CAPACITY OF THE VICTORIAN ELECTRICITY TRANSMISSION NETWORK TO INTEGRATE WIND POWER

Size: px
Start display at page:

Download "CAPACITY OF THE VICTORIAN ELECTRICITY TRANSMISSION NETWORK TO INTEGRATE WIND POWER"

Transcription

1 CAPACITY OF THE VICTORIAN ELECTRICITY TRANSMISSION NETWORK TO INTEGRATE WIND POWER DECEMBER 2007

2 [ This page is intentionally left blank ]

3 DISCLAIMER The purpose of this document is to provide information about VENCorp s assessment of the technical impacts of wind turbine generation developments in the Victorian shared electricity transmission network. VENCorp has prepared this document in reliance upon information available in the public domain and from a number of third parties (and which information may not have been verified). Anyone proposing to use the information in this document should independently verify and check the accuracy, completeness, reliability and suitability of the information in this document, and the reports and other information relied on by VENCorp in preparing it. VENCorp makes no representation or warranty as to the accuracy, reliability, completeness or suitability for particular purposes of the information in this document. VENCorp and its employees, agents and consultants shall have no liability (including liability to any person by reason of negligence or negligent misstatement) for any statements, opinions, information or other matters (expressed or implied) arising out of, contained in or derived from, or for any omissions from, the information in this document, except in so far as liability under any statute cannot be excluded.

4 CONTENTS EXECUTIVE SUMMARY 5 1 INTRODUCTION Background Objectives Overview of the Report 16 2 A REVIEW OF WIND POWER INTEGRATION INTERNATIONALLY AND NATIONALLY Introduction Global Wind Power Penetration Wind Power Generation Wind Turbine Technology Typical Wind Farm Layout Global Wind Power Experience NEM Wind Power Generation Operational Experiences Summary 26 3 WIND POWER AVAILABILITY AND VARIABILITY Introduction Possible Wind Farms Locations Regional Wind Speed Patterns Average Output and Capacity Factor Output Variability Victorian Average Daily Output Assumptions for the Analysis of Wind Power Generation Output Summary 39 4 ASSESSMENT OF SYSTEM TECHNICAL ISSUES Introduction Study Methodology and Modelling System Study Approach Steady State and Dynamic Analysis System Security Concerns Power Balance and Network Contingencies Power Quality Summary 56 APPENDIX A GLOSSARY 57 APPENDIX B REFERENCES 58

5 EXECUTIVE SUMMARY INTRODUCTION The Victorian Government s VRET (Victorian Renewable Energy Target) scheme 1 mandates that Victoria's consumption of electricity generated from renewable sources be increased to 10% by The new Federal Government has also committed to expand the Mandatory Renewable Energy Target (MRET) scheme to 20% by Wind energy is a significant renewable energy source to meet these targets. VENCorp s Vision 2030 report 3 assumed that a significant amount of wind turbine generation would be one of the generation scenarios required to meet future load growth. It concluded that a separate technical study would be required to examine the implications of integrating wind power generation with the Victorian transmission network. This report forms that technical study. To ensure that the Victorian electricity network can accommodate a significant amount of wind power generation, VENCorp studied the possible technical impact of incorporating wind plant into the Victorian shared transmission network and the National Electricity Market (NEM). KEY OBJECTIVES The key objectives of this study involved: reviewing international and national experiences of integrating wind power generation with the electricity network; investigating the technical impact of wind power generation developments on the Victorian shared transmission network and the NEM; and determining the amount of wind power generation that the Victorian shared transmission network can accommodate. CONTEXT In terms of the report s context, it is important to note that there are a number of challenges affecting the viability of increased Victorian wind power generation, which can be grouped into the following categories: transmission network; system security and operational; market, regulatory and commercial; and 1 Victorian Renewable Energy Act Federal Labor s 20 percent by 2020 Renewable Energy Target, 3 VENCorp VISION 2030 Report 25 year vision for Victoria s Energy Transmission Networks October

6 environmental. This report focuses solely on one of the key challenges, being the capacity of the Victorian transmission network to integrate increased wind power generation. The other three key areas clearly need to be considered when assessing the viability of wind generation, but are beyond the scope of this report. KEY FINDINGS This report s key findings include the following: The viability of wind power generation is subject to other challenges, such as system security and operational, market regulatory and commercial and environmental matters, which need to be considered. With the appropriate technical solutions, wind power generation of approximately 3,000 MW installed capacity (and possibly up to 4,000 MW, depending on where generation is located) can be accommodated by the Victorian transmission network. VENCorp is not proposing to set an absolute limit on the connection of wind power generation. Based on available information, most of the wind power generation in Victoria is expected to be located in the west and south west Victoria. The impact of wind power generation depends on its location (relative to the load) and the strength of the local transmission network. Major concerns relating to integration include the variability of wind and wind forecasting, thermal constraints, voltage control, fault-level control, fault ride-through capability, and the quality of the power supply. Technology is rapidly evolving around various innovative concepts to integrate high levels of wind power generation within the transmission network. A REVIEW OF WIND POWER INTEGRATION (INTERNATIONALLY AND NATIONALLY) Global wind power generation capacity has increased significantly over the last few years, totalling approximately 74,000 MW by the end of This is approximately 235% of the installed capacity in Figure 1 shows a comparison of wind power generation penetration among the top 10 wind power generating countries and Australia. Australia has an installed wind power generation capacity of 975 MW, which is approximately 1.3% of global wind power generation. South Australia has the largest installed capacity of 547 MW. Victoria s installed capacity is 134 MW. Figure 2 shows the rate of increase in the installed capacity of Australian wind power generation. 6

7 Figure 1: Global wind power generation penetration (as at end of 2006) Rest of the World, 13.7% Australia, 1.3% France, 2.1% Portugal, 2.3% Germany, 27.7% UK, 2.6% Italy, 2.9% China, 3.5% Denmark, 4.2% India, 8.4% Spain, 15.6% US, 15.6% Figure 2: Installed capacity growth of Australian wind power generation Installed wind generation capacity (MW) QLD NSW TAS VIC WA SA Total Year The review of the integration of wind power generation internationally and nationally found that the impact of wind farms on the transmission network depends on the: location of wind power plants relative to the load; strength of the transmission network at the point of connection; and correlation between wind power production and load consumption. 7

8 Major concerns relating to wind power generation integration include the variability of wind power and weather/wind forecasting, the fault ride-through capability, and the quality of the power supply. Since most wind power generation is connected to the weaker network and is remote from the major load centres, thermal constraints and voltage control are also significant concerns. However, technology is rapidly evolving around various innovative concepts to integrate high levels of wind power generation within the transmission network. Specific findings regarding the international experience include the following: The variability of wind power generation and weather/wind forecasting is addressed by: utilising special forecasting models that make use of meteorological predictions of wind speed and therefore expected power output; and maintaining a sufficient amount of generation reserve to ensure reliable power system operation, and providing additional network control services to prevent transmission overloading in the event of a powerful wind front. Thermal constraint issues are the same as for other types of generation and are not specific to wind power. Reactive power and voltage control issues are addressed by requiring wind power generation to provide network services, such as voltage control. Where wind power generation offsets conventional generation, additional reactive power sources close to load centers may also be required. Fault ride-through system stability issues are addressed by requiring greater levels of fault ridethrough capability from wind generation for a severe voltage depression due to a system fault. These requirements are now being met by certain newer types of wind turbines, with older models being retrofitted to comply. Some deterioration in system inertia, as wind turbines replace conventional generation, is a possible outcome from increased wind power generation penetration. Transmission network fault levels tend to increase with the connection of more wind turbines. This phenomenon also occurs with the connection of other types of generation, and is generally resolved on a case-by-case basis. Modelling, simulation, and wind turbine model validation issues occur due to confidentiality constraints, which prevent utilities from gaining access to detailed wind turbine models. While high-level studies can use generic wind turbine models to identify general behavior, accurate, validated models are very important for specific connection assessments. Specific findings regarding the national experience include the following: The Electricity Supply Industry Planning Council (ESIPC) in South Australia found that the impact of 400 and 500 MW of wind power should be modest, but that generation of 800 and 1,000 MW presented growing impacts on system reliability, security and price. A number of recommendations to minimise adverse impacts from increased wind power generation integration have been considered, and no absolute limit on wind power generation is recommended. 8

9 NEMMCO found that for high South Australian wind power generation penetration (1,200 MW), the Victoria-South Australia interconnector will not be sufficient to export power from South Australia to Victoria, and Murraylink will have to be used to regulate transfers. Additional reactive support will be required near Adelaide to utilise the interconnector s import capacity. Variability and wind power forecasting issues are being addressed by NEMMCO, which is developing a weather/wind forecasting mechanism for wind power generation. This development falls outside the scope of this report. Frequency control ancillary service usage and costs may increase with the increase in intermittent generation. Voltage control is primarily a local issue. However, additional reactive plants may be required to control voltages at a transmission level. System security and stability issues involving fault ride-through capabilities are an important requirement for all NEM generators. System security assessments may need to consider wind power output variability simultaneously with other credible contingencies. The output of wind power generation in some locations is limited so as to operate the transmission lines within their capability. Modelling, simulation, and wind turbine model validation issues have arisen due to the reluctance of some wind farm proponents to release detailed wind farm models. POSSIBLE WIND FARM LOCATIONS A significant number of locations in Victoria are being identified for possible wind farm developments. Based on publicly available information and information from VENCorp s connection enquiries and applications, most of the wind generation in Victoria is expected to be located in the west and southwest. Figure 3 shows the possible locations of these wind farms. Remote from the major load centres, these locations could possibly be connected to the 500 kv network, the weak 220 kv network, or the lower voltage network. 9

10 Figure 3: Possible wind farm locations and the regions considered 4 THE IMPACT OF WIND FARMS ON THE TRANSMISSION NETWORK Specific findings regarding wind farm impacts on the transmission network relate to the: variability of wind and associated probability factors; variability of wind due to seasonal weather; and assessment of technical issues. The variability of wind and associated probability factors Wind power generation output is subject to local wind conditions. As a result, a key element of the study involved obtaining realistic wind data representing the performance of actual wind power generation plants. Since most of the studies were done on a prospective basis, sufficient wind data were not available. Due to this limitation, and given that output variability is expected to be relatively similar between sites in close proximity, proposed wind farm locations are grouped into five broad regions (as shown in Figure 3). Table 1 lists the range of generation considered and the expected capacity factors 5 in each region. Figure 4 shows the typical output variability in each region, and for Victoria as a whole. This generic 4 Source: Victorian Wind Atlas published by Sustainable Energy Authority, Victoria December 2003 and Wind energy projects in Australia, 10

11 information shows that output variability increases over time. Due to the extreme variability of the wind in all locations, wind farm output can range from the total installed capacity to producing no power, and vice versa. Table 1: Capacity factor of proposed wind farms by region Region Indicative total installed capacity Estimated capacity factor Coastal South West 1,045 MW 35-45% Inland South West 1,010MW 30-39% Central 910 MW 26-37% North West 920 MW 31-41% South East 115 MW 31-39% Figure 4: Wind power variability 30% 25% Output variability (%) 20% 15% 10% 5% 0% Time (hours) NW C ISW CSW SE VIC Figure 4 shows typical (average) variability. Table 2 presents the expected 30-minute and 6-hour variability associated with probability factors of 25%, 50%, 75% and 90% of occurrence. For example, after 30 minutes, there is a 25% chance that the output power at the end of the interval is within 1% of the original output power (and a 90% chance that it is within 20%). Managing significant variation could become an issue, particularly with large amounts of wind power generation. 5 Capacity factor is one element used to measure the productivity of a wind turbine or any other power production facility. It compares the plant's actual production over a given period of time with the amount of power the plant would have produced if it had run at full capacity for the same amount of time. 11

12 Table 2: Maximum normalised variability at different probability factors Probability Level 25% 50% 75% 90% 30-minute variability 1% 4% 11% 20% 6-hour variability 4% 14% 32% 53% The variability of wind due to seasonal weather The daily output of wind power generation is mainly influenced by weather conditions. Figure 5 shows the expected average daily outputs of possible wind farms (for the case of 3,000 MW of installed capacity in Victoria). Summer is the season with the highest average daily output, although spring also shows significant average output. Summer is also the season with the highest average daily variability, with mid to late afternoon output being approximately double the output in the early morning. Autumn is the season with the lowest maximum daily output, with winter experiencing the lowest daily variation. Figure 5: Daily average output of possible Victorian wind farms by season (3,000 MW installed capacity) Output (MW) Time of Day (Hour) Summer Autumn Winter Spring 12

13 The assessment of technical issues The objective of this assessment was to: identify transmission network technical issues associated with the connection of significant wind power generation; and determine the amount of wind power generation that can be accommodated. Detailed system studies assessed the technical impact of wind power generation penetration for demand levels of 4,000 MW, 7,000 MW and 12,000 MW 6. These studies concluded that there is no significant impact on inter-regional power transfer levels. Dynamic reactive plant is likely to be required to manage voltage fluctuations and quality of supply issues. Management of thermal loading and increased fault levels will also become an issue, however, feasible technical solutions can be found to resolve this. Funding arrangements for these solutions will be determined during the connection application process under the National Electricity Rules (the Rules). Table 3 summarises the expected wind power generation technical impacts and possible solutions. Table 3: Expected technical impacts from wind power generation Technical Impact Issues Possible Solutions Thermal loading Fault levels Voltage control Transfer limits Power quality A number of 220 kv and 66 kv lines between terminal stations are likely to overload. Increased wind power generation will increase fault levels. Increased wind generation is likely to result in voltage regulation and fluctuation issues. Significant impacts on existing power transfer limits were not observed. Harmonic distortion, flicker, voltage unbalance and other power quality issues can become issue. Feasible technical and/or operational solutions can be found. Feasible technical solutions can be found to remove fault level constraints. Static and dynamic reactive plant may be needed to manage voltage control and related issues. For thermal loading related issues, feasible technical and/or operational solutions can be found. Feasible technical solutions can be found (see Table 4-12 for more information). Since wind power generation is subject to significant variability over time, an analysis of system security was undertaken over the following time frames: short-term security (up to 5 minutes); medium-term security (up to 30 minutes); and long-term security (over periods of 1-2 hours, 2-4 hours and 4-6 hours). For 4,000 MW of installed capacity (the maximum installed capacity examined by this study), the average estimated power output variability in the: 6 The medium growth scenario 10% POE summer maximum demand forecast for 2016/17 is 11,794 MW source VENCorp 2007 Electricity Annual Planning Report. 13

14 short term is estimated at ±163 MW - on-line thermal and hydroelectric plant can respond to this level of variation, which is within the regulation frequency control ancillary service (FCAS) margin and will not detrimentally impact system operation; medium term (less than 30 minutes) is estimated at ±338 MW - this variability is slightly larger than the regulation FCAS, however, 30 minutes is considered to be long enough for ancillary services to be procured from the market to deal with any excess variability; and long term (6 hours) is estimated at ±940 MW - this variability can be dealt with through the use of ancillary services from the market and/or by switching fast start generation on and off. Given that this variability is based on averages, studies were carried out to develop a variability profile, with the variability defined in terms of the probability of occurrence (see Table 2). At a 90% probability of occurrence (a level of variability that would not be exceeded in 90% of cases, representing a reasonable worst case scenario), it was found that over a: 30-minute period the variability was 20% (±836 MW); and 6-hour period the variability was 53% (±2,195 MW). Scheduling other generation in the NEM to manage the variability over a 6-hour period may become a significant issue. THE AMOUNT OF WIND FARM GENERATION THAT CAN BE ACCOMODATED VENCorp s 2007 Electricity Annual Planning Report forecasts 1,240 MW of installed wind power generation in Victoria by The studies indicate that wind power generation of approximately 3,000 MW installed capacity can be accommodated by the transmission network with appropriate technical solutions, such as improvement of thermal capacity of transmission lines, installation of additional static and dynamic reactive plant and mitigation works for fault level control and quality of supply issues. Increased wind power generation is likely to result in increased transmission network and power system technical issues, which will need to be dealt with progressively. Depending on where it is located, wind power generation of up to 4,000 MW installed capacity may be possible, but this would require further detailed analysis as operational experience is gained, and is subject to addressing any associated power system security and operational issues, which are not the subject of this report. VENCorp is not proposing to set an absolute limit on the connection of wind generation. 14

15 1 INTRODUCTION 1.1 Background VENCorp s Vision 2030 report [1] assumed that a significant amount of wind power generation would be one of the generation scenarios required to meet future load growth. It concluded that a separate technical study would be required to examine the implications of integrating wind power generation with the Victorian transmission network. This report forms that technical study. The Victorian Government s VRET (Victorian Renewable Energy Target) scheme 7 mandates that Victoria's consumption of electricity generated from renewable sources be increased to 10% by 2016 [2]. The new Federal Government has also now committed to expand the Mandatory Renewable Energy Target (MRET) scheme to 20% by Wind energy is a significant renewable energy source to meet these targets. To ensure that the Victorian electricity network can accommodate a significant amount of wind power generation, VENCorp studied the possible technical impact of incorporating wind plant into the Victorian shared transmission network and the National Electricity Market (NEM). Issues involving the physical connection of wind power generation to the transmission network, and the subsequent impact on market operations, were not investigated as part of this study. VENCorp published technical guidelines for connection to the Victorian shared transmission network in October 2006, which deals with the physical connection of new generation plant [3]. Impacts on market operations are dealt with by the National Electricity Market Management Company Limited (NEMMCO). 1.2 Objectives The key objectives of this study involved: reviewing international and national experiences of integrating wind power generation with the electricity network; investigating the technical impact of wind power generation developments on the Victorian shared transmission network and the NEM; and determining the amount of wind power generation that the Victorian shared transmission network can accommodate. In terms of the report s context, it is important to note that there are a number of issues affecting the viability of increased Victorian wind power generation, which can be grouped into the following categories: transmission network issues; system security and operational issues; market, regulatory and commercial issues; and 7 Victorian Renewable Energy Act Federal Labor s 20 percent by 2020 Renewable Energy Target, final.pdf 15

16 environmental issues. This report focuses solely on one of the key areas, being the Victorian transmission network issues resulting from increased wind power generation. The other three key areas clearly need to be considered when assessing the viability of wind generation, but are beyond the scope of this report. 1.3 Overview of the Report In this report: Chapter 2 provides a summary of the review of commonly used wind power generation technology, and the international and national experience with regards to integrating large amounts of wind power generation with the transmission network. Chapter 3 presents the findings from a preliminary investigation of the expected availability and variability of wind power generation in Victoria, for the purpose of assessing the technical impacts on the transmission network. Chapter 4 presents the methodology and findings from studies undertaken to identify the technical issues associated with the integration of increased wind power generation, and to determine the maximum amount of wind power generation that can be accommodated by the Victorian transmission network. Appendix A provides a list of abbreviations used in each chapter. Appendix B lists the references used throughout the document. Studies involving wind availability, wind variability, and the technical impacts of wind power generation, require a number of inputs, such as information about wind profiles, wind power generation outputs, wind turbine types and control mechanisms, and the transmission network. Except for the wind profiles, all other inputs are subject to future connection application proposals. As a result, a number of input assumptions are made for possible wind power generation connections, which are based on information available in the public domain and confidential information received by VENCorp. 16

17 2 A REVIEW OF WIND POWER INTEGRATION INTERNATIONALLY AND NATIONALLY 2.1 Introduction This chapter presents a review of the international and national experience of integrating wind power with the transmission network. This review was undertaken so as to gain a better understanding of the issues associated with greater wind power generation penetration. 2.2 Global Wind Power Penetration Global wind power generation capacity has increased significantly over the last few years, totalling approximately 74,000 MW by the end of 2006 [4]. Denmark, Spain and Germany have so far shown the greatest commitment to wind power generation with the largest addition to their electricity transmission networks. Figure 2-1 shows the global wind power generation penetration of the top 10 wind power generation countries and Australia. Wind power generation penetration in Denmark, Spain and Germany is approximately 24%, 18% and 18% of installed total generation capacity, respectively. In all other countries, wind power generation penetration is less than 5% of total installed generation capacity. Australia has a wind power generation installed capacity of 975 MW, approximately 1.3% of global wind power generation. A significant growth in wind power generation in Australia is proposed. Figure 2-2 shows the growth of wind power generation installed capacity in Australia. Table 2-1 lists the capacity of existing installed wind power generation in each State, along with the total proposed generating capacity [5]. Figure 2-1: Global wind power generation penetration (as at end of 2006) Rest of the World, 13.7% Australia, 1.3% France, 2.1% Portugal, 2.3% Germany, 27.7% UK, 2.6% Italy, 2.9% China, 3.5% Denmark, 4.2% India, 8.4% Spain, 15.6% US, 15.6% 17

18 Figure 2-2: Installed capacity growth of Australian wind power generation Installed wind generation capacity (MW) QLD NSW TAS VIC WA SA Total Year Table 2-1: Existing and proposed wind power generation installations in each State [5,6] State Existing [MW] Proposed [MW] Total [MW] New South Wales 17 1,088 1,105 Queensland South Australia ,710 2,257 Tasmania Victoria 134 2,385 2,519 Western Australia Total 976 5,997 6, Wind Power Generation Wind power generation is variable, its output mainly being influenced by wind speed. This variability occurs within all time frames: seconds, minutes, hours, days, months, seasons, and years. Understanding these variations and their predictability is essential for the efficient integration of wind power generation and the operation of the power system. A typical wind turbine will turn on when the wind speed is sufficient for the turbine to start generating (normally about 3 m/s). The wind turbine will generate the rated power at its rated wind speed and above until it reaches a cut-off wind speed, at which point the wind turbine turns off to prevent damage to its mechanical components. Figure 2-3 shows the typical electric power output curve of a wind turbine. 9 Includes the recently commissioned Lake Bonney Stage 2 wind farm in South Australia. 18

19 Figure 2-3: Typical generated power versus wind speed [7] Normalised power output Wind speed (m/s) 2.4 Wind Turbine Technology Wind turbine technology is rapidly evolving around various innovative concepts to meet the stringent transmission network connection requirements of network operators. The majority of wind turbines in use today can be classified as one of the following four types: 1. Type A - fixed speed wind turbines. This turbine is generally coupled to a squirrel cage induction generator via a gearbox. 2. Type B - limited variable speed wind turbine with variable rotor resistance. A wound rotor induction generator is used with a variable rotor resistor. 3. Type C - variable speed wind turbine with partial-scale frequency converter. This is commonly known as doubly fed induction generator (DFIG). 4. Type D - variable speed wind turbine with full-scale frequency converter. Either a synchronous or an induction generator is used. The Type C wind turbine is the most popular system in the wind power industry. This combines the advantage of the Type A and Type B systems, with advances in power electronics. Table 2-2 summarises the critical performance characteristics of the different wind turbine technologies commonly used in the global wind power industry. 19

20 Table Summary of performance characteristics of wind turbine technologies Wind turbine technology Type A: Type B 10 : Real power fluctuations Tends to create output power fluctuations during wind gusts. Reactive power capability Fault current contribution Inertial support and frequency control Fault ridethrough capability Provides inertial support. Not No. Poor. capable of Additional frequency control. Reactive power sources are needed. Yes. - - Type C: Type D: Less likely to propagate wind variations as power fluctuations. Yes. Capable of regulating reactive power in either direction. Yes for remote fault. Does not provide inertial support. Capable of frequency control support with additional control systems (subject to availability of wind). Good. Better. 2.5 Typical Wind Farm Layout Wind turbines are available in capacities of up to 5 MW with generated voltage levels of up to 1 kv. A typical wind farm layout involves groups of wind turbines being electrically connected to a substation via a feeder network. The substation acts as the interface between the wind power generation and the existing transmission network, with transformers and protection equipment used to ensure that the interface with the transmission network is adequate. The performance of the generation and the quality of the power can be monitored from a control kiosk that is normally located within the substation. Figure 2-4 shows a typical wind farm electrical topology. 10 This technology is dominated by one manufacturer and some of the details are not in the public domain. 20

21 Figure 2-4: Typical wind farm electrical topology 2.6 Global Wind Power Experience Variability of Wind Power and Wind Power Forecasting The load connected to an electricity network is dynamic, and generation varies to match the demand and losses. The system operator is responsible for maintaining a sufficient amount of generation reserve to ensure the reliable operation of the power system. The variability of wind power generation adds another dimension to reserve management by increasing the variability of generation required from other sources. The accuracy of wind power forecasts plays a vital role in the electricity market. Variation in system load is reasonably predictable, making demand forecast errors small when less wind power generation is installed. With more wind power generation, the demand forecast errors may become significant as, unlike demand, wind variations are less correlated with the time of day, and so may require special forecasting models to minimise errors. Danish wind energy views wind power forecasting as the most important element within the process of power system control, and uses a number of models that make use of meteorological predictions in order to predict wind speed and therefore the expected power output from wind power generation. Germany has good experience of wind power forecasting, with forecast errors of roughly 10% for day-ahead forecasts [8] System Security Denmark is often regarded as the model country in wind power generation, with both a high wind power generation penetration level and a high installed wind power capacity level. Disconnection of some of the wind farms to maintain system stability is required for interconnection constraints. A major system incident involving wind power generation occurred in Europe in November After tripping off many high voltage transmission lines in the Union for Coordination of Transmission of Electricity in Europe (UCTE) system, the transmission network was split into three islands, West, North 21

22 East and South Eastern. The event started in the north of Germany on 4 November 2006 and resulted in the loss of supply to more than 15 million European households across Europe. The final report issued on 30 November 2006 by the UCTE titled System Disturbance on 4 November 2006, highlighted issues related to wind power generation. It said: In the over-frequency area (North East), the lack of control over generation units contributed to the deterioration of system conditions in this area (long lasting over-frequency with severe overloading on high voltage transmission lines). Generally the operation of dispersed generation (mainly wind and combined-heat-and-power) during the disturbance complicated the process of re-establishing normal system conditions [10]. In Australia, the approach proposed to optimise the dispatch outcomes is referred to as the semidispatch of non-scheduled generation. Under this proposal, which is currently being considered by the Australian Energy Market Commission (AEMC), the wind farm operators are required to submit NEM bids for generation on a five-minute basis, and wind farm generation output can be limited via the central dispatch process to maintain power system security. When this arrangement has been put in place, the management of potential transmission network element overloading will become more manageable. When a powerful wind front passes across a region, the wind farm outputs can change by significant amounts over short time frames. Such steep wind fronts are not uncommon in South Australia. Under very high wind speeds, wind turbine protection systems can act to shut them down to avoid equipment damage. Under these circumstances it is possible to get very high outputs rapidly followed by very low outputs. The impact can be to require additional network control services in order to prevent transmission network overloading. The analysis and prediction of such events requires a review of historical information about wind farm generation patterns, and an extrapolation based on wind patterns in other locations and on the projected types of generation pattern. The solution proposed by the electricity industry in Australia involves implementing a sophisticated wind and wind power generation forecasting tool, and requiring future wind farms to be fitted with mechanisms to reduce wind power generation output prior to the onset of a wind front. Under very high temperature conditions, wind turbines may trip on over-temperature. In Australia, high demand conditions are typically associated with high temperatures, making the possible loss of wind power generation output at high temperatures a factor in the assessment of supply adequacy Thermal Constraints The location of wind power generation depends on the availability of wind, and is generally concentrated in a specific region in most countries. This geographic concentration causes transmission network thermal constraint issues. As a result, transmission capacity increases may be required to support high levels of wind power generation penetration. Thermal constraints are simple to predict prior to connecting a wind farm, and transmission network augmentation works can be implemented. The thermal constraint issues associated with wind farms are no different from any other type of generation connection, and the issues are not specific to wind generation Reactive Power and Voltage Control Traditionally, transmission network voltage control is undertaken by conventional generators connected to the transmission network. Capacitor banks, synchronous condensers and flexible AC transmission system (FACTS) devices are also used in certain cases, to assist with voltage regulation. Because of its unscheduled nature, wind power generation displaces conventional generation connected to the 22

23 transmission network. Therefore, as the penetration of wind power generation increases, traditional voltage control methods may be insufficient to maintain power system voltages. This is because wind power generation voltage control capability is not the same as traditional synchronous generation. System operators worldwide address this issue by requiring wind generators to provide network services, such as voltage control, as part of the transmission network code connection requirements. Although wind power generation technology has been evolving to provide this support, due to the fact that wind farms are often remotely located, transmission networks may need some additional reactive power sources closer to the load centres. When wind farms are connected to a distribution network, voltage regulation becomes a local issue. European countries with large numbers of wind turbines connected to their distribution networks have developed strategies to regulate reactive power and thus voltage at a distribution level. A similar approach could be applied in Victoria to manage reactive power and voltage control Frequency Control The concept of frequency control support from wind turbines has emerged with increasing wind power generation penetration levels. The pitch controlled variable speed wind turbine is inherently capable of the continuous control of output power [8]. However, the maximum power limit is governed by the availability of wind. The publication Primary Frequency Control Participation Provided by Doubly Fed Induction Wind Generators [11] provides a control system capable of continuous output regulation for generation of this type. When a power system needs frequency regulating services from wind turbines for under-frequency conditions, pitched control variable speed wind turbines can be partly loaded, based on the availability of wind. Additional electrical power is generated during a disturbance by pitching the wind turbine s blades to obtain the maximum power available from the wind. However, this operation depends heavily on the availability of wind Fault Ride-through and System Stability With the growth of wind power generation, it has become common for transmission network codes to demand the provision of greater fault ride-through capability from wind power generation for a severe voltage depression due to a system fault. The National Electricity Rules (the Rules) contain strict requirements in relation to ride-through capability, and therefore more modern technologies are likely to be used. Type A wind turbines are often incapable of fault ride-through, requiring a significant amount of additional dynamic reactive power (SVC or STATCOM) support to remain connected to the transmission network during a disturbance and so avoid stalling or tripping. Tripping off of wind turbines, due to system fault-induced voltage dips, may cause power imbalances between the load and the generation after clearing the fault, resulting in frequency deviations that may jeopardise system stability if sufficient numbers of units trip. However, wind turbine manufacturers have developed the Type C and Type D wind turbines to meet the ride-through requirements imposed by transmission network codes. Most old technology wind turbines connected to the European transmission network have been retrofitted to facilitate successful fault ride-through capability. System inertia plays a major role in damping oscillations after a disturbance. Typically, the combined inertia range of wind turbine generating units is from 2-6 MJ/MVA. This is comparable with conventional generating units. However, in the case of variable speed wind turbines (the most popular on the market), the kinetic energy stored in the rotating blades will not contribute to the inertia of the 23

24 transmission network, as the rotational speed is decoupled from the transmission network frequency by a power electronic converter [12]. As a result, and as wind turbines increasingly replace conventional generation (which has greater inertia), system inertia may deteriorate System Fault Level Transmission network fault levels tend to increase with the connection of more wind turbines. This phenomenon also occurs with the connection of other types of generation, and is generally resolved on a case-by-case basis Modelling, Simulation and Model Validation of Wind Turbines With the development of wind turbine technology, complex control techniques are applied to wind turbines to enhance their performance and to meet stringent transmission network code connection requirements. Certain aspects of a wind turbine s performance, such as fault ride-through capability, cannot be easily tested in the field unless the unit has experienced a real fault. Different wind turbine manufacturers have developed their own control models to represent wind turbine operations. Transmission network operators and service providers are particularly interested in dynamic models of wind turbines, because this enables simulation of the wind turbine s performance during disturbances. This requirement is included in transmission network codes, and the Rules. A computer simulation s validity depends on the accuracy of the models used. As models become more complex and different user-specific models become available, validation of wind turbine models becomes more important. Due to confidentiality constraints, however, complete details of these models may not be accessible. This leads to a risk of using un-validated or partial models that do not represent the true performance characteristics. For high-level studies, generic wind turbine models available in power system simulation software can be used to identify general behaviour, but accurate, validated models are extremely important for the assessment of specific connections. 2.7 NEM Wind Power Generation Operational Experiences Australia s wind power generation installed capacity is 975 MW, more than half of which is located in South Australia. As per the wind energy projects listed by the Australian Wind Energy Association, the proposed wind power generation capacity is expected to rise significantly over the next few years to a total of approximately 7,000 MW [5]. A number of investigations were undertaken into operational issues involving existing wind farms, and power system issues with increased levels of wind power generation. Some of the investigations relevant to large scale integration of wind power generation include the following: The Electricity Supply Industry Planning Council (ESIPC) of South Australia published a series of findings and recommendations in April 2005, in relation to the broader market and transmission network operation implications of significant wind power generation in South Australia [13]. The key conclusions include the following: The impact on power system security with 400 and 500 MW of wind power generation should be modest. The report states that there are risks to be managed at this level of wind power generation, which are only expected to occur on rare occasions. Wind power generation of 800 and 1,000 MW raises concerns, under the current arrangements, with growing impacts on power system reliability, security and price. 24

25 ESIPC does not recommend an absolute limit to wind power generation. The report states that the impact on the power system will result in progressively rising risks as penetration increases. A number of recommendations are made for the minimisation of any adverse impacts due to the integration of large-scale wind power generation. NEMMCO commissioned a study of the potential risks relating to high levels of wind power generation in South Australia in 2005 [14]. The report found that with high wind power generation penetration (1,200 MW), the Victoria-South Australia interconnector would not be sufficient to export power from South Australia to Victoria, and that Murraylink would have to be used to regulate power transfers. It was also noted that the interconnector s import capacity will rely on additional reactive power support near Adelaide. The impact of wind generation in South Australia will have a negligible effect on the transient stability of other interconnectors. In regards wind variability and wind power generation forecasting, the Federal Government has entered into an agreement with NEMMCO to manage the development and implementation of an Australian Wind Energy Forecasting System. NEMMCO is in the process of developing a suitable mechanism [15]. The usage and cost of frequency control ancillary services (FCAS) is likely to increase with increased intermittent generation, and the associated likelihood of an increase in the uncontrolled variation of generation levels [16]. NEMMCO and certain other network service providers (NSPs) have raised issues related to voltage control involving: flicker and other power quality issues; additional wear on voltage control equipment, such as transformer on-load tap changers and switched capacitors; and the possible requirement for additional network voltage control plants or network voltage control services. These are primarily local issues and have been effectively addressed in other countries. Additional reactive plant may be required, however, to control voltages at the transmission level. Fault ride-through capability in the event of transmission faults is an important requirement for all generation in the NEM, including wind farms. The variability in wind power generation output may need to be considered simultaneously with other credible contingencies when assessing system security. NEMMCO raises the concern about the adequacy of monitoring interconnector flows on a five-minute basis, as currently occurs. NEMMCO suggests that if sub-five-minute variations are significant, the existing process may need to be reviewed and modified. The Tasmanian power system incident on 25 November 2006, where the Woolnorth wind farm tripped off during a fault that was distant from the wind farm itself, was raised as an example of the importance of stringent fault ride-through requirements. The output of wind power generation in some locations is limited, so as to operate transmission lines within their capability. 25

26 Some wind farm proponents are reluctant to release accurate wind farm models. Simplified models have not always proven to be satisfactory and, in some cases, have indicated stability issues that are not evident with more accurate models. The complexity of the models has also made it more difficult to perform due diligence on network limit equations involving wind farms. In a number of cases, special control schemes, such as special voltage control schemes, run back schemes and generator dispatch limiting schemes, have been implemented. 2.8 Summary The impact of wind power generation on the transmission network depends on the location of wind power generation relative to the load, and the correlation between wind power production and load consumption. Major concerns relating to wind power generation integration into the transmission network include the variability of wind power generation and wind power generation forecasting, fault ride-through capabilities, and the quality of the power supply. Since many wind power generators are connected to the extremities of the network and are remote from the major load centres, thermal constraints and voltage control are also significant concerns. Wind turbine technologies, wind forecasting methodologies, and transmission network technologies, however, are rapidly evolving around various innovative concepts, enabling the integration of high levels of wind power generation. 26

27 3 WIND POWER AVAILABILITY AND VARIABILITY 3.1 Introduction This chapter presents the findings from a preliminary investigation of the expected capacity factors 11 and output variability of proposed Victorian wind farms. The intention of this investigation is to gain a greater understanding of the expected availability and variability of wind power, for the purpose of assessing the technical impacts on the transmission system. A more detailed analysis of wind farm availability and variability would have required wind data from the identified wind farms over a longer period of time and the provision of more appropriate wind turbine characteristics for the purposes of modelling. Section 3.7 provides a summary of the assumptions made in the conduct of this preliminary investigation. 3.2 Possible Wind Farms Locations Possible wind farm locations [5] are scattered around Victoria, with the majority in the west and the south west (as shown Figure 3-1). For the purpose of this investigation, possible wind farms, which are in relatively close proximity, have been grouped into regions. Possible wind farm locations and their regional groupings are listed in Table 3-1 and shown in Figure 3-2. Table 3-1: Regional groupings of existing and possible wind farms Region Existing/possible wind farm Indicative total installed capacity Coastal South West (CSW) Portland Nirranda Macarthur 1,045 MW Ryan Corner / Hawkesdale Codrington / Yambuk (existing) Inland South West (ISW) TGTS Mortlake Berrybank Close to Ballarat Winchelsea 1,010 MW Shelford (near Winchelsea) Mt Gellibrand Colac Central (C) Mt Mercer Werribee Baynton Around 50 km from South Morang along South 910 MW Morang-Dederang 330 kv line Around 100 km from South Morang along South Morang-Dederang 330 kv line North West (NW) Concongella Hill 920 MW Crowlands / Glen Lofty Challicum Hills (existing) 11 Capacity factor is one element used to measure the productivity of a wind turbine or any other power production facility. It compares the plant's actual production over a given period of time with the amount of power the plant would have produced if it had run at full capacity for the same amount of time. 27

28 Region Existing/possible wind farm Indicative total installed capacity South East (SE) Mount Misery Waubra BETS 66 kv Wonthaggi / Toora (existing) Dollar 115 MW 28

29 Figure 3-1: Map of possible wind farm locations considered in the study 13 29

30 Figure 3-2: Map of possible regions considered in the study Regional Wind Speed Patterns In order to analyse load duration and wind power generation output variability, a number of assumptions have been used. The significant assumptions are summarised towards the end of this chapter (see Section 3.7 for more information). From the available historical wind data, Figure 3-3 shows the indicative spatial distribution of diurnal wind speed patterns for the selected regions in Victoria. Since data was not available at each of the proposed wind farm locations, normalised diurnal 13 wind speed patterns have been created to show the daily average variation of wind speed around the mean wind speed, rather than looking at absolute values. 12 Source: Victorian wind Atlas (Sustainable Energy Authority, Vic), A diurnal wind speed pattern refers to the variation in wind speed that occurs with the transition from day to night. 30

NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017

NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 Published: July 2017 IMPORTANT NOTICE Purpose AEMO has prepared this report in accordance with clause 3.13.6A(a) of the National Electricity

More information

WIND TURBINE PLANT CAPABILITIES REPORT

WIND TURBINE PLANT CAPABILITIES REPORT WIND TURBINE PLANT CAPABILITIES REPORT 2013 Wind Integration Studies Published by AEMO Australian Energy Market Operator ABN 94 072 010 327 Copyright 2013 AEMO AEMO 2013 WIND TURBINE PLANT CAPABILITIES

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

POWER SYSTEM STABILITY GUIDELINES

POWER SYSTEM STABILITY GUIDELINES PREPARED BY: DOCUMENT REF: Planning PSSG-02 VERSION: 1.0 DATE: 25 May 2012 FINAL Final Matt Zema CEO Date 25/ 5 /2012 Version Release History VERSION DATE AUTHOR PEER REVIEW APPROVED COMMENTS 1.0 25/5/12

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

WESTERN VICTORIA RENEWABLE INTEGRATION PROJECT SPECIFICATION CONSULTATION REPORT

WESTERN VICTORIA RENEWABLE INTEGRATION PROJECT SPECIFICATION CONSULTATION REPORT WESTERN VICTORIA RENEWABLE INTEGRATION PROJECT SPECIFICATION CONSULTATION REPORT Published: April 2017 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about potential network

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying

More information

SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: December 2016 IMPORTANT NOTICE Purpose The purpose of this publication is to provide information about renewable

More information

SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: November 2017 IMPORTANT NOTICE Purpose The purpose of this publication is to provide information to the South Australian

More information

RECOMMENDED TECHNICAL STANDARDS FOR GENERATOR LICENSING IN SOUTH AUSTRALIA ADVICE TO ESCOSA

RECOMMENDED TECHNICAL STANDARDS FOR GENERATOR LICENSING IN SOUTH AUSTRALIA ADVICE TO ESCOSA RECOMMENDED TECHNICAL STANDARDS FOR GENERATOR LICENSING IN SOUTH AUSTRALIA ADVICE TO ESCOSA Published: 31 March 2017 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide advice to the Essential

More information

FORECASTS AND KEY INFLUENCING FACTORS FOR GRID SUPPLIED ENERGY

FORECASTS AND KEY INFLUENCING FACTORS FOR GRID SUPPLIED ENERGY FORECASTS AND KEY INFLUENCING FACTORS FOR GRID SUPPLIED ENERGY November 2016 NSW PRESENTED BY NICOLA FALCON MANAGER SUPPLY PLANNING SLIDE 1 CHANGING NATURE OF THE AUSTRALIAN ELECTRICITY INDUSTRY Market

More information

Ergon Energy Corporation Limited

Ergon Energy Corporation Limited Ergon Energy Corporation Limited Request for Information Emerging Distribution Network Limitations in the Palm Island Area 1 May 2012 Disclaimer While care was taken in preparation of the information in

More information

MAY 1, Variable Generation Integration Costs

MAY 1, Variable Generation Integration Costs MAY 1, 2014 Variable Generation Integration Costs Executive Summary The addition of variable generation (wind and solar) to the electrical system introduces additional costs associated with unit dispatch

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

Bulk Power System Integration of Variable Generation - Program 173

Bulk Power System Integration of Variable Generation - Program 173 Program Description Program Overview Environmentally driven regulations such as state-mandated renewable energy standards and federal air and water standards, along with improved economic viability for

More information

Review of AEMO s PSCAD Modelling of the Power System in South Australia

Review of AEMO s PSCAD Modelling of the Power System in South Australia Review of AEMO s PSCAD Modelling of the Power System in South Australia Prepared by For Reference Ranil de Silva Director of Engineering Power Systems Consultants Australian Energy Market Operator Operational

More information

Terms of Reference AG 2017/01

Terms of Reference AG 2017/01 Long-term Analysis of the Chilean National Electricity System Considering Variable and Intermittent Energy Resources Terms of Reference AG 2017/01 February 2017 Index 1. Introduction... 2 2. Objectives

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS

SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: July 2017 IMPORTANT NOTICE Purpose The South Australian Advisory Functions are independent reports prepared by the Australian

More information

ENABLING EMBEDDED GENERATION

ENABLING EMBEDDED GENERATION APRIL 2014 ENABLING EMBEDDED GENERATION Turning Australian electricity on its head WHAT IS EMBEDDED GENERATION? Energy supply systems around the world are being transformed by embedded (or distributed)

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Black Start Strategy

Black Start Strategy Issue 1 Revision Black Start Strategy Produced in accordance with Standard Condition C16 of the NGET Transmission Licence Effective from 1 st April 2017 to 31 st March 2018 DOCUMENT HISTORY Version 1.0

More information

Managing a High Penetration of Renewables A Tasmanian Case Study

Managing a High Penetration of Renewables A Tasmanian Case Study Managing a High Penetration of Renewables A Tasmanian Case Study 1 1. Background The Tasmanian power system has been rapidly evolving over the past 15 years with increasing levels of renewables penetration

More information

System Management Standard. System Restart Services. (System Restart Standard)

System Management Standard. System Restart Services. (System Restart Standard) System Management System Management Standard System Restart Services (System Restart Standard) This Standard is a guide to the acquisition of System Restart Services. 1 October 2014 Table of contents 1.

More information

Impacts of the Decentralized Wind Energy Resources on the Grid

Impacts of the Decentralized Wind Energy Resources on the Grid 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Impacts of the Decentralized Wind Energy Resources on the Grid Babak Enayati, PhD, Senior

More information

2 November Project Manager Queensland Renewable Energy Expert Panel PO Box 15456, City East Queensland Online:

2 November Project Manager Queensland Renewable Energy Expert Panel PO Box 15456, City East Queensland Online: 2 November 2016 Project Manager Queensland Renewable Energy Expert Panel PO Box 15456, City East Queensland 4002 Level 22 530 Collins Street Melbourne VIC 3000 Postal Address: GPO Box 2008 Melbourne VIC

More information

SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT

SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT Published: September 2017 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about the levels of system strength required to securely

More information

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION Published: AUGUST 2016 DRAFT REPORT CONSULTATION ON AMENDMENTS TO THE WIND ENERGY CONVERSION MODEL (ECM) GUIDELINES

More information

GRID CODE FOR ISOLATED SYSTEMS

GRID CODE FOR ISOLATED SYSTEMS 1 GRID CODE FOR ISOLATED SYSTEMS Susana Ludovino REDE ELÉCTRICA NACIONAL, S.A., 1749-061 Lisboa, PORTUGAL (e-mail: susana.ludovino@ren) Abstract The aim of this study is to verify the application of an

More information

Presentation Overview

Presentation Overview Innovative Short-Term Wind Generation Prediction Techniques Michael Negnevitsky Cameron Potter School of Engineering Presentation Overview Introduction: Global Wind Power Market Wind Power in Tasmania

More information

State of the Ar t. May Utility Wind Integration Group. American Public Power Association. Edison Electric Institute

State of the Ar t. May Utility Wind Integration Group. American Public Power Association. Edison Electric Institute Utility Wind Integration State of the Ar t Prepared By: Utility Wind Integration Group in cooperation with American Public Power Association Edison Electric Institute National Rural Electric Cooperative

More information

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission

More information

Summary of Studies on Rate of Change of Frequency events on the All-Island System

Summary of Studies on Rate of Change of Frequency events on the All-Island System Summary of Studies on Rate of Change of Frequency events on the All-Island System August 212 Authored by: Salim Temtem & Karen Creighton Checked by: David Cashman & Raymond Skillen Approved by: Jonathan

More information

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: 1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call

More information

Integrating variable renewables: Implications for energy resilience

Integrating variable renewables: Implications for energy resilience Integrating variable renewables: Implications for energy resilience Peerapat Vithaya, Energy Analyst System Integration of Renewables Enhancing Energy Sector Climate Resilience in Asia Asia Clean Energy

More information

Black Start Procurement Methodology

Black Start Procurement Methodology Issue 1 Revision Black Start Procurement Methodology Produced in accordance with Standard Condition C16 of the National Grid Transmission Licence Effective from 1 st April 2017 to 31 st March 2018 DOCUMENT

More information

Roadmap for Demand Response in the Australian National Electricity Market

Roadmap for Demand Response in the Australian National Electricity Market DRAFT Roadmap for DR in the Australian NEM Roadmap for Demand Response in the Australian National Electricity Market December 2006 The Australian Team International Energy Agency Demand Side Management

More information

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS TITLE: GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS DOCUMENT STATUS: FINAL REVISION: DATE: 1 21 September 2015 2015 Electricity Networks Corporation trading

More information

Comparison of compliance results obtained from the various wind farm standards used in Australia

Comparison of compliance results obtained from the various wind farm standards used in Australia Paper Number 50, Proceedings of ACOUSTICS 2011 Comparison of compliance results obtained from the various wind farm standards used in Australia Jonathan Cooper (1), Tom Evans (1) and Luis Najera (2) (1)

More information

R2 TESTING GUIDELINE. PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013

R2 TESTING GUIDELINE. PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013 PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013 Version Release History Version Date By Approved By Changes 0.1 June 2013 BB MS This document has been created by

More information

Renewable Integration at ERCOT

Renewable Integration at ERCOT Renewable Integration at ERCOT Dan Woodfin Director of System Operations ERCOT CIGRE Chile September 12, 2016 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external

More information

Lower Mornington Peninsula Supply Area

Lower Mornington Peninsula Supply Area Non Network Options Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including options and technical characteristics of non-network options

More information

The Australian National Electricity Market

The Australian National Electricity Market The Australian National Electricity Market Iain MacGill (Joint Director, Engineering) EVN Training Program UNSW, September 2007 CEEM established to formalise growing shared research interests + interactions

More information

EDF and Integration of Distributed Energy Resources

EDF and Integration of Distributed Energy Resources IEEE Power Engineering Society Tuesday, June 20, 2006. Montreal EDF and Integration of Distributed Energy Resources Bruno Meyer (presenter) Director Power Systems Technology and Economics Yves Bamberger,

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

Essential Reliability Services Task Force

Essential Reliability Services Task Force Essential Reliability Services Task Force A Concept Paper on Essential Reliability Services that Characterizes Bulk Power System Reliability October 2014 I Table of Contents Preface... ii Executive Summary...

More information

Dalrymple substation upgrade

Dalrymple substation upgrade Dalrymple substation upgrade RIT-T: Project Specification Consultation Report ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,

More information

Sensitivity Analysis Of The National Electricity Market

Sensitivity Analysis Of The National Electricity Market Sensitivity Analysis Of The National Electricity Market C. A. Baloi, J. A. Belward and M. Bulmer University of Queensland, Australia (s007678@student.uq.edu.au) Abstract: This paper presents a sensitivity

More information

DEMAND TERMS IN EMMS DATA MODEL

DEMAND TERMS IN EMMS DATA MODEL DEMAND TERMS IN EMMS DATA MODEL Published: September 2016 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about regional demand definitions, as at the date of publication.

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Accommodating High Levels of Distributed Energy Resources

Accommodating High Levels of Distributed Energy Resources Accommodating High Levels of Distributed Energy Resources John Moura, Director of Reliability Assessment and System Analysis 2017 NARUC Winter Committee Meetings February 14, 2017 About NERC: Mission To

More information

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Suite 2B, 08 Arnold Road, Rosebank, 2196, Johannesburg, South Africa Tel: +27 11 447 9852; Website: http://www.espcg.com Transaction advisory

More information

Initial Plant Assessment Report

Initial Plant Assessment Report Initial Plant Assessment Report Modelling and Optimisation Report (Public Release Version) RATCH-Australia Collinsville Solar Thermal Power Station www.ratchaustralia.com 1 P a g e Contents Introduction...

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: June 2016 IMPORTANT NOTICE Purpose AEMO has prepared this document in connection with its national transmission planning

More information

Impact of small solar PV on the NSW wholesale electricity market. Approved for Public Release 12 October 2017

Impact of small solar PV on the NSW wholesale electricity market. Approved for Public Release 12 October 2017 Impact of small solar PV on the NSW wholesale electricity market Approved for Public Release 12 October 2017 Disclaimer This report (Report) has been produced by Energy Synapse Pty Ltd ABN 34 616 603 082

More information

MARKET ANCILLARY SERVICE SPECIFICATION ISSUES PAPER

MARKET ANCILLARY SERVICE SPECIFICATION ISSUES PAPER MARKET ANCILLARY SERVICE SPECIFICATION ISSUES PAPER Published: January 2017 2017 Australian Energy Market Operator Limited. The material in this publication may be used in accordance with the copyright

More information

Review of Load Following Ancillary Service Quantity Requirements

Review of Load Following Ancillary Service Quantity Requirements Review of Load Following Ancillary Service Quantity Requirements Presentation to MAC Meeting 12 December 2012 by Brendan Clarke DM# 9973825 Topics for Today 1 Drivers for Review Now 2 System Frequency

More information

Comparison of Variable Speed Wind Turbine Control Strategies

Comparison of Variable Speed Wind Turbine Control Strategies Comparison of Variable Speed Wind Turbine Control Strategies S. Arnaltes Department of Electrical Engineering Escuela Politécnica Superior, Universidad Carlos III de Madrid Avda. Universidad 30, 8911 Leganés

More information

ADVICE TO COMMONWEALTH GOVERNMENT ON DISPATCHABLE CAPABILITY

ADVICE TO COMMONWEALTH GOVERNMENT ON DISPATCHABLE CAPABILITY ADVICE TO COMMONWEALTH GOVERNMENT ON DISPATCHABLE CAPABILITY Published: September 2017 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide advice to the Commonwealth Government on matters

More information

RENEWABLE ENERGY JOBS: FUTURE GROWTH IN AUSTRALIA 2017 SUPPLEMENT. Climate Council of Australia

RENEWABLE ENERGY JOBS: FUTURE GROWTH IN AUSTRALIA 2017 SUPPLEMENT. Climate Council of Australia RENEWABLE ENERGY JOBS: FUTURE GROWTH IN AUSTRALIA 2017 SUPPLEMENT Climate Council of Australia ACKNOWLEDGEMENTS Thank you for supporting the Climate Council. The Climate Council is an independent, crowd-funded

More information

Least cost combination of renewable generators, storage devices and transmission system in the NEM

Least cost combination of renewable generators, storage devices and transmission system in the NEM 21st International Congress on Modelling and Simulation, Gold Coast, Australia, 29 Nov to 4 Dec 2015 www.mssanz.org.au/modsim2015 Least cost combination of renewable generators, storage devices and transmission

More information

N O R T H W E S T E R N E N E R G Y M O N TA N A W I N D I N T E G R A T I O N S T U D Y

N O R T H W E S T E R N E N E R G Y M O N TA N A W I N D I N T E G R A T I O N S T U D Y N O R T H W E S T E R N E N E R G Y M O N TA N A W I N D I N T E G R A T I O N S T U D Y Submitted to: NorthWestern Energy 40 E. Broadway Butte, MT 59701 June 1, 2011 Prepared by: Andre Shoucri, B.Eng,

More information

MJA Energy Consulting and Modelling

MJA Energy Consulting and Modelling MJA Energy Consulting and Modelling Marsden Jacob Associates (MJA) provides economic, financial, strategic and public policy advice. Our strong reputation is based on consistent delivery of value to clients:

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

PJM Interconnection, L.L.C. ( PJM ) submits hereby submits its responses to the United

PJM Interconnection, L.L.C. ( PJM ) submits hereby submits its responses to the United PJM Interconnection, L.L.C. 2750 Monroe Boulevard Audubon, PA 19403 Jacqulynn B. Hugee Associate General Counsel T: (610) 666-8208 F: (610) 666-8211 jacqulynn.hugee@pjm.com Via WPTORFI@ee.doe.gov Hoyt

More information

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA Hannes Agabus 1, Ivo Palu 2 1 Estonian National Gird (Estonian TSO), grid analyst, doctoral student, M.Sc, Address: Kadaka tee 42, Tallinn 12915,

More information

Coal cost projections

Coal cost projections Coal cost projections Approach and risks to coal cost projections May 2016 Strategy with substance www.woodmac.com Background and Objectives Coal cost projections AEMO oversees system security of the National

More information

Operational Constraints Update 13/07/2017

Operational Constraints Update 13/07/2017 Operational Constraints Update 13/07/2017 Key Updates No updates Disclaimer EirGrid plc, the Transmission Operator (TSO) for, and SONI Limited, the TSO for Northern, make no warranties or representations

More information

TasNetworks Transformation Roadmap 2025

TasNetworks Transformation Roadmap 2025 DRAFT TasNetworks Transformation Roadmap 2025 JUNE 2017 Trusted by our customers to deliver today and create a better tomorrow 2 TasNetworks Transformation Roadmap 2025 June 2017 Purpose We deliver electricity

More information

Dispatching Variable Generation Resources

Dispatching Variable Generation Resources Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch

More information

Integration of Large Offshore Wind Power into Energy Supply

Integration of Large Offshore Wind Power into Energy Supply Integration of Large Offshore Wind Power into Energy Supply Dipl.-Ing. Bernhard Ernst Dr.-Ing. Martin Hoppe-Kilpper Dipl.-Ing. Kurt Rohrig Institut für Solare Energieversorgungstechnik Königstor 59 34119

More information

Solar Integration into the PJM Grid

Solar Integration into the PJM Grid Solar Integration into the PJM Grid Ken Schuyler Manager, Renewable Services PJM Interconnection September 14, 2017 Integrating Solar in PJM PJM Background PJM Initiatives to Address Impacts Analysis of

More information

System Management Action Flagging Methodology Statement

System Management Action Flagging Methodology Statement System Management Action Flagging Methodology Statement Effective Date: 01 April 20172018 Version Number: 910.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission

More information

A-Lab Innovation Frame 2: The wholesale markets are designed for renewable energy Research Context

A-Lab Innovation Frame 2: The wholesale markets are designed for renewable energy Research Context A-Lab Innovation Frame 2: The wholesale markets are designed for renewable energy Research Context 1.1 Background Australia s National Electricity Market (NEM) is one of the most complex and sophisticated

More information

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection 7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej

More information

BALANCING CODE NO. 1 (BC1)

BALANCING CODE NO. 1 (BC1) Paragraph No/Title BALANCING CODE NO. 1 (BC1) PRE GATE CLOSURE PROCESS CONTENTS (This contents page does not form part of the Grid Code) Page Number BC1.1 INTRODUCTION... 1 BC1.2 OBJECTIVE... 1 BC1.3 SCOPE...

More information

100% Renewables in Australia:

100% Renewables in Australia: 100% Renewables in Australia: A Research Summary by Dr Jenny Riesz*, Dr Ben Elliston, Dr Peerapat Vithayasrichareon, Assoc. Prof. Iain MacGill Centre for Energy and Environmental Markets University of

More information

Phasor measurement units gain credibility through improved test and calibration standards

Phasor measurement units gain credibility through improved test and calibration standards Phasor measurement units gain credibility through improved test and calibration standards Smart grid; PMU calibration position 1 The North American interconnection, or electric transmission grid, is a

More information

Integrating Variable Renewable Energy into the Grid: Sources of Flexibility Best Practices and Case Studies

Integrating Variable Renewable Energy into the Grid: Sources of Flexibility Best Practices and Case Studies Integrating Variable Renewable Energy into the Grid: Sources of Flexibility Best Practices and Case Studies Jessica Katz, Jaquelin Cochran, Michael Milligan National Renewable Energy Laboratory December

More information

Price separation observation during Haywards HVDC filter outages commencing 7 March Event No: 3229

Price separation observation during Haywards HVDC filter outages commencing 7 March Event No: 3229 Price separation observation during Haywards HVDC filter outages commencing 7 March 2016 Event No: 3229 Version Date Change 1.0 15/3/2016 Initial Issue Position Date Prepared By: System Operator 15/3/16

More information

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Magni Þ. Pálsson, Trond Toftevaag, Member IEEE, Kjetil Uhlen, Member IEEE, John Olav Giæver Tande SINTEF Energy Research

More information

WWSIS - 3: Western Frequency Response and Transient Stability Study

WWSIS - 3: Western Frequency Response and Transient Stability Study WWSIS - 3: Western Frequency Response and Transient Stability Study GE Energy Nicholas W. Miller (PM) Miaolei Shao Slobodan Pajic Rob D Aquila NREL Kara Clark (PM) NERC ERSTF Briefing Atlanta December

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

South Australian Department of the Premier and Cabinet

South Australian Department of the Premier and Cabinet Report to South Australian Department of the Premier and Cabinet Potential for Renewable Energy in South Australia 11 May 2009 Ref: J1754 Report V1 Project Team Ross Gawler Walter Gerardi Antoine Nsair

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

Grid Code Review Panel Paper Future Frequency Response Services. Paper by National Grid

Grid Code Review Panel Paper Future Frequency Response Services. Paper by National Grid Grid Code Review Panel Paper Future Frequency Response Services Paper by National Grid 1.0 Executive Summary 1.1 During the past 18 months, National Grid has been working with industry representatives

More information

LARGE WIND FARM AGGREGATION AND MODEL VALIDATION MULUMBA PROSPER PANUMPABI THESIS

LARGE WIND FARM AGGREGATION AND MODEL VALIDATION MULUMBA PROSPER PANUMPABI THESIS LARGE WIND FARM AGGREGATION AND MODEL VALIDATION BY MULUMBA PROSPER PANUMPABI THESIS Submitted in partial fulfillment of the requirements for the degree of Master of Science in Electrical and Computer

More information

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE GERHARD HACKL 1 HERWIG RENNER 2 MANFRED KRASNITZER 3 CHRISTIAN HOFBAUER 1 ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE Abstract The paper describes the process of

More information

Appendix 3.1: The Need for a Second North South Electricity Interconnector. A4 appendix.indd 4 25/05/ :59

Appendix 3.1: The Need for a Second North South Electricity Interconnector. A4 appendix.indd 4 25/05/ :59 Appendix 3.1: The Need for a Second North South Electricity Interconnector A4 appendix.indd 4 25/05/2015 13:59 North-South 400kV Interconnection Development The Need for a second North-South Electricity

More information

Grid Power Quality Improvement and Battery Energy Storage in Wind Energy System by PI and Fuzzy Based STATCOM Controller

Grid Power Quality Improvement and Battery Energy Storage in Wind Energy System by PI and Fuzzy Based STATCOM Controller Grid Power Quality Improvement and Battery Energy Storage in Wind Energy System by PI and Fuzzy Based STATCOM Controller Suhashini.D 1, Ambika.A 2 1 PG Scholar, Department of EEE, Sri Sairam Engineering

More information

Adrian Constable Asia Pacific Microgrid Manager

Adrian Constable Asia Pacific Microgrid Manager Adrian Constable Asia Pacific Microgrid Manager Integrating Renewable Energy in Distributed Power Networks Adrian Constable Asia Pacific Microgrid Manager Caterpillar Inc Agenda 1. Caterpillar in the Power

More information

Best Practices in Conducting Grid Integration Studies

Best Practices in Conducting Grid Integration Studies GREENING THE GRID Best Practices in Conducting Grid Integration Studies ENHANCING CAPACITY FOR LOW EMISSION DEVELOPMENT STRATEGIES (EC-LEDS) Agenda and Learning Objectives Part 1: Why conduct a grid integration

More information

Procurement Guidelines

Procurement Guidelines Procurement Guidelines Effective Date: 01 April 20172018 Version Number: 1516.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission Licence Procurement Guidelines

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

Technical Requirements for Distributed Generation Connection

Technical Requirements for Distributed Generation Connection Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting

More information

Wind power in modern power systems

Wind power in modern power systems J. Mod. Power Syst. Clean Energy (2013) 1(1):2 13 DOI 10.1007/s40565-013-0012-4 Wind power in modern power systems Zhe CHEN (&) Abstract In recent years, wind power is experiencing a rapid growth, and

More information