ENERGY ENGINEERING ANALYSIS PROGRAM. Fort KnoXj Kentucky FINAL REPORT MARCH 1993 VOLUME I EXECUTIVE SUMMARY. Prepared For:

Size: px
Start display at page:

Download "ENERGY ENGINEERING ANALYSIS PROGRAM. Fort KnoXj Kentucky FINAL REPORT MARCH 1993 VOLUME I EXECUTIVE SUMMARY. Prepared For:"

Transcription

1 ENERGY ENGINEERING ANALYSIS PROGRAM ENERGY SURVEY OF ARMY BOILER & CHILLER PLANTS AT Fort KnoXj Kentucky FINAL REPORT MARCH 1993 VOLUME I EXECUTIVE SUMMARY Prepared For: U.S. Army Corps of Engineers P.O. Box 59 Louisville, Kentucky IjggjjIsgQ?! gtätsmgggjl I IKSG t)"aisy INSPECTED 3 "^^Tta^bir^i^ 1 BENATECH, INC. Ugb**ja&ate±^! 77 7 NE Expressway Atlanta, Georgia (404) ARMY CONTRACT NO. DACA27-90-C-0170

2 CONSTRUCTION FNGIVEERIN'G RESEARCH LABORATORIES, CORPS OP F.NGrNEERS P.O. BOX 9005 CIIA.VIPAIGN, ILLINOIS REPLY-TO ATTENTION OF: TR-I Library 17 Sep 1997 Based on SOW, these Energy Studies are unclassified/unlimited. Distribution A. Approved for public release. Marie Wakei Librarian'Engineering

3 MASTER TABLE OF CONTENTS VOLUME I EXECUTIVE SUMMARY VOLUME II EXECUTIVE SUMMARY NARRATIVE Section 1 Introduction Section 2 Existing Conditions VOLUME ffl Section 3 O&Ms Section 4 ECOs Section 5 Studies by Others Section 6 Results Section 7 Recommendations & Conclusions Appendix A Scope of Work Appendix B Correspondence VOLUME IV Appendix C Programming Documentation VOLUME V Appendix D Boiler Efficiency Calculations Appendix E Chiller ECOs VOLUME VI Appendix E (Continued) Chiller ECOs VOLUME VE Appendix F Boiler ECOs VOLUME Vffl Appendix G Field Data Forms NOTE: In accordance with the Scope of Work, Appendix G - Field Data Forms, was submitted only with the Interim Submittal of this report.

4 ABBREVIATIONS A Amps BHP Boiler Horse Power BPO Back Pull Out Pump Configuration, allows Impeller Service without Disturbing Piping Connections BTU British Thermal Unit CC Cent. Close Coupled, End Suction Centrifugal Pump CHW Lvg. Chilled Water Temperature in F Leaving the Chiller Heat Exchanger CHW Ent. Chilled Water Temperature in F Entering the Chiller Heat Exchanger CHW Chilled Water C0 2 Carbon Dioxide DA Deaerator DB Dry Bulb Temperature, Ordinary Air Temperature ECO Cooling Tower, Two Speed Fan Analysis EMCS Energy Management and Control System ES Cent. End Suction Centrifugal Pump F Temperature in Degrees Fahrenheit FD Forced Draft FLA Full Load Amps FT WC Unit of Pressure, Feet of Water Column, Equal to.433 PSI

5 ABBREVIATIONS Page Two GPM Gallons Per Minute (H) Honeywell Combustion Data H-O-A Three Position, Hand-Off Automatic, Control Switch providing On, Off, and Automatic Operation of the Equipment Switched HW Hot Water ID Induced Draft kw kilowatts MBH Thousand BTU Per Hour N 2 Nitrogen (O) Orsat Combustion Data 0 2 Oxygen PF Power Factor, Ratio of Actual Electrical Power to Apparent Power; i.e, Actual Watts/(Volts x Amps). Specifically the Cosine of the Phase Angle between Volts and Amps. PPH Pounds Per Hour PRV Pressure Reducing Valve PSIG Pounds Per Square Inch, Gage RLA Running Load Amps (T) Teledyne Combustion Data V-3PH Voltage in Three Phase Circuit WB Wet Bulb Temperature, Temperature of Water in Equilibrium with Ambient Air, Obtained by Exposing a Moistened Wick to Ambient Air.

6 EXECUTIVE SUMMARY 1. INTRODUCTION 1.1 Background 1.2 Scope 2. BOILER PLANT DATA 3. CHILLER PLANT DATA 4. PRESENT ENERGY CONSUMPTION 4.1 Boilers 4.2 Chillers 5. ENERGY CONSERVATION ANALYSIS 5.1 ECOs Investigated 5.2 ECOs Recommended 5.3 ECOs Rejected 5.4 Projects Developed 5.5 Operation and Maintenance Recommendations 6. ENERGY AND COST SAVINGS 6.1 Total Potential Energy and Cost Savings 6.2 Percentage of Energy Conserved 6.3 Current and Projected Energy Use and Cost ES -

7 1.0 INTRODUCTION 1.1 BACKGROUND: This is the final report of an Energy Engineering Analysis Program (EEAP) study of boilers and chillers at Fort Knox, Kentucky. In September 1990, work was begun on the project by BENATECH, INC. under Contract No. DACA27-90-T-0080, with the Louisville District, U.S. Army Corps of Engineers. The following activities have been accomplished: Detailed field investigations have been conducted. ECO calculations have been performed and life-cycle analyses have been accomplished. Programming documentation has been prepared based on guidance provided by the Louisville District COE. Final report is complete and submitted for review. 1.2 SCOPE: The Scope of Work specified in Contract No. DACA27-90-T-0080 (included in this report in Appendix A) requires the performance of a detailed energy study. The energy conservation opportunities analyzed under this study will serve as part of the overall effort at Ft. Knox to reduce basewide energy use in accordance with the objectives set forth in the Armv Energy Program. The contract Scope of Work (SOW) for Ft. Knox outlines the following specific requirements. Determine the efficiency of the boiler/chiller plants by appropriate tests. ES

8 Survey the boiler/chiller plants to determine if efficiency can be improved by the repair, addition, or modification of equipment and recommend improvements. Evaluate the control system and recommend upgrading, adjustment, repair, or replacement of controls which will improve the efficiency of the plant. Review operations and maintenance practices and provide recommendations which will increase plant efficiency. Prepare a comprehensive report to document the work performed, results, and recommendations. ES -

9 2.0 BOILER PLANT DATA Figure ES2-1 provides a listing of the thirteen boilers addressed by this study and summarizes boiler efficiency test results. FIGURE ES2-1 BOILER PLANT DATA BLDG BOILER BOILER BOILER BOILER CALCULATED # # MAKE CAPACITY MODEL EFFICIENCY (Or Size Typ«) (At Tart Condition«) Vogt 35,000 PPH VF 69.8% 2 Vogt 35,000 PPH VF 69.5% 3 Vogt 35,000 PPH VF 70.9% LaMont 26,000 MBH LFW % 2 LaMont 26,000 MBH LFW % Burnham 6,900 PPH 3P % 2 Burnham 6,900 PPH 3P % 3 Burnham 2,760 PPH 3P % (L) Titusville 12,000 PPH HRT 66.5% 2 (R) Titusville 12,000 PPH HRT 63.7% Superior 4,312 PPH % 2 Superior 4,312 PPH % International 12,000 PPH IDH % ES

10 3.0 CHILLER PLANT DATA Figure ES3-1 provides a listing of the fifty-three chiller plants addressed by this study and summarizes chiller efficiency test results. ES -

11 E- 5 a «& o CO O N. O N 00 o a> N. CO oo SJ o l- CO CO O CM r- CO el CD S CM 10 CM 1- «* T- CM CM * CO CO CM T C0 a CO Ü at CM % " " r*. 0) o o' r^ T 1 o H a a» Z Tj- CO * CO LO CO LO l*~ ' LO CD CO LO CD t o> o g "fr CM CO CO CO CM N i^ CO ' CO CM i CO CO O) 00 1-CO O)»t CM 1- o CO CO LU CU c 3 RATED TONS CO O O o o O o o o * oo o o o CM Tl- * CO CM CM LO CO COCO CO CO O in o CO o CO CO CO CO o LO O o COCO CO o T- ^- T H H X X X X X X o cc X X XX X X X X X X X o Z & o oo ÜÜ o o o o o y y. oo o o o o o o < << << < < < < < << << < < < < < < as o us CM o < z o << << cc o < << << o CO CO CO LU LLI LU LU CO CC CO LU LU LU LU LL. CO CO o o o CO CO CO CO 3 CD o CO CO CO CO < o o 't * I-«oo o o CO CM o o CM CM v T Q o o o o o LO T CO ^ o o o o o ^ T- 3 3 < O CO CO CO CO I o a - CO s» coco CO CO ^- y 3 LO O << << < Q m o o << << < o o o o o <r < < CM < < < < < ^ o << << < (D LU o << << < o o o o o CM cc oc cc cc CC o o CO CM CC cc CC cc CC CM CM CM CM < tf 5 cu + < o T CU + " o j ü z a> CU z cu cu cu o cu O cu z CO z CO u 5 o> CU CD CU CD a» cu cu u 0) a) cu * * * ' ^J c c C C c c c c c c c c CU cu ^2 H CO CO co co co CO CO l-h t-i co co co co CO HH CU l-h h-l CU l-h m 5 CO c c C _ c _ C- CO CO _ C L. C - COCO CO coco CO 1 H t-h Hl h- H H Hl- hl- 1- H^ H H ' 1- a ~~. ^^^ 3 SI «"»N CM 00 s Q n i i 1 1 i 1 t i 1 X X X XX X X X X X XX X X X X X X XX X X Ü ÜÜ oo o o o o o oo oo o oo o oo o o BLl CHILI * 9 pa I*» 00 CO * LO O) CM CO <* lo CO o CO r- CO N r». 1*» 00 oo oo T oo 00 CM T- ~ * * * «t * >t <t * -* c». Ü N 00 CO O) O) CM CM CM oo % T" CM CO * lo co N 00 0) o T- CM CO * lo CO p* ES -

12 <s o a «- s 01 > > > > > > > fe o in > <t o SCO Sco N3 Soo S* O CM CO O) CO O CM H j;co lo CO JCO 00 SCO o o 0> CO CO T CO N ^ ^ a 9 &CM CM T- 1 Jzt c o ^ c o T^ c o ^^ c T- & C 8-T- C CM - CM - T- *-*- o CM H 2 «j Z > CO i CO i- N ' w i CO CM i ' CO N O) "* O) 00 co C0CO w o CM CO CM Ti- CO CO LO i ' CO CM T CO T CO LO r*. co H H CO CO LU CU C_ 3 CO H LL. RATED TONS O O o o O O o o o o O O o o O O o o 10 o o o o CO CO CO CO COCO CO CO CO CO CO CO CO CO CO CO CO CO CO CO CO o o CM CM H W X X X X XX X X XX XX XX X X X X o o o oo ÜÜ ü Ü ÜÜ ÜÜ oo o o oo o o o o o o o ÜÜ << << << << << << << << < < < < < << a «o 9 WS z z z << << << << << << << << s CO CO UJ UJ UJ UJ UJ UJ UJ LU UJ UJ LU UJ UJ UJ LU UJ < CO LU LU CO CO CO CO coco CO CO COCO CO CO CO CO CO CO UJ o a 1-1 oo CO o < o o o o o o o o o o o o o o o o o o CO LO o o CM CM CO CO CO CO CO CO CO CO CO CO CO CO -CO CO CO CO o CO CO CO a a << << << << << << << << CO o o o o oo = a. cc cc 33 << << << << << << << << < -1 _l 1 cc cr cr oc cr cc cc cc cc cc cc tr cc cc cc cc cc o < < < oo 0ti «S H u d ^ SI >> > >> cu cu a> cu a> a> CO CU a> a> cu a> CO CU cu cu a> 0) co co CO CO cu ^ c c c c c c c c c c c c c c c c c c c c 2 co co co co co co co co co co co co co co co co CO CO a a a CO CO 5* c c _ _ c c_ _ C _ _ _ C_ C_ _ L. C c c o o o c_ c l-h- Hl- Hl- Hh- hh H-H Hl- h- h- H H z = = t-h * BLDG CHILLER i-cm T- CM i- CM T- CM T- CM i- CM l- CM y~ CM T- T ^ 1- ^ T- CM X X X X X X X X X X X X X X X X X X X X X XX ÜO uu OO Ü o oo O O oo o o o o o o o oo * Ö 3 «CO * m (0 r- CO O) o T-" LO *t 0) o o N. r». r». l>» r>- f«n. CO CO CO CM -* LO 1^ CO co CO CO co CO CO CO CO CO N CM CM N CM CM CM CM CM CM CM CM CM CM CM * * * * & N CO en O,_ CM CO 't LO CO N. CO O) o T T 5 CM CM CM CM CM CM CM CM CM CM CO Cu ES -

13 ^ 5 W -i- * CO CM o 1 CO O) o CM in O) v CO O) CO CO CO T- Tt ~ o> CO o o i_ 5 CO 00 '- 0) CO CO CM 0) O) CO at CO O CM o o o o T- T- 1 H g cc Z (O O) O) >* T- CO eg m en <t T CM * Tj- r- *fr o in T- CO g T- CO CO CO CM in in CO m CO CM * CO co r- CO CO CM CO CO 4- O CO CO OT CU c 3 a> H RATED TONS O 0) in in O m in m m o o O in in p in in o CM «t CO v iv in v iv v N CO * in N. N CO N IV CO CO II ÜÜ H a 0CÜ o ü o o o o o Ü Ü o Ü Ü ü o O ü X o < << S S S g 8 i ü < 'S 8 s U Ü < in < m CD s OT CO d CO o o in o o O) * r- o m CO o E O o a o ü o o ü o ü <* o o Ü o o o Ü <o in m m in in in in CO a m m T w in o o *S Scvi v r*. v N. v iv N o 2 o< 3 N. iv CO iv IV 3 < C3 a o a CO o o a Ü a C5 o ÜO Ü o o ü ü o o Ü CO o Ü ü ss o o Ü CM ILLER DEL# a: es p «h H C T~ g 1 cu _ >. IV o a> a> a> a> a> a> V (1) co H cu cu a> CU cu cu z ^J c c c c c c c c 3 c c c c c c c ^ «BJJ CO HH CO as CO n co co co a _ co co CO CD co co co l-h CU COT c_ c c_ - c c_ c_ o co c_ c c 1 c c_ c CO cu H-t H H H H H = ü I- I- h- a H H H HOT * «2 SS ad I 1 1 i i I I 1 1 i i i 1 X X X X X X X X X X X X X X X X X X oo u Ü o o Ü Ü Ü Ü Ü Ü o Ü a o o o CM T- tfc ^ Q. 0. o o ÜÜ * Ö 9 «^ CO N CO o> o ^ CM o CM o> o r CM m r>» O) Tf o T" ^- ^ CM CM CM * * * t T ^ ^- CO * o> o> O) OJ 0) 0) OJ o> o> O) o o o o o CM in m m m in m in m m m m in CO CO CO CO CO CO CO % J T CM CO ^- m CO v CO O) o,_ CM CO * in CO r» CO 3 CO CO CO CO CO CO C0 CO CO <t * <t >t <* * 't <* * ON ES -

14 H TES kw/t c E CD CO «rh C- >, o CJ) CD rh CM c\i CM CO * s- C rh rh CD o «CO o j a> a c O CO Q. 6\ H co Ü H c ca.c: H ES WS Z co lo O i CO CO > CD CO i CM I s» 1 CO <* 1 E g RATED TONS o CM CM o o o o o CO LO LO CO CO CO CO CO + > H H W X X oo o CC CC o o << UNI a +- 1 H in a si the chil Typica CO O TJ ller er t iste H 3rH CO -C c o ü Q.C0 TJ H H CD 5 4-<TJ.C C C C CD CO O c 3 _ CD CO c CD TJ c 3 O) c H co c CD TJ C T> -H C --H CD +J CO >< Q.C C CD CD CD CD > TJTJ Q. c_ two in indepen indent o adings. 3 co > C_ 3 CO CD +-> «t- o CD 4- O CO co CD CD rh CD.c a. E O c o o o CD Q) Q. CD o c Ü C- CD - H cc < z z *»*. TJ " CC CO -O CD ft{ * CO -i- CM CO a a c_ CD c_ r_ «T3 E CO ^ J o m < oc cc o H <D CD H ca O CO -H 2 CM CD O) a CO CO co O H 3 "* E 5 +J 3 Ü i- +J N o o o co O rh o T- o ci - 9 o s o CM CO CO CO CD Ü H F.2 n-q CD c_ a o 00 u z o CD o o a a o o c Ü H a. < CD cc << H c rh _i O CD a 3 i CO o> H +J H < CM CO o o o o ft c rh co c H O Ü 1 O CD o CO U > CD cd TJ Ü H.C +J O W +-< 3 C_ a. CO o Q. E c_ 3 if BLDG HILLER.procating r. H O CD C 3 a. NOTES Is 90, 120, and s to the two sys - possible, data f< ermitted only com CD a. o C H C_ c o 3 CD H H «CD TJ CO CD CD CL +J CD c TJ -H CD CO CO O-H C < CD CO rh co CD CD CD CD l C_ CD ^J 3 c c c c r-l co TJ SE Q.O rj 3 rh 2 a h-4 CO CO ca CO CO f H je C O f" c CO 5* o CO _ _ _ C u H o o.38 S c w s H QH H hl- «X -C CO u rh CO 3 CD co C CD O a CO, CT rh c O ^- ;»! <" rh H O -H O) M L. 13? w H * TJ CO c C_ CD f CD H CD H H ^ P -H O) O f 3.C W o rh "" 0. c c H T" i- CM T- CM ^ i- CM O CO TJ H CD-H +J 1 i i 1 1 i 1 1 TJ TJ +J CO X XX X X X X X X o 3 O co o oo oo o oo ^o c O t- cncd c_ H f Q. TJ 3 C O. CD +J "S^ H CD tjhja CO O TJ rh O»TJ O c co u rh c n CO C_ c r-l O 4- O CD CD O CO 3 C CO c O t O-H C_ CD CO U E CD CJ> * c_ O 5 "» E H U _ grh CD CO CD CO o _ o CD E CO C CD > CD a 0) CO Ü in LO C-H- TJ _ 4-> +-> 3 _ H Ö LO LO LO LO CM H CD c H CO CO CD CO Q. + > CD J CO CO CO CO en < c l-l < S LEIHE CO rh es CD CD O c a. HP EO CD E rh CD Q. o H CD CO CD O o *.E.C CO JC C c O CO 3 -M hh 1 1 G O) o v- CM CO II II II II 3 «* L0 L0 X cc O o ft. 3 a O < 8 - CM CO o CO CO LU CD _ 3 a H u. ES -

15 4.0 PRESENT ENERGY CONSUMPTION 4.1 BOILERS: Figure ES4-1 summarizes current annual energy consumption by the thirteen boilers in the scope of this study. FIGURE ES4-1 PRESENT ENERGY CONSUMPTION AND COST BY BOILERS BLDG BOILER TEST CURRENT ANNUAL CURRENT ANNUAL # # EFFICIENCY FUEL CONSUMPTION FUEL COST ,100 therms 676,800 therms 671,500 therms $211,761 $209,808 $208, ,970 gallons 188,600 gallons $193,609 $194, ,500 therms 98,700 therms 24,100 therms $30,535 $30,597 $7, ,200 therms 111,900 therms $33,232 $34, ,100 therms 131,200 therms $40,641 $40, ,062 therms $47,759 TOTALS 2,888,162 therms natural gas 376,570 gallons #2 fuel oil $1,283, CHILLERS: Figure ES4-2 summarizes current annual energy consumption by the fiftythree chiller plants in the scope of this study. ES - 10

16 FIGURE ES4-2 PRESENT ENERGY CONSUMPTION AND COST BY CHILLERS PLANT # BLDG # ESTIMATED CFLH/YR TEST KW/TON OPERATING TONS PLANT KW CURRENT KWH/YR CURRENT ANNUAL COST , ,043 $8, , ,569 $6, , ,577 $5, , ,924 $16, , ,310 $5, , ,400 $13, , ,773 $5, , ,833 $13, , ,372 $6, , ,547 $11, , ,610 $12, , ,791 $7, , ,403 $11, , ,836 $18, , ,311 $10, , ,080 $17, , ,359 $8, , ,573 $6, , ,974 $5, , ,773 $6, , ,763 $8, , ,577 $5, , ,372 $6, , ,161 $8, , ,958 $9, , ,720 $6, , ,960 $16,128 ES - 11 Figure ES4-2 (1 of 2)

17 FIGURE ES4 2 PRESENT ENERGY CONSUMPTION AND COST BY CHILLERS PLANT # BLDG # ESTIMATED CFLH/YR TEST KW/TON OPERATING TONS PLANT KW CURRENT KWH/YR CURRENT ANNUAL COST , ,538 $4, , ,827 $4, , ,560 $23, , ,424 $4, , ,972 $6, , ,951 $10, ,000 $3, , ,974 $5, , ,975 $5, , ,970 $6, , ,973 $6, , ,109 $5, , ,978 $4, , ,200 $5, , ,968 $7, , ,977 $5, , ,574 $5, , ,979 $4, , ,976 $5, , ,280 $8, , ,399 $6, , ,773 $6, , ,497 $5, , ,120 $6, , ,580 $4, , ,640 $5,660 TOTALS 7,827,780 $426,789 ES - 12 Figure ES4-2 (2 of 2)

18 5.0 ENERGY CONSERVATION ANALYSIS 5.1 ECOS INVESTIGATED: The Scope of Work contains a list of specific ECOs to be studied for Fort Knox boilers and chillers. These ECOs were investigated after completing our field survey visits and compiling the raw data from the visits. The steps in collecting the field data were: Obtain nameplate data and methods of operation for the boilers and chillers. Inspect types and conditions of control systems. Take field measurements on boilers and chillers. Using the field data, the various ECOs were analyzed for feasibility of being implemented under Army guidelines. A list of ECOs evaluated is shown below. This list includes ECOs shown in Annex A of the contract Scope of Work and additional ECOs identified by BENATECH, INC. Controls to Assure Proper Combustion Air-Fuel Ratio Feedwater Treatment Waste Heat Recovery; i.e., Exhaust Gases, Process Steam Pressure Drop, and Steam Condensate and Blowdown Installation of New Burner Equipment Economizers/Air Pre-Heaters Reduce Excess Air Loading Characteristics and Scheduling Versus Equipment Capacity (Equipment Optimization) ES - 13

19 Variable Speed Circulation Pumps or Alternate Pumps Based on Seasonal Loading Steam Pressure or Hot Water Temperature Reductions Based on Seasonal Loading and/or Existing and Projected Requirements Reductions in Make-Up Water Quantities Control Systems to Operate Chillers at Their Most Energy Efficient Operating Condition Blowdown Control Prevent Air Leakage Condenser/Cooling Tower Water Treatment Variable or Two-Speed Cooling Tower Fan Free Cooling Cycles in Lieu of Chiller Operation Storage of Chilled Water High Efficiency Motors Steam Driven Auxiliaries Versus Electric Drives Variable Speed Induced Draft Fans and Forced Draft Blowers Instruments and Controls to Facilitate Efficient Operations Use Smaller Boilers Where Load has Been Reduced Automatic Chiller Tube Cleaners Correct Sizing of Traps Replace Inefficient Boilers with More Efficient Boilers m ES - 14

20 5.1.1 BOILER ECO DESCRIPTIONS: Boiler Feedwater Economizer This ECO investigates the energy savings achievable by preheating the boiler feedwater with recovered waste heat from the flue gas. Burner Replacement This ECO analyzes the energy savings achievable by replacing existing burners with modulating, cam-type burners. These burners modulate the air-to-fuel ratio as a function of boiler load. This modulation results in a combustion efficiency of approximately 80% over the operating range of the boiler. Boiler Tune-Up The boiler should be tuned for minimum excess air at their respective average operating loads. Ft. Knox boiler maintenance staff already perform quarterly tune-ups on all boilers. Pre-Heat Combustion Air The purpose of this ECO is to use waste heat recovered from the flue gas to preheat combustion air. "Summer" Boiler This ECO analyzes the potential of installing a boiler to handle the steam production requirements during the "summer" months. Available consumption data was examined to isolate the steam capacity requirements for each month. The "summer" boilers were then sized to meet average summer loads. The energy savings are realized in the increased efficiency of the new boilers (approximately 80%) as compared with the underloaded (during summer operations) existing boilers. ES - 15

21 Variable-Speed Motor Drives This ECO analyzes the potential for savings by installing inverters on combustion air fan motors. Inverters save energy by controlling the fan power in response to actual air flow requirements. Boiler Replacement This ECO evaluates the savings to be achieved by replacing the existing boiler with a new, high efficiency boiler of the same size. Downsize Boilers Existing boilers do not appear to be oversized for their respective loads, except for those which carry "summer" loads. See description of "Summer Boiler". Installation of Turbulators This ECO analyzes the energy savings achievable by installing turbulators in fire-tube boilers. Turbulators are baffles which create turbulent flow in the core of hot combustion gases. This turbulent flow maximizes heat transfer from combustion gases through the tube walls to the boiler water. Thus, more heat is used in the generation of steam and less is lost out the exhaust stack. This ECO is not applicable to water-tube boilers. Oxygen Trim System/Controls to Assure Proper Combustion Air-Fuel Ratio The purpose of an oxygen trim system is to control the air/fuel ratio of a boiler within the most efficient operating parameters. This is achieved by using an oxygen analyzer in the flue stack in conjunction with a microprocessor controller. The oxygen analyzer measures the oxygen content in the flue gas and a potentiometer monitors the fuel flow rate. The microprocessor controls adjust the air flow damper in order to get the most efficient combustion process. ES - 16

22 Feedwater Treatment This measure is addressed in Section 3, O&Ms. Waste Heat Recovery This ECO is covered by three approaches: economizers, air pre-heaters, and blowdown heat recovery. Reduce Excess Air This ECO is addressed in Section 3, O&Ms. Equipment Optimization This ECO is addressed in Section 3, O&Ms. Variable Speed Circulation Pumps Only one boiler plant-no. 5943, a hot water plant-has circulation pumps. Study of system distribution was not within the scope of this project. Steam Pressure or Hot Water Temperature Reductions Based on Seasonal Loading and/or Existing and Project Requirements This ECO is addressed in Section 3, O&Ms. Reductions in Make-up Water Quantities/Blowdown Control This ECO is addressed in the "Automatic Blowdown/Blowdown Heat Recovery ECO". ES - 17

23 High Efficiency Motors This ECO analyzes the savings to be achieved by replacing existing standard efficiency motors with premium efficiency motors. Steam Driven Auxiliaries Current operating pressures versus distribution pressures do not yield a pressure drop significant enough to make this ECO feasible. Correct Sizing of Traps All steam traps observed during field surveys appeared to be correctly sized for the respective applications CHILLER ECO DESCRIPTIONS: Automatic Chiller Tube Cleaning This ECO establishes representative savings which result form the installation of an on-line condenser tube cleaning system. This system uses slightly oversized brushes fitted into each condenser tube to remove rust and deposits. The brushing action is initiated by a diverted valve, which changes the direction of water flow, pushing the brushes to either end of the condenser. Flow through the condenser automatically changes. Savings result from improved heat transfer from the condenser water through the condenser tube wall. Chiller Shutdown/EMS Tie-in This ECO analyzes the energy savings achievable when equipment is operated only when it is needed to provide comfort conditioning. The savings are calculated for chillers (partially loaded), chilled water, and condenser water pumps, and cooling towers. This ECO is accomplished by tying the plant into existing basewide energy management system (EMS). ES - 18

24 Chilled Water Temperature Reset This ECO analyzes the energy savings resulting from resetting the chilled water supply temperature upward, without appreciable affecting comfort conditions. Savings result from decreasing the demand on the chiller compressor, and therefore, the amount of energy input to the chiller. This ECO is accomplished using the existing EMS. Water Treatment This ECO is addressed in Section 3, O&Ms. Waterside Economizer/Free Cooling This ECO evaluates the feasibility of installing a plate heat exchanger, new valves, and controls to enable the chiller to be shutdown during periods of the year when the wet bulb temperatures will provide sufficient evaporative cooling effect. Building load fluctuates with internal and external loads. During the fall, winter, and spring, the external cooling loads on a building are at a minimum or nonexistent. During these seasons, the wet bulb temperatures are low enough to maintain evaporation in sufficient quantity to provide condenser water cold enough to meet the internal loads of the building. Variable Speed Pumping This ECO is actually a "reduced speed" pumping analysis, whereby chilled water pumps are re-sized based on actual chiller plant loads. Two Speed Cooling Tower Fan Motors This ECO examines the energy savings resulting from replacing the constant speed cooling tower fan motor with a two speed motor. Savings result from the fan law which states that the power required to operate a fan varies as the cube of the fan speed. ES - 19

25 Replace Inefficient Chillers This ECO evaluates the electrical energy savings achievable by replacing existing chillers with new high-efficiency chillers. Field surveys indicated that typical chiller operating conditions were approximately 82 F outside air temperature and 52 F leaving chiller water temperature. At these conditions, reciprocating chillers kw/ton would be about 95% of the ARI values. Following is a list of chiller types and corresponding adjusted efficiencies used in the ECO calculations: ACX - Air cooled, outdoor, reciprocating compressor/condenser unit with mechanical room refrigerant/chw heat exchanger. New chiller kw/ton = ACR - Indoor reciprocating chiller with outdoor air cooled condensing unit. New chiller kw/ton = ACC - Air cooled, outdoor, packaged reciprocating chiller. New chiller kw/ton = WCC - Water cooled chiller, condenser pump, cooling tower. New chiller kw/ton = Chilled Water Pump Shutdown Currently, even when the chillers are shutdown (during unoccupied periods) by the basewide EMS, the chilled water pumps run continuously. This ECO evaluates the savings to be achieved by shutting down the chilled water pumps with the chillers, using the EMS. High Efficiency Motors This ECO was evaluated for all chiller plant motors. Because of relatively short annual hours of operation of these motors, all projects have SIRs < 1.0. Sample analyses were provided for one of each type of motor (Appendix E). ES - 20

26 Waste Heat Recovery This ECO evaluates the savings to be achieved by recovering chiller waste heat to make domestic hot water. Chilled Water Storage This ECO analyzes the savings to be achieved by generating chilled water during off-peak hours. Also analyzed is ice storage RESULTS OF ECOS INVESTIGATED: A summary of all boiler ECO results is shown in Figure ES A summary of all chiller ECO results is shown in Figure ES ES - 21

27 FIGURE ES5.1 1 BOILER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION BOILER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR PAGE# BLOWDOWN ,845 15, F-167 HEAVY OIL CONVERSION , , F-163 OXYGEN TRIM SYSTEM ,186 5, F- 137 TURBULATOR INSTALLATION , F-l TURBULATOR INSTALLATION , F-4 OXYGEN TRIM SYSTEM ,186 3, F- 134 TURBULATOR INSTALLATION , F- 16 TURBULATOR INSTALLATION , F- 19 TURBULATOR INSTALLATION , F-7 BLOWDOWN ,427 1, F- 176 OXYGEN TRIM SYSTEM ,186 2, F- 128 BLOWDOWN ,845 2, F- 170 TURBULATOR INSTALLATION , F- 13 TURBULATOR INSTALLATION , F-10 OXYGEN TRIM SYSTEM ,186 1, F-125 OXYGEN TRIM SYSTEM ,186 1, F-131 BLOWDOWN ,442 1, F-173 TURBULATOR INSTALLATION , F-22 BLOWDOWN ,797 1, F-179 ENERGY EFFICIENT MOTORS F-37 OXYGEN TRIM SYSTEM ,186 1, F-140 BOILER REPLACEMENT ,815 8, F-90 ECONOMIZER INSTALLATION ,671 1, F-148 BOILER REPLACEMENT ,815 7, F-96 ENERGY EFFICIENT MOTORS F-33 ENERGY EFFICIENT MOTORS 852 1, F-29 ENERGY EFFICIENT MOTORS 852 1, F-25 OXYGEN TRIM SYSTEM , F-123 ES - 22 HgureES5.1-l(lof2)

28 FIGURE ES5.1 1 BOILER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION BOILER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR PAGE # OXYGEN TRIM SYSTEM , F- 120 BOILER REPLACEMENT ,815 5, F-93 ENERGY EFFICIENT MOTORS F-77 ENERGY EFFICIENT MOTORS F-65 ENERGY EFFICIENT MOTORS , F-61 BOILER REPLACEMENT ,313 11, F-81 BURNER REPLACEMENT ,616 2, F-117 BOILER 852 1,312,964 28, F ENERGY EFFICIENT MOTORS , F-69 ENERGY EFFICIENT MOTORS F-41 BOILER REPLACEMENT ,313 9, F-84 BURNER REPLACEMENT ,616 1, F-114 ENERGY EFFICIENT MOTORS , F-73 ENERGY EFFICIENT MOTORS F-53 BOILER REPLACEMENT ,313 7, F-87 ENERGY EFFICIENT MOTORS , F-49 BURNER REPLACEMENT ,616 1, F-117 ENERGY EFFICIENT MOTORS F-45 BURNER REPLACEMENT ,330 2, F- 108 BURNER REPLACEMENT ,330 2, F-105 ALRPREHEATER ,891 1, F-154 ENERGY EFFICIENT MOTORS F-57 SUMMER BOILER , F-157 BOILER REPLACEMENT , F-99 BOILER REPLACEMENT , F-102 ECONOMIZER INSTALLATION , F-145 OXYGEN TRLM SYSTEM , F-143 ALRPREHEATER , F-151 ES - 23 Figure ES5.1-1 (2 of 2)

29 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE* CHW PUMP E-83 CHW PUMP E-88 CHW PUMP E-73 CHW PUMP E-78 CHW PUMP E-43 CHW PUMP E-68 CHW PUMP E-98 CHW PUMP E-118 CHW PUMP E-93 CHW PUMP E-103 CHW PUMP E-58 CHW PUMP E-63 CHW PUMP E-38 CHW PUMP E E E E E E E E E E E E-682 ES - 24 Figure ES5.1-2 (1 of 8)

30 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE# E E E E E E E-687 CHW PUMP E-173 CHW PUMP E-113 CHW PUMP E-203 CHW PUMP E-168 CHW PUMP E-123 CHW PUMP E-33 CHW PUMP E-48 CHW PUMP E E E E-622 CHW PUMP E E E E E E E-717 ES - 25 Figure ES5.1-2 (2 of 8)

31 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE# E E-732 CHW PUMP E-163 CHW PUMP E-148 CHW PUMP E-133 CHW PUMP E-198 CHW PUMP E-53 CHW PUMP E-188 CHW PUMP E-193 CHW PUMP E-158 CHW PUMP E-283 CHW PUMP E-153 CHILLER ,006 2, E- 1 CHILLER ,006 1, E-25 CHILLER ,006 1, E- 5 CHILLER WASTE HEAT REC ,549 2, E-507 CHILLER WASTE HEAT REC ,549 2, E-497 CHILLER WASTE HEAT REC ,549 2, E-562 CHILLER WASTE HEAT REC ,549 1, E-457 CHILLER , E-21 CHILLER WASTE HEAT REC ,549 1, E-467 CHILLER , E-17 CHILLER , E-29 CHILLER WASTE HEAT REC ,549 1, E-482 CHW PUMP E-208 ES - 26 Figure ES5.1-2 (3 of 8)

32 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE# CHILLER , E- 9 CHILLER WASTE HEAT REC ,549 1, E-477 CHILLER WASTE HEAT REC ,549 1, E-492 CHILLER WASTE HEAT REC ,549 1, E-502 CHILLED WATER RESET E-757 CHILLER , E-13 CHW PUMP E-178 CHW PUMP E-128 CHILLER WASTE HEAT REC ,549 1, E-552 CHILLER WASTE HEAT REC ,549 1, E-512 CHILLER WASTE HEAT REC ,549 1, E-582 CHILLED WATER RESET E-761 CHILLED WATER RESET E-769 CHILLER WASTE HEAT REC ,549 1, E-547 CHILLER WASTE HEAT REC , E-532 CHILLER WASTE HEAT REC , E-437 CHILLER WASTE HEAT REC , E-487 CHILLER WASTE HEAT REC , E-557 CHILLER WASTE HEAT REC , E-442 CHILLED WATER RESET E-777 CHILLED WATER RESET E-765 CHILLED WATER RESET E-789 REPLACEMENT CHILLER ,946 7, E-273 CHILLER WASTE HEAT REC , E-577 CHILLER WASTE HEAT REC , E-542 ES - 27 FigureES5.1-2(4of8)

33 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE# CHILLER WASTE HEAT REC , E-472 CHILLER WASTE HEAT REC , E-587 CHILLER WASTE HEAT REC , E-517 CHILLED WATER RESET E-785 CHILLER WASTE HEAT REC , E-592 CHILLER WASTE HEAT REC , E-527 CHILLER WASTE HEAT REC , E-462 REPLACEMENT CHILLER ,157 9, E-337 CHILLER WASTE HEAT REC , E-522 CHILLED WATER RESET E-797 CHILLED WATER RESET E-849 CHILLED WATER RESET E-805 REPLACEMENT CHILLER ,563 3, E-261 CHILLER WASTE HEAT REC , E-537 CHILLER WASTE HEAT REC , E-607 CHILLER WASTE HEAT REC , E-447 CHILLER WASTE HEAT REC , E-452 CHILLER WASTE HEAT REC , E-597 REPLACEMENT CHILLER ,900 9, E-293 REPLACEMENT CHILLER ,900 10, E-249 CHILLED WATER RESET E-841 CHILLED WATER RESET E-801 CHILLER WASTE HEAT REC , E-567 CHILLER WASTE HEAT REC , E-572 CHILLED WATER RESET E-809 ES - 28 Figure ES5.1-2 (5 of 8)

34 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE# CHILLER WASTE HEAT REC , E-602 REPLACEMENT CHILLER ,300 2, E-385 CHILLED WATER RESET E-837 CHILLED WATER RESET E-825 REPLACEMENT CHILLER ,946 5, E-329 REPLACEMENT CHILLER ,946 4, E-297 ENERGY EFFICIENT MOTORS E-225 ENERGY EFFICIENT MOTORS E-213 REPLACEMENT CHILLER ,946 4, E-325 CHILLED WATER RESET E-873 ENERGY EFFICIENT MOTORS 297 1, E-217 ENERGY EFFICIENT MOTORS E-221 CHILLED WATER RESET E-865 REPLACEMENT CHILLER ,946 4, E-313 REPLACEMENT CHILLER ,372 4, E-285 CHILLED WATER RESET E-845 CHILLED WATER RESET E-813 CHILLED WATER RESET E-869 CHILLED WATER RESET E-833 CHILLED WATER RESET E-781 CHILLED WATER RESET E-821 CHILLED WATER RESET E-857 CHILLED WATER RESET E -773 REPLACEMENT CHILLER ,900 6, E-265 REPLACEMENT CHILLER ,900 6, E-257 ES - 29 FigureES5.1-2(6of8)

35 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE* CHILLED WATER RESET E-817 REPLACEMENT CHILLER ,977 2, E-393 REPLACEMENT CHILLER ,900 5, E-277 CHILLED WATER RESET E-861 REPLACEMENT CHILLER ,023 3, E -413 CHILLED WATER RESET E-877 CHILLED WATER RESET E-829 REPLACEMENT CHILLER ,372 3, E-237 REPLACEMENT CHILLER ,977 2, E-373 REPLACEMENT CHILLER ,224 9, E-349 ENERGY EFFICIENT MOTORS E-233 CHILLED WATER RESET E-881 REPLACEMENT CHILLER ,946 2, E-241 REPLACEMENT CHILLER ,977 2, E-357 REPLACEMENT CHILLER ,977 2, E-353 REPLACEMENT CHILLER ,407 1, E-361 REPLACEMENT CHILLER ,900 4, E-281 REPLACEMENT CHILLER ,977 1, E-377 CHILLED WATER RESET E-793 REPLACEMENT CHILLER ,977 1, E-365 REPLACEMENT CHILLER ,990 1, E-389 REPLACEMENT CHILLER ,338 1, E-429 REPLACEMENT CHILLER ,946 2, E-321 REPLACEMENT CHILLER ,946 2, E-269 REPLACEMENT CHILLER ,990 1, E-253 ES - 30 Figure ES5.1-2 (7 of 8)

36 FIGURE ES5.1 2 CHILLER ECO RESULTS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE* REPLACEMENT CHILLER ,946 1, E-309 REPLACEMENT CHILLER ,946 2, E-301 WATERSIDE ECONOMIZER SAMPLE 2, E-885 ENERGY EFFICIENT MOTORS E-229 REPLACEMENT CHILLER ,946 1, E-333 REPLACEMENT CHILLER ,323 1, E-425 REPLACEMENT CHILLER ,977 1, E-369 REPLACEMENT CHILLER ,338 1, E-401 REPLACEMENT CHILLER ,946 1, E-305 REPLACEMENT CHILLER ,977 1, E-409 VARIABLE SPEED FAN SAMPLE 2, E-892 REPLACEMENT CHILLER , E-397 REPLACEMENT CHILLER ,281 1, E-289 REPLACEMENT CHILLER ,338 1, E-381 CHILLED WATER RESET E-853 REPLACEMENT CHILLER ,946 1, E-317 REPLACEMENT CHILLER ,946 1, E-245 REPLACEMENT CHILLER ,023 1, E-345 REPLACEMENT CHILLER ,023 1, E-341 CHILLED WATER STORAGE SAMPLE 172,800 3, E-896 AUTOMATIC TUBE CLEANERS SAMPLE 16, E-899 REPLACEMENT CHILLER , E-405 REPLACEMENT CHILLER , E-433 REPLACEMENT CHILLER , E-421 REPLACEMENT CHILLER , E-417 ES - 31 F1gureES5.1-2(8of8)

37 5.2 ECOS RECOMMENDED: As was shown in the previous section, results of all boiler and chiller ECO calculations are summarized in Figures ES5.1-1 and ES Recommended ECOs are those with savings-to-investment ratios (SIRs) greater than or equal to 1.0. These ECOs were then re-evaluated to include interaction with other recommended ECOs. Results were again summarized by SIR and revised ECOs with SIRs less than 1.0 were no longer recommended. Revised ECO calculations are included in Programming Documentation section in Volume IV, Appendix C. A final summary of recommended boiler ECOs (including interaction) is shown in Figure ES A final summary of recommended chiller ECOs (including interaction) is shown in Figure ES FIGURE ES5.2-1 RECOMMENDED BOILER ECOS - SORTED BY SIR ECO DESCRIPTION BOILER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR PAGE # BLOWDOWN HEAT REC ,845 15, F-167 HEAVY OIL CONVERSION , , F-163 OXYGEN TRIM SYSTEM ,186 5, F-137 TURBULATOR INSTALL , F-l TURBULATOR INSTALL , F-4 OXYGEN TRIM SYSTEM ,186 3, F-134 TURBULATOR INSTALL , F-16 TURBULATOR INSTALL , F-19 TURBULATOR INSTALL , F-7 BLOWDOWN HEAT REC ,427 1, F-176 OXYGEN TRIM SYSTEM ,186 2, F- 128 BLOWDOWN HEAT REC ,845 2, F-170 TURBULATOR INSTALL , F-13 TURBULATOR INSTALL , F-10 OXYGEN TRIM SYSTEM ,186 1, F-125 OXYGEN TRIM SYSTEM ,186 1, F-131 BLOWDOWN HEAT REC ,442 1, F-173 TURBULATOR INSTALL , F-22 BLOWDOWN HEAT REC ,797 1, F- 179 TOTALS $493,793 $201, ES - 32

38 FIGURE ES5 2 2 RECOMMENDED CHILLER ECOS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST (KWH) ANNUAL SAVINGS (THERMS) PAYBACK (YEARS) CHW PUMP , , , , , , CHW PUMP , CHW PUMP , CHW PUMP , , , , , , , , , , , , , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , , CHW PUMP , , CHW PUMP , SIR ES - 33 FigureES5.2-2(lof4)

39 FIGURE ES5.2-2 RECOMMENDED CHILLER ECOS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST (KWH) ANNUAL SAVINGS (THERMS) PAYBACK (YEARS) CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , äk w CHW PUMP , CHW PUMP , CHILLER ,006 81,051 2, , , , , , , , , CHILLER ,006 62,803 1, , CHW PUMP , CHILLER WASTE HEAT REC ,549 7,026 2, CHILLER ,006 41,738 1, CHW PUMP , CHW PUMP , CHW PUMP , SIR ES - 34 Figun i ES5.2-2 (2 < if 4)

40 FIGURE ES5.2-2 RECOMMENDED CHILLER ECOS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST (KWH) ANNUAL SAVINGS (THERMS) PAYBACK (YEARS) CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHW PUMP , CHILLER ,006 37, CHILLER WASTE HEAT REC ,549 5,116 1, CHILLER ,006 24, CHILLER ,006 34, CHILLER WASTE HEAT REC ,549 4,834 1, CHW PUMP , CHILLER WASTE HEAT REC ,549 4,318 1, CHILLER WASTE HEAT REC ,549 4,116 1, CHTT.T.FD WATER RESET , CHILLER ,006 17, CHILLER WASTE HEAT REC ,549 3,865 1, CHW PUMP , CHW PUMP , CHILLER WASTE HEAT REC ,549 3,583 1, CHILLER WASTE HEAT REC ,549 3,463 1, CHIT,T,FR WASTE HEAT REC ,549 3,440 1, CHILLED WATER RESET , CHILLED WATER RESET , CHILLER WASTE HEAT REC ,549 3,310 1, CHTT I ER WASTE HEAT REC ,549 3, CHILLER WASTE HEAT REC ,549 3, CHTT IHR WASTE HEAT REC ,549 3, CHILI.KR WASTE HEAT REC ,549 2, CHILLER WASTE HEAT REC ,549 2, SIR ES Figure t ES5.2-2 (3 c if 4)

41 FIGURE ES5.2 2 RECOMMENDED CHILLER ECOS - SORTED BY SIR ECO DESCRIPTION CHILLER PLANT ID INITIAL COST (KWH) ANNUAL SAVINGS (THERMS) PAYBACK (YEARS) CHILLED WATER RESET , CHILLED WATER RESET , CHILLED WATER RESET , REPLACEMENT CHILLER , ,765 7, CHILLER WASTE HEAT REC ,549 2, CHILLER WASTE HEAT REC ,549 2, CHILLER WASTE HEAT REC ,549 2, CHTLLER WASTE HEAT REC ,549 2, CHILLER WASTE HEAT REC ,549 2, CHTTJ.ED WATER RESET , CHTLLER WASTE HEAT REC ,549 2, CHILLER WASTE HEAT REC ,549 2, CHILLER WASTE HEAT REC ,549 2, CHILLED WATER RESET , CHTLLER WASTE HEAT REC ,549 2, CHILLED WATER RESET , CHTT TFT) WATFR RRSF.T , REPLACEMENT CHTLLER ,563 70,382 3, CHILLER WASTE HEAT REC ,549 1, CHILLER WASTE HEAT REC ,549 1, CHILLER WASTE HEAT REC ,549 1, CHTLLER WASTE HEAT REC ,549 1, REPLACEMENT CHTLLER , ,840 9, RFPT ACEMENT CHTT,T ER , ,621 10, RFPT ACEMENT CHTT T,F.R , , CHTT,TED WATER RESET , ftttttft) WATFR RRSFT , CHTT,T,ER WASTE HEAT REC ,549 1, CHTT I ED WATFR RESET , TOTALS $620,831 1,726,714 88,432 $99, SIR ES - 36 Figure ES5.2-2 (4 of 4)

42 5.3 ECOS REJECTED: Rejected ECOs are those with SIRs less than 1.0. Rejected boiler ECOs are shown in Figure ES Rejected chiller ECOs are shown in Figure ES53-2. ECO DESCRIPTION FIGURE ES5 3-1 BOILER ECOS REJECTED BOILER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR PAGE # ENERGY EFFICIENT MOTORS F- 37 OXYGEN TRIM SYSTEM ,186 1, F- 140 BOILER REPLACEMENT ,815 8, F- 90 ECONOMIZER INSTALLATION ,671 1, F- 148 BOILER REPLACEMENT ,815 7, F- 96 ENERGY EFFICIENT MOTORS F- 33 ENERGY EFFICIENT MOTORS 852 1, F- 29 ENERGY EFFICIENT MOTORS 852 1, F- 25 OXYGEN TRIM SYSTEM , F- 123 OXYGEN TRIM SYSTEM , F- 120 BOILER REPLACEMENT ,815 5, F- 93 ENERGY EFFICIENT MOTORS F- 77 ENERGY EFFICIENT MOTORS F- 65 ENERGY EFFICIENT MOTORS , F- 61 BOILER REPLACEMENT ,313 11, F- 81 BURNER REPLACEMENT ,616 2, F-117 BOILER 852 1,312,964 28, F- 160 ENERGY EFFICIENT MOTORS , F- 69 ENERGY EFFICIENT MOTORS F- 41 BOILER REPLACEMENT ,313 9, F- 84 BURNER REPLACEMENT ,616 1, F- 114 ENERGY EFFICIENT MOTORS , F- 73 ENERGY EFFICIENT MOTORS F- 53 BOILER REPLACEMENT , F- 87 ENERGY EFFICIENT MOTORS , F- 49 BURNER REPLACEMENT ,616 1, F-117 ENERGY EFFICIENT MOTORS F- 45 BURNER REPLACEMENT , F-108 BURNER REPLACEMENT ,330 2, F-105 ATRPREHEATER ,891 1, F-154 ENERGY EFFICIENT MOTORS F- 57 SUMMER BOrLER , F-157 BOILER REPLACEMENT , F- 99 BOILER REPLACEMENT , F-102 ECONOMIZER INSTALLATION , F-145 OXYGEN TRIM SYSTEM , F-143 ATRPREHEATER , F-151 ES - 37

43 FIGURE ES5.3-2 CHILLER ECOS REJECTED ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE* CHTTJER WASTF, , E-602 RFPT ACFMFNT CHTT,T ER ,300 2, E-385 CHTT JED WATF.R RF.SFT E-837 CHTT.TED WATF.R RF.SFT E-825 REPLACEMENT CHILLER ,946 5, E-329 RFPT ACFMF.NT CHTT,T ER ,946 4, E-297 ENERGY EFFICIENT MOTORS E-225 ENERGY EFFICIENT MOTORS E-213 REPLACEMENT CHTT.TF.R ,946 4, E-325 CHILLED WATER RESET E-873 ENERGY EFFICIENT MOTORS 297 1, E-217 ENERGY EFFICIENT MOTORS E-221 CHILLED WATER RESET E-865 RFPT ACFMFNT CHTT I,ER ,946 4, E-313 RFPT ACFMENT CHTT J ER ,372 4, E-285 CHTT I ED WATER RF.SFT E-845 CHTT I ED WATER RESET E-813 CHITTED WATER RESET E-869 CHTT I ED WATER RESET E-833 CHTT,TED WATER RESET E-781 CHTT,TED WATER RF.SFT E-821 CHTT.TED WATER RF.SFT E-857 CHTT.TED WATER RESET E-773 RFPT ACFMENT CHTT J ER ,900 6, E-265 RFPT ACFMENT CHTTJER ,900 6, E-257 CHTT JED WATER RF.SFT E-817 RFPT ACFMENT CHTTJER ,977 2, E-393 REPTACEMENT CHTTJER ,900 5, E-277 CHTT,T ED WATER RF.SFT E-861 REPLACEMENT CHTTJER ,023 3, E-413 CHILLED WATER RESET E-877 CHILLED WATER RESET E-829 RFPT ACFMENT CHTT J ER ,372 3, E-237 REPLACEMENT CHTTJER ,977 2, E-373 RFPT ACFMFNT CHTT J ER ,224 9, E-349 ENERGY EFFICIENT MOTORS E-233 CHTT JED WATER RESET E-881 RFPT ACFMFNT CHTT J ER ,946 2, E-241 ES - 38 FigureES5J-2(lof2)

44 FIGURE ES5 3-2 CHILLER ECOS REJECTED ECO DESCRIPTION CHILLER PLANT ID INITIAL COST ANNUAL SAVINGS PAYBACK (YEARS) SIR REPORT PAGE# REPLACEMENT CHILLER ,977 2, E-357 REPLACEMENT CHILLER ,977 2, E-353 REPLACEMENT CHILLER ,407 1, E-361 REPLACEMENT CHILLER ,900 4, E-281 RFPT ACFMFNT CHIT,T,F,R ,977 1, E-377 CHILLED WATER RESET E-793 RFPT ACFMFNT CHTT,T ER ,977 1, E-365 REPLACEMENT CHILLER ,990 1, E-389 REPLACEMENT CHILLER ,338 1, E-429 REPLACEMENT CHILLER ,946 2, E-321 REPLACEMENT CHILLER ,946 2, E-269 REPLACEMENT CHILLER ,990 1, E-253 RFPT ACFMFNT CHTLLF.R ,946 1, E-309 REPLACEMENT CHILLER ,946 2, E-301 WATERSIDE ECONOMIZER SAMPLE 2, E-885 ENERGY EFFICIENT MOTORS E-229 RFPT ACFMENT CHTT J ER ,946 1, E-333 REPLACEMENT CHILLER ,323 1, E-425 RFPT ACFMENT CHTLLF.R ,977 1, E-369 RFPT ACFMFNT CHTT J ER ,338 1, E-401 REPLACEMENT CHILLER ,946 1, E-305 RFPT ACFMFNT CHTT I ER ,977 1, E-409 VARIABLE SPEED FAN SAMPLE E-892 RFPT ACFMENT CHTT I ER , E-397 RFPT ACFMFNT CHTT,T ER ,281 1, E-289 REPLACEMENT CHILLER ,338 1, E-381 CHILLED WATER RESET E-853 RFPT ACFMFNT CHTT I ER ,946 1, E-317 RFPT ACFMFNT CHTT.1 ER ,946 1, E-245 RFPT ACFMFNT CHTT,T ER ,023 1, E-345 RFPT ACFMFNT CHTT,T ER ,023 1, E-341 CHTT JED WATER STORAGE SAMPLE 172,800 3, E-896 AUTOMATIC TUBE CLEANERS SAMPLE 16, E-899 RFPT ACFMFNT CHTT,T ER , E-405. RFPT ACFMFNT CHTT T F.R , E-433 REPLACEMENT CHTT,T ER , E-421 RFPT ACFMFNT CHTT I ER , E-417 ES - 39 KgureES5J-2(2of2)

Water Conservation Study (Water and Energy) Energy Engineering Analysis Program (EEAP) FY94S Fort Knox, Kentucky

Water Conservation Study (Water and Energy) Energy Engineering Analysis Program (EEAP) FY94S Fort Knox, Kentucky Water Conservation Study (Water and Energy) Energy Engineering Analysis Program (EEAP) FY94S Fort Knox, Kentucky Final Report EXECUTIVE SUMMARY CONTRACT #DACA01-94-D-0034 SYSTEMS CORP PROJECT #94013.03

More information

Large University Central Chiller Plant Design Considerations

Large University Central Chiller Plant Design Considerations Carrier Engineering Newsletter Volume 5, Issue 3 Large University Central Chiller Plant Design Considerations Large campus chilled water plants have unique constraints and need careful evaluation for successful

More information

Mechanical Project Proposal

Mechanical Project Proposal Mechanical Project Proposal Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State University Prepared by: Stephen Haines December 18

More information

Thesis Final Presentation

Thesis Final Presentation Acoustical lanalysis Thesis Final Presentation Facility Information Mechanical Information Goals Facility Information Location: Total Cost: $56,000,000 Occupancy: Office, Media Center Delivery Method:

More information

This presentation covers process steam energy reduction projects supported by the Ameren Illinois ActOnEnergy program.

This presentation covers process steam energy reduction projects supported by the Ameren Illinois ActOnEnergy program. This presentation covers process steam energy reduction projects supported by the Ameren Illinois ActOnEnergy program. 1 2 Before we get started, here are four questions to find out what you already know

More information

Central Chiller Plants

Central Chiller Plants Central Chiller Plants Institute for Facilities Management New Orleans, LA January 18,2016 Course 319 Presenter: John Vucci Associate Director HVAC Systems University of Maryland College Park, Maryland

More information

Thermal Distribution in District Energy and Cogeneration Systems

Thermal Distribution in District Energy and Cogeneration Systems International District Energy Association Thermal Distribution in District Energy and Cogeneration Systems Presented by William A. Liegois, P.E. Stanley Consultants, Inc. Topics Principles of Hot Water

More information

December 13, 2012 Energy Efficient Cooling Information Service Webinar Series Christine Brinker and Gearoid Foley CHP with Absorption Chilling

December 13, 2012 Energy Efficient Cooling Information Service Webinar Series Christine Brinker and Gearoid Foley CHP with Absorption Chilling December 13, 2012 Energy Efficient Cooling Information Service Webinar Series Christine Brinker and Gearoid Foley CHP with Absorption Chilling Technical Assistance Education and Outreach Executive Order

More information

7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS

7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS Regn No: Name: (To be written by the candidates) 7 th NATIONAL CERTIFICATION EXAMINATION Nov. 2008 FOR ENERGY MANAGERS & ENERGY AUDITORS PAPER 3: Energy Efficiency in Electrical Utilities Date: 23.11.2008

More information

ENERGY ENGINEERING ANALYSIS PROGRAM

ENERGY ENGINEERING ANALYSIS PROGRAM * ": Ik 41 US Army Corps of Engineers Europe Division ENERGY ENGINEERING ANALYSIS PROGRAM Schweinfurt Military Community Executive Summary Final Report \$\

More information

SGM Engineering, Inc.

SGM Engineering, Inc. SGM Engineering, Inc. 1. What is a typical Central Energy Plant consists of? BAS controls, chillers, pumps, cooling towers, electrical distribution, piping, chemicals, heating systems, and generators.

More information

Energy Efficiency in the Industrial Sector

Energy Efficiency in the Industrial Sector Energy Efficiency in the Industrial Sector Case Studies from Lebanon Nader Hajj Shehadeh Senior Energy & Sustainability Consultant WHY? WHY? Energy dominates an average of 30% 30% of industrial facilities

More information

US1 IEA. Renovation of Wausau West High School, Wisconsin, United States of America

US1 IEA. Renovation of Wausau West High School, Wisconsin, United States of America IEA Energy Conservation in Buildings and Community Systems, Annex 36 Case studies overview Renovation of Wausau West High School, Wisconsin, 1 Photos Figure 1: Wausau West High School 2 Project summary

More information

Project Information. Measure Description

Project Information. Measure Description Project Information Project ID#: CE07M016 Measure: Multiple Electric : 452,593 kwh, 8.84 kw, 39.26 kw Facility Type School Technology: Multiple Measure Description CH-1 - Chiller Plant Optimization and

More information

B. System Design and Performance Requirements

B. System Design and Performance Requirements 15625 Water Chillers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes

More information

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option The Milton S. Hershey Medical Center Academic Support Building AE Senior Thesis Kari Anne Donovan Mechanical Option Presentation Outline Existing Conditions Distributed Chilled Water Feasibility Study

More information

MONITORING AND DATA COLLECTION FOR DISTRIBUTED GENERATION/ COMBINED HEAT AND POWER (DG/CHP) SYSTEMS AT ALLIED FROZEN FOODS BROCKPORT, NEW YORK.

MONITORING AND DATA COLLECTION FOR DISTRIBUTED GENERATION/ COMBINED HEAT AND POWER (DG/CHP) SYSTEMS AT ALLIED FROZEN FOODS BROCKPORT, NEW YORK. MONITORING AND DATA COLLECTION FOR DISTRIBUTED GENERATION/ COMBINED HEAT AND POWER (DG/CHP) SYSTEMS AT ALLIED FROZEN FOODS BROCKPORT, NEW YORK. SYSTEM OVERVIEW The power generation shall be delivered via

More information

Ohio Energy. Workshop G. Best Practices in Energy Efficiency to Help You Reduce Your Energy Spend. Tuesday, February 21, :45 a.m.

Ohio Energy. Workshop G. Best Practices in Energy Efficiency to Help You Reduce Your Energy Spend. Tuesday, February 21, :45 a.m. Ohio Energy Workshop G Best Practices in Energy Efficiency to Help You Reduce Your Energy Spend Tuesday, February 21, 2017 10:45 a.m. to Noon Principles of Energy Efficiency Ohio Energy Management Conference

More information

Boiler Energy Efficiency & Overview of Economizers

Boiler Energy Efficiency & Overview of Economizers Boiler Energy Efficiency & Overview of Economizers May 2008 Presented by: Sunil Kumar, P.Eng. GENIVAR Ph: 905-475-7270 Sunil.kumar@genivar.com Outline of Presentation 1. Steam System Overview 2. Energy

More information

Building Operator Certification Level I

Building Operator Certification Level I Building Operator Certification Level I A Partnership of the CUNY Institute for Urban Systems Building Performance Lab, the CUNY School of Professional Studies, and the New York State Energy Research &

More information

Xavier University of Louisiana

Xavier University of Louisiana Annual Savings Report Year 2 May 1, 2012 to April 30, 2013 July 2013 For Marion Bracy Vice President Xavier University Facilities Planning 1 Drexel Drive New Orleans LA 70125 (504) 520 1056 Submitted By

More information

Chilled Water Plant Redesign

Chilled Water Plant Redesign 17 Chilled Water Plant Redesign OVERVIEW The chilled water plant redesign includes the addition of a thermal energy storage system. This allows for economic and operational benefits for the facility by

More information

Energy Efficient. & Cost Saving. Continuous Boiler Blowdown Package Heat Recovery Systems. 20 Models from 1,200 pph to 50,000 pph Capacity

Energy Efficient. & Cost Saving. Continuous Boiler Blowdown Package Heat Recovery Systems. 20 Models from 1,200 pph to 50,000 pph Capacity Continuous oiler lowdown Package Heat Recovery Systems 20 Models from 1,200 pph to 0,000 pph Capacity Energy Efficient & Cost Saving Type HX - For Smaller oiler Systems Type HV - Vertical Type Type - Horizontal

More information

Energy Upgrade Screening Study

Energy Upgrade Screening Study Energy Upgrade Screening Study Prepared for: The University of Maine Orono, ME Prepared by: R.G. Vanderweil Engineers, LLP 274 Summer Street Boston, MA 02210 Vanderweil Project No.: 28471.00 October 28,

More information

(For ASllRAE Staff Use Only)

(For ASllRAE Staff Use Only) ASHRAE TECHNOLOGY AWARDS APPLICATION FORM (Page 1) APPLICATION MUST BE COMPLETE TO BE CONSIDERED FOR JUDGING (Required for Society-Level Competition) 18 (For ASllRAE Staff Use Only) I. Identification (0

More information

South Jefferson High School Huyett Road Charles Town, WV 25414

South Jefferson High School Huyett Road Charles Town, WV 25414 Thesis Proposal Mechanical System Redesign Report Charles Town, WV 25414 Prepared for Dr. Jelena Srebric The Pennsylvania State University By Jonathon Gridley Friday, December 15, 2006 1.0 Table of Contents

More information

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available?

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available? Why an Energy Efficiency Program? Business Solutions Energy Efficiency Incentive Program MPSC 21st Century Electric Energy Plan More electricity is needed as soon as practicable. One way of achieving this

More information

Xavier Energy Initiative

Xavier Energy Initiative Xavier Energy Initiative By Ron Perkins Report of August Site Visit To paraphrase Blaise Pascal, if I had more time I would have written a shorter report. In deference to those who do not share my enthusiasm

More information

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity Energy Accounting & Education Energy Managers Kermit King School District of La Crosse John Daily School District of Holmen 1 Topics (Electricity) Creating electricity Defining degree days Customer charges

More information

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES This article was published in ASHRAE Journal, January 2014. Copyright 2014 ASHRAE. Posted at www. ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission

More information

Best Practices for Energy Efficient Boiler Plant Design, Operation and Control

Best Practices for Energy Efficient Boiler Plant Design, Operation and Control Best Practices for Energy Efficient Boiler Plant Design, Operation and Control A GREENING HEALTH CARE RESEARCH GUIDE ORIGINAL RELEASE: SEPTEMBER 2018 ENERLIFE CONSULTING INC. SPONSORED BY: This Best Practices

More information

Applying Geothermal Technology for Large Scale Projects

Applying Geothermal Technology for Large Scale Projects Jeff Urlaub, PE MEP Associates, LLC jeffu@mepassociats.com 715.832.5680 Engineering Future Focused Solutions Applying Geothermal Technology for Large Scale Projects Breakout Session Category (e.g. Residential)

More information

Industrial Waste Heat Recovery

Industrial Waste Heat Recovery Industrial Waste Heat Recovery Industrial Energy RoundTable Kathey Ferland Project Manager Texas Industries of the Future kferland@mail.utexas.edu Riyaz Papar, PE, CEM Director, Energy Assets & Optimization

More information

Section A: CUSTOMER INFORMATION. Customer Name Electric Account Number Rate Application Number. Facility Address City State Zip Code

Section A: CUSTOMER INFORMATION. Customer Name Electric Account Number Rate Application Number. Facility Address City State Zip Code New Equipment & Construction 2017 VFD Incentive Section A: CUSTOMER INFORMATION Customer Name Electric Account Number Rate Number Facility Address City State Zip Code Service Location Identification Email

More information

Challenges in Industrial Waste Heat Recovery. Texas Technology 2006 Showcase Tony Dafft December 6 & 7, 2006

Challenges in Industrial Waste Heat Recovery. Texas Technology 2006 Showcase Tony Dafft December 6 & 7, 2006 Challenges in Industrial Waste Heat Recovery Texas Technology 2006 Showcase Tony Dafft December 6 & 7, 2006 Outline Plant Statistics and Energy History Tools Used to Identify Projects Sample of Projects

More information

Rowan University Energy Management Optimization of our Central Chilled Water System

Rowan University Energy Management Optimization of our Central Chilled Water System Rowan University Energy Management Optimization of our Central Chilled Water System Presented at the 2014 IDEA Annual Campus Energy Conference Atlanta, GA FOUR PILLARS OF ROWAN ENERGY MANAGEMENT: GENERATION

More information

2.2 The Purposes and Advantages of a Central Utility Plant

2.2 The Purposes and Advantages of a Central Utility Plant 2.2 The Purposes and Advantages of a Central Utility Plant The purpose of the Central Utility Plant (CUP) at NIST is to provide steam, chilled water, and compressed air for hot and cold water, warm and

More information

Chilled Water Energy Savings Study

Chilled Water Energy Savings Study 1 Chilled Water Energy Savings Study Pressure Dependent Valve Sizing and Valve Authority Pressure Independent Valves (Mechanical and Electronic) Chilled Water System Design MIT Beta Site Study-Correcting

More information

Wood Products Energy Savings Guide

Wood Products Energy Savings Guide Wood Products Energy Savings Guide The Oregon wood products industry faces challenges of rising operating costs, rigorous product and safety standards, evolving environmental regulations and increasing

More information

Optimizing Central Chilled Water Systems

Optimizing Central Chilled Water Systems Optimizing Central Chilled Water Systems OPTIMIZING CENTRAL CHILLED WATER SYSTEMS kent.peterson@p2seng.com 1 O P T I M I Z I N G C E N T R A L C H I L L E D W A T E R S Y S T E M S Kent W. Peterson, PE,

More information

DOE Best Practice Software Tools. Joseph Chappell Adam Roget

DOE Best Practice Software Tools. Joseph Chappell Adam Roget DOE Best Practice Software Tools Joseph Chappell Adam Roget DOE Software Tool Use Over the past year 12 regular IAC assessments 3 large energy user assessments 1 SEN type assessment for a local hospital

More information

UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall th Street San Francisco, California

UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall th Street San Francisco, California UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall 1550 4th Street San Francisco, California Monitoring Based Recommissioning Project Project Implementation: June 2005 to December 2005 Funded by a

More information

DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES. David Payne, P.E Interim Associate Director October 16, 2012

DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES. David Payne, P.E Interim Associate Director October 16, 2012 DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES David Payne, P.E Interim Associate Director October 16, 2012 Agenda - Production System Overview - Distributions Systems Overview - Recently Completed

More information

How the design of a cooling tower impacts energy usage and operating costs

How the design of a cooling tower impacts energy usage and operating costs Introduction A variety of cooling tower technologies and configurations exist in the market today. Each type can offer different component technologies, different materials of construction, and different

More information

Economic Feasibility Study. September 12, 2008

Economic Feasibility Study. September 12, 2008 Economic Feasibility Study September 12, 2008 VERSION HISTORY Version Date Author Change Description 1.0 9-8-2009 Siemens SBT Initial creation. 1.1 9-9-2008 Siemens SBT 1.2 9-12-2008 Siemens SBT Deleted

More information

G eothermal. S ystems. The Earth Connection

G eothermal. S ystems. The Earth Connection G eothermal S ystems The Earth Connection T he Earth Connection Geothermal Systems in Southern Maryland Why Use a Geothermal System?... 3 Types of Geothermal Systems...4 Open Loop Systems...4 Closed Loop

More information

Retrocommissioning Investigation Report

Retrocommissioning Investigation Report Continuous Optimization for Commercial Buildings Program Retrocommissioning Investigation Report March 22, 2013 Prepared for: Thompson Rivers University International Building BC Hydro #:COP10-353 Prism

More information

ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE CAPITOL IDEA CAMPUS ENERGY CONFERENCE MARCH 8, 2018

ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE CAPITOL IDEA CAMPUS ENERGY CONFERENCE MARCH 8, 2018 WWW.AOC.GOV 1 ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE CAPITOL IDEA CAMPUS ENERGY CONFERENCE MARCH 8, 2018 ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE

More information

ENERGY AUDIT of FULLY CONDENSING BOILER STACK ECONOMIZER

ENERGY AUDIT of FULLY CONDENSING BOILER STACK ECONOMIZER FULLY CONDENSING BOILER STACK ECONOMIZER for: CENTRAL WASHINGTON UNIVERSITY Ellensburg, Washington prepared by: 12655 Center Drive, Suite 250 Beaverton, Oregon 97005 Contact: Mark E. Kinzer markk@abacusrm.com

More information

ADVANCED ABSORPTION CHILLER CONVERTS TURBINE EXHAUST TO AIR CONDITIONING

ADVANCED ABSORPTION CHILLER CONVERTS TURBINE EXHAUST TO AIR CONDITIONING International Sorption Heat Pump Conference June 22 24, 2005; Denver, CO, USA ISHPC-095-2005 ADVANCED ABSORPTION CHILLER CONVERTS TURBINE EXHAUST TO AIR CONDITIONING Jeanette B. Berry* Rod Schwass James

More information

IDEA Synopsis Submission

IDEA Synopsis Submission IDEA Synopsis Submission University of Minnesota 2017 IDEA Annual Energy Conference Abstract Topic: District Cooling: A Heating Highway Submitted by: Scott McCord, PE, University of Minnesota Abstract

More information

Energy Reduction in Hospitals

Energy Reduction in Hospitals Energy Reduction in Hospitals OSBORN ENGINEERING DAVE CHOUINARD, CBCP, LEED AP, DIRECTOR HEALTHCARE CARL SCHULTZ, PE, DIRECTOR ENERGY AND FACILITY SYSTEMS MARK WUTZ, PE, DIRECTOR ENERGY & COMMISSIONING

More information

Introduction. Food & Dairy Plants typically employ psig steam generated by firetube boilers. First cost of a steam boiler plant is exceeded

Introduction. Food & Dairy Plants typically employ psig steam generated by firetube boilers. First cost of a steam boiler plant is exceeded Introduction Food & Dairy Plants typically employ 100 135 psig steam generated by firetube boilers. First cost of a steam boiler plant is exceeded many times by the cost of energy over the life of the

More information

FINAL EXECUTIVE SUMMARY ENERGY SAVINGS OPPORTUNITY SURVEY U.S. ARMY FIELD STATION KUNIA OAHU, HAWAII PREPARED FOR:

FINAL EXECUTIVE SUMMARY ENERGY SAVINGS OPPORTUNITY SURVEY U.S. ARMY FIELD STATION KUNIA OAHU, HAWAII PREPARED FOR: FINAL EXECUTIVE SUMMARY ENERGY SAVINGS OPPORTUNITY SURVEY U.S. ARMY FIELD STATION KUNIA OAHU, HAWAII KB P"^^ PREPARED FOR: Department of the Army Pacific Ocean Division Corps of Engineers PREPARED BY:

More information

COOLING COIL (35% ETHYLENE GLYCOL)

COOLING COIL (35% ETHYLENE GLYCOL) APPENDIX Contents A1.1 Existing Mechanical Equipment Schedules A1.2 Existing Mechanical System Schematic Drawings A2. Building Design Loads, Energy Loads and Cost Data Tables A3. Standard 62n-2001 Ventilation

More information

District Cooling Sustainable Design. Presented by George Berbari CEO of DC PRO Engineering

District Cooling Sustainable Design. Presented by George Berbari CEO of DC PRO Engineering 2016 District Cooling Presented by George Berbari CEO of DC PRO Engineering District Cooling Brief History & Future Central Chilled Water plants existed in the Middle East as early as the 1960 s. Few examples

More information

NEBBinar: Managing Building Performance through Commissioning. March 28, 2013

NEBBinar: Managing Building Performance through Commissioning. March 28, 2013 NEBBinar: Managing Building Performance through Commissioning March 28, 2013 0 Moderator Jim Huber, NEBB Vice President and President of Complete Commissioning Jim Huber is the President of Complete Commissioning.

More information

how to read an energy model

how to read an energy model how to read an energy model Kohler Ronan, LLC is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported

More information

Fifteen Year Plan for Energy Efficiency and Conservation Projects

Fifteen Year Plan for Energy Efficiency and Conservation Projects Fifteen Year Plan for Energy Efficiency and Conservation Projects Presented to the Board of Trustees of the Northeastern Ohio Universities Colleges of Medicine and Pharmacy, December, 2008, in accordance

More information

Variable Frequency Drive Retrofit Opportunities. Michael Kuk CERx Solutions LLC

Variable Frequency Drive Retrofit Opportunities. Michael Kuk CERx Solutions LLC Variable Frequency Drive Retrofit Opportunities Michael Kuk CERx Solutions LLC Speaker Introduction» Founder / owner of CERx Solutions LLC» Veteran Owned Small Business Enterprise founded in 2013» 27+

More information

Small Oil-Less Centrifugal Compressors: Bringing Energy Efficiency and Reduced Costs to Chiller Plants

Small Oil-Less Centrifugal Compressors: Bringing Energy Efficiency and Reduced Costs to Chiller Plants Small Oil-Less Centrifugal Compressors: Bringing Energy Efficiency and Reduced Costs to Chiller Plants Ben Erpelding and Annika Moman, San Diego Regional Energy Office ABSTRACT According the U.S. Department

More information

Chilled Water Plant Design American Standard Inc.

Chilled Water Plant Design American Standard Inc. Chilled Water Plant Design 2003 American Standard Inc. Agenda Earthwise System Variable Primary Flow Series Configuration Case Study 20,000RT Project Parallel, primary/secondary, low temp, YK Series-counter,

More information

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.

More information

Case Studies in Energy Efficiency and Water Conservation Projects

Case Studies in Energy Efficiency and Water Conservation Projects Case Studies in Energy Efficiency and Water Conservation Projects Introduction About PepsiCo World leader in convenient snacks, foods and beverages + $60 billion revenues + 285,000 employees Fortune 50

More information

Minnesota Conservation

Minnesota Conservation Program Information MN Minnesota Conservation Programs Summary We offer solutions for business customers in a suite of energy conservation and energy management products that will help you increase your

More information

Energy Efficiency Strategies Waste Heat Recovery & Emission Reductions

Energy Efficiency Strategies Waste Heat Recovery & Emission Reductions Energy Efficiency Strategies Waste Heat Recovery & Emission Reductions TUR Continuing Education Conference Sturbridge Host Hotel April 14, 2010 With fuel prices increasing and environmental pressure to

More information

Application of Steam Turbine Driven Chillers in CHP/DES System

Application of Steam Turbine Driven Chillers in CHP/DES System Application of Steam Turbine Driven Chillers in CHP/DES System Bradley Cochrane, M. Eng., P. Eng., CEM, Director, Energy Management, York University. Edy Chiarotto, HVAC Equipment Sales Manager, Johnson

More information

MHWW-09-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 9,000 BTUH. Rev. 1.3

MHWW-09-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 9,000 BTUH. Rev. 1.3 MHWW-09-H-1 Chilled/Hot Water Hi-Wall Fan Coil Heat / Cool Fan Coil 9,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Hi-Wall Fan Coil 2-Pipe Nominal Size: 9,000 BTUH Multiaqua Model

More information

MHWW-18-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 18,000 BTUH. Rev. 1.3

MHWW-18-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 18,000 BTUH. Rev. 1.3 MHWW-18-H-1 Chilled/Hot Water Hi-Wall Fan Coil Heat / Cool Fan Coil 18,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Hi-Wall Fan Coil 2-Pipe Nominal Size: 18,000 BTUH Multiaqua Model

More information

MHWW-12-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 12,000 BTUH. Rev. 1.3

MHWW-12-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 12,000 BTUH. Rev. 1.3 MHWW-12-H-1 Chilled/Hot Water Hi-Wall Fan Coil Heat / Cool Fan Coil 12,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Hi-Wall Fan Coil 2-Pipe Nominal Size: 12,000 BTUH Multiaqua Model

More information

Ground-Coupled Heat Pump And Energy Storage

Ground-Coupled Heat Pump And Energy Storage Ground-Coupled Heat Pump And Energy Storage By Ed Lohrenz, Member ASHRAE; and Sergio Almeida, P.Eng., Member ASHRAE Ground-coupled heat pump (GCHP) systems consume less purchased energy than an HVAC system

More information

Sustainable Development at the University of Regina

Sustainable Development at the University of Regina Sustainable Development at the University of Regina Tom Atkins, P.Eng., LEED AP Vice President - Mechanical Stantec Consulting Jared Larson, P.Eng. Associate MacPherson Engineering Neil Paskewitz, P.Eng.

More information

Scoping Report. Montpelier District Energy CHP. Scoping Report

Scoping Report. Montpelier District Energy CHP. Scoping Report Montpelier District Energy CHP Last modified: 12/1/2009 Montpelier District Energy CHP System 1 Introduction... 4 2 Executive Summary... 4 2.1 Existing Capitol District Steam Plant. 2.2 Proposed System

More information

Environment & Power Systems International. VOCGEN /CHP Feasibility Screening Data Form. Level 1 Feasibility Analysis

Environment & Power Systems International. VOCGEN /CHP Feasibility Screening Data Form. Level 1 Feasibility Analysis VOCGEN /CHP Feasibility Screening Data Form VOCGEN /CHP Gensets and Systems (VOCGEN /CHP) can provide significant economic benefits to certain users. Whether VOCGEN /CHP can be economically beneficial

More information

OTAC EQUIPMENT CALCULATION FORMAT

OTAC EQUIPMENT CALCULATION FORMAT OTAC EQUIPMENT CALCULATION FORMAT The following format is to be used to determine each projects' operating expenses for OTAC. Please use this format for your projects' calculation and submit to the Director

More information

Absorption Chillers in Industry

Absorption Chillers in Industry Absorption Chillers in Industry With deregulation and recent advances, absorption can be the best suited chiller option available. For Robust Performance Look to the Horizon Series of Absorption Chillers

More information

Condenser Water Heat Recovery"

Condenser Water Heat Recovery PLEASE MUTE CELL PHONES Condenser Water Heat Recovery" Julian de Bullet ASHRAE Distinguished Lecturer Director of Industry Relations McQuay International 703-395-5054 1 What Is Sustainability? sustainable

More information

Princeton University Facilities Engineering

Princeton University Facilities Engineering Princeton University Facilities Engineering Environmental & Energy Study Institute International District Energy Association District Energy & Combined Heat & Power at Princeton University Rayburn House

More information

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012 Cogeneration and Thermal Chillers.. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012 Agenda Cogeneration Interest and Application Basics Equipment Matching Thermal Chiller Overview Steam Components

More information

High Technology Energy Savings Guide

High Technology Energy Savings Guide High Technology Energy Savings Guide The high-tech industry is a crucial and dynamic part of Oregon s economy that is expected to grow faster than other industries over the next decade. Working in a highly

More information

Chilled Water Loop Optimization. Kazimir Gasljevic Richard Dewey Sandro Sanchez

Chilled Water Loop Optimization. Kazimir Gasljevic Richard Dewey Sandro Sanchez Chilled Water Loop Optimization Kazimir Gasljevic Richard Dewey Sandro Sanchez WHAT WE STARTED WITH: LOOP OUTLINE: WHAT WE STARTED WITH: LOOP OUTLINE: - Justification for the loop WHAT WE STARTED WITH:

More information

Heat Recovery. Integrated CHP Systems Corp.

Heat Recovery. Integrated CHP Systems Corp. Heat Recovery In order to achieve CHP efficiencies of 80% the recovery of waste heat for useful purposes is more significant than the electric efficiency This isn t necessarily in sync with the economics

More information

Final Report for National Grid USA Service Company. Evaluation of 2003 Custom Process Installations Part I. August 24, 2005.

Final Report for National Grid USA Service Company. Evaluation of 2003 Custom Process Installations Part I. August 24, 2005. Final Report for National Grid USA Service Company Evaluation of 2003 Custom Process Installations Part I August 24, 2005 Submitted by Select Energy Services, Inc. is the energy services subsidiary of

More information

Gregory W. Stevens and Ronald K. Ishii, Alternative Energy Systems Consulting, Inc.

Gregory W. Stevens and Ronald K. Ishii, Alternative Energy Systems Consulting, Inc. A Study of Optimizing the System Integration of Combined Heat and Power (CHP) with Absorption Cooling for Cold Storage Applications: Design Considerations, Modeling and Life Cycle Costing Gregory W. Stevens

More information

Georgetown University New Science Center

Georgetown University New Science Center Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical

More information

ENERGY ENGINEERING ANALYSIS PROGRAM (EEAP) BOILER/CHILLER PLANT STUDY EXECUTIVE SUMMARY

ENERGY ENGINEERING ANALYSIS PROGRAM (EEAP) BOILER/CHILLER PLANT STUDY EXECUTIVE SUMMARY ENERGY ENGINEERING ANALYSIS PROGRAM (EEAP) X e^ht BOILER/CHILLER PLANT STUDY FORT HOOD, TEXAS FINAL SUBMITTAL EXECUTIVE SUMMARY U.S. ARMY CORPS OF ENGINEERS OCTOBER 1991 ROMINE, ROMINE & BURGESS, INC.

More information

Centerpoint Energy. Energy Efficiency & Technology Conference. Steam and Process Heat Recovery. May 23, 2017

Centerpoint Energy. Energy Efficiency & Technology Conference. Steam and Process Heat Recovery. May 23, 2017 Centerpoint Energy Energy Efficiency & Technology Conference Steam and Process Heat Recovery May 23, 2017 Madison, WI Tom Tucker, P.E. Principal 1 General Agenda About Kinergetics Boilers and Steam Systems

More information

Figure 26.5 Potential fan energy savings using fan speed limiting 16.

Figure 26.5 Potential fan energy savings using fan speed limiting 16. COMMISSIONING FOR ENERGY MANAGEMENT 685 Figure 26.5 Potential fan energy savings using fan speed limiting 16. 26.4.2.2. Set Minimum Outside Air Intake Correctly Outside air intake rates are often significantly

More information

BETTER BUILDINGS BY DESIGN Sheraton Conference Center Burlington, Vermont. February 8, 2012

BETTER BUILDINGS BY DESIGN Sheraton Conference Center Burlington, Vermont. February 8, 2012 BETTER BUILDINGS BY DESIGN - 2012 Sheraton Conference Center Burlington, Vermont February 8, 2012 What is a geothermal System? Technically, it is a water source heat pump (WSHP) system that uses the

More information

Building Energy Analysis for a Multi-Family Residential Building (Multi V III VRF Heat-Pump System)

Building Energy Analysis for a Multi-Family Residential Building (Multi V III VRF Heat-Pump System) Building Energy Analysis for a Multi-Family Residential Building (Multi V III VRF Heat-Pump System) Residential-Building Energy-Modeling Engineering Study VRF-ES-BH-001-US 012E03 Executive Summary Contents

More information

Campus-Wide Cooling Plant Load Analysis & Thermal Energy Storage (TES) System Concept Engineering Study

Campus-Wide Cooling Plant Load Analysis & Thermal Energy Storage (TES) System Concept Engineering Study North Orange County Community College District Campus-Wide Cooling Plant Load Analysis & Thermal Energy Storage (TES) System Concept Engineering Study Fullerton College Final September 8, 2017 Table of

More information

Equipment Design. Detailed Plant Conceptual Design. Version 7.0

Equipment Design.   Detailed Plant Conceptual Design. Version 7.0 Equipment Design Version 7.0 Detailed Plant Conceptual Design SOAPP CT sizes all major plant equipment, based on your Project Input, the process configuration derived from this input, and the results of

More information

Preparatory study for Steam Boilers Ecodesign

Preparatory study for Steam Boilers Ecodesign www.pwc.com Preparatory study for Steam Boilers Ecodesign Stakeholder Meeting Brussels, Task 1: Scope PwC - ICCS - Fraunhofer ISI Slide 2 Tasks structure Task 1: Scope Task 2: Task 3: Task 4: Markets Users

More information

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS NATIONAL CERTIFICATION EXAMINATION 004 FOR ENERGY MANAGERS PAPER EM3: Energy Efficiency in Electrical Utilities Date: 3.05.004 Timings: 0930-30 HRS Duration: 3 HRS Max. Marks: 50 General instructions:

More information

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68%

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68% Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68% Address 666 Burrard St, Vancouver Management QuadReal Property Group Type of Building Office Year of Construction 1984 Number

More information

OPERATING PARAMETERS Reliable Means to Continuously Monitor Facility Performance

OPERATING PARAMETERS Reliable Means to Continuously Monitor Facility Performance OPERATING PARAMETERS Reliable Means to Continuously Monitor Facility Performance RICHARD SCHERRER Ogden Martin Systems, Inc. Fairfield, New Jersey ABSTRACT Energy sales are a major source of revenues for

More information

Design Criteria for High Efficiency Centrifugal Chillers in District Cooling Plants

Design Criteria for High Efficiency Centrifugal Chillers in District Cooling Plants Design Criteria for High Efficiency Centrifugal Chillers in District Cooling Plants Presented by: Srinivasan Rangan Senior Manager ( Technical ) Key Accounts and Strategic Projects UTC Climate, Controls

More information

Benchmarking an Energy Evaluation Tool for Chilled Water Systems

Benchmarking an Energy Evaluation Tool for Chilled Water Systems Benchmarking an Energy Evaluation Tool for Chilled Water Systems Michael Stocki, University ofmassachusetts, Amherst Dragoljub Kosanovic, University ofmassachusetts, Amherst Lawrence Ambs, University ofmassachusetts,

More information

CFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH

CFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH CFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Universal Mount Fan Coil 2-Pipe Nominal Size: 60,000

More information