1 Innovations in Joint Restraint Systems for PVC Pressure Pipe S&B TECHNICAL PRODUCTS, INC EAST BERRY STREET FT. WORTH, TEXAS PH: FX:

2 What or Who Is Bulldog Restraint System?

3 About S&B Technical Products / Hultec S&B Technical Products is a family-owned business, founded in 1981 Core Business is Pipe Sealing Systems Elastomeric / Rubber Products for Pipelines & Appurtenances Largest Pipe Seals Market Share in the World (85-90% of North American Market, 50% of European Market) Other Businesses Include Rubber and Specialty Products for Oil and Gas Industry, and Corrosion Protection Systems. Products are Sold in Over 70 Countries

4 Offices, Warehouses & Manufacturing Worldwide USA Mexico Costa Rica Columbia Poland Germany France Turkey Romania China Vietnam Office Manufacturing /Splicing Warehouse Brazil Argentina Australia

5 Product Sales Worldwide Direct and/or Indirect Sales of Products

6 About S&B Technical Products / Global Technological Leaders in Pipe Sealing Solutions More Than 60 Patents and Patents Pending, More Than All Our Competitors Combined Engineers, Chemists and Scientists Provide the Best Technological Solutions to Meet Customers Needs Hultec

7 Today s Discussion Containing Thrust Forces Case Histories

8 Containing Thrust Forces

9 How Are Thrust Forces Contained? Concrete Thrust Blocks Mechanical Restraints

10 Design Guidance

11 Thrust Blocks Function: Transfer and Distribute Thrust Forces in Pipeline to Surrounding Soil Structure

12 Thrust Blocks

13 Disadvantages of Thrust Blocks Replication of Design in the Field Soil Bearing Capacity of In-situ Soils Availability of Space Time Required for Concrete to Dry & Cure Future Excavations

14 Mechanical Joint Restraint

15 Joint Restraint Options Hardware to track. Hardware time consuming to install. Exposed metal components have their own corrosion issues

16 Today s Discussion Containing Thrust Forces Case Histories

17 Today s Discussion Case Histories from Texas, Minnesota,

18 First Texan Case History: City of McKinney, Texas 6 Cast Iron water pipe serving approximately 18 homes Red water complaints City s Paving Department preparing to pave the street Designed new 1,110 Linear Feet of 8 PVC Water Pipe offset from existing main

19 First tie-in: Beyond a 6X8 reducer, several 8-inch MJ Field Lok- PV self restraining gaskets were used for fitting-to-pipe connections, as well as the BullDog for pipe-to-pipe connections. First Texan Case History: City of McKinney, Texas

20 First Texan Case History: City of McKinney, Texas

21 First Texan Case History: City of McKinney, Texas

22 Second tie-in: Three joints of BullDog Pipe were used. Joint restraints were utilized at valveto-pipe joints, pipe-to-pipe joint, pipe-to-reducer joints, and pipeto-fitting joints First Texan Case History: City of McKinney, Texas

23 First Texan Case History: City of McKinney, Texas

24 First Texan Case History: City of McKinney, Texas Successful installation Less install time compared to traditional materials No waiting for concrete to cure. Backfilled and ready for pavement repairs by the end of the day

25 Second Texan Case History: McKinney, Texas, Fabricated Fittings

26 Second Texan Case History: McKinney, Texas, Fabricated Fittings

27 Second Case History: McKinney, Texas, Fabricated Fittings

28 Third Texan Case History: City of Garland, Texas, Casing Installation

29 Third Texan Case History: City of Garland, Texas, Casing Installation

30 Third Texan Case History: City of Garland, Texas, Casing Installation

31 Third Case History: City of Garland, Texas, Casing Installation

32 Today s Discussion Case Histories from Texas, Minnesota,

33 South Saint Paul, Minnesota 4,400 lineal feet of 8-inch C900 DR18 (28) 8-inch fabricated PVC pressure fittings cross tees 90 bend 45 bends 22.5 bends bend

34 Site Conditions Water table above trench bottom 0.5 Miles from Mississippi floodplain Peats and sands, very poor trench conditions Many old, abandoned shallow drains Some blue clay at trench bottom Design called for all joints to be restrained

35 Commercial Development Bridgepoint Business Park On-site water service The site was a slaughterhouse since 1886

36 Fabricated PVC Pressure Fittings

37 Wet Conditions

38 Wet Conditions

39 Wet Conditions

40 Eagle Claw for Fitting Assembly

41 Eagle Claw for Fitting Assembly

42 Acceptance Testing All pipe and fittings joints passed the pressure test 150 psi minimum for 48 hours One segment was at 150 psi for 15 days.

43 South Saint Paul, Minnesota South Saint Paul City Engineer, John Sachi

44 South Saint Paul, Minnesota Bridgepoint Business Park Contractor, Bob Bruley, Frattalone Company

45 Today s Discussion Containing Thrust Forces Case Histories

46 Internal Joint Restraint Solution

47 Innovations in Joint Restraint Systems for PVC Pressure Pipe S&B TECHNICAL PRODUCTS, INC EAST BERRY STREET FT. WORTH, TEXAS PH: FX:

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015 Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings Clean & Safe Drinking Water Workshop Wednesday, March 25, 2015 Thrust forces Gasketed joints are made to seal and not to restrain,

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860)

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860) City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT 06457 TEL: (860) 638-3500 FAX: (860) 343-8091 GENERAL REQUIREMENTS SANITARY SEWER MAIN AND LATERAL INSTALLATION JANUARY 2017

More information

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE PART 1 - GENERAL 1.1 DESCRIPTION A. This section designates the requirements for the manufacture and installation of polyvinyl chloride, abbreviated PVC, pressure pipe. 1.2 RELATED WORK SPECIFIED ELSEWHERE

More information

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1993 Specifications CSJ 0144-01-060 SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1. General. (1) Scope. This Section includes the furnishing, installation, and subsequent

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 33 11 13.24 POLYETHYLENE PRESSURE PIPE PART 1 GENERAL... 2 1.1 Description... 2 1.2 Reference Specification... 2 1.3

More information

DUCTILE IRON PIPE AND FITTINGS

DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

PVC PRESSURE FITTINGS

PVC PRESSURE FITTINGS GUIDE FOR PVC PRESSURE FITTINGS TABLE OF CONTENTS Introduction 3 Standards and Specifications 3 Products 4 Manufacturing Methods 8 Fabricated Fittings 8 Injection-Molded Fittings 9 Machined Couplings 9

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

SECTION VII WATER. Concrete anchor and thrust blocks shall be provided at all discontinuities in accordance with Standard Details G-7.1 and G-7.2.

SECTION VII WATER. Concrete anchor and thrust blocks shall be provided at all discontinuities in accordance with Standard Details G-7.1 and G-7.2. SECTION VII WATER VII-1. DESIGN GUIDELINES Water pipelines and appurtenant structures within the jurisdiction of the City of Paso Robles shall be constructed in accordance with plans prepared by a Professional

More information

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated.

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated. SECTION 221316 SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA

SECTION WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA SECTION 6900 - WATER MAINS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA 6901 DESIGN CRITERIA A. General 1. The design standards presented in the City of Lee's Summit Design Criteria are the minimum standards

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Inspector. 812.2 SUBMITTALS: Contractor

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Plastic (PVC) Pressure Water Pipe & Fittings C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Plastic (PVC) Pressure Water Pipe & Fittings C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 15064 - Plastic (PVC) Pressure Water Pipe & Fittings C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 DELIVERY... 1 1.03 QUALITY ASSURANCE...

More information

Engineering Design Center. Standard Drawings. 1st Edition -January 2016

Engineering Design Center. Standard Drawings. 1st Edition -January 2016 Engineering Design Center Standard Drawings 1st Edition -January 2016 Golden State Water Company Standard Drawings 1/11/2016 Table of Contents PART A STANDARD DRAWINGS Section I Pipeline Construction P-1

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Engineer. 812.2 MATERIALS: The

More information

Presented By: Justin C Piccillo, P.E.

Presented By: Justin C Piccillo, P.E. Presented By: Justin C Piccillo, P.E. What Not To Do With Storm Pipe A Brief History of Pipe The Romans were the first to use aqueducts, for running water and sewer History of Storm/Sanitary Sewer Pipe

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860)

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860) City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT 06457 TEL: (860) 638-3500 FAX: (860) 343-8091 GENERAL REQUIREMENTS WATER MAIN AND SERVICE INSTALLATION JANUARY 2017 WATER MAINS:

More information

STANDARD DETAILS. Revised January Bonita Springs Utilities, Inc East Terry Street (239)

STANDARD DETAILS. Revised January Bonita Springs Utilities, Inc East Terry Street (239) STANDARD DETAILS Revised January 2018 Bonita Springs Utilities, Inc. 11900 East Terry Street Bonita Springs, FL 34135 (239) 992-0711 DETAIL SHEET INDEX WATER DETAILS W-1 CONSTRUCTION JUMPER ASSEMBLY W-2

More information

SECTION SANITARY SEWER SYSTEM

SECTION SANITARY SEWER SYSTEM SECTION 02530 SANITARY SEWER SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Section includes sanitary sewer system piping for collection of wastewater. B. Related Sections include but are not limited to: 1. Division

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

C900/RJ. CertainTeed. PVC Pipe. with CertainTeed s proven Certa-Lok restrained joint system. Directional Drilling

C900/RJ. CertainTeed. PVC Pipe. with CertainTeed s proven Certa-Lok restrained joint system. Directional Drilling 1 1 CertainTeed C900/RJ PVC Pipe with CertainTeed s proven Certa-Lok restrained joint system Directional Drilling Underground Water Mains and Restrained, Non-Metallic Change-of-Direction Fittings (No Thrust

More information

November 29, CITY OF PLANT CITY Purchasing Division (813)

November 29, CITY OF PLANT CITY Purchasing Division (813) November 29, 2018 CITY OF PLANT CITY Purchasing Division (813) 659-4270 IFB 18-014UM-LG 12-inch Water Transmission Main-Franklin St., Hancock St. and Terrace Drive West ADDENDUM No. 3 *Bidders are required

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 02080 FIRE HYDRANTS PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified The work specified shall include all labor, material, equipment, tools, services and incidentals necessary to furnish and

More information

SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017

SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017 SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017 STANDARD SPECIFICATIONS 102.12 Best Value Contracting Partial payments shall be withheld if contractor is working on site and has not satisfied

More information

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE SECTION 02632 POLYVINYL CHLORIDE (PVC) WATERLINE PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required, and install polyvinyl chloride (PVC) waterline,

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Furnish and Install PVC Force Main C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Furnish and Install PVC Force Main C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 02768 - Furnish and Install PVC Force Main C O N T E N T S PART 1 - GENERAL... 1 1.01 DESCRIPTION... 1 1.02 QUALITY ASSURANCE... 1 1.03 SUBMITTALS... 1 1.04

More information

CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE

CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE 1000.1 DESCRIPTION These specifications shall govern the furnishing of glass-fiber reinforced

More information

c. Sprinkler layout. Sprinkler layout may be modified to adjust for field conditions provided it complies with part

c. Sprinkler layout. Sprinkler layout may be modified to adjust for field conditions provided it complies with part Florida Building Code Plumbing APPENDIX F, 5 th Edition (2014) Amendment to APPENDIX F c. Sprinkler layout. Sprinkler layout may be modified to adjust for field conditions provided it complies with part

More information

2017 EDITION WELDED OUTLETS DUCTILE IRON NSF FOR WATER & WASTEWATER, FIRE PROTECTION & INDUSTRIAL APPLICATIONS. Certified to ANSI/NSF 61

2017 EDITION WELDED OUTLETS DUCTILE IRON NSF FOR WATER & WASTEWATER, FIRE PROTECTION & INDUSTRIAL APPLICATIONS. Certified to ANSI/NSF 61 DUCTILE IRON FOR WATER & WASTEWATER, FIRE PROTECTION & INDUSTRIAL APPLICATIONS Certified to 2 Table of Contents Welded Outlets/Specifications 3-4 Radial/Tangential Outlets 5-6 Welded Outlets Design Guidelines

More information

CONDITIONS EXISTING EXISTING CONDITIONS SURVEY PROVIDED BY EGAN, FIELD & NOWAK ON FEBRUARY 20, PRELIMINARY - NOT FOR CONSTRUCTION

CONDITIONS EXISTING EXISTING CONDITIONS SURVEY PROVIDED BY EGAN, FIELD & NOWAK ON FEBRUARY 20, PRELIMINARY - NOT FOR CONSTRUCTION K:\TWC_LDEV\\ABRA\Maple Grove, \ Design\CAD\PlanSheets\C- CONDITIONS.dwg April 4, 018 - :44pm 40 0 8 CONDITIONS SURVEY PROVIDED EGAN, FIELD & NOWAK ON FEBRUARY 0, 018. LIMITS OF CONSTRUCTION OVERHEAD POWER

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

Figure 1, Casing Installed Under A Road.

Figure 1, Casing Installed Under A Road. TO: Bulldog Licensees FROM: Craig Fisher, P.E. DATE: November 2, 2009 SUBJECT: Bulldog for Casing Applications MEMORA DUM A casing is often required for utilities installed within the Right-of-Way (ROW)

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

QuakeWrap, Inc. Pipe Repair October 2012

QuakeWrap, Inc. Pipe Repair October 2012 History Innovative Applications of Carbon FRP in Pipelines Mo Ehsani, Ph.D., P.E., S.E. President, PipeMedic, LLC and Professor Emeritus of Civil Engineering, Univ. of Arizona QuakeWrap, Inc. was founded

More information

PART 5 WATER SYSTEMS

PART 5 WATER SYSTEMS PART 5 WATER SYSTEMS Abbreviations and Symbols Plan 501 Abbreviations and symbols for water... 205 Concrete Boxes and Hardware 502 27" Frame and cover... 207 503 38" Frame and cover... 209 505 Concrete

More information

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS)

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) 00950 - Measurement & Payment Page 00950-1 00950 - MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) (Last revised 5/20/10) SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Base Course & Paving Curb & Gutter,

More information

7. Allowable Fittings.

7. Allowable Fittings. 7. Allowable Fittings. a. General Requirements. 1) The fittings listed in this section are generally the allowable fittings for the design of DIP and PVC pipe. For steel pipe and fittings, see Part One,

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 GENERAL 1.01 SUMMARY This Section includes ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE 4 3 2 1 D D C C B B A A 4 3 2 1 Thrust Restraint Design Equations and Soil Parameters These equations and soil

More information

UNI-BELL PVC PIPE ASSOCIATION UNI-B-15-10

UNI-BELL PVC PIPE ASSOCIATION UNI-B-15-10 UNI-BELL PVC PIPE ASSOCIATION UNI-B-15-10 RECOMMENDED STANDARD SPECIFICATION FOR POLYVINYL CHLORIDE (PVC) FABRICATED PRESSURE FITTINGS November 2010 UNI-BELL PVC PIPE ASSOCIATION 2711 LBJ Freeway, Suite

More information

C900/RJ. CertainTeed. PVC Pipe. with CertainTeed s proven Certa-Lok restrained joint system. Directional Drilling

C900/RJ. CertainTeed. PVC Pipe. with CertainTeed s proven Certa-Lok restrained joint system. Directional Drilling 1 CertainTeed C900/RJ PVC Pipe with CertainTeed s proven Certa-Lok restrained joint system Directional Drilling Underground Water Mains and Restrained, Non-Metallic Change-of-Direction Fittings (No Thrust

More information

1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings

1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings SECTION 33 34 00 SANITARY FORCE MAIN PART 1 GENERAL 1.1 SCOPE OF WORK A. This section specifies the requirements for furnishing and installing sanitary force main and appurtenances. The pipe shall be of

More information

WATER MAIN EXTENSION DESIGN REQUIREMENTS

WATER MAIN EXTENSION DESIGN REQUIREMENTS This guideline provides minimum requirements for the design of new water main extensions. This guide is not to be used as a substitution for the detailed design of the water system. The Developer s Engineer

More information

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa).

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa). SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS UTILITY LINE INSTALLATION REQUIREMENTS Index 26.01 JACK AND BORE OPERATIONS 26.02 PRESSURE PIPE RESTRAINT 26.03 PRESSURE CONNECTION BACK TO TABLE OF CONTENTS Section 26.01 JACK AND BORE OPERATIONS 26.01.01

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION

SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION A. CONSTRUCTION STEPS

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

Introduction to Aerated Floor Systems for Vapor Intrusion Mitigation

Introduction to Aerated Floor Systems for Vapor Intrusion Mitigation 2 nd Southeastern States Vapor Intrusion Symposium Introduction to Aerated Floor Systems for Vapor Intrusion Mitigation Atlanta, GA April 28, 2016 Justin Knight, P.E. Agenda Vapor Intrusion (VI) Conceptual

More information

Section 3 Fusible PVC Pipe Connections

Section 3 Fusible PVC Pipe Connections 3.0 Fusible PVC pipe is joined together using butt-fusion joints, however, it may be necessary to utilize other connections to integrate Fusible PVC pipe sections into an overall pipe system. There are

More information

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS 1109.1 DESCRIPTION: ITEM NO. 1109 SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS 1. Installation of sanitary sewer lateral stub outs in sanitary sewer mains serving areas where service did not previously

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 5100 - SANITARY SEWER MAIN PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of sanitary sewer mains and services. Topics include permits and fees, record drawings, pipe materials,

More information

CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER

CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER CITY OF WARRENVILLE STANDARD SPECIFICATIONS WATER MAIN, SANITARY SEWER AND STORM SEWER WATER MAIN 1. All open cut water main shall be polyvinyl chloride plastic (PVC) pressure pipe per AWWA specification

More information

Stanford University Facilities Design Guidelines SECTION UNDERGROUND CHILLED WATER SYSTEM. D. Section : Domestic & Lake Water Systems

Stanford University Facilities Design Guidelines SECTION UNDERGROUND CHILLED WATER SYSTEM. D. Section : Domestic & Lake Water Systems SECTION 33 61 01 UNDERGROUND CHILLED WATER SYSTEM PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 31 00 00: Earthwork C. Section 31 23 00: Excavation and Fill D. Section

More information

1 Exam Prep Installation Guide to Ductile Iron Pipe Questions and Answers

1 Exam Prep Installation Guide to Ductile Iron Pipe Questions and Answers 1 Exam Prep Installation Guide to uctile Iron Pipe Questions and nswers 1 uctile iron pipe to be moved a short distance may? e pushed or dragged Not be pushed or dragged Not be rolled by hand Not be lifted

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

Underground Piping for Private Hydrants & Sprinkler Supply Line

Underground Piping for Private Hydrants & Sprinkler Supply Line City of Brea Brea Fire Department Fire Prevention 1 Civic Center Circle Phone: (714) 990-7655 Underground Piping for Private Hydrants & Sprinkler Supply Line PURPOSE The provision of adequate water supplies

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO.

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. 2017-1 43 SOUTH GRANVILLE WATER AND SEWER AUTHORITY H STREET BY-PASS

More information

DUO-THERM 505 Specification Guide

DUO-THERM 505 Specification Guide STANDARD SPECIFICATION 3.101 7.01.08 Part 1 - General Duo - Therm 505 Steel Piping Systems suitable for Steam, High Temperature Hot Water, Gravity and Pumped Condensate. 1.1 Pre-insulated Piping - Furnish

More information

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS Rev: 3/26/18 Pipe and fittings used in sanitary sewer construction shall

More information

***************************************************************************************************************

*************************************************************************************************************** 02732 SANITARY FORCE MAIN *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 34 00. ***************************************************************************************************************

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

B. Fiberglass for construction in back lot easements placed on cast-in-place base.

B. Fiberglass for construction in back lot easements placed on cast-in-place base. Section 02083 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Fiberglass manholes for unpaved areas placed on top of a precast base to form a manhole. B. Fiberglass for construction in back lot easements

More information

Water & Industrial Products Catalog

Water & Industrial Products Catalog Water & Industrial Products Catalog www.smith-blair.com info@smith-blair.com Phone: 800..9705 or 870.77.527 After Hours Number: 90.277.998 Fax: 800.8.792 or 870.77.52 EMERGENCY PHONE 90.277.998 In the

More information

A. This Section includes gravity-flow, nonpressure storm drainage outside the building, with the following components:

A. This Section includes gravity-flow, nonpressure storm drainage outside the building, with the following components: SECTION 334100 - STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.I RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction. General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting

More information

CHAPTER 8 WATER SUPPLY SYSTEM

CHAPTER 8 WATER SUPPLY SYSTEM CHAPTER 8 WATER SUPPLY SYSTEM 8-1 INTRODUCTION These improvement standards shall govern the engineering design of all domestic water systems intended for operation and maintenance by the County of Sutter

More information

Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA TMWA Capital Project No.: October 3, 2018

Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA TMWA Capital Project No.: October 3, 2018 Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA-2019-004 TMWA Capital Project No.: 10-0001.053 October 3, 2018 The following information, clarifications, changes and modifications are by reference

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 1413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

Series 2000PV Mechanical Joint Restraint for PVC Pipe

Series 2000PV Mechanical Joint Restraint for PVC Pipe Series 2000PV Mechanical Joint Restraint for PVC Pipe Features and Applications: For restraining plain end PVC pipe at mechanical joint fittings and appurtenances Sizes 3 inch through 36 inch Sizes 42

More information

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe Design and Installation Guide PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar

More information

Index to Technical Specifications

Index to Technical Specifications Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation

More information

SECTION SANITARY UTILITY SEWERAGE PIPING

SECTION SANITARY UTILITY SEWERAGE PIPING SECTION 33 31 00 SANITARY UTILITY SEWERAGE PIPING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Sanitary sewer pipe and fittings. 2. Underground pipe markers. 3. Connection to existing manholes. 4.

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID:

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID: TECHNICAL SPECIAL PROVISION FOR 1001 WATER DISTRIBUTION SYSTEM FINANCIAL PROJECT ID: 200105-7-52-01 The official record of this Technical Special Provision is the electronic file signed and sealed under

More information

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.

More information

Job Order Sewer Repair Services

Job Order Sewer Repair Services Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified

More information

SECTION STORM DRAIN

SECTION STORM DRAIN PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract

More information

SECTION 2100 WATER MAIN

SECTION 2100 WATER MAIN SECTION 2100 WATER MAIN WATER MAIN PART 1 GENERAL 1.01 Section Summary A. This section includes product and installation requirements for water main pipe, gate valves, hydrants, fittings, and miscellaneous

More information

ROUTE 3 OLD WINTHROP ROAD PROJECT LOCATION I-95 PROJECT LOCATION WESTERN AVENUE NORTH BELFAST AVE.

ROUTE 3 OLD WINTHROP ROAD PROJECT LOCATION I-95 PROJECT LOCATION WESTERN AVENUE NORTH BELFAST AVE. PROJECT LOCATION PROJECT LOCATION NORTH BELFAST AVE. ROUTE 3 WESTERN AVENUE I-95 OLD WINTHROP ROAD INSTALL NEW 3" x 1" CC DOUBLE STRAP SERVICE SADDLE, 1" CC x 1 1/4" COMPRESSION CORPORATION AND 1 1/4"

More information

1. Will have water lines designed by a North Carolina Registered Professional Engineer.

1. Will have water lines designed by a North Carolina Registered Professional Engineer. 03/07/16 DEVELOPER/OWNER RESPONSIBILITES 1. Will have water lines designed by a North Carolina Registered Professional Engineer. 2. Will have the water line installed by a North Carolina Licensed Utility

More information

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES WATER DESIGN STANDARDS

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES WATER DESIGN STANDARDS WATER DESIGN STANDARDS This section of the manual contains the Washoe County Department of Water Resources (DWR) standards for: Designing Water Distribution Facilities ( Design Standards ) 1.1 DESIGN STANDARDS

More information

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation SECTION 33 40 00 STORM DRAINAGE UTILITIES 1. PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 00: Excavation and Fill B. Section 32 00 01: Site Restoration and Rehabilitation C. Special Conditions for

More information

PERMANENT PAVEMENT REPAIR NO SCALE

PERMANENT PAVEMENT REPAIR NO SCALE SAWCUT EXISTING PAVEMENT 2" BITUMINOUS CONCRETE SURFACE COURSE, CLASS 2 (MIN) CLEAN EDGE PRIOR TO PAVING AND PAINT WITH LIQUID BITUMEN. INSTALL SEALANT OVER JOINT UPON COMPLETION 2" BITUMINOUS CONCRETE

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS

CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS Storm Sewer System: 1. Detention/retention of stormwater runoff shall be provided in accordance with the requirements of the DuPage County Countywide Stormwater

More information

Contents. dimensions and weights external loads deflection and testing installation...17

Contents. dimensions and weights external loads deflection and testing installation...17 GRAVITY SEWER Contents 01 02 03 04 05 06 07 08 09 product description...2 short form specification...5 dimensions and weights....................... 6 flow/discharge charts....................... 8 external

More information

SECTION SEWER PIPE

SECTION SEWER PIPE SECTION 02530 SEWER PIPE PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: Furnish and install all piping as shown on the Drawings, described in the Specifications and as required for a complete and operable

More information

SECTION PUBLIC WATER SERVICE CONNECTIONS

SECTION PUBLIC WATER SERVICE CONNECTIONS SECTION 33 14 14 PUBLIC WATER SERVICE CONNECTIONS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe and fittings for water service connections to small commercial, light industrial, and residential

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which