Screening Statement. Pfizer Ireland Pharmaceuticals. Document Stage Document Version Prepared by Final 2 Pat Doherty MSc, MCIEEM. For and on behalf of

Size: px
Start display at page:

Download "Screening Statement. Pfizer Ireland Pharmaceuticals. Document Stage Document Version Prepared by Final 2 Pat Doherty MSc, MCIEEM. For and on behalf of"

Transcription

1 Screening Statement in Support of Appropriate Assessment Pfizer Ireland Pharmaceuticals, Newbridge, Co. Kildare Doherty Environmental September 2018 EPA Export :03:35:14

2 Screening Statement Pfizer Ireland Pharmaceuticals Document Stage Document Version Prepared by Final 2 Pat Doherty MSc, MCIEEM For and on behalf of Doherty Environmental Prepared By: Pat Doherty Signed: This report has been prepared by Doherty Environmental with all reasonable skill, care and diligence. Information report herein is based on the interpretation of data collected and has been accepted in good faith as being accurate and valid. This report is prepared for Environet Solutions and we accept no responsibility to third parties to whom this report, or any part thereof, is made known. Any such party relies on the report at their own risk. Doherty Environmental i 12/09/2018 EPA Export :03:35:14

3 Table of Contents 1.0 INTRODUCTION STAGE 1 SCREENING METHOD PROJECT SITE DESCRIPTION PROJECT DESCRIPTION GASEOUS EMISSIONS NOISE EMISSIONS DRAINAGE SOLID WASTE PROCESS EFFLUENT ABATEMENT STORM WATER DRAINAGE & CONTAINMENT CONTAINMENT OF SPILLS & LEAKS CONTAINMENT IN THE EVENT OF A FIRE EMISSIONS TO ATMOSPHERE ABATEMENT THE PROJECT & EUROPEAN SITE BASELINE IDENTIFICATION OF EUROPEAN SITES SCREENING STATEMENT CONCLUSION: FINDING OF NO SIGNIFICANT EFFECTS 29 REFERENCES 30 Doherty Environmental ii 12/09/2018 EPA Export :03:35:14

4 1.0 INTRODUCTION Doherty Environmental was commissioned by Environet Solution to undertake a Stage 1 Habitats Directive Assessment Screening for Appropriate Assessment for activities relating to the provision of a new (retrofitted) manufacturing suites dedicated to the manufacture of Eliquis and other similar drugs in the existing manufacturing Buildings 3A and 4-2, located within the existing Pfizer Ireland Pharmaceuticals Newbridge facility. This Screening for Appropriate Assessment forms Stage 1 of the Habitats Directive Assessment process and is being undertaken in order to comply with the requirements of the Habitats Directive Article 6(3). The function of this Screening Exercise is to identify the potential for the project to result in likely significant effects to European Sites and to provide information so that the competent authority can determine whether a Stage 2 Appropriate Assessment is required for the project. 1.1 STAGE 1 SCREENING METHOD The function of the Screening exercise is to identify whether or not the proposal will have the potential to result in likely significant effect on European Sites. In this context likely refers to the presence of doubt with regard to the absence of significant effects (ECJ case C-127/02) and significant means not trivial or inconsequential but an effect that has the potential to undermine the site s conservation objectives (English Nature, 1999; ECJ case C-127/02 &). In other words, any effect that compromises the conservation status of a European Sites and interferes with achieving its conservation objectives would constitute a significant effect. The nature of the likely interactions between the project and the conservation status of European Sites will depend upon the sensitivity of these sites and their reasons for designation to potential impacts arising from the project; the current conservation status of the features for which European Sites have been designated; and any likely changes to key environmental indicators (e.g. habitat structure; vegetation community) that underpin the conservation status of European Sites, in combination with other plans and projects. This Screening exercise has been undertaken with reference to respective National and European guidance documents: Appropriate Assessment of Plans and Projects in Ireland: Guidance for Planning Authorities (DEHLG 2010) and Assessment of Plans and Projects Doherty Environmental 1 12/09/2018 EPA Export :03:35:14

5 Significantly Affecting Natura 2000 sites Methodological Guidance of the Provisions of Article 6(3) and (4) of the Habitats directive 92/43/EEC and recent European and National case law (ECJ C-258/11 & High Court case ref JR). The following guidance documents were also of relevance during this Screening Assessment: A guide for competent authorities. Environment and Heritage Service, Sept Appropriate Assessment of Plans and Projects in Ireland Guidance for Planning Authorities (2010). DEHLG. Assessment of Plans and Projects Significantly Affecting Natura 2000 Sites Methodological Guidance of the Provisions of Article 6(3) and (4) of the Habitats Directive 92/42/EED. European Commission (2001). Managing Natura 2000 Sites The provisions of Article 6 of the Habitats directive 92/43/EEC. European commission (2000). (To be referred to as MN 2000). The EC (2001) guidelines outline the stages involved in undertaking a Screening exercise of a project that has the potential to have likely significant effects on European Sites. The methodology adopted for this Screening exercise is informed by these guidelines and was undertaken in the following stages: 1. Describe the project and determine whether it is necessary for the conservation management of European Sites; 2. Identify European Sites that could be influenced by the project; 3. Where European Sites are identified as occurring within the sphere of influence of the project identify potential effects arising from the project and screen the potential for such effects to negatively affect European Sites identified under Point 2 above; and 4. Identify other plans or projects that, in combination with the project, have the potential to affect European Sites. 2.0 PROJECT SITE DESCRIPTION The Pfizer site is located within the town-land of Little Connell, north east of Newbridge town centre and adjacent to the R445 as shown on Figure 2.1. The current Pfizer landholding Doherty Environmental 2 12/09/2018 EPA Export :03:35:14

6 consists of approximately 48.6 hectares. The facility is currently accessed from the R445 dual carriageway via a roundabout and single access road. The Fossit Level 3 habitats occurring within the site are amenity grassland GA2; dry meadow and grassy verge GS2; HedgerowsWL1/Treelines WL2; immature woodland WS2; and Buildings and artificial surfaces BL3. The buildings and artificial surface habitat on site consists of the footprint of the site buildings and parking areas. Landscaped hedgerows and treelines border the site. No watercourses or drainage ditches occur within or in the surrounding vicinity of the project site. Surrounding land use in the vicinity of the plant is a combination of agricultural, commercial and residential with neighbouring land use as follows: North: Stud Farm South: Supermarket Distribution Company West: Residential Area East: Agricultural Land The majority of the site is utilised by Pfizer for the overall production operation, access roads and car parking requirements. Approximately 60% of the site is utilised for production facilities, wastewater treatment plant and waste storage areas. The remainder is used for internal access road, car parking and open green space. Doherty Environmental 3 12/09/2018 EPA Export :03:35:14

7 Doherty Environmental 4 12/09/2018 EPA Export :03:35:14

8 3.0 PROJECT DESCRIPTION This project involves the retrofit of an existing manufacturing suites, which will be dedicated to the drug product manufacturing processes for the preparation of Eliquis and similar drug products within the existing Pfizer facility at Newbridge, Co. Kildare. For Eliquis it is proposed to retrofit an existing processing area in Building 4-2 (see Plate 3.1 for building location) to accommodate the associated manufacturing process. For other similar drugs it is proposed that an Extended Technology Innovation Centre is provided for within the existing production rooms of Building 3A. Here it is proposed to extend existing site pilot plant facilities for supporting future product technical developments for similar drug product manufacturing processes. In order to achieve this it is proposed to retrofit the existing production rooms in Building 3A. Plate 3.1: Location of manufacturing suite within the Pfizer Ireland facility Doherty Environmental 5 12/09/2018 EPA Export :03:35:14

9 3.1 GASEOUS EMISSIONS The project will involve the virtual relocation and modification of selected licenced main emissions to atmosphere that were not previously installed on-site or are off-line. These points are as follows: Eliquis: Building 4 - Emission Point Reference No. A2-60, A2-61, A2-62, A2-67, A2-89, A2-90, A2-91, A2-92, A2-93, A2-94). Extended Technology Innovation Centre: Building 4 - Emission Point Reference No. A2-14, A2-49c. The proposed modifications are as follows: Change the location (building) of emissions points (i.e. A2-49c, A2-60, A2-61, A2-62, A2-67, A2-89, A2-90, A2-91, A2-92, A2-93, A2-94) and modify the vent dimensions (diameter, height above ground) of emissions points A2-49c - height above ground only, A2-60, A2-61, A2-62, A2-67, A2-89, A2-90, A2-91, A2-92, A2-93, A2-94; Modify the source (change in production process that the emission points serve) and reclassify the chemical characteristics (change from hormonal to non-hormonal emissions) for emission points A2-60, A2-61, A2-62, A2-67, A2-89, A2-90, A2-91, A2-92, A2-93, A2-94; Doherty Environmental 6 12/09/2018

10 Decrease the permitted hourly flowrate (with an overall net decrease in daily flowrate) for emission points A2-60, A2-61, A2-62, A2-67, A2-89, A2-90, A2-91, A2-92, A2-93, A2-94; Extend the period of emission (to 24 hours/day for emission point A2-24 and to 365 days/year for emission points A2-14, A2-49c, A2-60, A2-61, A2-62, A2-67, A2-89, A2-90, A2-91, A2-92, A2-93, A2-94. All gaseous emissions arising from the facility will be directed to the HVAC system. The HVAC systems and non-process utility systems shall comprise of the following installations: New Supply and Extract Air Handling Systems to serve the Production and associated Technical areas House Vacuum System Local Exhaust Ventilation (LEV) System Low Pressure Hot Water (LPHW) System Medium Temperature Hot Water (MTHW) System Chilled Water (CHW) System Emergency and Mist Showers Building Management System (BMS) Qualified Building Management System (QBMS). All engineering, design, materials of construction, fabrication, inspection, testing/ commissioning and certification shall conform to the current applicable EU and Irish Standards, Codes & Statutory Requirements. 3.2 NOISE EMISSIONS Noise requirements on site shall be as follows: site perimeter 55 db (daytime) and 45 db (night time). Equipment not meeting these criteria shall be provided with acoustic attenuation as necessary. Doherty Environmental 7 12/09/2018

11 3.3 DRAINAGE There are existing process drains under the first floor slab and ground slabrunning under the footprint of building 3A (Extended Technology Innovation Centre) and 4-2 (Eliquis) respectively. 3.4 SOLID WASTE The handling of solid waste will be as per site procedures. 3.5 PROCESS EFFLUENT ABATEMENT The Pfizer Ireland facility at Newbridge has an onsite enclosed state of the art wastewater pretreatment plant (WWTP) commissioned in 2006 and is used to treat both foul sewer and trade effluent. Both networks serve the entire site through a conveyance system draining to the WWTP to the south-east of the site (see Plate 3.1 for location). Wastewater from the foul sewer and trade effluent networks, enter the WWTP through and an influent wet well. Initial treatment is with a drum screen to remove larger solids. Following screening, the wastewater enters one of two balance tanks which are equipped with propellers and agitators. Following physical treatment, the wastewater undergoes aerobic biological treatment followed by effluent polishing using ozone oxidation. The intent behind biological treatment is to reduce the wastewater bulk organic fraction and in doing so, minimize the downstream ozone demand. MBR technology (biological treatment coupled with ultrafiltration) is in place to yield a high quality effluent devoid of suspended solids and solids-associated APIs. Some removal of certain APIs occurs in the biological system. Ozone oxidation is used to remove APIs that passed through the biological system. The resultant treated wastewater stream (Emission Point Reference No. SE1) is pumped to the tiein with the Kildare County Council municipal sewer. Effluent discharged through this route is monitored in accordance with Schedule C.3.2 of Licence Register No. P Doherty Environmental 8 12/09/2018

12 The Annual Environmental Reports (AERs) for 2010 to 2017 have been reviewed and no exceedances in the emission limit values (ELVs) for all wastewater parameters have been recorded during each year of monitoring. During 2017 integrity tests of the wastewater pipework detected a drop in hydraulic pressures along the pipework. The pipework was repaired within 24 hours of detection of the initial test failure. As all ELVs were complied with there was no potential for the project site to result in the release of contaminated wastewater prior to the detection of the test failure. 3.6 STORM WATER DRAINAGE & CONTAINMENT Surface water generated from a rainfall event is collected through systems of storm water drains networked around the Pfizer site from building roofs, roads and all hard standing areas. The storm water systems are fitted with oil interceptors and flow underground directly to the site surface water discharge point (Emission Point Reference No. SW1), prior to discharge to the municipal surface water drainage system which in turn discharges to the River Liffey. Also located on the site is a 1,400m 3 surface water attenuation tank (to ensure that potential surges of water to the on-site surface water drainage system and subsequent surcharging of the municipal storm water sewer is prevented), which is connected to the surface water network from specific areas of the site and drained through SW1. There is a continuous TOC (Total Organic Carbon) monitor located at the SW1 discharge point, with all other specified parameters monitored periodically in line with the requirements of Schedule C.2.3 of Licence Register No. P The surface water penstock will be activated if the TOC analyser detects dissolved organic substances above an action set point value which has been agreed with the EPA or if the sprinkler system is activated. No issues have been detected either through visual controls or through continuous TOC monitoring. Monitoring results reviewed for 2010 to 2017 (as per AERs) indicate that the surface water discharge from the Pfizer facility at SW1, the surface water outfall point, is of good chemical quality, and surface water discharging from the site is not resulting in impacts to the receiving waters into which it ultimately discharges (i.e. River Liffey). Doherty Environmental 9 12/09/2018

13 3.7 CONTAINMENT OF SPILLS & LEAKS All bulk solvents used and generated on site are stored in above ground tanks in the Solvent Tank Farm which are located in bunds. These solvents are transferred to/from the process area in high integrity steel pipework. Liquid process materials in smaller quantities are stored in drums or intermediated bulk containers, which are stored in bunded Chemstores in designated outdoor impermeable paved areas (pads) or in the Solvent Storage Area located within Building 4 (see Plate 3.1 for location). Spill kits, containing absorbent materials, are stored strategically around the site and relevant staff are trained in the appropriate emergency response actions to take in the event of a spill or leak. If a spill or leak were to occur that is not contained at source, it is collected in either the process wastewater or the storm water drainage systems, depending on the location of the spill or leak. It is anticipated that any spill or leak that could occur cannot easily enter the ground or the groundwater across the site. If spilled or leaked process materials enters the storm water drainage system they would be detected by the continuous TOC monitoring system, as described in Section 3.6, and the penstock would automatically close thereby preventing discharge from the site. This retained surface water would be further analysed to determine the nature and extent of contamination and establish an appropriate means of disposal. If spilled or leaked process materials enter the process wastewater drainage system, they would drain to the waste water treatment plant and would be fully treated on site. 3.8 CONTAINMENT IN THE EVENT OF A FIRE Fire water retention facilities have been provided on site, which have sufficient capacity to contain the potentially contaminated runoff from a fire event from the identified high risk area (i.e. Solvent Tank Farm) combined with rainfall, in compliance with the requirements of the EPA s guidance on fire water retention, Fire-Water Retention Facilities (Draft) Guidance Note To Industry On The Requirements For Fire-Water Retention Facilities, EPA In the event of a fire on site at other areas, water used for fire-fighting initially enters the site surface water network where it would be retained (due to closure of penstock which occurs on Doherty Environmental 10 12/09/2018

14 activation of the sprinkler system) and subsequently pumped to the firewater retention tank for containment until an appropriate treatment route is determined e.g. discharge to the WWTP or off-site disposal. During integrity testing of the fire retention area, a failure was recorded in one of the bunded areas. This bund was taken out of active use until the first quarter of 2018 while repairs and further integrity testing was completed. The issues with the bund have now been rectified. 3.9 EMISSIONS TO ATMOSPHERE ABATEMENT The primary contaminants of air streams at the facility comprise of particulates and Volatile Organic Components (VOCs). Particulates may contain Active Pharmaceutical Ingredients (APIs). Particulate emissions occur mainly as a result of tablet manufacture and to a lesser extent from the tablet packaging process. Emissions are minimised through employing a combination of control and abatement measures. Particulates: Typically, tablet manufacturing process equipment is enclosed with built-in extraction systems. Tablet manufacture and tablet packaging areas also employ house cleaning vacuum systems. For both types of extraction systems, dusts are collected in a combination of cartridge/high Efficiency Particulate Air (HEPA) filters. These filters are designed to capture at least 99.97% of 0.3 m sized particles. To ensure effective operations, differential pressure across the filters is continuously monitored with fault situations (filter blockage/breach) addressed in a timely manner. VOCs: VOCs are produced as a result of solvent use, primarily in tablet manufacture. Both Dichloromethane (DCM) and Methanol are used as carrier agents for the coating material during the coating process of certain products. In order to prevent any emissions to atmosphere, the waste vent gases are vented to the solvent abatement system. Waste solvent generated during this process is recovered through a solvent condensing system. This solvent is then collected on site as hazardous waste and removed by the sites approved waste management company for treatment. Doherty Environmental 11 12/09/2018

15 Site boilers, which operate on natural gas, are fitted with burners to reduce the formation of NOx during the combustion process (low NOx burners). The site has been designed to minimise potential sources of fugitive emissions arising from process areas and buildings i.e. minor leakages from connections, isolation and control valves, relief valves, equipment seals, analysers and solvent dispensing operations. Dust emissions are vented to specific extract systems and house cleaning vacuum systems. Fugitive solvent emissions are minimised by the closed loop systems of the primary solvent coating process (associated with the Efexor process) and dedicated solvent recovery and abatement system on-site. Good housekeeping practices, including preventative maintenance and routine monitoring of equipment on-site minimises the potential for any equipment leaks. 4.0 THE PROJECT & EUROPEAN SITE BASELINE 4.1 IDENTIFICATION OF EUROPEAN SITES Current guidance on undertaking EU Habitats Directive Article 6 Assessments advises that all European Sites occurring within a 15km radius of a project site should be included within a Screening Assessment (Scott Wilson et al., 2006; DEHLG, 2010). Six European Sites, comprising of five SACs and one SPA occur within the surrounding 15km radius of the site (see Figure 4.1; Table 4.1 for list of European Sites). In addition to the European Sites occurring within a 15km area of the project site the DEHLG 2010 guidelines also advise that where the potential exists for a hydrological pathway to occur between the project site and European Sites beyond the 15km distance, then these sites should also be included as part of the Screening Assessment. The River Liffey, which receives both treated surface water and wastewater from the project site drains to Dublin Bay, where a number of European Sites are located. A total of four Doherty Environmental 12 12/09/2018

16 European Sites are located at Dublin Bay. These European Sites are shown in Figure 4.2 and listed Table 4.1. As the nearest European Site (Mouds Bog SAC) is located at a remote distance from the project site, approximately 2km to the northwest as the crow flies, the project will not have the potential to result in direct impacts to European Sites. Thus this Screening exercise focuses on investigating whether the project will have the potential to result in indirect effects to European Sites or effect mobile species associated with European Sites beyond the boundaries of their designated conservation areas. A source-pathway-receptor model has been used to establish which European Sites could occur within the sphere of influence of potential indirect impacts. Under such a model the project, as described in Section 3 of this Screening Report, represents the source. Potential impact pathways are restricted to hydrological and aerial pathways as these represent the principal emissions generated by activities at the project site. The receptors represent European Sites and their associated qualifying features of interest. European Sites and their associated qualifying features are likely to occur in the sphere of influence of the project only where hydrological or aerial pathways establish a link between the project and the European Site. Table 4.1 provides a determination as to whether each European Site within a 15km buffer distance of the project site occur within the sphere of influence of the project. This determination has been undertaken in line with the following assessment questions: Is there a hydrological pathway linking the Project site to European Sites and does this pathway have the potential to function as an impact pathway? Is there an aerial pathway linking the Project site to European Sites and does this pathway have the potential to function as an impact pathway Does the project site have the potential to interact with Annex II qualifying species/ special conservation interest species of these European Sites? Doherty Environmental 13 12/09/2018

17 Doherty Environmental 14 12/09/2018

18 Doherty Environmental 15 12/09/2018

19 Table 4.1: Assessment to Determine whether European Sites occur within the Projects Sphere of Influence European Distance Is there a Hydrological Pathway and Is there an Aerial Pathway and does Do the Project have the potential Do European Sites occur Sites from does it have the potential to function it have the potential to function as an to interact with Mobile Species within the Projects Mouds Bog SAC Project Site 2.2km to the northwest as an Impact Pathway Impact Pathway No. This SAC is designated for Annex 1 peatland habitats, namely raised bog, degraded raised bog and Rhynchosporion depressions. These Annex 1 habitats are ombrotrophic in nature and there is no hydrological pathway linking these habitats or this SAC to the project site. No. An air dispersion modelling study (ARUP, 2018) has been completed for the project. This study assessed the potential impact of dust emissions of the Active Pharmaceutical Ingredient (API) Hormone Treatment (HT), and non-hormonal dust (i.e. Particulate Matter (PM)). The study found that exposure to HT a active concentrations No. No Annex 2 species are listed as qualifying features of interest for this SAC. Sphere of Influence? No. No potential impact pathways link the project site to this SAC. will be exceedingly low for any individual in the vicinity of the Pfizer facility, and many orders of magnitude below the therapeutic dose level. No Doherty Environmental 16 12/09/2018

20 significant impact on air quality is predicted as a result of PM emissions associated with the project and all air quality standards will be complied with. In light of the findings of the Air Dispersion Modelling study, it can be concluded that the no potential aerial pathway exists between the project site and European Sites in the surrounding area and that emissions associated with the project will not have the potential to impact the Conservation Objectives and status of these European Sites. Pollardstown 3km to the No. This SAC is designated for the No. See reasons outlined for Mouds No. This SAC is designated for its No. No potential impact Fen SAC west presence of the Annex 1 habitats Bog SAC above. role in supporting three species of pathways link the project calcareous fens, alkaline fens and the Annex 2 Vertigo snails. These site to this SAC. petrifying spring. Both habitats rely on species are predominantly Doherty Environmental 17 12/09/2018

21 soligenous hydrological processes. There are no surface water or groundwater pathways linking the project site to this SAC and its associated Annex 1 qualifying habitats. sedentary in nature and there will be no potential for them to interact with the project site and associated activities at the project site. Ballynafagh Lake SAC 9km to the north No. This SAC is designated for the presence of the Annex 1 habitat alkaline fens. This habitat relies on soligenous hydrological processes. There are no surface water or groundwater pathways linking the project site to this SAC and its associated Annex 1 qualifying habitat. No. See reasons outlined for Mouds Bog SAC above. No. This SAC is designated for its role in supporting populations of the Annex 2 species marsh fritillary butterfly and Vertigo moulinsiana. No suitable habitat for either species occurs in the vicinity of the project and there are no indirect impacts linking the project to the populations of these species No. No potential impact pathways link the project site to this SAC. supported by this SAC. Ballynafagh 11km to the No. This SAC is designated for Annex 1 peatland habitats, namely raised bog No. See reasons outlined for Mouds No. No Annex 2 species are listed as qualifying features of interest for No. No potential impact pathways link the project Doherty Environmental 18 12/09/2018

22 Bog SAC north and Rhynchosporion depressions. Bog SAC above. this SAC. site to this SAC. These Annex 1 habitats are ombrotrophic in nature and there is no hydrological pathway linking these River Barrow and River Nore SAC 13.5km to the southwest habitats or this SAC to the project site. No. This SAC is designated for a range of lotic, riparian and coastal Annex 1 habitats. This SAC and its associated qualifying habitats are located at a remote distance from the project site and occur within a separate surface water No. See reasons outlined for Mouds Bog SAC above. No. This SAC is designated for its role in supporting Annex 2 freshwater species and the sedentary Killarney fern. This SAC and its associated qualifying species are located at a remote distance from the project No. No potential impact pathways link the project site to this SAC. catchment. As such there is no site and occur within a separate potential for a hydrological impact surface water catchment. As such pathway to occur. there is no potential for an impact pathway to occur between the project site and populations of these Doherty Environmental 19 12/09/2018

23 species supported by this SAC. Poulaphouca 14.7km to No. The wetland habitats associated No. See reasons outlined for Mouds No. This SPA is designated for its No. No potential impact Reservoir the southeast with this SPA are located at a remote Bog SAC above. role in supporting populations of pathways link the project SPA distance upstream from the project site. No hydrological pathway links the project site and associated activities to the wetland habitats of this SPA. greylag goose and lesser blackbacked gull. No suitable habitat for these species occur in the vicinity of the project site and there will be no potential for the project and its associated activities to interact with the populations of these species supported by this SPA. Furthermore there is no potential for an impact pathway site to this SPA. (hydrological or aerial) to link the project and associated activities to populations of these species at this SPA. Doherty Environmental 20 12/09/2018

24 South 65km Yes, there is a hydrological pathway. No. See reasons outlined for Mouds No. No Annex 2 species are listed No. No potential impact Dublin Bay downstream This SAC is designated for the Bog SAC above. as qualifying features of interest for pathways link the project SAC and to the presence of coastal Annex 1 habitats. this SAC. site to this SAC. east Treated wastewater and surface water from the project site eventually discharge to the River Liffey and as shown on Figure 5.2, the River Liffey forms a hydrological pathway between the project site and this SAC. However this hydrological pathway does not function as a potential impact pathway for the following reasons: This SAC is located approximately 65km downstream from the project site. All wastewater generated at the project site undergoes treatment within the onsite WWTP prior to discharge to the Doherty Environmental 21 12/09/2018

25 municipal sewer. The effluent discharged from the onsite WWTP is routinely monitored and no exceedances in ELV s for all parameters analysed have been detected under the current industrial wastewater discharge licence for the project site (IPPC Licence No. P ). In addition the effluent discharged to municipal sewer undergoes a second round of treatment at the municipal wastewater treatment plant at Oberstown prior to final release to the River Liffey. The approach to wastewater treatment on site has to date ensured that the release of treated effluent does not have the potential to negatively affect the surface water quality of the River Liffey or Dublin Bay downstream. This Doherty Environmental 22 12/09/2018

26 approach to the treatment of wastewater will be continued as part of the proposed project. The discharge of surface water generated on site is controlled (TOC, volumetric flow) via the stormwater drainage system prior to release from the site and eventual receiving waters of the River Liffey. No issues in surface water quality for all parameters measured have been detected during routine monitoring undertaken between 2010 and The approach to surface water management on site has to date ensured that the release of surface water does not have the potential to negatively affect the surface water quality of the River Liffey or Dublin Bay Doherty Environmental 23 12/09/2018

27 downstream. This approach to the treatment of surface water will be continued as part of the proposed project. As outlined in Section 3 above infrastructure is in place at the project site to contain and treat fire water. As such the potential for firewater to be released from the project site is very low. In summary, the measures in place at the project site are proven to be effective in ensuring that activities at the project site, including those proposed under the current project, do not have the potential to result in adverse effects to the water quality of the River Liffey. This in turn ensures that the River Liffey will not function Doherty Environmental 24 12/09/2018

28 as a potential impact pathway linking the project site and associated activities to this SAC. North Dublin Bay SAC North Bull Island SPA 65km downstream and to the east 65km downstream Yes there is a hydrological pathway, but this pathway does not have the potential for function as an impact pathway for reasons outlined for South Dublin Bay SAC above. No. See reasons outlined for Mouds Bog SAC above. Yes there is a hydrological pathway, No. See reasons outlined for Mouds but this pathway does not have the Bog SAC above. No. This SAC supports a population of the liverwort Petalophyllum ralfsii. This is a sedentary species and there is no potential for the project to interact with this species. No. This SPA is designated for its role in supporting a number of No. No potential impact pathways link the project site to this SAC. No. No potential impact pathways link the project and to the potential for function as an impact wetland bird species. Individuals site to this SPA. east pathway for reasons outlined for South associated with the SPA Dublin Bay SAC above. populations of these species are very unlikely to occur in the vicinity of the project site and there Doherty Environmental 25 12/09/2018

29 is no potential impact pathway (hydrological or aerial) linking the project site to the foraging and roosting ground upon which these species rely. South Dublin Bay & Tolka Estuary SPA 65km downstream and to the east Yes there is a hydrological pathway, but this pathway does not have the potential for function as an impact pathway for reasons outlined for South Dublin Bay SAC above. No. See reasons outlined for Mouds Bog SAC above. No. This SPA is designated for its role in supporting a number of wetland bird species, including breeding terns. Individuals associated with the SPA populations of these species are very unlikely to occur in the vicinity of the project site and there is no potential impact pathway (hydrological or aerial) linking the No. No potential impact pathways link the project site to this SPA. project site to the foraging, nesting and roosting ground upon which these species rely. Doherty Environmental 26 12/09/2018

30 Table 4.1 above shows that the six European Sites occurring within a 15km radius of the project site and the four European Sites occurring downstream at Dublin Bay do not occur within the sphere of influence of the project site. The Source-Pathway-Receptor model has not identified the presence of an impact pathway, be it hydrological, aerial or mobile species, linking the project site to European Sites in the wider surrounding area. The absence of any potential impact pathways, coupled with the approach to the management of operations and emissions generated at the project site will ensure that this project does not have the potential to result in likely significant effects to European Sites or the local environment surrounding the project site. A Screening Matrix, in line with European Commission (2001) guidelines is provided below in Table 4.2. Table 4.2: Screening Matrix for proposed project. Brief description of the project or plan Brief description of the European Sites Describe the individual elements of the project (either alone or in combination with other plans or projects) likely to give rise to impacts on the European Sites. Describe any likely direct, indirect or secondary impacts of the project (either alone or in combination with other plans or projects) on the European Sites site by virtue of: The project and associated activities are described in Section 2 above. The European Sites occurring in the wider surrounding area are identified and briefly described in Section 4 above. The elements of the project that could (conceivably) size and scale; land-take; distance from the Natura 2000 site or key features of the site; resource requirements (water abstraction etc.); emissions (disposal to land, water or air); excavation requirements; transportation requirements; duration of construction, operation, give rise to potential environmental effects relate to atmospheric, wastewater and surface water emissions arising from the project site and associated activities. The project will not have the potential to result in direct, indirect or secondary impacts to European Sites. As the project is not predicted to result in the emission of potentially polluting substances to the surrounding environment it will not have the potential to combine with other projects in the surrounding area to result in cumulative significant effects to the local environment or European Sites occurring in the wider surrounding area. Doherty Environmental 27 12/09/2018

31 decommissioning, etc.; Describe any likely changes to the site arising as a result of: reduction of habitat area: disturbance to key species; habitat or species fragmentation; reduction in species density; changes in key indicators of conservation value (water quality etc.); climate change. As the project is not predicted to result in the emission of potentially polluting substances to the surrounding environment it will not have the potential to result in changes to qualifying habitats or qualifying species of European Sites occurring in the wider surrounding area. Describe the potential for the project alone or in The project will not have the potential to combination with other plans or projects to result combine with other plans or projects to result in in likely significant effects to European Sites. in likely significant effects to European Sites. The emissions from the project site relate to air and process wastewater. Existing treatment and management systems are in place at the Pfizer Newbridge site that effectively treat all airand process wastewater generated at the project site prior to release to the environment. Ongoing monitoring of the treatment systems on site have shown that all emissions from the project site are consistently within the licenced ELV s and no exceedances in these limits have been recorded during ongoing monitoring at the project site. Given the above, the project will not have the potential to result in the release of emissions to the environment that could combine with other sources of such emissions to result in adverse environmental effects. Describe any likely impacts on the European Sites For reasons set out above the project will not site as a whole in terms of: have the potential to interfere with key interference with the key relationships that define relationships that define the structure and the structure of the site; function of European Sites. interference with key relationships that define the function of the site Doherty Environmental 28 12/09/2018

32 Provide indicators of significance as a result of the identification of effects set out above in terms of: loss; fragmentation; disruption; disturbance; change to key elements of the site (e.g. water quality etc.). For reasons set out above the project will not have the potential to result in such effects to European Sites. Describe from the above those elements of the project or plan, or combination of elements, where the above impacts are likely to be significant or where the scale or magnitude of impacts is not known. The project will not have the potential to result in likely significant effects to European Sites. 5.0 SCREENING STATEMENT CONCLUSION: FINDING OF NO SIGNIFICANT EFFECTS During the Screening of the proposed project and change in use of manufacturing suites in Buildings 3A and 4-2 (to facilitate the manufacture of the Eliquis product and other similar drug products) at the Pfizer Ireland Pharmaceuticals facility at Newbridge it was found that six European Sites occur within a 15km radius of the project site and an additional four European Sites occur at a greater distance (i.e. 65km) downstream. The nearest European Site to the project site is located over 2km to the northwest. All of these European Sites (and their associated qualifying features of interest/special conservation interests) are adjudged to be located outside the sphere of influence of all activities associated with the proposed project. No impact pathways were identified linking the wider Pfizer project site to the surrounding European Sites. In light of the findings of this Screening for Appropriate Assessment it is concluded that the project will not have a significant negative effect on European Sites and will not negatively affect their conservation objectives or integrity. Doherty Environmental 29 12/09/2018

33 This Screening has resulted in a Finding of No Significant Effects and as such a Stage II Appropriate Assessment is not required. REFERENCES ARUP (2018). Air Dispersion Modelling Study of Revised Emissions. Pfizer Newbridge: IE Licence Register No. P Department of the Environment Heritage and Local Government (DEHLG) (2008) Circular letter SEA 1/08 & NPWS 1/08. Department of the Environment Heritage and Local Government (DEHLG) (2010). Appropriate Assessment of Plans and Projects. Guidance for Local Authorities. English Nature (1999). Habitats regulations guidance note no. 3 (HRGN No. 3). Determination of Likely Significant Effect under The Conservation (Natural Habitats &c) Regulations Environment Agency, Environmental statement for the Humber Estuary Tidal Defences. Urgent works, Paull to Kilnsea and Whitton to Pyewipe. European Commission (2000). Managing Natura 2000 sites. The provisions of Article 6 of the Habitats Directive 92/43/EEC. Luxembourg. European Commission (2001). Assessment of plans and projects significantly affecting Natura 2000 sites. Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive 92/43/EEC. Luxembourg. European Commission (1992). EU Habitats Directive. Doherty Environmental 30 12/09/2018

34 Doherty Environmental 31 12/09/2018

Screening Statement in Support of Appropriate Assessment. Pfizer Ireland Pharmaceuticals, Newbridge, Co. Kildare. Doherty Environmental

Screening Statement in Support of Appropriate Assessment. Pfizer Ireland Pharmaceuticals, Newbridge, Co. Kildare. Doherty Environmental Screening Statement in Support of Appropriate Assessment, Newbridge, Co. Kildare Doherty Environmental May 2017 Screening Statement Document Stage Document Version Prepared by Final 2 Pat Doherty MSc,

More information

ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE DR-0021)

ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE DR-0021) ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE0310818-30-DR-0021) SITE SERVICES LAYOUT SHEET 2 OF 2 (IE0310818-30-DR-0022) LOCATION OF EMISSION TO SURFACE WATER (IE0310818-22-DR-

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

PROVISION OF INFORMATION REGARDING APPROPRIATE ASSESSMENT SCREENING PROPOSED DEVELOPMENT SOCIAL HOUSING AT ANNE STREET, PROSPEROUS, CO.

PROVISION OF INFORMATION REGARDING APPROPRIATE ASSESSMENT SCREENING PROPOSED DEVELOPMENT SOCIAL HOUSING AT ANNE STREET, PROSPEROUS, CO. PROVISION OF INFORMATION REGARDING APPROPRIATE ASSESSMENT SCREENING PROPOSED DEVELOPMENT SOCIAL HOUSING AT ANNE STREET, PROSPEROUS, CO. KILDARE PREPARED FOR MCORM ON BEHALF OF KILDARE COUNTY COUNCIL Project

More information

Screening for Appropriate Assessment Proposed residential development at Slievekeale, Waterford City. 13 April 2018

Screening for Appropriate Assessment Proposed residential development at Slievekeale, Waterford City. 13 April 2018 Proposed residential development at City 13 April 2018 NM Ecology Ltd Consultant Ecologists 276 Harold s Grange Road, Dublin 16 Website: www.nmecology.com Email: info@nmecology.com Tel: 087 6839771 Executive

More information

OFFICE OF ENVIRONMENTAL SUSTAINABILITY

OFFICE OF ENVIRONMENTAL SUSTAINABILITY This report has been cleared for submission by Patrick Byrne. Eve O'Sullivan, 21/11/2016 11:33 OFFICE OF ENVIRONMENTAL SUSTAINABILITY ENVIRONMENTAL LICENS ING PROGRAMME TO: FROM: Programme Manager Marian

More information

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories: 5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION The scope of the EIA falls under three broad categories: technical scope; spatial scope; and temporal scope. The scoping process for the

More information

Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT. EIS Screening Report

Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT. EIS Screening Report Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT IRISH WATER Vartry Water Supply Upgrade Project Environmental Impact Assessment Screening Report Nicholas O Dwyer Ltd Consulting Engineers Nutgrove Office

More information

Integrated Pollution Prevention & Control Licence Review

Integrated Pollution Prevention & Control Licence Review Integrated Pollution Prevention & Control Licence Review Johnson & Johnson Vision Care Ireland Attachment A1 Non Technical Summary This is a summary, in non-technical language, of the information provided

More information

OFFICE OF LICENSING & GUIDANCE

OFFICE OF LICENSING & GUIDANCE OFFICE OF LICENSING & GUIDANCE INSPECTORS REPORT ON A LICENCE APPLICATION To: Directors From: MARIE O CONNOR - LICENSING UNIT Date: 19 April 2007 RE: Application for a Review of IPPC Licence from Cara

More information

Outline Corrective Action Summary

Outline Corrective Action Summary Outline Corrective Action Summary Technical Note 20 October 2017 Quality information Prepared by Checked by Approved by Matteo Viganotti Senior Environmental Consultant David Mullan Associate Environmental

More information

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION 6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006 Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006 With respect to the Conclusions on BAT for this horizontal BREF, the details of applicability and status

More information

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence;

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence; 14 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 14.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

ATTACHMENT N o A1: NON-TECHNICAL SUMMARY

ATTACHMENT N o A1: NON-TECHNICAL SUMMARY ATTACHMENT N o A1: NON-TECHNICAL SUMMARY A1 INTRODUCTION Dairygold AgriBusiness Ltd is making an application to the Environmental Protection Agency for an Industrial Emissions Licence which relates to

More information

ACCIDENT PREVENTION & EMERGENCY RESPONSE

ACCIDENT PREVENTION & EMERGENCY RESPONSE Attachment J ACCIDENT PREVENTION & EMERGENCY RESPONSE Cadbury Ireland Limited Project Ref: OES1061_01 Cadbury Ireland Limited February 2007 Attachment J J.1 Accidental Emissions Control Accidental emissions

More information

1) TO: Dara Lynott, Director

1) TO: Dara Lynott, Director wa *o Environmental A n unhn mrtt vm Protectwn Ckmnm bmhhwr! 0 F F I C I This memo has been cleared for submission to the Director by Programme Marjager, Frank Clinton Signed : cxm:,,

More information

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:03:55

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:03:55 REPORT Appropriate Assessment Screening Rathcoffey WWTP Submitted to: Paul Hickey Water Services Section Kildare County Council Aras Chill Dara Devoy Park Naas Co.Kildare Report Number. 10507190132 Distribution:

More information

OFFICE OF CLIMATE, LICENSING, RESOURCES & RESEARCH

OFFICE OF CLIMATE, LICENSING, RESOURCES & RESEARCH This report has been cleared for submission to Director/Board by Breen Higgins. Grainne Power, 03/11/2015 14:44 OFFICE OF CLIMATE, LICENSING, RESOURCES & RESEARCH INSPECTORS REPORT ON A WASTE WATER DISCHARGE

More information

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents Site Description A description of construction activity. The proposed sequence for major activities. Estimates of the total

More information

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement Wellington Dock Planning Application, Liverpool Non-Technical Summary for Environmental Statement INTRODUCTION United Utilities PLC (UU) has applied for planning permission for an extension to Liverpool

More information

CONSTRUCTED WETLANDS OPPORTUNITIES FOR LOCAL AUTHORITIES

CONSTRUCTED WETLANDS OPPORTUNITIES FOR LOCAL AUTHORITIES CONSTRUCTED WETLANDS OPPORTUNITIES FOR LOCAL AUTHORITIES Don McEntee Chartered Engineer Dublin City Council November 2006 CONSTRUCTED WETLANDS OPPORTUNITIES FOR LOCAL AUTHORITIES In September 2006 the

More information

Draft Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report

Draft Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report Clean Harbors Canada Inc. Lambton Landfill Expansion Environmental Assessment Draft Air Quality & Odour Net Effects Analysis & Prepared By: JANUARY, 2014 Executive Summary Two expansion alternatives were

More information

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance

More information

Environmental Conditions. Mushroom Farms

Environmental Conditions. Mushroom Farms GBR No. 23 Environmental Conditions Mushroom Farms MEPA regulates the environmental impact of enterprises through two key mechanisms. Smaller scale activities are regulated through a set of General Binding

More information

City of Waukegan, Illinois

City of Waukegan, Illinois City of Waukegan, Illinois NPDES Phase II Stormwater Program Stormwater Pollution Prevention Plan Public Works Facility July 2011 City of Waukegan, Illinois Stormwater Pollution Prevention Plan for the

More information

4 Waste Licence Application

4 Waste Licence Application 4 Waste Licence Application Attachment F Page i63 of 215 EPA Export 25-07-2013:15:55:26 Attachment F.1: Treatment, Abatement and Control Systems The major emission sources with treatment, abatement and

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY S1014-0340-0008MPW NTS Rev1.doc Print Date 19 February 2009 ISSUE NUMBER 1 DATE 19/02/09 AUTHOR CHECKED MPW SMO Title Page

More information

Chapter 6 Objective: Protect and Enhance the Environment

Chapter 6 Objective: Protect and Enhance the Environment Chapter 6 Objective: Protect and Enhance the Environment 55 Irish Water Water Services Strategic Plan - October 2015 Our Strategic Aims Ensure that Irish Water services are delivered in a sustainable manner

More information

INSPECTORS REPORT DRAFT PD REGISTER NUMBER

INSPECTORS REPORT DRAFT PD REGISTER NUMBER INSPECTORS REPORT DRAFT PD REGISTER NUMBER 156-1 Applicant: KTK Sand and Gravel Ltd. Facility: Kimmeens, Ballymore Eustace, Co. Kildare Inspector s Recommendation: The licence be granted subject to conditions.

More information

APPENDIX III. Air Quality Modelling of NO X and PM 10 (2007) RFI Report (Dec 2007)

APPENDIX III. Air Quality Modelling of NO X and PM 10 (2007) RFI Report (Dec 2007) APPENDIX III Air Quality Modelling of NO X and PM 10 (2007) RFI Report (Dec 2007) 17 EPA Export 25-07-2013:22:32:47 Platin IPPC Licence Application Air Quality Modelling of NOx and PM (2007) EPA Export

More information

Mayo Renewable Power IPPC Licence Application. ATTACHMENT No. A NON- TECHNICAL SUMMARY TABLE OF CONTENTS

Mayo Renewable Power IPPC Licence Application. ATTACHMENT No. A NON- TECHNICAL SUMMARY TABLE OF CONTENTS Mayo Renewable Power IPPC Licence Application Attachment No. A ATTACHMENT No. A NON- TECHNICAL SUMMARY TABLE OF CONTENTS A.1. Installation and its Activities... 2 A.2. Raw and Auxilliary Materials... 2

More information

KANSAS CITY, MO INDUSTRIAL FACILITY INSPECTION FOR MS4 PROGRAM

KANSAS CITY, MO INDUSTRIAL FACILITY INSPECTION FOR MS4 PROGRAM KANSAS CITY, MO INDUSTRIAL FACILITY INSPECTION FOR MS4 PROGRAM Storm Water Pollution Prevention, Control, Reduction and Minimization In Compliance with Kansas City, MO Municipal Separate Storm Sewer System

More information

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001)

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001) IE0311133-22-RP-0001, Issue A 17/10/2013 Attachment 12 Stage 1 Flood Risk Assessment (IE0311133-30-RP-0001) IE0311133-22-RP-0001_A_02.DOC Flood Risk Assessment Celebrating 40 Years in Business Jazz Pharmaceuticals

More information

CONCLUSIONS 14 CONTENTS

CONCLUSIONS 14 CONTENTS CONTENTS Introduction... 14-1 Traffic... 14-1 Air Quality... 14-1 Noise and Vibration... 14-2 Geology and Hydrology... 14-2 Landscape and Visual... 14-3 Ecology... 14-4 Cultural Heritage... 14-4 Population

More information

Hazardous Substances Hazardous Substances Explanatory Statement Significant Issues Objective and Policies...

Hazardous Substances Hazardous Substances Explanatory Statement Significant Issues Objective and Policies... Section Contents Hazardous Substances... 2 9. Hazardous Substances... 2 Explanatory Statement... 2 9.1 Significant Issues... 3 9.2 Objective and Policies... 3 9.3 Activity Lists... 4 9.4 Quantity thresholds

More information

2. Discharges to waters

2. Discharges to waters There are 8 discharge points from the agglomeration. The primary discharge (SW001 Note 1 ) occurs into the Folly Stream, which discharges into Lough Leane (1km downstream of the WWTP outfall). There are

More information

Environmental Information Worksheet

Environmental Information Worksheet Environmental Information Worksheet Water System Owner (Attach additional sheets if necessary) Needs and Alternatives Provide a brief narrative that describes: Current drinking water system needs. Project

More information

Hazardous Substances. 9. Hazardous Substances. Explanatory Statement

Hazardous Substances. 9. Hazardous Substances. Explanatory Statement Hazardous Substances 9. Hazardous Substances Explanatory Statement The Western Bay of Plenty District is predominantly rural land in farming and horticulture and has a number of small urban centres containing

More information

Division 8 Intensive Animal Husbandry Code

Division 8 Intensive Animal Husbandry Code Division 8 Intensive Animal Husbry Code 12.8.1 Intensive Animal Husbry Code (1) The provisions in this division comprise the Intensive Animal Husbry Code. (2) They are compliance with the Intensive Animal

More information

This Chapter contains rules managing land uses in the Main Rural Zone. The boundaries of this zone are shown on the Planning Maps.

This Chapter contains rules managing land uses in the Main Rural Zone. The boundaries of this zone are shown on the Planning Maps. Chapter 34 MAIN RURAL ZONE RULES INTRODUCTION This Chapter contains rules managing land uses in the. The boundaries of this zone are shown on the Planning Maps. All rules apply throughout the unless otherwise

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

Garvagh Glebe Wind Energy Project County Leitrim

Garvagh Glebe Wind Energy Project County Leitrim HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's

More information

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Environmental Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Sustainable, Reliable, Affordable Stormwater Attenuation Systems Sustainable Drainage

More information

Assessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture

Assessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture Assessment of Landfill Footprint Alternatives Figure 422 99 Option #4 Impact on Agriculture The net effects with respect to continued service to customers, the optimized site life/ capacity is 65 million

More information

The following documentation was tabled:

The following documentation was tabled: Extract from the 564th meeting of the Agency held on 21 November 2008, in Headquarters, Johnstown Castle Estate, CO Wexford. 3. Report on the Oral Hearing of the Objections to a Proposed Decision on a

More information

Consent of copyright owner required for any other use. Attachment E. For inspection purposes only. Emissions. EPA Export :15:19:52

Consent of copyright owner required for any other use. Attachment E. For inspection purposes only. Emissions. EPA Export :15:19:52 Attachment E Emissions i TABLE OF CONTENTS 1 EMISSIONS TO ATMOSPHERE... 1 1.1 Boiler Emissions... 1 1.2 Main Emissions... 1 1.3 Minor Emissions... 3 1.4 Fugitive & Potential Emissions... 6 2 EMISSIONS

More information

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,

More information

Chapter 6 Objective: Protect and Enhance the Environment

Chapter 6 Objective: Protect and Enhance the Environment Chapter 6 Objective: Protect and Enhance the Environment 49 Irish Water Water Services Strategic Plan Our Strategic Aims Ensure that Irish Water services are delivered in a sustainable manner which contributes

More information

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval APPENDIX 2 Nova Scotia Department of Environment and Labour Terms and Conditions for Approval Approval Approval Date: March 14, 2007 Keltic Petrochemicals Inc. LNG and Petrochemical Plant Facilities Keltic

More information

Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS

Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Lagan Cement Ltd. IPPC Licence Application Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Air Contents F.2.0 Air Emissions.3 Water

More information

Pollution Prevention Team

Pollution Prevention Team Pollution Prevention Team Responsible Official: Team Leader: Responsibilities: Worksheet #1 Office Phone: (1) Responsibilities: Office Phone: (2) Responsibilities: Office Phone: (3) Responsibilities: Office

More information

Kerry Ingredients Ireland Ltd. Rathgoggan Middle, Charleville Co. Cork

Kerry Ingredients Ireland Ltd. Rathgoggan Middle, Charleville Co. Cork Kerry Ingredients Ireland Ltd. Rathgoggan Middle, Charleville Co. Cork Environmental Impact Assessment Report Volume IV: Non-Technical Summary June 2017 LoCall 1890 130 007 OES Consulting Dublin Newry

More information

Sulcor Pollution Incident Response Management Plan (PIRMP)

Sulcor Pollution Incident Response Management Plan (PIRMP) Sulcor Pollution Incident Response Management Plan (PIRMP) The Sulcor Limestone open cut mine is located 30Km north-west of Tamworth NSW. The limestone mined by conventional drill and blast processes is

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information

Section 85(1)b notice sent: 27 June Licence application received: 25 July Notices under Article 17 issued: 22 August 2003

Section 85(1)b notice sent: 27 June Licence application received: 25 July Notices under Article 17 issued: 22 August 2003 M E M O R A N D U M DATE: 31/10/03 TO: FROM: RE: Each Board Member Elaine Farrell Application for review of IPC licence Reg No. 581 from AHP Manufacturing BV trading as Wyeth Medica Ireland, Buckley s

More information

F3. Draft Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report

F3. Draft Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report F3. Draft Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report Clean Harbors Canada Inc. Lambton Landfill Expansion Environmental Assessment Draft Air Quality & Odour Net Effects Analysis

More information

(No. of pages excluding this page = 10)

(No. of pages excluding this page = 10) SPECIALIST CONSULTANT STUDIES 3-65 BIG ISLAND MINING PTY LTD (No. of pages excluding this page = 10) Ltd BIG ISLAND MINING PTY LTD 3-66 SPECIALIST CONSULTANT STUDIES This page has intentionally been left

More information

Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017

Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017 Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach October 2017 (Simulated FPF) INTRODUCTION Noront is proposing to develop a Ferrochrome Production Facility (FPF) in Northern

More information

RURAL CONSERVATION ZONE

RURAL CONSERVATION ZONE Chapter 37 RURAL CONSERVATION ZONE INTRODUCTION This Chapter contains rules managing land uses in the. The boundaries of this zone are shown on the Planning Maps. All rules apply throughout the unless

More information

Environmental Design Criteria for Project Engineering

Environmental Design Criteria for Project Engineering Environmental Design Criteria for Project Engineering Argentina Mining, Salta, September 2018 Simon Catchpole, February 2016 An Environmental Risk Model In the EA phase, the environmental professionals

More information

Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht

Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht MARINE NATURA IMPACT STATEMENTS IN IRISH SPECIAL AREAS OF CONSERVATION A WORKING DOCUMENT APRIL 2012 Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht

More information

Standard rules SR2012 No13 Treatment of Incinerator Bottom Ash (IBA)

Standard rules SR2012 No13 Treatment of Incinerator Bottom Ash (IBA) Standard rules Chapter 4, The Environmental Permitting (England and Wales) Regulations 2016 Standard rules SR2012 No13 Treatment of Incinerator Bottom Ash (IBA) Part A Installation - treatment capacity

More information

INSPECTORS REPORT ON A LICENCE APPLICATION

INSPECTORS REPORT ON A LICENCE APPLICATION OFFICE OF LICENSING & GUIDANCE INSPECTORS REPORT ON A LICENCE APPLICATION To: Directors From: Aoife Loughnane - Licensing Unit th Date: 20 July 2006 RE: Application for an IPPC Licence Review from Huntstown

More information

Kildare County Council

Kildare County Council Kildare County Council M7 Osberstown Interchange & R407 Sallins Bypass Scheme 2013 Errata to Environmental Impact Statement and Appropriate Assessment Screening Report Kildare County Council Áras Chill

More information

Rising Sun. Scaffold Hill. Flood Risk Assessment

Rising Sun. Scaffold Hill. Flood Risk Assessment Rising Sun Scaffold Hill Flood Risk Assessment August 2010 Contents 1.0 Introduction... 4 2.0 Site Description... 5 3.0 Legislative Framework... 6 4.0 Flood Risk... 10 5.0 Surface Water Drainage... 11

More information

Sustainability Statement

Sustainability Statement Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Sustainability Statement Doc Ref: 7.07 Appendix B.21 Greenwich Pumping Station

More information

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission

More information

INTEGRATED POLLUTION CONTROL LICENCE

INTEGRATED POLLUTION CONTROL LICENCE This licence was amended on 17 th September 2007 under Section 96(1) of the EPA Acts 1992 and 2003. The details of Amendment A must be read in conjunction with this licence. The amendment document is entitled

More information

F3. Final Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report

F3. Final Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report F3. Final Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report Clean Harbors Canada Inc. Lambton Landfill Expansion Environmental Assessment Air Quality & Odour Net Effects Analysis

More information

Environmental Conditions Laboratories (for commercial use) Group

Environmental Conditions Laboratories (for commercial use) Group GBR No. 20 Environmental Conditions Laboratories (for commercial use) Group ERA regulates the environmental impact of enterprises through two key mechanisms. Smaller scale activities are regulated through

More information

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4.1 INTRODUCTION This section describes the broad principles of the methodology adopted for the EIA of the Proposed Development. EIA is a procedure required

More information

Dublin City Council. Ringsend Wastewater Treatment Works Extension Environmental Impact Statement. Non Technical Summary.

Dublin City Council. Ringsend Wastewater Treatment Works Extension Environmental Impact Statement. Non Technical Summary. Dublin City Council Ringsend Wastewater Treatment Works Extension Environmental Impact Statement Non Technical Summary March 2012 Final Non-Technical Summary As part of the Dublin Bay Project, the Ringsend

More information

Section 1 - Introduction

Section 1 - Introduction VERSION 1.0 Stormwater Solutions for Residential Sites Section 1 - Introduction Prepared for EcoWater Solutions A Department of Waitakere City Council 113 Central Park Drive Henderson WAITAKERE CITY November

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Project Identification Project Name: Elyria East Side Relief Sewer Phase 1B South (CS390337-0018), Phase 1C (CS390337-0014), Phase 1D (CS390337-0017) Applicant: The Honorable Holly

More information

EPA Waste Water Discharge Licence Application

EPA Waste Water Discharge Licence Application Duleek Waste Water Treatment Works EPA Waste Water Discharge Licence Application ARTICLE 16 COMPLIANCE REQUIREMENTS Meath County Council EPA Document Ref: D0133-01 Section A: Non-Technical Summary Update

More information

E36. Natural hazards and flooding

E36. Natural hazards and flooding E36. Natural hazards and flooding E36.1. Background Auckland is affected by natural hazards including: those that occur frequently such as flooding, coastal erosion (including the effects of sea level

More information

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH DRD ROADS SERVICE, SOUTHERN DIVISION Environmental Statement, Volume 1 November 2005 Non Technical Summary i Introduction The Department for Regional

More information

TUAM WASTE WATER DISCHARGE LICENCE APPLICATION

TUAM WASTE WATER DISCHARGE LICENCE APPLICATION GALWAY COUNTY COUNCIL TUAM WASTE WATER DISCHARGE LICENCE APPLICATION NOTICE RESPONSE REGULATION 18(3)(B) July 2009 Report Conlrol Sheet FORM 214 Rev 000 Ryan Hanley conruhing engineers IS0 9001 2000 Quality

More information

ATTACHMENT E.3 EMISSIONS TO SEWER LOCATION OF EMISSION TO SEWER (IE DR-0003) Consent of copyright owner required for any other use.

ATTACHMENT E.3 EMISSIONS TO SEWER LOCATION OF EMISSION TO SEWER (IE DR-0003) Consent of copyright owner required for any other use. ATTACHMENT E.3 EMISSIONS TO SEWER LOCATION OF EMISSION TO SEWER (IE0310818-22-DR-0003) Page 152 of 217 Attachment E.3 Emissions to Sewer It is proposed that trade and foul effluent from the facility will

More information

Permeability across the entire site within the General Residential Zone is a minimum of 30%.

Permeability across the entire site within the General Residential Zone is a minimum of 30%. Partly Operative District Plan Rule Assessment The following assessment is to demonstrate compliance or non-compliance with the rules of the Partly Operative District Plan. The proposed duplex dwellings,

More information

Annual Environmental Report 2015

Annual Environmental Report 2015 Annual Environmental Report 2015 Agglomeration Name: Licence Register. D0063-01 Blessington Table of Contents Section 1. Executive Summary and Introduction to the 2015 AER 1 1.1 Summary report on 1 Section

More information

Review Register Number: 565 Notice under Section 85(1)(b) issued: 12 June 2000

Review Register Number: 565 Notice under Section 85(1)(b) issued: 12 June 2000 M E M O R A N D U M DATE: 29 January 2001 TO: FROM: RE: Each Board Member Patrick Geoghegan Application from National By-Products, Casatleblake, Rosegreen, Cashel, Co. Tipperary for Review of IPC Licence

More information

Storm Water Management

Storm Water Management Storm Water Management Policy September 2014 2 Sustainable drainage feature designed to control and manage flows through a series of check dams 3 Document Name: Storm Water Management Controlled Copy No:

More information

This Report has been cleared for submission to the Board by

This Report has been cleared for submission to the Board by 7 This Report has been cleared for submission to the Board by.- Article 1 1 (2)(b)(ii) response rec Site notice inspected: Fees) regulations 1994 to 2004. The installation is located in a rural area of

More information

5.9 Water (Drainage, Supply, Flood Risk and Groundwater)

5.9 Water (Drainage, Supply, Flood Risk and Groundwater) 5.9 Water (Drainage, Supply, Flood Risk and Groundwater) 5.9.1 Introduction This Chapter of the EIAR presents the water assessment for the Demolition, Construction and Operational Phase of the proposed

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Collection of Base line data in any season other than Monsoon season in study area of 10 kms radius from Lease Area. Based on the Meteorological data from

More information

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY ISSUE NUMBER 1 DATE 16/11/07 AUTHOR CHECKED SMO TME Title Page ISSUE NUMBER 1 DATE 16/11/07 AUTHOR CHECKED SMO TME Title Page TABLE

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

BAY OF ISLANDS PLANNING LIMITED 2 Totara Place, Kerikeri PO Box 795

BAY OF ISLANDS PLANNING LIMITED 2 Totara Place, Kerikeri PO Box 795 Far North District Council John Butler Centre Kerikeri Road Kerikeri Attention Ms Louise Wilson 30 May 2018 Dear Louise, BAY OF ISLANDS PLANNING LIMITED 2 Totara Place, Kerikeri PO Box 795 Kerikeri Phone

More information

EPA Guidance for Licensees on Requests for Alterations to the installation/facility

EPA Guidance for Licensees on Requests for Alterations to the installation/facility EPA Guidance for Licensees on requests for alterations to the installation/facility ISSUE NO: 1 REVISION NO: 1 DATE OF ISSUE: 08/12/2014 EPA Guidance for Licensees on Requests for Alterations to the installation/facility

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

Appendix 9 - Engineering Performance Standards

Appendix 9 - Engineering Performance Standards Appendix 9 - Engineering Performance Standards A9.1 Introduction A9.1.1 This Appendix contains standards that apply to the subdivision of land. It is referred to in the Subdivision Rules for the Living,

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

Sallins Playground, Co. Kildare. Sallins Playground Canal View Sallins, Co. Kildare Screening Report for Habitats Appropriate Assessment

Sallins Playground, Co. Kildare. Sallins Playground Canal View Sallins, Co. Kildare Screening Report for Habitats Appropriate Assessment Sallins Playground, Co. Kildare Sallins Playground Canal View Sallins, Co. Kildare Screening Report for Habitats Appropriate Assessment on behalf of Kildare Co. Council Parks Department August 2017 Mary

More information

Chapter 6 Regulations and Requirements

Chapter 6 Regulations and Requirements Chapter 6 Regulations and Requirements The information in this chapter is provided to help you comply with other Tacoma and Washington State regulations, which may apply to your project, industry or business

More information

STORM WATER MANAGEMENT STANDARDS DRAFT

STORM WATER MANAGEMENT STANDARDS DRAFT STORM WATER MANAGEMENT STANDARDS 1. Storm Water Management Plans (SWMP) - All development activity that is required to have a permit for land disturbing shall have an approved Storm Water Management Plan

More information

Managing Salt Impacted Water at Maintenance Yards

Managing Salt Impacted Water at Maintenance Yards Managing Salt Impacted Water at Maintenance Yards Presented to the: Transportation Association of Canada Calgary 2005 Abstract Managing Salt Impacted Water at Maintenance Yards The Code of Practice for

More information

Surface Water Guidance for Developers

Surface Water Guidance for Developers Surface Water Guidance for Developers Contents Overview of Sustainable Drainage Systems (SuDS)... 2 Information Required in a Flood Risk Assessment or Drainage Strategy... 3 Outline Planning Applications...

More information