quantity surveying firms and twenty-five contracting organisations were studied through an opinion survey, using a structured questionnaire supplemented by formal interviews. Differences found between the two groups are discussed. Keywords: Contractors, preliminaries, pricing, quantity surveyors. Sommaire Ce document décrit les résultats d'une étude empirique des méthods adoptées par les métreurs et les entrepreneurs pour estimer les éléments préliminaires des états de quantité. Les méthodes d'estimation de 27 entreprises de métrage et de 25 entreprises de construction ont été analysées à l'aide d'un sondage, par l'utilisation d'un questionnaire et par des entretiens formels. Des différences d'évaluation des coûts ont été identifiés entre les 2 groupes observés. 1 Introduction The preliminaries costs of construction projects can be defined as those items that are not directly related to the individual items of measured work. Where tender bills of quantities 1 Professor Paul Bowen is currently on sabbatical leave from the Department of Construction Economics and Management, University of Cape Town, and is Visiting Professor to the Department of Building and Surveying, Glasgow Caledonian University, Glasgow, Scotland.

2 are prepared, these items are usually grouped together in a `preliminaries' section. Examples of preliminaries costs include plant, accommodation, temporary services, scaffolding, and insurances. The preliminaries can be grouped into items that relate to the contractor's general overheads, and items relating to the client's requirements. Examples of the latter include insurances, penalties for non-completion and general site restrictions. The preliminaries items can be seen as falling into two categories, namely, time-related costs and fixed costs. Fixed costs can be further divided into costs that are value-related (e.g., insurances), method-related (e.g., temporary works and plant), and quantity-related (e.g., hoardings and scaffolding). Time-related costs relate to those items of the preliminaries directly affected by the time they are required on site e.g., the cost of supervision and site accommodation. Most preliminaries items possess both a fixed- and a time-related component in their overall cost build-up. This can be illustrated if one considers the cost components of an equipment item, such as a tower crane. The tower crane has fixed costs for the transportation of the crane to and from the site and for the erection and dismantling of the crane. In addition, time-related costs apply to the duration for which the crane is present on site - either in the form of hire charges or in the form of opportunity and depreciation costs if the crane is owned by the contracting organisation. Moreover, the method of construction and the quantity and type of materials to be placed per week may impact on the positioning of the crane and the number of cranes required. Studies conducted by Gray [1] [2] on the pricing of preliminaries by contractors concluded that 90% of the value of the preliminaries can be found in only six items, namely, the costs of site staff, plant, scaffolding, site accommodation, electricity and cleaning. He also found that contractors generally only price sixteen items in the preliminaries section of a tender bills of quantities. Bennett et al. [3] reached similar conclusions. The `Preliminaries' document published by the A.S.A.Q.S. [4] for use with the Joint Building Contracts Committee (J.B.C.C.) `Principal Building Agreement' [5] makes provision for items contained in the preliminaries section to be priced by the contractor as either `fixed', `variable with value' or `variable with time', or a combination of these. This breakdown is then used as the basis for the payment and any subsequent adjustment of the preliminaries. The purpose of this paper, then, is to document the results of an empirical study into the methods adopted by quantity surveyors and contractors in estimating and pricing the preliminaries component of project tenders. 2 Theoretical discussion of the pricing function The functional separation of design and construction has been reflected in the development of price forecasting/cost estimating techniques. For quantity surveyors, the object is to inform clients and architects about the price implications of design decisions. For contractors, the need is to be informed of the anticipated cash flow implications should the contract be acquired. Although the nature of the competitive tendering process is such that quantity surveyors and contractors are essentially concerned with the same function (forecasting the market price of the project), the potential for contractors to access production cost information is a determining factor in the type of technique used [6]. The

3 generic form of quantity surveyors' traditional price models are given below. These equations were developed by Bowen [7] from the work of Skitmore and Patchell [6]. P = [(p 1 + p p n ) + G].I (1) n = [ (q i r i ) + G ].I i (i = 1,..., n) (2) i=1 n k = [ (q i r i ).I i + (q j r j ).I j ] (i = 1,..., n; j = 1,..., k) (3) i=1 j=1 where: P = total price of the work p = the individual product price of each item or work package q i = measure (quantity) associated with the i th item or work package r i = price per unit measure of the i th item or work package q j = the measure associated with the j th preliminaries item or work package r j = price per unit measure of the j th preliminaries item or work package n = the number of items or work packages k = the number of preliminaries items or work packages G = the price of the preliminaries I = a general price index for time adjustment I i = a price index for the time adjustment of the i th item or work package I j = a price index for the time adjustment of the j th preliminaries item or work package Consider the method adopted by most quantity surveyors in the pricing of preliminaries. The basic form in which preliminaries items are represented in bills of quantities is that of ` (q j r j )' (Eq. 3). Throughout the early design stages when approximate price forecasting techniques are used, and often when pricing bills of quantities as the final pre-tender price forecast, quantity surveyors adopt the procedure of adding on a percentage allowance to the priced builders' work. This percentage allowance is usually obtained from an analysis of priced bills of quantities of a `similar' nature, with an intuitive adjustment allowing for the differences between projects. This presupposes that there is knowledge of the composition of the preliminaries and the relevant items which should be adjusted because of the varying circumstances of the project. The pricing of the preliminaries must be seen as a potential source of considerable forecasting error given that this section can account for some 15-20% of the tender value [1] [2]. Contractors recognise the dangers inherent in this approach, preferring to adopt an individual assessment of each project to calculate the work content and cost of each preliminaries item ` (q j r' j )' (Eq. 6 below) [3] [8]. Research in the United Kingdom [9] [1] showed that preliminaries costs, when expressed as a percentage of contract value, display wide variability. This variability is not significantly affected by the size of the project, its type of construction or complexity. There is also no significant correlation between the preliminaries percentage and the value of the project. The relationship between the preliminaries and the overall duration of the project reflects a higher correlation, which improves further in projects of a more complex nature. However, the standard data sources and methods of price forecasting used by quantity surveyors do not consider this relationship at all. The percentage addition

4 approach, determined in relation to the value of the project, is highly subjective and unrelated to the process of construction. Little published data exist in South Africa regarding the percentage contribution made by preliminaries to tender price for various types of projects. The pricing function employed by contractors in tender bidding may be represented by: B = Cm (4) where: = [( c 1 + c c n ) + G'].m (5) n k = [ (q i r' i ) + (q j r' j )].m (i = 1,..., n; j = 1,..., k) (6) i=1 j=1 B = the value of the market price bid made by the contractor C = the estimated costs of production m = a `mark-up' value to be determined by the bidder c = the product cost of each item or work package G' = the cost of the preliminaries q i = measure (quantity) associated with the i th item or work package r i ' = cost per unit measure of the i th item or work package q j = the measure associated with the j th preliminaries item or work package r j ' = cost per unit measure of the j th preliminaries item or work package n = the number of items or work packages k = the number of preliminaries items or work packages The emphasis in tender bidding is the determination of a suitable value for `m' which will provide the best trade off between the probability of winning the contract and the anticipated profit should the bid be successful. Component `C' of the model is essentially similar to the basic price forecast model for `P' (Eq. 2). Costs are usually current with little use being made of price indices. If the same items are used (a basic assumption inherent in Eq. 6) in providing both design and construction price forecasts (e.g., pricing the bills of quantities as the basis for the bid), Eq. 6 may be simplified to n n B = (q i r' i ).m = (q i r i ) = P (i = 1,..., n) (7) i=1 i=1 as `B' and `P' are essentially forecasts of the same value, namely, the market price of the contract [6]. Given this underlying theoretical framework to the pricing of the preliminaries component of project tenders, how do quantity surveyors and contractors differ in their practical approaches to this task?

5 3 Opinion survey 3.1 Survey design and administration An opinion survey, using interviews and incorporating a structured questionnaire, was conducted in the Western Cape region of South Africa, to establish the methods used by quantity surveyors and contractors for the pricing of preliminaries items. Telephone contact was made with twenty-seven quantity surveying practices and twenty-five contracting organisations and their participation sought. The quantity surveyors were selected using the directory of registered (regional) practices of the Association of South African Quantity Surveyors. Contracting organisations were drawn from the membership directory of the local Master Builders' Association. In all instances interviews were arranged with a quantity surveying partner or chief estimator/contracts manager. The survey interviews addressed a number of issues relating to quantity surveying and construction management processes. The questionnaire for quantity surveyors amounted to fifteen A4 pages; while that for contractors contained forty-seven pages. The interviews were thus quite lengthy. However, participants were sent a copy of the relevant questionnaire beforehand, thus enabling them to offer more informed and more considered opinions. The interviewer does not think that any of the question responses was affected by survey fatigue. The section of the questionnaire dealing with the pricing of contract preliminaries was similar in content and format for both sets of participants. After a number of questions relating to company demographics and workload statistics, the questionnaires dealt specifically with the relative proportion of various preliminaries cost items to the total preliminaries value; participants' methods of calculating the cost of the preliminaries; the use of standard formats and checklists; detailed pricing of preliminaries items; factors influencing the cost of preliminaries items; and factors influencing the accuracy of preliminaries estimates. 3.2 Survey results The survey results are discussed question by question and compare the participating quantity surveyors' and contractors' opinions about each issue. Question 1: On average, what proportion of the total contract value does the preliminaries section represent? Various authors have pointed to the cost significance of the contract preliminaries expressed as a percentage of total contract value [9] [1] [10]. None have compared the assessments of quantity surveyors and contractors, and the question sought to explore this gap. Table 1 summarises the opinions of the survey participants about this question. Most respondents believe that contract preliminaries, expressed as a proportion of total contract value, lie in the range 4% - 10%. Some contractors; however, believe that preliminaries may, on average, amount to more than 20% of contract value; suggesting that, in some instances at least, the proportion may be much greater than 20%. While quantity surveyors and contractors participating in the survey hold broadly similar opinions about this question, there is an underlying difference between them. So, although the modal response in each case was that preliminaries account for 7% - 8% of total contract value, most quantity surveyor respondents believed that preliminaries account for between 7% and 10% of contract value; whereas the large majority of contractors opted for

6 a wider range: 4% - 10%. Clearly contractors expect a greater variability in preliminaries costs. Table 1 Contribution of the preliminaries to total contract value Percentage contribution Assessment of quantity surveyors and contractors Quantity surveyors [n = 27] Contractors [n = 25] % % 0-1% % % % % % % % 0 0 Exceeding 20% 0 5

7 Question 2 (to quantity surveyors): 2(a) In undertaking (the preparation of) an approximate cost estimate, which of the following methods do you use to determine the (total) value of the preliminaries? And 2(b): In pricing bills of quantities, which of the following methods do you use to determine the (total) value of preliminaries? Question 3 (to contractors): Please indicate which of the following methods you use to determine the (total) value of the preliminaries for tender purposes. These questions were intended to explore how quantity surveyors and contractors might differ in their overall approach to determining the total value of the contract preliminaries for a project. Participants were given a choice of three alternative methods, plus `other'; and a choice of five frequencies ranging from `always' to `never'. Quantity surveyors were asked two questions to reflect situations where more project information is available to them when producing a final estimate by pricing the tender bills of quantities. By far the most common method chosen by quantity surveyors, when preparing approximate cost estimates, was that of making a percentage addition to the estimated net project cost (96% of respondents reckoned that they `always' or `frequently' use this method; with a third of these indicating that they `always' use it). Making a lump sum addition to the net estimated cost was a less popular method. Only a quarter of the quantity surveyors `frequently' use this approach; while three-quarters use it `occasionally', `seldom' or `never'. Less than ten per-cent of quantity surveyors `frequently' calculate the cost of each preliminaries item when preparing approximate cost estimates. Similarly, 93% of quantity surveyors `always' or `frequently' use the percentage addition method to value preliminaries when pricing bills of quantities. Even with the greater level of information now available, more than 80% of quantity surveyors only `occasionally', `seldom' or `never' price each individual bill item of preliminaries. Indeed, a somewhat surprising 40% of them `frequently' or `occasionally' resort to making a lump sum addition for preliminaries when pricing the bills of quantities. Clearly, the percentage addition method is the approach most favoured by quantity surveyors at any stage in the estimating process, notwithstanding the proven lack of significant correlation between preliminaries percentage and project price [9] [1] [10]. The adoption of this technique also ignores the influence of project duration on preliminaries costs [7]. In contrast to the quantity surveyors, most of the contractors interviewed do not favour making tender allowances for the cost of the preliminaries by applying a percentage addition based on the net contract value. Three-quarters of them `seldom' or `never' use this method. A similar number do not favour a lump sum addition approach to pricing preliminaries. More than half of the contractors interviewed `always' calculate the cost of each individual preliminaries item. Question 4: Where the cost of each preliminaries item is calculated, is a standard format (i.e., method of calculation) used? Fewer than fifteen per-cent of quantity surveyors answered `yes' to this question. Where standard formats are used, they may incorporate assessments relating to the fixed cost, time, or value-related components of preliminaries items.

8 Just over half of the contractors interviewed do use standard formats for assessing the cost of preliminaries items. They also include fixed cost, time- and value-related methods of assessment. Question 5: Is a formal checklist used to minimise errors/omissions in the pricing of preliminaries? Just over a third of the quantity surveyors reckoned to use a standard checklist of items when pricing preliminaries, compared with two-thirds of the contractors. At the bill-pricing stage, of course, the preliminaries bill itself forms the checklist for quantity surveyors. Some contractors still use their own standard checklist at this point to ensure that sufficient detail has been incorporated in the preliminaries section of the tender bills of quantities. Question 6: Please indicate the extent to which each of the following factors influences the total value of the preliminaries. The purpose of this question was to see to what extent quantity surveyors and contractors were in agreement about causal influences on preliminaries costs. Survey participants were offered a list of eleven different factors, plus `other'. Against each factor, five possible response choices ranged from `no influence' to `strong influence'. The survey results are shown in Table 2. No additional factors were specified by either group of respondents. Table 2 Influence of project factors on pricing of preliminaries Degree of influence of factors Factor None Little Moderate Significant Strong Q.S. Cont. Q.S. Cont. Q.S. Cont. Q.S. Cont. Q.S. Cont. (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) Project type Project value

9 Project size Contract duration Location Expected number of bidders State of market Quality of tender information Project timing Project complexity Client organisation Project type was considered to be a `significant' to `strong' influencing factor on the total value of preliminaries by most quantity surveyors (78%) and most contractors (75%). Project value attracted less support, particularly among the contractors. Over half of them (58%) thought that project value had `little' to `moderate' influence on preliminaries costs, and nearly ten per-cent thought it had `no' influence. No quantity surveyors thought that project value had `little' or `no' influence, but one third thought it had only `moderate' influence. Two thirds of the quantity surveyors; however, still thought of project value as having a `significant' to `strong' influence on preliminaries costs (compared with only 44% of contractors). Opinions on the influence of project size varied more sharply. Nearly ninety per-cent of the quantity surveyors thought it had a `significant' to `strong' influence on preliminaries costs, compared with less than 60% of contractors. No quantity surveyors thought that

10 project size exerted anything less than a `moderate' influence; whereas nearly 25% of the contractors thought the influence of project size would be `little' or even non-existent. Contract duration was considered to be a `significant' to `strong' influence on preliminaries costs by both quantity surveyors (89%) and contractors (79%). Project location was seen as less influential, with just over half of quantity surveyors, and half of the contractors, believing it to be a `significant' to `strong' influence. Competitiveness (the expected number of bidders) seems to be even less influential. Half of the quantity surveyors, and a little over half of the contractors, thought this factor had `little' or `no' influence on preliminaries costs. There was some intra-group disagreement; however, as over ten per-cent of quantity surveyors thought it might be a `significant' to `strong' factor; as did 21% of contractors. The state of the market was less favoured by contractors than by quantity surveyors. Three-quarters of the contractors considered it to have `moderate', `little' or `no' influence on the total cost of preliminaries; compared with 38% of quantity surveyors who thought its influence was `moderate' or `little'. Less than a quarter of the contractors suggested that its influence was `significant' or `strong'; while just over half the quantity surveyors believed this was the case. Rather surprisingly, the quality of tender information did not rate highly with either group as an influential factor in the total cost of preliminaries. Only about a third of each group considered it to be a `significant' to `strong' influence. Project timing attracted a little more favour. Nearly half of the quantity surveyors, and almost 40% of the contractors, thought this was a `significant' to `strong' influence on the total cost of preliminaries. Project complexity was generally thought to exert a `significant' to `strong' influence on the total cost of preliminaries; with 69% of quantity surveyors and 67% of contractors opting for this view. No quantity surveyors rated the client organisation above a `moderate' influence on the total cost of preliminaries. However, more than 40% of the contractors thought it would have a `significant' to `strong' influence. Question 7: Please indicate the extent to which the following cost centres contribute to the total cost of the preliminaries of an "average" project undertaken over the past three years (express cost centre value as a percentage of total preliminaries value). This question was intended to find out to what extent quantity surveyors and contractors were in agreement about the cost significance of individual preliminaries items. Interestingly, many of the quantity surveyor respondent group (44%) declined to answer this question, claiming that they `did not know'. The results are shown in Table 3 with those for quantity surveyors reflecting the views of the reduced group size. The displayed statistics represent the means of the values expressed by participants. It might be argued that the modal values would be a better indicator of group opinions in this instance, and future extended analysis will explore this. Compared with the contractors, the quantity surveyors appear to over-value the costs of site personnel and providing temporary site accommodation, mechanical plant, and site security. On the other hand quantity surveyors may tend to under-value preliminaries costs for scaffolding, hoardings and name boards, and site transport, when compared to contractor assessments of these items.

11 Table 3 Contractors' and quantity surveyors' opinions regarding the significance of individual preliminaries cost centres Preliminaries cost centres Mean group values for percentage contribution of preliminaries cost centres Contractors [n = 25] Quantity surveyors [n = 15] (mean response values %) (mean response values %) Head office personnel Site personnel Temporary accommodation Telephones Temporary power and lighting Plant (mechanical) Plant (non-mechanical) Protective clothing Setting out

12 Scaffolding Water supply Hoardings and name boards Security Temporary roads Temporary works (e.g., storage facilities) Drying out Rates, notices and fees Insurances Contract conditions Cleaning Transport Abnormal overtime

13 Attendance on nominated sub-contractors

14 Question 8: How important do you consider the following factors to be in the calculation of an "accurate" preliminaries value for a project? Quantity surveyors and contractors need to have confidence in the accuracy of their pricing, but this can be affected by a number of factors. For example, the heavy reliance by quantity surveyors on the percentage addition technique (as a means of determining a total preliminaries value) implies that the forecaster's judgement, project details and feedback from previous projects are all important in the selection of an appropriate percentage. The question sought to ascertain how participants viewed the importance of such factors. Survey participants were offered a choice of seven factors, with three levels of importance for each. The results are shown in Table 4. Table 4 Quantity surveyors' and contractors' opinions regarding the importance of factors influencing the accuracy of the preliminaries estimate Importance attached to factor Factor Unimportant Important Very important Quantity Surveyors Contractors Quantity Surveyors Contractors Quantity Surveyors Contractors (%) (%) (%) (%) (%) (%) Detailed knowledge of project Experience in estimating Extensive knowledge of construction techniques Feedback from previous projects

15 Extensive data base Time spent in estimating Quality of tender information Detailed knowledge of the project is considered to be an `important' or `very important' factor by virtually all respondents, with contractors tending to ascribe slightly more importance to this than quantity surveyors. However, it was not clear from the survey whether the type of detailed knowledge so highly valued by contractors is different to that enjoyed by quantity surveyors. Respondents were almost unanimously agreed that estimating experience is `important' to `very important' for accurate pricing of preliminaries. Contractors tended to rate the importance of extensive knowledge of construction techniques more highly for the accurate pricing of preliminaries than did quantity surveyors. This suggests that contractors may have a better understanding than quantity surveyors of the resource implications of these technologies. It might have been anticipated that both groups would overwhelmingly have rated factors such as feedback from previous projects, the availability of an extensive database, the time spent in estimating, and the quality of tender information, as `very important' in influencing the accuracy of preliminaries pricing. In fact, these were generally regarded more as `important' rather than `very important'. The availability of an extensive database was actually thought to be an unimportant influence on the accuracy of preliminaries pricing by a quarter of the quantity surveyors and by over one third of the contractors; which suggests that they thought such a resource to be an unnecessary luxury. More surprisingly, over two-fifths of each group believed that spending more time in estimating would not be an important factor in influencing the accuracy of preliminaries pricing. Question 9: As a standard procedure, do you use feedback from previous projects to check on the accuracy of your preliminaries pricing? More than 80% of quantity surveyors confirmed that they do use historical feedback as a standard procedure for checking the accuracy of their preliminaries pricing. Only 60% of contractors reckoned to do this, however. This suggests that contractors may be more prepared to take a `fresh' view of each new project. Conclusions Several important findings arise from the survey. Firstly, quantity surveyors may take an overly narrow view of the proportional contribution of preliminaries costs to total project tender value. Secondly, despite its recognised shortcomings, quantity surveyors rely

16 strongly on the percentage addition method of calculating an overall value for contract preliminaries. Thirdly, quantity surveyors may over-rate the influence of project value and project size on preliminaries costs. Fourthly, quantity surveyors may under-rate the influence that the nature of the client organisation exerts on the minds of tendering contractors. Fifthly, when estimating, quantity surveyors may under-rate the impact of scaffolding, site hoardings and site inspection items on preliminaries costs. In conclusion, it is evident that quantity surveyors are unlikely to improve their methods of pricing preliminaries without becoming more involved in, and aware of, the implications of the construction programme and its relationship with building design. References 1. Gray, C. (1981) Analysis of the Preliminary Element of Building Production Costs. Unpublished M.Phil. Dissertation, Department of Construction Management, University of Reading, Reading. 2. Gray, C. (1983) Estimating preliminaries. Building Technology and Management, Parts 1-7, Chartered Institute of Building, Englemere, Ascot. 3. Bennett, J., Morrison, N.A.D. and Stevens, S.D. (1980) Construction Cost Data Bases. Second Annual Report prepared by the Department of Construction Management, University of Reading, for the Property Services Agency, Department of the Environment. 4. Association of South African Quantity Surveyors (A.S.A.Q.S.) (1991) Preliminaries. June 1991 Edition, A.S.A.Q.S. 5. Joint Building Contracts Committee (J.B.C.C.) (1991) Principal Building Agreement Edition, J.B.C.C. 6. Skitmore, R.M. and Patchell, B. (1990) Developments in contract price forecasting and bidding techniques, in Quantity Surveying Techniques: New Directions (Ed. P.S. Brandon), Blackwell Scientific Publications, Oxford, pp Bowen, P.A. (1993) A Communication-based Examination of Price Modelling and Price Forecasting in the Design Phase of the Traditional Building Procurement Process in South Africa. Unpublished Ph.D. Thesis, University of Port Elizabeth. 8. Chartered Institute of Building (C.I.O.B.) (1983) Code of Estimating Practice. Fifth Edition, C.I.O.B, October. 9. Flanagan, R. (1980) Tender Price and Time Prediction for Construction Work. Unpublished Ph.D. Thesis, University of Aston in Birmingham, Birmingham. 10. Pearl, R.G. (1992) Factors Affecting the Accuracy of Quantity Surveyors' Pre-Tender Price Forecasts in South Africa. Unpublished M.Sc. Dissertation, University of Cape Town.

Construction Financial Management

Construction Financial Management Unit 8: Construction Financial Management Unit code: K/504/4352 QCF level: 6 Credit value: 15 Aim This unit gives learners an understanding of the methods used to determine the price of a proposed. Learners

More information

Design Cost Modelling A Way Forward by Peter Lawther and Peter Edwards

Design Cost Modelling A Way Forward by Peter Lawther and Peter Edwards DESIGN COST MODELLING A WAY FORWARD Peter M Lawther and Peter J Edwards Department of Building and Construction Economics Royal Melbourne University of Technology University, Australia 1. Introduction

More information

MATCHING A PROCUREMENT SYSTEM TO CLIENT AND PROJECT NEEDS: A PROCUREMENT SYSTEM EVALUATOR

MATCHING A PROCUREMENT SYSTEM TO CLIENT AND PROJECT NEEDS: A PROCUREMENT SYSTEM EVALUATOR MATCHING A PROCUREMENT SYSTEM TO CLIENT AND PROJECT NEEDS: A PROCUREMENT SYSTEM EVALUATOR M.D. AMBROSE and S.N. TUCKER CSIRO Building, Construction and Engineering, Melbourne, Australia Abstract The selection

More information

Social Impact Series

Social Impact Series Social Impact Series WESTERN AUSTRALIA Issue #5 July 2016 The practice, prevalence and funding of outcomes measurement in the community sector: Findings from the Outcomes Measurement in the Western Australian

More information

ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE. ADENUGA, O.A. 1 and DOSUMU, O.S. 2

ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE. ADENUGA, O.A. 1 and DOSUMU, O.S. 2 ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE ADENUGA, O.A. 1 and DOSUMU, O.S. 2 http://dx.doi.org/10.4314/ejesm.v5i4.s6 Received 16th August 2012; accepted 8th

More information

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY F.H.Mustapha, Department of Civil Eng. and Building, University of Glamorgan S.G.Naoum, Tarik Aygun, School of Construction

More information

* do not represent the realities of on-site operations and * cannot communicate the essence of the problems being modelled.

* do not represent the realities of on-site operations and * cannot communicate the essence of the problems being modelled. THE SIGNIFICANCE OF PRICE MODELLING IN PROJECT PROCUREMENT SYSTEM G.K. Le Roux P.A. Bowen Department of Quantity Surveying, University of Port Elizabeth, South Africa Department of Construction Economics

More information

Financial Provision for Construction Health and Safety (H&S)

Financial Provision for Construction Health and Safety (H&S) 1881 Financial Provision for Construction Health and Safety (H&S) John SMALLWOOD 1 and Fidelis EMUZE 2 1 Department of Construction Management, Nelson Mandela Metropolitan University, P.O. Box 77000, Port

More information

3. The Building Cost Information Service BCIS

3. The Building Cost Information Service BCIS 3. The Building Cost Information Service BCIS 3.1 Generally This service, originally titled the Building Cost Advisory Service was set up by the Royal Institution of Chartered Surveyors in 1962 to provide

More information

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

APPROACH OF STANDARD DESIGN MODELS IN THE SAUDI MINISTRY OF INTERIOR PROJECTS

APPROACH OF STANDARD DESIGN MODELS IN THE SAUDI MINISTRY OF INTERIOR PROJECTS APPROACH OF STANDARD DESIGN MODELS IN THE SAUDI MINISTRY OF INTERIOR PROJECTS S. Al-Otaibi, M. Osmani and A.D F. Price Department of Civil and Building Engineering, Loughborough University, Loughborough,

More information

The Impact of the Recession on Construction Professional Services. Executive Summary

The Impact of the Recession on Construction Professional Services. Executive Summary The Impact of the Recession on Construction Professional Services Executive Summary Executive summary The headlines The recession in the construction industry has hit the construction professional services

More information

November Introduction. What was your role with the company? Has your business awareness and use of BIM advanced in the last twelve months?

November Introduction. What was your role with the company? Has your business awareness and use of BIM advanced in the last twelve months? November 2016 Executive Summary The second national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed that 76% (67% 2015) of respondents possessed confidence

More information

CONSTRUCTION MANAGER

CONSTRUCTION MANAGER The South African Council for the Project and Construction Management Professions CONSTRUCTION MANAGER IDENTIFICATION OF WORK AND SCOPE OF SERVICES FOR CONSTRUCTION MANAGERS REGISTERED IN TERMS OF THE

More information

PROFESSIONS PRODUCTIVITY PACKAGE

PROFESSIONS PRODUCTIVITY PACKAGE www.contractsondemand.co.za PROFESSIONS PRODUCTIVITY PACKAGE This core Productivity Package has been developed to enable Professional Firms to gain access to Electronic Services / Applications and the

More information

Social Impact Series

Social Impact Series Social Impact Series WESTERN AUSTRALIA Issue #8 July 2017 Outcomes Measurement in the Community Sector: Are we Heading in the Right Direction? Authors: Zoe Callis, Paul Flatau and Ami Seivwright The University

More information

I.T. SURVEY WITHIN THE CONSTRUCTION INDUSTRY OF HONG KONG U.K.'s construct-i.t. health-check in Hong Kong

I.T. SURVEY WITHIN THE CONSTRUCTION INDUSTRY OF HONG KONG U.K.'s construct-i.t. health-check in Hong Kong I.T. SURVEY WITHIN THE CONSTRUCTION INDUSTRY OF HONG KONG U.K.'s construct-i.t. health-check in Hong Kong K.G.FUTCHER Department of Civil Engineering, University of Loughborough, Great Britain S.ROWLINSON

More information

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main

More information

The role of Evidence and Research in Local Government. Local Government Knowledge Navigator. Tim Allen, Clive Grace and Steve Martin

The role of Evidence and Research in Local Government. Local Government Knowledge Navigator. Tim Allen, Clive Grace and Steve Martin Local Government Knowledge Navigator The role of Evidence and Research in Local Government Results of a Local Government Knowledge Navigator survey initiated by the Society of Local Authority Chief Executives

More information

Guidance Note on the College Internal Audit Service

Guidance Note on the College Internal Audit Service THE FURTHER EDUCATION FUNDING COUNCIL Guidance Note on the College Internal Audit Service Supplement B to Audit Code of Practice CONTENTS Paragraph Introduction 1 Internal audit 2 Provision of service

More information

The Effect of Employment Status on Investment in Training

The Effect of Employment Status on Investment in Training The Effect of Employment Status on Investment in Training Research Report prepared for CITB and Department for Education and Skills (DfES) by IFF Research Ltd April 2003 TABLE OF CONTENTS 1 INTRODUCTION...

More information

Job description. 1. Job details. 2. Organisational position. Director of Asset Management. Asset Management. 3. Overall purpose of job

Job description. 1. Job details. 2. Organisational position. Director of Asset Management. Asset Management. 3. Overall purpose of job Langstane Housing Association Ltd 680 King Street Aberdeen AB24 1SL Main Phone No: 01224 423000 Recruitment Phone No: 01224 423178 recruitment@langstane-ha.co.uk Job description Post Development Manager

More information

AN INVESTIGATION INTO CURRENT COST ESTIMATING PRACTICE OF SPECIALIST TRADE CONTRACTORS

AN INVESTIGATION INTO CURRENT COST ESTIMATING PRACTICE OF SPECIALIST TRADE CONTRACTORS AN INVESTIGATION INTO CURRENT COST ESTIMATING PRACTICE OF SPECIALIST TRADE CONTRACTORS Moayad Al-Hasan, Andrew Ross and Richard Kirkham School of the Built Environment, Liverpool John Moores University,

More information

Job Title Quantity Surveyor/Estimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports

Job Title Quantity Surveyor/Estimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports Job Description and Person Specification Job Title Quantity Surveyor/stimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports Other Resources

More information

Project Success A Survey. Adam Collins. Broad Construction Services. 82 Royal Street. East Perth Western Australia.

Project Success A Survey. Adam Collins. Broad Construction Services. 82 Royal Street. East Perth Western Australia. Project Success A Survey Adam Collins Broad Construction Services 82 Royal Street East Perth 6004 Western Australia David Baccarini* School of Architecture, Construction & Planning Curtin University of

More information

Blue List. Green List. Civil Engineering Commercial Training Courses

Blue List. Green List. Civil Engineering Commercial Training Courses Blue List Green List Civil Engineering Commercial Training Courses From SURCO, the information business of the Chartered Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Chartered Institution of

More information

Request for Proposal For: 2018 American Bar Association Temporary Services

Request for Proposal For: 2018 American Bar Association Temporary Services Table of Contents Bid Timetable [2] 1.0 General Bid Information [3] 2.0 Proposal Requirements [5] 3.0 Criteria for Selection [7] 4.0 Specifications and Work Statement [7] Appendix A: Bidder Response Sheet

More information

IMPLEMENTING OCCUPATIONAL HEALTH AND SAFETY IN SMALL CONSTRUCTION ENTERPRISES

IMPLEMENTING OCCUPATIONAL HEALTH AND SAFETY IN SMALL CONSTRUCTION ENTERPRISES IMPLEMENTING OCCUPATIONAL HEALTH AND SAFETY IN SMALL CONSTRUCTION ENTERPRISES Anthony Mills, School of Property Construction and Project Management, Royal Melbourne Institute of Technology, Melbourne,

More information

Appraising the State of Procurement Methods on Educational Building Projects in Abuja, Nigeria

Appraising the State of Procurement Methods on Educational Building Projects in Abuja, Nigeria Appraising the State of Procurement Methods on Educational Building Projects in Abuja, Nigeria Aje, Isaac O., Adedokun, Olufisayo A., & Igbalaye, Wasiu, O. Department of Quantity Surveying School of Environmental

More information

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3 Prescription of qualifications ARB Criteria at Parts 1, 2 and 3 Approved: January 2010 Effective From: 2011/2012 Introduction Under the Architects Act 1997, the Architects Registration Board (ARB) has

More information

Quick guides to applying for ICES membership

Quick guides to applying for ICES membership Quick guides to applying for ICES membership 1 Contents Submitting your application..3 Applying to become an Affiliate.....4 Applying to become a Student member.....5 Applying to become a Graduate member....6

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

PROCSA CLIENT/CONSULTANT AGREEMENTS WEBINAR 2017

PROCSA CLIENT/CONSULTANT AGREEMENTS WEBINAR 2017 Professional Client Consultants Services Agreement PROCSA CLIENT/CONSULTANT AGREEMENTS WEBINAR 2017 Category 1 CPD Accredited by PROCSA Constituent Bodies This Series of Training Webinars is organised

More information

CLOSING DATE: INSETA. Recognition of Prior Learning Portfolio of Evidence for, Level. (Full Names) Identity number:

CLOSING DATE: INSETA. Recognition of Prior Learning Portfolio of Evidence for, Level. (Full Names) Identity number: 1 INSETA Recognition of Prior Learning Portfolio of Evidence for, Level A: CANDIDATE Candidate details: (Full Names) Identity number: Contact Tel No of Candidate: (H) (W) (C) Email Address: Address of

More information

What is your role with the company? Has your business awareness and use of BIM advanced in the last twelve months?

What is your role with the company? Has your business awareness and use of BIM advanced in the last twelve months? Organisation Type Nr Architecture 8 Engineering Consultancy 9 The third national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed a rise in the number

More information

COMPLEXITY OF STATUTORY REQUIREMENTS: CASE STUDY OF REFURBISHMENT PROJECTS IN MALAYSIA. * Azlan Shah Ali & 2 Rohayati Zakaria

COMPLEXITY OF STATUTORY REQUIREMENTS: CASE STUDY OF REFURBISHMENT PROJECTS IN MALAYSIA. * Azlan Shah Ali & 2 Rohayati Zakaria COMPLEXITY OF STATUTORY REQUIREMENTS: CASE STUDY OF REFURBISHMENT PROJECTS IN MALAYSIA * Azlan Shah Ali & 2 Rohayati Zakaria * Centre for Construction, Building and Urban Studies, Faculty of Built Environment,

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

FOREWORD... 3 INTRODUCTION... 4 EXECUTIVE SUMMARY... 5 RESEARCH METHODOLOGY Outline of the survey questionnaire... 6 SURVEY RESULTS...

FOREWORD... 3 INTRODUCTION... 4 EXECUTIVE SUMMARY... 5 RESEARCH METHODOLOGY Outline of the survey questionnaire... 6 SURVEY RESULTS... Contents FOREWORD... 3 INTRODUCTION... 4 EXECUTIVE SUMMARY... 5 RESEARCH METHODOLOGY... 6 Outline of the survey questionnaire... 6 SURVEY RESULTS... 6 Demographic data... 6 Survey Responses... 7 Open-ended

More information

HKIS QSD PQSL Series 2014

HKIS QSD PQSL Series 2014 HKIS QSD PQSL Series 2014 by Sr. TANG Ki-cheung FHKIS RPS(QS) FSZCEA MHKIVM Director of K C Tang Consultants Ltd. Quantity Surveyors. Construction Cost and Contract Consultants Ltd. on 9 May 2014 (Friday)

More information

THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA

THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA 034 THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA Azlan Shah Ali CEBUS, Faculty of Built Environment, University of Malaya 50603 Kuala Lumpur Email: asafab@um.edu.my

More information

Shetland Social Enterprise Review. Executive Summary

Shetland Social Enterprise Review. Executive Summary Shetland Social Enterprise Review Executive Summary January 2011 Voluntary Action Shetland, Shetland Islands Council and Highlands & Islands Enterprise Shetland Social Enterprise Review January 2011 Anderson

More information

CPD FRAMEWORK EVALUATION DOCUMENT

CPD FRAMEWORK EVALUATION DOCUMENT CPD FRAMEWORK EVALUATION DOCUMENT 1.0: INTRODUCTION The ASAQS Board appointed a committee to develop a Continuing Professional Development (CPD) Evaluation Framework that is in line with the CPD Policy

More information

INSTITUTE OF DIRECTORS

INSTITUTE OF DIRECTORS Mr Norman Murray, Audit Firm Governance Working Group, Chartered Accountants Hall, PO Box 433, Moorgate Place, London EC2P 2BJ. 9 February 2009 Dear Mr Murray, Audit Firm Governance: Evidence Gathering

More information

DBB, DB or DBM? Performance of Road Project Delivery Methods

DBB, DB or DBM? Performance of Road Project Delivery Methods DBB, DB or DBM? Performance of Road Project Delivery Methods Tiina Koppinen VTT Technical Research Centre of Finland (email: Tiina.Koppinen@vtt.fi) Pertti Lahdenperä VTT Technical Research Centre of Finland

More information

Sustainability and Legacy of Strategy Projects

Sustainability and Legacy of Strategy Projects Sustainability and Legacy of Strategy Projects Evaluation of the Stronger Families and Communities Strategy 2000-2004 Written by Associate Professor Patricia Rogers Ms Sue Kimberley Associate Professor

More information

Design Team Procedures Practice Note 1, February DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2)

Design Team Procedures Practice Note 1, February DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2) DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2) CHANGES TO STAGE 2b, STAGE 3 & STAGE 4 ARISING FROM AMENDMENTS TO THE PUBLIC WORKS CONTRACTS 1. Introduction 1.1 Changes to Public Works Contracts (a)

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Abstract. Keywords: Contracting Quantity Surveyor, Flow Activities, Lean Concepts, Sri Lankan construction industry. 1. Background

Abstract. Keywords: Contracting Quantity Surveyor, Flow Activities, Lean Concepts, Sri Lankan construction industry. 1. Background Acceptability of Lean Concepts to Functions of Quantity Surveyor in Sri Lanka Nissanka N.A.L.N., Department of Building Economics, University of Moratuwa (email: nimmiabc@yahoo.com ) Sepani Senarathne.,

More information

Boralex. Survey of Residents of Kirknewton and West Calder & Harburn Community Council Areas on Revised Proposal for a Wind Farm at Fauch Hill

Boralex. Survey of Residents of Kirknewton and West Calder & Harburn Community Council Areas on Revised Proposal for a Wind Farm at Fauch Hill Boralex Survey of Residents of and Community Council Areas on Revised Proposal for a Wind Farm at Fauch Hill Final Report March 2017 Contents Page Summary of Findings 1.0 Background, Objectives and Methodology

More information

NON BINDING GUIDANCE TO ENSURE A MINIMUM

NON BINDING GUIDANCE TO ENSURE A MINIMUM Doc.1598_EN NON BINDING GUIDANCE TO ENSURE A MINIMUM STANDARD OF COMPETENCE OF PERSONS WHO CARRY- OUT PERIODIC AND ASSEMBLY EXAMINATIONS OF TOWER AND MOBILE CRANES SLIC - Senior Labour Inspectors Committee

More information

AgriProfit$ Economics and Competitiveness. The Economics of Sugar Beet Production in Alberta 2007

AgriProfit$ Economics and Competitiveness. The Economics of Sugar Beet Production in Alberta 2007 AgriProfit$ Economics and Competitiveness The Economics of Sugar Beet Production in Alberta 2007 AGDEX 171/821-5 December, 2008 THE ECONOMICS OF SUGAR BEET PRODUCTION IN ALBERTA 2007 G. Nabi Chaudhary

More information

CONSTRUCTION TIME PERFORMANCE IN MULTI- UNIT RESIDENTIAL CONSTRUCTION -INSIGHTS INTO THE ROLE OF PROCUREMENT METHODS

CONSTRUCTION TIME PERFORMANCE IN MULTI- UNIT RESIDENTIAL CONSTRUCTION -INSIGHTS INTO THE ROLE OF PROCUREMENT METHODS CONSTRUCTION TIME PERFORMANCE IN MULTI- UNIT RESIDENTIAL CONSTRUCTION -INSIGHTS INTO THE ROLE OF PROCUREMENT METHODS Derek H.T. Walker 1 and Mark W. Vines Department of Building and Construction Economics,

More information

Identifying the Level of Awareness on Value Management Practice amongst Construction Developers

Identifying the Level of Awareness on Value Management Practice amongst Construction Developers MAT EC Web of Conferences 15, 010 29 (2014) DOI: 10.1051/ matecconf/ 201415 01029 C Owned by the authors, published by EDP Sciences, 2014 Identifying the Level of Awareness on Value Management Practice

More information

Paper P6 Management Accounting Business Strategy Post Exam Guide May 2007 Examination

Paper P6 Management Accounting Business Strategy Post Exam Guide May 2007 Examination General Comments This examination paper is designed to test the candidates ability to demonstrate their understanding and application of the following key syllabus areas: The evaluation of a product portfolio

More information

The Brickfields Trust. Procurement and Tendering Policy and Procedures

The Brickfields Trust. Procurement and Tendering Policy and Procedures Procurement and Tendering Policy and Procedures CONTENTS PAGE NO: 1. QUOTATION AND TENDERING... 3 2. PROCEDURES... 3 3. ACCEPTANCE OF TENDER... 4 4. UNSUCCESSFUL BIDS... 5 2 1. QUOTATION AND TENDERING

More information

Working to. Becoming professionally registered through the IET. Stephanie Smith Professional Registration Account Manager

Working to. Becoming professionally registered through the IET. Stephanie Smith Professional Registration Account Manager Working to engineer a better world Becoming professionally registered through the IET Stephanie Smith Professional Registration Account Manager 1 Agenda What next? The IET Application Form Professional

More information

Hazardous. Scheme. the power behind your business

Hazardous. Scheme. the power behind your business Hazardous Areas Scheme YOUR GUIDE TO REGISTRATION the power behind your business GUIDE TO REGISTRATION REQUIREMENTS Electrical work in potentially explosive atmospheres (hazardous areas) is not included

More information

Decision Making Delays with Regard to IT Investments

Decision Making Delays with Regard to IT Investments Available online at www.sciencedirect.com Procedia - Social and Behavioral Sciences 40 ( 2012 ) 258 263 2012 International Conference of Asia Pacific Business Innovation and Technology Management Decision

More information

Increasing African Participation in International Associations and Their Conferences

Increasing African Participation in International Associations and Their Conferences Increasing African Participation in International Associations and Their Conferences White Paper 22 May 2016 WHITE PAPER: INCREASING AFRICAN PARTICIPATION 22 May 2016 African Agenda 1 With excellent existing

More information

Audit monitoring visits cycle 1 / cycle 2 BUSINESS WITH CONFIDENCE

Audit monitoring visits cycle 1 / cycle 2 BUSINESS WITH CONFIDENCE Audit monitoring visits cycle 1 / cycle 2 Outline Recap on Cycle 1 monitoring activities and findings 2016 support between formal cycles Cycle 2 visit programme Cycle 2 what to expect Recap on cycle 1

More information

Keywords: Rework; Rework costs; Training cost, High rise construction, Indonesia.

Keywords: Rework; Rework costs; Training cost, High rise construction, Indonesia. 1 INVESTIGATION INTO THE RELATIONSHIP BETWEEN REWORK AND SITE SUPERVISION IN HIGH RISE BUILDING CONSTRUCTION IN INDONESIA The 2 nd CPR, 12-13 July 1999, Sydney Sugiharto Alwi Tarumanagara University, Jakarta,

More information

POSITION DESCRIPTION DIRECTOR TECHNICAL & DEVELOPMENT SERVICES MANAGER ENGINEERING AND OPERATIONS

POSITION DESCRIPTION DIRECTOR TECHNICAL & DEVELOPMENT SERVICES MANAGER ENGINEERING AND OPERATIONS POSITION DESCRIPTION POSITION: DESIGN OFFICER CLASSIFICATION: BAND 4 DEPARTMENT: SECTION: OCCUPANT: TECHNICAL & DEVELOPMENT SERVICES ENGINEERING & OPERATIONS VACANT DATE: DECEMBER 2006 REVISED: AUGUST

More information

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research Online Open Access publishing platform for Management Research Copyright by the authors - Licensee IPA- Under Creative Commons license 3.0 Research Article ISSN 2229 3795 Stakeholders perspective on cost

More information

PART C2: PRICING DATA. C2.1 : Pricing Instructions. C2.2 : Bills of Quantities

PART C2: PRICING DATA. C2.1 : Pricing Instructions. C2.2 : Bills of Quantities PART C2: PRICING DATA C2. : Pricing Instructions C2.2 : Bills of Quantities FORM: PRO-FAT-063 Rev02 Page of 6 Pricing Data C2.: Pricing Instructions Introduction These Pricing Preambles set out the basis

More information

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America)

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) 108 Appendix B: Questionnaire 109 CONSTRUCTION MANAGEMENT

More information

James Cook University. Internal Audit Protocol

James Cook University. Internal Audit Protocol James Cook University Internal Audit Protocol Table of Contents A. Introduction 2 B. Management Consultation during the Annual Internal Audit Planning Process 2 C. Support Provided to QAO/External Auditor

More information

Occupational stress and job demand, control and support factors among construction project consultants

Occupational stress and job demand, control and support factors among construction project consultants RESEARCH: SUMMARY SERIES Occupational stress and job demand, control and support factors among construction project consultants Paul Bowen, Peter Edwards, Helen Lingard, Keith Cattell, International Journal

More information

New thinking on benchmarking customer experience. Vicki Howe, Head of Product Development

New thinking on benchmarking customer experience. Vicki Howe, Head of Product Development New thinking on benchmarking customer experience Vicki Howe, Head of Product Development April 2015 Contents 1 Key points... 3 2 Introduction... 4 2a Satisfaction benchmarking from HouseMark... 4 3 Star

More information

UCS PRE-AWARD PROCESS PROJECT DEVELOPMENT CHECKLIST

UCS PRE-AWARD PROCESS PROJECT DEVELOPMENT CHECKLIST UCS PRE-AWARD PROCESS PROJECT DEVELOPMENT CHECKLIST You may find it helpful to consider the prompts below when you are developing your project proposal. Please remember that further support is available

More information

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Appendix B SOUTHERN CROSS UNIVERSITY. Professional Staff Secondary Classification Descriptors

Appendix B SOUTHERN CROSS UNIVERSITY. Professional Staff Secondary Classification Descriptors Appendix B SOUTHERN CROSS UNIVERSITY Professional Staff Secondary Classification Descriptors APPENDIX B INSTRUCTIONS FOR USING THE CLASSIFICATION DESCRIPTIONS 1. These descriptors present the classification

More information

The value of apprentices. A report for the Association of Accounting Technicians March 2014

The value of apprentices. A report for the Association of Accounting Technicians March 2014 The value of apprentices A report for the Association of Accounting Technicians March 2014 Disclaimer Whilst every effort has been made to ensure the accuracy of the material in this document, neither

More information

Registered as a Scottish Charity - No. SC Job Description

Registered as a Scottish Charity - No. SC Job Description Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Salary: Reports To: Neighbourhood Maintenance Surveyor Assets and Investment Selkirk Grade 8, salary

More information

Centre for Mining, Energy and Natural Resources Law

Centre for Mining, Energy and Natural Resources Law Review of the Corporate Governance Principles and Recommendations- Public Consultation 16 August 2013 Submission to ASX Corporate Governance Council Professor John Chandler Assistant Professor Barbara

More information

AgriProfit$ Economics and Competitiveness. The Economics of Sugar Beet Production in Alberta 2008

AgriProfit$ Economics and Competitiveness. The Economics of Sugar Beet Production in Alberta 2008 AgriProfit$ Economics and Competitiveness The Economics of Sugar Beet Production in Alberta 2008 AGDEX 171/821-5 December, 2009 THE ECONOMICS OF SUGAR BEET PRODUCTION IN ALBERTA 2008 G. Nabi Chaudhary

More information

Why Use an Architect?

Why Use an Architect? Architects Can Help Interpret Your Dreams Into A Built Reality Architects provide a service that extends well beyond producing a set of drawings. An architect will listen to your dreams, your aspirations,

More information

Sportnz.org.nz/facilityguide. Sport & Recreation Facility Development Guide

Sportnz.org.nz/facilityguide. Sport & Recreation Facility Development Guide Sportnz.org.nz/facilityguide Sport & Recreation Facility Development Guide INTRODUCTION Background Sport New Zealand s Strategic Plan 2015-20 has a vision for New Zealand to be the world s most successful

More information

REPORT 2014/010 INTERNAL AUDIT DIVISION. Audit of contract administration at the United Nations Office at Geneva

REPORT 2014/010 INTERNAL AUDIT DIVISION. Audit of contract administration at the United Nations Office at Geneva INTERNAL AUDIT DIVISION REPORT 2014/010 Audit of contract administration at the United Nations Office at Geneva Overall results relating to administration of contracts at the United Nations Office at Geneva

More information

A NOTE ON METHODS OF ESTIMATING REGIONAL INPUT-OUTPUT TABLES: CAN THE FLQ IMPROVE THE RAS ALGORITHM?

A NOTE ON METHODS OF ESTIMATING REGIONAL INPUT-OUTPUT TABLES: CAN THE FLQ IMPROVE THE RAS ALGORITHM? A NOTE ON METHODS OF ESTIMATING REGIONAL INPUT-OUTPUT TABLES: CAN THE FLQ IMPROVE THE RAS ALGORITHM? Steven Brand July 2012 Author contact details: Plymouth University Drake s Circus Plymouth PL4 8AA sbrand@plymouth.ac.uk

More information

Waste (Wales) Measure 2010 Site Waste Management Plans

Waste (Wales) Measure 2010 Site Waste Management Plans The Chartered Institute of Building submission to the Welsh Government on the consultation Waste (Wales) Measure 2010 Site Waste Management Plans 24 th April 2013 Waste (Wales) Measure 2010 Site Waste

More information

Financial literacy among Canadian entrepreneurs and business owners

Financial literacy among Canadian entrepreneurs and business owners Financial literacy among Canadian entrepreneurs and business owners Joint project: BDC Research and Market Intelligence, and the Telfer School of Business at the University of Ottawa December 2017 Table

More information

Application of TQM and TSM in UAE Construction Safety Management By: Ghanim Kashwani, PhD, CEng, MICE ADNOC ONSHORE

Application of TQM and TSM in UAE Construction Safety Management By: Ghanim Kashwani, PhD, CEng, MICE ADNOC ONSHORE Application of TQM and TSM in UAE Construction Safety Management By: Ghanim Kashwani, PhD, CEng, MICE 1 ADNOC ONSHORE Outline Introduction Problem statement Research Methodology Results and Discussion

More information

Managing the Risk of Delayed Completion in the 21 st Century. A Summary Report

Managing the Risk of Delayed Completion in the 21 st Century. A Summary Report Managing the Risk of Delayed Completion in the 21 st Century A Summary Report Acknowledgements The CIOB is grateful to all respondents who gave their time and effort in completing the survey. We would

More information

CDM FAQ Sheet

CDM FAQ Sheet CDM 2015 - FAQ Sheet 1. The change to the regulations means Domestic works are now included. What if you are doing DIY in your own house? Do the regulations apply to this? If the home owner is doing the

More information

GCSE EXAMINERS' REPORTS

GCSE EXAMINERS' REPORTS GCSE EXAMINERS' REPORTS BUSINESS STUDIES SUMMER 2016 Grade boundary information for this subject is available on the WJEC public website at: https://www.wjecservices.co.uk/marktoums/default.aspx?l=en Online

More information

NEW ZEALAND GOVERNMENT PROCUREMENT. New Zealand Government Procurement Business Survey 2016

NEW ZEALAND GOVERNMENT PROCUREMENT. New Zealand Government Procurement Business Survey 2016 NEW ZEALAND GOVERNMENT PROCUREMENT New Zealand Government Procurement Business Survey Published August New Zealand Government Procurement PO Box 1473 Wellington 6140 New Zealand www.procurement.govt.nz

More information

Proposal. The Impact of Economic Recession on. Customer Loyalty to Banks

Proposal. The Impact of Economic Recession on. Customer Loyalty to Banks Proposal The Impact of Economic Recession on Customer Loyalty to Banks Copyright Insta Research Ltd. All rights reserved. 1 Table of Contents 1. Introduction and Background...3 2. Aims and Objectives...4

More information

Challenges faced when taking strategic decisions. Results of 2010 Global Survey. Executive Summary

Challenges faced when taking strategic decisions. Results of 2010 Global Survey. Executive Summary Challenges faced when taking strategic decisions Results of 2010 Global Survey Executive Summary December 2010 Introduction In the third quarter of 2010, launched its second global survey to obtain a greater

More information

Previous applicants need not apply. Please note CV s are not accepted. For informal enquiries please contact:

Previous applicants need not apply. Please note CV s are not accepted. For informal enquiries please contact: Birmingham Graduate Opportunities Development Officer Economy Directorate 19,048-24,472 Lancaster Circus Working 36.5 hours per week Fixed term contracts for up to 3 years Birmingham is changing.and fast!

More information

Level 6 NVQ Diploma in Construction Contracting Operations Management

Level 6 NVQ Diploma in Construction Contracting Operations Management Level 6 NVQ Diploma in Construction Contracting Operations Management Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

2009 First Nations Client Survey

2009 First Nations Client Survey TOP-LINE REPORT 2009 First Nations Client Survey Prepared for: Prepared by: Malatest & Associates Ltd. CONTENTS SECTION 1: INTRODUCTION..... 1 1.1 Project Background... 1 1.2 Survey Objectives... 1 1.3

More information

Introduction to Business Research 3

Introduction to Business Research 3 Synopsis Introduction to Business Research 3 1. Orientation By the time the candidate has completed this module, he or she should understand: what has to be submitted for the viva voce examination; what

More information

Gearing Up: Business Readiness for Climate Change

Gearing Up: Business Readiness for Climate Change 5 1 15 2 25 3 35 4 45 5 55 6 65 7 75 Gearing Up: Business Readiness for Climate Change July 29 THIS REPORT IS PRINTED ON HP INDIGO RECYCLED ENVIRO GLOSS The Australian Industry Group, 29 The copyright

More information

Winston. The impetus for CRM. A new paradigm for marketing

Winston. The impetus for CRM. A new paradigm for marketing Papers Janet Winston has 14 years experience in data-driven direct marketing, and was previously CRM Manager at Dolphin Telecommunications. Having just completed an MBA (with distinction) at the University

More information

D39PZ Procurement & Contracts Course Consolidation- Revision and Mock Exam feedback (From Tutors Pack)

D39PZ Procurement & Contracts Course Consolidation- Revision and Mock Exam feedback (From Tutors Pack) D39PZ Procurement & Contracts Course Consolidation- Revision and Mock Exam feedback (From Tutors Pack) Purpose of the Tutorial Session: Provide feedback to the students on the mock exam and an overview

More information

Institute of Leadership & Management. Creating a coaching culture

Institute of Leadership & Management. Creating a coaching culture Institute of Leadership & Management Creating a coaching culture Contents Introduction 01 Executive summary 02 Research findings 03 Conclusion 07 Methodology 08 Introduction The world of work is complex

More information

COSCCOMO12 - SQA Unit Code FM7D 04 Obtain tenders and appoint successful contractors in construction contracting operations management

COSCCOMO12 - SQA Unit Code FM7D 04 Obtain tenders and appoint successful contractors in construction contracting operations management Obtain tenders and appoint successful contractors in construction Overview This unit is about shortlisting and selecting appropriate tenderers. It is also the about the review and amendment of tender documents

More information

Own Motion Inquiry: Compliance with Standard 8 of the 2014 Insurance Brokers Code of Practice ( Code Training )

Own Motion Inquiry: Compliance with Standard 8 of the 2014 Insurance Brokers Code of Practice ( Code Training ) REPORT Own Motion Inquiry: Compliance with Standard 8 of the 2014 Insurance Brokers Code of Practice ( Code Training ) December 2014 IBCCC Report: Own Motion Inquiry Code Training Page 1 of 27 Contents

More information

Digital Industries Apprenticeship: Assessment Plan. Unified Communications Technician. Published in November 2016

Digital Industries Apprenticeship: Assessment Plan. Unified Communications Technician. Published in November 2016 Digital Industries Apprenticeship: Assessment Plan Unified Communications Technician Published in November 2016 1 Digital Industries Apprenticeships: Assessment Plan General Introduction and Overview The

More information

For the first time in the history of corporate financial reporting and. Management Reporting on Internal Control. Use of COSO 1992 in.

For the first time in the history of corporate financial reporting and. Management Reporting on Internal Control. Use of COSO 1992 in. Cover Story Use of COSO 1992 in Management Reporting on Internal Control THE COSO FRAMEWORK provides an integrated framework that identifies components and objectives of internal control. But does it set

More information