1 Weymouth Water Treatment Plant Weymouth Oxidation Retrofit Program
2 Appropriate $9.8 M in budgeted funds Authorize final design to complete Weymouth Oxidation Retrofit Program Authorize final design of Weymouth raw water bypass line Authorize amendments to exist. agreements with Carollo Engineers & Tetra Design
3 Jensen Plant Weymouth Plant Diemer Plant Mills Plant Skinner Plant
4 Weymouth ORP and Raw Water Bypass
5 Effective, reliable disinfection Minimizes DBP formation Controls Taste & Odor Removes disease causing organisms Removes many PPCPs and EDCs Flexibility to manage shifts in source water quality Permanent strategy at all 5 treatment plants
6 Minimize disinfection by products by Increasing coagulant & acid dosages Delaying point of chlorination Temporarily reducing SPW blends Ensures Weymouth will continue to meet all primary drinking water regulations with operational constraints Disadvantages Limited control of Taste & Odor Source water limitations Higher TDS Potential limitations on plant capacity
7 April 2007 Bid Package Ozone facilities Inlet conduit Some electrical upgrades Access constraints Weymouth full plant shutdown revealed need for new rehabilitation projects Phased approach implemented Lower risk of construction delays Lower risk to plant operations
8 Weymouth 3 Phased Construction Approach Phase 1 Electrical Projects, Plant Inlet Conduit, Infrastructure Upgrades Phase 2 Ozone Implementation Phase 3 Process Improvements
9 Final Design Tasks Develop bidding documents for phased approach Structural design update to comply with new building codes Rejection line to Marshall Creek Channel District Force work Control systems & chlorine system modification Design Joint effort Metropolitan staff, Carollo Engineers & Tetra Design Amend agreements with Carollo Engineers & Tetra Design
10 Labor Owner Costs (Program mgmt, $805,000 permitting & biddingprocess) Final Design $6,665,000 Incidental le Expenses $25,000 Professional/ Technical Services Carollo Engineers $680,000 Tetra Design $125,000 Environmental Science Associates $45,000 Remaining Budget $1, Total $9,560,000
11
12 Design scope of work Connection to Upper Feeder Vault for temporary pipe spool upstream of ozone contactors Modifications to vault near finished water reservoir for another temporary pipe spool Bypass will be constructed during the ORP Carollo Engineers will perform final design under an existing agreement
13 Labor Owner Costs (Program mgmt & $48,000 permitting) Incidental Expenses $2,000 Professional/ Technical Services Carollo Engineers $158,000 Remaining Budget $32,000 Total $240,000
14 Weymouth ORP Schedule Project ORP Raw Water Bypass Final Design Shutdown Window/ Shutdown Advertise/Award Board Action Construction Completion of Construction
15 Option # 1 Adopt CEQA determination Appropriate $9.8 million Authorize completion of final design of Weymouth ORP Authorize final design of a raw water bypass line for the Weymouth plant Authorize an increase of $1 milion to existing agreement with Carollo Engineers, for new NTE total of $12.7 M Authorize an increase of $200,000 to existing agreement with Tetra Design, for new NTE total of $2.658 M
16 Option # 2 Adopt CEQA determination Appropriate $9.56 million Authorize completion of final design of Weymouth ORP Do not authorize final design of a raw water bypass line for theweymouth plant Authorize an increase of $1 milion to existing agreement with Carollo Engineers, for new NTE total of $12.7 M Authorize an increase of $200,000 to existing agreement with Tetra Design, for new NTE total of $2.658 M
17 Option # 3 Do not proceed with ozone facilities at Weymouth at this time
18 Option #1
Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary.
Report Engineering Services Group Capital Investment Plan (CIP) Quarterly Report for the period ending September 2012 Summary This report provides a summary of fiscal year accomplishments, capital expenditures
More informationCapital Investment Plan Quarterly Report for period ending September 2017
Report Engineering Services Group Capital Investment Plan Quarterly Report for period ending September 2017 Summary This report provides a summary of accomplishments to date on the Capital Investment Plan
More informationATTACHMENT A TO THE AGREEMENT FOR ENGINEERING SERVICES. Project: Chloramine Replacement Alternative Evaluation
ATTACHMENT A TO THE AGREEMENT FOR ENGINEERING SERVICES Owner: Board of Public Works, City of Hannibal, Missouri Project: Chloramine Replacement Alternative Evaluation DESCRIPTION OF SCOPE OF SERVICES On
More informationProposed Capital Investment Plan Appendix. Investing in Reliability Fiscal Years 2014/15 and 2015/16
Proposed Capital Investment Plan Appendix Investing in Reliability Fiscal Years 2014/15 and 2015/16 Table of Contents Introduction... 1 Capital Investment Plan Development... 3 Major Objectives for Fiscal
More informationProcess Treatment Selection and. Jeff Macomber, P.E. One Water Conference August 28, 2014
Process Treatment Selection and Design for the City of Piqua s New WTP Jeff Macomber, P.E. One Water Conference August 28, 2014 Agenda Project Background Water Treatment Goals Process Treatment Alternative
More informationHydrogen sulfide (H2S), is now regulated
FWRJ Seminole County Markham Regional Water Treatment Plant: Regulatory Compliance Considerations, Treatment Challenges, and Solutions Roberto Gonzalez, John Reed, Kevin Friedman, Mike Cliburn, Tim Brodeur,
More informationONLINE MONITORING PRACTICES FOR MANGANESE CONTROL IN DRINKING WATER TREATMENT
ONLINE MONITORING PRACTICES FOR MANGANESE CONTROL IN DRINKING WATER TREATMENT Vadim B. Malkov, Hach Company Water Systems Optimization, 10/30/2015 INTRODUCTION Manganese in US source water why is it a
More informationREAL WORLD APPLICATIONS OF USING DYNAMIC SIMULATION SOFTWARE TO OPTIMIZE WATER TREATMENT PLANT PROCESS OPERATIONS
REAL WORLD APPLICATIONS OF USING DYNAMIC SIMULATION SOFTWARE TO OPTIMIZE WATER TREATMENT PLANT PROCESS OPERATIONS (FRIT05) OCTOBER 30, 2015 Authors: Matt Ridens/CH2M, Jason Curl/CH2M Overview Drivers for
More information8-5. Engineering and Operations Committee. Board of Directors. 1/13/2015 Board Meeting. Subject. Executive Summary
Board of Directors Engineering and Operations Committee 1/13/2015 Board Meeting Subject Appropriate $34.3 million; and authorize: (1) final design to rehabilitate prestressed concrete cylinder pipe (PCCP)
More informationMatt Leach, P.E. CH2M. Mark Eppich, P.E. City of Columbus Division of Water. S. Dean Ramsey, P.E. CH2M
Matt Leach, P.E. CH2M Mark Eppich, P.E. City of Columbus Division of Water S. Dean Ramsey, P.E. CH2M 1 Presentation Topics Project Background Project Team Unique Challenges and Opportunities Risk Assessment
More informationOptimizing Filter Conditions for Improved Manganese Control During Conversion To Biofiltration [Project #4448]
Optimizing Filter Conditions for Improved Manganese Control During Conversion To Biofiltration [Project #4448] ORDER NUMBER: 4448 DATE AVAILABLE: May 2016 PRINCIPAL INVESTIGATORS: Chance V. Lauderdale,
More informationGranular Activated Carbon System
Granular Activated Carbon System Eliminating Use of Chloramines March 22, 2017 www.jacobs.com worldwide The Jacobs Team Mike McCarty, PE Project Manager Tobin Lichti, PE Water Treatment Engineer Russ Dahmer,
More informationInnovative Approach to Expanding the Olentangy WTP
Innovative Approach to Expanding the Olentangy WTP September 28, 2017 Spencer Sheldon, WTP Superintendent Bret M. Casey, P.E., BCEE Who is Del-Co Water? Member owned 501-(c) Non-Profit Corporation Governed
More informationReverse-osmosis membranes were
Benefits and Limitations of Utilizing A Raw-Water Blend Stream to Meet Production and Quality Goals at a Membrane Facility James E. Christopher Reverse-osmosis membranes were initially applied to the removal
More informationCITY OF LOMITA CYPRESS WATER PRODUCTION FACILITY OFF-LINE TESTING
CITY OF LOMITA CYPRESS WATER PRODUCTION FACILITY OFF-LINE TESTING 2 Good Results Title 22 Requirements California Department of Public Health monitors wells throughout the state Title 22 reports Lomita
More informationChloramine and Nitrification... Is There a Simple Solution?
Chloramine and Nitrification... Is There a Simple Solution? Scott Hibbs, P.E. & Dave Baker Enprotec/Hibbs & Todd 402 Cedar; Abilene TX 79601 325.698.5560 eht.com Workshop Objective Share your experiences
More informationNorth American Biofiltration Knowledge Base. Appendices A and B. Project #4459
rth American Biofiltration Knowledge Base Appendices A and B Project #4459 rth American Biofiltration Knowledge Base Appendices A and B Prepared by: Jess Brown and Giridhar Upadhyaya Carollo Engineers,
More informationIntegrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant
Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant City of Columbus Division of Water: Matt Steele CH2M HILL: Enoch Nicholson DRWP Source Water and Treatment DRWP Overview Current
More informationTreatment techniques for control of disinfection byproduct (DBP) precursors.
3745-81-77 Treatment techniques for control of disinfection byproduct (DBP) precursors. (A) (B) Surface water community and nontransient noncommunity public water systems using conventional filtration
More informationWRF Webcast Biofilter Conversion Guidance Manual
No part of this presentation may be copied, reproduced, or otherwise utilized without permission. WRF Webcast Biofilter Conversion Guidance Manual March 28, 2017 Biofiltration: Defining Benefits and Developing
More informationENVIRONMENTAL AND HEALTH ASPECTS OF WATER TREATMENT AND SUPPLY Design of Water Treatment Facilities - Katsuyoshi Tomono, Yasumoto Magara
DESIGN OF WATER TREATMENT FACILITIES Katsuyoshi Tomono Senior Engineering Advisor, Tokyo Engineering Consultants, Co., Ltd., Tokyo, Japan Yasumoto Magara Professor of Engineering, Hokkaido University,
More informationFPI Mag Flow Meter. Next Generation Mag Meter Measuring Flow in a Pump Station. McCrometer, Inc. (800)
FPI Mag Flow Meter Next Generation Mag Meter Measuring Flow in a Pump Station McCrometer, Inc. www.mccrometer.com/fpimag (800)220-2279 Michelle Pawlowicz Marketing Specialist Lit Number 81000-01 Rev 1.0/6-13
More informationIn-Reservoir TTHM Surface Aeration: A year of results, experience and lessons learned
In-Reservoir TTHM Surface Aeration: A year of results, experience and lessons learned Jeanne M. Jensen, P.E. Steve Acquafredda, P.E. Jacobs Engineering Group, Inc. February 2, 2012 Presentation Outline
More informationMaster System Shutdown Schedule- WSIP Projects Master Layout by Quarters
Project ID Critical / No. Project Name Purpose Start Finish Additional Comments 2002 Water System Improvement Program 10-Nov-06 A 05-Oct-14 Qtr 4, 2006 10-Nov-06 A 16-Jan-09 A Master System Schedule- WSIP
More informationChallenges in Municipal Water Treatment and the MIOX Solution
Challenges in Municipal Water Treatment and the MIOX Solution Part 1 of 3: Overview Surface & Groundwater Treatment Tuesday, December 11 th at 10AM CST Agenda for Part 1 Brief Introduction of MIOX General
More informationONET, WaterCAD, WATSYS, KYPIPE, and EPANET.
Over the last 15 years alone, Carollo has performed planning services for more than 70 municipal clients. We have evaluated over 100 water treatment facilities in 25 different states. Carollo offers a
More informationSide by Side Piloting of Process Alternatives Yields Direct Performance Comparison
OBG PRESENTS: OBG PRESENTS: Side by Side Piloting of Process Alternatives Yields Direct Performance Comparison LORI W. REID, P.E. New York State AWWA Spring Meeting, April 26, 2017 Outline Background Project
More informationIsabelle Papineau, Ph.D., École Polytechnique de Montréal Yves Dionne (V de G) and Benoit Barbeau (EPM)
Isabelle Papineau, Ph.D., École Polytechnique de Montréal Yves Dionne (V de G) and Benoit Barbeau (EPM) 16 th Canadian National Conference on Drinking Water October 28th 2014 1. Background City of Gatineau
More informationOxelia OXIDATION-ENHANCED BIOLOGICALLY ACTIVE FILTRATION
Oxelia OXIDATION-ENHANCED BIOLOGICALLY ACTIVE FILTRATION In the battle with hard-to-treat contaminants, drinking water just got a powerful new ally. Leopold Oxelia oxidation-enhanced biologically active
More informationAeration Strategies for TTHM Control
Aeration Strategies for TTHM Control Chad Seidel, Ph.D., P.E. Stephen Acquafredda, P.E. Damon S. Williams Associates, LLC AZWA Water Treatment Committee Seminar Series Water System Optimization Tuesday,
More informationPurpose of the Comprehensive Water System Plan
2006 TACOMA WATER COMPREHENSIVE WATER SYSTEM PLAN UPDATE EXECUTIVE SUMMARY Purpose of the Comprehensive Water System Plan Tacoma Water s planning activities center on the need to meet increasing demands
More informationThis qualification has been reviewed. The last date to meet the requirements is 31 December 2018.
NZQF NQ Ref 0880 Version 5 Page 1 of 7 National Certificate in Water Treatment (Level 4) Level 4 Credits 134 This qualification has been reviewed. The last date to meet the requirements is 31 December
More informationARSENIC IN DRINKING WATER
ARSENIC IN DRINKING WATER Treatment Technologies: Removal Background In water, the most common valence states of arsenic are As(V), or arsenate, which is more prevalent in aerobic surface waters and As(III),
More informationPartnership for Safe Water Distribution System Optimization Program. Barbara Martin, AWWA
Partnership for Safe Water Distribution System Optimization Program Barbara Martin, AWWA Why Optimize? Assessment benefits: System-specific learning opportunity Prepare for future regulations Water quality
More informationSeasonal Source Water Quality and Treatment Challenges Town of Newburgh s Chadwick Lake Filtration Plant
Seasonal Source Water Quality and Treatment Challenges Town of Newburgh s Chadwick Lake Filtration Plant Clayton Johnson GHD Kevin Castro GHD James Osborne Town of Newburgh Image placeholder Outline Introduction
More informationTaste and Odor Mitigation Strategies Laboratory-Based Analysis
Taste and Odor Mitigation Strategies Laboratory-Based Analysis 2013 PNWS-AWWA Conference Spokane, WA Kim Ervin, P.E., West Region Drinking Water Service Lead, CH2M HILL Outline Introduction - Sources of
More informationCity of San Diego Pure Water Project October 2014
City of San Diego Pure Water Project October 2014 SDCTA Position: SUPPORT Rationale for Position: Substantial study has demonstrated a potable reuse project within the City of San Diego would be safe,
More informationG E N E R A L M A N A G E R S M O N T H L Y A C T I V I T Y R E P O R T M A R C H
T H E M E T R O P O L I T A N W A T E R D I S T R I C T O F S O U T H E R N C A L I F O R N I A G E N E R A L M A N A G E R S M O N T H L Y A C T I V I T Y R E P O R T M A R C H 2 0 1 3 MARCH 31, 2013
More informationBIDS WILL BE CONSIDERED NON-RESPONSIVE WITHOUT THE REQUIRED SIGNATURE ACKNOWLEDGING THE FOLLOWING:
BID SHEET FOR CIP 17-101 CIPP LINING OF SANITARY SEWER SYSTEM Item No. 16 17 18 19 20 21 Description and Bid Unit Price Brim Style Service Line Connection Sealing System Temporary Bypass Facilities Set
More informationTHM Monitoring in Consecutive Drinking Water Systems
THM Monitoring in Consecutive Drinking Water Systems Rick Bacon rbacon@aquametrologysystems.com Rudy Mui rudy@aquametrologysystems.com Systems that Enable the Optimization of THM Control www.aquametrologysystems.com
More informationPOTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE. Michael Dalton. Toowoomba City Council
POTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE Paper Presented by: Michael Dalton Author: Michael Dalton, Rockhampton City Council, Toowoomba City Council 33rd Annual Qld Water Industry
More informationSECTION 3.0 SPECIFICATIONS FOR DRINKING WATER DISTRIBUTION SYSTEMS DESIGN
3.1 GENERAL SECTION 3.0 SPECIFICATIONS FOR DRINKING WATER DISTRIBUTION SYSTEMS DESIGN 3.1.1 The following specifications cover the general design, review of plans and specifications, and acceptance of
More informationChloramine Optimization through Proper Mixing and a Unique Chloramine Management System. John Kiernan
Chloramine Optimization through Proper Mixing and a Unique Chloramine Management System John Kiernan EPA has set a compliance date of April 1, 2016 but some states are accelerating their compliance To
More informationStage 1 Disinfectants and
by Lonnie Boller Disinfection Byproducts Rule (D/DBPR) monitoring and reporting issues Lonnie Boller Surface Water Tech R ecently, water systems were advised of the new Disinfection Byproducts Rule (D/DBPR).
More information600 MGD... What About 2 MGD?
600 MGD... What About 2 MGD? Small Municipal Water Treatment with Ozone Andrew Conner 11057 Allisonville Rd., #333 Fishers, IN 46038 Abstract Much attention is given to large water treatment facilities
More informationEngineer s Report. Santa Clara Valley Water District California Aqueduct Reverse Flow Project Project No
17 Santa Clara Valley Water District California Aqueduct Reverse Flow Project Project No. 60061007-6810 Engineer s Report February 2015 Water Utility Capital Division This page intentionally left blank.
More informationWATER SYSTEMS OPERATION AND MAINTENANCE VIDEO TRAINING SERIES COURSE OUTLINE
WATER SYSTEMS OPERATION AND MAINTENANCE VIDEO TRAINING SERIES COURSE OUTLINE Page 1. Wellhead Protection 1 2. Hypochlorination 35 3. Water Storage Tanks 65 4. Sampling and Testing 95 Page 5. Inspecting
More informationMAKING THE SWITCH FROM LIME TO MEMBRANE SOFTENING: WHEN IS IT THE RIGHT TIME? Introduction
MAKING THE SWITCH FROM LIME TO MEMBRANE SOFTENING: WHEN IS IT THE RIGHT TIME? Joseph R. Elarde CH2M HILL 5801 Pelican Bay Blvd., Suite 505 Naples, FL 34108 joe.elarde@ch2m.com 239-431-9225 Jeff Poteet,
More informationBeer Line Disinfection System
Beer Line Disinfection System Major Functions + Beer Line Disinfection Application + Pub + Club & Bar The World s Most Powerful Natural Disinfectant Ozone kills E.coli approximately 3,000 times faster
More informationNew York State Department of Environmental Conservation
May 2012 New York State Department of Environmental Conservation Award Submission for Environmental Excellence Awards Port Washington Water Pollution Control District (PWWPCD) Submitted by D&B Engineers
More informationUnique Riverbank Filtration System Provides 80 MGD
Unique Riverbank Filtration System Provides 80 MGD HENRY HUNT September 28, 2017 Outline Summary Basics of Riverbank Filtration Louisville Water Company Background LWC Decision Process System Construction
More informationBID FORM (LUMP SUM CONTRACT)
BID FORM (LUMP SUM CONTRACT) Place County of El Paso Purchasing Department Date Project No. 11-016 Proposal of (hereinafter called Bidder), a corporation organized under the laws of the State of /a partnership/an
More informationSECTION 5 E-Treat Water Conditioning Systems
SECTION 5 E-Treat Water Conditioning Systems WaTEr QualITy PrOduCTS Catalog 10 Watts product specifications in U.S. customary units and metric are approximate and are provided for reference only. Watts
More informationSAN ANTONIO DESAL MOVING FULL SPEED AHEAD: CONSTRUCTION OF THE SAWS BRACKISH GROUNDWATER DESALINATION FACILITY. Abstract
SAN ANTONIO DESAL MOVING FULL SPEED AHEAD: CONSTRUCTION OF THE SAWS BRACKISH GROUNDWATER DESALINATION FACILITY Esther Harrah, PE, San Antonio Water System, 2800 US Hwy 281 North, San Antonio, TX 78212
More informationTechnology Primers for the Simultaneous Compliance Tool
Technology Primers for the Simultaneous Compliance Tool Supplement to #91263 Subject Area: Water Quality NEW CHLORINE APPLICATION Chlorine is the most widely used disinfectant in water treatment primarily
More informationMemorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kerrie Romanow. SUBJECT: SEE BELOW DATE: May 30, 2017
CITY OF ^2 SAN TOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 6/20/17 ITEM: Q, \0 - Memorandum FROM: Kerrie Romanow SUBJECT: SEE BELOW DATE: Approved Date SUBJECT:
More informationOPERATOR CERTIFICATION EXAMINATION REGISTRATION PA Certification to Operate Water or Wastewater Systems PRINT CLEARLY
3900-FM-BSDW0109 9/2012 COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION STATE BOARD FOR CERTIFICATION OF WATER AND WASTEWATER SYSTEMS OPERATORS OPERATOR CERTIFICATION EXAMINATION REGISTRATION
More informationBoard authorization is required because the proposed contracting authority exceeds the amount previously authorized by the Board for each contract.
Date: April 23, 2014 To: From: Board of Directors Neil McFarlane Subject: RESOLUTIONS 14-04-23 AND 14-04-24 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING INCREASED
More informationIs Oxygen Injection the Solution for Your Collection System Odors and Corrosion?
Is Oxygen Injection the Solution for Your Collection System Odors and Corrosion? An Investigation into Current Applications and Industry Trends of Oxygen Injection for a Central Texas Municipality. Melissa
More informationSample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction
Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction 1.00 DESCRIPTION 1.01 WORK INCLUDED: This work shall include the furnishing of all labor, equipment and materials necessary
More informationHow can liquid ozone be used in different industries?
How can liquid ozone be used in different industries? WATER TREATMENT SYSTEMS AND PLANTS: Pre-oxidant, pre-disinfectant, coagulant aid, and biofilm remover. Effluent disinfection. ULTRA-FILTRATION SYSTEMS
More informationShould we use a residual in our drinking water distribution systems?
Should we use a residual in our drinking water distribution systems? R. Rhodes Trussell Trussell Technologies, Inc. Pasadena, CA Vernon L Snoeyink Lecture University of Illinois 10 March 2005 How did the
More informationWater Treatment & Purification Chemicals
F72 Water Treatment Cleaning Chemicals Super Iron Out - Powder Form Powder form, must be dissolved in water to work Dissolves lime, rust, calcium, soap scum & mineral deposits below the waterline Cleans
More informationDrinking Water Treatment Optimization Tools
Drinking Water Treatment Optimization Tools Introduction Treating water to meet today s potable drinking water regulations requires a delicate balance between seemingly conflicting or competing regulations,
More informationProvision of Excellent Water and High-Quality Service
Provision of Excellent Water and High-Quality Service Business Outline 2016 Tokyo Waterworks supports the capital of Tokyo Tokyo, the Japanese capital, is the largest city in Japan with a population of
More informationWatershed: an area or ridge of land that separates waters flowing to different rivers, basins, or seas. It is the interdependent web of living
Watershed: an area or ridge of land that separates waters flowing to different rivers, basins, or seas. It is the interdependent web of living organisms that inhabit a geographic area and depend on it
More informationWINTERHAVEN PUBLIC SAFETY FACILITY PROJECT
WINTERHAVEN PUBLIC SAFETY FACILITY PROJECT Funded by: California Department of Housing and Community Development (HCD) through its Community Development Block Grant (CDBG) Program and the County of Imperial.
More informationHydraulic Modeling Predicting and Resolving Water Quality Issues
Alliance of Indiana Rural Water September 21, 2016 Hydraulic Modeling Predicting and Resolving Water Quality Issues Jim McNulty, P.G. Strand Associates, Inc. The content of this presentation is not to
More informationWater Treatment Plant Startup Issues and Considerations
Water Treatment Plant Startup Issues and Considerations Joe Guistino, Coastside County Water District Aileen Kondo, Kennedy/Jenks Consultants California-Nevada Section AWWA Annual Fall Conference 2 October
More informationAESO Practices for System Access Service. May 31, 2013
AESO Practices for System Access Service May 31, 2013 Table of Contents 1 Purpose... 3 2 Introduction... 3 3 Practices for System Access Service... 4 3.1 Conditions for System Access Service... 4 3.2 Rationale
More informationDBP Treatment Strategies. Learning Objectives. DBP Control Options Optimize existing facilities
DBP Treatment Strategies Workshop developed by RCAP/AWWA and funded by the USEPA Learning Objectives Describe treatment strategies to address DBP formation Evaluate the various strategies to choose the
More informationLong Point Water Treatment Plant Process Evaluation and Design Upgrades for Performance Enhancement; Dover, DE
Long Point Water Treatment Plant Process Evaluation and Design Upgrades for Performance Enhancement; Dover, DE Christopher Walker, PE Christopher Curran, PE Mark Prouty, PE May 12, 2016 Long Point Water
More informationLagoons Operation and Management in New Brunswick
Lagoons Operation and Management in New Brunswick Lagoons Provide secondary treatment to domestic wastewater by the action of bacteria stabilizing the organic matter in the wastewater. Benefits of lagoons:
More informationOPERATORS PERSPECTIVE : OPTIMISATION OF A NEW PACKAGE WATER TREATMENT PLANT. Melina Entwistle. North East Water Authority
OPERATORS PERSPECTIVE : OPTIMISATION OF A NEW PACKAGE WATER TREATMENT PLANT Paper Presented by : Melina Entwistle Author: Melina Entwistle, Water and Wastewater Treatment Operator, North East Water Authority
More informationNeed-to-Know Criteria Water Treatment Operator Class I
2017 Need-to-Know Criteria Water Treatment Operator Class I A Need-to-Know Guide when preparing for the ABC Water Treatment Operator Class I Certification Exam Before You Dive In What is ABC s Need-to-Know
More informationHow Municipal Water Authorities Are Using Simulation Tools to Improve Performance and Reduce Costs
David Schowalter, PhD, Fluent Inc. Introduction With the unrelenting population growth in large and mid-size North American cities, water resources have become a critical concern. The old paradigm that
More informationDrinking Water Treatment: Filtration and Disinfection
Drinking Water Treatment: Filtration and Disinfection Subject Area(s) chemistry, physics Associated Unit Lesson Title Header Drinking Water Treatment Process Drinking Water Treatment: Filtration and Disinfection
More informationCity of Wentzville. Standard Specifications and Construction Details Amendment List
Amendment No. 1 Standard Specifications and Construction Details Amendment List Date: September 21, 2009 Subject: SCD 700.23 - Residential Entrance Layout and drawing revised to more clearly show the location
More informationCITY OF DAWSON CREEK WATER QUALITY ASSURANCE PLAN
WATER QUALITY ASSURANCE PLAN Table of Contents 1.0 INTRODUCTION... 1-1 1.1 AUTHORIZATION... 1-1 1.2 PURPOSE AND SCOPE... 1-1 2.0 SOURCE WATER... 2-1 2.1 KISKATINAW RIVER... 2-1 2.2 RIVER WATER QUALITY...
More informationFremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment
OWEA 2013 Annual Conference June 19, 2013 Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment Jeff Lamson, Superintendent, WPCC Robert Hrusovsky,
More informationThe Contract Documents may be examined at the following locations:
ADVERTISMENT FOR BIDS Separate sealed Bids for the replacement of Municipal Production Well will be received by the Department of Public Services at 301 W. Main Street, Owosso, MI 48867 until 2:00 p.m.
More informationRawal Lake Water Treatment Plant Rawalpindi, Pakistan
Rawal Lake Water Treatment Plant Rawalpindi, Pakistan 1. Background Information Rawal Lake Water Treatment Plant is managed by the Water & Sanitation Agency (WASA) under the Rawalpindi Development Authority
More informationWells No. 12/13 Pump Station and Hypochlorite Generation Facility (HDR s Claim Additional Design Fees)
Wells No. 12/13 Pump Station and Hypochlorite Generation Facility (HDR s Claim Additional Design Fees) Presentation By: HDR Engineering, Pasco Office and Pacific Groundwater Group, Inc. March 5, 2012 Pete
More informationReducing THM via Aeration: A Case Study August 28, 2014
1 Reducing THM via Aeration: A Case Study August 28, 2014 by Gary Williams, P.E. Jones & Henry Engineers WEA-AWWA 2014 Technical Conference & Expo Agenda 2 Location History Pilot Implementation Take Away
More informationRemoval of Manganese by Microfiltration in a Water Treatment Plant*
Removal of Manganese by Microfiltration in a Water Treatment Plant* Carl Schneider, Ph.D., P.E., Senior Process Engineer Wiedeman & Singleton, Inc., Atlanta, GA Peter Johns, P.E., Vice-President Wiedeman
More informationBIOLOGICAL MANGANESE REMOVAL A VERY SUSTAINABLE WATER TREATMENT TECHNOLOGY. Peter Baudish. Sinclair Knight Merz
BIOLOGICAL MANGANESE REMOVAL A VERY SUSTAINABLE WATER TREATMENT TECHNOLOGY Paper Presented by: Peter Baudish Author: Peter Baudish, Water Treatment Practice Leader, Sinclair Knight Merz 4 th Annual WIOA
More informationOwners Manual Models: 200-RODI4-XXX. US Water Systems 4 Stage RO/DI System Installation and Maintenance Manual.
Visit us online at www.uswatersystems.com US Water Systems 4 Stage RO/DI System Installation and Maintenance Manual Owners Manual Models: 200-RODI4-XXX US Water 4 Stage RO/DI System REVISION 1.0, 5/12/2015
More informationSERVICES and QUALIFICATIONS
SERVICES and QUALIFICATIONS Offices in Phoenix, Denver, Chicago, and San Juan PR. IFE Services and Qualifications Table of Contents TABLE OF CONTENTS Section Page IFE - Corporate Overview...1 IFE - Services...3
More informationSAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL
DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of
More informationWater System Service Categories, Post-Earthquake Interaction, and Restoration Strategies
OPINION PAPER Water System Service Categories, Post-Earthquake Interaction, and Restoration Strategies Craig A. Davis a) M.EERI This paper illustrates the relation between resilience and water system serviceability,
More informationThe primary goals of a water treatment plant for over a
C H A P T E R 1 Introduction The primary goals of a water treatment plant for over a century have remained the same: produce water that is biologically and chemically safe, is appealing to consumers, and
More informationSERVICE POOL CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
SERVICE POOL CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Revised September 14 The General Trade Knowledge portion of the examination is administered daily in Computer Based Testing
More informationGeneral Manager s monthly Activity Report March 2014
The Metropolitan Water District of Southern California General Manager s monthly Activity Report March 2014 March 31, 2014 Content by Group: THIS REPORT IDENTIFIES THE ACTIONS AND ACTIVITIES TAKING PLACE
More informationRenovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado
JUST ADD WATER Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado Thomas M. Getting, P.E., DEE, Filtration Product Manager John Geibel, P.E., Chief Engineer Michael
More informationAnn Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017
Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater
More informationLEARNINGS FROM SEVERAL HIGH CHLORINE EVENTS. Raj Mahendrarajah. Coliban Water
LEARNINGS FROM SEVERAL HIGH CHLORINE EVENTS Paper Presented by: Raj Mahendrarajah Author: Raj Mahendrarajah, Manager Water Quality Performance, Coliban Water 79 th Annual WIOA Victorian Water Industry
More informationBAYFILTER SPECIFICATIONS
PART 1.00 GENERAL 1.1 DESCRIPTION BAYFILTER SPECIFICATIONS A. The BayFilter system s internal components manufacturer selected by the Contractor and approved by the Engineer, shall furnish all labor, materials,
More informationNJWA 2014 Management & Technical Conference
NEW JERSEY WATER ASSOCIATION CONFERENCE Wednesday, October 21, 2015 MYTHBUSTERS PRESENTERS Andrew S. Holt, PE, PP, CME Vice President Eleni Giannikopoulos Senior Designer PRESENTATION OUTLINE NEW JERSEY
More informationWater Supply Planning Value Planning Study Council Presentation February 27, 2017
Water Supply Planning Value Planning Study Council Presentation February 27, 2017 Background Multiple water systems and water sources Canadian Drinking Water Guidelines not consistently met Rate inequity
More information1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:
SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification