The following approach was then taken to delineating recommended buffer zones for the initially mapped freshwater ecosystems:

Size: px
Start display at page:

Download "The following approach was then taken to delineating recommended buffer zones for the initially mapped freshwater ecosystems:"

Transcription

1 11 IMPACTS ON WETLANDS AND AQUATIC ECOSYSTEMS 11.1 Introduction The Freshwater Consulting Group (FCG) was appointed to provide specialist input relating to the potential impacts of the proposed development on freshwater ecosystems. A copy of the full wetlands and aquatic ecosystems report is included in Appendix E Methodology Establishing the Baseline Conditions The approach taken to generate a preliminary, desktop-based map of freshwater ecosystems for the site was as follows: The boundaries of the farms making up the proposed site and the proposed turbine layout were overlaid as GIS shapefiles onto existing geo-referenced 1: scale aerial photographs of the area obtained from Chief Directorate: National Geo-spatial Information(CD:NGI). Currently mapped rivers (perennial and non-perennial) were overlaid onto the GIS map (using the 1: digital map layer for rivers obtained from CD:NGI map sheet 3319); Currently mapped dams were overlaid onto the GIS map (using the 1: Inland Water Areas layer for map sheet 3319). Rivers and wetlands mapped by the NFEPA project were overlaid onto the GIS map of the area, and a distinction was made between those wetland categorised as natural versus those categorised as artificial. For the natural NFEPA wetlands and the NFEPA rivers, a further distinction was made between the mapped features categorised as a Freshwater Ecosystem Priority Area (FEPA) and those that weren t. The aquatic layers for the Witzenberg Municipality that were generated by the C.A.P.E. Fine-Scale Planning project for the Upper Breede River Valley planning domain (Job et al. 2008) were overlaid on the GIS map of the area, specifically the Aquatic Critical Biodiversity Area (CBA), Critical Ecological Support Area (CESA) and Other Ecological Support Area (OESA) layers. A distinction was made between the aquatic features and the mapped buffer areas for each layer. Additional aquatic ecosystems on site were manually digitised in GIS, based on visual cues, using geo-referenced digital aerial images in conjunction with Google Earth satellite imagery. Both wetlands and rivers were mapped in this way and a category for the confidence of these assessments was included in an attribute tables accompanying the GIS shapefiles. Information on the wetland type (sensu SANBI 2009) was also included in the attribute table for the wetland layer. Rivers or wetlands that were incorrectly mapped by the NFEPA or 1: map series were masked as non-aquatic features on the GIS map. The following approach was then taken to delineating recommended buffer zones for the initially mapped freshwater ecosystems: Final EIA Report 11-1

2 following the generic guideline for buffers provided in the NFEPA Implementation Manual, a 100 m no-go buffer zone was created around all FEPA priority wetlands on the GIS map. The buffers for the Aquatic CBA, CESA and OESA layers that were generated by the C.A.P.E. Fine-Scale Planning project for the Upper Breede River Valley planning domain (Job et al. 2008) were adopted as the recommended buffer areas for the aquatic features mapped through this conservation planning initiative. This project used a combination of 100, 50 and 32 m buffers, depending on the categorised conservation status of each mapped feature. A 30 m buffer zone was demarcated around all other wetlands and rivers, similar to the default 32 m buffer width used in the C.A.P.E. Fine-Scale Planning project (Snaddon et al. 2008) for all aquatic features that were not categorised as CBAs or CESAs. The desktop mapping was followed by a site visit undertaken in late August 2012, the purpose of which was to ground-truth the relevant portions of the preliminary map of freshwater ecosystems, and to collect sufficient information/data to determine the present ecological condition and conservation importance of the potentially affected ecosystems with a relatively high degree of confidence. During the site visit, a rough delineation of the location and extent of potentially affected wetlands that were confirmed to be present on the site was performed. This delineation followed the Department of Water Affairs guidelines for wetland identification and delineation i, and was based on a visual examination of the hydrological, soil and vegetation characteristics of the potential wetland areas that the proposed infrastructure may encroach into Assessment The impacts identified and described in Section 11.3 low are assessed in terms of the Assessment Criteria and Rating Scales reflected in Table 6.11 in Chapter 6, in order to derive the final impact significance rating for each identified impact Assessment Identification of Potential s (a) Design phase impacts (pre-construction) The main potential design-phase impact on freshwater ecosystems identified was the negative impact of the proposed wind turbines, roads and trenches encroaching into riverine corridors and wetlands, resulting in the loss and fragmentation of riverine/wetland habitat. Final EIA Report 11-2

3 Figure 11-1: Map of freshwater ecosystems on the proposed site in relation to the proposed turbines and roads for the Wolseley WEF (numbers in grey circles refer to mapped wetlands) Final EIA Report 11-3

4 The following proposed turbines would encroach into freshwater ecosystems (see map above): Turbine 1 would encroach into the edge of Wetland 11, rated to be of high conservation importance, while Turbine 2 would be close to the edge of this wetland; Turbine 13 would encroach into Wetland 10, rated to be of moderate conservation importance; Turbines 16 and 17 would encroach into Wetland 7, rated to be of moderate conservation importance; Turbine 18 would encroach into Wetland 6, rated to be of moderate conservation importance; Turbine 22 would encroach into the edge of Wetland 3, rated to be of moderate conservation importance; Turbines 15, 21, 25, 26 and 30 would encroach into wetlands rated to be of low conservation importance; and Turbines 14 and 27 would encroach into drainage lines. The proposed roads would be routed through the following mapped wetlands: Wetland 11, rated to be of high conservation importance; Wetlands 6, 7 and 10 (and the edge of Wetland 3), rated to be of moderate conservation importance; and Wetlands 1, 2, 4, 5 and 9, rated to be of low conservation importance. (b) Construction phase impacts The following potential impacts are associated with the construction phase of the project: Destruction/damage of wetland, river and riparian areas through constructionrelated activities; Pollution of freshwater ecosystems, resulting from the runoff of fuel and oil from vehicles and machinery, and from construction activities; and Disturbance to aquatic and semi-aquatic fauna. (c) Operational phase impacts The potential impacts associated with the construction phase include the following: Hydrological alteration of rivers/wetlands through the establishment of turbines and roads in or through these areas; Alteration of hydrology and water quality of rivers/wetlands through increased stormwater runoff; and Ongoing disturbance to aquatic and semi-aquatic fauna. (d) Decommissioning impacts The impacts on freshwater ecosystems that could be associated with the decommissioning phase of the project would be very similar to the construction phase. Final EIA Report 11-4

5 Assessment of Potential s (a) Design phase The direct loss and fragmentation of riverine and wetland habitat as a result of the establishment of turbines, roads and trenches in wetland areas, was rated to be a negative impact of medium significance without mitigation. If the recommended mitigation measures of altering the layout plan and compensating for the unavoidable loss of wetlands of moderate conservation importance through the rehabilitation and protection of degraded wetlands of moderate to high conservation importance were to be effectively implemented, it is predicted that the loss and fragmentation of freshwater ecosystems would be a negative impact of low to medium significance. To reduce the impact to a low level of significance, the encroachment of turbines and roads into wetlands of moderate importance would need to avoided. (b) Construction phase The construction of the turbines and the access roads could result in the destruction or damage of freshwater ecosystems that are located in close proximity to this infrastructure. In addition, freshwater ecosystems (wetlands in particular) could be damaged or destroyed through the establishment of temporary laydown areas and temporary tracks in or near to drainage lines or wetlands (especially the 13 m wide track for use by the crawler crane that would be used to erect the towers and turbines). The significance of the impact is medium (-) without, and low medium (-) with mitigations. The runoff of fuel, oil, concrete, sewage and other contaminants into rivers and wetlands will result in the pollution of these ecosystems and is rated as an impact of medium (-) significance without mitigation. With mitigation the impact is expected to be of low to medium (-) significance. A significant increase in noise levels during the construction phase is likely, relative to the current situation, caused by the use of large trucks and cranes to transport and manoeuvre the turbine components. The increased noise levels would inevitably lead to the disturbance of aquatic and semi-aquatic fauna associated with nearby freshwater ecosystems, for example wetland-associated birds, small mammals such as mongoose, and the frog species that could forage and breed in the wetlands (and surrounding terrestrial areas) on the site, possibly including the vulnerable Cape Caco. Due to the difficulty in mitigating this impact, the impact is rated to be of low medium (-) significance, with and without mitigation. (c) Operational phase The hydrology of rivers and wetlands will be altered due to the impeding or diverting of flows by turbine and road structures. Irrespective of whether or not the recommended mitigation measures are implemented, this potential negative operational-phase impact was rated to be of medium (-) significance. This is largely due to the potential for a number of wetlands across the site to be affected by this impact, including wetlands assessed to be of moderate conservation importance. The only way to reduce this impact to lower levels would be to alter the layout plan in such a way that there would be less encroachment into wetland areas, particularly those of moderate and high conservation importance. Final EIA Report 11-5

6 An increase in the hardened surfaces on the site would lead to increased quantities of stormwater runoff into freshwater ecosystems. The footprint of each turbine would, however, be limited to the area of the foundations (~5.5 m 2 ), and the proposed access roads would be relatively narrow (3-4 m wide) gravel-surfaced roads. The stormwater-related impacts on the hydrology and water quality of rivers and wetlands are likely to be of low medium (-) significance, and could be reduced to a low level of significance through the design and implementation of a stormwater management system that follows the principles of sustainable urban drainage systems (SUDS). The noise, possible vibration and increased air movement generated through the operation of the wind farm could potentially result in the disturbance of aquatic and semi-aquatic fauna associated with the rivers and wetlands located in close proximity to the proposed turbines. These potential disturbance-related impacts would occur continually, during the day and night, and could affect invertebrates (especially those with an aerial phase), frogs (including the vulnerable Cape Caco that may occur in the area), small mammals such as water mongoose, and birds (note that the potential impacts of the Wolseley WEF on birds and bats have been dealt with in other specialist reports). The potential impact of ongoing disturbance to aquatic and semiaquatic fauna was rated to be of medium (-) significance, and no mitigation of this negative impact is possible. (d) Decommissioning The decommissioning phase would be very similar to the construction-phase impacts. All of the potential impacts are predicted to be of low or low to medium (-) significance levels with the recommended mitigation measures assumed to be in place. The protection of rehabilitated wetlands, especially those of moderate to high conservation importance, from decommissioning-phase impacts would be of paramount importance. (e) Cumulative No cumulative impacts of major significance are anticipated to result from the proposed wind farm development. Further loss of wetlands in the region through the establishment of the wind farm was assessed to be a potential cumulative impact of low medium (-) significance without mitigation, due to the extensive loss of wetlands that has already occurred in the region and the likely loss of some wetlands areas of moderate conservation importance on the site. The cumulative impact would reduce to a low level of significance if the recommended design-phase mitigation measures are implemented Measures The most effective way to reduce the design-related impacts on freshwater ecosystems would be to modify the proposed layout plan, although rehabilitation and protection of degraded wetlands in compensation for wetland loss could also reduce the significance of such impacts. The following recommendations are made in this regard: No turbines or roads should be located in any wetlands of high conservation importance, and a no-development buffer area should be maintained around these wetlands. In particular, turbines 1 and 2 should be moved to a position that is 50 m or more outside of Wetland 11, and the roads for these turbines Final EIA Report 11-6

7 should not cross through the wetland. Turbines should only be placed within 50 m of Wetland 11 (but not in the wetland itself) if the degraded portions of this wetland are to be rehabilitated as part of the proposed project. The encroachment of turbines or roads into wetlands of moderate importance should be avoided as far as possible and, where unavoidable, the degree of encroachment should be minimised as far as possible and other portions of the wetland should be rehabilitated. In particular, Turbine 13 should be moved to the edge of Wetland 10 and Turbine 18 should be moved to the edge of Wetland 6 if the placement of turbines in these wetlands of moderate conservation importance is unavoidable, and the roads to these turbines should not cross through the wetlands. The road to Turbine 22 should also be re-routed around Wetland 3. The remaining portions of Wetlands 6 and 10 should be rehabilitated if the establishment of turbines and/or roads for the WEF in these wetlands is unavoidable. The loss of a portion of Wetland 7 through the establishment of Turbines 16 and 17, and their associated roads, in this wetland of moderate conservation importance should be compensated by the rehabilitation of other portions of this wetland and portions of adjacent Wetland 8 that is of high conservation importance. The rehabilitated wetland areas should be protected from agricultural and other activities that would lead to their ongoing degradation, and they should be managed for conservation purposes. The rehabilitation of wetlands as compensation for wetland loss should be planned and implemented under the guidance of a suitably qualified wetland ecologist. No turbines should be placed in drainage lines and no roads should be routed directly alongside drainage lines. In particular, Turbines 14 and 27 should be shifted away from the drainage lines that they would be in according to the proposed layout plan that was assessed in this report. Proposed mitigations during the construction, operation and decommissioning phase are indicated in the impact tables below Summary of Potential s The assessment of each impact is discussed and presented in tabular format as shown below for both pre and post mitigation. The different phases (Construction, Operation, and Decommissioning) are treated separately: Tables below provide a summary of the potential impacts with and without mitigation during construction and operation respectively Design phase (pre-construction) Table 11-1 Description and assessment of potential design-phase impacts on freshwater ecosystems associated with the proposed turbines, roads and trenches Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence : Encroachment into riverine corridors and wetlands Description: Direct loss and fragmentation of riverine and wetland habitat as a result of encroachment into these ecosystems from the Final EIA Report 11-7

8 development Without Negative High High High High Description: Alter the layout plan to minimise encroachment into wetlands and river corridors as far as possible (following the recommended changes outlined in this freshwater ecology impact assessment report) and, where encroachment into wetlands of moderate conservation importance is unavoidable, rehabilitate degraded portions of these wetlands and/or degraded portions of nearby wetlands of high and moderate conservation importance that are of a similar type. With Negative High Low High Low to * High Low to * High Cumulative : Cumulative impact of the Wolseley WEF on the further loss of wetlands in the region is likely to be of low to medium significance without mitigation, and low with the implementation of the recommended mitigation measures. * The ratings for the consequence and significance were adjusted on the basis of professional judgement, as the stipulated assessment method (Appendix 1) resulted in the same overall result with and without mitigation whereas the recommended mitigation measures would undoubtedly reduce the consequence and significance of the potential design-phase impacts Construction Phase Table 11-1: Potential impact of destruction/damage of wetland, river and riparian areas Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence 1: Destruction/damage of wetland, river and riparian areas through construction-related activities Description: Physical destruction or damage of wetlands and/or riparian vegetation through the storage of building materials, the temporary lay-down of equipment (sand, soil, bricks, steel, pipes, etc.), and/or the establishment of temporary roads in wetland and/or riparian areas Without Negative High Description: Construction camps and temporary laydown areas should be located at least 30 m from freshwater ecosystems identified to be of low or moderate conservation importance and 50 m from freshwater ecosystems identified to be of high conservation importance. Wetlands, rivers and riparian areas within which no wind turbines or access roads are to be established should be treated as no-go areas and appropriately demarcated as such. No vehicles, machinery, personnel, construction material, fuel, oil, bitumen or waste should be allowed into these areas without the express permission of and supervision by the ECO, except for rehabilitation work in these areas. Construction activities associated with the establishment of wind turbines and roads that are to be located in wetlands should be restricted to a working area of 10m around these structures, and these working areas should be clearly demarcated. No vehicles, machinery, personnel, construction material, fuel, oil, bitumen or waste should be allowed outside of the demarcated working areas. The temporary track for the crawler crane should not encroach within 10m of any wetlands for those turbines and access roads that are not located in wetlands. For the construction of wind turbines and roads that are located in wetland areas, the routing of the temporary track for the crane should be determined through consultation with a wetland ecologist and the rehabilitation of the track should be conducted under the guidance and supervision of a wetland ecologist. Workers should be made aware of the importance of not destroying or damaging the vegetation along rivers and in wetland areas, and this awareness should be promoted throughout the construction phase. Freshwater ecosystems located in close proximity to the construction areas should be inspected on a regular basis by the ECO for signs of disturbance from construction activities. If signs of disturbance are noted, immediate action should be taken to remedy the situation and, if necessary, a freshwater ecologist should be consulted for advice on the most suitable remediation measures. With Negative Low to Low to High Low to * medium Cumulative : Not applicable * The rating for the consequence was adjusted on the basis of professional judgement, as the stipulated assessment method (Appendix 1) resulted in the same overall result with and without mitigation whereas the recommended mitigation measures would undoubtedly reduce the consequence (and significance) of the potential construction-phase impact Final EIA Report 11-8

9 Table 11-2: potential pollution-related impacts on freshwater ecosystems during the construction phase Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence 2: Pollution of freshwater ecosystems, resulting from the runoff of fuel and oil from vehicles and machinery, and from construction-related activities Description: Pollution of wetlands and/or rivers through leakage of fuels, oils, etc. from construction machinery, or from washing of equipment or flushing of concrete mixers and other vehicles as well as sediments from de-watering of excavations Without Negative Low High Description: Toilets must be located at least 30 m from freshwater ecosystems identified to be of low or moderate conservation importance and 50 m from freshwater ecosystems identified to be of high conservation importance. No fuel storage, refuelling, vehicle maintenance or vehicle depots should be allowed within 30 m of freshwater ecosystems identified to be of low or moderate conservation importance and 50 m from freshwater ecosystems identified to be of high conservation importance; Refuelling and fuel storage areas, and areas used for the servicing or parking of vehicles and machinery, should be located on impervious bases and should have bunds around them. Bunds should be sufficiently high to ensure that all the fuel kept in the area will be captured in the event of a major spillage. Vehicles and machinery should not be washed within 30 m of freshwater ecosystems identified to be of low or moderate conservation importance and 50 m from freshwater ecosystems identified to be of high conservation importance. No discharge of effluents or polluted water shall be allowed into any rivers or wetland areas. If construction areas are to be pumped of water (e.g. after rains), this water must be pumped into an appropriate settlement area, and not allowed to flow into any rivers or wetland areas. No spoil material, including stripped topsoil, should be temporarily stockpiled within 30 m of freshwater ecosystems identified to be of low or moderate conservation importance and 50 m of freshwater ecosystems identified to be of high conservation importance. There should be as little disturbance to surrounding vegetation as possible when construction activities are undertaken, as intact vegetation adjacent to construction areas will assist in the control of sediment dispersal from exposed areas. Workers should be made aware of the importance of not polluting rivers or wetlands and of not undertaking activities that could result in such pollution, and this awareness should be promoted throughout the construction phase. Freshwater ecosystems located in close proximity to the construction areas should be inspected on a regular basis (but especially after rainfall) by the ECO for signs of sedimentation and pollution. If signs of sedimentation or pollution are noted, immediate action should be taken to remedy the situation and, if necessary, a freshwater ecologist should be consulted for advice on the most suitable remediation measures. With Cumulative : Not applicable Negative Low Low Low Low to medium Table 11-3: potential impact of disturbance to aquatic and semi-aquatic fauna during the construction phase Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence 3: Disturbance to aquatic and semi-aquatic fauna Description: Increased disturbance of aquatic and semi-aquatic fauna, as a result of the noise from construction teams and their machinery working within or in close proximity to wetlands and rivers Without Negative Low to Low Low Low Low to to Low to High Description: Final EIA Report 11-9

10 Construction camps and temporary laydown areas should be located at least 30 m from freshwater ecosystems identified to be of low or moderate conservation importance and 50 m from freshwater ecosystems identified to be of high conservation importance. Wetlands, rivers and river riparian areas within which no wind turbines or access roads are to be established should be treated as no-go areas and appropriately demarcated as such. No vehicles, machinery, personnel, construction material, fuel, oil, bitumen or waste should be allowed into these areas without the express permission of and supervision by the ECO, except for rehabilitation work in these areas. Construction activities associated with the establishment of wind turbines and roads that are to be located in wetlands should be restricted to a working area of 10m around these structures, and these working areas should be clearly demarcated. No vehicles, machinery, personnel, construction material, fuel, oil, bitumen or waste should be allowed outside of the demarcated working areas. Workers should be made aware of the importance of not killing or harming any animals that they encounter and this awareness should be promoted throughout the construction phase. With Negative Cumulative : Not applicable Low to Low Low to Low Low Low to High Low to Operational phase Table 11-4: potential impact of the hydrological alteration of freshwater ecosystems associated with the turbine and road placements Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence 1: Hydrological alteration of rivers/wetlands Description: Alteration of the hydrology of rivers and wetlands, due to the impeding or diverting of flows by turbine and road structures built in, across or adjacent to rivers and wetlands Without Negative High High Description: Formalisation of road crossings over rivers and drainage lines using structures that minimise the alteration of flows (e.g. box culverts with a wide span). Installation of adequate sub-surface drainage under roads that cross through wetland areas. With Negative High Low High Cumulative : Low significance at a regional scale Table 11-5: Potential stormwater-related impacts on freshwater ecosystems Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence 2: Stormwater runoff-related impacts Description: Alteration of the hydrology and water quality of freshwater ecosystems from increased stormwater runoff Without Negative High Low to * Low to Description: Design and implement a stormwater management system that follows the principles of a sustainable urban drainage system (SUDS), with input from a freshwater ecologist into the design of the management system. Ensure that roads that run through or adjacent to wetlands have multiple cross-drains, to prevent the concentration of flows into the wetlands at a limited number of points along the roads. Final EIA Report 11-10

11 With Negative High Low Low* Low Cumulative : Insignificant at a regional scale * The rating for the consequence was adjusted on the basis of professional judgement, as the stipulated assessment method (Appendix 1) resulted in a rating that was considered to be too high for this particular impact Table 11-6: potential ongoing operational-related disturbance to aquatic and semi-aquatic fauna Nature Extent Duration Intensity Reversibility on Irreplaceable Resources Consequence Probability Significance Confidence 3: Ongoing faunal disturbance Description: Disturbance to aquatic and semi-aquatic fauna from operation of wind turbines (which would generate noise, possible vibration and increased air movement) Without Negative High Low High Description: Not possible. Cumulative : Low to moderate significance at a regional scale Decommissioning Phase The decommissioning phase would be very similar to the construction-phase impacts Responses to Recommendations for The specialist wetland assessment has recommended the following mitigation measures be implemented. The extent to which SAGIT has agreed to implement these recommendations is also provided below. A revised layout which incorporates and responds to these changes was prepared in December 2012 and is reflected in Figure 4.1 in presented in Appendix G and. These changes are discussed further in Section of this EIR: 1. Move turbines 1 and 2 at least 50 m from wetland 11, and realign their access roads to ensure they do not cross the wetland. SAGIT has indicated that it will move turbines 1 and 2 at least 50 m north of the northern boundary of wetland 11. The access road to these turbines can, at its eastern most extremity, also be moved away from the wetland area. The portion of access road immediately south-west of the existing sub-station will however have to maintain its proposed alignment through a portion of wetland 11. Turbine 1 was moved away from the edge of a wetland of high importance (Wetland #11), approximately 50 m to the north of the wetland edge, but the proposed access road to Turbine 1 (and Turbine 2) still cuts through a portion of the wetland. Final EIA Report 11-11

12 2. If the placement of turbines 13 and 18 in wetlands of moderate conservation value (wetlands 10 and 6 respectively) is unavoidable, these turbines should be moved to the edge of the wetlands. Their access roads should not cross these wetlands. SAGIT has indicated that turbine 13 and 18 will be move to the edge of the wetlands. Despite the realignment of the access roads, it will not be possible to avoid crossing portions of wetlands 6 and 10. Turbine 13 was moved westward, closer to the edge of a wetland of moderate conservation importance (Wetland #10), whereas the previous turbine position was near centre of the wetland. The access road for Turbine 13 was realigned so that it only encroaches into the western portion of the Wetland #10 (of moderate conservation importance), whereas the road was previously routed straight through the centre of the wetland. Turbine 18 was moved slightly south, further into a wetland of moderate conservation importance (Wetland #6), but the access road for this turbine (which previously connected to Turbine 20) no longer cuts through the entire wetland as it did before. 3. The road to turbine 22 should be re-routed around wetland 3. SAGIT has indicated that this access road can easily be, and will be, rerouted around wetland 3. The access road for Turbine 22 was moved southward, out of and along the edge of a wetland of moderate conservation importance (Wetland #3), but the turbine position (within the wetland, along the southern edge) was not changed. 4. The remaining portions of Wetlands 6 and 10 should be rehabilitated if the establishment of turbines and/or roads for the WEF in these wetlands is unavoidable SAGIT have indicated that they will rehabilitate wetlands 6 and 10 accordingly. 5. The loss of a portion of Wetland 7 through the establishment of Turbines 16 and 17, and their associated roads, in this wetland of moderate conservation importance should be compensated by the rehabilitation of other portions of this wetland and portions of adjacent Wetland 8 that is of high conservation importance. Tubine 17 and the access road for this turbine were moved slightly to the south, but remain within a wetland of moderate conservation importance (Wetland #7). SAGIT have indicated that they will rehabilitate wetlands 7 and 8 accordingly. 6. No turbines should be placed in drainage lines and no roads should be routed directly alongside drainage lines. In particular, Turbines 14 and 27 should be shifted away from the drainage lines. Final EIA Report 11-12

13 SAGIT have indicated that these two turbines have been placed specifically on field margins so not as to interrupt agricultural activities. Considering that the drainage lines are artificial drainage lines positioned to accommodate the field layout pattern, and have not been designated of high conservation value, the proposed location is considered a workable compromise. The micrositing of these turbines will be adjusted to ensure impacts on the drainage lines is minimised. Turbine 14 was move south-eastward, away from and out of the recommended 30 m buffer zone for a drainage line, and the access road for this turbine was realigned to follow an existing road. Turbine 27 and the access road for this turbine were moved northward, out of the drainage line and to the edge of the recommended 30 m buffer area for the drainage line, but into Wetland #2 of low conservation importance. 7. Turbine 20 and its access road were moved eastward, slightly further away from edge of Wetland #6 of moderate conservation importance. 8. Turbine 19 was move south-eastward to a position adjacent to the recommended 30 m buffer area of a drainage line (the previous position for this turbine was in a non-wetland area in the middle of a wheat field) and the new proposed access road to this turbine has been routed along the edge of the recommended buffer area Summary and Conclusions No impacts of high negative significance on freshwater ecosystems are anticipated for the proposed wind farm project, partly due to incorporation of some of the recommendations of the preliminary freshwater ecosystem mapping report into the formulation of the final layout plan. The direct loss and fragmentation of wetland habitat that is likely to result from the establishment of turbines, roads and trenches in wetland areas was, however, assessed to be a negative design-phase impact of medium significance without mitigation. SAGIT have committed to accepting as many of the proposed mitigation measures possible. With implementation thereof, it is likely that the majority of the post mitigation impacts as listed in the summary table below will be realised. It is recommended that these commitments be made conditions of approval. Final EIA Report 11-13

14 Table 11-7: Summary of s on Wetlands and Aquatic Ecology Operation Decommissioning Construction (*preconstruction) Premitigation Postmitigation Premitigation Postmitigation Premitigation Postmitigation Encroachment into riverine corridors and wetlands * Med (-) Low Med (-) Destruction/damage of wetland, river and riparian areas Med (-) Low Med (-) Med (-) Low Med (-) Pollution of freshwater ecosystems (oil and fuel runoff) Med (-) Low Med (-) Med (-) Low Med (-) Disturbance to aquatic and semiaquatic fauna Low (-) Low (-) Low med (-) Low Med (-) Hydrological alteration of rivers/wetlands through construction of turbines and roads Hydrological and water quality alteration of rivers/wetlands through stormwater runoff Med (-) Med (-) Low-Med (-) Low (-) Ongoing faunal disturbance Med (-) i Department of Water Affairs and Forestry [DWAF] (2005). A Practical Field Procedure for Identification and Delineation of Wetlands and Riparian Areas. Department of Water Affairs and Forestry, Pretoria. Final EIA Report 11-14

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION)

8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION) 8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION) In order to manage the construction phase impacts associated with the establishment of the Compilation Yard and the Common User

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT

8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT 8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT 8.1. Hydrogeology 8.1.1. Introduction Bohlweki Environmental appointed SRK Consulting to undertake the necessary hydrogeological studies for the proposed CCGT

More information

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary

More information

4 PROJECT ALTERNATIVES

4 PROJECT ALTERNATIVES 4 PROJECT ALTERNATIVES 4.1 Introduction In terms of the EIA Regulations published in Government Notice R543 of 2 August 2010 in terms of Section 24 of the National Environmental Management Act (Act No.

More information

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction 2.7 Generic Mitigation Measures 2.7.1 Avifauna CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction Vehicles and machinery can impact on natural vegetation

More information

D9. Significant Ecological Areas Overlay

D9. Significant Ecological Areas Overlay D9. Significant Ecological Areas Overlay D9.1. Background Auckland's indigenous biodiversity is unique with a diverse range of ecosystems reflecting the complex physical environment of the region. Natural

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

Natura 2000 and Hydropower. Hydropower and Fish Workshop Brussels 29 May, 2017

Natura 2000 and Hydropower. Hydropower and Fish Workshop Brussels 29 May, 2017 Natura 2000 and Hydropower Hydropower and Fish Workshop Brussels 29 May, 2017 Christina Pantazi European Commission DG Environment, Nature Protection Unit (D3) Hydropower and Natura 2000 Hydropower one

More information

MT EDGECOMBE SOUTH RESIDENTIAL DEVELOPMENT (KINDLEWOOD): EIA/4667

MT EDGECOMBE SOUTH RESIDENTIAL DEVELOPMENT (KINDLEWOOD): EIA/4667 Moreland Developments (Pty) Ltd MT EDGECOMBE SOUTH RESIDENTIAL DEVELOPMENT (KINDLEWOOD): EIA/4667 FINAL ENVIRONMENTAL MANAGEMENT PLAN SiVEST Environmental Division 22 Pietermaritz Street, Pietermaritzburg,

More information

Rural Living Environment

Rural Living Environment 1 RLE.1 Rural Living Environment RLE.1.1 Description & Expectations The Rural Living Environment (RLE) covers rural areas within the District that are either already characterised by lifestyle activities

More information

Southern Africa perspective - Identification and Mapping National Freshwater Ecosystems Priority Areas in South Africa

Southern Africa perspective - Identification and Mapping National Freshwater Ecosystems Priority Areas in South Africa Southern Africa perspective - Identification and Mapping National Freshwater Ecosystems Priority Areas in South Africa SA National Wetland Inventory By N Mbona Outline National Wetland Inventory SA Wetland

More information

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

INVASIVE SPECIES CONTROL PLAN FOR CONSTRUCTION ACTIVITIES AND POST CONSTRUCTION MONITORING

INVASIVE SPECIES CONTROL PLAN FOR CONSTRUCTION ACTIVITIES AND POST CONSTRUCTION MONITORING INVASIVE SPECIES CONTROL PLAN FOR CONSTRUCTION ACTIVITIES AND POST CONSTRUCTION MONITORING INTRODUCTION Black Oak Wind Farm, LLC is proposing to develop a wind-powered electric generating facility (the

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

Pollution prevention (land and water)

Pollution prevention (land and water) 1 Purpose This document provides information on how to effectively manage pollutants for those working in Design, Construction and Maintenance activities. This guidance is to support the Level 2 Environment

More information

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Agricultural Expansion on Portion 2 of Farm 92, Tregaron, known as Sylvania, Sundays River Valley Municipality BACKGROUND INFORMATION DOCUMENT,

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

Notes for NEPA for Generic Terms of Reference

Notes for NEPA for Generic Terms of Reference TERMS OF REFERENCE IIRRIIGATIION AND WATER MANAGEMENT Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to the construction and/or the development of Irrigation

More information

Form 1: Application for resource consent

Form 1: Application for resource consent Form 1: Application for resource consent All sections must be completed in full and accompanied by the initial fixed application fee (see section 11) and the relevant activity form (see section 7). Failure

More information

ROUNDTABLE MEETING ON SUSTAINABLE PALM OIL. RSPO Guidance for the Management and rehabilitation of Riparian Reserves Holly Barclay

ROUNDTABLE MEETING ON SUSTAINABLE PALM OIL. RSPO Guidance for the Management and rehabilitation of Riparian Reserves Holly Barclay ROUNDTABLE MEETING ON SUSTAINABLE PALM OIL RSPO Guidance for the Management and rehabilitation of Riparian Reserves Holly Barclay Riparian reserves (also called riparian buffer zones ) = strips of natural

More information

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories: 5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION The scope of the EIA falls under three broad categories: technical scope; spatial scope; and temporal scope. The scoping process for the

More information

Advice to decision maker on coal mining project

Advice to decision maker on coal mining project . Advice to decision maker on coal mining project IESC 2015-063: West Muswellbrook Project New Development Requesting agency The New South Wales Mining and Petroleum Gateway Panel Date of request 27 January

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT The health of the world s oceans and marine life is degrading rapidly as a result of excess human activities.

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN Zitholele Consulting Reg. No. 2000/000392/07 PO Box 6002 Halfway House 1685 South Africa Thandanani Park, Matuka Close Halfway Gardens, Midrand Tel + (27) 011 207 2079 Fax + (27) 011 805-2100 E-mail :

More information

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below.

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below. SEDIMENT CONTROL NOTES 1.0 GENERAL 1.1 The Developer and Contractor shall comply with the requirements of all regulatory authorities, federal, provincial and municipal government departments including

More information

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 AGENDA Opening and Welcome Introduction of Consultants Profile of Izwelisha Consortium Explanation of the EMF process Environmental

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS I. POLICY STATEMENT Auburn University's (the University's) "Policy for Natural Resource Management Areas" implements the Campus Master Plan Land Use Element

More information

Planning & Building Department. Requirements for Erosion and Sediment Control

Planning & Building Department. Requirements for Erosion and Sediment Control Planning & Building Department 455 County Center, 2nd Floor Redwood City, California 94063 Tel: 540/863-4161/Fax: 650/363-4849 Mail Drop PLN122 plngbldg@smcgov.org http://planning.smcgov.org Requirements

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information

Emergency Nondabula Water Reticulation Project

Emergency Nondabula Water Reticulation Project Emergency Nondabula Water Reticulation Project Watercourse Crossings Construction Work Method Statement July 2015 I L E M B E D I S T R I C T M U N I C I P A L I T Y Document Description Royal HaskoningDHV

More information

Standards for SWMF s. (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities

Standards for SWMF s. (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities Standards for SWMF s (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities August 2017 PREAMBLE Development results in a great amount of impervious area,

More information

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions.

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions. 18. Air The Project Air quality team prepared an Air Quality Assessment Report for the Project, which is included in Volume 3 (Part 1). The Report provides an assessment of air quality effects associated

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 NOVEMBER 2012 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

LEBANON WATER SUPPLY AUGMENTATION PROJECT ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT

LEBANON WATER SUPPLY AUGMENTATION PROJECT ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized LEBANON WATER SUPPLY AUGMENTATION PROJECT ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT APPENDIX

More information

KENT BREEZE WIND FARMS

KENT BREEZE WIND FARMS Decommissioning Plan Report MAY 2010 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. DECOMMISSIONING PROCESS DESCRIPTION... 2 3. SITE RESTORATION... 3 4. EXCESS MATERIALS AND WASTE MANAGEMENT... 4 5. MANAGING

More information

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods. 1 FACTSHEET INTRODUCTION World Water Day, on 22 March every year, is about focusing attention on the importance of water. This year s theme, Nature for Water, explores nature-based solutions (NBS) to the

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

Maitland Valley WATERSHED

Maitland Valley WATERSHED Maitland Valley WATERSHED Report Card 2018 Maitland Conservation has prepared this report card as a summary of the state of your forests, wetlands, and water resources. WHERE ARE WE? We are one of 36 Conservation

More information

E7. Taking, using, damming and diversion of water and drilling

E7. Taking, using, damming and diversion of water and drilling E7. Taking, using, damming and diversion of water and drilling E7.1. Introduction Taking, using, damming and diversion of surface water and groundwater provisions in this plan apply in accordance with

More information

Environmental Management Programme (EMP)

Environmental Management Programme (EMP) Appendix D Environmental Management Programme (EMP) Please note that although Construction and Operational Phase measures are included in this EMP they are relevant to the issued Waste Management Licence

More information

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS By Marcus Rubenstein, CPESC WHAT IS STREAM RESTORATION? The return of a stream s lost natural functions, usually resulting from watershed alterations,

More information

Debrob Investments Limited FUNCTIONAL SERVICING REPORT DRAFT PLAN OF SUBDIVISION, CITYVIEW DRIVE CITY OF GUELPH

Debrob Investments Limited FUNCTIONAL SERVICING REPORT DRAFT PLAN OF SUBDIVISION, CITYVIEW DRIVE CITY OF GUELPH JULY 2013 DOCUMENT CONTROL Client: Project Name: Report Title: IBI Reference: 25528 Cityview Drive Version: JULY 2013 Digital Master: Originator: Reviewer: Authorization: [File Location] Scott MacDonald,

More information

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary Sizewell B Dry Fuel Store Environmental Statement Non-Technical Summary NON TECHNICAL SUMMARY 1 INTRODUCTION This Non Technical Summary (NTS) is submitted as part of the application to extend the existing

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

State of Florida Department of Community Affairs Areas of Critical State Concern Implementation Status Report Apalachicola Bay Area

State of Florida Department of Community Affairs Areas of Critical State Concern Implementation Status Report Apalachicola Bay Area State of Florida Department of Community Affairs Areas of Critical State Concern Implementation Status Report Apalachicola Bay Area Thaddeus L. Cohen, AIA Secretary November 2006 CONTENTS Part 1 - Summary

More information

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards 06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards THE APPLICATION Planning permission is sought for the construction of a noise attenuation

More information

AUMA Policy Paper 2013.A1

AUMA Policy Paper 2013.A1 AUMA Paper 2013.A1 AUMA Board of Directors Municipal Water on Wetlands WHEREAS in 2012 the AUMA Board of Directors issued the mandate of developing Municipal Water Policies and approved advancing polices

More information

Chapter 21 Stormwater Management Bylaw

Chapter 21 Stormwater Management Bylaw Chapter 21 Stormwater Management Bylaw SECTION 1. PURPOSE The purpose of this Bylaw is to: implement the requirements of the National Pollutant Discharge Elimination System (NPDES) General Permit for Storm

More information

Chapter 10 Natural Environment

Chapter 10 Natural Environment Chapter 10 Natural Environment Existing Conditions The Natural Environment Element addresses the protection, conservation, preservation, and restoration of the natural resources the Bayview Ridge Subarea,

More information

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and Introduction There are many tools that a reviewer of environmental impact assessment documents can use to help determine whether such documents are complete and adequate. Among the powerful tools that

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

Appendix General Environmental Risk Analysis

Appendix General Environmental Risk Analysis Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified

More information

Chapter 13 Management and Implementation

Chapter 13 Management and Implementation Chapter 13 Management and Implementation TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Overview of AGT Region Operating Management System... 13-1 13.3 Construction

More information

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017 Annesley Andalusite Mine: Section 24G Rectification Process Consultation with community members 15 June 2017 AGENDA Welcome and introduction Meeting protocol Purpose of the meeting Project background Project

More information

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,

More information

Assessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture

Assessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture Assessment of Landfill Footprint Alternatives Figure 422 99 Option #4 Impact on Agriculture The net effects with respect to continued service to customers, the optimized site life/ capacity is 65 million

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

WATERSHED. Maitland Valley. Report Card 201

WATERSHED. Maitland Valley. Report Card 201 Maitland Valley WATERSHED Report Card 201 The Maitland Valley Conservation Authority has prepared this report card as a summary on the state of our forests, wetlands, surface water, and ground water resources.

More information

Division 8 Intensive Animal Husbandry Code

Division 8 Intensive Animal Husbandry Code Division 8 Intensive Animal Husbry Code 12.8.1 Intensive Animal Husbry Code (1) The provisions in this division comprise the Intensive Animal Husbry Code. (2) They are compliance with the Intensive Animal

More information

EIGHT POINT WIND ENERGY CENTER

EIGHT POINT WIND ENERGY CENTER EIGHT POINT WIND ENERGY CENTER Case No. 16 F 0062 1001.11 Exhibit 11 Preliminary Design Drawings Contents Exhibit 11: Preliminary Design Drawings... 1 11(a) Site Plan... 1 11(b) Construction Operations

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

DESIGN BULLETIN #16/2003 (Revised July 2007) Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas.

DESIGN BULLETIN #16/2003 (Revised July 2007) Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas. Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas. July 2007 Update to Design Bulletin #16/2003: Added under Design Criteria Culverts of 600mm diameter are commonly used to

More information

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Construction Management Plan (CMP) 227 Princess Highway, Dandenong Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale

More information

February Reference Section in Supplemental. Reference Section in Consultants Reports. Reference Section in Application. TOR No.

February Reference Section in Supplemental. Reference Section in Consultants Reports. Reference Section in Application. TOR No. Request i Final Terms of Environmental Impact Assessment Report for Coal Valley Resources Inc. (CVRI) Proposed Robb Trend Project Cross (Concordance) Table to Location in ii PURPOSE OF THE TERMS OF REFERENCE

More information

Information Request 37

Information Request 37 Information Request 37 Information Request 37 37-1 Response to Information Request 37 Response to Information Requests 37a Response to Information Requests 37b 37-3 37-5 Federal Review Panel Information

More information

ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY. Town of Shelburne Long-Term Well for Additional Water Supply Project

ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY. Town of Shelburne Long-Term Well for Additional Water Supply Project ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY Town of Shelburne Long-Term Well for Additional Water Supply Project EXECUTIVE SUMMARY Introduction Project Summary In order to accommodate future growth

More information

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

Environmental Impact Statement for the Slave Falls Tramway Conversion Project Environmental Impact Statement for the Slave Falls Tramway Conversion Project Prepared for Submitted by 41844.101 March 2008 ENVIRONMENTAL IMPACT STATEMENT FOR THE SLAVE FALLS TRAMWAY CONVERSION PROJECT

More information

GAUTENG BIODIVERSITY GAP ANALYSIS

GAUTENG BIODIVERSITY GAP ANALYSIS GAUTENG BIODIVERSITY GAP ANALYSIS DEPARTMENT OF AGRICULTURE, CONSERVATION, ENVIRONMENT & LAND AFFAIRS Introduction Project aim Approach to project Data collection Threat layers Data analysis Time frame

More information

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet WELCOME Please sign in Representatives are available to answer questions Please complete a comment sheet Place it in the box or send it to the Consultant undertaking the study or to the Town of Wasaga

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5 Turbine Foundation Construction Method Statement Copyright ESB International Limited, all rights reserved. Farm Contents 1 Introduction

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Waitarere Beach Road Curves Project Erosion and Sediment Control Plan

Waitarere Beach Road Curves Project Erosion and Sediment Control Plan APPENDIX D Waitarere Beach Road Curves Project Prepared for The New Zealand Transport Agency November 2015 QUALITY STATEMENT PROJECT MANAGER Jon England PROJECT TECHNICAL LEAD Phil Peet PREPARED BY Stephen

More information

Water sensitive urban design. Developing design objectives for urban development in South East Queensland

Water sensitive urban design. Developing design objectives for urban development in South East Queensland Water sensitive urban design Developing design objectives for urban development in South East Queensland Version 2-8 November 2007 Contents Contents......... ii Executive Summary............1 1 Introduction.........1

More information

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for

More information

Galiuro Exploration Drilling Project

Galiuro Exploration Drilling Project Galiuro Exploration Drilling Project Range and Noxious Weeds Report Prepared by: Gwen Dominguez Range Staff for: Safford Ranger District Coronado National Forest Date September 2, 2016 Forest Plan/Policy

More information

Environmental Management Programme: Langhoogte Wind Farm, Western Cape

Environmental Management Programme: Langhoogte Wind Farm, Western Cape SAGIT Energy Ventures Environmental Management Programme: Langhoogte Wind Farm, Western Cape Version 1 February 2013 J30284A Head Office 14 Eglin Road, Sunninghill 2191 Johannesburg, South Africa Tel:

More information

Nez Perce National Forest Moose Creek Ranger District

Nez Perce National Forest Moose Creek Ranger District United States Department of Agriculture Forest Service Nez Perce National Forest Moose Creek Ranger District 831 Selway Road Kooskia, ID 83539 208 926-4258 TTY 208 926-7725 File Code: 1950 Date: Dec 30,

More information

Operations Mine Site, Tote Road and Railway

Operations Mine Site, Tote Road and Railway Operations Mine Site, Tote Road and Railway 2 Panel Members Michael Anderson Richard Cook John Binns Fernand Beaulac Steve Walker Mike Lepage Michael Sheahan 3 The Panel will address: FEIS Volumes 3, 5,

More information

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani DESCRIPTION OF

More information

Technical Guidance Document for Strategic Environmental Assessment (SEA)

Technical Guidance Document for Strategic Environmental Assessment (SEA) Technical Guidance Document for Strategic Environmental Assessment (SEA) EAD-EQ-PCE-TG-03 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General Originated

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Gold Coast. Rapid Transit. Chapter content. Chapter ten Environmental impacts

Gold Coast. Rapid Transit. Chapter content. Chapter ten Environmental impacts Chapter ten Environmental impacts Gold Coast Rapid Transit Chapter ten Environmental impacts Chapter content Environment overview...219 EPBC referral...220 Impacts and mitigation strategies for: Flora

More information

7. NATURAL HAZARDS 7.1 SECTION INTRODUCTION

7. NATURAL HAZARDS 7.1 SECTION INTRODUCTION 7. NATURAL HAZARDS 7.1 SECTION INTRODUCTION 7.1.1 The Resource Management Act empowers Council to control any actual or potential effects of the use, development, or protection of land for the purpose

More information

3.6 Riparian Ecosystem Wildlife

3.6 Riparian Ecosystem Wildlife 3.6 Riparian Ecosystem Wildlife 3.6.1 Introduction and Methodology Riparian areas and associated wetlands are widely recognized for the significant and diverse roles they play in the landscape. They clean

More information

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999 (No. JPBN. 1509/27 Vol. II CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999 In exercise of the powers conferred by section 5 of the Conservation

More information