THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS

Size: px
Start display at page:

Download "THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS"

Transcription

1 THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS ACOUSTIC ASSESSMENT PROPOSED GROUNDWATER CLEANUP PROJECT R3:NSC Prepared for: Orica Australia Beauchamp Road MATRAVILLE NSW FRED STREET, LILYFIELD, 2040, NSW, AUSTRALIA ph: (612) fx: (612) A.B.N

2 Acoustical Assessment Proposed Groundwater Cleanup Project CONTENTS Page No 1 Introduction 1 2 Noise Assessment Criteria 2 3 Construction Noise Impact GTP Additional Infrastructure Additional Extraction Wells in the PCA DNAPL Extraction Wells and DNAPL Pipeline Treated Water Pipeline Construction Traffic 9 4 GTP Noise Design Goals 10 5 Operational Noise for the BCG Project 12 6 Conclusion 13 APPENDICES A: Site Location B: Proposed Development C: Plant Items 9 th November, 2004

3 Acoustical Assessment Proposed Groundwater Cleanup Project Page 1 of 15 1 INTRODUCTION The purpose of this report is to present the results and findings of an acoustical assessment of noise emission from the proposed Botany Groundwater Cleanup (BGC) Project. It is proposed to construct and operate a groundwater treatment plant (GTP) to treat contaminated groundwater under the Botany Industrial Park and adjacent lands. The GTP site is shown in Appendix A. An Environmental Impact Statement is being prepared for the proposed construction and operation of the GTP and associated infrastructure with this acoustical report forming part of the EIS prepared by URS Australia Pty Ltd. It is proposed that the GTP will consist of a single treatment system involving groundwater feed storage, air strippers, off-gas oxidation and treatment (refer to Appendix B). Adjacent to the plant will be feed storage and treated water tanks and tanks for the temporary storage of recovered EDC. The BGC Project also includes extraction wells, piping to transfer the extracted water to the GTP and piping for the distribution of treated water and discharge of waste streams. Some aspects of this infrastructure, including the primary and secondary pipeline and extraction wells on Foreshore Road, are complete at the time of writing. The focus of this assessment is the GTP on the BIP. Consideration has also been given to the construction noise associated with the additional infrastructure which is yet to be built for the BGC Project. Operational noise impacts associated with all facets of the BGC Project have been assessed. The Director s requirements from DIPNR identify that the EIS must assess the predicted noise impact resulting from all noise sources during construction and operation, including road traffic noise. The noise assessment must be undertaken in accordance with the EPA s Industrial Noise Policy document and the Environmental Criteria for Road Traffic Noise document.

4 Acoustical Assessment Proposed Groundwater Cleanup Project Page 2 of 15 The Director s requirements nominate that in relation to construction noise, there must be consideration of the construction site noise guidelines from the EPA s Environmental Noise Control Manual and that potential impacts resulting from vibration generated during any drilling activities must be considered. The Botany Industrial Park premise operates under licenced conditions issued by the New South Wales Environment Protection Authority (now Department of Environment and Conservation). Licence conditions pertaining to noise govern the cumulative noise impact from the subject site and are part of the Botany Industrial Park Noise Reduction Program that has governed the control and reduction of noise from existing operations. 2 NOISE ASSESSMENT CRITERIA Noise is normally measured using the decibel (db) which is a logarithmic measure of a variation in air pressure (sound waves). Community noise is normally measured using an A weighted scale - noted as db(a). The A weighting is considered to approximate the frequency response of the human ear. For continuous noise emission from a subject site any increase in background (average minimum) noise levels of more than 5 db(a) is generally taken to be unacceptable. Due to the size and nature of the Botany Industrial Park, the GTP will be Scheduled under the Protection of the Environment Operations Act and falls under the jurisdiction of the NSW Department of Environment and Conservation (including the EPA).

5 Acoustical Assessment Proposed Groundwater Cleanup Project Page 3 of 15 The proposed project involves the creation of a new GTP on the Botany Industrial Park and associated pump and piping infrastructure. With respect to noise, any plant on the BIP is governed by the stringent noise emission criterion set down by the NSW EPA. The EPA noise emission limit for an L eq sound level contribution from the plant not exceeding 35 db(a) at night, results in a sound level contribution significantly less than the existing ambient background level around the perimeter of the Botany Industrial Park site. There are no specific operational noise criteria for off site infrastructure and such items are not near residential premises. Orica has chosen to require such noise to be consistent with BIP noise assessment procedures. The off site infrastructure is considered as part of the plant noise design criteria. The provision of a noise goal applicable to the subject plant which is noticeably less than both the ambient background level at residential boundaries and the amenity goal that is obtained from the INP, automatically realises full compliance with the EPA s Industrial Noise Policy document as nominated in the Director s requirements. As such standard noise assessment procedures with respect to the measurement of existing ambient sound levels is not required for this project as the design goal that has been specified by the NSW Environment Protection Authority renders the conduct of such measurements of no assistance. In addition to compliance with external noise emission limits, the Botany Industrial Site Noise Policy also identifies that the noise level in working areas not governed by speech communication or annoyance shall not exceed 85 db(a) so as to address the company s occupational noise goals. The specifications in relation to individual plant items provided for our assessment indicate that at the present time, the specification for various items is to achieve a noise level no greater than 82 db(a) at 1 metre, which in turn nominates various acoustic controls required for existing equipment.

6 Acoustical Assessment Proposed Groundwater Cleanup Project Page 4 of 15 The design of the GTP is currently in terms of a general concept and generic plant items have been determined for the purpose of this acoustic assessment. Primarily, working backwards from the permitted noise emission levels at residential boundaries results in the specification of an effective sound power level for the subject plant so as to achieve compliance with the noise goal. This sound power level in turn determines the effective noise control for individual plant items, of which the most significant noise emission sources are associated with the two air stripper blower (part of the off gas oxidation package). The EPA s Environmental Criteria for Road Traffic Noise document considers noise goals associated with various types of developments or road classifications. Access into and egress from the site is via the main (number 3) gate on Denison Street, which is not directly opposite residential premises. Denison Street is a designated heavy vehicle transport route in the subject area, particularly to Port Botany, and carries a significant volume of traffic not associated with the Botany Industrial Park site. The minimal number of truck movements associated with the subject plant result in an insignificant increase in terms of the existing road traffic noise levels and as a consequence would readily satisfy the EPA recommended criteria set out in their ECRTN document. The construction noise criteria set out in the Environmental Noise Control Manual (Chapter 171) nominates a series of noise goals at residential receivers dependent upon the period of construction. For a construction period of 4 weeks and under, the target is for an L 10 level measured over a period of not less than 15 minutes when the construction site is in operation and must not exceed the background level by more than 20 db(a). Where the construction period of greater than 4 weeks and not exceeding 26 weeks, the noise target becomes background +10 db(a). Where the construction period is greater than 26 weeks, there is no specification in the guidelines and it is assumed that the normal concept of background +5 db(a) would apply.

7 Acoustical Assessment Proposed Groundwater Cleanup Project Page 5 of 15 The off site infrastructure occurs in different areas for a short period of time and could be considered in terms of the background + 20 db(a) goal. However, considering such works as part of the overall construction of the project would see the use of the background + 5 db(a) target. The EPA has indicated in their Noise Guide for Local Government that the Construction Noise Guideline is under review. Whilst the noise control guideline is specified in terms of an L 10 (average maximum) descriptor, the EPA some 5 years ago (with the introduction of the INP and ECRTN) altered their acoustic design goals to be assessed in terms of an L eq level and it is envisaged that any condition pertaining to construction would be addressed in terms of an L eq requirement. 3 CONSTRUCTION NOISE IMPACT 3.1 GTP Activities associated with the construction phases are described in detail in the EIS. The construction techniques are relatively conventional and follow the following logical steps: Earthworks The site is currently used for parking tanker trailers and trucks. This area is raised and sealed with a two layer coat bitumen coating (2 coat seal). At this stage it is expected that new site area will reduce the existing parking area by approximately one metre and create a one level platform for most of the facilities required for the GTP. Site Drainage - Site drainage lines will be laid to carry stormwater via a first flush system into the established site storm water system. Concrete Work - the concrete work identified to date for the site are: First flush pit(s), Site drainage pits, Equipment slabs, Tank slabs and bund walls, Infill slabs (areas between equipment slabs), Roads and pathways Structural Steelwork - steelwork identified to date will be fabricated off-site for: Pipe rack, Stripper structure, Awning over part of the water processing equipment

8 Acoustical Assessment Proposed Groundwater Cleanup Project Page 6 of 15 Buildings - A control room and amenities building as well as an electrical switch room will be constructed on site to service the plant. Equipment and Plant Installation - Tank construction/erection, equipment installation, electrical, and pipe work will run concurrently. In accordance with EPA requirements construction work is normally limited to Monday to Friday 7am to 6pm, and Saturday from 7am to 1pm if required. Botany site has continuing work for existing plant maintenance and individual equipment overhauls that from previous monitoring of construction activities is found to be masked by general plant and traffic noise and clearly complied with EPA construction noise limits. The project will generally only use common sized equipment i.e. welders, small mobile cranes, forklifts etc. for general work. Loading and unloading of equipment and steel erection is likely to be carried out with a 35 to 50 tonne crane(s) with an occasional large crane brought in for heavy lifts. The nature of the construction of the plant involves regular tradespeople and general provision of buildings pipework installation of pumps, electrical cabling etc. Between 15 and 115 persons will be working on the plant over the construction period. Due to the location of the plant from the residential boundary there is a significant degree of distance attenuation which for normal construction activities would result in noise site boundary levels similar to existing day time background levels. In accordance with EPA requirements, cleaning of pipes during the short commissioning phase would be carried out during daytime only and noise levels from these activities would be less than background + 5 db(a) at residential boundaries. It is not envisaged that the proposed GTP will require piling. Therefore vibration is not an issue.

9 Acoustical Assessment Proposed Groundwater Cleanup Project Page 7 of Additional Infrastructure The following infrastructure is to be constructed for operation of the BGC project: Installation of additional extraction wells in the PCA Installation of DNAPL wells Construction of the DNAPL pipeline Cleaning and relining an existing pipeline that runs from the BIP to Bunnerong Canal and creating an outlet at this point for the discharge of excess treated water. This infrastructure was not installed at the time of writing and is likely to be constructed in advance of works on the GTP site. Construction of this additional infrastructure would occur during standard hours as discussed in section 3.1 above. Installation of the additional wells and the DNAPL pipeline are planned to occur over the period from November 2004 to May Works on the treated water pipeline are planned to occur over an approximately 4 month period from January to April A description of the construction works associated with this infrastructure is provided in the EIS Additional Extraction Wells in the PCA The key noise generating activity for installation of the PCA extraction wells would be drilling rigs. Two rigs would be used, with access to Southlands from McPherson Street. The rigs would be mounted on the back of 10 tonne trucks. Operation of these rigs would result in a maximum sound level for each rig of 84 db(a) at 4 metres.

10 Acoustical Assessment Proposed Groundwater Cleanup Project Page 8 of 15 Monitoring of drilling conducted in earlier stages of this project revealed that there will be no perceptible vibration, either adjacent to the rig or at sensitive receptors. The additional wells to be installed in the PCA are located in an industrial zone approximately 30 metres from commercial and industrial businesses on the southern side of McPherson Street and 400 metres from the nearest residential receivers off Botany Road in a south westerly direction The operation of two drilling rigs simultaneously would realise a sound level contribution less than 43 db(a) and clearly satisfy the background + 5 db(a) goal DNAPL Extraction Wells and DNAPL Pipeline The installation of the DNAPL extraction wells would involve similar activities to the PCA wells, with access via Gate No. 3 and the internal BIP road network. Construction of the DNAPL pipeline would involve minor clearing and excavation, concrete preparation, welding, fastening and other metal works, and sealing / painting. Minor equipment deliveries would be required. Other construction equipment would include cranes, excavators, welders, and forklift trucks. There are no sensitive receptors in close proximity to the DNAPL wells to be installed on the western boundary of BIP. Installation of these wells and the minor works required for the installation of the DNAPL pipeline would generate a sound level contribution less than 48 db(a) at the nearest residence in Denison Street for operations near the plant and a sound level contribution less than 42 db(a) at the nearest residence in Spring Street for activities at the northern end of line 6.

11 Acoustical Assessment Proposed Groundwater Cleanup Project Page 9 of Treated Water Pipeline The existing pipeline to be refurbished for the discharge of treated water is underground from the BIP to Bunnerong Canal. Access at a number of locations would be required for temporary works associated with the relining process. A diffuser would be installed at the discharge point in the Canal, for equal distribution of the discharge into the Canal. The access points are located in an industrial setting. The works at each access location would take approximately 2 weeks and involve the use of an excavator and a truck mounted compressor. These works would not result in construction noise being audible at residential premises. 3.3 Construction Traffic Additional traffic generated during the construction phase has been examined by URS as contained in the EIS. In comparison to existing traffic movements on the BIP Site the small number of movements associated with construction (up to 6 trucks per day) should be virtually imperceptible and have no significant impact. Traffic associated with the additional infrastructure is minimal and would only occur at particular sites outside the BIP for a short duration. Drilling rigs would enter the relevant site by truck and remain until the full number of wells had been installed (with only minor movements required as the wells were installed in progression). Construction of the DNAPL pipeline and the relining of the existing pipeline for water discharge to Bunnerong Canal would involve a minor number of work vehicles. Accordingly in terms of noise impact, vehicles associated with the construction phase should have negligible impact.

12 Acoustical Assessment Proposed Groundwater Cleanup Project Page 10 of 15 4 GTP NOISE DESIGN GOALS In accordance with the Botany Industrial Park Noise Reduction Program, the design goal for the subject GTP at residential boundaries is not greater than 35 db(a). Regular noise monitoring around the Botany Industrial Park has identified reference locations that are used for assessment purposes. Denison Street would be the nearest residential boundary to the proposed GTP with reference location 10 (just south of the intersection with Grace Campbell Crescent) considered to be the nearest residential location. At the EIS Stage the selection of equipment is not fully known and this assessment considers the effective sound power level to obtain compliance with the nominated criteria. The prevailing weather conditions at night are a still (neutral) conditions or a light NW wind. Temperature inversions are very rare at the site but may be associated with a light easterly wind or draft that would reduce noise levels along Denison Street. Working backwards from the residential boundaries would realise an effective sound power level of 98 db(a) for the GTP at reference location 10 under neutral conditions. This effective sound power level has been derived by use of the computer modelling program ENM, an average noise source height of 2.5 metres above ground level and typical ambient background level recorded at night for reference location 10. Under a light NW wind the enhancement due to the wind would require the effective sound power level to be reduced to 96 db(a) relative to reference location 9. Under a 4 m/s SW wind (towards location 14) the effective sound power required to maintain compliance with the design goal becomes 103 db(a) relative to location 14 but 97 db(a) relative to reference locations 10 and 11. The following table identifies the effective sound power level required for the proposed GTP relative to the BIP reference monitoring locations (these locations are identified in Appendix A).

13 Acoustical Assessment Proposed Groundwater Cleanup Project Page 11 of 15 Reference Effective Sound Power Level db(a) Location Neutral light NW SW (4 m/s) a Holloway Brighton From the above table it can be seen that an effective sound power level of 96 db(a) would apply for the proposed GTP with respect to the residential area south of the No 3 gate, whilst an effective design sound power level of 103 db(a) would apply to the residential area north of the intersection of Smith and Denison Streets. Based on the information provided in the above table, Orica has specified that the effective sound power level of the GTP must not exceed 96 db(a) with respect to reference location 10. A schedule of plant items is shown in Appendix C and indicates only 16 noise producing items. The majority of the plant items are small pumps that have a noise level significantly less than the occupational limit of 82 db(a) at 1 metre. From other plants one can utilise a nominal sound power of 75 db(a) per small pump/motor which would realise a cumulative sound power of 86.5 db(a). The two Air Stripper blowers in the Off Gas Oxidation Package are considered to each have a sound power level in excess of 120 db(a). Enclosing such units to achieve the occupational noise limit would require masonry construction with attenuated air inlets and outlets. Specifying an external sound power level of 90 db(a) for each of these sources would result in compliance with the overall effective design sound power levels.

14 Acoustical Assessment Proposed Groundwater Cleanup Project Page 12 of 15 The detail of specific noise control measures for the three major plant items is not available at the present point in time and would become available during the construction phase of the project. Accordingly the design phase of the project must utilise the noise emission goals derived above. This procedure for such plants has been applied for other plants on the BIP site. Typically before operation of the plant is permitted by the EPA (DEC) a detailed acoustic assessment is provided setting out all noise emission sources, noise data and specific controls incorporated into the development to achieve compliance with the EIS noise targets. Testing during installation and commissioning phase is standard practice on the BIP site with any non-compliance required to be rectified before the plant can be placed into operation. 5 OPERATIONAL NOISE FOR THE BGC PROJECT Operation of the pumps in the wells in the median strip of Foreshore Rd, southlands and along the western boundary of the BIP, the primary and secondary pipelines, the treated water discharge line to Bunnerong Canal and pipes throughout the BIP for pumping treated water are not expected to result in audible noise at any residential receivers. The untreated water is pumped from the bottom of each well by a submersible pump into the main delivery line to the plant. Each pump has sufficient capacity to pump the water from its own well back to the plant. There are no additional pumps in the untreated water supply line until on the plant. There are no wells in proximity to residential premises. The delivery line is fully sealed and is anticipated to generate a sound level contribution at the top of each well less than 45 db(a) at 1 metre, resulting in a sound level contribution significantly less than night time ambient background levels.

15 Acoustical Assessment Proposed Groundwater Cleanup Project Page 13 of 15 The treated water discharge line is supplied by the treated water distribution pump located on the plant. The line is to be buried and pass through the industrial area to Bunnerong Canal. No appreciable noise impact will arise from the treated water discharge line. 6 CONCLUSION An acoustical assessment of the proposed GTP Plant to be located on the former Silicates site at the BIP has been carried out in accordance with the requirements of the BIP Site Noise Reduction Program. The allowable noise emission for the new plant has been set at a Leq level of 35 db(a) at any residential boundary as directed by the overall site policy and EPA criteria. The design of the plant is at a preliminary stage using generic equipment with no specific noise emission levels available. From the design criteria at the residential boundary the effective sound power level of the plant has been derived by use of the ENM program. Such a sound power level is achievable but will required noise control measures to the three main plant items. Noise associated with the operation of the off site infrastructure will result in sound level contributions at residential properties significantly below the night time ambient background levels. As the design goal for the GTP is significantly less than the ambient background level (both day and night) any compliance testing, which would be a normal condition of approval from the EPA, would require near-field measurements with calculations to determine the resultant sound level contribution at residential boundaries. In accordance with the BIP site noise policy and EPA requirements it will be necessary for the contractor to provide evidence to the EPA that noise emission requirements have been satisfied and meet the targets set out in this assessment.

16 Acoustical Assessment Proposed Groundwater Cleanup Project Page 14 of 15 The location of the proposed plant is well away from the BIP site boundaries and as construction activities are limited to daytime only, construction noise is not envisaged to create an acoustical impact. The Director General s requirements nominated consideration of vibration during construction piling operations. Whilst not anticipated to be required, any piles are to be installed by rotary drilling and not hammer piling. As such, there is not expected to be any vibration impact at residential boundaries during such operations. Construction of the additional infrastructure off the BIP site is not in proximity to residential premises and will only occur during the daytime period there is not envisaged to be any acoustical impact of such construction works for residential receptors. Traffic arising from the construction and operational phase of the project have been addressed by the traffic engineers and result in a negligible traffic increase on Denison Street such that there would be no perceptible increase in existing road traffic noise at residential properties near the BIP site. An acoustical assessment of the proposed Botany Groundwater Cleanup Project has been undertaken in accordance with the BIP Noise Reduction Program. The GTP and off site infrastructure will achieve noise emission levels in accordance with the EPA noise limits specified for new plants on the BIP. Noise from construction activities on and off the BIP site will comply with the EPA Construction Noise Guideline criteria at all residential receivers.

17 Acoustical Assessment Proposed Groundwater Cleanup Project Appendix A APPENDIX A: Site Location Holloway 15 14a Brighton Proposed Plant 9 8

18 Acoustical Assessment Proposed Groundwater Cleanup Project Appendix B APPENDIX B: Proposed Ground Water Treatment Plant

19

20 Acoustical Assessment Proposed Groundwater Cleanup Project Appendix C APPENDIX C: Equipment List and Noise Levels EQUIP. NO. EQUIPMENT NAME TYPE NOISE LEVEL Pressure Vessels V3680 Backlog EDC Isotainer Modified ISO Tank Container Type IM01 No Noise V-4101 Feed Tank Vent Absorber Activated Carbon Absorber No Noise Tanks T4101 Feed Tank Cone roof / bottom cone up /API 650 No Noise T9110 Treated Water Tank Flat roof / AWWA D103 No Noise T3650 Hydorchloric Acid Tank Cone roof / sloping bottom / sump/ BS4994 No Noise T3651 Hydrochloric Acid Lute Pot Rectangular sump tank c/w grating. No Noise T6125 Caustic Day Tank Cone roof / sloping bottom/ BS4994 No Noise S5101A/B - S5120A/B Towers/Columns Air Stripper - (x40) Low profile trayed boxes, 6 trays No Noise Pumps P4101 Air Stripper Feed Pump Centrifugal / single seal /ANSI B73.1 < 80dB (A) at 1 m P5101 Stripped Water Pump Centrifugal / single seal /ANSI B73.1 < 80dB (A) at 1 m P9110 Treated Water Pump Centrifugal / single seal /ANSI B73.1 < 82dB (A) at 1 m P4102 Hydrochloric Acid Dosing Pump Metering Pump c/w pressure valve (PVC), < 80dB (A) at 1 m diaphragm pressure relief valve (PVC) and pulsation dampener (PVC / Viton). VSD controller 'by others'. P3680 Backlog EDC Dosing Pump API.675 Metering Pump c/w Ex D fixed speed < 80dB (A) at 1 m motor, pressure valve (316SS), diaphragm pressure relief valve (316SS) and pulsation dampener (316SS / Viton). P3701 Common 1 First Flush Sump Cent/Cantilever/single seal /ANSI B73.1 < 80dB (A) at 1 m Pump P3650 Common Hydrochloric Acid Magdrive Centrifugal Pump / ANSI B73.1 < 80dB (A) at 1 m Pump P3702 HCl Tank Sump Pump Air Diaphragm Pump < 80dB (A) at 1 m P3703 Feed Tank Sump Pump Air Diaphragm Pump < 80dB (A) at 1 m P7120 Stripped Water Treatment Sump Pump Air Diaphragm Pump P6125A/B Caustic Dosing Pump (x2) Pumps skid mounted. Includes one (1) standby pump. Z6101 Off Gas Oxidation Package Off Gas Oxidation - Vendor Package including two (2) Air Stripper Blowers (C5101A/B) Z7101 Stripped Water Treatment Stripped Water Treatment - Vendor Package Package Miscellaneous Equipment < 80dB (A) at 1 m < 80dB (A) at 1 m <90 db(a) sound power level < 80dB (A) at 1 m EDC Tank Container Trailer Tri Drop Deck Trailer No Noise F5111 Auxillary Air Filter Box type air filter No Noise Plant Air Compressor Package Skid mounted screw type air compressor with air receiver package < 80dB (A) at 1 m

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment.

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment. 8. NOISE AND VIBRATION 8.1 Introduction This report has been prepared by AWN to form part of an EIAR for the proposed residential development at Wonderful Barn, Barnhall, Leixlip. The chapter assesses

More information

THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS

THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS ACOUSTICAL ASSESSMENT PROPOSED ETHANOL UPGRADE SHOALHAVEN STARCHES, BOMBADERRY 38.3849.R52:ZJM Prepared for: PO Box 738 NOWRA NSW

More information

8. Appendix F Acoustic Assessment

8. Appendix F Acoustic Assessment 8. Appendix F Acoustic Assessment HFT Ltd 06-Jun-2017 Assessment of Noise Effects Mixed Industrial Development at 28 Inlet Road, Takanini Mixed Industrial Development at 28 Inlet Road, Takanini Client:

More information

Noise. Summary of key outcomes: CHAPTER 22

Noise. Summary of key outcomes: CHAPTER 22 Noise CHAPTER 22 Summary of key outcomes: Construction activities would typically be undertaken during the day time, however some activities, particularly dredging, would also be undertaken at night. Construction

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

Acoustic Consulting Australia PtyLtd. I Consultants on Noise and Vibration P0 Box 332

Acoustic Consulting Australia PtyLtd. I Consultants on Noise and Vibration P0 Box 332 Pg 'P. Acoustic Consulting Australia PtyLtd. I Consultants on Noise and Vibration P0 Box 332 Heidelberg i#i..wr. David, u.,0 Victoria 3054 Phone 0412 375 234 Email: acausteblgpond.corn ABN 49 095 932 092

More information

Southlands Remediation and Development Project

Southlands Remediation and Development Project Southlands Remediation and Development Project Environmental Assessment Project Application (MP 06_0191) Appendix M: Noise Assessment August 2009 REPORT 30-1596R1 Southlands Remediation & Redevelopment

More information

WAIKATO POWER PLANT SH31, KAWHIA ROAD OTOROHANGA ASSESSMENT OF NOISE EFFECTS

WAIKATO POWER PLANT SH31, KAWHIA ROAD OTOROHANGA ASSESSMENT OF NOISE EFFECTS 1/355 Manukau Road Epsom, Auckland 1023 PO Box 26283 Epsom, Auckland 1344 T: 09 638 8414 E: hegley@acoustics.co.nz WAIKATO POWER PLANT SH31, KAWHIA ROAD OTOROHANGA ASSESSMENT OF NOISE EFFECTS Report No

More information

BOTANY BAY CABLE PROJECT

BOTANY BAY CABLE PROJECT BOTANY BAY CABLE PROJECT CONSTRUCTION & OPERATIONAL NOISE ASSESSMENT REPORT NO. 06096 VERSION A BOTANY BAY CABLE PROJECT CONSTRUCTION & OPERATIONAL NOISE ASSESSMENT REPORT NO. 06096 VERSION A SEPTEMBER

More information

CARRYING OUT NOISE ASSESSMENTS FOR PROPOSED SUPERMARKET DEVELOPMENTS

CARRYING OUT NOISE ASSESSMENTS FOR PROPOSED SUPERMARKET DEVELOPMENTS Acoustics 2008 Geelong, Victoria, Australia 24 to 26 November 2008 Acoustics and Sustainability: How should acoustics adapt to meet future demands? CARRYING OUT NOISE ASSESSMENTS FOR PROPOSED SUPERMARKET

More information

Roma to Brisbane Pipeline Dalby Compressor Station Upgrade Environmental Management Plan. Appendix 8. Noise Assessment

Roma to Brisbane Pipeline Dalby Compressor Station Upgrade Environmental Management Plan. Appendix 8. Noise Assessment Roma to Brisbane Pipeline Dalby Compressor Station Upgrade Environmental Management Plan Appendix 8 Noise Assessment PR104962-1 Rev 0; June 2011 PR104962-1 Rev 0; June 2011 Roma to Brisbane Pipeline Dalby

More information

NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING FOR BLUEWATER RIVER CROSSING REPLACEMENT PROJECT

NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING FOR BLUEWATER RIVER CROSSING REPLACEMENT PROJECT Stantec Consulting Ltd. 300-675 Cochrane Drive West Tower Markham ON L3R 0B8 Tel: (905) 944-7777 Fax: (905) 474-9889 August 9, 2012 File: 160960699 NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING

More information

No significant construction or operational vibration impacts are expected.

No significant construction or operational vibration impacts are expected. 8 NOISE AND VIBRATION 8.1 SUMMARY OF RESIDUAL IMPACTS impacts for the construction and operation of the proposed CCGT power plant development are expected as these will be mitigated through design and

More information

1 18 August 2017 Version 2 (Noise and vibration)

1 18 August 2017 Version 2 (Noise and vibration) Table 8-6 s (Noise and Vibration only) EES Evaluation Noise and Vibration Health, amenity and environmental quality to minimise adverse air quality, noise and vibration effects on the health and amenity

More information

Chapter 4 Environmental Setting, Impacts, and Mitigation 4.6 NOISE Environmental Setting. Approach to Analysis

Chapter 4 Environmental Setting, Impacts, and Mitigation 4.6 NOISE Environmental Setting. Approach to Analysis 4.6 NOISE 4.6.1 Environmental Setting Approach to Analysis This section evaluates potential noise impacts associated with the construction and operation of the proposed LWRP upgrade and expansion within

More information

Impacts of Dredging and Reclamation on Noise and Amenity

Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5 Impacts of Dredging and Reclamation on Noise and Amenity Section 9.5.1 Management Goals for Noise and Amenity The management goals for noise and vibration are to: Minimise the noise associated

More information

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario Stationary Noise Feasibility Assessment 315 Chapel Street Ottawa, Ontario REPORT: GWE17-002 - Stationary Noise Prepared For: Leanne Moussa Allsaints 10 Blackburn Avenue K1N 6P8 Ottawa, Ontario Prepared

More information

HAZOP Checklist for Sewage Treatment Plant

HAZOP Checklist for Sewage Treatment Plant HAZOP Checklist for Sewage Treatment Plant CHECKLIST 1.0 Overall Layout of Treatment Plant 1.1 General Layout Property are fenced and gated and the fence height. State where these problems/impacts occur

More information

BROKEN HILL OPERATIONS PTY LTD

BROKEN HILL OPERATIONS PTY LTD RASP MINE, BROKEN HILL 130 Eyre Street, Broken Hill PO Box 5073 BROKEN HILL. NSW 2880 Kane Winwood Senior Planning Officer Major Development Assessment Department of Planning 23 33 Bridge Street SYDNEY

More information

1 Introduction. Mine EPL. report. Dear Leonard, J13083L2_24 assessment. operation of. the crusher, RASP Mine. 2015); and

1 Introduction. Mine EPL. report. Dear Leonard, J13083L2_24 assessment. operation of. the crusher, RASP Mine. 2015); and 14 January 2016 Leonard Sharp Environment and Community Liaison Officer CBH Resources RASP Mine Broken Hill Operations Pty Ltd 130 Eyre St, Broken Hill, NSW 2880 Level 5, 21 Bolton Street Newcastle NSW

More information

UC Press Building 2120 Berkeley Way Berkeley, CA

UC Press Building 2120 Berkeley Way Berkeley, CA CONSTRUCTION NOISE REDUCTION PROGRAM FOR: UC Press Building 2120 Berkeley Way Berkeley, CA RGD Project #: 17-057 PREPARED FOR: Berkeley Way, LLC 1958A University Ave. Berkeley, CA 94704 PREPARED BY: Harold

More information

Appendix B Noise and Blasting Impact Assessment

Appendix B Noise and Blasting Impact Assessment Appendix B Noise and Blasting Impact Assessment 19 August 2010 Ref: J0130-42-L4 Hansen Bailey Pty Ltd P.O. Box 473 SINGLETON NSW 2330 Attn: Ms. Melissa Walker Dear Mel, ABN: 73 254 053 305 78 Woodglen

More information

Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS.

Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS. 7. NOISE & VIBRATION Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS. 7.1 RECEIVING ENVIRONMENT 7.1.1 Monitoring Continuous noise monitoring was undertaken

More information

Ecologically Sustainable Development

Ecologically Sustainable Development 29 Ecologically Sustainable Development Ecologically Sustainable Development CHAPTER 29 29.1 Introduction The EP&A Act requires Ecologically Sustainable Development (ESD) principles to be considered in

More information

CRANBOURNE LANDFILL. Environmental Noise Assessment. Rp ML. 10 May 2013

CRANBOURNE LANDFILL. Environmental Noise Assessment. Rp ML. 10 May 2013 CRANBOURNE LANDFILL Environmental Noise Assessment Rp 001 2012351ML 10 May 2013 4/46 Balfour St Chippendale NSW 2008 T: +612 9282 9422 Fax: +612 9281 3611 www.marshallday.com Project: CRANBOURNE LANDFILL

More information

15.1. INTRODUCTION AND SUMMARY OF FINDINGS

15.1. INTRODUCTION AND SUMMARY OF FINDINGS Chapter 15: Noise 15.1. INTRODUCTION AND SUMMARY OF FINDINGS This Chapter analyzes the potential for the Proposed Project s operation to have an adverse noise impact on proximate receptors. The potential

More information

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES DECEMBER 2013 www.mcconnelldowell.com MCCONNELL DOWELL CORPORATION PAGE 1 OF 13 McConnell Dowell Constructors (Aust.)

More information

100 Avenue Road, Swiss Cottage, London

100 Avenue Road, Swiss Cottage, London 100 Avenue Road, Swiss Cottage, London 296993-01(00) NOVEMBER 2017 RSK GENERAL NOTES Project No.: 296993-01(00) Title: 100 Avenue Road, Swiss Cottage, London - Client: Date: 30 th November 2017 Office:

More information

Level of Significance after Mitigation Impacts would be less than significant.

Level of Significance after Mitigation Impacts would be less than significant. Level of Significance after Mitigation Impacts would be less than significant. 4.8 NOISE This section assesses noise impacts associated with the proposed project. It analyzes both potential noise impacts

More information

Noise Variance Review

Noise Variance Review Noise Variance #: NVAR17-0012 Noise Variance Review The noise variance (NVAR17-00012) request dated May 5, 2017 was evaluated based on the information provided in the variance submitted and any additional

More information

SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY

SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY 202 Uxbridge Road London W12 7JP Tel: +44(0)203 475 2280 Fax: +44(0)203 475 2281 info@clementacoustics.co.uk www.clementacoustics.co.uk SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY Report 8991-ENS-03

More information

PROPOSED KLONDYKE WATER STORAGE ASSESSMENT OF NOISE EFFECTS

PROPOSED KLONDYKE WATER STORAGE ASSESSMENT OF NOISE EFFECTS 1/355 Manukau Road Epsom, Auckland 1023 PO Box 26283 Epsom, Auckland 1344 T: 09 638 8414 E: hegley@acoustics.co.nz PROPOSED KLONDYKE WATER STORAGE ASSESSMENT OF NOISE EFFECTS Report No 15092v2 Prepared

More information

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario

Stationary Noise Feasibility Assessment. 315 Chapel Street Ottawa, Ontario Stationary Noise Feasibility Assessment 315 Chapel Street Ottawa, Ontario REPORT: GWE17 002 Stationary Noise Prepared For: Leanne Moussa Allsaints 10 Blackburn Avenue K1N 6P8 Ottawa, Ontario Prepared By:

More information

BSM SD PLN 0126 MANAGEMENT PLAN 1. COMMITMENT AND POLICY 2. BACKGROUND. 1.1 Purpose. 1.2 Scope. 2.1 Development Consent Requirements

BSM SD PLN 0126 MANAGEMENT PLAN 1. COMMITMENT AND POLICY 2. BACKGROUND. 1.1 Purpose. 1.2 Scope. 2.1 Development Consent Requirements Blakefield South Mine MANAGEMENT PLAN 1. COMMITMENT AND POLICY 1.1 Purpose The purpose of the Construction Noise Management Plan (CNMP) is to provide a structured process for managing, monitoring and reporting

More information

Woodlawn Mechanical Biological Treatment Facility. Project Approval (06_0239) Condition 28 - Noise Audit Report. Report Number 610.

Woodlawn Mechanical Biological Treatment Facility. Project Approval (06_0239) Condition 28 - Noise Audit Report. Report Number 610. Veolia Environmental Services (Australia) Pty Ltd Cnr Unwin and Shirley Streets Rosehill NSW 2142 Version: v1.0 Page 2 PREPARED BY: ABN 29 001 584 612 2 Lincoln Street Lane Cove NSW 2066 Australia (PO

More information

Noise Assessments for Construction Noise Impacts

Noise Assessments for Construction Noise Impacts Noise Assessments for Construction Noise Impacts Weixiong Wu a AKRF, Inc., 440 Park Avenue, 7th floor, New York, NY, 10016, USA. ABSTRACT Construction noise is one of the most disruptive noise sources

More information

ORICA VILLAWOOD REMEDIATION

ORICA VILLAWOOD REMEDIATION ORICA VILLAWOOD REMEDIATION NOISE AND VIBRATION ASSESSMENT REPORT NO. 09295 VERSION C ORICA VILLAWOOD REMEDIATION NOISE AND VIBRATION ASSESSMENT REPORT NO. 09295 VERSION C NOVEMBER 2010 PREPARED FOR THIESS

More information

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES

MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES JANUARY 2014 www.mcconnelldowell.com MCCONNELL DOWELL CORPORATION PAGE 1 OF 13 McConnell Dowell Constructors (Aust.)

More information

Monthly Noise Monitoring Assessment

Monthly Noise Monitoring Assessment Monthly Noise Monitoring Assessment Tomingley Gold Mine, December 2018 Prepared for: Tomingley Gold Operations Pty Limited December 2018 MAC160270RP28 Document Information Monthly Noise Monitoring Assessment

More information

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 11 NOISE AND VIBRATION ASSESSMENT

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 11 NOISE AND VIBRATION ASSESSMENT Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 11 NOISE AND VIBRATION ASSESSMENT October 2005 Contents 11. 11-1 11.1. Introduction 11-1 11.1.1. Scope of 11-1 11.2. Existing Noise

More information

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance Project: East Hampton Temporary Generation Facility Expansion Date: May 17, 2018 This notice is issued

More information

9. NOISE AND VIBRATION

9. NOISE AND VIBRATION 9. NOISE AND VIBRATION 9.1 Introduction 9.1.1 This Chapter details the existing baseline noise and vibration levels together with assessments of the suitability of the site for residential and commercial

More information

Division 15 Earthworks Code (including Lot Filling)

Division 15 Earthworks Code (including Lot Filling) Division 15 Earthworks Code (including Lot Filling) 12.15.1 Earthworks Code (1) The provisions in this division comprise the (2) They are compliance with the Earthworks Code (Section 12.15.2); overall

More information

Management Plan: Hazardous Materials Removal & Demolition

Management Plan: Hazardous Materials Removal & Demolition Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council

More information

TABLE OF CONTENTS LIST OF TABLES

TABLE OF CONTENTS LIST OF TABLES CHAPTER 7 NOISE AND VIBRATION TABLE OF CONTENTS 7 NOISE AND VIBRATION... 7-1 7.1 Introduction... 7-1 7.2 Methodology... 7-1 7.3 Existing Environment... 7-2 7.3.1 Project specific operational noise criteria...

More information

BLUESCOPE STEEL LIMITED PORT KEMBLA STEELWORKS ORE PREPARATION AREA UPGRADE NOISE IMPACT STATEMENT. REPORT J R2 5th MAY 2006

BLUESCOPE STEEL LIMITED PORT KEMBLA STEELWORKS ORE PREPARATION AREA UPGRADE NOISE IMPACT STATEMENT. REPORT J R2 5th MAY 2006 ABN: 73 254 053 305 78 Woodglen Close P.O. Box 61 PATERSON NSW 2421 Phone : (02) 4938 5866 Fax: (02) 4938 5831 Mobile: (0407) 38 5866 E-mail: bridgesacoustics@bigpond.com BLUESCOPE STEEL LIMITED PORT KEMBLA

More information

the Southern Plumes (from the former Solvents Plant and former Trichloroethylene (TCE) Plant);

the Southern Plumes (from the former Solvents Plant and former Trichloroethylene (TCE) Plant); 1 Introduction Introduction CHAPTER 1 1.1 Background to the Project URS Australia Pty Ltd (URS) has been commissioned by Orica Australia Pty Ltd (hereafter referred to as Orica or the Proponent ) to prepare

More information

TAURANGA CITY COUNCIL

TAURANGA CITY COUNCIL TAURANGA CITY COUNCIL CONDITIONS FOR SOUTHERN PIPELINE APPLICATION (RC13559) 1. The proposal shall proceed in accordance with the application submitted including: - The Assessment of Effects on the Environment

More information

COMMUNITY BRIEFING PAPER BOTANY GROUNDWATER PROJECT

COMMUNITY BRIEFING PAPER BOTANY GROUNDWATER PROJECT COMMUNITY BRIEFING PAPER BOTANY GROUNDWATER PROJECT ORICA AUSTRALIA PTY LTD 16 DECEMBER 2003 PURPOSE This briefing paper has been prepared as part of Orica s commitment to the Botany community to provide

More information

APPENDIX 8. Noise Impact Assessment

APPENDIX 8. Noise Impact Assessment APPENDIX 8 Noise Impact Assessment Orica Australia Pty Limited Noise Impact Assessment for Proposed Ammonium Nitrate Emulsion Production Facility and Continued Operation of Orica Mining Services Technology

More information

Environmental Noise Compliance Assessment Bass Point Quarry

Environmental Noise Compliance Assessment Bass Point Quarry P: 4421 4583 M: 0414 315 775 50 Junction Street, Nowra, NSW 2541 matthew@harwoodacsoutics.com.au www.harwoodacoustics.com.au ABN: 71634 997 937 Environmental Noise Compliance Assessment Bass Point Quarry

More information

Environmental Noise Monitoring. Hanson Quarry Wagga Wagga, NSW. October 2012

Environmental Noise Monitoring. Hanson Quarry Wagga Wagga, NSW. October 2012 Environmental Noise Monitoring Hanson Quarry Wagga Wagga, NSW October 2012 Contents 1. INTRODUCTION... 3 2. UNATTENDED NOISE MONITORING... 3 3. EXISTING BACKGROUND NOISE LEVELS... 5 4. EXISTING AMBIENT

More information

14: INTRODUCTION

14: INTRODUCTION Chapter 14: Noise 14.1. INTRODUCTION This Chapter analyzes the noise levels that would be produced by the Proposed Project and their potential to result in significant adverse noise impacts on the surrounding

More information

Notice of Clean Up Action

Notice of Clean Up Action ORICA AUSTRALIA PTY LTD, ABN 99 004 117 828, 16-20 BEAUCHAMP ROAD, MATRAVILLE NSW 2036 STANDARD POST Attention: Mr. Bruce E GOTTING Notice Number 1030236 File Number HO1706/03 Date 26-Sep-2003 NOTICE OF

More information

Noise & Vibration Impact Assessment

Noise & Vibration Impact Assessment Appendix Noise & Vibration Impact Assessment APPENDIX F KURNELL REFINERY CONVERSION INTO A FINISHED PRODUCT TERMINAL REPORT NO. 12315 VERSION F MAY 2013 PREPARED FOR URS AUSTRALIA PTY LTD 407 PACIFIC HIGHWAY

More information

APPENDIX 11. Bushfire Threat Assessment

APPENDIX 11. Bushfire Threat Assessment APPENDIX 11 Bushfire Threat Assessment Orica Mining Services Lot 2 DP 809377 George Booth Drive, Richmond Vale, NSW, 2327 Proposed Ammonium Nitrate Emulsion Production Facility Bushfire Threat Assessment

More information

The applicant has estimated a total of vehicle movements per day.

The applicant has estimated a total of vehicle movements per day. INSPECTORS REPORT WASTE LICENCE REGISTER NUMBER 147-1 Ashgrove Plant Limited (trading as Ashgrove Recycling) Churchfield Industrial Estate, Cork Recommendation: That a Licence subject to condition be granted

More information

8 Noise and Vibration

8 Noise and Vibration 8 Noise and Vibration 8.1 Introduction This chapter of the EIS assesses the potential noise and vibration impact of the Proposed Project on the baseline environment. The potential noise impact due to the

More information

South Branch Wind Farm Acoustic Audit - Immission Summary for Public Distribution

South Branch Wind Farm Acoustic Audit - Immission Summary for Public Distribution South Branch Wind Farm Acoustic Audit - Immission Summary for Public Distribution Introduction The South Branch Wind Farm (project) operates 10 Siemens SWT-3.0-113 wind turbines located within the Township

More information

Section 75J of the Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning and Assessment Act 1979 Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, approve the project referred to in Schedule 1, subject to the conditions in Schedule 2.

More information

Noise monitoring program for assessing the impact of maximum traffic noise levels

Noise monitoring program for assessing the impact of maximum traffic noise levels Proceedings of ACOUSTICS 2005 9-11 November 2005, Busselton, Western Australia Noise monitoring program for assessing the impact of maximum traffic noise levels Treagus, R.* & Beazley, C. J.* Department

More information

APPENDIX G NOISE ASSESSMENT

APPENDIX G NOISE ASSESSMENT Environmental Impact Statement Beryl Solar Farm APPENDIX G NOISE G.1 NOISE REPORT G.2 DRAFT CONSTRUCTION NOISE MANAGEMENT PLAN Beryl Solar Farm 16 347 Final V1 G i Acoustics Vibration Structural Dynamics

More information

Santos LNG Facility Noise Assessment

Santos LNG Facility Noise Assessment F4 Noise REPORT 20-2014-R7 Revision 1 Santos LNG Facility Noise Assessment PREPARED FOR URS Australia Pty Ltd Level 16, 240 Queen Street Brisbane QLD 4000 9 NOVEMBER 2009 HEGGIES PTY LTD ABN 29 001 584

More information

Section 4-7 Noise STUDY METHODS Acoustic Fundamentals Amplitude Frequency

Section 4-7 Noise STUDY METHODS Acoustic Fundamentals Amplitude Frequency Section 4-7 Noise This section includes a summary of applicable regulations, a description of ambient noise conditions, and an analysis of potential noise impacts of the proposed project. Traffic noise

More information

Noise October 22, Noise Existing Conditions. Noise Characteristics

Noise October 22, Noise Existing Conditions. Noise Characteristics 3.7 3.7.1 Existing Conditions Characteristics The noise analysis contained in this section of the DEIS has been conducted in accordance with the New York State Department of Environmental Conservation

More information

SUBURBAN COMMERCIAL ZONE - RULES

SUBURBAN COMMERCIAL ZONE - RULES Suburban Commercial Zone Chapter 18 SUBURBAN COMMERCIAL ZONE - RULES INTRODUCTION This chapter contains rules managing land uses that take place within the suburban shopping centres of the City. This includes

More information

Noise Impact Assessment

Noise Impact Assessment Noise Impact Assessment for Multi-Unit Residential Development Block 11, Section 6, Dickson ACT Prepared for: Melinda Dodson Architects 4b 20 Napier Close DEAKIN ACT 2600 By: GUZ BOX design + audio PO

More information

Appendix P. Construction Noise Assessment. (Prepared by Marshall Day Acoustics, November 2013)

Appendix P. Construction Noise Assessment. (Prepared by Marshall Day Acoustics, November 2013) Appendix P Construction Noise Assessment (Prepared by Marshall Day Acoustics, November 2013) WRIGHTS ROAD STORAGE PONDS Construction Noise Assessment Rp 001 R03 2013523C 5 December 2013 Project: Prepared

More information

ENVIRONMENTAL NOISE CONTROL FOR SEMICONDUCTOR MANUFACTURING FACILITIES

ENVIRONMENTAL NOISE CONTROL FOR SEMICONDUCTOR MANUFACTURING FACILITIES Presented at Inter-Noise 99 The 1999 Congress and Exposition on Noise Control Engineering December 8, 1999, Fort Lauderdale, Florida ENVIRONMENTAL NOISE CONTROL FOR SEMICONDUCTOR MANUFACTURING FACILITIES

More information

Appendix B2 Construction Noise and Vibration Management Plan

Appendix B2 Construction Noise and Vibration Management Plan Appendix B2 Construction Noise and Vibration Management Plan Project: Keepit Dam Work Package 2 - Post Tensioning Works Location: Keepit Dam, Namoi River, Northern NSW Client: WaterNSW Contract: 04532F31

More information

Community Liaison Committee Botany Groundwater Cleanup Project Briefing Paper for Meeting on 15 September 2009

Community Liaison Committee Botany Groundwater Cleanup Project Briefing Paper for Meeting on 15 September 2009 Community Liaison Committee Botany Groundwater Cleanup Project Briefing Paper for Meeting on 15 September 2009 1 INTRODUCTION This briefing paper has been prepared for the Community Liaison Committee (CLC),

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Air Quality Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006 Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006 With respect to the Conclusions on BAT for this horizontal BREF, the details of applicability and status

More information

APPENDIX 12 NOISE IMPACT ASSESSMENT USING HEALTH CANADA GUIDELINES

APPENDIX 12 NOISE IMPACT ASSESSMENT USING HEALTH CANADA GUIDELINES APPENDIX 12 NOISE IMPACT ASSESSMENT USING HEALTH CANADA GUIDELINES Suncor Energy Inc. - i - Noise Health Canada TABLE OF CONTENTS SECTION PAGE 1 INTRODUCTION... 1 2 ASSESSMENT APPROACH... 2 2.1 HEALTH

More information

Construction Noise Management Plan

Construction Noise Management Plan Construction Noise Management Plan Victoria Park Viaduct Side Protection Upgrade Project 27 November 2014 Final Page 2 Record of amendment Revision Description of change Effective date Updated by Incomplete

More information

Salem, Massachusetts

Salem, Massachusetts Salem, Massachusetts June 30, 2011 Prepared for: Meridian Associates Prepared by: Howard Quin Consulting LLC and Cavanaugh-Tocci Associates Contents 1 Introduction... 3 2 Noise Standards and Criteria...

More information

transfer of treated water via pipelines to users on the BIP or to Bunnerong Canal, and of waste water to sewer; and

transfer of treated water via pipelines to users on the BIP or to Bunnerong Canal, and of waste water to sewer; and 6 6.1 Scope A number of statutory planning controls need to be addressed for the Activity (which is defined below) and other components of the BGC Project. This chapter reviews the Commonwealth and State

More information

Environmental Noise Assessment

Environmental Noise Assessment July to September 2014 Rev 0 (Final) Report Details - July to September 2014 Filename: Job #: J0140003 Folder #: F13130 Revision: 0 (Final) Date: Prepared For Clark Potter, Senior Environmental Advisor

More information

TABLE OF CONTENTS LIST OF TABLES LIST OF FIGURES

TABLE OF CONTENTS LIST OF TABLES LIST OF FIGURES APPENDIX B NOISE TABLE OF CONTENTS SECTION PAGE 1.1 INTRODUCTION...1 1.2 METHODS...1 1.2.1 Study Area Boundaries...1 1.2.2 Baseline Case...6 1.2.3 Facility Noise Modelling...7 1.2.4 Noise at 1.5 km From

More information

REGISTRATION EXAMINATION, JUNE 2013 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours

REGISTRATION EXAMINATION, JUNE 2013 LICENSED PLUMBER QUESTION AND ANSWER BOOKLET. Time allowed THREE hours Affix label with Candidate Code Number here. If no label, enter candidate Number if known No. 9192 REGISTRATION EXAMINATION, JUNE 2013 LICENSED PLUMBER INSTRUCTIONS QUESTION AND ANSWER BOOKLET Time allowed

More information

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 12 AIR QUALITY ASSESSMENT

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 12 AIR QUALITY ASSESSMENT Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 12 AIR QUALITY ASSESSMENT October 2005 Contents 12. 12-1 12.1 Introduction 12-1 12.2 Factors Affecting Air Quality 12-1 12.3 Air

More information

Section 12: Noise & Vibration

Section 12: Noise & Vibration Section 12: Noise & Vibration 12.1 INTRODUCTION This section of the EIS has been prepared by Byrne Environmental Consulting Ltd to identify and assess the potential noise and vibrational impacts that the

More information

APPENDIX C NOISE STUDY TECHNICAL REPORT

APPENDIX C NOISE STUDY TECHNICAL REPORT APPENDIX C NOISE STUDY TECHNICAL REPORT Noise Study Technical Report Watertown South Connector US 81 to 29 th Street SE Watertown, South Dakota HDR Project No. 39319 Prepared by 6300 So. Old Village Place

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

Gunlake Quarry. Noise and Blast Management Plan

Gunlake Quarry. Noise and Blast Management Plan Gunlake Quarry Noise and Blast Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Noise Criteria 3 2.1 Operational Noise Assessment Criteria 3 2.2

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM

ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM CITY OF PASADENA 175 NORTH GARFIELD AVENUE PASADENA, CA 91109 PROPOSED MITIGATED NEGATIVE DECLARATION PROJECT

More information

Peak noise levels during any time period can be characterized with statistical terms.

Peak noise levels during any time period can be characterized with statistical terms. 3.11 NOISE Introduction This Noise section provides a discussion of applicable noise policies and standards, the results of ambient noise measurements, an evaluation of the projects compatibility with

More information

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement. Chapter 20: TERRESTRIAL NOISE AND VIBRATION

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement. Chapter 20: TERRESTRIAL NOISE AND VIBRATION ABERDEEN HARBOUR EXPANSION PROJECT November 2015 Volume 2: Environmental Statement Chapter 20: TERRESTRIAL NOISE AND VIBRATION 20. TERRESTRIAL NOISE AND VIBRATION 20.1 Introduction This chapter, which

More information

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED Chapter 17 Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.1.1 Applicability The regulations in this chapter apply to any private potable water supply system where plumbing fixtures are

More information

10 Noise and Vibration

10 Noise and Vibration 10 Noise and Vibration Introduction This chapter assesses the potential noise and vibration impacts on the surrounding environment associated with the construction and operation of the proposed at Ringaskiddy,

More information

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI Traffic Management Plan Environmental Management and Monitoring Program Appendix VI Gunlake Quarries December 2009 Olsen Consulting Group Pty Ltd 6/25 Victoria Street WOLLONGONG 2500 PO Box 353 FIGTREE

More information

Proposed Childcare and Café within SHA Development, Girven Road, Mount Maunganui - Noise Assessment

Proposed Childcare and Café within SHA Development, Girven Road, Mount Maunganui - Noise Assessment 14 June 2016 Momentum Planning and Design Tauranga Dear Sir, Re: Attention: Richard Coles 1.0 Dear Sir Re: Proposed Childcare and Café within SHA Development, Girven Road, Mount Maunganui - Noise Assessment

More information

GOOD PRACTICE GUIDELINES FOR CONTROLLING NOISE ON OFFSHORE INSTALLATIONS

GOOD PRACTICE GUIDELINES FOR CONTROLLING NOISE ON OFFSHORE INSTALLATIONS GOOD PRACTICE GUIDELINES FOR CONTROLLING NOISE ON OFFSHORE INSTALLATIONS Graham McPherson (CMFOH) OH2017 Harrogate International Centre 24 27 April 2017 Introduction UK Noise Regulations also apply in

More information

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane.

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane. 17. SERVICES 17.1 Introduction 17.1.1 WSP Development Limited has been appointed by CALA Homes to investigate and appraise the availability of services to serve a proposed mix-use development of approximately

More information

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS APPENDIX A: THE CONSTRUCTION OF A COMPOUND FOR USE BY RAILWAY STAFF AND TRAIN DRIVERS, INCLUDING THE ERECTION OF A TWO STOREY OFFICE AND WELFARE BLOCK WITH ASSOCIATED YARDS, SITE LEVELLING, EXTERNAL LIGHTING,

More information

NOISE MANAGEMENT PLAN

NOISE MANAGEMENT PLAN Young to Wagga Wagga Pipeline Looping Project Project No.: Q8291 Doc No: 8291-PLN-005 NOISE MANAGEMENT PLAN 1 07-08-10 Details revised as per NSW Dept of Planning G.O Mahony P. Grant G. O Mahony 0 28-07-10

More information

The Clem7 Motorway Tunnel: Mechanical and Electrical Plant Acoustic Design and Performance

The Clem7 Motorway Tunnel: Mechanical and Electrical Plant Acoustic Design and Performance Paper Number 67, Proceedings of ACOUSTICS 2011 2-4 November 2011, Gold Coast, Australia The Clem7 Motorway Tunnel: Mechanical and Electrical Plant Acoustic Design and Performance Claire Richardson and

More information

Section 12 Hydraulics.

Section 12 Hydraulics. Design Guidelines Section 12 Hydraulics. www.canterbury.ac.nz/learningresources Standards in the Design Guidelines Suite Design Standard Guidelines Index: 01 General 02 Architecture 03 Audio Visual 04

More information