INDONESIA S OIL AND GAS INFRASTRUCTURE DEVELOPMENT

Size: px
Start display at page:

Download "INDONESIA S OIL AND GAS INFRASTRUCTURE DEVELOPMENT"

Transcription

1 DIRECTORATE GENERAL OF OIL AND GAS MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA INDONESIA S OIL AND GAS INFRASTRUCTURE DEVELOPMENT Presented at JOGMEC Techno Forum 2017 TOKYO, JAPAN, 28 NOVEMBER 2017

2 THE ROLE OF OIL AND GAS IN INDONESIA S ENERGY MIX 2 Referring to Indonesia s General Plan of National Energy (RUEN) Target in the National Energy Policy (KEN) Role of Energy 46% 26% MTOE Driver of economic growth Portion of Gas in Energy Mix 22% 24% Energy Supply > 400 MTOE > MTOE Power Generation > 115 GW > 430 GW Energy Elasticity < 1 < 1 Power/capita/year kwh kwh Electrification Ratio 100% 100% % 23% 22% 30% MTOE 23% 25% TARGET IN % 24% MTOE 20% 31% Renewable Energy Oil Gas Coal TARGET IN 2050

3 Indonesia Oil & Gas Reserves OIL & GAS RESERVES NAD NORTH SUMATERA NATUNA OIL (Thousand MMSTB) GAS (TCF) MID SUMATERA 2, KALIMANTAN PAPUA SOUTH SUMATERA 1, WEST JAVA 1, , EAST JAVA SULAWESI MALUKU OIL RESERVES GAS RESERVES WORKING ACREAGE : 280 PSCs OIL Production as of Mar 26 th 2017 Kementerian ESDM Republik Indonesia Proven : 3.3 Billion STB Potential : 3.9 Billion STB Total : 7.3 Billion STB Production: 816 Thousand BOPD (oil + condensates) GAS Proven : TSCF Potential : 42.8 TSCF Total : 144 TSCF Production: 7.7 MMSCFD Exploration Exploitation : 195 PSCs : 85 PSCs 3

4 UNCONVENTIONAL OIL & GAS 48 PSC CMB 6 PSC Shale Gas Resources Coalbed Methane: TCF Shale Gas: TCF Kementerian ESDM Republik Indonesia 4

5 ENERGY POLICY 5 The availability of energy aimed to meet domestic demand Energy Regulations in Indonesia Aiming to strengthen the national energy resilient and sovereignty, our energy policy are focus in 5 main pillars: Increasing of electrification ratio, Managing Energy sustainably in order to support the continuity of national economic development Accessible Energy to users in all regions Fair distribution on equality & affordability, Sustainability, (Integrated resource plan, priorities local energy resources) Cultivating the price of energy affordably for all segments of end users Conducive investment & economic growth, and Good governance & streamlining bureaucracy and licensing.

6 6 NATIONAL ENERGY POLICY TARGET (Article 9, Government Regulation 79/2014 on National Energy Policy) 01 NEW PARADIGM Establishment of a new paradigm of energy sources as capital of the national development 02 ENERGY ELASTISITY Energy elasticity achievement shall be less than 1 (one) in 2025 that comply with the economic growth 04 ELECTRIFICATION RASIO Achievement of Electrification Ratio of 85% (eighty five percent) in 2015 and close on 100% (one hundred percent) in HOUSEHOLD GAS UTILIZATION RASIO Achievement of the household gas utilization ratio of 85% (eighty five percent) in ENERGY INTENSITY 06 ENERGY MIX Reduction in final energy intensity of 1% (one percent) per year up to 2025 Achievement of optimal primary energy mix

7 OIL & GAS POLICY REFORMS 7 What has been done? 1 Improvement of Cost Recovery System & Taxation (GR 27/2017 as a revision of GR 79/2010) 2 Improvement of PSC System by Introducing the new Gross Split Scheme (Ministerial Regulation 52/2017) 3 Improvement of recovery mechanism for sunk cost of the latest investment (MR 26/2017) 4 Participating Interest 10% (MR 37/2016) What s next? Asset management for contract termination during exploration phase (revision of GR 35/2004) Performance based commitment (reform of firm commitment) Concept of stabilization clause to accommodate assumed and discharge principle Profit tax regulation in PSC Gross Split Regulation for eligible cost for tax calculation in PSC Gross Split

8 GAS & LNG POLICY REFORMS 8 What has been done? 1 Improvement of gas allocation, pricing, & utilization policy (Ministerial Regulation 06/2016) 2 Gas prices for industries: petrochemical, fertilizer, steel (Ministerial Regulation 40/2016) 3 Acceleration of utilization of gas for transportation (Ministerial Regulation 25/2017) 4 Utilization and pricing of flare gas in upstream oil and gas (Ministerial Regulation No. 32/2017) 5 Improvement of natural gas for power generation (Ministerial Regulation 45/2017) What s next? 1 Downstream gas pricing mechanism 2 Pipeline gas policy reform (revision of Ministerial Regulation 19/2009) 3 LNG import policy 4 Gas governance

9 Net Gross Cost Recovery PSC Oil Production (100%) Equity to be Split (54%) CONTRACTOR S COST EFFICIENCY Cost Recovery 1 (46%) Gross Split PSC Oil Production (100%) Split excluded tax Government (40%) Contractor (14%) Government (57%) Contractor (including cost) (43%) Government (46%) 1 2 years average 2 Tax 40% (40% x 23% = 9%) Kementerian ESDM Republik Indonesia Tax (6%) Contractor (8%) Total Contractor (54%) GROSS SPLIT PSC BENEFIT : Procurement system will be more simple and efficient Contractor can manage their cost independently More incentive for more risky block Flexible and sensitive to oil price and cumulative production 9

10 ON GOING & UPCOMING UPSTREAM OIL & GAS PROJECTS Kementerian ESDM Republik Indonesia 10 ANDE ANDE LUMUT EAST NATUNA Production (Q1 2021): bopd Gas Reserves: 46 TCF CO2 Content: 72% BLOCK A ACEH Gas Reserves: 563 bscf Investment: US$ 1.3 Billion Production: Q IDD BANGKA Gas Reserves bscf Investment: US $ 8 Billion Production: 110 MMSCFD (onstream) JANGKRIK COMPLEX PROJECT Gas Reserves: 2.27 TCF Investment: US$ 4.1 Billion Production (Q3 2017): 450 MMSCFD TANGGUH TRAIN 3 Gas reserves 5.7 TCF Investment: US $ 8 Billion Production (Q2 2020): 700 MMSCFD JAMBARAN TIUNG BIRU Gas reserves: 97 bscf CO 2 Content: 34% Investment US $ 2.2 Billion Production (Q4 2019): 330 MMSCFD MADURA Production (Q1 2017): 110 MMSCFD Investment: US$642Million WASAMBO Production (Q1 2017): 70 MMSCFD Investment: US $ 55.2 million MASELA Gas Reserves: TCF Investment: US $ Billion

11 National Fuel Oil Supply Demand OIL REFINERY DEVELOPMENT Oil Refinery Development Plan in the Next 10 Years Regulations Kementerian ESDM Republik Indonesia Presidential Regulation 146/2015: Refinery Development Ministerial Regulation 25/2016: Privately Funded Oil Refineries Target refinery capacity in 2025: 2 million BPD No Refinery Project Investment (billion US$) 1 GRR Tuban GRR Bontang RDMP Balikpapan RDMP Balongan RDMP Cilacap RDMP Dumai 4.2 RDMP RDMP Balikpapan RDMP Balongan Stage 1 Balikpapan Stage 2 RDMP (existing refinery upgrade) RDMP Cilacap RDMP Dumai GRR Tuban GRR Bontang GRR (new refinery) 11

12 OIL REFINERY DEVELOPMENT PADANG LAWAS PT Indo Kilang Prima Capacity: 6 MBCD Planned Op: 2018 PALEMBANG PT PGRC Capacity: 300 MBCD Planned Op: 2020 PALEMBANG PT DEX Capacity: 10 MBCD Planned Op: 2019 BALONGAN Capacity: 280 MBCD (Existing: 125 MBCD) Complexity Index: 9 Planned Op: 2021 Kementerian ESDM Republik Indonesia DUMAI Capacity: 300 MBCD (Existing: 140 MBCD) Complexity Index: 8 Planned Op: BALIKPAPAN Capacity: 360 MBCD (Existing: 260 MBCD) Complexity Index: 9 Planned Op: CILACAP Capacity: 370 MBCD (Existing: 348 MBCD) Complexity Index: 9 Planned Operation: TUBAN Capacity: 300 MBCD Funding Scheme: Gov t Assignment Investor: Pertamina-Rosneft Planned Operation: 2024 BONTANG Capacity: 300 MBCD Funding Scheme: Gov t Assignment Investor: Tender Awardee Planned Op: 2024 Grassroot Refinery Refinery Upgrading Private Refinery SITUBUNDO PT Kilanindo Golden Star Capacity: 300 MBCD Planned Op:

13 MINI OIL REFINERY DEVELOPMENT MARGINAL OIL FIELDS FOR MINI OIL REFINERY CLUSTERING MoEMR Regulation 22/2016 on Small Scale Oil Refineries PROD (BOPD) CLUSTER I II III IV V VI VII VIII ,191 2,731 1,252 1,653 1,152 3,239 7,002 4, ,253 4,419 4,079 5,728 2, , Cluster I Sumatera Utara 2. Cluster II Selat Panjang Malaka 3. Cluster III Riau 4. Cluster IV Jambi Kementerian ESDM Republik Indonesia 5. Cluster V Sumatera Selatan 6. Cluster VI Kalimantan Selatan 7. Cluster VII Kalimantan Utara 8. Cluster VIII Maluku 13

14 LPG STORAGE FACILITIES IN EASTERN INDONESIA Total Capacity: 5,000 MT Investment Needed: 64.7 million USD Capacity: 2 x 500 MT & jetty Investment: US$ 15.2 million BIMA TOLI - TOLI PARIGI DONGGALA POSO MOUTONG PARE - PARE KOLAKA PALOPO MAKASSAR AMPANA KOLONDALE KENDARI TAHUNA GORONTALO LUWUK BANGGAI BAU -BAU RAHA BITUNG SANANA NAMLEA TERNATE LABUHA WAYAME WAYAME TOBELO HALMAHERA MASOHI RU VII. KASIM BULA Capacity: 2 x 1,000 MT & jetty Investment: US$ 18.4 million SORONG MANOKWARI FAK - FAK TUAL KAIMANA DOBO BIAK NABIRE SERUI Capacity: 2 x 1,000 MT & jetty Investment: US$ 15.2 million TIMIKA JAYAPURA JAYAPURA MANGGIS BADAS MAUMERE KALABAHI REO L. TUKA SAUMLAKI DILI MERAUKE AMPENAN ENDE WAINGAPU ATAPUPU KUPANG TENAU Capacity: 2 x 1,000 MT & jetty Investment: US$ 15.9 million LPG Storage Tank Kementerian ESDM Republik Indonesia 14

15 THE IMPORTANCE OF ENERGY BUFFER RESERVES Kementerian ESDM Republik Indonesia 15 1 crude import dependency (about 39%) and product (fuel 42% and LPG 63%) is increasing 2 IMPORT route prone is influences by geopolitic of exporting countries 3 Enhancing domestic oil / fuel reserves security (there is only operational reserves in the form of fuel for days owned by Pertamina) 4 Ensuring energy security as the last resort in coping with energy supply gas in the case of energy crisis 5 Increasing bargaining position regionally and globally (such as in trading oil/ product with other countries) 6 Supporting national security enhancement to preserve energy supply stability

16 BBTUD Kementerian ESDM Republik Indonesia UTILIZATION OF GAS 16 Average growth of domestic gas demand ( ): 9% Portion of domestic gas demand in 2017 : 58% Status: as of June Ekspor Export Domestik Domestic Utilization of Gas in Indonesia (2017) Domestic LNG 5,53% LNG Export 28,49% CNG for Vehicles 0,08% Pipeline Gas Export 12,62% Domestic LPG 2,11% Power Generation 13,67% Fertilizer 11,15% Industry 23,53% Oil City Gas Lifting 0,05% 2,77%

17 GAS SUPPLY DEMAND PER REGION ( ) 17 There is an oversupply of gas in East Indonesia & Kalimantan The largest gas demand exists in West Indonesia (Java & Sumatera) REGION I , ,8 Supply Demand REGION II , REGION V 495, REGION VI , REGION III ,2 133, REGION IV 545, Region I : Aceh & North Sumatera Region II : Sumatera (South & Central), Riau Islands, West Java Region III : Central Java Region IV : East Java & Bali Region V : East Kalimantan Region VI : Sulawesi, Maluku, Papua

18 EXISTING GAS INFRASTRUCTURE Description Non Pipeline Gas Infrastructure Facilities Existing FSRU Ongoing FSRU Planned FSRU Existing LNG Plant Planned LNG Plant Existing LPG Plant Planned LPG Plant Existing CNG Filling Station Planned CNG Filling Station Existing Receiving Terminal Regasification Terminal Existing CNG Station Gas Transmission & Distribution Network Existing Open Access Pipeline Ongoing Open Access Pipeline Planned Open Access Pipeline Existing Own Use Pipeline Planned Own Use Pipeline Existing Dedicated Upstream Pipeline Planned Dedicated Upstream Pipeline Existing Distribution Pipeline Ongoing Distribution Pipeline Planned Distribution Pipeline Existing Household Gas Network Planned Household Gas Network Kementerian ESDM Republik Indonesia 18

19 NATIONAL GAS INFRASTRUCTURE ROADMAP UNTIL 2030 Aggressive infrastructure development in eastern part of Indonesia Description Non Pipeline Gas Infrastructure Facilities Existing FSRU Ongoing FSRU Planned FSRU Existing LNG Plant Planned LNG Plant Existing LPG Plant Planned LPG Plant Kementerian ESDM Republik Indonesia Existing CNG Filling Station Planned CNG Filling Station Existing Receiving Terminal Regasification Terminal Existing CNG Station Gas Transmission & Distribution Network Existing Open Access Pipeline Ongoing Open Access Pipeline Planned Open Access Pipeline Existing Own Use Pipeline Planned Own Use Pipeline Existing Dedicated Upstream Pipeline Planned Dedicated Upstream Pipeline Existing Distribution Pipeline Ongoing Distribution Pipeline Planned Distribution Pipeline Existing Household Gas Network Planned Household Gas Network 19

20 35,000 MW Electricity Project 20 2,867 MW 267 MMSCFD 1,091 MW 86 MMSCFD 1,830 MW 147 MMSCFD 440 MW 48 MMSCFD 6,754 MW 423 MMSCFD 450 MW 38 MMSCFD TOTAL GAS NEEDED: 1,100 MMSCFD TOTAL POWER: 13,432 MW

21 21 LNG SUPPLY & INFRASTRUCTURE PROJECTS FOR POWER GENERATION PREPARED BY PLN PLN: Indonesia s state owned national electricity company 3* LNG Krueng Raya Nias Target: FSRU Belawan Target: * 8. FSRU Gorontalo Target: * LNG Maluku Papua Target: 2019 LNG Bangka Belitung Pontianak Target: * LNG Central Indonesia Target: FSRU Muara Tawar Target: LNG Terminal Gresik Target: 2021 *Scope of projects (1 4) include: LNG transport, storage & regasification facilities, jetty, and pipeline

22 NATURAL GAS UTILIZATION IN EASTERN INDONESIA USING VIRTUAL PIPELINE Kementerian ESDM Republik Indonesia 22 Gas distribution using Virtual Pipeline Scheme Realization: FSU Benoa, Bali

23 INDONESIA S 1 ST MINI LNG FOR POWER PLANT 23 Bringing LNG from Borneo to Bali Island LNG TERMINAL BENOA

24 CHALLENGES : OIL & GAS FACILITIES 24 Facilities that are not readily available/very limited in the domestic market: - Jack Up Rig - Jack Up Barge - Self Elevating Drilling Unit Semi Submersible Rig Deepwater Drill Ship Floating Production Storage and Offloading (domestic investment is still limited)

25 TECHNOLOGICAL CHALLENGES 25 Mitsubishi Heavy Industries FLOATING POWER PLANTS MINI LNG CARRIER INTEGRATED FLOATING MINI LNG AND POWER LNG MINI FLOATING STORAGE & REGAS UNIT

26 CLOSING REMARKS 26 1 Strategic projects in Indonesia s oil & gas industry which include: Upstream projects to boost reserves & production Midstream & downstream projects to make energy accessible from West to East Indonesia 2 3 Require significant technology to solve related challenges, accelerate development, and promote economic growth. To boost the role of gas as a driver for economic growth, Indonesia needs aggressive infrastructure development, particularly for LNG utilization for power generation in Eastern Indonesia.

27 27

Accelerating Integration of Natural Gas Infrastructure

Accelerating Integration of Natural Gas Infrastructure Accelerating Integration of Natural Gas Infrastructure Presentation to Gas Indonesia Summit Triharyo Soesilo, Director of Energy Sector Committee for Acceleration of Priority Infrastructure Projects Delivery

More information

Key approaches for small-scale LNG developments in Indonesia: ensuring cost-efficiency and project delivery. Julian Thomas AG&P July 13, 2017

Key approaches for small-scale LNG developments in Indonesia: ensuring cost-efficiency and project delivery. Julian Thomas AG&P July 13, 2017 Key approaches for small-scale LNG developments in Indonesia: ensuring cost-efficiency and project delivery Julian Thomas AG&P July 13, 2017 Agenda 1. Challenges and opportunities in the Indonesian energy

More information

Commercializing gas value chains to create and enhance demand for LNG. Ken Sauer Commercial 3 July 13, 2017

Commercializing gas value chains to create and enhance demand for LNG. Ken Sauer Commercial 3 July 13, 2017 Commercializing gas value chains to create and enhance demand for LNG Ken Sauer Commercial 3 July 13, 2017 Risco-AG&P: a snapshot The company RISCO-AG&P is a diversified oil and gas Infrastructure company

More information

Gas Pricing and Financing

Gas Pricing and Financing Gas Pricing and Financing Gigih Prakoso Pertamina Jakarta, 28 January 2015 PT Pertamina (Persero) Jln. Medan Merdeka Timur No.1A Jakarta 10110 Telp (62-21) 381 5111 Fax (62-21) 384 6865 http://www.pertamina.com

More information

INTEGRATING NATURAL GAS INFRASTRUCTURE TO MARKET

INTEGRATING NATURAL GAS INFRASTRUCTURE TO MARKET INTEGRATING NATURAL GAS INFRASTRUCTURE TO MARKET PT Perusahaan Gas Negara (Persero) Tbk May 2014 GEO ENERGY CONFERENCE AND EXIBITION : 4th LNG Supply, Transport & Storage INTRODUCTION PGN IS A STATE OWNED

More information

Delivering Energy. Upstream Stranded Domestic Gas Potential to meet Energy Demand through LNG Value Chain: Lessons Learned from Senoro-DSLNG

Delivering Energy. Upstream Stranded Domestic Gas Potential to meet Energy Demand through LNG Value Chain: Lessons Learned from Senoro-DSLNG Delivering Energy Upstream Stranded Domestic Gas Potential to meet Energy Demand through LNG Value Chain: Lessons Learned from Senoro-DSLNG Eka Satria, Development Director - PT Medco Energi International

More information

ACCELERATION OF SMALL SCALE LNG SUPPLY CHAIN INFRASTRUCTURE FOR CENTRAL AND EAST REGION OF INDONESIA

ACCELERATION OF SMALL SCALE LNG SUPPLY CHAIN INFRASTRUCTURE FOR CENTRAL AND EAST REGION OF INDONESIA ACCELERATION OF SMALL SCALE LNG SUPPLY CHAIN INFRASTRUCTURE FOR CENTRAL AND EAST REGION OF INDONESIA 1 Electricity Condition of Central & East Indonesia The installed capacity of power plants owned by

More information

Additional information on calculating the emission factors of Indonesia for the JCM. Table 1 Grid emission factor PV Case 1 and Case 2

Additional information on calculating the emission factors of Indonesia for the JCM. Table 1 Grid emission factor PV Case 1 and Case 2 Additional information on calculating the emission factors of Indonesia for the JCM In order to secure net emission reductions in the methodology, the following emission factors will be applied depending

More information

UPSTREAM PERSPECTIVE ON INDONESIA GAS SUPPLY DEMAND. Jean-Francois Hery Head of Commercial Division

UPSTREAM PERSPECTIVE ON INDONESIA GAS SUPPLY DEMAND. Jean-Francois Hery Head of Commercial Division Marc Roussel / Total UPSTREAM PERSPECTIVE ON INDONESIA GAS SUPPLY DEMAND Jean-Francois Hery Head of Commercial Division DISCLAIMER This presentation may include forward-looking statements within the meaning

More information

SUNSET OF OIL AND GAS INVESTMENT IN INDONESIA: IS IT TRUE?

SUNSET OF OIL AND GAS INVESTMENT IN INDONESIA: IS IT TRUE? MINISTRY OF ENERGY AND MINERAL RESOURCES DIRECTORATE GENERAL OF OIL AND GAS SUNSET OF OIL AND GAS INVESTMENT IN INDONESIA: IS IT TRUE? By Dr. Naryanto Wagimin Director of Upstream Business Development

More information

Ministry of Energy and Mineral Resources Republic of Indonesia Electricity Investment Opportunity In Indonesia Economic Development Corridors

Ministry of Energy and Mineral Resources Republic of Indonesia Electricity Investment Opportunity In Indonesia Economic Development Corridors Ministry of Energy and Mineral Resources Republic of Indonesia Electricity Investment Opportunity In Indonesia Economic Development Corridors Presented at Seminar of The for Promotion Clean Coal Technology

More information

Indonesia s Opportunity in the Development of Unconventional Gas Resources

Indonesia s Opportunity in the Development of Unconventional Gas Resources Panel Discussion 3 Tapping Indonesia s Unconventional Gas Resources Indonesia s Opportunity in the Development of Unconventional Gas Resources By: Ho Sook Wah Chairman, Coordination Committee International

More information

Indonesia s Geothermal Development: Where is it Going?

Indonesia s Geothermal Development: Where is it Going? PROCEEDINGS, 43rd Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, February 12-14, 2018 SGP-TR-213 Indonesia s Geothermal Development: Where is it Going? Anton S.

More information

Out line of MIGAS and overview of Gas in Indonesia

Out line of MIGAS and overview of Gas in Indonesia Out line of MIGAS and overview of Gas in Indonesia Presented on: Program Formulation Course Meeting on JCCP HRD & Technical Cooperation Program For MIGAS By: Arif Rahman Hakim Novita Mariyana Edy Wijaya

More information

Indonesia s $120 Billion Oil and Gas Opportunity

Indonesia s $120 Billion Oil and Gas Opportunity Indonesia s $120 Billion Oil and Gas Opportunity By Alex Dolya, Asheesh Sastry, Eddy Tamboto, and Fadli Rahman It s a prize within reach: between $90 billion and $120 billion of additional GDP over the

More information

Good morning ladies and gentlemen and thank your for the introduction. Trends and Opportunities in the Indonesian Oil and Gas sector

Good morning ladies and gentlemen and thank your for the introduction. Trends and Opportunities in the Indonesian Oil and Gas sector Good morning ladies and gentlemen and thank your for the introduction The title of my presentation today is: Trends and Opportunities in the Indonesian Oil and Gas sector 1 To convey my message and provide

More information

Asia s First FSRU And its Role in Pushing LNG Development in Indonesia

Asia s First FSRU And its Role in Pushing LNG Development in Indonesia Asia s First FSRU And its Role in Pushing LNG Development in Indonesia Tammy Meidharma PT Nusantara Regas 4 th LNG Supply, Transportation & Storage Indonesia, 20 May 2014, Stone Hotel, Legian, Bali Overview

More information

Investment Insights from Trends in Indonesian Gas Markets

Investment Insights from Trends in Indonesian Gas Markets Good morning Ladies and gentlemen and thank you for rising early to come and listen to what I have to say today. I trust I will make it worth your while. The title of my presentation today is: Investment

More information

RENEWABLE ENERGY AS A NATIONAL DEVELOPMENT PRIORITY

RENEWABLE ENERGY AS A NATIONAL DEVELOPMENT PRIORITY RENEWABLE ENERGY AS A NATIONAL DEVELOPMENT PRIORITY Rida Mulyana Director General of New, Renewable Energy and Energy Conservation Climate Change and REDD+ in the National Medium Term Development Plan

More information

Indonesia 2050 Pathway Calculator

Indonesia 2050 Pathway Calculator One Pagers Indonesia 2050 Pathway Calculator Cooperation of Ministry of Energy and Mineral Resources and Department of Energy & Climate Change United Kingdom http://calculator2050.esdm.go.id/pathways One

More information

DIRECTORATE GENERAL OF MINERAL AND COAL MINISTRY OF ENERGY AND MINERAL RESOURCES

DIRECTORATE GENERAL OF MINERAL AND COAL MINISTRY OF ENERGY AND MINERAL RESOURCES GOVERMENTPOLICY TO DEVELOP LOW RANK COAL Clean Coal Day 2013 International Symposium Change for Clean Coal Business & Sustainable Coal Supply Japan Coal Energy Center (JCOAL) Tokyo, on September 5 th,

More information

Opportunities and challenges of the Indonesian electrification drive. March 2015

Opportunities and challenges of the Indonesian electrification drive. March 2015 Opportunities and challenges of the Indonesian electrification drive March 2015 Indonesia s new cabinet has announced a new 35GW power plan to meet rising energy needs Opportunity to participate in one

More information

NATURAL GAS AND NITROGEN FERTILIZER PRODUCTION IN INDONESIA CURRENT SITUATION AND PROSPECT

NATURAL GAS AND NITROGEN FERTILIZER PRODUCTION IN INDONESIA CURRENT SITUATION AND PROSPECT NATURAL GAS AND NITROGEN FERTILIZER PRODUCTION IN INDONESIA CURRENT SITUATION AND PROSPECT Sutarto BUDIDARMO PT Pusri Holding, Indonesia PUSRI - PT Pusri Holding Pusri Building 6th Fl., Jl Taman Anggrek,

More information

Indonesia Energy Profile: Reorienting Away From Exports To Serve Domestic Consumption Analysis

Indonesia Energy Profile: Reorienting Away From Exports To Serve Domestic Consumption Analysis Indonesia Energy Profile: Reorienting Away From Exports To Serve Domestic Consumption Analysis By: EIA January 10, 2013 Indonesia is the most populous country in Southeast Asia and the fourth most populous

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Sustainable and Inclusive Energy Program (Subprogram 2) (RRP INO 49043-002) SECTOR ASSESSMENT (SUMMARY): ENERGY 1. Sector Performance, Problems, and Opportunities 1. Indonesia is striving hard to increase

More information

20% 5-6% 11% SWEDEN MANUFACTURING TECHNOLOGIES FOR INDONESIA. 203 Bio USD

20% 5-6% 11% SWEDEN MANUFACTURING TECHNOLOGIES FOR INDONESIA. 203 Bio USD 20% (Manufacturing contribution to Indonesia s total GDP 2017) 5-6% (CAGR of manufacturing sector between 2014-2017) 7% (Manufacturing export growth 2014-2017) 11% SWEDEN MANUFACTURING TECHNOLOGIES FOR

More information

NEW AND RENEWABLE ENERGY POLICY

NEW AND RENEWABLE ENERGY POLICY DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES, INDONESIA NEW AND RENEWABLE ENERGY POLICY By: Dr. Djadjang Sukarna Secretary of Director General

More information

PGN S S BUSINESS PRESENTATION 2005 RESULTS

PGN S S BUSINESS PRESENTATION 2005 RESULTS PGN S S BUSINESS PRESENTATION 2005 RESULTS Remarks By: Widyatmiko Bapang Corporate Secretary Mangatas Panjaitan Head of Accounting & Budget Division Jakarta April 6, 2006 Agenda I. PGN s Core Businesses

More information

NUSANTARA REPORT. Review of Regional Economic and Finance JULI 2013

NUSANTARA REPORT. Review of Regional Economic and Finance JULI 2013 JULI 2013 For further information, please contact: Bank Indonesia Department of Economic Research and Monetary Policy Monetary Policy Group Regional Economic and Inflation Division Ph. 021-3818161, 3818868

More information

Views from the Parliament

Views from the Parliament NATIONAL ENERGY POLICY Views from the Parliament BY: SATYA W. YUDHA MEMBER OF COMISSION VII, DPR RI THE VISION OF THE INDONESIA ENERGY UTILIZATION Article 33, UUD 1945 Natural resources controlled by the

More information

ISSN Ministry Of Energy and Mineral Resources Republic of Indonesia 2017 HANDBOOK OF ENERGY & ECONOMIC STATISTICS OF INDONESIA

ISSN Ministry Of Energy and Mineral Resources Republic of Indonesia 2017 HANDBOOK OF ENERGY & ECONOMIC STATISTICS OF INDONESIA ISSN 2528-3464 Ministry Of Energy and Mineral Resources Republic of Indonesia 2017 HANDBOOK OF ENERGY & ECONOMIC STATISTICS OF INDONESIA ISSN 2528-3464 Ministry Of Energy and Mineral Resources Republic

More information

Arun LNG Receiving Terminal & Arun- Belawan Gas Pipeline : Project Update

Arun LNG Receiving Terminal & Arun- Belawan Gas Pipeline : Project Update Arun LNG Receiving Terminal & Arun- Belawan Gas Pipeline : Project Update Hendra Jaya President Director PT Pertamina Gas Bali, May 20, 2014 CHOPPER : Customer Satisfaction, HSE Concern, Operation Excellent,

More information

Fiscal Support for the Efficient and Sustainable Management of Natural Resources in Indonesia: Renewable Energy and Forestry Resources

Fiscal Support for the Efficient and Sustainable Management of Natural Resources in Indonesia: Renewable Energy and Forestry Resources Fiscal Support for the Efficient and Sustainable Management of Natural Resources in Indonesia: Renewable Energy and Forestry Resources Irfa Ampri, PhD Vice Chairman of Fiscal Policy Agency for Climate

More information

Joint Crediting Mechanism Approved Methodology ID_AM013 Installation of Solar PV System

Joint Crediting Mechanism Approved Methodology ID_AM013 Installation of Solar PV System Joint Crediting Mechanism Approved Methodology ID_AM013 Installation of Solar PV System A. Title of the methodology Installation of Solar PV System, Ver. 1.0 B. Terms and definitions Terms Solar photovoltaic

More information

DEVELOPMENT OF DRAFT- NATIONAL ENERGY POLICY SECRETARIATE GENERAL OF NATIONAL ENERGY BOARD

DEVELOPMENT OF DRAFT- NATIONAL ENERGY POLICY SECRETARIATE GENERAL OF NATIONAL ENERGY BOARD DEVELOPMENT OF DRAFT- NATIONAL ENERGY POLICY SECRETARIATE GENERAL OF NATIONAL ENERGY BOARD Jakarta, 3 rd December 2012 0 CONTENT OF EXPLANATION 1. JOBS OF THE NATIONAL ENERGY BOARD 2. MECHANISM FOR SPECIFICATION

More information

Investment ng Opportunities. EMR Sector

Investment ng Opportunities. EMR Sector ng Opportunities EMR Sector Ministry of Energy and Mineral Resources 2011 Opportunities EMR Sector This material is not be reproduced without the permission of Ministry of Energy and Mineral Resources

More information

Shale Gas Energy Alternative towards a Rapid Growth of Coal Energy Demand An Analysis and Proposed Energy Diversification Model

Shale Gas Energy Alternative towards a Rapid Growth of Coal Energy Demand An Analysis and Proposed Energy Diversification Model Shale Gas Energy Alternative towards a Rapid Growth of Coal Energy Demand An Analysis and Proposed Energy Diversification Model Winarko. Bambang, Mahadewi. Lufina Faculty of Management, Sampoerna School

More information

By: Dr. Dadan Kusdiana Director for Bioenergy

By: Dr. Dadan Kusdiana Director for Bioenergy DIRECTORATE OF NEW, RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA By: Dr. Dadan Kusdiana Director for Bioenergy Forum on Biomass Industry in Indonesia:

More information

DECADES Tool to Make Comparative Assessment of Electricity Generation in Indonesia 1

DECADES Tool to Make Comparative Assessment of Electricity Generation in Indonesia 1 DECADES Tool to Make Comparative Assessment of Electricity Generation in Indonesia 1 Abubakar Lubis Agus Sugiyono Agency for the Assessment and Application of Technology (BPPT) Indonesia 1. Introduction

More information

Perusahaan Gas Negara Presentation to the investors. October 2010 update

Perusahaan Gas Negara Presentation to the investors. October 2010 update Perusahaan Gas Negara Presentation to the investors October 2010 update Disclaimer: The information contained in our presentation is intended solely for your personal reference. In addition, such information

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK R95-01 28 June 2001 TECHNICAL ASSISTANCE TO INDONESIA FOR PREPARING A GAS SECTOR DEVELOPMENT PLAN (FINANCED FROM THE JAPAN SPECIAL FUND) The attached Report is circulated for the

More information

Dr. Hasrul Laksmana Azahari

Dr. Hasrul Laksmana Azahari DIRECTORATE GENERAL NEW RENEWABLE ENERGY AND ENERGY CONSERVATION MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA By: Dr. Hasrul Laksmana Azahari Director of Various New Energy and Renewable

More information

Gas Infrastructure Development:

Gas Infrastructure Development: Gas Infrastructure Development: Mr. Pitak Janyapong Executive Vice President, Strategic Planning Department Gas Business Unit, PTT Public Company Limited January 29, 2015 agenda I. ASEAN GAS OUTLOOK II.

More information

TOWARDS GLOBAL RECOGNITION BUSINESS PROFILE

TOWARDS GLOBAL RECOGNITION BUSINESS PROFILE TOWARDS GLOBAL RECOGNITION BUSINESS PROFILE INTRODUCTION As Indonesia s flagship national company that is engaged in a broad spectrum of upstream and downstream energy operations, Pertamina has increased

More information

THE IMPACT OF THE NEW LAW OF REPUBLIC OF INDONESIA NUMBER 20 OF 2002 TO THE ENERGY PLANNING IN INDONESIA

THE IMPACT OF THE NEW LAW OF REPUBLIC OF INDONESIA NUMBER 20 OF 2002 TO THE ENERGY PLANNING IN INDONESIA THE IMPACT OF THE NEW LAW OF REPUBLIC OF INDONESIA NUMBER 20 OF 2002 TO THE ENERGY PLANNING IN INDONESIA By : Susy M. Simarangkir Jln. Daksinapati Barat I/3, Rawamangun, Jakarta 13220, Indonesia sms_sierra@hotmail.com

More information

Progressing CBM Development in Indonesia - An Industry Perspective -

Progressing CBM Development in Indonesia - An Industry Perspective - Progressing CBM Development in Indonesia - An Industry Perspective - Mohd. Radzif Mohamad VICO CBM Commercial Manager IndoGAS Conference 27 th 29 th January 2015 1 VICO Overview VICO is a 50:50 JV between

More information

SECTOR OVERVIEW. Government of Indonesia, State Electricity Corporation (PLN). Electricity Power Supply Business Plan (RUPTL ). Jakarta.

SECTOR OVERVIEW. Government of Indonesia, State Electricity Corporation (PLN). Electricity Power Supply Business Plan (RUPTL ). Jakarta. Eastern Indonesia Renewable Energy Project (Phase 1) (RRP INO 51209) SECTOR OVERVIEW A. Sector Performance 1. Indonesia is the largest economy in Southeast Asia, with an estimated gross domestic product

More information

Indonesia s Generation Fuel Mix in an Era of Price Uncertainty Tom Parkinson 14 April 2015

Indonesia s Generation Fuel Mix in an Era of Price Uncertainty Tom Parkinson 14 April 2015 Indonesia s Generation Fuel Mix in an Era of Price Uncertainty Tom Parkinson 14 April 215 Who we are Helping Our Clients Create Value Market analysis and insights Asset valuation / M&A Policy / regulation

More information

The Importance of Infrastructure in Expanding Gas Demand. - Nanang Untung -

The Importance of Infrastructure in Expanding Gas Demand. - Nanang Untung - The Importance of Infrastructure in Expanding Gas Demand - Nanang Untung - LNG Malaysia Forum 2013 Kuala Lumpur, March 21 st, 2013 DISCLAIMER The presentation is made solely for the purpose of this event

More information

TECHNICAL ASSISTANCE RELATED TO THE SUSTAINABLE AND INCLUSIVE ENERGY PROGRAM, SUBPROGRAM 2

TECHNICAL ASSISTANCE RELATED TO THE SUSTAINABLE AND INCLUSIVE ENERGY PROGRAM, SUBPROGRAM 2 Sustainable and Inclusive Energy Program (Subprogram 2) (RRP INO 49043-002) TECHNICAL ASSISTANCE RELATED TO THE SUSTAINABLE AND INCLUSIVE ENERGY PROGRAM, SUBPROGRAM 2 Pillar 1: Fiscal sustainability and

More information

Perusahaan Gas Negara. June 2010 update

Perusahaan Gas Negara. June 2010 update Perusahaan Gas Negara Presentation to the investors June 2010 update Disclaimer: The information contained in our presentation is intended solely for your personal reference. In addition, such information

More information

Perusahaan Gas Negara Presentation to the investors. April 2011 update

Perusahaan Gas Negara Presentation to the investors. April 2011 update Perusahaan Gas Negara Presentation to the investors April 2011 update Disclaimer: The information contained in our presentation is intended solely for your personal reference. In addition, such information

More information

Energy and Mineral Resources for the People s Welfare

Energy and Mineral Resources for the People s Welfare REPUBLIK INDONESIA The 11 th international Conference on Mining, Materials and Petroleum Engineering 11-13 November 2013, Centara Duangtawan Hotel, Chiang Mai, THAILAND MINISTRY OF ENERGY AND MINERAL RESOURCES

More information

EXPANDING OPPORTUNITIES GEOTHERMAL DEVELOPMENT IN INDONESIA. ABADI POERNOMO PRIJANDARU EFFENDI Indonesian Geothermal Association

EXPANDING OPPORTUNITIES GEOTHERMAL DEVELOPMENT IN INDONESIA. ABADI POERNOMO PRIJANDARU EFFENDI Indonesian Geothermal Association EXPANDING OPPORTUNITIES GEOTHERMAL DEVELOPMENT IN INDONESIA ABADI POERNOMO PRIJANDARU EFFENDI Indonesian Geothermal Association GRC ANNUAL MEETING 2017 Salt Lake City, 1-4 October 2017 CURRENT ENERGY CONDITION

More information

Presentation of. Clean Energy Asia 2013: Renewable Energy Policies in Indonesia A Report Card. Mini hydro power plants

Presentation of. Clean Energy Asia 2013: Renewable Energy Policies in Indonesia A Report Card. Mini hydro power plants Presentation of Mini hydro power plants Answering Indonesia s power crisis with renewable energy solutions Micro hydro power systems Clean Energy Asia 2013: Renewable Energy Policies in Indonesia A Report

More information

Chapter 7. Indonesia Country Report. September 2016

Chapter 7. Indonesia Country Report. September 2016 Chapter 7 Indonesia Country Report September 2016 This chapter should be cited as Malik, C. (2016), Indonesia Country Report in Kimura, S. and P. Han (eds.) in Energy Outlook and Energy Saving Potential

More information

" %&$, # " $, " " $ %#)$ % 2 3 BANGKOK, DEC

 %&$, #  $,   $ %#)$ % 2 3 BANGKOK, DEC BANGKOK, DEC 2016 OUTLINE ENERGY DATA COLLECTION CLUSTERING NEW AND RENEWABLE ENERGY, ENERGY CONSERVATION Liquified Coal Coal Bed Methane Gasified Coal Nuclear Hidrogen Geothermal Hydro Bioenergy Solar

More information

BP REDD+ REDD+ Management Agency: Operational Strategy

BP REDD+ REDD+ Management Agency: Operational Strategy BP REDD+ REDD+ Management Agency: Operational Strategy 2014-2015 Agus P. Sari Deputy Chair on Planning and Funding REDD+ Management Agency Keeping our forests standing and peatlands intact is important

More information

REGULATION OF GOVERNMENT OF THE REPUBLIC OF INDONESIA NO. 36/2004 ON OIL AND GAS DOWNSTREAM BUSINESS

REGULATION OF GOVERNMENT OF THE REPUBLIC OF INDONESIA NO. 36/2004 ON OIL AND GAS DOWNSTREAM BUSINESS REGULATION OF GOVERNMENT OF THE REPUBLIC OF INDONESIA NO. 36/2004 ON OIL AND GAS DOWNSTREAM BUSINESS PRESIDENT OF THE REPUBLIC OF INDONESIA, Considering: that, to enforce the provisions of Articles 8 paragraph

More information

GOVERNMENT REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 79 OF 2014 ON NATIONAL ENERGY POLICY THE PRESIDENT OF THE REPUBLIC OF INDONESIA,

GOVERNMENT REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 79 OF 2014 ON NATIONAL ENERGY POLICY THE PRESIDENT OF THE REPUBLIC OF INDONESIA, GOVERNMENT REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 79 OF 2014 ON NATIONAL ENERGY POLICY THE PRESIDENT OF THE REPUBLIC OF INDONESIA, Considering : a. that to implement the provision of Article 11

More information

POLICY ON SOLAR AND BIOENERGY DEVELOPMENT IN INDONESIA

POLICY ON SOLAR AND BIOENERGY DEVELOPMENT IN INDONESIA MINISTRY OF ENERGY AND MINERAL RESOURCES DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY, AND ENERGY CONSERVATION POLICY ON SOLAR AND BIOENERGY DEVELOPMENT IN INDONESIA Andriah Feby Misna Director of Bioenergy

More information

THE ROLE OF GEOTHERMAL ENERGY

THE ROLE OF GEOTHERMAL ENERGY Radja THE ROLE OF GEOTHERMAL ENERGY IN THE CONTEXT OF THE FUTURE ELECTRIC POWER SUPPLY IN INDONESIA Vincent T. Radja State Electricity Carporstion Key words: geothermal power, Indonesia JL. M 12043 Indonesia

More information

SONATRACH ALGERIA SONATRACH. Vision & Perspectives. ALGERIA - Energy Day 04th May, 2016 HOUSTON - TEXAS - USA

SONATRACH ALGERIA SONATRACH. Vision & Perspectives. ALGERIA - Energy Day 04th May, 2016 HOUSTON - TEXAS - USA SONATRACH ALGERIA SONATRACH Vision & Perspectives ALGERIA - Energy Day 04th May, 2016 HOUSTON - TEXAS - USA Sonatrach Corporate Profile : 2015 key figures E&P Midstream Downstream Marketing Discoveries

More information

The Extended Gateway of Tanjung Priok Eastern Ports Workshop. Presented By: David Wignall David Wignall Associates August 2015

The Extended Gateway of Tanjung Priok Eastern Ports Workshop. Presented By: David Wignall David Wignall Associates August 2015 The Extended Gateway of Tanjung Priok Eastern Ports Workshop Presented By: David Wignall David Wignall Associates August 2015 Tanjung Priok, Indonesia s major container port Throughput (Teus) Tanjung Priok

More information

SYNOPSIS OF THE 2017 NATIONAL GAS POLICY

SYNOPSIS OF THE 2017 NATIONAL GAS POLICY SYNOPSIS OF THE 2017 NATIONAL GAS POLICY Introduction On Wednesday, June 28, 2017, the Federal Executive Council (FEC) at its monthly meeting approved the National Gas Policy, 2017 ( NGP ). The NGP, which

More information

DSLNG Project Update. Andy Karamoy PT Donggi Senoro LNG. 4 th LNG Supply, Transport and Storage Indonesia May 2014 Bali, Indonesia

DSLNG Project Update. Andy Karamoy PT Donggi Senoro LNG. 4 th LNG Supply, Transport and Storage Indonesia May 2014 Bali, Indonesia DSLNG Project Update Andy Karamoy PT Donggi Senoro LNG 4 th LNG Supply, Transport and Storage Indonesia 19-21 May 2014 Bali, Indonesia Table of Contents 1. Introduction of Donggi Senoro LNG Project 2.

More information

WATER SUPPLY OF JAKARTA

WATER SUPPLY OF JAKARTA WATER SUPPLY OF JAKARTA Prof.Dr. Djoko M. Hartono Environmental Engineering Study Program. Civil Engineering Department, Faculty of Engineering University of Indonesia SMART ENGINEERING TOKYO 2018 UNITED

More information

Regulation and Development of New and Renewable Energy in Indonesia

Regulation and Development of New and Renewable Energy in Indonesia Ministry of Energy and Mineral Resources Republic of Indonesia Regulation and Development of New and Renewable Energy in Indonesia Japan-Indonesia Business Forum for Energy Efficiency, Conservation and

More information

ENERGIZING THE ECONOMY

ENERGIZING THE ECONOMY Terwatt-hours Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ENERGIZING THE ECONOMY Strategic Priorities for the POWER Sector in Indonesia

More information

Cleaner energy and shipping in Indonesia Small scale LNG. By: Jan Valkier

Cleaner energy and shipping in Indonesia Small scale LNG. By: Jan Valkier Cleaner energy and shipping in Indonesia Small scale LNG By: Jan Valkier Jakarta - Mareforum 2012 March 28, 2012 Outline Introduction Anthony Veder Group Fleet LNG focus Our experience in small scale LNG

More information

2017 HANDBOOK OF ENERGY & ECONOMIC STATISTICS

2017 HANDBOOK OF ENERGY & ECONOMIC STATISTICS ISSN 2528-3464 Ministry Of Energy and Mineral Resources Republic of Indonesia 2017 HANDBOOK OF ENERGY & ECONOMIC STATISTICS FINAL EDITION OF INDONESIA ISSN 2528-3464 Ministry Of Energy and Mineral Resources

More information

6th Annual LNG Transport Handling & Storage 2016 Forum. FSRU as The Pivotal Point for Effective LNG Distribution

6th Annual LNG Transport Handling & Storage 2016 Forum. FSRU as The Pivotal Point for Effective LNG Distribution 6th Annual LNG Transport Handling & Storage 2016 Forum FSRU as The Pivotal Point for Effective LNG Distribution Bali, 15 th September 2016 PGN LNG Business at FSRU Lampung Maximum capacity of sales gas:

More information

INDONESIAN MINING POLICY UPDATE

INDONESIAN MINING POLICY UPDATE INDONESIAN MINING POLICY UPDATE bauma FORUM bauma 2013 30th International Trade Fair for Construction Machinery, Building Material Machines, Mining Machines, Construction Vehicles and Construction Equipment

More information

PRIVATE SECTOR PLAYERS: LOGISTICS SOLUTIONS FOR EFFICIENT SUPPLY CHAIN MANAGEMENT IN INDONESIA

PRIVATE SECTOR PLAYERS: LOGISTICS SOLUTIONS FOR EFFICIENT SUPPLY CHAIN MANAGEMENT IN INDONESIA PRIVATE SECTOR PLAYERS: LOGISTICS SOLUTIONS FOR EFFICIENT SUPPLY CHAIN MANAGEMENT IN INDONESIA By Jeffrey Bahar Deputy Chief Executive Officer Spire Research and Consulting Topic 1 Market and Performance

More information

PROSPECTIVE BUSINESS COOPERATION IN INDONESIA S RENEWABLE ENERGY

PROSPECTIVE BUSINESS COOPERATION IN INDONESIA S RENEWABLE ENERGY PROSPECTIVE BUSINESS COOPERATION IN INDONESIA S RENEWABLE ENERGY Workshop Remarkable Indonesia ASPAC Forum Bavaria, Germany Dr.-Ing. Ilham A. Habibie, MBA Indonesia Head of Chamber of Commerce, Germany,

More information

FINDINGS, SUGGESTIONS AND CONCLUSION

FINDINGS, SUGGESTIONS AND CONCLUSION CHAPTER-VIII FINDINGS, SUGGESTIONS AND CONCLUSION.. 8.1 Major Findings of the Research This study has analyzed the economic aspects of petroleum during the pre-reform (1970-1990) and reform (1990-2010)

More information

Decreasing trends in annual rainfalls over Indonesia: A threat for the national water resource?

Decreasing trends in annual rainfalls over Indonesia: A threat for the national water resource? Decreasing trends in annual rainfalls over Indonesia: A threat for the national water resource? Edvin Aldrian 1 Agency for the Assessment and Application of Technology, Abstract This study diagnoses and

More information

Energy Procedia 4 (2011) Energy Procedia 00 (2010) GHGT-10. Status of CCS Development in Indonesia

Energy Procedia 4 (2011) Energy Procedia 00 (2010) GHGT-10. Status of CCS Development in Indonesia Energy Procedia 4 (2011) 6152 6156 Energy Procedia 00 (2010) 000 000 Energy Procedia www.elsevier.com/locate/procedia www.elsevier.com/locate/xxx GHGT-10 Status of CCS Development in Indonesia Dennis Best

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PHI 30546 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE REPUBLIC OF THE PHILIPPINES FOR INSTITUTIONAL STRENGTHENING FOR THE DEVELOPMENT OF THE NATURAL GAS

More information

COMPANY PROFILE. The Path Toward Sustainable Energy

COMPANY PROFILE. The Path Toward Sustainable Energy COMPANY PROFILE PT VENTURINDO ENGINEERING Jl. By Pass Jomin No.46 Cikampek, Karawang, West Java Telp : 0264 8385523 Fax. 0264 8385523 Mobile : 0811129423, 0811142243 Email : Didik.haryadi@venturindo.id

More information

Brunei Darussalam Country Report

Brunei Darussalam Country Report Chapter 3 Brunei Darussalam Country Report September 2016 This chapter should be cited as Energy and Industry Department of Prime Minister s office (2016), Brunei Darussalam Country Report, in Kimura,

More information

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati Introduction Indonesian power sector is one of the business sectors in Indonesia which is strictly regulated. For the

More information

Malaysia s oil and gas reserves

Malaysia s oil and gas reserves The Gas Era Malaysia s oil and gas reserves Billion Barrels 7 6 5 4 3 3.3 4.1 Oil Reserves 4.5 5.2 5.8 5.8 Trillion Standard cubic feet 120 100 80 60 52 Gas Reserves 85 84 85 89 98 2 1 0.9 40 20 18 0 1975

More information

17 May Shale Gas Cost And Technology Perspective. Kolkata

17 May Shale Gas Cost And Technology Perspective. Kolkata 17 May 2013 Shale Gas Cost And Technology Perspective Kolkata Supply / Demand Dynamics For Indian Gas AN ATTRACTIVE MARKET FOR YEARS TO COME Current gas supply by source Existing PVT / JV, 37% Existing

More information

REGULATION OF THE MINISTER OF ENERGY AND MINERAL RESOURCES NUMBER 19 OF 2009 ON NATURAL GAS BY PIPELINE BUSINESS ACTIVITIES

REGULATION OF THE MINISTER OF ENERGY AND MINERAL RESOURCES NUMBER 19 OF 2009 ON NATURAL GAS BY PIPELINE BUSINESS ACTIVITIES REGULATION OF THE MINISTER OF ENERGY AND MINERAL RESOURCES NUMBER 19 OF 2009 ON NATURAL GAS BY PIPELINE BUSINESS ACTIVITIES WITH THE BLESSINGS OF ALMIGHTY GOD THE MINISTER OF ENERGY AND MINERAL RESOURCES

More information

Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities

Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities Dendy Kurniawan Finance Director PT Geo Dipa Energi April 2013 1 Geo Dipa Energi (GDE) PT GEO DIPA ENERGI Est. 5 July 2002

More information

Coal Dynamics in Indonesia

Coal Dynamics in Indonesia Coal Dynamics in Indonesia Towards a just energy transition Image source: economy.okezone.com Fabby Tumiwa Cape Town, 27 February 2019 1 National Energy Policy National Energy Policy Coal in Primary Energy

More information

INDONESIA. Energy and Sustainable Development in Indonesia. A report

INDONESIA. Energy and Sustainable Development in Indonesia. A report INDONESIA Sustainable Energy Watch 2002 Report Energy and Sustainable Development in Indonesia A report by Kuki Soejachmoen kuki @ pelangi.or.id Most indicators show that Indonesia moved towards an un-sustainable

More information

REPUBLIC OF KENYA MINISTRY OF ENERGY AND PETROLEUM KENYA PETROLEUM TECHNICAL ASSISTANCE PROJECT (KEPTAP) PROJECT MANAGEMENT UNIT (PMU)

REPUBLIC OF KENYA MINISTRY OF ENERGY AND PETROLEUM KENYA PETROLEUM TECHNICAL ASSISTANCE PROJECT (KEPTAP) PROJECT MANAGEMENT UNIT (PMU) REPUBLIC OF KENYA MINISTRY OF ENERGY AND PETROLEUM KENYA PETROLEUM TECHNICAL ASSISTANCE PROJECT (KEPTAP) PROJECT MANAGEMENT UNIT (PMU) COMPONENT C SUSTAINABLE IMPACT OF OIL AND GAS INDUSTRY REFORMS AND

More information

POTENCY AND CHALLENGES OF NUCLEAR COGENERATION FOR INDONESIA EXPERIMENTAL POWER REACTOR DESIGN

POTENCY AND CHALLENGES OF NUCLEAR COGENERATION FOR INDONESIA EXPERIMENTAL POWER REACTOR DESIGN POTENCY AND CHALLENGES OF NUCLEAR COGENERATION FOR INDONESIA EXPERIMENTAL POWER REACTOR DESIGN ERLAN DEWITA NATIONAL NUCLEAR ENERGY AGENCY OF INDONESIA (BATAN) 21 23 November 2016 Background The Republic

More information

Keywords: Indonesia; Infrastructure; Provincial capitals; Rank; Transportation

Keywords: Indonesia; Infrastructure; Provincial capitals; Rank; Transportation International Journal of Technology (2016) 4: 544-552 ISSN 2086-9614 IJTech 2016 MAPPING PRIORITIES FOR THE DEVELOPMENT OF THE TRANSPORTATION INFRASTRUCTURE IN THE PROVINCIAL CAPITALS OF INDONESIA Yusuf

More information

Waste to Energy Status in Indonesia

Waste to Energy Status in Indonesia L/O/G/O Waste to Energy Status in Indonesia Fadjar Goembira Andalas University, INDONESIA 1 Where is Indonesia? the archipelago Around 260 million people Highest peak 4,884m above sea level Around 17,000

More information

Ministry of Village, Development of Disadvantaged Region, and Transmigration SEIZING THE OPPORTUNITY OF EQUITABLE DEVELOPMENT THROUGH VILLAGES

Ministry of Village, Development of Disadvantaged Region, and Transmigration SEIZING THE OPPORTUNITY OF EQUITABLE DEVELOPMENT THROUGH VILLAGES Ministry of Village, Development of Disadvantaged Region, and Transmigration SEIZING THE OPPORTUNITY OF EQUITABLE DEVELOPMENT THROUGH VILLAGES 1 1 Bring the country back to protect the entire nation and

More information

Shigeru Kimura. Tetsuo Morikawa. Han Phoumin

Shigeru Kimura. Tetsuo Morikawa. Han Phoumin Shigeru Kimura Tetsuo Morikawa Han Phoumin Economic Research Institute for ASEAN and East Asia, 2016 ERIA Research Project FY2016 No.03 Published in August 2017 All rights reserved. No part of this publication

More information

Ralf Dahrendorf Taskforce on the Future of the European Union

Ralf Dahrendorf Taskforce on the Future of the European Union Ralf Dahrendorf Taskforce on the Future of the European Union Working group IV Financial and economic crisis liberal solutions for a Europe that works A liberal perspective on energy and environmental

More information

LNG FORUM SERIES September 2018 Padma Resort, Bali, Indonesia. 8 th ANNUAL LNG TRANSPORT, HANDLING & STORAGE FORUM

LNG FORUM SERIES September 2018 Padma Resort, Bali, Indonesia. 8 th ANNUAL LNG TRANSPORT, HANDLING & STORAGE FORUM Accelerating Infrastructure and Distribution Projects along the Natural Gas and LNG Value Chain for Power Generation Conference Sponsors: Endorsed By: Organizers: Strategic Partner: Aviation & Logistics

More information

Table Electricity Purchase Tariff from Renewable Energy Plants (Government of Indonesia, 2017)

Table Electricity Purchase Tariff from Renewable Energy Plants (Government of Indonesia, 2017) 1.2. Indonesia Comprised of 17,508 islands that stretch over 5,000 kilometres, Indonesia s large and diverse population was 258 million in 2016 (BPS, 2017). Population growth in 2014 was 1.35%, but it

More information

Kardaya Warnika MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA. By: Director General of New Renewable Energy and Energy Conservation

Kardaya Warnika MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA. By: Director General of New Renewable Energy and Energy Conservation MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA By: Kardaya Warnika Director General of New Renewable Energy and Energy Conservation Presented at: The 2nd Clean Power Asia Conference and

More information

Natural Gas Outlook in India 2017

Natural Gas Outlook in India 2017 Natural Gas Outlook in India 2017 Fact March 2017 Why enincon s report upon Natural Gas Outlook in India 2017 GOVERNMENT OF INDIA AIMING TO INCREASE THE SHARE OF NATURAL GAS IN INDIA S ENERGY MIX BY MORE

More information

Developing efficient and reliable LNG infrastructure to support Indonesia s fast-growing energy demand

Developing efficient and reliable LNG infrastructure to support Indonesia s fast-growing energy demand Developing efficient and reliable LNG infrastructure to support Indonesia s fast-growing energy demand Gas Indonesia Summit Workshop Wednesday July 12, 2017 Welcome Mr. Hari Karyuliarto Chairman Risco

More information