Eastmain-1-A and Sarcelle Powerhouses and Rupert Diversion A project for present and future generations

Size: px
Start display at page:

Download "Eastmain-1-A and Sarcelle Powerhouses and Rupert Diversion A project for present and future generations"

Transcription

1 Eastmain-1-A and Sarcelle Powerhouses and Rupert Diversion A project for present and future generations Benoit Gagnon Tucuruí - Brasil 22 november 2011

2 Hydro-Québec Overview Generates, transmits, and distributes electricity in Québec Installed capacity > MW Clean energy leader 98 % of its total output generated by hydropower In Québec, the electric sector produces only 0.8 % of GHG emissions Exportation of clean energy to the neighbouring provinces and North Eastern United States 2

3 Three essentials conditions 1. Profitable under market conditions 2. Environmentally acceptable 3. Well received by local communities 3

4 Eastmain-1-A / Rupert project 5 billions $CDN investment Capacity of 918 MW Annual energy : 8.7 TWh Cost price : 5.1 / kwh Economic spinoff : 1.2 G$ 4

5 Eastmain-1-A / Rupert project Rupert river diversion : 314 km 4 dams and 74 dikes 2 powerhouses Tailbay/ forebay: 346 km² Transfer tunnel : 2.9 km 6 work camps 8 hydraulics structures 5

6 Eeyou Istchee : Land of the Cree 6 Cree communities 297 traplines 33 trappers affected 6

7 Main steps for a large Hydropower project Hydro-Québec Need identified Environmental impact assessment Project notice Filing of environmental impact statement Engineering Procurement Construction Commissioning Summary and follow-up Preliminary studies Draft design Permitting Project Post-project / Operation Impact statement guidelines Public hearings Government authorizations Screening analysis Recommendations to authorities Authorities and governement bodies 7

8 From design to operation Preliminary studies in collaboration with the Crees Agreement with Mistissini community Participation in geotechnical field surveys 20 public meetings in 6 Cree communities Paix des Braves (Cree Nation and Québec government) Boumhounam Agreement Cd (Cree Nation and Hydro-Québec) Preliminary studies

9 Project design criteria 1. Minimal flooding of land 2. Application of an ecological instream flow regime in the Rupert River 3. Maintenance of a flow equivalent to the natural flow in the Lemare and Nemiscau rivers 4. Building of hydraulic structures on the Rupert River to protect fish communities and habitat, preserve the landscape and support navigation and land use in some of its stretches 5. Mesgouez Lake, Champion Lake and Lake Nemiscau kept at their natural levels 6. Supply of drinking water ensured for the village of Waskaganish Preliminary studies

10 Eastmain-1-A A / Rupert Dam and Spillway 10

11 Rupert river Ecological Instream Flow Regime 416 m 3 /s If cold fall - October 28 Between 5 days Spring 45 days 9 days 3 days 267 m 3 /s Fall 3 days If warm fall - November m 3 /s 127 m 3 /s 20 to 30 days 127 m 3 /s Flow Winter Summer Winter Time Never before May 8 Early July October 5 11

12 12 Rupert River hydraulic structures

13 Rupert river hydraulic structures Weir PK 290 Spur KP 85 Weir PK 170 Rock blanket PK 20,4 13

14 Sand dune Wetlands 14 Old Nemaska village Nemiscau lake

15 From design to operation Draft design Cree Hydro-Québec Feasibility study group (Boumhounam Committee) 33 meetings Participation in technical and environmental studies and EIA ( person-day) Gathering and integration of traditional knowledge Workshops with trappers (24 meetings) Cd 15

16 Interview Traditional knowledge Land use 16

17 Field survey with a Cree collaborator Barge marbrée Barge marbrée 17

18 From design to operation Permitting Government authorizations Main steps Schedule Public consultation on directives Public consultation on EIA compliance Public hearings Provincial authorization 97 conditions Federal authorization 40 Cd conditions May June 2003 February April March 9 June 2006 November 2006 February

19 From design to operation Project EPC Monitoring Committee (Cree communities Niskamoon Society HQ) Participation in technical and environmental studies ( person-day) Individual interviews with 33 trappers (405 meetings) Roadshows in each community Cd 19 Sarcelle : 150 MW

20 Communication tools Newsletter Radio program Project EPC www 20 Web sites and CD-ROM

21 Measures to promote economic spinoff within Cree communities Project EPC Approval of 5 million $ in contracts for the design phase 200 construction contracts worth > 600 million $ with 39 Cree companies Hiring of a Cree employment counselor A 1.5-million $ fund for theoretical and hands-on training of Cree workers Allocation of 45 million $ worth of contracts during operations 21

22 Clearing of diversion bays to facilitate flow, navigation and land use Clearing of corridor Boat launch Safety signs Portage sign 22

23 23 Lake Sturgeon Spawning ground and hatchery

24 24 Wetlands, fish and GHG studies

25 Eastmain-1-A A / Rupert Walter Jolly Bay 25

26 From design to operation Operation Environmental follow-up ( ) Monitoring Committee Smokey Hill Liaison Committee Rupert River Water Management Board Trappers annual monitoring of navigation corridors Eastmain-1-A Public consultation in 2012 on mitigation measures effectiveness 26

27 Eastmain-1-A A / Rupert Scoop fishing at Smokey Hill 27

28 Hydro-Québec best practices 1. Continuous involvement of stakeholders at every stage of the projects 2. Agreements with the indigenous communities and Regional Authorities 3. Social, environmental and, technical criteria included in agreements 4. Extensive public participation 5. Maximizing social and economic spinoff for host-communities 6. Extensive environmental monitoring program 28

29 29 Obrigado - Gracias Thank you

The Project and Your Community

The Project and Your Community Eastmain-1-A/Sarcelle/Rupert The Project and Your Community Eastmain Signed in 2002, the Boumhounan Agreement launched the Eastmain-1-A and Sarcelle powerhouses and Rupert diversion project. Under this

More information

85 TH ICOLD ANNUAL MEETING

85 TH ICOLD ANNUAL MEETING 85 TH ICOLD ANNUAL MEETING Submitted by: Johanne Bibeau, Eng. AECOM Consultants Inc. tel :514 287 8500 85, rue Sainte-Catherine West fax :514 287 8600 Montreal (Quebec) Canada H2X 3P4 www.aecom.com 04001805-4129

More information

Report. Eastmain-1-A and Rupert Diversion hydropower project

Report. Eastmain-1-A and Rupert Diversion hydropower project Report Eastmain-1-A and Rupert Diversion hydropower project Report by the Provincial Review Committee to the Administrator of Chapter 22 of the James Bay and Northern Québec Agreement. REPORT EASTMAIN-1-A

More information

SALTWATER INTRUSION IN THE BAIE DE RUPERT, JAMES BAY, CANADA

SALTWATER INTRUSION IN THE BAIE DE RUPERT, JAMES BAY, CANADA IAIA17 Conference Proceedings IA s Contribution in Addressing Climate Change 37 th Annual Conference of the International Association for Impact Assessment 4-7 April 2017 Le Centre Sheraton Montréal Canada

More information

HYDRO-QUÉBEC ELECTRICITY: CLEAN, RENEWABLE AND RELIABLE. November 2015

HYDRO-QUÉBEC ELECTRICITY: CLEAN, RENEWABLE AND RELIABLE. November 2015 HYDRO-QUÉBEC ELECTRICITY: CLEAN, RENEWABLE AND RELIABLE Update from HQUS November 2015 Today s Energy Challenges Global Warming Solutions Act Role of large hydropower: multiple system benefits in a single

More information

Amisk Hydroelectric Project Update

Amisk Hydroelectric Project Update Amisk Hydroelectric Project Update AHP Development Corporation (AHP) is providing an update on the Amisk Hydroelectric Project ( Amisk /the Project ). Amisk is a proposed run-of-river hydroelectric project,

More information

A Major Effort to Harmonize Communities Energy, Economic and Social Development

A Major Effort to Harmonize Communities Energy, Economic and Social Development 30th Annual Meeting IAIA April 2010 Environmental Impact Assessment Studies at Hydro-Québec: A Major Effort to Harmonize Communities Energy, Economic and Social Development Louise Emond Background By their

More information

MINUTES OF THE. 279th MEETING OF COMEX (APPROVED)

MINUTES OF THE. 279th MEETING OF COMEX (APPROVED) MINUTES OF THE 279th MEETING OF COMEX (APPROVED) DATE: June 23, 2011 PLACE: James Bay Advisory Committee on the Environment (JBACE) office 383, rue Saint-Jacques Bureau C-220 Montréal PRESENT: Pierre Mercier

More information

The Adapted Forestry Regime (Chapter 3) of the Agreement concerning a new relationship between the Gouvernement of Québec and the Crees of Québec

The Adapted Forestry Regime (Chapter 3) of the Agreement concerning a new relationship between the Gouvernement of Québec and the Crees of Québec The Adapted Forestry Regime (Chapter 3) of the Agreement concerning a new relationship between the Gouvernement of Québec and the Crees of Québec ACHIEVEMENTS AND ISSUES September 2009 February 7, 2002

More information

Forestry and the Crees:

Forestry and the Crees: Isaac Voyageur Director of Environment and Remedial Works Department Cree Nation Government May 27, 2014 Forestry and the Crees: Yesterday, Today and Tomorrow According to Cree Elders, forestry companies

More information

MEETING ENERGY NEEDS WITH CLEAN AND RENEWABLE POWER

MEETING ENERGY NEEDS WITH CLEAN AND RENEWABLE POWER MEETING ENERGY NEEDS WITH CLEAN AND RENEWABLE POWER Christian G. Brosseau President HQ Energy Services US November 2010 A Snapshot of Hydro-Québec Hydro-Québec is the largest power generator in North America

More information

Adapting Project Descriptions for Climate Change

Adapting Project Descriptions for Climate Change IAIA 2017 Session: Adapting projects in a changing northern climate Adapting Project Descriptions for Climate Change April 6, 2017 Isaac Voyageur, Cameron McLean Introduction We will describe the observations

More information

Rainy-Namakan Rule Curves Final Letter Report following and considering Public Comments. November 8, 2017

Rainy-Namakan Rule Curves Final Letter Report following and considering Public Comments. November 8, 2017 Rainy-Namakan Rule Curves Final Letter Report following and considering Public Comments November 8, 2017 This document summarizes the public comments received by the International Rainy and Namakan Lakes

More information

October 31, Designated Project Nemaska Lithium (NMX) s Whabouchi Mine Project CEAA Registry Object Annual Report 2016

October 31, Designated Project Nemaska Lithium (NMX) s Whabouchi Mine Project CEAA Registry Object Annual Report 2016 450, rue de la Gare-du-Palais Québec (QC) G1K 3X2 Tél. 418 704-6038 Téléc. 418 614-0627 October 31, 2017 Michel Vitou Head of Compliance and Law Enforcement Department Canadian Environmental Assessment

More information

Columbia River Treaty 2014/2024 Review U.S. Army Corps of Engineers Bonneville Power Administration Review

Columbia River Treaty 2014/2024 Review U.S. Army Corps of Engineers Bonneville Power Administration Review Columbia River Treaty 2014 2024 Review Update January 11, 2013 PNUCC Presentation Stephen Oliver Bonneville Power Administration U.S. Co Coordinator for Columbia River Treaty Co Chair Sovereign Review

More information

Whabouchi Project: designed to account for both environmental, social and economic concerns

Whabouchi Project: designed to account for both environmental, social and economic concerns Whabouchi Project: designed to account for both environmental, social and economic concerns October 8, 2015 Simon Thibault Director Environmental and Social Responsibility Project Timeline from Now On

More information

1. Why is NB Power recommending Life Achievement as the best option?

1. Why is NB Power recommending Life Achievement as the best option? F.A.Q. Mactaquac Generating Station Life Achievement Project December 2016 1. Why is NB Power recommending Life Achievement as the best option? This approach has the lowest cost estimate when compared

More information

Integrity issues in Hydropower Development: Hydropower Development in Sikkim. Neena Rao, PhD. June 6th 2013

Integrity issues in Hydropower Development: Hydropower Development in Sikkim. Neena Rao, PhD. June 6th 2013 Integrity issues in Hydropower Development: Hydropower Development in Sikkim Neena Rao, PhD June 6th 2013 Neena@saciwaters.org Mountainous regions population engaged in subsistence farming & scarce land

More information

olumbia River Treaty The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct

olumbia River Treaty The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct 2006 1 Presentation Outline Geography of the Pacific Northwest Bonneville Power Administration

More information

Session: For more information:

Session: For more information: Session: For more information: www.hydropower.org/congress General Institute of Water Resources and Hydropower Planning and Design, Ministry of Water Resource Regulation of Downstream Flows in China Li

More information

POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION

POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION WATER POWER ACT LICENCES POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION SUPPORTING DOCUMENTATION Prepared for: Manitoba Sustainable Development 200 Saulteaux Crescent Winnipeg

More information

Klamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR

Klamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR Klamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR Agenda Time 1:00pm 2:00pm 3:00pm Item Presentation on Design-Build RFQ 1. Room Safety 2. Project Background

More information

Overview of Columbia River System Operations for Hydropower and Fish Passage

Overview of Columbia River System Operations for Hydropower and Fish Passage Consultation on MRC s Hydropower Programme Vientiane, Lao PDR, 25-26 September 2008 Overview of Columbia River System Operations for Hydropower and Fish Passage By Bolyvong Tanovan, PhD, PE Chief, Water

More information

EXECUTIVE SUMMARY. Executive Summary. Introduction to Water Use Planning

EXECUTIVE SUMMARY. Executive Summary. Introduction to Water Use Planning EXECUTIVE SUMMARY Executive Summary Introduction to Water Use Planning Water Use Planning was announced in 1996 to ensure that provincial water management decisions reflect changing public values and environmental

More information

Green, Renewable Power

Green, Renewable Power Green, Renewable Power Affordable Sust ainable R espec tfu l Growing North America s Renewable Energy Capacity Manitoba Hydro, one of Canada s largest energy utilities, generates clean, affordable energy

More information

Table of Contents. Nov. 2008

Table of Contents. Nov. 2008 Nov. 2008 What is involved? Electrical loads in Yukon are increasing. By 2011, Yukon Energy expects to need additional renewable power to help minimize the use of diesel to generate electricity. As outlined

More information

HYDRO-QUÉBEC A N AT U R A L A L LY F O R MA S S AC H U S E T T S E N E R G Y T R A N S I T I O N

HYDRO-QUÉBEC A N AT U R A L A L LY F O R MA S S AC H U S E T T S E N E R G Y T R A N S I T I O N HYDRO-QUÉBEC A N AT U R A L A L LY F O R M A S S A C H U S E T T S E N E R G Y T R A N S I T I O N 1,090 M W O F N E W, FIRM CLEAN ENERGY FOR MASSACHUSE T TS In response to the Massachusetts Clean Energy

More information

FEASIBILITY STUDY GUIDELINES

FEASIBILITY STUDY GUIDELINES FEASIBILITY STUDY GUIDELINES Pakhtunkhwa Energy Development Organization (PEDO) Energy and Power Department, KP Prepared by Pakhtunkhwa Energy Development Organization Feasibility Study Guidelines Volume

More information

Ontario s Changing Energy Landscape

Ontario s Changing Energy Landscape Ontario s Changing Energy Landscape Terry Young Vice-President, Policy, Engagement and Innovation January 23, 2018 IESO: Who we are and what we do Reliably operate Ontario s province-wide system 24/7 Support

More information

Guiding Principles on Sustainable Hydropower Development in the Danube River Basin

Guiding Principles on Sustainable Hydropower Development in the Danube River Basin Guiding Principles on Sustainable Hydropower Development in the Danube River Basin Lead Countries : Austria, Romania, Slovenia in the frame of the International Commission for the Danube River Protection

More information

Project Summary Table - Amisk Hydroelectric Project

Project Summary Table - Amisk Hydroelectric Project Proponent Name: AHP Development Corporation Date: 12 June 2015 Project Name: Amisk Hydroelectric Project Company Contact Name and Information: Name of Company that will hold Approval: Type of Project:

More information

Appendix A. Regulation of the HBDB. Chapter 3: Freshwater System Appendices. Reindeer Lake

Appendix A. Regulation of the HBDB. Chapter 3: Freshwater System Appendices. Reindeer Lake Appendix A Regulation of the HBDB Reindeer Lake As the largest lake in the Churchill River Basin, Reindeer Lake serves as an off-channel storage reservoir for Island Falls GS, a hydroelectric generating

More information

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project

More information

Pic Mobert First Nation White River Watershed Compensation Flow Management & Development

Pic Mobert First Nation White River Watershed Compensation Flow Management & Development Showcasing Water Innovation Pic Mobert First Nation White River Watershed Compensation Flow Management & Development Pic Mobert Leaders and Members celebrate a water ceremony at the site of the Gitchi

More information

Takatz Lake Project - Alaska

Takatz Lake Project - Alaska BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT SUBMITTED BY: City and Borough of Sitka Electric Department 105 Jarvis Street Sitka, Alaska 99835 June, 2008 Initial Statement

More information

ENVIRONMENTAL FLOWS PRINCIPLES AND METHODS

ENVIRONMENTAL FLOWS PRINCIPLES AND METHODS ENVIRONMENTAL FLOWS PRINCIPLES AND METHODS Medellin, November 2017 Dr. Brian Glover Bærekraftig Investering AS brian@bkraft.no Environmental flows- Overview 1 Principles and reasons for E-flow 2 Examples

More information

Building a Canadian Diamond Resource Base Stornoway s Renard Diamond Project

Building a Canadian Diamond Resource Base Stornoway s Renard Diamond Project 1 Building a Canadian Diamond Resource Base Stornoway s Renard Diamond Project June 1 st, 2011 Symposium MINES Baie-James 2011, Mistissini Patrick Godin, Vice-President and COO Forward Looking Information

More information

Xayaburi Hydropower Project

Xayaburi Hydropower Project The 5 th Regional Stakeholder Forum Basin Planning and Environmental Management 20-21 September 2018 Landmark Hotel, Vientiane, Lao PDR Review of the Design Changes made for the Xayaburi Hydropower Project

More information

Keeyask Generation Project

Keeyask Generation Project Keeyask Generation Project CEC Hearings - Environmental Impact Statement t t Moving Forward as Partners on Environmental Matters Carolyne Northover: Sr. Environmental Specialist, Manitoba Hydro Ted Bland:

More information

Key Issues: 8- Minority Group 11- Benefits due to Power Generation

Key Issues: 8- Minority Group 11- Benefits due to Power Generation IEA Hydropower Implementing Agreement Annex VIII Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 08-02: Minority Group - Minashtuk o G.S., Canada Key Issues: 8- Minority

More information

Columbia Basin Operations and Flood Risk Management

Columbia Basin Operations and Flood Risk Management Columbia Basin Operations and Flood Risk Management Julie Ammann, PE Chief, Reservoir Control Center Northwestern Division USACE US Army Corps of Engineers BUILDING STRONG The Columbia River Basin Drainage

More information

Removal of the Krebsbach Dam Lessons learned after 11 years. Hudiksvall/Sweden, Ercan Ayboga

Removal of the Krebsbach Dam Lessons learned after 11 years. Hudiksvall/Sweden, Ercan Ayboga Removal of the Krebsbach Dam Lessons learned after 11 years Hudiksvall/Sweden, 25.09.2018 Introduction Situated in low mountain range (300 m altitude) Rock embankment Dam 18,8 m high Impoundment length:

More information

The Hydro Province. *Manitoba Hydro is the licensee of the Trademark and Official Mark.

The Hydro Province. *Manitoba Hydro is the licensee of the Trademark and Official Mark. The Hydro Province Manitoba Hydro is one of the largest integrated electricity and natural gas distribution utilities in Canada, serving 548,000 electric customers across Manitoba and 269,000 natural gas

More information

WUSKWATIM GENERATION PROJECT

WUSKWATIM GENERATION PROJECT WUSKWATIM GENERATION PROJECT CANADIAN ENVIRONMENTAL ASSESSMENT ACT COMPREHENSIVE STUDY REPORT PREPARED BY FISHERIES AND OCEANS CANADA CENTRAL AND ARCTIC REGION October 2005 Fisheries and Oceans Canada

More information

Physical Works Terms of Reference

Physical Works Terms of Reference Physical Works Terms of Reference Williston Targeted Debris Management GMSWORKS #22 Order/Clause: Schedule A 3 (c ) and 5 (a) November 26, 2008 1.0 Introduction Terms of Reference for the Peace Water Use

More information

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis Andrew Hamann, Prof. Gabriela Hug Power Systems Laboratory, ETH Zürich February 8, 2017 Future Electric Power Systems and

More information

EXECUTIVE SUMMARY. commence as planned in the fall of 2012 with a projected in-service date of October Current Vulnerability

EXECUTIVE SUMMARY. commence as planned in the fall of 2012 with a projected in-service date of October Current Vulnerability This Environmental Impact Statement ( EIS ) is filed as part of the process to secure an Environment Act License for the Project in order that construction can commence as planned in the fall of 2012 with

More information

Session: For more information:

Session: For more information: Session: For more information: www.hydropower.org/congress VALUE CREATION AT HYDROPOWER PROJECTS IHA World Congress 2015 Session : Macroeconomic Benefits Emmanuel Branche, EDF Senior Economist EDF Project

More information

The Mackenzie River Hydroelectric Complex Concept Study

The Mackenzie River Hydroelectric Complex Concept Study 8 The Mackenzie River Hydroelectric Complex Concept Study F. Pierre Gingras ABSTRACT This chapter provides an overview of a recent study of the potential of harnessing the Northwest Territories Mackenzie

More information

Water/Energy Symposium

Water/Energy Symposium RECLAMATION Managing Water in the West Water/Energy Symposium Pittsburgh, PA September 29, 2010 U.S. Department of the Interior Bureau of Reclamation Western United States Early 1900 s Grand Valley Project,

More information

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME 1 Introduction and Background To meet its environmental and social obligations and commitments, the Lesotho Highlands Development

More information

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI 220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TERMS OF REFERENCE Transmission line Akhalsikhe-Batumi Georgia Terms of Reference for Tender docs and ESIA 2 1 PROJECT

More information

Columbia River Treaty: Recommendations December 2013

Columbia River Treaty: Recommendations December 2013 L O CA L G O V E R N M E N TS CO M M I TTEE Columbia River Treaty: Recommendations The BC Columbia River Treaty Local Governments Committee (the Committee) has prepared these Recommendations in response

More information

Geopolitical benefits of transboundary water cooperation. The Mekong River Basin Case

Geopolitical benefits of transboundary water cooperation. The Mekong River Basin Case Geopolitical benefits of transboundary water cooperation The Mekong River Basin Case Dr Anoulak Kittikhoun Coordinator, Basin Development Plan (BDP) Mekong River Commission Secretariat Mekong - Top 10

More information

US ARMY CORPS OF ENGINEERS ACTIONS DURING 2016 TEXAS SPRING FLOOD

US ARMY CORPS OF ENGINEERS ACTIONS DURING 2016 TEXAS SPRING FLOOD 1 US ARMY CORPS OF ENGINEERS ACTIONS DURING 2016 TEXAS SPRING FLOOD 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62

More information

The First Mekong River Commission Summit 2010

The First Mekong River Commission Summit 2010 15th Anniversary 5 April 1995 5 April 2010 The First Mekong River Commission Summit 2010 The Mekong Basin as a source of economic prosperity The water resources of the 795,000 square kilometer Mekong Basin

More information

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG)

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG) Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG) The RE CDM PoA in PNG Programme of Activities (PoA) for Sustainable RE Power in Papua New Guinea (PNG) envisages

More information

TALTSON HYDROELECTRIC EXPANSION PROJECT

TALTSON HYDROELECTRIC EXPANSION PROJECT TALTSON HYDROELECTRIC EXPANSION PROJECT Prepared for: Yellowknife Scoping Sessions December 7, 2007 Presented by: DEZÉ ENERGY CORPORATION TALTSON HYDROELECTRIC EXPANSION PROJECT Introduction Presentation

More information

7.9 Lake Whitney Reallocation

7.9 Lake Whitney Reallocation 7.9 Lake Whitney Reallocation 7.9.1 Description of Option Lake Whitney is a major impoundment located on the Brazos River approximately 30 miles north of the City of Waco in Hill and Bosque Counties. The

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

Nam Theun 2. TNC workshop April 2014

Nam Theun 2. TNC workshop April 2014 Nam Theun 2 1 TNC workshop April 2014 The Hydropower Project Build, Operate, Transfer 25 year concession for Nam Theun Power Co. US$1.3 Billion cost, financed by 27 parties (1/3 Equity; 2/3 debt) Generating

More information

Dear Ms. Bose, Thank you for the opportunity to comment on the application by Juneau Hydropower Inc. for a

Dear Ms. Bose, Thank you for the opportunity to comment on the application by Juneau Hydropower Inc. for a United States Department of Agriculture Forest Service Alaska Region Tongass National Forest 648 Mission Street Ketchikan, AK 99901 Phone: (907) 225-3101 Fax: (907) 228-6215 File Code: 2770-1 Date: November

More information

Columbia River Treaty Review: Iteration #2 Results, and Next Steps

Columbia River Treaty Review: Iteration #2 Results, and Next Steps Columbia River Treaty Review: Status, General Summary of Iteration #2 Results, and Next Steps Rick Pendergrass Bonneville Power Administration PNUCC May 3, 2013 Slide 1 Current Activities Sovereign Review

More information

The Project. Federal Regulatory Approvals and Involvement

The Project. Federal Regulatory Approvals and Involvement Government of Canada Response to the Report of the Joint Federal-Provincial Review Panel for Nalcor s Lower Churchill Generation Project in Newfoundland and Labrador The Project Nalcor Energy proposes

More information

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan EXECUTIVE SUMMARY The consultative process was initiated in April 2000 and completed in November 2001. The consultative process follows the steps outlined in the 1996 provincial government Water Use Plan

More information

GEIDCO Summit 22 February Designing collaborative and adaptive approaches to river basin development

GEIDCO Summit 22 February Designing collaborative and adaptive approaches to river basin development GEIDCO Summit 22 February 2017 60 50 40 30 20 10 0 Designing collaborative and adaptive approaches to river basin development International Hydropower Association Origin Created in 1995, under the auspices

More information

FEEDBACK FORM INSIDE. Peace River Site C Hydro Project. B.C. s growing electricity gap. and Feedback Form

FEEDBACK FORM INSIDE. Peace River Site C Hydro Project. B.C. s growing electricity gap. and Feedback Form FEEDBACK FORM INSIDE Peace River Site C Hydro Project An option to help close B.C. s growing electricity gap Pre-Consultation Discussion Guide and Feedback Form DECEMBER 2007 SITE C Pre-Consultation Discussion

More information

TOLEDO BEND PROJECT FERC NO DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES

TOLEDO BEND PROJECT FERC NO DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES TOLEDO BEND PROJECT FERC NO. 2305 DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES May 2011 Copyright 2011.Sabine River Authority of Texas and Sabine River

More information

PATHS FORWARD HYDROPOWER AND ABORIGINAL RELATIONSHIPS ACROSS CANADA

PATHS FORWARD HYDROPOWER AND ABORIGINAL RELATIONSHIPS ACROSS CANADA PATHS FORWARD HYDROPOWER AND ABORIGINAL RELATIONSHIPS ACROSS CANADA 2 PATHS FORWARD Communities and customers across Canada demand clean, renewable, reliable and affordable electricity. Hydropower delivers

More information

SURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) General Phase 1 Workshop Presentation (February 3 through March 8, 2017)

SURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) General Phase 1 Workshop Presentation (February 3 through March 8, 2017) SURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) General Phase 1 Workshop Presentation (February 3 through March 8, 2017) Agenda Introductions and Overview Project Overview Activity 1 Hazards BREAK Activity

More information

CANADA / U.S. TRANSMISSION LINE IMPACT ASSESSMENT. Leigh Hagan & Patrick Solomon. IAIA April 2017 Montréal, Canada

CANADA / U.S. TRANSMISSION LINE IMPACT ASSESSMENT. Leigh Hagan & Patrick Solomon. IAIA April 2017 Montréal, Canada IAIA17 4-7 April 2017 Montréal, Canada SESSION 203: INTERJURISDICTIONAL COLLABORATION - OPPORTUNITIES AND CHALLENGES CANADA / U.S. TRANSMISSION LINE IMPACT ASSESSMENT Leigh Hagan & Patrick Solomon 2017

More information

Columbia River Treaty Review. PNWA Summer Meeting LaConner, WA June 24, 2013

Columbia River Treaty Review. PNWA Summer Meeting LaConner, WA June 24, 2013 PNWA Summer Meeting LaConner, WA June 24, 2013 1 Treaty Basics Purpose of 2014/2024 Treaty Review Mechanics of Treaty Review Summary of Iteration 2 Navigation Impact Assessment Stakeholder involvement

More information

April 29, 2016 VIA ELECTRONIC FILING. Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

April 29, 2016 VIA ELECTRONIC FILING. Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 April 29, 2016 VIA ELECTRONIC FILING Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: FirstLight Hydro Generating Company, FERC Project

More information

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016 Welcome to the Boulevard Lake Dam Class Environmental Assessment Public Information Session #1 June 14, 2016 Boulevard Dam - Overview Built approximately 100 years ago Owned and operated by the City of

More information

Appendix P. U.S. Fish and Wildlife Service Planning Aid Letter

Appendix P. U.S. Fish and Wildlife Service Planning Aid Letter Appendix P U.S. Fish and Wildlife Service Planning Aid Letter This page is intentionally left blank. United States Department of the Interior FISH AND WILDLIFE SERVICE Missouri Ecological Services Field

More information

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE Q U É B E C S H Y D R O P O W E R R E S O U R C E S P O W E R I N G T H E E M P I R E S TAT E LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE Hydro-Québec, New York s energy partner for decades,

More information

Volume 7, Issue 4, December People with a powerful vision

Volume 7, Issue 4, December People with a powerful vision Volume 7, Issue 4, December 2009 People with a powerful vision A busy year is drawing to a close. 2009 It s been a year of intense efforts to deliver the goods. All the project objectives, and particularly

More information

Climate-resilient hydropower: Experiences from the EBRD region

Climate-resilient hydropower: Experiences from the EBRD region Climate-resilient hydropower: Experiences from the EBRD region Sandy Ferguson Manager, Knowledge and Policy European Bank for Reconstruction and Development fergusos@erbrd.com Hydropower is a major source

More information

Columbia River Treaty Frequently Asked Questions (FAQs)

Columbia River Treaty Frequently Asked Questions (FAQs) Columbia River Treaty Frequently Asked Questions (FAQs) Spring 2012 Columbia River Treaty 1. What is the Columbia River Treaty? The Columbia River Treaty is a trans-boundary water management agreement

More information

Environmental Monitoring at the La Grande Complex. Evolution of Fish Mercury Levels. Summary Report

Environmental Monitoring at the La Grande Complex. Evolution of Fish Mercury Levels. Summary Report Environmental Monitoring at the La Grande Complex Evolution of Fish Mercury Levels Summary Report 1978-2012 OCTOBER 2013 Environmental Monitoring at the La Grande Complex Evolution of Fish Mercury Levels

More information

Presenter: CLYDE HUNT. Project Manager Memphis District August 2010

Presenter: CLYDE HUNT. Project Manager Memphis District August 2010 Presenter: CLYDE HUNT Project Manager Memphis District 24-25 August 2010 US Army Corps of Engineers Memphis District Brief History Secretary Westphal ASA (Civil Works) received several letters from the

More information

Hydromorphology in the Danube River Basin

Hydromorphology in the Danube River Basin Workshop on Transboundary Water Resources Management in Western and Central Europe 8-10 February 2011, Budapest, HU Hydromorphology in the Danube River Basin Raimund MAIR, ICPDR Technical Expert on River

More information

Legal Basis of Water Management in Austria

Legal Basis of Water Management in Austria Legal Basis of Water Management in Austria Abstract by F. Oberleitner The following text is only a gross outline of the theme concerned. For essential further information see the script (in German only).

More information

Photo credit: Eastmain Cree Cultural Department

Photo credit: Eastmain Cree Cultural Department P-108 Presentation by the Cree Board of Health and Social Services of James Bay to the Public Inquiry Commission on Relations between Indigenous Peoples and Certain Public Services in Québec Bella M. Petawabano,

More information

Wildlife Management Area

Wildlife Management Area Proposed Wildlife Management Area A wildlife management area designation is being proposed for the Harrison-Chehalis area to conserve fish and wildlife habitats while also respecting existing and compatible

More information

SUSTAINABLE DEVELOPMENT Highlights

SUSTAINABLE DEVELOPMENT Highlights SUSTAINABLE DEVELOPMENT 2010 Highlights FIGHTING CLIMATE CHANGE Eastmain 1 reservoir, where gross greenhouse gas emissions are comparable to those of natural lakes. A REMARKABLE PERFORMANCE Our net exports

More information

Town of Canmore. Climate Change Adaptation Background Report and Resilience Plan

Town of Canmore. Climate Change Adaptation Background Report and Resilience Plan Town of Canmore Climate Change Adaptation Background Report and Resilience Plan PRAC Webinar Tools for Municipal Adaptation Action May 4 th, 2018 Lori Rissling Wynn Sustainability Coordinator/Development

More information

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impacts July 14-19, 2014 Content Project History Purpose and Scope The Project Area The Project The Project

More information

FORM B: DAMMING AND DIVERSION OF WATER

FORM B: DAMMING AND DIVERSION OF WATER APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan

More information

TOWARDS ADAPTATION edition. Caroline Larrivée Vulnerabilities, impacts and adaptation - OURANOS. Synthesis of Climate Change knowledge in Quebec

TOWARDS ADAPTATION edition. Caroline Larrivée Vulnerabilities, impacts and adaptation - OURANOS. Synthesis of Climate Change knowledge in Quebec TOWARDS ADAPTATION Synthesis of Climate Change knowledge in Quebec 2014 edition Caroline Larrivée Vulnerabilities, impacts and adaptation - OURANOS THE CHANGING CLIMATE : ADAPTATION BY FIRST NATIONS IN

More information

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

BC Hydro Contact: Vancouver Island Community Relations Phone:

BC Hydro Contact: Vancouver Island Community Relations Phone: BC Hydro Contact: Vancouver Island Community Relations Phone: 250 755-7173 Project Team: Trade-off Analyst and Facilitator: Tony Wong, Quintry Management Consulting Inc. Resource Valuation Task Manager:

More information

MINUTES OF THE (ADOPTED) Murdoch Archambault Avocats 407 McGill St., Suite 410 Montréal, QC H2Y 2G3

MINUTES OF THE (ADOPTED) Murdoch Archambault Avocats 407 McGill St., Suite 410 Montréal, QC H2Y 2G3 MINUTES OF THE 356 th MEETING OF THE REVIEW COMMITTEE () (ADOPTED) DATE: August 30, 2017 PLACE: PRESENT: Murdoch Archambault Avocats 407 McGill St., Suite 410 Montréal, QC H2Y 2G3, Chairperson, Québec

More information

Transboundary Cooperation Workshop # January 2010, Vientiane. Sharing of Benefits in Transboundary Water Resources Management

Transboundary Cooperation Workshop # January 2010, Vientiane. Sharing of Benefits in Transboundary Water Resources Management Transboundary Cooperation Workshop # 3 20-22 January 2010, Vientiane. Sharing of Benefits in Transboundary Water Resources Management Responses form civil society on stakeholder views on benefit and cost

More information

Avista Dam Relicensing Factsheet Commenting on the Draft License Application

Avista Dam Relicensing Factsheet Commenting on the Draft License Application Avista Dam Relicensing Factsheet Commenting on the Draft License Application Please Note: This is intended for informational purposes only and does not constitute legal advice. The life of every river

More information

WETLAND RESTORATION PROGRAMS IN THE PRUT RIVER BASIN

WETLAND RESTORATION PROGRAMS IN THE PRUT RIVER BASIN Scientific Papers. Series E. Land Reclamation, Earth Observation&Surveying, Environmental Engineering. Vol. I, 2012 Print ISSN 2285 6064, CD-ROM ISSN 2285 6072, ISSN-L 2285 6064 WETLAND RESTORATION PROGRAMS

More information

Hydropower Development, Mitigation and Best Practices in Ontario

Hydropower Development, Mitigation and Best Practices in Ontario April 2014 Hydropower Development, Mitigation and Best Practices in Ontario Imagine the result Contents Introduction 3 Construction Mitigation 5 Some General Lessons 7 Integration of EIA and Construction

More information

NWT Climate Change Strategic Framework. Backgrounder

NWT Climate Change Strategic Framework. Backgrounder NWT Climate Change Strategic Framework Backgrounder INTRODUCTION Climate change is one of the most serious environmental, economic and political challenges of our time and is an important issue to NWT

More information

5 Muskrat Falls Project

5 Muskrat Falls Project 5 Muskrat Falls Project Report by: P. Rae, P. Eng. 5.1 Introduction The Muskrat Falls Project comprises the hydropower generation facility proposed on the Lower Churchill River. The main project elements

More information