Santa Monica Airport Watershed Management Project City of Santa Monica
|
|
- Kelly Williamson
- 6 years ago
- Views:
Transcription
1
2 City of Santa Monica Project No. 1CSM Prepared for: City of Santa Monica th St. Suite 300 Santa Monica, CA Prepared by: 555 S. Flower Street, Suite 4400 Los Angeles, CA Catherine Tyrrell with GeoSyntec Consultants 2566 Overland Avenue, Suite 670 Los Angeles, CA Ken Susilo
3 TABLE OF CONTENTS TABLE OF CONTENTS... i TABLES... i FIGURES... i APPENDICES...iii 1.0 Introduction and Summary Approach City of Santa Monica Airport Watershed Project Site Description Drainage Areas and Land Use Opportunities and Constraints Key BMPs and Treatment Trains Pollutants of Concern Pollutants and Beneficial Uses in Receiving Waters Land Uses and Associated Pollutants Airport Watershed Description Physical Description of Watershed Drainage Sub-Areas Land Uses, Pollutants, and BMP Opportunities and Constraints BMPs Evaluated Stakeholder Workshop BMP List for Further Analysis Worksheets and Photos Feasibility at a Planning Scale AIRPORT PROPERTY RESIDENTIAL AREA BUSINESS PARK OTHER Amounts and values of Avoided Potable Water Use Next Steps Capital Improvement Plan Conclusion TABLES Table 2-1 Land Uses and Associated Pollutants Table 2-2 BMPs and Targeted Pollutants Table 3-1 Sub-Drainage Description and Tributary Areas Table 3-2 LAND USE BMP ASSESSMENT: ISSUES AND OPPORTUNITIES Table 4-1 Water Quality Calculations Summary FIGURES Figure Figure Figure Figure i
4 Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure ii
5 Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure APPENDICES Appendix A Technical Memorandum Appendix B Penmar Water Quality Improvement and Runoff Reuse Project Appendix C County Department of Health and Services and City Building and Safety Division Health Standards Appendix D Recommended BMPs Design Performance Appendix E Workshop Presentation 6/20/2007 iii
6 iv
7 1.0 Introduction and Summary This report builds upon the City of Santa Monica s citywide Watershed Management Plan focusing on a priority watershed, the Santa Monica Airport Watershed, creating a more detailed Airport Watershed Management Plan with the following goals: Recommend implementable BMPs consistent with the City s Hierarchy of BMPs: Harvest, treat and reuse Harvest and infiltrate Treat and release Support the restoration of a healthier balance between the urban environment and the natural ecosystem, including the Santa Monica Bay; Be consistent with the City s guiding principles for sustainability. Specifically the report is based on the following tasks: Evaluate and develop alternative solutions for runoff management and present and discuss these alternatives in a workshop coordinated by city staff; opportunities for reuse will be included. Based on feedback from the workshop, provide an analysis of up to 10 BMPs in terms of construction constraints and costs, pollutants targeted, site feasibility based on information available (planning level). At least one of the BMPs will include down stream reuse opportunities. For the pertinent BMPs, provide information on treatment design and performance. Present information on the volume of water that can be reused and the avoided cost of potable water that it is replacing. 1.1 Approach To initiate the project, background information was provided by the City of Santa Monica, including the 1998 Hydrology Study, 1985 Master Plan of Drainage for the Santa Monica Municipal Airport, the 2005 Draft Santa Monica Airport Watershed Management Plan, and the Airport SWPPP and Monitoring Program. Information on soil type and porosity was provided in the Santa Monica Municipal Airport Master Plan of Drainage. FAA rules and regulations were considered in assessing potential best management practices BMPs for the airport drainage area. Specifically, the 1984 Santa Monica Airport Agreement with the Federal Aviation Administration (FAA) was reviewed for regulations on the types of improvements that may take place on the airport runway area. Restrictions include the runway/taxiway configuration, aircraft parking and tie-down space, and fixed base operator space, among others. 1-1
8 1.2 City of Santa Monica Airport Watershed Project Site Description The Airport Watershed is located in the southeastern corner of Santa Monica. It includes the Santa Monica Airport and surrounding both single family and multi-family residential land use, with a small amount of commercial areas and parks. The Airport Watershed, including the airport itself, totals about acres. The watershed flows to the Rose Ave. Drain in the City of Los Angeles and from there to Santa Monica Bay. Figure 1-1 shows the Santa Monica Airport Watershed. Figure 1-1 Santa Monica Airport Watershed Site Map 1-2
9 As shown in Figure 1-2, the Santa Monica Airport Watershed is part of a larger watershed all of which drains to the Rose Ave. storm drain adjacent to Penmar Park and Golf Course and exits to Santa Monica Bay. It is joined by the 16 th Ave. storm drain from within the city of Santa Monica and other city of Los Angeles Mar Vista hillside and Penmar adjacent drainage. Figure 1-2 Rose Ave Drainage Area Including the Santa Monica Airport Watershed Within the Santa Monica Airport Watershed, land uses can be seen in Figure
10 Figure 1-3 Land Uses Within the Santa Monica Airport Watershed 1.3 Drainage Areas and Land Use Opportunities and Constraints The Santa Monica Airport Watershed is composed of four drainage areas within the City. These are described in section 3.2. Section 3.3 provides the analysis of BMP opportunities and constraints. The watershed has been analyzed to determine locations for storm water reuse, retention, detention, and treatment. 1-4
11 1.4 Key BMPs and Treatment Trains Based on a stakeholder workshop held on June 20, 2007, 10 BMPs were chosen for more detailed analysis. They are: Airport Property: 1. Airport Avenue Landscaping 2. SMC Parking Lot Underground Retention 3. Zinc Hangar Runoff Management Residential Area: 4. Traffic Calming Landscape Modification 5. Pearl Street Rain Gardens 6. Grant Elementary School Underground Retention 7. Clover Park Underground Retention 8. Pico Boulevard Porous Pavement Business Park: 9. Business Park Bioretention Retrofit Other: 10. Penmar Water Quality Improvement and Runoff Reuse 2.0 Pollutants of Concern 2.1 Pollutants and Beneficial Uses in Receiving Waters The Santa Monica Airport Watershed is part of the greater Rose Ave. Watershed which, in turn, is part of the 414 square-mile Santa Monica Bay Watershed. The Santa Monica Bay Watershed reaches from the crest of the Santa Monica Mountains on the north from the Ventura-Los Angeles County line to downtown Los Angeles. From there it extends south and west across the Los Angeles plain to include the area east of Ballona Creek and north of Baldwin Hills. South of Ballona Creek, the natural drainage area is a narrow strip between Playa del Rey and Palos Verdes. The Santa Monica Bay has many beneficial uses, including fishing, swimming, surfing, diving and other REC-1 classified activities. Santa Monica Bay Beaches also have separate beneficial uses. The Los Angeles Regional Water Quality Control Board s 2002 Clean Water Act Section 303(d) List includes the Santa Monica Bay Offshore/Nearshore. The pollutants listed for this area include: Chlordane (sediment) 2-5
12 DDT (tissue & sediment) Debris Fish Consumption Advisory PAHs (Sediment) PCBs Polychlorinated biphenyls (tissue & sediment) Sediment Toxicity All are listed as low TMDL priority, with the exception of Chlordane which is listed as medium. The Santa Monica Bay Offshore/Nearshore pollutants listed on the (d) list includes a shorter list of the following pollutants: DDT (tissue and sediment), Debris, Fish Consumption Advisory, PCBs (Polychlorinated biphenyls) (tissue and sediment), and Sediment Toxicity. The beaches of Santa Monica Bay are listed separately from the receiving waters. The key pollutant listed is coliform (bacteria).the Santa Monica Bay Beaches Bacteria Total Maximum Daily Load (TMDL) was adopted on December 12, 2002 by the Regional Board (Resolution No ). As a result of these listings, the pollutant of greatest concern is bacteria. 2.2 Land Uses and Associated Pollutants Typical pollutants are associated with types of development (land use) that contribute to urban runoff. Table 2-1 below provides an overview of various land use classifications and the degree to which specified pollutants may be expected as a result of each land use. Type of Development (Land Use) Detached Residential Development Attached Residential Development Commercial/ Industrial Automotive Repair Shops Sediment/ Turbidity Table 2-1 Land Uses and Associated Pollutants Nutrients Organic Compounds Trash & Debris Oxygen Demanding Substances Bacteria & Viruses Oil & Grease Pesticides E E N E E E E E N E E N E P (1) P P (2) E N P (1) P (1) P(5) E P (1) P(3) E P (1) P N N E(4,5) E N N E N P Restaurants N N N E E E E N N Metals Hillside Development E E N E E E E E N 2-6
13 Parking Lots P(1) P(1) E(4) E P(1) P(6) E P(1) E Streets, Highways & Freeways Parks and Open Space E P(1) E(4) E P(1) P(6) E P(1) E E E N N E N N E N Source: Riverside County Flood Control and Conservation District, Riverside County Water Quality Management Plan for Urban Runoff (September 17, 2004). Abbreviations: E = Expected P = Potential N=Not expected Notes: (1) A potential pollutant if landscaping or an open area exists. (2) A potential pollutant if area includes uncovered parking areas. (3) A potential pollutant is land use involves animal waste. (4) Specifically, petroleum hydrocarbons. (5) Specifically, solvents. (6) Bacterial indicators are routinely detected in pavement runoff. The following descriptions are provided for each pollutant identified in Table 2-1 above: Sediments Sediments are soils or other surficial materials eroded and then transported or deposited by the action of wind, water, ice, or gravity. Sediments can increase turbidity, clog fish gills, reduce spawning habitat, lower young aquatic organisms survival rates, smother bottom dwelling organisms, and suppress aquatic vegetation growth. Nutrients Nutrients are inorganic substances, such as nitrogen and phosphorus. They commonly exist in the form of mineral salts that are either dissolved or suspended in water. Primary sources of nutrients in urban runoff are fertilizers and eroded soils. Excessive discharge of nutrients to water bodies and streams can cause excessive aquatic algae and plant growth. Such excessive production, referred to as cultural eutrophication, may lead to excessive decay of organic matter in the water body, loss of oxygen in the water, release of toxins in sediment, and the eventual death of aquatic organisms. Organic Compounds Organic compounds are carbon-based. Commercially available or naturally occurring organic compounds are found in pesticides, solvents, and hydrocarbons. Organic compounds can, at certain concentrations, indirectly or directly constitute a hazard to life or health. When rinsing off objects, toxic levels of solvents and cleaning compounds can be discharged to the MS4. Dirt, grease, and grime retained in the cleaning fluid or rinse water may also adsorb levels of organic compounds that are harmful or hazardous to aquatic life. Pesticides (including herbicides) are chemical compounds commonly used to control nuisance growth or prevalence of organisms. Excessive or improper application of a pesticide may result in runoff containing toxic levels of its active ingredient. Trash and Debris Trash (such as paper, plastic, polystyrene packing foam, and aluminum materials) and biodegradable organic matter (such as leaves, grass cuttings, and food waste) are general waste products on the landscape. The presence of trash and debris may have a significant impact on the recreational value of a water body and aquatic habitat. Excess organic matter can create a high biochemical oxygen demand in a stream and thereby lower its water quality. In addition, in areas where stagnant water exists, the presence of excess 2-7
14 organic matter can promote septic conditions resulting in the growth of undesirable organisms and the release of odorous and hazardous compounds such as hydrogen sulfide. Oxygen-Demanding Substances This category includes biodegradable organic material as well as chemicals that react with dissolved oxygen in water to form other compounds. Proteins, carbohydrates, and fats are examples of biodegradable organic compounds. Compounds such as ammonia and hydrogen sulfide are examples of oxygen-demanding compounds. The oxygen demand of a substance can lead to depletion of dissolved oxygen in a water body and possibly the development of septic conditions. Pathogens Pathogens and viruses ( measured by bacteria indicators) are ubiquitous microorganisms that thrive under certain environmental conditions. Their proliferation is typically caused by the transport of animal or human fecal wastes from the watershed. Water, containing excessive bacteria and viruses can alter the aquatic habitat and create a harmful environment for humans and aquatic life. Also, the decomposition of excess organic waste causes increased growth of undesirable organisms in the water. Metals The primary source of metal pollution in urban runoff is typically commercially available metals and metal products. Metals of concern include cadmium, chromium, copper, lead, mercury, and zinc. Lead and chromium have been used as corrosion inhibitors in primer coatings and cooling tower systems. Metals are also raw material components in non-metal products such as fuels, adhesives, paints, and other coatings. At low concentrations naturally occurring in soil, metals may not be toxic. However, at higher concentrations, certain metals can be toxic to aquatic life. Humans can be impacted from contaminated groundwater resources, and bioaccumulation of metals in fish and shellfish. Environmental concerns, regarding the potential for release of metals to the environment, have already led to restricted metal usage in certain applications. A comparison of the pollutants existing in the Santa Monica Watershed and receiving waters of the Santa Monica Bay with pollutants associated with land use activity in the Santa Monica Airport Watershed shows an overlap of common pollutants. Because of the wide range of land uses in the Santa Monica Airport Watershed, all of the pollutants listed can be considered of concern in the Watershed. However as BMPs are identified by location, one or another of the land uses and their specific pollutants of concern will dominate. In general the strategy is as follows: 1) where reuse is possible, treat to remove all pollutants to a Title 24 equivalency; 2) otherwise provide filtration or infiltration to remove bacteria and other pollutants in storm water. Table 2-2 provides a list of treatment control BMP categories identifying their effectiveness in treating various pollutants of concern. 2-8
15 Pollutant of Concern Table 2-2 BMPs and Targeted Pollutants Treatment Control BMP Categories (9) Veg. Swale /Veg. Filter Strips Detention Basins (2) Infiltration Basins & Trenches/Porous Pavement (3)(10) Wet Ponds or Wetlands Sand Filter or Filtration Water Quality Inlets Hydrodynamic Separator Systems (4) Sediment/Turbidity H/M M H/M H/M H/M L H/M (L for turbidity) Yes/No? Nutrients L M H/M H/M L/M L L U Yes/No? Organic Compounds U U U U H/M L L U Yes/No? Trash & Debris L M U U H/M M H/M U Yes/No? Oxygen Demanding Substances L M H/M H/M H/M L L U Yes/No? Bacteria & Viruses U U H/M U H/M L L U Yes/No? YES Oils & Grease H/M M U U H/M M L/M U Yes/No? Pesticides (non-soil bound) U U U U U L L U Yes/No? Metals H/M M H H H L L U Yes/No? Manufactured/ Proprietary Devices U 2-9
16 Abbreviations: L: Low removal efficiency M: Medium removal efficiency H: High removal efficiency U: Unknown removal efficiency Notes: (1) Periodic performance assessment and updating of the guidance provided by this table may be necessary. (2) Includes grass swales, grass strips, wetland vegetation swales, and bioretention. (3) Includes extended/dry detention basins with grass lining and extended/dry detention basins with impervious lining. Effectiveness based upon minimum hour drawdown time. (4) Includes infiltration basins, infiltration trenches, and porous pavements. (5) Includes permanent pool wet ponds and constructed wetlands. (6) Includes sand filters and media filters. (7) Also known as hydrodynamic devices, baffle boxes, swirl concentrators, or cyclone separators. (8) Includes proprietary stormwater treatment devices as listed in the CASQA Stormwater Best Management Practices Handbooks, other stormwater treatment BMPs not specifically listed in this report or newly developed/emerging stormwater treatment technologies. (9) Project proponents should base BMP designs on the Los Angeles County Stormwater Quality Best Management Practice Design Handbook. However, project proponents may also wish to reference the California Stormwater BMP Handbook New Development and Redevelopment ( The Handbook contains additional information on BMP operation and maintenance. (10) Note: Projects that will utilize infiltration-based Treatment Control BMPs (e.g., Infiltration Basins, Infiltration Trenches, Porous Pavement) without an underdrain will need to demonstrate with a property/project specific soils report that the soils are of the appropriate porousity. The selection of a Treatment Control BMP (or BMPs) for the project must specifically consider the effectiveness of the Treatment Control BMP for pollutants identified as causing an impairment of Receiving Waters to which the project will discharge Urban Runoff. 2-10
17 3.0 Airport Watershed Description 3.1 Physical Description of Watershed The Airport Basin Watershed is located in the southeastern corner of Santa Monica. It includes the Santa Monica Airport and both single-family and multi-family residential land use with a small amount of commercial areas and parks. The watershed flows to the Rose Avenue Drain in the City of Los Angeles and from there to Santa Monica Bay. Figure 3-1 shows the Santa Monica Airport Watershed Project Site. Figure 3-1 Santa Monica Airport Watershed Site Map 3-11
18 As shown in Figure 3-2, the Santa Monica Airport Watershed drains to the Rose Avenue storm drain adjacent to Penmar Park and Golf Course and exits to Santa Monica Bay. It is joined by the 16 th Avenue storm drain from within the city of Santa. Figure 3-2 Rose Avenue Drainage Area Including the Santa Monica Airport Watershed The Santa Monica Municipal Airport Master Plan of Drainage (May 1985) states that the soils in the drainage area are classified as 013 and 014, according to the Los Angeles County Flood Control District s classification of soil types. Soil type 013 has a low infiltration capacity and produces a maximum amount of runoff. Soil type 014 also produces a relatively high rate of runoff. These soil types were a factor in determining the feasibility of infiltration best management practices, as discussed in section
19 3.2 Drainage Sub-Areas The Santa Monica Airport Watershed is composed of four drainage areas. Table 3-1 Sub-Drainage Description and Tributary Areas Sub-Area Description Area [ac] DA 1-25th-S Airport DA 2-25th-N Northern Residential and Business Park DA 3 23 rd Cloverfield / 23 rd Street Residential DA 4 21 st Western Reidential 40.2 Total
20 Figure 3-3 Santa Monica Airport Watershed Drainage Areas 3-14
21 3.3 Land Uses, Pollutants, and BMP Opportunities and Constraints Figure 3-4 shows the Airport Watershed land uses. Figure 3-4 Santa Monica Airport Watershed Land Uses 3-15
22 Table 3-2 LAND USE BMP ASSESSMENT: ISSUES AND OPPORTUNITIES (Figures referred to follow the table) LAND USE ISSUE/CONSTRAINTS OPPORTUNITY Airport General Drainage Area 1 (DA1) - Airport Asphalt / Runways Parking Lots Majority of existing airport is impervious (Figure 3-5, 3-6, 3-7, 3-42, 3-43) Storm flows currently flood Airport Rd. Most of the Airport runs into the City of LA. Slurry Seal performed annually on taxiways. Impervious parking lots contribute pollutants into Per 1984 FAA agreement, can not remove asphalt on runway area (including taxiways and infill areas). Runoff from plane washing areas needs to be captured/treated. (Figure 3-6) Airplane tie-downs/airplane parking areas are on leased land to the owners until (Figure 3-11, 3-12 Pollutants include heavy metals, trash and debris, oil and grease, with potential for nutrients and pesticides, sediments, and oxygen demanding substances. Remove gunite area and create terracing to allow runoff to percolate in vegetation. (Figure 3-7) Culvert at end drainage point has potential to provide infiltration as treatment. (Figure 3-34, 3-35, 3-36, 3-37) Slot drains with underground treatment vault (vortex-type, separation screening units) near culvert at end drainage point. (Figure 3-38, 3-39, 3-41) Grass-crete near fire station Porous pavement, grass-crete, or underground retention at Santa Monica City College parking area (Figure 3-71, 3-72, 3-73). 3-16
23 LAND USE ISSUE/CONSTRAINTS OPPORTUNITY Hangers runoff. Metal roofs are source of pollution. Metal building/zinc roofs are a source of metals pollution. (Figure 3-28, 3-31) Insert landscaping/vegetation in parking lot medians to treat pollutants (Examples: Figure 3-15, 3-16, 3-17) Metal surfaces painted and maintained Possible use of planter boxes to capture and infiltrate roof runoff. (Figure 3-77) Outdoor Plane Parking Areas (Tie-down areas) Restaurants Fueling, Fuel storage, oil recycling Areas Airport Park The area is mostly impervious. Grease and oil from cooking, and leftover food may contribute bacterial pollutants. Oil recycling areas are provided onsite near the plane washing areas. Newly completed park provides Impervious plane parking areas contribute oil and grease pollutants. (Figure 3-10, 3-13, 3-40) Pollutants include pathogens, trash and debris, oil and grease, and oil demanding substances. Pollutants include heavy metals, organic compounds, trash and debris, and oil and grease. Adequacy of berming near oil recycling areas needs to be evaluated. (Figure 3-29, 3-30, 3-32). Plane washing areas (Figure 3-14) and gas station need to be reviewed for adequate capture. New Airport Park includes 4 infiltration basins, permeable asphalt is included in parking areas, and synthetic turf on soccer Direct runoff to slot drains with underground treatment vault (vortex-type, separation screening units). Direct runoff to slot drain to underground treatment vault. Review berming procedures for runoff. New park will serve as new infiltration site for a portion of the Airport watershed (Figure 3-74, 3-75, 3-76). 3-17
24 LAND USE ISSUE/CONSTRAINTS OPPORTUNITY Education (College building) treatment for runoff. fields. All runoff on new park site will be infiltrated, therefore this amount of treated runoff will reduce the total volume of water needed to be treated by future BMPs. Pollutants include heavy metals, trash and debris, oil and grease, with potential for nutrients and pesticides, sediments, and oxygen demanding substances. Water reuse for landscape irrigation. Landscape surrounding education buildings. 3-18
25 LAND USE ISSUE/CONSTRAINTS OPPORTUNITY Residential/ Commercial General Drainage Area 2 (DA2) Northern Residential Open Space (Clover Park) Clover Park parking lot drains to infiltration pit under park for treatment. Potential to store northern residential watershed in Clover Park (Figure 3-49, 3-50, 3-51). Education (Elementary School property) Often difficult to enter into agreement with school districts to treat offsite stormwater. Potential to store portion of northern residential watershed runoff (Figure 3-60, 3-61, 3-62, 3-63) Open Space (Recreational Fields) Currently, the field closest to the airport serves as a retention basin (Figure 3-49) during large storms when capacity in the 39 line exceeds the downstream 24 line capacity and water overflows into field. Ball fields can be used to treat, store, and reuse runoff from neighborhoods and commercial buildings (airport business park). (Figure 3-50) Major Streets (Ocean Park Blvd.) Smaller Residential Streets Residential runoff from household pollutants. Residential runoff from household pollutants. Residential runoff, including pathogens, nutrients, pesticides, sediments, trash & debris, oxygen demanding substances. (Figure 3-52, 3-53, 3-54, 3-55, 3-66, 3-67, 3-68, 3-69, 3-70) Residential runoff, including pathogens, nutrients, pesticides, sediments, trash & debris, oxygen demanding substances. (Figure 3-18, 3-24, 3-25, 3-56, 3-57, 3-58, 3-59, 3-64, 3-65) Combine traffic calming vegetation with infiltration/bioretention areas (Figure 3-21, 3-22, 3-78) Curb extensions throughout neighborhood streets. (Example: Figure 3-19, 3-20) Landscaping augmented with bioretention cells for infiltration and storm water treatment along streets and on residential properties. (Figure 3-23, 3-26) Combine traffic calming vegetation with infiltration/bioretention areas (Figure 3-21, 3-22, 3-78) Curb extensions throughout neighborhood streets. 3-19
26 LAND USE ISSUE/CONSTRAINTS OPPORTUNITY (Example: Figure 3-19, 3-20) Single-family residential Multi-family Neighborhoods adjacent to Ocean Park Blvd Education (School building) Residential runoff from household pollutants. Residential runoff from household pollutants. Pollutants include pathogens, nutrients, pesticides, sediments, trash & debris, oxygen demanding substances. Pollutants include nutrients, pesticides, sediments, trash & debris, with potential for pathogens, oxygen demanding substances, oil & grease. There may be limitations to diverting stormwater runoff to school areas due to human health concerns for students. Landscaping augmented with bioretention cells for infiltration and storm water treatment along streets and on residential properties. (Figure 3-23, 3-26) Curb extensions throughout neighborhood streets. (Example: Figure 3-19, 3-20) Landscaping augmented with bioretention cells for infiltration and storm water treatment along streets and on residential properties. (Figure 3-23, 3-26) Combine traffic calming vegetation with infiltration/bioretention areas (Figure 3-21, 3-22) Curb extensions throughout neighborhood streets. (Example: Figure 3-19, 3-20) Potential to use school fields to store and treat water from watershed. (Figure 3-60, 3-61, 3-62, 3-63) Commercial (Airport Business Park) Pollutants include heavy metals, trash and debris, oil and grease, with potential for nutrients and pesticides, sediments, and oxygen demanding substances. Connect roof runoff to landscaping and planter boxes. Residential General Drainage Area 3 and 4 (DA3/4) Southern and Western Residential Single-family residential Residential Lots in Single-family Areas Pollutants include pathogens, nutrients, pesticides, sediments, trash & debris, oxygen demanding substances. Area is hilly and may not be conducive to Landscaping augmented with bioretention cells for infiltration and storm water treatment along streets and on residential properties. (Figure 3-23, 3-26) Combine traffic calming vegetation with 3-20
27 LAND USE ISSUE/CONSTRAINTS OPPORTUNITY Multi-family Residential Multi-family Neighborhoods adjacent to Ocean Park Blvd treatment approaches infiltration/bioretention areas (Figure 3-21, 3-22, 3-78) Pollutants include nutrients, pesticides, Landscaping augmented with bioretention cells for sediments, trash & debris, with potential infiltration and storm water treatment along streets for pathogens, oxygen demanding and on residential properties. (Figure 3-23, 3-26) substances, oil & grease. Combine traffic calming vegetation with infiltration/bioretention areas (Figure 3-21, 3-22, 3-78) 3-21
28 LAND USE ISSUE/CONSTRAINTS OPPORTUNITY Other General Other Open Space Future Enhancements/ Alternatives Penmar Park and Golf Course Golf Course is owned by the City of Los Angeles so would need to coordinate potential BMPs included in the City of LA Penmar Water Quality Improvement and Runoff Reuse Project Concept Report. (Figure 3-33, 3-46, 3-47) Funding is a constraint. Health standards and water quality requirements for urban runoff treatment and reuse are currently at Title 22 standards, however alternative requirements may be proposed in the future. The City of Los Angeles has completed a concept report for Penmar Golf Course that includes a project that involves infiltration basins in Golf Course and the adjacent ball fields. The project may also include an impermeable pond for retention on Golf Course and water reuse. Runoff from the Airport watershed may be directed to the Golf Course for treatment (Figure 3-45, 3-47, 3-48). Coat roofs and downspouts instead of using zinc/copper for new development/redevelopment. Recycled Water used for toilets/urinals may be implemented if meets Title 22 regulations. Proposed underground storage of storm water may be used by fire department for fire fighting. 3-22
29 Figure 3-5 Figure
30 Figure 3-7 Figure
31 Figure 3-9 Figure
32 Figure 3-11 Figure
33 Figure 3-13 Figure
34 Figure 3-15 Possible location for biotention in The Business Park Figure 3-16 Possible location for biotention in The Business Park 3-28
35 Figure 3-17 Possible location for biotention in The Business Park Figure
36 Figure 3-19 Figure
37 Figure
38 Figure
39 Figure 3-23 Figure
40 Figure 3-25 Figure
41 Figure 3-27 Figure
42 Figure 3-29 Figure
43 Figure 3-31 Figure
44 Figure 3-33 Figure
45 Figure 3-35 Figure
46 Figure 3-37 Figure
47 Figure 3-39 Figure 3-40 Airport Avenue landscaping 3-41
48 Figure 3-41 Figure
49 Figure 3-43 Figure
50 Figure 3-45 Figure
51 Figure 3-47 Figure
52 Figure 3-49 Figure
53 Figure 3-51 Figure
54 Figure 3-53 Figure
55 Figure 3-55 Grant Elementary School on Pearl Street Figure rd and Pearl Street catch basin, facing west on 23 rd Street 3-49
56 Figure 3-57 Pearl at 31 st Street Figure 3-58 Pearl at 31 st Street 3-50
57 Figure 3-59 Figure
58 Figure 3-61 Figure
59 Figure 3-63 Figure
60 Figure 3-65 Figure
61 Figure 3-67 Santa Monica College Parking Lot Figure 3-68 Santa Monica College Parking Lot facing southwest. 3-55
62 Figure 3-69 Figure
63 Figure
64 Figure 3-72 Proposed locations for traffic calming landscaping 3-58
65 4.0 BMPs Evaluated 4.1 Stakeholder Workshop A workshop was held on June 20, 2007 convened by the City. At the workshop, the information included in Appendix E was presented. Based on feedback from the workshop a shortlist of BMPs was chosen for further analysis. These are described in section 4.2 below. 4.2 BMP List for Further Analysis A total of 10 BMPs was identified in this process that can be categorized into the following areas: Airport Property: 1. Airport Avenue Landscaping 2. SMC Parking Lot Underground Retention 3. Zinc Hangar Runoff Management Residential Area: 4. Traffic Calming Landscape Modification 5. Pearl Street Rain Gardens 6. Grant Elementary School Underground Retention 7. Clover Park Underground Retention 8. Pico Boulevard Porous Pavement Business Park: 9. Business Park Bioretention Retrofit Other: 10. Penmar Water Quality Improvement and Runoff Reuse Water quality calculations were performed based on the City of Los Angeles SUSMP (Standard Urban Stormwater Management Plan) methodology to provide design guidance on BMPs. This method determines the peak flow (Q PM ) or stormwater volume (V PM ) that should be mitigated as a result of ¾ of rainfall. Water quality calculations are summarized in Table 4-1 below. 4-59
66 Table 4-1 Water Quality Calculations Summary Sub-area Q PM [cfs] V PM [cf] WASE [cf] TMDL [cf] Drains to 21st ,694 36,565 23,847 Penmar Pk 23rd , ,225 96,016 Penmar Pk 25th-N , , ,589 Clover Pk to Rose 25th-S , , ,292 Airport Ave to Rose TOTAL 935, , ,745 Penmar Park ,403 22,542 14,702 To Rose See Appendix for Water Quality Calculations. 4-60
67 4.3 Worksheets and Photos Feasibility at a Planning Scale AIRPORT PROPERTY Airport Avenue Landscaping This proposed BMP will remove gunite along Airport Avenue and replace it with landscaping and trees. Due to the long length of the street, vegetated swales may be utilized within landscaping. Airport Avenue drains from east to west and there is an existing storm drain on Dewey Street. Targeted pollutants are sediment, oil and grease, and metals. There are no major construction constraints other than demolition, possible utility relocation, earthwork, landscaping, and drainage piping. The cost of this BMP is estimated to be roughly $440,000. Figure 4-1 Airport Avenue Landscaping 4-61
68 SMC Parking Lot Underground Retention As shown in Figure 4-2, this proposed BMP will build an underground extended retention basin (ERB) with pretreatment (for proprietary trash, suspended solids, oils, and etc.) underneath an existing Santa Monica College parking lot adjacent to the Airport Avenue. If soil conditions allow, this EDB would have a pervious membrane to allow infiltration. This BMP would collect drainage from other parking lots to the east and possibly from Airport Avenue. Low-flow runoff should be treated via infiltration, and high-flow runoff should be bypassed to a nearby storm drain system on Dewey Street or to an airport runway storm drain system which eventually drains to the Dewey Street storm drain. Targeted pollutants are nutrients, trash and debris, oxygen demanding substances, oils and grease, bacteria and viruses, and metals. There are no major construction constraints other than demolition, installation of BMPs, earthwork, paving, and drainage piping. The cost of this BMP is estimated to be roughly $1,380,000. Figure 4-2 SMC Parking Lot Underground Retention 4-62
69 Zinc Hangar Management As shown in Figure 4-3, this proposed BMP will build planter boxes along the sides of airport hangars to treat its roof runoff. The planter boxes should be designed to treat the low-flow runoff. High-flow runoff should overflow onto the adjacent areas as in the existing condition. Targeted pollutants are metals. There are no major construction constraints other than earthwork, landscaping, and if necessary, drainage piping. The cost of this BMP is estimated to be roughly $75,000. Figure 4-3 Zinc Hangar Runoff Management 4-63
70 4.3.2 RESIDENTIAL AREA Traffic Calming Landscape Modification As shown in Figure 4-4, this proposed BMP will modify existing traffic calming devices into street rain gardens. The existing landscape will be sunken into the ground to provide storage for water quality treatment. Curb cuts should be made so that the street surface flow would be directed into the rain gardens. The depth of depression for each rain garden should be determined by the water quality mitigation volume (V PM ) of its tributary area. There are total of nine possible locations identified in Figure 4-4. Targeted pollutants are sediment, oil and grease, and metals. There are no major construction constraints other than earthwork, landscaping, and if necessary, drainage piping and relocation of existing utilities. The cost of this BMP (for all nine locations) is estimated to be roughly $450,
71 Figure 4-4 Traffic Calming Landscape Modification (Yellow Highlighted Areas = Possible BMP Locations) Pearl Street Rain Gardens This proposed BMP will build two new street rain gardens along Pearl Street. Pearl Street is one of the major residential streets that carry relatively large amounts of surface runoff due to the lack of storm drain systems within the street. Possible BMP locations should 4-65
72 be identified so that the proposed location is strategic from a drainage point of view (i.e. downstream portion of street where surface flow is most concentrated) and is acceptable in terms of traffic and safety. Targeted pollutants are sediment, oil and grease, and metals. There are no major construction constraints other than earthwork, possible utility relocation, landscaping, and if necessary, drainage piping. The cost of this BMP is estimated to be roughly $200, Grant Elementary School Underground Retention As shown in Figure 4-5, this proposed BMP will build an underground retention basin with pretreatment (for proprietary trash, suspended solids, oils, and etc.) underneath an existing playing field at Grant Elementary School. The school is located near the upstream end of the Airport Watershed. Also, there is an existing storm drain system that drains south along the eastern property of the school site. Drainage from this storm drain should be diverted to a pretreatment device before discharging into the proposed underground retention basin. Low-flow runoff should be treated via infiltration; highflow runoff should be bypassed to the storm drain on 25 th Street. Targeted pollutants are nutrients, trash and debris, oxygen demanding substances, oils and grease, bacteria and viruses, and metals. There are no major construction constraints other than demolition, earthwork, repaving, and drainage piping. School buildings may cause some site constraints when diverting drainage from the adjacent existing storm drain system. The cost of this BMP is estimated to be roughly $795,000. Figure 4-5 Grant Elementary School Underground Retention 4-66
73 Clover Park Underground Retention As shown in Figure 4-6, this proposed BMP will build an underground retention basin (ERB) with pretreatment (for proprietary trash, suspended solids, oils, and etc.) underneath existing baseball fields at Clover Park. There is an existing storm drain system adjacent to the park on 25 th Street draining from north to south. Its drainage areas include the park itself, drainage on 25 th Street, and portions of The Business Park to the northeast and airport runway to the east. The existing storm drain on the 25 th Street should be diverted to a pretreatment device before discharging into the proposed underground retention basin. A soils analysis is recommended to determine the soil condition and infiltration capacity of Clover Park. Additionally, storm water stored in the underground retention basin may be reused to complement the park s irrigation demands. Targeted pollutants are nutrients, trash and debris, oxygen demanding substances, oils and grease, bacteria and viruses, and metals. There are no major construction constraints other than installation of BMPs, earthwork, possible utility relocation, storm drain connection, and drainage piping. The cost of this BMP is estimated to be roughly $2,155,000. Figure 4-6 Clover Park Underground Retention 4-67
74 Pico Boulevard Porous Pavement This proposed BMP will repave pedestrian crossings at one or more of the intersections along Pico Boulevard with porous pavement. Along Pico Boulevard, stormwater runoff flows from east to west at the sides of the street via gutter usually. Thus, porous pavements at the pedestrian crossings would be ineffective since it would have minimal contact area with the runoff. Targeted pollutants are sediment, oils and grease, and metals. There are no major construction constraints other than paving. The cost of this BMP is estimated to be roughly $180,
75 4.3.3 BUSINESS PARK Business Park Bioretention Retrofit As shown in Figure 4-7, this proposed BMP will retrofit the existing landscaping within The Business Park with bio-swales and rain gardens. These BMPs should be designed to treat the low-flow volumes based on its tributary areas. High-flow runoff can overflow onto the parking lots as in the existing condition. Targeted pollutants are sediment, oil and grease, and metals. There are no construction constraints other than demolition, earthwork, landscaping, and if necessary, drainage piping. The cost of this BMP is estimated to be roughly $1,250,000. Figure 4-7 Business Park Bioretention Retrofit 4-69
76 4.3.4 OTHER Penmar Park Water Quality Improvement & Runoff Reuse As shown in Figure 4-8, this proposed project will implement underground retention, infiltration, and possible reuse of storm water to address sub-regional water quality issues. This sub-regional BMP is expected to treat runoff from both the cities of Los Angeles and Santa Monica. Refer to the Penmar Water Quality Improvement and Runoff Reuse Project prepared by the City of Los Angeles and the City of Santa Monica, dated March 2007, for detailed project information and cost estimate. Figure 4-8 Penmar Park Water Quality Improvement & Runoff Reuse 4-70
77 4.4 Amounts and values of Avoided Potable Water Use In the scenarios above, avoided potable water use as a result of reuse occurs within the City of Los Angeles at Penmar Golf Course. As a result, no savings in dollars to the City of Santa Monica will occur. 5.0 Next Steps 5.1 Capital Improvement Plan Based on costs of BMPs, work with City staff to allocate costs by fiscal year. 6.0 Conclusion The intent of this report is to identify possible BMPs that will help improve the overall storm water quality of the Airport Watershed in the City of Santa Monica. Total of ten BMPs were identified and analyzed in terms of construction constraints and costs, pollutants targeted, and site feasibility at a planning level. A detailed engineering analysis is recommended for prospective BMPs to determine design-specific information. A cost-benefit analysis should be conducted for the proposed BMPs to help determine priority for each of the BMPs. The cost-benefit analysis should take into consideration, at the least, the drainage area, capacity, and cost of the BMPs. The prioritizing of BMPs should consider, at the least, the results of the cost-benefit analysis, existing BMPs, financial and timing logistics, and the City s needs. It is important to note that the entire Airport Watershed is one of the tributary areas of the Penmar Water Quality Improvement and Runoff Reuse Project, which is a sub-regional storm water quality improvement project. Thus, the Penmar Project is designed to mitigate much of the Airport Watershed s storm water runoff (V PM ). However, implementation of the recommended BMPs would improve the storm water quality closer to the pollutant source. Moreover, implementation of the recommended BMPs would likely reduce the design capacity and construction cost of the Penmar Project. Therefore, additional study is recommended to analyze the impacts of proposed BMPs on the design and cost of the Penmar Project. 6-71
78 APPENDIX A Technical Memorandum 6-1
79 APPENDIX B Penmar Water Quality Improvement and Runoff Project
80 APPENDIX C County Department of Health Services Health Standards
81 APPENDIX D Recommended BMPs Design Performance
82 APPENDIX E Workshop Presentation June 20, 2007
83
DC STORMWATER PLAN CONSOLIDATED TOTAL MAXIMUM DAILY LOAD (TDML) IMPLEMENTATION PLAN
DC STORMWATER PLAN CONSOLIDATED TOTAL MAXIMUM DAILY LOAD (TDML) IMPLEMENTATION PLAN CONTENTS Introduction 1 The Challenge 5 The Solution 7 Tracking Progress 11 What can you do? 15 INTRODUCTION The DC Stormwater
More information11. Public Utilities. Key Terminology: OVERVIEW STORMWATER MANAGEMENT WATERSHED MANAGEMENT ORGANIZATIONS AND COMMISSIONS. Inventory and Analysis
Inventory and Analysis 11. Public Utilities Urbanized (drainage): Defined as an area where natural soils, waterways, and environmental functions are replaced with impervious surfaces (roads, parking lots,
More informationBest Management Practices for Stormwater Quality Treatment in Urban Settings. Lower Mississippi River WMO September 2017
Best Management Practices for Stormwater Quality Treatment in Urban Settings Lower Mississippi River WMO September 2017 Stormwater 101 Impervious surfaces (pavement, parking lots, etc.): quickly produce
More informationStormwater Bio-Infiltration Pilot Project Concept Proposal Submitted by
Concept Proposal Submitted by Public Works Department 1947 Center Street, Fourth Floor Berkeley, CA 94704 December 17, 2009 Executive Summary The s Public Works Department submits this concept proposal
More informationStakeholder Meeting #1
Santa Clara Basin Stormwater Resource Plan Stakeholder Meeting #1 October 4, 2017 Jill Bicknell, P.E. SCVURPPP Presentation Overview Background SCVURPPP Green Infrastructure Stormwater Resource Plan (SWRP)
More informationG. HYDROLOGY Existing Conditions
G. HYDROLOGY Existing Conditions Surface Water Runoff This section is based on the hydrology and drainage analysis for the proposed Project, which was prepared by KPFF Consulting Engineers and is attached
More informationStormwater Management in Your Backyard: Stormwater 101
Stormwater Management in Your Backyard: Stormwater 101 Gregory Rusciano Program Associate, Water Resources Rutgers Cooperative Extension New Jersey Sea Grant Extension Program How much water do we have?
More informationCity of Texarkana, Arkansas. Storm Water Pollution
City of Texarkana, Arkansas Storm Water Pollution STORM WATER GUIDE What is Storm Water Pollution? Stormwater can provide a toxic discharge which can enter into a lake, river or coastal water system. As
More informationORDINANCE # 854. Stormwater Management / Operation and Maintenance Requirements
ORDINANCE # 854 Stormwater Management / Operation and Maintenance Requirements Section 1. Purpose and Authority In accordance with the provisions of Chapters 98, 124, 126, 440, 444, and 446h of the General
More informationMODEL STORMWATER MANAGEMENT GUIDELINES FOR INFRASTRUCTURE NEW DEVELOPMENT AND REDEVELOPMENT
SALMON-SAFE INC. MODEL STORMWATER MANAGEMENT GUIDELINES FOR INFRASTRUCTURE NEW DEVELOPMENT AND REDEVELOPMENT MAY 2018 Introduction Polluted stormwater is the largest threat to the health of the Pacific
More informationIV.E. HYDROLOGY AND WATER QUALITY
IV.E. HYDROLOGY AND WATER QUALITY The following section presents the information provided in the hydrology report prepared by Sukow Engineering. Supporting hydrology data from this report is included in
More informationTABLE B.3 - STORMWATER BMP POLLUTANT REMOVAL EFFICIENCIES
BMPS DESCRIPTION p p p p TSS TP Sol P TN Stormwater Ponds**, 8 Stormwater Wetland** and extended detention, and some elements of a shallow marsh equivalent capable of treating the full water quality volume.
More informationStormwater BMP Maintenance
Stormwater BMP Maintenance Background and Definitions What is Stormwater Runoff? Stormwater Stormwater is the result of precipitation that flows overland to streams and other bodies of water Stormwater
More informationLow Impact Development and Municipal Stormwater Permits in Southern California: What, Where, Why, and How
Low Impact Development and Municipal Stormwater Permits in Southern California: What, Where, Why, and How Matt A. Yeager, D.Env San Bernardino County Stormwater Program Coastal Coalition April 24, 2008
More informationTMDL Report for Chesapeake Bay Shellfish Waters: Ware Creek, Taskinas Creek, and Skimino Creek Bacterial Impairments (VADEQ, 2010)
As part of a long term commitment to environmental stewardship, James City County volunteers and staff have been gathering information about stream health throughout the County since 2008. The goal of
More informationATTACHMENT 4 Section Project Status Quarterly Report - Dec 31, 2015 Measure V - Clean Beaches and Ocean Parcel Tax
ATTACHMENT 4 Section 3.0 - Project Status Quarterly Report - Dec 31, 2015 Completed Projects Description Bicknell Avenue Green Street Pier Storm Drain Improvement Pier Water Quality Improvement Permeable
More informationSustainable Water Resource Practices
Sustainable Water Resource Practices This section is related to and shoudl be read in conjunction with the Land Use Element, and Conservation Element. Implementing sustainable water resource practices
More informationMODEL STORMWATER MANAGEMENT GUIDELINES FOR ULTRA-URBAN REDEVELOPMENT
SALMON-SAFE INC. MODEL STORMWATER MANAGEMENT GUIDELINES FOR ULTRA-URBAN REDEVELOPMENT MAY 2018 Introduction Polluted stormwater is the largest threat to the health of the Pacific Northwest s urban watersheds.
More informationCHAPTER 7: guidance. categories: Pollutant Removal. Jordan Lake watershed) Cisterns. Bioretention Areas. Green Roofs. Dry. Proprietary Devices
CHAPTER 7: TOOLBOXES A. Water Quality BMP Toolbox The Water Quality BMP Toolbox is intended for use by Town off Cary staff and citizens for guidance regarding implementation of traditional, non-traditional,
More informationInfiltration Trench Factsheet
Infiltration Trench Factsheet Infiltration Trench is a practice that provides temporary storage of runoff using the void spaces within the soil/sand/gravel mixture that is used to backfill the trench for
More informationIntended users: City and County public works Young engineers Developers Public officials and other non-engineers
1 2 3 4 Intended users: City and County public works Young engineers Developers Public officials and other non-engineers The Decision Tree distills information from many manuals and sources into one spot,
More informationDesign Handbook. Low Impact Development Best Management Practices
Design Handbook for Low Impact Development Best Management Practices Prepared by: 9/2011 Riverside County Flood Control and Water Conservation District 1995 Market Street Riverside, CA 92501 TABLE OF CONTENTS
More informationProject Priority List scoring worksheet - stormwater Guidance document
www.pca.state.mn.us Project Priority List scoring worksheet - stormwater Guidance document PLEASE NOTE: THE MINNESOTA STATE FISCAL YEAR IS FROM JULY 1 JUNE 30 The first step towards receiving either a
More information10/16/2013. The Big Picture of LID and Green Infrastructure. Learning Objectives
Low impact development (LID) the basic idea behind LID is to manage stormwater in a way that imitates the natural hydrology of a site. Details Matter Selection, Design, and Implementation of Low Impact
More informationNonpoint Source Storm Water Management Plan
Nonpoint Source Storm Water Management Plan Christine Pomeroy Dept. of Civil & Environnmental Eng. University of Utah Carl Adams Watershed Protection Utah Division of Water Quality Definitions Nonpoint
More informationHoosier Creek Watershed All of Ely drains into Hoosier Creek, which runs north to south along the west side of Ely. Hoosier Creek, Hydrologic Unit Cod
Hoosier Creek Watershed All of Ely drains into Hoosier Creek, which runs north to south along the west side of Ely. Hoosier Creek, Hydrologic Unit Code (HUC) 8 07080208, drains into the Coralville Reservoir,
More informationNON-PRIORITY PROJECT WATER QUALITY PLAN (NPP)
NON-PRIORITY PROJECT WATER QUALITY PLAN (NPP) For: (Insert Project Name) (Site Address or Tract/Lot Number) Prepared for: (Insert Owner/Developer Name) (Insert Address) (Insert City, State, ZIP) (Insert
More informationLatest MWELO Updates + Storm Water Requirements Kliffs Notes New Storm Water Permit and BMP Design Manual: Impacts on Future Development Presented
Latest MWELO Updates + Storm Water Requirements Kliffs Notes New Storm Water Permit and BMP Design Manual: Impacts on Future Development Presented by: Kenneth Kozlik, Fuscoe Engineering San San Diego Diego
More informationDESIGN DEVELOPMENT HYDROLOGY REPORT & LOW IMPACT DEVELOPMENT PLAN (LID PLAN)
DESIGN DEVELOPMENT HYDROLOGY REPORT & LOW IMPACT DEVELOPMENT PLAN ( PLAN) ALAMITOS BEACH CONCESSION BUILDING 780 E. SHORELINE DRIVE LONG BEACH, CALIFORNIA Prepared For: Long Beach Public Works 333 W. Ocean
More informationSTORMWATER MANAGEMENT DIVISION
STORMWATER MANAGEMENT DIVISION Western Branch Restoration Plan Public Meeting January 28, 2019 Welcome from Jerry Maldonado Purpose of Meeting Review why watershed restoration plans are needed in Prince
More informationSTORMWATER MANAGEMENT AND IMPAIRED WATERS. Eric H. Livingston Watershed Management Services, LLC Crawfordville, FL
STORMWATER MANAGEMENT AND IMPAIRED WATERS Eric H. Livingston Watershed Management Services, LLC Crawfordville, FL Impaired Waters Not meet their WQS Loss of designated uses TOTAL MAXIMUM DAILY LOADS Section
More informationPRELIMINARY DRAINAGE STUDY
PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,
More informationHome Remodeling Projects
Should your project require a Standard Urban Stormwater Mitigation Plan (SUSMP), please see the City of Pomona s Standard Urban Stormwater Mitigation Plan (SUSMP) Pamphlet Best Management Practices For
More information7 DEVELOPMENT PLANNING & MODEL WATER QUALITY MANAGEMENT PLAN (WQMP)
7 DEVELOPMENT PLANNING & MODEL WATER QUALITY MANAGEMENT PLAN (WQMP) 7.1 INTRODUCTION The Development Planning and Model Water Quality Management Plan (WQMP) Section of the City s LIP has been developed
More informationPROTECTING OUR WATERWAYS: STORMWATER POLLUTION REDUCTION EFFORTS
PROTECTING OUR WATERWAYS: STORMWATER POLLUTION REDUCTION EFFORTS Public Information Meeting ~ May 2, 2018 Public Works Stormwater Management Division OVERVIEW Surface Water Quality Protection Municipal
More informationMCM 5 - POST CONSTRUCTION STORM WATER MANAGEMENT
MCM 5 - POST CONSTRUCTION STORM WATER MANAGEMENT POST CONSTRUCTION STORM WATER MANAGEMENT Minimum Control Measure 5 5.1 INTRODUCTION Riverdale City has committed to Joint Permit with Weber County to meet
More informationPRIORITY WATER QUALITY MANAGEMENT PLAN (WQMP)
PRIORITY WATER QUALITY MANAGEMENT PLAN (WQMP) For: () (Site address or tract/lot number) Prepared for: (Insert Owner/Developer Name) (Insert Address) (Insert City, State, ZIP) (Insert Telephone) Prepared
More informationIV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY
IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to
More information3F. Hydrology and Water Quality
This section provides an analysis of potential hydrological and water quality impacts associated with implementation of the proposed project. The section also evaluates and describes the potential impacts
More informationExisting Conditions and Environmental Consequences Water Quality
3.6 3.6.1 HOW IS WATER QUALITY ASSESSED? The Clean Water Act (CWA) of 1972 requires that each state set water quality standards for all contaminants in surface waters. These standards are typically based
More informationCORBIN AND NORDHOFF IV. ENVIRONMENTAL IMPACT ANALYSIS ENV EIR F. HYDROLOGY
F. HYDROLOGY ENVIRONMENTAL SETTING Project Site The Project Site is located at 19601 Nordhoff Street in the Chatsworth area of the City of Los Angeles, California, within the Chatsworth - Porter Ranch
More informationE. STORMWATER MANAGEMENT
E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson
More informationThe Status of Pompeston Creek, : From Data to Action. Pompeston Creek Watershed Association
Pompeston Creek Watershed Association P.O. Box 2883 Cinnaminson, NJ 08077 (856) 235-9204 www.pompestoncreek.org The Status of Pompeston Creek, 1998-2008: From Data to Action Pompeston Creek Watershed Association
More informationContractors, Illicit Discharges, & Best Management Practices. Chris Allen Stormwater Inspector
Contractors, Illicit Discharges, & Best Management Practices Chris Allen Stormwater Inspector What is an Illicit Discharge? Georgetown County Stormwater Ordinance defines an Illicit Discharge as: Any activity
More informationJune 27, 2012 Holly Galavotti U.S. EPA
June 27, 2012 Holly Galavotti U.S. EPA Urban stormwater is a leading source of water quality impairment Urban stormwater identified as source of impairment (2004 WQ Report) 22,559 miles of impaired rivers
More informationIV. ENVIRONMENTAL IMPACT ANALYSIS D. DRAINAGE AND SURFACE WATER QUALITY
IV. ENVIRONMENTAL IMPACT ANALYSIS D. DRAINAGE AND SURFACE WATER QUALITY The analysis of drainage impacts included in this section is based on the Storm Drainage Environmental Impact Report prepared by
More informationMS4 Programs: Quality, the Other Stormwater Q. Dan Bounds, PE, D.WRE IAFSM March 9, 2017
MS4 Programs: Quality, the Other Stormwater Q Dan Bounds, PE, D.WRE IAFSM March 9, 2017 MS4 Rule and Regulations MS4 Municipal Separate Storm Sewer System A conveyance or system of conveyances (catch basins,
More informationMunicipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No.
Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates 2005 VNH File No. 35317-210-21 Table of Contents Introduction... 3 Goals... 3 Storm water Discussion...
More informationWater Resources Management Plan Appendix B
B u r n s v i l l e M i n n e s o t a Water Resources Management Plan Appendix B Appendix B Page B-1 Burnsville, Minnesota STORM WATER LOW-IMPACT DEVELOPMENT GUIDE MANUAL SHORT ELLIOTT HENDRICKSON INC.
More informationStorm Water - Priority Development Project Submittal
Storm Water - Priority Development Project Submittal Project Summary Information Project Name Project Address Form I-2a Assessor's Parcel Number(s) Permit Application Number Project Watershed (Hydrologic
More informationNonpoint Source Pollution A Challenge to Control
Nonpoint Source Pollution A Challenge to Control Connecticut Envirothon Aquatics Workshop January 14, 2017 Presented by Denise Savageau Conservation Director, Town of Greenwich Point Source Pollution is
More informationCENTRALIZED BMPS TYPICALLY PUBLICLY OWNED & MAINTAINED BMPS, TREATING A LARGE (>20 ACRES) URBAN DRAINAGE WITH MULTIPLE LAND
BMP RAM BMP Type Definitions 1 CENTRALIZED BMPS TYPICALLY PUBLICLY OWNED & MAINTAINED BMPS, TREATING A LARGE (>20 ACRES) URBAN DRAINAGE WITH MULTIPLE LAND USES AND OWNERSHIP STRUCTURAL BMP TYPE OTHER NAMES
More informationStreamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators
Page 1 of 5 STREAMLINES A Newsletter for North Carolina Water Supply Watershed Administrators Volume 2, Number 2 May 1997 Non-Point Source (NPS) Pollution This issue of Streamlines provides basic information
More informationWELCOME. Eastern Subwatersheds Stormwater Management Retrofit Study. Online Information Session
WELCOME Eastern Subwatersheds Stormwater Management Retrofit Study Online Information Session July 31 to Septemberember 19, 2014 1 Eastern Subwatersheds Stormwater Management Retrofit Study This study
More informationInnovation In Stormwater Management
Innovation In Stormwater Management DETENTION/RETENTION PERMEABLE SOLUTIONS HARVESTING/REUSE BIORETENTION/BIOFILTRATION MEDIA FILTRATION HYDRODYNAMIC SEPARATION INLET FILTRATION TRASH CAPTURE Oldcastle
More informationALMY POND TMDL MANAGEMENT PLAN
ALMY POND TMDL MANAGEMENT PLAN PUBLIC WORKSHOP Presented by: City of Newport Department of Utilities And Pare Corporation May 7, 2014 Presentation Overview Introduction to Almy Pond Project Introduction
More informationNORTH SANTA MONICA BAY COASTAL WATERSHEDS ENHANCED WATERSHED MANAGEMENT PROGRAM
NORTH SANTA MONICA BAY COASTAL WATERSHEDS ENHANCED WATERSHED MANAGEMENT PROGRAM Public Workshop #2 King Gillette Ranch, Calabasas November 13, 2014 NSMBCW WATERSHED ASBS = Area of Special Biological Significance
More informationAPPENDIX I WATER QUALITY FACTORS FOR FEE CREDIT CALCULATIONS
APPENDIX I WATER QUALITY FACTORS FOR FEE CREDIT CALCULATIONS January 2018 Storm Water Management Design Manual Appendix I-1 I.1. Purpose There are a wide variety of water quality best management practices
More informationBackground / Regulatory Requirements
Chapter 2 Background / Regulatory Requirements This Chapter summarizes the impacts of development on stormwater quality and quantity and explains the postconstruction stormwater control requirements for
More informationAPPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary
APPENDIX J-3 Orcem Stormwater Management and Treatment Facilities Design Summary Stormwater Management & Treatment Facilities Design Summary INTRODUCTION KPFF Consulting Engineers has compiled this report
More informationCounty of Los Angeles - Department of Public Works
GENERAL PROJECT INFORMATION County of Los Angeles - Department of Public Works Building and Safety/Land Development Division LOW IMPACT DEVELOPMENT REVIEW SHEET (2017 Los Angeles County Building Code,
More informationPractices that capture and temporarily store the WQ v before allowing it to infiltrate into the soil.
Chapter 5: Acceptable Stormwater Management Practices (SMPs) This section presents a list of practices that are acceptable for water quality treatment. The practices on this list are selected based on
More information3.2 INFILTRATION TRENCH
3.2 INFILTRATION TRENCH Type of BMP Priority Level Treatment Mechanisms Infiltration Rate Range Maximum Drainage Area LID Infiltration Priority 1 Full Retention Infiltration, Evapotranspiration (when vegetated),
More informationCity of Santa Clarita Project-Specific Urban Stormwater Mitigation Plan
Project-Specific Urban Stormwater Mitigation Plan The purpose of this checklist is to assist developers and project engineers in the preparation of a uniform and comprehensive Project-Specific Urban Stormwater
More informationAppendix O: Potential Strategies
Appendix O: Potential Strategies APPENDIX O - POTENTIAL STRATEGIES As required by Provision B.2.e, the Permittees must identify potential strategies that may result in improvements to water quality in
More informationStormwater Management Fact Sheet: Porous Pavement
Stormwater Management Fact Sheet: Porous Pavement Description Porous pavement is a permeable pavement surface with an underlying stone reservoir that temporarily stores surface runoff before infiltrating
More informationA Case for the Design and Modeling of BMP Infiltration and LID Techniques. By: Bob Murdock
A Case for the Design and Modeling of BMP Infiltration and LID Techniques 2009 IAFSM Annual Conference 2009 IAFSM Annual Conference By: Bob Murdock Presentation Outline 1. Runoff Reduction (RR) and Low
More informationAPPENDIX C. RECOMMENDED BMPs for SITE PLANNING, POST-CONSTRUCTION, and REDEVELOPMENT/INFILL
APPENDIX C RECOMMENDED BMPs for SITE PLANNING, POST-CONSTRUCTION, and REDEVELOPMENT/INFILL Site Planning BMPs Minimize Storm Water Runoff Pervious Drainage System Reduce Area of Impervious Surface Site
More informationA Primer on Stormwater Management, your Facility and the Chesapeake Bay. Tom Schueler Chesapeake Stormwater Network June
A Primer on Stormwater Management, your Facility and the Chesapeake Bay Tom Schueler Chesapeake Stormwater Network June 5. 2017 Key Themes Why do we need to be concerned about Stormwater? What are all
More informationBUREAU OF CLEAN WATER
COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF CLEAN WATER NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) STORMWATER DISCHARGES FROM SMALL MUNICIPAL SEPARATE STORM
More informationInfiltration Guidelines
Appendix E Infiltration Guidelines As a stormwater management method, infiltration means retaining or detaining water within soils to reduce runoff. Infiltration can be a cost-effective method to manage
More informationMunicipal Regional Stormwater Permit Provision C.3 Model Conditions of Approval
County Government Center P 650.599.1514 555 County Center, 5 th Floor F 650.363.7882 Redwood City, CA 94063 flowstobay.com ATTACHMENT 1 Municipal Regional Stormwater Permit Provision C.3 Model Conditions
More informationPost-Development Stormwater Runoff Performance Standards
Post-Development Stormwater Runoff Performance Standards December 9, 2014 Topics Why performance standards? What practices/requirements are in effect in other States? The Workgroup s preliminary and final
More informationPart 2.0 Non-Numeric Effluent Limitations
2017 NH Small MS4 General Permit Page 50 of 67 report on its findings and progress towards making the practices allowable. (Information available at: http://www.epa.gov/region1/npdes/stormwater/assets/pdfs/addressingbarrier2lid.pdf
More information4. Ponds and infiltration BMPs can achieve 60 to 100% removal efficiencies for sediment.
Landscape BMPs For the purposes of this project, preventive measures have been categorized into two categories: landscape BMPs and source prevention BMPs. Landscape BMPs includes both vegetative practices
More informationPOST-CONSTRUCTION STORMWATER MANAGEMENT FOR EROSION CONTROL PROFESSIONALS
POST-CONSTRUCTION STORMWATER MANAGEMENT FOR EROSION CONTROL PROFESSIONALS Shannon Tillack, P.E., CPESC Wright Water Engineers, Inc. Why do we care about stormwater quality? Board 1 Recreational Uses Slide
More informationGUIDELINES FOR STORMWATER BACTERIA REDUCTIONS THROUGH BMP IMPLEMENTATION NY/NJ HARBOR TMDL DEVELOPMENT
GUIDELINES FOR STORMWATER BACTERIA REDUCTIONS THROUGH BMP IMPLEMENTATION NY/NJ HARBOR TMDL DEVELOPMENT Elevated bacteria in stormwater runoff in urban areas are well documented by many researchers. Monitoring
More informationMarina del Rey Enhanced Watershed Management Program Plan
Marina del Rey Enhanced Watershed Management Program Plan Prepared For: Marina del Rey Enhanced Watershed Management Program Agencies County of Los Angeles Los Angeles County Flood Control District City
More informationProject Name: Add a unique name that appropriately identifies the submission
PTAPP Online Municipal Tracking Tool Instructions Project Name: Add a unique name that appropriately identifies the submission Municipal Project: Check this box if the project is part of municipal efforts
More informationSewage Overflows in the Detroit River. Photo Credit: Bob Burns, Detroit Riverkeeper
Sewage Overflows in the Detroit River Photo Credit: Bob Burns, Detroit Riverkeeper Great Lakes Regional Collaboration In May of 2004, President Bush issued an Executive Order Recognized Great Lakes as
More informationFOR THE DOMINGUEZ CHANNEL WATERSHED MANAGEMENT AREA GROUP
Enhanced Watershed Management Program FOR THE DOMINGUEZ CHANNEL WATERSHED MANAGEMENT AREA GROUP March 2015 Prepared by: Dominguez Channel Watershed Management Area Group City of Los Angeles County of Los
More informationAdvanced Stormwater Biofiltration. MWS Linear
Advanced Stormwater Biofiltration MWS Linear Contents 1 Introduction 2 Applications 3 Configurations 4 Advantages 5 Operation 6 Orientations Bypass 7 Performance Approvals 8 Sizing 9 Installation Maintenance
More informationChapter 3 Previous Studies
Chapter 3 Previous Studies The Vista Grande stormwater conveyance system and watershed area has been evaluated in a number of reports and studies for the CCSF, the Daly City and San Mateo County over the
More informationDry Swale Wet Swale Grass Channel Dry Well Permeable Pavement Bioretention DESIGN ELEMENTS
FACILITY ID: DATE: / / ASSESSED BY: NAME: ADDRESS: PHOTO IDS: SECTION 1- BACKGROUND INFORMATION (GIS) BMP TYPE : Dry Detention Pond Extended Detention Pond Wet Pond Filter (specify: ) Infiltration (specify:
More informationNon-Priority Projects WQMP Preparation Guidance Manual
Non-Priority Projects WQMP Preparation Guidance Manual December 2005 Table of Contents 1.0 Introduction... 1 2.0 Requirements for Development Projects...1 3.0 WQMP Preparation... 2 3.1 Cover Page... 2
More informationCHAPTER 15 WATER POLLUTION. INTO THE GULF Researchers try to pin down what s choking the Gulf of Mexico
CHAPTER 15 WATER POLLUTION INTO THE GULF Researchers try to pin down what s choking the Gulf of Mexico SAVING THE BAY Teams of researchers try to pin down what s choking the Chesapeake Water pollution
More informationSuggested Best Management Practices (BMPs)
Suggested Best Management Practices (BMPs) Preface The purpose of this Best Management Practices (BMP) Manual is to help educate and instruct on ways to reduce stormwater pollution and help prevent it
More informationSection 2 Stormwater Quality Planning For New. New Development and Redevelopment
Stormwater Quality Planning For New Development and Redevelopment 2.1 Introduction State and Federal programs require BMPs to be implemented by developers, property owners, and public agencies engaged
More informationLesson W9 Wastewater and CSOs
Lesson W9 Wastewater and CSOs Where Does our Water Go When We Flush it Down the Drain? When you flush your toilet or wash your dishes, where does the water go? We learned that only 2-3% of the water used
More informationCity of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017
City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017 Why is Water Quality Important? Water has always been important to Minnesota and is a key part of our history, culture, economy
More informationSizing Calculations and Design Considerations for LID Treatment Measures
SCVURPPP C.3 Workshop December 18, 2012 Sizing Calculations and Design Considerations for LID Treatment Measures Jill Bicknell, P.E., EOA, Inc. Santa Clara Valley Urban Runoff Pollution Prevention Program
More informationPlaza and Sidewalk Cleaning
Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Pollutants on sidewalks and other pedestrian traffic areas and plazas are typically due to littering and vehicle use. This
More informationConcurrent Session B: LID Design Specifications (Chapter 4 in Draft Manual)
Concurrent Session B: LID Design Specifications (Chapter 4 in Draft Manual) Should vs. Must In Chapter 4, should means should, and must means must. Poorly Drained Soils Well-Drained Soils Flat Terrain
More information1.1 MONITORING PROGRAM OBJECTIVES The major objectives of the Monitoring Program outlined in the Municipal Stormwater Permit are to:
1.1 MONITORING PROGRAM OBJECTIVES The major objectives of the Monitoring Program outlined in the Municipal Stormwater Permit are to: Assess compliance with the Los Angeles County Municipal Stormwater Permit
More informationStormwater Awareness Training
Stormwater Awareness Training 2014 Purpose of Stormwater Awareness Training To educate City of Aurora employees on the importance of identifying non stormwater discharges and reducing pollution through
More informationWestside Water Quality Treatment Project Proposition 13 Photo Diary Final Report March /31/02 QMM02B
Westside Water Quality Treatment Project Proposition 13 Photo Diary Final Report March 2008 Southern California Region Westside Water Quality Treatment Project Project Objective: Design and construct a
More informationSlide 1: Welcome to today s The Nitrogen Cycle presentation, where we ll be talking to you about the importance of nitrogen in our environment.
Slide 1: Welcome to today s The Nitrogen Cycle presentation, where we ll be talking to you about the importance of nitrogen in our environment. 1 Slide 2: Barnegat Bay, like many coastal areas in the country,
More information3.10 Hydrology and Water Quality. Environmental Setting
3.10 Hydrology and Water Quality This section describes the potential hydrology and water quality impacts associated with the proposed changes to the approved project. Environmental Setting This section
More informationChapter 3: Post Construction Water Quality Best Management Practices
Chapter 3: Post Construction Water Quality Best Management Practices 3.1 Introduction to Stormwater Quality Under the regulations governing the NPDES Stormwater Phase II program, Montgomery County is required
More information