1. Introduction to the Project

Size: px
Start display at page:

Download "1. Introduction to the Project"

Transcription

1 1

2 TABLE OF CONTENTS 1. Introduction to the Project Project justication Project location Project description Planning approval process Public participation process (PPP) Key environmental issues Key social issues Resettlement and livelihoods Terms of reference Conclusion

3 1. Introduction to the Project The Administração Regional de Águas do Sul (ARA-Sul) proposes to implement the Building Climate Resilience in the Limpopo Basin in Mozambique project, which will be funded by the African Development Bank. This Project aims to improve climate change resilience of communities, infrastructure and livelihoods in the lower Limpopo River basin by better management of water resources during flood and dry conditions. The Project combines flood mitigation, irrigation development and power production, which address important local, regional and national objectives in reducing flood risks, contributing to food security and increasing energy availability within the country. A major Project component is to develop a dam and reservoir on the Limpopo River. A number of engineering feasibility and alternative site selection studies were undertaken and a proposed dam site near Mapai was identified as the best option based on engineering, cost, environmental and social aspects. ARA-Sul has now commissioned an independent consultant to undertake detailed environmental and social studies, and to prepare an Environmental and Social Impact Assessment (ESIA) report and associated management plans. As part of the approval process a Estudo de Pré-viabilidade Ambiental e Definição de Âmbito (EPDA), or scoping report must be prepared and made available for public consultation. The purpose of the Scoping report is to identify any potential fatal flaws, possible positive and negative impacts, and project alternatives, and to determine the terms of reference for specialist studies to be conducted. The scoping report identifies a range of issues that will need to be investigated including the main potential adverse and beneficial impacts, mitigation measures and opportunities for positive enhancements. The full Scoping report is available at the Mapai and Chicualacuala District Administrative centres or on 2. Project justication The Resilience Project will provide an adaptive response to hydrological variability, thereby allowing improved access to water during dry periods and more effective management of flood flows. In addition the Project will supply up to 52 MW to the national grid and allow significant expansion of irrigated cropland. The Limpopo climate resilience Project is consistent with Mozambique s national policies and strategic frameworks, and has the potential to be a major asset for adaptation to the increasing hydrological extremes and enhancing climate change resilience. It will have important socioeconomic effects in Mozambique, especially in the Gaza Province, through the mitigation of extreme floods and drought impacts, provision of water for hydropower, irrigation, and other multi-purpose benefits including mechanisms for local benefit sharing and improved social equity. It will also ensure environmental flows are managed and maintained. 3. Project location The proposed Mapai dam and reservoir are located on the Limpopo River near Mapai, approximately 85 kilometres (km) from the Pafuri border with Zimbabwe. The Limpopo National Park is located on the western site of the reservoir and the main national road and railway linking Mozambique to Zimbawbe are located to the east (see Figure 1 and Figure 2). The study area falls within the districts of Chicualacuala and Mapai in the province of Gaza. There are 11 villages in Chicualacuala and 10 villages in Mapai that may be directly affected by the Proposal. 3

4 Figure 1 Site location 4

5 Figure 2 Site details 5

6 4. Project description Important Project parameters are: The proposed reservoir will be approximately 60 km long, with an average width of approximately 5 km. The reservoir will have a storage capacity of 68,370 megalitres (ML) and a surface area of 350 square kilometres (km 2 ). A compacted earth fill dam wall with concrete spillway will be 3.17 km long and 52.0 meters (m) high. A saddle dam will be located on the right bank, with a crest length of 155 m. Approximately 15 million cubic metres of quarried material will be required to construct the dam wall. A power plant will be located at the toe of the dam with a maximum output of 52 megawatts (MW). Other infrastructure includes construction camp, workshops and offices. The dam spillway has been designed to accommodate a 1 in 2,000 year flood event, however the auxillary spillway will safeguard the dam up to a 1 in 5,000 year flood event. Construction is expected to take approximately four years and require up to 500 workers. During this time affected people will be resettled to new areas and the reservoir area prepared for filling, which will take approximately two years after construction is completed. Construction areas will be rehabilitated and a 350 meter buffer zone established around the perimeter of the reservoir. The dam will be operated to provide for irrigation, power production and to ensure maintenance of downstream flows. 6

7 7

8 5. Planning approval process Planning and development of the Project will be in accordance with Mozambique regulatory requirements, policies and international agreements, as well as Afrcian Development Bank and relevant international guidelines. The Resilience Project is categorised as Category A and a full Environmental and Social Impact Assessment (ESIA) must be prepared by independent consultants for consideration and authorisation by the Ministry of Land, Environment and Rural Development (MITADER). The overall aim of the ESIA is to identify and assess potential environmental and social impacts associated with the life of the Project, in order to support a decision by MITADER. The ESIA process is divided into four distinct stages, namely: 1. Screening: EIA Pre-assessment Application All major developments must be screened in order to determine the process for environmental impact assessment. The screening process involves the submission of a Screening Report (Instrução do Processo) together with an Environmental Application Form (Ficha de Informação Ambiental Preliminar) to MITADER, specifically to the Provincial Directorate of Land, Environment and Rural Development (Direcção Provincial da Terra, Ambiente e Desenvolvimento Rural DPTADER) and National Directorate of Environment - DINAB). The screening report for the Project was submitted on 31 st March Scoping: Environmental Pre-Feasibility and Scoping An Environmental Pre-feasibility and Scoping Study (Estudo de Pré-Viabilidade Ambiental e Definição de Âmbito EPDA) has been prepared (this report) with the main aim of: Determining any fatal flaws and the most significant potential environmental and social impacts associated with the development of the proposed Project; Developing the Terms of Reference (ToR) for the ESIA, with input from study team specialists; and Consultation with stakeholders, so as to ensure that the ESIA process is focused on key issues. The draft EPDA report and non-technical summary will be made available for stakeholder comment at a number of locations such as district authority offices (Mapai and Chicualacuala) and DPTADER based in Xai Xai, as well as other physical locations to be confirmed. Direct s will be largely used to forward the documents to stakeholders The non-technical summary will be distributed with formal letters of invitation to stakeholders and will contain a summary of the proposed project, and the ESIA and associated public participation process. It will be compiled in Portuguese and distributed to Stakeholders prior to the Scoping Phase public meetings and will include a comment sheet allowing stakeholders to provide initial comment and formally register as a stakeholder. Following consultation the EPDA report will be submitted to MITADER for approval. 3. Environmental and Social Impact Assessment (ESIA) The ESIA stage comprises a number of steps that collectively assess the manner in which the proposed project will interact with elements of the physical, biological, and socio-economic environments. The ESIA will evaluate what mitigation measures are required so as to avoid or reduce impacts. Based on a balanced view of the advantages and disadvantages of the Project, the ESIA will make a recommendation as to whether the Project should be authorised. 8

9 Issues identified during the Scoping Phase will be assessed in the ESIA report, so as to understand what receptors and resources will be significantly affected by the Project. It will also describe baseline conditions that will influence the assessment of both social and environmental impacts. Specialist studies will: Identify the key conditions and sensitivities in areas potentially affected by the proposed Project; Provide a basis for extrapolation of the current situation, and development of future scenarios without the proposed Project; Provide information to aid the prediction and evaluation of possible impacts of the proposed Project; Understand stakeholder concerns, perceptions and expectations regarding the proposed Project; Facilitate the development of appropriate mitigation measures; and Provide a benchmark against which future changes and the effectiveness of mitigation measures can be assessed. 4. Environmental and Social Management Plans (ESMPs) ESMPs will be developed for the construction, operation and decommissioning phases of the project, so as to effectively implement the recommended mitigation measures identified during the ESIA. ESMPs will generally include the following: An environmental vision and associated strategies; High level measures and actions to be adopted to ensure that strategies are met; Procedures for specific action programmes and plans; Monitoring procedures, including environmental auditing; Risk and emergency response plan; An environmental awareness and education programme; A compensation and offset programme to address irreversible impacts; and A demobilisation and rehabilitation plan. 6. Public participation process (PPP) The PPP is a regulatory requirement and is designed to ensure that the views of stakeholders are taken into account in determining the terms of reference of the EIA and are reported throughout the ESIA process. The objective of public participation is to ensure the assessment is robust, transparent and has considered the full range of issues. Detailed stakeholder engagement usually starts during the present scoping phase and will continue throughout the assessment, ensuring that legislative requirements and Project standards are met, that stakeholder concerns are addressed in the assessment and that sources of existing information and expertise are identified. Specific objectives of the PPP are to: Provide sufficient, accessible and transparent information in a timely manner to enable stakeholders to understand the project and its potential impacts; Identify issues of concern and suggestions for enhanced benefits, and to obtain contributions of local knowledge and experience; 9

10 Consider comments and suggestions to be evaluated in the Terms of Reference (ToRs) for the ESIA; Support an open and inclusive social dialogue, and identify stakeholder s perceptions and expectations; Engage vulnerable groups; Inform the establishment of a grievance and redress mechanism as part of the complaints procedure; and Ensure compliance with national regulations. Consultation activities: Meetings will be conducted in Portuguese and Changane as required. When deemed appropriate, women in the project team will conduct the meetings in Changane to welcome the engagement of other women and facilitate this process. The communication materials available at the meetings will be selected according to the type of meeting and the target audience to ensure that messages are clearly understood by all. Meetings will be supported by relevant posters and illustrations. Comments and responses: Each public participation event will be designed to be inclusive and record attendee s details. Relevant Project team members will be involved in the meetings to ensure that particular focus is given to the vulnerable groups and women s engagement in the process. All comments will be captured, recorded and analysed. An Issues and Response Report (IRR), and Public Participation Report (PPR) will be produced to accompany the main ESIA report. 7. Key environmental issues Preliminary studies have identified a number of potential Project impacts and risks related to the Biophysical and social environments. These can be broardly summarised as follows: Air quality, noise, water quality and waste Construction and materials transport will generate potentially significant impacts that may affect the environment and people. These will be carefully assessed and mitigation measures recommended to ensure impacts are within accepted regulatory and guideline requirements. Water resources - Flow releases will need to be managed to protect river flow patterns, which are important for maintaining downstream ecological resources and current water uses. Many of the potential water impacts are likely to be beneficial, as the river flow will be regulated so that it can be used more effectively and benefit a larger number of people. Climate Change vulnerability - Mozambique is extremely vulnerable to climate variability and change. Drought, severe flooding, and coastal storms have damaging impacts and are expected to increase in severity and frequency. It is likely that climate and weather variability will increase and coupled with developments in the upstream portions of the international catchment this may further increase the variability of surface water flows. The project s resilience will be appraised against current and projected climate risks, and capacity to realise potential opportunities. Recommendations for improving climate resilience over the Project s operational lifetime will be provided. Flood and Drought Risk Management - The lower reaches of the Limpopo river basin in Mozambique are prone to devastating floods that damage infrastructure and undermine people s livelihoods. The assessment will consider how flood management can be best achieved, and will plan project activities with mitigation measures to minimise the risks. The study will review the implications of the project for disaster risk reduction and management by assessing the vulnerability of the lower reaches of Limpopo to disasters related to natural 10

11 hydrological variations increased by climate change effects and the areas stricken by frequent flooding causing major damages. Biodiversity There are a number of regional conservation areas, however intial studies indicate that the Project area does not form an important wildlife link between these areas (Figure 4). The Project area has been extensively cleared and there are limited areas of natural vegetation and fauna habitat. No rare or endangered species have been recorded. The river is habitat to a small number of fish species, however fish numbers have have been depleted by overfishing and increased drought periods (Figure 5). The Project is likely to improve biodiversity due to the creation of a significant water body attracting local species and improved catchment management activities, includinjg rehabilitation of forest areas around the reservoir perimeter. Regulating downstream flows will also improve biodiversity during drought conditions and major flood conditions. 11

12 Figure 4 Protected areas 12

13 Figure 5 Habitat distribution 13

14 8. Key social issues The study area falls within the districts of Chicualacuala and Mapai in the province of Gaza, which are among the least developed districts in Mozambique. Important activities include small scale agriculture, raising of cattle and other small animals, and exploitation of forest and wildlife resources. There are 21 villages within the Project affected area and approximately 10,000 people will be affectd by the Project (Figure 6 and Figure 7). Economic Important economic activities relate to natural resources (land for agriculture, water and forests), physical resources (roads, railway), financial resources (sale of livestock, cash crops and forestry products), human resources (skills in agro-livestock techniques, health personnel and veterinarians) and social resources (churches, NGOs, savings groups, traditional resource management systems and women's income generating groups). Major issues relate to: Lack of irrigation systems, financial resources for support and agro-processing units; Inadequate public infrastructure including poor access roads, unreliable communication services, limited power connections; and Cyclical droughts and floods are significant constraints to agriculture. There will be potentially significant beneficial impacts as a result of the project, including improved access to irrigation, regulation of flood waters and economic stimulus due to employment opportunities and improved business opportunities. Crop and livestock production - Subsistence rain-fed agriculture is carried out with each family requiring an average of 1 to 1.5 hectares (ha) of land per agricultural season. Livestock commonly includes cattle, goats and pigs and small animals such as chickens. The reliance on agriculture will be determined during the detailed population survey and included in the assessment of compensation and resettlement. Local Amenities and Services in Chicualacuala and Mapai districts Schools: There are 49 schools, ranging from primary to secondary, as well as 29 voluntary operated literacy centres that cater for literacy and adult education. Health services: Services are scarce and include 1 Hospital, 2 Health centres, 1 First aid station and 15 Community Offices that provide first-aid. In some villages in the project area, formal infrastructure and health services are practically non-existent. This situation is filled at the local level by the recurrence of traditional medicine services. Water, sanitation and waste: Water for domestic and stock is sourced from hand pump wells, surface storages (holes) and dykes. Many of the wells are faultly and domestic water is prone to contamination from unregulated waste disposal. Most people lack access to basic sanitation facilities. Solid waste is done at the individual level and is typically burned, buried near the household or accumulated in identified places. Electricity: Both districts are connected to the national grid, however less than 1% of the population has access to electricity. The main sources of energy are paraffin and kerosene, followed by candlestick and firewood. Transport: A main national road (N221) and railway are located east of the Project site. Unsealed local and regional roads service villages and larger town centres. Approximately 52 km of Road N222 is affected by the proposed Project and will need to be realigned. Other roads may be used for access for plant and material access during construction. The ESIA will assess the loss of public infrastructure and recommendations made for replacement and/or improvements. 14

15 Figure 6 Administrative centres and villages 15

16 Figure 7 Infrastructure 16

17 Health and safety: Health and Safety (H&S) issues will be significant on a project of this scale, with potential for accidents and spread of infectious diseases. Health impacts may occur not only on the reservoir site but also upstream, downstream, and at national or even regional levels. The detailed socio-economic survey will identify the baseline conditions including the health facilities available in areas around the Project area. Initial review indicates a scarcity of health facilities with limited capacity for maternal and child care, and HIV and AIDS services. Impact assessment will therefore need to identify any additional requirements for health care infrastructure and education programs needed to inform the public about health and safety risks. Cultural Heritage and Archaeology: Cultural sites identified include 13 common graves, a number of historical sites and archaelological sites. The ESIA will consider how the Project will potentially impact on cultural heritage and archaeology with a focus on tangible sites. A cultural heritage and archaeology plan will be prepared to outline key responsibilities and measures to comply with Mozambican legislation and international industry good practice and requirements applicable to the protection and preservation of tangible and intangible cultural heritage. 9. Resettlement and livelihoods Twenty one (21) villages and approximately 10,000 Project Affected People (PAP) may be directly affected by the Project. The project will therefore lead to involuntary resettlement of people and livelihoods, and a Resettlement Action Plan (RAP) will need to be developed in compliance with national legislation as well as Africa Development Bank requirements. Detailed Socio-economic and asset surveys will be undertaken to confirm the number of PAP and document affected livelihoods and assets. Livelihood restoration measures will take into account the current livelihood practices of the affected households and also existing livelihood-improvement government programs both in the areas of impact and proposed relocation. A Livelihood Restoration Plan (LRP) will be included with the resettlement Action Plan (RAP) to be implemented in future studies. i. Impact on public infrastructure The Proposal will have direct impacts on public infrastructure such as water sources, schools, health centres, etc. Replacement of these infrastructure in an appropriate timeframe is necessary to ensure continuance of these services. ii. Livelihood restoration Initial studies indicate that farming is the major source of livelihood for people in the project area. Farming is mostly practiced along the river banks, which are characterised by fertile soils and a reliable water supply from the river. The proposed reservoir will lead to loss of fertile farmland for people in 21 villages. In addition, there will be loss of livelihoods in terms of fishing through loss of access to the river during the construction period. A Livelihood Restoration Plan will fully document these potential losses and propose a range of mitigation measures to ensure People s livelihoods are maintained, and if possible enhanced as a result of the Project. iii. Identification of resettlement land It will be important to identify suitable resettlement land for affected communities. This process will be spearheaded by ARA-Sul, who will coordinate with the authorities at the different government levels to identify suitable land for resettlement. The negotiations between the host communities will also be undertaken by government authorities. Also important is the reinstatement of public infrastructure such as water sources, schools, health facilities etc. in the resettlement areas. 17

18 iv. Impact on the use of natural resources Communities currently rely on the surrounding shrubs, reeds and wild trees for firewood, construction materials, wild fruits and local medicine. They also depend on the uninhabited land for grazing their animals. In addition, many of them depend on the river for water supply and fishing activities. The proposal will negatively impact on these resources and alternative resources will need to be canvassed. v. Public disclosure of resettlement information It is important to inform the affected communities about the possibility of resettlement at an early stage of the Project. However, experience shows that there is often a long period between public disclosure of information related to resettlement and actual implementation of the project and the resettlement. This makes it difficult to define the actual cut-off date, whereby no additional people moving into the affected area or property/asset improvements will be compensated. Furthermore, it becomes difficult for the communities to continue living a normal life before actual displacement. vi. Resettlement committees The Mozambican legislation as well as the AfDB safeguard policies provide for resettlement committees. The composition of the committees and their functions are well defined in the Regulations for the Resettlement Process Resulting from Economic Activities Decree 31/2012 of 8 August. Some members of the committees will be involved in the preparation of the RAP. The committees will also be instrumental in the identification of resettlement land and negotiations with host communities. Building their capacity will be of great importance to successful implementation of the RAP. 10. Terms of reference The EPDA report also provides a Terms of Reference (ToR) for progressing with environmental and social studies and preparation of an ESIA report and associated management plans. The purpose of the ToR is to set out the technical approach and methodology for addressing environmental and social aspects relating to the Mapai dam Project. Specialist impact assessment studies will address baseline conditions, Project impact assessment, recommended mitigation measures and residual risk assessment. Speciis areas of study include the following: Air Quality Noise Water Resources (surface and groundwater water) Environmental Flow Management Climate Change Vulnerability and Adaptation Flood and Drought Risk Management Flora and Fauna Socio-economic Environment Resettlement and Livelihoods Occupational Health and Safety Cultural Heritage and Archaeology Geology and Soils Land Quality and Waste Management Landscape, Visual Amenity and Lighting Transport, Traffic and Access 11. Conclusion The proposed Mapai dam Project will generate significant benefits to the local and regional communities, as well as to the economic prosperity of Mozambique. The Project aims will improve climate change resilience of communities, infrastructure and livelihoods in the lower Limpopo River 18

19 basin by better management of water resources during flood and dry conditions. There will also be tangible benefits related to improved irrigation and food security opportunities, as well as providing energy to the national power grid. Preliminary studies have been undertaken and a number of important Project uissues identified, including: There are 21 villages within the Project footprint and a current estimate of 10,000 people may be directly affected by the Project. This will require detailed socio-economic and asset surveys, identification of relocation areas and preparation of a Resettlement Action Plan (RAP). Project integration with other projects, including the Limpopo National Park (PNL) resettlement project. Initial review indicates that PNL has undertaken planning activities to relocate people within a small part of the proposed reservoir. The proposed reservoir and infrastructure will encroach on a designated conservation area The Limpopo National Park The Park is managed by the National Administration of Conservation Areas (ANAC), who will be responsible for issuance of a special licence. Relocation of public infrastructure including an important regional road that currently runs through the proposed reservoir area. Regional wildlife corridors between important conservation areas. Construction issues associated with air quality, noise, water management, water quality and social distruption. Operational issues associated with maintenance of environmental flows, catachment management and flood control. In accordance with Mozambique planning regulatory requirements a Estudo de Pré-viabilidade Ambiental e Definição de Âmbito (EPDA), or scoping report has been prepared, which is now available for public comment. This report identifies: Any potential fatal flaws, possible positive and negative impacts, and project alternatives, and planning approval requirements. A range of issues that will need to be investigated including the main potential adverse and beneficial impacts, mitigation measures and opportunities for positive enhancements. The report also presents the Terms of Reference for preparing the ESIA report. A copy of the scoping report can be viewed online at????, or at the following locations: 19

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI 220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TERMS OF REFERENCE Transmission line Akhalsikhe-Batumi Georgia Terms of Reference for Tender docs and ESIA 2 1 PROJECT

More information

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e) Checklist: 3. Hydropower Stations, Dams and Reservoirs (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders Main Check s Have EIA reports been

More information

1 Environmental and Social Action Plan

1 Environmental and Social Action Plan 1 and Social Plan The table below constitutes the ESAP. It identifies the required actions during pre-construction, construction and operation of the project. of the actions is the responsibility of Koridori

More information

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS 4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS 4.1 INTRODUCTION This Chapter provides a summary of the EIA process that is being followed for the Sasol Pipeline and FSO Project. The process is structured

More information

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR Overview of Presentation 1. Objectives of the Consultancy 2. Hydropower in Myanmar 3. Draft Table of Contents 4.

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

Environmental Checklist: 26. Forestry Projects(1) Confirmation of Environmental and Social Considerations. Environmental Item.

Environmental Checklist: 26. Forestry Projects(1) Confirmation of Environmental and Social Considerations. Environmental Item. Checklist: 26. Forestry Projects(1) 1. Permits and Approvals, Explanations 2. Antipollution Measures (1) ESIA and Permits (2) Explanations to the Public (1) Air Quality (2) Water Quality (3) Waste (4)

More information

Main Check Items. 1 Are wastes properly treated and disposed of in accordance with the laws and regulations of the host country?

Main Check Items. 1 Are wastes properly treated and disposed of in accordance with the laws and regulations of the host country? Checklist: 16. Power Transmission and Distribution Lines(1) Confirmation of and Social (1) ESIA and Permits 1 Have ESIA reports been officially completed? Have ESIA reports been written in the official

More information

Nam Theun 2. TNC workshop April 2014

Nam Theun 2. TNC workshop April 2014 Nam Theun 2 1 TNC workshop April 2014 The Hydropower Project Build, Operate, Transfer 25 year concession for Nam Theun Power Co. US$1.3 Billion cost, financed by 27 parties (1/3 Equity; 2/3 debt) Generating

More information

PUBLIC DISCLOSURE OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT FOR THE MZIMBA TURN OFF- MZUZU-KACHECHE SECTION OF THE M1 ROAD.

PUBLIC DISCLOSURE OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT FOR THE MZIMBA TURN OFF- MZUZU-KACHECHE SECTION OF THE M1 ROAD. Malawi Government Accelerating Malawi s Economic Growth PUBLIC DISCLOSURE OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT FOR THE MZIMBA TURN OFF- MZUZU-KACHECHE SECTION OF THE M1 ROAD.

More information

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify) PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION Interested Organization Name: Project Location: Projected amount of required project funding ($ /USD): TOTAL: Project Sector or Similar:

More information

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item Checklist: 17. Roads, Railways and Bridges(1) 1. Permits and Approvals, Explanations (1) ESIA and Permits (2) Explanations to the Public Main Check s 1 Have ESIA reports been officially completed? Have

More information

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item Checklist: 17. Roads, Railways and Bridges(1) 1. Permits and Approvals, Explanations (1) ESIA and Permits (2) Explanations to the Public Main Check s 1 Have ESIA reports been officially completed? Have

More information

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process 10 January 2018 Introduction 1. Environmental and social screening is an essential and

More information

COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW

COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW Section 1: Description of the project (Final Version of 17

More information

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impacts July 14-19, 2014 Content Project History Purpose and Scope The Project Area The Project The Project

More information

ENVIRONMENTAL AND SOCIAL ACTION PLAN

ENVIRONMENTAL AND SOCIAL ACTION PLAN ENVIRONMENTAL AND SOCIAL ACTION PLAN 0 Corporate s 0.1 Maintain a Corporate EHS management system and CSR reporting for Zorlu Enerji in line with GRI4. Need to maintain and implement best practice. Disclose

More information

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN Taking into account the findings of the ESDD, an Environmental and Social Plan (ESAP) has been developed

More information

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d) Checklist:. 10.Ports and Harbors (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders (3) Examination of Alternatives (1) Air Quality (2) Water

More information

IUCN Standard on the Protection of Natural Habitats

IUCN Standard on the Protection of Natural Habitats IUCN Standard on the Protection of Natural Habitats July 2013 A. Introduction 1. This Standard stems from the need to protect and conserve biodiversity, maintain ecosystem functions and services, and manage

More information

Agency (or Institution) Responsible for Implementing the Project

Agency (or Institution) Responsible for Implementing the Project Summary of Preparatory Study Full Title of the Project The Study on Integrated Flood Management for Nyando River asin in the Republic of Kenya Type of Study Master Plan ategorisation and Its Reason 3.1

More information

CHAPTER 7 STAKEHOLDER ENGAGEMENT

CHAPTER 7 STAKEHOLDER ENGAGEMENT CHAPTER 7 STAKEHOLDER ENGAGEMENT TABLE OF CONTENTS 7 STAKEHOLDER ENGAGEMENT PROCESS... 7-1 7.1 INTRODUCTION... 7-1 7.2 STAKEHOLDERS IDENTIFIED... 7-2 7.3 STAKEHOLDER ENGAGEMENT PROCESS... 7-4 7.3.1 Stakeholder

More information

WEST RAND DISTRICT MUNICIPALITY CASE STUDY 2018

WEST RAND DISTRICT MUNICIPALITY CASE STUDY 2018 WEST RAND DISTRICT MUNICIPALITY CASE STUDY 2018 LOCAL ACTION FOR BIODIVERSITY: WETLANDS SOUTH AFRICA Spatial mapping developed to address West Rand District Municipality s gaps in wetland planning Identifying

More information

DRAFT FOR CONSULTATION OCTOBER 7, 2014

DRAFT FOR CONSULTATION OCTOBER 7, 2014 The Board has authorized the release of this document for consultation purposes to seek feedback on its content. It has not endorsed the content of the draft, and the Committee on Development Effectiveness

More information

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME 1 Introduction and Background To meet its environmental and social obligations and commitments, the Lesotho Highlands Development

More information

CLEAN AND CONTINUOUS WATER FOR 1.6 MILLION PEOPLE IN LEBANON

CLEAN AND CONTINUOUS WATER FOR 1.6 MILLION PEOPLE IN LEBANON CLEAN AND CONTINUOUS WATER FOR 1.6 MILLION PEOPLE IN LEBANON CLEAN AND CONTINUOUS WATER FOR 1.6 MILLION PEOPLE IN LEBANON Over 1.6 million people living across the Greater Beirut & Mount Lebanon (GBML),

More information

SEA and Green Growth The African Development Bank Experience

SEA and Green Growth The African Development Bank Experience SEA and Green Growth The African Development Bank Experience Presented By Justin Ecaat, Principal Environmental Safeguards Officer Lusaka, Zambia. January 2013 Content Background: SEA: Beyond project level

More information

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Greater Mekong Subregion Nam Ngum 3 Hydropower Project (RRP LAO 41385) Supplementary Appendix 5 TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Strengthening Biodiversity

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

Environmental, Social and Governance (ESG) management

Environmental, Social and Governance (ESG) management 28 Environmental, Social and Governance (ESG) management Our policy The development of solar projects involves environmental and social implications. In alignment with Scatec Solar s policies, requirements

More information

Droughts and floods, crop failures, degradation of natural resources are increasingly linked to, or exacerbated by climate

Droughts and floods, crop failures, degradation of natural resources are increasingly linked to, or exacerbated by climate WFP sees climate change as a multiplier of existing risks to food security, threatening to undermine the gains in eradicating food insecurity and poverty. It is affecting the livelihoods of the vulnerable

More information

SANDCRETE ENGINEERING NIG. LTD. Background Information Document (BID)

SANDCRETE ENGINEERING NIG. LTD. Background Information Document (BID) ENVIRONMENTAL IMPACT ASSESSEMENT (EIA) FOR THE PROPOSED GOLD (Au) EXPLORATION AND MINING PROJECT AT RANDEGI DISTRICT, BIRNIN GWARI L.G.A OF KADUNA STATE BY SANDCRETE ENGINEERING NIG. LTD Background Information

More information

BACKGROUND INFORMATION DOCUMENT

BACKGROUND INFORMATION DOCUMENT BACKGROUND INFORMATION DOCUMENT Environmental and Social Impact Assessment (ESIA) December 2017 Malingunde Graphite Project, Lilongwe District, Malawi Purpose of this document This document provides information

More information

5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION

5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION 5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION This Chapter presents a summary of the stakeholder engagement activities planned as part of the EIA process. It serves as a summary of a more detailed Stakeholder

More information

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary 1 Introduction This document provides a non-technical overview of Aquanova Development Nyzhniy Bystryi Hydropower Plant project

More information

LAW OF THE REPUBLIC OF INDONESIA NUMBER 7 OF 2004 REGARDING WATER RESOURCES

LAW OF THE REPUBLIC OF INDONESIA NUMBER 7 OF 2004 REGARDING WATER RESOURCES LAW OF NUMBER 7 OF 2004 REGARDING WATER RESOURCES BY THE GRACE OF THE ALMIGHTY GOD, THE PRESIDENT OF Considering : a. that water resources is the gift of the Almighty God which gives benefits for the realization

More information

Summary of Preliminary Study Result for Technical Cooperation Project

Summary of Preliminary Study Result for Technical Cooperation Project Summary of Preliminary Study Result for Technical Cooperation Project 1. Title of the Cooperation Project, Relevant Project Report The Project for Bridge Construction in Southeast Sulawesi Province Project

More information

BURUNDI, RWANDA, TANZANIA

BURUNDI, RWANDA, TANZANIA Financing water for growth in Africa Rusumo Falls: water for power generation and multipurpose use, Burundi, Rwanda, Tanzania Summary The Regional Rusumo Falls Hydroelectric and Multipurpose Project is

More information

Environmental and Social Review for GDF Projects

Environmental and Social Review for GDF Projects Environmental and Social Review for GDF Projects Laurie Hietter Sacramento, California October 24, 2016 Introduction 1 Importance of Environmental and Social Assessment 2 Regulations and Overview of Environmental

More information

SRESA of a Regional Transmission development in Mozambique

SRESA of a Regional Transmission development in Mozambique SRESA of a Regional Transmission development in Mozambique Adriana Lafleur; Stephen Lindley Environment & Water, SNC-Lavalin Inc., Toronto, Ontario, Canada Electricidade de Moçambique (EDM), the national

More information

Sustainable Development 6 and Ecosystem Services

Sustainable Development 6 and Ecosystem Services Sustainable Development 6 and Ecosystem Services 6 28 On Target for People and Planet: Setting and Achieving Water-related Sustainable Development Goals Sustainable Development and Ecosystem Services Lead

More information

S e c t i o n B i o d i ve r s i t y

S e c t i o n B i o d i ve r s i t y S e c t i o n 2. 2 - B i o d i ve r s i t y The District has a wealth of ecosystems which support indigenous vegetation and habitats of indigenous fauna. Many of these ecosystems are the remnants of the

More information

Performance Requirements

Performance Requirements Environmental and Social Policy 15 Performance Requirements PR 1: Environmental and Social Appraisal and Management Introduction 1. The EBRD considers it important that all companies receiving EBRD financing

More information

SUSTAINABLE HYDROPOWER DEVELOPMENT A NORWEGIAN-GEORGIAN COOPERATION PROGRAM. A Citizen s Guide. Communication and Hydropower EIA

SUSTAINABLE HYDROPOWER DEVELOPMENT A NORWEGIAN-GEORGIAN COOPERATION PROGRAM. A Citizen s Guide. Communication and Hydropower EIA Communication and Hydropower EIA September, 2014 Dhillion, S.S. and Bakhtadze, M. 2014. A Citizen s Awareness Guide: Communication and Hydropower EIA. Sustainable Hydropower Development in Georgia. Report

More information

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS UNRAVELING THE MYRAID OF STANDARDS AND TOOLS HYDRO POWER DEVELOPMENT IN MEKONG REGION: CYCLING THROUGH FROM POLICY TO IMPLEMENTATION WORKSHOP SEPTEMBER 12-13, 2013 Basin Wide National regulations Project

More information

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods. 1 FACTSHEET INTRODUCTION World Water Day, on 22 March every year, is about focusing attention on the importance of water. This year s theme, Nature for Water, explores nature-based solutions (NBS) to the

More information

Case Study. Irrigated and integrated agro production systems help Mozambique adapt to climate change. SDGs addressed CHAPTERS.

Case Study. Irrigated and integrated agro production systems help Mozambique adapt to climate change. SDGs addressed CHAPTERS. Case Study Irrigated and integrated agro production systems help Mozambique adapt to climate change MAPUTO SDGs addressed This case study was prepared based on the joint programme, Mozambique: environment

More information

CI-GEF PROJECT AGENCY SCREENING RESULTS AND SAFEGUARD ANALYSIS (To be completed by CI-GEF Coordination Team)

CI-GEF PROJECT AGENCY SCREENING RESULTS AND SAFEGUARD ANALYSIS (To be completed by CI-GEF Coordination Team) CI-GEF PROJECT AGENCY SCREENING RESULTS AND SAFEGUARD ALYSIS (To be completed by CI-GEF Coordination Team) I. BASIC INFORMATION A. Basic Project Data Country: Kenya GEF Project ID: Project Title: Strengthening

More information

Notes for NEPA for Generic Terms of Reference

Notes for NEPA for Generic Terms of Reference TERMS OF REFERENCE IIRRIIGATIION AND WATER MANAGEMENT Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to the construction and/or the development of Irrigation

More information

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Environmental and Social Action Plan August 2016 Project: Bosnia and Herzegovina

More information

Results of a Problem and Objective Analysis, and the Application of the Logical Framework Approach An Example from the Nam Tong Watershed, the Lao PDR

Results of a Problem and Objective Analysis, and the Application of the Logical Framework Approach An Example from the Nam Tong Watershed, the Lao PDR Chapter 4.3.2: Problem Analysis and Scoping 1 Module 4: Planning Case Study Results of a Problem and Objective Analysis, and the Application of the Logical Framework Approach An Example from the Nam Tong

More information

Domestic adaptation to climate change in Rwanda

Domestic adaptation to climate change in Rwanda Annex I Expert Global Forum on Sustainable Development: Key Issues for the Post-2012 Climate Change Framework OECD, Paris 4-5 March 2009 Domestic adaptation to climate change in Rwanda By URAMUTSE Charles

More information

European Climate Adaptation Platform. istockphoto/ AndresGarciaM. Assessing Adaptation Knowledge in Europe: Ecosystem-based Adaptation

European Climate Adaptation Platform. istockphoto/ AndresGarciaM. Assessing Adaptation Knowledge in Europe: Ecosystem-based Adaptation European Climate Adaptation Platform Climate-ADAPT factsheet istockphoto/ AndresGarciaM Assessing Adaptation Knowledge in Europe: Ecosystem-based Adaptation What is ecosystem-based adaptation? Ecosystem-based

More information

LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA

LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA Additional Financing of Local Government Enhancement Sector Project (RRP SRI 42759) LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA A. Eligible Local Authority and Subprojects 1. Unless otherwise agreed

More information

Madagascar: Makira REDD+

Madagascar: Makira REDD+ Madagascar: Makira REDD+ Madagascar is considered to be one of the top five biodiversity hotspots in the world. More than 80% of its animal and plant species are not found anywhere else on earth, but historically

More information

The Project will be undertaken in line with a number of national laws and standards. Key local laws relating to ESIA include:

The Project will be undertaken in line with a number of national laws and standards. Key local laws relating to ESIA include: 1 EXECUTIVE SUMMARY 1.1 CONTEXT OF THE PROJECT Myanmar UPA Company Limited ( MUPA or the Project Sponsor or the Project Proponent ) intends to develop a 200MW Combined Cycle Power Plant (CCPP) to supply

More information

Category Environmental Item Main Check Items Confirmation of Environmental and Social Considerations

Category Environmental Item Main Check Items Confirmation of Environmental and Social Considerations al Checklist: 5. Non-Ferrous Metals Smelting and Refining(1) (1) ESIA and al Permits 1 Have ESIA reports been officially completed? Have ESIA reports been written in the official language or a language

More information

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017 Annesley Andalusite Mine: Section 24G Rectification Process Consultation with community members 15 June 2017 AGENDA Welcome and introduction Meeting protocol Purpose of the meeting Project background Project

More information

Environmental and Social Action Plan Adjaristskali Hydropower Plants

Environmental and Social Action Plan Adjaristskali Hydropower Plants Environmental and Social Plan Adjaristskali Hydropower Plants The International Finance Corporation (IFC), the Asian Development Bank (ADB), and the European Bank for Reconstruction and Development (EBRD)

More information

TRAINING Seminar POVERTY ENVIRONMENT MAINSTREAMING IN TAJIKISTAN

TRAINING Seminar POVERTY ENVIRONMENT MAINSTREAMING IN TAJIKISTAN + TRAINING Seminar POVERTY ENVIRONMENT MAINSTREAMING IN TAJIKISTAN + Outline of the Seminar Introduction P-E Mainstreaming and MDGs Relevance to Tajikistan P-E Mainstreaming Process Responsibilities for

More information

(20 April, 2016 Tsagaannuur Soum of Selenge aimag)

(20 April, 2016 Tsagaannuur Soum of Selenge aimag) The Public Consultations on the draft Terms of Reference /TORs/ for Regional Environmental Assessment /REA/ and Environmental and SocialImpact Assessment /ESIA/ for Shuren Hydropower Plant Project / SHPP/

More information

3.0 APPROACH AND METHODOLOGY

3.0 APPROACH AND METHODOLOGY 3.0 APPROACH AND METHODOLOGY The EIA will be completed to meet the requirements as set out in the Environmental Impact Assessment Guidelines and Procedures for Barbados, 1998 and the Thermal Power Guidelines

More information

GATSUURT GOLD MINE : ENVIRONMENTAL AND SOCIAL ACTION PLAN

GATSUURT GOLD MINE : ENVIRONMENTAL AND SOCIAL ACTION PLAN GATSUURT GOLD MINE : ENVIRONMENTAL AND SOCIAL ACTION PLAN DRAFT FOR DISCLOSURE PURPOSES. FINAL ESAP TO BE AGREED POST DISCLOSURE AND PRIOR TO FINANCING DECISION (Liabil/ PR1 Assessment and Management of

More information

SUMMARY 2013 EDITION

SUMMARY 2013 EDITION SUMMARY 2013 EDITION RSAT Joint Initiative on Rapid Basin-wide Hydropower Sustainability Assessment Tool PART 1: OVERVIEW OF THE RSAT The RSAT is designed as an integrative tool to assess hydropower development

More information

Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT. EIS Screening Report

Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT. EIS Screening Report Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT IRISH WATER Vartry Water Supply Upgrade Project Environmental Impact Assessment Screening Report Nicholas O Dwyer Ltd Consulting Engineers Nutgrove Office

More information

The three alternative sites were inspected by the specialists in order to:

The three alternative sites were inspected by the specialists in order to: 5. SITE SELECTION PROCESS UNDERTAKEN DURING THE ENVIRONMENTAL SCOPING STUDY The Environmental Scoping Study identified the potential positive and negative environmental (biophysical and social) impacts

More information

MDB-Sponsored Regional Workshops to Mainstream Gender Equality in Infrastructure Policies and Projects

MDB-Sponsored Regional Workshops to Mainstream Gender Equality in Infrastructure Policies and Projects MDB-Sponsored Regional Workshops to Mainstream Gender Equality in Infrastructure Policies and Projects Gender Dimension in Multinational Projects- Ethiopia/Kenya: Mombasa-Nairobi-Addis Ababa Road Corridor.

More information

Figure 1-1. Project location with site boundaries shown with red shaded area and red line

Figure 1-1. Project location with site boundaries shown with red shaded area and red line 1.0 INTRODUCTION 1.1 Background and Objective An Environmental and Social Impact Assessment (ESIA) study has been conducted for the Elazig Integrated Health Campus Project (IHC or Project) located in the

More information

CCAI Demonstration Projects in Viet Nam. Dr. Nguyen Anh Duc National CCAI Coordinator, Viet Nam National Mekong Committee

CCAI Demonstration Projects in Viet Nam. Dr. Nguyen Anh Duc National CCAI Coordinator, Viet Nam National Mekong Committee 1 CCAI Demonstration Projects in Viet Nam Dr. Nguyen Anh Duc National CCAI Coordinator, Viet Nam National Mekong Committee Outline Project: Preliminary Study on Climate Change Adaptation Plan in Kien Giang

More information

Project Appraisal Report

Project Appraisal Report Project Appraisal Report REPUBLIC OF MOZAMBIQUE Feasibility Studies for Building Climate Resilience of Limpopo Basin in Mozambique November 2014 Table of Contents Logical Framework 5 Executive Summary

More information

EBRD Environmental and Social Action Plan

EBRD Environmental and Social Action Plan PR 1 Assessment and Management of Environmental and Social Impacts and Issues 1.1 to establish PIU and dedicate a responsible person (head of PIU) for coordination between the various departments so as

More information

Annexure: Need & Desirability

Annexure: Need & Desirability Annexure: Need & Desirability Table 1 Need for the proposed expansion QUESTION: NEED (TIMING) OF PROPOSED PROJECT 1. Is the land use (associated with the activity being applied for) considered within the

More information

Nepal Earthquake Building Back Better, Safer and Greener for a More Resilient Nepal

Nepal Earthquake Building Back Better, Safer and Greener for a More Resilient Nepal Nepal Earthquake 2015 Building Back Better, Safer and Greener for a More Resilient Nepal The Nepal earthquake in April 2015 and its aftershocks resulted in huge loss of life, injury, and economic damage.

More information

Evidence of global warming

Evidence of global warming INTRODUCTION Climate Change can be attributed directly or indirectly to human activities (e.g. through burning fossil fuels, deforestation, reforestation, urbanization, desertification) that alters the

More information

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS TERMS OF REFERENCE ELECTRICAL TRANSMISSION LINES & SUBSTATIONS Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to development projects involving the construction

More information

Resettlement Action Plan

Resettlement Action Plan 2017 DECEMBER Trans Anadolu Doğal Gaz Boru Hattı Projesi (TANAP) Resettlement Action Plan Second External Monitoring and Evaluation Report Summary TANAP PROJECT Second Semi-Annual External RAP Monitoring

More information

Proposed additional financing to the Kingdom of Cambodia for the Tonle Sap Poverty Reduction and Smallholder Development Project

Proposed additional financing to the Kingdom of Cambodia for the Tonle Sap Poverty Reduction and Smallholder Development Project Document: EB 2017/LOT/P.20 Date: 17 November 2017 Distribution: Public Original: English E President s memorandum Proposed additional financing to the Kingdom of Cambodia for the Tonle Sap Poverty Reduction

More information

MINISTRY OF LAND HOUSING AND URBAN DEVELOPMENT ALBERTINE REGION SUSTAINABLE DEVELOPMENT PROJECT

MINISTRY OF LAND HOUSING AND URBAN DEVELOPMENT ALBERTINE REGION SUSTAINABLE DEVELOPMENT PROJECT MINISTRY OF LAND HOUSING AND URBAN DEVELOPMENT ALBERTINE REGION SUSTAINABLE DEVELOPMENT PROJECT Procurement of a Project Environmental Specialist TERMS OF REFERENCE The Ministry of Lands Housing and Urban

More information

1. Background Provisioning Regulating: Cultural:

1. Background Provisioning Regulating: Cultural: IN PARTNERSHIP WITH EXECUTIVE SUMMARY The Myanmar hydropower sector, in the early stages of development, has the opportunity to develop sustainably by balancing electricity generation with environmental

More information

Lesotho Highlands Water Project. Refiloe Tlali Chief Executive LHDA 22 May 2015

Lesotho Highlands Water Project. Refiloe Tlali Chief Executive LHDA 22 May 2015 Lesotho Highlands Water Project Refiloe Tlali Chief Executive LHDA 22 May 2015 Today s roadmap Why the LHWP? What is the mandate? How is LHDA governed? What has been achieved? Where to from here? Why the

More information

Project: Category A Road Project, Kazakhstan Kurty Buribaytal 62 km Road Project

Project: Category A Road Project, Kazakhstan Kurty Buribaytal 62 km Road Project Project: Category A Road Project, Kazakhstan Kurty Buribaytal 62 km Road Project Date: May 2015 Version: Final Version Appendix D: Environmental and Social Plan (ESAP) No. PR1 Assessment and Management

More information

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT EXTERNAL/INDEPENDENT SOCIAL, ENVIRONMENTAL, HEALTH, AND SAFETY COMPLIANCE MONITORING

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT EXTERNAL/INDEPENDENT SOCIAL, ENVIRONMENTAL, HEALTH, AND SAFETY COMPLIANCE MONITORING NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT EXTERNAL/INDEPENDENT SOCIAL, ENVIRONMENTAL, HEALTH, AND SAFETY COMPLIANCE MONITORING GENERAL TERMS OF REFERENCE APRIL 2006 BACKGROUND Newmont Ghana Gold Ltd.

More information

STRATEGIC PROGRAM FOR CLIMATE RESILIENCE MOZAMBIQUE

STRATEGIC PROGRAM FOR CLIMATE RESILIENCE MOZAMBIQUE 1 STRATEGIC PROGRAM FOR CLIMATE RESILIENCE MOZAMBIQUE BUILDING RESILIENCE OF THE MOZAMBIQUE ECONOMY AND LOCAL COMMUNITIES HE. ANA PAULO CHICHAVA Deputy Minister Coordination of Environmental Affairs Government

More information

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary Norfolk Minerals and Waste Local Plan Minerals Site Specific Allocations Development Plan Document (DPD) Single Issue Silica Sand Review Sustainability Appraisal Report Non-technical summary March 2016

More information

Environmental and Social Data Sheet

Environmental and Social Data Sheet Environmental and Social Data Sheet Luxembourg, 08.09.2014 Overview Project Name: Project Number: 2013-0468 Country: Project Description: OUARZAZATE III (TOWER) Morocco Construction and operation of a

More information

5. ENVIRONMENTAL IMPACT ASSESSMENT

5. ENVIRONMENTAL IMPACT ASSESSMENT 5. ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION Environmental Impact Assessment (EIA) is a process that considers how a proposed development will change existing environmental conditions, and what

More information

Session: For more information:

Session: For more information: Session: For more information: www.hydropower.org/congress VALUE CREATION AT HYDROPOWER PROJECTS IHA World Congress 2015 Session : Macroeconomic Benefits Emmanuel Branche, EDF Senior Economist EDF Project

More information

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Agricultural Expansion on Portion 2 of Farm 92, Tregaron, known as Sylvania, Sundays River Valley Municipality BACKGROUND INFORMATION DOCUMENT,

More information

Mining & Communities

Mining & Communities Mining & Communities Supporting human rights-based development in the context of industrial mining in Guinea Abridged version of the Practical guide for civil society organizations and local authorities

More information

Hydropower Sustainability Assessment Protocol Section III Trail ESKOM. Ingula Pumped Storage Scheme. November 2009

Hydropower Sustainability Assessment Protocol Section III Trail ESKOM. Ingula Pumped Storage Scheme. November 2009 Hydropower Sustainability Assessment Protocol Section III Trail ESKOM Ingula Pumped Storage Scheme November 2009 Assessor: Rob Griffin Date: 2009-11-25 Table of Contents 1 Introductory Information... 3

More information

REQUEST FOR PROPOSALS FOR CONSULTANCY SERVICES FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR NAMPULA-CUAMBA ROAD PROJECT (ROADS 3)

REQUEST FOR PROPOSALS FOR CONSULTANCY SERVICES FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR NAMPULA-CUAMBA ROAD PROJECT (ROADS 3) GABINETE DO DIRECTOR GERAL REQUEST FOR PROPOSALS FOR CONSULTANCY SERVICES FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR NAMPULA-CUAMBA ROAD PROJECT (ROADS ) RFP No 5/DG/07 Roads and Bridges Management

More information

Two Case Studies from USAID s Multilateral Development Bank Project Review Team

Two Case Studies from USAID s Multilateral Development Bank Project Review Team IAIA18 Conference Proceedings Environmental Justice in Societies in Transition 38 th Annual Conference of the International Association for Impact Assessment 16-19 May 2018 Durban Intl. Convention Center

More information

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10.1 Objective The main objective is to confirm the implementation of mitigation measures recommended in

More information

Role of Climate Smart Agriculture in achieving Land Degradation Neutrality in Sri Lanka. Champika S Kariyawasam

Role of Climate Smart Agriculture in achieving Land Degradation Neutrality in Sri Lanka. Champika S Kariyawasam Role of Climate Smart Agriculture in achieving Land Degradation Neutrality in Sri Lanka Champika S Kariyawasam Land Degradation Neutrality- Global Developments 2012 - UN Conference on Sustainable Development

More information

AMATHOLE DISTRICT MUNICIPALITY CASE STUDY 2018

AMATHOLE DISTRICT MUNICIPALITY CASE STUDY 2018 AMATHOLE DISTRICT MUNICIPALITY CASE STUDY 2018 LOCAL ACTION FOR BIODIVERSITY: WETLANDS SOUTH AFRICA Focused wetland prioritisation in Amathole District Municipality Planning for wetland rehabilitation

More information

POLICY BRIEF. BORDERING ON A WATER CRISIS: The Need for Integrated Resource Management in the Mara River Basin

POLICY BRIEF. BORDERING ON A WATER CRISIS: The Need for Integrated Resource Management in the Mara River Basin POLICY BRIEF BORDERING ON A WATER CRISIS: The Need for Integrated Resource Management in the Mara River Basin Bordering on a Water Crisis: The Need for Integrated Resource Management in the Mara River

More information

Resolution XI.3. Adjustments to the Strategic Plan for the triennium

Resolution XI.3. Adjustments to the Strategic Plan for the triennium 11 th Meeting of the Conference of the Parties to the Convention on Wetlands (Ramsar, Iran, 1971) Wetlands: home and destination Bucharest, Romania, 6-13 July 2012 Resolution XI.3 Adjustments to the Strategic

More information

Ecosystem conservation and restoration initiatives in Zimbabwe. Chip Chirara Biodiversity Coordinator Livingstone 15 May 2014

Ecosystem conservation and restoration initiatives in Zimbabwe. Chip Chirara Biodiversity Coordinator Livingstone 15 May 2014 Ecosystem conservation and restoration initiatives in Zimbabwe Chip Chirara Biodiversity Coordinator Livingstone 15 May 2014 Overview of Environmental Policies and Strategies Zimbabwe has fairly policies

More information

Category Environmental Item Main Check Items Confirmation of Environmental Considerations

Category Environmental Item Main Check Items Confirmation of Environmental Considerations al Checklist: 2. Oil and Natural Gas Development 1 1 Permits and Explanation 2 Mitigation (1) EIA and al Permits (2) Explanation to the Public (1) Air Quality (2) Water Quality (3) Wastes Have EIA reports

More information

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4.1 INTRODUCTION This section describes the broad principles of the methodology adopted for the EIA of the Proposed Development. EIA is a procedure required

More information