Safety Enhancement Based on the Lessons learned from the Fukushima Accident

Size: px
Start display at page:

Download "Safety Enhancement Based on the Lessons learned from the Fukushima Accident"

Transcription

1 Safety Enhancement Based on the Lessons learned from the Fukushima Accident March 27, IAEA Technical Meeting on Operational Experience with Implementation of Post-Fukushima Actions in NPP Akira KAWANO

2 The Great East Japan Earthquake of March 11, 2011 Earthquake Mw 9.0: the largest earthquake recorded in Japan Plate movement in a wide (200km) and long (500km) area No significant damage or loss of safety systems Tsunami Max. height: 13~15m (design: 6.1m) Almost entire site area was flooded Loss of all AC and DC power supplies (no instrumentations) Loss of ultimate hear sink 1

3 Damage to Fukushima Daiichi NPS Unit 5 sea side seawater pump area Unit 1 containment seawater cooling system pump Confirmation result for the main flooding route by on-site confirmation surrounding the building (1) Building entry/exit (2) Equipment hatch (3) Emergency D/G air supply louver (4) Trench, duct (penetration of cables) etc. Flooding of D/G, electric panel room etc. through these. Unit 1 D/G (1B) Unit 1 power panel at turbine building level 1 Tokyo Electric Power Company, Inc. All Rights 2

4 Accident at Fukushima Daiichi NPS Serious core damage (melt through) of Unit 1-3 Damage of the PCV of Unit 1-3 (Significant amount of radio nuclide release from these Units) Explosion of the reactor building of Unit 1, 3 and 4 Evacuation of about 160,000 local residents 3

5 Overview of the 10-Unit Simultaneous Accidents Date 3/11 3/12 3/13 3/14 3/15 Fukushima Daiichi (1F) Fukushima Daini (2F) /11 15:27 1 st Tsunami, 15:35 2 nd Tsunami 3/11 15:22~ Tsunamis Station Blackout Water Injection: NO Heat Removal: NO 3/12 15:36 Unit 1 Explosion 3/14 11:01 Unit 3 Explosion 3/12 8:13 D/G-6B 3/15 6:00-6:10 Unit 4 Explosion Water Injection: YES Heat Removal: NO 3/14 1:24 RHR 3/14 17:00 3/14 7:13 RHR 3/14 18:00 3/12 12:15 Loss of Ultimate Heat Sink 3/14 15:42 RHR 3/15 7:15 3/ /19 5:00 RHR 3/19 22:14 RHR 3/20 3/20 15:46 P/C-2C 3/20 15:46 P/C-2C 3/22 10:36 P/C-4D 3/22 10:35 P/C-4D 3/20 14:30 3/20 14:30 Water Injection: YES Heat Removal: YES Cold Shutdown 4

6 Lessons Learned from the Fukushima Daiichi Accident Protection against a tsunami exceeding assumption was weak Sufficient preparations were not made for - preventing station blackout (SBO) - mitigating the influence of SBO by ensuring high-pressure core injection, depressurization, low pressure core injection, heat removal Measures were not well prepared to mitigate the impact after reactor core damage : prevention of containment failure hydrogen control countermeasures for core melt-through prevention of a large release of radioactive material into the environment, etc. 5

7 Basic Policies for Reactor Safety Enhancement 1. Reinforce defense in depth against external events 2. Adopt a concept of Phased Approach to emergency response 3. Ensure integrity of Containment Vessel in severe accidents 6

8 Basic Policies for Reactor Safety Enhancement (Continued) 1. Reinforcement of defense in depth against external events Reinforce defense in depth based on the assumption that multiple function failures could be caused by external events Establish safety measures along with defense in depth concept focusing on diversity and physical separation Consider not only earthquake and tsunami but also 40 natural events and 20 human induced external events shown in US NUREG* and the IAEA Safety Guide** Select the external events based on their cliff edge effect and their probability, and establish safety measures against them Strengthen measures also against internal flooding and internal fire Use of probabilistic risk assessment (PRA) to: select accident sequences to be evaluated confirm effectiveness of the established safety measures * NUREG/CR-2300 Vol.2, PRA Procedures Guide ** IAEA Specific Safety Guide SSG-3, Development and Application of Level 1 Probabilistic Safety Assessment for Nuclear Power Plants 7

9 Basic Policies for Reactor Safety Enhancement (Continued) 2. Adoption of phased approach Select safety measures based on the assumption that possible measures and their required reliabilities are different depending on time to spare Accident Occurrence initial response phase Installed equipment Shift team Action by installed equipment Complexity of accident progression (1) (2) (3) second response phase Portable equipment On-sites team Support from off-site Action by Portable Equipment and Management final response phase Support from off-site Augmented by off-site team [time] Fire engines High pressure injection pump (installed equipment) Power supply cars Tank trucks from off-site 8

10 Basic Policies for Reactor Safety Enhancement (Continued) 3. Ensuring integrity of Containment Vessel in severe accidents Clarify requirements for Containment Vessel and auxiliary equipment after core damage and then implement safety measures Define twice design pressure as upper limit pressure of Containment Define 200 ºC as upper limit temperature of Containment Define function requirements for auxiliary systems in order to contain fission products in Containment as long as possible 9

11 Safety Measures to enhance 1 st Layer of Defense in Depth Measures against tsunami (15m) Sea Wall, Tidal Embankment, Tidal Walls, Boards, Water-tight Doors, etc. 10m 15m above sea Sea Wall Tidal wall Tidal board Water-tight door Measures against Tornado (Fujita Scale 3) Hardened fuel tanks for emergency diesel generators Put N 2 to prevent explosion タンク液面上部の空隙に 窒素を封入することで防爆構造とする Hardened Tank Thickness 32 mm (Originally 9mm) 板厚 40mm * ( 従来 9mm) *: 今後の詳細検討により決定 Measures against External (Forest) Fire Creation of the fireproof belt Fireproof belt Unit 3 Unit 1 Unit 4 Unit 2 Fireproof belt 防火帯 Unit 6 Unit 7 Unit 5 防火帯設置イメージ図 Map of the plant with fireproof belt 10

12 Safety Measures to Enhance 2 nd Layer of Defense in Depth Measures against Tsunami Flooding and Internal Flooding Reduce flooding sources (seismic reinforcement of low class equipment) Waterproof treatments/ flap gates to protect important equipment Install drain pumps for inundation beyond postulated damage Waterproof Filler R/B R/B Stair Case R/B 階段室 Room T/B RW/B Rw/B Stair RW/B Case 階段室 Room T/B Waterproof treatment for piping Waterproof treatment of Upper Hatch 1FL 1FL Waterproof treatment for cables Important Equipment Flap Gate for HVAC ducts Watertight Door B3FL RCIC/RHR(A) Room室 RCIC B3FL MUWC MUWC Room 室 MUWC Funnel with check function 常設排水可搬式排水 Potable Permanent ポンプポンプ Drain Drain Pump Pump R/B : 原子炉建屋 T/B : タービン建屋 RW/B : 廃棄物処理建屋 RCIC : 原子炉隔離時冷却系 RHR : 残留熱除去系 MUWC: 復水補給水系 Permanent 常設排水ポンプ Drain Pump 常設排水 Permanent ポンプ Drain Pump 可搬式排水 Potable ポンプ Drain Pump Measures against internal flooding Installation of Drain Pumps 11

13 Safety Measures to Enhance 2 nd Layer of DiD (continued) Measures for Fire Protection Prevention Fireproof or fire-retardant materials (incombustible cable has been used since construction) Rigid management of combustible materials like lubricant oil Early detection and extinction Diversified fire detection devices Installed fire suppression systems Mitigation Fire Barriers with 3-hour fire resistance capability Fire proof dumpers Fireproof treatment on piping and cable penetrations Cable wrapping Fire Suppression System Cable Wrapping (7 layers) Fireproof Treatment of Cable Penetrations 12

14 Measures to Enhance 3 rd Layer of DiD and Support Systems Water Injection and Heat Removal Functions Enhance High Pressure Injection Function: High Pressure Alternate Cooling System Enhance Depressurization: Back-up Actuation Mechanisms for SRVs Additional Water Source: Reservoir Enhance Heat Removal Function: Alternative Heat Exchange Vehicles HP Injection Enhanced Power Supply of Existing Injection SLC pump RHR pump CRD pump MUWC pump LP Injection Depressurization Fire Engine HPAC Reactor Heat Removal SRVs PCV 1 次格納容器 2 次格納容器 Back-up Battery and Cylinder R/B Additional Water Source K L M E F G N R S T C A B H U P D J C D A B Alternate Heat Exchange Vehicle Reservoir Self-Operated 3-way Valves Nitrogen Cylinders SRV Back-up Actuation Mechanisms 13

15 Safety Measures to Enhance 3 rd Layer of DiD (continued) High Pressure Alternate Cooling System (HPAC) Back-up system of RCIC to enhance reliability of high pressure injection, activated in case of malfunction of RCIC under SBO to prevent core damage Illustration of the system PCV RPV S/C Battery Turbine Power supply from battery on an upper floor Installed at an elevation higher than RCIC from the viewpoint of locational diversity M O RCIC Pump HPAC Turbine Pump R/B MCR HPAC Steam Line HPAC Water Line Control from MCR Remote manual operation is possible from MCR CST Operation could be done by open/close operation of steam inlet valve Use of a steam-driven turbine pump which requires no powered auxiliary system, improving reliability under SBO conditions 14

16 Safety Measures to Enhance 3 rd Layer of DiD (continued) Reactor Alternative Heat Exchange Vehicle Back-up ultimate heat sink for the Reactor in case of LUHS events [Freshwater Pump Specification] Quantity: 1; Flow rate: 420m 3 /h; Pump head: 40m Connection Port Cold shutdown can be achieved within 48 hours. Heat exchanging capacity: 18.6MW Freshwater flow rate: 420m 3 /h Seawater flow rate: 500m 3 /h Freshwater outlet temperature: 32 Seawater intake design temperature: 29 Freshwater pump Hx Hx Reactor Building Alternative Seawater Heat Exchanging System 海水熱交換器建屋 Seawater Heat Exchange Building RHR Hx 原子炉補機冷却海水ポンプ Inundated and cannot be used 電動機 RHR pump Seawater 15

17 Safety Measures to Enhance Support Systems Power Supply Functions Measures for quick power supply Gas-turbine generators and power supply cars on higher ground Emergency switchgears and installed electrical cable Enhancement of reliability of DC Power Additional DC power with a small generator on the top floor of the Reactor Building Additional DC Battery Charge Placed on top floor of Reactor Building Power Supply Car GTG Emergency Switchgear (Placed on higher ground) Safety Area Safety Area Tokyo Electric Power Company Holdings, Inc. All M/C Rights Reserved. M/C 16

18 Safety Measures to Enhance 4 th Layer of Defense in Depth Protection of Containment Vessel and prevention of uncontrolled release Protection of Containment by preventing over-pressure/temperature: Top head flange cooling, increased durability of seal in severe accident environment Mitigation of radioactive material release: Filtered Vent Prevention of hydrogen explosion: Passive Autocatalytic Recombiner Prevention of leakage from primary containment vessel Hydrogen treatment Passive Autocatalytic Recombiner Increased durability of seal material Control over radioactive material release and Discharge of hydrogen Top head flange cooling line Water intake canal Alternative spray means for primary containment vessel The second filtered vent facilities Water injection into lower drywell The first filtered vent facility 17

19 Safety Measures to enhance 4 th Layer of DiD (Continued) Failure of the Containment Vessel at Unit 2 of Fukushima Daiichi NPS Significant leakage occurred at 0.75 MPa and 175 ºC Near the Containment top flange radiation level after the accident was relatively higher than the other areas in the reactor building Top flange gaskets made of silicon rubber must have been degraded in high temperature steam environment, which continued much longer than design basis LOCA conditions 格納容器圧力 (MPa[abs]) D/W 圧力 (MAAP5.01) S/C 圧力 (MAAP5.01) 実測値 (D/W) 実測値 (S/C) トーラス室に浸水した水による S/C の除熱開始 ( 仮定 ) Significant 格納容器漏えい Leakage ( 仮定 ) SRV 開 格納容器温度 ( ) トーラス室に浸水した水による S/C の除熱開始 ( 仮定 ) SRV 開 Significant Leakage 格納容器漏えい ( 仮定 ) 0.2 計装バッテリ枯渇に伴うハンチング S/C 圧力計指示不良 50 D/W(MAAP5.01) S/C( 気相 )(MAAP5.01) S/C( 液相 )(MAAP5.01) S/C( 液相 )(MAAP4) 0.0 3/11 12:00 3/12 0:00 3/12 12:00 3/13 0:00 3/13 12:00 3/14 0:00 3/14 12:00 日時 Pressure and temperature trend of Fukushima Daiichi Unit 2 during the accident 3/15 0:00 Date 3/15 12:00 3/16 0:00 Containment Pressure 3/16 12:00 3/17 0:00 3/17 12:00 3/18 0:00 0 3/11 12:00 3/12 0:00 3/12 12:00 3/13 0:00 3/13 12:00 3/14 0:00 3/14 12:00 日時 Date 3/15 0:00 3/15 12:00 3/16 0:00 Containment Temperature 3/16 12:00 3/17 0:00 3/17 12:00 3/18 0:00 18

20 Safety Measures to Enhance 4 th Layer of DiD (Continued) Reinforcement of Containment robustness in SA environment Buck-up seal Improved EPDM seal Top head side Body side Outside of PCV Increased durability of seal material No. 1 2 Results of improved EPDM seal performance tests Heating condition Dry 200, 168h Steam 1MPa, 250, 168h Flange opening 0.8mm* 0.8mm* 0.3MPa 0.65MPa 0.9MPa No leakage No leakage No leakage No leakage No leakage No leakage * Tests were conducted in ½ scale. A opening of 0.8 mm is equivalent to 1.6 mm in real scale. Water intake canal Alternative spray means for the Containment Vessel Water injection into lower drywell 19

21 Safety Measures to Enhance 4 th Layer of DiD (Continued) Filtered Containment Venting System developed by TEPCO Metal filter 金属フィルタ Organic iodine filters Mixing elements Scrubber Nozzles 気泡細分化装置 ノズル Silver zeolite Decontamination Factors Aerosols: over 1000 Elemental Iodine: over 1000 Organic Iodine: over 50 Aerosol and elemental iodine filter 20

22 Safety Measures to Enhance 4 th Layer of DiD (Continued) ph Control (alkaline control) Inhibit production of iodine gas, and reduce amount of iodine released from the Containment Vessel by making water in the Containment alkaline Containment Vessel Alkaline control Condensate Storage Pool Sodium Hydroxide Solution MUWC pump (Make Up Water Condensate) 21

23 Safety Measures to Enhance 4 th Layer of DiD (Continued) Alternate Recirculation Cooling System(ARCS) developed by TEPCO Containment venting can be avoided by continuous heat removal from suppression chamber Containment spray RHR 1 Containment Vessel alternate Hx External connection port CSP Water injection into reactor MUWC (A) Suppression chamber MUWC (B) MUWC (C) SPCU RHR (B) HPCF (B) Hx (B) 1 Rw/B Alternate circulation cooling system (established part) Alternate circulation cooling system (newly established part) 22

24 Safety Measures to Enhance 4 th Layer of DiD (Continued) Containment Pressure [MPa(gage)] Effectiveness of ARCS ARCS starts PCV pressure limit for severe accident (620kPa) Dry Well Suppression Chamber Pressure suppression by spray Time Containment pressure trend of Kashiwazaki Kariwa Unit 7 in a severe accident with large break LOCA, SBO, and loss of all ECCS 23

25 Challenges in the Process of Safety Enhancement Examples of Additional Measures Required by NRA Measures against Tornado Fujita Scale 3 that has never appeared in the areas facing Japan Sea was required to be applied, and consequently the oil tanks were replaced by new ones with 40mm wall thickness Fire Protection Measures needed to increase the number of fixed fire suppression system (from 20 to 120) due to conservative consideration of the capability of self fire brigade Measure to maintain negative pressure in Reactor Building during severe accident SGTS was required to be activated under SBO condition during severe accident based on conservative assumption of decontamination factor (DF=1) for PCV leakage and ventilation rate (infinite) of Reactor Building Tokyo Electric Power Company, Inc. All Rights 24

26 Lessons Learned Challenges to be Considered How independent external events should be considered during the response period against severe accident, that could be very long How seismic robustness of equipment, that is expected as diversified function, should be required How the reliability of operations in the buildings and in the field should be secured redundancy, diversity, environment, human factor Development of multi-unit PRA method Establishment of organic iodine removal technology More realistic simulation model on how the object could fly in a wind speed field caused by tornado How field walk-down and coordination between works should be made most effectively to optimize the design & layout and minimize the cost Tokyo Electric Power Company, Inc. All Rights 25

27 Organizational and Cultural Challenges in TEPCO Negative linkage of the lack of Safety awareness, Engineering capability and Communication ability went into insufficient readiness for accident. Underestimate external event risk Underestimate severe accident risk Consider capacity factor as an only important performance indicator Not to learn from others experience Safety Awarenes s Lack of daily effort to improve safety Excess costs for SCC and seismic measures for an availability factor Worried plant shutdown because of minor mistakes Explanation is required if we admit it is not safe Overconfidence that safety had been established Desire that it is safe enough Communicatio n Ability Continue risk communicatio n Too much dependence on plant manufacturer Engineering Capability Insufficient inhouse design capability Insufficient ability to understand total system High-cost structure Focused on supervision work Excess dependence on partner companies Avoid direct work by inexperienced personnel Technical Capability Insufficient inhouse direct work capability Ritual emergency training Cannot explain additional measures necessity if it is safe enough Insufficient readiness for accidents 26

28 Nuclear Safety Reform Plan Reflection of Fukushima Nuclear Accident and Nuclear Safety Reform Plan was issued on March 29, It contains six action plans. Governance Action plan 2 Action plan 3 Enhancement of Oversight and Support for Top Management Enhancement of Ability to Propose Defense-in- Depth Measures Safety Awarenes s Action plan 1 Reform from Top Management Engineering Ability Action plan 5 Action plan 6 Reorganization of Emergency Response Organizations Enhancement of Human Development for Improving Nuclear Safety Engineering Ability Communication Ability Action plan 4 Enhancement of Risk Communication Activities Our Determination Improve safety level day by day reflecting the experience of Fukushima Nuclear Accident and be a nuclear operator who can continuously create supreme safety. 27

29 Output Output Output Actions to Improve Issues and Accelerate Reforms Improvement in Governance [Critical success factors for improvement] Good management [Action] Management Model Project Expand the project output to the entire Nuclear Power Division so that tasks are conducted with the same objectives at any level and in any organization. Improvement in Engineering Capability Continuous Strong Leadership [Individual] Systematic Education and Training of Global Standards Management model Fundamentals (Ideal behavior for each business field) Succession plan Job Description Human Resource Database Nuclear Human Resource Development Center World s Best Education and Training Program Personnel with Engineering and Management Capabilities [Organization] Strengthening in-house Engineering Capability Nuclear Engineering Center 28

30 Management Model Vision Mission Sense of values Keep the Fukushima Nuclear Accident firmly in mind; we should be safer today than we were yesterday, and safer tomorrow than today; we call for nuclear power plant operators that keep creating unparalleled safety. Power Generation Division Efficiently generate nuclear power under the world s highest standards of safety / Decommissioning Division Continue to reduce risk and complete decommissioning Uncompromising safety and the pursuit of quality (Safety Awareness) Basic plan for achieving these goals Efficient Operation under the World s Highest Safety Standards Operation and Tasks that directly support Operation Tasks that support Efficient Operation/Management Work Management Equipment Reliability Build trust with stakeholders (ability to promote dialogue) Engage in never-ending reform and improvements Radiation Protection Maintenance Project Management Configuration Management Operation Chemistry Engineering Emergency Response Fire Protection Further foster individual ability and strengthen the organization's ability to learn (Technical Capability) Promote in-house participation where employees see, listen and touch for themselves Radioactive Waste and Environmental Management 運転上の意思決定反応度管理 Quality Assurance Budget Management/Fiscal Assessment Power Generation Division work configuration Tasks that support pre-operation and post-operation Activities to support Reform and Improvement Safety Culture Cultivation Risk Management/PRA Performance Improvements Construction Safety Awareness Nuclear Security/Cyber- Security Occupational Safety Leveraging of Operating Experience Decommissioning External Communication Siting Community PR Cooperation with contractors Communication Capability Fundamentals Internal Communication General Affairs Change management Nuclear Fuel Cycle Human Resource Management Education/Training Procurement Engineering Capability Standards IT/AI Technical Development and Introduction Management Performance Tokyo Electric Management Power Company Holdings, Inc. All Rights Review Reserved. CFAM Monitoring Observation Performance Review Safety Steering Committee Nuclear Risk Management Committee Nuclear Safety Oversight Office Chief Nuclear Engineer Nuclear Safety Review Board Internal Audit Office Nuclear Reform Monitoring Committee Board of Directors 29

31 Emergency Response Capability Restructure of Emergency Response Organization Emergency Response Director Before Information Team Logistics Team 12 teams in parallel Emergency Response Director After (ICS) Public Communication Plant Control Leader Engineering Leader Logistics Leader Safety Supervisor Administration Leader Planning team (unit 1-4) Planning team (unit 5-7) Information team RP team 30

32 Emergency Response Capability (Continued) Training for Emergency Response Comprehensive emergency drills and specific skill trainings have been conducted for 45 times and 7600 times respectively since the accident Night trainings were carried out with temporary lighting (Car headlight, flashlight, balloon light) ERC Rubble removal by wheel loader Gas turbine generator Power supply car Offsite center Firefighting training Alternative heat exchanger Hose Laying Logistics support base Transport of injured person Satellite communications vehicle Transport of N 2 compressed gas cylinder 31

33 Emergency Response Capability (Continued) Offsite Emergency Support Center Sufficient food and fuel are stored on-site to support emergency response (food for 8 days and fuel for 150 days) Making emergency transportation contract with transportation company and giving drivers lectures on radiation. Offsite emergency support centers has been prepared to control entry into affected zone and support materials On-site Emergency Food Image of Offsite Emergency Support Center (Picture of J-Village) 32

34 Emergency Response Capability (Continued) Offsite Emergency Support Center for Enhancement in Logistics Kashiwazaki Kariwa NPS TEPCO Shinanogawa Power Station (23km) Kashiwazaki Energy Hall (8km) Atema Highland Resort (44km) 33

35 Emergency Response Capability (Continued) Nuclear Emergency Assistance Center (J-NEACE) Located in Fukui Prefecture (350km from Kashiwazaki Kariwa NPP) Operated by JAPC (Japan Atomic Power Co.) 20 staff, on-call around the clock, 5 remote-control robots Main missions are: - Emergency transportation of robots - Support of robot operation - Training of emergency response staff of nuclear operators 34

36 Conclusions Our Resolution: We will never forget the Fukushima Nuclear Accident. We will increase the level of safety today more than yesterday and tomorrow more than today, and we will become a nuclear operator that continues to create unparalleled safety. Tokyo Electric Power Company, Inc. All Rights 35

37 Thank you for your attention 36

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya International Conference on Nuclear Governance Post-Fukushima Marina Bay Sands, Singapore, 31 October 2013 Safety Enhancement of Nuclear Power Plant Post Fukushima October 31,2013 Kumiaki Moriya Hitachi-GE

More information

Flow of Assessment. (1) Select events. (2) Select facilities. (3) Evaluate margins. (4) Identify cliff edge

Flow of Assessment. (1) Select events. (2) Select facilities. (3) Evaluate margins. (4) Identify cliff edge Mar. 2, 202 Comprehensive Assessment for the Safety of Units and 7 at Kashiwazaki-Kariwa Nuclear Station (Stress Tests) - Results of Primary Assessment and Safety Ensuring Measures Tokyo Electric Company

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA

More information

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S) Loss of Ultimate Heat Sink ANS AESJ AESJ Fukushima Symposium, March h4, 2012 Hisashi Ninokata, Tokyo Institute of Technology Available ultimate heat sinks at 1F1~3 1F1 (Fukushima Dai ichi Unit 1) Sea water

More information

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations March 31, 2011 Tokyo Electric Power Company Tohoku Pacific Ocean Earthquake Time: 2:46 pm on Fri, March 11, 2011. Place:

More information

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Hitachi Review Vol. 62 (2013), No. 1 75 Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Masayoshi Matsuura Kohei Hisamochi Shinichiro Sato Kumiaki

More information

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs October 27, 2014 H. Hoshi, R. Kojo, A. Hotta, M. Hirano Regulatory Standard and Research Department, Secretariat of Nuclear

More information

Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident

Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident 2012 Begell House, Inc. Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident T. Narabayashi 1 1 Division of Energy and Environmental Systems, Hokkaido University, Kita 13, Nishi 8, Kita-ku,

More information

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned Jun Sugimoto Abstract The nuclear accident that occurred at the Fukushima Daiichi Nuclear

More information

Fundamental Policy for the Reform of TEPCO Nuclear Power Organization. October 12, 2012 Nuclear Reform Special Task Force

Fundamental Policy for the Reform of TEPCO Nuclear Power Organization. October 12, 2012 Nuclear Reform Special Task Force Fundamental Policy for the Reform of TEPCO Nuclear Power Organization October 12, 2012 Nuclear Reform Special Task Force How to Proceed with the Development of the Reform Plan (1) Measures Measures Adopted

More information

Chapter VI. VI.Situation regarding efforts to address lessons learned (28 items)

Chapter VI. VI.Situation regarding efforts to address lessons learned (28 items) VI.Situation regarding efforts to address lessons learned (28 items) Japan is making its greatest possible efforts to address the 28 lessons learned indicated in the June report. The state of progress

More information

Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano

Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano Side Event of IAEA General Conference Severe Accident Analyses of Fukushima-Daiich Units 1 to 3 Harutaka Hoshi and Masashi Hirano Japan Nuclear Energy Safety Organization (JNES) September 17, 2012 Side

More information

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University

More information

XII. Lessons Learned From the Accident Thus Far

XII. Lessons Learned From the Accident Thus Far XII. Lessons Learned From the Accident Thus Far The Fukushima NPS accident has the following aspects: it was triggered by a natural disaster; it led to a severe accident with damage to nuclear fuel, Reactor

More information

Development and use of SAMGs in the Krško NPP

Development and use of SAMGs in the Krško NPP REPUBLIC OF SLOVENIA Development and use of SAMGs in the Krško NPP Tomaž Nemec Slovenian Nuclear Safety Administration tomaz.nemec@gov.si IAEA TM on the Verification and Validation of SAMGs, Vienna, 12

More information

Post-Fukushima Assessment of the AP1000 Plant

Post-Fukushima Assessment of the AP1000 Plant ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,

More information

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations 1. Outline of Fukushima Nuclear Power Stations (1) Fukushima Daiichi Nuclear Power Station Fukushima Daiichi Nuclear

More information

Contents of summary. 1. Introduction

Contents of summary. 1. Introduction Contents of summary 1. Introduction 2. Situation regarding Nuclear Safety Regulations and Other Regulatory Frameworks in Japan before the Accident 3. Disaster Damage in Japan from the Tohoku District -

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,

More information

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director Simposyum Siting of New Nuclear Power Plants and Irradiated Fuel Facilities Buenos Aires Argentina 24-28 June 2013 Panel Fukushima Daiichi s Impact in Nuclear Power Programs Worldwide Brazilian Operator

More information

The ESBWR an advanced Passive LWR

The ESBWR an advanced Passive LWR 1 IAEA PC-Based Simulators Workshop Politecnico di Milano, 3-14 October 2011 The ES an advanced Passive LWR Prof. George Yadigaroglu, em. ETH-Zurich and ASCOMP yadi@ethz.ch 2 Removal of decay heat from

More information

Measures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station

Measures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station Nuclear and Industrial Safety Agency Ministry of Economy, Trade and Industry IEM 3: International Expert s Meeting (Earthquakes / Tsunamis) 4-7 September, 2012 Vienna Measures against Earthquakes and Tsunamis

More information

Inside Japan s s Nuclear Meltdown ~A A TEPCO Nuclear Engineer s s Perspective~

Inside Japan s s Nuclear Meltdown ~A A TEPCO Nuclear Engineer s s Perspective~ Inside Japan s s Nuclear Meltdown ~A A TEPCO Nuclear Engineer s s Perspective~ Program on U.S.-Japan Relations Harvard University Cambridge, Massachusetts September 9 th, 2014 Kenji Tateiwa Manager, Nuclear

More information

Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident

Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident O Phillips: Senior Executive Manager - National Nuclear Regulator The Fukushima Ministerial

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

Swedish action plan. for nuclear power plants

Swedish action plan. for nuclear power plants Swedish action plan for nuclear power plants Response to ENSREG s request December 2012 Page 2 (48) Abstract Following the severe accidents which started in the Fukushima Dai-ichi nuclear power plant,

More information

Topics on Current Nuclear Regulation in Japan

Topics on Current Nuclear Regulation in Japan Topics on Current Nuclear Regulation in Japan Commissioner Toyoshi Fuketa Nuclear Regulation Authority(NRA 26 th Annual Regulatory Information Conference Bethesda North Marriott Hotel & Conference Center

More information

OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D

OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D 16 NOVEMBER, 2011 Hiroshi RINDO JAPAN ATOMIC ENERGY AGENCY Table of Contents 1. What s happened at Fukushima Dai-Ichi NPSs

More information

Current Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning

Current Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning 2017 IAEA General Conference, Side Events Current Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning @Vienna International Centre, Vienna September 18, 2017 Naohiro MASUDA Chief

More information

The Fukushima Nuclear Accident: Insights on the Safety Aspects

The Fukushima Nuclear Accident: Insights on the Safety Aspects World Journal of Nuclear Science and Technology, 2015, 5, 169-182 Published Online July 2015 in SciRes. http://www.scirp.org/journal/wjnst http://dx.doi.org/10.4236/wjnst.2015.53017 The Fukushima Nuclear

More information

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford Post-Fukushima Action Plan in Korea WNU-SI 2011, August 11 Christ Church, Oxford Contents Korean nuclear overview BK Kim Government action plan BS Jeong Post-Fukushima action plan MK Jo Nuclear Power Plants

More information

The Accident at Fukushima: What Happened?

The Accident at Fukushima: What Happened? The Accident at Fukushima: What Happened? February 27, 2012 Takao Fujie President and Chief Executive Officer (JANTI) Copyright 2012. All Rights Reserved. The Accident at Fukushima: What Happened? Foreword

More information

Outline of the Fukushima Daiichi Accident. Lessons Learned and Safety Enhancements

Outline of the Fukushima Daiichi Accident. Lessons Learned and Safety Enhancements EPJ Web of Conferences 153, 08001 (2017) DOI: 10.1051/ epjconf/201715308001 ICRS-13 & RPSD-2016 Outline of the Fukushima Daiichi Accident. Lessons Learned and Safety Enhancements Masashi Hirano * Nuclear

More information

Report on TEPCO s Self-Assessment of Progress Keep the Fukushima Nuclear Accident firmly in mind; we should be safer today than we were yesterday,

Report on TEPCO s Self-Assessment of Progress Keep the Fukushima Nuclear Accident firmly in mind; we should be safer today than we were yesterday, Report on TEPCO s Self-Assessment of Progress Keep the Fukushima Nuclear Accident firmly in mind; we should be safer today than we were yesterday, and safer tomorrow than today; we call for nuclear power

More information

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements Sorin Holostencu IAEA Technical Meeting on Operational Experience with Implementation of Post-Fukushima Actions in Nuclear Power Plants,

More information

BWR Safety Improvement as a Lesson Learned from Fukushima Accident

BWR Safety Improvement as a Lesson Learned from Fukushima Accident BWR Safety Improvement as a Lesson Learned from Fukushima Accident M. M. Zaky and S. A. Kotb ETRR-2, Atomic Energy Authority, Cairo, Egypt Received: 20/5/2016 Accepted: 15/7/2016 ABSTRACT The serious accident

More information

Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP

Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP 1/12 Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP Summary M. Naitoh, M. Pellegrini. H. Suzuki, H. Mizouchi, and H. Okada The Institute of Applied Energy, Japan This paper

More information

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant

More information

HTGR Brayton Cycle Technology and Operations

HTGR Brayton Cycle Technology and Operations MIT Workshop on New Cross-cutting Technologies for Nuclear Power Plants, Cambridge, USA, January 30-3, 207 HTGR Brayton Cycle Technology and Operations Xing L. Yan HTGR Hydrogen and Heat Application Research

More information

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station Provisional Translation Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi Nuclear Power Station June 12, 2015 Inter-Ministerial Council for Contaminated Water and Decommissioning

More information

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi Nuclear Power Station Information about when each measure and action will begin and end will be added later upon further

More information

Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning

Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning Eiichiro WATANABE Waste Technology Section Division of Nuclear Fuel Cycle and Waste Technology Department of Nuclear

More information

Summary on Fukushima Related Activities in Japan

Summary on Fukushima Related Activities in Japan 0 Keynote Presentation Summary on Fukushima Related Activities in Japan Masashi HIRANO Director-General for Regulatory Standard and Research Nuclear Regulation Authority (NRA) International Conference

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

Japan s Energy White Paper 2017

Japan s Energy White Paper 2017 Japan s Energy White Paper 207 Japan s Energy Landscape and Key Policy Measures PART Fukushima Reconstruction Progress PART 2 New Developments in Energy Policy PART 3 Energy System Reform and Bolstering

More information

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC 3.10.2016 ČEZ, a. s. Meeting at IAEA Vienna Overview of topics ČEZ nuclear fleet (basic features) Systematic measures targeted to improve

More information

Tentative translation (as of March 1, 2016) March 1, 2016

Tentative translation (as of March 1, 2016) March 1, 2016 Tentative translation (as of March 1, 2016) March 1, 2016 Office of Manufacturing/Quality and Compliance Pharmaceuticals and Medical Devices Agency GMP Compliance Inspection concerning Pharmaceuticals

More information

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS Todd Brumfield World Association of Nuclear Operators (WANO) Atlanta, Georgia, USA ABSTRACT: The requirements for performance of pre-startup reviews

More information

Provision of containment integrity at Russian VVER NPPs under BDBA conditions

Provision of containment integrity at Russian VVER NPPs under BDBA conditions Provision of containment integrity at Russian VVER NPPs under BDBA conditions IAEA Technical Meeting Severe Accident Mitigation through Improvements in Filtered Containment Venting for Water Cooled Reactors

More information

AP1000 European 19. Probabilistic Risk Assessment Design Control Document

AP1000 European 19. Probabilistic Risk Assessment Design Control Document 19.39 In-Vessel Retention of Molten Core Debris 19.39.1 Introduction In-vessel retention of molten core debris through water cooling of the external surface of the reactor vessel is a severe accident management

More information

THE NATIONAL REPORT OF SOUTH AFRICA FOR THE SECOND EXTRAORDINARY MEETING OF THE CONVENTION FOR NUCLEAR SAFETY

THE NATIONAL REPORT OF SOUTH AFRICA FOR THE SECOND EXTRAORDINARY MEETING OF THE CONVENTION FOR NUCLEAR SAFETY THE NATIONAL REPORT OF SOUTH AFRICA FOR THE SECOND EXTRAORDINARY MEETING OF THE CONVENTION FOR NUCLEAR SAFETY South African National Report August 2012 1 Table of Contents Executive Summary... 5 1 Purpose...

More information

Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C

Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C Int. Conf. on Topical Issues in Nuclear Installation Safety, Vienna Austria, 6~9 Jun. 2017 Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C Contents 1. Introduction

More information

Safety Challenges for New Nuclear Power Plants

Safety Challenges for New Nuclear Power Plants Implementing Design Extension Conditions and Fukushima Changes in the Context of SSR-2/1 Michael Case Office of Nuclear Regulatory Research United States Nuclear Regulatory Commission Outline of Presentation

More information

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) 1.3.2016 Prof.Dr. Böck Technical University Vienna Atominstitut Stadionallee 2, 1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at

More information

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant 8 Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant KOZO TABUCHI *1 MASAYUKI TAKEDA *2 KAZUO TANAKA *2 JUNICHI IMAIZUMI *2 TAKASHI KANAGAWA *3 ATMEA1 TM is a 3-loop 1100

More information

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants 2016 OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants The company is certified according to three management systems: Certificate stn en iso 9001:2008 Quality management system

More information

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C August25, 2016

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C August25, 2016 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August25, 2016 Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467 SUBJECT:

More information

NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station September 18, 2017 Yutaka HARA Nuclear Regulation Authority (NRA), Japan 1 Contents Approach in NRA s Regulation

More information

Frequently Asked Questions: Japanese Nuclear Energy Situation

Frequently Asked Questions: Japanese Nuclear Energy Situation NUCLEAR ENERGY INSTITUTE Frequently Asked Questions: Japanese Nuclear Energy Situation 1. What will be the impact of the Fukushima Daiichi accident on the U.S. nuclear program? It is premature to draw

More information

Nuclear Power after Fukushima

Nuclear Power after Fukushima Nuclear Power after Fukushima Michael Corradini American Nuclear Society President: http://ans.org UW Energy Institute Chair: http://www.energy.wisc.edu 1 ANS Special Committee on Fukushima The special

More information

FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP

FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP NKS January 12-13, 2016 Ove Nilsson Sekretessklass: Open (S1) 1 2015-12-23 FOSH Forsmark Safety Enhancement Project F-0003165

More information

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES JOON-EON YANG Integrated Safety Assessment Division, Korea Atomic Energy Research Institute, Daedeok-daero 989-111,

More information

APR1400 Safe, Reliable Technology

APR1400 Safe, Reliable Technology APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics

More information

Request for 4M change self management strengthening

Request for 4M change self management strengthening Request for 4M change self management strengthening 1.Aug.2016 Device engineering Dep. Partner management Dep. Sony Global M&O Corp. 1 Request for 4M change self management strengthening Past cases of

More information

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis Verification of the Code Against SCDAP/RELAP5 for Severe Accident Analysis Jennifer Johnson COLBERT 1* and Karen VIEROW 2 1 School of Nuclear Engineering, Purdue University, West Lafayette, Indiana 47907-2017,

More information

Applicability of PSA Level 2 in the Design of Nuclear Power Plants

Applicability of PSA Level 2 in the Design of Nuclear Power Plants Applicability of PSA Level 2 in the Design of Nuclear Power Plants Estelle C. SAUVAGE a, Gerben DIRKSEN b, and Thierry COYE de BRUNELLIS c a AREVA-NP SAS, Paris, France b AREVA-NP Gmbh, Erlangen, Germany

More information

Strategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori

Strategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori Nuclear Damage Compensation and Decommissioning Facilitation Corporation Strategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori International

More information

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 Classification requirements 3 3.1 Principles of safety classification 3 3.2 Classification

More information

Current Status and Future Challenges of Innovative Reactors Development in Japan

Current Status and Future Challenges of Innovative Reactors Development in Japan Innovation for Cool Earth Forum 2017, Tokyo, Japan, October 4-5, 2017 Current Status and Future Challenges of Innovative Reactors Development in Japan 5 October, 2017 Yutaka Sagayama Assistant to the President

More information

-Update - Ministry of Economy, Trade and Industry Government of Japan

-Update - Ministry of Economy, Trade and Industry Government of Japan Japan s Nuclear Emergency -Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan Table of Contents A. Japan Faces an Unprecedented Challenge (Enormous Earthquake, Tsunamis

More information

Safety Research for the Disposal of Radioactive Waste Generated by Decommissioning of of Nuclear Power Facilities

Safety Research for the Disposal of Radioactive Waste Generated by Decommissioning of of Nuclear Power Facilities Safety Research for the Disposal of Radioactive Waste Generated by Decommissioning of of Nuclear Power Facilities Kenkichi ISHIGURE Japan Radioisotope Association 1 Decommissioning of nuclear power facilities

More information

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012 NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012 AP1000 IN FEBRUARY 2012, THE FIRST NUCLEAR POWER PLANTS IN THE US IN 35 YEARS WERE LICENSCED TO BEGIN CONSTRUCTION. TWO WESTINGHOUSE AP1000 NUCEAR REACTOR

More information

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear

More information

Technical Strategic Plan 2016 for Decommissioning of the Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Company Holdings, Inc.

Technical Strategic Plan 2016 for Decommissioning of the Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Company Holdings, Inc. Technical Strategic Plan 2016 for Decommissioning of the Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Company Holdings, Inc. Overview July 13, 2016 Nuclear Damage Compensation and Decommissioning

More information

EFFICIENCY OF FORTUM'S CSTREAT AND SRTREAT IN CESIUM AND STRONTIUM REMOVAL IN FUKUSHIMA DAIICHI NPP ABSTRACT

EFFICIENCY OF FORTUM'S CSTREAT AND SRTREAT IN CESIUM AND STRONTIUM REMOVAL IN FUKUSHIMA DAIICHI NPP ABSTRACT EFFICIENCY OF FORTUM'S CSTREAT AND SRTREAT IN CESIUM AND STRONTIUM REMOVAL IN FUKUSHIMA DAIICHI NPP ESKO TUSA Fortum Power and Heat Oy PO Box 100, 00048 Fortum, Finland ABSTRACT After the accident of March

More information

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as

More information

ACR-1000: ENHANCED RESPONSE TO SEVERE ACCIDENTS

ACR-1000: ENHANCED RESPONSE TO SEVERE ACCIDENTS ACR-1000: ENHANCED RESPONSE TO SEVERE ACCIDENTS Popov, N.K., Santamaura, P., Shapiro, H. and Snell, V.G Atomic Energy of Canada Limited 2251 Speakman Drive, Mississauga, Ontario, Canada L5K 1B2 1. INTRODUCTION

More information

Use of PSA to Support the Safety Management of Nuclear Power Plants

Use of PSA to Support the Safety Management of Nuclear Power Plants S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Use of PSA to Support the Safety Management of Nuclear Power Plants РР - 6/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS

More information

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT Z.K. Jankovsky The Ohio State University Columbus, USA Email: jankovsky.3@osu.edu

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

Development of technologies for the processing and disposal of radioactive waste

Development of technologies for the processing and disposal of radioactive waste Development of technologies for the processing and disposal of radioactive waste International Experts' Symposium on the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power Plant Unit 1-41 March

More information

CURRENT SENSING RESISTOR KRL SERIES- Susumu Co. Ltd. Thin Film Innovator

CURRENT SENSING RESISTOR KRL SERIES- Susumu Co. Ltd. Thin Film Innovator CURRENT SENSING RESISTOR KRL SERIES- Susumu Co. Ltd. Thin Film Innovator OUTLINE -CURRENT SENSING RESISTOR KRL SERIES- 1 STRUCTURE 2 SEVERAL ADVANTAGES WITH COMPARISON DATA 3 APPLICATION MANUAL STRUCTURE

More information

Monitoring of the EU Stress test improvement actions in neighbouring countries

Monitoring of the EU Stress test improvement actions in neighbouring countries Monitoring of the EU Stress test improvement actions in neighbouring countries Public Workshop: Five Years Fukushima, Thirty Years Chernobyl 26 th February 2016 Approach Review & monitoring of post Fukushima

More information

Demolition and Removal of Structures Damaged or Contaminated as a Result of the Fukushima Accident

Demolition and Removal of Structures Damaged or Contaminated as a Result of the Fukushima Accident IAEA International Experts Meeting on Decommissioning and Remediation after a Nuclear accident 0 Demolition and Removal of Structures Damaged or Contaminated as a Result of the Fukushima Accident January

More information

Belgian Stress Test Nuclear Power Plants (BEST)

Belgian Stress Test Nuclear Power Plants (BEST) Belgian Stress Test Nuclear Power Plants (BEST) 2013-08-26 TM IAEA: Belgian Stress Tests Stress Test Specifications Technical scope Initiating events Earthquake Flooding Other extreme natural events (extreme

More information

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK Impact of Extreme Events on Nuclear Facilities following Fukushima by Dr C H Shepherd Nuclear Safety Consultant, UK CRA PSA/HFA Forum 8-9 September 2011, Warrington Contents of the Presentation IAEA views

More information

Advanced Boiling Water Reactor

Advanced Boiling Water Reactor Advanced Boiling Water Reactor Energy production technologies for sustainable future Advanced Boiling Water Reactor - The only generation Ⅲ+ Reactor in Operation today - with Enhanced Safety, Performance

More information

Plant-specific safety review (RSK-SÜ) of German nuclear power plants in the light of the events in Fukushima-1 (Japan)

Plant-specific safety review (RSK-SÜ) of German nuclear power plants in the light of the events in Fukushima-1 (Japan) Note: This is a translation of Chapter 1 of the document entitled STATEMENT - Anlagenspezifische Sicherheitsüberprüfung (RSK-SÜ) deutscher Kernkraftwerke unter Berücksichtigung der Ereignisse in Fukushima-I

More information

Harmonized EUR revision E requirements corresponding to currently available technical solutions

Harmonized EUR revision E requirements corresponding to currently available technical solutions Harmonized EUR revision E requirements corresponding to currently available technical solutions Csilla TOTH - EUR Steering Committee MVM Paks II Ltd., Hungary, Technical Director IAEA International Conference

More information

Nuclear accident in Fukushima-I nuclear power plant: Critical Analysis

Nuclear accident in Fukushima-I nuclear power plant: Critical Analysis Nuclear accident in Fukushima-I nuclear power plant: Critical Analysis Sara Silva Pinto Wahnon Under supervision of José Joaquim Gonçalves Marques and Carlos António Abreu Fonseca Varandas Instituto Superior

More information

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY GUIDE YVL C.1 / 15 November 2013 STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 General design requirements 3 4 Radiation safety aspects in the layout design

More information

Activities of the Japan Gas Association in the National Projects for Fuel Cell and Hydrogen Society

Activities of the Japan Gas Association in the National Projects for Fuel Cell and Hydrogen Society Activities of the Japan Gas Association in the National Projects for Fuel Cell and Hydrogen Society By Yasuharu Kawabata, Hideyuki Kishi, Tatsuro Yasumatsu, Kazuhiro Matsumoto, Kouzou Kurahashi and Ryoichi

More information