PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY

Size: px
Start display at page:

Download "PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY"

Transcription

1 PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT

2

3 INTRODUCTION Shell U.K. Limited (Shell), with the support of SSE Generation Limited (SSE), is proposing to develop the world s first commercial scale gas fired carbon capture and storage (CCS) project at the existing SSE Power Station in Peterhead, Aberdeenshire, Scotland (see Figure 1). The Peterhead CCS Project (the Project) aims to demonstrate CCS technology from capture of carbon dioxide (CO 2 ) at the Power Station to injection into a depleted gas reservoir below the North Sea, at an industrial scale, in the UK. The Project will help to reduce carbon emissions from the UK s power sector. The Project aims to capture 1 million tonnes of CO 2 a year for years. The whole Project consists of three main components: Constructing and operating a CO 2 capture (known as, carbon capture) plant at the existing Peterhead Power Station. The CC plant will capture CO 2, which would otherwise be released to the atmosphere from one of the Power Station s existing gas turbines. It will then compress and dry the captured CO 2 in preparation for onward transportation. Transporting the CO 2 via a combination of new and existing pipelines to the Shell operated Goldeneye platform in the North Sea some 100 km to the north east of Aberdeen. A new direct offshore pipeline, approximately 20 km in length, will tie-in to the existing disused pipeline to the Goldeneye platform that runs from the Shell St. Fergus Gas Terminal north of Peterhead. Injecting the CO 2 into the depleted Goldeneye gas reservoir for permanent geological storage. The Goldeneye reservoir has the key geological features required for storing CO 2 : a body of high quality porous rock overlain and surrounded by layers of impermeable rock, which provide effective barriers to keep the CO 2 securely contained deep beneath the seabed. The Peterhead Power Station is owned and operated by SSE, while the Peterhead CCS Project will be operated by Shell with support from SSE. Goldeneye Platform St Fergus Terminal Peterhead Power Station Figure 1 Project Location and Schematic Plan i

4 PROJECT SCOPE This Non-Technical Summary (NTS) has been produced as part of the Environmental Statement (ES) for the onshore parts of the Project. This means it describes the likely significant impacts of the onshore components of the Project as far as the Mean Low Water Spring (MLWS). This is illustrated in Figure 2. Figure 2 Schematic of the split between the Project Onshore and Offshore ESs. The Project is considered to constitute Schedule 1 (Class 22) development, as prescribed by the Scottish Environmental Impact Assessment (EIA) regulations. (1) Therefore, an EIA is required to be carried out to inform the development consent process for the Project. Subject to gaining Planning Permission, the Project will require a number of other permits and consents to operate. This includes, but may not be limited to: Pollution Prevention and Control (PPC) Permits, regulated by the Scottish Environment Protection Agency (SEPA); Controlled Activities Regulations (CAR) permits, regulated by SEPA; Control of Major Accident Hazards (COMAH) site registration, regulated by the Health and Safety Executive (HSE) and SEPA; Hazardous Substances Consents, regulated by Aberdeenshire Council; and Minutes of Agreement with Transport Scotland for highways works. The onshore EIA is reported within this NTS and ES which supports a planning application to Aberdeenshire Council. Shell engaged the services of Environmental Resources Management Ltd (ERM), to lead the EIA, subsequent ES and planning permission for the onshore components of the Project. A separate offshore ES covers the Project elements from the MLWS out to the Goldeneye CO 2 Store. The offshore ES has been prepared by Genesis Oil and Gas Consultants Ltd (Genesis). 1 The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011 ii

5 ENVIRONMENTAL CONTEXT The Project is located in Aberdeenshire, on the north east coast of Scotland, between the settlements of Peterhead to the north and Boddam to the south (see Figure 3). There are various individual residential properties around the Power Station boundary. Aberdeen is the nearest city, located approximately 50 km to the south. The A90(T) is the main road in the area and runs in a north/south direction to the west of the Power Station. The site entrance for the Power Station is directly off this road. The Power Station is located within farmland which is generally slopes from the west down to the coastline in the east. Stirling Hill and Sandford Hill to the southwest, and Meethill to the north, are notable hills and give a sense of elevation and afford long distance views. Sandford Bay is to the north east of the Power Station and Boddam Harbour to the south. Peterhead Port is around the headland to the north of the Power Station. There are two small streams in the area: Invernettie Burn, which flows to the north of the Power Station into Sandford Bay; and Den of Boddam Burn which runs from around Sandford Hill passes under the A90(T) in culvert and remains in culvert around the Power Station before discharging into Sandford Bay. The grounds of the Power Station are predominantly grassland with areas of hedgerows and tree plantations. The land around is currently tenanted for grazing. The shoreline adjacent to the plant is predominantly common rocky and sediment shore. To the south of the site is the Buchan Ness to Collieston Coast Special Protection Area (SPA) which is a European designation for the protection of nesting seabirds. A 2 km marine extension area to the SPA covers the marine area to the east of the Power Station. This is designated to protect the area for the use of designated seabird species in the SPA. To the north of the Power Station site is Sandford Lodge, a listed building and the Burnside farm steading. These buildings are within the Power Station ownership and have an existing access from the A90(T). To the west of the Power Station, over the A90(T), is an existing SHETL substation. To the east of the Power Station is a coastal Right of Way running from Boddam to Peterhead. The Power Station area lies within the Energetica Corridor 2 which is an Aberdeenshire Council Strategic Framework Area for investment in energy technologies. Further details on the surrounding environment are provided in the ES within the individual impact assessment chapters (Chapters 5 15). 2 accessed 12/02/15 iii

6 PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT Figure 3 Environmental Context iv

7 PROJECT DESCRIPTION The EIA assesses all aspects of the Project which will occur onshore (i.e. above MLWS). The EIA has assessed construction, operation and decommissioning of the following elements: Modifications to the existing Power Station, including the construction of flue gas infrastructure, the steam turbine, Selective Catalytic Reduction (SCR) system, replacement auxiliary boilers and sea water cooling system expansion; New carbon capture and compression and conditioning plant at the Power Station; Associated infrastructure e.g. control room, power supply and substations, access road, storage tanks, workshop, drainage, Waste Water Treatment Plant (WWTP); Onshore section of the CO 2 export pipeline up to MLWS; and High voltage (HV) electricity cables from the SHETL substation to the west. The overall Project area required for construction and operation is set out in Figure 4. Once operational, all surface elements of the Project will be within the existing Power Station boundary. Figure 4 Project Extent/Planning Boundary Further details on the main Project elements and construction are set out in the following Figures: Figure 5 Main Project Components Figure 6 Description of Project Element Changes to Existing Power Station Figure 7 Description of Project Elements Carbon Capture Plant Figure 8 Description of Project Elements Compression and Conditioning Plant and Other Elements Figure 9 Construction Details 1 Figure 10 Construction Details 2 v

8 This page is intentionally blank vi

9 Figure 5 Main Project Components vii

10 Figure 6 Description of Project Element Changes to Existing Power Station viii

11 Figure 7 Description of Project Elements Carbon Capture Plant ix

12 Figure 8 Description of Project Elements Compression and Conditioning Plant and Other Elements x

13 PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT Figure 9 Construction Details 1 xi

14 PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT Figure 10 Construction Details 2 xii

15 OPTION SELECTION/ ALTERNATIVES The design of the Project has developed iteratively to reduce impacts, alongside the EIA process. Throughout design, a number of the alternatives were considered and reviewed prior to project design selection. Given the nature of the Project as a post combustion gas carbon capture technology there are limited alternative sites in the UK which could be considered for this sort of project. In addition, the Peterhead site was commercially available to the project team and has the advantage of being the closest possible facility to the Goldeneye Platform for the CO 2 injection and storage phase, reducing the additional infrastructure required. Various alternative site layouts have been reviewed and progressed. Where site layout alternatives have the potential to influence the environmental impacts this has been taken into account. Alternative design options were considered for: Waste Water Treatment Plant (WWTP); Auxiliary boiler locations; CO 2 transportation; CO 2 source; and CO 2 capture technology. IMPACT ASSESSMENT METHODOLOGY The impact assessment process is aimed at identifying the Project activities that are likely to result in significant impacts to the natural and social environment throughout the life of the project. In accordance with EIA best practice and guidance, the EIA assesses the significance of the impacts identified in relation to their magnitude and sensitivity. The term magnitude is used as shorthand to encompass all the dimensions of the predicted impact including: The nature of the change (what is affected and how); Its size, scale or intensity; Its geographical extent and distribution; Its duration, frequency, reversibility; and Where relevant, the probability of the impact occurring as a result of accidental or unplanned events. No relevant unplanned events are identified in the onshore EIA. Major accidents and threats to the environment will be considered by an assessment required under the Control of Major Accident Hazards (1999) Regulations, as amended, at a later stage of Project development, prior to operation. The significance of an impact of a given magnitude will depend on the characteristics of resources and receptors subject to that impact in terms of their value (e.g. importance, quality) or sensitivity. Evaluation of sensitivity is subjective and is based on the judgement of those undertaking the EIA informed by legal standards, current industry good practice, Government policy and stakeholder views. As such, what specifically defines sensitivity varies depending on the receptor of the impact. The magnitude of the impact and sensitivity of the receiving environment is then combined to determine the impact significance as shown in Table 1. Impacts can be positive and negative, short or long term, permanent or temporary and/or direct (as in an integral part of the project) or indirect (as in an impact arising from activities not directly related to the Project). xiii

16 Table 1 Evaluation of Significance SENSITIVITY A - Low B - Medium C - High 0 - Positive Impact Positive Positive Positive MAGNITUDE 1 - Negligible Negligible Negligible Negligible 2 - Small Negligible Minor Moderate 3 - Medium Minor Moderate Major 4 - Large Moderate Major Major Within the ES, further information on the specific methodology applied to each topic is provided. The EIA identifies mitigation measures that can be put in place to prevent, reduce or offset the identified adverse environmental impacts, or indeed to create or enhance environmental benefits. These are then taken into account in defining a residual impact. CONSULTATION Through the EIA process Shell has undertaken extensive public consultation. In addition, meetings with regulators and statutory consultees have been undertaken. Throughout the consultation there were a number of comments of support as well as a number of concerns raised. Shell has recorded and taken into account this feedback throughout the EIA process. The feedback from consultation has informed and influenced the design of the Project. The planning application is supported by a Pre-Application Consultation Report. ASSESSMENTS OF IMPACT Introduction The sections below provide a brief non-technical summary of the topic assessments undertaken to complete the ES. Traffic, Transport and Public Rights of Way The construction, operation and decommissioning of the Project will generate additional traffic through the transport of materials and waste to and from the site and the transport of workers. Additional traffic will be concentrated on the A90(T). Construction will generate the most additional traffic on the A90(T). The peak traffic flows of around 450 total daily traffic movements (a movement is a single vehicle journey to or from the Project, so one vehicle will result in two movements). The peak traffic flow will occur for a 6 month period from late The increases in traffic flows over the construction period are shown in Figure 11. During public consultation in February 2015 concerns were raised regarding the peak traffic flows during xiv

17 Aug-16 Oct-16 Dec-16 Feb-17 Apr-17 Jun-17 Aug-17 Oct-17 Dec-17 Feb-18 Apr-18 Jun-18 Aug-18 Oct-18 Dec-18 Feb-19 Apr-19 Jun-19 No. of Movements PETERHEAD CCS PROJECT ONSHORE ENVIRONMENTAL STATEMENT construction. Based on this feedback, Shell reappraised the delivery programme and the phasing of works to avoid peak activities for the various elements of the Project happening simultaneously. This has allowed the Project team to reduce the estimated peak daily construction traffic flow HGV Car/Van Coaches Total Vehicles 50 0 Date Figure 11 Estimated traffic movements during the construction period Table 2 provides a summary of impacts resulting from increased generation of traffic during construction. Table 2 Assessment of Impacts during Construction Period SOURCE OF POTENTIAL IMPACT UNMITIGATED POTENTIAL IMPACT MITIGATION MEASURES RESIDUAL IMPACT Construction Trips Worker Increased traffic on: A90(T) A982 Potential to impact other road users. Some workers will be transported by coach (managed via construction traffic management plan). The construction traffic management plan will promote car sharing. Modularised construction will be promoted. Negligible increase in traffic and negligible impact on other road users. HGV construction traffic Increased HGV numbers on: A90(T) A982 Potential to impact other road users. Delivery timings to be monitored to avoid peak periods (managed via construction traffic management plan). Right hand turning lane will be constructed on A90 (T) at main access to reduce congestion and increase safety. Excavated material will be reused within the site boundary wherever Negligible increase in HGV movements and negligible impact on other road users xv

18 possible to avoid transportation to landfill. A batching plant will be located on site to reduce concrete deliveries by road. Upgrade of existing junction to make a second construction access at Sandford Lodge. Abnormal Loads (AILs) Indivisible Obstruction for normal vehicles Requirement for minor and temporary street furniture removal/relocation Load Routing to be agreed with local authority and police. AILs will be transported outside of peak traffic and marshalled by patrols. Street furniture to be removed in advance. Maximise use of Peterhead Port. Minor impact on other road users The construction impacts assessed are for the peak flows during construction and these will only occur over a short period within the Construction Programme. Once in operation the amount of traffic generated will be notably reduced to 30 cars entering and leaving the Project. There will also be deliveries in HGVs the maximum being up to 40 tankers in a 24 hour period, two times a year, when amine is delivered. In relation to access and Public Rights of Ways, the assessment of impacts has identified one moderate impact on community severance during construction. This is the temporary closure of Right of Way GB207, which runs along the coast to the east of the Power Station from Boddam to Peterhead. This closure could be up to nine months during construction of the export pipeline, if open cut trenching is used. This would result in a diversion along the A90(T) of approximately 4 km. Local residents will be notified of the temporary closure of the Right of Way prior to closure. Pedestrians will be directed using clear instructions. When construction is complete, the paths will be reinstated. Should Horizontal Direction Drilling (HDD), the preferred option, be technically feasible then the closure period will be reduced to an approximate two week period and the assessed impact will be negligible. No significant impacts have been identified during the operational phase. Impacts during decommissioning will be similar to, and no worse than, those identified during construction. Noise and Vibration The EIA has considered the likely noise and vibration impacts of the Project against regulatory guidance and existing planning conditions applied to the Power Station. The assessment has evaluated the impacts at seven Noise Sensitive Receptors (NSRs). These are the seven nearest residential properties around the Project. During construction daytime works are predicted to have Minor impacts or below at all NSRs. Some activities will require construction works to continue at night. These activities are predicted to result in Moderate impacts at four of the NSRs. These moderate impacts would not occur if Horizontal Directional Drilling (HDD), which is the preferred option, is progressed. If HDD cannot be progressed the construction phasing and construction techniques employed for the offshore trenching will be reviewed to reduce night time noise where possible. Once operational, impacts are predicted to be Minor or below at all NSRs. This is due, in part, to noise control measures such as acoustic housings which have been integrated into the Project design. xvi

19 Air Quality The air quality impact assessment has undertaken modelling to predict the dispersion of emissions from the Project. The emissions modelled include Oxides of Nitrogen (NO x ), Nitrogen Dioxide (NO 2 ), amines, nitrosamines and nitramines (collectively referred to as N-amines), ammonia and odour. The key findings of the assessment are that the operation of the Project is not predicted to result in any Environmental Assessment Levels (EALs) being exceeded. EALs are criteria for the protection of human health derived from air quality standards and air quality guidelines. The Project, once operational, is predicted to result in a reduction in impacts associated with emissions of NOx and NO 2, both at sensitive human and sensitive ecological receptors. The operation of the Project is predicted to result in the reduction of impacts at designated habitat sites. These are positive impacts. Considerable efforts have been made, in consultation with SEPA, to develop methodologies for the assessment of the emissions of amines and subsequent impacts associated with N-amines. The methods that have been investigated and established, consider several aspects of the atmospheric chemistry of amines. Overall, the assessment has been able to present robust, yet conservative, results. The results demonstrate that impacts from N-amines are expected to be below the SEPA adopted EAL. No significant impacts have been identified associated with emissions from traffic during either construction phase or operational phase. Odour emissions are also of negligible impact, this is due in part to the inclusion of odour abatement technology on the Waste Water Treatment Plant which will mitigate risks of odour from this process. Dust emissions during construction have the potential to result in significant impacts at sensitive residential receptors around the Project. However, the implementation of the recommended dust management mitigation measures within the Construction Environmental Management Plan (CEMP) will manage these impacts. Geology, Contaminated Land and Hydrology During construction, procedures will be in place to manage spill risks to minimise the potential for impacts to the underlying groundwater. If historical contamination is encountered the contamination source or linkage will be removed, providing a beneficial impact to the environment and therefore a minor positive residual impact. Waste The EIA has considered the likely waste streams to be generated by the Project and the management of these waste streams. During construction the following waste are expected: Excavation materials: all are expected to be re-used on site with little waste being generated. Demolition materials will be re-used where possible. However it is estimated that less than 6,000 tonnes will leave the site for recycling, recovery or disposal. This waste amount is expected to be easily accommodated by the capacity available within north east Scotland. Construction waste: it is anticipated that approximately 5,700 tonnes of construction wastes will leave the site either for recycling, recovery or disposal. This waste amount is expected to be easily accommodated by the capacity available within north east Scotland. Once operational, general waste flows from the facility are expected to be similar in scale to the current operational facility. xvii

20 The Project will include some sludge wastes which are a new waste stream. They are expected to be treated at licensed facilities off-site including a high temperature incinerator facility. The facilities will be selected based on their ability and capacity to treat the wastes. The impact of the waste is to remove capacity at these facilities that would otherwise have been available. The Project will have both construction and operation waste management plans. The waste management plans, when developed, will monitor waste arisings, how they are managed and performance against any waste targets set in this area. Water Quality and Flooding The EIA has considered the potential impacts to surface water features, such as rivers and the risk of flooding both to and from the Project. The Construction Environmental Management Plan and the design of the Project will minimise spill risks to surface water. As is currently the case, the Den of Boddam burn has the potential to cause flooding to some parts of the Project. Sensitive equipment will be located away from potentially affected areas, and escape or refuge routes provided for staff. Ecology The EIA has considered the impacts of the Project on ecological and nature conservation features. The Project will result in some loss of existing, low value, habitats and disturbance during construction. The habitat loss will be mitigated in the long term by planting of new woodland and the temporary construction areas being restored. Suitable species mixes will be used to maintain and where possible enhance ecological value. The presence of breeding birds has been considered and once construction is completed and habitat restored there will be no significant operational impacts. Impacts from the Project on seabirds will be temporary and mitigation measures will help reduce any impacts if open trenching is required. If HDD is possible, then there will be no significant onshore impacts to seabirds. Landscape and Visual The EIA has considered the landscape and visual effects of the Project. This has been done in accordance with Landscape Institute and Institute of Environmental Management and Assessment guidance and Scottish Natural Heritage Guidance. The assessment considered 19 surrounding viewpoints as shown in Figure 12. xviii

21 Figure 12 Location of viewpoints The assessment found that there will be no significant residual impacts on the landscape character of the area during construction, operation or decommissioning. During construction and decommissioning, the following visual receptors will experience visual impacts: Coastal footpath adjacent power station; Sea View Road/View Gardens, Boddam; Properties adjacent Boddam Playing Fields along the B9108; and Elevated viewpoint adjacent Power Station. During operation the following visual receptors will experience visual impacts: Sea View Road/View Gardens, Boddam; Property opposite Gatehouse on A90(T); and Newton. It is recognised in the Assessment that the Project is part of the Energetica Peterhead Southern Gateway Environmental Improvement Masterplan. This means there is the opportunity to improve the setting of the Peterhead Power Station and the approach to the town of Peterhead along the A90(T) corridor. These opportunities have been included within the Landscape Masterplan, proposed for the project and include: stone entrance wall features, possible mounding, and woodland planting to infill some areas of existing planting and enhance the setting of the Power Station. The Landscape Masterplan will also include a new education board and view facility at the public carpark adjacent to the A90(T). xix

22 Cultural Heritage The EIA has considered the impacts on cultural heritage features, including the setting of listed buildings, and archaeology. Direct physical impacts on buried archaeological remains will only occur during the construction and decommissioning phase, when there is ground disturbance. The open cut trenching of the export pipeline and the HV cables have the potential to disturb features of archaeological interest. It is proposed that an archaeological watching brief is agreed with the Council for these works. The construction, operation or decommissioning of the Project will result in no significant impacts on cultural heritage. Socio-economics The Project will employ an average of 400 people during construction, with a peak of 600. operational the Project will employ up to 30 new people. Once The Project s construction phases will bring significant economic and social benefits through direct expenditure and the supply chain, safeguarding existing employment and creating new direct, indirect and induced jobs. Strategies are being developed to prioritise local procurement, enhancing the economic benefits experienced by communities and businesses local to the Project. The anticipated influx of itinerant workers has the potential to negatively affect communities in proximity of their accommodation and the Power Station, through increasing pressure on local services and social cohesion impacts. Workers will stay at a wide range of locations in the area, to spread the load on services and also benefit of the additional income generated. Wider economic benefits will be realised through the Project demonstrating feasibility of commercial-scale CCS and the benefits that wider CCS deployment will deliver in contributing to decarbonisation of the UK energy mix and industrial activities, securing energy security, supporting industrial activities (particularly energy-intensive industries) and reducing energy poverty. Marine Environment The Project will include additional discharge, from the Waste Water Treatment Plant, through the existing Power Station outfall to the sea in Sandford Bay. The EIA has assessed and modelled the impact of this effluent discharge stream to the marine environment. The discharge plume is largely contained within Sandford Bay. The results from the plume modelling exercise indicate that the proposed combined discharge of treated effluent is not likely to exceed any consent thresholds within 100 m of the outfall. The effluent stream from the Waste Water Treatment Plant will be subject to regular testing, as agreed with SEPA. On the basis of the modelling, all impacts to marine environment receptors have been assessed as not significant or of negligible significance. Cumulative Effects The ES has considered the impacts of the Project with other reasonably foreseeable developments in the area. Cumulative impacts of the Project in combination with the new substation at Newton of Sandford and the proposed converter station at the Fourfields site have been identified. Minor cumulative impacts are identified on landscape and visual receptors. These will be partially mitigated through woodland planting at the project boundary frontage, adjacent to Boddam and north of the compression plant. A minor cumulative impact is identified on the setting of Buchan Ness Lighthouse. A moderate cumulative noise impact is identified at NSR R5 (Newton) for a period of up to 10 months during construction. xx

23 The proposed extension of the Stirling Hill Quarry by Breedon Aggregates has been considered. It is understood that these proposals, whilst not yet approved, will not change the current quarry operations, so cumulative effects are not expected. The Aberdeen Western Peripheral Road, Balmedie-Tipperty Section, was discussed during initial consultations with Aberdeenshire Council. However, as it is located approximately 20 km from the Project, it is not included within the Project assessment. Shell has, following feedback from the public regarding the simultaneous construction of the two projects, contacted the AWPR project team directly. With regards to traffic, the AWPR is predominantly offline, and it is understood that dual carriageway access along the northern Balmedie to Tipperty section of the A90(T) is expected to be maintained throughout construction. Shell will continue to consult with the AWPR project to manage potential cumulative impacts as the PCCS Project progresses. The assessment also identifies the potential for in-combination intra project impacts, for example impacts from both the on and offshore elements of the Project at residential properties surrounding the Project. Should intra project impacts occur they are expected to be for short durations only during the construction period. The CEMP will seek to minimise construction impacts. Residual Impacts and Mitigation The Environmental Statement includes a summary table of the impacts identified, mitigation proposed and residual impact concluded by the Assessment. Consultation, Feedback and Further Information The planning application for this Project has now been submitted to Aberdeenshire Council and will be subject to a 28 day consultation period. If you would like to make comment upon, support, or object to this application please contact Aberdeenshire Council: Ms Victoria Moore Planning Officer, Strategic Development Delivery Team Local Planning Office, Aberdeenshire Council Arbuthnot House Broad Street Peterhead AB42 1DA If you would like further information, the full application can viewed on the Aberdeenshire Council Planning Portal: A copy of the full ES is also available on the Project website: xxi

24 In addition, hard copies of the full ES can be viewed at the following locations: Shell UK Office, 1 Altens Farm Road, Nigg, Aberdeen, AB12 3FY, United Kingdom Boddam Library, 26 Queens Road, Boddam, Peterhead, AB42 3AX The Hot Spot, 1-3 Kirk Street, Peterhead, AB42 1LA Arbuthnot House, Broad Street, Peterhead, AB42 1DA Maud Area Office, Nethermuir Road, Maud, AB42 4ND A copy of the full ES can be purchased, by request, at the cost of printing for 350. Please peterheadccs@shell.com or call if you wish to order a copy. xxii

25 ACRONYMS NSR Noise Sensitive Receptors BAT Best Available Technique NTS Non Technical Summary CAR Controlled Activities Regulations PPC Pollution Prevention and Control CC Carbon Capture SCR Selective Catalytic Reduction CCP CCS CEMP Carbon Capture Plant Carbon Capture and Storage Construction Environmental Management Plan SEPA SPA SSE Scottish Environment Protection Agency Special Protection Area SSE Generation Limited CIA Cumulative Impact Assessment WWTP Waste Water Treatment Plant CO 2 Carbon Dioxide COMAH Control of Major Accident Hazards DCC Direct Contact Cooler EAL Environmental Assessment Levels EIA Environmental Impact Assessment ES Environmental Statement GT Gas Turbine GT13 Gas Turbine 13 HDD HGV HSE HV IX m MLWS NO x NO 2 Horizontal Directional Drilling Heavy Goods Vehicle Health and Safety Executive High Voltage Ion Exchange Metre(s) Mean Low Water Spring Oxides of Nitrogen Nitrogen Dioxide XXIII

26 This page is intentionally blank xxiv

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

A proposed new gas-fired power station on the Wilton International site

A proposed new gas-fired power station on the Wilton International site TEES CCPP PROJECT A proposed new gas-fired power station on the Wilton International site Welcome This event is intended to provide you with information about the proposed Tees Combined Cycle Power Plant

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

High Pressure Natural Gas Pipeline Pembroke Refinery. Environmental Statement Non-technical Summary

High Pressure Natural Gas Pipeline Pembroke Refinery. Environmental Statement Non-technical Summary High Pressure Natural Gas Pipeline Pembroke Refinery Environmental Statement Non-technical Summary July 2010 1. Introduction 1.1 Overview 1. Chevron Limited (Ltd) is seeking detailed planning permission

More information

Thorn Turn Winter Maintenance and Highways Depot

Thorn Turn Winter Maintenance and Highways Depot Thorn Turn Winter Maintenance and Highways Depot Non-Technical Summary Central Bedfordshire Council 12 May 2015 1 Notice This document and its contents have been prepared and are intended solely for Central

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

Ardersier Wastewater Treatment Works

Ardersier Wastewater Treatment Works Ardersier Wastewater Treatment Works Environmental Statement: Non-Technical Summary March 2010 Scottish Water Ardersier Wastewater Treatment Works 251886 SNI INV ES 021 10 March 2010 Environmental Statement:

More information

Interim Public & Stakeholder Communication Plan

Interim Public & Stakeholder Communication Plan Interim Public & Stakeholder Communication Plan Department Permitting Doc. Last approval: Date: 2015.08.13 By: Fiona Henderson Control: Jason Ormiston Approved by: Øyvind Øtterson 1 1 Contents 1 Executive

More information

npower who we are Tilbury Power Station

npower who we are Tilbury Power Station npower who we are npower who we are RWE npower, part of the RWE Group, is the leading UK energy company committed to conducting its business with a sense of responsibility for the environment, its customers

More information

Appendix A: Project Characteristics

Appendix A: Project Characteristics Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project

More information

Western Rail Link To Heathrow

Western Rail Link To Heathrow Non-T echnical Summar y - Initi al Envir onmental Infor mati on R eport Networ k R ail Western Rail Link To Heathrow Network Rail Non-Technical Summary - Initial Environmental 129088-JAC-REP-HEN-000014

More information

Air Quality. Executive Summary

Air Quality. Executive Summary Air Quality Executive Summary Air quality adjacent to the Scheme is currently good with low background concentrations of air pollutants. However, there are areas within Cambridge city centre which currently

More information

NON-TECHNICAL SUMMARY

NON-TECHNICAL SUMMARY NON-TECHNICAL SUMMARY S1 INTRODUCTION This Environmental Statement (ES) Addendum presents the findings of the Environment Impact Assessment (EIA) conducted by TOTAL E&P UK Limited (TOTAL) for the development

More information

Introduction. The Need for Wind Energy. Consultation. The Applicant

Introduction. The Need for Wind Energy. Consultation. The Applicant Introduction Peel Wind Farms (UKC) Ltd (Peel) propose to construct a wind farm on an area of land that forms part of the former Asfordby mine and tip site and part of the existing Asfordby Business Park

More information

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT Welcome Eggborough Power Ltd (EPL) is proposing to develop a new gas-fired power station on the site of its existing coal-fired

More information

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes MINISTRY OF ENVIRONMENT AND NDU ENVIRONMENTAL GUIDELINE No. 31 Asphalt Plant Set Up Temporarily For The Purposes Of A Project By A Public Department 1.0 Purpose of guideline This environmental guideline

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

BUT001: Land to the east of Benington Road, Butterwick Sustainability Objective

BUT001: Land to the east of Benington Road, Butterwick Sustainability Objective BUT001: Land to the east of Benington Road, Butterwick Sustainability Objective 1. Provide a miture of sustainably designed new housing to provide everybody in South East Lincolnshire with the opportunity

More information

Welcome To Our Exhibition

Welcome To Our Exhibition Welcome To Our Exhibition Welcome to the exhibition of our proposals for a Waste Recycling and Renewable Energy Facility Distributed Renewable Energy Networks Ltd (DRENL) propose to develop a 10MW Waste

More information

Environmental Information Worksheet

Environmental Information Worksheet Environmental Information Worksheet Water System Owner (Attach additional sheets if necessary) Needs and Alternatives Provide a brief narrative that describes: Current drinking water system needs. Project

More information

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

(1) Site Suitability PURPOSE

(1) Site Suitability PURPOSE 3.3 Code for Development and Use of Rural Service Industries PURPOSE This purpose of this code is to encourage the development and use of suitable rural service industries on rural, industrial or suitable

More information

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT The health of the world s oceans and marine life is degrading rapidly as a result of excess human activities.

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

Overview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition

Overview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition and Stronelairg s Overview SSE Renewables SSE Renewables is the renewable energy development division of SSE. The company is responsible for the development of onshore and offshore wind farms in the UK,

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies...

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies... Section Contents Rural-Residential... 2 16. Rural-Residential... 2 Explanatory Statement... 2 16.1 Significant Issues... 2 16.2 Objectives and Policies... 3 16.3 Activity Lists... 3 16.4 Activity Performance

More information

THE NORTH EAST OF SCOTLAND PARTNERSHIP WRITTEN SUBMISSION

THE NORTH EAST OF SCOTLAND PARTNERSHIP WRITTEN SUBMISSION THE NORTH EAST OF SCOTLAND PARTNERSHIP FREIGHT TRANSPORT IN SCOTLAND WRITTEN SUBMISSION The Scottish Parliament s Infrastructure and Capital Investment Committee has announced that it will undertake an

More information

6.0 CONSTRUCTION PROGRAMME

6.0 CONSTRUCTION PROGRAMME 6.0 CONSTRUCTION PROGRAMME Introduction 6.1 This chapter of the ES describes the expected construction works programme and the key activities that will be undertaken. Detailed consideration of potential

More information

Chapter 14 Overall Project Assessment

Chapter 14 Overall Project Assessment Chapter 14 Overall Project Assessment TABLE OF CONTENTS 14 OVERALL PROJECT ASSESSMENT... 14-1 14.1 Introduction... 14-1 14.2 Development of the ESIA... 14-1 14.2.1 Adopted Process... 14-1 14.2.2 Challenges

More information

energy, environment & design aterman Poniel, South Lanarkshire Environmental Statement: Non-Technical Summary

energy, environment & design aterman Poniel, South Lanarkshire Environmental Statement: Non-Technical Summary aterman energy, environment & design Poniel, South Lanarkshire Poniel, South Lanarkshire Non-Technical Summary INTRODUCTION SRG Estates Limited (SRGE) (hereafter referred to as the Applicant ) is seeking

More information

Chapter 3 Affected Environment and Environmental Consequences

Chapter 3 Affected Environment and Environmental Consequences Sterling Highway MP 45 60 Draft SEIS and Draft Section 4(f) Evaluation Chapter 3 Affected Environment and Environmental Consequences Prepared for: Alaska Department of Transportation and Public Facilities

More information

Rural Living Environment

Rural Living Environment 1 RLE.1 Rural Living Environment RLE.1.1 Description & Expectations The Rural Living Environment (RLE) covers rural areas within the District that are either already characterised by lifestyle activities

More information

BSkyB Site Levelling and Remediation Works. Environmental Statement Volume 3. Planning Application June 2013 Non-Technical Summary

BSkyB Site Levelling and Remediation Works. Environmental Statement Volume 3. Planning Application June 2013 Non-Technical Summary BSkyB Site Levelling and Remediation Works Environmental Statement Volume 3 Planning Application June 2013 Non-Technical Summary BSkyB Site Levelling and Remediation Works Environmental Statement Volume

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

Inveraray to Crossaig Overhead Line Reinforcement

Inveraray to Crossaig Overhead Line Reinforcement About Scottish Hydro Electric (SHE) Transmission plc Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the electricity networks in

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information

Environmental Impact Assessment (EIA) Owen Struthers Development Management Branch Welsh Government

Environmental Impact Assessment (EIA) Owen Struthers Development Management Branch Welsh Government Environmental Impact Assessment (EIA) Owen Struthers Development Management Branch Welsh Government Environmental Impact Assessment Introduction New Directive: Directive 2014/52/EU of the European Parliament

More information

H2. Residential Rural and Coastal Settlement Zone

H2. Residential Rural and Coastal Settlement Zone H2. Residential Rural and Coastal Settlement Zone H2.1. Zone description The Residential Rural and Coastal Settlement Zone applies to rural and coastal settlements in a variety of environments including

More information

Waste Management, a Role for Surveyors - Linking the Environment and Planning

Waste Management, a Role for Surveyors - Linking the Environment and Planning Waste Management, a Role for Surveyors - Linking the Environment and Planning John R PARKER, Australia Key words: Waste management, environment, planning, extractive industry, recycling, landfill SUMMARY

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

SHELL ONSHORE OPERATING PRINCIPLES

SHELL ONSHORE OPERATING PRINCIPLES SHELL ONSHORE OPERATING PRINCIPLES FOR TIGHT SAND OR SHALE OIL AND GAS In 2011, Shell publicly shared five aspirational operating principles that govern the activities where we operate and where hydraulic

More information

Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects

Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects Insert then choose Picture select your picture. Right click your picture and Send to back. August 6-8 th, 2014 Craig A. Reid Partner,

More information

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0 RMB Chivenor Flood Defence Scheme Non-Technical Summary FINAL Version 3.0 RMB CHIVENOR FLOOD DEFENCE SCHEME ENVIRONMENTAL STATEMENT CONTENTS 1 INTRODUCTION AND BACKGROUND II 2 THE PROPOSED PROJECT III

More information

Sustainability Roadmap for Myanmar (Environment Perspective) Dr. San Oo Director Environmental Conservation Department 20 January 2015

Sustainability Roadmap for Myanmar (Environment Perspective) Dr. San Oo Director Environmental Conservation Department 20 January 2015 Sustainability Roadmap for Myanmar (Environment Perspective) Dr. San Oo Director Environmental Conservation Department 20 January 2015 1 Ministry of Environmental Conservation and Forestry (MOECAF) Environmental

More information

H3. Residential Single House Zone

H3. Residential Single House Zone H3. Residential Single House Zone H3.1. Zone description The purpose of the Residential Single House Zone is to maintain and enhance the amenity values of established residential neighbourhoods in number

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION

BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION Force 9 Energy is seeking to develop a 5 turbine wind farm 1.5km to the east of Auldgirth, approximately 15km north of Dumfries. It is bounded to the north

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

Port of Hull Local Development Order

Port of Hull Local Development Order Port of Hull Local Development Order Integrated Environmental Assessment Non Technical Summary March 2012 Final Prepared for: Hull City Council UNITED KINGDOM & IRELAND REVISION SCHEDULE Rev Date Details

More information

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. The site comprises the employment element of the South West Rugby allocation

More information

Surrey County Council: Environmental Impact Assessment (EIA) Screening Opinion Report

Surrey County Council: Environmental Impact Assessment (EIA) Screening Opinion Report Surrey County Council: Environmental Impact Assessment (EIA) Screening Opinion Report Prepared under Regulation 6 of the Town & Country Planning (Environmental Impact Assessment) Regulations 2017 Site:

More information

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary

More information

PUBLIC November Dogger Bank Stakeholder Engagement Plan

PUBLIC November Dogger Bank Stakeholder Engagement Plan PUBLIC November 2011 Dogger Bank Stakeholder Engagement Plan Dogger Bank Stakeholder Engagement Plan PUBLIC November 2011 Dogger Bank Stakeholder Engagement Plan Document no. : Contract no. (if applicable):

More information

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment

More information

Construction of Dariali HEPP. Reinstatement Plan

Construction of Dariali HEPP. Reinstatement Plan Construction of Dariali HEPP Reinstatement Plan 2016 Table of Content 1. Introduction... 3 2. Site Clean-up... 4 3. Headwork Site Reinstatement... 4 4. Reinstatement Of The Pipeline Corridor.9 5. Cable

More information

Division 8 Intensive Animal Husbandry Code

Division 8 Intensive Animal Husbandry Code Division 8 Intensive Animal Husbry Code 12.8.1 Intensive Animal Husbry Code (1) The provisions in this division comprise the Intensive Animal Husbry Code. (2) They are compliance with the Intensive Animal

More information

Loy Yang B Environment Improvement Plan

Loy Yang B Environment Improvement Plan Loy Yang B Environment Improvement Plan 2017 Table of Contents 1 Endorsement 1 2 Environment Policy 2 3 Operating Arrangements 3 4 Site Management and Business Systems 4 5 Environmental Impacts and Risks

More information

NSN LINK. Environmental Statement. Environmental Statement Figures and Appendices

NSN LINK. Environmental Statement. Environmental Statement Figures and Appendices NSN LINK Environmental Statement Environmental Statement Figures and Appendices July 2014 NSN LINK UK ONSHORE DEVELOPMENTS Prepared by TEP For NSN Link Ltd TEP Genesis Centre Birchwood Science Park Warrington

More information

Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events)

Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events) Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events) TABLE OF CONTENTS 12 HAZARD ANALYSIS AND RISK ASSESSMENT... 12-1 12.1 Introduction... 12-1 12.2 Pipeline Design and Risk... 12-1 12.2.1

More information

LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY

LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 1 LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY Document Production &

More information

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2 Summary of LAE ONTARIO 1. Requiring SPC approval: LO SEW 3 LO FUEL 2 2. Information (editorial, revised, new): LO G 1 (revised) LO NGS 1 (revised) LO G 2 (revised) LO SEW 2 (revised) LO G 6 (revised) LO

More information

Ecological Mitigation and Management Plan

Ecological Mitigation and Management Plan Ecological Mitigation and Management Plan LONDON ARRAY OFFSHORE WIND FARM PROJECT AND ASSOCIATED GRID CONNECTION WORKS Version / Date : Ver 1.00 / October 2007 Prepared by : Tim Proudler / Keith Henson

More information

H3 Residential Single House Zone

H3 Residential Single House Zone H3. Residential Single House Zone [ENV-2016-AKL-000243: K Vernon] Addition sought [CIV-2016-404-002333: Franco Belgiorno-Nettis]-Note: The properties affected by this appeal are identified on the Auckland

More information

SUTTON ESTATE, CHELSEA ENVIRONMENTAL STATEMENT JULY 2015 Volume I - Non-Technical Summary

SUTTON ESTATE, CHELSEA ENVIRONMENTAL STATEMENT JULY 2015 Volume I - Non-Technical Summary SUTTON ESTATE, CHELSEA ENVIRONMENTAL STATEMENT JULY 2015 Volume I - Environmental Statement Volume 1 Sutton Estate, Chelsea Project no: KU048600 Document title: Environmental Statement Volume 1 - Revision:

More information

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure Additional Information Regarding The Implementation Programme

More information

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate Project Overview Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate a natural gas-tomethanol production plant and storage facilities, and a new marine terminal, in the

More information

13 Section 32 Summary for the Residential Chapter

13 Section 32 Summary for the Residential Chapter 13 Section 32 Summary for the Residential Chapter The purpose of this section is to present a summary of the evaluation of the objectives, policies and methods of the Residential Zone Chapter of the Proposed

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

Former MOD Site Hempsted Lane, Gloucester

Former MOD Site Hempsted Lane, Gloucester FORMER MOD SITE, HEMPSTED LANE, GLOUCESTER NON-TECHNICAL SUMMARY Introduction Bovale Ltd proposes to undertake the redevelopment of the former MOD site, Hempsted Lane, Gloucester. The redevelopment will

More information

Background and Project Description. Chapter 05: Description of Development

Background and Project Description. Chapter 05: Description of Development Background and Project Description Chapter 05: Description of Development Background and and Project Project Description Description DESCRIPTION OF DEVELOPMENT OF Chapter Chapter Contents Contents...

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1 AMDAL Procedure (This is only indicative and for reference purposes. This is not exhaustive and therefore, the Consultants are requested to familiarize themselves with all the laws, rules, regulations,

More information

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group Environmental Management System Integrated Pollution Control Document No. 5.2.1 Version no. 1 Origination Date 1 st February 2017 Area: The Group Approval: Group Services & Facilities Last Revision Date

More information

South Bristol Link Sustainability Statement. May 2013

South Bristol Link Sustainability Statement. May 2013 May 2013 1 2 Notice This document and its contents have been prepared and are intended solely for West of England Partnership s information and use in relation to the of South Bristol Link. It may not

More information

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards 06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards THE APPLICATION Planning permission is sought for the construction of a noise attenuation

More information

4. Project Description

4. Project Description 4. Project Description 4.1 Introduction This chapter provides information on the principal elements of the proposed redevelopment of St Louis Power Station. A description of the existing site and surrounding

More information

Parc Adfer Energy Recovery Facility, Deeside Industrial Park, Flintshire. Volume 3 NON TECHNICAL SUMMARY. August 2014 SLR Ref:

Parc Adfer Energy Recovery Facility, Deeside Industrial Park, Flintshire. Volume 3 NON TECHNICAL SUMMARY. August 2014 SLR Ref: Parc Adfer Energy Recovery Facility, Deeside Industrial Park, Flintshire Volume 3 NON TECHNICAL SUMMARY August 2014 SLR Ref: 403.04097.00005 Wheelabrator Technologies Inc. TABLE OF CONTENTS Contents Introduction...

More information

EIA Case Study of Implementing Mitigation Measures in Hong Kong

EIA Case Study of Implementing Mitigation Measures in Hong Kong EIA Case Study of Implementing Mitigation Measures in Hong Kong Mable M.H. CHAN Steve T.S. LI Metro Assessment Group, Environmental Protection Department, Hong Kong Special Administrative Region Government,

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

URS- EIA- REP Date of Issue 19th November 2012

URS- EIA- REP Date of Issue 19th November 2012 DocID: External DocID: URS-EIA-REP-201040 46369085_Doc020_REP_Rev03 Date of Issue 19th November 2012 This report has been prepared by URS Infrastructure & Environment UK Limited on behalf of South Stream

More information

SUNDERLAND RENEWABLE ENERGY CENTRE

SUNDERLAND RENEWABLE ENERGY CENTRE LAND AT HILLTHORN FARM, WASHINGTON SUNDERLAND RENEWABLE ENERGY CENTRE ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY PREPARED BY PEGASUS GROUP OCTOBER 2017 K.0178_19 ROLTON KILBRIDE Pegasus Group LAND AT

More information

5.0 PROJECT ALTERNATIVES

5.0 PROJECT ALTERNATIVES 5.0 ALTERNATIVES 5.1 INTRODUCTION GENERAL CEQA REQUIREMENTS California Environmental Quality Act (CEQA) Guidelines Section 15126.6(a) states an EIR shall describe a range of reasonable alternatives to

More information

ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES

ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES 5 Training materials produced in Turkey to aid reinstatement / biorestoration 5 5 ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES 5.1 PROJECT WIDE APPROACH Training

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Corallian Colter Offshore Exploration Well - EIA Scoping Report

Corallian Colter Offshore Exploration Well - EIA Scoping Report Corallian Colter Offshore Exploration Well - EIA Scoping Report Bournemouth Borough Council comments on the potential scope of the Environmental Statement and the identification of sources of information.

More information

Annex A. Consultation Responses

Annex A. Consultation Responses Annex A Consultation Responses CONTENTS A1.1 INTRODUCTION A-1 A1.2 STATUTORY STAKEHOLDERS A-1 A1.3 PUBLIC EXHIBITIONS A-1 APPENDIX 1 ENVIRONMENTAL SCOPING DOCUMENT A1.1 INTRODUCTION This Annex summarises

More information

WE EEN Wizard of the Environment: the Enterprise Europe Network. Eurosportello del Veneto Via delle Industrie 19/C Venezia

WE EEN Wizard of the Environment: the Enterprise Europe Network. Eurosportello del Veneto Via delle Industrie 19/C Venezia WE EEN Wizard of the Environment: the Enterprise Europe Network Eurosportello del Veneto Via delle Industrie 19/C Venezia Directive 2008/98/EC on waste (Waste Framework Directive) The Directive introduces

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

An indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20.

An indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20. The land required for the Sydney Park construction compound would be used temporarily throughout construction only. The construction compound site would be rehabilitated at the completion of construction,

More information

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT For ease of local identification this Environmental Impact Statement

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

Enclosed farmland: Arable and Horticultural, Improved and Neutral Grasslands

Enclosed farmland: Arable and Horticultural, Improved and Neutral Grasslands executive summary Executive summary 1 Countryside Survey 2000 (CS2000) and the Northern Ireland Countryside Survey 2000 (NICS2000) have been designed to provide detailed information about the habitats

More information