1 12.0 WASTE MANAGEMENT EU Legislation such as: This section addresses the subject of waste management for the proposed installation of a new dryer and evaporator at Lakeland Dairies Co-operative Society Limited (Bailieboro) Lear, Bailieboro, Co. Cavan. Waste management is addressed for both the construction and operational phases of the project. Council Directive 1999/31/EC, on the landfill of waste. Council Decision 2003/33/EC, establishing criteria and procedures for the acceptance of waste at landfills pursuant to Article 16 of Annex II to Directive 1999/31/EC. European Waste Catalogue - Council Decision 94/3/EC (as per Council Directive 75/442/EC) Introduction Hazardous Waste List - Council Decision 94/904/EC (as per Council Directive 91/689/EEC). European Waste Catalogue and Hazardous Waste List, 2002, Environmental Protection Agency, Wexford. A site specific Construction Waste Management Plan (CWMP) will be prepared for the construction phase of the development in advance of the commencement of the construction works. Similarly an Operational Waste Management Plan (OWMP) will be prepared for the operational phase of the proposed development. This will ensure proper management and significant recycling of wastes generated at the proposed development. Statutory Instruments (as amended) such as: Waste Management Act 1996 (S.I. No. 10 of 1996) as amended by the Waste Management (Amendment) Act 2001 and Regulations including: Implementation of both the CWMP and the OWMP will help ensure the management of waste at the proposed development is undertaken in accordance with the Waste Management Plan for the North East Region, the most recent version of which was completed between Table 12.1 Waste Management (Amendment) Act 2001 and Regulations No. Waste Management (Amendment) Act 2001 and Regulations 12.2 Methodology 1 Waste Management (Collection Permit) Regulations S.I No. 820 of 2007 as amended 2008 (S.I No 87 of 2008). Waste Management (Facility Permit and Registration) Regulations, S.I No. 821 of 2007 as amended 2008 (S.I No. 2 This section assesses the waste management effects of the proposed development at the Lakeland Dairies Bailieboro facility. The types of wastes that are expected to be generated during the operational and construction phase of this project are identified in this section. The management of these different types of waste is also outlined of 2008). Waste Management (Licensing) Regulations 2000 (S.I 185 of 2000) as amended 2002 (S.I 336 of 2002) Waste Management (Hazardous Waste) Regulations Waste Management (Packaging) Regulations 2003 (S.I. No. 61 of 2003) An extensive document review was completed to assist in identifying current and future requirements for waste management, including the following; Waste Management (Landfill Levy) Regulations 2002 (S.I 86 of 2002) Waste Management (Planning) Regulations 1997 (S.I. 137 of 1997) Local Government Act 1994 and Regulations Taking Stock and Moving Forward, DoEHLG, 2004 A Resource Opportunity, Waste Management Policy in Ireland, DoECLG, WEEE Directive 2002/96/EC and Regulations Litter Pollution Act 1997 and Regulations. Changing Our Ways; A Policy Statement on Waste Management, DoEHLG, 1998 County of Cavan (Collection, storage and presentation of waste and certain related waste management matters) 11 Preventing and Recycling Waste Delivering Change, DoEHLG, 2002 Bye-Laws 2008 Making Ireland s Development Sustainable Review, Assessment and Future Action, World Summit on Sustainable Development, 2002 Local Authority Plans such as: Best Practice Guidelines on the Preparation of Waste Management Plans for Construction and Demolition Projects, Department of the Environment, Heritage and Local Government (DoEHLG), Construction and Demolition Waste Management a handbook for Contractors and Site Managers, FÁS and the Waste Management Plan for the North East Region (current plan for the region due for review) Cavan County Development Plan Construction Industry Federation, Characterisation of Building Uses, US EPA; and National Waste Database Reports , Environmental Protection Agency, Wexford. It is a policy of Cavan County Council to continue to encourage recycling and the minimisation of waste and to work with the community in the provision of recycling facilities. Also to ensure towns and villages have an adequate solid waste collection system. The council will also facilitate the provision of recycling banks in easily accessible locations. Environmental Impact Statement (EIS) Lakeland Dairies Co-Operative Society Ltd - Lear, Bailieborough, Co. Cavan 123
2 (CWMP)&(CEMP) A Construction Waste Management Plan (CWMP) has been developed as part of the Contractor s Construction Environmental Management Plan (CEMP) which defines a structured approach to the management, and recycling of waste on-site and identifies licensed waste management contractors. The waste contractor that currently services Lakeland Dairies Bailieboro has a valid waste collection permit, issued by the National Waste Collection Permit Office (NWCPO) for all of the waste types collected and transfers the waste to permitted and/or licensed facilities. It is anticipated that the proposed new development will be services by the same/similar licensed waste contractor. The CWMP objective is to provide better control of the regulatory risks relating to materials and wastes generated on-site with the result that any queries from the EPA can be dealt with effectively. This has been prepared as per the Best Practice Guidelines Projects on the Preparation of Waste Management Plans for Construction and Demolition Projects which is available from the Department of Environment, Community and Local Government. These guidelines outline, among other recommendations that waste can be minimised by: 1. Ensuring the correct volume of materials is ordered for the work to be undertaken and storing the materials appropriately to avoid contamination or deterioration; 2. Co-ordinating with other contractors or developers in the supply of materials and services to avoid repeated deliveries or excavations; and 3. Ensuring when preparing contracts for demolition and construction operations that clauses are included requiring the reuse of materials where practicable Construction and Demolition Waste Management a handbook for Contractors and Site Managers published by FÁS and the Construction Industry Federation in 2002 was also referenced. In the absence of specific guidelines at present on the preparation of operational waste management plans, the OWMP for the proposed development will be prepared in accordance with best practice, legal and industry standards and with due regard to the requirements of the Waste Management Act 1996, the Waste Management Plan for the North East Region and the Cavan County Development Plan Characteristics of the Proposed Development The proposed development will consist of the following: An extension to the existing Dryer facility to contain a new Dryer Plant with a total floor area of 3,516m 2 on 5 floors with a total height above ground level of 40.00m. The new dryer building will incorporate a full height fire escape stairs and full height lift shaft. An extension to the existing Dryer building to contain 2 no. Evaporators with a total floor area of 1,325m 2 on 3 floors and occasional access platforms, with a total height above ground level of 31.27m. An extension to the existing milk powder silo area to incorporate new milk powder silos and milk powder handling with a total floor area of 387m 2 on 3 floors, with a total height above ground level of 24.21m. An extension to the existing Bagging Area to contain additional bagging area and electrical control panels with a total floor area of 170 m 2 on two floors, highest height above ground level of 10.96m. All associated local underground drainage and miscellaneous site works including a 480m 3 covered water tank. The external metal cladding of all new construction will match the existing colour and type of existing metal cladding. Revised Traffic Arrangements New Car Parking Spaces New Security Hut. Revised Traffic Arrangements Receiving Environment In terms of waste management, the baseline environment is largely defined by Cavan County Council as the local authority responsible for setting and administering waste management activities in the area. This is largely governed by the requirements set out in the Waste Management Plan for the North East Region The Plan addresses all areas of waste management from waste prevention and minimisation to its collection treatment, recovery and final disposal Potential Impacts Construction Phase The construction phase will result in the generation of surplus waste materials such as off-cuts from timber, tiles, insulation wiring, packaging and general waste. Packaging and oversupply of materials could also contribute to waste during these phases. The Plan is guided by international, EU and Irish Legislation and policy on waste management. The plan has set a number of targets for the region in terms of recycling, energy recovery and landfilling. The majority of this waste will be reused and recycled if possible, with the remaining waste materials being disposed of by licensed waste contractors to an approved landfill site in accordance with the relevant national and EU legislation. The site is within the Cavan administrative area. In terms of waste management, the receiving environment is characterised by waste collection services provided by a number of private waste contractors. Environmental Impact Statement (EIS) Lakeland Dairies Co-Operative Society Ltd - Lear, Bailieborough, Co. Cavan 124
3 The main waste streams that will be generated by the construction activities at the site are: Table 12.2: Typical Waste Types and EWC Codes Stones and soil Concrete, brick, tiles and ceramics Steel Tar and tar products Plasterboard Metal Cardboard (packaging) Plastic (wrapping, packaging) Waste wood Paper Waste electrical and electronic components Batteries Wood Preservatives Liquid Fuels Excavated Material. It is envisaged that all spoil generated during the site preparation excavation process mostly comprising topsoil and subsoil will, where feasible, be reused in the landscaping and levelling of the site during construction. Contractors will be required to submit and adhere to a method statement indicating the extent of the areas likely to be affected and demonstrating that this is the minimum disturbance necessary to achieve the required works. Where stripping occurs, the resulting excavated fractions will be separated into subsoil and topsoil stockpiles. Temporary storage of spoil will be managed to prevent accidental release of dust and uncontrolled surface water run-off which may contain sediment etc. Operators used to transport any waste off site for land filling will need to hold valid Waste Collection Permits and the waste disposal facility must have a waste licence also. Main C & D Waste Categories The European Waste Codes (EWC) for typical waste materials expected to be generated during the construction of the proposed development are provided in Table 12.2 Waste Material EWC Non Hazardous Concrete, bricks, tiles, ceramics Wood, glass and plastic Bituminous mixtures, tar and tarred products Iron and Steel Metals (including their alloys) Soil and stones Gypsum-based construction material General Waste 2003 Hazardous (Construction and Operational) Electrical and Electronic Components 1602 Batteries 1606 Wood Preservatives 0302 Liquid Fuels 1307 Laboratory Waste 1605 Printer ink cartridges 2001 Oils 1305 Fluorescent tubes 2001 Potential Hazardous Waste Arising Fuels used during the construction phase are classed as hazardous. It is anticipated that there will be some fuel stored on the site for machinery and construction vehicles. All fuel tanks and draw-off points will be bunded. If the fuel is correctly contained and bunded, it is not expected that there will be any fuel wastage at the site or related contamination of soil. Waste mixtures on C & D sites can often contain dangerous substances classifying the material as hazardous waste. This material cannot be used as fill on sites even if a waste licence is held. Disposal can only be undertaken at a licensed hazardous waste facility. Environmental Impact Statement (EIS) Lakeland Dairies Co-Operative Society Ltd - Lear, Bailieborough, Co. Cavan 125
4 Operational Phase General non-hazardous and hazardous waste that may be generated at the proposed development may include the following: Paper and Cardboard Plastic Metals Chemicals containing dangerous detergents, etc Fluorescents tubes and other mercury containing waste; Batteries; Waste electrical and electronic equipment (WEEE) Wastewater Sludge Generated from the Extra 300m 3 of wastewater generated. These will ensure the waste arising from the development is dealt with in compliance with the provisions of the Waste Management Act as amended, and associated Regulations, the Litter Act of 1997 and the Waste Management Plan for the North East Region, and achieve optimum levels of reduction, re-use and recycling. Waste Management: Policies and Practices Production and associated activities at the proposed facility will unavoidably generate waste. The facility implements an Environmental Management System (ISO Cert Reg No. GB05/64056), which includes the management and minimisation of waste by setting a series of objectives and targets to reduce resource / material use and waste production where feasible Construction Phase The potential impacts of the operational phase on the environment are that, should an OWMP not be put in place on the site, the development would lead to the quantities and volumes of waste described in the previous section being sent to landfill, with low levels of segregation of wastes into recyclable materials. There may also be litter pollution created from incorrect storage of waste. However the OWMP will ensure that the environmental impact of the operational phase of the development will be imperceptible and long term. The construction phase will begin with initial soil excavation in preparation of the site foundations. This work is expected to last for approximately months (up to and including commissioning the new dryer). Waste Management will form part of the overall Environmental Management Plan for the Construction Phase. This plan will be implemented by the Management Contractor for the entirety of the construction activities and will include specific detail relating to waste segregation and disposal as summarised below. The Construction Waste Management Plan identifies waste streams requiring segregation for further reuse or recycling off site. This will particularly focus on opportunities to re-use or recycle excavation and construction waste. To ensure compliance Process Waste The process effluent for the project has similar characteristics to the existing effluent loads and it is expected that there will be a discharge increase of 300m 3 per day to the existing wastewater treatment plant. The WWTP has been upgraded in 2010 and with legislation, waste streams will be kept in a separate skip and will be appropriately demarcated. Mitigation measures proposed to manage impacts arising from waste generated during construction of the proposed development is summarised below and is described in more detail in the CWMP: planning for a new clarifier has been granted to cater for the increase in flow. Due to the upgrade works the wastewater treatment plant will have the capacity to deal with additional volumes treated. Currently approximately 850m 3 of wastewater is generated on site, and with the extension to the facility this will be increased to 1150m 3 /day On site segregation of all waste materials into appropriate categories including: Top-soil, subsoil, bedrock Concrete, bricks, tile, ceramics, plasterboard Tar and tar products 12.6 Mitigation Measures Metals, Dry Recyclables e.g. cardboard, plastic, timber This section details the mitigation measures that will be implemented in order to ensure that the waste generated on the site is handled in a legally compliant manner, and that significant levels of reuse, recovery or recycling are achieved. Paints, sealants, hazardous chemicals During the design process, a number of measures will be applied to design out and therefore prevent waste arising on-site. A site specific CWMP has been developed and an OWMP will be developed to ensure effective waste management and recycling of wastes generated at the site, in accordance with the legislation and prevailing best practice. Contractors will be required to supply separate labelled skips for plastic, cardboard packaging waste and other waste materials they generate themselves. Subcontractors will also be required to follow the site construction Waste Management Plan and will be advised of such at tender stage and pre-appointment meetings. Environmental Impact Statement (EIS) Lakeland Dairies Co-Operative Society Ltd - Lear, Bailieborough, Co. Cavan 126
5 The regulation of the waste management and segregation will be overseen by the site agent and safety officers and all of the construction management team in general. All waste will be stored in skips or other suitable receptacles in a designated area of the site; wherever possible, leftover materials (e.g. timber off cuts) and any suitable demolition materials will be reused on-site; Uncontaminated excavated material (top-soil, sub soil, etc) will be re-used on site in preference to importation of clean fill, where possible; All waste leaving site will be recycled, with the exception of those waste streams where appropriate recycling facilities are currently not available In line with the principles of sustainable development, the scheme will seek to minimise the amount of materials brought into the construction site. This will be achieved by re-using as much of the materials generated during demolition activities as possible, provided that they satisfy the specific engineering standards. The majority of new materials brought to site will be used immediately or will be stored on-site within the site boundary. Other materials such as asphalt or concrete will be brought directly to the construction site from the relevant batching plant as and when required and immediately placed Operational Phase All waste leaving the site will be transported by suitable permitted contractors and taken to suitably permitted/licensed facilities; The OWMP will enable the facility to contribute to the targets outlined in the Waste Management Plan for the North East Region and to comply with the byelaws for commercial waste. All waste leaving the site will be recorded and copies of relevant documentation maintained; The site manager will investigate whether nearby construction sites may require fill material, to both minimise the costs of transport and to reuse as much material as possible. The CWMP will also include: the identification of measures to prevent nuisance; the organisation of the contractor s approach to waste management including permit details (etc.); the identification of disposal sites; the identification of quantities to be excavated and disposed of; The operation phase will generate a range of mostly non-hazardous wastes with some hazardous wastes. Segregation at the source will be practiced for waste generated on site (in accordance with the OWMP to be developed for the site). Mitigation measures proposed to manage impacts arising from waste generated during operation of the proposed development are summarised below and will be described in more detail in the OWMP: On-site segregation of all waste materials into appropriate categories including: - organic waste e.g sludge - cardboard and paper - plastic - packaging waste - metals the identification of the amounts intended to be stored temporarily on-site and the location of such storage; - mixed non-recyclables the identification of intended transport means for materials; - empty plastic drums (containing residues of or contamination by dangerous substances) procedures for dealing with Waste Management including liaison with third parties, statutory bodies, undertakers - landscaping waste and other companies; - Non-hazardous WEEE procedures for the provision of documentation necessary to instigate and maintain an Environmental Management All waste materials will be stored in bins or other suitable receptacles in a designated, easily accessible area of the System (EMS); site/buildings. procedures for the control of off-site activities associated with the Waste Management Plan; and All waste leaving site will be recycled, with the exception of those waste streams where appropriate recycling facilities are procedures for the management review/audits to monitor and demonstrate control over the implementation of the currently not available CWMP No damaged packaging will be accepted on site. Hazardous waste may be generated following the return of packaging (drums) from customers. If the returned drums are found to be unsuitable for re-use, they will be classed as a waste. If the packaging contains residues of or is contaminated Importing Materials by dangerous substances, it may be classed as a hazardous waste (depending on the volume and concentration of contaminants). Any waste classed as hazardous will be stored in a designated area and will be removed off site by a The proposed development will have a requirement for imported materials, primarily comprising stone for below the licensed hazardous waste contractor buildings, concrete for road kerbs, concrete yard areas and building and steel for the buildings. All waste leaving the site will be transported by suitable permitted contractors and taken to suitably licensed or permitted facilities All waste leaving the site will be recorded and copies of relevant documentation maintained. Environmental Impact Statement (EIS) Lakeland Dairies Co-Operative Society Ltd - Lear, Bailieborough, Co. Cavan 127
6 12.7 Predicted Impacts with Mitigation Construction Phase There will be a short-term impact associated with the construction phase of the development. Due to the high level of recycling that will be achieved during the construction phase through the implementation of the CWMP, it is envisaged that the environmental impact will be short term and imperceptible. It should be noted that it is proposed to reuse as much as possible of the soil and stones generated from excavations in the landscaping of the area. Although it is anticipated that the majority of spoil generated in excavations will be reused on site, any excess clean material may be disposed of at the designated infill site. A section V has been granted by Cavan County Council for an infilll site along the western boundary of the Lakeland Dairies Bailieboro facility. Figure 12.1 Detailed Layout of the Infill site along the Western boundary levels of waste reduction, re-use and recycling. The predicted impact of the operational phase will be long term and imperceptible. The Do-Nothing Scenario Under a do nothing scenario there would be no development, hence no additional waste management from the existing situation would be required. The Worst-Case Scenario The worst-case scenario, is that, should a CWMP and OWMP not be implemented, the target recycling rates outlined in the Waste Management Plan, Government policy document Changing Our Ways, 2001 will not be achieved. In addition, if waste is not managed and stored correctly on site, this may lead to litter or pollution issuess on the site or adjacent sites. However this is thought to be unlikely having taken into consideration the mitigation measures outlined above Monitoring Monitoring requirements for the development will be stipulated in the OWMP and the CWMP. This will include the requirement for recording of all waste materials arising at the site and maintenance of contractor waste collection permits and facility permits/licences on site. Sludge movements and spreading from the increase in the production will be in accordance with Nutrient Management Plans and be monitored in accordance with Licence Requirements Operational Phase The proposed development will give rise to a wide variety of waste streams during the operational phase. Provided that the OWMP is implemented fully, no significant impacts are predicted for the operational phase. The mitigation measures, i.e. the implementation of the OWMP for the development will ensure the waste arising from the development is dealt with in compliance with the provisions, the prevailing legislation and best practice and achieve optimum Environmental Impact Statement (EIS) Lakeland Dairies Co-Operative Society Ltd - Lear, Bailieborough, Co. Cavan 128
GREENACRE RESIDENTIAL DAC. Chonaill Bradley Environmental Consultant CB/17/9461WMR01. Report Prepared For. Report Prepared By.
CONSTRUCTION & DEMOLITION WASTE MANAGEMENT PLAN FOR A PROPOSED RESIDENTIAL DEVELOPMENT AT CITY WEST, DUBLIN 24 FORTUNESTOWN LANE & GARTER LANE RESIDENTIAL DEVELOPMENT Report Prepared For GREENACRE RESIDENTIAL
More informationDevelopment for further replacement of Fossil Fuel with Alternative Fuels and for use of Alternative Raw Materials
Waste Management Introduction The principal objective of sustainable resource and waste management is to use material and energy resources more efficiently, to reuse, recycle and recover material and reduce
More informationWaste Management Policy
Waste Management Policy Contents 1. Introduction 2. Policy Statement 3. Policy Objectives 4. Application 5. Organisation and Management 6. Glossary of Terms Document Control Information: Last updated on:
More informationMANAGEMENT OF THE INSTALLATION. Attachment C. Cadbury Ireland Limited, Rathmore Installation Rathmore Installation IPPC Licence Application
MANAGEMENT OF THE INSTALLATION Cadbury Ireland Limited, Project Ref: OES1061_01 EPA Export 25-07-2013:19:20:35 Cadbury Ireland Limited, July 2006 Site Management and Control Cadbury Ireland Limited manufactures
More informationMANAGEMENT OF THE INSTALLATION
MANAGEMENT OF THE INSTALLATION Cadbury Ireland Limited Project Ref: OES1061_01 EPA Export 25-07-2013:21:15:11 Site Management and Control Cadbury Ireland Limited manufactures and distributes over 25 products
More informationReference Number: (For office use only) GBR
Application for Waste Carrier Registration Address: Environment and Resources Authority Environmental Permitting Unit Hexagon House, Spencer Hill, Marsa. MRS 1441. Malta. Telephone: 2292 3500 E-mail: waste.carriers@era.org.mt
More informationSydney Port Botany Terminal 3 Project Waste Management Plan
Civil Works Construction Contract Phase 1 1/20 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP
More informationAssessing the costs and benefits of reducing waste in construction
Assessing the costs and benefits of reducing waste in 20 new build timber-framed houses Value Percentage of 1.36m cost Cost saving potential 21,470 1.58% Additional costs to achieve these savings TOTAL
More informationChapter 6 Objective: Protect and Enhance the Environment
Chapter 6 Objective: Protect and Enhance the Environment 49 Irish Water Water Services Strategic Plan Our Strategic Aims Ensure that Irish Water services are delivered in a sustainable manner which contributes
More informationViridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton
Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management
More informationGuidance on the Standards for Storage and Treatment of End-of-life vehicles
Guidance on the Standards for Storage and Treatment of End-of-life vehicles Introduction This guidance has been prepared by the Environment Agency and the Scottish Environment Protection Agency (SEPA),
More informationTo reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.
Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems
More informationMMU Non-hazardous Waste Management Procedure
1. Introduction and Purpose To explain how waste and recycling is managed at Manchester Metropolitan University (MMU). To ensure that waste management objectives and targets are achieved. To ensure that
More informationConstruction Site Waste Management Process.
Construction Site Waste Management Process. EMS DOCUMENT TYPE: ENVIRONMENTAL ASPECT: PURPOSE: Operational Control Document Waste Management To ensure we manage our waste in compliance with legislation
More informationState of the Nation Report
State of the Nation Report Landfilling Practices and Regulation in Scotland Contents 1. Summary of Solid Waste Management Sector... 2 2. Overview of Landfill Practices... 5 3. Key Stakeholders in the solid
More information9.3.9 Industry uses code
9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of
More informationHazardous Waste Management
Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective
More informationAppendix B7 Construction Waste Management Plan
Appendix B7 Project: Keepit Dam Work Package 2 - Post Tensioning Works Location: Keepit Dam, Namoi River, Northern NSW Client: WaterNSW Contract: 04532F31 Page 2 of 27 Document Acceptance and Release Notice
More informationEnvironmental Management Programme (EMP)
Appendix D Environmental Management Programme (EMP) Please note that although Construction and Operational Phase measures are included in this EMP they are relevant to the issued Waste Management Licence
More informationConstruction Waste Measurement Guide
Draft V6 Last updated: February 2013 Construction Waste Measurement Guide A guide to measuring and reporting waste from construction activities 1 Introduction This document provides guidance on how to
More informationCURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN. A VAN VUUREN / 16 September 2014
CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN A VAN VUUREN / 16 September 2014 THE CAPE TOWN WE LOVE OTHER IMAGES OF OUR CITY ILLEGAL DUMPING IS A REALITY During 2013: There were more than
More informationWaste Management Plan
Boral Cement Limited Berrima Works Waste Management Plan Document Filename: Document Owner: Approved By: CMT-ENV-006 Berrima Waste Management Plan HSE Advisor, Berrima Works Operations Manager, Berrima
More informationQUALITY RECYCLING LTD CUSTOMER CHARTER
QUALITY RECYCLING LTD CUSTOMER CHARTER CUSTOMER CHARTER FOR HOUSEHOLD WASTE COLLECTION 1. INTRODUCTION Quality Recycling Ltd. is committed to providing the highest standards in the provision of waste management
More informationConstruction waste collection good practice: Gloucester Quays
Case Study Construction waste collection good practice: Gloucester Quays This case study examines how applying good practice, such as segregation at source, produced material streams suitable for direct
More informationHazardous Waste Management Policy
Level 3 - H&S Policy Structure Hazardous Waste Management Policy BACKGROUND The University produces hazardous waste from all areas, not just laboratories and workshops, which means that this policy potentially
More information18 Cumulative Impacts and Interaction of Effects
18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly
More informationEnvironmental Guidelines for Preparation of an Environmental Management Plan
2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF
More informationExamples of Hazardous Wastes produced by the University include:
Introduction This guidance document outlines how hazardous waste should be managed and disposed of from University of Kent premises at the Canterbury and Medway campuses. Further information about collection
More informationUCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS
Mandatory Fire Safety Instruction UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS UCL general hoardings details - what you need to know: Prohibited Note Prior
More informationConstruction Management Plan (CMP) 227 Princess Highway, Dandenong
Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale
More informationWASTE COLLECTION PERMIT APPLICATION FORM SUPPLEMENTARY QUESTIONS
WASTE COLLECTION PERMIT APPLICATION FORM SUPPLEMENTARY QUESTIONS Applicant Name: Telephone Number: Postal Address: FORM 3 OF 4 THIS FORM IS APPLICABLE FOR SPECIFIC WASTE TYPES ONLY. (SEE QUESTION 5.4 OF
More information6.0 CONSTRUCTION PROGRAMME
6.0 CONSTRUCTION PROGRAMME Introduction 6.1 This chapter of the ES describes the expected construction works programme and the key activities that will be undertaken. Detailed consideration of potential
More informationDust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation
Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission
More informationBNPB3: Plasterboard - legislation and policy drivers
BNPB3: Plasterboard - legislation and policy drivers Version 1.6 This Briefing Note and referenced information is a public consultation document and will be used to inform Government decisions. The information
More informationENVIRONMENTAL MANAGEMENT DOCUMENT ISSUE 1 REVISION 1
ENVIRONMENTAL MANAGEMENT DOCUMENT ISSUE 1 REVISION 1 BATT CABLES PLC HEAD OFFICE: THE BELFRY FRASER ROAD ERITH KENT DA8 1QH Tel: 01322 441166 Fax: 01322-443681 EMS Manual Issue 1 Revision 1 March 2010
More informationHiggins Environmental Ltd The Kerries Tralee Co Kerry MOBILE Phone Web
Higgins Environmental Ltd The Kerries Tralee Co Kerry MOBILE 0872639746 Phone 066723059 Web www.higginswaste.com Email info@higginsenvironmental.ie CUSTOMER CHARTER FOR HOUSEHOLD WASTE COLLECTION 1. INTRODUCTION
More informationNovartis Animal Health Ireland Limited
ANNUAL ENVIRONMENTAL REPORT 2008 For Novartis Animal Health Ireland Limited IPC Licence No. P0085-01 Document Number: 1046-01 v1.00 Tel: 353 1 276 1428 Fax: 353 1 276 1561 Email: energy@iol.ie www.enviro-consult.com
More information4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:
4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:
More information12 WASTE. Introduction. Review of proposed development
12 WASTE Introduction 12.1 This chapter provides a qualitative assessment of the likely significant environmental effects of solid waste generation, associated with the construction and operation of the
More informationNew South Wales Concrete by-product Recycling and Disposal Industry Guidelines
New South Wales Concrete by-product Recycling and Disposal Industry Guidelines Cement Concrete & Aggregates Australia (CCAA) is the peak industry body for the heavy construction materials industry in Australia,
More informationLand Reclamation Site Siting and Application Guidelines
Department of Environment and Local Government Land Reclamation Site Siting and Application Guidelines Rationale In an effort to reduce the cost associated with the transportation of demolition wastes,
More informationEnvironmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department
2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote
More informationConstruction Waste and Resource Sub-Plan
Construction Waste and Resource Sub-Plan Project Name: WestConnex New M5 Project number: 15.7020.2597 Document number: M5N-ES-PLN-PWD-0008 Revision date: 9/08/2016 Revision: 06 Document Approval Rev. Date
More information(24 July 2015 to date) NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008
(24 July 2015 to date) NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT 59 OF 2008 (Gazette No. 32000, Notice No. 278. Commencement date: 1 July 2009 save for sections 28(7)(a), sections 35 to 41 and section
More informationConstruction Environment Management Plan
Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated
More informationTable of Contents. 1.0 Introduction Environmental Policy Statement Environmental Management Programme... 7
Table of Contents 1.0 Introduction... 3 2.0 Environmental Policy Statement... 4 3.0 Environmental Management Programme... 7 4.0 Water and Wastewater EcoMap... 8 5.0 Air, Noise, Dust EcoMap... 12 6.0 Wastes
More informationREQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.
REQUEST FOR TENDER - SERVICES 1. PURPOSE AND SCOPE This specification is intended to govern the supply of all labour, materials and equipment for the dismantling, demolition of a single dwelling on the
More informationContaminated Land - Managing the Risk
Contaminated Land - Managing the Risk Signatures removed from electronic version Submitted by... Peter Wigley Nominated Responsible Manager Approved by... Tom Stevenson Chairman, Civil Engineering Subject
More informationProcedures for handling waste
Recycling The colour of the containers can sometimes be different from the colour that the routine indicates. This is because there are sometimes a shortage of containers of a certain colour. However,
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a
More informationS O L I D W A S T E O R D I N A N C E * * * S T. G E O R G E, M A I N E
S O L I D W A S T E O R D I N A N C E * * * S T. G E O R G E, M A I N E SECTION I. - TITLE This ordinance shall be known and may be cited as the "SOLID WASTE AND RECYCLING ORDINANCE OF THE TOWN OF ST.GEORGE,
More informationACCIDENT PREVENTION & EMERGENCY RESPONSE
Attachment J ACCIDENT PREVENTION & EMERGENCY RESPONSE Cadbury Ireland Limited Project Ref: OES1061_01 Cadbury Ireland Limited February 2007 Attachment J J.1 Accidental Emissions Control Accidental emissions
More informationWater Pollution Control for Work in Sensitive Areas
Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed
More informationDEPARTMENT OF ENVIRONMENTAL AFFAIRS. No November 2013 NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT, 2008 (ACT NO.
STAATSKOERANT, 29 NOVEMBER 2013 No. 37083 3 GOVERNMENT NOTICE DEPARTMENT OF ENVIRONMENTAL AFFAIRS No. 921 29 November 2013 NATIONAL ENVIRONMENTAL MANAGEMENT: WASTE ACT, 2008 (ACT NO. 59 OF 2008) LIST OF
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site
More informationAnnex F Scoping Checklist
Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve
More informationCONSTRUCTION AND WASTES FROM RESIDENTIAL RECUPERATION
CONSTRUCTION AND WASTES FROM RESIDENTIAL RECUPERATION M. T. Santos 1, P. Lamego 2, P. Frade 2 1 ADEQ, Instituto Superior de Engenharia de Lisboa - ISEL, Lisboa, Portugal. 2 ADEC, Instituto Superior de
More informationViridor (Cardiff Energy Recovery Facility) Substantial Variation
Natural Resources Wales permitting decisions Viridor (Cardiff Energy Recovery Facility) Substantial Variation www.naturalresourceswales.gov.uk Issued 2 nd March 2017 Page 1 of 14 Contents Variation...
More informationWASTE MANAGEMENT CHAPTER TWENTY-FOUR
WASTE MANAGEMENT CHAPTER TWENTY-FOUR 24 Waste management This chapter provides an assessment of waste associated with the project and identifies mitigation measures to minimise impacts. 24.1 Secretary
More informationEuropean Packaging Legislation and Packaging Waste Recovery
22 European Packaging Legislation and Packaging Waste Recovery P Fielding Packaging Consultant, DuPont Nonwovens, Luxembourg The primary objective of the European Commission s new approach to environmental
More informationRECYCLING CONSTRUCTION AND DEMOLITION MATERIAL
1st Edition January 2007 RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL GUIDANCE ON COMPLYING WITH THE OCCUPATIONAL HEALTH AND SAFETY (ASBESTOS) REGULATIONS 2003 The information presented in Recycling
More informationOconee County Solid Waste
C&D DEBRIS GUIDEBOOK Oconee County Solid Waste Roughly 80% of a home builder s waste stream is recyclable, and contractors are partially liable for waste generated at jobsites. Date: 07/01/04 Waste Generation
More informationGUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY
GUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY A working plan is an essential document and consists of a written statement accompanied by plans, drawings and specifications detailing
More informationGuidance on use of Disposal and Recovery Codes (Waste Management Act, 1996 as amended)
Guidance on use of Disposal and Recovery Codes (Waste Management Act, 1996 as amended) This information is provided as a source of reference for operators completing waste surveys for the EPA. Under each
More informationPermit with introductory note
Permit with introductory note The Environmental Permitting (England & Wales) Regulations 2010 Glazewing Limited Saxon Pit Peterborough Road Whittlesey Peterborough Cambridgeshire PE7 1LQ Permit number
More informationDevelopment on Peatland Guidance Waste. Objective
Development on Peatland Guidance Waste Objective This document is written as internal guidance for SEPA staff engaged in the consideration of planning applications involving developments on peat or in
More informationPrinces Square Shopping Centre Sustainability Policy. June 2014
Princes Square Shopping Centre Sustainability Policy June 2014 Contents 2 Sustainability Policy Princes Square s Environmental Management System (EMS) describes our strategy for managing our environmental
More informationDIRECTIVE 2000/53/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 18 September 2000 on end-of life vehicles
L 269/34 DIRECTIVE 2000/53/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 18 September 2000 on end-of life vehicles THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION, Having regard to
More information(1) Site Suitability PURPOSE
3.3 Code for Development and Use of Rural Service Industries PURPOSE This purpose of this code is to encourage the development and use of suitable rural service industries on rural, industrial or suitable
More informationPollution prevention (land and water)
1 Purpose This document provides information on how to effectively manage pollutants for those working in Design, Construction and Maintenance activities. This guidance is to support the Level 2 Environment
More informationClogrennane Lime Ltd. Toonagh Lime Works AER Licence # P
Clogrennane Lime Ltd Toonagh Lime Works AER 2010 Licence # P0 771-01 Section 1 Overview. 3 1.0 Introduction 1.1 Description of Activities 1.2 Responsibility for Environmental Management 1.3 Environmental
More informationGuidelines for THE MANAGEMENT OF WASTE FROM NATIONAL ROAD CONSTRUCTION PROJECTS
Guidelines for THE MANAGEMENT OF WASTE FROM NATIONAL ROAD CONSTRUCTION PROJECTS Revision 1, 12 November 2014 contents 1. Introduction 7 2. Environmental Operating Plans 9 3. National Initiatives 11 3.1.
More informationAn environmental solution potential savings on waste disposal SECTION 3 : 3.1
SECTION 3 : 3.1 An environmental solution......potential savings on waste disposal Superwool Plus a new standard of high temperature insulation wool which has both health and performance advantages for
More informationGreen Stamp Certification Criteria for Printing Businesses
Green Stamp Certification Criteria for Printing Businesses The Green Stamp program is a joint initiative of the Printing Industries Association of Western Australia and the Western Australian Department
More informationDerbyshire Constabulary ENVIRONMENTAL MANAGEMENT PLAN NOVEMBER POLICY REFERENCE 07/190. This plan is suitable for Public Disclosure
Derbyshire Constabulary ENVIRONMENTAL MANAGEMENT PLAN NOVEMBER 2015-2018 POLICY REFERENCE 07/190 This plan is suitable for Public Disclosure Owner of Doc: Head of Department, Finance & Business Services
More informationISO14001 Training. ALPS Electric (Ireland) Ltd.. Rev 08 Updated August Consent of copyright owner required for any other use.
ISO14001 Training Rev 08 Updated August 2007 What is ISO14001? ISO14001 is an International Standard which specifies the requirements for an Environmental Management System (EMS). It allows a company to:
More informationZero waste to landfill: Construction waste collection good practice
Case study Zero waste to landfill: Construction waste collection good practice Zero waste policies are a key step towards sustainable waste management. This case study examines the economic and environmental
More informationOPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME
OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen
More informationENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors
1. Increased water demand (12 KLD) due water usage for, dust suppression and for workers 2. Sewage generation (11 KLD) and disposal 3. Municipal solid waste generation (15 kg/day) by workers 4. Construction
More informationWASTE ACCEPTANCE CRITERIA AND DEVELOPMENT OF SOIL TRIGGER VALUES FOR EPA-LICENSED SOIL RECOVERY FACILITIES
WASTE ACCEPTANCE CRITERIA AND DEVELOPMENT OF SOIL TRIGGER VALUES FOR EPA-LICENSED SOIL RECOVERY FACILITIES 1. Introduction This guidance document applies to soil recovery facilities which exceed the operational
More informationMcGrath works in partnership with Hackney Homes
Case study: Achieving good practice waste recovery McGrath works in partnership with Hackney Homes Hackney Homes is using a partnering approach across the whole supply chain, to deliver the Decent Homes
More informationAPPENDIX B CONSTRUCTION WASTE MANAGEMENT SAMPLE SPECIFICATION
APPENDIX B CONSTRUCTION WASTE MANAGEMENT SAMPLE SPECIFICATION The following appendix includes information and standard drawings that are diagrammatic and are used only to convey intent. Construction Waste
More informationActivity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes
MINISTRY OF ENVIRONMENT AND NDU ENVIRONMENTAL GUIDELINE No. 31 Asphalt Plant Set Up Temporarily For The Purposes Of A Project By A Public Department 1.0 Purpose of guideline This environmental guideline
More informationTABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...
TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed
More informationCONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES
Nova Scotia Environment and Labour CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Approval Date: October 24, 1997 Effective Date: October 24, 1997 Approved By: Peter Underwood Version Control:
More informationEnvironmental Policy and Guide December 2010
Environmental Policy and Guide December 2010 Page 1 of 11 ENVIRONMENTAL POLICY A responsible and forward-looking approach to environmental issues is an important factor in Intu Properties plc s continuing
More informationLIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695]
LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695] 1. Notwithstanding all other permits and clearances, the following clearances shall be obtained prior to
More informationCOUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY NEVADA COUNTY CDA GUIDELINES FOR ASH AND BURN DEBRIS CLEAN UP AND REMOVAL AFTER A FIRE
COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY Environmental Health Department 950 MAIDU AVENUE, SUITE 170 NEVADA CITY, CA 95959-8617 (530) 265-1222 FAX (530) 265-9853 http://mynevadacounty.com Amy Irani,
More informationConstruction Waste Minimization and Reuse Management
Construction Waste Minimization and Reuse Management Mr.M.KalilurRahman 1, Mr.S.S.Janagan 2 1 Student M.E., (CE&M), Gnanamani College of Engineering, Namakkal-637018, Tamilnadu, India 2 Assistant Prof,
More informationWelcome to ChaseWarner Waste Management
Welcome to ChaseWarner Waste Management Chase Warner is a growing company. It was formed in 2005 and has been going from strength to strength. We started small in Waste Management and from there quickly
More informationSustainability Social,Economic and Environmental Responsibility Policy
Sustainability Social,Economic and Environmental Responsibility Policy PURPOSE Autism Initiatives recognises that our work may have a direct or indirect effect on the local, regional and global environment.
More informationIRISH CEMENT PLATIN INVESTING IN OUR FUTURE
IRISH CEMENT PLATIN INVESTING IN OUR FUTURE INTRODUCTION Investing in our future. The next phase of investment in Platin will see further energy efficiency improvements with on site electricity generation
More informationCity of Brisbane Construction and Demolition Debris Recycling and Waste Reduction Plan
City of Brisbane Construction and Demolition Debris Recycling and Waste Reduction Plan This form is to be completed for all demolition, remodel, re-roofing and new construction projects covered by Ordinance
More informationThe Official BIFM Information Service Partner
The Official BIFM Information Service Partner 01 Introduction Sustainability and a company s environmental credentials have become ever more important, with many investors considering performance in these
More informationENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009
ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,
More informationKDC Environment 001. Environmental Awareness
KDC Environment 001 Environmental Awareness Environmental Awareness Content 1.0 Introduction 2 2.0 The Environment & Pollution 2 3.0 Environmental Action 4 4.0 Environmental Aspects & Impacts 5 5.0 Environmental
More informationTompkins County Solid Waste Management Plan Executive Summary
Tompkins County Solid Waste Management Plan Executive Summary Tompkins County has prepared a comprehensive, twenty-year Solid Waste Management Plan to comply with the requirements of the Solid Waste Management
More informationSCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS
SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary
More informationIrish Country Meats Camolin
Irish Country Meats Camolin Annual Environmental Report 2009 Index 1 Introduction 2 Environmental Policy 3 Site Description 4 Summary Information 4.1 Emission to Water 4.2 Surface Water 4.3 Boiler Emissions
More informationGENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 180 NOVEMBER 2005 GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS TABLE OF CONTENTS 180.01 SCOPE 180.02 REFERENCES 180.03 DEFINITIONS
More information