Assessment of High Temperature Gas-Cooled Reactor (HTGR) Capital and Operating Costs

Size: px
Start display at page:

Download "Assessment of High Temperature Gas-Cooled Reactor (HTGR) Capital and Operating Costs"

Transcription

1 Document ID: TEV-96 Revision ID: 0/09/202 Technical Evaluation Study Project No Assessment of High Temperature Gas-Cooled Reactor (HTGR) Capital and Operating Costs

2 0/09/202

3 TEV-96 0/09/202 Page: 2 of 45 REVISION LOG Rev. Date Affected Pages Revision Description 0 04/29/20 All Newly issued document. 0/09/202 4, 38, 39 Fixed a small error in the calculation of NEI costs.

4 TEV-96 0/09/202 Page: 3 of 45 EXECUTIVE SUMMARY This technical evaluation (TEV) has been prepared as part of a study for the Next Generation Nuclear Plant (NGNP) Project to address estimating the capital, operating, and decommissioning costs of a high-temperature gas-cooled reactor (HTGR). These results are preliminary and should be refined as the design of the HTGR progresses, if the design of the HTGR is changed significantly, or if additional refinements of the costs become available. The results of this evaluation will be used to update the HTGR capital and operating costs used in previous and future TEVs and economic models developed for the NGNP process heat applications study. The capital, operating, and decommissioning costs are based on the HTGR design presented in the NGNP Pre-Conceptual Design Report (INL 2007a). Capital costs include the preconstruction costs, direct costs, indirect costs, and project contingency. Operating costs include operating and maintenance (O&M) costs and fuel costs. In addition to estimating the capital, operating, and decommissioning costs for a reactor outlet temperature (ROT) of 950C, costs for ROTs of 750C, 800C, 850C, and 900C were also evaluated. HTGR costs were also developed with and without power cycles; the power cycles evaluated included both Brayton and Rankine cycles. Finally, the estimates were generated for single and four-pack reactor configurations for both 350 MWt and 600 MWt power levels, for the NGNP (demonstration), first of a kind, and nth of a kind (NOAK) project phases. Table ES- presents the projected capital, operating, and decommissioning costs of an HTGR with a Rankine cycle for the NGNP and NOAK project phases at a ROT of 850 C. The results include costs for the 350 MWt and 600 MWt power levels for single and four-pack rector configurations (the NGNP phase includes only a single reactor option). The O&M costs presented are based on staffing estimates from the reactor design suppliers; currently there are differences in the projected staffing between designers and the INL estimate, in part because required staffing levels have not yet been established. The capital costs are graphically presented in Figure ES- and on a dollar-per-kwt basis in Figure ES-2. The cost model is capable of adjusting capital, operating, and decommissioning costs based on the desired reactor configuration to provide input to multiple process modeling scenarios. The level of project definition for this study was determined to be an AACE International Class 4 estimate, which has a probable error of -30% and +50%.

5 TEV-96 0/09/202 Page: 4 of 45 Table ES-. Cost Summary for NGNP & NOAK HTGR with a Rankine power cycle, 850 C ROT (2009 basis). Reactor Phase NGNP NOAK Reactor Size 600 MWt 350 MWt 600 MWt 350 MWt Number of Modules 4 4 Capital Costs ($0 6 ) Preconstruction Costs Direct Costs Indirect Costs Contingency Overnight Cost ($0 6 ) Lower Bound Upper Bound Overnight Cost ($/kwt) Lower Bound Upper Bound Yearly O&M Costs ($0 6 ) Yearly O&M Costs ($/MWt-hr) Yearly Fuel Costs ($0 6 ) Yearly Fuel Costs ($/MWt-hr) Decommissioning Costs ($0 6 ) Figure ES-. Capital Cost Summary for NGNP and NOAK HTGR with a Rankine power cycle, 850 C ROT ($ basis).

6 TEV-96 0/09/202 Page: 5 of 45 Figure ES-2. Capital Cost Summary for NGNP and NOAK HTGR with a Rankine power cycle, 850 C ROT ($/kwt 2009 basis).

7 TEV-96 0/09/202 Page: 6 of 45 CONTENTS EXECUTIVE SUMMARY...3 ACRONYMS AND NOMENCLATURE...7. INTRODUCTION CAPITAL COST MODELING OVERVIEW Preconstruction Costs Direct Costs Indirect Costs Project Contingency Total Capital Investment Correlation Development for Direct Capital Costs Correlations for the HTGR Cost, Less Power Cycle Correlations for the Brayton Cycle Cost Correlations for the Rankine Cycle Cost Capital Cost Results Comparisons ESTIMATION OF O&M Costs Fuel Costs DECOMMISSIONING COSTS FUTURE WORK AND RECOMMENDATIONS REFERENCES APPENDIXES...44 Appendix A... A-45

8 TEV-96 0/09/202 Page: 7 of 45 ACRONYMS AND NOMENCLATURE AACE BLS BOE BWR CEPCI COLA DOE DP ESP FCL FOAK GA GIF HP HTGR I&C IHX INL INPO ISI LLW LWR NDE NEI NGNP NOAK NRC O&M PWR R&D Association for the Advancement of Cost Engineering Bureau of Labor Statistics balance of equipment boiling water reactor chemical engineering plant cost index combined operating license application Department of Energy duplicate position early site permit fuel cycle length first of a kind General Atomics GEN-IV International Forum health physics high temperature gas-cooled reactor instrumentation and control intermediate heat exchanger Idaho National Laboratory Institute of Nuclear Power Operations in-service inspection low level waste light water reactor non-destructive exams Nuclear Energy Institute Next Generation Nuclear Plant nth of a kind Nuclear Regulatory Commission operations and maintenance pressurized water reactor research & development

9 TEV-96 0/09/202 Page: 8 of 45 RO ROT SC SCM STA SWU TCI TEV reactor operator reactor outlet temperature subcontract supply chain management shift technical advisors separative work unit total capital investment technical evaluation

10 TEV-96 0/09/202 Page: 9 of 45. INTRODUCTION This technical evaluation (TEV) has been prepared as part of a study for the Next Generation Nuclear Plant (NGNP) Project to address estimating the capital, operating, and decommissioning costs of a high-temperature gas-cooled reactor (HTGR). The NGNP Project is being conducted under U.S. Department of Energy (DOE) direction to meet a national strategic need identified in the 2005 Energy Policy Act to promote reliance on safe, clean, economic nuclear energy and to establish a greenhouse-gas-free technology for the production of hydrogen. The NGNP represents an integration of high-temperature reactor technology with advanced hydrogen, electricity, and process heat production capabilities, thereby meeting the mission need identified by DOE. The strategic goal of the NGNP Project is to broaden the environmental and economic benefits of nuclear energy in the U.S. economy by demonstrating its applicability to market sectors not being served by light water reactors. The HTGR produces high-temperature helium that can be used to produce electricity and/or process heat for export in the form of steam or high-temperature helium. This TEV presents the methodology and results of a cost model which was developed to estimate the capital, operating, and decommissioning costs of an HTGR. These costs are based, in general, on the HTGR design presented in the NGNP Pre-Conceptual Design Report (INL 2007a). Although initial HTGR implementations may target a reactor outlet temperature (ROT) of approximately 750 C, temperatures of up to 950 C are anticipated for later designs. Therefore, the cost model was developed to be capable of estimating costs for the ROT range of 750 C to 950 C, in 50 C increments. HTGR costs were also developed with and without power cycles; the power cycles evaluated included both Brayton and Rankine cycles. Correlations are developed for the power cycles, such that combined heat and power facility costs can be evaluated. Finally, the estimates were generated for single and four-pack reactor configurations for both 350 MWt and 600 MWt power levels, for the NGNP, first of a kind (FOAK), and nth of a kind (NOAK) project phases. A four-pack reactor plant includes four reactor vessels with shared control facilities. The NGNP plant is the initial demonstration of the current HTGR design funded through a public-private-partnership cost-share, a FOAK plant is the first privately funded commercial installation of the HTGR technology, while the NOAK plant is a mature privately funded commercial installation of the HTGR technology. The intended application of the cost model is to develop capital and operating costs for a wide variety of HTGR deployment options, such that the economic impact of HTGR integration into electricity, heat, and/or commercial chemical production can be assessed for business development, project screening, and economic feasibility. As the HTGR is still in the early stages of project development, the cost model has an expected accuracy of -30% to +50%. This TEV assumes familiarity with the NGNP Pre-Conceptual Design Report; hence, detailed descriptions of the HTGR design are not presented here. The cost model used for this analysis has been developed in Microsoft Excel (Excel 2007). This study makes

11 TEV-96 0/09/202 Page: 0 of 45 extensive use of this model; this TEV assumes familiarity with Excel. A detailed explanation of the software capabilities is beyond the scope of this study. This TEV first presents the approach for generating the HTGR capital costs as a function of the reactor parameters described above. Next the approach for generating the operating costs is presented, followed by the approach for estimating decommissioning costs. Finally, results of the cost models are presented and discussed. These results are preliminary and should be refined as the design of the HTGR progresses, if the design of the HTGR is changed significantly, or if additional refinements of the costs become available. The results of this evaluation will be used to update the HTGR capital and operating costs used in previous and future TEVs and economic models developed for the NGNP process heat applications study. 2. CAPITAL COST MODELING OVERVIEW The capital costs for the HTGR were assessed using a top-down evaluation; including factored cost estimates for major equipment items and ratio factors based on industry experience and/or program guidance for balance of equipment costs, indirect costs, and project contingency. The costs were evaluated in detail for the following cases : Project phases: NGNP FOAK NOAK ROTs of 750C to 950C, in 50C increments Single and four-pack reactor modules, NGNP phase includes a single reactor only Power levels: 350 MWt 600 MWt Power cycle configurations: No power cycle, i.e. heat only Brayton cycle Rankine cycle The detailed cost assessments were used to develop correlations that can be used to estimate the costs for other operating conditions and configurations, e.g., more than four modules in a plant and ROTs other than 750 C to 950 C, in 50 C increments.

12 TEV-96 0/09/202 Page: of 45 The total capital investment (TCI), based on preconstruction, direct, and indirect costs are included in the capital cost estimate for the HTGR. The Association for the Advancement of Cost Engineering (AACE) International recognizes five classes of estimates. The level of project definition for this study was determined to be an AACE International Class 4 estimate, which has a probable error of -30% and +50%. A Class 4 estimate is associated with a feasibility study or top-down cost estimate and has one to fifteen percent of full project definition (AACE 2005). 2. Preconstruction Costs Preconstruction costs include the followings costs: Land and land rights Licensing and application Costs for land and land rights were based on the acreage required for a single reactor or for a four-pack of reactors. It was assumed that a single HTGR requires 50 acres of land, while a four-pack requires 00 acres. This data was approximated based on information provided by General Atomics (GA). A rule of thumb cost of $00,000 per acre was assumed (Wallace 20). Licensing and application costs were developed based on input from NGNP regulatory affairs for the various reactor phases; the costs are presented in Table. Licensing cost development associated with the single module NGNP HTGR are as described in the NGNP Program Planning Bases for the Schedule and Cost Estimates (INL 200). Table. Licensing cost summary ($ basis). Reactor Phase NGNP FOAK NOAK Task Number of Modules 4 4 Pre-Application ESP 2 and COLA 3 Preparation ESP and COLA Review by NRC Support of Construction & Initial Operation State and Local Permitting Total Early site permit (ESP). 3 Combine operating license application (COLA).

13 TEV-96 0/09/202 Page: 2 of 45 Design certification costs are included in the licensing costs for the NGNP plant. It is assumed that design certification costs would only be incurred for the initial plant and would cover all downstream builds. Costs for land and land rights and licensing and application are summed to determine the total preconstruction costs, summarized in Table 2. Table 2. Total preconstruction cost summary ($ basis). Reactor Phase NGNP FOAK NOAK Task Number of Modules 4 4 Land and Land Rights Licensing and Application Costs Total Direct Costs Direct costs for the reactor plant are associated with the cost of materials and installation for the equipment items that make up the reactor plant. Given the nascent stage of the HTGR design, previous reactor cost estimates provided by the reactor design suppliers were assessed to determine the reactor plant equipment items that make up the majority of the direct costs. Based on this analysis, the following equipment items make up approximately 80% of the installed equipment costs: Reactor building Reactor vessel Reactor initial core Reactor metallic internals Reactor graphite internals Reactor cavity cooling system Core refueling equipment Heat rejection system Intermediate heat exchanger (IHX) Power generation equipment Rankine cycle Brayton cycle, includes power conversion vessel The direct costs of the above items were estimated by Dominion for the INL through a separate subcontract. Costs were estimated for the prismatic block

14 TEV-96 0/09/202 Page: 3 of 45 reactor, the pebble bed reactor costs will be included in the future revisions of the TEV. Dominion estimated the direct component costs based on information provided in the GA Pre-Conceptual Design Report (GA 2007) and cost data in the public domain for the GA gas turbine-modular helium reactor. For each ROT (750 C to 950 C, in 50 C increments), the most probable material is selected for each component, choosing from SA-508, 2¼Cr-Mo, and Incoloy 800H, based on the expected component temperature, taking into account allowances for creep-fatigue and corrosion. Certain components, such as the Rankine power cycle, did not include options for material selection as the increase in ROT would have no impact on the material choice. The resulting component costs were adjusted based on the cost ratios for the raw materials as well as a ratio for ease of component fabrication, which is applied to the labor portion of the cost for the component for each material option. The breakdown between material, forming and fabrication, final fabrication, transportation, etc. is based on Dominion s extensive experience with LWR capital costs. Exponential scaling factors, based on LWR and other industrial experience, are used to adjust the capital costs for changes in the component sizes associated with slight capacity adjustments for changes in ROT and the overall thermal and/or power rating. A scaling factor was also used to adjust the costs from single to multiple module units, based on industrial LWR experience. Finally, factors were included to adjust the costs for the NGNP and FOAK project phases, based on data provided by the GEN-IV International Forum (GIF) (2007). Appendix A presents more detailed information on the methodology and approach Dominion used to estimate the direct costs for the specified reactor equipment items. Cost indices were used to adjust equipment prices provided in the Dominion assessment from 2007 dollars to 2009 dollars using the Chemical Engineering Plant Cost Index (CEPCI) shown in Table 3. Table 3. CEPCI data. Year CEPCI To account for the balance of equipment (BOE) costs not included in the Dominion direct cost estimate, the total cost of the items above were multiplied by a factor of.25. This factor was based upon the assessment of the previous cost estimates provided by the reactor design suppliers, in which the remaining equipment items contribute 20% of the installed equipment costs, as described previously.

15 TEV-96 0/09/202 Page: 4 of 45 The costs provided by Dominion, the associated balance of equipment costs, and the resulting total direct costs are summarized in Table 4 for the NGNP plant at all ROTs and power levels, Table 5 for a single and four-pack FOAK plant at all ROTs and power levels, and Table 6 for a single and four-pack NOAK plant at all ROTs and power levels. Table 4. Direct costs NGNP HTGR ($ basis). Power Modules Level Equipment Item ROT Reactor Building Reactor Vessel Reactor Initial Core Reactor Metallic Internals Reactor Graphite Internals Reactor Cavity Cooling System Core Refueling Equipment Heat Rejection System IHX Brayton Power Conversion Vessel Power Generation Brayton Cycle Power Generation Rankine Cycle BOE No Power Cycle BOE Brayton Power Cycle BOE Rankine Power Cycle Total No Power Cycle Total Brayton Power Cycle Total Rankine Power Cycle Reactor Building Reactor Vessel Reactor Initial Core Reactor Metallic Internals Reactor Graphite Internals Reactor Cavity Cooling System Core Refueling Equipment Heat Rejection System IHX Brayton Power Conversion Vessel Power Generation Brayton Cycle Power Generation Rankine Cycle BOE No Power Cycle BOE Brayton Power Cycle BOE Rankine Power Cycle Total No Power Cycle Total Brayton Power Cycle Total Rankine Power Cycle MWt 350 MWt

16 TEV-96 0/09/202 Page: 5 of 45 Table 5. Direct costs FOAK HTGR ($ basis). Power Modules 4 Level Equipment Item ROT Reactor Building Reactor Vessel Reactor Initial Core Reactor Metallic Internals Reactor Graphite Internals Reactor Cavity Cooling System Core Refueling Equipment Heat Rejection System IHX Brayton Power Conversion Vessel Power Generation Brayton Cycle Power Generation Rankine Cycle BOE No Power Cycle BOE Brayton Power Cycle BOE Rankine Power Cycle Total No Power Cycle Total Brayton Power Cycle Total Rankine Power Cycle MWt 350 MWt Reactor Building Reactor Vessel Reactor Initial Core Reactor Metallic Internals Reactor Graphite Internals Reactor Cavity Cooling System Core Refueling Equipment Heat Rejection System IHX Brayton Power Conversion Vessel Power Generation Brayton Cycle Power Generation Rankine Cycle BOE No Power Cycle BOE Brayton Power Cycle BOE Rankine Power Cycle Total No Power Cycle Total Brayton Power Cycle Total Rankine Power Cycle

17 TEV-96 0/09/202 Page: 6 of 45 Table 6. Direct costs NOAK HTGR ($ basis). Power Modules 4 Level Equipment Item ROT Reactor Building Reactor Vessel Reactor Initial Core Reactor Metallic Internals Reactor Graphite Internals Reactor Cavity Cooling System Core Refueling Equipment Heat Rejection System IHX Brayton Power Conversion Vessel Power Generation Brayton Cycle Power Generation Rankine Cycle BOE No Power Cycle BOE Brayton Power Cycle BOE Rankine Power Cycle Total No Power Cycle Total Brayton Power Cycle Total Rankine Power Cycle MWt 350 MWt Reactor Building Reactor Vessel Reactor Initial Core Reactor Metallic Internals Reactor Graphite Internals Reactor Cavity Cooling System Core Refueling Equipment Heat Rejection System IHX Brayton Power Conversion Vessel Power Generation Brayton Cycle Power Generation Rankine Cycle BOE No Power Cycle BOE Brayton Power Cycle BOE Rankine Power Cycle Total No Power Cycle Total Brayton Power Cycle Total Rankine Power Cycle

18 TEV-96 0/09/202 Page: 7 of Indirect Costs The capital required for construction overhead and other costs not included in the direct costs are included in the indirect costs. Again, given the nascent stage of the HTGR design, it was necessary to estimate the indirect costs as a percentage of the direct costs based on previous reactor design supplier estimates and historical indirect costs for light water reactors (LWRs). Indirect costs included in the analysis are: Construction services including but not limited to costs for construction management, procurement, scheduling, cost control, site safety, and quality inspections Home office and engineering services - including but not limited to costs for estimating, scheduling, project expediting, project general management, design allowance, and project fees Field office and engineering services including but not limited to costs for the field office, field engineering, field drafting, field procurement, and field administrative and general expenses Owner s costs including but not limited to project fees, taxes, and insurance; spare parts and other capital expenses; staff training and startup costs; and administrative and general expenses Design costs Table 7 provides a list of HTGR (based on information provided by the reactor design suppliers) and historical LWR values for indirect costs. These values were averaged to determine the appropriate factors to use in the HTGR capital cost assessment for the indirect costs. These percentages were used for the NGNP plant, FOAK plant, and the NOAK plant. Table 7. Indirect cost summary (% of total direct cost). Const. Services Home Office & Eng. Field Office & Eng. Reference Services Services Owner s Costs Total GA 907 (GA 2007) % 4.7% 0.4% 8.8% 44.2% DOE/NE-0009 (DOE 980) 5 6% 9% 6% 0% 5% DOE/NE-0095 (DOE 988) 6 24% 25% 3% 6% 77% Average 20% 6% 0% 2% 57% 4 Based on data from cost estimate from GA for the NGNP Pre-Conceptual Design Report 5 Based on historical LWR costs up to Based on historical LWR costs including reactors constructed after Three Mile Island

19 TEV-96 0/09/202 Page: 8 of 45 Table 8 provides additional estimates for the total indirect cost as percentage of the direct costs. The values were not used in the average for this estimate as the breakdown for the indirect costs did not match the level of detail desired for this analysis. However, these references provide validation for the calculated average indirect cost. Table 8. Total indirect cost validation. Total % WSRC-MS (DOE 2006) 55% IAEA Bulletin Vol. 20, No. (IAEA 978) 52% The following design costs were also added to the indirect costs outlined above: Table 9. Design costs ($ basis). Item Phase NGNP FOAK & NOAK Conceptual Design Preliminary Design Final Design R&D Costs Total, The NGNP design costs are referenced from the design costs presented in the NGNP Program Planning Bases for the Schedule and Cost Estimates (INL 200). Final design costs for the FOAK and NOAK plants are based on information provided by reactor design suppliers and have been adjusted for recent project development and assumed design maturation. 2.4 Project Contingency A project contingency of 20% was selected for the HTGR capital cost analysis for all project phases (INL 2007a). 2.5 Total Capital Investment The TCI was calculated by summing the preconstruction costs, direct costs, indirect costs, and project contingency described in the previous sections. These costs are outlined in Table 0 for the NGNP plant at all ROTs and power levels, Table for the FOAK single and four-pack plants at all ROTs and power levels, and Table 2 for the NOAK single and four-pack plants at all ROTs and power levels. In addition to the TCI the costs on a dollar-per-kwt basis are also presented. 7 Research and development (R&D), includes INL s R&D costs.

20 TEV-96 0/09/202 Page: 9 of 45 Table 0. TCI NGNP HTGR ($ basis). Power Modules Level Item ROT Preconstruction Costs Direct Costs No Power Cycle Direct Costs Brayton Cycle Direct Costs Rankine Cycle Indirect Costs No Power Cycle Indirect Costs Brayton Cycle Indirect Costs Rankine Cycle Contingency No Power Cycle Contingency Brayton Cycle Contingency Rankine Cycle TCI No Power Cycle $/kwt TCI Brayton Power Cycle $/kwt TCI Rankine Power Cycle $/kwt MWt 350 MWt Preconstruction Costs Direct Costs No Power Cycle Direct Costs Brayton Cycle Direct Costs Rankine Cycle Indirect Costs No Power Cycle Indirect Costs Brayton Cycle Indirect Costs Rankine Cycle Contingency No Power Cycle Contingency Brayton Cycle Contingency Rankine Cycle TCI No Power Cycle $/kwt TCI Brayton Power Cycle $/kwt TCI Rankine Power Cycle $/kwt

21 TEV-96 0/09/202 Page: 20 of 45 Table. TCI FOAK HTGR ($ basis). Power Modules 4 Level Item ROT Preconstruction Costs Direct Costs No Power Cycle Direct Costs Brayton Cycle Direct Costs Rankine Cycle Indirect Costs No Power Cycle Indirect Costs Brayton Cycle Indirect Costs Rankine Cycle Contingency No Power Cycle Contingency Brayton Cycle Contingency Rankine Cycle TCI No Power Cycle $/kwt TCI Brayton Power Cycle $/kwt TCI Rankine Power Cycle $/kwt MWt 350 MWt Preconstruction Costs Direct Costs No Power Cycle Direct Costs Brayton Cycle Direct Costs Rankine Cycle Indirect Costs No Power Cycle Indirect Costs Brayton Cycle Indirect Costs Rankine Cycle Contingency No Power Cycle Contingency Brayton Cycle Contingency Rankine Cycle TCI No Power Cycle $/kwt TCI Brayton Power Cycle $/kwt TCI Rankine Power Cycle $/kwt

22 TEV-96 0/09/202 Page: 2 of 45 Table 2. TCI NOAK HTGR ($ basis). Power Modules 4 Level Item ROT Preconstruction Costs Direct Costs No Power Cycle Direct Costs Brayton Cycle Direct Costs Rankine Cycle Indirect Costs No Power Cycle Indirect Costs Brayton Cycle Indirect Costs Rankine Cycle Contingency No Power Cycle Contingency Brayton Cycle Contingency Rankine Cycle TCI No Power Cycle $/kwt TCI Brayton Power Cycle $/kwt TCI Rankine Power Cycle $/kwt MWt 350 MWt Preconstruction Costs Direct Costs No Power Cycle Direct Costs Brayton Cycle Direct Costs Rankine Cycle Indirect Costs No Power Cycle Indirect Costs Brayton Cycle Indirect Costs Rankine Cycle Contingency No Power Cycle Contingency Brayton Cycle Contingency Rankine Cycle TCI No Power Cycle $/kwt TCI Brayton Power Cycle $/kwt TCI Rankine Power Cycle $/kwt

23 TEV-96 0/09/202 Page: 22 of Correlation Development for Direct Capital Costs Correlations were developed for the HTGR and power cycle costs based on the ROT, thermal rating, power cycle rating, number of modules, and project phase. These correlations were developed in order to scale the costs for project variations not included in this study. For example, these correlations would be used to estimate the cost of six HTGR modules at an ROT of 775C for an NOAK HTGR plant. Separate correlations are developed for the HTGR cost without power cycles (i.e. for heat production only), the Brayton cycle cost, and the Rankine cycle cost. The correlations presented are base direct costs, less the adders, which can be added to the correlations to account for the balance of equipment costs, indirect costs, preconstruction costs, and project contingency Correlations for the HTGR Cost, Less Power Cycle The correlation for the HTGR cost as a function of ROT is best fit using a linear step function. The following equation set is used: The above correlation provides the base cost for an NOAK single 600 MWt HTGR as a function of the ROT. This base cost is then adjusted to account for the number of reactors using an exponential correlation:. A similar adjustment can be made for the reactor thermal rating: 600. Thus, the overall correlation for the NOAK HTGR cost is as follows:. 600 Finally, multipliers for the project phases were determined to adjust the cost for FOAK and NGNP project phases:

24 TEV-96 0/09/202 Page: 23 of 45 Table 3 presents a comparison of the correlation results and the data for the HTGR costs less the power cycles. The costs predicted by the correlations have a percent error of 0% to 4.3%, when compared to the actual cost data. Table 3. Correlation results and comparison for HTGR costs, less power cycles ($ basis). Power Project Modules 4 Level Phase Item ROT Value NOAK Model Prediction % Error Value FOAK Model Prediction % Error Value NGNP Model Prediction % Error Value NOAK Model Prediction % Error Value FOAK Model Prediction % Error Value NGNP Model Prediction % Error MWt 350 MWt

25 TEV-96 0/09/202 Page: 24 of 45 Figure presents the HTGR cost correlations for the NOAK project phase. Figure. NOAK HTGR cost correlations, less power cycles Correlations for the Brayton Cycle Cost The correlation for the Brayton cycle cost as a function of ROT is best fit using a linear step function. The following equation set is used: The above correlation provides the base cost for an NOAK single 28 MWe Brayton cycle, which includes both the power conversion vessel and the turbo-machinery. This base cost is then adjusted to account for the number of cycles using an exponential correlation:. A similar adjustment can be made for the power cycle size. Note that the base power cycle size at 750 C for a 600 MWt HTGR is used for this correlation: 28.

26 TEV-96 0/09/202 Page: 25 of 45 Thus, the overall correlation for the NOAK Brayton cycle cost is as follows:. 28. Finally, multipliers for the project phases were determined to adjust the cost for FOAK and NGNP project phases: Table 4 presents a comparison of the correlation results and the data for the Brayton cycle costs. The costs predicted by the correlations have a percent error of 0% to 7.5%, when compared to the actual cost data. Figure 2 presents the Brayton cycle cost correlation for the NOAK project phase. Figure 2. NOAK Brayton cycle cost correlations.

27 TEV-96 0/09/202 Page: 26 of 45 Table 4. Correlation results and comparison for Brayton cycle costs ($ basis). Power Project Modules 4 Level Phase Item ROT Value NOAK Model Prediction % Error MWt (28 MWe at 750 C) 350 MWt (64 MWe at 750 C) FOAK NGNP NOAK FOAK NGNP Value Model Prediction % Error Value Model Prediction % Error Value Model Prediction % Error Value Model Prediction % Error Value Model Prediction % Error

28 TEV-96 0/09/202 Page: 27 of Correlations for the Rankine Cycle Cost The correlation for the Rankine cycle cost as a function of ROT is best fit using a linear function; however, a step function is not required for the Rankine cycle cost as the fabrication materials are consistent for all ROTs. The following equation is used: The correlation for the ROT provides the base cost for an NOAK single 267 MWe Rankine cycle. This base cost is then adjusted to account for the number of cycles using an exponential correlation: A similar adjustment can be made for the power cycle size. Note that the base power cycle size at 750 C for a 600 MWt HTGR is used for this correlation:. 267 Thus, the overall correlation for the NOAK Rankine cycle cost is as follows:. 267 Finally, multipliers for the project phases were determined to adjust the cost for FOAK and NGNP project phases: Table 5 presents a comparison of the correlation results and the data for the Rankine cycle costs. The costs predicted by the correlations have a percent error of 0% to 0.8%, when compared to the actual cost data.

29 TEV-96 0/09/202 Page: 28 of 45 Table 5. Correlation results and comparison for Rankine cycle costs ($ basis). Power Project Modules 4 Level Phase Item ROT Value NOAK Model Prediction % Error MWt (267 MWe at 750 C) 350 MWt (56 MWe at 750 C) FOAK NGNP NOAK FOAK NGNP Value Model Prediction % Error Value Model Prediction % Error Value Model Prediction % Error Value Model Prediction % Error Value Model Prediction % Error

30 TEV-96 0/09/202 Page: 29 of 45 Figure 3 presents the Rankine cycle cost correlation for the NOAK project phase. Figure 3. NOAK Rankine cycle cost correlations. 2.7 Capital Cost Results Comparisons In order to assess the accuracy of the capital cost model, results from the INL cost model were compared to reactor design supplier cost estimates. In order to provide a direct comparison, the cost model design costs (for the NGNP project phase) and project contingencies were adjusted to match the estimates provided by the reactor design suppliers. This allows a more accurate comparison of the project costs, as the design costs and contingencies vary widely between the reactor design suppliers. Furthermore, reactor design supplier costs were adjusted to exclude costs for hydrogen production facilities. The projected model cost is compared to the reactor design supplier average costs, along with the associated cost accuracy range of -30% to +50% for an AACE International class four estimate. The specifics of the design supplier estimates are withheld, as certain aspects of the costs may be considered business sensitive. Figure 4 and Figure 5 present two separate comparisons for a reactor plant with a thermal rating of approximately 600 MWt and a ROT greater than 850 C from separate reactor design suppliers. Both comparisons include costs for NGNP and NOAK project phases. These comparisons demonstrate that the cost model is within the range of the costs projected by the reactor design suppliers.

31 TEV-96 0/09/202 Page: 30 of 45 Figure 4. HTGR Model Cost Comparison Prismatic Block Design, ~600 MWt ROT 850 C. Figure 5. HTGR Model Cost Comparison Prismatic Block Design 2, ~600 MWt ROT 850 C. Figure 6 and Figure 7 present two separate comparisons for a reactor plant with a thermal rating less than 350 MWt and a ROT less than 750 C from separate reactor design suppliers. Only one of the comparisons includes costs for NGNP and NOAK project phases. Again, these comparisons demonstrate that the cost model is within the range of the costs projected by the reactor design suppliers.

32 TEV-96 0/09/202 Page: 3 of 45 Figure 6. HTGR Model Cost Comparison Prismatic Block Design 3, 350 MWt ROT 750 C. Figure 7. HTGR Model Cost Comparison Pebble Bed Design, 350 MWt ROT 750 C. 3. ESTIMATION OF Operating costs were evaluated for the HTGR for the NGNP, FOAK, and NOAK plants, for single and multiple module scenarios. Operating costs are assumed to include operations and maintenance (O&M) costs and refueling costs.

33 TEV-96 0/09/202 Page: 32 of O&M Costs O&M costs were estimated based on methodology presented for a study of advanced reactor technologies, specifically the study of O&M staffing and costs conducted by Dominion with advice from Entergy (Dominion 2004). O&M costs are assumed to include the following items: Staffing requirements, including expenses for overtime, benefits and retirement, bonuses and incentives, and payroll taxes Nuclear Regulatory Commission (NRC) fees Institute of Nuclear Power Operations (INPO) fees Nuclear Energy Institute (NEI) fees Insurance and taxes Material supplies, services, and upgrades Outage costs Administration and general cost overhead Staffing requirements were estimated based on the staff positions outlined in the Dominion study with input from Entergy. Staffing was estimated for single modules as well as estimates for an additional unit for multiple module scenarios. It was assumed that staffing levels would be the same for both the 600 MWt and 350 MWt power levels. Staffing assumes five shifts, three shifts active per day, one shift inactive, and one shift in training. It is assumed that staffing levels are independent of ROT, heat or power production, power cycle type, as well as the reactor phase, i.e. staffing levels are the same for the NGNP, FOAK, and NOAK project phases. Table 6 presents the staffing levels for the HTGR modules. SC indicates a position that is subcontracted if required, DP indicates a position that is duplicated by another staff member. The lower levels of staffing assumed for the HTGR when compared to current LWR operations take into account advanced system automation, passive reactor safety systems, and reductions in security due to partially burying the core. Table 6. Staffing levels by title. Position Units Single Unit Additional Unit Management Supervisory Vice President 0 Director O&M 0 Director Site Safety 0 Non-Supervisory Executive Assistant 0 Human Resources Generalist 0

Summary Decision Paper. Reference Modular HTGR Reactor Design Concept and. Plant Configuration for Initial Applications

Summary Decision Paper. Reference Modular HTGR Reactor Design Concept and. Plant Configuration for Initial Applications Summary Decision Paper Reference Modular HTGR Reactor Design Concept and Plant Configuration for Initial Applications This paper summarizes the considerations in the selection of the High Temperature Gas-cooled

More information

Preliminary Cost Information for Nuclear Components. Lee Cadwallader Fusion Safety Program ARIES meeting Gaithersburg, MD, July 27-28, 2011

Preliminary Cost Information for Nuclear Components. Lee Cadwallader Fusion Safety Program ARIES meeting Gaithersburg, MD, July 27-28, 2011 Preliminary Cost Information for Nuclear Components Lee Cadwallader Fusion Safety Program ARIES meeting Gaithersburg, MD, July 27-28, 2011 Nuclear versus Non-nuclear component costs for mechanical parts

More information

NGNP Licensing Approach & Status

NGNP Licensing Approach & Status www.inl.gov NGNP Licensing Approach & Status IAEA Course on High Temperature Gas Cooled Reactor Technology Tsinghua University, Beijing October 22-26, 2012 Presented by: Javier Ortensi Based on material

More information

The Next Generation Nuclear Plant (NGNP)

The Next Generation Nuclear Plant (NGNP) The Next Generation Nuclear Plant (NGNP) Dr. David Petti Laboratory Fellow Director VHTR Technology Development Office High Temperature, Gas-Cooled Reactor Experience HTGR PROTOTYPE PLANTS DEMONSTRATION

More information

GT-MHR OVERVIEW. Presented to IEEE Subcommittee on Qualification

GT-MHR OVERVIEW. Presented to IEEE Subcommittee on Qualification GT-MHR OVERVIEW Presented to IEEE Subcommittee on Qualification Arkal Shenoy, Ph.D Director, Modular Helium Reactors General Atomics, San Diego April 2005 Shenoy@gat.com GT-MHR/LWR COMPARISON Item GT-MHR

More information

Status of Development, ANS Standard 53.1, Nuclear Safety Criteria for the Design of Modular Helium Cooled Reactor Plants

Status of Development, ANS Standard 53.1, Nuclear Safety Criteria for the Design of Modular Helium Cooled Reactor Plants Status of Development, ANS Standard 53.1, Nuclear Safety Criteria for the Design of Modular Helium Cooled Reactor Plants M. LaBar General Atomics 3550 General Atomics Court San Diego, CA 92121-1122 Abstract

More information

Economic Analysis of the Modular Pebble Bed Reactor

Economic Analysis of the Modular Pebble Bed Reactor Pebble Bed Reactor Project MIT Nuclear Engineering Department Economic Analysis of the Modular Pebble Bed Reactor These slides present the conclusions of a preliminary study based d on existing cost data

More information

Overview and Status of SMRs Being Developed in the United States

Overview and Status of SMRs Being Developed in the United States Overview and Status of SMRs Being Developed in the United States Daniel Ingersoll Oak Ridge National Laboratory ingersolldt@ornl.gov October 10-14, 2011 INPRO Dialog Forum on Common User Considerations

More information

Small Modular Reactor Materials R&D Program Materials Coordination Webinar

Small Modular Reactor Materials R&D Program Materials Coordination Webinar Small Modular Reactor Materials R&D Program Materials Coordination Webinar William Corwin Office of Advanced Reactor Technologies U.S. Department of Energy August 2012 SMRs Are Strong Contenders to Augment

More information

Nuclear Energy Market Overview Tony Robinson AREVA NP Senior Vice President, Customer Accounts & Government Affairs May 12, 2017

Nuclear Energy Market Overview Tony Robinson AREVA NP Senior Vice President, Customer Accounts & Government Affairs May 12, 2017 Nuclear Energy Market Overview Tony Robinson Senior Vice President, Customer Accounts & Government Affairs May 12, 2017 Nuclear Performance in the U.S. Nuclear energy provides reliable, efficient, and

More information

NRC Licensing Process for Review of SMRs

NRC Licensing Process for Review of SMRs NRC Licensing Process for Review of SMRs Small Modular Reactors for Nuclear Power LAS/ANS Symposium On Behalf of Commissioner William D. Magwood, IV Commissioner of the U.S. Nuclear Regulatory Commission

More information

NRC s Advanced Reactor Program. Edward Baker Advanced Reactor Program Office of New Reactors

NRC s Advanced Reactor Program. Edward Baker Advanced Reactor Program Office of New Reactors NRC s Advanced Reactor Program Edward Baker Advanced Reactor Program Office of New Reactors TOPICS Licensing Process Commission Policy Statement on Advanced Reactors Vendors requesting early interaction

More information

NEW POWER REACTOR DESIGNS

NEW POWER REACTOR DESIGNS NUCLEAR ENERGY RENAISSANCE: ADDRESSING THE CHALLENGES OF CLIMATE CHANGE AND SUSTAINABILITY NCSR DEMOKRITOS Athens May 8, 2008 NEW POWER REACTOR DESIGNS Dimitrios Cokinos Brookhaven National Laboratory

More information

Current Activities on the 4S Reactor Deployment

Current Activities on the 4S Reactor Deployment PSN Number: PSN-2010-0586 Document Number: AFT-2010-000134 rev.000(1) Current Activities on the 4S Reactor Deployment The 4th Annual Asia-Pacific Nuclear Energy Forum on Small and Medium Reactors: Benefits

More information

MIT/INEEL Modular Pebble Bed Reactor. Andrew C. Kadak Massachusetts Institute of Technology

MIT/INEEL Modular Pebble Bed Reactor. Andrew C. Kadak Massachusetts Institute of Technology MIT/INEEL Modular Pebble Bed Reactor Andrew C. Kadak Massachusetts Institute of Technology March 22, 2000 Observations No New Construction of Nuclear Plants for Many Years Current Generation of Plants

More information

NuScale SMR Technology

NuScale SMR Technology NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by

More information

ANTARES Application for Cogeneration. Oil Recovery from Bitumen and Upgrading

ANTARES Application for Cogeneration. Oil Recovery from Bitumen and Upgrading ANTARES Application for Cogeneration Oil Recovery from Bitumen and Upgrading Michel Lecomte Houria Younsi (ENSEM) Jérome Gosset (ENSMP) ENC Conference Versailles 11-14 December 2005 1 Presentation Outline

More information

3/20/2011. Key technical characteristics

3/20/2011. Key technical characteristics Small reactor technologies of SC ROSATOM 300 According to IAEA classification small-sized reactors are reactors under 300 MWe Electrical output, MWe 100 10 SVBR-10 (12 MWe) SVBR-100 (101 MWe) KLT-40S (38,5

More information

Design Features, Economics and Licensing of the 4S Reactor

Design Features, Economics and Licensing of the 4S Reactor PSN Number: PSN-2010-0577 Document Number: AFT-2010-000133 rev.000(2) Design Features, Economics and Licensing of the 4S Reactor ANS Annual Meeting June 13 17, 2010 San Diego, California Toshiba Corporation:

More information

REQUIREMENTS OF SMR TECHNOLOGY DEVELOPMENT & DEPLOYMENT IN THE UK

REQUIREMENTS OF SMR TECHNOLOGY DEVELOPMENT & DEPLOYMENT IN THE UK REQUIREMENTS OF SMR TECHNOLOGY DEVELOPMENT & DEPLOYMENT IN THE UK DAN MATHERS HEAD OF TECHNICAL SMR AND EMERGING NUCLEAR POLICY TEAM UK energy mix 2 Planned nuclear generation in UK Capacity Megawatts

More information

Advanced Reactor Technology

Advanced Reactor Technology Advanced Reactor Technology Robert N. Hill Nuclear Engineering Division Argonne National Laboratory 2012 Nanonuclear Workshop Gaithersburg, Maryland June 6, 2012 Outline Advanced Reactor Trends Small Modular

More information

Joint ICTP-IAEA Workshop on Nuclear Reaction Data for Advanced Reactor Technologies May 2008

Joint ICTP-IAEA Workshop on Nuclear Reaction Data for Advanced Reactor Technologies May 2008 1944-19 Joint ICTP-IAEA Workshop on Nuclear Reaction Data for Advanced Reactor Technologies 19-30 May 2008 Gas-Cooled Reactors Technology Options, Operating Research Reactors and Demonstration Plant Project

More information

Nuclear Innovation in Action Small Modular Reactors (SMRs)

Nuclear Innovation in Action Small Modular Reactors (SMRs) Nuclear Innovation in Action Small Modular Reactors (SMRs) David Shropshire Planning and Economic Studies Connecting Roadmaps for Innovative Nuclear Energy to the NDC Timeline (COP23 Side IETA Pavilion)

More information

HTR-PM Project Status and Test Program

HTR-PM Project Status and Test Program IAEA TWG-GCR-22 HTR-PM Project Status and Test Program SUN Yuliang Deputy Director, INET/ Tsinghua University March 28 April 1, 2011 1 Project organization Government INET R&D, general design, design of

More information

Development of the Next Generation of Nuclear Energy Plants

Development of the Next Generation of Nuclear Energy Plants Development of the Next Generation of Nuclear Energy Plants United States Energy Association Washington, DC Phil Hildebrandt Special Assistant to the Laboratory Director Idaho National Laboratory February

More information

Chemical Engineering 412

Chemical Engineering 412 Chemical Engineering 412 Introductory Nuclear Engineering Lecture 20 Nuclear Power Plants II Nuclear Power Plants: Gen IV Reactors Spiritual Thought 2 Typical PWR Specs Reactor Core Fuel Assembly Steam

More information

HTGR Brayton Cycle Technology and Operations

HTGR Brayton Cycle Technology and Operations MIT Workshop on New Cross-cutting Technologies for Nuclear Power Plants, Cambridge, USA, January 30-3, 207 HTGR Brayton Cycle Technology and Operations Xing L. Yan HTGR Hydrogen and Heat Application Research

More information

Department of Energy Experience with Small Modular Reactors

Department of Energy Experience with Small Modular Reactors Department of Energy Experience with Small Modular Reactors The Nuclear Option: Is Small Scale Nuclear Energy an Option for Alaska? - Exploratory Workshop Craig Welling Office of Nuclear Energy U.S. Department

More information

Technologies of HTR-PM Plant and its economic potential

Technologies of HTR-PM Plant and its economic potential IAEA Technical Meeting on the Economic Analysis of HTGRs and SMRs 25-28 August 2015, Vienna, Austria Technologies of HTR-PM Plant and its economic potential Prof. Dr. Yujie Dong INET/Tsinghua University

More information

INL/EXT Key Design Requirements for the High Temperature Gascooled Reactor Nuclear Heat Supply System

INL/EXT Key Design Requirements for the High Temperature Gascooled Reactor Nuclear Heat Supply System INL/EXT-10-19887 Key Design Requirements for the High Temperature Gascooled Reactor Nuclear Heat Supply System September 2010 DISCLAIMER This information was prepared as an account of work sponsored by

More information

Codes and Standards Needs for PBMR

Codes and Standards Needs for PBMR ASME NUCLEAR CODES AND STANDARDS South Africa, October 7-8, 2008 Codes and Standards Needs for PBMR Neil Broom Code Specialist PBMR What is the PBMR? The Pebble Bed Modular Reactor is: A graphite-moderated,

More information

Development and Global Deployment of ABWR

Development and Global Deployment of ABWR Document No. G3-815 Rev.0 Export Control No. PSN-2009-1032 IAEA International Conference on Opportunities and Challenges for Water Cooled Reactors in the 21 st Century Vienna, Austria Development and Global

More information

The Next Generation Nuclear Plant Project. The Case for Utility Interest

The Next Generation Nuclear Plant Project. The Case for Utility Interest The Next Generation Nuclear Plant Project The Case for Utility Interest 1016759 The Next Generation Nuclear Plant Project The Case for Utility Interest 1016759 Technical Update, December, 2008 EPRI Project

More information

The Gen IV Modular Helium Reactor

The Gen IV Modular Helium Reactor The Gen IV Modular Helium Reactor and its Potential for Small and Medium Grids presented to Society of Nuclear Engineers of Croatia 26 January 2007 by David E. Baldwin, Ph.D. Sustainable Energy has Become

More information

Philip Moor December, 2010 Anchorage Alaska

Philip Moor December, 2010 Anchorage Alaska Philip Moor December, 2010 Anchorage Alaska SMR s potential for changing social and energy supply paradigms is compelling Jobs US goods and services National Security and energy policy Climate change benefits

More information

AREVA HTR Concept for Near-Term Deployment

AREVA HTR Concept for Near-Term Deployment AREVA HTR Concept for Near-Term Deployment L. J. Lommers, F. Shahrokhi 1, J. A. Mayer III 2, F. H. Southworth 1 AREVA Inc. 2101 Horn Rapids Road; Richland, WA 99354 USA phone: +1-509-375-8130, lewis.lommers@areva.com

More information

SMR: Opportunities and Challenges. Dr. Jaejoo HA Head, Division of Nuclear Development, OECD/NEA

SMR: Opportunities and Challenges. Dr. Jaejoo HA Head, Division of Nuclear Development, OECD/NEA SMR: Opportunities and Challenges Dr. Jaejoo HA Head, Division of Nuclear Development, OECD/NEA jaejoo.ha@oecd.org SMR 2016, London, 8-9 June 2016 Previous OECD/NEA work on SMRs (1991) Small and Medium

More information

A NUCLEAR RENAISSANCE

A NUCLEAR RENAISSANCE A NUCLEAR RENAISSANCE Ping Wan The Tenth Nuclear Utility Meteorological Data Users Group Meeting June 2005 2 Concerns in Development of Nuclear Power High front-end project development and plant capital

More information

Very High Temperature Reactor

Very High Temperature Reactor Very High Temperature Reactor LI Fu GIF VHTR SSC Chair INET, Tsinghua University, China GIF Symposium San Diego November 15-16, 2012 Outline 1. Original VHTR Features 2. Key VHTR Development Targets 3.

More information

BNFL/Westinghouse s Perspective on the Nuclear Hydrogen Economy

BNFL/Westinghouse s Perspective on the Nuclear Hydrogen Economy BNFL/Westinghouse s Perspective on the Nuclear Hydrogen Economy Dr PJA Howarth Head of Group Science Strategy BNFL/Westinghouse is a large, international supplier of products and services for nuclear industry

More information

High Temperature Gas-Cooled Reactors Now More Than Ever!

High Temperature Gas-Cooled Reactors Now More Than Ever! High Temperature Gas-Cooled Reactors Now More Than Ever! Dr. Finis SOUTHWORTH Chief Technology Officer AREVA Inc. On behalf of the NGNP Industrial Alliance, LLC Washington DC Section ANS Rockville, MD

More information

Modular Helium Reactor (MHR) for Oil Sands Extraction

Modular Helium Reactor (MHR) for Oil Sands Extraction Modular Helium Reactor (MHR) for Oil Sands Extraction Alexander Telengator and Arkal Shenoy General Atomics 30th Annual CNS Conference 1 WORLD ENERGY COMPOSITION Fossil fuels provide ~ 85% of World energy

More information

ADVANCED REACTOR TECHNOLOGY. Everett Redmond, Ph.D. Nuclear Energy Institute. January 9, 2018

ADVANCED REACTOR TECHNOLOGY. Everett Redmond, Ph.D. Nuclear Energy Institute. January 9, 2018 Everett Redmond, Ph.D. Nuclear Energy Institute ADVANCED REACTOR January 9, 2018 TECHNOLOGY Generation IV International Forum (GIF) website https://www.gen-4.org/. September 2015 WHAT IS AN ADVANCED REACTOR?

More information

Module 12 Generation IV Nuclear Power Plants. Atominstitute of the Austrian Universities Stadionallee 2, 1020 Vienna, Austria

Module 12 Generation IV Nuclear Power Plants. Atominstitute of the Austrian Universities Stadionallee 2, 1020 Vienna, Austria Module 12 Generation IV Nuclear Power Plants Prof.Dr. H. Böck Atominstitute of the Austrian Universities Stadionallee 2, 1020 Vienna, Austria boeck@ati.ac.at Generation IV Participants Evolution of Nuclear

More information

ANTARES The AREVA HTR-VHTR Design PL A N TS

ANTARES The AREVA HTR-VHTR Design PL A N TS PL A N TS ANTARES The AREVA HTR-VHTR Design The world leader in nuclear power plant design and construction powers the development of a new generation of nuclear plant German Test facility for HTR Materials

More information

VI International Forum ATOMEXPO 2014

VI International Forum ATOMEXPO 2014 VI International Forum ATOMEXPO 2014 Moscow, 9 th to 11 th June, 2014 Gostiny Dvor Round Table: Planning and Optimization of the NPP Generated Power Cost at the Design and Construction Stages NPP Capital

More information

Highlights of DOE Nuclear Reactor Technologies Program

Highlights of DOE Nuclear Reactor Technologies Program Highlights of DOE Nuclear Reactor Technologies Program SFANS Meeting Paris France Dr. John E. Kelly Deputy Assistant Secretary for Nuclear Reactor Technologies U.S. Department of Energy 23 September 2015

More information

New Builds Panel Discussion Moderated by: Jay Wileman

New Builds Panel Discussion Moderated by: Jay Wileman New Builds Panel Discussion Moderated by: Jay Wileman Senior Vice President, Nuclear Plant Projects and Chief Operating Officer, GE Hitachi Nuclear Energy February 4, 2014 Marilyn Kray Vice President Exelon

More information

Concept and technology status of HTR for industrial nuclear cogeneration

Concept and technology status of HTR for industrial nuclear cogeneration Concept and technology status of HTR for industrial nuclear cogeneration D. Hittner AREVA NP Process heat needs from industry Steam networks In situ heating HTR, GFR 800 C VHTR > 800 C MSR 600 C SFR, LFR,

More information

Modular Helium-cooled Reactor

Modular Helium-cooled Reactor Modular Helium-cooled Reactor The role of the GTMHR in GNEP E. Michael Campbell Francesco Venneri General Atomics April 2007 SEMA Conference 1 OUTLINE Motivation High Temperature gas reactors MHR as burner

More information

Fast and High Temperature Reactors for Improved Thermal Efficiency and Radioactive Waste Management

Fast and High Temperature Reactors for Improved Thermal Efficiency and Radioactive Waste Management What s New in Power Reactor Technologies, Cogeneration and the Fuel Cycle Back End? A Side Event in the 58th General Conference, 24 Sept 2014 Fast and High Temperature Reactors for Improved Thermal Efficiency

More information

Nuclear-Power Ammonia Production

Nuclear-Power Ammonia Production Nuclear-Power Ammonia Production William L. Kubic, Jr. Process Engineering, Modeling,and Analysis Group, New Mexico October 9, 2006 Why Nuclear-Powered Ammonia Production? Many in the nuclear community

More information

HT 3 R. Building For The Future On 50 Years of Nuclear Experience

HT 3 R. Building For The Future On 50 Years of Nuclear Experience HT 3 R Building For The Future On 50 Years of Nuclear Experience GENERAL ATOMICS TECHNOLOGIES CORPORATION Founded 1955 Privately Owned Since 1986 Operations - US (CA, CO, DC, HI, MS, NJ, NM, OK, IA, TX,

More information

Advanced Nuclear Technology

Advanced Nuclear Technology Advanced Nuclear Technology Program Description Program Overview New nuclear power plants incorporating advanced light water reactor (ALWR) technology must overcome a number of regulatory, economic, technical,

More information

Future of Small Modular Reactors Roundtable

Future of Small Modular Reactors Roundtable Future of Small Modular Reactors Roundtable Small Modular Reactors Roundtable Participants Why Are We Here? Knowledge exchange on Small Modular Reactors between Utilities (demand side) Vendors (supply

More information

INTRODUCTION TO SMR S

INTRODUCTION TO SMR S 1 INTRODUCTION TO SMR S Ferry Roelofs 20 April 2018 EU DuC = N 2 CONTENTS 1. What is an SMR? 2. Why SMR s? 3. Which SMR s? WHAT IS AN SMR? 3 4 WHAT IS AN SMR? DEFINITION: IAEA IAEA Small to Medium sized

More information

SASOR Canada Ltd. Tetra Tech Inc. 4S reactor applications - Economic case studies. May 2009

SASOR Canada Ltd. Tetra Tech Inc. 4S reactor applications - Economic case studies. May 2009 SASOR Canada Ltd Tetra Tech Inc. 4S reactor applications - Economic case studies May 2009 Agenda Roles of Tetra Tech and SASOR Canada Why the 4S Reactor and not others Size Production and Cost Environmental

More information

Fast Reactor Fuel Cycle Cost Estimates for Advanced Fuel Cycle Studies

Fast Reactor Fuel Cycle Cost Estimates for Advanced Fuel Cycle Studies Fast Reactor Fuel Cycle Cost Estimates for Advanced Fuel Cycle Studies Technical Meeting on Fast Reactors and Related Fuel Cycle Facilities with Improved Economic Characteristics IAEA Headquarters, Vienna,

More information

Sargent & Lundy LLC April 8, 2014

Sargent & Lundy LLC April 8, 2014 Farid M. Berry Vice President & Project Director Sargent & Lundy LLC April 8, 2014 Role of the OWNER S ENGINEER Technical Meeting on Becoming a Knowledgeable Customer Obninsk and Novovoronezh, Russian

More information

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 Tim Beville Office of Nuclear Energy U.S. Department of Energy Administration

More information

Status of Advanced Reactor Development and Deployment. Global Nexus Initiative Workshop

Status of Advanced Reactor Development and Deployment. Global Nexus Initiative Workshop Status of Advanced Reactor Development and Deployment Global Nexus Initiative Workshop Gary T. Mays, Group Leader Advanced Reactor Systems & Safety Reactor and Nuclear Systems Division February 23, 2016

More information

VHTR System Prof. Dr. LI Fu

VHTR System Prof. Dr. LI Fu VHTR System Prof. Dr. LI Fu GIF VHTR SSC INET, Tsinghua University, China GIF Symposium, Chiba, Japan May 19, 2015 Outlines What s VHTR? How about VHTR? What are main R&D topics? How to collaborate in

More information

Advanced High Temperature Reactor Project PBMR relaunch

Advanced High Temperature Reactor Project PBMR relaunch Advanced High Temperature Reactor Project PBMR relaunch D.R. Nicholls Chief Nuclear Officer, Eskom Africa Utility Week, CTICC May 2017 Potential for Pebble Bed Modular Reactor - PBMR PBMR was based on

More information

Small Reactors R&D in China. ZHENG Mingguang Ph D Presented on the meeting of TWG-LWR June 18 th -20 th 2013 IAEA, Vienna

Small Reactors R&D in China. ZHENG Mingguang Ph D Presented on the meeting of TWG-LWR June 18 th -20 th 2013 IAEA, Vienna Small Reactors R&D in China ZHENG Mingguang Ph D Presented on the meeting of TWG-LWR June 18 th -20 th 2013 IAEA, Vienna CONTENT 1 Introduction of SMR 2 CAP150 developed by SNERDI/SNPTC 3 CAP FNPP developed

More information

Status of PBMR Process Heat Plant Project

Status of PBMR Process Heat Plant Project Status of PBMR Process Heat Plant Project Presented by Mr. Willem Kriel - PBMR (Pty) Ltd. -1- Expert Opinions The South African PBMR technology will become the world's first successful commercial Generation

More information

EPRI Utility Requirement Document

EPRI Utility Requirement Document EPRI Utility Requirement Document 11 February 2015 Sang-Baik KIM Analyst, NEA NDD Overview of URD Background and Objectives - Purpose of the URD is to present a clear, comprehensive set of design requirements

More information

AN INTRODUCTION TO SMALL MODULAR REACTORS (SMRs)

AN INTRODUCTION TO SMALL MODULAR REACTORS (SMRs) AN INTRODUCTION TO SMALL MODULAR REACTORS (SMRs) February 2013 Tony Irwin Technical Director SMR Nuclear Technology Pty Ltd 1 AN INTRODUCTION TO SMALL MODULAR REACTORS (SMRs) Background Nuclear power plants

More information

Nuclear Application in Asia

Nuclear Application in Asia The 32 nd IAEE International Conference June 21-24,2009 Energy,Economy, Environment The Global View Nuclear Application in Asia Tuesday, JUNE 23,2009 Makoto Takada Senior Coordinator, Nuclear energy Group

More information

Nuclear Energy in the UK and the Role of Advanced Nuclear Technology

Nuclear Energy in the UK and the Role of Advanced Nuclear Technology Nuclear Energy in the UK and the Role of Advanced Nuclear Technology Dr Fiona Rayment Executive Director, NIRO GIF, October 2018, Paris, France BEIS - Delivering against the Climate Change Act The UK Climate

More information

Reactor Technology and Cogeneration for a Cleaner Environment

Reactor Technology and Cogeneration for a Cleaner Environment Reactor Technology and Cogeneration for a Cleaner Environment I. Khamis Head, Non-electric Applications Unit Nuclear Power Technology Development Section Department Nuclear Energy Content Reactor technology

More information

Government and Industry Roles in Commercialization of Nuclear Power Lessons from the First Round

Government and Industry Roles in Commercialization of Nuclear Power Lessons from the First Round Government and Industry Roles in Commercialization of Nuclear Power Lessons from the First Round Andrew Sowder, Technical Executive Advanced Nuclear Technology 4th Gen IV International Forum Symposium

More information

Pre-Conceptual Hydrogen Production Modular Helium Reactor Designs. IAEA International Conference on Non-Electric Applications of Nuclear Energy

Pre-Conceptual Hydrogen Production Modular Helium Reactor Designs. IAEA International Conference on Non-Electric Applications of Nuclear Energy Pre-Conceptual Hydrogen Production Modular Helium Reactor Designs Matt Richards, Arkal Shenoy, and Mike Campbell General Atomics IAEA International Conference on Non-Electric Applications of Nuclear Energy

More information

Very-High-Temperature Reactor System

Very-High-Temperature Reactor System Atomic Energy Society of Japan Journal of NUCLEAR SCIENCE and TECHNOLOGY (JNST) Very-High-Temperature Reactor System Ing. S. BOUČEK 1, Ing. R. VESECKÝ 2 1 Faculty of Electrical Engineering, Czech Technical

More information

NuScale Plant Market Competitiveness & Financeability

NuScale Plant Market Competitiveness & Financeability NuScale Plant Market Competitiveness & Financeability Jay Surina Chief Financial Officer NuScale Exposition August 20-21, 2015 TM SMR Market Potential UK NNL* calculated the potential SMR market to be

More information

Overview of Small Modular Reactor Research at ORNL

Overview of Small Modular Reactor Research at ORNL Overview of Small Modular Reactor Research at ORNL INMM Central Region Chapter Fall Training Event Gary Mays, Group Leader Advanced Reactor Systems & Safety Reactor and Nuclear Systems Division Oak Ridge

More information

Nuclear Energy for Remote Applications

Nuclear Energy for Remote Applications Nuclear Energy for Remote Applications 23 October, 2014 Michael Kuca (University of Alaska) Vishal Patel (Texas A&M) Alana Vilagi (University of Alaska) 1 Objectives Consider GenIII+/GenIV nuclear power

More information

Introduction to Generation IV Nuclear Energy Systems

Introduction to Generation IV Nuclear Energy Systems Introduction to Generation IV Nuclear Energy Systems Dr. Ralph Bennett, Technical Director, Generation IV International Forum, and Director, International and Regional Partnerships, Idaho National Laboratory

More information

Materials Aging Management Programs at

Materials Aging Management Programs at Materials Aging Management Programs at Nuclear Power Plants in the United States Timothy J. Griesbach Structural Integrity Associates IAEA 2 nd International Symposium on Nuclear Power Plant Life Mgmt.

More information

HTR reactors within Polish strategy of nuclear energy development Cooperation with Japan

HTR reactors within Polish strategy of nuclear energy development Cooperation with Japan HTR reactors within Polish strategy of nuclear energy development Cooperation with Japan Taiju SHIBATA Senior Principal Researcher Group Leader, International Joint Research Group HTGR Hydrogen and Heat

More information

Workshop on PR&PP Evaluation Methodology for Gen IV Nuclear Energy Systems. Tokyo, Japan 22 February, Presented at

Workshop on PR&PP Evaluation Methodology for Gen IV Nuclear Energy Systems. Tokyo, Japan 22 February, Presented at PR&PP Collaborative Study with GIF System Steering Committees A Compilation of Design Information and Crosscutting Issues Related to PR&PP Characterization Presented at Workshop on PR&PP Evaluation Methodology

More information

2/24/2012. Generation mpower LLC. Major Complexity. Design & Manufacturing Complexities in SMR Technology

2/24/2012. Generation mpower LLC. Major Complexity. Design & Manufacturing Complexities in SMR Technology 2/2/2012 Design & Manufacturing Complexities in SMR Technology Regulatory Information Conference March 1, 2012 Ali Azad President & CEO Generation mpower LLC Generation mpower LLC Formal alliance between

More information

PERSPECTIVE OF HTGR AND ITS COMMERCIAL DEVELOPMENT

PERSPECTIVE OF HTGR AND ITS COMMERCIAL DEVELOPMENT PERSPECTIVE OF HTGR AND ITS COMMERCIAL DEVELOPMENT H. SEKIMOTO Japan Atomic Industrial Forum (JAIF), Tokyo Institute of Technology (TIT), Tokyo, Japan S. SHIOZAWA Japan Atomic Industrial Forum (JAIF),

More information

Modularity Approach of the Modular Pebble Bed Reactor (MPBR)

Modularity Approach of the Modular Pebble Bed Reactor (MPBR) Modularity Approach of the Modular Pebble Bed Reactor () Marc Berte Professor Andrew Kadak Massachusetts Institute of Technology Nuclear Engineering Department Nuclear Energy Research Initiative Grant

More information

FBNR Letter FIXED BED NUCLEAR REACTOR FBNR

FBNR Letter FIXED BED NUCLEAR REACTOR FBNR FBNR Letter FIXED BED NUCLEAR REACTOR FBNR http://www.rcgg.ufrgs.br/fbnr.htm Farhang.Sefidvash@ufrgs.br Dear coworkers and potential coworkers around the world, As number of coworkers is increasing, we

More information

NuScale Small Modular Reactors:

NuScale Small Modular Reactors: PNWER Energy Working Group July 25, 2017 NuScale Small Modular Reactors: Advanced, Scalable, Flexible, Economic Charles Marcinkiewicz Director, Marketing NuScale Power, LLC NuScale Nonproprietary Copyright

More information

Safeguards and Security by Design Support for the NGNP Project

Safeguards and Security by Design Support for the NGNP Project Safeguards and Security by Design Support for the NGNP Project Trond Bjornard, PhD ESARDA/INMM Joint Workshop on "Future Directions For Nuclear Safeguards and Verification" Aix-en-Provence, France October

More information

Generation IV Gas-cooled Reactor System Concepts

Generation IV Gas-cooled Reactor System Concepts Generation IV Gas-cooled Reactor System Concepts Technical Working Group 2 -- Gas Cooled Reactor Systems Generation IV Roadmap Session ANS Winter Meeting Reno, NV November 13, 2001 1 People Involved in

More information

Small Modular Reactors & waste management issues

Small Modular Reactors & waste management issues Small Modular Reactors & waste management issues 8 th May 2014, Bucharest International Framework For Nuclear Energy Cooperation Infrastructure development working group meeting Dan Mathers Business Leader

More information

USE OF THE MODULAR HELIUM REACTOR FOR HYDROGEN PRODUCTION

USE OF THE MODULAR HELIUM REACTOR FOR HYDROGEN PRODUCTION G A-A24428 USE OF THE MODULAR HELIUM REACTOR FOR HYDROGEN PRODUCTION by K.R. SCHULTZ r c SEPTEMBER 2003 This report was prepared as an account of work sponsored by an agency of the United States Government.

More information

A STUDY ON THE STANDARD SYSTEM FOR HTGR POWER PLANTS

A STUDY ON THE STANDARD SYSTEM FOR HTGR POWER PLANTS SMiRT-23, Paper ID 636 A STUDY ON THE STANDARD SYSTEM FOR HTGR POWER PLANTS ABSTRACT Lihong Zhang *, Fu Li, Yujie Dong, and Jingyuan Qu Institute Nuclear and New Energy Technology Collaborative Innovation

More information

Current Status and Future Challenges of Innovative Reactors Development in Japan

Current Status and Future Challenges of Innovative Reactors Development in Japan Innovation for Cool Earth Forum 2017, Tokyo, Japan, October 4-5, 2017 Current Status and Future Challenges of Innovative Reactors Development in Japan 5 October, 2017 Yutaka Sagayama Assistant to the President

More information

GE Hitachi Nuclear Opportunities for Localization in RSA

GE Hitachi Nuclear Opportunities for Localization in RSA GE Hitachi Nuclear Opportunities for Localization in RSA October 2012 GE Hitachi Nuclear Alliance Wilmington, NC USA Tokyo, Japan Wilmington, NC USA Wilmington, NC Yokosuka, Japan Peterborough, ON Canada

More information

LARGE-SCALE PRODUCTION OF HYDROGEN BY NUCLEAR ENERGY FOR THE HYDROGEN ECONOMY

LARGE-SCALE PRODUCTION OF HYDROGEN BY NUCLEAR ENERGY FOR THE HYDROGEN ECONOMY GA A24265 LARGE-SCALE PRODUCTION OF HYDROGEN BY NUCLEAR ENERGY FOR THE HYDROGEN ECONOMY by K.R. SCHULTZ, L.C. BROWN, G.E. BESENBRUCH, and C.J. HAMILTON FEBRUARY 2003 DISCLAIMER This report was prepared

More information

X-energy and the Xe-100

X-energy and the Xe-100 X-energy and the Xe-100 N I C/ETEC Nuclear Supplier Workshop Dr. Pete Pa ppano, Vice President Fuel Production September 7, 2017 Reimagining Nuclear Energy X-energy is reimagining nuclear s role in solving

More information

Fuel Reliability (QA)

Fuel Reliability (QA) Program Description Fuel Reliability (QA) Program Overview Fuel failures and other fuel-related issues can have significant operational impacts on nuclear power plants. Failures, for example, can cost

More information

FOURTH GENERATION REACTOR CONCEPTS

FOURTH GENERATION REACTOR CONCEPTS Chapter 6 FOURTH GENERATION REACTOR CONCEPTS M. Ragheb 3/11/2014 6.1 INTRODUCTION Nuclear power plants across the globe are producing about 16 percent of the world s electricity. With the depletion of

More information

Safety Aspects of SMRs: A PRA Perspective

Safety Aspects of SMRs: A PRA Perspective Safety Aspects of SMRs: A PRA Perspective Mohammad Modarres Minta Martin Professor of Engineering Director, Reliability Engineering Program Department of Mechanical Engineering University of Maryland,

More information

Small Modular Reactors

Small Modular Reactors Small Modular Reactors Nuclear Institute Joint Nuclear Energy CDT Event, York University, 24 May 2017 Kevin Hesketh Senior Research Fellow Scope To highlight generic design issues from SMRs But not to

More information

Small Modular Reactors (SMRs) What are they? Why are they cool?

Small Modular Reactors (SMRs) What are they? Why are they cool? Westinghouse Non-Proprietary Class 3 Small Modular Reactors (SMRs) What are they? Why are they cool? Alex Harkness SMR Design Lead/Fellow Engineer ANS Meeting Rocky Hill, CT January 19, 2012 1 Westinghouse

More information

Revival of Nuclear Energy (Part 3)

Revival of Nuclear Energy (Part 3) Revival of Nuclear Energy (Part 3) Jasmina Vujic Associate Professor Department of Nuclear Engineering University of California, Berkeley May 16, 2001 Revival of Nuclear Energy in USA? Just a few years

More information