PRELIMINARY TECHNICAL NOTE RTS/003/2015 SABESP'S EXTRAORDINARY TARIFF REVISION
|
|
- Cornelia Atkins
- 6 years ago
- Views:
Transcription
1 PRELIMINARY TECHNICAL NOTE RTS/003/2015 SABESP'S EXTRAORDINARY TARIFF REVISION March 2015
2 PRELIMINARY TECHNICAL NOTE - SABESP'S EXTRAORDINARY TARIFF REVISION TABLE OF CONTENTS 1. INTRODUCTION OVERVIEW BRIEF HISTORY THE EXTRAORDINARY TARIFF REVISION REQUESTED BY SABESP INCREASE IN ELECTRIC POWER COST GROUNDS REDUCTION IN THE WATER DEMAND CAUSED BY THE WATER CRISIS GROUNDS ARSESP'S ANALYSIS OF SABESP'S REQUEST FOR EXTRAORDINARY TARIFF REVISION VARIATIONS IN THE ELECTRIC POWER COST VARIATIONS IN THE DEMAND FOR WATER AND SANITARY SEWER SYSTEM TARIFF ADJUSTMENT REPOSITIONING INDEX OF THIS EXTRAORDINARY TARIFF REVISION ANNUAL ADJUSTMENT OF TOTAL TARIFF ADJUSTMENT FINAL REMARKS
3 1. INTRODUCTION The purpose of this Technical Note is to present the preliminary results produced by ARSESP for SABESP's Extraordinary Tariff Revision [Revisão Tarifária Extraordinária - RTS], requested by the Concessionaire through Official Letter P-0096/2015 of March 06, 2015, which will be submitted to public consultation and hearing. The basic data used to establish the new authorized tariff level derive from the new estimates made by SABESP in March 2015, subject of Administrative Proceeding In addition to the data sent by SABESP, the following data were considered to prepare this Technical Note: the result of SABESP's First Ordinary Tariff Revision [Revisão Tarifária Ordinária - RTO], focused on the business plan projections related to the events that led to the RTE; ARSESP's analyses during this process; the legislation in force; and the current water crisis scenario. This Extraordinary Tariff Revision uses the same methodology employed in the process of the First Ordinary Tariff Revision, whose results were presented in the Final Technical Note RTS/004/2014 and published in ARSESP's Resolution no. 484/2014, available on the Agency's website OVERVIEW BRIEF HISTORY The 2007 State Supplementary Law 1025 establishes that it is incumbent upon ARSESP to regulate and inspect the basic sanitation services, which include tariff issues. Based on these duties and under the legislation, in 2011 ARSESP began the First Tariff Revision process for SABESP, for the tariff cycle of 2012 to As a result of the issues identified by SABESP and ARSESP during this process, especially the determination and validation of the assets basis, ARSESP concluded the tariff revision in April 2014, and established the tariff repositioning index of % in relation to the tariffs in force at the time, as such index ensured the concessionaire's economic and financial balance in the tariff cycle and the Efficiency Factor (X Factor) set as % to be applied to the next annual adjustments, to be made in April 2015 and April The results were published by ARSESP through Resolution no. 484/2014 and Final Technical Note RTS/004/2014. However, due to the water crisis, in early 2014 SABESP asked for ARSESP's authorization to implement a Water Consumption Reduction Incentive Program for consumers of the Metropolitan Region served by the Cantareira water system, in order to ensure water supply. This program, which was approved by ARSESP Resolution no. 469/2014 of February/2014, aimed at granting a 30% tariff discount to users that reduced their monthly water consumption by at least 20% in relation to their average consumption in the period from February/2013 to January/
4 As the water crisis persisted, the Water Consumption Reduction Incentive Program was extended to all cities of the Metropolitan Region of São Paulo served by SABESP, and such extension was approved by ARSESP Resolution no. 480/2014. Later on, ARSESP authorized SABESP to increase the tariff bonus ranges of the Water Consumption Reduction Incentive Program, and give a bonus to users whose reduction was higher than 10% as of November 1, 2014, as established in ARSESP Resolution no. 514/2014. In this scenario of water crisis and adoption of measures to stimulate water savings, when the result of SABESP's First Tariff Revision was published in April 2014 ARSESP authorized the concessionaire to apply, on a future date, the repositioning index resulting from the tariff revision, as established in art. 1 of ARSESP Resolution no. 484/2014, which approved the Ordinary Tariff Revision (RTO) that had been concluded. Article 1, item III, of ARSESP Resolution no. 484/2014 also established that the next tariff adjustments would occur on April 11, 2015 and April 11, 2016, and that the next tariff revision would occur on April 11, In November/2014, Sabesp asked for ARSESP's authorization to apply the results of the RTO approved in April/2014, recalculating the amounts as a result of the application in December/2014. Therefore, ARSESP authorized SABESP to apply the % index as of December 27, 2014, which corresponds to the % index approved in the end of the Tariff Revision in April plus 1% on account of compensation for the postponement in its application, as published in ARSESP Resolution no. 520/2014. It is worth pointing out that such authorized index did not include any compensation to SABESP for decreased income caused by the Water Consumption Reduction Incentive Program that was in effect. Tariff discounts in relation to the maximum tariff approved by the regulatory body may be granted by the Concessionaire, but they do not justify a request for compensation. In January/2015, as the water crisis persisted, ARSESP authorized SABESP to apply the Contingency Tariff to users covered by the Water Consumption Reduction Incentive Program who exceeded the average consumption established, under the terms of ARSESP Resolution no. 545/
5 2. THE EXTRAORDINARY TARIFF REVISION REQUESTED BY SABESP The extraordinary tariff revision is an instrument established in art. 38, item II, of Federal Law no /2007, which provides that the revision will revaluate the conditions for the service provision and tariffs charged when facts not established in the agreement occur, facts that cannot be controlled by the service provider and that change its economic and financial balance. Upon publication of the Final Technical Note RTS/01/2012, which establishes the detailed methodology to be employed in SABESP's tariff revision, ARSESP defined that the events giving rise to an extraordinary tariff revision are those that: occur during the Tariff Cycle; for the most part cannot be controlled by the company; were not addressed in the Tariff Revision; and have a significant impact on the balance. In addition, when the request for extraordinary tariff revision was on SABESP's initiative, the request has to be submitted to ARSESP by means of a document specifying: the extraordinary event(s); the elements of the balance equation that were affected by the event (that is, the elements that were in disagreement with what was established in the tariff revision); a preliminary measurement of the (significant) impact on the company's economic and financial balance. Thus, on March 06, 2015, SABESP sent to ARSESP Official Letter P-0096/2015 requesting an Extraordinary Tariff Revision, with the Technical Note enclosed detailing the information. The events that caused SABESP to request an extraordinary tariff revision are: Increase in the electric power cost; Reduction in the water demand caused by the water crisis. These items will be detailed below. 2.1 INCREASE IN ELECTRIC POWER COST GROUNDS Two facts increased the costs of electric power generation and distribution: the water crisis that affects the hydroelectric power production (and has been adversely affecting the production and distribution of water by SABESP) and its combination with the effects of Federal Law 12783/2013. The criteria and premises used by SABESP to calculate the expenses estimated for 2015 and 2016 are explained below. For 2013 and 2014, the amounts indicated in table 2.1 (below) are realized amounts. 5
6 In 2014, 55% of the electric power used by SABESP came from electricity distributors (Regulated Contracting Environment [Ambiente de Contratação Regulada - ACR]) and 45% came from Free Contracting Environment [Ambiente de Contratação Livre - ACL], a total of 2,387 GWh; Electric power adjustments of the distributors with which SABESP is connected, through the increase in the price of electric power purchased by these distributors in the Short- Term Market in 2015 and 2016; The introduction, as of 2015, of the Tariff Flags system in the electricity bills, based on the evaluation of the National Electric System Operator [Operador Nacional do Sistema Elétrico - ONS], which defines the best strategy for thermal power plants to generate power and meet the demand. SABESP adopted the red flag for the most part of 2015 and the yellow flag for 2016; Non-application of the 15% discount of the sanitation sector to the additional amount referring to tariff flags as of March 2015, according to a resolution of the National Agency of Electric Power [Agência Nacional de Energia Elétrica - ANEEL], which increased the cost for SABESP; As of February 2015, application by ANEEL of Extraordinary Tariff Revision for all 58 electricity distributors; Based on the inflation estimate (measured by the Broad Consumer Price Index [Índice de Preços ao Consumidor Amplo - IPCA]), adjustment in the Tariff of Use of the Electricity Distribution System [Tarifas de Uso do Sistema de Distribuição - TUSD] and the Electric Power Tariff [Tarifa de Energia - TE] applicable to the electricity volume purchased in the ACR for For 2016, the IPCA was applied again, and part of the loans intended to bail out electricity distributors is expected to be paid; Elimination of the conventional tariff category by ANEEL, in the captive market of distributors where SABESP operates, which enabled purchase of electricity in voltage higher than 1 kv at lower costs. The elimination of the conventional tariff category as of 2015 entails classification in the blue or green time-season tariff categories, which means increased costs; With regard to the costs of electricity agreements in the Free Contracting Environment (ACL), the premise is that the electric power for the estimated load be adjusted by the General Price Index - Market [Índice Geral de Preços - Mercado IGPM]. The agreements in force end in December New agreements will take effect as of January 2016; For 2016, SABESP already has agreements to supply 40% of the load established in the ACL, with adjustments by IGPM; The remaining 60% supplied by the ACL will be contracted, and prices are estimated to be higher due to the current market conditions, with high prices and low liquidity. The electric power management strategy adopted by SABEST in the ACL establishes that the company will not work with risks resulting from an electric power transaction (exposição) (no contract) with the Electric Power Trade Chamber [Câmara de Comercialização de Energia Elétrica - CCEE]; 6
7 As to the electric power TUSD in the free market, the IPCA is estimated to be applied to the TUSD, using the same parameters of tariff Adjustments in ACR, TUSD and TE; and Increase in electric power consumption in 2015 and 2016: In 2015, SABESP estimates a consumption growth of 1.87% over 2014, which corresponds to 2,432 GWh (57% in the ACR and 43% in the ACL), resulting from the start-up of operations of new sewage pumping stations and maintenance of consumption levels in the cities outside the Metropolitan Region of São Paulo, despite the estimated reduction in water production and distribution and sewage collection for the year; In 2016, the estimate for electric power consumption is 2,681 GWh, which corresponds to a 10.26% increase over 2015, as a result of the resumption of water consumption levels. The table 2.1 below shows a summary of amounts realized (2013 and 2014) and projected ( ) by SABESP for electric power consumption and expenses. Table 2.1 Summary of electric power consumption and expenses for the period of Values in R$ millions at current prices Historical and Estimate of Electric Power Consumption GWh Description Variation (2015/2014) 2016 Variation (2016/2015) ACL Consumption % % ACR Consumption 1, % % TOTAL Consumption 2, % % Historical and Estimate of Electric Power Expenses R$ million Description Variation (2015/2014) 2016 Variation (2016/2015) ACL: electric power expenses % % Adjustment of agreements Tax variation Consumption variation ACL: TUSD expenses % % RTE in TUSD Tariff adjustment Consumption variation Previous year s adjustments residual effect ACR: Electric Power + TUSD expenses % % Consumption variation Residual effect of adjustments of the previous year Elimination of tariff categories Flags RTE Tariff adjustment published until Mar/ Estimated tariff adjustment TOTAL expenses % 1, % 7
8 As demonstrated in table 2.2 below, for 2013 and 2014 the realized amounts are nearly 1.5% above the amounts estimated in the Business Plan of the Ordinary Tariff Revision (RTO). For 2015 and 2016, SABESP projected an increase of 55.5% and 96.2%, respectively, in relation to the amounts projected previously. Table 2.2 Comparison of the electric power costs realized and projected by SABESP for Values in R$ millions at prices of December/2012 Description Electric power costs (R$ thousands) Realized Estimate Business Plan (RTO) 527, , , ,359 Realized and SABESP s Projection 535, , ,750 1,040,110 (RTE) Variation (RTE/RTO) 1.56% 1.49% 47.55% 85.28% 2.2 REDUCTION IN THE WATER DEMAND CAUSED BY THE WATER CRISIS GROUNDS In accordance with the Technical Note presented by SABESP, to complement Official Letter P- 0096/2015, the month-by-month comparison of the flow of the Cantareira system for 2014 demonstrates that there was a significant reduction in such flow, which is a rare and extreme event, without a specific frequency and therefore unpredictable. As a result of such decrease, there was a 25% reduction in water production in the Metropolitan Region of São Paulo, from 70 m³/s in January 2013 to 52 m³/s in January This event changed the water demand, as consumers had economic incentives (bonus and contingency tariff) to reduce consumption as an alternative to a more severe reduction in the water supply. The variations between the estimated amounts and the realized amounts of physical data related to the demand from 2012 to 2014 are presented in table 2.3. In 2014, there was a 7.85% reduction in the total measured volume in comparison with the volume estimated in the Business Plan approved in the RTO. 8
9 Table 2.3 Estimated demand data in the business plan and data realized to 2014 Description WATER SEWAGE TOTAL Connections Business Plan (RTO) 7,013,260 7,182,670 7,356,128 5,692,333 5,996,650 6,245,153 12,705,593 13,179,320 13,601,281 Realized (RTE) 7,006,288 7,184,610 7,475,771 5,686,826 5,866,535 6,161,134 12,693,114 13,051,145 13,636,905 Variation -0.10% 0.03% 1.63% -0.10% -2.17% -1.35% -0.10% -0.97% 0.26% Savings Business Plan (RTO) 9,544,740 9,715,017 9,934,487 7,998,082 8,329,044 8,658,279 17,542,822 18,044,061 18,592,766 Realized (RTE) 9,512,280 9,777,078 10,201,745 7,992,956 8,260,431 8,688,581 17,505,236 18,037,509 18,890,326 Variation -0.34% 0.64% 2.69% -0.06% -0.82% 0.35% -0.21% -0.04% 1.6% Measured Volume Business Plan (RTO) 1,894,880 1,927,115 1,968,777 1,377,036 1,440,100 1,495,262 3,271,916 3,367,215 3,464,038 Realized (RTE) 1,895,264 1,926,895 1,821,224 1,379,529 1,414,224 1,370,832 3,274,793 3,341,118 3,192,056 Variation 0.02% -0.01% -7.49% 0.18% -1.80% -8.32% 0.09% -0.78% -7.85% Billed Volume Business Plan (RTO) 2,097,632 2,133,316 2,179,436 1,524,379 1,594,191 1,655,255 3,622,011 3,727,507 3,834,691 Realized (RTE) 2,088,635 2,131,455 2,058,413 1,533,242 1,577,670 1,564,433 3,621,876 3,709,125 3,622,846 Variation -0.43% -0.09% -5.55% 0.58% -1.04% -5.49% 0.00% -0.49% -5.52% SABESP also presented a new projection of the physical data related to the demand for the remaining period of the tariff cycle - years of 2015 and 2016, shown in table 2.4. To define the new projected physical data, SABESP considered that there will be no reversal of, but rather increase in, the trend for reduction in the volume measured for In 2016, the volume will grow again in relation to 2015, but it will not reach the consumption levels projected before the crisis. Table 2.4 Projected demand data and 2016 Description WATER SEWAGE TOTAL Connections Business Plan (RTO) 7,531,193 7,706,776 6,499,095 6,758,447 14,030,288 14,465,223 New estimate (RTE) 7,587,995 7,764,995 6,348,000 6,601,000 13,935,995 14,365,995 Variation 0.75% 0.76% -2.32% -2.33% -0.67% -0.69% Savings Business Plan (RTO) 10,155,857 10,377,801 8,994,843 9,338,682 19,150,700 19,716,483 New estimate (RTE) 10,429,995 10,672,995 9,031,000 9,391,000 19,460,995 20,063,995 Variation 2.70% 2.84% 0.40% 0.56% 1.62% 1.76% Measured Volume Billed Volume Business Plan (RTO) 2,010,749 2,052,934 1,551,620 1,609,261 3,562,368 3,662,195 New estimate (RTE) 1,712,022 1,887,780 1,334,169 1,493,745 3,046,190 3,381,525 Variation % -8.04% % -7.18% % -7.66% Business Plan (RTO) 2,225,899 2,272,598 1,717,643 1,781,452 3,943,542 4,054,050 New estimate (RTE) 1,937,469 2,136,173 1,524,599 1,706,474 3,462,068 3,842,647 Variation % -6.00% % -4.21% % -5.21% 9
10 3. ARSESP'S ANALYSIS OF SABESP'S REQUEST FOR EXTRAORDINARY TARIFF REVISION The Extraordinary Tariff Revision (RTE), depending on the reason and circumstances that led to it, may be limited to a specific fact or have a more general nature, with a complete revision of the service provision conditions. Likewise, and according to the evaluation of the regulatory entity, it may be applied only to the remaining period of the tariff cycle under way, or a new and complete tariff cycle may be initiated. Given the urgent nature of an Extraordinary Tariff Revision, and recognizing the impact of the water crisis, and consequent reduction in the demand, and the changes in the electric power costs on SABESP's economic and financial situation, ARSESP decided to grant the request of this RTE. In the case of SABESP's Extraordinary Tariff Revision, ARSESP understands that the water crisis will set new paradigms for the provision of water and sewage services as to aspects of demand and supply, given that such water reduction was not anticipated when SABESP's business plan was approved in the Ordinary Tariff Revision concluded in early Its effects and impacts will be known only in the medium term. ARSESP adopted new projections for 2015 and 2016 related to the parameters mentioned above, whose deviations will be assessed by the end of the tariff cycle, and compensatory measures will be adopted in the following cycle, if necessary. It is worth pointing out that, given the severity of the water crisis, the projections presented have a degree of uncertainty as to the new consumption level, the offer of water and sewage services, and the new scenario of the electric power sector, which will be known once the effects of the crisis are clear. The adoption of measures by SABESP to reduce costs and improve operating efficiency to manage the crisis may contribute to reduce the physical and financial impacts of the water shortage. Likewise, the Concessionaire must carefully analyze its discount policy, in order to protect the economic and financial situation of the Company. Finally, it is important to clarify that the reduction in SABESP's revenue caused by discounts (bonus) granted to users under the Water Consumption Reduction Incentive Program is not being offset; in the price cap category (regulação por preço máximo), granting tariff discounts is a prerogative of the service provider, therefore not subject to future offset. 3.1 VARIATIONS IN THE ELECTRIC POWER COST In the Ordinary Tariff Revision concluded in early 2014, considering that the electric power expenses represent a significant part of SABESP's operating expenses (OPEX), ARSESP adopted a 15% discount in the unit costs of electric power originally estimated in the company's Business Plan, as a result of the enactment of Law no /2013 (see Final Technical Note RTS/004/2014 item 7.3). Such measure was adopted after comparison between the electric power unit cost of January to September/2013 (after such law was enacted) and the unit cost of the same period in 10
11 2012. Therefore, the conclusion was that a new level of electric power costs had been set, and it was projected for the remaining period of the tariff cycle. However, this scenario changed significantly by the end of 2013, as indicated in item 2.1 of this Technical Note, and that raised the electric power costs projected by SABESP. The nominal unit costs resulting from the amounts presented in table 2.1 are: R$ /MWh for 2013; R$ /MWh for 2014; R$ /MWh for 2015; and R$ /MWh for To quantify the impact of this cost increase on SABESP's maximum tariff (P 0 ), ARSESP revaluated the Discounted Cash Flow [Fluxo de Caixa Descontado - FCD] of the period presented in the Ordinary Tariff Revision (Chart 12.1 of Technical Note RTS/004/2014). To that effect, the agency used the new electric power unit costs realized ( ) and projected ( ) by SABESP, mentioned above, to assess the actual annual variation of the unit cost, used as an indicator of such cost increase. Table 3.1 below shows the annual actual variation of the electric power unit costs at constant prices of Dec/2012 (currency used in the Discounted Cash Flow presented in the Ordinary Tariff Revision), obtained from the above-mentioned unit costs considering the IPCA variations used in SABESP's projections. Table 3.1 Actual Increase in Power Unit Costs Year IPCA Electric Power Cost (R$/MWh) Variation Dec/Dec (*) Index Dec (*) Year Average Index Nominal Actual** Prices Dec/12 Actual Δ on previous year Actual accrued Δ % 3, , % 3, , % % , , % -7.22% % 4, , % 30.74% % 4, , % 52.59% (*) Used by SABESP to estimate electric power costs. (**) Actual electric power costs at prices of Dec/2012 = nominal cost of year X (year average index / index of Dec/12) 11
12 These actual variations were applied to all electric power unit costs used by ARSESP's Economic and Financial Model to calculate the new power expenses taken into account in this Extraordinary Tariff Revision for the period , thus using the same methodology employed in the Ordinary Tariff Revision concluded in April VARIATIONS IN THE DEMAND FOR WATER AND SANITARY SEWER SYSTEM The Economic and Financial Model used by ARSESP in the tariff revision process makes the market projections contained in SABESP's Business Plan based on estimates of unit consumption for residential users and on annual growth rates for non-residential users and permit holders. It is worth mentioning that, when the result of the Ordinary Tariff Revision (RTO) was published, the demand data for 2011 and 2012 were already known, and therefore were considered to calculate the P 0. ARSESP evaluated the total measured and billed volumes realized in this tariff cycle and found that the projection in the RTO for 2013 was in line with the values effectively realized. However, reductions of 7.85% and 5.52% in the total volumes measured and billed, respectively, were found for 2014 in relation to those estimated in the Business Plan. Such reduction was caused exclusively by the reduced offer, a result of the water crisis (see Table 2.3). After analysis of the data, ARSESP accepted the demand projections presented by SABESP and understands that the current scenario still does not enable an accurate definition of the water crisis effects. Tables 3.2 and 3.3 demonstrate the values considered by ARSESP to calculate the new repositioning index of this RTE. Table 3.2 Data of water supply demand considered in the RTE Description WATER SUPPLY Realized Estimated CONNECTIONS Unit 7,006,288 7,184,610 7,475,771 7,587,995 7,764,995 (December) Annual 2.79% 2.55% 4.05% 1.50% 2.33% Δ Residential 6,276,408 6,443,267 6,686,229 6,796,751 6,955, Commercial (includes 633, , , , ,791 Proprietary Buildings) Industrial 60,935 61,778 65,519 66,503 68, Public 35,186 35,345 36,446 36,993 37, SAVINGS (December) Unit 9,512,280 9,777,078 10,201,745 10,429,995 10,672,995 Annual 2.99% 2.78% 4.34% 2.24% 2.33% Δ Residential 8,773,077 9,027,246 9,412,232 9,622,818 9,847, Commercial (includes 642, , , , ,121 Proprietary Buildings) Industrial 60,939 61,788 65,562 67,029 68, Public 35,542 35,372 36,582 37,400 38,272 12
13 3 MEASURED VOLUMES Unit 1,895,264,433 1,926,894,676 1,821,223,935 1,712,021,589 1,887,779,693 (Annual total m3) Annual 2.22% 1.67% -5.48% -6.00% 10.27% Δ 3.1 Retail 1,598,252,774 1,627,462,343 1,574,385,433 1,492,228,440 1,648,077, Residential 1,361,433,616 1,387,703,486 1,346,842,446 1,276,559,450 1,409,883, Commercial (includes 148,554, ,788, ,979, ,570, ,624,739 Proprietary Buildings) Industrial 35,400,586 38,244,817 35,444,563 33,594,941 37,103, Public 52,863,726 52,725,190 50,119,291 47,503,889 52,465, Permit holder 297,011, ,432, ,838, ,793, ,702, BILLED VOLUME (Annual Unit 2,088,634,690 2,131,455,167 2,058,412,660 1,937,469,145 2,136,172,959 total m3) Annual Δ 1.76% 2.05% -3.43% -5.88% 10.26% Table 3.3 Data of sanitary sewer system demand considered in the RTE Description SANITARY SEWER SYSTEM Realized Estimate CONNECTIONS Unit 5,686,826 5,866,535 6,161,134 6,348,000 6,601,000 (December) Annual 3.53% 3.16% 5.02% 3.03% 3.99% Δ Residential 5,052,136 5,218,653 5,476,169 5,642,260 5,867, Commercial (includes 555, , , , ,507 Proprietary Buildings) Industrial 51,356 52,000 55,414 57,095 59, Public 27,354 27,768 28,925 29,802 30, SAVINGS (December) Unit 7,992,956 8,260,431 8,688,581 9,031,000 9,391,000 Annual 3.72% 3.35% 5.18% 3.94% 3.99% Δ Residential 7,348,998 7,603,897 7,993,484 8,308,509 8,639, Commercial (includes 565, , , , ,985 Proprietary Buildings) Industrial 511,356 52,000 55,448 57,633 59, Public 27,381 27,790 29,029 30,173 31,376 3 MEASURED VOLUMES Unit 1,379,528,939 1,414,223,665 1,370,832,391 1,334,168,539 1,493,745,048 (Annual total m3) Annual 7.18% 2.51% -3.07% -2.67% 11.96% Δ 3.1 Retail 1,352,192,731 1,384,827,669 1,346,593,765 1,291,450,599 1,447,155, Residential 1,131,388,974 1,159,657,391 1,130,982,110 1,084,668,265 1,215,442, Commercial (includes 140,705, ,029, ,155, ,538, ,397,971 Proprietary Buildings) Industrial 38,758,701 41,769,828 39,417,425 37,803,277 42,361, Public 41,339,303 41,370,849 39,038,820 37,440,176 41,954, Permit holder 27,336,208 29,395,996 24,238,626 4,717,940 46,589, BILLED VOLUME (Annual Unit 1,533,241,743 1,577,669,916 1,564,433,350 1,524,599,169 1,706,473,757 total m3) Annual Δ 7.61 % 2.90% -0.84% -2.55% 11.93% 13
14 4. TARIFF ADJUSTMENT 4.1. REPOSITIONING INDEX OF THIS EXTRAORDINARY TARIFF REVISION The new level for the Maximum Price (P 0 ) established in this RTE includes the cumulative effect, in the Discounted Cash Flow, of the two components that gave rise to this RTE, namely: i) adjustments due to reduction in the demand for services, caused by a decreased supply resulting from the water crisis; and ii) adjustments due to the increase in the electric power costs caused by changes in the energy industry. To generate the Discounted Cash Flow for this RTE, the changes made in the original Business Plan used in the Ordinary Tariff Revision exclusively refer to the above-mentioned variations in the demand for water and sewage services and in the electric power costs. With regard to the demand (connections, savings and volumes), the data realized for 2013 and 2014 and new projections for 2015 and 2016 were used, as previously presented. To determine the new electric power costs, the actual increases mentioned in item 3.1 of this technical note were applied to the unit costs related to the projection basis used in the RTO (2012). The other components of the OPEX were re-projected by the Economic and Financial Model based on the new demand that was considered. For the other components used to calculate the Maximum Price (Basis of Assets, Investments and other items not affected by the demand variations), the amounts of the Business Plan approved for the Ordinary Tariff Revision were maintained. Changes in these items were not the subject of the request in this RTE, and no new Business Plan was developed. All projections of FCD still refer to prices of Dec/2012, which was the original currency used in the Business Plan of the 1st Ordinary Tariff Revision. Table 4.1 below shows the FCD with the adjustments to the demand and to the electric power cost subject of this RTE, as well as its effects on other components used to calculate the maximum price (P 0 ). 14
15 Table 4.1 Discounted Cash Flow - RTE Description Formula Elements 2012 Present Value Tariff Cycle (R$ Dec/2012) Billed volume (A+E) - (1000m3) VF 12,096,945 3,709,125 3,622,846 3,462,068 3,842,647 + Direct required revenue (tariff) RRD 32,388,192 93,930,760 9,699,758 9,269,294 10,288,249 + Indirect revenue RI 632, , , , ,079 + Other Revenue RN 46,296 13,997 13,997 13,997 13,997 - COFINS/PASEP COP 2,413, , , , ,670 - Operating expenses (OPEX) OPEX 14,275, ,454 4,144,735 4,300,613 4,721,822 - Irrecoverable revenue (bad debt) INC 652, , , , ,188 - Income tax/social contribution IRCS 4,315,208 1,411,289 1,341,448 1,141,354 1,303,316 - Investments CAPEX 7,596,528 2,403,450 2,275,913 2,126,199 2,370,128 - Works in progress remuneration JOAR 459, , , , ,274 - Working capital variation DWK 43, ,957-23,544-91,608 15,400 - Initial base of capital BRL0 26,733, Final base of capital BRLT 23,423, ,938,139 = Free cash flow + Bdk VPL = 0,00-26,733, ,282 1,103, ,059 32,934,664 P 0 Calculated (Dec/12 prices) = R$ / m3 IRR = 8.060% As seen above, the Maximum Price resulting from the adjustments in SABESP's Business Plan considered for this first Extraordinary Tariff Revision, at prices of Dec/2012, is R$ /m3 which, if compared to the value of the first Ordinary Tariff Revision (R$ /m3), results in a Repositioning Index of % ANNUAL ADJUSTMENT OF 2015 In April 2014, upon publication of the repositioning index of % on the tariffs in force at the time resulting from the RTO, whose publication was estimated for May 11, 2014, the tariffs were adjusted for inflation based on the IPCA variation until March The next annual tariff adjustment occurs on May 11, 2015, effective on May 11, 2015, as published in ARSESP Resolution no. 484/2014. Thus, it is necessary to adjust for inflation the Maximum Price (P 0 ) in force for the price of March 2015, which corresponds to the 12-month period since the approval of the Ordinary Tariff 15
16 Revision. It will be adjusted based on the IPCA variation in the period from March 2014 to March When this Technical Note was concluded, the IPCA variation index for March 2015 had not been published yet. An estimate of IPCA variation of 1.2% (March 2015) was temporarily used to calculate the Maximum Price, which results in an IPCA variation of 8% accrued in 12 months. This estimate will be duly adjusted when the official index for March 2015 is published. According to Technical Note RTS/004/2014, the annual X Factor of % must be deducted at each tariff adjustment. Thus, the annual adjustment estimated for 2015 is % TOTAL TARIFF ADJUSTMENT Considering the cumulative effect of the Extraordinary Tariff Revision and of the 2015 annual adjustment, described in items 4.1 and 4.2, respectively, the total tariff adjustment will be %, which corresponds to the application of % to the tariff in force, resulting from the Extraordinary Tariff Revision, and then application of % of inflation adjustment by IPCA minus the X Factor. Table 4.2 Total Tariff Adjustment RTE Result 6.36% 2015 Adjustment 7.06% IPCA* 8.00% X Factor 0.94% Total Adjustment (RTE+Adjustment) 13.87% * Considering an estimate of 1.2% for March/2015 The total tariff adjustment, which will include the official IPCA of March 2015, will be applied to the tariffs currently in force, whose amounts will be disclosed in the Final Technical Note to be prepared after the end of the public consultation and public hearing. These values may be applied 30 days after their publication, under Law 11445/
17 5. FINAL REMARKS After analysis of the request for Extraordinary Tariff Revision submitted by SABESP, ARSESP decided to grant it, making changes to the unit costs of electric power and to the demand components in the business plan, and keeping the methodology used in the First Ordinary Tariff Revision concluded in April This Extraordinary Tariff Revision concerns the remaining period of the current tariff cycle and it may be applied at any time. The estimated date for the next tariff adjustment continues to be April 2016, and the next ordinary tariff revision will occur in April It is important to point out that, since this is an extraordinary tariff revision, there is no minimum frequency established in the legislation; it may occur at any time, irrespective of the date the previous tariff adjustments occurred. The evaluations to be carried out in the end of the current tariff cycle will also consider the effects of this RTE to determine any compensatory adjustments for the following cycle, in order to ensure the economic and financial balance of the Concessionaire. We reiterate that the loss of income caused by bonus granted by the Concessionaire is not being considered in this RTE and cannot be offset through tariffs. Therefore, SABESP should evaluate its discount policy, which is a prerogative of the Concessionaire, considering the balance in the provision of services. 17
GOOD PRACTICES IN CITY ENERGY EFFICIENCY. Campinas, Brazil Energy Management in the Provision of Water Services
GOOD PRACTICES IN CITY ENERGY EFFICIENCY Campinas, Brazil Energy Management in the Provision of Water Services Energy Sector Management Assistance Program (ESMAP) reports are published to communicate the
More informationTARIFF ASSESSMENT: HELPING THE ENERGY CONSUMER TO GET THE BEST TARIFF
TARIFF ASSESSMENT: HELPING THE ENERGY CONSUMER TO GET THE BEST TARIFF Carlos C. Barioni de OLIVEIRA Cristiano da Silva SILVEIRA Mauro Manoel MACHADO Daimon Engineering Brazil Daimon Engineering Brazil
More informationNATIONAL ELECTRICITY RULES ELECTRICITY CONNECTION FOR RETAIL CUSTOMERS CHAPTER 5A. Page 615
ELECTRIC ITY CONN ECTION FOR RET AIL CU STOM ERS NATIONAL ELECTRICITY RULES Page 615 Chapter 5A Electricity connection for retail customers Part A 5A.A.1 Preliminary Definitions In this Chapter: basic
More informationFFQA 1. Complied by: Mohammad Faizan Farooq Qadri Attari ACCA (Finalist) Contact:
FFQA 1 Objective of IAS 2 The objective of IAS 2 is to prescribe the accounting treatment for inventories. It provides guidance for determining the cost of inventories and for subsequently recognising
More informationBusiness Plan Template (For a Start-up Business)
Business Plan Template (For a Start-up Business) Your Business Name ABN Number Address Line 1 Address Line 2 City, State Postcode Telephone Fax E-Mail 1/15 Table of Contents Table of Contents... 2 Executive
More informationBrazil. North Northeast. Central West. Southeast. South. estimated population Dec million inhabitants
MOBILIZING FINANCING FOR URBAN INFRASTRUCTURE World Bank Conference ASER CORTINES Caixa Econômica Federal Vice-President for Urban Development and Government Jaipur, January, 2005 Brazil - overview Caixa
More informationSri Lanka Accounting Standard LKAS 2. Inventories
Sri Lanka Accounting Standard LKAS 2 Inventories CONTENTS paragraphs SRI LANKA ACCOUNTING STANDARD LKAS 2 INVENTORIES OBJECTIVE 1 SCOPE 2 5 DEFINITIONS 6 8 MEASUREMENT OF INVENTORIES 9 33 Cost of inventories
More informationSection 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.
Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required
More informationResults 2Q15_. Investor Relations Telefônica Brasil S.A. July, Investor Relations Telefônica Brasil S.A.
Results _ July, 2015. Disclaimer For the first time, in this quarter we are presenting pro forma numbers combining Telefônica Brasil and GVT results for all financial and operational indicators. For a
More informationPresentation to CTA: Electricity Pricing Assessment for Mozambique
Presentation to CTA: Electricity Pricing Assessment for Mozambique Donald Hertzmark Nathan Associates June 2008 Maputo, Mozambique Electricity Pricing Analysis Objectives Assess cost and quality of electricity
More informationCHAPTER 6. Inventory Costing. Brief Questions Exercises Exercises 4, 5, 6, 7 3, 4, *14 3, 4, 5, 6, *12, *13 7, 8, 9, 10, 11, 12, 13
CHAPTER 6 Inventory Costing ASSIGNMENT CLASSIFICATION TABLE Study Objectives Brief Questions Exercises Exercises Problems Set A Problems Set B 1. Describe the steps in determining inventory quantities.
More informationELECTRIC COST OF SERVICE AND RATE DESIGN STUDY
DRAFT Report ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY Navajo Tribal Utility Authority August 2007 DRAFT NAVAJO TRIBAL UTILITY AUTHORITY ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY Table of Contents
More informationCommitted Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day.
Proposed Tariff Revisions Attachment K-Appendix and Schedule 1 of the Operating Agreement Generator Offer Flexibility Senior Task Force Revisions Related To Make-Whole and Lost Opportunity Cost Payments
More informationINCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS. Activities carried out and further guidelines
CONSULTATION DOCUMENT 645/2017/R/EEL INCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS Activities carried out and further guidelines Consultation document as part of the proceeding
More informationPre-Engagement Activities and Audit Planning By: Tariq Mahmood FCA, ACMA
Model Audit Practice Manual Pre-Engagement Activities and Audit Planning By: Tariq Mahmood FCA, ACMA Today s Learnings Pre-Engagement Activities Audit Planning Procedures Completion of Sample Forms (Annexures)
More informationElectricity Distribution Services Default Price-Quality Path Draft Determination 2015
ISSN 1178 2560 Decision Series Project no. 14.07/14118 Public version Electricity Distribution Services Default Price-Quality Path Draft Determination 2015 Mark-ups by Vector Limited for submission purposes
More informationInvestor Presentation. Santander Conference January 12 14, 2016
Investor Presentation Santander Conference January 12 14, 2016 Forward Looking Statements This presentation contains certain forward-looking statements and information relating to Grupo Rotoplas S.A.B.
More informationMusterreport Softwareentwickler
10.07.2017 22994 Report number Compensation-Online Hoheluftchausee 18 20253 Hamburg Tel.: 040 42 10 47 5-0 Fax: 040 42 10 47 5-25 Services GmbH powered by 1. Your Data These data were selected by you to
More informationBANQUE CARNEGIE LUXEMBOURG REMUNERATION POLICY
BANQUE CARNEGIE LUXEMBOURG REMUNERATION POLICY JANUARY 2017 Adopted by Board of Directors of Banque Carnegie Luxembourg S.A. (the Bank ) Date 31 January 2017 Previous adoption 25 May 2016 To be revised
More informationEnergy Retailers Association of Australia. South Australian Energy Market Reform one year on
Energy Retailers Association of Australia South Australian Energy Market Reform one year on 11 February 2014 This page left intentionally blank 2 Contents Executive summary 4 1 Introduction 7 1.1 Competition
More informationStandards on Auditing
Standards on Auditing 1. SA 320 (Revised) Materiality in Planning and Performing an Audit 2. SA 530 (Revised) Audit Sampling 1 SA 320 (Revised) Materiality in Planning and Performing an Audit 2 Scope:
More informationCARTAGENA, COLOMBIA. Case Study (Water) Project Summary:
CARTAGENA, COLOMBIA Case Study (Water) Project Summary: Cartagena is a city of almost 900,000 people on the northern coast of Colombia, and serves as the capital of one of the country s departments (states),
More informationAccount Determination in SAP
Manish Patel Account Determination in SAP Bonn Boston Contents at a Glance 1 Overview... 15 2 General Ledger Transactions... 35 3 Accounts Receivable/Accounts Payable Transactions... 57 4 Tax Transactions...
More informationPRO FORMA PRELIMINARY CONDENSED CONSOLIDATED FINANCIAL INFORMATION
PRO FORMA PRELIMINARY CONDENSED CONSOLIDATED FINANCIAL INFORMATION The following pro forma preliminary condensed consolidated financial information and related notes ( Pro forma financial information )
More informationBNDES support to Infrastructure
BNDES support to Infrastructure 32th German-Brazilian Economy Meeting Hamburg, Germany September 1st, 2014 Claudia Cristina de Campos Manager of the Logistics Department - Infrastructure Division AGENDA
More informationPLANNING FOR SUCCESS P a g e 0
PLANNING FOR SUCCESS P a g e 0 PLANNING FOR SUCCESS P a g e 1 Planning for Success: Your Guide to Preparing a Business and Marketing Plan This guide is designed to help you put together a comprehensive,
More informationERG S.p.A. Ordinary Shareholders' Meeting 20/21 April Remuneration Report
ERG S.p.A. Ordinary Shareholders' Meeting 20/21 April 2017 Remuneration Report 1 SUMMARY LETTER OF THE CHAIRMAN OF THE NOMINATIONS AND COMMITTEE 2 EXECUTIVE SUMMARY 3 INTRODUCTION 5 SECTION I: Remuneration
More informationThe Board of Finance of Baltimore City Department of Finance Bureau of Treasury Management
The Board of Finance of Baltimore City Department of Finance Bureau of Treasury Management Tax Increment Financing Policy and Project Submission Requirements January 23, 2012 PART I: TAX INCREMENT FINANCING
More informationA U D I T R E P O R T. Audit of Lee County Utilities
A U D I T R E Audit of Lee County Utilities P O R T Internal Audit Department Audit Number 2012.17 October 2012 October 04, 2012 Linda Doggett, COO Re: Audit of Lee County Utilities Dear Mrs. Linda Doggett:
More informationLNG FROM COLOMBIA Platts 13 th Annual Caribbean Energy Jan 24 th 2013
LNG FROM COLOMBIA Platts 13 th Annual Caribbean Energy Jan 24 th 2013 FORWARD LOOKING STATEMENT All monetary amounts are in U.S. dollars unless otherwise stated. This presentation contains forward-looking
More informationTHE POTOMAC EDISON COMPANY Electric P. S. C. Md. No. 53 Fifth Revision of Original Page No. 28 Canceling Fourth Revision of Original Page No.
Fifth Revision of Original Page No. 28 Fourth Revision of Original Page No. 28 NET ENERGY METERING RIDER AVAILABILITY This Rider is available to all Customers who own and operate a biomass, solar, fuel
More informationPRESENTATION. Aguas Andinas S.A. JUNE 2013
CORPORATE PRESENTATION Aguas Andinas S.A. JUNE 2013 01 OVERVIEW 02 CHILEAN WATER INDUSTRY 03 AGUAS ANDINAS 04 RECENT EVENTS 05 FINANCIAL PERFORMANCE 01 OVERVIEW 4 Aguas Andinas at a Glance Summary Largest
More informationON REMUNERATIONS AND COMPENSATIONS PAID TO MEMBERS OF THE BOARD OF DIRECTORS OF JOINT-STOCK COMPANY CHELYABINSK TUBE-ROLLING PLANT
APPROVED BY Extraordinary General Meeting of Shareholders of Joint-Stock Company Chelyabinsk Tube-Rolling Plant (Minutes without number dd.23.08.2010) Chairperson of extraordinary general meeting of shareholders
More information1. Introduction Background Purpose Scope of the Tariff Structure Statement... 3
Contents 1. Introduction... 3 1.1 Background... 3 1.2 Purpose... 3 1.3 Scope of the Tariff Structure Statement... 3 1.4 Application of the Tariff Structure Statement... 4 2. Compliance matrix... 7 3. Understanding
More informationPUBLIC-PRIVATE PARTNERSHIPS CONFERENCE JUNE 5-8, 2012 DAKAR, SENEGAL
Squeezing out the Drop$ Improving Water Utility Efficiency through Performance-Based Investment PUBLIC-PRIVATE PARTNERSHIPS CONFERENCE JUNE 5-8, 2012 DAKAR, SENEGAL There is an $80B global water market
More informationDEMAND RESPONSE WHEREDO WESTAND, WHEREDO WEGO ANDHOW DO WEGO CHALLENGES, OPPORTUNITIES AND PERSPECTIVES JOISA DUTRA
DEMAND RESPONSE WHEREDO WESTAND, WHEREDO WEGO ANDHOW DO WEGO CHALLENGES, OPPORTUNITIES AND PERSPECTIVES JOISA DUTRA CIGRE DEMAND RESPONSE SEMINAR SÃO PAULO DECEMBER 15, 2016 ROADMAP Disrupting the Use-of-Energy
More informationMH s Draft of Application for Approval of Energy Intensive Industrial Rate, Tab 1
RCM/TREE/MH II-1 Subject: Reference: Marginal Cost MH s Draft of Application for Approval of Energy Intensive Industrial Rate, Tab 1 a) Please provide the derivation of the $57.5 per MW.h average price
More informationPage 1. Pty Ltd. provides. Key points. The SRES. 30 June 2012; The price of just over $ which is. The STP. year the.
RESEARCH NOTE 2 Understanding the Small-scale Renewable Energy Scheme This Research Note has been prepared for r the REC Agents Association by Green Energy Markets Pty Ltd. This research note analyses
More informationPRO FORMA PRELIMINARY CONDENSED CONSOLIDATED FINANCIAL INFORMATION
PRO FORMA PRELIMINARY CONDENSED CONSOLIDATED FINANCIAL INFORMATION The following pro forma preliminary condensed consolidated financial information and related notes ( Pro forma financial information )
More informationIV Sem BASIC INFORMATICS FOR MANAEMENT
BBA IV Sem BASIC INFORMATICS FOR MANAEMENT 1. Drawings account is to be created by linking with A. Capital B. Current asset C. Current liability D. Drawings 2. The options Use Common Narration and Narration
More informationBylaws. for the Supervisory Board of Siemens Aktiengesellschaft. Version dated September 20, 2017
s This edition of our Bylaws for the Supervisory Board, prepared for the convenience of English-speaking readers, is a translation of the German original. In the event of any conflict the German version
More informationREMUNERATION POLICY FOR THE DIRECTORS OF REPSOL, S.A.
REMUNERATION POLICY FOR THE DIRECTORS OF REPSOL, S.A. March 2015 1 CONTENTS 1. INTRODUCTION... 3 2. REMUNERATION POLICY FOR THE DIRECTORS... 3 2.1. Philosophy of the Remuneration Policy: principles and
More information(Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013)
Thomas Cook Group plc THE AUDIT COMMITTEE TERMS OF REFERENCE (Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013) Chairman and members
More informationContract For Biomass-Fueled Generation. Presentation to the Gainesville City Commission May 7, 2009
Contract For Biomass-Fueled Generation Presentation to the Gainesville City Commission May 7, 2009 Presentation Outline Project History And Description Market Changes Adjustments To Original Proposal Economic
More informationPROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO
PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO This Proposal outlines the terms and conditions in a proposed Appendix to the Southwest Power Pool's ("SPP's") Membership Agreement
More informationElectricity Supply Agreement
Electricity Supply Agreement 1. General 1.1 Mazoon Electricity Company SAOC (the Supplier) shall on or from the Start Date, subject to the satisfactory completion of a Supply Application Form, provide
More informationElectricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)
For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold
More informationDah Sing Banking Group Limited Nomination and Remuneration Committee - Terms of Reference
Dah Sing Banking Group Limited Nomination and Remuneration Committee - Terms of Reference 1. Constitution 1.1 The Nomination and Remuneration Committee (the "Committee or NRC") is established by the Board
More information1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.
1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh. There is no target for MW of renewable capacity (except in
More informationElectricity and Gas Retail Markets Report Q3 2017
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Electricity and Gas Retail Markets Report Q3 2017 Information Paper Reference: CRU 17354 Date Published: 20/12/2017 Public/ Customer
More information1). Fixed cost per unit decreases when:
1). Fixed cost per unit decreases when: a. Production volume increases. b. Production volume decreases. c. Variable cost per unit decreases. d. Variable cost per unit increases. 2). Prime cost + Factory
More informationMemorandum Issue Date September 2012
Memorandum Issue Date September 2012 Project Topic Revenue from Contracts with Customers Summary of user outreach The following summarizes user outreach conducted with analysts and investors that cover
More informationPolicy for determining capital contributions on Vector s electricity distribution networks. From 1 December 2017
Policy for determining capital contributions on Vector s electricity distribution networks From 1 December 2017 Pursuant to: Electricity Distribution Information Disclosure Determination 2012 1 Table of
More informationCity of San Diego Pure Water Project October 2014
City of San Diego Pure Water Project October 2014 SDCTA Position: SUPPORT Rationale for Position: Substantial study has demonstrated a potable reuse project within the City of San Diego would be safe,
More informationAnnex II Program: Corporate Governance of State-Owned Enterprises (SOEs) Proposed Measures
Annex II Program: Corporate Governance of State-Owned Enterprises (SOEs) Proposed Measures BM&FBOVESPA proposes a reflection on how to enhance the corporate governance practices of SOEs. The measures to
More information1. CONTEXT OF THE APPROVAL OF ROYAL DECREE-LAW 9/2013
2-2013 July 2013 CHANGES TO THE ENERGY SECTOR INTRODUCED BY ROYAL DECREE-LAW 9/2013, OF JULY 12, 2013, ADOPTING URGENT MEASURES TO GUARANTEE THE FINANCIAL STABILITY OF THE ELECTRICITY SYSTEM Royal Decree-Law
More informationΕπιχειρησιακή Συνέχεια και Εφοδιαστική Αλυσίδα, 14 Οκτωβρίου Moving ahead in a changing environment
Moving ahead in a changing environment Changes in consumer behavior and their effect on customer service levels Change of customer requirements to smaller quantities and shorter delivery times due to:
More informationFGB and NBAD have released pro forma financials preliminary condensed consolidated financial information
21 August 2016 FGB and NBAD have released pro forma financials preliminary condensed consolidated financial information Further to the release of 1H 2016 results and in line with transparent disclosure
More informationWith the support of the PV Market Alliance. APVIA Q Market Report
With the support of the PV Market Alliance APVIA Q3 2017 Market Report Introduction Launched in 2017, this 3 rd edition of APVIA s quarterly PV market report focus on Brazil, anticipated to witness solid
More informationRevenue for chemical manufacturers
Revenue for chemical manufacturers The new standard s effective date is coming. US GAAP August 2017 kpmg.com/us/frv b Revenue for chemical manufacturers Revenue viewed through a new lens Again and again,
More informationResidual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources
Market Issues Bulletin Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources March 10, 2015 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400
More informationTAX INFORMATION BOOKLET
2016 TAX INFORMATION BOOKLET Enduro Royalty Trust Important Tax Information 919 Congress Avenue 2016 Austin, TX 78701 Telephone (512) 236-6545 EIN: 45-6259461 This booklet provides 2016 tax information
More informationFASB Emerging Issues Task Force
EITF Issue No. 06-1 FASB Emerging Issues Task Force Issue No. 06-1 Title: Accounting for Consideration Given by a Service Provider to Manufacturers or Resellers of Specialized Equipment Necessary for an
More informationLuc Gregoire Chief Financial Officer. Drexel Hamilton Annual Telecom, Media and Technology Conference September 6, 2017
Luc Gregoire Chief Financial Officer Drexel Hamilton Annual Telecom, Media and Technology Conference September 6, 2017 Forward Looking Statements This presentation and oral statements made from time to
More informationPayback & Return Analysis for Solar in Mueller - Revision 1
Payback & Return Analysis for Solar in Mueller - Revision 1 This document should serve to help residents of the Mueller Community understand the financial implications of the solar system proposals they
More informationSanjay Srinivas PH:
Microsoft Dynamics AX 2012 Training course Content [Financials I, II, and Fixed Assets] Financials I Financials I course introduces the student to the Microsoft Dynamics AX 2012 General Ledger Accounting
More informationCHAPTER 6. Inventories 12, 13, , , 11 16, , 13
CHAPTER 6 Inventories ASSIGNMENT CLASSIFICATION TABLE Study Objectives Questions Brief Exercises Do It! Exercises A Problems B Problems 1. Describe the steps in determining inventory quantities. 1, 2,
More informationBOARD OF DIRECTORS RYDER SYSTEM, INC. CORPORATE GOVERNANCE GUIDELINES
BOARD OF DIRECTORS RYDER SYSTEM, INC. CORPORATE GOVERNANCE GUIDELINES The Board of Directors (the Board ) of Ryder System, Inc. (the Company ) has adopted the following Corporate Governance Guidelines
More informationGovernance Principles
Governance Principles Governance Principles The following principles have been approved by the board of directors and, along with the charters and key practices of the board committees, provide the framework
More informationCritical Equation #2 for Business Leaders. Variance = OM I - OM J. "Understanding and Analyzing Variances" Overview
"Understanding and Analyzing Variances" Critical Equation #2 for Business Leaders Variance OM I - OM J Overview All business leaders need to be able to create and manage a budget. This can be a relatively
More informationwith Fatih Birol, IEA Executive Director
Interview Edited by Chiara Martini and Alessandro Federici (ENEA) with Fatih Birol, IEA Executive Director As we have seen in submissions to COP21, energy efficiency is at the top of the agenda for a large
More informationMKT IBO Training. Updated: 29 November 2016
MKT-3193 IBO Training Updated: 29 November 2016 v About EnergyAustralia ACN has a partnership with EnergyAustralia to market competitive electricity and gas offers to residential and small business customers.
More informationPRUDENTIAL FINANCIAL, INC. CORPORATE GOVERNANCE PRINCIPLES AND PRACTICES
PRUDENTIAL FINANCIAL, INC. CORPORATE GOVERNANCE PRINCIPLES AND PRACTICES A. THE ROLE OF THE BOARD OF DIRECTORS 1. Direct the Affairs of the Corporation for the Benefit of Shareholders The Prudential board
More informationInvestment Seminar, March 2007, Vienna, Austria.
Page 1 of 5 Reference: Initial comments of the Project Participants to the registration requests for review of the Project Activities Pão de Açúcar - Demand Side Electricity Management - PDD 1 (1055),
More informationGROUP AUDIT COMMITTEE TERMS OF REFERENCE
Prepared by: Legal & Secretarial Version: 2.0 Status: Signed Off Owned by: Group Board Authorised by: Group Board Dept: Legal & Secretarial Sign-Off Date: 15/03/2017 GROUP AUDIT COMMITTEE TERMS OF REFERENCE
More informationTranslation from Polish
Declaration of Bank Handlowy w Warszawie S.A. (hereinafter referred to as the Company ) regarding the compliance with corporate governance rules incorporated in Best Practices in Public Companies Warsaw,
More informationWater Pricing in South Africa incorporating social and environmental elements Sacramento Water Pricing Workshop, February 2016 Barbara Schreiner
Water Pricing in South Africa incorporating social and environmental elements Sacramento Water Pricing Workshop, February 2016 Barbara Schreiner Background Middle income country Extremely high Gini co-efficient
More informationPIGEO s Detailed Position. on Oversupply of Green Certificates
Warsaw, 20 th February 2013 PIGEO s Detailed Position on Oversupply of Green Certificates The Polish Economic Chamber of Renewable Energy (PIGEO), representing a broad range of entrepreneurs from all RES
More informationEU Parliament, ITRE Committee Hearing
EU Parliament, ITRE Committee Hearing Energy Costs & EU Industry Competitiveness 23.02.2016 1 EU Steel Industry EU steel industry 500 production sites 166 bln turnover 1.3% of EU s GDP 328000 direct jobs
More informationProduct Oracle FLEXCUBE Universal Banking Release [April] [2014] Oracle Part Number E
Product Oracle FLEXCUBE Universal Banking Release 11.3.83.02.0 [April] [2014] Oracle Part Number E53607-01 Table of Contents Product 1. ABOUT THIS MANUAL... 1-1 1.1 INTRODUCTION... 1-1 1.2 AUDIENCE...
More informationCorporate Reporting (INT) (P2) September 2017 to June 2018
Corporate Reporting (INT) (P2) September 2017 to June 2018 This syllabus and study guide is designed to help with planning study and to provide detailed information on what could be assessed in any examination
More informationCorporate and Business Law (ENG) (F4) September 2016 to August 2017
Corporate and Business Law (ENG) (F4) September 2016 to August 2017 This syllabus and study guide is designed to help with planning study and to provide detailed information on what could be assessed in
More informationTopic 8 Stakeholders. Higher Business Management
Topic 8 Stakeholders Higher Business Management 1 Learning Intentions / Success Criteria Learning Intentions Stakeholders Success Criteria Learners should be aware of the differing objectives of groups
More informationCOMPARATIVE STUDY OF ENERGY COSTS IN IRRIGATION ACCORDING TO THE NEW BRAZILIAN ELECTRICITY TARIFF MODEL
Journal of the Brazilian Association of Agricultural Engineering ISSN: 1809-4430 (on-line) TECHNICAL PAPER ALEX N. DE ALMEIDA 1*, RUBENS D. COELHO 1, ASDRÚBAL J. FARÍAS 1, RODRIGO O. C. MONTEIRO 2, JÉFFERSON
More informationFRAMEWORK FOR SETTING ENERGY TARIFFS AND PRICES IN MONGOLIA, AND ITS POTENTIAL IMPROVEMENT IN THE FUTURE
FRAMEWORK FOR SETTING ENERGY TARIFFS AND PRICES IN MONGOLIA, AND ITS POTENTIAL IMPROVEMENT IN THE FUTURE Energy Regulatory Authority of Mongolia May 27, 2010 ELECTRICITY TARIFF DESIGN 2001 year 2009 year
More informationEvaluation of Energy Efficiency policies in Italy
Evaluation of Energy Efficiency policies in Italy Daniel Giannetti EPATEE 1 st European Peer Learning Workshop, Paris, 3 rd October 2017 Agenda Energy Efficiency targets and results in Italy White certificates
More information1) Operating costs, such as fuel and labour. 2) Maintenance costs, such as overhaul of engines and spraying.
NUMBER ONE QUESTIONS Boni Wahome, a financial analyst at Green City Bus Company Ltd. is examining the behavior of the company s monthly transportation costs for budgeting purposes. The transportation costs
More information<Insert Picture Here> JD Edwards EnterpriseOne Financial Management
JD Edwards EnterpriseOne Financial Program Agenda Financial Integration General Accounting Advanced Cost Accounting Accounts Payable Environmental Accounting and Reporting Accounts
More informationPakistan Bin Qasim Thermal Power Station Unit 6 Project. Report date: March 2001 Field survey: August Project Profile and Japan s ODA Loan
Pakistan Bin Qasim Thermal Power Station Unit 6 Project Report date: March 2001 Field survey: August 2000 1. Project Profile and Japan s ODA Loan Project site Project Site: 50-km east of the city of Site
More informationReform of energy subsidies The Asian experience
Reform of energy subsidies The Asian experience Shikha Jha, Asian Development Bank Asia and the Pacific Policy Society Conference Australian National University Canberra, 11 March 2014 Outline of the presentation
More informationIndivior PLC. Terms of Reference of the Audit Committee. Adopted: November 5, 2014 Last Updated: September 22, 2016 Owner: Company Secretary
Indivior PLC Terms of Reference of the Audit Committee Adopted: November 5, 2014 Last Updated: September 22, 2016 Owner: Company Secretary AUDIT COMMITTEE TERMS OF REFERENCE 1. Purpose and Policy 1.1 The
More informationRegulating Public Utility Performance The Law of Market Structure, Pricing and Jurisdiction Scott Hempling
Regulating Public Utility Performance The Law of Market Structure, Pricing and Jurisdiction Scott Hempling Regulatory Law: Purposes, Power, Rights and Responsibilities Market Structure: From Monopolies
More informationAn Economic Overview of Automated Pallet Handling Systems (Part 1) William G. Howard, Jr. Product Line Manager
An Economic Overview of Automated Pallet Handling Systems (Part 1) William G. Howard, Jr. Product Line Manager An economic overview of automated pallet handling systems (Part 1) In addition to the technical
More informationPrinciples of implementation and best practice regarding the application of Retail Minus pricing methodologies IRG (05) 39
Principles of implementation and best practice regarding the application of Retail Minus pricing methodologies IRG (05) 39 IRG PUBLIC CONSULTATION DOCUMENT Principles of Implementation and Best Practice
More information2016/17 Accounting Separation Methodology Statement
Water Plus Limited 2016/17 Accounting Separation Methodology Statement 1 Table of Contents 2 Introduction... 2 3 Period covered... 2 4 Cost allocation principals... 3 5 Statutory accounting allocations...
More informationCONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS
Ontario Energy Board Commission de l énergie de l Ontario CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS Issued: September 16, 2010 Table of Contents 1. GENERAL AND ADMINISTRATIVE
More information1.1. Please explain the meaning of the percentages in the table on page 3 of the material.
Discovery no. 1 from expert Paul L. Chernick to Gaz Métro related to the application regarding the allocation of costs and rate structure of Gaz Métro phase 3, part A (Methodology for the determination
More informationMcGraw-Hill/Irwin. Copyright 2013 by The McGraw-Hill Companies, Inc. All rights reserved.
McGraw-Hill/Irwin Copyright 2013 by The McGraw-Hill Companies, Inc. All rights reserved. Chapter 03 Engagement Planning "Vision without action is a daydream. Action without vision is a nightmare. Japanese
More informationDistribution Code Definitions
Distribution Code Definitions Version 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System Operator
More informationCEBU CPAR CENTER. M a n d a u e C I t y
Page 1 of 9 CEBU CPAR CENTER M a n d a u e C I t y AUDITING PROBLEMS AUDIT OF INVENTORIES PROBLEM NO. 1 The Pasay Company is a wholesale distributor of automobile replacement parts. Initial amounts taken
More information