1 A CASE STUDY OF HOW IRRIGATION SCHEMES IN NEW ZEALAND ARE EVOLVING TO MEET CHANGES IN FARMING PRACTISE AND REGULATION 1 David Carshalton, 1. Beca PTY Ltd, Melbourne, Victoria ABSTRACT Beca Ltd (Beca) has been working with several existing irrigation schemes in Canterbury, New Zealand over the past five years to determine how schemes can meet the changing needs of irrigators. In the last fifteen years a large portion of irrigators on these schemes have installed new spray irrigation systems to replace existing border dyke (flood) systems that have been in operation since the 1940s. These on-farm system upgrades have been driven by a desire to improve the efficiency of their irrigation systems on light Canterbury soils. Regulation has evolved over this period to require a higher standard of monitoring and control to meet water quantity and quality standards. The irrigation schemes currently consist of open channel infrastructure that requires at least minor upgrades to adjust to the changing environment. This paper offers a case study of the response of three irrigation schemes to the changes in irrigation practise and regulatory requirements. Figure 1 shows the location of the schemes within the South Island of New Zealand. The infrastructure in each scheme is owned by a co-operative company whose shareholders are the farmers supplied by the scheme. All of the schemes are run-of-river schemes, with no storage originally constructed for them. The schemes are each manually controlled by racemen adjusting weirs on open channels. Typically the flow in each channel is set once per day. The schemes require about one raceman per 10,000ha to operate efficiently. Water is delivered in accordance with a fixed roster, and is recorded manually by the racemen. Investigation into the efficiency of the schemes demonstrates that the water taken into the scheme is around 20% more than what each scheme allocates to the farmer irrigators. This water is either leaked from the open channels, bywashed back into the river, or given to farmers above their allocated flow to avoid bywashing the water. (Bywash is water taken into the irrigation scheme that is not used and released back to the river). INTRODUCTION Description of Schemes Referred to in this Case Study This case study refers to the work Beca has undertaken for three irrigation schemes: Mayfield Hinds Irrigation Scheme (MHIS) This scheme was built in the mid-1940 s and supplies 33,000ha of farm land between the Rangitata and Hinds Rivers in Mid Canterbury. Valetta Irrigation Scheme (VIS) This scheme was built in the mid-1940 s and supplies 13,000ha of farm land to the west of Ashburton in mid Canterbury. Amuri Irrigation Company (AIC) AIC operates three irrigation schemes built in the 1980 s supplying about 25,000 ha of farm land between the Hurunui and Waiau Rivers in North Canterbury. Figure 1: Locations in the South Island, NZ, of the Irrigation Schems Considered in this Case Study

2 OPERATING ENVIRONMENT Irrigation Practises Originally the farms were irrigated using border dyke irrigation on a fortnightly roster. In the past 15 years around 80% of irrigators, varying for each scheme, have converted from border dyke to spray irrigation, mostly using centre pivots. This has allowed water use efficiency to be greatly increased from the original border dyke irrigation which has an uneven distribution on the light soils typical of the Canterbury Region in New Zealand. The on farm spray irrigators are supplied by pumping either directly from the existing open channels (used on the AIC schemes) or from onfarm storage ponds (as on the MHIS and the VIS schemes). Pumping directly from the open channels is the lower cost option as it doesn t require the construction of on-farm storage ponds. However due to the manual control of the open channels it requires excess water to be run through the channels in order to maintain a continuous supply to farms, which leads to bywash back to the river at the downstream end of the scheme. The use of onfarm ponds requires additional capital expenditure, but allows flow buffering in the open channel system to prevent bywash from the scheme. Changes in Land Use There has been a substantial shift in land use of the last 10 years from cropping and meat/wool production (sheep and cattle) to dairy farming. Dairy farms are a more intensive land use that requires greater certainty over production levels. This results in a need for more efficient and reliable irrigation systems. Further, the returns on sheep and beef farming have been unable to support the cost of the increased efficiency required by regulation and hence farmers have shifted to dairy production. Summary of the Regulatory Setting The use of water for in New Zealand is the responsibility of the respective regional council. For all of the schemes covered by this study this is the Canterbury Regional Council, which is branded Environment Canterbury (ECan). The regional council has authority to grant resource consents (under the Resource Management Act 1991) that control the take and use of surface and groundwater. The water supplied to each irrigation scheme is governed by a resource consent which contains conditions of use. The bywash from the scheme (water taken into the scheme that is not used) is also subject to a resource consent. Water leached from the irrigated land into ground water, or runoff that is washed into waterways has not previously required resource consent. In the last ten years the quality of natural water ways has become a focus of national politics in New Zealand, which has led to the regional councils being required to improve the quality of natural waterways. This principally will be done by adding conditions onto existing water use consents that will limit the amount of nutrients that can be discharged into water ways and ground water. In August 2012, ECan released the Proposed Land and Water Regional Plan (plwrp) which sets out how the council will achieve the improvements required in water quality in natural waterways. In this plan, ECan proposes some significant changes for farmers, including: Shifting the focus of water use quantity regulation to include both quantity and quality. Taking into account the effect of nutrients in the runoff (to waterways) and leaching (into ground water) from irrigated land. ECan has begun to impose limits on nutrients allowed to move from farms into waterways. Requiring a farm environmental plan for each farm to demonstrate how the environmental measures will be met. Requiring land use consent when the land use is changed (for example if a farm changes for cropping to dairy). As it stands, the plan requires farmers to record their nitrogen runoff until 2017, when further decisions will be made. In the interim, the nitrogen runoff allowable in each catchment is being defined by variations to the plwrp plan. The plwrp requires irrigation schemes to install more extensive flow monitoring and finer control of water distribution to demonstrate efficient use of the resource and to inform on farm environmental plans. SCHEME CAPITAL WORKS TO MEET THE CHANGED OPERATING ENVIRONMENT Requirements of Capital Works Project Motivated by the changing land use, irrigation practices and regulatory requirements, the Boards of the respective companies have been investigating what capital upgrades are required to better match shareholder requirements. Beca has been engaged by each of the mentioned irrigation

3 companies to support them in the investigation of, design and delivery of scheme upgrades. Initially Beca met with the Boards of each company to understand their drivers for the scheme upgrades. The drivers were similar across the three schemes and are summarised as: Improve water use efficiency currently up to 20% of each scheme s water is lost to leakage, over-allocation, or by-washed back to the river. The water realised from scheme improvements can be used to expand the scheme, which can part-fund other upgrade projects. Allow accurate flow measurement and improved flow control to support farmers in meeting the new regulatory requirements. On schemes that operate a flow roster - provide water at a continuous flow, removing the requirement to buffer rostered flows in on-farm ponds. This can allow existing on-farm ponds to be used for reliability storage rather than operational storage. Consider the business case of using pipe networks to supply water at 40m pressure (sufficient for centre pivot irrigators) and so remove the need for on-farm pumping. Improve the flexibility of supply to allow for water trading in the future. Pty Ltd (Rubicon). The design and construction cost of this option was sourced directly from Rubicon. Open channel construction and control is typically significantly less costly that pipe infrastructure. However, the level of control is significantly less and channels will continue to leak, which doesn t fully meet the objective of improving water use efficiency. Manual control would still be required on smaller races, and flow measurement to farmers would rely on a flowmeter at each farm s pump station. About a dozen gates were proposed to be installed on each irrigation scheme, which were expected to reduce scheme bywash by 50% (around 10% of the total allocation saved). Table 1: Annual costs for upgrading the the existing open channel network using Concept 1 AIC and MHIS only Cost per ha per Item year $0/ha/yr (both) Capital Cost minus capital raised from shares Operating cost of existing open channel network Neutral cost because capital from new shares is approximately equal to capital cost $30/ha/yr (MHIS) $25/ha/yr (AIC) Although not formally identified as a driver for the project, there is a strong sense of wanting to preserve the resource for future generations. In many cases, the shareholders grandfathers helped build the original scheme infrastructure and they have a personal desire to upgrade scheme infrastructure so the water resource can be sustainably utilised by their grandchildren. Concept Design Pumping cost and maintenance (where pipe pressure is below 40m) Scheme overhead cost Total $160/ha/yr (MHIS) $200/ha/yr (AIC) $60/ha/yr (MHIS) $55/ha/yr (AIC) $250/ha/yr (MHIS) $280/ha/yr (AIC) In the concept design phase, the options to meet the project drivers were considered. For all three schemes, there are two basic concepts to meet the drivers, these are: 1. Concept 1 Retain the existing open channels, and add flow control gates at major junctions. 2. Concept 2 Replace the open channels with a pipe network to deliver water at 40m pressure. 1. Additional Control on the Existing Open Channels This concept consists of installing control gates, typically falling weir gates at critical locations, such as the FlumeGate produced by Rubicon Water 2. Replace the open channels with a pipe network to deliver water at 40m pressure. Each of the schemes has a natural gradient fall of approximately 1:125 across the length of the scheme. The total fall ranges from 120m (on the AIC schemes) to 360m (on MHIS). Therefore there is sufficient fall to generate 40m pressure to most farm offtakes though gravity pressure pipelines. Offtakes at the top of the scheme will still require booster pumping to supply spray irrigation. Table 2 presents a breakdown of annual costs for this concept.

4 Table 2: Annual costs for construction of a pipe network (Concept 2) Cost per ha per Item year Debt servicing of capital cost minus income from new shares sold amortised over 30 years at 7.5% interest Operating cost of pipe network Booster pumping cost and maintenance (where pipe pressure is below 40m) Scheme overhead cost Total Annual Costs (in 2014) $200/ha/yr (VIL) $250/ha/yr (MHIS) $180/ha/yr (AIC) $20/ha/yr (All schemes) $0/ha/yr (VIL) $30/ha/yr (MHIS) $40/ha/yr (AIC) $30/ha (VIL) $60/ha (MHIS) $50/ha (AIC) Preferred Option and Business Case $240/ha/yr (VIL) $360/ha/yr (MHIS) $290/ha/yr (AIC) Analysis of the business case demonstrated that the key variable to the project is real increases in electricity costs. Historically New Zealand has had a 3% annual increase in electricity costs above inflation for the last 40 years. Figure 2 shows the annual cost, in present value, of running a pipe network compared to an open channel scheme if a 3% annual increase of electricity cost is included, and other items are held with no increase above inflation. Based on this, the pipe network option is better value for all three schemes. If there is no real electricity cost rise, then the MHIS pipe network upgrade is not attractive and the AIC pipe network upgrade is marginally worse than Concept 1. When reviewing the options, the MHIS company board preferred the pipe network, even though it was not the lowest cost option for the medium term, because: 1) Over time, the pipe network lowered the cost of pressurised water if there is an increase in the electricity costs. In the case of AIC this is a short term payoff, in the case of MHIS this is a long term payoff. 2) The pipe network met the project drivers better than the upgraded open channels, particularly giving a better level of control, and removed most of the existing open In summary, for all three schemes the respective Boards preferred the pipe network concept, although the AIC project is still being developed and the Board s initial preference for a piped network will depend upon the project contract price and remains subject to shareholder approval. Risks to the Projects The risks to the projects were considered at the concept and preliminary design phases. The common risks across all three projects were: Interest Rates fluctuating. The business cases assumed a 30 year average interest rate of 7.5%. Exchange Rate Fluctuation this will affect pipe supply and installation costs. Oil price the price of pipe is linked to the oil price. This can also be an opportunity (a negative risk), currently the oil price is less than when the estimates were completed. Not all new shares are sold this would reduce the income to the scheme to offset the capital cost for shareholders, and effectively increase the cost per hectare of the capital cost. Point where open channel network is cheaper than a pipe network for AIC Point where open channel network is cheaper than a pipe network for MHIS Figure 2: Graph showing the annual cost, in present value, of a pipe network scheme compared to an open channel scheme, allowing for a real increase of 3% in electricity costs

5 preferred contractor. The final design build tender offer was voted on by the MHIS shareholders in 2014 and fell short of the required 75% majority. Environmental Impacts of the Capital Projects The upgrading of the schemes infrastructure is considered to be a permitted activity by ECan since the water use is not changing. Nonetheless there will still be effects on the environment of the projects, including: Less groundwater recharge. The 15 20% distribution losses are partly due to leakage from the open channels into the ground water. Removing this will reduce groundwater levels, affecting borehole yields and flows in spring fed waterways. Irrigating a greater area, by selling water saved from leakage and bywash, will result in increased farm activity, resulting in economic benefit to the community, but potentially increasing nutrient loadings. The implementation of more efficient practises, as set out in the farm environmental plans, are intended to mitigate this change. Current Status of Capital Project in Valetta Irrigation Scheme The VIS scheme completed construction and commissioning on a pipe network to replace the existing open channels in mid The project included some notable innovations, including: Onsite manufacture of all pipe using PE100, with diameters ranged from 300mm to 1600mm. Transporting the pipe in lengths up to 200m, thereby reducing the number of welds required on site. This saved significant amounts of time and cost. Inclusion of a small hydropower generator on the main pipeline. Current Status of Capital Project in Mayfield Hinds Irrigation Scheme The preliminary design for a pipe network and associated business case, were completed in mid The MHIS Board of Directors approved the project to proceed to the procurement phase via a design and build tender. A request for tender was issued to prequalified consortiums in early 2013, which led to a 12 month value engineering and negotiation period with the The pipeline project is still considered an option by the Board, but several other smaller capital projects are being completed before the pipe network project is revisited. It is likely that a pipe network with a lower level of service, and accompanying lower capital cost, will be presented for the shareholders to vote on. Current Status of Capital Project in the Amuri Irrigation Company s Schemes The developed design of the AIC scheme pipe network has been completed. At time of writing the design and cost estimate were being considered by the company Board. Subject to Board approval, consultation with shareholders and a request for tender to design and build contractors are likely to be the next steps for this project. Comparisons between the Projects on Each Scheme The challenges from regulation and irrigation evolution facing the three schemes are very similar, and the upgrade plans being consider by each of the three solutions have the same key components. However, there are a number schemes that have not elected to install a pipe network to respond to these challenges. There are several factors the make pipe networks possible for these schemes: Sufficient fall across the scheme to generate pressure in a pipe network to remove the need for pumping. Storage can be supplied above the pipe networks if required. The Valetta Irrigation Scheme pipe network is the only capital project that has been completed to date of the three schemes covered in this case study. There are several reasons for this: 1. The farmers on this scheme had not invested in spray irrigation and associated on-farm pumping systems to the same extent as MHIS and AIC. The benefit of pressurised water without pumping was attractive since it avoided the capital expenditure of on-farm pump stations. 2. The Valetta Irrigation Scheme is the smallest of the three considered in this case study. Therefore it was less complex to design a solution that best suited the shareholders requirements and easier to inform the shareholders prior to voting on the capital expenditure.

6 3. The existing shareholders on VIS purchased the new shares resulting from the water savings through the pipe network upgrade. This gave the project greater financial certainty than when shares are sold to new shareholders. Comparisons to the Australian Experience Both Australia and New Zealand irrigators are experiencing pressure to improve water quality and water use efficiency, from regulation and the value of water. There are several key similarities: - The value of water is increasing - The higher costs imposed by regulation and requirements for more efficient irrigation require agricultural practises to become more intensive. There are several key differences between the New Zealand response to: - Heavier soils with less slope leading to greater use of open channels for flow conveyance and much on-farm flood irrigation - Different ownership structures - Power supply costs Conclusions The three schemes presented in this case study have supplied up to three generations of farmers without any significant changes to the scheme infrastructure. Over time, the on-farm land use and irrigation practises and the regulatory environment has changed significantly. This has driven the scheme s respective Boards of Directors to consider how they can improve their schemes to meet the needs of the next generation of farmers. The initial preferred solution for the schemes considered has been to use pipe networks to replace the open channels to meet efficiency and measurement targets required by new regulations and the pressure required by spray irrigation without on-farm pumping. For MHIS the shareholders voted not to proceed with a piped network at the price presented, for VIC the pipe network was accepted and installed and AIC has not yet voted on the solution offered. Pipe networks have the highest capital cost of the options considered, and require selling new shares in the scheme using the water saved to become financially viable. In conclusion, the preferred solution to the current market opportunities is to install a pipe network. However the capital cost of the pipe network still needs to be affordable compared to the current scheme pumping costs. ACKNOWLEDGEMENTS I would like to acknowledge the input David Heiler (Technical Director Water Infrastructure, Beca Ltd) for his extensive effort in delivering the studies for each of the three schemes and in the preparation and review of this paper, and to Andrew Barton (General Manager, Amuri Irrigation Scheme) for his review of this paper.

BEFORE THE HEARING COMMISSIONERS AT CHRISTCHURCH

BEFORE THE HEARING COMMISSIONERS AT CHRISTCHURCH BEFORE THE HEARING COMMISSIONERS AT CHRISTCHURCH In the Matter of: Between: And: A hearing of submissions relating to Proposed Variation 1 to the proposed Canterbury Land and Water Regional Plan New Zealand

More information

DRAFT Assessment of Possible Allocation Approaches

DRAFT Assessment of Possible Allocation Approaches DRAFT Assessment of Possible Allocation Approaches This assessment has been prepared by Bay of Plenty Regional Council staff. It is draft only and does not represent official views. Purpose and scope The

More information

research report The Impact of a Carbon Price on Australian Farm Businesses: Beef Production Australia s Independent Farm Policy Research Institute

research report The Impact of a Carbon Price on Australian Farm Businesses: Beef Production Australia s Independent Farm Policy Research Institute research report June 2011 The Impact of a Carbon Price on Australian Farm Businesses: Beef Production A report prepared by The Australian Farm Institute with funding from Meat & Livestock Australia 2011

More information

CON 509: APPLICATION FOR A RESOURCE CONSENT UNDER THE RESOURCE MANAGEMENT ACT 1991

CON 509: APPLICATION FOR A RESOURCE CONSENT UNDER THE RESOURCE MANAGEMENT ACT 1991 APPLICATION TO USE LAND FOR FARMING ACTIVITY PAGE 1 OF 15 August 2016 CON 509: APPLICATION FOR A RESOURCE CONSENT UNDER THE RESOURCE MANAGEMENT ACT 1991 TO USE LAND FOR A FARMING ACTIVITY WITHIN THE SELWYN

More information

HYDROLOGY, IRRIGATION DEMAND AND SUPPLY: AN INTEGRATED MODELLING APPROACH USING MATLAB

HYDROLOGY, IRRIGATION DEMAND AND SUPPLY: AN INTEGRATED MODELLING APPROACH USING MATLAB HYDROLOGY, IRRIGATION DEMAND AND SUPPLY: AN INTEGRATED MODELLING APPROACH USING MATLAB B.Veendrick and N.F.D. Ward (Pattle Delamore Partners Ltd ) ABSTRACT The environmental effects and performance of

More information

IMPROVING NUTRIENT MANAGEMENT FOR DAIRY FACTORY WASTEWATER LAND TREATMENT SYSTEMS

IMPROVING NUTRIENT MANAGEMENT FOR DAIRY FACTORY WASTEWATER LAND TREATMENT SYSTEMS Brown, J.N., 2016. Improving nutrient management for dairy factory wastewater land treatment systems. In: Integrated nutrient and water management for sustainable farming. (Eds L.D. Currie and R. Singh).

More information

PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name

PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name Balochistan Small Scale Irrigation Project Region SOUTH ASIA

More information

AGRICULTURAL TRADE AND ITS IMPORTANCE

AGRICULTURAL TRADE AND ITS IMPORTANCE AGRICULTURAL TRADE AND ITS IMPORTANCE 1. SOME HISTORICAL REFLECTIONS Since the founding of the Common Agricultural Policy (CAP) in 1959, one of the objectives was to increase productivity and the volume

More information

Acknowledgements. For more information please contact

Acknowledgements. For more information please contact Acknowledgements The Canterbury Certified Farm Environment Plan (FEP) Auditor Manual has been written by Andy Barbati (Environment Canterbury) in collaboration with representatives of the Primary Industry,

More information

Acknowledgements. For more information please contact

Acknowledgements. For more information please contact Acknowledgements The Canterbury Certified Farm Environment Plan (FEP) Auditor Manual has been written by Andy Barbati (Environment Canterbury) in collaboration with representatives of the Primary Industry,

More information

final report Water quality improvement strategy for a processing site

final report Water quality improvement strategy for a processing site final report Project title: Water Quality Improvement Strategy Project code: P.PSH.0449 Prepared by: GHD Date published: July 2010 PUBLISHED BY Meat & Livestock Australia Limited Locked Bag 991 NORTH SYDNEY

More information

ACCORD TWO YEARS ON... SUMMARY. What have we achieved? What do we need to keep working on? SUSTAINABLE DAIRYING WATER

ACCORD TWO YEARS ON... SUMMARY. What have we achieved? What do we need to keep working on? SUSTAINABLE DAIRYING WATER SUSTAINABLE DAIRYING WATER ACCORD A commitment to New Zealand by the dairy sector TWO YEARS ON... SUMMARY What have we achieved? What do we need to keep working on? Foreword This is the second annual progress

More information

PLANNING ASSESSMENT SHEET: FARMING ACTIVITY IN HINDS/HEKEAO CATCHMENT

PLANNING ASSESSMENT SHEET: FARMING ACTIVITY IN HINDS/HEKEAO CATCHMENT APPLICATION TO USE LAND FOR FARMING ACTIVITY IN HINDS/HEKEAO CATCHMENT PAGE 1 OF 11 MAY 2017 PLANNING ASSEMENT SHEET PREPARED FOR FARMING ACTIVTIES WITHIN HINDS/HEKEAO CATCHMENT The Resource Management

More information

SPATE IN GASH BARKA. Findings from the Field

SPATE IN GASH BARKA. Findings from the Field Session 3 SPATE IN GASH BARKA Findings from the Field Ministry of Agriculture and SOS Faim Ian McAllister Anderson for SOS Faim ianmcanderson@aol.com What is the role of spate irrigation in Gash Barka?

More information

Site 31: Gilberton Farm, Tarnbrook

Site 31: Gilberton Farm, Tarnbrook Site 31: Gilberton Farm, Tarnbrook Site Assessment Report Title Figure 1 Map showing general layout Gilberton Farm is located between the watercourses Tarnbrook Wyre and Delph Beck. The land is owned by

More information

1 General questions on zone and catchment management plans

1 General questions on zone and catchment management plans 1 General questions on zone and catchment management plans 1.1 What is a zone plan? The Waikato region is divided into eight zones. There is a separate, non statutory, zone plan for each one. The key purpose

More information

Replacing an old Sewage Treatment Plant

Replacing an old Sewage Treatment Plant Replacing an old Sewage Treatment Plant GILGANDRA S ASSET MANAGEMENT AND FINANCIAL PLANNING JOURNEY Rolly Lawford Director of Works and Technical Services Gilgandra Shire Council Jacqui Hansen Principal

More information

12747/12 ADD 3 KZV/mp 1 DG E 1B

12747/12 ADD 3 KZV/mp 1 DG E 1B COUNCIL OF THE EUROPEAN UNION Brussels, 19 July 2012 Interinstitutional File: 2012/0191 (COD) 12747/12 ADD 3 COVER NOTE from: ENV 630 ENT 182 CODEC 1945 Secretary-General of the European Commission, signed

More information

The Coalition s Policy

The Coalition s Policy The Coalition s Policy Key Commitments A strong agriculture sector will boost Australia s productivity, jobs and exports. The Coalition has delivered a $4 billion Agriculture White Paper that will support

More information

Minimum grade (%) Velocity at full flow (m s 1 )

Minimum grade (%) Velocity at full flow (m s 1 ) 1.6 Pipes Effluent can be conveyed by channels or pipes under gravity or in dedicated pipelines under pressure. If pipes are used, pressure rating, water-hammer and excessive friction losses must be considered

More information

South West Water Strategic Environmental Assessment of Water Resources Plan Summary Document

South West Water Strategic Environmental Assessment of Water Resources Plan Summary Document South West Water Strategic Environmental Assessment of Water Resources Plan 2009 Summary Document Hyder Consulting (UK) Limited 2212959 5th Floor The Pithay All Saints Street Bristol BS1 2NL United Kingdom

More information

Nutrient Budgeting. An Overview of What, How and Why. June 2014

Nutrient Budgeting. An Overview of What, How and Why. June 2014 Nutrient Budgeting An Overview of What, How and Why 2014 Topics to Cover 1. Why the need for nutrient budgets 2. What is OVERSEER? 3. Principles Behind OVERSEER 4. User Inputs 5. Importance of accurate

More information

Criteria for Siting Dams

Criteria for Siting Dams 1 Criteria for Siting Dams 3 Dams including Hout Dam Limpopo Province Dr Nicholas Papenfus PrEng Dams for Africa (Pty) Ltd. Dams for Africa, Suite 499, Private Bag X09, Weltevreden Park, 1715, Gauteng,

More information

Successful Approaches to Reducing Greenhouse Gas Emissions from Australian Agriculture :

Successful Approaches to Reducing Greenhouse Gas Emissions from Australian Agriculture : Successful Approaches to Reducing Greenhouse Gas Emissions from Australian Agriculture : Minimising Loss of Valuable Resources James Shevlin, David Ugalde and Anthony McGregor Australian Greenhouse Office

More information

Plan Change 5 to the Canterbury Land and Water Regional Plan

Plan Change 5 to the Canterbury Land and Water Regional Plan Plan Change 5 to the Canterbury Land and Water Regional Plan Table of contents PART 1 (HOW TO READ THIS DOCUMENT)... 1-1 Introduction... 1-2 Information for the Reader... 1-2 How amendments to the Plan

More information

National Water Demand Management Policy

National Water Demand Management Policy National Water Demand Management Policy Introduction In 1997, the Ministry of Water and Irrigation developed Jordan s Water Strategy and the following four policies, which include: Water Utility Policy;

More information

Australian vegetable-growing farms An economic survey, and

Australian vegetable-growing farms An economic survey, and Australian vegetable-growing farms An economic survey, 2014 15 and 2015 16 Dale Ashton and Aruni Weragoda Research by the Australian Bureau of Agricultural and Resource Economics and Sciences Research

More information

For personal use only

For personal use only Wattle Health Australia Signs HOA with Organic Dairy Farmers of Australia Wattle Health Australia has entered into a non-binding heads of agreement with Organic Dairy Farmers of Australia Pty Ltd, Mason

More information

VIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION. FORM B - ANIMAL FEEDING OPERATIONS (AFOs)

VIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION. FORM B - ANIMAL FEEDING OPERATIONS (AFOs) VIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION FORM B - ANIMAL FEEDING OPERATIONS (AFOs) Department of Environmental Quality Rev. 02-2013 VIRGINIA POLLUTION ABATEMENT (VPA) PERMIT APPLICATION FORM

More information

2015/16 Annual review of Landcorp Farming Limited

2015/16 Annual review of Landcorp Farming Limited 2015/16 Annual review of Landcorp Farming Limited Report of the Primary Production Committee Contents Recommendation 2 About Landcorp Farming Limited 2 Financial performance 2 Transformation of Landcorp

More information

NAIT Scheme. Tag Ordering System Requirements & Options Consultation Paper. March 2013

NAIT Scheme. Tag Ordering System Requirements & Options Consultation Paper. March 2013 NAIT Scheme Tag Ordering System Requirements & Options Consultation Paper March 2013 1 Contents Introduction 4 Document purpose 4 Approval & consultation process 4 Tag ordering: background 6 NAIT 6 AHB

More information

Rising Sun. Scaffold Hill. Flood Risk Assessment

Rising Sun. Scaffold Hill. Flood Risk Assessment Rising Sun Scaffold Hill Flood Risk Assessment August 2010 Contents 1.0 Introduction... 4 2.0 Site Description... 5 3.0 Legislative Framework... 6 4.0 Flood Risk... 10 5.0 Surface Water Drainage... 11

More information

BEFORE THE HEARING COMMISSIONERS

BEFORE THE HEARING COMMISSIONERS BEFORE THE HEARING COMMISSIONERS IN THE MATTER of the Resource Management Act 1991 ( the Act ) AND IN THE MATTER of the Resource Management Act 1991 and the Environment Canterbury (Temporary Commissioners

More information

Innovative Water Management Award

Innovative Water Management Award International Commission on Irrigation and Drainage (ICID) WATSAVE AWARDS 2012 Innovative Water Management Award ----------------------------------------------------------------------------------------------------------------

More information

Proceedings, The Range Beef Cow Symposium XXII November 29, 30, & December1, 2011, Mitchell, NE

Proceedings, The Range Beef Cow Symposium XXII November 29, 30, & December1, 2011, Mitchell, NE Proceedings, The Range Beef Cow Symposium XXII November 29, 30, & December1, 2011, Mitchell, NE Implications of the Ethanol Industry for Cow-Calf Producers Ted C. Schroeder 1 Agricultural Economics Kansas

More information

Farming challenges & farmer wellbeing

Farming challenges & farmer wellbeing Farming challenges & farmer wellbeing 2015 Regional Wellbeing Survey - Farmer Report 1 October 2016 Dominic Peel, Jacki Schirmer, Mel Mylek Introduction This report examines the barriers to farm development

More information

On-Farm Water Management. More Crop Production

On-Farm Water Management. More Crop Production On-Farm Water Management towards More Crop Production Dr. Saeed Nairizi Vice President Hon, ICID Presentation on the Strategy Theme (On-Farm) 61st International Executive Council Meeting, 10 16 October

More information

ORARI-OPIHI-PAREORA ZONE WATER MANAGEMENT COMMITTEE MEETING. Commencing at 1pm. Meeting room 1 Timaru District Council King George Place Timaru

ORARI-OPIHI-PAREORA ZONE WATER MANAGEMENT COMMITTEE MEETING. Commencing at 1pm. Meeting room 1 Timaru District Council King George Place Timaru ORARI-OPIHI-PAREORA ZONE WATER MANAGEMENT COMMITTEE MEETING Commencing at 1pm on Friday 8 June 2012 Meeting room 1 Timaru District Council King George Place Timaru ORARI-OPIHI-PAREORA ZONE WATER MANAGEMENT

More information

THE ROLE OF THE AGRICULTURAL SECTOR IN BIODIVERSITY OFFSETTING

THE ROLE OF THE AGRICULTURAL SECTOR IN BIODIVERSITY OFFSETTING THE ROLE OF THE AGRICULTURAL SECTOR IN BIODIVERSITY OFFSETTING Jussi Lankoski OECD Trade and Agriculture Directorate Environment Division Biodiversity Offsets: Opportunities and challenges for their effective

More information

Farming Challenges and Opportunities

Farming Challenges and Opportunities RURAL Farming Challenges and Opportunities Managing water and nutrient at the farm and paddock scale Roger MacGibbon National Technical Director Opus Rural November 2016 Opus Rural Our Rural team comprises

More information

A. M Shahidi, R. Smith & M. Gillies National Centre for Engineering in Agriculture, University of Southern Queensland, Australia.

A. M Shahidi, R. Smith & M. Gillies National Centre for Engineering in Agriculture, University of Southern Queensland, Australia. Sustainable Irrigation and Drainage IV 115 Seepage rate estimation from total channel control data during periods of shut down: preliminary data quality assessment case study Coleambally irrigation system

More information

BENEFITS FROM IMPROVING FLOOD IRRIGATION EFFICIENCY

BENEFITS FROM IMPROVING FLOOD IRRIGATION EFFICIENCY BENEFITS FROM IMPROVING FLOOD IRRIGATION EFFICIENCY Report of Progress 544 Agricultural Experiment Station Kansas State University, Manhattan Walter R. Woods, Director BENEFITS FROM IMPROVING FLOOD IRRIGATION

More information

Strategic procurement in capital expenditure the use of program management & delivery

Strategic procurement in capital expenditure the use of program management & delivery Strategic procurement in capital expenditure the use of program management & delivery Project Scope Changes Changing Client Needs Environment of Uncertainty Diverse Stakeholder Interests Community Involvement

More information

MEMORANDUM OF COUNSEL FOR THE ENVIRONMENTAL DEFENCE SOCIETY INC. REPLY TO PROPOSED AMENDMENTS TO RULE TT1(j)

MEMORANDUM OF COUNSEL FOR THE ENVIRONMENTAL DEFENCE SOCIETY INC. REPLY TO PROPOSED AMENDMENTS TO RULE TT1(j) BEFORE THE BOARD OF INQUIRY IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER of the Tukituki Catchment Proposal MEMORANDUM OF COUNSEL FOR THE ENVIRONMENTAL DEFENCE SOCIETY INC REPLY

More information

Implications of changing a Friesian dairy system to a Friesian- Jersey crossbred dairy system

Implications of changing a Friesian dairy system to a Friesian- Jersey crossbred dairy system Extension Farming Systems Journal volume 1 number 1 Research Forum 37 Implications of changing a Friesian dairy system to a Friesian- Jersey crossbred dairy system Bill Malcolm 1 and C Grainger 2 1 The

More information

COST AND REVENUES OF DIRECT USE APPLICATIONS

COST AND REVENUES OF DIRECT USE APPLICATIONS Presented at Short Course VI on Utilization of Low- and Medium-Enthalpy Geothermal Resources and Financial Aspects of Utilization, organized by UNU-GTP and LaGeo, in Santa Tecla, El Salvador, March 23-29,

More information

SECTION 6 STORMWATER AND LAND DRAINAGE

SECTION 6 STORMWATER AND LAND DRAINAGE SECTION 6 STORMWATER AND LAND DRAINAGE Final Version, Approved September 2003 Section 6 and Land Drainage Contents 6.1 PERFORMANCE STANDARDS... 2 6.1.1 General... 2 6.2 MEANS OF COMPLIANCE... 3 6.2.1 General...

More information

Global experience of automating irrigation systems

Global experience of automating irrigation systems Global experience of automating irrigation systems Sumith Choy 07 Apr 2016 Agenda 1 Irrigation 2 3 4 5 6 Automation benefits Automation enablers SCADA vs Autonomous Control Case study - On farm productivity

More information

S91 REQUEST FOR A FURTHER APPLICATION AND S92(1) REQUEST FOR FURTHER INFORMATION

S91 REQUEST FOR A FURTHER APPLICATION AND S92(1) REQUEST FOR FURTHER INFORMATION Please Quote File: 39494 JCRA : JWAL 8 December 2017 Tegel Foods Limited C/- Attention: Andrea Brabant Tonkin and Taylor abrabant@tonkintaylor.co.nz Dear Andrea RESOURCE CONSENT APPLICATION APP.039494.01.01

More information

Australian carbon policy: Implications for farm businesses

Australian carbon policy: Implications for farm businesses Australian carbon policy: Implications for farm businesses Australian carbon policy Carbon markets and prices Some CFI case studies Farm business implications Key messages Atmosphere Sequestration Mitigation

More information

RESOURCE CONSENT CRC174931

RESOURCE CONSENT CRC174931 RESOURCE CONSENT CRC174931 Pursuant to Section 104 of the Resource Management Act 1991 The Canterbury Regional Council (known as Environment Canterbury) GRANTS TO: A WATER PERMIT (S14): Gary Thomas Tomes

More information

C.1. Minutes of meeting with DWS

C.1. Minutes of meeting with DWS C.1. Minutes of meeting with DWS G038_REP-01_r2_TH_MvZ_Bokpoort GW abstract Jones & Wagener (Pty) Ltd Engineering & Environmental Consultants Jones & Wagener Engineering & Environmental Consultants 59

More information

INTERNATIONAL FARM MANAGEMENT ASSOCIATION. Background and Features of New Zealand Arable Farming in Canterbury

INTERNATIONAL FARM MANAGEMENT ASSOCIATION. Background and Features of New Zealand Arable Farming in Canterbury INTERNATIONAL FARM MANAGEMENT ASSOCIATION Background and Features of New Zealand Arable Farming in Canterbury SUMMARY: In New Zealand most farms are in sole or family ownership. Climate The island climate,

More information

Land Use Rules in Taupo Jon Palmer & Megan Coup

Land Use Rules in Taupo Jon Palmer & Megan Coup Land Use Rules in Taupo Jon Palmer & Megan Coup Hello I am Jon Palmer I am Megan Coup and This is the Lake Taupo catchment Nitrogen Leaching 101 Nitrate leaching = loss of N down through soil into groundwater

More information

MONITORING EFFECTS OF SOUTHLAND DEMONSTRATION FARM ON STREAM WATER NITRATE

MONITORING EFFECTS OF SOUTHLAND DEMONSTRATION FARM ON STREAM WATER NITRATE MONITORING EFFECTS OF SOUTHLAND DEMONSTRATION FARM ON STREAM WATER NITRATE KC Cameron 1*, HJ Di 1, A Roberts 2, N Beale 1, J Weir 3, and N Borrie 3 1 Centre for Soil and Environmental Research, PO Box

More information

Watercourses and Wetlands and Agricultural Activities

Watercourses and Wetlands and Agricultural Activities Watercourses and Wetlands and Agricultural Activities Watercourses and regulated wetlands can be found throughout New Brunswick, including on agricultural lands. The Clean Water Act defines a watercourse

More information

STORMWATER MANAGEMENT LEGISLATION IN COOK COUNTY (P.A )

STORMWATER MANAGEMENT LEGISLATION IN COOK COUNTY (P.A ) STORMWATER MANAGEMENT LEGISLATION IN COOK COUNTY (P.A. 093-1049) Summary of the Act In November 2004, the responsibility of Stormwater Management* in Cook County was placed under the authority of the MWRDGC

More information

SOME ASPECTS OF AGRICULTURAL POLICY IN AUSTRALIA

SOME ASPECTS OF AGRICULTURAL POLICY IN AUSTRALIA SOME ASPECTS OF AGRICULTURAL POLICY IN AUSTRALIA R. A. Sherwin, Agricultural Attache Australian Embassy, Washington, D. C. Before discussing government programs relating to agriculture in Australia I propose

More information

Estimating the drivers of regional rural land use change in New Zealand

Estimating the drivers of regional rural land use change in New Zealand Estimating the drivers of regional rural land use change in New Zealand Suzi Kerr, Jo Hendy, Kelly Lock and Yun Liang Motu Economic and Public Policy Research, PO Box 24390, Manners Street, 6142, Wellington

More information

Collaborative Management: Community Engagement Process as the Decision Making Process

Collaborative Management: Community Engagement Process as the Decision Making Process Collaborative Management: Community Engagement Process as the Decision Making Process Bryan Jenkins 1 Waterways Centre for Freshwater Management, University of Canterbury and Lincoln University, Private

More information

WASTE MINIMISATION AND LANDFILL LIFE EXPECTANCY AT QUEENSTOWN LAKES DISTRICT COUNCIL

WASTE MINIMISATION AND LANDFILL LIFE EXPECTANCY AT QUEENSTOWN LAKES DISTRICT COUNCIL WASTE MINIMISATION AND LANDFILL LIFE EXPECTANCY AT QUEENSTOWN LAKES DISTRICT COUNCIL William Clifford 1 *, John Cocks 1, Linda Wright 2 1 MWH NZ Ltd; 2 One World Consulting Ltd * P O Box 4, Dunedin, william.m.clifford@mwhglobal.com,

More information

Commentary on Results

Commentary on Results Commentary on Results Number of farms In 2010, there were 139,860 farms in Ireland. This compares to a total of 141,527 farms in 2000. Therefore, the total number of farms decreased by less than 2,000

More information

ENVIRONMENTAL OUTLOOK TO 2050: The consequences of Inaction

ENVIRONMENTAL OUTLOOK TO 2050: The consequences of Inaction Km3 ENVIRONMENTAL OUTLOOK TO 25: The consequences of Inaction Key Findings on Water Around the world, cities, farmers, industries, energy suppliers, and ecosystems are increasingly competing for their

More information

Water Issues in Cyprus

Water Issues in Cyprus Water Issues in Cyprus Sofoclis Aletraris Minister of Agriculture, Natural Resources and Environment 7 July, 2012 Water scarcity and droughts in Cyprus Severe water scarcity problem in Cyprus for centuries

More information

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods. 1 FACTSHEET INTRODUCTION World Water Day, on 22 March every year, is about focusing attention on the importance of water. This year s theme, Nature for Water, explores nature-based solutions (NBS) to the

More information

EVIDENCE OF RICHARD TREVOR de JOUX HEARING THREE ORARI SUB CHAPTER

EVIDENCE OF RICHARD TREVOR de JOUX HEARING THREE ORARI SUB CHAPTER BEFORE THE CANTERBURY REGIONAL COUNCIL In the Matter of The Resource Management Act 1991 Between CANTERBURY REGIONAL COUNCIL And ORARI WATER SOCIETY INCORPORATED Submitter EVIDENCE OF RICHARD TREVOR de

More information

Assessment Schedule 2016 Scholarship Economics (93402)

Assessment Schedule 2016 Scholarship Economics (93402) Scholarship Economics (93402) 2016 page 1 of 9 Assessment Schedule 2016 Scholarship Economics (93402) Evidence Question One Key points A natural monopoly occurs when one firm can supply an entire market

More information

Allocation and cost sharing in agricultural greenhouse gas markets

Allocation and cost sharing in agricultural greenhouse gas markets Allocation and cost sharing in agricultural greenhouse gas markets Suzi Kerr 1 & Levi Timar 2 1 Motu Economic & Public Policy Research, N.Z. 2 GNS Science, Wellington, N.Z. Paper presented at the 2013

More information

Port of Brisbane Stormwater Management

Port of Brisbane Stormwater Management Port of Brisbane Stormwater Management The Port of Brisbane Pty Ltd is committed to managing our activities to help protect our surrounding natural environment and ensuring our Port operations do not adversely

More information

PROGRAMME: A CONSERVING AND RESTORING

PROGRAMME: A CONSERVING AND RESTORING PROGRAMME: A CONSERVING AND RESTORING Project: SDR-A3 Carbon Club Project elements: Landowner led discussion group Energy audits Project description Aim Carbon Club aims to conserve or restore the South

More information

Using Dairy Manure as a Fertilizer Source for Forage Crops. Workgroup. Marsha Campbell Mathews University of California Farm Advisor Stanislaus County

Using Dairy Manure as a Fertilizer Source for Forage Crops. Workgroup. Marsha Campbell Mathews University of California Farm Advisor Stanislaus County Using Dairy Manure as a Fertilizer Source for Forage Crops Marsha Campbell Mathews University of California Farm Advisor Stanislaus County David Crohn University of California Waste Management Specialist,

More information

FLOOD RESPONSE IN THE WAIMAKARIRI DISTRICT

FLOOD RESPONSE IN THE WAIMAKARIRI DISTRICT FLOOD RESPONSE IN THE WAIMAKARIRI DISTRICT Kate Purton (Beca) & Gerard Cleary (Waimakariri District Council) ABSTRACT The Waimakariri District lies to the north of the Waimakariri River in North Canterbury.

More information

Implications of Applying Tukituki River Catchment Plan Change 6 to the Heretaunga Plains

Implications of Applying Tukituki River Catchment Plan Change 6 to the Heretaunga Plains Implications of Applying Tukituki River Catchment Plan Change 6 to the Heretaunga Plains A report for LandWISE Inc. by Rachel Eatherly and Makenzie Read University of Tennessee, Knoxville 24 July 2014

More information

Agriculture, Food and GHGs

Agriculture, Food and GHGs Agriculture, Food and GHGs P A U L M C K I E R N A N C L I M A T E C H A N G E D I V I S I O N D E P A R T M E N T O F A G R I C U L T U R E, F O O D A N D T H E M A R I N E 9 TH O C T O B E R 2 0 1 3

More information

Australian beef. Financial performance of beef cattle producing farms, to Peter Martin. Research report 15.5.

Australian beef. Financial performance of beef cattle producing farms, to Peter Martin. Research report 15.5. Australian beef Financial performance of beef cattle producing farms, 2012 13 to 2014 15 Peter Martin Research by the Australian Bureau of Agricultural and Resource Economics and Sciences Research report

More information

Dams. & Hydropower. Australia, New Zealand and the Pacific

Dams. & Hydropower. Australia, New Zealand and the Pacific Dams & Hydropower Australia, New Zealand and the Pacific World class dam expertise We see a community s interaction with water as part of a holistic system, not a series of independent connections. Now

More information

THAI-AUSTRALIAN NORTHEAST VILLAGE WATER RESOURCE PROJECT

THAI-AUSTRALIAN NORTHEAST VILLAGE WATER RESOURCE PROJECT THAI-AUSTRALIAN NORTHEAST VILLAGE WATER RESOURCE PROJECT Report No. 10 SPRING DEVELOPMENT APPRAISAL NONG SUNG MUKDAHARN June 1987 Kevin Hewison (Sociologist) Graham Jackson (Engineer) TABLE OF CONTENTS

More information

THE N CAP IN TAUPO A FARMER PERSPECTIVE. NZARM/Fert Research Conference 11 June 2012 MIKE BARTON.

THE N CAP IN TAUPO A FARMER PERSPECTIVE. NZARM/Fert Research Conference 11 June 2012 MIKE BARTON. THE N CAP IN TAUPO A FARMER PERSPECTIVE NZARM/Fert Research Conference 11 June 2012 MIKE BARTON. CONTENT An outline of the process leading to capping Nitrogen Emissions from farms in the Taupo catchment

More information

Agri-Service Industry Report

Agri-Service Industry Report Agri-Service Industry Report December 2016 Dan Hassler 2017 U.S. Industry Outlook A little better or a little worse is the quickest way to sum up the expectations for the agricultural equipment industry

More information

VIRGINIA POLLUTION ABATEMENT PERMIT APPLICATION

VIRGINIA POLLUTION ABATEMENT PERMIT APPLICATION VIRGINIA POLLUTION ABATEMENT PERMIT APPLICATION FORM B ANIMAL WASTE Department of Environmental Quality VPA FORM B ANIMAL WASTE INSTRUCTIONS This form is to be completed by applicants requesting a VPA

More information

Public-Private Partnership (PPP) for Transmission Gully Highway

Public-Private Partnership (PPP) for Transmission Gully Highway Public-Private Partnership (PPP) for Transmission Gully Highway Questions and Answers 21 November 2012 Questions and answers on how the NZTA will use a Public-Private Partnership to finance and build the

More information

Teagasc National Farm Survey 2016 Results

Teagasc National Farm Survey 2016 Results Teagasc National Farm Survey 2016 Results Emma Dillon, Brian Moran and Trevor Donnellan Agricultural Economics and Farm Surveys Department, Rural Economy Development Programme, Teagasc, Athenry, Co Galway,

More information

ROOF AND PROPERTY DRAINAGE

ROOF AND PROPERTY DRAINAGE CHAPTER 4 ROOF AND PROPERTY DRAINAGE 4.1 INTRODUCTION... 4-1 4.2 ROOF DRAINAGE SYSTEM... 4-1 4.3 ROOF DRAINAGE DESIGN PROCEDURE... 4-2 4.3.1 Catchment Area... 4-2 4.3.2 Design Average Recurrence Intervals...

More information

Trans-Tasman Mutual Recognition Arrangement. Occupations

Trans-Tasman Mutual Recognition Arrangement. Occupations Trans-Tasman Mutual Recognition Arrangement Occupations Structure of Presentation What is the Trans-Tasman Mutual Recognition Arrangement? Why did we put this scheme in place? How did we go about negotiating

More information

Drainage, Sewerage System, Groundwater and Surface Water drainage

Drainage, Sewerage System, Groundwater and Surface Water drainage Drainage, Sewerage System, Groundwater and Surface Water drainage Summary There are significant impacts to the community from high levels of groundwater on a regular basis. In extreme cases, these can

More information

IRRIGATION WATER MANAGEMENT OPTIONS FOR ALFALFA ABSTRACT

IRRIGATION WATER MANAGEMENT OPTIONS FOR ALFALFA ABSTRACT IRRIGATION WATER MANAGEMENT OPTIONS FOR ALFALFA Larry Schwankl 1, Dan Putnam 2, Khaled Bali 3, and Daniele Zaccaria 4 ABSTRACT All types of irrigation systems, including border strip flood systems, various

More information

Water, Wastewater and Refuse

Water, Wastewater and Refuse Water, Wastewater and Refuse - 116 - Wastewater KEY FACTS Council operates and maintains: 17 wastewater systems 16 wastewater treatment plants (11 ponds, 4 activated sludge plants) 333 kilometres of sewer

More information

What Does It All Mean? CWA? Sara Esposito, P.E. DNREC Division of Watershed Stewardship

What Does It All Mean? CWA? Sara Esposito, P.E. DNREC Division of Watershed Stewardship What Does It All Mean? CWA? Sara Esposito, P.E. DNREC Division of Watershed Stewardship sara.esposito@state.de.us Why are we here? Just like pavement has helped move cars faster; it has also helped water

More information

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS I. POLICY STATEMENT Auburn University's (the University's) "Policy for Natural Resource Management Areas" implements the Campus Master Plan Land Use Element

More information

GERDIE LANDMAN: DON T REINVENT THE WHEEL

GERDIE LANDMAN: DON T REINVENT THE WHEEL In His Voice: GERDIE LANDMAN: DON T REINVENT THE WHEEL We don t need to reinvent the wheel. There are excellent models of farmer development and land reform in South Africa that are highly appropriate

More information

SURVEY OF RURAL DECISION MAKERS: TRUST, GOALS, & MANAGEMENT

SURVEY OF RURAL DECISION MAKERS: TRUST, GOALS, & MANAGEMENT SURVEY OF RURAL DECISION MAKERS: TRUST, GOALS, & MANAGEMENT Pike Brown Senior Economist Capability Leader, Economics and Land Use Modelling SURVEY OF RURAL DECISION MAKERS 1 SURVEY OF RURAL DECISION MAKERS

More information

by Geraud Ramond MAPM RPP & Peter Ratcliffe Bsc CEng MICE

by Geraud Ramond MAPM RPP & Peter Ratcliffe Bsc CEng MICE Oldham and Royton Integrated Strategy (ORIS) UUs 80m project in the Oldham area of Manchester to improve the environment, future-proof wastewater treatment assets and optimise operation and maintenance

More information

WATER QUALITY OFFSETS FRAMEWORK: AN INNOVATION IN WATERWAY REGULATION

WATER QUALITY OFFSETS FRAMEWORK: AN INNOVATION IN WATERWAY REGULATION WATER QUALITY OFFSETS FRAMEWORK: AN INNOVATION IN WATERWAY REGULATION Author: Kate Berg Western Water, Sunbury, VIC, Australia ABSTRACT Western Water has led the development of the Victorian Water Industry

More information

Site 15: Gresgarth Hall, Caton

Site 15: Gresgarth Hall, Caton Site 15: Gresgarth Hall, Caton Site Assessment Report Title Figure 1 Map showing general layout This mill is thought to have been built between 1770 and 1790 as a corn mill, becoming a threshing mill in

More information

and the Environment Canterbury (Temporary Commissioners and Improved Water Management) Act 2010

and the Environment Canterbury (Temporary Commissioners and Improved Water Management) Act 2010 BEFORE THE HEARING COMMISSIONERS IN THE MATTER of the Resource Management Act 1991 ( the Act ) AND IN THE MATTER of the Resource Management Act 1991 and the Environment Canterbury (Temporary Commissioners

More information

NZQA registered unit standard version 4 Page 1 of 5

NZQA registered unit standard version 4 Page 1 of 5 Page 1 of 5 Title Describe drinking-water supply reticulation systems Level 5 Credits 8 Purpose People credited with this unit standard are able to describe: the reticulated services found on public and

More information

Soil and Land Management

Soil and Land Management Soil and Land Management David Scholefield 1 and Phil Haygarth 2 1 Team Leader: Nutrient Flows and System Modelling 2 Deputy Manager: Cross Institute Programme for Sustainable Soil Function David Scholefield

More information

BEFORE THE HEARING COMMISSIONERS. of the Resource Management Act 1991 ( the Act )

BEFORE THE HEARING COMMISSIONERS. of the Resource Management Act 1991 ( the Act ) BEFORE THE HEARING COMMISSIONERS IN THE MATTER of the Resource Management Act 1991 ( the Act ) AND IN THE MATTER of the Resource Management Act 1991 and the Environment Canterbury (Temporary Commissioners

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information